This is the accessible text file for GAO report number GAO-07-227R 
entitled 'Capitol Power Plant Utility Tunnels' which was released on 
November 16, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

November 16, 2006: 

The Honorable Wayne Allard:
Chairman:
The Honorable Richard Durbin:
Ranking Minority Member:
Subcommittee on the Legislative Branch: Committee on Appropriations:
United States Senate: 

The Honorable Jerry Lewis
Chairman:
The Honorable David Obey:
Ranking Minority Member:
Committee on Appropriations:
House of Representatives: 

Subject: Capitol Power Plant Utility Tunnels: 

The Architect of the Capitol (AOC), through the Capitol Power Plant 
(CPP), operates five walkable utility tunnels[Footnote 1] containing 
steam and chilled water pipes associated with serving the heating and 
cooling requirements of the U.S. Capitol and 23 surrounding facilities. 
The tunnels also carry other utilities, such as fiber optic and 
telephone lines. The Office of Compliance (OOC), which is responsible 
for advancing safety, health, and workplace rights in the legislative 
branch, and the tunnel workers have raised concerns about health and 
safety issues in the tunnels. Specifically, in March 2006, the utility 
tunnel workers sent a letter to Congress complaining of unsafe working 
conditions in the tunnels, including falling concrete, asbestos, and 
extreme heat.[Footnote 2] In February 2006, OOC filed a complaint 
against AOC concerning hazards in the tunnels, including falling 
concrete, an inadequate communication system for these confined spaces, 
and inadequate escape exits. According to OOC officials, these 
conditions had been previously brought to the attention of AOC by OOC 
inspectors as early as 1999. Following a reinspection in mid-2005, OOC 
determined that AOC had not made sufficient progress in addressing them 
and that conditions in the tunnels had deteriorated further. In 
addition, in January 2006, OOC issued citations for and asked AOC to 
address a potential asbestos hazard and heat stress conditions. In 
light of these concerns, you asked us to review the condition of the 
tunnels. Accordingly, we examined (1) the current condition of the 
tunnels, (2) AOC's plan for making repairs and improvements to the 
tunnels, and (3) the responsiveness of AOC's plan to the issues raised 
by OOC and the tunnel workers. 

To report on the condition of the tunnels, we reviewed various reports 
on the condition of the tunnels from 2000 to the present, viewed 
videotapes of the tunnels, hired a mechanical engineer to tour the 
tunnels, and interviewed tunnel workers and other AOC staff. To assess 
AOC's plans for making repairs and improvements, we reviewed the August 
31, 2006, Utility Tunnel Improvement Plan that AOC submitted to 
Congress and various projects that AOC initiated to implement this 
plan; interviewed AOC officials; and attended weekly AOC meetings at 
CPP on the repair efforts in the tunnels. Generally, it is our policy 
not to address issues in litigation. Thus, given the ongoing complaint 
and negotiations between OOC and AOC regarding the concerns identified 
in the tunnels, we did not address whether issues identified in the 
complaint or the actions taken by AOC complied with legal standards. To 
understand the concerns that had been raised and the status of the 
concerns, we interviewed the tunnel workers and officials from both AOC 
and OOC. We also compared the plan with the concerns that had been 
raised. Furthermore, in accordance with our policy, we did not address 
concerns the tunnel workers have raised in its recent whistleblower 
complaint. 

This report is based on information gathered through October 2006, and 
AOC is continuing to work on solving the problems in the utility 
tunnels. We did not conduct an audit: We performed our work to assist 
Congress in considering the future needs of the Capitol Power Plant 
Utility Tunnel System. We requested comments on the draft of this 
letter from AOC and OOC. 

Results in Brief: 

AOC has started to address problems in the tunnels, but their condition 
remains substantially unchanged--that is, the conditions OOC cited as 
hazardous remain. For example, AOC has installed supports in some areas 
of one tunnel to minimize the potential for falling concrete and has 
required individuals entering the tunnels to wear protective equipment 
and clothing to shield them from potential asbestos exposure. In 
addition, AOC is working toward removing the delaminated concrete and 
cleaning the tunnels, so that the exhaust fans can be turned on to 
reduce the temperature in the tunnels.[Footnote 3] An AOC contractor 
has completed assessments of three of the tunnels and determined that 
they are not in danger of collapse. The contractor is still assessing 
the two remaining tunnels and expects to complete these assessments by 
December 31, 2006. Most other AOC efforts are in the study, planning, 
or procurement stage. As a result, the potential for falling concrete, 
asbestos exposure, excessive heat, poor communications, and inadequate 
escape procedures continue to pose problems.[Footnote 4] Progress in 
resolving the problems in the tunnels has been hindered because the 
tunnel conditions that AOC and its contractors are trying to address 
make it difficult to work in the tunnels. 

AOC issued its Utility Tunnel Improvement Plan on August 31, 2006, as 
directed by the House Committee on Appropriations, but the plan is 
incomplete, in part because AOC has not completed its assessment of the 
tunnels. In a June 1, 2006, House report,[Footnote 5] the House 
Committee on Appropriations directed AOC to provide to the committee "a 
plan and budget that strategically addresses long term repairs to the 
steam tunnels." Combining the information it currently has on the 
condition of the tunnels, AOC categorized the tunnel projects into 
immediate and short-term repairs that it estimates will cost about $119 
million over the next 6 years. AOC identified another $14.4 million in 
longer-range initiatives to mitigate the known problems in the tunnels. 
Such initiatives include conducting quarterly structural inspections 
and making necessary annual repairs. The plan does not contain an 
analysis or discussion of options for addressing the immediate and 
short-term needs of the tunnels, as called for in the House report. AOC 
does indicate in the plan that it will conduct an alternatives study to 
evaluate the long-term use of the existing tunnels and options for 
meeting the Capitol Hill Complex's future utility distribution needs. 
AOC recognizes that the current plan does not fully respond to the 
questions raised in the committee's report. According to AOC officials, 
AOC could not complete the work necessary to respond to all of the 
requested information in the time allotted. But without information on 
options and recommendations for addressing tunnel problems and future 
utility distribution needs, Congress does not get a full picture of the 
potential solutions to the tunnel problems and their costs. 

AOC and OOC are working cooperatively to resolve the health and safety 
concerns in the utility tunnels, but the slow progress of the work has 
left the tunnel workers frustrated. To settle OOC's January 2006 
citations and February 2006 complaint, AOC and OOC are exchanging 
proposals and discussing ongoing technical issues. OOC has been 
reviewing AOC's utility improvement plan. While AOC's plan covers the 
issues raised by the OOC and the tunnel workers, limited work has been 
completed to date and the workers have no clear picture of when the 
work will be done. To improve communication, AOC began holding weekly 
meetings with the tunnel shop workers in April 2006 to discuss tunnel 
issues and the actions being taken. 

Background: 

CPP, which is managed by AOC, is located in Washington, D.C., at New 
Jersey and E Streets, Southeast. It is the central heating and cooling 
plant that provides steam, chilled water, or both, year-round for about 
16 million square feet of space in 24 facilities.[Footnote 6] Steam is 
used for comfort heating, heating domestic hot water, cooking, and 
humidification. Chilled water is used for comfort and equipment 
cooling. 

CPP consists of four main facilities: the steam plant, the East 
Refrigeration Plant, the West Refrigeration Plant, and administration 
buildings. The plant also includes a coal yard south of the power 
plant. CPP's distribution infrastructure consists of approximately 2-1/ 
2 miles of walkable utility tunnels containing steam pipes, chilled 
water pipes, and other utility services, such as fiber optic and 
telephone lines for CPP customers. Access to the utility tunnels is 
provided through various manholes and tunnel entrances in buildings. In 
addition, some steam and chilled water pipes are buried in more than a 
half mile of covered trenches. Access to the buried utilities is 
through manholes. The walkable tunnels were built at various times--one 
in 1908, two in the 1930s, and two in the 1950s. 

In 2000, an AOC contractor reported that its study of the walkable 
utility tunnels indicated deterioration of the tunnel structure due to, 
among other things, aging and failure of the waterproofing system. 
According to the contractor, the deterioration was rapidly advancing in 
some sections and required immediate attention, and the tunnels posed a 
danger to worker safety, especially from delaminating concrete in the 
tunnel roofs that could fall without warning. On December 7, 2000, 
OOC's General Counsel issued a citation for unabated hazards in the 
tunnels--falling concrete, an inadequate communication system, and 
inadequate escape exits from these confined spaces. In 2005, OOC 
inspected the tunnels and determined that AOC had not made sufficient 
progress in addressing the previously identified hazards; OOC also 
identified additional concerns. As a result, in January 2006, OOC's 
General Counsel issued two more citations--one for an asbestos hazard 
and one for a heat stress hazard--and asked AOC to address them. In 
addition, on February 28, 2006, OOC's General Counsel issued a 
complaint stating that AOC had not taken sufficient action to address 
the problems identified in the December 2000 citation. 

Since OOC's initial citation in December 2000, AOC has reported taking 
some actions to address some of the problems in the tunnels, including 
the following: 

* In 2001, AOC contracted with the Federal Occupational Health (FOH) to 
assess the condition of asbestos in the entire CPP, including the 
tunnels.[Footnote 7] FOH found that the asbestos in the tunnels was 
generally in good condition--that is it was not damaged or 
exposed.[Footnote 8] 

* In 2004, AOC replaced 600 feet of the roof in one tunnel in response 
to the 2000 contractor's report on tunnel conditions. 

* In 2004, AOC began another project to upgrade 15 tunnel entry and 
exit points. 

* In 2005, AOC removed asbestos from one of the tunnels.[Footnote 9] 

In addition, since 1999, AOC's Construction Management Division has 
been working to identify and remove developing spalls[Footnote 10] and 
has recently increased its efforts to identify and remove any spalling 
concrete. 

Condition of the Utility Tunnels Remains Substantially Unchanged: 

AOC has taken some steps to mitigate problems in the tunnels and has 
initiated some actions to resolve them, but little change has taken 
place thus far. To mitigate problems, AOC has installed supports to 
parts of the ceiling of one tunnel to minimize the potential of falling 
concrete; required individuals entering the tunnels to wear protective 
equipment and clothing; contracted with FOH for air sampling and 
asbestos condition assessments; purchased a portable air-conditioning 
system; begun upgrades to the tunnels' communication system; and 
improved several tunnel emergency escape exits. In addition, an AOC 
contractor has completed structural assessments of three of the five 
tunnels and determined that they are not in danger of collapse. AOC has 
received a draft assessment report on the fourth tunnel, and the 
assessment of the fifth tunnel is still in progress. AOC is scheduled 
to receive the final reports for these two tunnels by December 31, 
2006. Most of the actions AOC has initiated to resolve the tunnel 
problems are still in the study, planning, or procurement stage. (For 
specific information about the tunnel projects, see enc. I.) 

While AOC has taken a number of actions to begin addressing the 
problems identified in the tunnels, few of the problems have been 
resolved thus far and the condition of the tunnels remains 
substantially unchanged. Problems persist, including the potential for 
falling concrete, loose asbestos, and high heat; communication systems 
that do not provide consistent coverage throughout the tunnels; a lack 
of adequate emergency egress; inadequate lighting; and a lack of 
emergency lighting. Progress in addressing the tunnel problems has been 
hindered because the conditions that AOC and its contractors are trying 
to address make it difficult for them to work, according to AOC 
officials. 

In a preliminary report in July 2006, FOH identified asbestos in the 
material used to insulate pipe and pipe fittings in three of the four 
walkable tunnels.[Footnote 11] According to FOH, in two of the tunnels 
inspected, the condition of the insulation on both steam pipes and 
condensate lines was good overall. FOH has not completed its inspection 
of the third tunnel because the tunnel had been closed.[Footnote 12] 
FOH does not believe that dust in the tunnels contains asbestos except 
where the asbestos insulation has been damaged. According to OOC 
officials, OOC does not concur with this assessment because it found 
asbestos in dust samples taken off pipe coverings in areas where damage 
to the insulation material was not apparent. FOH recommends the 
complete abatement of all asbestos in the tunnels. However, if complete 
abatement is not practicable, then FOH recommends that damaged 
insulation be removed or repaired. Specifically, according to FOH, 
insulation on either side of the stanchions that hold utility pipes has 
been damaged by pipe movement and should be removed; other damaged 
insulation should be repaired; and periodic inspections should be done. 
FOH has provided limited data analysis indicating that for some 
activities in the tunnels, protective equipment may not be necessary. 
However, AOC has stated that it will continue to require protective 
equipment until further analysis is completed. 

AOC's Utility Tunnel Improvement Plan Provides Some Required 
Information, but Does Not Address Options for Improvement: 

AOC issued its Utility Tunnel Improvement Plan on August 31, 2006, as 
directed by the House Committee on Appropriations, but the plan 
includes only some of the required information and discusses future 
efforts to provide all of the requested information. House Report 109- 
485, dated June 1, 2006, directed the Architect of the Capitol to 
"provide a plan and budget to the committee that strategically address 
long term repairs to the steam tunnels over the next 5 years." 
According to the report, the plan should include, at a minimum, "an 
assessment of the tunnel problems that need to be corrected, the 
priorities from safety and operational standpoints, options for 
addressing the problems along with the costs and benefits and 
advantages and disadvantages of each option, the recommended options 
and schedule for implementation, and the identification of officials 
who will be accountable." 

As noted, because AOC's contractor has not finished assessing two of 
the five tunnels, AOC's plan does not fully identify the tunnel 
problems. The contractor expects to complete its assessment of the two 
tunnels in December 2006. Combining the information it currently has on 
the condition of the tunnels, AOC prioritized the tunnel projects into 
immediate, short-term, and longer-range initiatives and established 
accountability for these projects. AOC plans to initiate its immediate 
improvements--designed to mitigate health, life safety, structural, and 
heat stress concerns--by September 2007. AOC plans to initiate its 
short-term improvements--designed to correct mechanical, electrical, 
and structural defects--in fiscal years 2008 through 2012. AOC 
estimates the cost for the improvements in the plan to be $119 million 
over the next 6 years. AOC also reported $14.4 million in longer-range 
initiatives intended to mitigate the known problems in the tunnels 
through 2015. AOC's longer-range initiatives include conducting 
quarterly structural inspections, making necessary annual repairs, and 
modifying procedures to reflect changing tunnel conditions. According 
to AOC, its plans were based on information known at the time the 
report was being developed and are preliminary. As the condition 
assessments and alternatives study are completed, AOC expects to adjust 
its work plans, cost estimates, and schedules as appropriate. 

Without information on the condition of the two tunnels that remain to 
be assessed, AOC's plan lacks a full picture of tunnel conditions, the 
work that needs to be done, and the cost and time it will take to 
complete the necessary work. In addition, the plan does not include a 
discussion of options for addressing the immediate and short-term needs 
of the tunnels. From the plan, it is not clear whether AOC considered 
various options for addressing the tunnel problems or explored the 
cost, benefits, advantages, and disadvantages of different options 
before determining what work to include in the plan. AOC does indicate 
in the plan that it will conduct an alternatives study to evaluate the 
long-term use of the existing tunnels and options for meeting the 
Capitol Hill Complex's future utility distribution needs. AOC officials 
said they wanted to addressed the total utility distribution system's 
needs in their alternative studies to ensure that Congress has a 
complete understanding of the system's requirements and associated 
costs. While the immediate improvements might need to be done before an 
alternatives study can be completed, AOC has reported needing more than 
$100 million to address problems in the tunnels before it identifies 
and considers the different options for resolving the 
problems.[Footnote 13] Thus, Congress does not have assurance that the 
proposed improvements and costs provide the best solutions for solving 
the problems in the tunnels. In addition, the plan focuses only on 
needs in the walkable tunnels and, as AOC points out, does not address 
the buried steam lines or utility vaults, where, according to AOC 
officials, other problems are known to exist. 

AOC recognizes that the current plan does not fully respond to the 
questions raised in the committee's report. According to AOC officials, 
they are continuing to develop the requested information and will 
provide it to the committee when available. They stated that the plan 
does not include all of the requested information because they could 
not complete the work in the time allotted. AOC officials said they 
wanted to be sure they addressed the total utility distribution 
system's needs in their alternatives study to ensure that Congress has 
a complete understanding of the systems requirements and associated 
costs. 

Efforts to Address OOC and Workers' Concerns Are Moving Forward, but 
Progress on Worker Safety Issues Has Been Limited: 

AOC and OOC are moving toward resolving OOC's February 28, 2006, 
complaint on the deteriorating condition of the tunnels, the tunnel 
communication system, and emergency exits and the two January 2006 
citations for asbestos and heat stress problems. Both AOC and OOC are 
discussing proposals to satisfy the applicable legal requirements and 
enable AOC to resolve the issues in the complaint and the two 
citations. However, according to OOC officials, some essential 
provisions that are critical to reaching any settlement, including what 
hazards will be covered under the agreement, have not to date been 
accepted by AOC. Furthermore, OOC officials said they have not been 
fully successful in obtaining necessary tunnel-related information from 
AOC on a timely basis. Part of this effort is to understand the extent 
to which OOC's Office of General Counsel will be involved in 
implementing activities to resolve the issues. AOC regularly keeps the 
General Counsel's office up to date on the status of tunnel operations 
and planned repair activities. OOC also says that it has been working 
amicably with AOC to resolve the complaint and citations. AOC and OOC 
are also continuing to meet to discuss and resolve new health and 
safety issues in the tunnels as they arise. 

The tunnel workers have expressed concern about the safety of the 
tunnels due to the presence of asbestos, falling concrete, excessive 
heat, inadequate emergency exits, and a poor communication system. 
AOC's Utility Tunnel Improvement Plan covers these issues for the 
walkable tunnels, but, as noted, progress in resolving these issues has 
been limited. The tunnel workers told us they are discouraged and have 
no clear idea of when the problems will be solved. To improve 
communication, AOC began holding weekly meetings with the tunnel shop 
workers in April 2006 to discuss tunnel issues and the actions being 
taken. However, the tunnel workers have expressed frustration about the 
lack of progress in addressing their safety and health concerns. 

AOC officials noted it has taken several actions to address the safety 
concerns cited by OOC and the tunnel workers. These actions include the 
establishment of safety and access control procedures for the tunnels, 
the requirement that protective equipment and clothing be worn, the 
upgrade of 15 tunnel entry and exit points, the shoring of delaminated 
concrete, and improvements to the reliability of the communication 
system in the tunnels. OOC officials noted that additional concerns in 
the tunnels, such as mold in one of the steam stations, continue to be 
identified. 

Agency Comments: 

We provided a draft of this report to the Architect of the Capitol and 
the General Counsel of the Office of Compliance for their review and 
comment. The Architect of the Capitol provided us with written comments 
that are reproduced in enclosure II. AOC generally agreed with the 
information as presented in the report and provided technical comments 
that were incorporated, as appropriate. We received oral comments from 
the General Counsel at the Office of Compliance. He generally agreed 
with the information as presented in the report and provided technical 
comments that were incorporated, as appropriate. 

We are sending copies of this report to the Architect of the Capitol, 
the General Counsel of the Office of Compliance, and others interested 
parties. We will also make copies available to others on request. In 
addition, the report will be available at no charge on GAO's Web site 
at [Hyperlink, http://www.gao.gov]. 

If you or your staff have any questions about this report, please 
contact me at (202) 512-6923 or dornt@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. GAO staff who made major contributions to 
this report are Maria Edelstein and Tom Keightley. 

Signed by: 

Terrell G. Dorn: 
Director, Physical Infrastructure Issues: 

Enclosures: 

Enclosure I: Tunnel Projects: 

Company; Entech Engineering, Inc; 
Award date: 9/29/2005; 
Work to be performed: Prepare scoping and inspection plan for the 
utility tunnel system. 

Company; Lord & Co., Inc; 
Award date: 11/2/2005; 
Work to be performed: Maintain radio. 

Company; GRA, Inc; 
Award date: 1/9/2006; 
Work to be performed: Provide management consulting services. 

Company; The Safety Company, Inc; 
Award date: 1/13/2006; 
Work to be performed: Develop heat stress programs and policies. 

Company; The Safety Company, Inc; 
Award date: 3/3/2006; 
Work to be performed: Provide tunnel evaluation for one tunnel. 

Company; WACO, Inc; 
Award date: 4/14/2006; 
Work to be performed: Perform minor insulation and minor abatement 
throughout; one tunnel. 

Company; B&W Fabricating; 
Award date: 4/20/2006; 
Work to be performed: Capitol Power Plant (CPP) emergency egress. 

Company; Lord & Co., Inc; 
Award date: 5/4/2006; 
Work to be performed: Provide radios for tunnels. 

Company; US Public Health / FOH; 
Award date: 5/5/2006; 
Work to be performed: Provide exposure and hazard assessment, air 
sampling, asbestos; condition inspection, and lead paint inspection. 

Company; James Posey Assoc; 
Award date: 5/12/2006; 
Work to be performed: Provide engineering services for tunnel design 
documents for one tunnel. 

Company; Jacobs Engineering; 
Award date: 6/12/2006; 
Work to be performed: Provide construction manager services for CPP 
tunnel program. 

Company; Entech Engineering, Inc; 
Award date: 7/21/2006; 
Work to be performed: Perform facility conditions assessment of the 
utility tunnels. 

Company; Topp Portable Air; 
Award date: 7/21/2006; 
Work to be performed: Rental of portable air units. 

Company; URS Greiner Woodard Clyde; 
Award date: 7/25/2006; 
Work to be performed: Provide structural, environmental, safety, and 
health consulting services. 

Company; Ameri-can Engineering; 
Award date: 7/25/2006; 
Work to be performed: Purchase decontamination trailer. 

Company; US Public Health / FOH; 
Award date: 7/28/2006; 
Work to be performed: Tunnel entry procedures. 

Company; IDS Blast Finishing; 
Award date: 8/1/2006; 
Work to be performed: Rental of Decontamination trailer. 

Company; CESI; 
Award date: 8/2/2006; 
Work to be performed: Provide miscellaneous general housekeeping. 

Company; The Safety Company, Inc; 
Award date: 8/15/2006; 
Work to be performed: Develop emergency evacuation plan for CPP utility 
distribution system. 

Company; A. Morton Thomas & Assoc; 
Award date: 8/16/2006; 
Work to be performed: Provide surveying services for one tunnel, lot 
12. 

Company; Centennial Contractors; 
Award date: 9/8/2006; 
Work to be performed: Excavation and asbestos abatement for the egress 
point, lot 12. 

Company; Topp Portable Air; 
Award date: 9/30/2006; 
Work to be performed: Purchase portable air units. 

Company; Construction Management Division, AOC; 
Award date: 11/2006[A]; 
Work to be performed: Begin removing delamination in one tunnel. 

Company; To be determined; 
Award date: 11/2006[ A]; 
Work to be performed: Clean debris and dust from one tunnel. 

Company; To be determined; 
Award date: 12/2006[ A]; 
Work to be performed: Clean mold and abate asbestos from one tunnel. 

Company; To be determined; 
Award date: 12/2006[ A]; 
Work to be performed: Study alternative communication system. 

Company; To be determined; 
Award date: 12/2006[ A]; 
Work to be performed: Design and initial construction of two new egress 
points for one tunnel. 

Source: AOC. 

[A] These contracts have not yet been awarded. The date provided is 
when AOC expects to award the contract. 

[End of table] 

[End of Section] 

Enclosure II: Comments from the Architect of the Capitol: 

The Architecht of the Capitol: 
Washington, DC 20515: 

November 16, 2006: 

Mr. Terrell G. Dorn: 
Director, Physical Infrastructure Issues: 
Government Accountability Office: 

Dear Mr. Dorn: 

We appreciate receiving the Government Accountability Office's draft 
correspondence on the Capitol Power Plant Utility Tunnels and the 
opportunity to provide comment. The Architect of the Capitol (AOC) 
agrees that implementation of the planning and execution of work as 
outlined in the AOC Tunnel Improvement Plan issued August 31; 2006, has 
not proceeded as originally anticipated. In executing this important 
work, AOC considers safety an integral part of every project, and 
continues to place priority on protecting employees prior to commencing 
work. Safety requirements put in place to mitigate heat stress and 
overhead hazards to tunnel employees and other workers have affected 
our efficiency, productivity and access. 

Our estimate for immediate and short-term repairs totaling 
approximately $119 million is driven by our goal to correct the Office 
of Compliance's Complaint and Citations within 5 years, in accordance 
with the time line being discussed with this office. The estimate also 
includes work necessary to keep the tunnels in continuous operation 
throughout the repair and improvement period. The Alternatives Study 
will provide recommendations for the Agency's future, long tern utility 
distribution system. The corrections for structural, egress, 
temperature, asbestos, and communications issues cited by the Office of 
Compliance are complex and interrelated. They require thorough 
planning, study, and design,, resulting in prolonged construction 
activity. However, AOC has taken substantial planning efforts to 
mitigate hazards to the tunnel employees in the short-term. 

In summary, AOC recognizes that there are many challenges facing us in 
completing the physical tunnel upgrades. We are committed to our plan 
for immediate and short-term repairs and those-actions for improving 
worker safety. When` the Alternatives Study is completed, we will 
furnish the Government Accountability Office, Office of Compliance, 
Congress and our employees with a comprehensive plan to move forward 
with an improved utility distribution system. 

We appreciate the opportunity to comment on the Government 
Accountability Office's draft . report. We also have provided separate 
technical comments and clarifications. If you have further questions, 
please contact Anna Franz, Director of the Office of Planning and 
Project Management at 202-225-5900. 

Sincerely, 

Sincerely, 

Alan M. Hantman, FAIA: 
Architect of the Capitol: 

Doc. # 061109-1301: 

[End of Section] 

(543175): 

FOOTNOTES 

[1] The tunnels are not identified by name in this report for security 
reasons. 

[2] On October 18, 2006, the utility tunnel workers filed a 
whistleblower complaint against AOC alleging that they were retaliated 
against after they informed Members of Congress about the conditions in 
the tunnels. 

[3] Delaminating concrete is concrete that is separated from the steel 
reinforcing and is in danger of falling from the wall or ceiling. 

[4] The hot working conditions in the tunnels throughout the year are a 
result of the heat given off by the steam pipes in an enclosed area. 
The heat is not related to seasonal changes in temperature. 

[5] H.R. Rep. No. 109-485, at 21-22 (2006). 

[6] CPP provides chilled water to 19 of the 24 facilities and steam to 
24 facilities. Five of the buildings are not part of the Capitol Hill 
Complex; however, they are served by CPP and are billed for services 
provided. 

[7] FOH is a component of the United States Public Health Service 
within the Department of Health and Human Services. 

[8] According to OOC officials, FOH's finding is inconsistent with 
OOC's observations in the tunnels. 

[9] According to an AOC official, AOC has determined that there is 
still some asbestos in the far end of this tunnel. 

[10] A spall indicates an area of concrete delamination that may expose 
the existing reinforcing steel in the tunnel structure. 

[11] According to the FOH study, in the fourth tunnel, asbestos was 
found in the insulation at one entrance area to the tunnel. FOH did not 
inspect the fifth tunnel because the asbestos was in the process of 
being abated. 

[12] AOC closed access to one of the tunnels until supports could be 
installed to reduce the chance of concrete falling. 

[13] Since the plan was issued, an AOC contractor has estimated that it 
will cost between $61.5 million and $102.2 million to repair the 
structure of four of the five tunnels. These costs were not available 
when the Utility Tunnel Improvement Plan was issued. 


GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: