Offshore Oil and Gas: Interior Needs to Improve Decommissioning Enforcement and Mitigate Related Risks
Fast Facts
Oil and gas companies with offshore infrastructure must decommission it when it's no longer useful—by plugging wells and removing platforms within set deadlines.
As of June 2023, more than 2,700 wells and 500 platforms were overdue for decommissioning in the Gulf of Mexico.
Delays can increase environmental, safety, and financial risks. For example, delays could indicate that companies are in financial trouble and may leave the government to pay for decommissioning. The Department of the Interior only holds about $3.5 billion in bonds from companies to cover a potential cost of $40-$70 billion.
Our recommendations address this and other risks.
Corrosion—as shown on Platform Hogan in the Pacific—can make offshore infrastructure more unsafe over time.
Highlights
What GAO Found
The Department of the Interior's Bureau of Safety and Environmental Enforcement (BSEE) does not effectively ensure that industry operators meet decommissioning deadlines for offshore wells and platforms at the end of their useful lives. BSEE's administrative enforcement tools and its use of them are ineffective at incentivizing noncompliant operators—for example, citations for regulatory violations and orders to comply are essentially warnings. BSEE rarely takes more punitive actions such as issuing civil penalty fines, which can take years, or disqualifying operators, which has unclear trigger criteria. Long-standing uncertainties in the enforceability of some deadlines also undermine BSEE's effectiveness for idle infrastructure on active leases and end-of-lease infrastructure in the Pacific. These enforcement issues have contributed to widespread decommissioning delays that have grown into a substantial backlog. For example, for Gulf leases that ended in 2010 through 2022, operators missed BSEE's 1-year decommissioning deadline for more than 40 percent of wells and 50 percent of platforms—many of which still have not been decommissioned. Over 75 percent of end-of-lease and idle infrastructure in the Gulf was overdue under BSEE's deadlines as of June 2023—over 2,700 wells and 500 platforms.
End-of-Lease and Idle Offshore Wells and Platforms Overdue for Decommissioning in the Gulf of Mexico
Moreover, Interior's Bureau of Ocean Energy Management (BOEM) does not effectively assure that operators have the financial and technical capacity to meet decommissioning obligations in advance of potential delays, bankruptcies, or other defaults. Specifically, BOEM held about $3.5 billion in supplemental bonds to cover between $40 billion and $70 billion in total estimated decommissioning costs as of June 2023. As a result, the federal government remains exposed to billions of dollars in financial risks from decommissioning liabilities if operators do not meet their obligations. BOEM has been working for over a decade on proposals to better address these risks but has not finalized changes in its approach. Additionally, BOEM has limited operator qualification standards that do not address decommissioning capacity or consider any past issues with meeting these obligations safely and timely.
Interior could better enforce decommissioning deadlines and mitigate the safety, environmental, and financial risks that unmet decommissioning obligations pose by ensuring BSEE and BOEM prioritize completing planned actions. Additionally, given the extended duration and magnitude of these issues and insufficient progress in Interior's efforts to address them, congressional oversight or direction may be warranted to better limit the growing scale of related risks.
Why GAO Did This Study
Since the 1940s, the offshore oil and gas industry has installed more than 55,000 wells and 7,000 platforms on the outer continental shelf, mostly in the Gulf of Mexico. Interior is responsible for enforcing requirements for industry operators to safely decommission this infrastructure at the end of its useful life within deadlines set by regulations.
Delayed decommissioning increases environmental, safety, and financial risks. Over time, infrastructure becomes increasingly vulnerable to damage and deterioration from storms and corrosion, which can topple platforms, cause oil spills, and make decommissioning more expensive and dangerous. The federal government may become liable for these costs if industry defaults on its obligations.
GAO was asked to review Interior's oversight of offshore decommissioning. This report examines Interior's effectiveness in (1) enforcing decommissioning deadlines and (2) assuring industry capacity to meet them. GAO reviewed decommissioning regulations, procedures, guidance, and data; interviewed agency officials; and obtained perspectives from industry and environmental groups.
Recommendations
GAO is making four recommendations to Interior to strengthen BSEE and BOEM's decommissioning oversight and enforcement. Congress also may want to consider providing oversight by establishing a reporting mechanism or direction by clarifying how Interior should balance statutory priorities for offshore decommissioning.
Matter for Congressional Consideration
Matter | Status | Comments |
---|---|---|
To the extent that Congress wants to further encourage Interior to manage risks posed by decommissioning liabilities, it should consider implementing an oversight mechanism—such as requiring annual reporting on the status of decommissioning enforcement efforts and associated liabilities—or providing additional direction to Interior on how to balance the goals outlined by the Outer Continental Shelf Lands Act as it makes decisions about decommissioning oversight and enforcement priorities. (Matter 1) | On July 25, 2024, the Plug Offshore Wells Act was introduced and referred to the House Committee on Natural Resources (H.R. 9168, 118th Cong.), and on December 12, 2024, the parallel Plug Offshore Wells Act was introduced and referred to the Senate Committee on Energy and Natural Resources (S. 5508, 118th Cong.). Both bills would have required the Secretary of the Interior to report annually on the status and timeliness of offshore decommissioning activities and related enforcement actions. No further actions were taken on these bills after they were introduced and referred to committee, and we were unable to locate any other legislation addressing these issues as of January 2025. Therefore, this matter remains open. Addressing this matter could help protect the environment and minimize the government's financial risk. As of February 11, 2025, Congress has not passed legislation that would implement this matter, and we were unable to identify any bills in the 119th Congress responsive to this matter. |
Recommendations for Executive Action
Agency Affected | Recommendation | Status |
---|---|---|
Department of the Interior | The Secretary of the Interior should direct the BSEE Director to strengthen BSEE's approach to proactively overseeing and enforcing decommissioning deadlines, including by (1) assessing the effectiveness of enforcement tools to incentivize compliance and data and practices supporting their timely use, and (2) identifying and implementing regulatory or policy changes as needed in consultation with BOEM, such as by providing clear timelines or other trigger criteria for use of existing enforcement tools and identifying additional enforcement tools. (Recommendation 1) |
Interior agreed with this recommendation. According to BSEE's fiscal year 2025 budget justification, the agency is developing a strategy that will include a risk assessment; objectives and performance measures; and roles, responsibilities, and resource needs to address these issues. By August 2024, BSEE had established a project team that planned to review regulations, policies, and standard operating procedures, and recommend changes by June 2025 to ensure more consistent decommissioning enforcement. In December 2024, BSEE indicated that it had made some progress toward identifying improvements to its data and enforcement tools.
|
Department of the Interior |
Priority Rec.
The Secretary of the Interior should ensure the BSEE Director completes planned actions to identify, propose, finalize, and fully implement changes to decommissioning regulations and guidance, including by (1) clarifying decommissioning criteria and deadlines for idle infrastructure in all regions and for end-of-lease infrastructure in the Pacific Region, and (2) addressing any other identified limitations. (Recommendation 2)
|
Interior agreed with this recommendation. BSEE first published notice that it intended to update subpart Q decommissioning regulations, including on idle infrastructure, in the fall 2021 regulatory agenda. As of January 2025, BSEE had not yet published a proposed rule but planned to do so within the year. As part of this effort, BSEE established a project team to review regulations, policies, and standard operating procedures, and expected to recommend changes by June 2025 to ensure more consistent decommissioning enforcement.
|
Department of the Interior |
Priority Rec.
The Secretary of the Interior should ensure the BOEM Director completes planned actions to further develop, finalize, and fully implement changes to financial assurance regulations and procedures that reduce financial risks, including by (1) requiring higher levels of supplemental bonding, and (2) addressing other known weaknesses. (Recommendation 3)
|
Interior agreed with this recommendation and finalized BOEM's financial assurance rule in April 2024. The rule has an effective date of June 29, 2024, and by August 2024 BOEM had laid out a planned timeline for the rule's implementation. Specifically, BOEM planned to send notices to companies by the end of August 2024 and to give them up to 6 months to respond with the requested information. BOEM estimated it will take up to 24 months from the date that these notices are distributed to complete processing of financial assurance demands for execution. As of December 2024, BOEM indicated that companies were beginning to submit the requested information on their properties and finances.
|
Department of the Interior | The Secretary of the Interior should ensure the BOEM Director completes planned actions to assess and revise qualification procedures to address decommissioning capacity and compliance history in consultation with BSEE, such as through qualification and disqualification criteria or fitness to operate standards. (Recommendation 4) |
Interior agreed with this recommendation. BOEM posted in the spring and fall 2024 regulatory agendas a target date of January 2025 for publication of a proposed rule on fitness to operate standards. In August 2024, BOEM told us it is coordinating with BSEE to develop a fitness to operate standard. As of the end of January 2025, BOEM had not yet proposed a rule or updated the regulatory agenda to indicate when it intends to do so.
|