This is the accessible text file for GAO report number GAO-04-643R 
entitled 'Uncertainties Remain Concerning the Airborne Laser's Cost and 
Military Utility' which was released on May 19, 2004.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

May 17, 2004:

The Honorable Bill Nelson:

Ranking Minority Member:

Subcommittee on Strategic Forces:

Committee on Armed Services:

United States Senate:

The Honorable Daniel K. Akaka:

United States Senate:

Subject: Uncertainties Remain Concerning the Airborne Laser's Cost and 
Military Utility:

In 1996, the Air Force launched an acquisition program to develop and 
produce a revolutionary laser weapon system, the Airborne Laser (ABL), 
capable of defeating an enemy ballistic missile during the boost phase 
of its flight. Over the last 8 years, the program's efforts to develop 
this technology have resulted in significant cost growth and schedule 
delays. These events led you to request that we answer the following 
questions: (1) How much and why has the ABL's cost increased since the 
program's inception? (2) What is the expected military utility of the 
initial ABL aircraft? (3) What support systems will be required when 
the ABL is fielded and what is the likely cost of those systems? (4) 
Have recent program changes resulted in a more cost effective strategy 
for developing the weapon?

After we began our review, the Missile Defense Agency (MDA) refocused 
the ABL program to pursue a more knowledge-based approach, where 
program knowledge is demonstrated at critical points in the development 
cycle.[Footnote 1] We examined the planned changes to determine whether 
they will result in a more cost-effective strategy for developing the 
ABL element. This report summarizes that information and transmits the 
briefing charts that have been revised to address program changes made 
by MDA after our presentation to your staff on March 4, 2004.

In conducting our review, we analyzed Department of Defense (DOD), MDA, 
Air Force, and ABL program documents and interviewed key program 
officials. To determine how much ABL's cost increased since the program 
was initiated and why this growth occurred, we reviewed both the ABL 
prime contract awarded in 1996 and significant modifications made to 
the contract through July 2003. We also assessed the contractor's cost 
and schedule performance by analyzing contractor cost performance 
reports using Earned Value Management principles. To determine the 
expected military utility of the initial ABL aircraft, we interviewed 
key DOD, MDA, and intelligence officials and analyzed relevant 
documents, including studies and reports. To determine the necessary 
support systems and their costs, we examined relevant documents and 
held discussions with the Air Force Air Combat Command. We also 
reviewed the Air Force Total Ownership Cost database to identify 
support systems and costs for other high value air assets. To determine 
whether recent program changes resulted in a more cost-effective 
strategy for developing the ABL, we compared the program office's 
previous plans, goals and activities with its recent efforts to refocus 
the program. We conducted our work from October 2003 through May 2004 
in accordance with generally accepted government auditing standards.

Results in Brief:

The prime contractor's costs for developing ABL have nearly doubled 
from the Air Force's original estimate and additional cost growth is 
occurring. The cost growth occurred primarily because the program did 
not adequately plan for and could not fully anticipate the complexities 
involved in developing the system. MDA continues to face significant 
challenges in developing the ABL's revolutionary technologies and in 
achieving cost and schedule stability. From 1996 through 2003, the 
value of the prime contract, which accounts for the bulk of the 
program's cost, increased from about $1 billion to $2 billion. 
According to our analysis, costs could increase between $431 million to 
$943 million more through first full demonstration of the ABL system. 
Cost growth has been spurred by rework that was necessary because rapid 
prototyping forced the program to integrate components before all 
subcomponents were fully tested. In addition, fabricating ABL's unique 
components and developing its complex software proved more costly and 
time-consuming than anticipated. Although ABL's prime contractor has 
added additional personnel to the contract, the program is faced with a 
bow wave of uncompleted work from prior years. Recognizing that the 
technology development activities directed by the contract could not be 
completed within the contract's cost ceiling, the ABL program office 
began development of a new cost estimate for completing these 
activities.

Predictions of the military utility of the initial ABL aircraft are 
still highly uncertain because these forecasts are not based on any 
demonstrated capability of the system, but rather on modeling, 
simulations, and analysis. These assessment tools predict that the 
initial Airborne Laser will be militarily useful against most theater 
and intercontinental ballistic missiles; but flight-test data are not 
yet available to anchor these tools. According to test officials, the 
models and simulations are adequate for establishing system parameters, 
but may not be sufficient for estimating the effectiveness of a fielded 
system. Additionally, other factors will influence ABL's military 
utility, including the availability of support infrastructure and the 
number of aircraft available.

When it is fielded, ABL is expected to require unique support for its 
laser and beam control and fire control components in addition to the 
support burdens attached to all high-value air assets.[Footnote 2] For 
example, to carry out a wider range of missions, ABL will need laser 
fuel production facilities close to the theater of operations. ABL will 
also require unique maintenance, such as re-calibration and re-coating 
of beam control and fire control subcomponents. In addition, it will 
require the typical support systems needed by other high-value air 
assets, such as escort aircraft for protection. MDA has not yet 
determined the cost of ABL's unique support systems, but operating 
costs[Footnote 3] for other high-value air assets range from about 
$24,000 per hour to $92,000 per hour.

MDA refocused the ABL program in February 2004 to pursue a more cost-
effective development strategy. The program now plans to follow a 
knowledge-based rather than a schedule-driven approach to the element's 
development. For example, the program is no longer working to deliver a 
contingency sensor capability in Block 2004. Instead it will 
concentrate on maturing and demonstrating ABL's critical technologies. 
In addition, the program has delayed indefinitely the purchase of a 
second aircraft and a test facility.

To provide better information to decision makers as they consider 
whether to continue investing in the ABL program, we are recommending 
that DOD provide an analysis that quantifies the confidence that 
decision makers should have in the new cost estimate. DOD concurred.

Background:

From 1996 to 2001, the ABL program was an Air Force major defense 
acquisition program. However, in October 2001, the Department of 
Defense (DOD) transferred responsibility for the program to the 
Ballistic Missile Defense Organization (now MDA) where the ABL became 
one element of the Ballistic Missile Defense System (BMDS). The ABL's 
mission is to destroy enemy ballistic missiles in the boost phase as 
part of the layered defense strategy. Similar to other BMDS elements, 
the ABL is being developed incrementally in a series of 2-year blocks. 
During the first block, known as Block 2004, MDA's goal is to mature 
the ABL's critical technologies.

The ABL includes four major components: a modified 747 aircraft, which 
serves as the platform for other components; a high-energy chemical 
laser; a beam control and fire control system; and a battle management 
and command and control system. The high-energy laser is a chemical 
oxygen-iodine laser that generates energy through chemical reactions. 
The prototype, or demonstrator aircraft, that is under development will 
include six laser modules that will be linked together to produce a 
laser beam with megawatts of power. The beam control and fire control 
component is designed to track and stabilize the beam so that its 
energy remains focused on a small area of an enemy missile. ABL uses 
its high-energy laser to defeat enemy missiles by rupturing a missile's 
motor casing, causing the missile to lose power. MDA expects that the 
battle management and command and control component will plan and 
execute each ABL engagement.

Program Complexity Drives Cost Growth:

Because it did not adequately plan for and could not fully anticipate 
the complexity of developing and demonstrating ABL's critical 
technologies, the program has experienced continual cost growth and 
schedule delays. The prime contract, which consumes the bulk of the 
program's funding, will reach its cost ceiling in May 2004. The program 
office is in the process of developing a new cost estimate as the basis 
for raising the contract's ceiling price. Additionally, in recognition 
of the contract's rising cost, MDA has increased its cost goal for 
completing ABL's technology development phase during Block 2004.

Contract's Current Value Has Doubled Since 1996 and Continues to 
Increase:

From the contract's award in 1996 through 2003, the cost of ABL's 
primary research and development contract increased from about $1 
billion to about $2 billion. In fiscal year 2003 alone, work completed 
by the contractor cost about $242 million more than expected. The 
contractor also experienced schedule delays and was unable to complete 
$28 million of work planned for the fiscal year. Based on the 
contractor's 2003 cost and schedule performance, we estimate that the 
prime contract will exceed the contractor's July 2003 cost estimate of 
about $2.1 billion by between $431 million and $943 million through 
first full demonstration of the ABL system.

Since 1996, the ABL program has experienced several major 
restructurings and contract re-baselines, due primarily to the 
unforeseen complexity in manufacturing and integrating critical 
technology. According to program officials, rapid prototyping 
(integrating components into a prototype system prior to demonstrating 
the maturity of all critical technologies) limited subcomponent 
testing, causing rework and changing requirements. Today the program 
faces a bow wave of incomplete work from previous years even though the 
prime contractor has increased the number of people devoted to the 
program and has added additional shifts to bring the work back on 
schedule. In addition, unanticipated difficulties in software coding 
and integration issues, as well as difficulty in manufacturing advanced 
optics and laser components, have caused cost growth.

Increasing Cost of Prime Contract Causes Revisions in Technology 
Development Cost Goal:

According to program officials, the prime contract will reach its cost 
ceiling in May 2004. The ABL program office is in the process of 
developing a new cost estimate for the remaining technology development 
activities, including component ground tests, beam control and fire 
control flight-tests, integration of components into a working ABL 
prototype, and a demonstration of the prototype's lethality against a 
boosting ballistic missile. The program will use this estimate as the 
basis for raising the contract's ceiling price.

MDA also recognized the impact that the prime contract's rising cost is 
having on the agency's cost goal for completing ABL's technology 
development. In February 2003, MDA reported in its fiscal year 2004 
Budget Estimate Submission[Footnote 4] that its cost goal for maturing 
and demonstrating ABL's critical technologies during Block 2004 was 
about $494 million. However, in its fiscal year 2005 submission, MDA 
increased its Block 2004 cost goal by $583 million to $1.077 billion by 
moving ABL funds from Blocks 2006 and 2008 to Block 2004. The program 
manager told us that MDA plans to continue updating its cost goal for 
completing technology development as part of each year's budgeting 
process. To better assess the program's annual funding needs, the 
contractor will plan work in about 12-month increments.

Successful developers have found that it is difficult to make highly 
reliable cost and schedule estimates until the maturity of a product's 
critical technologies has been demonstrated. The ABL program has not 
yet reached this point. One well-established tool for providing 
decision makers with an increased understanding of the reliability of 
developed cost estimates is an "uncertainty analysis." An uncertainty 
analysis simulates a model by randomly and repeatedly generating values 
for certain variables. After hundreds or thousands of trials, one can 
view the statistical results and determine the confidence level in any 
outcome. For example, the model may show that there is a 10-percent 
chance that the project can be completed for $50 million, a 50-percent 
chance that it can be completed for $70 million, or a 90-percent chance 
that the project will cost $100 million or less. Although there remains 
a gap in the knowledge MDA needs to make highly reliable estimates of 
the cost to complete ABL's technology development, other programs have 
found that uncertainty analyses help to understand the size of such a 
gap.

Military Utility of Initial ABL Aircraft Is Highly Uncertain:

Predictions of the military utility of the initial ABL aircraft are 
highly uncertain because these forecasts are based on modeling, 
simulations, and analysis, rather than the demonstrated capability of 
the system. The Airborne Laser program office predicts that the ABL 
prototype being developed during Block 2004 will have a capability to 
defeat most classes of theater and intercontinental ballistic missiles. 
However, program officials base these predictions on analyses, models, 
and simulations that are not yet anchored by flight test data. These 
assessment tools take into consideration various factors, such as the 
projected power output of the 6-module laser weapon, the stand-off 
range that ABL maintains to protect itself from threat weapons, and the 
characteristics of the threat missiles. Should any of the assumptions 
made in modeling these factors prove incorrect, the output of the 
assessment tools might prove similarly incorrect. According to test 
officials, models and simulations are adequate for establishing system 
parameters, but may not be sufficient for understanding the 
effectiveness of a fielded system.[Footnote 5] In addition, the 
Department of Defense has not yet assessed the Airborne Laser's 
military utility and has no fixed time frame for doing so.

Even if the program office's assessment proves to be correct, other 
factors, such as reduced time on station and limited forward operating 
capability, will limit ABL's initial military utility. For example, 
with only one aircraft, 24-hour operations are not possible. In 
addition, in order to operate from a forward location the aircraft will 
require a forward-based chemical facility for replenishment of the 
chemicals that fuel the high-energy laser. Without these facilities, 
the Airborne Laser is capable of performing three constrained missions.

Support Costs Will Likely Be Higher Than Those of Other High Value Air 
Assets:

The ABL will require unique support in addition to the already 
substantial support required for all high-value air assets. For 
example, to remain on station for extended periods of time, ABL will 
need a production facility close to the theater of operations that can 
store and mix chemicals for the high-energy laser. Likewise, ABL will 
require unique maintenance, such as re-calibration and re-coating of 
beam control and fire control subcomponents; chemical facilities must 
be secured; and a ground support squadron and chemicals must be 
transported to a forward location.

The ABL will also require support systems, such as a protective escort, 
that are typical of all high-value air assets. Our review of the U.S. 
Air Force Total Ownership Costs Database[Footnote 6] shows that 
operating costs for other high-value air assets, such as the Airborne 
Warning and Control System or Joint Surveillance Target Attack Radar 
System, range from about $24,000 per hour to $92,000 per hour. While 
the ABL program office has identified some of the support systems ABL 
will require once it is fielded, the program does not plan to fully 
address this issue, including support costs, before Block 2006.

Program Changes Likely to Result in a More Cost-Effective Strategy:

MDA made program changes in February 2004 that should make its strategy 
for developing ABL more cost-effective. The primary change is that the 
program will no longer try to develop ABL according to a set schedule, 
but will follow a more knowledge-based approach. For example, MDA no 
longer plans to deliver a contingency sensor capability in the Block 
2004 time frame. Instead it plans to focus on ground-and flight-testing 
components and demonstrating technologies before proceeding to the next 
development phase. However, it does not intend to lose sight of its 
overall objective of testing the prototype ABL aircraft against a 
short-range ballistic missile in what has become known as a lethal 
demonstration. Program officials also told us that they plan to defer 
indefinitely the purchase of a second aircraft and other hardware, 
which MDA initially planned to initiate during Block 2004.

Conclusion:

We believe the ABL program made a sound and cost-effective decision to 
defer the purchase of the second aircraft and additional hardware and 
to pursue a more knowledge-based approach to the element's development. 
It has also taken an important first step by setting a cost goal for 
ABL's technology development phase. However, good investment decisions 
depend upon an understanding of the total funds that will be needed to 
obtain an expected benefit, and, at this time, MDA has not been able to 
provide decision makers assurances that the agency's cost projections 
to complete technology development can be relied upon. Decision makers 
could make more informed decisions about further investments in the ABL 
program if they understood the likelihood and confidence associated 
with MDA's cost projections.

Recommendation:

To provide a better framework for making investment decisions during 
the program's research and development phase, we recommend that the 
Secretary of Defense direct the Director, MDA, to complete an 
uncertainty analysis on the contractor's new cost estimate that 
quantifies the confidence that may be placed in the estimate.

Agency Comments and Our Evaluation:

In written comments to a draft of this report (see encl. II), the DOD 
concurred with our recommendation. DOD also provided separate technical 
comments, which we have incorporated as appropriate.

As requested by your offices, unless you publicly announce the contents 
of this report earlier, we plan no further distribution of it until 30 
days from the date of this letter.

At that point, copies of this report will be sent to the Secretary of 
Defense; the Director, Missile Defense Agency; and other interested 
congressional committees. We will also make copies available to others 
upon request. In addition, the report will be available at no charge on 
the GAO Web site at http://www.gao.gov.

Should you or your staff have any questions on matters discussed in 
this report, please contact me on (202) 512-4841 or Barbara Haynes at 
(256) 922-7535. Principal contributors to this report were Beverly 
Breen, Alan Frazier, LaTonya Miller, and Karen Richey.


Signed by: 

Robert E. Levin 
Director, Acquisition and Sourcing Management:

Enclosure:

Comments From the Department of Defense:

ACQUISITION, TECHNOLOGY AND LOGISTICS:

OFFICE OF THE UNDER SECRETARY OF DEFENSE:

3000 DEFENSE PENTAGON 
WASHINGTON, DC 20301-3000:

Mr. Robert E. Levin:

Director, Acquisition and Sourcing Management 
U. S. General Accounting Office:
441 G. Street, N.W. 
Washington, DC 20548:

Dear Mr. Levin:

This is the Department of Defense's (DoD's) response to the GAO Draft 
Report, "MISSILE DEFENSE: Uncertainties Remain Concerning the Airborne 
Laser's Cost and Military Utility" dated April 9, 2004 (GAO Report 04-
643R/Audit 120290).

The DoD has reviewed the draft report. We concur with the 
recommendation, with the specific comments enclosed. We also recommend 
some factual corrections. My action officer for this effort is Lt Col 
Mark Arbogast, (703) 695-7328, mark.arbogast@osd.mil.

We appreciate the opportunity to comment on the draft report.

Sincerely,

Signed for: 

Glenn F. Lamartin 
Director:
Defense Systems:

Enclosure: As stated:

MAY 3 2004:

GAO DRAFT REPORT - DATED April 9, 2004 GAO Report 04-643R/Audit 120290:

"MISSILE DEFENSE: Uncertainties Remain Concerning the Airborne Laser's 
Cost and Military Utility" (GAO Report 04-643R/Audit 120290)":

DEPARTMENT OF DEFENSE COMMENTS TO THE RECOMMENDATION:

RECOMMENDATION 1: The GAO recommended that the Secretary of Defense 
direct the Director, Missile Defense Agency (MDA) to complete an 
uncertainty analysis on the contractor's new cost estimate that 
quantifies the confidence that may be placed in the estimate (page 10, 
GAO Draft Report).

DOD RESPONSE: Concur. However, it should be noted that the program 
office is producing the new cost estimate, as mentioned on page 3 of 
the report's discussion, not the contractor. The program office has 
already been using uncertainty analysis in its early formulation of the 
new estimate.

(120290):

FOOTNOTES

[1] A knowledge-based approach contains three phases that are each 
distinguished by the knowledge attained. During technology development, 
scientists apply scientific knowledge to a practical engineering 
problem and demonstrate that components with the desired form, fit, and 
function can be developed. During product development, the second 
phase, engineers integrate components into a stable design and 
demonstrate that the design will result in a product that meets the 
customer's needs and can be produced with the time and money available. 
The final phase, production, is the manufacturing of the product. 

[2] Examples of other high-value air assets are the Airborne Warning 
and Control System and the Joint Surveillance Target Attack Radar 
System.

[3] According to the U.S. Air Force Total Ownership Costs Database, 
operating costs include costs for mission personnel, unit-level 
consumption, intermediate maintenance, depot maintenance, contractor 
support, sustaining support, and indirect support.

[4] For the last 2 fiscal years, MDA has issued a document known as a 
Budget Estimate Submission that lays out planned expenditures for each 
near-term block by element and the activities planned during those 
blocks. 

[5] We did not examine the models and simulations that MDA uses to 
forecast ABL's capability or attempt to replicate MDA's predictions of 
ABL's military utility.

[6] The Air Force Total Ownership Costs database provides detailed cost 
information on all Air Force major weapon systems.