Skip to main content

Suspension and Debarment: DOD Has Active Referral Processes, but Action Needed to Promote Transparency

GAO-12-932 Published: Sep 19, 2012. Publicly Released: Sep 19, 2012.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The four Department of Defense (DOD) components GAO examined have active processes for referring identified cases of contractor misconduct for appropriate action, including suspension or debarment. The components identify numerous cases of actual or alleged contractor misconduct each year from various internal and external sources. The figure below shows the process for identifying and referring cases to the suspension and debarment official for consideration.

DOD received hundreds of leads on contractor misconduct from sources such as lawsuits against contractors or contractor disclosures in fiscal years 2009 through 2011, although it is not possible to know the full extent of potential leads. Some cases are referred to suspension and debarment officials for their consideration or to other agencies for further action. GAO’s analysis of selected cases shows that DOD follows its procedures for identifying and referring cases involving contractor misconduct or poor performance for possible suspension and debarment.

Once a case is referred, DOD generally makes suspension and debarment decisions in accordance with the discretion provided by the Federal Acquisition Regulation (FAR). GAO found in reviewing 75 case files that DOD generally maintained adequate records, informed the contractor of the cause and rationale for its decisions, and provided notice of the action to the contractor as required by the FAR. Given the discretion provided by the FAR, suspension and debarment periods vary based on the circumstances of the case, as do the reasons for removing contractors from the suspension and debarment list. For example, the FAR provides that the period of debarment generally should not exceed 3 years, but notes that the debarment period must be for a period commensurate with the seriousness of the cause. GAO found that nearly half the contractors DOD debarred during fiscal years 2009 through 2011 had debarment periods that exceeded 3 years.

The FAR prohibits all agencies from doing business with suspended or debarred contractors unless there is a compelling reason for doing so. The four DOD components made 14 compelling reason determinations during fiscal years 2009 through 2011. In none of these cases, however, did the components provide notice of their compelling reason determinations to the General Services Administration (GSA), as required by statute and regulation, until GAO raised this as an issue. Component officials said they were uncertain why these determinations which can promote transparency to the public were not forwarded to GSA.

Why GAO Did This Study

DOD spends more than any other federal agency on contracts for goods and services and must be able to protect itself from irresponsible contractors. Once a case of misconduct—such as fraud—is identified, DOD can use suspensions and debarments to prevent irresponsible contractors from receiving new contracts. As requested, GAO determined (1) the extent to which DOD has processes for identifying and referring cases of contractor misconduct for possible suspension or debarment, and (2) how DOD makes suspension and debarment decisions once cases have been referred for potential action. GAO’s review focused on four DOD components—the Departments of the Air Force, Army, Navy (including the U.S. Marine Corps), and Defense Logistics Agency—which together took a total of 3,443 suspension and debarment actions during fiscal years 2009 through 2011, accounting for nearly 100 percent of all such actions in DOD. GAO reviewed DOD and component regulations, procedures, and policies; reviewed case files; analyzed information from federal databases; and interviewed DOD and component officials.

Recommendations

GAO recommends that DOD ensure that DOD components are aware of and comply with the requirement to notify GSA when awarding contracts to suspended or debarred contractors based on compelling reason determinations. DOD concurred with this recommendation.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Defense The Secretary of Defense should direct the Under Secretary of Defense for Acquisition, Technology, and Logistics to ensure that each DOD component is aware of and complies with the requirement to notify the GSA of determinations that a compelling reason exists to do business with a suspended or debarred contractor.
Closed – Implemented
We found that DOD had not been complying with a requirement to provide written notice to GSA when it decides there is a compelling reason to award a contract to a suspended or debarred entity. The availability of the notification of compelling reason determinations is important for transparency to the public not only on the quantity of these determinations but also to demonstrate that compelling reason determinations are carefully considered and used only when necessary. Accordingly we recommended that each DOD component is aware of and complies with the requirement to notify the GSA of these determinations. The Director, Defense Procurement and Acquisition Policy issued a memo dated October 5, 2012,ensuring that each DOD component was aware of the requirement to notify GSA.

Full Report

GAO Contacts

William T. Woods
Director
Contracting and National Security Acquisitions

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Contractor debarmentFederal contractorsMilitary forcesFederal acquisition regulationsDefense AcquisitionGovernment contractsDefense logisticsContract terminationGovernment procurementSuspension and debarment