Skip to main content

Water Resources Projects: Army Corps of Engineers Can Further Enhance Acceleration of Feasibility Studies

GAO-19-561 Published: Jul 29, 2019. Publicly Released: Jul 29, 2019.
Jump To:

Fast Facts

The Army Corps of Engineers undertakes water resources projects to reduce the risk of damage from coastal storms, among other things. The Corps first conducts a feasibility study to determine costs, benefits, and whether the project is in the federal interest. Such studies can take years. To accelerate feasibility studies, Congress and the Corps introduced reforms.

The Corps has not fully implemented recent reforms, evaluated the impact of its reforms, or maintained complete data on its feasibility studies.

We recommended developing plans to implement remaining reforms and evaluate the impacts of reforms, and taking other actions.

A waterway with an ongoing Corps feasibility study at Colorado River Locks, TX.

Aerial photo of the area where two rivers meet

Aerial photo of the area where two rivers meet

Skip to Highlights

Highlights

What GAO Found

The U.S. Army Corps of Engineers has taken steps to address some feasibility study acceleration provisions under the Water Resources Reform and Development Act of 2014 (WRRDA 2014) but not others. For example, to implement a provision related to coordination, the Corps in September 2015 issued guidance emphasizing the importance of early coordination with other federal agencies to avoid delays later in the process. However, the Corps has not taken steps to address other provisions, such as one that calls for the Corps to establish a database to make publicly available information on the status of feasibility studies, citing resource constraints. The Corps does not have a plan to address these other provisions. A plan that includes resource estimates would better position the Corps to address the remaining acceleration provisions.

The Corps regularly monitors feasibility studies and has conducted some reviews of its acceleration reforms, such as an analysis that found that some studies were too complex to complete within the agency's timing and cost requirements—i.e., within 3 years and for less than $3 million. However, the Corps has not comprehensively evaluated the reforms' impacts. Corps officials and stakeholders expressed differing views on the reforms' impacts on the costs, time frames, and quality of feasibility studies. For example, many Corps officials GAO interviewed said the reforms' overall goals to reduce studies' cost and time frames were positive, but others raised concerns, such as that the $3 million cost limitation may not be realistic for different geographic areas. Corps officials said they have not conducted a comprehensive impact review in part because they are focused on monitoring ongoing studies. These officials said they see the value in conducting such a review as they complete more studies, but they have not developed a plan to do so. Developing an evaluation plan would help the Corps conduct a timely and effective review.

The Corps has not maintained complete milestone data in its central data system for the 19 feasibility studies GAO reviewed (see figure). For example, 12 studies did not include data for one or more milestones. Corps officials said agency policy requires the entry of information on 10 key milestones in the agency's central data system. However, GAO found that the policy only explicitly requires that two of the key 10 milestones be entered into the agency's central data system. Without clarifying its policy to help ensure officials enter data on all milestones in the central data system, the Corps will not have complete data to efficiently monitor the progress of feasibility studies.

Examples of Waterways with Ongoing Corps Feasibility Studies: Port of Long Beach, CA, and Colorado River Locks, TX

U:\Work in Process\Teams\FY19 Reports\NRE\102756_561\Graphics\Highlight_5_v4_102756-01.tif

Why GAO Did This Study

Water resources development projects undertaken by the Corps—such as those to reduce the risks from coastal storms—historically have taken years or even decades to complete. To implement these projects, the Corps first conducts a feasibility study, which includes an analysis of the federal interest and the costs, benefits, and environmental impacts of a project; such studies can take several years to complete.

WRRDA 2014 requires the Corps to, among other things, conduct activities to accelerate the completion of feasibility studies. The act also includes a provision for GAO to assess acceleration reforms. This report examines the extent to which the Corps has (1) addressed the WRRDA 2014 feasibility study acceleration provisions, (2) reviewed the impact of its feasibility study acceleration reforms, and (3) maintained complete milestone data for its studies. GAO reviewed WRRDA 2014 and Corps documents; reviewed 19 feasibility studies subject to the act's acceleration provisions; analyzed data on key milestones; and interviewed Corps officials and stakeholders.

Recommendations

GAO is making three recommendations to the Department of Defense to direct the Assistant Secretary of the Army for Civil Works to (1) develop a plan with resource estimates to address the remaining WRRDA 2014 provisions, (2) develop a plan to comprehensively evaluate the impacts of the agency's acceleration reforms, and (3) clarify its policy to help ensure district officials enter data on required milestones for feasibility studies in its central data system. The agency concurred with the recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense The Secretary of the Army should direct the Assistant Secretary of the Army for Civil Works to develop an implementation plan that includes resource estimates to address the remaining WRRDA 2014 acceleration provisions. (Recommendation 1)
Open
As of July 2024, officials from the Army Corps of Engineers told us they have made progress to implement this plan but have not yet completed all needed work. We will continue to monitor the Corps' progress.
Department of Defense The Secretary of the Army should direct the Assistant Secretary of the Army for Civil Works to develop a plan to conduct a comprehensive evaluation of the impacts of the agency's feasibility study acceleration reforms. (Recommendation 2)
Open
As of July 2024, officials from the Army Corps of Engineers told us they have made progress to implement this plan but have not yet completed all needed work. We will continue to monitor the Corps' progress.
Department of Defense The Secretary of the Army should direct the Assistant Secretary of the Army for Civil Works to clarify its policy to help ensure district officials enter data on all key milestones for feasibility studies into its central data system. (Recommendation 3)
Closed – Implemented
In December 2019, the Corps included updated information on key milestones for feasibility studies in policies governing its central data system.

Full Report

GAO Contacts

Anne-Marie Fennell
Director
Natural Resources and Environment

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Coastal zone managementEnvironmental impact statementsEnvironmental impactsEnvironmental reviewWater resourcesWater resources developmentEngineersAgency evaluationsFederal agenciesDatabase management systems