This is the accessible text file for GAO report number GAO-11-387 
entitled 'Nuclear Weapons: DOD and NNSA Need to Better Manage Scope of 
Future Refurbishments and Risks to Maintaining U.S. Commitments to 
NATO' which was released on May 2, 2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
GAO: 

Report to Congressional Requesters: 

May 2011: 

Nuclear Weapons: 

DOD and NNSA Need to Better Manage Scope of Future Refurbishments and 
Risks to Maintaining U.S. Commitments to NATO: 

GAO-11-387: 

GAO Highlights: 

Highlights of GAO-11-387, a report to congressional requesters. 

Why GAO Did This Study: 

U.S. nuclear weapons are aging, with key components reaching the end 
of their service life. In September 2008, the Department of Defense 
(DOD) and the National Nuclear Security Administration (NNSA) began a 
study of military requirements and design options for extending the 
B61 bomb’s service life. The B61 is used to support the U.S. strategic 
deterrent and the North Atlantic Treaty Organization (NATO). GAO was 
asked to assess the extent to which DOD and NNSA have (1) considered 
the time available to begin producing refurbished bombs when 
determining the scope of the study; and (2) taken actions to avoid 
operational gaps in U.S. nuclear weapons commitments to NATO during 
the life extension program. To evaluate these objectives, GAO analyzed 
DOD and NNSA policies, guidance, and reports on life extension 
programs, and interviewed officials responsible for B61 operations, 
life extension program planning, management, and oversight. This is 
the unclassified version of a classified report issued in December 
2010. 

What GAO Found: 

DOD and NNSA have made progress in studying and updating the 
military’s performance requirements for the B61 bomb and have ruled 
out some design options, but the broad scope of the study has 
complicated the effort, given the time available to begin producing 
refurbished bombs. Key components of the B61 bombs need to be replaced 
or they will begin reaching the end of their service life. However, 
the time and effort required to evaluate the broad scope, and other 
factors identified by DOD and NNSA officials, have prolonged the study 
by 1 year. Unlike prior life extension programs, the ongoing B61 study 
was broadly scoped to accomplish a variety of goals—such as 
considering previously untried design options and concepts—in addition 
to replacing the bomb’s aging components. GAO’s prior work on 
designing evaluative studies has shown that tailoring a study’s scope 
to reflect relevant time constraints is a critical and well-
established practice. However, the guidance for conducting life 
extension programs does not require DOD and NNSA to consider the 
available time when setting the scope for a life extension study. 
Because they have until September 2011 to complete the study, DOD and 
NNSA officials told GAO that it was premature to assess whether the 
study’s broad scope put the life extension program at risk. However, 
future life extension programs are also likely to occur against the 
end of the existing warhead’s service life. Unless DOD and NNSA 
clarify their procedures to require that future studies are properly 
scoped for the available time, they risk setting unrealistic goals and 
delaying future life extensions. 

Although DOD and NNSA believe the B61 study will be completed by 
September 2011, they have not yet prepared a long-term risk management 
plan to help avoid operational gaps and ensure that the United States 
will be able to maintain the capability to support its NATO 
commitments if the B61 life extension program is delayed or canceled. 
The United States has pledged to support its nuclear weapons 
commitments to NATO while the B61 life extension program is under way. 
In light of this pledge, NNSA and DOD plan to perform just-in-time 
maintenance on the affected bombs to ensure they remain operational 
until NNSA can deliver refurbished bombs to DOD. However, avoiding an 
operational capability gap over the long term may prove challenging, 
as previous nuclear weapons life extension programs have experienced 
schedule delays for a variety of reasons. GAO’s prior work has shown 
that a risk management plan is a useful tool for identifying and 
measuring risks, developing and implementing risk handling options, 
and assessing risk reduction measures. DOD and NNSA have identified 
potential steps that could be taken to mitigate operational risks if 
the B61 life extension program is delayed, but they have not prepared 
a plan to offer options for managing these risks. Developing such a 
plan would help ensure that DOD and NNSA are prepared to implement 
necessary measures to preserve U.S. commitments to NATO. Furthermore, 
without guidance requiring that DOD and NNSA prepare such risk 
management plans, operational requirements for other weapons could 
also be at risk as they go through future life extension programs. 

What GAO Recommends: 

GAO is making recommendations that address the need to scope future 
requirements and design studies to reflect the time available to 
complete the program and prepare risk management plans to address 
operational concerns caused by potential life extension program 
delays. DOD and NNSA agreed with the recommendations. 

View [hyperlink, http://www.gao.gov/products/GAO-11-387] or key 
components. For more information, contact John Pendleton at (202) 512-
3489 or pendletonj@gao.gov or Gene Aloise at (202) 512-3841 or 
aloisee@gao.gov. [End of section] 

Contents: 

Letter: 

Background: 

The DOD-NNSA Review of B61 Performance Requirements and Design Options 
Is Progressing but the Review's Broad Scope Complicated the Study 
Efforts, Given the Available Time: 

DOD and NNSA Have Not Planned for Maintaining Operational Nuclear 
Weapons Commitments to NATO if the B61 Life Extension Program Is 
Delayed: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department of Defense: 

Appendix III: Comments from the National Nuclear Security 
Administration: 

Appendix IV: GAO Contacts and Staff Acknowledgments: 

Tables: 

Table 1: Scope of B61 Phase 6.2 Study Compared to Prior Nuclear Weapon 
Life Extension Programs and Major Refurbishments: 

Table 2: Status of Potential Design Options for the B61 Life Extension 
Program as of September 2010: 

Table 3: Options for Mitigating a Gap in U.S. Commitments to NATO: 

Figures: 

Figure 1: Notional Life Extension Program Schedule, May 2010: 

Figure 2: DOD-DOE Phase 6.X Process for Managing Nuclear Weapons 
Refurbishments and Life Extension Programs: 

Figure 3: Key Dates in the Planning and Execution of the B61 Life 
Extension Program: 

Figure 4: Bomb Design Consolidation in the B61 Life Extension Program: 

Figure 5: Key Operational Dates for the B61 Bombs during the Life 
Extension Program: 

Abbreviations: 

DOD: Department of Defense: 

DOE: Department of Energy: 

ICBM: Intercontinental Ballistic Missile: 

NATO: North Atlantic Treaty Organization: 

NNSA: National Nuclear Security Administration: 

SHAPE: Supreme Headquarters Allied Powers Europe: 

SLBM: Submarine-Launched Ballistic Missile: 

USAFE: United States Air Forces in Europe: 

USEUCOM: United States European Command: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

May 2, 2011: 

The Honorable Michael R. Turner: 
Chairman: 
Subcommittee on Strategic Forces: 
Committee on Armed Services: 
House of Representatives: 

The Honorable James R. Langevin: 
House of Representatives: 

Nuclear weapons have long been a cornerstone of the nation's defense 
strategy. These weapons--deployed on intercontinental ballistic 
missiles (ICBM), submarine-launched ballistic missiles (SLBM), heavy 
bombers, and fighter aircraft capable of performing nuclear missions-- 
have played an essential role in deterring a nuclear attack on the 
United States and its allies and partners, including the North 
Atlantic Treaty Organization (NATO). At the same time, arms control 
agreements and other policies since the 1960s have led the United 
States to maintain its nuclear deterrent with decreasing numbers of 
weapons. In the April 2010 Nuclear Posture Review Report,[Footnote 1] 
the current administration declared its commitment to further reducing 
U.S. nuclear forces, while maintaining a safe, secure, and effective 
nuclear deterrent for the United States and its allies, even as the 
weapons in the nuclear stockpile continue to age and weapon components 
reach the end of their operational life. Further, recognizing that 
NATO was undertaking a review of its Strategic Concept, which 
expresses the alliance's fundamental security tasks, the 
administration pledged in April 2010 not to prejudge NATO's review, 
even as it committed to retain the capability to forward deploy 
nuclear bombs.[Footnote 2] 

The Department of Defense (DOD) and the National Nuclear Security 
Administration (NNSA), a separately organized agency within the 
Department of Energy (DOE), are currently in the process of planning a 
life extension affecting four of the five versions of the B61 bomb. 
[Footnote 3] The B61 bomb is one of seven types of nuclear weapons 
that remain in the U.S. stockpile. The bomb is used to support U.S. 
nuclear commitments to NATO, where, as part of NATO's forces, it is 
intended to signal cohesion among NATO members, and when deployed, 
versions of the bomb could be carried on U.S. and NATO fighter 
aircraft during conflict. DOD and NNSA have stated that the B61 life 
extension program is necessary because key bomb components will soon 
need replacement or the bombs would become nonoperational. Although 
Congress initially limited the scope and funding for the B61 life 
extension study to the bomb's nonnuclear components during fiscal year 
2010, the April 2010 Nuclear Posture Review Report endorsed completing 
a "fullscope" life extension of the B61 bomb's nuclear and nonnuclear 
components.[Footnote 4] In May 2010, as directed by Congress, DOE 
requested approval from the House and Senate Committees on 
Appropriations to study options for a fullscope life extension; 
[Footnote 5] the fullscope life extension study was approved in August 
2010. 

The administration's continued commitment to extending the life of 
nuclear weapons is accompanied by requirements for significant 
investment in DOD delivery platforms and NNSA nuclear weapons 
production infrastructure. In a May 2010 report to Congress,[Footnote 
6] the administration identified a 10-year cost estimate of over $100 
billion to sustain and modernize strategic delivery systems and U.S. 
dual-capable fighter aircraft. Additionally, NNSA has identified $80 
billion in nuclear weapons stockpile and infrastructure costs over the 
same period to maintain the safety and reliability of the nuclear 
weapons stockpile without nuclear testing. Among other things, these 
infrastructure investments are to support not only the B61 life 
extension, but future life extension programs for ICBM, SLBM, and 
bomber-delivered cruise missile warheads. 

Our prior work has shown that nuclear weapons life extension programs 
can be complicated and risky endeavors that require disciplined 
management and effective collaboration among all the participating DOD 
and NNSA organizations. Although DOD and NNSA have improved management 
practices since our first report on NNSA's life extension programs was 
issued in 2000,[Footnote 7] in March 2009, we reported that DOD and 
NNSA have continued to experience problems carrying out life 
extensions within the agreed-upon schedule, and within estimated 
costs.[Footnote 8] 

In March 2008 the Nuclear Weapons Council--a statutorily authorized 
joint activity composed of DOD and DOE officials--approved an Air 
Force request for a study of military performance requirements and 
potential design options for the B61 life extension program. As 
requested, we have reviewed the extent to which DOD and NNSA have (1) 
considered the time available to begin producing refurbished bombs 
when determining the scope of the study; and (2) taken actions to 
avoid operational gaps in U.S. nuclear weapons commitments to NATO 
during the B61 life extension program. In December 2010, we reported 
to you on the results of our work in a classified report. This is the 
unclassified version of that classified report. To prepare this 
unclassified version, we removed certain references to nuclear weapons 
quantities, storage locations, designs, and performance 
characteristics. 

To evaluate our objectives, we analyzed DOD, DOE, and Nuclear Weapons 
Council policies and guidance on planning and carrying out nuclear 
stockpile life extension programs; and reviewed DOD and NNSA reports 
and B61 Project Officers Group status briefings on the B61 life 
extension program. We also interviewed DOD and NNSA officials 
responsible for coordinating the joint DOD-NNSA study of requirements 
and design options for the planned B61 life extension program, and 
other officials from the Office of the Secretary of Defense, Air 
Force, and NNSA, including the former NNSA manager for nuclear weapons 
stockpile sustainment, the current NNSA manager for the B61 weapon 
system, and NNSA managers for ICBM, SLBM, and cruise missile weapon 
systems. We analyzed documents from the Office of the Secretary of 
Defense, NNSA, U.S. Strategic Command, U.S. European Command, and NATO 
and met with officials from these organizations. Our scope and 
methodology are described in more detail in appendix I. 

We conducted this performance audit from October 2009 to December 2010 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

Most modern nuclear weapons consist of three sets of components--a 
primary, a secondary, and a set of nonnuclear components enclosed in a 
case. When detonated, the primary and secondary components, which 
together are referred to as the weapon's "nuclear explosive package," 
produce the weapon's explosive force, or "yield." The array of 
nonnuclear components surrounding the nuclear explosive package serves 
to control the detonation sequence and helps ensure the weapon's 
safety and security from human tampering and accidental detonation. 
Some of these nonnuclear components--collectively called "limited-life 
components"--have shorter service lives than the weapon itself, and 
therefore must be periodically replaced. 

The U.S. stockpile includes more than 5,000 nuclear weapons, the vast 
majority of which are either operationally deployed in the United 
States or on submarines at sea, or held in storage.[Footnote 9] Based 
on guidance and direction provided by the President, Secretary of 
Defense, and Chairman of the Joint Chiefs of Staff, the Commander of 
U.S. Strategic Command is responsible for developing an operational 
plan and identifying targets for an arsenal that includes 1,700 to 
2,200 operationally deployed strategic nuclear weapons. The Air Force 
maintains and operates nuclear-armed ICBMs, cruise missiles, and 
gravity bombs, whereas the Navy maintains and operates nuclear-armed 
SLBMs. The Commander of U.S. Strategic Command has operational command 
and control over these nuclear forces but only the President is 
authorized to direct the use of nuclear weapons. 

In addition to the nuclear forces under U.S. Strategic Command's 
operational control, the United States retains a limited number of 
nonstrategic, or "tactical" B61 bombs in the nuclear weapons stockpile 
to support NATO commitments. These bombs are maintained in an 
operational configuration, and can be delivered by both U.S. fighter 
aircraft and aircraft of predesignated, trained, and certified NATO 
allies. The Commander of U.S. European Command also serves as the 
Supreme Allied Commander of European forces, and would exercise 
command and control of these weapons during a conflict. The Air Force 
exercises day-to-day custody of the B61 bombs used to support NATO 
commitments. As is the case for the employment of nuclear weapons 
under U.S. Strategic Command's control, only the President of the 
United States can authorize the NATO Supreme Allied Commander to 
employ the B61 bomb. 

While U.S. Strategic Command has prepared an operational plan for 
employing nuclear weapons, neither NATO nor U.S. European Command, in 
accordance with the NATO Strategic Concept, have prepared standing 
peacetime nuclear contingency plans or identified targets involving 
nuclear weapons. The B61 bombs assigned to support NATO are intended 
to provide for the collective security of all its members. According 
to U.S. European Command officials, the B61 bombs couple U.S. and NATO 
security, and tangibly assure the members of NATO that the United 
States is committed to their national security. The April 2010 Nuclear 
Posture Review Report recognizes that the risk of nuclear attack 
against NATO members is at a historic low. However, the Nuclear 
Posture Review Report emphasized that NATO's unique arrangements, in 
which nonnuclear members participate in nuclear planning and possess 
specially configured aircraft capable of delivering nuclear weapons, 
[Footnote 10] contribute to alliance cohesion and provide reassurance 
to allies and partners who feel exposed to regional threats. 

The U.S. stockpile includes five different versions of the B61 bomb, 
which first entered the stockpile in the late 1970s and is the oldest 
weapon in the U.S. stockpile. Two of the five versions, considered 
"strategic" versions, would be carried into combat by B-52 and B-2 
bomber aircraft, whereas the other three "nonstrategic" versions would 
be carried into combat by U.S. or NATO allied fighter aircraft. The 
five versions have different military characteristics, which identify 
key military performance requirements, such as safety requirements or 
explosive yield, for a given nuclear bomb or warhead. Furthermore, to 
protect against access by unauthorized persons, the nonstrategic 
versions were designed with advanced security systems. 

To sustain the nuclear deterrent as weapons age, the current 
administration has endorsed a policy--also followed by prior 
administrations--to perform life extension programs on existing 
stockpiled weapons, rather than design, test, and produce new weapons. 
DOD and DOE both play crucial roles in planning and executing nuclear 
weapons life extension programs. DOE formally initiated the Stockpile 
Life Extension Program in 1996; NNSA has administered the program 
since fiscal year 2000. DOD and NNSA (or its predecessor DOE 
organizations) have previously planned and executed several nuclear 
weapons life extension programs and refurbishments, including life 
extensions of the W87 warhead, which is deployed on ICBMs, and the W76 
warhead, which is deployed on SLBMs. NNSA also performed a significant 
refurbishment to the secondary component of the strategic versions of 
the B61 in the mid-2000s.[Footnote 11] NNSA, due to limited production 
capacity, has conducted these life extension programs consecutively, 
rather than concurrently. Although their durations have varied, life 
extension programs can take nearly a decade or more from the start of 
the planning phases until refurbished weapons are delivered to DOD for 
reintroduction into the stockpile. The B61 life extension program and 
other planned life extension programs also are expected to occur 
sequentially, as shown in figure 1. 

Figure 1: Notional Life Extension Program Schedule, May 2010: 

[Refer to PDF for image: time line] 

Production dates: 

W76: Current to end of 2017. 

B61: 2017 through end of 2021. 

W78: 2021 through end of 2025. 

W88: 20206 through 2030 and beyond. 

Study and Design dates: 

W80-1: 2021-2030: Study, design and engineering activities; production 
to start after 2030. 

B83/B61-11 and W87: Startup of design activities for one of these
systems is anticipated in mid-2020s. 

Source: NNSA. 

[End of figure] 

NNSA and DOD use the "Phase 6.X" process to manage all nuclear weapons 
refurbishments, including not only alterations to fix or replace aging 
nuclear weapons components, but also fullscope life extension 
programs. The Procedural Guideline for the Phase 6.X Process 
establishes the joint process for nuclear weapons refurbishments. 
[Footnote 12] After the Nuclear Weapons Council--the joint DOD and 
NNSA activity responsible for executive-level management of the 
nuclear weapons stockpile[Footnote 13]--formally authorizes the 
beginning of a Phase 6.2 feasibility study for a life extension 
program, [Footnote 14] a Service-led project officers group manages 
the study of design options for the weapon.[Footnote 15] The steps for 
the Phase 6.X process are described in figure 2. 

Figure 2: DOD-DOE Phase 6.X Process for Managing Nuclear Weapons 
Refurbishments and Life Extension Programs: 

[Refer to PDF for image: illustration] 

Phase 6.X Weapon Production, Maintenance, and Evaluation: 

The illustration depicts an interlocking circular pattern: 6.1 to 6.6 
and recycling. 

6.1: DOD, NNSA, or the responsible project officers group conducts 
studies to determine if a weapon in the stockpile needs refurbishment 
or to investigate refurbishment concepts. 

6.2: For a weapon needing refurbishment, the project officers group 
coordinates DOD and NNSA efforts to update the weapon’s military 
requirements, develop feasible design options to meet the 
requirements, and identify a preferred design option(s). 

6.2A: The project officers group coordinates further DOD and NNSA 
investigation of a preferred design option(s) and the expected 
refurbishment costs. 

6.3: NNSA-led tests and experiments to validate the design option(s) 
in consultation with DOD. 

6.4: NNSA-led activities to adapt the design for production and 
prepare its production facilities. 

6.5: Refurbishment of a limited number of weapons for analysis and 
production process qualification. 

6.6: Full-scale production at NNSA’s facilities. 

Source: Nuclear Weapons Council. 

[End of figure] 

In March 2008, the Nuclear Weapons Council approved the Air Force's 
request for a study, under Phases 6.2 and 6.2A, to explore the 
feasibility and costs of conducting a fullscope life extension program 
of the B61 bomb.[Footnote 16] In June 2008, the council directed the 
study to begin no later than September 2008 and be completed within 24 
months; however, the study's completion has been extended by 1 year. 
[Footnote 17] As shown in figure 3, DOD and NNSA plan to deliver the 
first refurbished B61 bomb[Footnote 18]--Phase 6.5 in the 6.X process--
in 2017. According to the Air Force lead project officer for the B61 
bomb, NNSA plans to produce enough refurbished bombs by the end of 
fiscal year 2022 to meet both U.S. Strategic Command's requirements 
and U.S. European Command's requirements to support NATO. The project 
officers group is seeking to extend the bomb's service life for 
another 30 years. According to the NNSA program manager for the B61 
bomb, the preliminary cost estimate for the life extension program is 
about $4 billion through 2022, when the program would be completed. 

Figure 3: Key Dates in the Planning and Execution of the B61 Life 
Extension Program: 

[Refer to PDF for image: illustration] 

2008-2011: Study: 

June 2008: Nuclear Weapons Council directs start of B61 life extension 
program. 

September 2008: Start of B61 life extension program Phase 6.2/6.2A 
study. 

September 2011 (estimated): Nuclear Weapons Council decision on design 
options for the B61 life extension program and approval to move to 
Phase 6.3. 

2011-2017: Development and production engineering: 

2017-2022: Production and delivery: 

September 2017 (estimated): NNSA to deliver first production unit to 
DOD. 

September 2022 (estimated): completion of full-scale production. 

Source: GAO analysis of DOD information. 

[End of figure] 

NNSA's Office of Defense Programs is primarily responsible for the B61 
life extension program. This office plans and coordinates NNSA 
activities to maintain the nuclear stockpile, including the 
manufacture, maintenance, refurbishment, surveillance, and 
dismantlement of weapons; annual assessment of the weapons' safety and 
reliability; and research, development, and nonnuclear testing to 
support these activities. A national complex of three national nuclear 
weapons design laboratories, four production plants, and the Nevada 
National Security Site (formerly the Nevada Test Site) carries out the 
Office of Defense Programs' mission. For the B61 life extension 
program, Los Alamos National Laboratory, in New Mexico, and Sandia 
National Laboratory, in New Mexico and California, are directly 
involved in designing the refurbished B61; while Lawrence Livermore 
National Laboratory, in California, will peer-review the design. Once 
production has begun, NNSA's Pantex Plant, in Texas, will assemble key 
subcomponents of the refurbished bomb, including many of the 
nonnuclear components, manufactured at the Kansas City Plant, in 
Missouri, and, for a fullscope life extension, any nuclear components 
refurbished at other sites in the complex. 

The DOD-NNSA Review of B61 Performance Requirements and Design Options 
Is Progressing but the Review's Broad Scope Complicated the Study 
Efforts, Given the Available Time: 

Since initiating the joint study for the B61 life extension program at 
the request of the Nuclear Weapons Council in September 2008, DOD and 
NNSA have made progress evaluating the military's performance 
requirements for the refurbished B61 bomb and have ruled out key 
design options, but the broad scope of the council's request has 
complicated the joint study effort, given the time available to begin 
producing refurbished weapons. For example, the Nuclear Weapons 
Council, in its June 2008 letter, scoped the study to include options 
for incorporating previously untried technologies and design concepts 
into the refurbished bomb, in addition to replacing its aging 
components. As a result of the broad scope and other factors 
identified by DOD and NNSA officials, the study is expected to take 
until September 2011--1 year longer than initially planned. Our prior 
work on designing evaluative studies has shown that tailoring a 
study's scope to reflect the time constraints for conducting the study 
is a critical and well-established research practice.[Footnote 19] 
Because the B61 Project Officers Group has made progress in the study, 
NNSA and DOD officials told us it was premature to assess whether the 
broad scope will affect their ability to begin producing refurbished 
B61 bombs by 2017. However, the complications raised by the B61 
study's broad scope and limited time frame have implications for 
future life extension programs, because those programs also are likely 
to occur against the approaching end of the existing weapon's service 
life. Unless DOD and NNSA clarify their procedures to require that 
future life extension studies are properly scoped for the available 
time, they risk setting unrealistic goals and delaying future life 
extension programs. 

DOD and NNSA Have Made Progress Identifying Military Performance 
Requirements and Design Options for the B61 Life Extension Program: 

DOD and NNSA have reached a tentative agreement to consolidate several 
older versions of the B61 bomb into a single design. According to U.S. 
Strategic Command and NNSA officials, consolidating the versions could 
reduce the risks and costs of maintaining the bomb, improve the safety 
and security of the weapon, eliminate the need to conduct a life 
extension on multiple B61 versions, and reduce expenses by prolonging 
the interval for replacing key limited-life components. As a result of 
this agreement, as shown in figure 4, DOD plans to retire four 
versions of the B61 and replace them with a refurbished weapon based 
generally around the design of one of those versions, the B61-4. 
Because the B61-4 has the lowest yield among the different versions, 
consolidating the versions in this manner would also remove 
significant quantities of nuclear material from the deployed B61 bombs. 

Figure 4: Bomb Design Consolidation in the B61 Life Extension Program: 

[Refer to PDF for image: illustration] 

4 Bomb types: 
B61-3; 
B61-4; 
B61-7; 
B61-10. 

Consolidated to 1 bomb design: 
B61 Life Extension. 

Source: U.S. Strategic Command. 

Note: Figure is for illustrative purposes and does not accurately 
convey weapons design information or characterize differences among 
the B61-3/4/7/10 versions of the bomb. The B61-11 is not included as 
part of the scope of the B61 life extension program. 

[End of figure] 

In agreeing to consolidate the B61 stockpile around a single design, 
DOD components--including U.S. Strategic Command, U.S. European 
Command, and the Air Force--reached agreement on some of the key 
performance requirements, or military characteristics, for the 
refurbished bomb. A nuclear weapon's military characteristics describe 
DOD's official requirements for the weapon's size, weight, and other 
physical attributes; performance characteristics, such as nuclear 
yields or heights-of-burst; safety and security standards, such as 
minimizing military personnel's radiation exposure; and other factors 
that affect nuclear weapons design. When conducting a Phase 6.2 study, 
NNSA officials told us that its design laboratories need DOD to reach 
agreement on its requirements early in the process so that they are 
able to assess the extent to which various design options for the life-
extended weapon meet the military's needs. 

The agreements reached to date have come about only through 
significant effort and time. For example, DOD required about 18 months 
from the beginning of the study to confirm NATO's requirements for the 
weapon. NATO's Supreme Headquarters, Allied Powers Europe (SHAPE), 
[Footnote 20] originally submitted requirements for the refurbished 
B61 bomb in March 2009, 6 months after the study began. However, the 
Air Force lead project officer, and officials from U.S. European 
Command and SHAPE, told us that the original submission did not 
provide the B61 Project Officers Group with the specific requirements 
that it needed to conduct the Phase 6.2 study. In October 2009, the 
group asked DOD to clarify NATO requirements, and U.S. European 
Command led a DOD-wide effort throughout early 2010 to resolve key 
issues with certain NATO allies. In April 2010, DOD and the NATO 
allies reached agreement on key military characteristics of the bomb, 
including the yield, that it be capable of freefall (rather than 
parachute-retarded) delivery,[Footnote 21] its accuracy requirements 
when used on modern aircraft and that it employ a guided tailkit 
section,[Footnote 22] and that it have both midair and ground 
detonation options. They further agreed that the weapon should be 
capable of being carried by both existing and modernized fighter 
aircraft, including the F-35,[Footnote 23] and be compatible with 
current weapon storage vaults abroad. Subsequently, after U.S. 
Strategic Command expressed a requirement for a different yield, U.S. 
European Command and SHAPE agreed to the proposal. 

According to Air Force and NNSA officials, DOD's ability to reach 
agreement with the allies on these issues was a significant 
achievement. For example, had the allies opposed the guided tailkit, 
then the strategy to consolidate the different versions of the bomb 
may have been in jeopardy. 

Broad Scope and Tight Time Frames Have Complicated the Joint B61 
Refurbishment Study: 

Although DOD and NNSA have made progress defining requirements and 
identifying design options for the B61, the Nuclear Weapons Council's 
June 2008 request was considerably broader than prior life extension 
programs and has complicated the agencies' effort, given the tight 
time frames for completing the study. Our prior work on designing 
evaluative studies has shown that tailoring a study's scope to reflect 
the time constraints for conducting the study is a critical and well-
established research practice. Furthermore, the failure to align a 
study's scope with the time available can adversely affect the quality 
of the study. 

The scope of the B61 study--which includes studying new features and 
designs, in addition to replacing aging components--is considerably 
broader than previous life extension programs. For example, the 
Nuclear Weapons Council requested the joint Navy and NNSA project 
officers group to only develop design options and cost estimates for 
refurbishing the W76 SLBM warhead,[Footnote 24] which the Navy and 
NNSA concluded could be best accomplished by adhering as closely as 
possible to the weapon's original specifications.[Footnote 25] 
Similarly, during the life extension of the W87 ICBM warhead, which 
was begun before DOD and DOE formalized the Phase 6.X process and 
completed in 2005, NNSA's actions were limited and not based on 
changes to the warhead's military requirements. However, for the 
current B61 life extension program, the Nuclear Weapons Council 
instructed the joint Air Force and NNSA project officers group that it 
should pursue not only the complete refurbishment of the bomb, but 
also opportunities to improve other characteristics affecting the 
bomb's safety, security, and performance, as well as investigate 
alternative design concepts untried during prior life extension 
programs. Table 1 compares the scope of the current B61 study with the 
scope of prior life extension programs and major refurbishments. 

Table 1: Scope of B61 Phase 6.2 Study Compared to Prior Nuclear Weapon 
Life Extension Programs and Major Refurbishments: 

Life extension program or refurbishment: 

Current life extension program: B61 bomb, strategic and nonstrategic 
versions (B61-3, -4, -7, -10); 
Service: Air Force; 
Scope: Refurbishment of aging components: Yes, many; 
Scope: Safety and security enhancements: Yes, many; 
Scope: Other enhancements or design changes: Yes, many. 

Prior life extensions or major refurbishments: B61 bomb, strategic 
versions (B61-7, -11)[A]; 
Service: Air Force; 
Scope: Refurbishment of aging components: Yes; 
Scope: Safety and security enhancements: None; 
Scope: Other enhancements or design changes: None. 

Prior life extensions or major refurbishments: W80-1 cruise missile 
warhead[B]; 
Service: Air Force; 
Scope: Refurbishment of aging components: Yes; 
Scope: Safety and security enhancements: Yes; 
Scope: Other enhancements or design changes: None. 

Prior life extensions or major refurbishments: W76 SLBM warhead; 
Service: Navy; 
Scope: Refurbishment of aging components: Yes; 
Scope: Safety and security enhancements: None; 
Scope: Other enhancements or design changes: None. 

Prior life extensions or major refurbishments: W87 ICBM warhead[C]; 
Service: Air Force; 
Scope: Refurbishment of aging components: None; 
Scope: Safety and security enhancements: None; 
Scope: Other enhancements or design changes: Yes. 

Source: GAO analysis of DOD and NNSA data. 

[A] The scope of this refurbishment included only the replacement of 
the nuclear secondary component in the strategic versions of the bomb. 

[B] Safety and security enhancements were not originally part of the 
scope of the Phase 6.2 study for the W80-1 cruise missile warhead's 
life extension program. The W80 Project Officers Group first 
considered enhancements to the weapon's safety and security features 
after the Phase 6.2 study was under way, in response to a joint DOD 
and NNSA requirement that the W80 Project Officers Group consider 
opportunities for such enhancements. The life extension program, 
however, was canceled in May 2006 after DOD re-evaluated its cruise 
missile force structure requirements. According to a senior official 
from the Office of the Secretary of Defense, the life extension 
program may be resumed for the warhead after the Air Force assesses 
the requirements for long-range strike capabilities. 

[C] The W87 refurbishment was initiated before DOD and DOE established 
the Phase 6.X process. 

[End of table] 

The broad scope of the B61 life extension program study also differs 
from prior life extension program studies in how it instructed the B61 
Project Officers Group to review and address the weapon's key military 
performance requirements. Unlike the ongoing B61 life extension 
program study, prior programs did not require significant changes to 
the military performance requirements for the weapon being refurbished 
because these requirements were generally fixed by the type of 
delivery systems that carried them. For example, the W76 SLBM warhead 
and W80 cruise missile warhead life extension programs were intended 
to result in refurbished weapons carried by SLBMs and cruise missiles, 
respectively, and therefore the programs largely adhered to the 
military characteristics associated with the original weapon.[Footnote 
26] In contrast, the Nuclear Weapons Council's June 2008 request 
letter instructed the B61 Project Officers Group to consider revisions 
to the bomb's military performance requirements in line with the 
aforementioned strategy to consolidate multiple B61 versions. As a 
result, the group has been working to consolidate the requirements for 
strategic and nonstrategic versions of the bomb, which currently have 
different requirements based on their mission. Also unlike prior 
programs, the B61 Project Officers Group also has been reviewing 
design options to ensure that the refurbished weapon will be able to 
be employed on existing and yet-to-be fielded aircraft--particularly 
the F-35. According to the Air Force official leading the requirements 
subgroup, consolidating the military performance requirements for the 
various versions of the bomb required considerably more time than 
previous life extension programs had taken to establish the 
refurbished weapons' military characteristics. 

The B61 life extension program is also unique in that the stockpiled 
B61 bombs are approaching the end of their service lives, thus 
constraining the amount of time available to complete the study and 
the subsequent phases of the life extension program. The Nuclear 
Weapons Council recognized this urgency, when it emphasized, in the 
June 2008 letter, that the target date for production must ensure no 
capability gaps with respect to preserving U.S. nuclear weapons 
commitments to NATO, which would require NNSA to achieve Phase 6.5 
(first production) no later than 2017. According to Air Force and NNSA 
officials, meeting this schedule will require the Air Force to perform 
maintenance on the existing weapons in order to give NNSA time to 
complete the life extension program before the weapons begin reaching 
the end of their service life. In contrast, prior life extension 
programs have not faced firm deadlines driven by end-of-life issues. 
For example, a senior Navy official told us that the Nuclear Weapons 
Council tasked the Navy and NNSA to begin the W76 life extension 
program study well before that weapon was expected to reach the end of 
its service life. 

In addition to improving the bomb's safety and performance and reduce 
maintenance costs, the Nuclear Weapons Council had various other goals 
in mind when it requested a broad scope for the B61 refurbishment 
study, according to DOD and NNSA officials. According to DOD 
officials, the B61 life extension offers a unique opportunity to 
implement national policy on safety and security of nuclear weapons. 
[Footnote 27] In particular, Office of the Secretary of Defense 
officials told us that the council scoped the study broadly to provide 
opportunities to broaden the range of weapons-design and production 
activities being performed at the NNSA weapons complex. The council 
also wanted to potentially make use of the design innovations being 
developed at NNSA's nuclear design laboratories to improve the safety, 
security, and performance of aging weapons. Furthermore, in 
preparation for future life extension programs, the council wanted to 
take advantage of the B61 study to explore novel and innovative 
concepts that could be applied when conducting future life extension 
programs. As of September 2010, the B61 Project Officers Group had not 
yet reached agreement on some of the design options that were included 
in the scope of the study. The status of the review is summarized in 
table 2. 

Table 2: Status of Potential Design Options for the B61 Life Extension 
Program as of September 2010: 

Potential design option: Multipoint safety technology[A]; 
Description: The June 2008 letter instructed the B61 Project Officers 
Group that it should explore options for enhancing the bomb's safety 
and security; 
Risk: Has not been used in existing stockpiled weapons; 
Status: The B61 Project Officers Group is continuing its evaluation of 
costs and benefits of different multipoint safety technologies, 
including the potential impacts of different approaches on how the Air 
Force maintains and operates the weapons. 

Potential design option: Alternative power supply components; 
Description: Although the B61 bombs currently use a well-proven 
technology for power supplies, the B61 Project Officers Group studied 
alternative power supply technologies in order to potentially lower 
the bomb's overall costs; 
Risk: The alternative technologies have not been used in the 
stockpile. NNSA estimates that the initial development and production 
costs of one of the technologies would be significantly greater than 
using the existing technology; 
Status: The B61 Project Officers Group ruled out one technology in 
August 2009. However, according to senior Air Force officials, the 
group had not yet determined whether the existing power supply 
technology is the most cost-effective approach for the refurbished 
bomb. 

Potential design option: Alternative bomb shapes; 
Description: To create space for more safety and security features 
inside the tightly packed B61 bomb case, the council asked the B61 
Project Officers Group to study alternative bomb bodies. In response, 
the group investigated the Mark-84 bomb shape and the Joint Standoff 
Weapon[B]; 
Risk: Significant programmatic and design risks to incorporate 
alternative bomb shapes; did not meet the military's performance 
requirements; 
Status: The Joint Standoff Weapon was ruled out as a design option in 
April 2009, and the Mark-84 was ruled out in August 2009. 

Potential design option: Alternative nuclear explosive components; 
Description: Due to limitations in NNSA's capacity to manufacture new 
nuclear components, the council asked the B61 Project Officers Group 
to study options for reusing nuclear components from other weapons, in 
addition to reusing the B61 bomb's components. In particular, the 
group investigated reusing components from the W84 ground-launched 
cruise missile warhead[C]; 
Risk: Significant programmatic and performance risks to adapt these 
components to a new weapon; did not meet the military's performance 
requirements; insufficient quantities to meet expected production 
requirements; 
Status: Ruled out as a design option in April 2009. 

Source: GAO analysis of DOD and NNSA data. 

[A] "Multipoint safety" means that the probability is no greater than 
1 in 1 million that a weapon will detonate with a yield of greater 
than 4 pounds of TNT if more than one point on the weapon's high 
explosive is accidentally detonated. Currently, all nuclear weapons in 
the U.S. stockpile are judged to be one-point safe. 

[B] The Mark-84 is a 2,000-pound, unguided, conventional bomb. The 
Joint Standoff Weapon is a precision-guided, 1,000-pound air-to-
surface conventional missile. 

[C] Ground-launched cruise missiles were withdrawn from Europe 
beginning in the late 1980s. The W84 warheads, while not in the 
current U.S. stockpile, remain in a "managed retirement" status. 
Because they are a modern design, the warheads could be used as 
replacements for existing weapons, should those weapons develop 
performance problems. 

[End of table] 

Another factor complicating the B61 study is that the B61 Project 
Officers Group lacked the time to perform a formal concept assessment 
during Phase 6.1 of the Phase 6.X process. DOD and NNSA officials 
agreed that exploring novel design concepts would ideally occur before 
starting a Phase 6.2 study, consistent with the joint guidelines. 
Under the guidelines, either DOD or NNSA can begin a formal Phase 6.1 
assessment to address a requirement change, or to study refurbishment 
options. Our prior work reviewing life extension programs also has 
concluded that, had NNSA taken the time needed to follow the Phase 6.X 
process during the earlier effort to refurbish components for the 
strategic versions of the B61 bomb, then the agency might have been 
better prepared to develop and test key materials that it had not 
manufactured in decades. However, in preparing for the ongoing B61 
study, the B61 Project Officers Group lacked the time to perform a 
Phase 6.1 concept assessment, where requirements and design options 
could be more thoroughly explored, according to DOD and NNSA 
officials. As a result, the group required about 6 months to work 
through issues that might have been addressed during a Phase 6.1 
study, added the NNSA program manager for the B61 bomb. 

Broad Scope among the Factors That Prolonged the B61 Study: 

According to DOD and NNSA officials, the broad scope of the B61 study 
is one of several factors that have lengthened the time for completing 
the study. According to DOD and NNSA officials, the final study report 
is expected to be completed in September 2011, or 1 year later than 
the Nuclear Weapons Council's original deadline. DOD and NNSA 
officials told us that, while investigating these options, they were 
initially concerned that the broad scope would leave the B61 Project 
Officers Group without sufficient time or resources to select a 
preferred design option and develop more detailed cost information 
about that option. Prior GAO work on best practices for managing 
program costs has shown that poorly defining a program at the outset 
increases the risk that the program will fail to meet its cost, 
schedule, or operational goals.[Footnote 28] According to DOD and NNSA 
members of the B61 Project Officers Group, absent the ability to 
rigorously define the military performance requirements and design 
options during the Phase 6.2 study, the later phases of the life 
extension program could be at risk. According to a March 2009 progress 
report from the B61 Project Officers Group, the scope of the study and 
progress made up to that point in time, among other factors, had put 
the study at risk of not meeting its deadline to produce the first 
refurbished B61 bombs in 2017. In August 2009, according to DOD and 
NNSA officials, the group was still considering multiple design 
options because of the broad scope, which made it difficult for it to 
investigate any particular option in greater detail. 

Despite these delaying factors, members of the B61 Project Officers 
Group and other DOD and NNSA officials told us that they believe there 
is enough time remaining to complete the study and deliver the first 
refurbished bomb in fiscal year 2017, as noted by the Nuclear Weapons 
Council. Moreover, the officials added that factors aside from the 
Nuclear Weapons Council's broad scope also delayed progress in 
completing the study. First, according to DOD and NNSA officials, the 
B61 study was not fully funded during fiscal years 2009 and 2010. For 
example, the NNSA program manager for the B61 bomb stated that NNSA's 
fiscal year 2009 budget had already been submitted to Congress when 
the Nuclear Weapons Council authorized the B61 study; as a result, the 
NNSA had only about $28 million of a required $60 million for the 
study in fiscal year 2009. Additionally, the officials told us that 
Congress's prohibiting NNSA to obligate or expend funds during fiscal 
year 2010 for nuclear components for the refurbished B61 bomb without 
prior approval also delayed progress on the study.[Footnote 29] For 
example, the NNSA program manager told us that the B61 Project 
Officers Group would have begun an investigation of the extent to 
which nuclear components from some versions of the bomb could be 
reused, had the congressional prohibitions not been in place. In its 
committee report accompanying the Energy and Water Development 
Appropriations Bill, 2010, the House of Representatives Committee on 
Appropriations recommended that no funds be appropriated for the B61 
6.2/6.2A study in the absence of a clearly articulated strategy for 
the bomb.[Footnote 30] With the lifting of this restriction and 
reprogramming of about $53.7 million to the program in August 2010, 
[Footnote 31] however, an NNSA official told us that NNSA has 
developed a recovery plan to put the life extension program back on 
track to meet the 2017 deadline. 

According to DOD and NNSA officials, the B61 Project Officers Group is 
responsible for completing the study and assessing the cost, schedule, 
and performance risk of the recommended design options to completing a 
fullscope life extension program and producing the initial refurbished 
weapons in 2017. The officials told us that, until the group completes 
its study and recommends particular design options to the Nuclear 
Weapons Council for approval, it would be premature to judge whether 
the scope of the study or other factors have placed the future phases 
of the life extension program at risk. However, the officials do 
acknowledge that, at the outset of the study, the scope of the effort 
was highly ambitious given the time that was originally allowed for 
completing the review. 

Future Life Extension Programs Could Be at Risk If Scope and Schedule 
Are Not Reconciled: 

The complications raised by the B61 study's broad scope and narrow 
time frames have implications for future life extension programs. 
Future life extension programs are likely to be increasingly complex. 
According to the April 2010 Nuclear Posture Review Report, every 
weapon currently in the stockpile will require some level of technical 
attention over the next 30 years to extend its service life. The 
Nuclear Posture Review Report also declared the administration's 
intention to study options for ensuring the safety, security, and 
reliability of the weapons on a case-by-case basis when planning 
future life extension programs, including whether to refurbish weapons 
components, reuse nuclear components from previously tested weapons or 
designs, or replace nuclear components with newly manufactured 
components. Adding to the complexity, the report added further the 
administration's intent, beginning with the planned W78 ICBM life 
extension program, to reduce the number of warhead types in the 
stockpile by considering the possibility of using refurbished warheads 
on multiple platforms. 

Moreover, like the B61 life extension program, future life extension 
programs also are likely to occur against the approaching end of the 
existing warhead's service life. The W80-1 cruise missile warhead, for 
example, is expected to begin becoming nonoperable in about 2017 
unless the Air Force replaces key limited-life components in the 
stockpiled weapons, according to the Air Force lead project officer 
for that weapon. Although NNSA expects to begin studying options for 
the W80-1 warhead life extension in the early 2020s, the Nuclear 
Weapons Council has not yet decided whether to authorize a life 
extension program for the warhead. Additionally, the Air Force is now 
leading a concept assessment for the W78 ICBM warhead so that the life 
extension program for the warhead could begin production as early as 
fiscal year 2020.[Footnote 32] According to the Air Force, the W78 
warhead life extension program is needed to meet ICBM operational 
requirements through 2030. 

When faced with the approaching end of the B61 bomb's service life, 
the Nuclear Weapons Council was able to broadly scope the B61 study 
without fully reconciling it to the available time because it was not 
required to do so. In particular, the DOD-DOE Procedural Guideline for 
the Phase 6.X Process does not require the council to consider time 
constraints when requesting a refurbishment study. Officials from the 
Office of the Secretary of Defense, the Air Force, and NNSA agreed 
that the joint Phase 6.X process guidelines should be updated to 
require that the scope of future Phase 6.2 studies reflect time 
constraints for conducting the study. For example, DOD officials told 
us that although the planned concept assessment for the W78 ICBM life 
extension program is expected to help clarify and narrow the scope of 
the requirements and design options that would be evaluated during the 
subsequent Phase 6.2 review, the underlying guidance for implementing 
the Phase 6.X process gives the Nuclear Weapons Council the 
flexibility to scope the Phase 6.2 study as its members see fit. 
Unless DOD and DOE clarify their procedures to require that future 
life extension studies are properly scoped given available time, they 
may set unrealistic goals for future life extension programs and raise 
the risk of delay. 

DOD and NNSA Have Not Planned for Maintaining Operational Nuclear 
Weapons Commitments to NATO if the B61 Life Extension Program Is 
Delayed: 

Although DOD and NNSA expect the B61 study to be completed by 
September 2011, a life extension program delay could affect the U.S. 
pledge to maintain operational nuclear weapons to support its NATO 
commitments. However, DOD and NNSA have not yet prepared a long-term 
risk management plan to help ensure that the United States will be 
able to maintain these commitments should such delays occur. In the 
Nuclear Posture Review Report and in remarks to NATO allies, DOD has 
committed to avoid a gap in its nuclear weapons capability for NATO 
while the B61 bomb's fullscope life extension is under way. However, 
meeting this commitment may prove challenging, as previous nuclear 
weapons life extension programs have experienced schedule delays for a 
variety of reasons. Our prior work has shown that developing a risk 
management plan is a useful program management tool for identifying 
and measuring risks, developing and implementing risk handling 
options, and assessing risk reduction measures.[Footnote 33] NNSA has 
developed a risk management plan designed to keep the life extension 
program on schedule, and NNSA and DOD have developed some risk 
management measures that address near-term operational capability 
risks. However, they have not developed a long-term plan to offer 
options for preserving the ability to maintain the U.S. commitments to 
NATO if the life extension program is delayed or canceled. Developing 
such a plan would help ensure that DOD and NNSA are prepared to take 
the measures necessary to maintain these commitments during the B61 
life extension. Furthermore, without guidance requiring that DOD and 
NNSA prepare such risk management plans, operational requirements for 
other weapons could also be at risk as they go through life extension 
programs, because these weapons are also reaching the end of their 
operational life. 

The United States Has Pledged to Avoid a Capability Gap in Its NATO 
Commitments: 

Recognizing the B61 bomb's importance to NATO security, United States 
officials have stated they will complete the B61 life extension 
program while maintaining the U.S. commitment to NATO. Under National 
Security Presidential Directive 35, the President establishes the 
number and type of weapons the U.S. commits to NATO. The United States 
has demonstrated its commitment to preserving this capability in a 
variety of ways. In 2008, the Nuclear Weapon Council stated that the 
first production target date for the B61 life extension--Phase 6.5 in 
the Phase 6.X process--must ensure that no gap in capability occurs 
with respect to this commitment. In the unclassified April 2010 
Nuclear Posture Review Report, DOD pledged that the B61 life extension 
program would ensure the U.S. capability to deploy these weapons in 
support of NATO commitments, and that the program would enhance the 
bomb's safety and security features in order to maintain the allies' 
confidence in the U.S. deterrent. Further, in June 2010, the Secretary 
of Defense stated to NATO's senior nuclear decision-making body that 
the United States was committed to supporting the current and future 
NATO nuclear weapons requirements during the B61 life extension 
program. Given these commitments, a senior official from the Office of 
the Secretary of Defense told us that failing to perform the B61 life 
extension on schedule could create significant doubt among some NATO 
allies regarding the U.S. intentions to preserve its nuclear security 
guarantees. 

While NATO is currently reviewing its reliance on nuclear weapons, 
officials from DOD and NATO do not expect the alliance to change its 
nuclear weapons requirements in the short term.[Footnote 34] U.S. 
policy emphasizes that change to NATO's nuclear weapons requirements 
should be made based on a thorough review by the alliance and by 
consensus among NATO's 28 members. In November 2010, the NATO 
Secretary General is expected to provide NATO leaders with a revision 
to The Alliance's Strategic Concept, which was last published in 1999. 
[Footnote 35] Given their expectation that NATO members will approve 
the revised Strategic Concept only by consensus, DOD and NATO 
officials told us that they believe the alliance will continue to rely 
on U.S. nuclear weapons commitments to maintain alliance cohesion for 
several reasons. First, the U.S. Secretary of State said in April 
2010, shortly after the Nuclear Posture Review Report's publication, 
that NATO's review should be guided by the principles that NATO will 
remain a nuclear alliance for as long as nuclear weapons exist and, as 
a nuclear alliance, sharing nuclear risks and responsibilities widely 
among members is fundamental.[Footnote 36] Second, the officials told 
us they believed that some NATO members, who joined the alliance since 
the Strategic Concept was last updated, were unlikely to seek changes 
to NATO's nuclear requirements, because they joined the alliance 
specifically because of strong U.S. security guarantees. Third, like 
the U.S. Secretary of State, a group of experts from 12 NATO members-- 
convened by NATO to help revise the Strategic Concept[Footnote 37]-- 
recommended that NATO should continue to maintain secure and reliable 
nuclear weapons capabilities with widely shared responsibility at the 
minimum level required by the prevailing security environment. 
Although officials from DOD and NATO told us that they believed that 
NATO could consider altering specifics about its nuclear posture after 
the Strategic Concept was completed, they stated that the basic 
requirement for the United States to retain the capability to deploy 
nuclear weapons in support of NATO was likely to endure, even if NATO 
changes its policy. 

DOD and NNSA Have Plans to Preserve Operational Requirements over the 
Short Term: 

In light of these commitments, both DOD and NNSA plan to take steps to 
ensure that the nuclear weapons committed to NATO remain operational 
while the B61 life extension program progresses. These steps include 
just-in-time maintenance actions on the existing bombs because 
critical components are expected to soon begin reaching the end of 
their service lives.[Footnote 38] As shown in figure 5, DOD requires 
NNSA to deliver refurbished B61 bombs to meet its NATO commitments in 
2018. To extend the operational life of the bombs committed to NATO 
for a few years while the life extension program is ongoing, the Air 
Force plans to replace key components--neutron generators and power 
supplies--with newer components removed from bombs that are no longer 
in the active stockpile. NNSA is supporting this effort by inspecting 
the components that are to be reintroduced to the weapons and by 
designing and manufacturing the containers, tooling, and related 
hardware needed to retrofit the deployed bombs. 

Figure 5: Key Operational Dates for the B61 Bombs during the Life 
Extension Program: 

[Refer to PDF for image: timeline] 

2008-2011: Study: 

2011-2017: Development and production engineering: 

2011-2015: The Air Force plans to replace limited-life components in 
the B61 bombs committed to NATO to prevent them from becoming 
nonoperational. This action temporarily extends the life of the bombs 
during the planned life extension program. 

2018-2022: Production and delivery: 

2018-2022: DOD requires NNSA to deliver the refurbished B61 bombs that 
are intended to meet NATO commitments. 

Source: GAO analysis of DOD information. 

[End of figure] 

In addition to these planned maintenance actions, NNSA has drafted a 
risk management plan to help ensure that the life extension program 
meets its milestones.[Footnote 39] The plan, which includes the 
generally accepted elements of a risk management approach,[Footnote 
40] is focused on managing the cost, schedule, and performance risks 
to help ensure that the program is completed on time and within 
expected costs. The NNSA project manager for the B61 bomb told us that 
the plan will be updated as the B61 life extension program moves 
through the Phase 6.X process. Successfully executing this risk 
management plan is intended to avoid the operational consequences 
caused by delays to the life extension program, according to the B61 
bomb's project manager, because the NNSA plan would minimize these 
delays. 

NNSA also may design the refurbished B61 bomb so that some types of 
limited-life components could be used both on the existing weapons and 
on the newer version. In particular, the Air Force lead project 
officer and NNSA program manager for the B61 bomb stated that NNSA 
could produce neutron generators that could be used in both the 
existing versions that support NATO, and in the refurbished B61 bomb. 
According to NNSA's project manager for SLBM warheads, NNSA followed a 
similar strategy when it was unable to meet the Navy's production 
requirements during the W76 life extension program; in that instance, 
NNSA produced new neutron generators and took another nonnuclear 
component out of its reserve inventory for the Navy to install in 
existing W76 SLBM warheads. Similarly, if appropriate neutron 
generators are produced and available during the B61 life extension 
program, then they could be installed in the older bombs before the 
existing components reach the end of their service life. However, the 
B61 project manager also told us that the B61 Project Officers Group 
has yet to determine whether power supply requirements for the 
refurbished weapon will be significantly different from the existing 
weapons' requirements; such requirements would depend on other weapons-
design issues that have yet to be settled, according to the official. 
Moreover, NNSA would have to initiate a new production line for the 
power supply components used in the older bombs, because unlike 
neutron generators, NNSA currently is not manufacturing these 
components. Given the complexity of the B61 life extension program 
compared to the W76 life extension program, it is not clear that NNSA 
will design components that could be easily used in both the new and 
old weapons. 

Key Factors Challenge the Commitment to Preserve Operational Nuclear 
Weapons Capability during the Life Extension Program: 

Even as DOD has plans to preserve the U.S. operational capability 
while the life extension program moves forward, preserving this 
capability in the event that the B61 life extension program is delayed 
could prove challenging, given the complexity of the task and the 
tight time lines for completing the program. Nuclear weapons life 
extensions are by their nature complex technical endeavors, and the 
B61 life extension program has a broader scope than prior life 
extensions. According to DOD and NNSA officials, the B61 life 
extension is the most complex life extension effort undertaken by NNSA 
to date. The effort involves replacing three times as many aging 
components as the W76 SLBM warhead life extension program, and NNSA 
has less time to complete the program, according to DOD and NNSA 
officials. The B61 life extension program is expected to produce far 
fewer weapons than did the W76 life extension program; however, NNSA 
has less time--8 years--from the start of the Phase 6.2 study to 
produce the first refurbished B61 bomb, than the 10 years that NNSA 
required to produce the first refurbished W76 SLBM warhead. According 
to the B61 Project Officers Group, this development schedule is 
aggressive. 

Potentially, the B61 life extension program will face key challenges, 
several of which have delayed prior life extension programs. These 
include potential challenges in manufacturing critical materials and 
components; difficulties in meeting production requirements; problems 
with the quality of finished weapons; and coordinating the production 
of bomb components with the Air Force. Because the B61 bomb is 
approaching the end of its operational life during its life extension 
program, the consequences of delays caused by these or other 
challenges could have a greater impact on the weapons' operational 
availability than they had during prior life extension programs. 

* Challenges in manufacturing critical materials and components: NNSA 
could experience challenges in producing key materials and components, 
as it has in prior life extension programs. The W76 SLBM warhead life 
extension program experienced a yearlong delay when NNSA determined 
that it lacked the knowledge, expertise, and facilities to produce a 
key material required for the refurbished warhead. Also, as we found 
in our prior work,[Footnote 41] NNSA experienced significant technical 
challenges when refurbishing secondary components in the strategic 
models of the B61, when testing revealed that NNSA was unable to reuse 
a critical material as planned because it did not function under 
certain conditions. Similar infrastructure-related issues could affect 
the B61 life extension program as well, according to NNSA officials. 
In particular, NNSA's construction of a new Kansas City Plant could 
present challenges for certain production activities in support of the 
B61 life extension program. The current Kansas City Plant, which was 
built in 1943, supplies about 85 percent of the nonnuclear components 
that compose a typical nuclear weapon, including those used in the 
B61. The transition from the old plant to the modern facility is 
scheduled to occur during fiscal years 2013 and 2014 at the same time 
the B61 life extension program will be conducting preproduction 
activities that support the life extension program. According to NNSA 
program officials, this means that some of the preproduction 
activities may have to be conducted at the old plant, then continued 
after the new plant is operating. In 2009, we reported that the 
program to replace the Kansas City Plant had already been delayed by 1 
year.[Footnote 42] If the plant's modernization schedule is delayed 
further, then there could be a risk to completing the first 
refurbished B61 bomb in 2017, according to NNSA officials. However, 
the NNSA officials added that the risks can be managed by thorough 
planning. 

* Difficulties in meeting production requirements: As it has in past 
life extension programs, NNSA may have difficulty meeting production 
requirements to deliver refurbished B61 bombs to DOD on time. For 
example, NNSA and Navy officials involved in the W76 SLBM warhead life 
extension program told us that NNSA was unable to meet the Navy's 
production requirements for refurbished W76 warheads; the Navy 
official explained that funding shortfalls left NNSA unable to 
purchase certain components, obtain necessary tooling, or hire more 
technical personnel needed to increase production rates. Regarding the 
B61 life extension program, after NNSA achieves first production in 
2017--Phase 6.5 in the Phase 6.X process--the agency will require 
additional time to increase its weapons production rate in order to 
produce enough weapons suitable for delivery to DOD beginning in 
fiscal year 2018. However, as of August 2010 DOD and NNSA officials 
were uncertain that NNSA could meet the production rate required to 
meet NATO commitments given the time available to do so. Principally, 
NNSA has not determined how long it will take to achieve a full rate 
of production after reaching Phase 6.5, because the agency has not yet 
finalized the designs for key components that it would have to 
produce, according to NNSA and Air Force officials. Additionally, the 
NNSA program manager for the B61 bomb told us that he did not yet know 
whether NNSA was capable of producing enough weapons in time to meet 
not only DOD's operational requirements, but also NNSA's requirement 
to produce additional weapons for surveillance testing. The NNSA 
official added that DOD established its operational requirements and 
deadlines without considering NNSA's need to produce such weapons. 
However, DOD officials told us simply that DOD and NNSA have not been 
able to come to an agreement on projected out-year production 
requirements. 

* Problems with the quality of finished weapons: Even as the need to 
produce weapons for quality assurance testing could pose challenges, 
the B61 life extension program also could face delays because of 
problems with the finished weapons that are discovered when NNSA 
performs surveillance tests. DOD officials have emphasized the 
importance of a surveillance testing program to ensure that newly 
refurbished bombs and warheads are reliable. In the past, NNSA has 
detected problems resulting from NNSA's manufacturing processes in 
finished warheads resulting in delivery delays to DOD. 

* Coordinating the production of bomb components between NNSA and the 
Air Force: Uncertainty exists that the B61 life extension program will 
be completed on time because doing so will require NNSA and the Air 
Force to synchronize the production of different components of the 
bomb. While NNSA is responsible for refurbishing the bomb's nuclear 
and many of its nonnuclear components, the Air Force is responsible 
for acquiring a new guided tailkit section for the refurbished B61. 
The new bomb tail section is estimated to cost $800 million and is 
designed to increase accuracy, enabling the military to achieve the 
same effects as the older bomb, but with lower nuclear yield. The 
addition of the new tail section also allows NNSA to consolidate the 
different versions of the B61 bomb into a single version. Delivery of 
the refurbished B61 bombs with the new tail section is essential to 
meeting DOD's initial operating requirements to support NATO 
commitments. The Air Force is studying the requirements for the new 
tail section concurrently with the B61 study, and officials told us 
that the Air Force included funding in its budget request for fiscal 
year 2011. However, if the Air Force does not receive adequate funds, 
or the program is canceled altogether, NNSA would have to use a less 
sophisticated tail design in order to produce the first refurbished 
weapon in 2017. If the new tail is only delayed, and not canceled, 
then it could be fitted to the already-refurbished bombs at a later 
time, according to NNSA officials; however, this would involve 
increased cost and logistics efforts. 

DOD and NNSA Have Not Established a Long-Term Plan to Avoid 
Operational Capability Gaps If the B61 Life Extension Program Is 
Delayed: 

Although Air Force and NNSA officials told us that DOD's planned 
measures should mitigate the risk of a capability gap in the U.S. 
commitments to NATO during the B61 life extension program, DOD and 
NNSA have not established a plan to mitigate the long-term operational 
risks to these commitments, should the program be delayed. Our prior 
work shows that risk management is a useful tool that integrates a 
systematic concern for risk into the cycles of decision making. 
[Footnote 43] Risk management principles help organizations to manage 
risk by assessing current threats and vulnerabilities; evaluating, 
selecting, and implementing risk reduction actions; and monitoring 
their implementation. 

DOD and NNSA officials told us that there are several options that 
could be taken to manage the long-term risks to U.S. operational 
commitments. As of September 2010, the official program of record was 
for NNSA to develop options for a fullscope, 30-year life extension of 
the B61 bomb's nuclear and nonnuclear components, as requested by the 
Nuclear Weapons Council in June 2008. However, if the B61 Project 
Officers Group determines that the fullscope life extension is too 
high risk, it could recommend a more limited refurbishment, involving 
the bomb's nonnuclear components and communications systems, according 
to the Air Force's B61 lead project officer and other DOD and NNSA 
officials. The officials told us that while this option would extend 
the operational life of the B61 for several years, it would involve 
significant drawbacks. According to the Air Force lead project officer 
for the B61 bomb, the bomb would require continued patchwork 
maintenance to ensure the bomb's performance, safety, and security, 
even after NNSA completed the more limited refurbishment. 
Additionally, the NNSA would be unable to address the enhanced safety 
and security goals established for the program without making more 
extensive changes to the weapon's design than the limited 
refurbishment would allow. Moreover, according to NNSA, the bomb would 
require a second life extension program beginning in the mid 2020s; 
together, NNSA estimates that performing two life extension programs 
would cost roughly $2 billion more than the currently planned program. 
Moreover, because other nuclear weapons are expected to require 
refurbishment throughout the 2020s, NNSA officials told us that NNSA's 
limited production capacity would make it impractical to perform a 
second life extension effort on the B61 bomb at that time. 

Regardless of the approach that NNSA undertakes for the life extension 
program, DOD and NNSA officials told us that there are options that 
could be taken to mitigate gaps in the U.S. commitments to NATO that 
are caused by delays to the program. These options include changing 
the refurbished weapon's required delivery schedules; allowing the 
bomb's power supply to expire, which reduces the reliability of the 
weapon; and changing the quantity of U.S. nuclear weapons committed to 
NATO. However, as shown in table 3, each of these options has 
considerable drawbacks. 

Table 3: Options for Mitigating a Gap in U.S. Commitments to NATO: 

Option: Change required delivery schedules; 
Description: Currently, DOD requires the delivery of strategic 
versions of the refurbished bombs about 6 months earlier than those 
committed to support NATO. This option reverses these schedules, so 
that the initially refurbished bombs are used to meet U.S. NATO 
commitments if production schedules are delayed. Alternatively, NNSA 
produces and replaces limited-life components for the strategic 
versions of the bomb; 
Principal drawbacks: 
* U.S. Strategic Command would be required to offset lost capabilities 
with other nuclear weapons; 
* Added cost to NNSA for producing and replacing limited life 
components. 

Option: Existing weapons allowed to operate with reduced reliability; 
Description: Power supplies allowed to reach the end of their life; 
Principal drawbacks: 
* According to officials from the Office of the Deputy Assistant 
Secretary of Defense for Nuclear and Missile Defense Policy, this 
option would require "unacceptable" changes to U.S. and NATO policy. 

Option: Change U.S. nuclear weapons posture; 
Description: The U.S. President reduces the number of weapons 
authorized to be committed to support NATO; 
Principal drawbacks: 
* Would require United States to alter the capability to deploy 
weapons to NATO during a crisis; 
* Could reduce opportunities for NATO allies to actively take part in 
the nuclear mission; 
* Could be unsettling to NATO allies. 

Source: GAO analysis of DOD information. 

[End of table] 

Although DOD officials told us that such options could be available to 
DOD as the B61 life extension program moves forward, they added that 
DOD and NNSA have not prepared a long-term risk management plan to 
preserve operational capability. DOD and NNSA have not developed such 
a plan because there is no such requirement in the Procedural 
Guideline for the Phase 6.X Process, the principal document that 
establishes the joint DOD-DOE process for nuclear weapons 
refurbishments. Such a plan would describe the measures that NNSA and 
DOD could take at different points in time to preserve U.S. 
commitments to NATO, should the B61 life extension program be delayed. 
A risk management plan also would identify the resources required to 
manage and mitigate risk, according to the risk management principles 
identified in our prior work. Moreover, according to these principles, 
DOD and NNSA would continuously monitor and update the plan as 
circumstances changed. Lacking a long-term risk management plan, DOD 
may be unprepared to weigh the costs and benefits of potential risk 
management actions. 

DOD and NNSA officials agreed that the B61 Project Officers Group 
should be responsible for preparing a long-term plan to address 
potential operational risks, but they added that the group has not 
done so because it is focused instead on developing the plans and 
approaches for refurbishing the weapon within required time frames. 
According to the NNSA program manager for the B61 bomb, because the 
B61 Project Officers Group is responsible for overseeing activities to 
sustain the B61 bomb as an operational weapon, the group should 
develop a long-term plan for sustaining the weapon's capability as the 
life extension program moves forward. DOD officials agreed that a long-
term risk management plan would help DOD identify how to move forward 
and prepare for potential schedule slippages in the B61 life extension 
program, and begin thinking about options before they were required. 
U.S. European Command officials stated that developing such a plan in 
advance of the life extension program's execution could help DOD and 
NNSA identify steps to be taken--and when to take them--to preserve 
the U.S. nuclear weapons commitments to NATO. 

According to the Risk Management Guide for DOD Acquisition,[Footnote 
44] the alternative to risk management is crisis management, which 
usually involves increased resources and a restricted set of available 
options. An operational risk management plan would help the United 
States to be better prepared to take the steps needed to maintain its 
nuclear weapons commitments to NATO with no gaps in operational 
capability during the B61 life extension program. Moreover, like the 
B61 life extension program, future life extension programs are also 
expected to increasingly be scheduled against rapidly approaching 
service-life deadlines, leaving DOD with fewer options to draw upon in 
order to cover contingencies. Officials from the Office of the 
Secretary of Defense and NNSA agreed that the relevant project 
officers group responsible for preparing the Phase 6.2 study should 
also be responsible for developing plans during that study to manage 
potential operational risks in order to avoid crisis management. An 
Air Force official told us that, unless DOD and NNSA prepare plans to 
mitigate operational risks as they plan and execute future life 
extension programs, the programs could end up adversely affecting 
other nuclear weapons maintenance and sustainment actions as resources 
are reprioritized to meet operational requirements on an emergency 
basis. Unless the Procedural Guideline for the Phase 6.X Process is 
updated to require the preparation of an operational risk mitigation 
plan, operational capability gaps could arise during future life 
extension programs if they experience schedule delays. 

Conclusions: 

Given that future nuclear weapons life extension programs are expected 
to increasingly be scheduled against rapidly approaching service-life 
deadlines, DOD and NNSA will likely face increased risk to their 
ability to complete the programs within available time frames and 
without operational ramifications. We have identified two areas where 
DOD and NNSA can take steps to reduce or manage such risk. First, DOD 
and NNSA may incur undue risk unless the time available to complete a 
life extension program is considered when setting the scope of 
activities to be considered during the program. The joint DOD-DOE 
guidance governing the performance of life extension programs does not 
require the Nuclear Weapons Council to factor in time available to 
complete life extension programs. For example, the Nuclear Weapons 
Council requested an ambitious scope for the study that will be used 
as the basis for the B61 life extension program, in spite of a 
compressed time schedule and potentially significant risk to U.S. 
commitments to its NATO allies. The reasons for this ambitious scope 
were many and included desires to improve nuclear weapons safety, 
minimize maintenance requirements, and exercise NNSA's nuclear weapons 
design and production capabilities. These goals should have been 
weighed against the reality that the B61 life extension program will 
be conducted within very tight time frames to ensure completion before 
the existing weapons begin to become nonoperational. However, the 
Nuclear Weapons Council may not have fully accounted for the time 
available to plan for and complete the life extension program when it 
laid out the broad scope. The B61 Project Officers Group has until 
September 2011 to complete the study and assess the risk of different 
design options. Although we are not making a recommendation that the 
Nuclear Weapons Council revise the scope of this effort to better 
reflect the available time, it is important to note that these actions 
have implications for future life extension programs, which are also 
expected to face highly constrained time lines. Without a requirement 
to factor in the time available to complete future life extension 
programs, the Nuclear Weapons Council may increase the risk that the 
programs will not be properly scoped. 

Second, similar to the B61 life extension program, future nuclear 
weapons life extension programs, including those for weapons deployed 
on ICBMs and submarines, will have their own complexities and 
challenges to overcome. The operational consequences of failing to 
complete these programs on time could be significant, given the 
purposes for which these weapons are deployed. However, the joint DOD- 
DOE guidance governing the performance of life extension programs does 
not require DOD and NNSA to prepare a plan for managing operational 
risks that may occur if a life extension program is delayed. As a 
result, DOD and NNSA have not prepared a long-term risk management 
plan for ensuring operationally capable B61 bombs to support NATO 
commitments throughout the life extension program. Such a plan would 
help ensure that the weapons remain operational throughout the life 
extension program, thus helping preserve the commitment to NATO. 
Looking ahead, unless DOD and DOE take steps to update their guidance 
to reflect the need for such a plan, DOD and NNSA may be required to 
take difficult policy and programmatic actions to preserve operational 
requirements during the execution of the B61 life extension and future 
life extension programs. 

Recommendations for Executive Action: 

We are recommending that the Secretaries of Defense and Energy direct 
the Nuclear Weapons Council to take the following three actions: 

To reduce the risk that future Phase 6.2 studies for nuclear weapons 
life extension programs are not properly scoped given available time 
for completing a life extension, revise the Procedural Guideline for 
the Phase 6.X Process to require that the council factor in the time 
available for completing a life extension program when establishing 
the scope of a Phase 6.2 feasibility study of military performance 
requirements and design options. 

To mitigate the risk that U.S. operational commitments will be 
affected by life extension program schedule delays: 

* Direct the appropriate DOD components, in coordination with NNSA, to 
prepare an operational risk management plan identifying the measures 
that would be required to ensure that the United States is able to 
maintain its commitments to NATO with no gaps in operational 
capability while the B61 life extension program is being carried out. 

* Revise the Procedural Guideline for the Phase 6.X Process to require 
the council to direct the preparation of operational risk management 
plans during the planning and execution of future life extension 
programs. 

Agency Comments and Our Evaluation: 

We provided DOD and NNSA with copies of our draft classified report 
for their review and comment. DOD concurred with all three of the 
recommendations, and identified actions that it would take toward 
implementing each one. NNSA also generally concurred with our report 
and recommendations, but did not comment on specific findings or 
recommendations in the draft report. DOD's comments appear in their 
entirety in appendix II, and NNSA's in appendix III. Both agencies 
also provided technical comments, which we have incorporated into the 
draft as appropriate. 

DOD concurred with our recommendation that the Secretaries of Defense 
and Energy direct the Nuclear Weapons Council to revise the Procedural 
Guideline for the Phase 6.X Process to require that the council factor 
in time available for completing a life extension program when 
establishing the scope of a Phase 6.2 feasibility study. In its 
comments, DOD stated that the Under Secretary of Defense for 
Acquisition, Technology, and Logistics will recommend that the Nuclear 
Weapons Council revise these guidelines to take into consideration the 
available time. However, DOD also commented that while working within 
established time constraints is important, the time available to 
complete a life extension program is one of many competing factors 
that the Nuclear Weapons Council must consider when scoping a Phase 
6.2 study. DOD also commented that the Nuclear Weapons Council should 
avoid placing unnecessary restrictions on exploring the design options 
identified by technical experts early in the study. While we agree 
that the time available to carry out a life extension program is one 
of many competing factors to consider when scoping a Phase 6.2 study, 
and that prudent exploration of design options should not be 
restricted, scoping the study to meet the available time has become 
critical to the success of life extension programs. As we stated in 
our draft report, the broad scope of the B61 Phase 6.2 study 
complicated the study effort, given the limited time for NNSA to 
produce refurbished weapons before the currently deployed B61 bombs 
begin reaching the end of their service life. While it is too soon to 
tell what effect the broad scope will have on the B61 life extension 
program overall, future life extension programs will face similar time 
constraints, as other weapons in the stockpile approach the end of 
their service life. We believe that if the procedural guideline is 
revised and the Nuclear Weapons Council factors time constraints into 
setting the scope of Phase 6.2 studies for future life extension 
programs, the likelihood of success will be improved. 

DOD also concurred with our two recommendations that are intended to 
mitigate the risk that U.S. operational commitments will be affected 
by life extension program schedule delays. First, DOD concurred with 
our recommendation that the Secretaries of Defense and Energy direct 
the appropriate DOD components, in cooperation with NNSA, to prepare 
an operational risk management plan to ensure no gaps in operational 
capability while the B61 life extension program is being carried out. 
In response to this recommendation, DOD stated that the Under 
Secretary of Defense for Acquisition, Technology, and Logistics will 
recommend that the Nuclear Weapons Council formally task the "B61 Life 
Extension Group"[Footnote 45] to provide an operational risk 
assessment plan and mitigation scenarios ensuring there is no gap in 
supporting the NATO nuclear deterrent mission. DOD also concurred with 
our recommendation that the Secretaries of Defense and Energy direct 
the Nuclear Weapons Council to revise the Procedural Guideline for the 
Phase 6.X Process to direct the preparation of operational risk 
management plans during future life extension programs. In its 
comments DOD stated that the Under Secretary for Defense for 
Acquisition, Technology, and Logistics will request that the council 
revise the guideline to require operational risk management plans as 
part of the Phase 6.X process. We agree that DOD's proposed actions to 
provide an operational risk management plan for the B61 life extension 
program as well revise the procedural guideline to require such plans, 
will meet the intent of our recommendations once they are implemented. 

We are sending copies of this report to the appropriate congressional 
committees; the Secretary of Defense; the Secretary of the U.S. Air 
Force; the Chairman, Joint Chiefs of Staff; the Commander, U.S. 
Strategic Command; the Commander, U.S. European Command, and NATO 
Supreme Allied Commander Europe; the Secretary of Energy; and the 
Administrator of the National Nuclear Security Administration. In 
addition, the report will be available at no charge on our Web site at 
[hyperlink, http://www.gao.gov]. 

If you or your staffs have any questions about this report, please 
contact Gene Aloise at (202) 512-3841 aloisee@gao.gov or John 
Pendleton at (202) 512-3489 or pendletonj@gao.gov. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. Key contributors to this report are 
listed in appendix IV. 

Signed by: 

Gene Aloise: 
Director, Natural Resources and Environment: 

Signed by: 

John Pendleton: 
Director, Defense Capabilities and Management: 

[End of section] 

Appendix I: Scope and Methodology: 

For this review we addressed the extent to which the Department of 
Defense (DOD) and the National Nuclear Security Agency (NNSA) have (1) 
considered the time available to begin producing refurbished bombs 
when determining the scope of military performance requirements and 
design options for the B61 life extension program; and (2) taken 
actions to avoid operational gaps in U.S. nuclear weapons commitments 
to NATO during the B61 life extension program. For our review of these 
two objectives, we obtained and reviewed key DOD and Department of 
Energy (DOE) documentation for implementing the Phase 6.X process in 
order to understand the roles of the DOD, DOE, Nuclear Weapons 
Council, B61 Project Officers Group, and other organizations 
throughout the B61 life extension process. This documentation 
included: the Joint DOD-DOE Procedural Guideline for Implementing the 
Phase 6.X Process, dated April 2000; DOE's Procedural Guidelines for 
the Phase 6.X Process, dated October 2000, and DOD Instruction 
5030.55, DOD Procedures for Joint DOD-DOE Nuclear Weapons Life Cycle 
Activities, dated January 2001. We obtained and reviewed briefings 
from the Office of the Deputy Assistant to the Secretary of Defense 
for Nuclear Matters, Office of the Deputy Assistant Secretary of 
Defense for Nuclear and Missile Defense Policy, U.S. Strategic 
Command, U.S. European Command, and the Air Force Nuclear Weapons 
Center to understand their roles and responsibilities in the 
management and oversight of the U.S. stockpile, including the Phase 
6.X process. We also reviewed briefings from the NNSA Office of the 
Deputy Administrator for Defense Programs to understand NNSA's role in 
the day-to-day activities of managing the U.S. stockpile and executing 
the B61 life extension program. To provide us with an understanding of 
the role that the B61 bomb plays in U.S. national security, we 
obtained and reviewed briefings from U.S. Strategic Command, U.S. 
European Command, and the North Atlantic Treaty Organization (NATO). 
We also met with the Deputy Assistant Secretary of Defense for Nuclear 
and Missile Defense Policy to discuss how DOD determines requirements 
for nuclear weapons capabilities and force structure, and reviewed 
briefings outlining the roles played by the President, Secretary of 
Defense, and Chairman of the Joint Chiefs of Staff, to prepare 
operational direction and guidance for the employment of nuclear 
weapons. To put the B61 life extension program in a broader 
programmatic context, we reviewed the administration's Nuclear Posture 
Review Report, dated April 2010; the May 2010 Report in Response to 
National Defense Authorization Act Fiscal Year 2010 Section 1251 New 
START Treaty Framework and Nuclear Force Structure Plans; and the 
NNSA's Fiscal Year 2011 Stockpile Stewardship and Management Plan 
Summary, also published in May 2010.[Footnote 46] To provide context 
on the challenges of implementing life extension programs on nuclear 
weapons, we reviewed prior GAO reports, and reviewed the Nuclear 
Weapons Council's annual Report on Stockpile Assessments, which 
include reports by the directors of Sandia, Los Alamos, and Livermore 
National Laboratories on the status of the U.S. stockpile. We also 
obtained and reviewed reports and briefings prepared by the U.S. 
Strategic Command Strategic Advisory Group, and reports prepared by 
the JASON group.[Footnote 47] 

To determine the extent to which DOD and NNSA considered the time 
available to begin producing refurbished B61 bombs when determining 
the scope of the on-going study of military performance requirements 
and design options, we examined both the scope of the study and the 
time frames for performing the B61 life extension program by reviewing 
documents and interviewing officials from both DOD and NNSA. In 
particular, we analyzed the June 2008 memorandum to the Members of the 
Nuclear Weapons Council's Standing and Safety Committee, requesting 
that the B61 Project Officers Group conduct a Phase 6.2/6.2A study, 
evaluate military performance requirements, and recommend design 
options for the B61 life extension program. We reviewed documentation 
for the B61 life extension program from the Office of the Secretary of 
Defense, U.S. Strategic Command, U.S. European Command, U.S. Air 
Forces in Europe, and NATO. To track the B61 Project Officers Group's 
progress in evaluating military performance requirements, we compared 
successive revisions to the refurbished B61 bomb's draft military 
characteristics, and discussed how they have changed with key NNSA and 
Air Force officials, including the official responsible for managing 
the changes to the B61 bomb's requirements. We reviewed relevant 
documents and discussed the challenges of reconciling requirements 
with officials from the Air Force, U.S. European Command, NATO, and 
the NNSA. We also reviewed the Air Force's requirements documentation 
prepared to support the acquisition of a tailkit for the refurbished 
B61 bomb, and determined the linkage of this design option to key DOD 
requirements by obtaining and reviewing documentation from U.S. 
Strategic Command, U.S. European Command, NNSA, and the B61 Project 
Officers Group. We identified and reviewed key NNSA and Air Force 
briefings that evaluated design options for the life extension 
program, and tracked the B61 Project Officers Group's progress in 
narrowing the scope of design options by obtaining and analyzing 
status briefings that the B61 Project Officers Group prepared 
throughout the 6.2/6.2A study for the Nuclear Weapons Council's 
Standing and Safety Committee. We compared the scope of the ongoing 
B61 6.2/6.2A study with the scope of the life extension programs for 
the W87 intercontinental ballistic missile warhead, the W76 submarine-
launched ballistic missile warhead, the W80 cruise missile warhead, 
and the refurbishment of the secondary components of the strategic 
versions of the B61 bomb. We identified the scope of these prior life 
extension programs and refurbishments by obtaining the Nuclear Weapons 
Council's direction to establish the life extension programs and other 
key documentation. We identified criteria for assessing the scope of 
the B61 life extension program study, given available time, by 
reviewing our prior work on best practices for designing evaluations 
and conducting studies.[Footnote 48] To understand the challenges of 
evaluating requirements and design options for the B61 study, we 
traveled to the Air Force Nuclear Weapons Center in Albuquerque, New 
Mexico, to interview the lead project officer of the B61 Project 
Officers Group, and other key officials involved in the preparing the 
B61 bomb's requirements. We interviewed NNSA officials involved in the 
management and oversight of the B61 stockpile, both in NNSA 
headquarters and at the NNSA Service Center in Albuquerque, New 
Mexico. These officials included the NNSA program manager for the B61 
bomb and other officials from NNSA's Office of the Deputy 
Administrator for Defense Programs. We met with senior DOD officials, 
including officials from the Office of the Deputy Assistant to the 
Secretary of Defense for Nuclear Matters; the Office of the Deputy 
Assistant Secretary of Defense for Nuclear and Missile Defense Policy; 
U.S. Strategic Command; U.S. European Command; U.S. Air Forces in 
Europe; and NATO. We visited U.S. Strategic Command in Omaha, 
Nebraska, and met with the U.S. Strategic Command Chief of Staff and 
other senior military officers and civilian officials from the 
command. We also interviewed other DOD officials throughout our work, 
including officials from: the Deputy Director for Strategy and Policy 
(J5), Joint Staff; Defense Threat Reduction Agency; Office of the 
Assistant Chief of Staff of the Air Force for Strategic Deterrence and 
Nuclear Integration. We also analyzed briefings from, and met with, 
the Air Force lead project officers for the B83, W78, W80, and W87 
Project Officers Groups; the Navy lead project officer for the W76 and 
W88 Project Officers Group; the U.S. Army Nuclear and Combating 
Weapons of Mass Destruction Agency, and the NNSA program managers for 
the W76, W78, W80, B83, W87, and W88 nuclear weapon systems. 

To determine the extent to which DOD and NNSA have taken actions to 
avoid operational gaps in U.S. nuclear weapons commitments to NATO 
during the B61 life extension program, we identified U.S. nuclear 
weapons commitments for NATO by reviewing National Security 
Presidential Directive 35, the presidential guidance that establishes 
the required number of nuclear weapons to be committed to NATO; and by 
obtaining and reviewing DOD's requirements for declaring an initial 
operating capability for both strategic and nonstrategic B61 bombs. 
Further, we reviewed key NATO documentation, including The Alliance's 
Strategic Concept, the Nuclear Planning Group's Political Principles 
for Nuclear Planning and Consultation, and High Level Group reports, 
and received briefings from the U.S. European Command and NATO 
outlining these operational requirements. We determined the 
commitments made by the United States to preserve this operational 
capability by reviewing the June 2008 memorandum requesting the start 
of the B61 life extension program study; the April 2010 Nuclear 
Posture Review Report; and the June 2010 speech by the Secretary of 
Defense to NATO. We clarified that we fully understood these 
commitments by interviewing the Deputy Assistant Secretary of Defense 
for Nuclear and Missile Defense Policy and other DOD officials. To 
obtain operational perspectives on these commitments, we traveled to 
Stuttgart, Germany, and Kaiserslautern, Germany, where we met with 
officials from U.S. European Command and U.S. Air Forces in Europe, 
respectively, and visited NATO in Brussels, Belgium, to meet with 
officials from the U.S. Mission to NATO, with an official from NATO's 
Supreme Headquarters, Allied Powers Europe, the NATO Deputy Assistant 
Secretary General for Weapons of Mass Destruction Policy, and a member 
of the NATO International Military Staff. We identified potential 
challenges to the B61 life extension program by reviewing our prior 
work on nuclear weapons life extension programs and by interviewing 
NNSA nuclear weapons program managers, Navy and Air Force lead project 
officers, officials from the Office of the Deputy Assistant to the 
Secretary of Defense for Nuclear Matters, and other DOD officials. To 
identify risk management criteria and the key elements of a risk 
management approach, we used prior GAO work and the Defense 
Acquisition University's August 2006 Risk Management Guide for DOD 
Acquisition. We obtained information on the B61 Project Officers 
Group's overall risk management approach by reviewing the December 
2008 B61 Life Extension Project Risk Management Plan and interviewing 
the NNSA program manager and Air Force lead project officer for the 
B61 bomb. We discussed possible risk mitigation steps in light of the 
potential challenges to the B61 life extension program with officials 
from the Office of the Deputy Assistant to the Secretary of Defense 
for Nuclear Matters; Office of the Deputy Assistant to the Secretary 
of Defense for Nuclear and Missile Defense Policy; U.S. European 
Command; and both DOD and NNSA members of the B61 Project Officers 
Group, including the Air Force lead project officer and the NNSA 
program manager for the B61 bomb. 

We conducted this performance audit from October 2009 to December 2010 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

[Redacted]
Assistant To The Secretary Of Defense: 
Nuclear And Chemical And Biological Defense Programs: 
3050 Defense Pentagon: 
Washington, DC 20301-3050: 

November 17, 2010: 

Mr. John Pendleton: 
Director, Defense Capabilities and Management: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, D.C. 20548: 

Dear Mr. Pendleton: 

This is the Department of Defense (DoD) response to the Government 
Accountability Office (GAO) draft report [redacted] "Nuclear Weapons: 
DoD and NNSA Need To Better Manage Scope of Future Refurbishments and 
Risks to Maintaining U.S. Commitments to NATO," dated October 4, 2010 
(GAO Code 351404). The DoD concurs with all GAO recommendations 
contained in the draft report. We have provided specific comments to 
each recommendation in the enclosed Department of Defense Comments to 
the GAO Recommendations. 

Technical corrections suggested to further enhance the report were 
forwarded under separate cover. If you have any questions, please call 
me at 703-697-1771. The point of contact for this issue is Mr. David 
Court, 703-693-4304, david.eourt@osd.smil.mil or david.court@osd.mil. 

Sincerely, 

Signed by: 

Andrew Weber: 

Enclosure: As stated: 

Unclassified when separated from enclosure. 

[End of letter] 

GAO Draft Report Dated October 4, 2010: 

Nuclear Weapons: 

DOD and NNSA Need to Better Manage Scope of Future Refurbishments and 
Risks to Maintaining U.S. Commitments to NATO: 

Department of Defense Comments to the GAO Recommendations: 

Recommendation 1: The GAO recommends that the Secretaries of Defense 
and Energy direct the Nuclear Weapons Council to revise Procedural 
Guideline for the Phase 6.X Process to require the Council factor in 
the time available for completing a life extension program when 
establishing the scope of a Phase 6.2 feasibility study of military 
performance requirements and design options. (See page 40 of the Draft 
report) 

DOD Response: The Department concurs with the recommendation but 
recognizes that the time available for completing a life extension 
program is one of many competing factors that the Nuclear Weapons 
Council (NWC) must consider when establishing the scope of a Phase 6.2 
feasibility study. The Department considers it important to work 
within established time constraints, but must also avoid unnecessary 
restrictions on design options that are identified by the technical 
experts during the initial study phases. The USD (AT&L) will recommend 
that the NWC revise the Procedural Guideline for the Phase 6.X Process 
to take into consideration the amount of time available for completion 
of the life extension program when assigning the scope of the 6.2 
study. The Department recognizes that the Phase 6.X Process must 
maintain the ability to document deviations with acknowledgment that 
changes within contingency are allowed. 

Recommendation 2: The GAO recommends that the Secretaries of Defense 
and Energy direct the Nuclear Weapons Council to direct the 
appropriate DoD components, in coordination with NNSA, to prepare an 
operational risk management plan identifying the measures that would 
be required to insure that the United States is able to maintain its 
commitments to NATO [redacted] with no gaps in its operational 
capability while the B61 life extension program is being carried out. 
(See page 40 of the Draft report). 

Dod Response: The Department concurs with the recommendation and the 
USD (AT&L) will recommend the NWC formally task the B61 Life Extension 
Group to provide an operational risk assessment plan and mitigation 
scenarios ensuring there is no gap in supporting [redacted]. 

Recommendation 3: The GAO recommends that the Secretaries of Defense 
and Energy direct the Nuclear Weapons Council to revise the Procedural 
Guideline for the Phase 6.X Process to require the Council to direct 
the preparation of operational risk management plans [illegible] the 
planning and execution of future life extension programs. (See page 40 
of the Draft report). 

Dod Response: The Department concurs with the recommendation and the 
USD (AT&L) will request the NWC revise the Procedural Guideline for 
the Phase 6.X Process to require operational risk management plans as 
a part of the Phase 6.X process for the planning and execution of 
future life extension programs. 

[End of section] 

Appendix III: Comments from the National Nuclear Security 
Administration: 

Department of Energy: 
National Nuclear Security Administration: 
Washington, DC 20585: 

November 4, 2010: 

Mr. Gene Aloise: 
Director: 
Natural Resources and Environment: 
Government Accountability Office: 
Washington, DC 20548: 

Dear Mr. Aloise: 

The National Nuclear Security Administration (NNSA) appreciates the 
opportunity to review the Government Accountability Office's (GAO) 
draft report, [redacted] Nuclear Weapons: DOD and NNSA Need to Better 
Manage Scope of Future Refurbishments and Risks to Maintaining U.S. 
Commitments to NATO. We understand that this work was done at the 
request of the Subcommittee on Strategic Forces, Committee on Armed 
Services, House of Representatives, to review the Department of 
Defense's military requirements for nuclear weapons and force 
structure. 

NNSA generally agrees with the report and the recommendations. NNSA 
recognizes that a life extension Phase 6.2 Study is the single 
opportunity to determine a weapon's optimal balance of performance, 
surety, and life-cycle cost over its next 30 to 40 years of stockpile 
service. Hence, we believe it to be the best course of action to 
consider all viable enhancements consistent with schedule, funding and 
acceptable risk as part of the Phase 6.1/6.2 Study. 

Under separate cover we will send technical comments to help clarify 
and improve the report in areas that may be confusing or misleading. 

If you have any questions related to this response, please contact 
JoAnne Parker, Director, Office of Internal Controls, at 202-586-1913. 

Sincerely, 

Signed by: 

Gerald L. Talbot, Jr. 
Associate Administrator for Management and Administration: 

cc: Deputy Administrator for Defense Programs: 

[End of section] 

Appendix IV: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Gene Aloise (202) 512-3841 or aloisee@gao.gov: 

John H. Pendleton (202) 512-3489 or pendletonj@gao.gov: 

Staff Acknowledgments: 

In addition to the contacts named above, Jonathan M. Gill, Assistant 
Director; Penney Harwell Caramia, Assistant Director; Colin L. 
Chambers; Grace A. Coleman; David G. Hubbell; Katherine S. Lenane; 
Gregory A. Marchand; Kevin L. O'Neill, Analyst in Charge; Timothy M. 
Persons; Steven R. Putansu; Robert Robinson; Jeff R. Rueckhaus; and 
Rebecca Shea also made key contributions to this report. 

[End of section] 

Footnotes: 

[1] Section 1070 of the National Defense Authorization Act for Fiscal 
Year 2008, Pub. L. No. 110-181 (2008), required the Secretary of 
Defense, in consultation with the Secretary of Energy and Secretary of 
State, to conduct a comprehensive review of the nuclear posture of the 
United States for the next 5 to 10 years. DOD published the 
conclusions and recommendations from that review in the April 2010 
Nuclear Posture Review Report. 

[2] On November 19, 2010, shortly after we received comments on our 
draft report, NATO members completed this review and adopted a new 
Strategic Concept. 

[3] The planned life extension program covers the B61-3, B61-4, B61-7, 
and B61-10 versions, but does not cover the B61-11 version. 

[4] A fullscope life extension would include the refurbishment of the 
bomb's nuclear components and nonnuclear components, whereas a limited 
life extension would include only the nonnuclear components. 

[5] The Energy and Water Development and Related Agencies 
Appropriations Act, 2010, restricted NNSA from obligating or expending 
funds for "B61-12" nuclear components without prior approval of the 
Appropriations Committees. Pub. L. No. 111-85, 123 Stat. 2866 (2009). 

[6] White House, Report in Response to Fiscal Year 2010 National 
Defense Authorization Act Section 1251 New START Treaty Framework and 
Nuclear Force Structure Plans, May 13, 2010. 

[7] GAO, Nuclear Weapons: Improved Management Needed to Implement 
Stockpile Stewardship Program Effectively, [hyperlink, 
http://www.gao.gov/products/GAO-01-48] (Washington, D.C.: Dec. 14, 
2000). 

[8] GAO, Nuclear Weapons: NNSA and DOD Need to More Effectively Manage 
the Stockpile Life Extension Program, [hyperlink, 
http://www.gao.gov/products/GAO-09-385] (Washington, D.C.: Mar. 2, 
2009). 

[9] As of September 30, 2009, the U.S. stockpile totaled 5,113 
warheads, including deployed weapons, spares, and warheads kept in 
reserve for operational crises or to replace weapons that have become 
unreliable due to aging or other defects. "Operationally deployed" 
weapons are those that are deployed on either ICBMs in their launchers 
or on SLBMs onboard submarines, and nuclear armaments loaded on 
bombers, or stored in weapons storage areas on bomber bases. 

[10] Although NATO has no standing operational plans for the use of 
nuclear weapons, the United States and certain NATO allies provide 
forces and are required to maintain the ability to be on alert for 
nuclear operations within a 30-day, 180-day, or 365-day period. 

[11] We reviewed this refurbishment in our prior work. See GAO-09-385. 

[12] Department of Defense and Department of Energy, Procedural 
Guideline for the Phase 6.X Process (Washington, D.C.: Apr. 19, 2000). 

[13] The Nuclear Weapons Council membership includes the Under 
Secretary of Defense for Acquisition, Technology and Logistics 
(chair), the Under Secretary of Defense for Policy, the Vice Chairman 
of the Joint Chiefs of Staff, the Commander of U.S. Strategic Command, 
and the Under Secretary for Nuclear Security of the Department of 
Energy (dual-hatted as the Administrator of the National Nuclear 
Security Administration). 10 U.S.C. § 179. 

[14] Although the Phase 6.X process begins with activities under Phase 
6.1, DOD officials told us that life extension programs formally begin 
with a Phase 6.2 study authorization from the Nuclear Weapons Council, 
after weapons needing a life extension have been identified in Phase 
6.1. 

[15] A "project officers group" is a group of DOD and DOE personnel 
assigned to coordinate the development and compatibility assurance of 
a designated nuclear weapon system and its associated interfaces. 

[16] The B61-11 entered the stockpile in the 1990s and was not 
included as part of the scope of the life extension program. 

[17] According to the B61 Project Officers Group, the congressional 
direction to initially limit the scope of the study extended the time 
required to complete the study for a fullscope life extension program. 
In August 2010, the project officers group informed the Standing and 
Safety Committee that the study would be completed by September 2011. 

[18] Although we recognize the distinctions among different life 
extension approaches that would "refurbish," "reuse," or "replace" 
nuclear weapons components, we use the expression "refurbished B61 
bomb" throughout this report in a generalized way to distinguish the 
resulting B61 weapon from the existing versions currently in the 
stockpile, and the term "refurbishment" to refer to the B61 life 
extension program itself. 

[19] GAO, Designing Evaluations, [hyperlink, 
http://www.gao.gov/products/GAO/PEMD-10.1.4] (Washington, D.C.: May 
1991). 

[20] The Supreme Headquarters, Allied Powers Europe, is the 
Headquarters of Allied Command Operations, one of NATO's two military 
commands, and is responsible for all alliance military operations. 

[21] The currently deployed B61 bombs use a parachute to slow the bomb 
in midair and allow time for delivery aircraft to exit the targeted 
area before the bomb detonates. 

[22] The guided tailkit section is a nonnuclear component that will 
replace the existing parachute and is intended to allow for increased 
aircraft survivability, safer delivery profiles, and more space for 
additional components, such as safety and security enhancements. 

[23] The F-35 is the U.S. Air Force's next-generation fighter 
aircraft. The United States and other NATO allies are currently 
planning to use the F-35 for nuclear operations when it becomes 
available later this decade. 

[24] Nuclear Weapons Council Standing and Safety Committee, Memorandum 
for Director, Strategic Systems Program Office, Subject: W76/MK4 RBA 
Phase 6.2/6.2A Life Extension Study, August 6, 1998. 

[25] According to a Navy official, some improvements to the W76 
warhead's safety and security features were also made during the 
refurbishment. 

[26] In the late 1990s, DOD and NNSA initiated a life extension 
program for the W80-1 cruise missile, which is designed for employment 
on air-launched cruise missiles. Although the W80 Project Officers 
Group completed the Phase 6.2 study for the life extension, and NNSA 
was preparing for production, the Nuclear Weapons Council canceled the 
effort in May 2006 after DOD re-evaluated its cruise missile force 
structure requirements. 

[27] National Security Presidential Directive 28, issued in 2003, 
called for upgrading, where appropriate, safety and use control 
capabilities for all nuclear warheads during their refurbishment. 

[28] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: Mar. 2009). 

[29] Pub. L. No. 111-85, 123 Stat. 2866 (2009). 

[30] H.R. Rep. No. 111-203, at 129 (2009). 

[31] Of this amount about, $39.6 million will support the B61 life 
extension study, and about $14.1 million will be used to replenish the 
stockpile systems account that was used to support the nonnuclear 
portions of the study. 

[32] Associate Air Force Chief of Staff for Strategic Deterrence and 
Nuclear Integration, Memorandum for Chairman, Nuclear Weapons Council 
Standing and Safety Committee, Subject: W78 Life Extension Program 
Phase 6.1 Study, August 18, 2010. 

[33] GAO, Homeland Defense: Greater Focus on Analysis of Alternatives 
and Threats Needed to Improve DOD's Strategic Nuclear Weapons 
Security, [hyperlink, http://www.gao.gov/products/GAO-09-828] 
(Washington, D.C.: Sept. 18, 2009). 

[34] In November 2010, as we were preparing to publish the classified 
version of this report, NATO completed its review and published a new 
Strategic Concept. Regarding NATO's nuclear posture, the revised 
strategic concept states that deterrence, based on an appropriate mix 
of nuclear and conventional capabilities, remains a core element of 
NATO's overall strategy and that as long as nuclear weapons exist, 
NATO will remain a nuclear alliance. See NATO, Active Engagement, 
Modern Defense: Strategic Concept for the Defense and Security of the 
Members of the North Atlantic Treaty Organization, Adopted by the 
Heads of State and Government in Lisbon (Nov. 2010). 

[35] NATO, The Alliance's Strategic Concept, Approved by the Heads of 
State and Government participating in the meeting of the North 
Atlantic Council in Washington, D.C. (Apr. 1999). 

[36] Five Points on NATO Nuclear for the Secretary's Intervention at 
Tallinn, Apr. 22, 2010, Tallinn, Estonia. 

[37] NATO, NATO 2020: Assured Security; Dynamic Engagement, Analysis 
and Recommendations of the Group of Experts on a New Strategic Concept 
for NATO, May 17, 2010. 

[38] In contrast, the strategic B61-7 version of the bomb faces end-of-
life issues later. 

[39] NNSA, B61 Life Extension Project Risk Management Plan 
(Albuquerque, New Mexico: Dec. 10, 2008). 

[40] The five elements of a risk management approach are: setting 
strategic goals, objectives, and determining constraints; assessing 
risk; evaluating alternatives for addressing risks; selecting 
alternatives; and implementation and monitoring. See [hyperlink, 
http://www.gao.gov/products/GAO-09-828]. 

[41] [hyperlink, http://www.gao.gov/products/GAO-09-385]. 

[42] GAO, Nuclear Weapons: National Nuclear Security Administration 
Needs to Better Manage Risks Associated with Modernization of Its 
Kansas City Plant, [hyperlink, http://www.gao.gov/products/GAO-10-115] 
(Washington, D.C.: Oct. 23, 2009). 

[43] [hyperlink, http://www.gao.gov/products/GAO-09-828]. 

[44] Department of Defense, Defense Acquisition University, Risk 
Management Guide for DOD Acquisition, Sixth Edition, Version 1.0 (Fort 
Belvoir, Va.: Aug. 2006). 

[45] The B61 Life Extension Group is a subgroup of the B61 Project 
Officers Group, according to the Air Force lead project officer of the 
B61 bomb. 

[46] Department of Energy, National Nuclear Security Administration, 
Fiscal Year 2011 Stockpile Stewardship and Management Plan Summary 
(Washington, D.C.: May 2010). 

[47] JASON is an independent group of accomplished scientists that 
advises the U.S. government on matters of science and technology. The 
name "JASON" is not an acronym. Its sponsors include DOD, DOE, and the 
U.S. Intelligence Community. 

[48] GAO, Designing Evaluations, [hyperlink, 
http://www.gao.gov/products/GAO-PEMD-10.1.4 (Washington, D.C.: May 
1991). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: