Skip to main content

Federal Courthouses: Recommended Construction Projects Should Be Evaluated under New Capital- Planning Process

GAO-13-263 Published: Apr 11, 2013. Publicly Released: Apr 17, 2013.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The Asset Management Planning (AMP) process represents progress by the federal judiciary (judiciary) in better aligning its capital-planning process with leading capitalplanning practices, but its 5-year plan for fiscal years 2014 to 2018--the document the judiciary uses to request courthouse construction projects--lacks transparency and key information on how projects qualify for new construction, alternatives the judiciary considered, and their cost. For example, the plan lists costs for the next phase of the 12 recommended courthouse projects, which have several phases, but does not list previous funding or ongoing annual costs for the projects. As a result, the plan lists about $1 billion in costs for the 12 projects, but the projects would actually cost the federal government an estimated $3.2 billion over the next 20 years. Congress has appropriated a small share of the money needed for the projects, and most will need design changes before construction can begin. As a result, there is a risk that congressional funding decisions could be made without complete and accurate information. However, with this information, decision makers could weigh current-year budget decisions within the context of projects' expected future costs, spur discussion and debate about actions to address them, and put the judiciary's requests in context with other federal spending.

Ten of the 12 recommended projects were not evaluated under the AMP process. Judiciary officials said that they did not want to delay the current projects or force them to undergo a second capital-planning process after they had already been approved. Two courthouse projects from a previous 5-year plan that were assessed under AMP were removed from the list and are now ranked behind more than 100 other courthouse construction projects. Furthermore, 10 of the 12 recommended construction projects do not qualify for a new courthouse under the AMP criterion, which requires that new courthouses need two or more additional courtrooms. These conditions call into question the extent to which the projects remaining on the 5-year plan represent the judiciary's most urgent projects and whether proceeding with these projects represents the most fiscally responsible proposal. While 10 additional AMP evaluations would involve some additional costs, not conducting those evaluations could involve spending $3.2 billion over the next 20 years on courthouses that may not be the most urgent projects.

Why GAO Did This Study

Rising costs and fiscal challenges have slowed the multibillion-dollar courthouse construction program of the judiciary and the General Services Administration (GSA). In 2006, the judiciary developed AMP to address increasing costs and incorporate best practices and has evaluated about 67 percent of its courthouses under the new system. As requested, GAO assessed changes introduced with AMP. GAO examined: (1) the extent to which the AMP process aligns with leading practices and provides information needed for informed decision making and (2) the extent to which courthouse projects recommended for funding in fiscal years 2014 to 2018 were assessed under the AMP process. GAO compared the judiciary's capitalplanning practices with leading practices, analyzed courthouseplanning documents, and interviewed officials from the judiciary and GSA. GAO visited three courthouses selected because they were highly ranked by the judiciary for replacement, although observations from these site visits cannot be generalized.

Recommendations

The judiciary should (1) provide more information to decision makers related to how projects qualify for new construction, any alternatives the judiciary considered, and their cost and (2) impose a moratorium on the projects currently on the judiciary's 5- year plan until they are evaluated under AMP. The judiciary partially agreed with the first recommendation and disagreed with the second recommendation. GAO believes that a moratorium would allow the judiciary to ensure that it makes the best investments in courthouse construction.

Recommendations for Executive Action

Agency Affected Recommendation Status
Administrative Office of the United States Courts To further improve the judiciary's capital-planning process, enhance transparency of that process, and allow for more informed decision making related to the federal judiciary's real property priorities, the Director of the Administrative Office of the U.S. Courts, on behalf of the Judicial Conference of the United States should better align the AMP process with leading practices for capital planning. This should include linking the AMP process to the judiciary's strategic plan and developing and sharing with decision makers a long-term capital investment plan. In the meantime, future 5- year plans should provide comprehensive information on new courthouse projects, including: a) a summary of why each project qualifies for new construction and is more urgent than other projects, including information about how the AMP process and other judiciary criteria for new courthouse construction were applied to the project; b) complete cost estimates of each project; and c) the alternatives to a new project that were considered, including courtroom-sharing, and why alternatives were deemed insufficient.
Closed – Implemented
Rising costs and fiscal challenges have slowed the multibillion-dollar courthouse construction program of the federal judiciary (judiciary) and the General Services Administration (GSA). In 2006, the judiciary developed Asset Management Planning (AMP) to address increasing costs and incorporate best practices. In 2013, GAO reported that the AMP process represented progress by the judiciary in better aligning its capital-planning process with leading capital-planning practices to assess, identify, and rank its space needs. The AMP process results in an urgency score for construction or renovation based primarily on the current and future need for courtrooms and chambers and the condition assessment of the existing building. However, the judiciary 5-year plan for fiscal years 2014 to 2018 lacked transparency and key information on how projects qualify for new construction, alternatives the judiciary considered, and their cost. Specifically, the 5-year plan was a one-page document that lists proposed projects by fiscal year and the estimated costs for various project phases that the judiciary uses the plan to communicate its most urgent projects to Congress and other decision makers. The 5-year plan did not provide decision makers with detailed information about proposed construction projects or how they were selected. Unlike a long-term capital investment plan-usually the end product under leading capital-planning practices-the 5-year plan lacked complete cost and funding information, linkage to the judiciary's strategic plan, and information on why projects were selected. Given these conditions, the 5-year plan only aligns to a limited extent with leading capital-planning practices. Therefore, GAO recommended that the judiciary better align the AMP process with leading practices for capital-planning by linking the AMP process to the judiciary's strategic plan and developing and sharing with decision makers a long-term capital investment plan. In 2015, the judiciary made changes to how it presents courthouse projects to Congress by developing the courthouse project priorities (CPP) document that linked several objectives of its strategic plan to a list of Fiscal Year 2017 priorities and future priorities that included AMP urgency evaluation scores and total estimated costs. In 2016, GSA also provided comprehensive project information on courthouse projects to congress-such as why the project qualifies for new construction, alternatives considered and courtroom sharing. Given the additional information that the judiciary provided to Congress along with the project information contained in the GSA prospectus, together these action meet the intent of meets of GAO's recommendation. As a result, Congress and decision makers now have access to the information they need to weigh current-year budget decisions within the context of projects' expected future costs, spur discussion and debate about actions to address them, and put the judiciary's requests in context with other federal spending.
Administrative Office of the United States Courts To further improve the judiciary's capital-planning process, enhance transparency of that process, and allow for more informed decision making related to the federal judiciary's real property priorities, the Director of the Administrative Office of the U.S. Courts, on behalf of the Judicial Conference of the United States should impose a moratorium on projects on the current 5-year plan until AMP evaluations are completed for them and then request feasibility studies for courthouse projects with the highest urgency scores that qualify for new construction under the AMP process.
Closed – Implemented
Rising costs and fiscal challenges slowed the multibillion-dollar courthouse construction program of the federal judiciary (judiciary) and the General Services Administration (GSA). In 2006, the judiciary developed the Asset Management Planning (AMP) process to address increasing costs and incorporate best practices. In 2013, GAO reported that 10 of the 12 recommended courthouse construction projects--included in the judiciary's 5-year plan for fiscal years 2014-2018--were not evaluated under the AMP process. Judiciary officials said that they did not want to delay the current projects or force them to undergo a second capital-planning process after they had already been approved. Furthermore, 10 of the 12 recommended construction projects did not qualify for a new courthouse under the AMP criterion, which requires that new courthouses need two or more additional courtrooms. These conditions called into question the extent to which the projects remaining on the 5-year plan represent the judiciary's most urgent projects and whether proceeding with these projects represents the most fiscally responsible proposal. While 10 additional AMP evaluations would involve some additional costs, not conducting those evaluations could involve spending $3.2 billion over the next 20 years on courthouses that may not be the most urgent projects. Therefore, GAO recommended the judiciary impose a moratorium on projects until it could apply the AMP process to the remaining projects on the 5-year plan. In 2017, GAO confirmed that shortly after GAO's report was issued the judiciary placed a moratorium on courthouse construction projects until it was able to apply the AMP process to the courthouses on the 5-year plan. In 2015, the judiciary issued the Federal Judiciary Courthouse Project Priorities List that assessed all projects under the AMP process and ranked the recommended projects according to their urgency. By applying the improved AMP process, the judiciary ensured that it requested funding for its most urgent courthouses projects.

Full Report

GAO Contacts

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Topics

CapitalCapital improvementsCapital investment planningCourthousesDecision makingEvaluation criteriaFederal courthouse constructionFederal fundsFederal propertyGovernment facility constructionStrategic planningUse of fundsCourthouse constructionLaw courtsReal property