Skip to main content

Information Technology: HUD Needs to Address Significant Weaknesses in Its Cost Estimating Practices

GAO-17-281 Published: Feb 07, 2017. Publicly Released: Feb 07, 2017.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The cost estimates that the Department of Housing and Urban Development (HUD) developed for the four selected information technology (IT) investments were unreliable and, thus, lacked a sound basis for informing the department's investment and budgetary decisions. GAO's Cost Estimating and Assessment Guide (Cost Guide) defines best practices that are associated with four characteristics of a reliable estimate—comprehensive, well documented, accurate, and credible. However, none of the cost estimates for the selected investments exhibited all of these characteristics. Only one estimate—for the Customer Relationship Management investment—more than minimally met best practices associated with any of the four characteristics because it partially met the practices for a comprehensive and accurate estimate. The remaining three investments minimally or did not meet the best practices associated with the four characteristics. For example, the Enterprise Data Warehouse estimate minimally met all four characteristics; the Enterprise Voucher Management System estimate did not meet the characteristic for being accurate and minimally met the other three characteristics; and the Federal Housing Administration Automation and Modernization estimate did not meet the characteristic for being credible, while minimally meeting the remaining characteristics (see table).

GAO's Assessment of Cost Estimates for Selected Information Technology (IT) Investments at the Department of Housing and Urban Development (HUD)

Characteristic

Customer Relationship Management

Enterprise Data Warehouse

Enterprise Voucher Management System

Federal Housing Administration Automation and Modernization

Comprehensive

Well-documented

Accurate

Credible

Legend: ●=Fully met ◕=Substantially met ◑=Partially met ◔=Minimally met ○=Not met

Source: GAO analysis of data provided by HUD officials. | GAO-17-281

The significant weaknesses in the cost estimates for the selected investments can largely be attributed to the department's lack of guidance for developing reliable cost estimates. HUD officials responsible for the selected investments stated that the department had not required the development of estimates that exhibit the four characteristics of a reliable estimate. As a result, according to these officials, cost estimating practices have been decentralized and inconsistent across the department. While HUD drafted guidance in June 2015 that was intended to conform to the best practices in GAO's Cost Guide, the department has not yet finalized the guidance because it has focused on establishing the infrastructure needed to support improved cost estimation practices. Until HUD finalizes and ensures the implementation of guidance to improve its cost estimating practices, the department is at risk of continuing to make investment decisions based on unreliable information.

Why GAO Did This Study

HUD relies extensively on IT to deliver services and manage programs in support of its mission. For fiscal year 2017, HUD requested $36 million for IT investments intended to deliver modernized enterprise-level capabilities that better support the department's mission. Critical to the success of such efforts is the department's ability to develop reliable cost estimates that project life-cycle costs and provide the basis for, among other things, informed decision making and realistic budget formulation.

The joint explanatory statement that accompanied the Consolidated and Further Continuing Appropriations Act, 2015, included a provision for GAO to evaluate HUD's cost estimating practices. This review determined the extent to which HUD implemented cost estimating best practices for selected IT investments. GAO selected four IT modernization investments with the largest portion of requested funding for fiscal year 2017, interviewed relevant agency officials, and analyzed and compared each investment's cost estimate to best practices in the Cost Guide. This guide states that, when most or all of the practices are “fully” or “substantially” met, an estimate is considered reliable.

Recommendations

To improve cost estimating practices, GAO recommends that HUD finalize and implement guidance that incorporates best practices called for in the Cost Guide. HUD concurred with this recommendation.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Housing and Urban Development To increase the likelihood that its IT investments develop reliable cost estimates, the Secretary of HUD should finalize, and ensure the implementation of, guidance that incorporates the best practices called for in the GAO Cost Estimating and Assessment Guide.
Open
HUD agreed with our recommendation. In October 2022, HUD reported that a cost estimation project team has been developed and efforts are underway to address this recommendation; however, an estimated date of completion was not provided. As of August 2024, we have not received any updates regarding the status of HUDs efforts to implement this recommendation. When we confirm what actions the agency has taken to address this recommendation, we will provide updated information.

Full Report

GAO Contacts

Valerie C. Melvin
Managing Director
Information Technology and Cybersecurity

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Topics

Administrative costsAgency missionsCost analysisHousing programsInformation technologyLife cycle costsStrategic information systems planningStrategic planningCost estimatesIT investmentsIT investment management