Skip to main content

James Webb Space Telescope: Project Meeting Commitments but Current Technical, Cost, and Schedule Challenges Could Affect Continued Progress

GAO-14-72 Published: Jan 08, 2014. Publicly Released: Jan 08, 2014.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The James Webb Space Telescope (JWST) project is generally executing to its September 2011 revised cost and schedule baseline; however, several challenges remain that could affect continued progress. The National Aeronautics and Space Administration (NASA) has requested funding that is in line with the rebaseline and the project is maintaining 14 months of schedule reserve prior to its launch date. Performance data from the prime contractor indicate that generally work is being accomplished on schedule and at the cost expected; however, monthly performance declined in fiscal year 2013. Project officials have maintained and enhanced project oversight by, for example, continuing quarterly NASA and contractor management meetings and instituting a tool to update cost estimates for internal efforts. Program officials, however, are not planning to perform an updated integrated cost/schedule risk analysis, as GAO recommended in 2012, stating that the project performs monthly integrated risk analyses they believe are adequate. Updating the more comprehensive analysis with a more refined schedule and current risks, however, would provide management and stakeholders with better information to gauge progress.

The JWST project has made progress addressing some technical challenges that GAO reported in 2012, such as inadequate spacecraft mass margin, but others have persisted, causing subsystem development delays and cost increases. For example, the development and delivery schedule of the cryocooler--which cools one instrument--was deemed unattainable by the subcontractor due to technical issues and its contract was modified in August 2013 for the second time in less than 2 years, leading to a cumulative 120 percent increase in contract costs. While recent modifications have been made, execution of the cryocooler remains a concern given that technical performance and schedule issues persist.

Overall the project is maintaining a significant amount of cost reserves; however, low levels of near-term cost reserves could limit its ability to continue to meet future cost and schedule commitments. Development challenges have required the project to allocate a significant portion of cost reserves in fiscal year 2014. Adequate cost reserves for the prime contractor are also a concern in fiscal years 2014 and 2015 given the rate at which these cost reserves are being used. Limited reserves could require work to be extended or work to address project risks to be deferred--a contributing factor to the project's prior performance issues. Potential sequestration and funding challenges on other major NASA projects could limit the project's ability to address near-term challenges.

GAO's analysis of three subsystem schedules determined that the reliability of the project's integrated master schedule--which is dependent on the reliability of JWST's subsystem schedules--is questionable. GAO's analysis found that the Optical Telescope Element (OTE) schedule was unreliable because it could not adequately identify a critical path--the earliest completion date or minimum duration it will take to complete all project activities, which informs officials of the effects that a slip of one activity may have on other activities. In addition, reliable schedule risk analyses of the OTE, the cryocooler, or the Integrated Science Instrument Module schedules were not performed. A schedule risk analysis is a best practice that gives confidence that estimates are credible based on known risks so the schedule can be relied upon to track progress.

Why GAO Did This Study

JWST is one of NASA's most complex and costly science projects. Effective execution of the project is critical given the potential effect further cost increases could have on NASA's science portfolio. The project was rebaselined in 2011 with a 78 percent life-cycle cost estimate increase --now $8.8 billion--and a launch delay of 52 months--now October 2018. GAO has made a number of prior recommendations, including that the project perform an updated cost and schedule risk analysis to improve cost estimates. GAO was mandated to assess the program annually and report on its progress. This is the second such report.

This report assesses the (1) extent to which the JWST project is meeting its cost and schedule commitments and maintaining oversight, (2) current major technological challenges facing the project, (3) extent to which cost risks exist that may threaten the project's ability to execute as planned, and (4) extent to which the JWST project schedule is reliable based on scheduling best practices. GAO reviewed relevant NASA and contractor documents, interviewed NASA and contractor officials, and compared the project schedule with best practices criteria.

Recommendations

Congress should consider directing NASA to perform an updated integrated cost/schedule risk analysis. GAO recommends that NASA address issues related to low cost reserves and perform schedule risk analyses on the three subsystem schedules GAO reviewed. NASA concurred with GAO's recommendations.

Matter for Congressional Consideration

Matter Status Comments
To help ensure that NASA officials are making decisions using up to date and reliable information about the JWST project, Congress should consider requiring the NASA Administrator to direct the JWST project to conduct an updated joint cost and schedule confidence level analysis that is based on a reliable schedule and current risks.
Closed – Not Implemented
Congress has not taken action to require the NASA Administrator to direct the JWST project to conduct an updated joint cost and schedule confidence level analysis based on a reliable schedule and current risks. The FY2017 Appropriations and Authorization Acts do not contain any language directing the JWST Project to conduct a joint cost and schedule confidence level analysis. Since JWST launches in October 2018, we are closing as non-implemented this because there would be no reason to do a joint cost and schedule confidence level analysis with less than a year from launch.

Recommendations for Executive Action

Agency Affected Recommendation Status
National Aeronautics and Space Administration In order to ensure that the JWST project has sufficient available funding to complete its mission and meet its October 2018 launch date and reduce project risk, the NASA Administrator should ensure the JWST project has adequate cost reserves to meet the development needs in each fiscal year, particularly in fiscal year 2014, and report to Congress on steps it is taking to do so.
Closed – Not Implemented
No actions were taken to address this recommendation. JWST Project did not report to Congress on steps it was taking and the JWST project has continued to request budgets consistent with the 2011 replan.
National Aeronautics and Space Administration In order to help ensure that the JWST program and project management has reliable and accurate information that can convey and forecast the impact of potential issues and manage the impacts of changes to the integrated master schedule, the NASA Administrator should perform a schedule risk analysis on OTE, Integrated Science Instrument Module, and cryocooler schedules, as well as any other subschedules for which a schedule risk analysis was not performed. In accordance with schedule best practices, the JWST project should ensure that the risk analyses are performed on reliable schedules.
Closed – Not Implemented
JWST Project provided both the OTE and ISIM schedule risk analyses to GAO. We found these analyses did not meet best practices because they were based on unreliable schedules--counter to the recommendation. The JWST project did not do a cryocooler schedule risk analysis because they had no plans to revise the schedule and with a short period of time remaining on the schedule, we advised the project that the analysis would not be a useful exercise. Since then, events have taken over this recommendation as the contractors have delivered OTE, ISIM, and the cryocooler and the schedules are no longer relevant.

Full Report

GAO Contacts

Cristina T. Chaplain
Director
Contracting and National Security Acquisitions

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

BudgetingCost analysisCost overrunsEarned value management systemsFuture budget projectionsInternal controlsPerformance measuresProgram evaluationProgram managementRisk assessmentSchedule slippagesSpace explorationDelivery schedulesTimelinessBest practicesCost estimatesLife cycle costs