Skip to main content

Information Security: Federal Communications Commission Needs to Strengthen Controls over Enhanced Secured Network Project

GAO-13-155 Published: Jan 25, 2013. Publicly Released: Feb 01, 2013.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The Federal Communications Commission (FCC) did not effectively implement appropriate information security controls in the initial components of the Enhanced Secured Network (ESN) project. Although FCC took steps to enhance its ability to control and monitor its network for security threats, weaknesses identified in the commission's deployment of components of the ESN project as of August 2012 resulted in unnecessary risk that sensitive information could be disclosed, modified, or obtained without authorization. This occurred, in part, because FCC did not fully implement key information security activities during the development and deployment of the initial components of the project. While FCC policy is to integrate security risk management into system life-cycle management activities, the commission instead deployed the initial components of the ESN project without, among other things, first selecting and documenting the security controls, assessing the controls, or authorizing the system to operate. As a result of these deficiencies, FCC's information remained at unnecessary risk of inadvertent or deliberate misuse, improper disclosure, or destruction. Further, addressing these deficiencies could require costly and timeconsuming rework.

FCC's efforts to effectively manage the ESN project were hindered by its inconsistent implementation of procedures for estimating costs, developing and maintaining an integrated schedule, managing project risks, and conducting oversight. If not addressed, these weaknesses could pose challenges for the commission to achieve the project's goal of improved security. Specifically, FCC

  • had not developed a reliable life cycle cost estimate for ESN that includes all implementation costs;
  • did not, in its project schedule, adequately identify the sequence in which activities must occur, ensure that detailed activities were traceable to higherlevel activities, or establish a baseline schedule;
  • documented and managed some risks to project success, but its prime contractor did not identify any project risks until after the deployment of the initial components of the ESN project had begun; and
  • had not included the ESN project in its processes for conducting regular oversight of information technology projects.

According to FCC officials, a key reason that they had not fully applied their policies or widely accepted best practices for security risk management and project management is because the ESN project was an emergency project and, therefore, needed to be initiated quickly. However, while GAO agrees that the security threat makes implementation urgent, it does not negate the need to perform key security risk management activities. Unless FCC more effectively implements its IT security policies and improves its project management practices and effectively applies them to the ESN project, unnecessary risk exists that the project may not succeed in its purpose of effectively protecting the commission's systems and information.

Why GAO Did This Study

In September 2011, FCC discovered that it had experienced a security breach on its computer network, which potentially allowed sensitive information to be compromised. The commission initiated the ESN project to implement enhanced security controls and an improved network architecture to defend against cyber attacks and reduce the risk of a successful future attack. GAO was asked to assess the extent to which FCC has (1) effectively implemented appropriate information security controls for the initial components of the ESN project, and (2) implemented appropriate procedures to manage and oversee its ESN project. To do so, GAO determined the effectiveness of ESN security controls by evaluating control configurations and identifying management controls; and determined how FCC applied them to the ESN project by analyzing documentation and interviewing commission officials.

Recommendations

GAO is making seven recommendations to the FCC to implement management controls to help ensure that ESN meets its objective of securing FCC's systems and information. In commenting on a draft of this report, FCC concurred with the recommendations. In a separate report with limited distribution, GAO is also making 26 recommendations to resolve technical information security weaknesses related to access controls and configuration management of the ESN.

Recommendations for Executive Action

Agency Affected Recommendation Status
Federal Communications Commission To help strengthen Information Technology (IT) and project management controls over the ESN project, the Chairman of the FCC should perform key security risk management activities for the ESN project including selecting and documenting the security controls, assessing the implementation of the controls, and authorizing the system to operate.
Closed – Implemented
We verified that, based on our findings and recommendations as a factor in the decision, FCC decommissioned the ESN project in order to pursue a solution intended to better meet the project's initial objective of securing FCC's systems and information. Based on this action, we are closing this recommendation as implemented.
Federal Communications Commission To help strengthen IT and project management controls over the ESN project, the Chairman of the FCC should conduct appropriate gate reviews, such as the Requirements Approval, at major transition points in the project.
Closed – Implemented
We verified that, based on our findings and recommendations as a factor in the decision, FCC decommissioned the ESN project in order to pursue a solution intended to better meet the project's initial objective of securing FCC's systems and information. Based on this action, we are closing this recommendation as implemented.
Federal Communications Commission To help strengthen IT and project management controls over the ESN project, the Chairman of the FCC should develop a life-cycle cost estimate for the ESN project that reflects current project status.
Closed – Implemented
We verified that, based on our findings and recommendations as a factor in the decision, FCC decommissioned the ESN project in order to pursue a solution intended to better meet the project's initial objective of securing FCC's systems and information. Based on this action, we are closing this recommendation as implemented.
Federal Communications Commission To help strengthen IT and project management controls over the ESN project, the Chairman of the FCC should establish an integrated and reliable master schedule for the ESN project.
Closed – Implemented
We verified that, based on our findings and recommendations as a factor in the decision, FCC decommissioned the ESN project in order to pursue a solution intended to better meet the project's initial objective of securing FCC's systems and information. Based on this action, we are closing this recommendation as implemented.
Federal Communications Commission To help strengthen IT and project management controls over the ESN project, the Chairman of the FCC should document, evaluate, and manage all identified project risks in a risk management process, and document mitigation strategies for all risks.
Closed – Implemented
We verified that, based on our findings and recommendations as a factor in the decision, FCC decommissioned the ESN project in order to pursue a solution intended to better meet the project's initial objective of securing FCC's systems and information. Based on this action, we are closing this recommendation as implemented.
Federal Communications Commission To help strengthen IT and project management controls over the ESN project, the Chairman of the FCC should commit to a time frame for establishing commission guidance on project management, including cost estimating, scheduling, and risk management.
Closed – Implemented
We verified that FCC has established standard operating procedures related to project management. These guidance documents instruct officials in performing key project management activities, including cost estimating, scheduling, and project scope management.
Federal Communications Commission To help strengthen IT and project management controls over the ESN project, the Chairman of the FCC should monitor and oversee the ESN project on a regular basis and ensure that project data used for this purpose are current and valid.
Closed – Implemented
We verified that, based on our findings and recommendations as a factor in the decision, FCC decommissioned the ESN project in order to pursue a solution intended to better meet the project's initial objective of securing FCC's systems and information. Based on this action, we are closing this recommendation as implemented.

Full Report

GAO Contacts

Valerie C. Melvin
Managing Director
Information Technology and Cybersecurity

Gregory C. Wilshusen
Director
Information Technology and Cybersecurity

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Topics

Risk managementInformation securityProgram managementCyber securityCost and scheduleSystems acquisitionAuditsInformation systemsLife cycle costsSensitive data