Skip to main content

Offshore Oil and Gas Resources: Actions Needed to Better Protect Against Billions of Dollars in Federal Exposure to Decommissioning Liabilities

GAO-16-40 Published: Dec 18, 2015. Publicly Released: Jan 19, 2016.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The Department of the Interior (Interior) has developed procedures to oversee the decommissioning of offshore oil and gas infrastructure and estimate costs associated with decommissioning liabilities but has not addressed limitations with its system for tracking cost estimates. According to officials, Interior's procedures include (1) identifying and tracking unused infrastructure, (2) reviewing lessee plans to decommission infrastructure, and (3) using different cost estimates for decommissioning in shallow and deep water. However, inconsistent with internal control standards, Interior officials must manually enter cost estimates into Interior's main data system to override inaccurate estimates automatically calculated by the system. Without a more accurate data system, Interior does not have reasonable assurance that it will consistently estimate the costs associated with decommissioning.

Interior's procedures for obtaining financial assurances for decommissioning liabilities pose financial risks to the federal government, and Interior is planning to revise its procedures to address these risks but has not finalized its approach. As of October 2015, for an estimated $38.2 billion in decommissioning liabilities in the Gulf, Interior officials identified about $2.3 billion in liabilities that may not be covered by financial assurances. However, these officials were unable to determine the extent to which these data were valid due to limitations with Interior's data system, among other things. Of the remaining $35.9 billion in decommissioning liabilities, Interior held or required about $2.9 billion in bonds and other financial assurances, and had foregone requiring about $33.0 billion in bonds for the remaining liabilities. Interior has procedures that allow it to waive its requirement for a lessee to provide a bond if the lessee passes a financial strength test. Prior GAO work has shown that the use of financial strength tests in lieu of bonds poses risks to the federal government. Interior recognizes the risks associated with its procedures, and Interior officials stated that they issued draft guidance to clarify their procedures in September 2015. Interior has not issued any final revisions to its procedures; therefore, it is too soon to evaluate the details of these proposed changes. Until Interior improves its ability to obtain valid data from its data system and revises and implements its financial assurance procedures, the federal government remains at increased risk of incurring costs should lessees fail to decommission oil and gas infrastructure.

Interior faces challenges managing potential decommissioning liability. For example, until December 2015, Interior did not have a requirement for lessees to report on costs associated with decommissioning activities in the Gulf. Instead, Interior contracted studies to obtain data on decommissioning costs, but some data were decades old. Federal internal control standards call for agencies to obtain information from external stakeholders that may significantly affect their ability to achieve agency goals. However, in December 2015, Interior issued final regulations (proposed in 2009) requiring lessees to report data on most, but not all, decommissioning costs to Interior. Unless and until Interior obtains accurate and complete data on decommissioning costs, Interior may not have reasonable assurance that its cost estimates of decommissioning liabilities in the Gulf are accurate, or that it is requiring sufficient amounts of financial assurance based on these estimates.

Why GAO Did This Study

Oil and gas produced on federal leases in the Gulf of Mexico are important to the U.S. energy supply. Historically, most offshore production was in shallow water, but more than two-thirds of the more than 5,000 active oil and gas leases in the Gulf are now located in deep water. When oil and gas infrastructure is no longer in use, Interior requires lessees to decommission it so that it does not pose safety and environmental hazards. Decommissioning can include plugging wells and removing platforms, which can cost millions of dollars. Interior requires lessees to provide bonds or other financial assurances to demonstrate that they can pay these costs; however, if lessees do not fulfill their decommissioning obligations, the federal government could be liable for these costs.

GAO was asked to review Interior's management of liabilities from offshore oil and gas production. This report examines Interior's (1) procedures for overseeing decommissioning and estimating its costs, (2) procedures for obtaining financial assurances for these liabilities, and (3) challenges managing these liabilities. GAO reviewed agency regulations and procedures and interviewed officials from Interior, credit rating agencies, academia, and trade associations.

Recommendations

GAO recommends that Interior take several steps to improve its data system, complete plans to revise its financial assurance procedures, and revise its cost reporting regulations, among other things. Interior concurred with GAO's recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of the Interior To improve the effectiveness of Interior's oversight of the decommissioning process, the Secretary of the Interior should direct the Bureau of Safety and Environmental Enforcement (BSEE) to establish documented procedures for identifying and tracking idle and terminated lease infrastructure.
Closed – Implemented
On August 31, 2016, BSEE issued a directive providing documentation of BSEE's process for identifying and tracking idle and terminated lease infrastructure.
Department of the Interior To better ensure that the government obtains sufficient financial assurances to cover decommissioning liabilities in the event of lessee default, the Secretary of the Interior should ensure that BSEE collects all relevant data associated with decommissioning from lessees.
Closed – Implemented
On November 16, 2016, BSEE issued regulations requiring lessees to submit summaries of actual expenditures incurred for decommissioning oil and gas pipelines on the Outer Continental Shelf. These regulations became effective on December 16, 2016.
Department of the Interior To better ensure that the government obtains sufficient financial assurances to cover decommissioning liabilities in the event of lessee default, the Secretary of the Interior should direct BSEE to establish documented procedures for estimating decommissioning liability.
Closed – Implemented
On April 12, 2017, BSEE issued standard operating procedures on how decommissioning liabilities for wells, platforms/facilities, and pipelines located in Gulf of Mexico Outer Continental Shelf and site clearance verification are estimated, recorded, and disseminated.
Department of the Interior To better ensure that the government obtains sufficient financial assurances to cover decommissioning liabilities in the event of lessee default, the Secretary of the Interior should develop a plan and set a time frame to ensure that Interior's data system for managing offshore oil and gas activities includes processes to accurately and completely record estimated decommissioning liabilities.
Closed – Implemented
In September 2016, the Department of the Interior (DOI) developed a plan and set a time frame to ensure that DOI's data system includes processes to accurately and completely record estimated decommissioning liabilities. According to this plan, DOI will complete work associated with these activities by December 16, 2020.
Department of the Interior To better ensure that the government obtains sufficient financial assurances to cover decommissioning liabilities in the event of lessee default, the Secretary of the Interior should develop a plan and set a time frame to ensure that Interior's data system for managing offshore oil and gas activities will be able to identify, capture, and distribute data on decommissioning liabilities and financial assurances in a timely manner.
Closed – Implemented
In September 2016, DOI developed a plan and set a time frame to ensure that DOI's data system will be able to identify, capture, and distribute data on decommissioning liabilities and financial assurances in a timely manner. According to this plan, DOI will complete work associated with these activities by December 16, 2020.
Department of the Interior To better ensure that the government obtains sufficient financial assurances to cover decommissioning liabilities in the event of lessee default, the Secretary of the Interior should ensure that the Bureau of Ocean Energy Management (BOEM) completes its plan to revise its financial assurance procedures, including the use of alternative measures of financial strength.
Closed – Implemented
On July 18, 2016, DOI issued revised procedures related to financial assurances for offshore oil and gas leases. These revised procedures, which become effective on September 12, 2016, contain several changes to BOEM's policy concerning additional security requirements for leases, pipelines, rights-of-way, and rights-of-use, including the use of alternative measures of financial strength.
Department of the Interior To better ensure that the government obtains sufficient financial assurances to cover decommissioning liabilities in the event of lessee default, the Secretary of the Interior should revise BOEM's regulations to establish a clear deadline for the reporting of transfers to require that lessees report the transfer of rights to lease production revenue.
Closed – Implemented
On March 30, 2016, DOI published final regulations clarifying that the transfer of rights to lease production revenue must be provided to DOI within 90 days after a transfer is executed.

Full Report

GAO Contacts

Frank Rusco
Director
Natural Resources and Environment

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Data collectionData entryData integrityFederal agenciesGas leasesInternal controlsOffshore gas resourcesOffshore oil resourcesOil leasesRisk factorsWaiversCost estimatesFinancial assurancePolicies and procedures