Skip to main content

NASA Lunar Programs: Moon Landing Plans Are Advancing but Challenges Remain

GAO-22-105533 Published: Mar 01, 2022. Publicly Released: Mar 01, 2022.
Jump To:

Fast Facts

NASA plans to conduct a lunar landing mission, known as the Artemis III mission, no earlier than in 2025. This is a delay of at least a year from earlier plans.

While NASA has made progress on preparing for Artemis III (including planning its first test flight), we testified about challenges it faces in meeting its goal.

For example, NASA is behind schedule on developing a lunar lander to transport crew to the lunar surface and back. It also needs to ensure that space suits for lunar surface operations will be available in time.

NASA's current proposed schedule for first three Artemis missions

illustration showing uncrewed test flight in 2022, crewed test flight in 2024, and planned lunar landing in 2025

Skip to Highlights

Highlights

What GAO Found

The National Aeronautics and Space Administration (NASA) effort to return U.S. astronauts to the Moon and then travel to Mars—known as Artemis—has made progress. Since GAO's May 2021 report, NASA conducted integration and test events for the Artemis I mission (an uncrewed test flight) and manufactured some hardware for the Artemis II mission (a test flight that will carry crew). NASA also made progress on completing planning activities for the Artemis III moon landing mission, such as reviewing integration efforts across lunar programs.

Artist's Rendition of Artemis Lunar Landing Mission

Artist's Rendition of Artemis Lunar Landing Mission

NASA now plans to conduct the Artemis III moon landing mission no earlier than 2025, a year later than originally planned. While this delay will allow more time for NASA to acquire a lunar lander and new space suit (shown above), Artemis III schedule and costs remain challenging for several reasons, including:

Delays to the lunar lander contract. NASA officials stated they estimated a 7-month delay in working on the lander, subsequent to a bid protest and federal court complaint regarding the award of the lander's contract. The schedule to develop the landing system is ambitious; the program plans to develop and launch the system months faster than other spaceflight programs and needs to mature critical technologies.

Change to spacesuit acquisition strategy. In July 2021, NASA approved a change from developing its new spacesuits in-house to using a contractor, which may affect planned development time frames. Under this strategy, NASA officials stated they will not have the contract awardee's proposed schedule until after the contract is awarded. Officials told GAO the award is planned for spring 2022.

Increasing costs. Key Artemis III programs have experienced cost growth. For example, costs for the Space Launch System and ground systems grew by more than $1 billion in 2020.

Why GAO Did This Study

NASA is developing multiple highly complex and interdependent programs to achieve the lunar landing mission, known as Artemis III, as well as longer-term goals to create a sustained lunar presence. In the fiscal year 2022 president's budget request, NASA requested at least $32 billion over the next 5 years to support these efforts.

To land astronauts on the Moon, NASA will need to develop a lunar lander and new space suits. It will also need to execute uncrewed and crewed test flights, planned for spring 2022 and 2024, respectively, of the Orion Multi-Purpose Crew Vehicle and the Space Launch System. NASA has delayed the first test flight multiple times, which places pressure on the schedule for subsequent missions. In prior reports, GAO highlighted progress NASA has made toward these missions, as well challenges the agency faces in managing and integrating these systems and missions. This statement updates NASA's progress and challenges in working towards the first three Artemis missions.

This statement is primarily based on GAO's previously issued work on NASA's lunar programs, as well as its ongoing annual assessment of NASA major projects. GAO updated some areas by following up with NASA through other ongoing work.

Recommendations

Since 2019, GAO has made 10 recommendations related to improving NASA's management of its Artemis efforts and related programs. NASA generally agreed with these recommendations and plans to take steps to implement them.

Full Report

GAO Contacts

William Russell
Director
Contracting and National Security Acquisitions

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Topics

Acquisition strategyCost and scheduleCritical technologiesExplorationHigh-risk issuesMoonsTechnology developmentCost and schedule performanceAcquisition managementSocial media