Skip to main content

Discretionary Transportation Grants: DOT Should Take Actions to Improve the Selection of Freight and Highway Projects

GAO-18-38 Published: Nov 02, 2017. Publicly Released: Nov 02, 2017.
Skip to Highlights

Highlights

What GAO Found

In 2016, the Department of Transportation (DOT) developed a multi-phased review and selection process for a new grant program—the Fostering Advancement in Shipping and Transportation for the Long-term Achievement of National Efficiencies (FASTLANE). DOT awarded FASTLANE grants to 18 freight and highway projects. Multiple teams of reviewers evaluated 218 applications based on an evaluation plan that outlined the criteria and process for evaluating applications. GAO found that the awarded projects addressed key program requirements, such as ensuring that at least 10 percent of awarded funds went to small projects and 25 percent to projects located in rural areas.

DOT generally followed the process outlined in the FASTLANE evaluation plan; however the plan resulted in inconsistencies and allowed for broad discretion during certain team reviews. GAO found the Technical Review Teams—teams of modal administration representatives tasked with assessing potential projects against established criteria—used different definitions when assigning technical ratings, likely contributing to scoring variances. In addition, GAO found the evaluation plan gave the Senior Review Team—a team of senior officials responsible for assembling the list of projects for consideration by the Secretary—broad discretion when assembling the list. For example, the evaluation plan and other guidance did not specify the conditions under which the Senior Review Team may take certain actions to potentially advance large projects that did not initially meet certain statutory requirements—likely affecting which projects were forwarded to the Secretary of Transportation to be considered for awards. Without defined procedures in the evaluation plan to ensure all applications are reviewed similarly, DOT may be vulnerable to questions about the integrity of the selection process.

DOT's FASTLANE review process followed some and partially followed other recommended discretionary grant award practices that GAO has previously identified based on Office of Management and Budget and other guidance. For example, DOT followed the practice of assessing applicants' capability to account for funds. However, DOT only partially followed some grant practices, including the recommended practice to document the rationale for award selections. Based on a review of FASTLANE's decision-making documentation, GAO was unable to determine the rationale for selecting the 18 awarded projects. This documentation restated the anticipated benefits of the selected projects, but did not otherwise provide insight into why some projects were selected for awards over others. Without complete documentation of the decision-making, the transparency of the application review and selection process is limited. Further, DOT did not finalize the evaluation plan prior to announcing the solicitation of applications for fiscal year 2016 grants, as required by DOT guidance. In June 2017, DOT announced a new grant program that supersedes the FASTLANE program. According to DOT officials, the solicitation of applications for the new program was also made without an evaluation plan in place, raising concerns the new program may encounter consistency and transparency issues similar to those identified in the FASTLANE program.

Why GAO Did This Study

In December 2015, the Fixing America's Surface Transportation Act (FAST Act) authorized DOT to award $4.5 billion in discretionary grants for fiscal years 2016 through 2020; DOT awarded $759.2 million in fiscal year 2016.

The FAST Act required GAO to assess FASTLANE's processes for selecting grants. This report addresses: (1) the processes used to evaluate and award FASTLANE grants, (2) the extent to which DOT followed its FASTLANE evaluation plan, and (3) the extent to which the process aligned with recommended practices and DOT's own guidance for awarding discretionary grants. GAO reviewed DOT and FASTLANE documentation, analyzed FASTLANE's fiscal year 2016 data, and interviewed DOT officials and 13 FASTLANE applicants selected to include projects of varying sizes, locations, and modes.

Recommendations

GAO is making three recommendations to DOT, including that DOT develop an evaluation plan that clearly defines how review teams apply criteria, assess applications, and assign ratings, among other things before soliciting applications; and that key decisions be documented throughout the application review and selection process. DOT concurred with our recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Transportation The Secretary of Transportation should develop an evaluation plan for the Infrastructure for Rebuilding America (INFRA) program in advance of issuing the notice of funding opportunity and ensure the program's evaluation plan clearly defines how all review teams should apply criteria, assess applications, and assign ratings to ensure that all applications are consistently reviewed. (Recommendation 1)
Closed – Implemented
Federal transportation grants provide critical funding to help build highways, bridges, and port infrastructure. DOT awarded $759.2 million in fiscal year 2016 through the Fostering Advancement in Shipping and Transportation for the Long-term Achievement of National Efficiencies (FASTLANE) grant program. In 2017 GAO reported that DOT generally followed the application review process outlined in the FASTLANE evaluation plan. However, DOT did not finalize the evaluation plan prior to publishing the notice of funding opportunity (NOFO) as required by DOT guidance. DOT's guidance states that grant programs should finalize the evaluation plan prior to publishing a NOFO and make no subsequent...
Department of Transportation The Secretary of Transportation should ensure all program applicants be notified in writing of the outcomes of the application selection process. For unsuccessful applicants, the notification should include a brief explanation of the decision. (Recommendation 2)
Closed – Implemented
Federal transportation grants provide critical funding to help build highways, bridges, and port infrastructure . DOT awarded $759.2 million in fiscal year 2016 through the Fostering Advancement in Shipping and Transportation for the Long-term Achievement of National Efficiencies (FASTLANE) grant program . States and local governments are among the eligible entities that may apply for FASTLANE grants . In 2017, GAO reported that DOT did not inform unsuccessful FASTLANE applicants of their status . GAO had previously found that notifying both successful and unsuccessful applicants of selection decisions in writing, and providing feedback on applications were recommended practices for...
Department of Transportation The Secretary of Transportation should require INFRA program teams document their decision-making rationale throughout all levels of review in the application selection process. (Recommendation 3)
Closed – Implemented
Federal transportation grants provide critical funding to help build highways, bridges, and port infrastructure. DOT awarded $759.2 million in fiscal year 2016 through the Fostering Advancement in Shipping and Transportation for the Long-term Achievement of National Efficiencies (FASTLANE) grant program. Funding for highway and freight projects is highly competitive, as demonstrated by the over 200 applications submitted to the FASTLANE program. States and local governments are among the eligible entities that may apply for FASTLANE grants. In 2017 GAO reported that DOT partially followed the recommended discretionary grant practice for agencies to document the rationale for award...

Full Report

GAO Contacts

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Cost analysisDiscretionary grantsEligibility criteriaEvaluation criteriaGrant administrationGrantsQuality controlProgram evaluationPublic roads or highwaysGrant awardsGrant programsHighway projectsFreight