Nuclear Waste Cleanup: DOE Faces Project Management and Disposal Challenges with High-Level Waste at Idaho National Laboratory
Fast Facts
Decades of nuclear energy research at the Department of Energy’s Idaho National Laboratory produced two forms of high-level radioactive waste. DOE must treat all 2 million gallons of this waste and prepare it for removal from Idaho by 2035.
DOE finished an on-site treatment facility for one form of this waste in 2012, but initial testing revealed problems and a need for more work. Total project spending approached $1 billion in February. We found DOE could improve how it manages the work. DOE may also need to retrofit the facility to treat the other form of waste.
We made 5 recommendations, including ways to better manage DOE’s facility work.
The Integrated Waste Treatment Unit at the Department of Energy’s Idaho National Laboratory
A large white building with a bright blue sky in the background
Highlights
What GAO Found
The Department of Energy's (DOE) Office of Environmental Management (EM) has not fully followed selected project management best practices in managing the reengineering of the Integrated Waste Treatment Unit (IWTU), shown in the figure, to treat 900,000 gallons of liquid sodium-bearing waste (SBW) that must be solidified for disposal. EM's cost and schedule estimates for IWTU reengineering did not fully meet selected best practices for cost (i.e., did not account for all costs) and schedule estimates (e.g., did not have a valid critical path). For example, EM did not follow best practices for a comprehensive cost estimate because EM did not include both government and contractor costs over the entire project. As of February 2019, EM has experienced approximately $64 million in added costs and a more than 1-year delay in IWTU reengineering. Without fully following best practices for cost and schedule estimates, EM is at risk of future cost overruns and delays in meeting its target disposal milestones.
The Department of Energy's Integrated Waste Treatment Unit at Idaho National Laboratory
Based on GAO's review of EM documents, EM faces challenges with its plans for SBW disposal at its preferred disposal site, the Waste Isolation Pilot Plant (WIPP), an underground repository for waste contaminated by nuclear elements, near Carlsbad, New Mexico. These challenges include a statutory prohibition on the disposal of high-level waste (HLW) at WIPP. Further, EM does not have a strategy or timeline to address these challenges or to identify an alternative disposal pathway. Without such a strategy or timeline, EM risks not meeting its commitments with Idaho to prepare the SBW for removal from the state by 2035.
EM faces challenges implementing its selected technology to further treat 1.2 million gallons of granular calcine waste and selecting a potential waste disposal pathway. For example, DOE has identified challenges with retrofitting the IWTU for calcine waste treatment. As a result, EM is deferring further development of its plans to treat the calcine waste. EM officials said that the agency is making progress toward calcine waste disposal by testing options for removing the waste from its storage bins, a precursor to treating or packaging the waste for disposal. However, EM does not have a strategy or timeline for determining its next steps for the treatment and disposal of calcine waste. Such a strategy could help EM in seeking alternatives to its selected treatment technology and provide assurance that it will meet its commitments with Idaho for removing calcine waste from the state by the end of 2035.
Why GAO Did This Study
Decades of defense activities at DOE's Idaho National Laboratory produced two forms of waste that EM has managed as HLW: liquid SBW and granular calcine waste. Under an agreement with the state, DOE must treat the waste to prepare it for removal from Idaho by 2035. Construction on the IWTU, EM's facility to treat such waste, was completed in 2012, but initial testing of the SBW treatment process revealed design problems. EM has since been working to reengineer the IWTU. Total project construction and reengineering expenditures have reached nearly $1 billion as of February 2019.
GAO was asked to review EM's efforts to treat and dispose of the SBW and calcine waste. This report examines (1) the extent to which EM's management of the IWTU follows selected project management best practices; (2) challenges EM faces in disposing of the SBW; and (3) challenges EM faces in treating and disposing of the calcine waste.
GAO reviewed agency documents and IWTU project data from March 2017 through February 2018, analyzed EM project management efforts against selected project management best practices for cost and schedule, and interviewed DOE officials.
Recommendations
GAO is making five recommendations, including that DOE develop a strategy for the disposal of the waste. DOE generally agreed with all of these recommendations.
Recommendations for Executive Action
Agency Affected | Recommendation | Status |
---|---|---|
Department of Energy | The Secretary of Energy should direct the Assistant Secretary of EM to develop cost estimates for the IWTU reengineering project and the SBW treatment operations that meet best practices for being comprehensive (e.g., account for all costs). (Recommendation 1) |
DOE agreed with our recommendation and provided additional documentation on its cost estimate in July 2023. Based on our analysis of this documentation, DOE has substantially met the best practice of ensuring that the estimate documents all cost-influencing ground rules and assumptions. As a result, DOE has improved the comprehensiveness of its cost estimate for the IWTU reengineering project.
|
Department of Energy | The Secretary of Energy should direct the Assistant Secretary of EM to develop schedule estimates for the IWTU reengineering project and the SBW treatment operations that meet best practices for being well-constructed. (Recommendation 2) |
DOE agreed with our recommendation and provided documentation on its December 2023 schedule. Based on our analysis of this documentation, DOE has substantially met the characteristic of well-constructed. As a result, DOE has improved the construction of its schedule estimate for the IWTU reengineering project and SBW treatment operations.
|
Department of Energy | The Secretary of Energy should direct the Assistant Secretary of EM to follow best practices for ensuring the reliability for the IWTU reengineering project's earned value management system. (Recommendation 3) |
DOE agreed with our recommendation and provided additional documentation of it's earned value management system in November 2021. Based on our analysis of this documentation, DOE has substantially met best practices for ensuring the reliability of data resulting from its earned value management system.
|
Department of Energy | The Secretary of Energy should direct the Assistant Secretary of EM to develop a strategy, including a timeline, for implementing the actions required to achieve its preferred disposal pathway, or an alternative, for the SBW. (Recommendation 4) |
In an update provided by DOE in January 2024, DOE stated that treatment of the SBW started in April 2023 and that the Integrated Waste Treatment Unit had processed approximately 68,000 gallons of waste, or about 8 percent of the total. According to DOE, EM will assess the range of potential strategies and pathways for disposal of the SBW once the waste is treated. Once this effort is completed, GAO will review EM's strategy and timeline for achieving its preferred disposal pathway, or an alternative, and update the status of this recommendation accordingly.
|
Department of Energy | The Secretary of Energy should direct the Assistant Secretary of EM to develop a strategy, including a timeline, to identify and develop a treatment approach for the disposal of the calcine waste to ensure that EM meets the milestone for completing the treatment of this waste by the target date of December 31, 2035. (Recommendation 5) |
In an update provided by DOE in June 2023, DOE stated that based on the results of its updated Analysis of Alternatives for the calcine waste, completed in October 2021, DOE conducted a National Environmental Policy Act (NEPA) Supplemental Analysis in fiscal year 2023. According to DOE, the agency plans to develop a strategy for the treatment of calcine waste based on the results of the Analysis of Alternatives and the NEPA Supplemental Analysis. Once the strategy is completed, GAO will update the status of this recommendation after it has received and analyzed this information.
|