This is the accessible text file for GAO report number GAO-09-451 
entitled 'Nuclear and Worker Safety: Limited Information Exists on 
Costs and Reasons for Work Stoppages at DOE's Hanford Site' which was 
released on June 8, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Requesters: 

United States Government Accountability Office: 
GAO: 

May 2009: 

Nuclear and Worker Safety: 

Limited Information Exists on Costs and Reasons for Work Stoppages at 
DOE's Hanford Site: 

GAO-09-451: 

GAO Highlights: 

Highlights of GAO-09-451, a report to congressional requesters. 

Why GAO Did This Study: 

The Department of Energy’s (DOE) Hanford Site in Washington State 
stores 56 million gallons of untreated radioactive and hazardous wastes 
resulting from decades of nuclear weapons production. DOE is 
constructing facilities at the site to treat these wastes before 
permanent disposal. As part of meeting health, safety, and other 
standards, work at the site has sometimes been suspended to address 
safety or construction quality issues. This report discusses (1) work 
stoppages from January 2000 through December 2008 and what is known 
about them, (2) the types of costs associated with work stoppages and 
who paid for them, and (3) whether more effective regulation or 
oversight could have prevented the work stoppages. GAO interviewed 
knowledgeable DOE and contractor officials about these events. When 
documentation was available, GAO obtained DOE and contractor accident 
and safety incident reports, internal DOE and independent external 
evaluations, and costs. 

What GAO Found: 

DOE officials reported that from January 2000 through December 2008, 
activities to manage hazardous wastes stored in underground tanks and 
to construct a waste treatment facility have been suspended at least 31 
times to address safety concerns or construction quality issues. 
Federal regulations governing contracts do not require contractors to 
formally report work stoppages and the reasons for them, and DOE does 
not routinely collect information on them. As a result, supporting 
documentation on work stoppages was limited. DOE reported that work 
stoppages varied widely in duration, with some incidents lasting a few 
hours, and others lasting 2 years or more. Officials reported that 
about half the work stoppages resulted from concerns about worker or 
nuclear safety and included proactive safety “pauses,” which typically 
were brief and taken to address an unsafe condition that could 
potentially harm workers. The remainder of the work stoppages occurred 
to address concerns about construction quality at the waste treatment 
plant. 

Under the terms of the cost-reimbursement contracts for managing the 
tanks and constructing the waste treatment plant, DOE generally pays 
all costs associated with temporary work stoppages and does not require 
the contractor to separately track these costs, although DOE and the 
contractors do track some costs under certain circumstances. For 
example, the costs for cleaning up, investigating, and implementing 
corrective actions were collected for a July 2007 hazardous waste spill 
at one of the tank farms; these costs totaled over $8 million. The 
contractors, too, can face financial consequences, such as reduction in 
earned fee or fines and penalties assessed by DOE or outside 
regulators. For example, DOE may withhold payment of a performance 
award, called a fee, from contractors for failure to meet specified 
performance objectives or to comply with applicable environmental, 
safety, and health requirements. 

For the majority of DOE’s reported work stoppages, supporting 
documentation was not available to evaluate whether better oversight or 
regulation could have prevented them. For 2 of 31 work stoppages where 
some information was available—specifically, accident investigations or 
prior GAO work—inadequate oversight contributed to the work stoppages. 
For example, the accident investigation report for the tank farm spill 
found that oversight and design reviews by DOE’s Office of River 
Protection failed to identify deficiencies in the tanks’ pump system 
design, which did not meet nuclear technical safety requirements. 
Similarly, in 2006, GAO found that DOE’s failure to effectively 
implement nuclear safety requirements contributed substantially to 
schedule delays and cost growth at Hanford’s waste treatment plant. 
With regard to regulations, however, officials from DOE, the Defense 
Nuclear Facilities Safety Board, and DOE’s Office of Inspector General 
said they did not believe that insufficient regulation was a factor in 
these events. 

What GAO Recommends: 

GAO is recommending that the Secretary of Energy (1) establish criteria 
for when DOE should direct contractors to track and report reasons for 
and costs of work stoppages and (2) specify the types of costs to be 
tracked. In commenting on a draft of the report, DOE generally agreed 
with GAO’s recommendations but plans to implement them only within 
Environmental Management. 

View [hyperlink, http://www.gao.gov/products/GAO-09-451] or key 
components. For more information, contact Gene Aloise at (202) 512-3841 
or aloisee@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

DOE Officials Reported Varied Reasons for Work Stoppages at Tank Farms 
and the Waste Treatment Plant, but Supporting Documentation Is Limited: 

DOE Generally Pays Costs Associated with Work Stoppages: 

Inadequate Oversight Cited as Contributing to Some Work Stoppages: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Work Stoppages Identified by the Office of River 
Protection: 

Appendix III: Comments from the Department of Energy: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Table: 

Table 1: Summary of Work Stoppages at the Hanford Site, January 2000 to 
December 2008 (in order of duration): 

Figures: 

Figure 1: Double-Shell Waste Tanks under Construction and Completed 
Tank Farm at DOE's Hanford Site: 

Figure 2: Waste Treatment Plant Primary Facilities under Construction 
as of November 2008: 

Abbreviations: 

CH2M Hill: CH2M Hill Hanford Group 

DOE: Department of Energy: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

May 7, 2009: 

The Honorable Henry A. Waxman: 
Chairman: 
The Honorable John D. Dingell: 
Chairman Emeritus: 
The Honorable Joe Barton: 
Ranking Member: 
Committee on Energy and Commerce: 
House of Representatives: 

The Honorable Bart Stupak: 
Chairman: 
The Honorable Greg Walden: 
Ranking Member: 
Subcommittee on Oversight and Investigations: 
Committee on Energy and Commerce 
House of Representatives: 

The Honorable Jay Inslee: 
House of Representatives: 

The Department of Energy (DOE) is responsible for one of the world's 
largest environmental cleanup programs--the treatment and permanent 
disposal of wastes created by the production of materials for the 
nation's nuclear weapons program. At the production sites, more than 5 
decades of nuclear weapons production left a legacy of chemical, 
hazardous, and radioactive waste. DOE's Hanford Site in southeastern 
Washington State stores the majority of the untreated nuclear waste-- 
about 56 million gallons held in 177 large underground storage tanks 
clustered in areas known as tank farms.[Footnote 1] DOE has estimated 
that it will take tens of billions of dollars and decades to treat and 
permanently dispose of this waste. 

DOE's Office of River Protection oversees activities at the tank farms 
but relies on contractors to carry out the work. At the Hanford Site, 
one contractor, CH2M Hill Hanford Group (CH2M Hill) is responsible for 
managing and operating the tank farms, which includes maintaining safe 
storage of the waste and preparing it for eventual retrieval.[Footnote 
2] A second contractor, Bechtel National Inc. (Bechtel), is responsible 
for carrying out a multibillion dollar construction project for new 
facilities, known as the waste treatment plant, to treat the tank waste 
and prepare it for permanent disposal.[Footnote 3] DOE spends about $1 
billion annually on these two contracts alone. In carrying out these 
activities, DOE and its contractors must comply with health and safety 
standards to protect workers, the public, and the environment. 

As part of meeting health and safety standards, work activities have, 
at times, been suspended[Footnote 4] over the past several years to 
address concerns with worker safety or nuclear safety at the tank farms 
and during the design and construction of waste treatment facilities. 
Such suspensions vary in duration and allow for additional worker 
training or corrective actions. In this report, we refer to these 
suspensions as work stoppages. To provide a better understanding of 
these occurrences and potential financial consequences, this report 
discusses (1) work stoppages from January 2000 through December 2008 at 
DOE's Hanford Site tank farms and waste treatment plant and what is 
known about their nature, duration, and scope; (2) the types of costs 
associated with work stoppages and what portions were paid by the 
government and by the contractor; and (3) whether more effective 
regulation or oversight might have prevented the work stoppages. 

In conducting our work, we obtained a listing of work stoppages at the 
tank farms and waste treatment plant from officials at DOE's Office of 
River Protection. We attempted to independently verify any work 
stoppages that occurred at the tank farms or waste treatment plant by 
reviewing accident investigation reports and existing DOE reporting 
systems for events that could have resulted in a temporary work 
stoppage. Of the 31 work stoppages reported, only 3 had any supporting 
documentation. For those 3 work stoppages, we reviewed and analyzed the 
documents provided to obtain a more thorough understanding of the 
events, causes, and corrective actions and whether DOE regulation or 
oversight was a contributing factor. We also interviewed DOE officials 
with the Office of River Protection, as well as DOE headquarters 
officials with the Offices of Environmental Management; Health, Safety, 
and Security; and General Counsel. We interviewed officials with 
regulatory and oversight entities, including the Defense Nuclear 
Facilities Safety Board, the Occupational Safety and Health 
Administration, and the Nuclear Regulatory Commission. Further, we met 
with union representatives at the Hanford Site to obtain union 
perspectives on work stoppages and safety. A more detailed description 
of our scope and methodology appears in appendix I. We conducted this 
performance audit from June 2008 to April 2009, in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

Background: 

Since plutonium production ended at the Hanford Site in the late 1980s, 
DOE has focused on cleaning up the radioactive and hazardous waste 
accumulated at the site. It has established an approach for 
stabilizing, treating, and disposing of the site's tank wastes. Its 
planned cleanup process involves removing, or retrieving, waste from 
the tanks; treating the waste on site; and ultimately disposing of the 
lower-activity radioactive waste on site and sending the highly 
radioactive waste to a geologic repository for permanent disposal. As 
cleanup has unfolded, however, the schedule has slipped, and the costs 
have mounted. According to DOE's latest estimate in June 2008, 
treatment of the waste is not expected to begin until late 2019 and 
could continue until 2050 or longer. The following two figures show a 
tank farm and construction of waste treatment plant facilities at the 
Hanford Site. 

Figure 1: Double-Shell Waste Tanks under Construction and Completed 
Tank Farm at DOE's Hanford Site: 

[Refer to PDF for image: two photographs] 

Source: DOE. 

[End of figure] 

Figure 2: Waste Treatment Plant Primary Facilities under Construction 
as of November 2008: 

[Refer to PDF for image: photograph] 

Source: DOE. 

[End of figure] 

Most of the cleanup activities at Hanford, including the emptying of 
the underground tanks, are carried out under the Hanford Federal 
Facility Agreement and Consent Order among DOE, Washington State's 
Department of Ecology, and the federal Environmental Protection Agency. 
Commonly called the Tri-Party Agreement, this accord lays out legally 
binding milestones for completing the major steps of Hanford's waste 
treatment and cleanup processes. The agreement was signed in May 1989 
and has been amended a number of times since then. A variety of local 
and regional stakeholders, including county and local governmental 
agencies, citizen and advisory groups, and Native American tribes, also 
have long-standing interests in Hanford cleanup issues. 

Two primary contractors are carrying out these cleanup activities; one 
is responsible for managing and operating the tank farms, and the other 
for constructing the facilities to treat the tank waste and prepare it 
for permanent disposal. During our review, these contractors were CH2M 
Hill and Bechtel, respectively. Both contracts are cost-reimbursement 
contracts, which means that DOE pays all allowable costs.[Footnote 5] 
In addition, the contractors can also earn a fee, or profit, by meeting 
specified performance objectives or measures. Applicable DOE orders and 
regulations are incorporated into these contracts, either as distinct 
contract clauses or by reference. For example, contractors are required 
to use an accounting system that provides consistency in how costs are 
accumulated and reported so that comparable financial transactions are 
treated alike. Such a system is to include consistent practices for 
determining how various administrative costs are assessed or how 
indirect costs for labor are calculated. Contractors also are required 
to implement an integrated safety management system, a set of 
standardized practices that allow the contractor to identify hazards 
associated with a specific scope of work, to establish controls to 
ensure that work is performed safely, and to provide feedback that 
supports continuous improvement. The system, which allows contractors 
to stop work when conditions are unsafe, is intended to instill in 
everyone working at the site a sense of responsibility for safety. This 
policy is reinforced by labor agreements between the contractor and its 
workforce that explicitly allow work stoppages as needed for safety and 
security reasons. 

With few exceptions, DOE's sites and facilities are not regulated by 
the Nuclear Regulatory Commission or by the Occupational Safety and 
Health Administration. Instead, DOE provides internal oversight at 
several different levels. DOE's Office of River Protection oversees the 
contractors directly. In addition, the Office of Environmental 
Management provides funding and program direction. DOE's Office of 
Enforcement[Footnote 6] and other oversight groups within the Office of 
Health, Safety, and Security oversee contractors' activities to ensure 
nuclear and worker safety. Finally, the Defense Nuclear Facilities 
Safety Board, an independent oversight organization created by Congress 
in 1988, provides advice and recommendations to the Secretary of Energy 
to help ensure adequate protection of public health and safety. 

DOE Officials Reported Varied Reasons for Work Stoppages at Tank Farms 
and the Waste Treatment Plant, but Supporting Documentation Is Limited: 

DOE officials reported that from January 2000 through December 2008, 
work on the Hanford tank farms and the waste treatment plant 
temporarily stopped at least 31 times to address various safety or 
construction concerns. These work stoppages ranged in duration from a 
few hours to more than 2 years, yet little supporting documentation of 
these occurrences exists. 

Work Was Stopped to Address Safety or Construction Concerns: 

DOE reported that of the 31 work stoppages, 12 occurred at the tank 
farms and 19 at the waste treatment plant. Sixteen of the work 
stoppages reportedly resulted from concerns about safety. A complete 
listing of these work stoppages is included in appendix II. These work 
stoppages were initiated to respond directly to an event in which 
property was damaged or a person injured, or they addressed an unsafe 
condition with the potential to harm workers in the future. Four of 
these work stoppages were relatively brief, lasting less than 2 days, 
and were characterized by DOE and officials as proactive safety 
"pauses." For example, in October 2007, after a series of slips, trips, 
or falls during routine activities, contractor managers stopped work at 
the waste treatment plant site for 1 hour to refresh workers' 
understanding of workplace hazards. 

The following two examples, for which supporting documentation was 
available, illustrate the types of work stoppages occurring at the 
Hanford Site because of safety concerns: 

* Controlling worker exposure to tank farm vapors. Beginning in 2002, 
as activities to transfer waste from leak-prone, single-shell tanks to 
more secure double-shell tanks disturbed tank contents, the number of 
incidents increased in which workers complained of illnesses, coughing, 
and skin irritation after exposure to the tank vapors. The Hanford 
underground storage tanks contain a complex variety of radioactive 
elements and chemicals that have been extensively mixed and commingled 
over the years, and DOE is uncertain of the specific proportions of 
chemicals contained in any one tank. These constituents generate 
numerous gases, such as ammonia, hydrogen, and volatile organic 
compounds, which are purposely vented to release pressure on the tanks, 
although some gases also escape through leaks. During the 1990s, the 
tank farm contractor evaluated potential hazards and determined that if 
workers around the tanks used respirators, they would be sufficiently 
protected from harmful gases. DOE reported in 2004, however, that 
disturbing the tank waste during transfers had changed the 
concentration of gases released in the tanks and that no standards for 
human exposure to some of these chemicals existed. To protect workers' 
health, in 2004 the tank farm contractor equipped workers with tanks of 
air like those used by firefighters. Work at the tank farms stopped 
intermittently for about 2 weeks as a result, in part because the 
contractor had to locate and procure sufficient self-contained air and 
equipment for all workers. 

* Accidental spill of radioactive and chemical wastes at tank S-102. In 
July 2007, as waste was being pumped out of a single-shell to a double- 
shell tank, about 85 gallons of waste was spilled. DOE has been 
gradually emptying waste from Hanford's single-shell tanks into double- 
shell tanks in preparation for treatment and permanent disposal, but 
because the tank waste contains sludge and solids, waste removal has 
been challenging. Because the tanks were not designed with specific 
waste retrieval features, waste must be retrieved through openings, 
called risers, in the tops of the tanks; technicians must insert 
specially designed pumps into the tanks to pump the waste up about 45 
to 60 feet to ground level. DOE has used a variety of technologies to 
loosen the solids, including sprays of acid or water to help break up 
the waste and a vacuum-like system to suck up and remove waste through 
the risers at the top. On July 27, 2007, during retrieval of 
radioactive mixed waste from a 758,000-gallon single-shell tank, a pump 
failed, spilling 85 gallons of highly radioactive waste to the ground. 
At least two workers were exposed to chemical vapors, and later several 
workers reported health effects they believed to be related to the 
spill. Retrieval operations for all single-shell tanks were suspended 
after the accident, and DOE did not resume operations until June 2008, 
a delay of 1 year, while the contractor cleaned up the spill and DOE 
and the contractor investigated the accident to evaluate the cause, the 
contractor's response, and appropriate corrective action. 

DOE officials reported that the remaining 15 work stoppages resulted 
from concerns about construction quality and involved rework to address 
nuclear safety or technical requirements that had not been fully met, 
such as defective design, parts fabrication and installation, or faulty 
construction. For example: 

* Outdated ground-motion studies supporting seismic design of the waste 
treatment plant. In 2002, the Defense Nuclear Facilities Safety Board 
began expressing concerns that the seismic standards used to design the 
waste treatment facilities were not based on the most current ground- 
motion studies and computer models or on the geologic conditions 
present directly beneath the construction site. After more than 2 years 
of analysis and discussion, DOE contracted for an initial seismic 
analysis, which confirmed the Defense Nuclear Facilities Safety Board's 
concerns that the seismic criteria were not sufficiently conservative 
for the largest treatment facilities--the pretreatment facility and the 
high-level waste facility. Revising the seismic criteria caused Bechtel 
to recalculate thousands of engineering estimates and to rework 
thousands of design drawings to ensure that tanks, piping, cables, and 
other equipment in these facilities were adequately anchored. Bechtel 
determined that the portions of the building structures already 
constructed were sufficiently robust to meet the new seismic 
requirements. By December 2005, however, Bechtel estimated that 
engineering rework and other changes to tanks and other equipment 
resulting from the more conservative seismic requirement would increase 
project costs substantially and add as much as 26 months to the 
schedule. Ultimately, work on the two facilities was suspended for 2 
years, from August 2005 until August 2007. About 900 workers were laid 
off as a result. 

Information on Work Stoppages Is Not Consistently Collected: 

DOE does not routinely collect or formally report information about 
work stoppages, in part because federal regulations governing contracts 
do not require contractors to track work stoppages and the reasons for 
them.[Footnote 7] While federal acquisition regulations do require that 
contractors implement a reliable cost-accounting system, the 
regulations do not require contractors to centrally collect information 
on the specific circumstances surrounding a work stoppage. Without a 
centralized system for collecting explanatory data on work stoppages, 
the majority of information DOE reported to us is based on contractors' 
and DOE officials' recollections of those events or on officials' 
review of detailed logs maintained at each of the facilities. 

Officials expressed concern that systematically monitoring all work 
stoppages could send the message that work stoppages should be avoided, 
possibly hampering effective implementation of DOE's integrated safety 
management policy. This policy explicitly encourages any employee to 
"stop work" to address conditions that raise safety concerns. Officials 
said they believe that work stoppages help bolster workplace safety and 
construction quality because work can be halted and corrective action 
taken before someone is seriously injured, property is seriously 
damaged, or poor workmanship has compromised the quality and 
functionality of a facility. Officials said that systematically 
monitoring all types of work stoppages could ultimately discourage 
workers from halting activities when unsafe conditions or construction 
problems emerge in the workplace. 

DOE Generally Pays Costs Associated with Work Stoppages: 

Under the terms of the cost-reimbursement contracts for the tank farms 
and the waste treatment plant, DOE generally pays the costs for 
corrective action or construction rework associated with temporary work 
stoppages and does not require the contractor to separately track these 
costs. 

Costs Associated with Work Stoppages Can Include Corrective Action and 
Lost Productivity: 

Various categories of costs can be associated with work stoppages, with 
some easier to measure or separately identify than others. The category 
of costs related to correcting a problem that precipitates a work 
stoppage, such as the cost of investigating and cleaning up a hazardous 
waste spill or the cost of rework to address improper construction, is 
usually more easily measured. In contrast, lost productivity-- 
expenditures for labor during periods workers were not fully engaged in 
productive work or the difference between the value of work that should 
have been accomplished against the value of work that was accomplished--
is more difficult to quantify. 

Most of the work stoppages reported by DOE officials involved some 
corrective action or construction rework to address the problem 
precipitating the work stoppage. These are costs that tend to be easier 
to separately identify and track, and DOE has directed contractors to 
do so in certain instances, as it did for the July 2007 tank waste 
spill. For the work stoppages at the tank farms, corrective actions 
encompassed such activities as investigating and cleaning up the July 
2007 spill, monitoring and testing vapors escaping from the tanks to 
determine the constituents, and training contractor employees on 
required new procedures or processes. For the work stoppages at the 
waste treatment plant, corrective actions at times involved retraining 
workers or developing new procedures to prevent future problems, 
although many of the work stoppages at the waste treatment plant 
involved construction rework. Construction rework can include obtaining 
new parts to replace substandard parts or labor and materials to undo 
installations or construction, followed by proper installation or 
construction--pouring new concrete, for example, or engineering and 
design work to address nuclear safety issues. 

The cost of lost productivity associated with a work stoppage can be 
more difficult to measure or separately identify, although under a cost-
reimbursement contract, the government would generally absorb the cost. 
While no generally accepted means of measuring lost productivity 
exists, two methods have been commonly used. The first, a measure of 
the cost of idleness, or doing nothing, calculates the expense incurred 
for labor and overhead during periods that no productive work is taking 
place. These were the types of costs associated with a July 2004 
suspension, or "stand-down," of operations at the Los Alamos National 
Laboratory, where a pattern of mishaps led the contractor to stop most 
work at the facility for many months to address safety and security 
concerns. Laboratory activities resumed in stages, returning to full 
operations in May 2005. Although officials with both the National 
Nuclear Security Administration, which oversees the laboratory, and the 
Los Alamos contractor, tried to measure lost productivity at the 
laboratory, each developed widely differing estimates--of $370 million 
and $121 million, respectively--partly because of difficulties 
measuring labor costs.[Footnote 8] According to DOE officials, when 
work stopped at the Hanford Site tank farms, CH2M Hill reassigned 
workers to other productive activities. Therefore, according to DOE 
officials, no costs of idleness were incurred as a result of those work 
stoppages. We were unable to verify, however, that tank farm workers 
had been reassigned to other productive work after the S-102 tank waste 
spill or during other tank farm work stoppages. During the period that 
work stopped on the pretreatment and high-level waste facilities of the 
waste treatment plant, in contrast, the contractor substantially 
reduced its workforce. According to Bechtel officials and documents, 
about 900 of 1,200 construction workers were laid off during the work 
stoppage, and the remaining workers were employed on the other 
facilities under construction. 

An alternative means of measuring lost productivity associated with 
suspension of work activities is to measure the value of work planned 
that should have been accomplished but was not. This method 
concentrates on the work that was not done, as opposed to the cost of 
paying workers to do little or nothing. This method of measuring lost 
productivity is typically undertaken as part of a formal earned value 
management system, a project management approach that combines the 
technical scope of work with schedule and cost elements to establish an 
"earned value" for a specific set of tasks. If the earned value of work 
accomplished during a given period is less than the earned value of 
work planned for that period, then a loss in productivity has occurred, 
and the cost is equal to the difference in value between planned and 
finished work.[Footnote 9] DOE officials were unable to provide this 
measure for the three work stoppages that had supporting documentation, 
partly because the analyses of productivity under earned value 
management techniques did not disaggregate activities in a manner that 
could capture the three work stoppages. For example, with regard to the 
tank farms, DOE measures the overall progress made on waste 
stabilization and retrieval for all 177 storage tanks in aggregate but 
does not measure the direct impact of setbacks at any one storage tank, 
such as the spill at tank S-102. 

Contractors Are Not Ordinarily Required to Track Work Stoppage Costs 
Separately: 

The contracts for the tank farms and the waste treatment plant do not 
generally require the contractors to separately track costs associated 
with work stoppages. Contractors must use an accounting system adequate 
to allow DOE to track costs incurred against the budget in accordance 
with federal cost-accounting standards. These standards permit a 
contractor to establish and use its own cost-accounting system, as long 
as the system provides an accurate breakdown of work performed and the 
accumulated costs and allows comparisons against the budget for that 
work. For the tank farm and waste treatment plant contracts, the 
contractors must completely define a project by identifying discrete 
physical work activities, essentially the steps necessary to carry out 
the project. This "work breakdown structure" is the basis for tracking 
costs and schedule progress. Corrective action and rework associated 
with work stoppages are generally not explicitly identified as part of 
a project's work breakdown structure, although these costs are 
generally allowable and contractors do not have to account for them 
separately. 

Despite the lack of a requirement to track costs associated with work 
stoppages, DOE and contractors sometimes do track these costs 
separately, as in the following three circumstances: 

* DOE can request the contractor to separately track costs associated 
with corrective action when DOE officials believe it is warranted. DOE 
specifically asked CH2M Hill to separately track costs associated with 
addressing the July 2007 tank spill because of the potential impacts on 
tank farm operations, workers, and the environment and because of 
heightened public and media attention to the event. 

* Contractors may voluntarily track selected costs associated with a 
work stoppage if they believe that a prolonged suspension of work will 
alter a project's cost and schedule. Contractors may want to collect 
this information for internal management purposes or to request an 
adjustment of contract terms in the future. For example, Bechtel 
estimated costs for both redesign work and lost productivity resulting 
from a change in seismic standards for the waste treatment plant. 

* DOE may require a contractor to track particular costs associated 
with investigating an incident that it believes may violate DOE nuclear 
safety requirements or the Atomic Energy Act of 1954, as amended (these 
violations are referred to as Price-Anderson Amendment Act violations). 
DOE's Office of Enforcement notifies the contractor in a "segregation 
letter" that an investigation of the potential violation will be 
initiated and that the contractor must segregate, or separately 
identify, any costs incurred in connection with the investigation. 
These are not costs of corrective action or rework. The costs incurred 
in connection with the investigation are generally not allowable. Not 
all such investigations involve a work stoppage, however. 

Of the 31 work stoppages reported to us by DOE officials, costs are 
available only for the July 2007 spill at the tank farm, since DOE 
specifically required the contractor to separately identify and report 
those costs. The costs of that incident totaled $8.1 million and 
included expenditures for cleaning up contamination resulting from the 
spill, investigating the causes of the accident, investigating health 
effects of the accident on workers, administrative support, and 
oversight of remediation activities. These were all considered 
allowable costs, and DOE has reimbursed the contractor for them. 
Although a subsequent investigation took place to determine whether 
nuclear safety rules had been violated, the costs to participate in 
that investigation ($52,913) were segregated as directed by DOE's 
Office of Enforcement and were not billed to the government. 

Although DOE officials said that none of the reported work stoppages 
involved lost-productivity costs, the work stoppage to address the tank 
spill could well contribute to delays and rising costs for tank waste 
retrieval activities over the long run. Given that DOE was emptying 
only about one tank per year when we reported on Hanford tanks in June 
2008,[Footnote 10] the 1-year suspension of waste retrieval activities, 
without additional steps to recover lost time, may contribute to 
delayed project completion. Many factors already contribute to delays 
in emptying the tanks. DOE has acknowledged that it will not meet the 
milestones agreed to with Washington State and the Environmental 
Protection Agency in the Tri-Party Agreement. We found that DOE's own 
internal schedule for tank waste retrieval, approved in mid-2007, 
reflects time frames almost 2 decades later than those in the 
agreement. Ultimately, delays contribute to higher costs because of 
ongoing costs to monitor the waste until it is retrieved, treated, and 
permanently disposed of, and estimated costs for tank waste retrieval 
and closure have been growing. DOE estimated in 2003 that waste 
retrieval and closure costs from 2007 onward--in addition to the $236 
million already spent to empty the first seven tanks--would be about 
$4.3 billion. By 2006, this estimate had grown to $7.6 billion. Because 
of limitations in DOE's reporting systems, however, we were unable to 
determine the specific effect of the tank spill on overall tank 
retrieval costs beyond the $8.1 million in corrective action costs. 

In addition, although specific costs were not available for the 2-year 
suspension of construction activities at two of the facilities in the 
waste treatment plant, we have previously reported on some of the 
potential impacts. In an April 2006 testimony,[Footnote 11] we reported 
on the many technical challenges Bechtel had encountered during design 
and construction of the waste treatment plant. These ongoing technical 
challenges included changing seismic standards that resulted in 
substantial reengineering of the design for the pretreatment and high- 
level waste facilities, problems at the pretreatment plant with "pulse 
jet mixers" needed to keep waste constituents uniformly mixed while in 
various tanks, and the potential buildup of flammable hydrogen gas in 
the waste treatment plant tanks and pipes. In December 2005, Bechtel 
estimated that these technical problems could collectively add nearly 
$1.4 billion to the project's estimated cost. 

DOE Generally Pays All Costs, but Contractors Can Face Some Financial 
Consequences: 

Under the cost-reimbursement contracts for the tank farms and the waste 
treatment plant, costs associated with work stoppages, such as the 
costs of corrective action or construction rework, generally are 
allowable costs. As such, DOE generally pays these costs, regardless of 
whether they are separately identified or whether they are included in 
the overall costs of work performed. 

Even though the contractors are being reimbursed for the costs 
associated with work stoppages, they can experience financial 
consequences, either through loss of performance fee or fines and 
penalties assessed by DOE or its regulators. For example, DOE may 
withhold payment of a performance award, called a fee, from contractors 
for failure to meet specified performance objectives or measures or to 
comply with applicable environmental, safety, and health requirements. 
The tank farm and waste treatment plant contractors both lost 
performance fee because of work stoppages as follows: 

* For the July 2007 spill at the tank farms, under CH2M Hill's 
"conditional payment of fee" provision, DOE reduced by $500,000 the 
performance fee the contractor could have earned for the year. In its 
memo to the contractor, DOE stated that the event and the contractor's 
associated response were not consistent with the minimum requirement 
for protecting the safety and health of workers, public health, and the 
environment. Nevertheless, DOE did allow CH2M Hill to earn up to 
$250,000, or half the reduction amount, provided the contractor fully 
implement the corrective action plan developed after the accident 
investigation, with verification of these actions by DOE personnel. 

* Bechtel also lost performance fee because of design and construction 
deficiencies at the waste treatment plant facilities and the 2-year 
delay on construction of the pretreatment and high-level waste 
facilities. Overall, DOE withheld $500,000 in Bechtel's potential 
performance fee for failure to meet construction milestones. In 
addition, DOE withheld $300,000 under the "conditional payment of fee" 
provision in the contract after a number of serious safety events and 
near misses on the project. 

Furthermore, in addition to having potential fee reduced for safety 
violations and work stoppages, DOE and other federal and state 
regulators may also assess fines or civil penalties against contractors 
for violating nuclear safety rules and other legal or regulatory 
requirements. These fines and penalties are one of the categories of 
costs that are specifically not allowed under cost-reimbursement 
contracts, and these costs are borne solely by the contractor. For 
example, DOE's Office of Enforcement can assess civil penalties for 
violations of nuclear safety and worker safety and health rules. Both 
contractors were assessed fines or civil penalties for the events 
associated with their work stoppages. 

* Fines and penalties assessed against CH2M Hill for the July 2007 tank 
spill totaled over $800,000 and included (1) civil penalties of 
$302,500 assessed by DOE's Office of Enforcement for violation of 
nuclear safety rules, such as long-standing problems in ensuring 
engineering quality and deficiencies in recognizing and responding to 
the spill; (2) a Washington State Department of Ecology fine of 
$500,000 for inadequacies in design of the waste retrieval system and 
inadequate engineering reviews; and (3) a fine of $30,800 from the 
Environmental Protection Agency for delays in notification of the 
event. The contractor was required to notify the agency within 15 
minutes of the spill but instead took almost 12 hours. 

* From March 2006 through December 2008, DOE's Office of Enforcement 
issued three separate notices of violation to Bechtel, with civil 
penalties totaling $748,000. These violations of nuclear safety rules 
were associated with procurement and design deficiencies of specific 
components at the waste treatment plant. In its December 2008 letter to 
the contractor, DOE stated that significant deficiencies in Bechtel's 
quality-assurance system represented weaknesses that had also been 
found in the two earlier enforcement actions. 

Inadequate Oversight Cited as Contributing to Some Work Stoppages: 

For the majority of DOE's reported work stoppages, no supporting 
documentation was available to evaluate whether better oversight or 
regulation could have prevented them. For two incidents for which 
documentation was available--internal investigations and prior GAO 
work--a lack of oversight contributed to both. These two work stoppages 
occurred at the tank farms and the waste treatment plant, and both 
resulted from engineering-design problems. In a third case--efforts to 
address potentially hazardous vapors venting from underground waste 
storage tanks--DOE's efforts to enforce worker protections were found 
to have been inadequate, although this lack of oversight does not 
appear to have directly caused the work stoppage associated with the 
vapors problem. 

Insufficient oversight was a factor in these three events as follows: 

* Accidental spill of radioactive and chemical wastes at tank S-102. 
Specifically, the accident investigation report for the tank farm spill 
found that oversight and design reviews by DOE's Office of River 
Protection failed to identify deficiencies in CH2M Hill's tank pump 
system, which did not meet nuclear safety technical requirements. The 
Office of River Protection failed to determine that this pump system 
did not have a needed backflow device to prevent excessive pressure in 
one of the hoses serving a tank, ultimately causing it to fail and 
release waste, which then overflowed from the top of this tank and 
spilled to the ground. In addition, the investigation found that CH2M 
Hill failed to respond to the accident in a timely manner and failed to 
ensure that nuclear safety requirements had been met. 

* Outdated ground-motion studies supporting seismic design of the waste 
treatment plant. Lax oversight was also a factor in a second event at 
the waste treatment plant. GAO in 2006 found that DOE's failure to 
effectively implement nuclear safety requirements, including 
requirements that all waste treatment plant facilities would survive a 
potential earthquake, contributed substantially to delays and growing 
costs at the plant. The Defense Nuclear Facilities Safety Board first 
expressed concerns with the seismic design in 2002, believing that the 
seismic standards followed had not been based on then-current ground- 
motion studies and computer models or on geologic conditions directly 
below the waste treatment plant site. It took DOE 2 years to confirm 
that the designs for two of the facilities at the site--the 
pretreatment and the high-level waste facilities--were not sufficiently 
conservative. Revising the seismic criteria required Bechtel to 
recalculate thousands of design drawings and engineering estimates to 
ensure that key components of these facilities would be adequately 
anchored. Work was halted at the two facilities for 2 years as a 
result. 

* Controlling worker exposure to tank farm vapors. In 2004, DOE's then 
Office of Independent Oversight and Performance Assurance (today 
reorganized as DOE's Office of Health, Safety, and Security) 
investigated vapor exposures at the Hanford tank farms and the adequacy 
of worker safety and health programs at the site, including the 
adequacy of DOE oversight. Investigators were unable to determine 
whether any workers had been exposed to hazardous vapors in excess of 
regulatory limits but found several weaknesses in the industrial 
hygiene (worker safety) program at the site, in particular, hazard 
controls and DOE oversight. According to the investigation, the Office 
of River Protection had not effectively overseen the contractor's 
worker safety program; had failed to provide the necessary expertise, 
time, and resources to adequately perform its management oversight 
responsibilities at the tank farms; and had failed to ensure corrective 
action for identified problems. After the investigation, DOE stepped up 
its monitoring efforts at the tank farms, and the contractor provided 
tank farm workers with supplied air, an action that slowed or halted 
work at the tank farms for about 2 weeks while supplied air equipment 
was secured and workers were trained to use it. 

With regard to regulations, however, officials we interviewed from DOE, 
the Defense Nuclear Facilities Safety Board, and the Office of 
Inspector General said they did not believe that insufficient 
regulation was a factor in these two events. Officials from the Nuclear 
Regulatory Commission declined to comment on the sufficiency of 
regulations. 

Conclusions: 

The final cost to the American public of cleaning up the Hanford Site 
is expected to reach tens of billions of dollars. Consequently, factors 
that can potentially escalate costs--including work stoppages--matter 
to taxpayers, DOE, and Congress. Depending on what causes a work 
stoppage and how long it lasts, some stoppages could increase already 
substantial cleanup costs. Although prudent oversight would seem to 
call for DOE to understand the reasons for work stoppages and the 
effects of these work stoppages on costs, neither law nor regulation 
requires that this information be systematically recorded and reported. 
DOE and other stakeholders have expressed reservations that collecting 
information on work stoppages could send a message that work stoppages 
should be minimized, thus discouraging managers or workers from 
reporting potential safety or construction quality issues. We recognize 
that the opportunity for any manager or worker to call a work stoppage 
when worker safety or construction quality is at stake is an integral 
part of DOE's safety and construction management strategies and should 
not be stifled. Yet DOE has also recognized the importance of cost 
information and in one recent case--the 2007 tank waste spill--required 
the contractor to separately track detailed cost information. In 
addition, we previously recommended that DOE require contractors to 
track the costs associated with future work stoppages, similar to the 
one at Los Alamos National Laboratory in 2004, and DOE agreed with this 
recommendation. While acknowledging these competing pressures, we 
believe that systematically collecting cost information on selected 
work stoppages can increase transparency and yet balance worker and 
public safety. 

Recommendations for Executive Action: 

To provide a more thorough and consistent understanding of the 
potential effect of work stoppages on project costs, we recommend that 
the Secretary of Energy take the following two actions: (1) establish 
criteria for when DOE should direct contractors to track and report to 
DOE the reasons for and costs associated with work stoppages, ensuring 
that these criteria fully recognize the importance of worker and 
nuclear safety, and (2) specify the types of costs to be tracked. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to the Secretary of Energy for 
review and comment. In written comments, the Chief Operations Officer 
for Environmental Management generally agreed with our recommendations, 
stating that they will be accepted for implementation within the 
Environmental Management program. The comments (which are reproduced in 
app. III) were silent on whether the recommendations will be 
implemented in other DOE programs. 

In its comments, DOE expressed concern that readers of appendix II 
could misconstrue the information in the column labeled "Duration" as 
representing a delay in the entire listed project, not simply the time 
required to resolve the specific issue in question; DOE maintains that 
during this time, workers were shifted to other work activities. We 
found, however, that some of the short work stoppages, which DOE termed 
"safety pauses," were specifically called to allow the contractor to 
refresh workers' understanding of workplace hazards; in these cases, 
which were essentially training exercises, workers were not reassigned 
to other work activities. Other work stoppages may have led to workers' 
assignment to other activities, but we were unable to verify to what 
extent reassignment occurred because the documentation available on 
work stoppages was limited. Finally, during the 2-year delay due to 
seismic concerns in waste treatment plant construction, work on two 
facilities--the pretreatment plant and high-level waste facility--was 
ultimately suspended from August 2005 until August 2007, and about 900 
workers were laid off, not reassigned. We added a footnote to table 1 
to clarify the "Duration" column. 

Regarding our discussion of the role of oversight in several work 
stoppages, DOE acknowledged that inadequate oversight was a factor in 
the cited work stoppages and stated that the Office of Environmental 
Management has implemented corrective actions to address these 
contributing factors. Evaluating these actions and the resulting 
outcomes, if any, however, was beyond the scope of our report. We 
incorporated other technical comments in our report as appropriate. 

As agreed with our offices, unless you publicly announce the contents 
of this report earlier, we plan no further distribution until 30 days 
from the report date. At that time, we will send copies to the 
Secretary of Energy and interested congressional committees. The report 
also will be available at no charge on the GAO Web site at [hyperlink, 
http://www.gao.gov]. 

If you or your staffs have any questions about this report, please 
contact me at (202) 512-3841 or aloisee@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. GAO staff who made major contributions to 
this report are listed in appendix IV. 

Signed by: 

Gene Aloise: 
Director, Natural Resources and Environment: 

[End of section] 

Appendix I: Scope and Methodology: 

To determine the number of times work was suspended at the Hanford 
site, we obtained from the Department of Energy's (DOE) Office of River 
Protection officials a listing of work stoppages occurring from January 
2000 through December 2008 at either the waste treatment plant or the 
tank farms. We did not review other work stoppages that may have 
occurred elsewhere at the Hanford Site during this period. 

We sought to independently verify the 31 work stoppages identified by 
DOE and to uncover additional information about them, including the 
nature of the event and the duration and the scope of each, by 
reviewing the following: 

* DOE's Occurrence Reporting and Processing System, a database of 
reportable accidents and other incidents affecting worker, public, and 
environmental safety; 

* DOE's database of investigation reports on accidents causing serious 
injury to workers or serious damage to the facility or the environment; 

* DOE citations issued against contractors for violating nuclear safety 
regulations;[Footnote 12] 

* Defense Nuclear Facilities Safety Board reports addressing Hanford 
Site safety problems; and: 

* Bechtel National Inc. and CH2M Hill Hanford Group Problem Evaluation 
Requests, internal reports of incidents or accidents involving safety 
issues. 

We were unable to independently verify DOE's list of work stoppages 
from these sources, however, because in most cases, the reporting 
systems did not indicate whether safety incidents had halted work or, 
if so, for how long. In addition, these reporting systems focus on 
safety incidents and do not specifically address construction rework 
and design problems, which represent about half the work stoppages 
reported by DOE. 

Of the 31 work stoppages reported, however, we were able to obtain 
additional information from other sources for three specific events. 
These were (1) ongoing problems protecting workers from potentially 
harmful vapors venting from the tank farms, (2) a radioactive waste 
spill from tank S-102 in July 2007, and (3) the seismic redesign from 
August 2005 to August 2007 of the waste treatment plant pretreatment 
and high-level waste facilities. To obtain a more thorough 
understanding of these three work stoppages, what caused them, and how 
problems were corrected, we reviewed DOE, contractor, and Office of the 
Inspector General evaluations of these events, including official 
accident reports, external independent investigations, and our 2006 
testimony on cost and schedule problems at the Hanford waste treatment 
plant.[Footnote 13] 

To determine the types of costs associated with work stoppages, we 
reviewed Federal Acquisition Regulation reporting requirements for cost-
reimbursement contracts and Defense Contract Audit Agency guidance on 
auditing incurred costs. To gain a better understanding of the costs 
associated with lost productivity resulting from a work stoppage, we 
reviewed cost-estimating guidance from the Association for the 
Advancement of Cost Engineering International and earned value 
management guidance by GAO and by the National Research Council. To 
develop an understanding of the costs paid by the government, compared 
with those absorbed by the contractor, we reviewed Bechtel National 
Inc. and CH2M Hill Hanford Group requests to DOE for equitable 
adjustments to their respective contracts to recover lost productivity 
and other costs linked to work stoppages. We reviewed the Atomic Energy 
Act of 1954, as amended, and the letters sent from DOE to contractors 
requesting that they segregate costs incurred in connection with 
investigations of potential violations of the law and DOE nuclear 
safety requirements. We reviewed assessments by Washington State, DOE, 
and federal regulators fining Bechtel and CH2M Hill Hanford Group for 
safety violations and other problems at the Hanford Site since 2000. 
Finally, we interviewed contractor and Office of River Protection 
finance officials to determine cost-accounting requirements and 
practices. 

To determine whether more-effective regulation or oversight might have 
prevented the work stoppages, we relied primarily on Office of River 
Protection and Bechtel officials' assessments of these events because 
supporting documentation was generally unavailable. For 3 of the 31 
work stoppages, we reviewed numerous internal DOE, external 
independent, and contractor evaluations to assess whether lack of 
oversight was a contributing factor. To gain further perspective on how 
lack of oversight or regulations might have played a role in these work 
stoppages, we interviewed DOE headquarters officials with the Offices 
of Environmental Management; Health, Safety, and Security; and General 
Counsel. We interviewed officials with regulatory and oversight 
entities, including the Defense Nuclear Facilities Safety Board, the 
Occupational Safety and Health Administration, and the Nuclear 
Regulatory Commission. We also interviewed union representatives at the 
Hanford Site to obtain the union's and workers' perspectives on work 
stoppages and safety. 

We conducted this performance audit from June 2008 to April 2009, in 
accordance with generally accepted government auditing standards. Those 
standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of section] 

Appendix II: Work Stoppages Identified by the Office of River 
Protection: 

We obtained and reviewed information on 31 work stoppages that occurred 
at the Hanford Site from January 2000 to December 2008; these are 
summarized in table 1. 

Table 1: Summary of Work Stoppages at the Hanford Site, January 2000 to 
December 2008 (in order of duration): 

1. 
Date of occurrence: Oct. 2007; 
Duration[A]: 1 hour; 
Reason for work stoppage: Sitewide safety pause; 
Type of event[B]: A; 
Location: Waste treatment plant. 

2. 
Date of occurrence: Oct. 2007; 
Duration[A]: ½ day; 
Reason for work stoppage: Safety pause; 
Type of event[B]: A; 
Location: Tank farms. 

3. 
Date of occurrence: Mar. 2007; 
Duration[A]: ½ day; 
Reason for work stoppage: Safety pause to address newly implemented 
improvements to safety statistics and management program; 
Type of event[B]: A; 
Location: Tank farms. 

4. 
Date of occurrence: Oct. 2004; 
Duration[A]: 6 hours; 
Reason for work stoppage: Injury to worker exiting heavy equipment at 
the integrated disposal facility; 
Type of event[B]: C; 
Location: Tank farms. 

5. 
Date of occurrence: Oct. 2006; 
Duration[A]: 1 day; 
Reason for work stoppage: Forklift collision with a vehicle; 
Type of event[B]: C; 
Location: Tank farms. 

6. 
Date of occurrence: Sept. 2005; 
Duration[A]: 1 ½ days; 
Reason for work stoppage: Sitewide pause to address hazardous energy 
use; 
Type of event[B]: A; 
Location: Waste treatment plant. 

7. 
Date of occurrence: June 2003; 
Duration[A]: 2 days; 
Reason for work stoppage: Personnel contaminated by radiation exposure 
during removal of a waste transfer line jumper assembly; 
Type of event[B]: C; 
Location: Tank farms. 

8. 
Date of occurrence: June 2008; 
Duration[A]: 2 days; 
Reason for work stoppage: Changed workers' protective equipment from 
self-contained tank air to respirators with contaminant-filtering 
cartridges; 
Type of event[B]: A; 
Location: Tank farms. 

9. 
Date of occurrence: June 2008; 
Duration[A]: 2 days; 
Reason for work stoppage: Radiation contamination spread to the back 
area of a facility that evaporates water contained in tank waste, to 
reduce the volume of that waste. As a result, the Office of River 
Protection issued a new order outlining additional work controls for 
the area; 
Type of event[B]: A; 
Location: Tank farms. 

10. 
Date of occurrence: July 2004; 
Duration[A]: 1 week; 
Reason for work stoppage: A nuclear chemical operator exceeded the 
maximum extremity and skin radiation exposure level during removal of 
an instrument used to measure temperature in the tanks; 
Type of event[B]: C; 
Location: Tank farms. 

11. 
Date of occurrence: June 2002; 
Duration[A]: 1 month; 
Reason for work stoppage: Damage to a crane due to operator error 
requiring repair; delayed use of site cranes; required alternate crane 
configuration, causing inefficiencies; 
Type of event[B]: C; 
Location: Waste treatment plant. 

12. 
Date of occurrence: Jan. 2007; 
Duration[A]: 1 month; 
Reason for work stoppage: Hazardous air sample identified during 
welding operations; 
Type of event[B]: A; 
Location: Waste treatment plant. 

13. 
Date of occurrence: Not available; 
Duration[A]: 1 ½ months; 
Reason for work stoppage: Repeated violations of a safety procedure, 
called a lock-out, tag-out, to ensure that dangerous machines are 
properly shut off and not started up again before completion of 
maintenance or servicing. Procedure requires that a tag be affixed to 
the locked device, indicating that it should not be turned on; 
Type of event[B]: A; 
Location: Tank farms. 

14. 
Date of occurrence: Oct. 2002; 
Duration[A]: 3 months; 
Reason for work stoppage: Reinspection and reinforcement of undersized 
structural steel welds at the low-activity waste facility; 
Type of event[B]: B; Location: 
Waste treatment plant. 

15. 
Date of occurrence: Feb. 2005; 
Duration[A]: 4 months; 
Reason for work stoppage: Welding manual rewritten to comply with 
requirements of the authorization basis for waste treatment plant; 
Type of event[B]: B; 
Location: Waste treatment plant. 

16. 
Date of occurrence: May 2005; 
Duration[A]: 6 months; 
Reason for work stoppage: Redesign of structural steel fabrication 
drawings; 
Type of event[B]: B; 
Location: Waste treatment plant. 

17. 
Date of occurrence: Oct. 2005; 
Duration[A]: 6 months; 
Reason for work stoppage: Laboratory testing showed that recently 
poured concrete was not meeting the necessary strength requirements of 
either 4,000 or 5,000 pounds of pressure per square inch. The 
contractor found that the concrete plant supplying the aggregate had 
changed the grind of its constituents during the winter months, 
weakening the concrete; 
Type of event[B]: B; 
Location: Waste treatment plant. 

18; 
Date of occurrence: Apr. 2005; 
Duration[A]: 6 months; 
Reason for work stoppage: Faulty fabrication of leak detection box; 
Type of event[B]: B; 
Location: Waste treatment plant. 

19. 
Date of occurrence: Oct. 2007; 
Duration[A]: 6 months; 
Reason for work stoppage: Contractor procured from suppliers piping 
that had not received the required 100 percent radiographic testing to 
identify hidden flaws in welds. These pipes were to be installed in 
heavily shielded concrete cells (called black cells) that would not be 
physically accessible following the completion of construction because 
of high radiation exposure; 
Type of event[B]: B; 
Location: Waste treatment plant. 

20. 
Date of occurrence: July 2002; 
Duration[A]: 7 months; 
Reason for work stoppage: "Cold joint" formed in concrete at the low-
activity waste facility because pouring was interrupted, creating a 
weak area that could allow water to enter; 
Type of event[B]: B; 
Location: Waste treatment plant. 

21. 
Date of occurrence: Sept. 2004; 
Duration[A]: 9 months; 
Reason for work stoppage: Process tanks intended for installation in 
black cells did not receive the required 100 percent radiographic 
testing to identify hidden flaws. Three tanks had already been 
installed and had to be examined and repaired in place at the 
pretreatment and high-level waste facilities as a result; 
Type of event[B]: B; 
Location: Waste treatment plant. 

22. 
Date of occurrence: Mar. 2007; 
Duration[A]: 10 months; 
Reason for work stoppage: Repairs to degraded air compressors and 
equipment; 
Type of event[B]: B; 
Location: Waste treatment plant. 

23. 
Date of occurrence: June 2005; 
Duration[A]: 1 year; Reason for work stoppage: Delay covering coaxial 
transfer pipe with soil because it did not meet sloping requirements 
and had to be reconfigured; 
Type of event[B]: B; 
Location: Waste treatment plant. 

24. 
Date of occurrence: July 2007; 
Duration[A]: 1 year; 
Reason for work stoppage: Suspension of work in S-102 and C-108 tanks 
to address radioactive waste spill; C-104 activities also suspended; 
Type of event[B]: C; 
Location: Tank farms. 

25. 
Date of occurrence: Jan. 2006; 
Duration[A]: 1 ½ years; 
Reason for work stoppage: Rework to reapply appropriate fire protection 
coating onto structural steel; 
Type of event[B]: B; 
Location: Waste treatment plant. 

26. 
Date of occurrence: Feb. 2006; 
Duration[A]: 2 years; 
Reason for work stoppage: Requirements were not met to ensure that 
commercially procured components for the facility were suitable for 
nuclear use. As a result, the contractor halted activities until fully 
developing and implementing a new procurement program to ensure those 
requirements could be met; 
Type of event[B]: B; 
Location: Waste treatment plant. 

27. 
Date of occurrence: Aug. 2005; 
Duration[A]: 2 years; 
Reason for work stoppage: Seismic ground-motion review including soil 
sampling, data analysis, and development of appropriate design criteria 
and implementation of changes; 
Type of event[B]: B; 
Location: Waste treatment plant. 

28. 
Date of occurrence: Oct. 2005; 
Duration[A]: 2 ¼ years; 
Reason for work stoppage: Revised requirements to ensure that design of 
joggle boxes had adequate shielding from radiation hazards. Joggle 
boxes are used to ensure that structural penetrations at 90-degree 
angles (such as walls or floors) are designed in such a way that 
radiation is blocked from leaving one room and entering another; 
Type of event[B]: B; 
Location: Waste treatment plant. 

29. 
Date of occurrence: July 2003; 
Duration[A]: Unknown; 
Reason for work stoppage: Rework to address construction equipment and 
temporary power installations that did not comply with electrical 
codes; 
Type of event[B]: B; 
Location: Waste treatment plant. 

30. 
Date of occurrence: Feb. 2008; 
Duration[A]: Unknown; 
Reason for work stoppage: Failed battery in a respirator halted work 
inside high-contamination area; 
Type of event[B]: A; 
Location: Tank farms. 

31. 
Date of occurrence: 2004; 
Duration[A]: Intermittent during 2-week period; 
Reason for work stoppage: Protection of workers exposed to potentially 
hazardous vapors escaping from underground tanks; 
Type of event[B]: C; 
Location: Tank farms. 

Source: GAO summary of DOE Office of River Protection information. 

[A] Time spans in this column represent the time needed to resolve the 
issue described. Workers may have been reassigned to other activities 
during these times, but we were unable to verify the extent to which 
reassignment occurred. 

[B] Letters in this column denote the following: 
A, pause in work activity to address unsafe situation or prevent 
recurrence of unsafe incident; 
B, delay of activity to perform rework or to address faulty 
workmanship, poor installation, or quality assurance issues, including 
compliance with nuclear safety management requirements identified in 10 
C.F.R. part 830; 
C, suspension of activity to address workplace accident, physical 
damage, or injury. 

[End of table] 

[End of section] 

Appendix III: Comments from the Department of Energy: 

Department of Energy: 
Washington, DC 20585: 

April 24, 2009: 

Mr. Gene Aloise: 
Director: 
Natural Resources and Environment: 
Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

The Environmental Management (EM) Program has reviewed the Government 
Accountability Office (GAO) draft report entitled Nuclear and Worker 
Safety. Limited Information Exists on Costs and Reasons for Work 
Stoppages at DOE's Hanford Site, GAO-09-451, which was provided to the 
Secretary of Energy on March 27, 2009. The recommendations included: 1) 
establish criteria for when Department of Energy (DOE) should direct 
contractors to track and report the reasons for and costs associated 
with work stoppages, and 2) specify the types of costs to be tracked. 
EM accepts these recommendations for implementation within the EM 
program. 

However, there is a significant likelihood for misrepresentation in 
Appendix II. The table lists the "Duration" it took to resolve the 
"Reason for the work stoppage" issue. As stated throughout the body of 
the report, when there was a work stoppage, whether due to a safety 
concern or a quality concern, the workers were shifted to other work 
activities until the issue was resolved. Thus, it is imperative to 
ensure that the reader of Table 1 understands that when an issue 
resulted in work stoppage, it did not affect the work on the entire 
project and workers affected by the work stoppage in the specific area 
were shifted to other work activities. Therefore, it is essential that 
the following clarification be made to Table 1, Appendix II: 1) revise 
the column which reads "Duration" to "Issue Resolution Duration", and 
2) add to the title - "The "Issue Resolution Duration" is the time to 
resolve the issue for the "Reason for the work stoppage" and during 
this period workers were assigned to other work activities". 

Page 17 of the report identifies inadequate oversight as factors in 
several work stoppages. EM acknowledges that inadequate oversight was a 
factor in the cited work stoppages; however EM has implemented 
corrective actions to address these contributing factors. Additionally, 
EM has established a number of processes that promote enhanced DOE 
engagement in oversight of design and engineering activities. These 
include use of technology readiness assessments, external technical 
reviews, and establishment of a Technical Authority Board. 

Further, on page 6, the 3rd paragraph indicates the work stoppages 
result from safety or construction concerns. Thus, in the 3rd sentence, 
"accident" should be replaced with "event or issue". 

Thank you for the opportunity to provide comments on the draft report. 
If you have any further questions, please contact Mr. Dae Chung, Deputy 
Assistant Secretary for Safety Management and Operations, at (202) 586-
5151. 

Sincerely, 

Signed by: 

James M. Owendoff: 
Chief Operations Officer for Environmental Management: 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Gene Aloise, (202) 512-3841, or aloisee@gao.gov. 

Staff Acknowledgments: 

In addition to the individual named above, Janet Frisch, Assistant 
Director; Carole Blackwell; Ellen W. Chu; Brenna McKay; Mehrzad Nadji; 
Timothy M. Persons, Chief Scientist; Jeanette Soares; Ginny 
Vanderlinde; and William T. Woods made key contributions to this 
report. 

[End of section] 

Footnotes: 

[1] Of the 177 underground storage tanks at Hanford, 149 have only a 
single carbon-steel shell. At more than 40 years old, 67, or almost 
half, of these single-shell tanks have leaked or are presumed to have 
leaked waste into the soil below. Newer double-shell tanks were built 
starting in the late 1960s. For more information on the underground 
tanks and stabilization activities, see GAO, Nuclear Waste: DOE Lacks 
Critical Information Needed to Assess Its Tank Management Strategy at 
Hanford, [hyperlink, http://www.gao.gov/products/GAO-08-793] 
(Washington, D.C.: June 30, 2008). 

[2] CH2M Hill managed and operated the tank farms from October 1, 1999, 
through September 30, 2008. As part of its overall strategy for cleanup 
at the Hanford site, DOE awarded a new contract for the management and 
operation of the tank farms. Since October 1, 2008, Washington River 
Protection Solutions LLC has managed and operated the tank farms. For 
the purposes of this report, we refer to CH2M Hill as the tank farms' 
contractor, since it was the contractor when all of the reported work 
stoppages occurred. 

[3] The waste treatment plant under construction consists of a 
pretreatment facility that separates waste into high-level waste 
(containing highly radioactive elements, such as strontium-90, cesium- 
137, technetium-99, and iodine-129) and low-activity waste. The plant 
will also include two other facilities to treat the separated portions 
of the waste, one analytical laboratory, and a variety of supporting 
facilities. In April 2006, we reported that since the construction 
contract was awarded in 2000, the project's estimated cost had 
increased more than 150 percent, to about $11 billion, and the 
completion date had been extended from 2011 to 2017 or later. See GAO, 
Hanford Waste Treatment Plant: Contractor and DOE Management Problems 
Have Led to Higher Costs, Construction Delays, and Safety Concerns, 
[hyperlink, http://www.gao.gov/products/GAO-06-602T] (Washington, D.C.: 
Apr. 6, 2006). 

[4] Under the contracts for the tank farms and the waste treatment 
plant, either DOE or the contractor can suspend work for various 
reasons, including responding to concerns about worker and nuclear 
safety. 

[5] A cost is only allowable when it meets the following requirements: 
reasonableness, allocability, generally accepted accounting principles 
or other appropriate practices, the terms of the contract, and Federal 
Acquisition Regulation, part 31.2. For the purposes of this report, we 
will refer to costs that meet all these requirements as "allowable 
costs." 

[6] DOE's Office of Enforcement is responsible for identifying 
violations of the nuclear safety rules and assessing civil penalties 
against contractors. This enforcement program, originally established 
in 1995, now also includes enforcement of rules that have been issued 
for security and safeguarding of classified information and for worker 
or industrial health and safety. 

[7] DOE officials said that while DOE does not formally collect or 
report information on work stoppages, officials are aware of these 
events, which are identified in daily and weekly reports submitted by 
DOE staff monitoring the worksite. 

[8] In a 2005 report on this stand-down of operations, we recommended 
that DOE require contractors to improve their ability to track such 
costs. See GAO, Stand-Down of Los Alamos National Laboratory: Total 
Costs Uncertain; Almost All Mission-Critical Programs Were Affected but 
Have Recovered, GAO-06-83 (Washington, D.C.: Nov. 18, 2005). 

[9] For further information on earned value management systems, see 
GAO, GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: Mar. 2, 
2009). 

[10] [hyperlink, http://www.gao.gov/products/GAO-08-793]. 

[11] [hyperlink, http://www.gao.gov/products/GAO-06-602T]. 

[12] DOE is authorized under 42 U.S.C. § 2282a to impose civil monetary 
penalties for violations of DOE nuclear safety regulations. 

[13] [hyperlink, http://www.gao.gov/products/GAO-06-602T]. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: