Skip to main content

Weapon Systems Sustainment: DOD Needs to Improve Its Reporting for Warehousing Pilot Program

GAO-23-105929 Published: Mar 09, 2023. Publicly Released: Mar 09, 2023.
Jump To:

Fast Facts

The military services and contractors use warehouses to store and distribute parts to repair weapon systems, among other things. The Defense Logistics Agency (DLA) has 400 warehouses, but contractors also use commercial warehouses.

In 2017, Congress authorized a pilot program seeking to more fully use DLA warehouses and avoid paying for commercial space. We reviewed the agency's report on this program.

We found that DOD didn't collect all the information it needed to fully understand the costs and benefits of the pilot program—for example, it didn't assess the effects of inflation on the program. Our recommendations address this issue and more.

A photo inside a warehouse: a massive concrete and metal room with items stored on pallets, and in boxes, crates, and cartons

Skip to Highlights

Highlights

What GAO Found

The National Defense Authorization Act (NDAA) for Fiscal Year 2017 authorized a 6-year pilot program for the Defense Logistics Agency (DLA) to provide storage and distribution services for weapon system contractors. Specifically, the Department of Defense (DOD) was authorized to enter into no more than five contracts for contractors to use DLA's warehouses to store and distribute weapon system parts. DOD was also required to submit a report by the end of 2021 describing the cost-effectiveness of the pilot program and how the warehousing contracts affected the contractors' ability to meet the requirements of their existing contracts to support weapon systems sustainment. DOD issued its report to Congress in March 2021 and recommended the pilot program be made permanent and expanded to non-weapon systems. DOD further submitted a legislative proposal for the NDAA for Fiscal Year 2023 for Congress to enact its recommendations. The James M. Inhofe NDAA for Fiscal Year 2023 extended the pilot program for an additional year.

GAO found that DOD's report did not fully assess the cost-effectiveness of the pilot program. DOD guidance establishes seven elements that must be addressed for a complete cost-effectiveness analysis. GAO found that DOD substantially addressed one, partially addressed five, and did not address one element. For example, DOD's report provided some cost information for three existing contracts in the pilot program. However, the report included projected rather than actual costs, and did not fully evaluate alternatives. DOD officials told GAO that they were not aware of DOD's guidance identifying the elements of a complete cost-effectiveness analysis and did not use other relevant guidance. By applying the guidance and conducting a complete cost-effectiveness analysis, DOD can help ensure that Congress has the information it needs to evaluate the costs and benefits of the pilot program.

DOD's report did not comprehensively assess how the warehousing contracts affected contractors' ability to meet the requirements of their existing primary contracts. For example, DOD's report described contractor's views but did not include any supporting data or information. The report also did not include challenges described to GAO by stakeholders managing these contracts. Without this assessment, DOD may not have complete information on the potential effects of these contracts to inform congressional decisions about the pilot program.

Why GAO Did This Study

DLA is DOD's largest logistics combat support agency. It operates 400 warehouses to, among other things, store and distribute parts for producing and repairing weapon systems. The military services and their weapon system contractors have used commercial warehouses to store inventory that were in close proximity to DLA's distribution centers, potentially incurring higher costs and longer delivery times in doing so.

Section 883 of the NDAA for Fiscal Year 2017 authorized a 6-year pilot program for DLA to provide storage and distribution services for weapon systems contractors. Section 883 also required DOD to report on the program and included a provision for GAO to review the report for sufficiency.

This review addresses the extent to which DOD's report assessed (1) the cost-effectiveness of the program and (2) whether the support contracts affected contractors' ability to meet the requirements of their existing primary contracts. GAO reviewed DOD's report and compared it to required elements in the mandate, and interviewed DOD officials.

Recommendations

GAO made three recommendations, including that DOD perform a complete cost-effectiveness analysis and assess how support contracts may affect contractors' ability to meet their requirements under the primary contracts. DOD concurred with these recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense The Secretary of Defense should ensure that the Under Secretary of Defense for Acquisition and Sustainment performs a complete costeffectiveness analysis of the pilot program that follows the guidelines established in DOD Instruction 7041.03. (Recommendation 1)
Closed – Implemented
DOD concurred with this recommendation. As of July 2023, DOD officials have conducted the cost-effectiveness analysis in accordance with DOD Instruction 7041.03, and stated that calculations were based on historical data and assumptions (using local rates and research), when available. DOD provided the completed revised report to us in August 2023. The analysis has been updated to reflect current conditions and was conducted in accordance with DOD Instruction 7041.03. We believe that this updated report meets the intent of our recommendation.
Department of Defense The Secretary of Defense should ensure that the Under Secretary of Defense for Acquisition and Sustainment develops guidance to assess how support contracts in the warehousing pilot program may affect contractors' ability to meet the requirements of the primary contracts. (Recommendation 2)
Open
DOD concurred with this recommendation. As of August 2024, DOD officials told us that DLA will work with the DOD contracts policy officials in the Office of the Assistant Secretary of Defense for Acquisition (ASD(A)) to ensure guidance to assess how support contracts in the warehousing pilot program may affect contractors' ability to meet primary contract requirements is drafted and published. The estimated completion date is December 31, 2024.
Department of Defense The Secretary of Defense should ensure that the Under Secretary of Defense for Acquisition and Sustainment assesses how support contracts in the warehousing pilot program may affect contractors' ability to meet the requirements of the primary contracts and reports its results to Congress. (Recommendation 3)
Open
DOD concurred with this recommendation. As of August, 2024, DOD officials told us that DLA will perform assessments of the warehousing pilot program's effects on contractors' ability to meet the requirements of primary contracts once the guidance developed in response to Recommendation #2 has been approved and published. The estimated completion date is June 30, 2025.

Full Report

GAO Contacts

Diana Maurer
Director
Defense Capabilities and Management

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Defense logisticsMilitary materielPublic and private partnershipsReporting requirementsWarehouse facilitiesWeapon systemsMilitary forcesSystems acquisitionEconomic analysisLogistics