Skip to main content

NASA Human Space Exploration: Integration Approach Presents Challenges to Oversight and Independence

GAO-18-28 Published: Oct 19, 2017. Publicly Released: Oct 19, 2017.
Jump To:

Fast Facts

NASA is developing 3 programs to put astronauts into space—the Orion crew vehicle, Space Launch System, and Exploration Ground Systems. All 3 programs must work together.

We found challenges in NASA's approach to integrating these programs. For example, the technical authorities for engineering and safety also have program roles that include managing resources. When technical authorities must also deal with cost and schedule pressures, it can potentially impair their independence. A review board concluded this type of tension contributed to the 2003 Columbia shuttle accident.

We made recommendations to strengthen oversight and independence.

Competing Interests between Engineering Technical Authority Role and Program Role

Dual, competing interests of engineering technical authority and program authority positions

Dual, competing interests of engineering technical authority and program authority positions

Skip to Highlights

Highlights

What GAO Found

The approach that the National Aeronautics and Space Administration (NASA) is using to integrate its three human spaceflight programs into one system ready for launch offers some benefits, but it also introduces oversight challenges. To manage and integrate the three programs—the Space Launch System (SLS) vehicle; the Orion crew capsule; and supporting ground systems (EGS)—NASA's Exploration Systems Development (ESD) organization is using a more streamlined approach than has been used with other programs, and officials GAO spoke with believe that this approach provides cost savings and greater efficiency. However, GAO found two key challenges to the approach:

  • The approach makes it difficult to assess progress against cost and schedule baselines. SLS and EGS are baselined only to the first test flight. In May 2014, GAO recommended that NASA baseline the programs' cost and schedule beyond the first test flight. NASA has not implemented these recommendations nor does it plan to; hence, it is contractually obligating billions of dollars for capabilities for the second flight and beyond without establishing baselines necessary to measure program performance.
  • The approach has dual-hatted positions, with individuals in two programmatic engineering and safety roles also performing oversight of those areas. As the image below shows, this presents an environment of competing interests.

Competing Interests between Engineering Technical Authority Role and Program Role

Competing Interests between Engineering Technical Authority Role and Program Role

These dual roles subject the technical authorities to cost and schedule pressures that potentially impair their independence. The Columbia Accident Investigation Board found in 2003 that this type of tenuous balance between programmatic and technical pressures was a contributing factor to that Space Shuttle accident.

NASA has lowered its overall cross-program risk posture over the past 2 years, but risk areas—related to software development and verification and validation, which are critical to ensuring the integrated body works as expected—remain. For example, delays and content deferral in Orion and SLS software development continue to affect ground systems software development and could delay launch readiness. GAO will continue to monitor these risks.

Why GAO Did This Study

NASA is undertaking a trio of closely related programs to continue human space exploration beyond low-Earth orbit. All three programs (SLS, Orion, and EGS) are working toward a launch readiness date of no earlier than October 2019 for the first test flight. Each program is a complex technical and programmatic endeavor. Because all three programs must work together for launch, NASA must integrate the hardware and software from the separate programs into a working system capable of meeting its goals for deep space exploration.

The House Committee on Appropriations report accompanying H.R. 2578 included a provision for GAO to assess the progress of NASA's human space exploration programs. This report assesses (1) the benefits and challenges of NASA's approach for integrating these three programs and (2) the extent to which cross-program risks could affect launch readiness. GAO examined NASA policies, the results of design reviews, risk data, and other program documentation and interviewed NASA and other officials.

Recommendations

Congress should consider directing NASA to establish baselines for SLS and EGS's missions beyond the first test flight. NASA's ESD organization should no longer dual-hat officials with programmatic and technical authority responsibilities. NASA partially concurred with our recommendation and plans to address it in the next year. But NASA did not address the need for the technical authority to be independent from programmatic responsibilities for cost and schedule. GAO continues to believe that this component of the recommendation is critical.

Matter for Congressional Consideration

Matter Status Comments
Congress should consider requiring the NASA Administrator to direct the Exploration Systems Development organization within the Human Exploration and Operations Mission Directorate to establish separate cost and schedule baselines for work required to support SLS and EGS for Exploration Mission 2 and establish separate cost and schedule baselines for each additional capability that encompass all life cycle costs, to include operations and sustainment. (Matter for Consideration 1)
Closed – Implemented
The House Committee on Appropriations included language in the Commerce, Justice, Science, And Related Agencies Appropriations Bill for Fiscal Year 2020 directing NASA to establish cost and schedule baselines for SLS and EGS for Exploration Mission-2 and to establish separate cost and schedule baselines for each additional capability of SLS, Orion, and EGS that encompass all lifecycle costs, to include operations and sustainment.

Recommendations for Executive Action

Agency Affected Recommendation Status
Exploration Systems Development Division
Priority Rec.
Exploration Systems Development should no longer dual-hat individuals with both programmatic and technical authority responsibilities. Specifically, the technical authority structure within Exploration Systems Development should be restructured to ensure that technical authorities for the Offices of the Chief Engineer and Safety and Mission Assurance are not fettered with programmatic responsibilities that create an environment of competing interests that may impair their independence. (Recommendation 1)
Closed – Implemented
NASA partially agreed with this recommendation. NASA stated that it created the technical authority governance structure after the Columbia Accident Investigation Board report and that the dual-hat technical authority structure has been understood and successfully implemented within Exploration Systems Development. NASA recognized, however, that as the program moves from the design and development phase into the integration and test phase, it anticipates that the Exploration Systems Development environment will encounter more technical issues that will, by necessity, need to be quickly evaluated and resolved. As a result, NASA has taken steps to separate technical authority positions from programmatic positions-for engineering in February 2018 and for safety in March 2019.

Full Report

GAO Contacts

Topics

Performance managementProgram managementRisk assessmentSoftwareSoftware verification and validationSpace explorationStrategic planningCost savingsProgram coordinationExploration