This is the accessible text file for GAO report number GAO-12-66 
entitled 'Immigration Benefits: Consistent Adherence to DHS's 
Acquisition Policy Could Help Improve Transformation Program Outcomes' 
which was released on November 22, 2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
GAO: 

Report to Congressional Requesters: 

November 2011: 

Immigration Benefits: 

Consistent Adherence to DHS's Acquisition Policy Could Help Improve 
Transformation Program Outcomes: 

GAO-12-66: 

GAO Highlights: 

Highlights of GAO-12-66, a report to congressional requesters. 

Why GAO Did This Study: 

Each year, the Department of Homeland Security’s (DHS) U.S. 
Citizenship and Immigration Services (USCIS) processes millions of 
applications for immigration benefits using a paper-based process. In 
2005, USCIS embarked on a major, multiyear program to transform its 
process to a system that is to incorporate electronic application 
filing, adjudication, and case management. In 2007, GAO reported that 
USCIS was in the early stages of the Transformation Program and that 
USCIS’s plans partially or fully met key practices. In 2008, USCIS 
contracted with a solutions architect to help develop the new system. 
As requested, GAO evaluated the extent to which USCIS has followed DHS 
acquisition policy in developing and managing the Transformation 
Program. GAO reviewed DHS acquisition management policies and 
guidance; analyzed transformation program planning and implementation 
documents such as operational requirements; compared schedule and cost 
information with GAO best practice guidance; and interviewed USCIS 
officials. 

What GAO Found: 

USCIS has not consistently followed the acquisition management 
approach that DHS outlined in its management directives in developing 
and managing the Transformation Program. USCIS awarded a solutions 
architect contract in November 2008, in effect selecting an 
acquisition approach before completing documents required by DHS 
management directives. Specifically, DHS’s acquisition policy requires 
that prior to selecting an acquisition approach, programs establish 
operational requirements, develop a program baseline against which to 
measure progress, and complete a plan that outlines the program’s 
acquisition strategy. However, USCIS did not complete an Operational 
Requirements Document until October 2009, which was to inform the 
Acquisition Program Baseline and the Acquisition Plan. Consequently, 
USCIS awarded a solutions architect contract to begin capability 
development activities prior to having a full understanding of the 
program’s operational requirements and the resources needed to execute 
the program. GAO has previously reported that firm requirements must 
be established and sufficient resources must be allocated at the 
beginning of an acquisition program, or the program’s execution will 
be subpar. The lack of defined requirements, acquisition strategy, and 
associated cost parameters contributed to program deployment delays of 
over 2 years. In addition, through fiscal year 2011, USCIS estimates 
it will have spent about $703 million, about $292 million more than 
the original program baseline estimate. 

USCIS expects to begin deployment of the first release of the 
Transformation Program in December 2011. However, USCIS is continuing 
to manage the program without specific acquisition management 
controls, such as reliable schedules, which detail work to be 
performed by both the government and its contractor over the expected 
life of the program. As a result, USCIS does not have reasonable 
assurance that it can meet its future milestones. USCIS has 
established schedules for the first release of the Transformation 
Program, but GAO’s analysis shows that these schedules are not 
reliable as they do not meet best practices for schedule estimating. 
For example, program schedules did not identify all activities to be 
performed by the government and solutions architect. Moreover, as 
outlined by DHS acquisition management guidance, a life-cycle cost 
estimate is a required and critical element in the acquisition 
process. USCIS has developed and updated the $1.7 billion life-cycle 
cost estimate for the Transformation Program, but USCIS’s individual 
schedules for the Transformation Program did not meet best practices 
for schedule estimating, raising questions about the credibility of 
the program’s life-cycle cost estimates. Because some program costs 
such as labor, supervision, and facilities cost more if the program 
takes longer, reliable schedules can contribute to an understanding of 
the cost impact if the program does not finish on time. Collectively, 
and moving forward, not meeting best practices increases the risk of 
schedule slippages and related cost overruns, making meaningful 
measurement and oversight of program status and progress, and 
accountability for results, difficult to achieve. 

What GAO Recommends: 

GAO recommends that USCIS ensure its program schedules and life-cycle 
cost estimates are developed in accordance with best practices 
guidance. DHS concurred with GAO’s recommendations and outlined the 
actions that USCIS is taking or has taken to address each 
recommendation. 

View [hyperlink, http://www.gao.gov/products/GAO-12-66]. For more 
information, contact Richard M. Stana at (202) 512-8777 or 
stanar@gao.gov. 

Contents: 

Letter: 

Background: 

USCIS Did Not Always Follow Acquisition Policy Contributing to Program 
Delays, Cost Increases, and Unreliable Schedules: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Detailed Results of GAO Assessment of USCIS's Detailed 
Transformation Program Schedules: 

Appendix II: Comments from the Department of Homeland Security: 

Appendix III: GAO Contact and Staff Acknowledgments: 

Related GAO Products: 

Tables: 

Table 1: USCIS ELIS's Five Core Business Processes: 

Table 2: Transformation Program Planned Deployment: 

Table 3: Transformation Program Spending, Fiscal Years 2006-2011: 

Table 4: Program Milestones and Acquisition Planning Postcontract 
Award: 

Table 5: Description of GAO Scheduling Best Practices: 

Table 6: Transformation Program Schedules' Satisfaction of Schedule 
Estimating Best Practices: 

Table 7: Detailed Results of Transformation Program's OIT Schedule 
Satisfaction of Scheduling Best Practices: 

Table 8: Detailed Results of Transformation Program's Contractor 
Schedule Satisfaction of Scheduling Best Practices: 

Figures: 

Figure 1: USCIS ELIS Features from Customer Perspective: 

Figure 2: USCIS ELIS Features from Adjudicator Perspective: 

Figure 3: Overview of the DHS Acquisition Process: 

Abbreviations: 

ADE: acquisition decision event: 

APB: Acquisition Program Baseline: 

ARB: Acquisition Review Board: 

DHS: Department of Homeland Security: 

ELIS: Electronic Immigration System: 

ESAR: Enterprise Segment Activity Roadmap: 

EVM: Earned Value Management: 

FTE: full-time equivalents: 

IMS: Integrated Master Schedule: 

LOE: level of effort: 

OIT: Office of Information Technology: 

OMB: Office of Management and Budget: 

ORD: Operational Requirements Document: 

PIPT: Program Integrated Product Team: 

PMR: Program Management Review: 

SDR: System Definition Review: 

SNET: Start No Earlier Than: 

SRA: Schedule Risk Analysis: 

TLT: Transformation Leadership Team: 

TPO: Transformation Program Office: 

USCIS: United States Citizenship and Immigration Services: 

WBS: Work Breakdown Structure: 

WIPT: Working Integrated Product Teams: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

November 22, 2011: 

Congressional Requesters: 

Each year, the U.S. Citizenship and Immigration Services (USCIS), 
within the Department of Homeland Security (DHS), processes millions 
of applications and petitions for more than 50 types of immigrant and 
nonimmigrant-related benefits for persons seeking to study, work, 
visit, or live in the United States, and for persons seeking to become 
U.S. citizens. Having a system that allows USCIS to accurately grant 
immigration and citizenship benefits in a timely manner to eligible 
applicants and deny benefits to those who are ineligible, as well as 
one that can quickly and accurately identify fraudulent and criminal 
activity, is essential for ensuring the integrity of the immigration 
process. USCIS has long recognized the need to improve its benefits 
application and adjudication processes and underlying technology 
infrastructure. Moreover, we have previously reported on benefit 
processing inefficiencies that make it difficult to manage and process 
immigration benefit applications in a timely manner.[Footnote 1] 
Further, the current systems and paper records do not allow USCIS to 
easily share information with other government agencies, limiting 
their ability to quickly identify criminals and possible terrorists. 
We have previously recommended that USCIS improve its quality 
assurance program to help ensure that immigration benefits are 
provided only to eligible individuals. USCIS generally agreed with 
this recommendation and has taken action to address. 

To address program inefficiencies, USCIS embarked on a major 
initiative in 2005 to transform its current paper-based system into an 
electronic account-based system that is to use electronic adjudication 
and account-based case management tools, including tools that are to 
allow applicants to apply online for benefits. In July 2007, we 
reported that USCIS was in the early stages of its Transformation 
Program and that its plans partially or fully addressed most key 
practices for organizational transformations.[Footnote 2] However, we 
identified gaps in USCIS's plans that created risks that could 
undermine its success as it began to implement the program, such as 
the lack of clear performance measures and targets for the transformed 
agency to show progress towards goals. We recommended that USCIS 
address gaps in its plans in the areas of performance measurement, 
strategic human capital management, communications, and information 
technology management practices. USCIS agreed with these 
recommendations and has taken actions to address them. In October 
2007, USCIS prepared an acquisition plan that described its planned 
phased approach for acquiring new electronic tools (i.e., 
capabilities), established key milestones, and included an estimated 
program cost. In November 2008, USCIS selected a solutions architect 
to help design, build, and implement the Transformation Program. 
[Footnote 3] 

To help its component agencies manage large-scale acquisitions such as 
the Transformation Program, DHS has established an acquisition review 
process to provide departmental oversight at key points in an 
investment's life-cycle to assess the cost, schedule, and performance 
of these acquisitions. At critical steps in the acquisition process, 
agency components are required to prepare certain documents and to 
obtain approval from DHS's Acquisition Review Board (ARB) before 
moving into the next phase of the acquisition process.[Footnote 4] In 
2007, DHS established an Acquisition Program Management Division to 
support the ARB in managing DHS acquisitions.[Footnote 5] 

Given the critical nature of the Transformation Program to USCIS, you 
asked that we evaluate USCIS's efforts to implement the program. 
Specifically, this report addresses the extent to which USCIS has 
followed DHS acquisition policy in developing and managing the 
Transformation Program. 

To address this objective, we reviewed DHS departmental policies and 
guidance, such as DHS acquisition management directives, and relevant 
Transformation Program planning documents, including the 2007 
Acquisition Plan and Expenditure Plan; 2008, 2010, and 2011 
Acquisition Program Baseline; and 2009, 2010, and 2011 Operational 
Requirements Document. We also reviewed the program's monthly status 
reports dated April 2010, when we began our work, through July 2011; 
the solutions architect contract for contractual program milestones; 
and program schedules for tracking program milestones and activities. 
Further, we reviewed DHS ARB decision memorandums for information on 
DHS-level approval of the Transformation Program's key acquisition 
events and action items to be addressed by the program. We interviewed 
USCIS's Transformation Program officials concerning early program 
planning efforts and challenges, schedule estimates and costs, and the 
development and planned deployment of the first phase of the program, 
among other things. We also interviewed DHS Acquisition Program 
Management Division officials about the acquisition process and 
decisions related to the Transformation Program. We analyzed two key 
Transformation Program schedules as of November 2010, and one updated 
schedule as of August 2011, against nine best practices associated 
with developing and maintaining reliable schedules in our Cost 
Estimating and Assessment Guide.[Footnote 6] We used commercially 
available software to determine whether these schedules, among other 
best practices, included all major activities and had a logical 
sequence of activities and reasonable activity durations.[Footnote 7] 

We conducted this performance audit from April 2010 through November 
2011, in accordance with generally accepted government auditing 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives. 

Background: 

Overview of Transformation Program: 

Once the Transformation Program is completed, USCIS envisions that the 
new electronic adjudication capabilities and improved information 
technology will improve agency operations and enable greater data 
sharing and management of information. USCIS expects the new system, 
named the USCIS Electronic Immigration System (ELIS), to have features 
that will allow USCIS to meet its transformation goals of enhanced 
national security and system integrity, better customer service, and 
operational efficiency. For example, once USCIS ELIS is implemented, 
USCIS expects that: 

* Individuals will be able to establish an account with USCIS and file 
applications over the internet, as well as obtain information on the 
status of their application. 

* USCIS will automatically apply risk-based rules to incoming 
applications to identify potentially fraudulent applications and 
national security risks. 

* Adjudicators will have electronic access to applications, as well as 
relevant USCIS policies and procedures and external databases, to aid 
in decision making. 

* USCIS will have the necessary management information to help it 
allocate workload and measure performance. 

* USCIS will have electronic linkages with other agencies, such as the 
Departments of Justice and State, for data sharing and security 
purposes. 

Figure 1 depicts the key features of USCIS ELIS, as envisioned, from a 
USCIS customer perspective. Figure 2 depicts these key features, as 
envisioned, from a USCIS adjudicator perspective. 

Figure 1: USCIS ELIS Features from Customer Perspective: 

[Refer to PDF for image: illustration] 

How customers/third party representatives will file: 

1) Create user account: 
* Select notification preferences and password. 

2) Enter benefit application data: 
* Enter data using a wizard that guides the user step=by=step through 
the electronic application. 

3) Review and submit application to USCIS online and pay online. 

4) Receive e-mail notification to access account information to view 
recent action on the benefit application, or receive USCIS notices by 
mail. 

5) Check case status through online account. 

6) Manage submitted application: 
* Uses account to change customer/representative relationship, change 
address, respond to request for evidence and access USCIS notices 
online. 
           
Source: USCIS: and Art Explosion (clipart). 

[End of figure] 

Figure 2: USCIS ELIS Features from Adjudicator Perspective: 

[Refer to PDF for image: illustration] 

How USCIS Immigration Services Officer (adjudicator) will process 
benefits requests: 

1) Accesses system online to view a list of all assigned cases. 

2) Selects and reviews case. Validates evidence; identifies previous 
prerequisite related cases.  

3) Reviews risk assessments completed automatically by the system and 
reviewed by a background check officer before case is made available 
for adjudication.           

4) Reviews immigration history and associated policy and resources: 
* Accesses related information and resources from existing sources to 
support decision making. Documents completion of activities.  

5) Assesses eligibility and completeness, based on current law and 
policy.
 
6) Indicates and documents adjudication decision. Generates proof of 
benefit and notifies customer. 

Source: USCIS; and Art Explosion (clipart). 

[End of figure] 

Implementation of Transformation Program Business Processes: 

The Transformation Program intends to design and develop five core 
business processes to form the foundation of USCIS ELIS and process 
and manage all applications. Table 1 identifies and briefly describes 
the five core business processes. 

Table 1: USCIS ELIS's Five Core Business Processes: 

Business process: Immigration Account Management; 
Description: Enable USCIS customers to establish and maintain their 
account information electronically and USCIS employees to access case 
information when adjudicating cases. 

Business process: Benefits Case Management; 
Description: Enable USCIS customers to apply for immigration benefits 
online via the internet, and enable USCIS employees to access case 
information in one location for more efficient processing and managing 
of benefits requests. 

Business process: Electronic Content Management; 
Description: Enable USCIS employees to access electronic evidence and 
information from within USCIS and from agency partners such as the 
Departments of State and Labor to support decision making. 

Business process: Agency and Knowledge Management; 
Description: Enable USCIS management to electronically access and 
centrally manage workload, resources, and performance. 

Business process: Risk and Fraud Management; 
Description: Enable USCIS employees to access actionable risk 
information to help quickly identify potential threats, risks, and 
fraud. Information to be integrated from across USCIS and from other 
agencies. 

Source: GAO analysis of USCIS documentation. 

[End of table] 

USCIS plans to deploy USCIS ELIS in a series of five releases, labeled 
A through E.[Footnote 8] Within the first two releases, USCIS ELIS is 
to be available to USCIS customers applying for nonimmigrant benefit 
types, followed by immigrant benefits, humanitarian benefits, and 
citizenship benefits.[Footnote 9] Much of the functionality needed to 
operate the five core business processes are to be established during 
Releases A and B, with an enhanced level of functionality to be added 
during Releases C through E. Table 2 below shows the order in which 
ELIS's five releases are to be deployed and available to USCIS 
customers. 

Table 2: Transformation Program Planned Deployment: 

Release: A; 
Planned deployment: Five core business processes for individuals 
applying for selected nonimmigrant benefits such as application to 
change immigration status; 
Examples of benefits: Extend/Change nonimmigrant status; Employment 
authorization; Temporary protected status. 

Release: B; 
Planned deployment: Enhanced core business processes' functionality 
for USCIS customers applying for nonimmigrant benefit types not 
addressed in Release A; 
Examples of benefits: Replace permanent resident card; Petition for a 
nonimmigrant worker. 

Release: C; 
Planned deployment: USCIS customers applying for immigrant benefits; 
Examples of benefits: Petition for alien relative; Petition for alien 
worker; Permanent residency (except for asylees and refugees). 

Release: D; 
Planned deployment: USCIS customers applying for humanitarian benefits; 
Examples of benefits: Permanent residency for asylees and refugees; 
Asylum. 

Release: E; 
Planned deployment: USCIS customers applying for citizenship benefits; 
Examples of benefits: Naturalization. 

Source: GAO analysis of USCIS data. 

[End of table] 

Overview of the Transformation Program Management Structure, 
Acquisition Approach, and Funding Sources: 

In 2006, USCIS drafted a transformation strategic plan to guide its 
modernization efforts and established the Transformation Program 
Office (TPO) to lead and carry out the effort. By 2007, USCIS 
established a governance structure for the overall management, 
leadership, decision making, and oversight of the Transformation 
Program. The TPO governance structure includes three key groups: (1) 
Transformation Leadership Team (TLT) responsible for the overall 
program direction and coordination of transformation initiatives 
within the agency; (2) Program Integrated Product Teams (PIPT) 
responsible for advising on and approving strategy and performance 
measures, and overseeing and managing the program, including cost, 
schedule, and performance; and, (3) Working Integrated Product Teams 
(WIPT), composed of agencywide representatives with expertise to help 
define the transformed business processes and its operational aspects. 

In addition to these key groups, USCIS also holds Program Management 
Review (PMR) meetings to help manage the transformation effort. Each 
month, the Transformation Program conducts PMR meetings to assess the 
status of the overall program and solutions architect activities in 
terms of cost, schedule, performance, and risk. Major program groups 
associated with USCIS's transformation efforts, and the solutions 
architect, report on the status of activities and deliverables for 
which they have responsibility.[Footnote 10] The monthly PMR reports 
help provide an up-to-date snapshot of top program risks and concerns 
and how they are being mitigated, as well as the overall status of the 
program in meeting its milestones, among other information. 

In November 2008, USCIS awarded a solutions architect contract for 
approximately $500 million to be allocated over a 5-year period, to 
design, develop, test, deploy, and sustain the Transformation Program 
by November 2013.[Footnote 11] As such, the Transformation Program is 
USCIS's largest acquisition and according to USCIS's current Director 
"no project is more important to long-term operational improvement and 
efficiency than Transformation."[Footnote 12] USCIS has funded the 
Transformation Program through both direct legislative appropriations 
and revenue from applicants' application fees paid. In fiscal years 
2006 and 2007, Congress appropriated a combined total of $71.7 million 
to fund Transformation Program efforts. Since fiscal year 2007, 
USCIS's premium processing fee revenue has been the primary source of 
funding for the Transformation Program.[Footnote 13] In addition, the 
program has used funds from its application fee account to pay for the 
salaries and benefits of USCIS Transformation Program staff. As shown 
in Table 3, USCIS spent about $455 million from fiscal years 2006 
through 2010, which includes costs incurred by both the solutions 
architect and USCIS. USCIS estimates it will spend approximately $248 
million in fiscal year 2011 for an estimated total cost of about $703 
million through fiscal year 2011. 

Table 3: Transformation Program Spending, Fiscal Years 2006-2011: 

Fiscal year: 2006; 
Transformation Program spending: $19.3 million. 

Fiscal year: 2007; 
Transformation Program spending: $26.9 million. 

Fiscal year: 2008; 
Transformation Program spending: $52.5 million. 

Fiscal year: 2009; 
Transformation Program spending: $122.6 million. 

Fiscal year: 2010; 
Transformation Program spending: $233.2 million. 

Fiscal year: Total spending 2006-2010; 
Transformation Program spending: $454.5 million. 

Fiscal year: Estimated spending 2011; 
Transformation Program spending: $248.4 million. 

Fiscal year: Total estimated spending 2006-2011; 
Transformation Program spending: $702.9 million. 

Source: GAO analysis of USCIS data. 

Note: Transformation Program did not incur solutions architect costs 
in fiscal years 2006 through 2007. 

[End of table] 

Overview of DHS Acquisition Process: 

In 2003, DHS established an investment review process to help reduce 
risk and increase the chances for successful acquisition outcomes by 
providing departmental oversight of major investments throughout their 
life-cycles. The process was intended to help ensure that funds 
allocated for investments through the budget process were being spent 
wisely, efficiently, and effectively. In March 2006, DHS issued 
Management Directive No. 1400 that defined and updated DHS's 
investment review process. The directive required programs to prepare 
certain documents before transitioning to the next acquisition phase 
to ensure the program is ready to move to the next phase. To implement 
more rigor and discipline in its acquisition processes, DHS created 
the Acquisition Program Management Division in 2007 to develop and 
maintain acquisition policies, procedures, and guidance as a part of 
the system acquisition process.[Footnote 14] In November 2008, DHS 
issued an interim acquisition directive and guidebook that superseded 
Management Directive No. 1400, which provided programs guidance to use 
in preparing key documentation to support component and departmental 
decision making.[Footnote 15] In January 2010, DHS finalized the 
acquisition directive, which established acquisition life-cycle phases 
and senior-level approval of each major acquisition program at key 
acquisition decision events during a program's acquisition life- 
cycle.[Footnote 16] This directive established the acquisition life- 
cycle framework with four phases: 

1. identify a capability need (need phase); 

2. analyze and select the means to provide that capability (analyze/ 
select phase); 

3. obtain the capability (obtain phase); and: 

4. produce, deploy, and support the capability (produce/deploy/support 
phase). 

Each acquisition phase culminates in a presentation to the DHS ARB, 
which is to review each acquisition at least three times at key 
acquisition decision events during a program's life-cycle. Figure 3 
presents the four DHS acquisition phases, including the documents 
presented to ARB and their review as defined in the acquisition 
directive. 

Figure 3: Overview of the DHS Acquisition Process: 

[Refer to PDF for image: illustration] 

Need: Define the problem; review mission need statement; 
ADE 1; 
Analyze/select: Identify the alternatives and resource requirements; 
REview planning documents, including operational requirements 
document, acquisition program baseline, and acquisition plan; 
DHS approves selected acquisition approach; 
ADE 2A; 
Obtain: DHS approves supporting acquisitions including small-scale 
productions; 
ADE 2B; 
Develop and evaluate capabilities; DHS approves the acquisition to go 
into production. 
Produce/deploy/support: ADE 3; Produce and maintain those capabilities. 

Legend: 
ADE: Acquisition Decision Event. 

Source: GAO analysis of DHS Acquisition Management Directive 102-01; 
and Art Explosion (clipart). 

[End of figure] 

The Acquisition Decision Authority--the Chief Acquisition Officer or 
other designated senior-level official--is to chair ARB and decide 
whether the proposed acquisition meets certain requirements necessary 
to move onto the next phase and eventually to full production. The 
directive outlines the extent and scope of required program, project, 
and service management; level of reporting; and the acquisition 
decision authority based on whether the acquisition is considered a 
major life-cycle cost[Footnote 17] (estimated at or above $300 
million) or nonmajor (life-cycle costs estimated to be below $300 
million). DHS considers the USCIS Transformation Program a major 
acquisition, and as such, the decision authority is the DHS Under 
Secretary for Management.[Footnote 18] 

Following an ARB meeting, the Acquisition Program Management Division 
is to prepare an acquisition decision memorandum as the official 
record of the meeting. This memorandum is to be signed by the 
acquisition decision authority and must describe the approval or other 
decisions made at the ARB and any action items to be satisfied as 
conditions of the decision. The ARB reviews provide the department an 
opportunity to determine a program's readiness to proceed to the 
following life-cycle phase. However, we reported in March 2011 that 
the ARB had not reviewed most of DHS's major acquisition programs by 
the end of fiscal year 2009, and the programs that were reviewed had 
not consistently implemented action items identified in the review by 
established deadlines.[Footnote 19] Our prior work has shown that when 
these types of reviews are skipped or not fully implemented, programs 
move forward with little, if any, early department-level assessment of 
the programs' costs and feasibility, which contributes to poor cost, 
schedule, and performance outcomes.[Footnote 20] In June 2011, DHS 
reported that it was taking action to strengthen its acquisition 
management processes by reviewing programs on an ongoing basis rather 
than only at key acquisition decision events, and developing decision-
making support tools to aid with oversight. These are positive steps 
that if effectively implemented should help strengthen its acquisition 
management processes. 

USCIS Did Not Always Follow Acquisition Policy Contributing to Program 
Delays, Cost Increases, and Unreliable Schedules: 

USCIS has not consistently followed the acquisition management 
approach that DHS outlined in its management directives in developing 
and managing the Transformation Program. Consistent with DHS 
acquisition policy, USCIS prepared a Mission Needs Statement to 
justify the need and value of the Transformation Program in pursuing 
the proposed acquisition. In addition, USCIS identified and analyzed 
various alternatives for transforming its business processes. However, 
USCIS did not complete several acquisition planning documents required 
by DHS policy prior to moving forward with an acquisition approach and 
selecting a solutions architect to develop USCIS ELIS's capabilities. 
The lack of this program documentation contributed to the 
Transformation Program being more than 2 years behind schedule in its 
planned initial deployment of USCIS ELIS and increased program costs. 
In addition, USCIS has not developed reliable or integrated schedules, 
both of which, under DHS acquisition guidance, are required and 
essential acquisition management elements. As a result, USCIS cannot 
reliably estimate when all releases of the Transformation Program will 
be delivered. 

USCIS Awarded a Contract to Develop Program Capabilities without Fully 
Understanding Requirements and Resources Needed: 

USCIS awarded a solutions architect contract to begin capability 
development activities prior to having a full understanding of 
requirements and resources needed to execute the program. DHS's 
acquisition policy requires that programs conduct planning efforts to 
establish a program's operational requirements, to develop a program 
baseline against which to measure progress, and a plan that outlines 
the program's acquisition strategy. These planning efforts are to be 
documented in three key documents: the Operational Requirements 
Document, the Acquisition Program Baseline, and the Acquisition Plan. 
According to DHS policy, these key documents are to be completed 
before selecting and moving forward with an acquisition 
approach.[Footnote 21] According to agency officials, the goal is to 
help ensure that before committing funds to develop a capability, the 
program's operational requirements, cost, schedule, and performance 
parameters have been fully defined. We have previously reported that 
firm requirements must be established and sufficient resources must be 
allocated at the beginning of an acquisition program, or the program's 
execution will be subpar.[Footnote 22] We have also reported that well-
defined requirements are critical to ensuring communication about what 
the government needs from the contractor providing services.[Footnote 
23] However, when the solutions architect contract was awarded in 
November 2008, one document had not been completed and the other two 
did not fully address the program's estimated cost, planned schedule, 
or performance parameters. Below is a summary of the three planning 
documents that USCIS did not develop according to DHS policy: 

Operational Requirements Document (ORD)--According to DHS acquisition 
policy, this document is to describe the operational mission, 
objectives, capabilities, and operational user key performance 
parameters (i.e., the minimum as well as the desired levels of 
performance that must be met to provide a useful capability to the 
user) and should be completed before an acquisition approach is 
selected.[Footnote 24] However, USCIS did not develop the first 
version of the ORD until October 2009, almost a year after the award 
of the solutions architect contract.[Footnote 25] 

Program officials acknowledged that an ORD was not prepared prior to 
selecting an acquisition approach but stated that the solutions 
architect had sufficient information on the program's operational 
requirements to begin work. For example, they stated that the 
contractor received USCIS's Enterprise Segment Activity Roadmap 
(ESAR), which described various activities related to ELIS's core 
business process. However, in a February 2009 memorandum, the USCIS 
Chief Information Officer stated that the ESAR did not provide a 
realistic capability to guide, constrain, or measure the solutions 
architect because the business process mappings were incomplete and 
vague, among other reasons. 

Acquisition Program Baseline (APB)--This document is to provide cost, 
schedule, and performance parameters. DHS policy requires it to be 
prepared prior to selecting an acquisition approach. USCIS completed a 
draft acquisition program baseline in May 2008 prior to awarding the 
solutions architect contract. However, the May 2008 APB did not fully 
address cost, schedule, and performance parameters as required by DHS 
policy. Regarding cost, the APB estimated the Transformation Program 
would cost approximately $410.7 million for fiscal years 2009 through 
the second quarter of fiscal year 2013. However, this estimate only 
included the estimated contract cost for a solutions architect. 
According to program officials, the estimate did not include USCIS 
costs for upgrading its information technology infrastructure, such as 
upgrading networks and servers or the costs of USCIS Transformation 
Program personnel and other support contractors, because these costs 
had yet to be defined. Moreover, USCIS had not yet developed a life- 
cycle cost estimate, which per DHS acquisition policy, is a source 
document used to develop the APB's cost parameters. 

Regarding the schedule included in the May 2008 APB, it was a high- 
level view of the program's key milestones. The acquisition program 
baseline shows that the program's start was expected in fiscal year 
2009 and the deployment of all benefit types in USCIS ELIS by fiscal 
year 2013. According to DHS acquisition policy, this high-level 
schedule is to be based upon a program's integrated master schedule, a 
larger and more detailed delineation of program milestones and 
associated deliverables. However, USCIS did not complete an integrated 
master schedule prior to contract award. In the absence of an 
integrated master schedule, program officials were unable to clarify 
for us how USCIS determined the program's key milestones, which had 
USCIS implementing USCIS ELIS from fiscal years 2009 through 2013. 
Lastly, DHS acquisition policy required that performance parameters be 
based upon operational requirements. The May 2008 acquisition program 
baseline captured performance parameters, but they were not based on 
operational requirements since USCIS had not yet developed operational 
requirements, as discussed above. 

Acquisition Plan--This document is to address, among other things, 
technical, business, management, and other significant considerations 
affecting the acquisition strategy and contract selection. USCIS 
developed an acquisition plan in October 2007; however, this document 
did not address all capabilities for sustaining and maintaining the 
acquisition, such as certain technical considerations that would 
affect the acquisition strategy, as required by DHS acquisition 
guidance. For example, USCIS was to upgrade its information technology 
infrastructure. However, the October 2007 acquisition plan did not 
reflect these technical considerations. 

Moreover, cost information in the acquisition plan is not traceable to 
other documents, such as a validated life-cycle cost estimate or an 
acquisition program baseline, as required by DHS guidance. 
Specifically, the October 2007 acquisition plan presented a $3.4 
billion estimated cost for the Transformation Program. According to 
program officials, the $3.4 billion included information technology 
costs and covered the life of the program, which is similar to a life- 
cycle cost estimate. However, the $3.4 billion cost had not been 
validated as a life-cycle cost estimate by the DHS Cost Analysis 
Division. Moreover, the May 2008 acquisition program baseline makes no 
reference to the $3.4 billion cost over the life of the program. 
However, as required by DHS guidance, the acquisition program baseline 
is to reflect all cost parameters. 

According to program officials, the solutions architect contract was 
performance-based, meaning that USCIS specified the outcomes it was 
seeking to achieve and gave the solutions architect responsibility for 
identifying and delivering the assets needed to achieve these 
outcomes.[Footnote 26] As a result of this approach, many of the 
specifics that would affect the program's cost and schedule were to be 
determined after the contract was signed. The contract called for the 
solutions architect to use the 90-day base period from November 2008 
to February 2009 to develop a plan to (1) identify work activities to 
be performed; (2) assign resources to these activities; (3) project 
the start and completion dates for these activities; (4) provide 
deliverables to the TPO; and (5) establish performance measures that 
the contractor and USCIS could use to measure progress. For example, 
the specific operational requirements and USCIS information technology 
upgrades that would be needed would depend upon the solutions 
architect plan. However, as early as 2004--4 years prior to the 
solutions architect contract--we reported that this type of 
acquisition strategy and contracting approach had led to poor 
acquisition outcomes at DHS. Specifically, we reported that a 
contracting approach that assigned a U.S. Coast Guard contractor 
significant responsibilities, such as the identification of work 
activities and deliverables had been a primary reason for performance, 
cost, and schedule problems, as it had led to incomplete information 
about performance and production risks.[Footnote 27] Program officials 
emphasized that the work completed during this 90-day base period was 
done in conjunction with USCIS, which helped to inform the production 
of these deliverables. 

Incomplete Planning Contributed to Missed Milestones, Increased Costs, 
and Anticipated Benefits That Were Not Achievable: 

Incomplete program planning documents at the start of the program 
contributed to the delayed deployment of USCIS ELIS, increased costs, 
and anticipated benefits not being achieved. 

Missed Milestones: 

According to the November 2008 solutions architect contract, the 
deployment of capabilities was to begin by September 2009 and be 
completed by 2013. USCIS did not meet the September 2009 deployment 
milestone. In an April 2009 memorandum to USCIS's Acting Deputy 
Director and Chief Financial Officer, the program manager stated that 
based on the solutions architect's proposal, the program did not have 
sufficient staff to provide adequate government oversight of the 
solutions architect or funding to support the proposed solution 
"rendering the solution unachievable." Consequently, the solutions 
architect contract was modified by scaling back the scope to allow the 
contractor to focus on work activities necessary to develop the five 
core business processes. Accordingly, TPO was not authorized to start 
preliminary design work for Release A until December 2009. By December 
2009, TPO proposed deployment of this first release by April 2011. 
However, as noted in its July 2010 Acquisition Decision Memorandum, 
TPO experienced delays while defining Release A requirements. These 
delays resulted in a revised deployment milestone to occur between 
June and August 2011. Difficulties defining requirements continued and 
in November 2010, USCIS revised the deployment milestone to December 
2011. By January 2011, the requirements had not yet been completed, 
and by April 2011 USCIS reduced the scope of the first release to meet 
the newly revised December 2011 deployment time-frame. Operational 
requirements were completed in April 2011 and approved by the ARB in 
July 2011, nearly 3 years after the solutions contract was awarded. 
Table 4 provides information on Transformation Program milestones, 
status, and acquisition planning postcontract award. 

Table 4: Program Milestones and Acquisition Planning Postcontract 
Award: 

Milestone date: Sept. 2009; 
Milestone: Begin deployment of the first phase of USCIS ELIS to 
Citizenship benefit types; 
Milestone status: Not met; 
Description: USCIS awarded the solutions architect contract in 
November 2008, with a contractual milestone to deploy five core 
business processes for customers to file, and adjudicators to process, 
all benefit applications associated with its Citizenship line of 
business; 
Acquisition planning postaward of contract: USCIS reviewed staff needs 
and costs and scope of upgrading USCIS's technology infrastructure, 
among other things, as proposed in the solutions architect's plan--
concluding that USCIS did not have the resources, including funding, 
or infrastructure to support the proposed solution. 

Milestone date: April 2011; 
Milestone: Proposed Release A deployment, to first deliver core 
processes to Non-Immigrant benefit types; 
Milestone status: Not met; 
Description: USCIS requested and was authorized by the ARB in December 
2009 to change the order of deployment of its lines of business (start 
from Non-Immigrant instead of Citizenship); 
Acquisition planning postaward of contract: Costs of digitizing 
existing paper files in support of the schedule for the program were 
defined, showing that original plans were not achievable within 
associated budget and timeframe. 

Milestone date: June to Aug. 2011; 
Milestone: Revised deployment of Release A, to deliver a release that 
was reduced in scope; 
Milestone status: Not met; 
Description: By July 2010, USCIS had changed the scope of the first 
release moving certain capabilities to Release B because of delays in 
fully defining Release A requirements; 
Acquisition planning postaward of contract: Contract structure was 
reviewed, showing there was a cost risk due to lack of alignment 
between key events and deliverables for each release. 

Milestone date: Dec. 2011; 
Milestone: Revised deployment of Release A, to first deliver core 
processes to one Non-Immigrant benefit type; 
Milestone status: n/a[A]; 
Description: By February 2011, USCIS proposed reducing the scope of 
the first release because the solutions architect indicated that it 
was unable to support a timely deployment unless the release was 
limited to one benefit type. By April 2011, USCIS reduced the scope of 
Release A and expected the additional benefit types associated with 
the Non-Immigrant business line to be deployed by October 2012; 
Acquisition planning postaward of contract: Requirements were in the 
process of being defined, showing that USCIS and the solutions 
architect had underestimated the time and effort needed to develop 
requirements based on the complexity of the immigration process (i.e., 
workflow process business rules, legacy environment, and subject 
matter). 

Source: GAO analysis of DHS data. 

[A] The December 2011 milestone had not occurred as of the date this 
report was issued. 

[End of table] 

Cost Increases: 

Because the acquisition strategy and associated cost parameters were 
not fully outlined at the start of the program, costs associated with 
the Transformation Program have increased above the original estimate. 
The program's May 2008 acquisition program baseline estimated that the 
total cost of the program from fiscal years 2009 to 2013 would be 
$410.7 million. However, the estimated cost through fiscal year 2011 
is about $703 million, about $292 million more than estimated in May 
2008. This increase in the cost estimate is due to the fact that 
USCIS's original planning efforts did not cover the entire program, as 
required by DHS acquisition planning guidance. For example, the 
acquisition program baseline did not include USCIS's information 
technology enabling costs which, based on data gathered from program 
officials, totals approximately $618 million and includes activities 
such as upgrading its technology infrastructure. In addition, the 
staffing levels have significantly increased from original 
projections. At the start of the Transformation Program, USCIS had 
allocated funding for 20 full-time equivalent staff assigned to TPO. 
As of June 2011, the program had an authorized staffing level of 98. 
Other costs not planned for have contributed to the program's overall 
cost increases. For example, the cost of an operational testing agent, 
who would be responsible for planning, conducting and reporting 
independent operational testing and evaluation for Release A, was not 
included in the acquisition planning process. USCIS officials from TPO 
and the Office of Information Technology (OIT) agreed that an 
operational test agent appeared to be a duplicative effort because TPO 
had already planned to conduct independent testing.[Footnote 28] 
However, DHS denied TPO's request for a waiver of the operational 
testing agent. As a result, USCIS contracted with an independent 
operational test agent by October 2010, and as of June 2011, TPO has 
awarded approximately $1.8 million towards this contract. 

Deferred Capabilities and Reduced Scope: 

USCIS's Transformation Program planned to deploy USCIS ELIS first to 
USCIS customers applying for citizenship benefits. However, once USCIS 
defined the costs associated with digitizing (scanning paper documents 
into an electronic format) existing records following the June 2009 
ARB, USCIS concluded that the original plans were not achievable 
within the associated budget. As a result, in December 2009, USCIS 
requested--and was authorized by the ARB--to change the order of 
deployment and begin with the nonimmigrant instead of citizenship line 
of business. Moreover, according to program officials, from June 2010 
to March 2011, USCIS worked to fully define the operational 
requirements that had not been developed prior to the start of the 
solutions architect contract. For example, an operational requirement 
of USCIS ELIS is account set up and intake, which is the ability of 
USCIS customers to set up accounts and for adjudicators to process 
them through one, person-centric account. TPO worked with subject-
matter experts from USCIS's field and headquarters offices who were 
most familiar with the adjudication process to map out steps that were 
needed to fully define USCIS ELIS's operational requirements. However, 
in an ARB meeting held in July 2010, and in a program management 
review meeting for January 2011, program officials explained that 
defining operational requirements was taking longer than expected due 
to the complexity of the rules that needed to be defined in USCIS 
ELIS, and the review of and agreement to these rules by all 
stakeholders. For example, one requirement--the account set-up and 
intake requirement--identified 35 operational functions for USCIS ELIS 
to perform this action, including set up account online, schedule an 
appointment, and evaluate any identity discrepancy. To enable 
completion of the operational requirements needed to move into 
subsequent phases of development for Release A, USCIS moved 
approximately 10 percent of the capabilities into the second release. 
In May 2011, program officials told us they changed the scope of the 
first release and that full automation of Release A would not be in 
place in December 2011. Further, only one nonimmigrant benefit would 
be deployed at that time. Other nonimmigrant benefits were scheduled 
to be deployed between January and October 2012. 

DHS Increased Its Oversight to Help Ensure Transformation Program's 
Compliance with DHS Acquisition Process: 

DHS has increased its oversight of the Transformation Program since it 
authorized USCIS to award the solutions architect contract in October 
2008. In 2008, we reported that DHS's investment review process had 
not provided the oversight needed to identify and address cost, 
schedule, and performance problems in its major acquisitions, 
including ensuring that programs prepared key documents prior to 
moving into subsequent phases of program development. At the time, we 
made several recommendations aimed at better ensuring DHS fully 
implemented and adhered to its acquisition review process, including 
tracking major investments.[Footnote 29] DHS generally agreed with our 
recommendations and has since taken actions to improve its acquisition 
review process, including developing a database to capture and track 
key program information, such as cost and schedule performance, 
contract awards, and program risks. The database became fully 
operational in September 2009. DHS Acquisition Program Management 
Division officials acknowledged that there was limited oversight of 
the Transformation Program at the time the contract was signed 
primarily due to having limited staff to oversee DHS's programs. These 
officials further stated that DHS was continuing to develop its 
acquisition oversight function and had begun to implement the revised 
acquisition management directive that included more detailed guidance 
for programs to use when informing component and departmental decision 
making. 

Since the contract award, the ARB has met six times to review the 
Transformation Program's status. At these meetings, the ARB has 
directed the TPO to address a number of issues related to cost, 
schedule, and performance. For example, in June 2009, the ARB held two 
meetings to discuss risks that had been identified during the 90-day 
baseline period, such as inadequate staffing levels and delays in 
delivering required government-furnished items to the contractor. As a 
result of these risks, the ARB authorized USCIS to move forward with 
awarding contract options one and two, but restricted the amount that 
could be expended. The Transformation Program Office was also required 
to return to the ARB for authorization to award any additional 
options. According to the ARB Acquisition Decision Memorandum from 
December 2009, the program had improved its staffing significantly, 
but issues remained, including the need to fully define system 
requirements prior to returning to the ARB for authorization to enter 
into design, development, and testing phases, as noted in the August 
2010 ARB Acquisition Decision Memorandum. As a result of this and 
other outstanding action items, the ARB did not grant the program 
permission to proceed with development as requested by USCIS at the 
July 2010 and November 2010 ARBs. Subsequently, in April 2011, the 
program completed development of operational requirements and the 
acquisition program baseline. USCIS received departmental approval for 
both the requirements and acquisition baseline in July 2011, along 
with approval to proceed with development. DHS Acquisition Program 
officials stated that USCIS had received approval because they had 
fully defined operational requirements for Release A, but that USCIS 
was expected to return to the ARB in December 2011 in order to obtain 
a decision on whether Release A can be deployed as scheduled at the 
end of the year. In addition, DHS officials stated that before the ARB 
approves releases beyond Release A, TPO will need to demonstrate that: 

* USCIS ELIS's core business processes work in accordance with its 
operational requirements, and: 

* USCIS can afford to pay for the rest of the program. 

In several meetings, the ARB has requested that USCIS refine or 
otherwise provide a complete and documented life-cycle cost estimate 
for DHS review and validation. USCIS subsequently completed life-cycle 
cost estimates in September 2009, November 2010, and an updated 
version in March 2011. This most recent version estimated that the 
Transformation Program's life-cycle cost would be approximately $1.7 
billion from fiscal years 2006 through 2022. However, as referenced in 
the life-cycle cost estimate--a planning document--USCIS cannot 
estimate several work elements because the program does not have 
required information to estimate complete cost, such as requirements 
beyond Release A.[Footnote 30] According to the TPO Program Manager, 
DHS has reviewed and provided guidance on the development of the life- 
cycle cost estimate, but it has not yet validated the life-cycle cost 
estimate as being sound and reasonable. Therefore, at this time, the 
total expected costs of the program from initiation through completion 
remain uncertain. Prior to validation of the life-cycle cost estimate, 
program officials stated that TPO and the DHS Cost Analysis Division 
are to work closely to ensure the cost estimate is sound and 
reasonable. According to best practices in cost estimating, an updated 
life-cycle cost estimate is to, among others, show the source of data. 
In the case of the Transformation Program, an updated life-cycle cost 
estimate should show the source of data underlying the software design 
and cost estimating model, and the equations used to estimate the 
costs of this large effort. The most recent Acquisition Decision 
Memorandum dated July 7, 2011, states that the Transformation Program 
Office must work closely with the DHS Cost Analysis Division to 
complete a life-cycle cost estimate by September 30, 2011. 

Improved Acquisition Planning Could Help USCIS Avoid Further Delays 
and Potential Cost Overruns for the Transformation Program: 

USCIS Does Not Have Reasonable Assurance That Future Milestones Are 
Achievable: 

USCIS is continuing to manage the Transformation Program without 
specific acquisition management controls such as reliable schedules 
and as a result it will be difficult for USCIS to provide reasonable 
assurance that it can meet its future milestones. USCIS has 
established schedules for the first release of the Transformation 
Program, but our analysis shows that these schedules are not reliable 
as they do not meet best practices for schedule estimating. For 
example, the schedules did not identify all activities to be performed 
by the government and solutions architect. Additionally, USCIS has 
encountered a number of challenges in implementing the schedules, such 
as assumptions that have not been met regarding the time frames that 
either the solutions architect or USCIS would complete certain tasks. 
For example, according to an April 2010 program management review, 
USCIS planned to provide the solutions architect with two technical 
environments to conduct production and testing activities by December 
2010.[Footnote 31] However, USCIS has since revised the schedule due 
to challenges in procuring hardware and software needed before these 
two environments were ready for the solutions architect. 

Based on the revised schedule, delivery of the technical environments 
was delayed to April 2011, according to USCIS, so that OIT could take 
actions to address the delay, such as borrowing equipment until a 
contract protest was resolved, and providing the solutions architect 
with a walk-through of the technical environments to ensure it met 
their needs. Program officials stated that factors outside their 
control, such as contract protests or review and approval of system 
requirements, have contributed to challenges in implementing the 
schedules.[Footnote 32] According to program officials, defining and 
developing requirements was expected to last about 2 ½ to 3 months. 
However, USCIS completed the requirements in 9 months, which included 
review and validation of these requirements by agency leadership. 
Program officials stated that detailed reviews and approval by agency 
leadership took longer than expected. 

Best practices in schedule estimating state that a comprehensive 
schedule should include a schedule risk analysis, so that the risk to 
the estimate if items are delayed can be modeled and presented to 
management including, among others, assumptions on equipment 
deliveries or length of internal and external reviews. However, 
according to a January 2011 program management review, as changes to 
the program were happening rapidly, there was no analysis completed to 
determine the impact on the schedule. 

In addition to the challenges USCIS has encountered in carrying out 
the schedules as originally planned, on the basis of our analysis we 
found that the current schedules for the first release of the 
Transformation Program are of questionable reliability. Best practices 
state that the success of a large-scale system acquisition program, 
such as the Transformation Program, depends in part on having reliable 
schedules that identify: 

* when the program's set of work activities and milestone events will 
occur; 

* how long they will take; and: 

* how they are related to one another. 

Among other things, reliable schedules provide a road map for 
systematic execution of a program and the means by which to gauge 
progress, identify and address potential problems, and promote 
accountability. Our research has identified nine best practices 
associated with developing and maintaining a reliable 
schedule.[Footnote 33] To be considered reliable, a schedule should 
meet all nine practices. In a July 2008 memorandum, DHS's Under 
Secretary for Management endorsed the use of these scheduling 
practices and noted that DHS would be using them. The nine scheduling 
best practices are summarized in table 5. 

Table 5: Description of GAO Scheduling Best Practices: 

Characteristic: Capturing all activities; 
Description: The schedule should reflect all activities (steps, 
events, outcomes, etc.) as defined in the program's work breakdown 
structure, to include activities to be performed by both the 
government and its contractors. 

Characteristic: Sequencing all activities; 
Description: The schedule should be planned so that critical project 
dates can be met. To meet this objective, activities need to be 
logically sequenced--that is, listed in the order in which they are to 
be carried out. In particular, activities that must be completed 
before other activities can begin (predecessor activities), as well as 
activities that cannot begin until other activities are completed 
(successor activities), should be identified. This helps ensure that 
interdependencies among activities that collectively lead to the 
accomplishment of events or milestones can be established and used as 
a basis for guiding work and measuring progress. 

Characteristic: Assigning resources to all activities; 
Description: The schedule should reflect what resources (e.g., labor, 
materials, and overhead) are needed to do the work, whether all 
required resources will be available when needed, and whether any 
funding or time constraints exist. 

Characteristic: Establishing duration of all activities; 
Description: The schedule should reflect how long each activity will 
take to execute. In determining the duration of each activity, the 
same rationale, data, and assumptions used for cost estimating should 
be used. Durations should be as short as possible and have specific 
start and end dates. Excessively long periods needed to execute an 
activity should prompt further decomposition of the activity so that 
shorter execution durations will result. 

Characteristic: Integrating schedule activities horizontally and 
vertically; 
Description: The schedule should be horizontally integrated, meaning 
that it should link products and outcomes associated with other 
sequenced activities. These links are commonly referred to as 
"handoffs" and serve to verify that activities are arranged in the 
right order to achieve aggregated products or outcomes. The schedule 
should also be vertically integrated, meaning that traceability exists 
among varying levels of activities and supporting tasks and subtasks. 
Such mapping or alignment among levels enables different groups to 
work to the same master schedule. 

Characteristic: Establishing a critical path; 
Description: Scheduling software should be used to identify the 
critical path, which represents the longest total duration through the 
sequenced list of activities. Establishing a project's critical path 
is necessary to examine the effects of any activity slipping along 
this path. Potential problems along or near the critical path should 
also be identified and reflected in scheduling the duration of high-
risk activities. 

Characteristic: Identifying float between activities; 
Description: The schedule should identify the float--the amount of 
time by which a predecessor activity can slip before the delay affects 
successor activities--so that a schedule's flexibility can be 
determined. As a general rule, activities along the critical path have 
the least float. 

Characteristic: Conducting a schedule risk analysis; 
Description: A schedule risk analysis should be performed using 
statistical techniques to predict the level of confidence in meeting a 
project's completion date. This analysis focuses not only on critical 
path activities but also on activities near the critical path, since 
they can affect the project's status. 

Characteristic: Updating the schedule using logic and durations to 
determine dates; 
Description: The schedule should be continuously updated using logic 
and durations to determine realistic start and completion dates for 
program activities. The schedule should be analyzed continuously for 
variances to determine when forecasted completion dates differ from 
planned dates. 

Source: GAO. 

[End of table] 

The Transformation Program has 18 individual schedules. Table 6 
summarizes the findings of our assessments of two of these individual 
schedules as of November 2010 representing the bulk of the 
Transformation Program efforts and those most critical to the 
production of USCIS ELIS. Specifically, these schedules track 
activities associated with USCIS's OIT and the solutions architect. 
TPO is responsible for managing key acquisition functions associated 
with the Transformation Program; thus, USCIS is responsible for 
tracking and oversight of the OIT and solutions architect's activities 
and associated schedules. Appendix I includes a detailed discussion of 
our analysis. 

Table 6: Transformation Program Schedules' Satisfaction of Schedule 
Estimating Best Practices: 

Best practice: 1. Capturing all activities; 
GAO assessment of USCIS approved OIT schedule: Minimally met; 
GAO assessment of USCIS approved solutions architect schedule: 
Partially met. 

Best practice: 2. Sequencing all activities; 
GAO assessment of USCIS approved OIT schedule: Minimally met; 
GAO assessment of USCIS approved solutions architect schedule: 
Minimally met. 

Best practice: 3. Assigning resources to all activities; 
GAO assessment of USCIS approved OIT schedule: Minimally met; 
GAO assessment of USCIS approved solutions architect schedule: 
Minimally met. 

Best practice: 4. Establishing the duration of all activities; 
GAO assessment of USCIS approved OIT schedule: Partially met; 
GAO assessment of USCIS approved solutions architect schedule: 
Substantially met. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
GAO assessment of USCIS approved OIT schedule: Partially met; 
GAO assessment of USCIS approved solutions architect schedule: 
Partially met. 

Best practice: 6. Establishing the critical path for all activities; 
GAO assessment of USCIS approved OIT schedule: Not met; 
GAO assessment of USCIS approved solutions architect schedule: Not met. 

Best practice: 7. Identifying float between activities; 
GAO assessment of USCIS approved OIT schedule: Minimally met; 
GAO assessment of USCIS approved solutions architect schedule: 
Minimally met. 

Best practice: 8. Conducting a schedule risk analysis; 
GAO assessment of USCIS approved OIT schedule: Minimally met; 
GAO assessment of USCIS approved solutions architect schedule: 
Minimally met. 

Best practice: 9. Updating the schedule using logic and durations to 
determine dates; 
GAO assessment of USCIS approved OIT schedule: Minimally met; 
GAO assessment of USCIS approved solutions architect schedule: 
Minimally met. 

Source: GAO analysis of USCIS data and information. 

Note: "Not met" means the program provided no evidence that satisfies 
any of the criterion. "Minimally met" means the program provided 
evidence that satisfies a small portion of the criterion. "Partially 
met" means the program provided evidence that satisfies about half of 
the criterion. "Substantially met" means the program provided evidence 
that satisfies a large portion of the criterion. "Fully met" means the 
program provided evidence that completely satisfies the criterion. 

[End of table] 

As shown above, the two Transformation Program schedules, for the most 
part, did not substantially or fully meet the nine best practices. For 
example, neither the OIT nor the USCIS-approved solutions architect 
schedule contained detailed information for Release A activities 
beyond March 2011. In addition, both schedules were missing a 
significant number of logic links between activities which indicate 
activities that must finish before others and which activities may not 
begin until others have been completed.[Footnote 34] While we cannot 
generalize these findings to all 18 schedules, our review raises 
questions about the reliability of the program's schedules. 

Based on our discussions with the Transformation Program's lead 
program scheduler, this condition stems, in part, from the 
"aggressiveness of the Transformation Program to implement most of the 
capabilities within the first 3 years of the program," and a lack of 
program management resources for developing knowledge to create and 
maintain schedules. Moreover, and regardless of the aggressiveness of 
the solution, our best practices call for schedules to reflect all 
activities--government, contractors, and any other necessary external 
parties--essential for successful program completion. As such, neither 
of the Transformation Program schedules we reviewed substantially met 
this practice. Furthermore, as demonstrated in the challenges USCIS 
has encountered in carrying out the schedule as originally planned, 
not including all work for all deliverables, regardless of whether the 
deliverables are the responsibility of the government or contractor, 
may result in confusion among team members and lead to management 
difficulties because of an incomplete understanding of the plan and of 
the progress being made. 

Collectively, and moving forward, not meeting the nine key practices 
increases the risk of schedule slippages and related cost overruns and 
makes meaningful measurement and oversight of program status and 
progress, as well as accountability for results, difficult to achieve. 
For example, in June 2011, a program management review noted a 
schedule risk if the development, testing, and deployment process slip 
again. This could result in USCIS being unable to deliver the first 
release in December 2011. A schedule risk analysis could be used to 
determine the level of uncertainty and to help mitigate this risk. 
Similarly, capturing and sequencing all activities, as outlined in 
best practices, could help identify the extent to which other 
activities linked to this schedule risk are affecting its progress. 
Furthermore, without the development of a schedule that meets 
scheduling best practices, it will be difficult for USCIS to 
effectively monitor and oversee the progress of an estimated $1.7 
billion to be invested in the acquisition of USCIS ELIS. 

In August 2011, TPO provided us the updated USCIS-approved solutions 
architect schedule. Program officials indicated that this updated 
schedule addressed some areas in which their previous schedule was 
deficient according to our assessment of the nine scheduling best 
practices. For example, they said that this schedule included 
activities through December 2011 rather than only through March 2011. 
In addition, officials indicated that they have confidence in meeting 
the December 2011 milestone. Specifically, they said that USCIS and 
the solutions architect have tested over 70 percent of the Release A 
capabilities that are to be released in December 2011, and 
demonstrated these capabilities to the USCIS leadership team in August 
2011. On the basis of our analysis of the updated USCIS-approved 
solutions architect schedule, we determined that the updated schedule 
did not address many of the deficiencies we identified in the earlier 
version of the schedule. For example, the USCIS-approved solutions 
architect schedule did contain activities through December 2011, but 
logical links were missing between activities indicating which 
activities must finish before others and which activities may not 
begin until others have been completed.[Footnote 35] The schedule's 
authorized work has therefore not been established in a way that 
describes the sequence of work, which prevents the schedule from 
meeting other best practices, such as establishing a critical path or 
developing a schedule risk analysis. Thus, the updated USCIS-approved 
solutions architect schedule does not fully meet all nine key 
practices, making meaningful measure and oversight of program status 
and progress difficult to achieve. USCIS did not provide us with an 
updated OIT schedule; therefore, we were unable to determine to what 
extent many of the deficiencies we identified in the earlier versions 
were addressed. 

Further, USCIS established the Transformation Program as a long-term 
program made up of five releases to procure, test, deploy, and 
maintain USCIS ELIS, but USCIS officials confirmed in October 2010 
that there was no integrated master schedule for the entire 
Transformation Program. In addition, the schedules we received in 
August 2011 were also not integrated into a master schedule. According 
to best practices, an integrated master schedule is to contain the 
detailed tasks necessary to ensure program execution and is a required 
document to develop key acquisition planning documents under DHS 
acquisition management guidance.[Footnote 36] Among other things, best 
practices and related federal guidance call for a program schedule to 
be programwide in scope, meaning that it should include the integrated 
breakdown of the work to be performed by both the government and its 
contractors over the expected life of the program.[Footnote 37] 
According to program officials, when the Transformation Program's 
planning efforts began, USCIS was unable to develop an integrated 
master schedule for the Transformation Program due to the complexity 
of integrating the numerous individual schedules and the lack of 
skilled staff necessary to develop and manage such an integrated 
master schedule. In addition, program officials explained that 
scheduling software to develop and maintain individual schedules was 
not used by every organization performing transformation work, such as 
OIT, even though the program issued guidance in August 2010 to all 
organizations on scheduling best practices, including the use of 
scheduling software. 

As an alternative to an integrated master schedule and for ease of 
reporting to the ARB and other senior officials, TPO developed a high- 
level tracking tool summarizing dates and activities for the first 
release of the program and based on individual schedules such as the 
OIT and solutions architect schedule, which are not directly managed 
by TPO.[Footnote 38] According to program officials, in a September 
2010 briefing to agency leadership, this high-level tracking tool 
created capacity for USCIS to analyze the schedule. In this briefing, 
program officials stated TPO used the high-level tracking tool to 
ensure coordination and alignment of activities by collaborating with 
staff responsible for the management of individual schedules. However, 
this tracking tool is not an integrated master schedule as it does not 
integrate all activities necessary to meet the milestones for Release 
A; rather, it is a selection of key activities drawn from the 
individual schedules maintained by USCIS components and the solutions 
architect. Moreover, the Transformation Program Manager expressed 
concern in a May 2011 program management review that the information 
reported in the high-level tracking tool was not being reported in the 
individual schedules. In addition, this tracking tool is not an 
integrated master schedule because it does not show activities over 
the life of the program. That is, there are no dates or activities for 
when the other four releases' set of work activities will occur, how 
long they will take, and how they are related to one another. As a 
result, it will be difficult for program officials to predict, with 
any degree of confidence, how long it will take to complete all five 
releases of the Transformation Program. It will also be difficult for 
program officials to manage and measure progress in executing the work 
needed to deliver the program, thus increasing the risk of cost, 
schedule, and performance shortfalls. Lastly, USCIS's ability to 
accurately communicate the status of Transformation Program efforts to 
key stakeholders such as its employees, Congress and the public will 
be hindered. 

Unreliable Schedules Affect USCIS's Ability to Develop Reliable Life- 
Cycle Cost Estimates: 

Because USCIS lacks reliable schedules, its ability to develop 
reliable life-cycle cost estimates is hampered. As outlined by DHS 
acquisition management guidance, a life-cycle cost estimate is a 
required and critical element in the acquisition process. USCIS has 
developed and updated the life-cycle cost estimate for the 
Transformation Program, but USCIS's individual schedules for the 
Transformation Program do not meet best practices for schedule 
estimating, thus raising questions about the credibility of the 
program's life-cycle cost estimates. For example, neither the OIT nor 
the solutions architect schedule fully captured all activities to be 
performed by the government and contractor. Therefore, when USCIS is 
developing the life-cycle cost estimate there is an incomplete 
understanding of the work necessary to accomplish the five releases of 
the Transformation Program. Further, in the case of both individual 
schedules, the absence of a schedule risk analysis makes it difficult 
for officials to account for the cost effects of schedule slippage 
when developing the life-cycle cost estimate. Further, a reliable life-
cycle cost estimate is essential for helping the program determine how 
much funding is needed and whether it will be available to achieve the 
Transformation Program's goals. 

Best practices that we have previously identified for cost estimation 
state that because some program costs such as labor, supervision, 
rented equipment, and facilities cost more if the program takes 
longer, a reliable schedule can contribute to an understanding of the 
cost impact if the program does not finish on time.[Footnote 39] 
Meeting planned milestones and controlling costs are both dependent on 
the quality of a program's schedule. An integrated schedule is key to 
managing program performance and is necessary for determining what 
work remains and the expected cost to complete the work. 

Conclusions: 

USCIS's effort to develop a modern, automated system for processing 
benefit applications and addressing the many current program 
inefficiencies has been in progress for nearly 6 years. The program is 
now more than 2 years behind its planned deployment schedule for 
implementing the agencywide transformed business process, and given 
the enormity, significance, and complexity of this transformation, it 
is essential that USCIS ensures it takes the proper steps for 
implementation. Although only one benefit type is expected to be 
available for online account management and adjudication in December 
2011, the decision to channel resources and efforts to focus on 
ensuring the core businesses are ready for a December 2011 launch 
prior to making other application types available for online-
processing appears to be prudent. 

Moving forward, it is essential that USCIS consistently follows DHS 
acquisition management guidance to best position the department to 
develop and share information within the department and with Congress 
and the public that can be relied upon for purposes of informed 
decision making. Moreover, ensuring that the program's schedules are 
consistent with schedule estimating best practices and integrated 
through an integrated master schedule would better position USCIS to 
reliably estimate the amount of time and effort needed to complete the 
program. Reliable schedules could also assist USCIS in developing and 
maintaining a complete and reliable life-cycle cost estimate for the 
program which is essential for helping the program determine how much 
funding is needed and whether it will be available to achieve the 
Transformation Program's goals. 

Recommendations for Executive Action: 

To help ensure that USCIS takes a comprehensive and cost-effective 
approach to the development and deployment of transformation efforts 
to meet the agency's goals of improved adjudications and customer 
services processes, we recommend that the Director of USCIS take the 
following three actions: 

1. Ensure program schedules are consistent with the nine estimating 
best practices. 

2. Develop and maintain an Integrated Master Schedule consistent with 
these same best practices for the Transformation Program. 

3. Ensure that the life-cycle cost estimate is informed by milestones 
and associated tasks from reliable schedules that are developed in 
accordance with the nine best practices we identified. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to DHS for comment. DHS provided 
written comments, which are reprinted in Appendix II. In commenting on 
this report, DHS, including USCIS, concurred with the recommendations. 

DHS's letter outlined the actions that USCIS is taking action or has 
taken to address each recommendation. Regarding the first 
recommendation to ensure program schedules are consistent with best 
practices, DHS stated that USCIS is incorporating the nine schedule 
estimating best practices we identified into Transformation Program 
management reviews, as well as the Acquisition Review Board review. 
Regarding the second recommendation to develop and maintain an 
Integrated Master Schedule consistent with these same best practices 
for the Transformation Program, DHS stated that USCIS will develop an 
Integrated Master Schedule to depict the multiple tasks, 
implementation activities, and interrelationships needed to 
successfully develop and deploy the Transformation Program. Regarding 
the third recommendation to ensure that life-cycle cost estimates are 
developed in accordance with the nine best practices, DHS stated that 
they will refine the Transformation Program life-cycle cost estimate 
in accordance with GAO's 12-Step Process for Cost Estimation. In 
addition, DHS noted that their revised master schedule will clearly 
identify work elements to ensure a reasonable and cost-effective 
timeframe for accomplishing the five releases associated with the 
program. If fully implemented, we believe that the actions that DHS 
identified will address our recommendations. 

DHS also provided technical comments, which we have incorporated, as 
appropriate. 

We are sending copies of this report to the Secretary of Homeland 
Security and other interested parties. The report also will be 
available at no charge on the GAO Web site at [hyperlink, 
http://www.gao.gov]. 

If you or your staff members have any questions about this report, 
please contact me at (202) 512-8777 or stanar@gao.gov. Contact points 
for our Offices of Congressional Relations and Public Affairs may be 
found on the last page of this report. GAO staff who made major 
contributions to this report are listed in appendix III. 

Sincerely, 

Richard M. Stana: 
Director, Homeland Security and Justice Issues: 

List of Requesters: 

The Honorable Joseph I. Lieberman:
Chairman:
Committee on Homeland Security and Governmental Affairs:
United States Senate: 

The Honorable Charles Grassley:
Ranking Member:
Committee on the Judiciary:
United States Senate: 

The Honorable Charles E. Schumer:
Chairman:
Subcommittee on Immigration, Refugees and Border Security:
Committee on the Judiciary:
United States Senate: 

The Honorable John Conyers, Jr.
Ranking Member:
Committee on the Judiciary:
House of Representatives: 

The Honorable Zoe Lofgren:
Ranking Member:
Subcommittee on Immigration Policy and Enforcement:
Committee on the Judiciary:
House of Representatives: 

[End of section] 

Appendix I: Detailed Results of GAO Assessment of USCIS's Detailed 
Transformation Program Schedules: 

In prior work, we have identified nine best practices associated with 
effective schedule estimating.[Footnote 40] These are (1) capturing 
all activities; (2) sequencing all activities; (3) assigning resources 
to all activities; (4) establishing the duration of all activities; 
(5) integrating activities horizontally and vertically; (6) 
establishing the critical path for all activities; (7) identifying 
float time between activities; (8) conducting a schedule risk 
analysis; and (9) updating the schedule using logic and durations. We 
assessed the extent to which two detailed schedules, Office of 
Information Technology (OIT) and the solutions architect, dated 
November 2010, met each of the nine practices. We characterized 
whether the schedules met each of the nine best practices as follows: 

* Not met--the program provided no evidence that satisfies any portion 
of the criterion. 

* Minimally met--the program provided evidence that satisfies less 
than one-half of the criterion. 

* Partially met--the program provided evidence that satisfies about 
one-half of the criterion. 

* Substantially met--the program provided evidence that satisfies more 
than one-half of the criterion. 

* Met--the program provided evidence that satisfies the entire 
criterion. 

Tables 7 and 8 provide the detailed results of our analysis of these 
schedules. 

Table 7: Detailed Results of Transformation Program's OIT Schedule 
Satisfaction of Scheduling Best Practices: 

Best practice: 1. Capturing all activities; 
Explanation: The schedule should reflect all activities as defined in 
the project's work breakdown structure, which defines in detail the 
work necessary to accomplish a project's objectives, including 
activities to be performed by the government; 
Criterion met (November 2010): Minimally met; 
GAO analysis: The schedule only reflects government effort for the 
completion of Release A. Because the OIT program schedule does not 
account for all planned government work for the five phases of the 
program to be fully deployed by 2014, program officials are not able 
to reliably estimate planned finish dates beyond the schedule's 
current end date of April 20, 2012. Moreover, the schedule does not 
include a standardized Work Breakdown Structure (WBS). The WBS should 
be the basis of all project schedules. Aligning the schedule to the 
program WBS will ensure that the total scope of work is accounted for 
within the schedule. These shortcomings in this best practice will 
have cascading effects on the remaining best practices. Unless all 
activities are accounted for, it is uncertain whether all activities 
are properly sequenced, resources are properly assigned, the critical 
path is valid, or a Schedule Risk Analysis (SRA) accounts for all 
risk. If the schedule does not fully and accurately reflect the 
project, it will not serve as an appropriate basis for analysis and 
may result in unreliable completion dates, time extension requests, 
and delays. 

Best practice: 2. Sequencing all activities; 
Explanation: The schedule should be planned so that critical project 
dates can be met. To meet this objective, activities need to be 
logically sequenced--that is, listed in the order in which they are to 
be carried out. In particular, activities that must be completed 
before other activities can begin (predecessor activities), as well as 
activities that cannot begin until other activities are completed 
(successor activities), should be identified. This helps ensure that 
interdependencies among activities that collectively lead to the 
accomplishment of events or milestones can be established and used as 
a basis for guiding work and measuring progress; 
Criterion met (November 2010): Minimally met; 
GAO analysis: Our analysis of the OIT program schedule shows that 377 
of the remaining 618 activities (or 61 percent) have missing 
predecessor or successor logic. The detailed planning period leading 
up to System Definition Review (SDR) shows 233 of the remaining 317 
activities (74 percent) have missing predecessor or successor logic. 
Missing predecessors or successors reduce the credibility of the 
calculated dates. If an activity that has no logical successor slips, 
the schedule will not reflect the effect on the critical path, float, 
or scheduled start dates of downstream activities. We also found 293 
activities with Start No Earlier Than (SNET) constraints. These are 
considered "soft" date constraints in that they allow the activity to 
slip into the future based on what happens to their predecessor 
activities. However, while activities may be soft constrained, for 
example, to represent receipt of delivery of equipment, in general 
constraining an activity's start date prevents managers from 
accomplishing work as soon as possible and consumes flexibility in the 
project. 

Best practice: 3. Assigning resources to all activities; 
Explanation: The schedule should reflect what resources (e.g., labor, 
materials, and overhead) are needed to do the work, whether all 
required resources will be available when needed, and whether any 
funding or time constraints exist; 
Criterion met (November 2010): Minimally met; 
GAO analysis: According to program officials, resources are not 
assigned to activities in the schedule. In lieu of putting resources 
in the schedule, program officials said they perform a full-time 
equivalents (FTE) projection where they work with each division and 
ask them to estimate the number of FTEs. However, assigning resources 
to activities in the schedule ensures that resources are used to 
determine activity durations because resource requirements may 
directly relate to the duration of an activity. Furthermore, if the 
current schedule does not allow for insight into current or projected 
over-allocation of resources, then the risk of the program slipping is 
significantly increased. 

Best practice: 4. Establishing the duration of all activities; 
Explanation: The schedule should realistically reflect how long each 
activity will take to execute. In determining the duration of each 
activity, the same rationale, data, and assumptions used for cost 
estimating should be used. Durations should be as short as possible 
and have specific start and end dates. Excessively long periods needed 
to execute an activity should prompt further decomposition of the 
activity so that shorter execution durations will result; 
Criterion met (November 2010): Partially met; 
GAO analysis: The majority of remaining activities in the schedule 
meet best practices for durations; however, leading up to SDR, we 
found that majority of the remaining activities did not meet best 
practices for durations 44 days or less. This does not support program 
officials' statement that activities leading up to SDR are detail 
planned and with durations of 44 days or less. 

Best practice: 5 Integrating schedule activities horizontally and 
vertically; 
Explanation: The schedule should be horizontally integrated, meaning 
that it should link products and outcomes associated with other 
sequenced activities. These links are commonly referred to as 
"handoffs" and serve to verify that activities are arranged in the 
right order to achieve aggregated products or outcomes. The schedule 
should also be vertically integrated, meaning that the dates for 
starting and completing activities in the integrated master schedule 
should be aligned with the dates for supporting tasks and subtasks. 
Such mapping or alignment among levels enables different groups to 
work to the same master schedule; 
Criterion met (November 2010): Partially met; 
GAO analysis: Vertical integration is partially demonstrated in the 
schedule. While we were able to trace some activities between the OIT 
and USCIS high-level schedules, the program's WBS numbers did not 
match. In addition, the name and WBS numbers for the SDR activity, 
which is a critical milestone necessary for detail planning to 
continue, is also not consistent across the OIT, contractor and USCIS 
high-level master schedules. Without a standardized WBS, identifying 
activities across different schedules is hampered, if not impossible. 
Issues with missing dependencies, activities with dangling logic, and 
overuse of date constraints prevent the schedule from fully complying 
with the requirement of horizontal integration--that is, the overall 
ability of the schedule to depict relationships between different 
program elements and product handoffs. 

Best practice: 6. Establishing the critical path for all activities; 
Explanation: Scheduling software should be used to identify the 
critical path, which represents the chain of dependent activities with 
the longest total duration. Establishing a project's critical path is 
necessary to examine the effects of any activity slipping along this 
path. Potential problems along or near the critical path should also 
be identified and reflected in scheduling the duration of high-risk 
activities; 
Criterion met (November 2010): Not met; 
GAO analysis: Our analysis could not determine a valid critical path 
within the schedule, particularly because over 61 percent of remaining 
activities have missing or incomplete logic. Unless all activities are 
included and properly linked, it is not possible to generate a true 
critical path. Program Management Office officials acknowledged that a 
critical path cannot be calculated within the schedule. 

Best practice: 7. Identifying reasonable float between activities; 
Explanation: The schedule should identify the float--the amount of 
time by which a predecessor activity can slip before the delay affects 
successor activities--so that a schedule's flexibility can be 
determined. As a general rule, activities along the critical path have 
the least float; 
Criterion met (November 2010): Minimally met; 
GAO analysis: Our analysis found that float calculations within the 
OIT schedule are not reliable because of missing logic links and the 
high number of date constraints. In addition, because the schedule is 
missing dependencies, float estimates will be miscalculated since 
float is directly related to the logical sequencing of events. Because 
the critical path is directly related to the amount of float in the 
schedule, excessive float will cause an invalid critical path. 

Best practice: 8. Conducting a schedule risk analysis; 
Explanation: A schedule risk analysis should be performed using 
statistical techniques to predict the level of confidence in meeting a 
project's completion date. This analysis focuses not only on critical 
path activities but also on activities near the critical path, since 
they can affect the project's status; 
Criterion met (November 2010): Minimally met; 
GAO analysis: The agency has not performed a schedule risk analysis on 
the schedule. However, program officials provided risk management 
documentation that identified the list of top risks, their impacts, 
probability of occurrence, mitigation strategy and actions, and risk 
status. It appears that USCIS is managing risk, but these program 
management reviews do not provide management with the necessary 
program information to determine if the program will meet its planned 
completion date. Moreover, before a schedule risk analysis can be 
performed and produce realistic results, the agency must fix the 
missing dependencies, remove the date constraints, break down the long 
durations and examine and address unrealistic float values. 

Best practice: 9. Updating the schedule using logic and durations to 
determine dates; 
Explanation: The schedule should be continuously updated using logic 
and durations to determine realistic start and completion dates for 
program activities. The schedule should be analyzed continuously for 
variances to determine when forecasted completion dates differ from 
planned dates; 
Criterion met (November 2010): Minimally met; 
GAO analysis: Our analysis shows that the schedule does not have a 
valid status date. Both the initial and updated schedules provided by 
the program office showed a status date of July 5, 2011, which was 
more than 7 months in the future relative to our November 2010 
analysis. A status date denotes the date of the latest update to the 
schedule and thus defines the point in time at which completed work 
and remaining work are calculated. As a result of this incorrect 
status date, we found several activities in the schedule that should 
have started in the past with no actual start dates and several 
activities that should have finished in the past with no actual finish 
dates. As a best practice, maintaining the integrity of the schedule 
logic is not only necessary to reflect true status, but is also 
required before conducting a schedule risk analysis. 

Source: GAO analysis of USCIS data. 

[End of table] 

Table 8: Detailed Results of Transformation Program's Contractor 
Schedule Satisfaction of Scheduling Best Practices: 

Best practice: 1. Capturing all activities; 
Explanation: The schedule should reflect all activities as defined in 
the project's work breakdown structure, which defines in detail the 
work necessary to accomplish a project's objectives, including 
activities to be performed by both the owner and contractors; 
Criterion met (November 2010): Partially met; 
GAO analysis: The contractor's schedule accounts for key activities to 
be performed by the government and contractor across all five phases, 
but officials stated that work beyond SDR is not sufficiently planned 
because they were not authorized to do so by the government. Without 
an IMS that accounts for all planned effort, management is not able to 
reliably estimate planned dates beyond the current schedule's end date 
of August 8, 2014. In addition, activities in the schedule are not 
aligned with government master schedules via a work breakdown 
structure (WBS). Because the contractor activities are not aligned to 
a program WBS we cannot be certain that the schedule captures the work 
necessary to accomplish the program's objectives. 

Best practice: 2. Sequencing all activities; 
Explanation: The schedule should be planned so that critical project 
dates can be met. To meet this objective, activities need to be 
logically sequenced--that is, listed in the order in which they are to 
be carried out. In particular, activities that must be completed 
before other activities can begin (predecessor activities), as well as 
activities that cannot begin until other activities are completed 
(successor activities), should be identified. This helps ensure that 
interdependencies among activities that collectively lead to the 
accomplishment of events or milestones can be established and used as 
a basis for guiding work and measuring progress; 
Criterion met (November 2010): Minimally met; 
GAO analysis: Specifically, 2,812 of the 7,053 activities (40 percent) 
have missing logic. The detailed planning period leading up to SDR 
shows 587 (38 percent) of the 1,561 remaining activities have missing 
logic. The high number of activities with missing logic is cause for 
concern because missing predecessors or successors links reduce the 
credibility of the calculated dates. We also found 935 activities (13 
percent) with Start No Earlier Than (SNET) constraints, including 251 
activities (16 percent) with SNET constraints within the detail 
planning period. SNET constraints are considered "soft" date 
constraints in that they allow the activity to slip into the future 
based on what happens to their predecessor activities. However, while 
activities may be soft constrained, for example, to represent receipt 
of delivery of equipment, in general constraining an activity's start 
date prevents managers from accomplishing work as soon as possible and 
consumes flexibility in the project. The schedule includes 1,284 
activities (18 percent) that are linked to their successor activities 
with lags, including 498 negative lags. The detail planning period 
leading up to SDR shows 190 activities (12 percent), including 51 
negative lags. Lags are often used to put activities on a specific 
date or to insert a buffer for risk; negative lags predict when the 
successor activity will start prior to the finish of its predecessor; 
however, these lags persist even when predecessor activities are 
delayed (that is, when the buffer should be consumed). Lags should be 
justified because they cannot have risk or uncertainty. There are also 
221 activities (3 percent) in the schedule that have dangling logic. 
Of these, 82 activities are missing logic that would determine their 
start dates and 139 are missing a successor from their finish dates. 
The detail planning period leading up to SDR shows 51 activities with 
dangling logic, of which 22 are missing logic that would determine 
their start and 29 are missing a successor from their finish date. 
Regarding activities with dangling logic, activities missing 
predecessors to their start date would have to start earlier in order 
to finish on time if they ran longer than their planned durations; 
and activities missing successors from their finish date could 
continue indefinitely and not affect the start or finish dates of 
future activities. 

Best practice: 3. Assigning resources to all activities; 
Explanation: The schedule should reflect what resources (e.g., labor, 
materials, and overhead) are needed to do the work, whether all 
required resources will be available when needed, and whether any 
funding or time constraints exist; 
Criterion met (November 2010): Minimally met; 
GAO analysis: The schedule does not directly assign resources needed 
to complete the captured activities. Instead, the contractor's 
resource data are maintained separately as part of its Earned Value 
Management (EVM) system. According to program and contract 
representatives, the contractor manages resources through detailed EVM 
reporting on a monthly basis. Program officials agreed to provide 
documentation showing that the contractor has associated control 
accounts with schedule activity codes. However, the documentation we 
received did not show the mapping between control accounts and 
schedule activities. Without this information, we were unable to 
reconcile the resource information in the EVM system with activities 
planned in the schedule. 

Best practice: 4. Establishing the duration of all activities; 
Explanation: The schedule should realistically reflect how long each 
activity will take to execute. In determining the duration of each 
activity, the same rationale, historical data, and assumptions used 
for cost estimating should be used. Durations should be as short as 
possible and have specific start and end dates. Excessively long 
periods needed to execute an activity should prompt further 
decomposition of the activity so that shorter execution durations will 
result; 
Criterion met (November 2010): Substantially met; 
GAO analysis: The durations of the majority of remaining activities 
(82 percent) met best practices for durations, being less than 44 days 
(or 2 working months). In addition, the majority of the long-duration 
activities (462 activities or 7 percent), that is, activities longer 
than 100 days, occur after SDR in the nondetail planning period. 
Program officials stated that all activities prior to SDR are detail 
planned and that long duration activities are level of effort (LOE) 
activities. However, many of these long duration activities are 
included in schedules to represent effort that has no measurable 
output and cannot be associated with any one single product. We also 
found 150 remaining activities that are scheduled to start on a 
Saturday or Sunday. Officials stated these activities are related to 
the start and finish dates of specific contract periods; 
however, we found that only 14 of the 150 activities were associated 
with a 7-day workweek calendar. 

Best practice: 5. Integrating schedule activities horizontally and 
vertically; 
Explanation: The schedule should be horizontally integrated, meaning 
that it should link products and outcomes associated with other 
sequenced activities. These links are commonly referred to as 
"handoffs" and serve to verify that activities are arranged in the 
right order to achieve aggregated products or outcomes. The schedule 
should also be vertically integrated, meaning that the dates for 
starting and completing activities in the integrated master schedule 
should be aligned with the dates for supporting tasks and subtasks. 
Such mapping or alignment among levels enables different groups to 
work to the same master schedule; 
Criterion met (November 2010): Partially met; 
GAO analysis: Our analysis determined that the schedule is not fully 
vertically integrated. While the schedule is vertically integrated 
within itself because low-level tasks and milestones are traceable to 
higher-level summary tasks, it does not roll up into an overall 
government integrated master schedule. In addition, and similar to the 
OIT schedule, the name and WBS numbers for the SDR activity, which is 
a critical milestone necessary for detail planning to continue, is 
also not consistent. Without a standardized WBS, identifying 
activities across different schedules is hampered, if not impossible. 
The schedule is also not fully horizontally integrated. The horizontal 
traceability is hampered due to the issues noted in Best Practice 2 
with incomplete logic and reliance on date constraints. Unless the 
schedule is fully horizontally integrated, the effects of slipped 
tasks on downstream work cannot be determined. Further, when schedules 
are not horizontally integrated, relationships between different 
program teams cannot be seen and product handoffs cannot be identified. 

Best practice: 6. Establishing the critical path for all activities; 
Explanation: Scheduling software should be used to identify the 
critical path, which represents the chain of dependent activities with 
the longest total duration. Establishing a project's critical path is 
necessary to examine the effects of any activity slipping along this 
path. Potential problems along or near the critical path should also 
be identified and reflected in scheduling the duration of high-risk 
activities; 
Criterion met (November 2010): Not met; 
GAO analysis: The schedule does not reflect a valid critical path for 
several reasons. First, the schedule does not include all logic links 
between activities. Second, there are excessive constraints, lags and 
open-ends in the schedule. Unless all activities are included and 
properly linked, it is not possible to generate a true critical path. 
Without clear insight into a critical path at the project level, 
management will not be able to monitor critical or near-critical 
detail activities that may have a detrimental impact on downstream 
activities if delayed. 

Best practice: 7. Identifying reasonable float between activities; 
Explanation: The schedule should identify the float--the amount of 
time by which a predecessor activity can slip before the delay affects 
successor activities--so that a schedule's flexibility can be 
determined. As a general rule, activities along the critical path have 
the least float; 
Criterion met (November 2010): Minimally met; 
GAO analysis: We found a relatively high number of remaining 
activities 1,282 (18 percent) with negative float ranging from -308 
days to -2 days. Negative float means that an activity must be 
completed ahead of schedule in order for the overall program to be on 
time. However, the float calculations within the contractor schedule 
are not reliable because of missing logic links and a high number of 
date constraints. In addition, because the critical path is directly 
related to the amount of float in the schedule, excessive float will 
cause an invalid critical path. 

Best practice: 8. Conducting a schedule risk analysis; 
Explanation: A schedule risk analysis should be performed using 
statistical techniques to predict the level of confidence in meeting a 
project's completion date. This analysis focuses not only on critical 
path activities but also on activities near the critical path, since 
they can affect the project's status; 
Criterion met (November 2010): Minimally met; 
GAO analysis: Based on documentation provided by program officials and 
contract representatives, we found that the contractor has not 
performed a schedule risk analysis. Program officials provided 
cumulative schedule variance data from their monthly EVM reports and a 
Risk Report, which identifies risk. However, these risks are not tied 
to activities in the schedule and therefore have no direct impact on 
the schedule's forecasted completion date. Moreover, before a schedule 
risk analysis can be credible, the program must have a quality 
schedule that reflects reliable logic and clearly identifies the 
critical path--conditions that the solutions architect schedule does 
not meet. 

Best practice: 9. Updating the schedule using logic and durations to 
determine dates; 
Explanation: The schedule should be continuously updated using logic 
and durations to determine realistic start and completion dates for 
program activities. The schedule should be analyzed continuously for 
variances to determine when forecasted completion dates differ from 
planned dates; 
Criterion met (November 2010): Minimally met; 
GAO analysis: Contractor and USCIS officials review the schedule 
during the weekly and monthly Program Management Reviews to discuss 
updates, identify critical work and ensure schedule coordination. In 
addition, the program schedule team, including contractor officials, 
provides weekly status updates to management. However, despite these 
status updates, data anomalies exist. For example, 107 tasks that 
should have started in the past have no actual start dates and 116 
tasks that should have finished in the past have no actual finish 
dates. As a best practice, the schedule should be continually 
monitored to determine when forecasted completion dates differ from 
the planned dates, which can be used to determine whether schedule 
variances will affect downstream work. Maintaining the integrity of 
the schedule logic is not only necessary to reflect true status, but 
is also required before conducting a schedule risk analysis. 

Source: GAO analysis of USCIS data. 

[End of table] 

Appendix II: Comments from the Department of Homeland Security: 

U.S. Department of Homeland Security: 
Washington, DC 20528: 

November 16, 2011: 

Richard Stana: 
Director, Homeland Security and Justice: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20548: 

Re: Draft Report GAO-12-66, "Immigration Benefits: Consistent 
Adherence to DHS's Acquisition Policy Could Help Improve 
Transformation Program Outcomes" 

Dear Mr. Stana: 

Thank you for the opportunity to review and comment on this draft 
report. The U.S. Department of Homeland Security (DHS) appreciates the 
U.S. Government Accountability Office's (GAO's) work in planning and 
conducting its review and issuing this report. 

The Department is pleased to note GAO's positive acknowledgment of the 
actions DHS has taken in establishing key institutional acquisition 
and Information Technology (IT) investment oversight controls and 
implementing them in major programs. The Department and The U.S. 
Citizenship and Immigration Services (USCIS) are committed to 
continuing efforts to instill more discipline and rigor in acquisition 
and IT processes. 

The draft report contained three recommendations directed at DHS with 
which the Department concurs. Specifically, GAO recommended that the 
Director of USCIS: 

Recommendation 1: Ensure program schedules are consistent with the 
nine estimating best practices. 

Response: Concur. USCIS is incorporating the nine schedule estimating 
best practices into Transformation Program management reviews, as well 
as the Acquisition Review Board process administered under Acquisition 
Management Directive 102-1, and will work with the Acquisition Program 
Management Division to ensure Directive 102-1 reflects focus in its
Directive 102-1 Instructions and Guideline documents. A more detailed 
management response describing specific implementation actions USCIS 
will take related to each of the nine best practices can be found in 
the attachment to this memorandum. 

The USCIS Transformation Program will also be transitioning the second 
release from a traditional waterfall software methodology (a classical 
linear and sequential approach of software design and systems 
development) to an agile development methodology (a parallel approach 
that emphasizes working in weekly or monthly cycles to quickly 
demonstrate working software). An agile process will allow USCIS to 
focus on delivering the highest business value in the shortest amount 
of time. The features and functions of the program will be identified 
and prioritized by the business, and the highest priorities developed 
first, enabling the program to produce a consumable solution on a 
regular basis and providing greater value to stakeholders. Beginning 
in Fiscal Year (FY) 2012, the program will incorporate the agile 
project management concepts using cross-functional teams to design, 
test, and implement the features and functions. A product-oriented 
work breakdown structure and schedule will be developed to (1) capture 
the necessary activities for each build, (2) allocate the necessary 
resources for each product, (3) establish a duration for each build or 
iteration, and (4) identify integration points throughout the process. 
By implementing the nine best practices and the agile project 
management concepts, the program will ensure consistent schedules. 

Recommendation 2: Develop and maintain an Integrated Master Schedule 
consistent with these same best practices for the Transformation 
program. 

Response: Concur. We agree that an Integrated Master Schedule (IMS) 
must be developed to depict the multiple tasks, implementation 
activities, and interrelationships needed to successfully develop and 
deploy the Transformation Program. USCIS will first validate the Work 
Breakdown Structure (WBS) as a basis for developing a schedule for 
reliable estimates of all program activities. To help ensure no 
extended activities exist that may cause slippage in the schedule,
USCIS will analyze and evaluate activities within the duration of the 
schedule, further defining more granular activities into a manageable 
timeframe, as necessary. 

Improvement in the WBS will correct IMS related deficiencies the GAO 
identified in the areas of: resource allocation, materials cost, 
overhead expenses, interdependencies, missing dependencies, and 
"handoffs." The result will be the Transformation Program's improved 
ability to meet planned milestones and control program costs. 

Successful completion of the program IMS will enable USCIS to adopt an 
industry standard tracking tool for purposes of integrating the 
numerous individual program schedules into a single IMS. This calendar-
based IMS will be used in program management reviews, Acquisition
Review Boards, and ad hoc meetings and will be capable of identifying 
required tasks to support program execution, support risk management 
activities, and identify the program's critical path. 

Modifying the IMS and using an industry-proven tracking tool will 
demonstrate relationships within activities creating dependencies and 
further identify and define required pre-requisite activities. IMS 
Report Generation will include the "forecasted" versus "actual" 
percentage complete in tracking the progress of each activity and 
associated performance measures.Periodic analysis of the program's 
progress will be performed using the IMS Report, alleviating potential 
risks while providing USCIS the ability to immediately mitigate risks 
observed "cradle-to-grave" across the total schedule and program. 

Recommendation 3: Ensure that the life-cycle cost estimate is informed 
by milestones and associated tasks from reliable schedules that are 
developed in accordance with the nine best practices identified. 

Response: Concur. A refined life-cycle cost estimate (LCCE) will 
evolve in accordance with GAO's 12-Step Process for Cost Estimation. 
Moreover, in relation to the LCCE, the improved IMS will clearly 
identify work elements contributing to the depiction of a reasonable 
and cost-effective timeframe for accomplishing the five releases 
associated with the program, through 2014 and beyond. Specifically: 

* The level of detail within the estimate will be consistent with the 
level of detail available for the five releases, and this relationship 
will be clear and included in the life cycle costs. 

* USCIS will utilize additional cost analysis resources offered at the 
Department level to assist with the estimation planning, which will 
include the IMS. 

* The LCCE will identify requirements, purpose; technical 
characteristics (including predecessor or similar systems), physical 
characteristics and parameters, relationships to other systems, 
development plan and schedule, acquisition strategy, operational plan, 
and risk (including technology implications). Moreover, USCIS will 
identify any technical, programmatic, or schedule changes that have 
taken place to date. 

* A clearly defined WBS will be developed to the appropriate level of 
detail, at minimum level 3.[Footnote 1] The WBS will be developed in a 
standard format for future use and easily aligned to cost analysis 
data. All changes to the WBS will be documented in real time, and a 
WBS dictionary will be developed. 

* All ground rules and assumptions will be documented and contain risk 
analysis, identification of possible budget constraints, program 
delays, program dependencies, and technology maturity. Moreover, 
approval authority will be identified in relation to each action and 
this will be vetted within the program as well as with the cost 
analyst at the Department level. 

* Historical actual cost, schedule, program, technical sources (i.e., 
past invoices related to the program as the basis of cost), and 
government personnel costs will additionally be used, and the data 
collection method and source will be identified. 

* Cost data will be segregated into nonrecurring and recurring costs, 
where applicable. 

* The cost estimating methodology will be documented to include the 
reports to be used on a recurring basis for analysis and statistical 
purposes. 

* If resources are available, a sensitivity analysis will be conducted 
and documented and all outcomes will be evaluated for the parameters 
most sensitive to change. 

* Risk analysis will be conducted, to include cost drivers (e.g., 
requirements, cost estimation errors, and uncertainty in business, 
technology, schedule, program, and software). 

* All information, sources, and approvals will be documented, 
evaluated for risk, and made available for review and reference, as 
appropriate, once finalized. 

USCIS is also committed to vetting its cost estimate documentation 
with the DHS Cost Analysis Division to demonstrate accuracy of source 
data and validity of the LCCE. 

Again, thank you for the opportunity to review and comment on this 
draft report. General, technical, and sensitivity comments were 
previously provided under separate cover. We look forward to working 
with you on future Homeland Security issues. 

Sincerely, 

Signed by: 

Jim H. Crumpacker: 
Director: 
Departmental GAO-OIG Liaison Office: 

[End of letter] 

DHS Detailed Management Response to GAO's Nine Schedule Estimating 
Best Practices: 

Best Practice: 1. Capturing all activities; 
Description: The schedule should reflect all activities (steps, 
events, outcomes, etc.) as defined in the program's work breakdown 
structure to include activities to be performed by  both the 
government and its contractors; 
Response: Extend the IMS to include the five phases of the program to 
full deployment by 2014. Develop and sequence program activities 
within the IMS via use of a Work Breakdown Structure; align the IMS to 
ensure total scope of program work is accounted for, resources are 
properly assigned, critical path is validated, and a Schedule Risk 
Analysis is documented. 

Best Practice: 2. Sequencing all activities; 
Description: The schedule should be planned so that critical project 
dates can be met. To meet this objective, activities need to be 
logically sequenced—-that is, listed in the order in which they are to 
be carried out. In particular, activities that must be completed 
before other activities can begin (predecessor activities), as well as 
activities that cannot begin until other activities are completed 
(successor activities), should be identified. This helps ensure that 
interdependencies among activities that collectively lead to the 
accomplishment of events or milestones can be established and used as 
a basis for guiding work and measuring progress; 
Response: Identify and reconcile interdependencies to avoid program 
slippage and improve credibility of schedule. 

Best Practice: 3. Assigning resources to all activities; 
Description: The schedule should reflect what resources (e.g., labor, 
materials, and overhead) are needed to do the work, whether all 
required resources will be available when needed, and whether any 
funding or time constraints exist; 
Response: Utilize project management tools to effectively plan and 
allocate resources calculating labor hours, cost of material, and 
other project related expenses. 
  
Best Practice: 4. Establishing the duration; 
Description: The schedule should reflect of all activities how long 
each activity will take to execute. In determining the duration of 
each activity, the same rationale, data, and assumptions used for cost 
estimating should be used. Durations should be as short as possible 
and have specific start and end dates. Excessively long periods needed 
to execute an activity should prompt further decomposition of the 
activity so that shorter execution durations will result; 
Response: Further the use of the WBS to analyze any potential 
prolonging in remaining activities by decomposing to make efficient 
execution durations. 

Best Practice: 5. Integrating schedule  activities horizontally and 
vertically; 
Description: The schedule should be horizontally integrated, meaning 
that it should link products and outcomes associated with other 
sequenced activities. These links are commonly referred to as 
"handoffs" and serve to verify that activities are arranged in the 
right order to achieve aggregated products or outcomes. The schedule 
should also be vertically integrated, meaning that traceability exists 
among varying levels of activities and supporting tasks and sub-tasks. 
Such mapping or alignment among levels enables different groups to 
work to the same master schedule; 
Response: Identify logical and vertical dependencies of tasks and 
subtasks, and integrate all other programs schedules for seamless 
transitioning. 

Best Practice: 6. Establishing the critical path for all activities; 
Description: Scheduling software should be used to identify the 
critical path, which represents the longest total duration through the 
sequenced list of activities. Establishing a project's critical path 
is necessary to examine the effects of any activity slipping along 
this path. Potential problems along or near the critical path should 
also be identified and reflected in scheduling the duration of high-
risk activities; 
Response: Adopt the use of a project scheduling tool to upload 
schedule dates for the purpose of identifying and resolving critical 
path issues. 

Best Practice: 7. Identifying reasonable float between activities; 
Description: The schedule should identify the float-—the amount of 
time by which a predecessor activity can slip before the delay affects 
successor activities—-so that a schedule's flexibility can be 
determined. As a general rule, activities along the critical path have 
the least float; 
Response: Adopt the use of a project scheduling tool to upload 
schedule dates for the purpose of identifying and adjusting float 
estimates. 
 
Best Practice: 8. Conducting a schedule risk analysis; 
Description: A schedule risk analysis should be performed using 
statistical techniques to predict the level of confidence in meeting a 
project's completion date. This analysis focuses not only on critical 
path activities but also on activities near the critical path, since 
they can affect the project's status; 
Response: Correct missing dependencies, remove date constraints, 
decompose extended activity durations, analyze, and evaluate float 
values as inclusive of developing Schedule Risk Analysis to be 
included in the Risk Management documentation. 

Best Practice: 9. Updating the schedule using logic and durations to 
determine dates; 
Description: The schedule should be continuously updated using logic 
and durations to determine realistic start and completion dates for 
program activities. The schedule should be analyzed continuously for 
variance to determine when forecasted completion dates differ from 
planned dates;  
Response: Review program schedule activities in weekly, monthly, and 
ad hoc meetings, ensuring current depiction of "start," "end," "actual 
start," "actual end," and variances of planned versus forecasted 
dates; ensure accuracy in Status Date. 

[End of table] 
 
Appendix II Footnote: 

[1] GAO, Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, GAO-09-
35P (Washington, D.C.: March 2009) Figure 10, page 66; "level 3 would 
be the lowest level of the breakdown; for others, still lower levels 
would be required" page 67. 

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Richard M. Stana at (202) 512-8777 or stanar@gao.gov: 

Staff Acknowledgments: 

In addition to the contact named above, Mike Dino, Assistant Director; 
Kathryn Bernet, Assistant Director; and Carla Brown, Analyst-in-
Charge; managed this assignment. Sylvia Bascopé, Jim Russell, and 
Ulyana Panchishin made significant contributions to the work. Nate 
Tranquilly and Bill Russell provided expertise on acquisition issues. 
Tisha Derricotte and Jason Lee provided expertise on scheduling best 
practices. Frances Cook provided legal support. Linda Miller and 
Labony Chakraborty provided assistance in report preparation, and 
Robert Robinson developed the report's graphics. 

[End of section] 

Related GAO Products: 

Acquisition Planning: Opportunities to Build Strong Foundations for 
Better Services Contracts. [hyperlink, 
http://www.gao.gov/products/GAO-11-672]. Washington, D.C.: August 9, 
2011. 

Opportunities to Reduce Potential Duplication in Government Programs, 
Save Tax Dollars, and Enhance Revenue. [hyperlink, 
http://www.gao.gov/products/GAO-11-318SP]. Washington, D.C.: March 1, 
2011. 

Secure Boarder Initiative: DHS Needs to Strengthen Management and 
Oversight of its Prime Contractor. [hyperlink, 
http://www.gao.gov/products/GAO-11-6]. Washington, D.C.: October 18, 
2010. 

Department of Homeland Security: Assessments of Selected Complex 
Acquisitions. [hyperlink, http://www.gao.gov/products/GAO-10-588SP]. 
Washington, D.C.: June 30, 2010. 

GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs. [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP]. Washington, D.C.: March 2009. 

Department of Homeland Security: Billions Invested in Major Programs 
Lack Appropriate Oversight. [hyperlink, 
http://www.gao.gov/products/GAO-09-29]. Washington, D.C.: November 18, 
2008. 

Defense Acquisitions: Realistic Business Cases Needed to Execute Navy 
Shipbuilding Programs. [hyperlink, 
http://www.gao.gov/products/GAO-07-943T]. Washington, D.C.: July 24, 
2007. 

USCIS Transformation: Improvements to Performance, Human Capital, and 
Information Technology Management Needed as Modernization Proceeds. 
[hyperlink, http://www.gao.gov/products/GAO-07-1013R]. Washington, 
D.C.: July 17, 2007. 

Immigration Benefits: Additional Efforts Needed to Help Ensure Alien 
Files Are Located when Needed. [hyperlink, 
http://www.gao.gov/products/GAO-07-85]. Washington, D.C.: October 27, 
2006. 

Information Technology: Near-Term Effort to Automate Paper-Based 
Immigration Files Needs Planning Improvements. [hyperlink, 
http://www.gao.gov/products/GAO-06-375]. Washington, D.C.: March 31, 
2006. 

Immigration Benefits: Improvements Needed to Address Backlogs and 
Ensure Quality of Adjudications. [hyperlink, 
http://www.gao.gov/products/GAO-06-20]. Washington, D.C.: November 21, 
2005. 

Contract Management: Coast Guard's Deepwater Program Needs Increased 
Attention to Management and Contractor Oversight. [hyperlink, 
http://www.gao.gov/products/GAO-04-380]. Washington, D.C.: March 9, 
2004. 

[End of section] 

Footnotes: 

[1] GAO, Immigration Benefits: Additional Efforts Needed to Help 
Ensure Alien Files Are Located when Needed, [hyperlink, 
http://www.gao.gov/products/GAO-07-85] (Washington, D.C.: Oct. 27, 
2006); Information Technology: Near-Term Effort to Automate Paper-
Based Immigration Files Needs Planning Improvements, [hyperlink, 
http://www.gao.gov/products/GAO-06-375] (Washington, D.C.: Mar. 31, 
2006); and Immigration Benefits: Improvements Needed to Address 
Backlogs and Ensure Quality of Adjudications, [hyperlink, 
http://www.gao.gov/products/GAO-06-20] (Washington, D.C.: Nov. 21, 
2005). 

[2] GAO, USCIS Transformation: Improvements to Performance, Human 
Capital, and Information Technology Management Needed as Modernization 
Proceeds, [hyperlink, http://www.gao.gov/products/GAO-07-1013R] 
(Washington, D.C.: July 17, 2007). 

[3] A solutions architect is a person or company contracted by an 
agency to help with the overall execution and organization of a large- 
scale technology development effort. 

[4] DHS Acquisition Directive 102-01 established the ARB as a cross-
component within the department that determines whether a proposed 
acquisition has met the requirements of key phases in the acquisition 
life-cycle framework and is able to proceed to the next phase and 
eventual full production and deployment. The board is comprised of the 
Acquisition Decision Authority (chair of the ARB); the Under Secretary 
for Management; the Under Secretary for Science and Technology; the 
Assistant Secretary for Policy; the General Counsel; the Chief 
Financial Officer; the Chief Procurement Officer; the Chief 
Information Officer; the Chief Human Capital Officer; the Chief 
Administrative Officer; the Chief Security Officer; user 
representatives from components sponsoring the capability; and other 
officials within the department determined to be appropriate to the 
subject matter by the Acquisition Decision Authority. 

[5] The Acquisition Program Management Division has recently been 
replaced by the Program Accountability and Risk Management office. 

[6] In March 2009, we published our Cost Estimating and Assessment 
Guide that identifies best practices for developing and managing 
capital program costs. Agencies can follow the 12-step process which 
addresses best practices in cost estimating, including defining the 
program's purpose; developing the estimating plan; defining the 
program's characteristics; determining the estimating approach; 
identifying ground rules and assumptions; obtaining data, developing 
the point estimate; conducting sensitivity analysis (examine the 
effects of changing assumptions and ground rules); performing a risk 
or uncertainty analysis; documenting the estimate; presenting it to 
management for approval; and updating it to reflect actual costs and 
changes. In addition, within this guide, we have developed nine best 
practices for schedule estimating, which, when followed, should result 
in reliable and valid schedules that management can use to make 
informed decisions. GAO, Cost Estimating and Assessment Guide: Best 
Practices for Developing and Managing Capital Program Costs, 
[hyperlink, http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: 
Mar. 2009). 

[7] The USCIS Program schedule consists of 18 individual program 
schedules and one high-level tracking tool that summarizes activities 
from these 18 individual schedules, called a "Critical Task Schedule." 
To independently determine which schedules to review, we requested all 
program schedules from the Transformation Program Office. We reviewed 
the schedules and related documentation, and interviewed program 
officials on the content of the schedules. We selected two individual 
program schedules for assessment: the USCIS Office of Information 
Technology schedule and the solutions architect's schedule. We 
selected these two schedules for assessment because the work that the 
solutions architect and the Office of Information Technology are doing 
make up the bulk of the work and they are the most critical drivers 
affecting the overall Transformation Program time frames. 
Specifically, the Office of Information Technology schedule is a 
summary of 10 of the 18 individual schedules and the solutions 
architect schedule represents their effort. We did not review the high-
level tracking tool as it did not integrate all activities necessary 
to meet the milestones for Release A; rather, the tracking tool was a 
selection of key activities drawn from the individual schedules 
maintained by USCIS components and the solutions architect. 

[8] Within Release A there are to be several phases of deployment. The 
first phase of Release A will be deployed to customers applying for an 
extension of stay or change of status, which are nonimmigrant 
benefits. Subsequent phases of Release A and Release B will 
incorporate additional nonimmigrant benefit types. 

[9] Nonimmigrant benefits are for individuals seeking to enter the 
United States temporarily for a specific purpose, such as tourism or 
temporary employment; Immigrant benefits are for foreign nationals 
(citizens of another country) seeking to live or work in the United 
States permanently; Humanitarian benefits are for persons who are 
brought to the United States or are currently in the United States, 
who are fleeing persecution, require temporary protection from 
removal, or need an extended stay due to emergent circumstances (e.g., 
those placed in Temporary Protected Status, seeking asylum or entering 
as refugees, granted significant public benefit parole), as a form of 
humanitarian aid, such as those in need of shelter or aid from 
disaster, oppression, or other specific circumstances; and, 
Citizenship benefits can be granted to a noncitizen who meets certain 
eligibility requirements and seeks to become a United States citizen. 

[10] There are six program groups associated with the Transformation 
Program: Increment Release Management; Business Integration; 
Organizational Change Management; Program Management and Integration; 
Regulatory, Privacy, and Policy; and Office of Information Technology. 

[11] The solutions architect contract was awarded with a 90-day 
initial base period and five option periods for a total of 5 years. 

[12] Testimony of USCIS Director before the House Subcommittee on 
Homeland Security on the U.S. Citizenship and Immigration Services 
Fiscal Year 2011 Budget Request; March 16, 2010. 

[13] The premium processing fees are part of USCIS's Immigration 
Examination Fee Account, and are a fee that certain USCIS customers 
pay in addition to the base filing fee. Premium processing guarantees 
that USCIS will process an application within 15 days. 

[14] System acquisition process means the sequence of acquisition 
activities starting from the agency's reconciliation of its mission 
need with its capabilities, priorities and resources, and extending 
through the introduction of a system into operational use or the 
otherwise successful achievement of program objectives. OMB Circular A-
109, Major System Acquisitions. 

[15] The department operated under the March 2006 Management Directive 
No. 1400, Investment Review Process, until November 2008 when DHS 
issued Acquisition Management Directive 102-01, Interim Version, which 
superseded Management Directive No. 1400. DHS Acquisition Instruction/ 
Guidebook 102-01, Interim Version 1.9 (Nov. 7, 2008). 

[16] DHS Management Directive No. 102-01, January 20, 2010. 
Acquisition Decision Events occur when the Acquisition Review Board 
meets to determine whether a program has all of the necessary 
acquisition documents and other DHS requirements to move to the next 
phase in the acquisition process, such as when a program wants to move 
from analyzing and selecting a desired capability (phase 2) to 
actually acquiring that capability (phase 3). Key acquisition decision 
events are labeled 1, 2A, 2B, and 3. The 2A and 2B acquisition events 
may be combined into one acquisition decision event. See figure 2 for 
additional details. 

[17] Life-cycle costs represent all resources and associated cost 
elements required to develop, produce, deploy, and sustain a 
particular program from initial concept through operations, support, 
and disposal. 

[18] According to agency officials, until late August 2010, the DHS 
Deputy Secretary was the decision authority and chaired the ARB. 

[19] GAO, Opportunities to Reduce Potential Duplication in Government 
Programs, Save Tax Dollars, and Enhance Revenue, [hyperlink, 
http://www.gao.gov/products/GAO-11-318SP] (Washington, D.C.: Mar. 1, 
2011). 

[20] GAO, Department of Homeland Security: Assessments of Selected 
Complex Acquisitions, [hyperlink, 
http://www.gao.gov/products/GAO-10-588SP] (Washington, D.C.: June 30, 
2010). 

[21] These planning documents were required by the March 2006 
Management Directive No. 1400 Investment Review Process and continued 
to be required in November 2008 when DHS issued Acquisition Management 
Directive 102-01, Interim Version which superseded Management 
Directive No. 1400. 

[22] GAO, Defense Acquisitions: Realistic Business Cases Needed to 
Execute Navy Shipbuilding Programs, [hyperlink, 
http://www.gao.gov/products/GAO-07-943T] (Washington, D.C.: July 24, 
2007). 

[23] GAO, Acquisition Planning: Opportunities to Build Strong 
Foundations for Better Services Contracts, [hyperlink, 
http://www.gao.gov/products/GAO-11-672] (Washington, D.C.: Aug. 9, 
2011). 

[24] For example, one key performance parameter of the Transformation 
Program is that USCIS ELIS will be able to establish only one account 
per identical set of key personal data. 

[25] USCIS's Component Acquisition Executive signed the first version 
of the USCIS Transformation Program's Operational Requirements 
Document on October 21, 2009. 

[26] According to program officials, all vendors received a Statement 
of Objectives, which enabled vendors to propose widely varying 
solutions that could meet the stated performance objectives. 

[27] GAO, Contract Management: Coast Guard's Deepwater Program Needs 
Increased Attention to Management and Contractor Oversight, 
[hyperlink, http://www.gao.gov/products/GAO-04-380] (Washington, D.C.: 
Mar. 9, 2004), and [hyperlink, http://www.gao.gov/products/GAO-11-6]. 

[28] OIT officials explained that TPO had planned for 5 weeks of 
Independent Verification and Validation as well as 6 weeks of 
Operational Testing and Evaluation. Both of these activities are an 
examination of the system and are to be performed by an independent 
organization. Since these efforts were to overlap, OIT officials 
agreed with TPO officials that including an operational test agent in 
the Operational Test and Evaluation process was a duplicative effort 
because Independent Verification and Validation was already going to 
take place. However, according to DHS acquisition policy, an 
operational test agent is a required element in the deployment of a 
system. 

[29] GAO, Department of Homeland Security: Billions Invested in Major 
Programs Lack Appropriate Oversight, [hyperlink, 
http://www.gao.gov/products/GAO-09-29] (Washington, D.C.: Nov. 18, 
2008). 

[30] Per the USCIS planning document, Transformation Program Life 
Cycle Cost Estimate, March 2011, version 1.5, the present estimate's 
margin of error remained in the low to moderate range despite certain 
costs not being included. 

[31] The technical environments are physical locations equipped with 
hardware and software, and which USCIS is making available for the 
solutions architect to conduct production and testing activities prior 
to full deployment. 

[32] A contract award protest was filed with GAO by a vendor that 
competed for the solutions architect contract. This protest was filed 
in November 2008, and required that the winning vendor, IBM, stop work 
on the contract until the protest was resolved. The vendor withdrew 
its protest in December 2008, and the contract moved forward by 
January 2009. 

[33] [hyperlink, http://www.gao.gov/products/GAO-09-3SP], 218-224. 

[34] Our analysis of the OIT program schedule showed 74 percent of 
activities were missing predecessor or successor logic. In addition, 
the USCIS-approved solutions architect schedule contained 38 percent 
of activities with missing logic. 

[35] The updated USCIS-approved solutions architect schedule contained 
over 40 percent of activities with missing predecessor or successor 
logic. Therefore, in both the original and updated USCIS-approved 
solutions architect schedules, more than one-third of the remaining 
activities are missing logic links. 

[36] For example, an acquisition program baseline requires that an 
updated integrated master schedule be used to support the schedule 
parameters, and a life-cycle cost estimate is to be developed 
following GAO's Cost Assessment Guide: Best Practices for Estimating 
and Managing Program Costs, which includes the development of an 
integrated master schedule. 

[37] See, for example, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] and OMB, Capital Programming 
Guide V 2.0, Supplement to the Office of Management and Budget 
Circular A-11, Part 7: Planning, Budgeting, and Acquisition of Capital 
Assets (Washington, D.C.: June 2006). 

[38] USCIS refers to this tracking tool as a Critical Task Schedule. 
The Critical Task Schedule consists of the dates for major milestones 
and the activities for the Transformation Program, but program 
officials stated that the Critical Task Schedule is not an integrated 
master schedule. 

[39] See [hyperlink, http://www.gao.gov/products/GAO-09-3SP]. 

[40] GAO Cost Estimating and Assessment Guide, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009). 

[End of section] 

GAO’s Mission: 

The Government Accountability Office, the audit, evaluation, and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the 
performance and accountability of the federal government for the 
American people. GAO examines the use of public funds; evaluates 
federal programs and policies; and provides analyses, recommendations, 
and other assistance to help Congress make informed oversight, policy, 
and funding decisions. GAO’s commitment to good government is 
reflected in its core values of accountability, integrity, and 
reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO’s website [hyperlink, http://www.gao.gov]. Each 
weekday afternoon, GAO posts on its website newly released reports, 
testimony, and correspondence. To have GAO e mail you a list of newly 
posted products, go to [hyperlink, http://www.gao.gov] and select “E-
mail Updates.” 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of 
production and distribution and depends on the number of pages in the 
publication and whether the publication is printed in color or black 
and white. Pricing and ordering information is posted on GAO’s 
website, [hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or 
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card, 
MasterCard, Visa, check, or money order. Call for additional 
information. 

Connect with GAO: 

Connect with GAO on facebook, flickr, twitter, and YouTube.
Subscribe to our RSS Feeds or E mail Updates. Listen to our Podcasts.
Visit GAO on the web at www.gao.gov. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 
Website: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]; 
E-mail: fraudnet@gao.gov; 
Automated answering system: (800) 424-5454 or (202) 512-7470. 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov, (202) 512-4400
U.S. Government Accountability Office, 441 G Street NW, Room 7125
Washington, DC 20548. 

Public Affairs: 
Chuck Young, Managing Director, youngc1@gao.gov, (202) 512-4800
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, DC 20548.