Skip to main content

Coast Guard Acquisitions: Opportunities Exist to Reduce Risk for the Offshore Patrol Cutter Program

GAO-21-9 Published: Oct 28, 2020. Publicly Released: Nov 12, 2020.
Jump To:

Fast Facts

In 2018, Hurricane Michael devastated the shipyard where construction of the Coast Guard's Offshore Patrol Cutters was about to begin. The service needs the 25 new cutters soon to replace others that are more than 50 years old, but the hurricane added delays and cost.

The Coast Guard accepted significant risk with the design, schedule, and cost—both before and after the hurricane—to get the cutters built quickly. But the cutter's design is unstable, its schedule optimistic, and its cost estimate incomplete—making it likely that building it will take longer and cost more.

Our 8 recommendations could help set the program on a better path.

Rendering of the Coast Guard's Offshore Patrol Cutter

A Coast Guard Cutter underway off the coast of Florida.

Skip to Highlights

Highlights

What GAO Found

The Coast Guard divided the Offshore Patrol Cutter (OPC) program into two stages and revised its cost and schedule goals following widespread disruptions from Hurricane Michael in October 2018, which led the shipbuilder to request relief from certain requirements under contract. Under this revised plan, the current shipbuilder will build up to four OPCs in the first stage, while the acquisition of the remaining 21 OPCs will be awarded under one or more new contracts starting in fiscal year 2022 in the second stage.

The Coast Guard's determination to deliver the OPCs in a timely manner has driven the program through key acquisition decisions despite significant design, testing, schedule, and cost risks, which remained or were exacerbated after the hurricane (see figure).

Offshore Patrol Cutter Program Moved Forward Despite Major Risks

HL_5_v4-103742

Unstable Design. The Coast Guard authorized the start of construction for the first two OPCs despite not having a stable design, which is inconsistent with shipbuilding best practices. Proceeding towards OPC 3 construction before stabilizing the design—including maturing the design drawings of major ship systems—increases the risk of construction rework if changes are needed. This could further delay schedules and increase costs.

Deficient and Optimistic Schedule. Prior to the construction award for OPC 1, the OPC program's schedule has contained significant deficiencies that are contrary to what is called for in best practices for developing schedules that GAO identified. Further, the revised post-hurricane delivery dates for the first four OPCs are optimistic and do not fully incorporate schedule risks, increasing the likelihood that the OPCs will not be delivered when promised.

Incomplete Cost Estimate. The cost estimate used to inform the program's new cost goals did not include key analyses called for in best practices for developing cost estimates GAO identified. These key analyses include varying assumptions to determine how sensitive the estimates are to various factors and quantifying the effects of potential risks. Omitting these analyses undermines the credibility of the estimated program costs, increasing the risk that decision makers do not have a complete picture of the full range of costs the program could incur.

Why GAO Did This Study

The Coast Guard—a component of the Department of Homeland Security (DHS)—is planning to spend over $12 billion to acquire a fleet of 25 OPCs. This is the component's highest investment priority and will help ensure a variety of missions, such as drug and migrant interdiction, are carried out in offshore waters once its aging Medium Endurance Cutters are decommissioned. After Hurricane Michael—a category 5 storm—significantly disrupted the OPC shipbuilder's ability to continue work in October 2018, DHS granted up to $659 million in extraordinary contractual relief to the shipbuilder.

GAO was asked to review the status of the OPC acquisition program. This report examines, among other objectives, how the Coast Guard revised the OPC program after Hurricane Michael and the extent to which the program addressed major risks—particularly in the areas of design maturity, schedule, and cost— before proceeding through key acquisition decisions both pre- and post-hurricane. GAO reviewed Coast Guard program and contract documents, analyzed Coast Guard data, and interviewed Coast Guard and DHS officials.

Recommendations

GAO is making eight recommendations to the Coast Guard and DHS, including ensuring that the program stabilizes its design before proceeding with construction of the next OPC, updates its schedule to address deficiencies and incorporate risks, and updates its cost estimate to improve its credibility.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Homeland Security The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard to revise OPC's acquisition program baseline for stage 1 to include OPC's delivery dates. (Recommendation 1)
Open
In providing comments on this report, DHS concurred with our recommendation and stated that it will direct the Coast Guard to revise the OPC's acquisition program baseline to include stage 1 asset delivery dates for the lead ship and OPC 4. As of June 2023, officials anticipated that the stage 1 acquisition program baseline will be completed in fall 2023. However, as of April 2024, the program's updated baseline for stage 1 has not been approved. The Coast Guard told us that they anticipate approval of the program's stage 1 baseline by June 2024. We will review the stage 1 acquisition program baseline once the Coast Guard provides it and determine whether the actions taken meet the intent of this recommendation.
Department of Homeland Security The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard to include in OPC's acquisition program baseline for stage 2 OPC's delivery dates when the stage 2 acquisition program baseline is established and approved at ADE 2B. (Recommendation 2)
Open
In providing comments on this report, DHS concurred with our recommendation and stated that it will direct the Coast Guard to include delivery dates for OPCs 5 and 25 in the stage 2 acquisition program baseline. As of June 2023, officials said that ADE 2B for stage 2 of the OPC program is projected to occur in fall 2023 at which point the updated baseline will be approved. However, as of April 2024, the program's updated baseline for stage 2 has not been approved. The Coast Guard told us that they anticipate approval of the program's stage 2 baseline by June 2024. We will review the stage 2 acquisition program baseline once the Coast Guard provides it and determine whether the actions taken meet the intent of the recommendation.
United States Coast Guard The Commandant of the Coast Guard should ensure the OPC program demonstrates that the OPC design for stage 1 is stable prior to approval of construction start for OPC 3 by (1) completing ESG's basic and functional designs and (2) maturing the davit technology to a TRL of 7, consistent with shipbuilding best practices. (Recommendation 3)
Closed – Not Implemented
In providing comments on this report, the Coast Guard concurred with our recommendation and stated that it would ensure the OPC design was stable and that davit was matured to at least a TRL of 7 or they would pursue a different davit before awarding OPC 3. However, in April 2021, the OPC program awarded construction on OPC 3 prior to completing the functional design and maturing the davit technology to a TRL of 7. As of June 2021, the functional design remains incomplete and Coast Guard officials said that the program has to wait until operational testing on OPC 1 is completed (expected in late fiscal year 2022) to achieve a TRL of 7 for the davit.
United States Coast Guard The Commandant of the Coast Guard should ensure the Coast Guard Component Acquisition Executive revises Coast Guard's acquisition policy to include criteria and a methodology for demonstrating design maturity for shipbuilding programs that are aligned with shipbuilding best practices, including specifying the completion of basic and functional designs and maturing critical technologies to a TRL of 7. (Recommendation 4)
Open – Partially Addressed
In providing comments on this report, the Coast Guard concurred with our recommendation and stated that it planned to identify guidelines outlining design stability parameters to be reviewed before starting construction of shipbuilding programs. In September 2022, the Coast Guard issued formal guidance on design stability but did not specify full completion of the basic and functional designs or maturation of critical technology to a TRL 7. In April 2023, the Coast Guard revised its guidance to specify that critical technologies should be matured to a TRL of 7 by Production Readiness Review, which occurs right before construction and well after design. However, this is not aligned with shipbuilding best practices which call for programs to require critical technologies to be matured to a TRL 7 before the award of the contract for lead ship design. Additionally, the Coast Guard's revised guidance did not specify full completion of basic and function design consistent with GAO's shipbuilding best practices, which call for programs to achieve completion of the basic and functional ship designs prior to starting construction.
Department of Homeland Security The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard, prior to approval of construction start for OPC 3, to identify the associated cost, schedule, and operational risks of the program's testing strategy for stage 1; and document these analyses in an updated test and evaluation master plan. (Recommendation 5)
Closed – Implemented
In April 2021, the Coast Guard revised the OPC test and evaluation master plan to align with changes in the program's acquisition strategy and schedule and identified the associated cost, schedule, and operational risks with the program's test activities for stage 1.
United States Coast Guard The Commandant of the Coast Guard should ensure the OPC program updates its shipbuilder and government schedules for OPCs 1 through 4 to (1) fully address deficiencies identified in the shipbuilder's schedule, and (2) fully incorporate schedule risk analysis in accordance with schedule best practices. (Recommendation 6)
Open
In providing comments on this report, the Coast Guard concurred with our recommendation and stated that it planned to continuously review ESG's schedules while also pursuing various efforts to develop an integrated government schedule in accordance with GAO's scheduling practices. In April 2022, the Coast Guard and its shipbuilder revised the integrated schedules for OPCs 1-3 and completed the schedule for OPC 4 in December 2022. However, both the Coast Guard and the Defense Contract Management Agency identified that the shipbuilder's updated schedules continue to contain deficiencies and risks, inconsistent with shipbuilding best practices. In April 2024, the Coast Guard told us the program is undergoing a review of the shipbuilder's schedule at the same time as it is updating its acquisition program baseline, both with expected completions by June 2024. We will reassess the program's schedule after its rebaseline.
Department of Homeland Security The DHS Secretary should ensure the DHS Under Secretary for Management directs the Coast Guard, as it develops the next life cycle cost estimate for the OPC program, to update its cost estimate for stage 1 in accordance with best practices for cost estimation, including: (1) conducting a sensitivity analysis, (2) conducting a risk and uncertainty analysis, (3) reflecting information from the program's most recent technical baseline, and (4) conducting an independent cost assessment of the estimate. (Recommendation 7)
Open
In providing comments on this report, DHS concurred with our recommendation and stated that it planned to work with the Coast Guard to ensure that the next full lifecycle cost estimate follows GAO's cost estimating best practices but this will not be developed until fiscal year 2022 in support ADE 2B for stage 2 of the program. In April 2021, the Coast Guard updated the stage 1 annual estimate to reflect actual costs and included a sensitivity and risk analysis and, in June 2021, officials confirmed that the cost estimate developed to support the stage 2 award will include a more comprehensive analysis consistent with GAO practices. As of June 2023, officials anticipate that the stage 2 cost estimate will be completed in fall 2023. We will review the stage 2 ADE 2B cost estimate once the Coast Guard provides it and determine whether the actions taken meet the intent of this recommendation.
United States Coast Guard The Commandant of the Coast Guard should ensure the OPC program improves its risk management processes to follow the format and include content as indicated in DHS acquisition policy and Coast Guard guidance, including (1) holding monthly risk management board meetings and updating its risk register regularly; (2) revising the risk register to include the risks we identified in this report—proceeding into construction with an incomplete 3D model, conducting late operational testing, challenges with ESG's scheduling practices, and challenges with ESG's accounting system; and (3) revising the risk register to comprehensively track risk management information. (Recommendation 8)
Closed – Implemented
In October 2020, the Coast Guard improved the OPC program's risk management processes to follow the format and include content as indicated in the DHS acquisition policy and Coast Guard guidance. This included updates to the OPC program's risk and opportunities management plan and regularly holding meetings to monitor risk. Additionally, the Coast Guard updated its risk register to capture the specific risks we identified in this report and to include supporting information such as mitigation plans to ensure risks are being comprehensively tracked.

Full Report

GAO Contacts

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Topics

Acquisition programsBest practicesCompliance oversightConstruction costsConstruction schedulesContractual reliefCost analysisCost and schedule performanceCost assessmentsCost at completionCost estimatesCost overrunsDesign specificationsDrug interdictionFinancial risksHomeland securityHurricanesOperational testingProduct designProgram evaluationRisk adjustmentsRisk assessmentRisk factorsRisk managementSchedule slippagesShipbuilding