Skip to main content

Correction of Bid in Which Bidder Inserted Words "Per Month" in Yearly Price Column

B-187132 Nov 17, 1976
Jump To:
Skip to Highlights

Highlights

A company protested the award of a contract for refuse and arbage collection at Eglin AFB, Florida, contending that the awardee inserted a per month amount in the yearly price column of the bid. The contracting officer determined that the winning bid was responsive, and correction of the error did not cause the bid to be nonresponsive.

Downloads

GAO Contacts

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries