Ford-Class Carriers: Lead Ship Testing and Reliability Shortfalls Will Limit Initial Fleet Capabilities

GAO-13-396 Published: Sep 05, 2013. Publicly Released: Sep 05, 2013.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The Navy faces technical, design, and construction challenges to completing Gerald R. Ford (CVN 78) that have led to significant cost increases and reduced the likelihood that a fully functional ship will be delivered on time. The Navy has achieved mixed progress to date developing CVN 78's critical technologies, such as a system intended to more effectively launch aircraft from the ship. In an effort to meet required installation dates aboard CVN 78, the Navy has elected to produce some of these systems prior to demonstrating their maturity--a strategy that GAO's previous work has shown introduces risk of late and costly design changes and rework, and leaves little margin to incorporate additional weight growth in the ship. In addition, progress in constructing CVN 78 has been overshadowed by inefficient out-of-sequence work, driven largely by material shortfalls, engineering challenges, and delays developing and installing critical technology systems. These events are occurring in a constrained budget environment, even as lead ship costs have increased by over 22 percent since construction authorization in fiscal year 2008--to $12.8 billion. Additional increases could follow due to uncertainties facing critical technology systems and shipbuilder underperformance.

The Navy's strategy for providing timely demonstration of CVN 78 capabilities is hampered by post-delivery test plan deficiencies, Joint Strike Fighter aircraft delays, and reliability shortfalls affecting key ship systems. Additional risk is introduced due to the Navy's plan to conduct integration testing of key systems with the ship at the same time as initial operational test and evaluation (IOT&E). This strategy will constrain opportunities to implement timely, corrective actions if problems are discovered with key ship systems. In addition, significant discoveries during IOT&E could delay demonstration of ship capabilities. The Joint Strike Fighter, intended to operate with the carrier, has faced delays, and there is the likelihood of costly retrofits to the ship to accommodate the aircraft after CVN 78 is delivered to the Navy. But even after the ship commissions, several key ship systems will continue to face significant reliability shortfalls that will likely increase costs to the government and limit the ship's mission effectiveness. The extent of these limitations will not be known until after IOT&E. GAO contemplated making a recommendation to delay CVN 78 commissioning until the ship successfully completes IOT&E. However, based on additional information provided by DOD, GAO decided not to include this recommendation in the report.

The Navy and shipbuilder are implementing process improvements aimed at reducing the cost of the follow-on ship, John F. Kennedy (CVN 79), ahead of the main construction contract award for that ship, currently planned for September 2013. CVN 79 is to be of nearly identical design to CVN 78. The shipbuilder plans to employ a new, more efficient build strategy, but remaining technical and design risks with the lead ship could interfere with the Navy's ability to achieve its desired cost savings for CVN 79. These uncertainties also affect the soundness of the Navy's current CVN 79 cost estimate, which is optimistic. These factors, when coupled with the existing sole source environment for aircraft carrier construction, may compromise the government's negotiating position for CVN 79.

Why GAO Did This Study

The Navy plans to spend over $43 billion to produce three Ford-class aircraft carriers. The lead ship, CVN 78, is under construction, and preparation work is underway for the second, CVN 79. These ships will feature new technologies designed to increase capability and reduce crew size. GAO was asked to evaluate the progress of the Ford class. This report examines (1) technical, design, and construction challenges to delivering the lead ship within budget and schedule estimates; (2) the Navy's test strategy for demonstrating CVN 78's required capabilities; and (3) actions the Navy is taking to improve CVN 79 cost outcomes. GAO analyzed documents related to mission requirements, acquisition plans and performance, and testing strategies, and interviewed Department of Defense (DOD) and contractor officials.

Recommendations

GAO recommends the Secretary of Defense take several actions aimed at ensuring Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, including conducting a cost-benefit analysis of required capabilities and associated costs. GAO is also recommending actions to improve the Navy’s knowledge about CVN 79 capabilities and costs before beginning contract negotiations. DOD concurred with one recommendation, partially concurred with three others, and did not concur with the recommendation to defer CVN 79’s detail design and construction contract award. GAO maintains that DOD’s current schedule for awarding this contract undermines the government’s negotiating position.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense
Priority Rec.
To ensure Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, and to promote the introduction of reliable, warfighting capable ships into the fleet, the Secretary of Defense should direct the Secretary of the Navy to take the following action prior to accepting delivery of Gerald R. Ford CVN 78. The Secretary of Defense should direct the Secretary of the Navy to conduct a cost-benefit analysis on (1) currently required capabilities, including increased sortie generation rates and reduced manning and (2) the time and money needed to field systems to provide these capabilities, in light of known and projected reliability shortfalls for critical systems. This analysis should be informed by demonstrated system performance from land-based testing, including updated reliability growth projections, and should identify trade space among competing cost, schedule, and performance parameters. The analysis should also consider whether the Navy should seek requirements relief from the Joint Requirements Oversight Council, to the extent necessary, to maximize its return on investment to the warfighter. The Navy should report the results of this analysis to Congress within 30 days of CVN 78 commissioning.
Closed – Not Implemented
We recommended that DOD conduct a cost-benefit analysis on currently required capabilities, and report the results to Congress within 30 days of CVN 78 commissioning. DOD agreed with our recommendation for a cost-benefit analysis, but disagreed with the timing of it, stating that it plans to measure CVN 78 capabilities through completion of operational testing after ship delivery. Since the release of our report, the Navy completed cost-benefit analyses to determine the acquisition strategy for CVN 79, making two major changes to the ship (replacing the Dual Band Radar (DBR) with a different radar solution and introducing a phased construction and delivery approach.) While these are major program changes, the department did not evaluate the fundamental reason for conducting a cost-benefit analysis, namely that known and projected reliability shortfalls make it unlikely that the program will achieve its sortie generation requirements. In December 2016, an Independent Review Team commissioned by the Under Secretary of Defense, Acquisition, Technology and Logistics completed a comprehensive assessment of the CVN 78's systems, but did not recommend any capability trade-offs or requirements relief. CVN 78 was commissioned on July 21, 2017. The Navy did not conduct a cost benefit analysis on the ship's currently required capabilities and reliability shortfalls, as we recommended, which could have informed decisions regarding CVN 80. CVN 79 is under construction and CVN 80 has started advanced construction. As a result, we consider this recommendation as closed not implemented.
Department of Defense
Priority Rec.
To ensure Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, and to promote the introduction of reliable, warfighting capable ships into the fleet, the Secretary of Defense should direct the Secretary of the Navy to take the following action prior to accepting delivery of CVN 78. The Secretary of Defense should direct the Secretary of the Navy to update the Ford class program's test and evaluation master plan to account for developmental testing outcomes experienced since 2013 and ensure that sufficient time is allotted post-delivery to complete developmental testing activities deferred from land to sea prior to initiating integration testing.
Closed – Not Implemented
DOD accepted delivery of CVN 78 on 30 May 2017. DOD agrees that sufficient time should be allotted after ship delivery to complete developmental testing and plans to update the test plan in February 2018. Further, the delay in ship delivery until May 2017 did allow more time for developmental testing, but land-based testing was still not completed before integration testing began. Since the ship has now been delivered, but the test plan was not updated, we consider this recommendation closed but not implemented.
Department of Defense
Priority Rec.
To ensure Ford-class carrier acquisitions are supported by sound requirements and a comprehensive testing strategy, and to promote the introduction of reliable, warfighting capable ships into the fleet, the Secretary of Defense should direct the Secretary of the Navy to take the following action prior to accepting delivery of CVN 78. The Secretary of Defense should direct the Secretary of the Navy to adjust the planned post-delivery test schedule to ensure that system integration testing is completed prior to entering initial operational test and evaluation.
Closed – Not Implemented
The Navy partially agreed with this recommendation, and Navy officials indicated they plan to manage the overlap by only conducting operational testing on systems that had completed integrated testing. As of July 2018, the CVN 78 schedule still shows integrated testing will continue after the start of initial operational test and evaluation. We consider this recommendation closed-not implemented, since the Navy accepted delivery of CVN 78 in May 2017 and the Navy has no plans to complete integrated testing prior to starting initial operational test and evaluation.
Department of Defense To improve the Navy's ability to manage the costs and schedule of John F. Kennedy CVN 79 detail design and construction, the Secretary of Defense should direct the Secretary of the Navy to defer the CVN 79 detail design and construction contract award until land-based testing for critical, developmental ship systems including the dual band radar, advanced arresting gear, and EMALS is completed.
Closed – Implemented
Although DOD did not initially concur with our recommendation to defer award of the CVN 79 detail design and construction contract, the program deferred contract award until the first quarter of fiscal year 2015, consistent with recommendations we made. According to the Navy, continuing contract negotiations provide an opportunity to incorporate process improvements into construction plans.
Department of Defense
Priority Rec.
To improve the Navy's ability to manage the costs and schedule of CVN 79 detail design and construction, during the recommended deferral period, the Secretary of Defense should direct the Secretary of the Navy to update the Navy's CVN 79 cost estimate on the basis of actual costs and labor hours associated with CVN 78 construction to determine whether the preliminary information and assumptions remain relevant and accurate.
Closed – Implemented
DOD agreed with our recommendation to update CVN 79's cost estimate on the basis of actual costs and labor hours associated with CVN 78 construction. As of October 2016, the Department had updated the CVN 79 cost estimate in support of the decision to award the CVN 79 construction contract in April 2015. According to the department, the cost estimate reflects actual costs and labor hours associated with CVN 78 construction, but takes into account changes in the construction process and the two-phase delivery approach for CVN 79.

Full Report

GAO Contacts

Michele Mackin
Managing Director
Contracting and National Security Acquisitions