Skip to main content

B-244993.2, B-245521.2, October 9, 1991

B-244993.2,B-245521.2 Oct 09, 1991
Skip to Highlights

Highlights

Bidder's failure under a total small disadvantaged business (SDB) set- aside to certify that all end items to be furnished will be manufactured or produced by a small business concern does not render the firm's bid nonresponsive where the bidder is obligated by another solicitation provision to furnish only SDB end items in its performance of the contract. 2. Which was issued as a total small disadvantaged business (SDB) set-aside. Belknap otherwise was eligible for award. Belknap was not otherwise eligible for award because it failed to certify that all end items to be furnished under the contract would be manufactured by a small business concern. Belknap's bid is nonresponsive because Ft.

View Decision

GAO Contacts

Kenneth E. Patton
Managing Associate General Counsel
Office of the General Counsel

Edward (Ed) Goldstein
Managing Associate General Counsel
Office of the General Counsel

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries