Skip to main content

Presidential Helicopter: Program is Meeting Cost Goals but Some Technical and Schedule Risks Remain

GAO-20-356 Published: Apr 16, 2020. Publicly Released: Apr 16, 2020.
Jump To:

Fast Facts

The President relies on a fleet of military helicopters for transportation. The Navy plans to replace the more than 40-year-old fleet with 23 new VH-92A helicopters.

The VH-92A program remains generally on target with cost and schedule. The Navy now expects the total cost of buying and operating the aircraft for the next 40 years to be $20.5 billion. That’s about 10 percent lower than original estimates in 2014.

The Navy targeted January 2021 for deciding when to begin using the new helicopters, but some communications software issues still need to be resolved. Delays could defer the decision and postpone the helicopters’ addition to the fleet.

Presidential helicopter

Presidential helicopter

Skip to Highlights

Highlights

What GAO Found

The Navy estimates the cost to develop, procure, and maintain the VH-92A ® over its 40-year operational life to be just over $20.5 billion, or about 10 percent less than the Navy's 2014 baseline estimate (see table).

VH-92A Helicopter Program Cost Estimate Has Decreased


Then-year dollars in millions

April 2014
Baseline

April 2019
Estimate


Change

Development

$2,805.7

$2,648.8

-5.6%

Procurement

2,379.0

2,246.5

-5.6

Total Program Acquisition Costs

5,184.7

4,895.3

-5.6

Operations and support

17,674.3

15,641.9

-11.5

Total Estimated Life Cycle Costs

$22,859.0

$20,537.2

-10.2

Source: GAO presentation of Navy data l GAO-20-356

Navy and contractor officials worked to remain within the program's April 2014 cost baseline estimate, in part, by keeping program requirements stable, limiting design changes, and taking advantage of cost saving initiatives. The Navy also plans to use Navy personnel and facilities to perform depot-level maintenance for the VH-92A fleet, rather than sending the helicopters back to the contractor as is currently done.

The program has made progress addressing technical risks and performance challenges GAO discussed in prior reports; however, an April 2019 operational assessment confirmed several other risks that could affect the helicopter's ability to meet its reliability and availability requirements. For example, Navy officials stated that the assessment confirmed known limitations with the mission communications system. Upgraded software intended to address those limitations is to be evaluated during the initial operational test and evaluation scheduled to be conducted between June and September 2020. The results of that testing could impact the Navy's planned January 2021 decision to begin using the helicopters as part of the presidential helicopter fleet.

Why GAO Did This Study

The mission of the presidential helicopter fleet is to provide safe, reliable, and timely transportation in support of the President. The Navy plans to acquire a fleet of 23 VH-92A helicopters to replace the current Marine Corps fleet which has been in use for more than 40 years. Delivery of production VH-92A helicopters is scheduled to begin in April 2021 and be completed in January 2023.

The National Defense Authorization Act of 2014 included a provision for GAO to report annually on the acquisition of the VH-92A helicopter. This report, GAO's sixth related to the provision, examines (1) the extent to which the program is meeting cost goals and (2) performance and schedule challenges that the program has experienced.

To conduct this work, GAO compared the Navy's April 2019 cost estimates for acquiring and maintaining the new helicopters and October 2019 program schedule information to its April 2014 acquisition baseline. GAO reviewed development test results and status reports from the program. GAO also interviewed officials from the program office, Navy test organizations, and the contractor.

GAO is not making any recommendations in this report.

For more information, contact Timothy J. DiNapoli at (202) 512-4841 or dinapolit@gao.gov.





Full Report

GAO Contacts

Timothy J. DiNapoli
Managing Director
Contracting and National Security Acquisitions

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Acquisition costsCost and scheduleCost and schedule performanceCost assessmentsCost estimatesDevelopmental testingHelicoptersLessons learnedOperational testingPerformance shortfallsPresidential travelSoftwareTechnical challenges