Skip to main content

DOE and NNSA Project Management: Analysis of Alternatives Could Be Improved by Incorporating Best Practices

GAO-15-37 Published: Dec 11, 2014. Publicly Released: Dec 11, 2014.
Jump To:
Skip to Highlights

Highlights

What GAO Found

GAO identified 24 best practices for analysis of alternatives (AOA)—a process that is a key first step in capital asset acquisition. The process entails identifying, analyzing, and selecting a preferred alternative to best meet the mission need by comparing the operational effectiveness, costs, and risks of potential alternatives. Because no single set of best practices for AOAs was broadly recognized by government and private-sector entities, GAO developed a set of practices by reviewing AOA policies and guidance used by seven public and private-sector entities with experience in the AOA process, and verified these practices with subject matter experts. These best practices include, among other things, defining functional requirements based on mission need, conducting the AOA without a predetermined solution, including the status-quo alternative, and conducting an independent review of the entire AOA process. These practices can be applied to a wide range of activities, projects, and programs.

The Department of Energy's (DOE) requirements and guidance—found in the agency's orders and associated guides—for conducting an AOA do not conform to the 24 best practices GAO identified. Therefore, DOE does not have assurance that applying these requirements and guidance may lead to reliable AOAs. GAO's review of DOE's requirements for AOAs found that they conform to only 1 of the 24 best practices: the practice of defining functional requirements based on mission need. GAO's review of DOE's requirements combined with associated guidance—which includes nonmandatory approaches for meeting requirements—found that they conform to 9 of the 24 best practices. For example, DOE's guidance suggests identifying and considering at least three viable alternatives, including the status quo—a best practice that is not included in the requirements. Federal standards for internal control related to risk assessment call for agency management to decide on actions to mitigate identified risks. Without developing a reliable AOA process, DOE may not be successful in mitigating the risk it has identified related to this process.

DOE's requirements and guidance for AOAs also apply to the National Nuclear Security Administration (NNSA), a separately organized agency in DOE. For three recent NNSA projects that GAO reviewed, NNSA did not conform to most of the best practices GAO identified for conducting AOAs, therefore, raising concerns about the reliability of these AOAs. Specifically, for the three projects' AOAs, NNSA conformed to 6, 8, and 11 of the 24 identified best practices, respectively. For all three projects, NNSA consistently followed the one DOE requirement that conformed to a best practice—to define functional requirements based on mission need. DOE and NNSA officials acknowledge that unreliable AOAs are a risk factor for major cost increases and schedule delays for NNSA projects. As GAO has previously reported, NNSA has spent billions of dollars designing and partially constructing projects with an estimated cost of $750 million or more, only to later reassess alternatives. Without a process to develop reliable AOAs, NNSA may continue on this path and continue to have limited assurance that it is selecting alternatives that best meet its mission needs and will not result in major cost increases and schedule delays in the future.

Why GAO Did This Study

NNSA manages numerous programs that require the design and construction of one-of-a-kind facilities. NNSA's selection of preferred alternatives for these projects is governed by DOE requirements and guidance related to conducting an AOA. In recent years, NNSA has incurred substantial cost increases and schedule delays for such projects.

GAO was mandated to review the AOA process applied by NNSA. This report (1) identifies and describes AOA best practices, (2) determines the extent to which DOE requirements and guidance for conducting an AOA conform to AOA best practices, and (3) determines the extent to which NNSA conformed to best practices and followed certain DOE requirements and guidance in conducting the AOAs for recent NNSA projects.

To do this work, GAO examined relevant AOA guidance from the public and private sectors and DOE's AOA requirements and guidance, sought input from AOA experts, and interviewed agency officials. GAO reviewed three AOAs that NNSA completed or was scheduled to complete between November 2010 and September 2014.

Recommendations

GAO recommends that DOE incorporate best practices into its AOA requirements. DOE agreed with this recommendation.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Energy
Priority Rec.
To minimize the risk of developing unreliable AOAs and incurring major cost increases and schedule delays on projects, the Secretary of Energy should direct DOE's Office of Acquisition and Project Management to update its project management order requirements to incorporate best practices for conducting an AOA.
Closed – Implemented
In May 2016, DOE updated its project management order (Order 413.3B) to require that the Analysis of Alternatives (AOA) for capital asset acquisition projects be consistent with published GAO best practices. DOE also planned to issue an AOA guide that would provide DOE procedures for conducting reliable AOAs. According to a DOE official, development of the guide is on hold indefinitely, along with all other actions to publish new or update existing departmental directives in response to the two Presidential Executive Orders issued in January and February 2017 that directed federal agencies to, among other things, reduce and reform agency regulations. Instead of a guide, DOE issued an AOA handbook in April 2017. The handbook meets the intent of our recommendation.

Full Report

GAO Contacts

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Topics

Agency missionsAssetsBest practicesCapitalCost overrunsDocumentationInternal controlsProject managementReporting requirementsRequirements definitionRisk managementSchedule slippagesPolicies and procedures