This is the accessible text file for GAO report number GAO-11-705R 
entitled 'Federal Protective Service: Actions Needed to Resolve Delays 
and Inadequate Oversight Issues with FPS's Risk Assessment and 
Management Program' which was released on August 15, 2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

GAO-11-705R: 

United States Government Accountability Office: 
Washington, DC 20548: 

July 15, 2011: 

The Honorable Bennie G. Thompson:
Ranking Member:
Committee on Homeland Security:
House of Representatives: 

Subject: Federal Protective Service: Actions Needed to Resolve Delays 
and Inadequate Oversight Issues with FPS's Risk Assessment and 
Management Program: 

Dear Mr. Thompson: 

The Federal Protective Service (FPS), which is within the Department 
of Homeland Security's (DHS) National Protection and Programs 
Directorate (NPPD), is responsible for protecting the more than 1 
million federal employees and members of the public who work in and 
visit the over 9,000 federal facilities owned or leased by the General 
Services Administration (GSA) from a potential terrorist attack or 
other acts of violence.[Footnote 1] To accomplish its facility 
protection mission, FPS has about 1,200 full-time employees and 
approximately 13,200 contract security guards. FPS has an annual 
budget of about $1 billion and receives its funding from the revenues 
and collections of security fees charged to tenant agencies for 
protective services such as facility security assessments (FSA) and 
providing contract security guard services. Since 2008, we have issued 
numerous reports that address major challenges FPS faces in protecting 
federal facilities. For example, in 2009 and 2010 we reported that FPS 
had problems completing high-quality FSAs in a timely manner and did 
not provide adequate oversight of its contract guard program.[Footnote 
2] 

In September 2007, FPS decided to address the challenges with its 
legacy security assessment and guard management systems with a new 
system. On August 1, 2008, DHS's Immigration and Customs Enforcement 
(ICE) competitively awarded and FPS funded a $21 million, 7-year 
contract to develop and maintain the Risk Assessment and Management 
Program (RAMP) system.[Footnote 3] RAMP is a web-enabled risk 
assessment and guard management system, and its initial implementation 
was scheduled for July 31, 2009. Among other things, RAMP is intended 
to: 

* provide FPS with the capability to assess risks at federal 
facilities based on threat, vulnerability, and consequence, and track 
countermeasures to mitigate those risks; and: 

* improve the agency's ability to monitor and verify that its contract 
security guards are trained and certified to be deployed to federal 
facilities.[Footnote 4] 

In response to your request that we examine RAMP, this report 
addresses the following questions: 

1. What is RAMP's current status, including whether it can be used as 
planned? 

2. What are the factors that contributed to this status? 

3. What are the actions FPS is taking to develop and implement RAMP? 

Scope and Methodology: 

To answer these questions, we reviewed documents from FPS and ICE 
including: RAMP's requirement and project management documents, cost 
estimates, FPS's risk calculator and template, DHS's security 
standards such as the National Infrastructure Protection Plan (NIPP) 
and the Interagency Security Committee's (ISC) Physical Security 
Criteria for Federal Facilities, and RAMP contract files. We reviewed 
FPS's and ICE's requirement and project documents to determine whether 
FPS complied with selected GAO and industry best practices in project 
management such as: managing changes in requirements and conducting 
user acceptance testing in developing and implementing RAMP.[Footnote 
5] These practices were selected because they are critical in 
developing information technology systems. To understand how FPS is 
conducting risk assessments currently, we also reviewed FPS's risk 
calculator and FSA template. We reviewed the original and follow-on 
RAMP contracts and contract documentation files to determine if FPS 
and ICE complied with DHS's acquisition policy and the Federal 
Acquisition Regulation (FAR). 

In addition, we interviewed officials at FPS, ICE, DHS, NPPD, GSA; 
officials from 5 tenant agencies in GSA buildings; the primary RAMP 
contractor; and 7 of FPS's 37 contract guard vendors. We selected 
these contractors based on the number of guards they employed and 
geographic locations. We also visited 2 of FPS's 11 regions and 
interviewed regional directors, commanders, and inspectors about their 
use of RAMP and the FSA template and risk calculator, and observed 
guard post inspections. We selected these regions based on criteria 
such as: number of federal facilities in the region and their facility 
security levels, the number of contract guards in the region, and 
geographic dispersion. Our work is not generalizable to all FPS's 
regions and guard contractors. 

We conducted this performance audit from July 2010 through July 2011 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Results in Brief: 

RAMP is over budget, behind schedule, and cannot be used to complete 
FSAs and reliable guard inspections as intended. RAMP's contract award 
amount totals $57 million, almost three times more than the $21 
million original development contract amount. As of June 2011, FPS has 
spent almost $35 million of the $57 million to develop RAMP. RAMP's 
costs increased in part because FPS changed the original system 
requirements and the contractor had to add additional resources to 
accommodate the changes. FPS also has experienced delays in developing 
and implementing RAMP, as it is almost 2 years behind its original 
July 2009 implementation date. FPS cannot use RAMP to complete FSAs 
because the agency did not verify the accuracy of the federal facility 
data it obtained from GSA or include an edit feature in RAMP that 
would allow inspectors to edit these data when necessary. FPS is also 
experiencing difficulty using RAMP to ensure that its approximately 
13,200 contract guards have met training and certification 
requirements to be deployed at federal facilities because it does not 
have a process for verifying this information before it is entered 
into RAMP. RAMP also does not yet fully incorporate certain government 
security standards. For example, according to an FPS official, RAMP 
does not support the April 2010 ISC Physical Security Criteria for 
Federal Facilities because FPS did not have time to incorporate it in 
the June 2010 version of RAMP.[Footnote 6] FPS is planning to 
incorporate these standards in the next version of RAMP. 

Several factors have contributed to FPS being unable to use RAMP as 
planned. Most importantly, FPS and ICE did not adequately follow GAO's 
project management best practices in developing and implementing RAMP. 
For example, FPS did not manage requirement changes or conduct user 
acceptance testing with its inspectors as part of RAMP's development. 
[Footnote 7] In addition, ICE did not always comply with DHS's 
acquisition policy and the FAR as we found that contractor performance 
evaluations were not completed. Contractor performance evaluations are 
important tools for ensuring that the contractor meets the terms of 
the contract. 

FPS is taking some steps to address RAMP's problems. Most notably, FPS 
has preliminarily decided to discontinue its current RAMP development 
contract and is considering using a new contractor to finish 
developing RAMP. FPS is also working to incorporate ISC's Physical 
Security Criteria for Federal Facilities into RAMP before the next 
version is implemented. Given the technological changes that may have 
occurred since FPS began developing RAMP 4 years ago, there could be 
alternative systems that would better meet FPS's needs. However, FPS 
has not evaluated whether further developing RAMP is the most cost-
beneficial approach compared to possible alternatives. In addition, 
FPS has not developed a plan to address the problems we found with 
RAMP, for example, ensuring the accuracy of federal facility and 
contract guard data. See enclosure I for more information. 

Conclusions: 

After almost 4 years of effort and spending almost $35 million, FPS 
has not accomplished its goals of using RAMP to complete FSAs and 
reliable guard inspections. Consequently, until FPS resolves RAMP's 
problems, FPS will not have a comprehensive method of identifying 
risks to Federal facilities or a reliable method for overseeing its 
contract guard workforce. While FPS plans to take some actions, if it 
does not take additional steps to specifically address the problems we 
found, these problems are likely to continue. It is also crucial that 
FPS take immediate steps to follow project management best practices 
in further development of RAMP or any alternative system. Until FPS 
does so, it risks repeating some of the same mistakes it made during 
the last 4 years, which have resulted in significant expenditures on a 
risk assessment and management system that is not functional. 

Completing the required contractor performance evaluations and 
ensuring that contract files are maintained in accordance with DHS and 
FAR requirements is important. For example, completing the required 
contractor performance evaluations would have provided FPS and ICE 
officials with the ability to assess the contractor's performance 
during key phases of RAMP's development and the opportunity to take 
corrective action if necessary. Maintaining contract files that comply 
with DHS's acquisition policy and the FAR is also important because 
the contract files should contain information that explains the basis 
for key acquisition decisions. 

FPS's ongoing efforts to protect federal facilities should not be 
impeded by its decision to finish developing RAMP, particularly since 
the agency continues to charge GSA and tenant agencies millions of 
dollars to protect their facilities. Thus, it is important that FPS 
not only resolve the problems with RAMP but also, while doing so, 
continue to pursue interim measures to enhance the protection of the 
over 1 million government employees and members of the public that 
visit such facilities each year from a potential terrorist attack or 
other acts of violence. Finally, we agree with FPS that incorporating 
the ISC's Physical Security Criteria for Federal Facilities into RAMP 
is important and encourage FPS to continue its efforts to ensure that 
this happens before the next version of RAMP is rolled out. 

Recommendations for Executive Action: 

Given the challenges FPS faced thus far with developing RAMP, 
technological changes that may have occurred in the last 4 years, and 
to help guide and ensure the successful development and implementation 
of any risk assessment and contract guard management system, we 
recommend that the Secretary of Homeland Security direct the Under 
Secretary of NPPD and the Director of FPS to take the following four 
actions: 

* evaluate whether it is cost-beneficial to finish developing RAMP or 
if other alternatives for completing FSAs and managing security guards 
would be more appropriate, 

* increase the use of project management best practices by managing 
requirements and conducting user acceptance testing for any future 
RAMP development efforts, 

* establish a process for verifying the accuracy of federal facility 
and guard training and certification data before entering them into 
RAMP, and: 

* develop interim solutions for completing FSAs and guard inspections 
while addressing RAMP's challenges. 

To improve contract administration, we recommend that the Secretary of 
Homeland Security direct the Directors of ICE and FPS to complete 
contract performance evaluations for the current RAMP contractor, and 
ensure that the evaluations and other required documents are 
maintained in the contract file in accordance with DHS's acquisition 
policy and the FAR. 

Agency Comments and Our Evaluation: 

We provided a draft of this letter and attached enclosures to DHS for 
comment. DHS concurred with our recommendations and provided technical 
comments that we incorporated where appropriate. 

As agreed upon with your office, unless you publicly announce the 
contents of this report earlier, we plan no further distribution until 
30 days from the report date. At that time, we will send copies of 
this report to appropriate congressional committees, the Secretary of 
Homeland Security, and the Director of the FPS. The report will be 
available at no charge on GAO's website at [hyperlink, 
http://www.gao.gov/]. 

If you or your staff members have any questions about this 
information, please contact me at (202) 512-2834 or 
goldsteinm@gao.gov. Contact points for our Offices of Congressional 
Relations and Public Affairs may be found on the last page of this 
report. Additionally, Tammy Conquest, Assistant Director; Greg Hanna; 
Alicia Loucks; Justin Reed; Amy Rosewarne; Susan Michal-Smith; and 
Frank Taliaferro made key contributions to this report. 

Sincerely yours, 

Signed by: 

Mark Goldstein: 
Director, Physical Infrastructure Issues: 

Enclosures - 4: 

[End of section] 

Enclosure I: RAMP Briefing Report: 

Federal Protective Service: Actions Needed to Resolve Delays and 
Inadequate Oversight Issues with FPS's Risk Assessment and Management 
Program: 

Briefing for the Ranking Member, Committee on Homeland Security,
House of Representatives: 

For more information, contact Mark Goldstein, goldsteinm@gao.gov or 
202-512-2834.  

Overview: 
* Introduction; 
* Background; 
* Objectives; 
* Summary of Results; 
* RAMP Is Over Budget, Behind Schedule, and Cannot Be Used to Complete 
FSAs and Reliable Guard Inspections; 
* FPS Did Not Follow Some Project Management Best Practices in 
Developing and Implementing RAMP; 
* FPS Is Taking Some Steps to Address RAMP's Problems; 
* Conclusions; 
* Recommendations for Executive Action; 
* Agency Comments and Our Evaluation; 

Introduction: 

The Federal Protective Service (FPS), which is within the Department 
of Homeland Security's (DHS) National Protection and Programs 
Directorate (NPPD), is responsible for protecting the more than 1 
million federal employees and members of the public who work in and 
visit the over 9,000 federal facilities owned or leased by the General 
Services Administration (GSA) from a potential terrorist attack or 
other acts of violence'[Footnote 8] To accomplish its facility 
protection mission, FPS has about 1,200 full-time employees and 
approximately 13,200 contract security guards. 

FPS has an annual budget of about $1 billion and receives its funding 
from the revenues and collections of security fees charged to tenant 
agencies for protective services such as conducting facility security 
assessments (FSA) and providing contract guard services.
Since 2008, GAO has issued numerous reports that discuss major 
challenges FPS faces in protecting these facilities. For example, in 
2009 we reported that FPS had problems with completing high-quality 
FSAs in a timely manner and could not comprehensively assess risk 
across federal facilities.[Footnote 9] We also found in 2010 that FPS 
lacked adequate oversight of its contract guard program.[Footnote 10] 

Background: 

In September 2007, FPS decided to replace its legacy facility security 
assessment and guard management systems with a new system. On August 
1, 2008, DHS's Immigration and Customs Enforcement (ICE) competitively 
awarded and FPS funded a $21 million, 7-year (1 base year and 6 option 
years) cost-plus fixed fee contract to develop and maintain the Risk 
Assessment and Management Program (RAMP) system. RAMP is a web-enabled 
risk assessment and guard management system and was to, among other 
things: 

* provide FPS with the capability to assess risks to federal 
facilities based on threat, vulnerability, and consequence, and track 
countermeasures to mitigate those risks; and; 

* improve FPS's ability to monitor and verify that its approximately 
13,200 guards are trained and certified to be deployed to federal 
facilities.[Footnote 11] 

According to the original development contract, RAMP was to be 
designed, developed, and implemented in three phases and completed by 
July 31, 2011. 

* Phase 1 would create a system that would enable a user to conduct
FSAs that would assess risks, calculate a risk score, and recommend 
countermeasures for facilities by July 31, 2009. 

* Phase 2 would add the capability to manage FPS's contract guard 
workforce, including monitoring whether individual guards were 
certified by July 31, 2010. 

* Phase 3 would add more functions to the system, such as providing
FPS with the ability to modify imported GSA facility data and 
assessing risks across FPS's portfolio of federal facilities by July 
31, 2011. 

FPS also developed RAMP to comply with government security standards, 
such as those outlined by DHS's National Infrastructure Protection 
Plan (NIPP) and the Interagency Security Committee (ISC), which were 
not incorporated in FPS's previous risk assessment system. 

* The NIPP sets forth DHS's coordinated approach to protect the 
nation's critical infrastructure and key resources to reduce 
vulnerability, deter threats, and minimize the consequences of attacks 
and other incidents. 

* The ISC Physical Security Criteria for Federal Facilities 
establishes a baseline set of countermeasures to be applied to all 
federal facilities based on their facility security level, and 
provides a framework for customizing security countermeasures to 
address the unique risks faced at each facility. 

Finally, during RAMP's initial development, FPS was part of ICE. ICE 
provided software development and project management technical 
expertise and was responsible for awarding, administering, and 
overseeing the contract. FPS funded RAMP's development and was
responsible for defining RAMP's requirements. 

Objectives: 

Our objectives for this briefing are to discuss: 

(1) RAMP's current status, including whether it can be used as planned; 

(2) factors that contributed to this status; and; 

(3) actions FPS is taking to develop and implement RAMP. 

Summary of Results: 

RAMP is over budget, behind schedule, and cannot be used as intended. 
RAMP's contract award amount totals $57 million, almost three times 
more than the $21 million original development contract amount. As of 
June 2011, FPS has spent almost $35 million of the $57 million to 
develop RAMP. FPS also has experienced delays in developing and 
implementing RAMP, as it is almost 2 years behind its original July 
2009 implementation date. FPS cannot use RAMP to complete FSAs because 
the agency did not verify the accuracy of the federal facility data it 
obtained from GSA or include an edit feature in RAMP that would allow 
inspectors to edit these data when necessary. 

FPS is also experiencing difficulty using RAMP to ensure that its 
approximately 13,200 contract guards have met training and 
certification requirements to be deployed at federal facilities 
because it does not have a process for verifying this information 
before it is entered into RAMP. 

RAMP also does not yet fully incorporate certain government security 
standards. For example, according to an FPS official, RAMP does not 
support the April 2010 ISC Physical Security Criteria for Federal
Facilities because FPS did not have time to incorporate it in the June 
2010 version of RAMP. FPS is planning to incorporate these standards 
in the next version of RAMP. 

Several factors have contributed to FPS being unable to use RAMP as 
planned. Most importantly, FPS and ICE did not adequately follow GAO's 
project management best practices in developing and implementing RAMP. 
[Footnote 12] For example, FPS did not manage requirement changes or 
conduct user acceptance testing with its inspectors as part of RAM P's 
development. In addition, ICE did not always comply with DHS's 
acquisition policy and the Federal Acquisition Regulation (FAR), as we 
found that contractor performance evaluations were not completed. 
Contractor performance evaluations are one of the most important tools 
for ensuring that the contractor meets the terms of the contract. 

FPS is taking some steps to address RAMP's problems. Most notably,
FPS has preliminarily decided to discontinue its current RAMP 
development contract and is considering using a new contractor to 
finish developing RAMP. Given the technological changes that may have 
occurred since FPS began developing RAMP 4 years ago, there could be 
alternative systems that would better meet FPS's needs. However,
FPS has not evaluated whether further developing RAMP is the most cost-
beneficial option compared to possible alternatives. In addition,
FPS has not developed a plan to address the problems we found with
RAMP, for example ensuring the accuracy of federal facility and 
contract guard data. 

Objective 1: What is RAMP's current status? 

RAMP Is Over Budget, Behind Schedule, and Cannot Be Used to Complete 
FSAs and Reliable Guard Inspections: 

RAMP Is Over Budget: 

RAMP's potential costs have increased significantly from the initial 
award amount. RAMP's contract award amount totals $57 million, almost 
three times more than the $21 million original development contract 
amount. As of June 2011, FPS has spent almost $35 million of the $57 
million to develop RAMP. RAMP's costs increased, in part, because: 

* FPS changed the original requirements and the contractor had to add 
additional resources to accommodate them, for example, FPS requested 
that RAMP operate independently of the web; and; 

* unanticipated costs associated with FPS needing to meet DHS's
Office of Security requirement for a more secure laptop occurred. 

RAMP Is Behind Schedule: 

RAMP has been under development for almost 4 years and is currently 
almost 2 years behind its original July 2009 implementation date. FPS 
planned to have the FSA component of RAMP completed by July 31,
2009 and the contract guard inspection module completed by July 31,
2010 as well as provide the capability to modify imported GSA facility 
data and assess risk across FPS's portfolio of federal facilities 
completed by July 31, 2011. However, as of June 2011, FPS cannot 
reliably use RAMP to complete FSAs because the agency did not verify 
the accuracy of the federal facility data it obtained from GSA. See 
enclosure II for a timeline of RAMP's original and actual milestones. 

RAMP Cannot Be Used to Complete FSAs: 

One of the key functions of RAMP was to significantly improve how FPS 
completes FSAs. Specifically, with RAMP, FPS was supposed to be able 
to complete FSAs that were based on threat, vulnerability, and 
consequence. Moreover, FPS would be able to complete FSAs according to 
government security standards. However, FPS officials said RAMP cannot 
be used to complete FSAs because data for federal facilities (e.g., 
the address, government tenants, or the number of floors) obtained from
GSA are either missing or unreliable. In addition, FPS did not design
RAMP to allow inspectors to edit these data from GSA when necessary, 
which would have led to incomplete FSA reports. 

Although GSA officials informed FPS that the facility data had 
limitations and were not designed for FPS's purpose, an FPS official 
stated that the agency chose to use these data in RAMP because they 
were the best source available on federal facilities. However, FPS did 
not verify the completeness or accuracy of the data. We have reported 
that agencies should consider the level of risk associated with using 
data that have missing values in key elements.[Footnote 13] 

Instead of using RAMP to complete FSAs as planned, FPS inspectors are 
using a risk calculator spreadsheet and FSA template document. 
According to FPS guidance, inspectors are to use the calculator to 
determine threat, vulnerability, and consequence information for 
facilities. This information is then entered into the template and 
provided to tenant agencies as a report. There are several issues with 
these tools. First, according to an FPS official, the template does 
not meet the ISC standards because it should associate a facility's 
risks with appropriate countermeasures. Second, because these tools 
produce individual reports and FPS does not aggregate their results, 
the agency's ability to assess risk across its portfolio of federal 
facilities remains limited. 

Third, FPS stakeholders also raised concerns about the FSA risk 
calculator and template. For example, in December 2010, FPS training 
personnel at the Federal Law Enforcement Training Center identified 
problems with the risk calculator and decided not to teach new 
inspectors how to use the FSA risk calculator or template. An FPS area 
commander also said that to identify credible threats using the FSA 
template, inspectors are using the same subjective approach used in
FPS's previous security assessment tool. As a result of the problems 
with this tool, FPS does not currently employ a comprehensive method 
for assessing risk to federal facilities but instead must rely on more 
manual methods until the permanent solution to the problem is 
implemented. 

RAMP Cannot Be Used to Complete Reliable Guard Inspections: 

FPS designed RAMP to help manage its contract guard workforce, 
including conducting guard post inspections, but the agency is 
experiencing difficulty using RAMP to ensure that its approximately 
13,200 contract guards have the required training and certifications 
to be deployed at federal facilities. FPS is using RAMP to conduct 
guard post inspections to ensure that qualified guards are standing 
post, but neither FPS's guard training and certification information 
nor its method for determining the qualification status of contract 
guards in RAMP is reliable. 

FPS does not have reliable information on its contract guards, in part 
because it did not fully verify the accuracy of the guard training and 
certification information from its previous system before migrating it 
into RAMP, as we recommended in 2010.[Footnote 14] In addition, FPS 
relies on guard companies to electronically submit guard training and 
certification information and does not verify these data before they 
are uploaded into RAMP. As a result, some guards may be designated in 
RAMP as unqualified when they are qualified, or as qualified when they 
are unqualified. 

Furthermore, once guard training and certification information is 
uploaded into RAMP, FPS still cannot internally verify this 
information because it no longer maintains physical files. Also, 
inspectors cannot verify this information during guard post 
inspections because FPS no longer requires guards to carry certain 
physical credentials, such as a firearms qualification and training 
certificate. 

According to FPS headquarters officials, each region is required to 
audit 10 percent of each guard company's files each month to determine 
if they contain the required training and certification information. 
However, the process for selecting the 10 percent can vary by region 
and guard company, and FPS does not use the results of those audits to 
verify the information in RAMP. 

In addition to challenges with the reliability of its guard 
information, FPS is also experiencing difficulty using RAMP to 
determine whether a guard is qualified. For example, FPS did not 
design RAMP to: 

* take into account the differences in guard certification 
requirements specified in FPS's 119 contracts; 

* distinguish between newly hired guards in training and guards that 
are unqualified because they have not met training and certification 
requirements; or; 

* account for training and certification records when a guard works 
for more than one company. 

These factors contribute to FPS having limited assurance that RAMP can 
be used to determine whether or not a guard is qualified to stand post 
at a federal facility. We have previously reported that an agency must 
have reliable information relating to its mission on a real-time
basis to effectively manage and control its operations, and should 
ensure that data validation is performed to identify erroneous data. 
[Footnote 15] 

FPS Has Experienced Difficulty Incorporating Certain Government
Security Standards: 

FPS intended for RAMP to support government security standards, such 
as the NIPP, and to implement ISC security standards—both of which 
were lacking in the previous systems. Compliance with DHS's NIPP risk 
assessment framework is important because it ensures that FPS is 
calculating risk in a manner consistent with other agencies with 
federal protection responsibilities. Similarly, compliance with ISC 
standards provides agencies with federal protection responsibilities a 
consistent approach to mitigate risks at federal facilities. 

RAMP meets the NIPP's risk assessment framework by including questions 
to determine the threats, vulnerabilities, and consequences associated 
with a facility, and calculating an overall numerical risk score for 
the facility based on the product of these factors. However, according 
to an FPS official, RAMP does not yet support the April 2010 ISC
Physical Security Criteria for Federal Facilities because FPS did not 
incorporate them in the June 2010 version of RAMP. FPS is planning to 
incorporate these standards in the next version of RAMP. 

Objective 2: What factors contributed to RAMP's current status?  

FPS Did Not Follow Some Project Management Best Practices in 
Developing and Implementing RAMP: 

GAO's project management best practices indicate that agencies should 
manage changes in requirements and conduct user acceptance testing.
FPS did not follow these practices in developing RAMP. For example, 
while FPS originally planned for RAMP Phase 1 to focus on FSAs, FPS 
changed the requirements for this phase to include the development of 
the contract guard module. Additionally, FPS changed RAMP from 
requiring an Internet connection to a system that users could work on 
while not connected to the Internet and that would also meet ICE 
network security standards. The contractor informed FPS that these 
requirement changes were beyond the contract scope and would take more 
time and resources. 

FPS and ICE officials authorized the contractor to add staff to 
implement the changes requested by FPS and resulting additional work, 
but did not agree to extend the deadline for deploying RAMP. This 
authorization resulted in FPS spending the entire $21 million original 
contract amount by April 2010, as opposed to 2015 when the 7-year 
contract was supposed to end. However, this increase in resources was 
not effective, as the contractor could not deliver a functional RAMP 
on this schedule. Our prior work on information technology project 
management indicates that increasing staff to speed up work is 
generally not effective and can actually cause greater delays because 
of the need to coordinate the work and integrate new staff onto the 
project.[Footnote 16] 

Additionally, in order to deploy RAMP in November 2009, FPS and ICE 
did not conduct user acceptance testing with its inspectors, which is 
a GAO project management best practice. Although the contractor 
conducted limited system testing, FPS and ICE did not conduct user 
acceptance testing, which could have identified technical and design 
problems before RAMP was deployed.[Footnote 17] For example, during 
the initial rollout of RAMP, many inspectors had problems logging in 
and thus were not able to use it. In another example, once logged into 
RAMP, some inspectors experienced significant delays because RAMP 
downloaded training and certification information on approximately 
13,200 guards although the inspector did not need all of this 
information. Our previous work indicates that user acceptance and 
system testing help programs meet technical requirements to deliver 
needed capabilities, and proceeding with acquisitions prior to the 
completion of testing can result in delays in achieving technical 
capability.[Footnote 18] 

As part of DHS, ICE and FPS are required to comply with DHS's
Homeland Security Acquisition Regulation and the FAR. For example,
DHS and the FAR require that a performance evaluation be completed 
annually and at the conclusion of the contract for those contracts 
exceeding $100,000. These evaluations are one of the most important 
tools for ensuring that the contractor meets the terms of the contract.
DHS policy also requires contracting officials to consider past 
performance as one of several evaluation factors in awarding new 
contracts. 

However, when we reviewed the original RAMP contract file in March 
2011, we did not find any performance evaluations for the RAMP 
contractor. According to ICE contracting officials, the performance 
evaluations were not completed because developing and implementing an 
initial version of RAMP was the higher priority. 

We also did not find any documentation in the contract files that
ICE took action against the contractor for performance issues, 
although an ICE official provided us with a March 2010 memorandum to 
the contractor indicating performance issues. Specifically, the 
memorandum noted that, as of February 2010, RAMP was over budget, 
behind schedule, and not performing as expected. This memo is the 
first official indication that ICE was not satisfied with the 
contractor's performance. In response to this memo, the contractor 
provided a corrective action plan in April 2010 to address the 
performance issues. 

Finally, although DHS's acquisition policy and the FAR specify that 
the basis for changes to contracts should be documented, we found that 
key decisions regarding the change in RAMP's requirements were not 
documented in the contract files. For example, the justification for the
decision to spend the entire $21 million of the original contract in 
less than 2Y ears was not documented in the contract files. According 
to ICE contracting officials, these documents were also not completed 
because developing and implementing the initial version of RAMP was a 
higher priority. 

Objective 3: What are the actions FPS is taking to develop and 
implement RAMP?  

FPS Is Taking Some Steps to Address RAMP's Problems: 

FPS is taking some steps to address RAMP's problems. For example, 
FPS's Director acknowledges that RAMP is not working, and that 
continuing the current course will not make it functional. As a 
result, FPS has preliminarily decided to discontinue its current 
development contract and is considering a new contractor to finish 
developing RAMP. According to FPS officials, this change will, among 
other things, reduce development costs and increase the functionality 
of RAMP. In addition, FPS plans to conduct user testing with its 
inspectors to ensure that the next version of RAMP functions, 
integrates stakeholder comments, and incorporates ISC standards. 

Given the technological changes that may have occurred since FPS began 
developing RAMP 4 years ago, there may be alternative FSA and guard 
management systems that would better meet FPS's needs. However, FPS 
has not evaluated whether further developing RAMP is the most cost-
beneficial option or if alternative systems would better meet FPS's 
needs. In addition, FPS has not developed a plan to address all the 
problems we found with RAMP, such as ensuring the accuracy of federal 
facility and contract guard data. 

Conclusions: 

After almost 4 years of effort and spending almost $35 million, FPS 
has not accomplished its goals of using RAMP to complete FSAs and 
reliable guard inspections. Consequently, until FPS resolves RAMP's 
problems, FPS will not have a comprehensive method of identifying 
risks to federal facilities or a reliable method for overseeing its 
contract guard workforce. While FPS plans to take some actions, if it 
does not take additional steps to specifically address the problems we 
found, these problems are likely to continue. It is also important 
that FPS take immediate steps to follow project management best 
practices in further development of RAMP or any alternative. Until FPS 
does so, it risks repeating some of the same mistakes it made during 
the last 4 years, which have resulted in a risk assessment and 
management system that is not functional. 

Completing the required contractor performance evaluations and 
ensuring that contract files are maintained in accordance with DHS and 
the FAR is important. For example, completing the required contractor 
performance evaluations would have provided FPS and ICE officials with 
the ability to assess the contractor's performance during key phases 
of RAMP's development and the opportunity to take corrective action if 
necessary. Maintaining contract files that comply with DHS's 
acquisition policy and the FAR is also important because the contract 
files should contain information that explains the basis for key 
acquisition decisions. 

FPS's ongoing efforts to protect federal facilities should not be 
impeded by its decision to finish developing RAMP, particularly since 
the agency continues to charge GSA and tenant agencies millions of 
dollars to protect their facilities. Thus, it is important that FPS 
not only resolve challenges with RAMP but also concurrently pursue 
interim measures to enhance the protection of the over 1 million 
government employees and members of the public that visit such 
facilities each year from a potential terrorist attack or other acts 
of violence. Finally, we agree with FPS that incorporating the ISC 
Physical Security Criteria for Federal Facilities into RAMP is 
important, and encourage FPS to continue its efforts to ensure that 
this happens before the next version of RAMP is rolled out. 

Recommendations for Executive Action: 

Given the challenges FPS faced with developing RAMP, technological 
changes that may have occurred in the last 4 years, and to help guide 
and ensure the successful development and implementation of any future 
risk assessment and contract guard management system, we recommend 
that the Secretary of Homeland Security direct the Under Secretary of 
NPPD and the Director of FPS to take the following four actions: 

* evaluate whether it is cost-beneficial to finish developing RAMP or 
if other alternatives for completing FSAs and managing security guards 
would be more appropriate; 

* increase the use of project management best practices by managing 
requirements and conducting user acceptance testing for future RAMP 
development efforts; 

* establish a process for verifying the accuracy of federal facility 
and guard training and certification data before entering them into 
RAMP; and; 

* develop interim solutions for completing FSAs and guard inspections 
while addressing RAMP's challenges. 

To improve contract administration, we recommend that the Secretary of 
Homeland Security direct the Directors of ICE and FPS to complete 
contract performance evaluations for its current RAMP contractor and 
ensure that the evaluations and other required documents are 
maintained in the contract file in accordance with DHS's acquisition 
policy and the FAR. 

Agency Comments and Our Evaluation: 

We provided a draft of these briefing slides and enclosures to DHS for 
comment. DHS concurred with our recommendations and provided technical 
comments that we incorporated where appropriate. 

[End of briefing slides] 

Enclosure II: Risk Assessment and Management Program (RAMP) Detailed 
Timeline and Capability: 

[Refer to PDF for image: timeline] 

Original milestones: 

April 2007: 
Initial planning. 

August 1, 2008: 
RAMP development contract awarded. 

July 31, 2009: 
End of contract base year and original deadline for release of RAMP 
Phase 1. 

July 31, 2010: 
End of option year 1 and original deadline for release of RAMP Phase 2. 

July 31, 2011: 
End of option year 2 and original deadline for release of RAMP Phase 3. 

July 31, 2012: 
End of option year 3. 

July 31, 2013: 
End of option year 4. 

July 31, 2014: 
End of option year 5. 

July 31, 2015: 
End of option year 6 and original end of RAMP's life cycle. 

Actual schedule: 

April 2007: 
Initial planning. 

August 1, 2008: 
RAMP development contract awarded. 

March 10, 2009: 
Contract modification to provide funding for different laptops. 

May 27, 2009: 
Exercise option period in its entirety, increasing the contract amount. 

November 16, 2009: 
Federal Protective Service (FPS) launches initial version of RAMP. 

November 2009–April 2010: 
RAMP users encounter challenges with the log-in credential process and 
extensive processing time delays following the release of the initial 
version of RAMP. 

December 29, 2009: 
Exercise option years 4, 5, and 6 early. 

April 12, 2010: 
Release of next RAMP version to enhance processing capabilities. 

June 4, 2010: 
Signed 2-year follow-on contract, first year fully funded up front. 

June 28, 2010: 
Release of next RAMP version to enhance processing capabilities. 

July 26, 2010: 
Word Facility Security Assessment (FSA) template and Excel risk 
calculator issued to FPS inspectors to complete FSAs. 

January 2012 (anticipated milestone): 
Anticipated release for next RAMP version. 

September 20, 2022 (anticipated milestone): 
Current projected end of RAMP's life cycle. 

Source: GAO analysis of FPS data. 

[End of figure] 

[End of section] 

Enclosure III: Federal Protective Service's (FPS) Process for Entering 
Guard Training and Certification Information into Risk Assessment and 
Management Program (RAMP): 

Step 1: Within 7 days of a certifying event (e.g., completing 
cardiopulmonary resuscitation training), FPS requires guard companies 
to electronically submit guard training and certification information 
to FPS through an extensible markup language (XML) forms format, such 
as Microsoft InfoPath.[Footnote 19] 

Step 2: An FPS contractor uploads the XML forms into RAMP. FPS 
requires that the guard training and certification information be 
uploaded within 24 hours of submission from the guard company. 

Step 3: RAMP refreshes daily to include new uploads. During the 
refresh period, RAMP may reject a guard company's submission because 
of data input errors such as mismatched Social Security numbers or a 
misspelled name. The guard company then has to correct the guard 
information and resubmit it to FPS to be reuploaded into RAMP. 

Step 4: At this point in the process, guard training and certification 
information is available in RAMP for guard post inspections. 

Source: GAO analysis of FPS information. 

Enclosure IV: Comments from the Department of Homeland Security: 

U.S. Department of Homeland Security: 
Washington, DC 20528: 

July 8, 2011: 

Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20548: 

Re: Draft Report GAO-11-705R, "Federal Protective Service: Actions
Needed to Resolve Delays and Inadequate Oversight Issues with FPS's Risk
Assessment and Management Program" 

Dear Mr. Goldstein: 

Thank you for the opportunity to review and comment on this draft 
report. The U.S. Department of Homeland Security (DHS) appreciates the 
U.S. Government Accountability Office's (GAO's) work in planning and 
conducting its review and issuing this report on the Federal 
Protective Service's (FPS's) Risk Assessment and Management Program 
(RAMP). 

RAMP is intended to provide FPS personnel with a centralized source of 
information for Federal facilities they protect. The DHS National 
Protection and Programs Directorate (NPPD)/FPS is responsible for the 
safety of more than a million people who pass through our security 
portals each day. Our contracted Protective Security Officers (PSOs) 
conduct millions of inspections each year in pursuit of genuine 
security—and not just the illusion of it. More than 700,000 dangerous 
objects and contraband, including weapons, are confiscated each year 
from entrants at NPPD/FPS screening posts. Our NPPD/FPS officers and 
inspectors conduct facility security assessments (FSAs), cover more than
1,000 demonstrations and disturbances, and make more than 1,600 
arrests annually. 

Addressing GAO recommendations is a top priority for NPPD/FPS., and 
work is under way to resolve the issues identified in this report, 
including GAO's determination that deficiencies in RAMP development 
may have impacted security at Federal facilities. As stated above, FPS 
conducts comprehensive FSAs to identify credible threats for each 
facility and assess specific vulnerabilities and likely consequences 
associated with those threats. It should be noted that FSAs are one 
piece of the protective services provided to the Federal community and 
FPS's other efforts, such as patrol and response, tenant awareness 
training, countermeasure testing, etc., are ongoing and have a direct 
bearing on the security of Federal facilities. 

The development of RAMP has been under way for nearly 4 years. Yet, 
after careful consideration and review, FPS has determined that RAMP 
development—as it was being pursued—was not cost-effective and has not 
fulfilled its original goals. However FPS has a continuing need for 
elements of RAMP and its basic functionality—which is discussed 
further in the Departmental response to GAO's specific recommendations. 

The draft report contained five recommendations, with which DHS 
concurs. Specifically, GAO recommended that the Secretary of Homeland 
Security direct the Under Secretary of NPPD and the Director of FPS 
take the following actions: 

Recommendation 1: Evaluate whether it is cost beneficial to finish 
developing RAMP or if other alternatives for completing FSAs and 
managing security guards would be more appropriate. 

Response: Concur. NPPD/FPS is revalidating RAMP requirements with its 
stakeholders and accessing next generation architecture to ensure that 
future RAMP investments deliver robust capability to the end user, and 
maximize network efficiencies and information sharing. NPPD/FPS has 
already begun carefully assessing alternative programs, such as the 
DHS Science and Technology Directorate's recommended Integrated Rapid 
Visual Screen solution and the NPPD/Office of Infrastructure 
Protection (IP) Infrastructure Survey Tool (1ST). Thus far, the 
results of our preliminary assessment indicate that, at a minimum, 
NPPD/FPS will gain efficiencies and improve RAMP capability by 
leveraging the IST that is housed on the Link Encrypted Network System 
(LENS), an NPPD/IP gateway. With this adjustment, NPPD/FPS will move 
toward greater collaboration and integration with other NPPD elements. 
While RAMP is re-engineered to incorporate threat level calculations, 
recommended countermeasures, and Interagency Security Committee 
standards, a version of 1ST was selected as an interim solution, 
enabling NPPD/FPS to continue processing credible FSAs. 

Placing RAMP on the same network backbone will enable information 
sharing between NPPD/IP and NPPD/FPS, which will further enhance the 
Department's ability to protect Federal facilities. Presently, the 
Department of Energy (DOE), Argonne National Laboratory (ANL) supports 
LENS. Further, our preliminary assessment also indicates that 
development of RAMP by DOE ANL for LENS would be more economical than 
our current approach. As a result, NPPD/FPS suspended RAMP development 
with our current contractor while DOE ANL and other alternatives are 
considered. 

Recommendation 2: Increase the use of project management best 
practices by managing requirements and conducting user acceptance 
testing for any future RAMP development efforts. 

Response: Concur. Additional RAMP development activities will 
incorporate project management best practices. NPPD requires all 
acquisition efforts to comply with the Acquisition Management 
Directive 102.1 (MD 102). Further. NPPD has implemented the NPPD 
Acquisition Instruction 102-01-01 describing our internal acquisition 
review process. The Directive was developed on the basis of project 
management best practices. NPPD/FPS's adherence to these documents 
will address GAO's recommendation that future RAMP development efforts 
have robust requirements development, change management, and user 
acceptance testing processes. 

Key to success will be to engage and involve the end users and any 
other stakeholders throughout the entire process to ensure the product 
delivered meets all expectations and requirements. Best management 
practices also include development and tracking project activities, 
milestones, costs, and deliverables through monthly cost reports, 
project schedule reviews, systems engineering lifecycle gate reviews, 
and weekly status reports. NPPD/FPS is now identifying stakeholders to 
fully develop a new integrated project team and also intends to hire a 
Program Manager immediately to oversee NPPD/FPS information technology 
(IT) projects, which will ensure compliance with DHS's Systems
Engineering Lifecycle requirements and guidance. 

Lastly, NPPD/FPS will adhere to the Office of Management and Budget's 
recent "25 Point Implementation Plan to Reform Federal Information 
Technology Management" (December 9, 2010). This document mandates 
inclusion of value-added activities and requires Federal IT programs 
to be structured to deploy business functionality in predetermined 
release cycles, with initial deployment to end users not more than 18 
months after the program begins. 

Recommendation 3: Establish a process for verifying the accuracy of 
federal facility and guard training and certification data before 
entering into RAMP. 

Response: Concur. With the further development of RAMP, NPPD/FPS 
intends to make improvements to the PS0 certification validation 
process, as well as the post-inspection and administrative audit 
processes. These improvements will focus on accountability for data 
integrity, metrics and trend analysis, and should also help identify 
and correct process deficiencies. 

Recommendation 4: Develop interim solutions for completing FSAs and 
guard inspections while addressing RAMP's challenges. 

Response: Concur. As an interim assessment solution, NPPD/FPS is 
utilizing the 1ST until the development, testing, training, and 
implementation of future RAMP capabilities have been completed. 

A modified version of the 1ST will replace the current Microsoft Excel 
Survey Tool template currently in use by NPPD/FPS. This modified 1ST 
will be incorporated into the future capabilities of RAMP. It will 
enable field-based inspectors to complete and file their assigned FSAs 
electronically in the on-line database, and provide supervisors the 
ability to approve or comment on the assessments electronically. 
Additionally, the data collected via the interim IST will ultimately 
be available in the shared risk assessment database. NPPD plans for 
the completed FSAs to become a part of the national critical 
infrastructure and key resources (CIKR) database, allowing NPPD the 
capability to view and share all CIKR assessments. 

The new PSO inspection process will focus on assessing the PSOs" 
knowledge of the post-orders and emergency preparedness and response 
measures specific to the facility they protect (e.g., Active Shooter, 
Code Adam, Occupant Emergency Plans, Shelter-in-Place, response to 
suspicious packages and bomb threats, etc.). NPPD/FPS will analyze 
data collected from PSO inspections to identify opportunities for 
remedial improvements. 

Finally, NPPD/FPS has established a policy to employ a common matrix 
to collect, categorize, and validate certification data and conduct 
trend analysis on inspection deficiencies. This common matrix will be 
designed so that monthly reporting on deficiencies can be incorporated 
in the Contractor Performance Appraisal Reporting System (CPARS) for 
guard services contracts. NPPD/FPS will ensure contractual actions 
taken by the contracting officer in response to performance problems 
are documented in the contract file. NPPD/FPS will conduct an ongoing 
assessment of the contractor's performance on the basis of regular 
inspections and will employ a common format for documenting and 
addressing performance problems. 

GAO also recommended that the Secretary of Homeland Security direct 
the Directors of U.S. Immigration and Customs Enforcement (ICE) and 
FPS to: 

Recommendation 5: Complete contract performance evaluations for its 
current RAMP contractor and ensure that the evaluations and other 
required documents are maintained in the contract file in accordance 
with DHS's acquisition policy and Federal Acquisition Regulations 
(FAR). 

Response: Concur. The DHS Office of Procurement Operations (OPO) now 
administers the current contract. OPO will ensure that the Contracting 
Officer's Technical Representative and the OPO contracting officer 
complete the required assessments in the CPARS and maintain this 
information in the contract files per DHS acquisition policy and FAR. 
NPPD/FPS and OPO are working to complete the contract performance 
evaluations on the existing RAMP contract. The first contractor 
performance evaluation under OPO administration is in progress and is 
due mid-October 2011. 

Prior to the transfer of contract administration to OPO, ICE had 
administered the contract. Since that time, ICE has made improvements 
to its contractor performance reporting program. ICE has created a 
permanent full-time position to manage CPARS. The manager will track 
and monitor performance reporting and provide hands-on training to 
CPARS users. The Head of Contracting Activity receives a monthly 
status report on CPARS compliance. Additionally, timely CPARS 
registration has been included in the employee performance plan for 
every contract specialist/contracting officer. 

Subsequent to the GAO review, ICE provided copies of monthly quality 
assurance evaluations that had previously been completed. As described 
earlier, performance assessments will be placed in CPARS for the 
expired RAMP contract. 

Again, we thank you for the opportunity to review and provide comment 
on this draft report. Sensitivity comments were submitted under 
separate cover. We look forward to working with you on future Homeland 
Security-related engagements. 

Sincerely, 

Signed by: 

Jim. H. Crumpacker: 
Director: 
Departmental GAO/OIG Liaison Office: 

[End of section] 

Footnotes: 

[1] We refer to property that is owned by the federal government and 
under the control and custody of the GSA as GSA-owned property. 

[2] GAO, Homeland Security: Greater Attention to Key Practices Would 
Improve the Federal Protective Service's Approach to Facility 
Protection, [hyperlink, http://www.gao.gov/products/GAO-10-142] 
(Washington, D.C.: Oct. 23, 2009) and GAO, Homeland Security: Federal 
Protective Service's Contract Guard Program Requires More Oversight 
and Reassessment of Use of Contract Guards, [hyperlink, 
http://www.gao.gov/products/GAO-10-341] (Washington, D.C.: Apr. 13, 
2010). 

[3] During RAMP's initial development, FPS was part of ICE. ICE 
provided software development and project management technical 
expertise and was responsible for contract award and administration. 

[4] According to DHS, risk is influenced by the nature and magnitude 
of threats, the vulnerabilities to these threats, and the consequences 
that could result. 

[5] GAO, Information Technology Investment Management: A Framework for 
Assessing and Improving Process Maturity, [hyperlink, 
http://www.gao.gov/products/GAO-04-394G] (Washington, D.C.: Mar. 2004) 
and Carnegie Mellon Software Engineering Institute, Capability 
Maturity Model® Integration for Acquisition (CMMI-ACQ), Version 1.2 
(November 2007). 

[6] The ISC Physical Security Criteria for Federal Facilities 
establishes a baseline set of countermeasures to be applied to all 
federal facilities based on their facility security level, and 
provides a framework for customizing security countermeasures to 
address the unique risks faced at each facility. 

[7] Managing requirements entails managing the capabilities or 
conditions that a product is required to meet to satisfy an agreement 
or standard. User acceptance testing is conducted to ensure that a 
system meets contract requirements and performs satisfactorily for the 
users of the program. 

[8] We refer to property that is owned by the federal government and 
under the control and custody of the GSA as GSA-owned property.  

[9] GAO, Homeland Security: Greater Attention to Key Practices Would 
Improve the Federal Protective Service's Approach to Facility 
Protection, [hyperlink, http://www.gao.gov/products/GAO-10-142] 
(Washington, D.C.: Oct. 23, 2009). 

[10] GAO, Homeland Security: Federal Protective Service's Contract 
Guard Program Requires More Oversight and Reassessment of Use of 
Contract Guards, [hyperlink, http://www.gao.gov/products/GA0-10-341] 
(Washington, D.C.: Apr. 13, 2010). 

[11] According to DHS, risk is influenced by the nature and magnitude 
of threats, the vulnerabilities to these threats, and the consequences 
that could result. 

[12] GAO, Information Technology Investment Management: A Framework 
for Assessing and Improving Process Maturity, [hyperlink, 
http://www.gao.gov/products/GAO-04-394G] (Washington, D.C.: March 
2004). 

[13] GAO, Assessing the Reliability of Computer-Processed Data, 
[hyperlink, http://www.gao.gov/products/GAO-09-365G] (Washington, 
D.C.: February 2009).  

[14] [hyperlink, http://www.gao.gov/products/GA0-10-341].  

[15] [hyperlink, http://www.gao.gov/products/GA0-10-341]. See also 
GAO, Internal Control Management and Evaluation Tool, [hyperlink, 
http://www.gao.gov/products/GAO-01-1008G] (Washington, D.C.: August 
2001).  

[16] [hyperlink, http://www.gao.gov/products/GA0-04-394G].  

[17] User acceptance testing is conducted to ensure that a product 
meets contract requirements and performs satisfactorily. 

[18] GAO, Department of Homeland Security: Assessments of Selected 
Complex Acquisitions, [hyperlink, 
http://www.gao.gov/products/GAO-10-588SP] (Washington, D.C.: June 30, 
2010). 

[19] Microsoft InfoPath is an XML forms-creation and data-gathering 
tool that permits businesses to gather information without program 
coding. It requires manual data entry. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: