This is the accessible text file for GAO report number GAO-11-380R 
entitled 'Defense Acquisitions: Application of Lessons Learned and 
Best Practices in the Presidential Helicopter Program' which was 
released on March 25, 2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

GAO-11-380R: 

United States Government Accountability Office: 
Washington, DC 20548: 

March 25, 2011: 

Congressional Committees: 

Subject: Defense Acquisitions: Application of Lessons Learned and Best 
Practices in the Presidential Helicopter Program: 

In June 2009, following the expenditure of close to $3 billion and a 
critical Nunn-McCurdy breach[Footnote 1] of the cost growth threshold, 
the Department of Defense (DOD) terminated[Footnote 2] the Navy's VH-
71 presidential helicopter acquisition program and contract because of 
cost growth, schedule delays, and projected system performance. The 
Presidential Helicopter VXX program is a successor Navy program to the 
terminated VH-71 program acquisition and has been initiated to develop 
aircraft to replace the current, aging presidential helicopter fleet. 

The Ike Skelton National Defense Authorization Act for Fiscal Year 
2011 (the Act) directed GAO to review and report annually to the 
congressional defense committees on the VXX program through 2013. 
[Footnote 3] This is the first of the required GAO reports. It 
discusses (1) major lessons learned from the terminated VH-71 program 
that should be applied to the follow-on VXX program and (2) the 
current acquisition approach of the VXX program and sufficiency of the 
underlying acquisition plans and related documentation. 

To identify major VH-71 program lessons learned, we examined the cost, 
schedule, and performance experience of the terminated VH-71 program 
through discussions with agency officials and review of reported 
lessons learned and then assessed how those lessons relate to 
acquisition best practices. To determine the current status of the VXX 
program, we examined available program documents and interviewed 
knowledgeable officials. To assess the sufficiency[Footnote 4] of the 
program's efforts, we discussed the Navy's plans for the program with 
knowledgeable officials and obtained and analyzed the one completed 
VXX program baseline acquisition document, the program's Initial 
Capabilities Document (ICD),[Footnote 5] to determine whether it 
incorporates acquisition best practices and addresses DOD's 
acquisition policy and guidance. We also obtained preliminary 
information on the ongoing VXX program Analysis of Alternatives 
(AOA)[Footnote 6] and made preliminary observations on this effort and 
the terminated VH-71 program's AOA conducted in 2003. 

We conducted this performance audit from September 2010 to March 2011 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

The Marine Corps's HMX-1 squadron currently utilizes two types of 
helicopters--the VH-3D and the VH-60N--to carryout the presidential 
helicopter mission. Over the past several years, numerous 
modifications and improvements have been made to both aircraft types 
to incorporate emerging technologies and address new requirements. 
These improvements have increased the gross weight of the helicopters--
decreasing some aspects of mission capability, for example, range, and 
severely limiting the ability to incorporate future improvements 
because of the impact of further weight growth. 

According to program officials, over time it had become increasingly 
difficult to accommodate the demands placed on the HMX-1 aircraft in 
support of presidential requirements. The events following the 
terrorist attacks on the United States on September 11, 2001, 
highlighted the need for improved transportation, communication, and 
security capabilities for presidential support aircraft. As a result, 
a VXX replacement helicopter program was initiated in April 2002 to 
begin fielding a new helicopter in the 2011 time frame. A subsequent 
November 2002 White House memo to the Secretary of Defense articulated 
a goal of having the new helicopter available earlier, and in 
response, the Navy developed an accelerated program plan to develop 
and initially field a new helicopter by the end of 2008. The VXX 
program was subsequently redesignated the VH-71 program. 

In January 2005, the Navy entered into a contract with Lockheed Martin 
Systems Integration to develop the replacement helicopter. By January 
2009, after schedule slips and significant cost increases, the Navy 
reported a Nunn-McCurdy breach of the critical cost growth threshold 
and in June 2009 terminated the VH-71 program. However, the need for a 
replacement helicopter remains. An ICD was drafted by the Marine Corps 
and approved by DOD in August 2009 to start a successor VXX Helicopter 
Replacement Program. According to program officials, the current 
projected VH-3D and VH-60N service life will support the development 
and fielding of the VXX. 

In the last few years, Congress and DOD have put in place new defense 
acquisition policy provisions that replace risk with knowledge--
placing greater emphasis on front-end planning and establishing sound 
business cases for starting programs. For example, both DOD's December 
2008 acquisition policy revisions and the Weapon Systems Acquisition 
Reform Act of 2009 require programs to invest more time and resources 
in the front end of the acquisition process in line with a knowledge-
based acquisition approach.[Footnote 7] As a result, DOD's current 
acquisition policy and guidance reflect a knowledge-based acquisition 
framework in line with acquisition best practices GAO has been 
identifying since the late 1990s. We will use this framework in this 
report to analyze both the VH-71 and the VXX programs. 

A knowledge-based acquisition framework involves achieving the right 
knowledge at the right time--enabling leadership to make informed 
decisions about when and how best to move into various acquisition 
phases. In essence, knowledge supplants risk over time. Our best 
practices work has demonstrated that this building of knowledge 
consists of information that should be gathered at three critical 
points over the course of a program. 

² Knowledge point 1: Resources and requirements match. Achieving a 
high level of technology maturity and preliminary system design backed 
by robust systems engineering by the start of system development is an 
important indicator of whether this match has been made. This means 
that the technologies needed to meet essential product requirements 
have been demonstrated to work in their intended environment. In 
addition, the developer has completed a preliminary design of the 
product that shows the design is feasible. If the above conditions are 
met, a solid business case is established at this point. 

² Knowledge point 2: Product design is stable. This point occurs when 
a program determines that a product's design will meet customer 
requirements, as well as cost, schedule, and reliability targets. A 
best practice is to achieve design stability at the system-level 
critical design review, usually held midway through system 
development. Completion of at least 90 percent of engineering drawings 
at this point provides tangible evidence that the product's design is 
stable, and a prototype demonstration shows that the design is capable 
of meeting performance requirements. 

² Knowledge point 3: Manufacturing processes are mature. This point is 
achieved when it has been demonstrated that the developer can 
manufacture the product within cost, schedule, and quality targets. A 
best practice is to ensure that all critical manufacturing processes 
are in statistical control--that is, they are repeatable, sustainable, 
and capable of consistently producing parts within the product's 
quality tolerances and standards--at the start of production. 

Summary: 

Several lessons learned from the acquisition strategy and eventual 
termination of the VH-71 program apply to the VXX program. For 
example, had the VH-71 program followed acquisition best practices and 
conducted early systems engineering, it could have led to a feasible, 
stable preliminary design ideally before development start. In turn, a 
stable, early design allows for more accurate program cost estimates 
and a better foundation for sufficient funding commitments. Instead, 
it began without completing systems engineering until well after 
development start. As a consequence, it never achieved design 
stability and experienced significant cost and schedule problems in 
development. Its cost estimates doubled--from about $6.5 billion at 
development start in 2005 to about $13 billion when terminated in 
2009. More than good systems engineering is necessary, however. A key 
to successful development is the ability to make early trade-offs 
either in the design of a product or the customer's expectations to 
avoid outstripping the resources available for product development. 
The VH-71 program was not afforded room needed to pursue these needed 
trade-offs. Stringent performance requirements (some with no 
flexibility) were laid out for the system prior to the start of 
development and did not appear to involve significant consideration of 
trade-offs of cost, performance, and schedule negotiated between the 
customer and the developer. 

The VH-71 program's experience validated the need to execute a 
knowledge-based acquisition process with discipline, confirming the 
danger of not replacing risk with knowledge earlier in the acquisition 
process. VXX program officials seem to understand this lesson learned 
from the VH-71 program and appear to be establishing a knowledge-based 
acquisition process emphasizing early systems engineering. One of the 
primary lessons they learned from the VH-71 program's experience is 
that there must be an early, solid business case with a rational 
balance between requirements, cost, and schedule. To accomplish this, 
they have stated that a rigorous four-phase systems engineering and 
technical review process will be used. Early VXX program efforts 
appear to reflect the intent to pursue a knowledge-based acquisition. 
The VXX program is currently in the materiel solution analysis phase 
of the acquisition process, and an ICD has been developed to formally 
document the capabilities required to perform the defined mission, the 
specific capability gaps that exist, and the need to address them. Our 
review of the VXX program's ICD indicates that it addresses all three 
of these areas and also appears to align with acquisition best 
practices. An AOA has been initiated but not yet completed. According 
to DOD officials, it will be more robust than the AOA developed for 
the VH-71 program. The program is in the earliest stages of 
development, still developing a business case to launch product 
development. We will, as you have requested, assess and report on a 
wide range of VXX program activities moving forward. Throughout, we 
will be looking for the implementation of a knowledge-based 
acquisition through application of key best practice process controls. 

Lesson Learned from the VH-71 Program: 

The VH-71 program's failure to follow acquisition best practices was a 
critical factor in the program's poor performance that led to its 
ultimate termination. It started with a faulty business case, did not 
perform appropriate systems engineering analysis to gain knowledge at 
the right times, and failed to make necessary trade-offs between 
resources and requirements even after years of development. Because of 
these failures, the program was unable to achieve stable design and 
experienced significant cost growth and schedule delays before being 
terminated in 2009. 

The Program Began with a High-Risk Business Case: 

The VH-71 program was knowingly initiated with a high-risk business 
case. To accelerate the program's initial delivery of helicopters from 
2011 to 2008, the Navy adopted a two-step acquisition approach and 
initiated production at the same time it began development.[Footnote 
8] Prior to the start of development, a March 2004 Office of the Under 
Secretary of Defense for Acquisition, Technology and Logistics 
(OUSD(AT&L)) Defense Acquisition Program Support Assessment of the 
program concluded that the program had a high-risk schedule because of 
concurrent design and production efforts. However, the Office of the 
Secretary of Defense (OSD) recognized and accepted the program's risk 
and strategy in its January 2005 Acquisition Decision Memorandum 
approving the program's entry into development. Concurrency and lack 
of systems engineering knowledge to achieve a match between required 
capabilities and resources contributed to the cost overruns and 
schedule delays experienced by the program prior to its termination in 
2009. 

Systems Engineering Knowledge Was Not Available: 

The risk of the VH-71 program's business case was even higher than 
anticipated because early systems engineering wasn't done when it 
should have been to be in accord with acquisition best practices. As 
we have previously reported,[Footnote 9] a primary reason for cost and 
schedule problems is too many technical unknowns and insufficient 
knowledge about performance and production risks. If this early 
systems engineering is not performed, significant cost increases can 
occur as the system's requirements become better understood by the 
government and contractor. The VH-71 program's experience exemplified 
this. System requirement reviews are conducted to ensure that system 
requirements have been properly identified and that a mutual 
understanding between the government and the contractor exists. These 
steps should occur prior to the start of development. However, when 
the VH-71 program's system requirements review occurred in May 2005--4 
months after the start of development--it was found that the 
contractor's design was significantly noncompliant with what the 
contract required. In June 2006, the VH-71 program's Defense 
Acquisition Executive Summary reported that it had taken considerable 
effort over the prior 14 months to resolve related issues and that 
good progress had been made in aligning the contractor's design with 
what the contract required. It also noted, though, that related 
activities had resulted in delay of technical reviews and contract 
milestones and additional cost. 

Having a feasible, stable preliminary design for a weapons program 
early in the acquisition process is important for lessening risk, both 
by ensuring that there is a match between resources and requirements 
and by demonstrating that a product's design can meet customer 
requirements, as well as cost, schedule, and reliability targets. The 
VH-71 program did not, however, complete needed systems engineering 
until well after the start of development for both increments and, in 
the case of Increment 1, after approval of production as well, as 
Increment 1 was approved to enter development and production at the 
same time. OSD approved the Increment 1 entry into development and 
production in January 2005. A preliminary design review (PDR), which 
best practices indicate should occur prior to a program entering 
development, was not completed for the Increment 1 effort until 
February 2006--13 months after the start of development. OSD also 
approved Increment 2 development in January 2005. A PDR for Increment 
2 had not occurred by the time a stop work order was placed on the 
Increment 2 effort in December 2007--35 months after the start of 
Increment 2 development. The stop work order was placed as a result of 
a concern that the required work would exceed available funding. 

Similarly, it is a best practice to achieve design stability at a 
system-level critical design review (CDR), usually held midway through 
system development--that is, halfway between the start of development 
and approval to enter production. A CDR for Increment 1 was held in 
August 2006 but was not completed as significant elements remained to 
be addressed. Subsequently, an airframe CDR did not occur until 
February 2007--more than 2 years after the start of Increment 1 
development and production. A CDR was scheduled for Increment 2 to 
occur in fiscal year 2008, but the stop work order for Increment 2 was 
issued prior to the scheduled completion of the CDR. As knowledge from 
the successive systems engineering reviews builds, uncertainty and 
associated risks in the cost estimate decrease. As noted, this 
knowledge was developed late, if at all, in the VH-71 program and the 
consequence was cost growth to the degree that at the time the VH-71 
program was terminated in June 2009, it had grown from a total 
estimated cost of about $6.5 billion at the start of development in 
January 2005 to about $13 billion. 

The Program Did Not Make Appropriate Trade-offs between Capability 
Requirements and Allowable Resources: 

While good systems engineering can identify and inform trade-offs, the 
customer and developer must be willing to make trade-offs to achieve a 
successful business case. We have found that key to successful 
developments was the ability to make early trade-offs either in the 
design of the product or the customer's expectations to avoid 
outstripping the resources available for product development. 
Conversely, as we have found with other programs--such as the Armed 
Reconnaissance Helicopter program--an unwillingness to make 
performance trade-offs can contribute to programs being unexecutable, 
ultimately resulting in their termination. 

The VH-71 program was not afforded sufficient room needed to pursue 
needed trade-offs. Stringent performance requirements (some with no 
flexibility) were laid out for the system prior to the start of 
development and did not appear to involve significant consideration of 
trade-offs of cost, performance, and schedule negotiated between the 
customer and the developer. Rather, as a July 2007 Institute for 
Defense Analyses[Footnote 10] independent review team reported on the 
executability of Increment 2: 

"Unfortunately, the requirements for the program are still not well 
founded. Initially this reflected a hurried program start, without the 
foundation-laying analyses and design and requirements tradeoffs, 
necessary to initiate a program with an acceptable level of stability. 
Currently, incomplete requirements documentation and poor 
configuration management presage further instability in the future. 
The [independent review team] also observed that the two directions 
given to the program by the Acquisition Decision Memorandum were not 
followed: 

* Leadership engagement and clear guidance were imperative for program 
success. 

* Disciplined application of systems engineering practices, early 
configuration control decisions, and strict configuration control were 
essential." 

VXX Program Appears Set to Use a Knowledge-Based Acquisition Approach: 

The VH-71 program experience validated the need to execute a knowledge-
based process with discipline and confirmed the danger of not 
replacing risk with knowledge earlier in the acquisition process. VXX 
program officials seem to understand this and appear to be moving 
forward in an attempt to apply these lessons. They have stated that 
their aim is to establish an initial knowledge-based acquisition 
business case that will emphasize early systems engineering; mature 
technologies; an incremental, knowledge-based approach; and the 
ability to trade capability for resources. The program is currently in 
its earliest stages, nearing completion of the materiel solution 
analysis phase, and is likely still years away from establishing its 
business case. Therefore, we do not have much acquisition 
documentation to review beyond the ICD, information on the preliminary 
acquisition planning, and AOA plans. 

VXX program management indicated that one of the primary lessons 
learned from the VH-71 program experience is that DOD must establish 
and maintain a solid business case, where a balance exists between 
requirements, cost, and schedule that results in an executable program 
with acceptable risk. To accomplish this, the program intends to use a 
rigorous four-phase systems engineering and technical review process 
constituting a more knowledge-based acquisition approach. This process 
differs greatly from the process followed during the VH-71 program. 
According to VXX program officials, the VXX program's systems 
engineering and technical review process will begin earlier during the 
technology development phase (pre-Milestone B). VXX program officials 
stated that they plan to enter the systems development phase with a 
preliminary technical design and possibly an early prototype of 
subsystems. 

Early VXX program efforts appear to reflect the intent to pursue a 
best practices-aligned knowledge-based acquisition. The VXX program is 
currently in the pre-Milestone A[Footnote 11] phase of the acquisition 
process. An ICD has been approved and an AOA is currently being 
finalized; both are required for Milestone A. After termination of the 
VH-71 program contract, DOD conducted an analysis to determine if a 
nonmateriel solution existed to fill the identified gap in the 
presidential helicopter program's vertical lift capability. DOD 
determined that there were no nonmaterial approaches that would 
significantly improve or resolve the capability gaps.[Footnote 12] It 
was determined that a materiel solution must be pursued, and as a 
result, an ICD for the VXX program was developed in August 2009. 
According to the Chairman of the Joint Chiefs of Staff instruction 
that guides the process that develops ICDs, an ICD is a formal 
capability assessment by a military service, defense agency, or other 
sponsor and it formally documents (1) the capabilities required to 
perform the defined mission, (2) the specific capability gap or set of 
gaps that exist, and (3) the need to address the capability gap(s). 
[Footnote 13] Our review of the VXX program's ICD indicates that it 
addressed all three of these areas. The ICD and its intended use also 
appear to align with acquisition best practices. Unlike the 
requirements document that led to the VH-71 program, the VXX program's 
ICD identifies performance attributes as "preferred values" rather 
than key performance parameters. Program officials indicated that the 
use of preferred values instead of firm requirements will allow the 
program room to do trade-offs needed to achieve a match between the 
users' requirements and available resources before development begins--
an acquisition best practice. 

According to a DOD official, the Navy expects to issue the results of 
its AOA in the second quarter of 2011. According to DOD officials, it 
will be more robust than the AOA used to support the VH-71 program. 
While we cannot assess its sufficiency until it is complete, 
statements by DOD officials on the nature of the AOA effort suggest 
the pursuit of an acquisition approach in line with best practices. 
Plans are for the AOA to analyze in detail the estimated cost and 
effectiveness of a range of potential materiel solutions to support 
the need. In the past, we have reported that many AOAs do not 
effectively consider a broad range of alternatives for addressing a 
need or assess technical and other risks associated with each 
alternative.[Footnote 14] Without a sufficient comparison of 
alternatives and focus on technical and other risks, AOAs may identify 
solutions that are not feasible and decision makers may approve 
programs based on limited knowledge. While many factors can affect 
cost and schedule outcomes, we have found that programs that had a 
limited assessment of alternatives tended to have poorer outcomes than 
those that had more robust AOAs. When the AOA is issued, we will 
assess it for robustness--the range of alternatives it considers, its 
depth of analysis, and its consideration of trade-offs. 

As the program progresses, we will continue to assess and report its 
performance as directed in the Ike Skelton National Defense 
Authorization Act for Fiscal Year 2011 (the Act). Figure 1 illustrates 
the acquisition process and where the VXX program currently stands in 
that process, and identifies some of the key program documents we will 
review in the future and the best practices criteria that the program 
should meet as it progresses. We will use this as a template for 
future reviews of the program. 

Figure 1: Alignment of DOD's Acquisition Process, Key Program 
Documents, and Best Practices: 

[Refer to PDF for image: illustration] 

DOD Acquisition process: Materiel solution analysis: 
* Materiel development	decision; 
* Current VXX status;	
* Key program documents: 
- ICD. 

Milestone A: 
Milestone A documents: 
AOA; 
Component cost estimate; 
Systems	engineering plan; 
Technology development strategy; 
Test and evaluation strategy. 

DOD Acquisition process: Technology development: 
* PDR; 
Best practices knowledge-based acquisition model:	
Knowledge Point 1: Technologies, time, funding and other resources 
match customer needs. Decision to invest in product development.	
Key steps:	
* PDR completed;	
* Technologies demonstrated to high levels; 
* Incremental acquisition strategy in place; 
* Knowledge-based cost estimate. 

Milestone B: Development start; 
Milestone B documents: 
Acquisition strategy; 
Capability development document; 
Independent cost estimate;	
Technology readiness assessment (TRA); 
Test and evaluation master plan. 

DOD Acquisition process: Engineering and manufacturing development: 
Integrated system design: 
CDR; 
Knowledge Point 2: Design is stable and performs as expected. Decision 
to start building and testing production representative prototypes. 
Key steps:	
* System-level CDR and subsystem design reviews completed; 
* Ninety percent of engineering drawings released; 
* Integrated system prototype demonstrated;	
* Critical manufacturing processes identified. 

DOD Acquisition process: Engineering and manufacturing development: 
Capability and	manufacturing	demo:	
Knowledge Point 3: Production meets cost, schedule, and quality 
targets. Decision to produce first units for customer. 
Key steps: 
* Production-representative prototype demonstrated in intended 
environment; 
* Manufacturing processes in control; 
* Product reliability demonstrated via production-representative 
prototype testing. 

Milestone C: Production start. 
Milestone C documents: 
Acquisition strategy; 
Capability production document; 
Independent cost estimate; 
TRA; 
Test and evaluation master plan. 

DOD Acquisition process: Production. 

Source: GAO analysis of DOD's acquisition process and GAO's best 
practices. 

[End of figure] 

By using this framework, we will address the issues identified in the 
Act. Specifically: 

* the extent to which the program is meeting development and 
procurement cost, schedule, performance, and risk mitigation goals; 

* the progress of developmental and operational testing of aircraft 
and plans for correcting deficiencies in aircraft performance, 
operational effectiveness, reliability, suitability, and safety; 

* the program procurement plans, production results, and efforts to 
improve manufacturing efficiency and supplier performance; 

* the program's acquisition strategy, including whether it is in 
accord with acquisition best practices and DOD's acquisition policy 
and regulations; 

* risk assessments of its integrated master schedule and test and 
evaluation master plan; and: 

* our assessment of the sufficiency of the program's ICD (if revised), 
AOA, capabilities development document, and a systems requirement 
document (if produced). 

Overall, we will assess the use of acquisition best practices 
throughout the VXX program's acquisition through management's 
adherence to key best practice model controls. Those controls are 
outlined in the table in enclosure I. 

Agency Comments: 

DOD provided technical comments on the information in this report, 
which GAO incorporated as appropriate, but declined to provide 
additional comments. 

We are sending copies of this report to interested congressional 
committees; the Secretary of Defense; the Under Secretary of Defense 
for Acquisition, Technology and Logistics; and the Secretary of the 
Navy. This report also is available at no charge on GAO's Web site at 
[hyperlink, http://www.gao.gov]. 

Should you or your staff have any questions on the matters covered in 
this report, please contact me at (202) 512-4841 or sullivanm@gao.gov. 
Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this report. Key contributors 
to this report are listed in enclosure II. 

Signed by: 

Michael J. Sullivan, Director:
Acquisition and Sourcing Management: 

Enclosures - 2: 

List of Committees: 

The Honorable Carl Levin:
Chairman:
The Honorable John McCain:
Ranking Member:
Committee on Armed Services:
United States Senate: 

The Honorable Daniel K. Inouye:
Chairman:
The Honorable Thad Cochran:
Ranking Member:
Subcommittee on Defense:
Committee on Appropriations:
United States Senate: 

The Honorable Howard P. McKeon:
Chairman:
The Honorable Adam Smith:
Ranking Member:
Committee on Armed Services:
House of Representatives: 

The Honorable C. W. Bill Young:
Chairman:
The Honorable Norman D. Dicks:
Ranking Member:
Subcommittee on Defense:
Committee on Appropriations:
House of Representatives: 

[End of section] 

Enclosure I: Best Practices Model Controls at Key Acquisition Process 
Points: 

Milestone A: Occurs as programs begin the technology development phase; 
Criteria: 
* Complete robust Analysis of Alternatives. 

Milestone B (knowledge point 1): Occurs as programs begin the 
engineering and manufacturing development phase (Milestone B). Match 
exists between requirements and resources. Completed when technologies 
needed to meet essential product requirements have been demonstrated 
to work in their intended environments and the producer has completed 
a preliminary design of the product; 
Criteria: 
* Demonstrate high technology readiness levels; 
* Ensure that product requirements are informed by the systems 
engineering process; 
* Establish cost and schedule estimates for the product based on 
knowledge from preliminary design using systems engineering tools; 
* Complete preliminary design review; 
* Conduct decision review for program launch. 

Critical design review (knowledge point 2): Occurs at the critical 
design review between integration and demonstration. Completed when 
design is stable and has been demonstrated through prototype testing 
and 90 percent of engineering drawings are releasable to manufacturing 
organizations; 
Criteria: 
* Complete 90 percent of design drawings; 
* Complete subsystem and system design reviews; 
* Demonstrate with prototype that design meets requirements; 
* Obtain stakeholder concurrence that drawings are complete and 
producible; 
* Complete failure modes and effects analysis; 
* Identify key system; characteristics; 
* Identify critical manufacturing processes; 
* Establish reliability targets and growth plan based on demonstrated 
reliability rates of components and subsystems; 
* Conduct design review to enter system demonstration. 

Milestone C (knowledge point 3): Occurs at low-rate initial production 
commitment. Completed when product is ready to be manufactured within 
cost, schedule, and quality targets and all key manufacturing 
processes are under statistical control and product reliability has 
been demonstrated; 
Criteria: 
* Demonstrate manufacturing processes; 
* Build production-representative prototypes; 
* Test production-representative prototypes to achieve reliability 
goal; 
* Test production-representative prototypes to demonstrate the product 
in a realistic environment; 
* Collect statistical process control data; 
* Demonstrate that critical processes are capable and under 
statistical control; 
* Conduct decision review to begin production. 

Source: GAO. 

[End of table] 

[End of section] 

Enclosure II: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Michael J. Sullivan, (202) 512-4841 or sullivanm@gao.gov: 

Staff Acknowledgments: 

Key contributors to this report were Bruce H, Thomas, Assistant 
Director; Jerry Clark, Analyst-in-Charge; Marie P. Ahearn; Michael 
Aiken; Kenneth Patton; Don Springman; Robert Swierczek; and J. Andrew 
Walker. 

[End of section] 

Related GAO Products: 

Defense Acquisitions: Strong Leadership Is Key to Planning and 
Executing Stable Weapon Programs. [hyperlink, 
http://www.gao.gov/products/GAO-10-522]. Washington, D.C.: May 6, 2010. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-10-388SP]. Washington, 
D.C.: March 30, 2010. 

Defense Acquisitions: Many Analyses of Alternatives Have Not Provided 
a Robust Assessment of Weapon System Options. [hyperlink, 
http://www.gao.gov/products/GAO-09-665]. Washington, D.C.: September 
24, 2009. 

Defense Acquisitions: Measuring the Value of DOD's Weapon Programs 
Requires Starting with Realistic Baselines. [hyperlink, 
http://www.gao.gov/products/GAO-09-543T]. Washington, D.C.: April 1, 
2009. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-09-326SP]. Washington, 
D.C.: March 30, 2009. 

Defense Acquisitions: DOD Must Balance Its Needs with Available 
Resources and Follow an Incremental Approach to Acquiring Weapon 
Systems. [hyperlink, http://www.gao.gov/products/GAO-09-431T]. 
Washington, D.C.: March 3, 2009. 

GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs. [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP]. Washington, D.C.: March 2009. 

Defense Acquisitions: Perspectives on Potential Changes to Department 
of Defense Acquisition Management Framework. [hyperlink, 
http://www.gao.gov/products/GAO-09-295R]. Washington, D.C.: February 
27, 2009. 

Defense Acquisitions: A Knowledge-Based Funding Approach Could Improve 
Major Weapon System Program Outcomes. [hyperlink, 
http://www.gao.gov/products/GAO-08-619]. Washington, D.C.: July 2, 
2008. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-08-467SP]. Washington, 
D.C.: March 31, 2008. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-07-406SP]. Washington, 
D.C.: March 30, 2007. 

Defense Acquisitions: Assessments of Selected Major Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-06-391]. Washington, D.C.: 
March 31, 2006. 

Defense Acquisitions: Major Weapon Systems Continue to Experience Cost 
and Schedule Problems under DOD's Revised Policy. [hyperlink, 
http://www.gao.gov/products/GAO-06-368]. Washington, D.C.: April 13, 
2006. 

Best Practices: Better Support of Weapon System Program Managers 
Needed to Improve Outcomes. [hyperlink, 
http://www.gao.gov/products/GAO-06-110]. Washington, D.C.: November 
30, 2005. 

Best Practices: Capturing Design and Manufacturing Knowledge Early 
Improves Acquisition Outcomes. [hyperlink, 
http://www.gao.gov/products/GAO-02-701]. Washington, D.C.: July 15, 
2002. 

Best Practices: Better Matching of Needs and Resources Will Lead to 
Better Weapon System Outcomes. [hyperlink, 
http://www.gao.gov/products/GAO-01-288]. Washington, D.C.: March 8, 
2001. 

Best Practices: A More Constructive Test Approach Is Key to Better 
Weapon System Outcomes. [hyperlink, 
http://www.gao.gov/products/GAO/NSIAD-00-199]. Washington, D.C.: July 
31, 2000. 

Best Practices: Better Management of Technology Development Can 
Improve Weapon System Outcomes. [hyperlink, 
http://www.gao.gov/products/GAO/NSIAD-99-162]. Washington, D.C.: July 
30, 1999. 

[End of section] 

Footnotes: 

[1] 10 U.S.C. § 2433 establishes the requirement for the Department of 
Defense (DOD) to prepare unit cost reports on major defense 
acquisition programs or designated major defense subprograms. If a 
program exceeds cost growth thresholds specified in the law, this is 
commonly referred to as a Nunn-McCurdy breach. DOD is required to 
report these breaches to Congress, and in certain circumstances, DOD 
must reassess the program and submit a certification to Congress in 
order to continue the program, in accordance with 10 U.S.C. § 2433a. 
The Nunn-McCurdy breach experienced by the VH-71 program was estimated 
to represent program acquisition unit cost (PAUC) growth of more than 
50 percent above the original acquisition program baseline--a level 
that would have required certification to Congress for continuation of 
the program if the program had not been terminated. PAUC represents 
the expected acquisition cost for each unit procured, as determined by 
dividing the sum of a program's total program development, 
procurement, and system-specific military construction costs by the 
number of fully configured end items to be procured. 

[2] A memorandum canceling the program was issued in May 2009. 
Subsequently, a notice terminating the contract was sent to the 
contractor in June 2009. In accordance with the termination clause, 
the contractor was required to submit a termination settlement 
proposal within 1 year. The contractor submitted its termination 
proposal in May 2010. The termination proposal is currently being 
audited and a final settlement is expected by the end of fiscal year 
2011. 

[3] Pub. L. No. 111-383 § 233. 

[4] We have defined sufficiency as meaning objective and in accord 
with acquisition best practices and DOD acquisition policy and 
guidance. 

[5] A sponsor, usually a military service, submits a capability 
proposal called an ICD through DOD's requirements determination 
process--the Joint Capabilities Integration and Development System. An 
ICD identifies the existence of capability gap(s), the operational 
risks associated with the gap(s), and a recommended solution or 
preferred set of solutions for filling the gap(s). 

[6] An AOA is an evaluation of the performance, effectiveness, 
suitability, and estimated costs of alternative systems to meet a 
capability. 

[7] In December 2008, DOD revised its acquisition instruction-- 
Department of Defense Instruction 5000.02, Operation of the Defense 
Acquisition System. The Weapon Systems Acquisition Reform Act of 2009, 
Pub. L. No. 111-23, was enacted on May 22, 2009. 

[8] If done correctly, the use of an incremental approach to 
development is a best practice that our work has shown enables 
organizations to achieve a match between needs and resources. Under 
this approach, basic requirements are achieved first, with additional 
capabilities planned for future generations of the product. Because 
product development is incremental, achieving knowledge is more 
manageable. As we have reported, commercial companies have found that 
trying to capture the knowledge needed to stabilize the design of a 
product with considerable new technical content is an unwieldy task-- 
especially if the goal is to reduce development cycle times and get 
the product to the marketplace as quickly as possible. GAO, Best 
Practices: Using a Knowledge-Based Approach to Improve Weapon 
Acquisition, [hyperlink, http://www.gao.gov/products/GAO-04-386SP] 
(Washington, D.C.: January 2004). 

[9] GAO, Defense Acquisitions: Strong Leadership Is Key to Planning 
and Executing Stable Weapon Programs, [hyperlink, 
http://www.gao.gov/products/GAO-10-522] (Washington, D.C.: May 6, 
2010). 

[10] Institute for Defense Analyses, VH-71 Presidential Helicopter 
Program Assessment, IDA Paper P-4243 (Alexandria, Va., July 2007) 
(Distribution authorized to U.S. government agencies and their 
contractors; Specific Authority. Other requests must be referred to 
OUSD(AT&L).) 

[11] The VXX Milestone A is currently expected to occur sometime in 
fiscal year 2011. 

[12] The analysis typically evaluates military doctrine, organization, 
training, materiel, leadership and education, personnel, and 
facilities to try to identify a nonmaterial solution to a capability 
gap or gaps. 

[13] Chairman of the Joint Chiefs of Staff Instruction 3170.01G, Joint 
Capabilities Integration and Development System (2009), encl. A, 2(d). 
When the Joint Requirements Oversight Council approves an ICD, it 
validates the capabilities required to perform the mission as defined, 
the gaps in capabilities along with their priorities and operational 
risks, and the need to address the capability gaps. 

[14] GAO, Defense Acquisitions: Many Analyses of Alternatives Have Not 
Provided a Robust Assessment of Weapon System Options, [hyperlink, 
http://www.gao.gov/products/GAO-09-665] (Washington, D.C.: Sept. 24, 
2009). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: