This is the accessible text file for GAO report number GAO-11-48 
entitled 'Neighborhood Stabilization Program: HUD and Grantees Are 
Taking Actions to Ensure Program Compliance but Data on Program 
Outputs Could be Improved' which was released on December 17, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
GAO: 

Report to Congressional Committees: 

December 2010: 

Neighborhood Stabilization Program: 

HUD and Grantees Are Taking Actions to Ensure Program Compliance but 
Data on Program Outputs Could be Improved: 

GAO-11-48: 

GAO Highlights: 

Highlights of GAO-11-48, a report to congressional committees. 

Why GAO Did This Study: 

Congress created the Neighborhood Stabilization Program (NSP) to help 
reduce the number of foreclosed and abandoned properties and restore 
depressed local housing markets. The Housing and Economic Recovery Act 
of 2008 (HERA) authorized the program’s first round (NSP 1), providing 
$3.92 billion in grant funds to states and local governments. The 
Department of Housing and Urban Development (HUD) administers the 
program. HERA mandated that GAO report on whether grantees were using 
NSP 1 funds in accordance with the act’s criteria. For this mandate, 
GAO examined (1) grantees’ progress and challenges in meeting NSP 1 
obligation and income-targeting requirements, (2) HUD’s actions to 
mitigate program risks and ensure grantees’ compliance with key NSP 1 
requirements, and (3) HUD’s efforts to collect program data and assess 
program performance. To address these objectives, GAO analyzed HUD 
data and the information system used for NSP 1; interviewed HUD 
officials and representatives of NSP 1 grantees; analyzed HUD’s 
internal control processes; and conducted limited tests of 8 grantees’ 
compliance with key NSP 1 requirements. 

What GAO Found: 

According to HUD data, the vast majority of the 309 NSP 1 grantees 
obligated their funds within the required 18-month time frame. As a 
result, over 99 percent of NSP 1 funds were obligated as of early 
October 2010. Also, consistent with HERA criteria, most grantees 
obligated at least 25 percent of their funds for housing for low-
income households. Some grantees with whom GAO spoke modified their 
NSP 1 strategies to meet obligation deadlines and overcome other 
challenges such as competition from private investors in acquiring 
foreclosed and abandoned homes. For instance, with HUD approval, some 
grantees expanded the geographic areas they were targeting. Grantees 
also participated in banks’ “first look” programs, which give grantees 
the chance to bid on bank-owned properties before other potential 
buyers. 

HUD provided training, guidance, and technical assistance to grantees 
to address new requirements and risks posed by NSP 1. Although the 
grantees GAO spoke with were generally satisfied with HUD’s guidance 
and program support, some said these efforts would have been more 
useful if provided earlier. HUD officials said that some of the 
assistance grantees found useful was delivered using funds that HUD 
received well after the start of NSP 1. HUD also established various 
internal control processes for NSP 1 and hired additional staff to 
help oversee the program. HUD field office staff conducted remote 
monitoring of all grantees and on-site monitoring for 176 grantees 
that HUD considered to be higher risk. Although HUD is still 
aggregating the results of its on-site monitoring, available results 
from the four field offices GAO contacted generally showed compliance 
with key NSP 1 requirements but also found some financial management 
deficiencies. HUD is requiring grantees to take corrective actions, 
where appropriate. GAO’s review of records for 32 properties at 8 
grantees found no instances of significant noncompliance with key NSP 
1 requirements. 

To collect information on NSP 1, HUD adapted an existing financial and 
information system—the Disaster Recovery Grant Reporting (DRGR) system—
and provided training and guidance on its use. HUD has used the system 
to monitor NSP 1 grantees’ obligations and summarize program outputs 
for specific types of activities (rehabilitation and construction, 
demolition, and homeownership assistance). However, variation in the 
way grantees entered information into DRGR makes it difficult to 
summarize outputs for each activity (e.g., housing units acquired) 
without undercounting, and overall outputs (e.g., total benefiting 
households) without overcounting. HUD has developed a method for 
addressing the overcounting problem, but insufficient guidance to 
grantees and HUD field staff may be contributing to variation in data 
entry that limits the usefulness of DRGR output information. For 
example, HUD has not provided grantees with specific written guidance 
on selecting output measures, which can lead to inconsistency among 
grantees. HUD is planning an assessment of NSP outcomes that will 
focus primarily on the program’s second round (NSP 2) but will also 
include NSP 1 in geographic areas where the two phases of the program 
overlap. 

What GAO Recommends: 

GAO recommends that HUD provide additional guidance to NSP grantees 
and HUD field staff to help ensure that information on output measures 
is collected in HUD’s data system in a more consistent manner. HUD 
agreed with the report’s recommendations. 

View [hyperlink, http://www.gao.gov/products/GAO-11-48] or key 
components. For more information, contact Mathew Scirè at (202) 512-
8678 or sciremj@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

NSP 1 Grantees Overcame Challenges and Used a Variety of Strategies to 
Meet Obligation and Income-Targeting Requirements: 

HUD Has Taken Actions to Mitigate NSP 1 Program Risks through 
Training, Technical Assistance, and the Establishment of Internal 
Controls: 

HUD Adapted an Information System for NSP 1, but Data on Program 
Outputs Have Limitations: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: Comments from the Department of Housing and Urban 
Development: 

Appendix III: GAO Contact and Staff Acknowledgments: 

Table: 

Table 1: Activities Reviewed for 32 NSP 1 Properties: 

Figures: 

Figure 1: NSP 1 Implementation Time Line: 

Figure 2: Total NSP 1 State and Local Government Allocations, by State: 

Figure 3: NSP 1 Grantees' Obligations as of June 24, 2010, and as of 
October 1, 2010: 

Figure 4: Reported NSP 1 Grantee Obligations by Activity, as of 
October 1, 2010: 

Figure 5: States' Reallocation of NSP 1 Funds to Units of Local 
Government That also Received Funds Directly from HUD: 

Figure 6: NSP Strategies for Acquiring and/or Rehabilitating Homes: 

Figure 7: Selected HUD Internal Controls for NSP 1: 

Figure 8: Program Requirements and Controls We Reviewed: 

Abbreviations: 

AMI: area median income: 

ARRA: American Recovery and Reinvestment Act of 2009: 

CDBG: Community Development Block Grant: 

CPD: Office of Community Planning and Development: 

DRGR: Disaster Recovery Grant Reporting: 

FERA: front-end risk assessment: 

HERA: Housing and Economic Recovery Act of 2008: 

HUD: Department of Housing and Urban Development: 

NOFA: Notice of Funding Availability: 

NCST: National Community Stabilization Trust: 

NSP: Neighborhood Stabilization Program: 

OIG: Office of the Inspector General: 

PD&R: Office of Policy Development and Research: 

QPR: Quarterly Performance Report: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

December 17, 2010: 

The Honorable Christopher J. Dodd: 
Chairman: 
The Honorable Richard C. Shelby: 
Ranking Member: 
Committee on Banking, Housing, and Urban Affairs: 
United States Senate: 

The Honorable Barney Frank: 
Chairman: 
The Honorable Spencer Bachus: 
Ranking Member: 
Committee on Financial Services: 
House of Representatives: 

In recent years, declining home prices and weak economic conditions 
have contributed to a surge in vacant and foreclosed properties that 
has negatively impacted many communities across the United States. 
Such properties can destabilize neighborhoods by lowering the value of 
surrounding homes and attracting crime. They also can impose costs on 
communities, for example by reducing property tax revenue and 
straining the resources of local police and code enforcement offices. 
To address these issues, Congress created the Neighborhood 
Stabilization Program (NSP), which provides grants to states and local 
governments to help reduce the number of foreclosed and abandoned 
properties and restore depressed local housing markets. The first 
phase of this program, NSP 1, was authorized by the Housing and 
Economic Recovery Act of 2008 (HERA), which provided $3.92 billion in 
grant funds.[Footnote 1] The program is administered by the Department 
of Housing and Urban Development (HUD) through its existing Community 
Development Block Grant (CDBG) program.[Footnote 2] In October 2008, 
HUD allocated NSP 1 funds to 309 CDBG grantees, including all 50 
states.[Footnote 3] Under NSP 1, state grantees may use funds directly 
or reallocate them to local governments within their states. 

HERA defines a variety of "eligible uses" of NSP 1 funds to allow 
grantees to address issues associated with foreclosed and abandoned 
properties. For example, grantees may choose to acquire and 
rehabilitate properties for rental or resale, or demolish blighted 
structures. HERA also imposed several key requirements governing the 
use of NSP 1 funds. For example, grantees must use the funds in "areas 
of greatest need" within 18 months of receiving them from HUD; for 
this requirement, HUD interpreted "use" to mean obligate. In addition, 
HERA required that all NSP 1 funds benefit households with incomes at 
or below 120 percent of area median income (AMI), and at least 25 
percent of the funds benefit households with incomes at or below 50 
percent of AMI; for the 25 percent requirement, HUD interpreted "use" 
to mean expended. 

HERA mandated that GAO conduct periodic audits of whether NSP 1 funds 
are being used in a manner consistent with criteria set forth in HERA. 
This review examines (1) grantees' progress and challenges in meeting 
HERA obligation time frames and income-targeting criteria, (2) HUD's 
actions to mitigate program risks and ensure grantees' compliance with 
key NSP 1 requirements, and (3) HUD's efforts to collect program data 
and assess program performance. 

To review grantees' progress and challenges in meeting HERA obligation 
time frames and income-targeting criteria, we analyzed HUD data on 
program obligations and grantees' uses of funds. We reviewed state 
grantees' action plans and reports on NSP 1 activities to determine 
the methods states used to distribute NSP 1 funds to subrecipients, 
and the factors they considered in making these decisions. We analyzed 
Disaster Recovery Grant Reporting (DRGR) data to determine the extent 
to which the subrecipients also received NSP 1 funds directly from 
HUD. We spoke with selected grantees to discuss their approaches to 
using NSP 1 funds and the challenges they faced in implementing the 
program. 

To determine the actions HUD has taken to mitigate program risks and 
ensure grantees' compliance with key NSP 1 requirements, we reviewed 
NSP 1 regulations and guidance, examined HUD's efforts to oversee the 
use of NSP 1 funds and provide technical assistance to grantees, and 
interviewed HUD headquarters and field office officials and 
representatives of selected grantees. In addition, we reviewed HUD's 
guidance and procedures for monitoring grantee compliance with program 
requirements and obtained and summarized on-site monitoring results 
(as of September 15, 2010) from four HUD field offices responsible for 
overseeing grantees we visited. We also conducted limited tests of 
selected grantees' compliance with key NSP 1 requirements and relevant 
internal controls through reviews of property-level records of 
completed NSP 1 activities (see discussion of site visits below). 
Additionally, we spoke with staff from the HUD Office of the Inspector 
General (OIG) about their NSP-related audits and reviewed the results 
of their completed audits. 

To review HUD's efforts to collect program data and to assess the 
reliability of the data, we reviewed HUD OIG audits of the information 
system HUD adapted for NSP 1 (the DRGR system) and HUD documentation 
and guidance for using the system. We also interviewed HUD and grantee 
staff responsible for entering and monitoring DRGR data. We also 
assessed the reliability of the DRGR information we used by conducting 
reasonableness checks to identify any missing or erroneous data and by 
interviewing knowledgeable HUD officials to ensure we interpreted the 
data correctly. For the purpose of this and the first objective, we 
concluded that the data we used were sufficiently reliable for our 
purposes. To review HUD's efforts to assess program performance, we 
interviewed HUD's Office of Policy Development and Research and Office 
of Community Planning and Development (CPD) staff knowledgeable of a 
planned NSP assessment. 

To address all of our objectives, we interviewed representatives from 
18 NSP 1 grantees. We interviewed a group of 11 grantees selected to 
represent different housing markets, grant amounts, and grantee types 
to discuss their approaches for using NSP 1 funds, progress they had 
made, and challenges they faced in implementing the program. We 
conducted site visits at another group of 8 grantees selected to 
represent a variety of completed NSP 1 activities, types of grantees, 
and geographic areas.[Footnote 4] To avoid overburdening grantees, we 
focused our site visits on grantees that, on the basis of information 
from HUD, were not receiving extensive technical assistance or being 
monitored on-site by HUD staff. At these sites, we interviewed grantee 
staff to obtain information on their processes for complying with NSP 
1 requirements and internal control procedures, and reviewed property- 
level records of completed NSP 1 activities. We also interviewed staff 
from four HUD field offices: Columbus, Ohio; Miami, Florida; 
Philadelphia, Pennsylvania; and San Francisco, California. Appendix I 
contains a more detailed description of our scope and methodology and 
a list of NSP 1 grantees we contacted. 

We conducted our work in two phases. We did our initial audit work 
(April through December 2009) in Washington, D.C., and at 15 sites 
across the United States, including Florida, Indiana, Maryland, 
Nevada, Pennsylvania, and Virginia. This work resulted in briefings to 
your staff in December 2009 on the status of HUD's and grantees' 
initial implementation of NSP 1. The second phase of our NSP 1 work 
was conducted in Washington, D.C., and at 8 sites across the United 
States, including locations in Arizona, Florida, Ohio, Pennsylvania, 
and Virginia from January through December 2010. This report focuses 
on the results of our audit work during the second phase. We conducted 
all of our NSP 1 work in accordance with generally accepted government 
auditing standards. Those standards require that we plan and perform 
the audit to obtain sufficient, appropriate evidence to provide a 
reasonable basis for our findings and conclusions based on our audit 
objectives. We believe that the evidence obtained provides a 
reasonable basis for our findings and conclusions. 

Background: 

Congress established NSP to try to reduce inventories of foreclosed 
homes by providing funding to state and local governments to, among 
other things, acquire and rehabilitate or demolish foreclosed and 
abandoned homes. HERA allows grantees to use NSP 1 funds to: 

* establish financing mechanisms for the purchase and redevelopment of 
foreclosed homes and residential properties; 

* purchase and rehabilitate homes and residential properties that have 
been abandoned or are in foreclosure in order to sell, rent, or 
redevelop them; 

* establish land banks for foreclosed homes and residential properties; 

* demolish blighted structures; and: 

* redevelop demolished or vacant properties.[Footnote 5] 

Land banks are governmental or nongovernmental nonprofit entities 
established, at least in part, to assemble, temporarily manage, and 
dispose of vacant land for the purpose of stabilizing neighborhoods 
and encouraging reuse or redevelopment of urban property. Land banks 
often acquire properties through tax foreclosures, intergovernmental 
transfers, nonprofit transfers, and open-market purchases but can also 
acquire them through foreclosure. 

In addition to these five eligible uses, HERA outlined the following 
key requirements for using NSP 1 funds, as follows: 

1. All NSP 1 funds must be used within areas of greatest need as 
determined by grantees on the basis of the following factors: 

* percentage of foreclosures, 

* percentage of homes financed by subprime loans, and: 

* likelihood of a significant rise in the rate of foreclosures. 

2. All NSP 1 funds must be used to benefit households with incomes at 
or below 120 percent of AMI. 

3. At least 25 percent of NSP 1 funds must benefit households with 
incomes at or below 50 percent of AMI. 

4. The sale, rental, or redevelopment of abandoned and foreclosed 
homes must remain affordable to the above income groups for the 
longest feasible term. 

5. All NSP 1 funds must be used (obligated) by grantees within 18 
months of their receipt. 

6. All properties must be acquired at a discount established by HUD. 

7. If a property is sold to an individual as a primary residence, the 
sale price cannot be more than the total acquisition and redevelopment 
costs. 

In October 2008, HUD issued guidance on implementing NSP 1 in a Notice 
in the Federal Register.[Footnote 6] With respect to the requirement 
that NSP 1 funds be used within 18 months, HUD stated, "funds are used 
when they are obligated by a state, unit of general local government, 
or any subrecipient thereof for a specific NSP activity; for example 
the acquisition of a specific property." According to the Notice, 
funds are considered to be obligated for an activity when orders are 
placed, contracts are awarded, and goods and services are received. 
HUD specified that funds are not obligated for an activity when 
subawards (for example, grants to subrecipients or units of local 
government) are made. The Notice also stated that grantees must expend 
their NSP 1 funds within 4 years of receipt. In accordance with HERA, 
HUD established a required discount rate that would apply to any 
property acquired through NSP 1. Initially, HUD set the discount at 15 
percent for grantees' total acquisition portfolios but subsequently 
reduced it to 1 percent per property acquired.[Footnote 7] HUD reduced 
the required discount to provide grantees with more flexibility in 
acquiring foreclosed properties and to avoid the potentially adverse 
impact of discounts on neighborhood property values. Among other 
provisions, HUD required that each NSP-assisted homebuyer complete at 
least 8 hours of homebuyer counseling. 

HUD also required that NSP 1 grantees submit "NSP 1 action plans" in 
the form of substantial amendments to their existing CPD consolidated 
plan.[Footnote 8] HUD required grantees to identify in these plans 
areas of greatest need within their states or communities, approaches 
for implementing NSP 1 and expected program outputs, and plans for 
complying with key requirements. After grantees submitted these plans 
and HUD approved them, HUD executed grant agreements for NSP 1. 

NSP 1 implementation has a tight time frame (see figure 1). For 
instance, HUD had to establish its formula for allocating funds 60 
days after the enactment of HERA. As HERA linked NSP 1 to CDBG, HUD 
was able to take advantage of the administrative infrastructure of one 
of the federal government's largest and most flexible community and 
economic development programs. Established in 1974, CDBG provides 
states and local entitlement communities--eligible metropolitan cities 
and counties--with funding to address locally determined community and 
economic development priorities.[Footnote 9] CDBG funds may be used to 
rehabilitate housing, improve infrastructure, provide job training, 
and fund other community-determined projects.[Footnote 10] 

Figure 1: NSP 1 Implementation Time Line: 

[Refer to PDF for image: time line] 

October 2008: 
$3.92 billion allocated to grantees by HUD formula. 

December 2008: 
Grantees submitted NSP 1 substantial amendments for approval. 

March 2009: 
Grant agreements signed. 

September 2010: 
Deadline to obligate NSP 1 funds[A]. 

March 2013: 
Deadline to expend NSP. 

Source: GAO analysis of HUD information. 

[A] A grantee's specific deadline depended on the date it received NSP 
1 funds from HUD, so obligation deadlines varied among grantees. 
According to HUD, 300 NSP 1 grantees had obligation deadlines expiring 
in September 2010. The obligation deadlines for the remaining grantees 
were some time in August, October, or November 2010. 

[End of figure] 

In accordance with the time frames and criteria established by HERA, 
in October 2008 HUD allocated NSP 1 funds using formulas based on the 
number and percentage of the following: 

* foreclosed homes in each state or locality, 

* subprime mortgages in each state or locality, and: 

* homes in default or delinquency in each state or locality.[Footnote 
11] 

As required by HERA, all 50 state governments and Puerto Rico received 
an allocation of at least $19.6 million. HUD also allocated NSP 1 
funds to local (city and county) governments.[Footnote 12] Figure 2 
shows the total state and local government allocations for each state. 

Figure 2: Total NSP 1 State and Local Government Allocations, by State: 

[Refer to PDF for image: illustrated U.S. map and associated vertical 
bar graph] 

State: Florida; 
Total NSP 1 State and Local Government Allocations: $541.4 million. 

State: California; 
Total NSP 1 State and Local Government Allocations: $529.6 million. 

State: Michigan; 
Total NSP 1 State and Local Government Allocations: $263.6 million. 

State: Ohio; 
Total NSP 1 State and Local Government Allocations: $258.1 million. 

State: Texas; 
Total NSP 1 State and Local Government Allocations: $178.1 million. 

State: Illinois; 
Total NSP 1 State and Local Government Allocations: $172.5 million. 

State: Georgia; 
Total NSP 1 State and Local Government Allocations: $153.0 million. 

State: Indiana; 
Total NSP 1 State and Local Government Allocations: $151.9 million. 

State: Arizona; 
Total NSP 1 State and Local Government Allocations: $121.1 million. 

State: New York; 
Total NSP 1 State and Local Government Allocations: $100.3 million. 

State: Pennsylvania; 
Total NSP 1 State and Local Government Allocations: $88.1 million. 

State: Tennessee; 
Total NSP 1 State and Local Government Allocations: $72.5 million. 

State: Nevada; 
Total NSP 1 State and Local Government Allocations: $71.9 million. 

State: Missouri; 
Total NSP 1 State and Local Government Allocations: $64.9 million. 

State: New Jersey; 
Total NSP 1 State and Local Government Allocations: $64.0 million. 

State: Minnesota; 
Total NSP 1 State and Local Government Allocations: $57.8 million. 

State: North Carolina; 
Total NSP 1 State and Local Government Allocations: $57.7 million. 

State: Massachusetts; 
Total NSP 1 State and Local Government Allocations: $54.8 million. 

State: Colorado; 
Total NSP 1 State and Local Government Allocations: $53.1 million. 

State: South Carolina; 
Total NSP 1 State and Local Government Allocations: $49.2 million. 

State: Wisconsin; 
Total NSP 1 State and Local Government Allocations: $48.0 million. 

State: Maryland; 
Total NSP 1 State and Local Government Allocations: $46.4 million. 

State: Mississippi; 
Total NSP 1 State and Local Government Allocations: $46.3 million. 

State: Virginia; 
Total NSP 1 State and Local Government Allocations: $46.0 million. 

State: Kentucky; 
Total NSP 1 State and Local Government Allocations: $44.4 million. 

State: Alabama; 
Total NSP 1 State and Local Government Allocations: $41.8 million. 

State: Louisiana; 
Total NSP 1 State and Local Government Allocations: $38.8 million. 

State: Oklahoma; 
Total NSP 1 State and Local Government Allocations: $32.9 million. 

State: Washington; 
Total NSP 1 State and Local Government Allocations: $28.2 million. 

State: Connecticut; 
Total NSP 1 State and Local Government Allocations: $25.0 million. 

State: Iowa; 
Total NSP 1 State and Local Government Allocations: $21.6 million. 

State: Kansas; 
Total NSP 1 State and Local Government Allocations: $21.0 million. 

State: Alaska; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Arkansas; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Delaware; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Hawaii; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Idaho; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Maine; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Montana; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: North Dakota; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Nebraska; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: New Hampshire; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: New Mexico; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Oregon; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Rhode Island; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: South Dakota; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Utah; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Vermont; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: West Virginia; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: Wyoming; 
Total NSP 1 State and Local Government Allocations: $19.6 million. 

State: District of Columbia; 
Total NSP 1 State and Local Government Allocations: $2.8 million. 

Source: GAO analysis of HUD data; MapInfo. 

[End of figure] 

HUD CPD is implementing NSP 1. CPD administers CDBG and other formula 
and competitive grant programs from its offices at HUD headquarters 
and 43 field offices located throughout the United States. The 
headquarters office sets program policy, while field office staff are 
responsible for a wide range of grant management activities, including 
annual reviews and approval of grantee action plans, execution of 
grant agreements, and monitoring of grant recipients. CPD's monitoring 
of the CDBG program focuses on high-risk recipients. Each year, CPD 
sets a formal monitoring goal. For fiscal year 2010, the overall goal 
for CPD and each of its field offices was to monitor a minimum of 870 
formula and competitive grant recipients. For each CPD program, field 
staff analyze potential risks for grantees in a number of areas, 
including: financial (size of grant, financial compliance), physical 
(physical control of assets), management (staff capacity), 
satisfaction (citizen complaints and grantee responsiveness), and 
services (meeting program objectives and progress). 

HUD modified the DRGR system for the purposes of collecting and 
maintaining information on NSP activities. DRGR is new to NSP 1 
grantees and HUD field staff unless they had prior experience with 
Disaster Recovery Assistance grants, another program managed by CPD. 
[Footnote 13] In its NSP 1 Notice, HUD explained that no other 
reporting system was as flexible as DRGR and that statutory time 
frames did not allow sufficient time to develop a new system or modify 
an existing one to perfectly fit NSP. HUD's key modifications to DRGR 
included: 

* adding data fields to collect information specific to NSP, such as 
land banking; 

* removing drop-down menu selections for ineligible uses under NSP; 
and: 

* adaptations to enable grantees to designate whether properties had 
been resold or rented or were single-or multifamily. 

DRGR was set up to monitor grantees' progress in implementing NSP 1 by 
tracking budgets, obligations, expenditures, and program outputs. DRGR 
also serves as a financial management system through which grantees 
obligate and draw down funds. At the beginning of NSP 1, grantees 
inputted their NSP 1 action plans into DRGR. In their actions plans in 
DRGR, grantees set up their budgets and performance measures for 
different DRGR activities that were linked to larger projects. The 
action plan serves as a template for required progress reports, or 
Quarterly Performance Reports (QPR), that grantees must submit to HUD 
field staff on a quarterly basis. QPRs show updated information on NSP 
1 progress for grantees' projects and activities listed in DRGR. 

For each DRGR activity, NSP 1 grantees complete data fields that 
include (1) the projected start date, (2) the national objective (the 
income group the activity benefits), (3) the responsible organization 
(either the grantee or a subrecipient), and (4) the activity type 
(e.g., acquisition, rehabilitation, demolition).[Footnote 14] For each 
DRGR activity, grantees must also include a narrative and output 
measures--for example, the number of housing units or properties 
acquired, rehabilitated, land banked, or demolished, or the numbers of 
households or persons benefiting from the activity. In addition, 
grantees must list the addresses of properties benefiting from the 
activity but are not required to include the amount of funds spent on 
each property in DRGR. In a June 2009 report, the HUD OIG concluded 
that DRGR was sufficient to collect the basic information that HUD 
needed to monitor NSP 1.[Footnote 15] In a September 2009 report, the 
HUD OIG reviewed selected controls within DRGR in order to examine 
whether funds were properly safeguarded. While the OIG did not find 
misuse of funds in their review, they did identify several weaknesses, 
including access policies and testing of transactions, that CPD staff 
have been addressing.[Footnote 16] 

NSP 1 Grantees Overcame Challenges and Used a Variety of Strategies to 
Meet Obligation and Income-Targeting Requirements: 

Most Grantees Met the Deadline for Obligating Funds: 

HERA required NSP 1 grantees to obligate all of their funds within 18 
months, creating a September 2010 deadline for most grantees.[Footnote 
17] In order to obligate their funds, grantees had to satisfy certain 
conditions, including providing a specific property address and (where 
applicable) a detailed scope of work for rehabilitating, constructing, 
or demolishing a property. According to HUD guidance, grantees are 
considered to have obligated NSP 1 funds once they have placed orders, 
awarded contracts, received goods and services, or executed similar 
transactions that will require payment by the grantee. For example, 
funds for acquiring a property are considered obligated when the 
property seller accepts the grantee's purchase offer. 

Data in DRGR indicate that the vast majority of the 309 NSP 1 grantees 
met their deadline for obligating funds.[Footnote 18] As a result, 
more than 99 percent of NSP 1 funds were obligated as of October 1, 
2010. Figure 3 shows grantees' progress toward meeting obligation 
deadlines as of June 24, 2010 (about 3 months prior to most grantees' 
deadlines), compared with their progress by their deadlines. As of the 
earlier date, 27 grantees had obligated an amount equal to 100 percent 
of their total NSP 1 grant funds. In contrast, 275 grantees had 
obligated 100 percent by October 1, 2010--at which point the vast 
majority of grantee's deadlines had passed--and 29 had obligated 
between 80 percent and 99.9 percent. These figures are preliminary 
because HUD (1) gave grantees 30 days after their deadlines to ensure 
that all obligations prior to the deadline were recorded in DRGR and 
(2) is in the process of reviewing whether grantees' obligated their 
NSP 1 funds properly.[Footnote 19] CPD staff told us that 1 business 
day after a grantee's obligation deadline passes, they are blocking 
the grantee's access to funds and reviewing samples of obligations to 
ensure they are proper. As of the end of September, HUD officials told 
us that field office staff had reviewed samples for 20 grantees and 
found no improper obligations. They plan to review all grantees for 
compliance with obligation guidance. Additionally, the OIG is 
reviewing obligations as part of its compliance audits of selected NSP 
1 grantees.[Footnote 20] In August 2010, HUD outlined a process for 
addressing a grantee's failure to meet its obligation deadline and 
anticipated that many such grantees would face a choice of entering 
into an agreement with HUD to use the remaining funds or having their 
funds recaptured.[Footnote 21] 

Figure 3: NSP 1 Grantees' Obligations as of June 24, 2010, and as of 
October 1, 2010: 

[Refer to PDF for image: combined table and horizontal bar graph] 

Percentage of funds obligated: 0% to 19.9%; 
Number of grantees, June: 18; 
Number of grantees, October: 0. 

Percentage of funds obligated: 20.0% to 39.9%; 
Number of grantees, June: 28; 
Number of grantees, October: 0. 

Percentage of funds obligated: 40.0% to 59.9%; 
Number of grantees, June: 70; 
Number of grantees, October: 1. 

Percentage of funds obligated: 60.0% to 79.9%; 
Number of grantees, June: 87; 
Number of grantees, October: 2. 

Percentage of funds obligated: 80.0% to 99.9%; 
Number of grantees, June: 77; 
Number of grantees, October: 29. 

Percentage of funds obligated: 100%; 
Number of grantees, June: 27; 
Number of grantees, October: 275. 

Total: 
Number of grantees, June: 307[A]; 
Number of grantees, October: 307[A]. 

Source: GAO analysis of HUD DRGR data. 

[A] There are 307 entries representing 309 grantees in HUD's DRGR 
system because the State of Colorado reports information in DRGR for 
both the State and for the City of Colorado Springs, and Clark County 
reports information for both the County and the City of North Las 
Vegas (Nevada) under their cooperative grant agreements. 

[End of figure] 

Figure 4 shows the percentage of grantee obligations that fell under 
different NSP 1 activities as of October 1, 2010. NSP 1 grantees 
obligated most NSP 1 funds for acquisition and rehabilitation, with 
smaller amounts obligated for other activities such as construction of 
new housing, demolition, and land banking. 

Figure 4: Reported NSP 1 Grantee Obligations by Activity, as of 
October 1, 2010: 

[Refer to PDF for image: pie-chart] 

Acquisition and rehabilitation: 66%; 
Construction for new housing: 11%; 
Administration: 9%; 
Homeownership assistance: 6%; 
Demolition: 5%; 
Other: 4%: 
- Public improvement, public facilities, nonresidential structures: 2%; 
- Land banking: 2%. 

Source: GAO analysis of HUD DRGR data. 

Notes: The purpose of this graph is to show the relative magnitude of 
NSP 1 obligations by activity type. As discussed later in this report, 
some grantees may group multiple activities under a single activity 
type (for example, both acquisition and rehabilitation activities 
under rehabilitation) when entering obligation data into DRGR. Because 
this practice is most likely to occur when grantees enter data on 
acquisition and rehabilitation activities, we combined the data for 
these two activities. The "disposition" activity type is also likely 
to be included under rehabilitation, therefore we included obligations 
for disposition within the "acquisition and rehabilitation" grouping. 

"Homeownership assistance" includes various types of homeownership 
assistance such as down-payment assistance and housing counseling for 
those applying for down-payment assistance. 

Due to rounding, the percentages in the graphic add up to a total of 
101 percent. Funds spent toward public services and relocation 
payments and assistance were not included in the graph because they 
each rounded to zero percent, as did the total amount of funds not yet 
obligated. 

[End of figure] 

HUD data also show that 298 NSP 1 grantees obligated at least 25 
percent of their grant funds for activities benefiting low-income 
households. As of October 1, 2010, the data indicate that, in total, 
grantees obligated 35.1 percent of funds set aside for activities that 
would benefit this group. This pattern is consistent with a HERA 
requirement that 25 percent of NSP 1 funds be used to benefit 
households at or below 50 percent of AMI. In the NSP 1 Notice, HUD 
stated that it will assess grantees' compliance with this provision 
prior to and at grant closeout on the basis of grantees' expenditures. 

State Grantees Often Used a Combination of Methods to Distribute NSP 1 
Funds within Their States: 

As discussed earlier, HUD made NSP 1 allocations to 309 units of 
government, including each of the 50 states. Collectively, the states 
received more than half of NSP 1 funds. States had some flexibility in 
how they chose to distribute NSP 1 funds but were required to target 
areas of greatest need. States could choose to use funds themselves 
through state-administered programs or could reallocate funds to local 
entitlement or nonentitlement communities within their areas of 
greatest need.[Footnote 22] In their HUD-approved action plans, states 
had to identify areas of greatest need using factors that included the 
following: 

* foreclosure rates, 

* percentage of homes financed by subprime loans, and: 

* likelihood of a significant rise in foreclosure rates. 

Our review of NSP 1 action plans for all states (including the 
District of Columbia) found that all of the states included these 
factors among their criteria for determining their areas of greatest 
need. Some states also used factors not listed in HERA in determining 
their areas of greatest need, such as unemployment rates or 
percentages of the population at or below 50 percent of AMI. In their 
action plans, states had to outline their methods for reallocating NSP 
1 funds or for using the funds themselves to make the most impact 
within the areas of greatest need within their state. HERA also 
allowed states to allocate their funds to local entitlement 
communities that may have already received NSP 1 funds directly from 
HUD, as well as to nonentitlement communities. According to HUD data 
as of June 2010, of the total NSP 1 funds that HUD allocated to the 
states, states reallocated approximately 9 percent, or $176 million, 
to 57 local governments in 21 different states that had already 
received NSP 1 funds directly from HUD (see figure 5).[Footnote 23] 

Figure 5: States' Reallocation of NSP 1 Funds to Units of Local 
Government That also Received Funds Directly from HUD: 

[Refer to PDF for image: illustration] 

HUD: Direct funding to: 
* 50 states; 
* 253 units of local government. 

21 of the 50 states gave additional funding to: 
* 57 of the 253 units of local government. 

Source: GAO analysis of HUD DRGR data; Art Explosion. 

[End of figure] 

Once states determined the areas of greatest need, many of them used 
competitions to award NSP funds for specific purposes. For example, 
one state used a competition for the acquisition and rehabilitation of 
multifamily properties, and another state used a competition 
specifically to help it meet NSP 1's 25 percent set-aside requirement 
to benefit households with incomes at or below 50 percent of AMI. 
Eligible applicants--nonprofits, for-profit developers, and local 
governments, among others--often varied by state and by the type of 
competition. While some states invited nonprofits and for-profit 
developers to compete for funds directly, other states allowed only 
local jurisdictions to apply or required nonprofits to get buy-in from 
their local governments in order to receive funds. 

Our review of NSP 1 action plans found that states distributed funds 
using three main methods: (1) reallocation through competitions, (2) 
reallocation on the basis of formulas, and (3) through state- 
administered programs. Many state grantees used a combination of 
methods to distribute funds, while a smaller number relied on a single 
method. More specifically, our review found that 14 states distributed 
all of their NSP 1 funds by reallocating them on a competitive basis, 
7 states used a formula to reallocate all of their funds, and 1 state 
used all of the funds itself by administering the program through its 
housing finance agency and by contracting with other entities. In 
contrast, 26 states used a combination of two or more of the methods. 
[Footnote 24] For example, a number of states with some of the largest 
NSP 1 grants, including California and Ohio, used a formula to 
allocate funds to areas of greatest need within the state and then 
held a competition for the 25 percent set-aside to benefit households 
with incomes at or below 50 percent of AMI. Six states utilized all 
three distribution methods--competition, formula, and use of funds--
through state-administered programs. A number of states decided to 
administer some of their NSP 1 funds themselves through state-
administered programs; for example, 1 state created a new statewide 
soft second loan financing program (Arizona) and another state 
channeled some of its NSP 1 funds into the Low Income Housing Tax 
Credit Program and the Permanent Supportive Housing Program (Georgia). 
[Footnote 25] 

Many states that used competitions to distribute NSP funds used 
similar criteria to rank applicants and award funds. For example, on 
the basis of our review of their action plans, many states considered 
applicants' capacity to carry out projects and project readiness, as 
well as whether applicants' proposals focused on projects that would 
serve the areas of greatest need within the state. Other frequently 
used competitive factors included applicants' experience administering 
NSP-related activities and ability to leverage other funding sources. 
A few states ranked applicants based on green building activities or 
gave priority to applicants that proposed projects that would help 
meet the 25 percent set-aside requirement. 

Grantees Employed Various Strategies for Using NSP 1 Funds: 

NSP 1 grantees with whom we spoke employed various different 
strategies for obligating and expending funds for NSP-eligible 
activities.[Footnote 26] For example, as shown in figure 6, some 
grantees found that homebuyer-driven strategies--that is, strategies 
that allowed individual homebuyers to identify NSP-eligible properties 
and receive NSP 1 funds from grantees to assist with the acquisition 
or rehabilitation--were the most appropriate for the market conditions 
in their area. An example of a homebuyer-driven strategy would be one 
in which a grantee provided homebuyers with financial assistance--down-
payment assistance, closing costs, rehabilitation costs, or soft 
second loans--to enable them to acquire a home within an NSP 1 target 
area. Another approach grantees used was a more property-driven 
strategy in which grantees or their subrecipients--such as housing 
authorities, nonprofits, or for-profit developers--directly acquired, 
rehabilitated, and resold or rented NSP properties to individuals or 
families meeting NSP-specific income requirements. Finally, in some 
cases, grantees' strategies included demolishing blighted structures 
and land banking the parcels on which the demolished properties stood 
for future use. 

Figure 6: NSP Strategies for Acquiring and/or Rehabilitating Homes: 

[Refer to PDF for image: illustration] 

Homebuyer-driven strategy: 

Homebuyer: 
Identifies and purchases property. 

NSP 1 grantee: 
Provides financial assistance (downpayment assistance, closing costs, 
etc.) and ensures NSP 1 due diligence has been completed. 

Homebuyer: 
(meets NSP 1-specific income requirements). 

Property-driven strategy: 

NSP 1 grantee: 
Acquires and/or rehabilitates property within an NSP 1 target area; 
Grantee resells or rents property to homebuyer; 
Homebuyer (meets NSP 1-specific income requirements). 

Source: GAO; Art Explosion. 

[End of figure] 

NSP 1 grantees we spoke with used different NSP strategies depending 
on the particular housing market conditions in their target areas. For 
example, one grantee we contacted used a homebuyer-driven strategy in 
areas where the generally good condition of the properties could 
attract potential purchasers. Under that strategy, qualified 
homebuyers looked for properties in NSP 1 target areas and chose NSP-
eligible homes that did not require a lot of rehabilitation. The 
grantee then conducted the required due diligence on the home, 
including having it appraised and inspected, and completing 
environmental reviews. After the due diligence had been completed, the 
grantee assisted buyers with the acquisition of a property (at the 
required discount) and provided some funding for down-payment 
assistance and closing costs. The same grantee implemented a more 
property-driven strategy in target areas where homes required a higher 
level of rehabilitation--a potential deterrent for some homebuyers. 
Under this strategy, the grantee worked with nonprofit developers to 
acquire and rehabilitate the homes, then resold the homes to NSP-
eligible buyers. Another grantee with whom we spoke used NSP 1 funds 
for demolition projects and the removal of blight to help stabilize 
its communities. Some of the land on which the demolished properties 
were located will be land banked for future use. This strategy made 
the most sense for this particular grantee as it did not have a strong 
housing market for sale or rental. 

In order to meet the 25 percent set-aside requirement to benefit 
households with incomes at or below 50 percent of AMI, most of the 
grantees we spoke with employed similar strategies. Several of the 
grantees we spoke with planned to acquire, rehabilitate, and rent out 
multifamily properties to meet this requirement. A couple of grantees 
also had back-up strategies for meeting the 25 percent set-aside as 
well, such as acquiring and rehabilitating single-family homes and 
renting them out to low-income individuals or families. 

Some Grantees Modified Their Strategies to Meet the Obligation 
Deadline and Address Implementation Challenges: 

Grantees we spoke with faced several challenges implementing NSP 1-- 
including tight time frames, competition from private investors, and 
challenges in acquiring properties--but generally found ways to 
address them. While 16 of the 18 NSP 1 grantees that we contacted had 
obligated their full grant allocations by October 1, 2010, most said 
they had faced some difficulties in trying to meet this requirement. 
[Footnote 27] For example, several grantees mentioned they had 
encountered competition from private investors in their efforts to 
acquire NSP-eligible properties. One grantee said both in-state and 
out-of-state investors have seized the opportunity to acquire NSP-
eligible properties at low prices, and another grantee provided an 
example where a group of investors acquired about 90 properties at one 
time. One grantee official expressed concern that investors looking to 
rent out properties may not be responsible landlords, which could 
undermine efforts to stabilize neighborhoods. Finally, private 
investors sometimes outbid grantees for NSP-eligible properties, and 
because investors may pay with cash and do not have to meet the same 
due diligence requirements as NSP 1 grantees, they are able to act 
more quickly and have more success acquiring properties. 

Furthermore, a few of the grantees we spoke with that planned to rent 
out multifamily properties said they faced challenges meeting the 25 
percent set-aside obligation requirement. Officials from two grantees 
told us it was difficult to find foreclosed multifamily rental 
projects to purchase in NSP 1 target areas. Additionally, one grantee 
told us that they were facing neighborhood opposition to a multifamily 
project because neighbors feared that affordable housing units would 
depress home values in the area. 

A broader study of NSP grantees sponsored by the Board of Governors of 
the Federal Reserve System and two Federal Reserve banks cited 
challenges similar to those that we identified. For example, the study 
highlights competition from private-sector investors, grantees' 
difficulties identifying a potential pool of foreclosed properties to 
acquire, and the reluctance of some property holders to work with 
grantees. The study also noted that local requirements and practices, 
such as stringent local standards for publicly financed 
rehabilitation, often put NSP grantees at a competitive disadvantage 
to investors.[Footnote 28] 

In order to overcome implementation challenges such as meeting 
deadlines or competition from investors, some grantees we spoke with 
modified their implementation strategies by: 

* moving away from homebuyer-driven models to directly acquiring 
properties, 

* expanding target areas, 

* working with banks' "first look programs," and: 

* working with the National Community Stabilization Trust (NCST). 

To overcome implementation challenges, some grantees had to make 
changes to their original program strategies. For example, several 
grantees we contacted said it would be difficult to meet the 
obligation deadline using their homebuyer-driven strategies. 
Competition from private investors and tight obligation time frames 
required some grantees to move funds from their homebuyer-driven 
models towards supporting more property-driven strategies where they 
purchased and rehabilitated homes themselves. Using a more direct 
strategy allowed some grantees to speed up the pace of obligations. In 
addition, one grantee shifted its focus from homebuyers to renters in 
order to help it meet the deadline for obligating funds, as potential 
homebuyers in its housing market were finding it difficult to obtain 
mortgages due to job loss and poor credit. 

Some NSP 1 grantees also expanded their target areas to expedite 
property acquisition. With HUD approval, some NSP grantees expanded 
their target areas to include more ZIP codes or census tracts in order 
to expedite acquisitions and circumvent investor competition. Several 
grantees also worked with banks' "first look" programs, which gave 
them the opportunity to bid on bank-owned foreclosed properties before 
other potential buyers. Grantees also worked with NCST, a national 
nonprofit organization to acquire foreclosed properties in their 
target areas. NCST facilitates communication between NSP grantees and 
banks and provides grantees with listings of NSP-eligible properties 
from which to choose. Many grantees with whom we spoke found NCST to 
be very helpful in acquiring properties, and one grantee we contacted 
said working with NCST helped it acquire 80 percent of the homes on 
which it had placed bids. In an effort to standardize the acquisition 
process for NSP grantees, HUD recently partnered with NCST to create 
the "National First Look Program" in September 2010. The program gives 
communities participating in NSP a "first look" or right of first 
refusal to purchase foreclosed homes before the properties are made 
available to private investors.[Footnote 29] According to HUD 
officials, the program grew out of an initiative HUD announced in July 
2010, which gave NSP-eligible purchasers the opportunity to acquire 
foreclosed properties owned by HUD's Federal Housing Administration at 
10 percent below the appraised value.[Footnote 30] 

HUD Has Taken Actions to Mitigate NSP 1 Program Risks through 
Training, Technical Assistance, and the Establishment of Internal 
Controls: 

As previously noted, HERA established specific program requirements 
for NSP 1 beyond those for CDBG, including an accelerated timeline for 
obligating funds and the requirement that grantees must use 25 percent 
of their NSP 1 funds to benefit households at or below 50 percent AMI. 
Additionally, HERA required that NSP 1 grantees ensure, among other 
things, that properties are acquired at a discount and properties sold 
to individuals as a primary residence cannot be resold for more than 
the total cost of acquisition and redevelopment. 

At the start of NSP 1, HUD conducted a front-end risk assessment 
(FERA) to assess NSP 1 program risks and identify actions required to 
reduce control risks to an acceptable level.[Footnote 31] Among other 
risks, HUD's review noted that the scale of the effort could overwhelm 
some grantees; meeting the requirement to obligate funds within an 18-
month time frame could be challenging for grantees, especially those 
with limited real estate experience; and HUD's personnel resources 
were not adequate to oversee the program. The FERA concluded that 
implementing NSP 1 successfully and within required time frames would 
require early and regular deployment of controls, including training, 
technical assistance, and monitoring. The FERA also recommended 
additional HUD staff to support NSP-related activities, because field 
staff were already overextended managing existing programs. 

HUD Provided Training and Guidance and Made Program Modifications to 
Address Program Challenges, but Some Grantees Said Some of These 
Efforts Were Not Timely: 

HUD provided training and guidance on NSP 1 using a variety of 
methods, including: 

* online guidance, webinars, and answers to frequently asked questions; 

* e-mail updates; 

* teleconferences and increased communication with field staff; and: 

* classroom and one-on-one instruction (e.g., on DRGR). 

HUD provided eight online video training presentations with associated 
printouts ("modules") that outlined NSP 1-specific requirements, 
policies, and procedures. For example, the first module provided 
overall NSP 1 guidance and rules on eligible uses, activities, and 
properties.[Footnote 32] HUD also released webinars, hosted by HUD 
staff and technical assistance providers, on a weekly basis that 
provided guidance on topics such as obligating funds and meeting the 
25 percent set-aside requirement. A majority of the grantees we spoke 
with said that, overall, the material covered in the modules and 
webinars provided good information and helped them implement their NSP 
1 programs. 

HUD faced significant challenges in issuing comprehensive guidance and 
training to grantees at NSP 1's outset because the program was 
relatively complex and had to be implemented quickly. Most of the 
grantees that we interviewed said that the combination of HUD's 
guidance and training was helpful but some grantees had raised some 
concerns. Several grantees that we spoke with about 1 year after the 
program began said that the guidance and training they received was 
not always timely. For example, one grantee said that the information 
it received at an NSP problem-solving clinic in early 2010 would have 
been more useful had it been provided 6 months earlier. Additionally, 
two grantees said they did not always get timely answers to questions 
about program rules when the field office staff they asked had to 
obtain clarification from HUD headquarters. HUD officials said that 
some of the assistance grantees found useful was delivered using funds 
that HUD received well after the start of NSP 1. 

HUD modified NSP policy in two key respects to address challenges 
faced by grantees in implementing the program. Grantees we spoke with 
said that the first of these modifications helped them overcome 
difficulties they were experiencing in acquiring properties. More 
specifically, in June 2009, HUD reduced the required discount from the 
appraised value at which grantees must purchase NSP-eligible 
properties. HUD reduced the discount from a minimum of 5 percent for 
individual acquisitions to a minimum of 1 percent, and eliminated the 
15 percent discount for aggregate acquisitions.[Footnote 33] This 
change was intended to mitigate the potentially adverse impact that 
the larger discounts could have on neighborhood property values and 
the inability or unwillingness of the holders of foreclosed properties 
to sell at prices that reflect the higher discount. 

NSP 1 grantees had mixed views about the effect of the other program 
modification, implemented in April 2010, which expanded the 
definitions of foreclosed and abandoned properties.[Footnote 34] As a 
result of the program modification, properties no longer had to have 
completed the foreclosure process to be purchased with NSP funds, and 
the standards for what constituted an abandoned property eligible for 
NSP were loosened--for example, to include tenant-occupied properties. 
[Footnote 35] HUD made these changes in response to suggestions from 
local communities to increase the reach of NSP by allowing more 
properties to qualify. HUD headquarters staff said this change also 
enabled some NSP 1 grantees to increase the pace of their acquisitions 
and meet their obligation deadlines. They added that, on the basis of 
comments from grantees, the expanded definitions had helped grantees 
acquire multifamily properties but had not yet been used to acquire 
single-family homes. Similarly, some CPD field staff said the expanded 
definitions helped grantees that were facing challenges in meeting the 
obligation deadline by increasing the number of eligible properties 
they could acquire. Specifically, field staff reported that it helped 
some of their grantees to fulfill the 25 percent set-aside requirement 
by easing restrictions on acquiring multifamily properties, which many 
grantees we spoke with intend to rent to low-income households. 
Several grantees we spoke with expressed similar views, noting that 
the new definitions helped them acquire multifamily properties. 
However, others indicated that the broader definitions would not make 
a significant impact at this stage in their NSP 1 efforts because they 
had made many of their acquisitions prior to the definition changes or 
had a large inventory of fully foreclosed homes available. The 
expanded definitions may have a greater effect on acquisitions of 
properties for the more recent rounds of funding (NSP 2 and NSP 3), 
since they are in earlier stages of planning and implementation. 

HUD Provided Technical Assistance to Support Grantees in Implementing 
NSP 1: 

In August 2009, HUD awarded $50 million in ARRA funds through a 
competition to provide technical assistance for NSP grantees (under 
both NSP 1 and NSP 2). According to HUD, as of October 2010, $28.6 
million had been budgeted for NSP technical assistance and $11 million 
of that amount had been drawn down. Nine national technical assistance 
providers were awarded 89 percent of the funds to operate at the 
national level, and three local technical assistance providers 
received 11 percent of the funds to operate at the local level. 
[Footnote 36] Among other areas, NSP technical assistance providers 
were tasked with: 

* helping NSP grantees implement sound underwriting, management, and 
fiscal controls; 

* building the capacity of public-private partnerships; 

* developing strategies to serve low-income households; 

* providing training on the operation and management of land banks; 
and: 

* training grantees and their subgrantees on HUD program rules and 
financial management requirements. 

The providers delivered support to grantees through various methods, 
including "direct assistance" (assistance provided in person), "on-
call remote assistance" (assistance provided via phone or e-mail), and 
"Web-based" assistance, which provides answers to questions submitted 
via HUD's NSP resource exchange Web site. 

* Direct. HUD headquarters and field staff identified grantees that 
demonstrated a need for support in specific NSP program areas or 
exhibited capacity concerns in meeting the obligation deadline. 
Technical assistance providers conducted needs assessments for direct 
assistance for 98 grantees during late 2009 and early 2010. As of 
August 2010, 59 grantees had requested direct assistance, 58 of which 
received it. 

* On-call remote. As of August 2010, technical assistance providers 
had received 93 requests for on-call remote technical assistance and 
responded to 84 of those requests (with 27 completed and 57 in 
progress). HUD officials said they received approximately 3 to 4 on- 
call remote technical assistance requests weekly. Technical assistance 
providers also facilitated NSP problem-solving clinics that were open 
to all grantees and field staff. 

* Web-based. HUD officials said that technical assistance providers 
had established the NSP resource exchange Web site as a place for 
grantees to submit technical assistance requests and share knowledge. 
The Web site also has a "frequently asked questions" link that is 
regularly updated with answers to questions from grantees that can be 
searched by topic. According to HUD, technical assistance providers 
answered 2,389 out of 2,544 NSP questions submitted between April and 
August 2010. 

HUD officials said that NSP 1 grantees mostly requested technical 
assistance in two major areas: (1) program design and (2) financial 
underwriting skills. In terms of program design, HUD staff said that 
some grantees had selected unsuitable NSP 1 approaches for their local 
housing markets. For example, some grantees had planned to implement 
strategies for selling homes or increasing home ownership in what were 
primarily rental markets. In another example, one grantee was 
initially not planning to use NSP 1 funds for demolition, even though, 
according to HUD staff, demolition was an appropriate use of NSP 1 
funds given the grantee's local housing market conditions. Grantees 
also requested technical assistance to enhance their knowledge of 
property financing. 

HUD set up accounts in DRGR for each technical assistance provider to 
track the use of technical assistance funds and the performance of 
grantees receiving the assistance. HUD staff told us they plan to use 
this information to assess whether the technical assistance improved 
grantees' performance. HUD staff also said they will conduct post- 
technical assistance monitoring to assess grantees' compliance with 
NSP 1 requirements and determine if additional assistance is 
necessary. Additionally, HUD officials said that the agency is 
collecting feedback on the quality of technical assistance at training 
events and through the NSP resource exchange Web site, among other 
means. HUD officials said they would use this feedback to determine 
potential needs for NSP 2 and 3, and to help determine whether current 
technical assistance providers should continue to participate in HUD 
programs. Given the critical role that HUD assigned to technical 
assistance for mitigating program risks, it will be important for HUD 
to follow through with these planned assessments to ensure that the 
assistance had the intended effect. 

HUD Hired Staff and Implemented Internal Control Processes for NSP 1: 

The FERA conducted for NSP 1 cited the lack of HUD staff capacity to 
absorb the additional workload and recommended the addition of 20 to 
25 staff to support NSP 1. With funding from the fiscal year 2009 
continuing resolution, as of November 2010, HUD had hired 10 term 
staff as NSP specialists--whose duties include monitoring and 
oversight of grantees--placing 7 in field offices that generally had 
more than 20 NSP 1 grantees and 3 in headquarters.[Footnote 37] Also 
as of November 2010, the agency had hired an additional 32 field staff 
with funding provided by the American Recovery and Reinvestment Act of 
2009 (ARRA) to work on implementing NSP 2 but also to contribute to 
NSP 1 efforts, such as monitoring grantee compliance with program 
requirements. 

The FERA also noted the importance of implementing controls to 
mitigate program risks. HUD adapted a range of internal control 
processes already in place for the CDBG program to ensure compliance 
with program requirements and mitigate the risks posed by NSP 1 (see 
figure 7). Before releasing grantees' NSP 1 funds, HUD required all 
grantees to submit a substantial amendment (or "NSP 1 action plan") to 
their CPD consolidated and annual action plans by December 2008 to 
describe how they would use NSP 1 funds. As noted earlier, NSP 1 
action plans identify areas of greatest need, establish expected 
program outputs, set forth plans for complying with key requirements, 
and define relevant NSP 1 terms (such as blighted structures, housing 
rehabilitation standards, and affordable rents). HUD reviewed NSP 1 
action plans to determine if grantees' planned uses of funds were in 
accordance with key HERA requirements. After approving the action 
plans, HUD signed the grant agreements (most were signed in March 
2009, according to HUD officials, resulting in 18-month obligation 
periods ending in September 2010). 

Figure 7: Selected HUD Internal Controls for NSP 1: 

[Refer to PDF for image: illustration] 

I. Prior to access to NSP 1 funds: 

HUD reviewed NSP 1 Action Plan (substantial amendments to consolidated 
CPD plan) then signed grant agreement; Grant Agreement Approved. 

Grantees input NSP 1 action plan into DRGR; High-risk grantees must 
also submit NSP 1 Management Plan. 

HUD reviewed using checklist: NSP 1 Action Plan DRGR Checklist. 

Funds released. 

II. NSP 1 funds monitoring: 

HUD reviewed and approved QPRs submitted by all grantees, using Guide 
for QPR Checklist. 

HUD identified high-risk grantees in CPD analysis. 

HUD conducted additional on-site monitoring of high-risk grantees 
using NSP 1 Program Exhibit. 

Funds can be frozen in cases of noncompliance. 

Source: GAO analysis of HUD information. 

[End of figure] 

Also prior to releasing NSP 1 funds, HUD implemented additional 
controls for grantees at higher risk of noncompliance with program 
requirements. For example, in the initial stage of the program, HUD 
designated 104 grantees as high risk because their NSP 1 grants were 
at least three times greater than their annual CDBG allocations or 
they had audit findings or other performance problems in similar HUD 
grant programs. HUD added a "special condition" to the NSP 1 
agreements of these high-risk grantees that required them to submit 
management plans along with their NSP 1 action plans. The management 
plans detail the number, types, and responsibilities of staff 
positions supporting the grantee's NSP 1 program.[Footnote 38] 

Furthermore, after grantees inputted their action plans into DRGR, CPD 
field office staff used a checklist to confirm that the action plans 
were entered in a manner that would allow HUD to track NSP 1 funds and 
monitor whether some key reporting requirements were met (see figure 
7). Field staff used an action plan checklist to verify that grantees 
had identified eligible NSP 1 uses, responsible organizations, and 
income-based national objectives associated with activities in DRGR. 
[Footnote 39] Once field office staff reviewed and approved a 
grantee's action plan in DRGR, HUD headquarters released the grantee's 
NSP 1 funds. 

After releasing grantees' funds, HUD has used remote and on-site 
monitoring of grantees' ongoing performance to assess compliance with 
program requirements. HUD field staff used a QPR checklist to review 
areas covered by the action plan checklist and to monitor grantees' 
progress in meeting their obligation deadlines. 

Additionally, CPD field office staff conducted on-site monitoring of 
176 grantees (57 percent of NSP 1 grantees). The field offices 
selected these grantees on the basis of risk scores calculated using 
five risk factors: (1) financial soundness, (2) overall management 
capacity, (3) client satisfaction with services, (4) extent to which 
services benefit targeted areas and clientèle, and (5) NSP 1 program 
progress.[Footnote 40] The factor for management, which constituted 
the largest part of the score, considered grantees' capacity to 
implement NSP 1 based on HUD monitoring information and grantees' use 
of subrecipients. The factor for NSP 1 program progress--the second-
largest scoring component--considered other aspects of grantee 
capacity, including how much NSP 1 funding the grantee received 
relative to its regular CDBG allotment, the type of activities 
undertaken, and the grantee's capacity to manage its NSP 1 program. 
Although CPD field offices primarily used the risk analysis scores to 
select grantees for monitoring and identifying specific compliance 
areas to review, they also considered HUD OIG audit findings, where 
applicable.[Footnote 41] 

To prepare for on-site monitoring, CPD issued a revision to HUD's 
Community Planning and Development Monitoring Handbook in April 2010 
that provided HUD staff with guidance for monitoring grantees' 
compliance with NSP 1 requirements. The guidance includes "exhibits," 
or checklists that cover key NSP 1 requirements, including the income 
qualifications of program beneficiaries, rules on continued 
affordability, obligation deadlines, and the 25 percent set-aside for 
low-income families. 

HUD field offices conducted the majority of on-site monitoring from 
April through September 2010. As of September 2010, HUD officials told 
us they were still in the process of aggregating on-site monitoring 
results. As a result, program-wide data on the extent to which 
grantees are complying with NSP 1 requirements are not readily 
available. In the absence of centralized data, we reviewed the 
monitoring results for 40 NSP 1 grantees overseen by the four CPD 
field offices that we contacted during the course of our work (the 
field offices are in Philadelphia, Pennsylvania; Columbus, Ohio; 
Miami, Florida; and San Francisco, California).[Footnote 42] The on-
site monitoring found that 32 of the 40 grantees were in full 
compliance with the requirements reviewed. However, CPD field staff 
identified a total of 13 findings (potential deficiencies requiring 
corrective action) for the other 8 grantees.[Footnote 43] Most of the 
findings were related to financial management and accounting issues--
for example, deficiencies in accounting systems for personnel and 
other administrative costs--and others related to oversight of 
subrecipients. Additionally, 1 grantee did not clearly document that 
two homebuyers received homebuyer counseling prior to obtaining their 
mortgages loans. The same grantee did not take adequate steps to 
ensure that a multifamily rental property would remain affordable to 
income-eligible households. HUD required the 8 grantees to take 
corrective actions on the findings and has an established process for 
following up on the status of corrective actions. Because many 
grantees are still completing their NSP 1 activities, following 
through on this process will be key to ensuring grantees' compliance 
with program requirements. 

In cases where HUD identifies major compliance problems, it may freeze 
a grantee's access to NSP 1 funds. HUD officials said they had not 
needed to take this action as of September 2010. 

Selected Grantees Complied with Key NSP 1 Requirements for Properties 
We Reviewed: 

We reviewed selected grantee's compliance with key NSP 1 requirements 
for a nonstatistical sample of 32 NSP 1 properties. We selected eight 
grantees in five states covering different geographic regions and 
housing market conditions and reviewed records for four properties at 
each grantee.[Footnote 44] Our review focused on requirements relevant 
to activities (e.g., acquisition, rehabilitation, etc.) that had been 
completed when we conducted our selection process.[Footnote 45] We did 
not conduct a financial audit of the grantee or the funds expended on 
the properties. 

As shown in figure 8, we reviewed grantee compliance with key NSP 1 
requirements and relevant internal controls concerning the use of 
grant funds. Some of the requirements and controls were relevant to 
all types of NSP 1 activities. Other requirements and controls applied 
only to specific activity types. 

Figure 8: Program Requirements and Controls We Reviewed: 

[Refer to PDF for image: illustrated table] 

All activities: 

Property was located within a defined area of greatest need; 
NSP 1 statutory or regulatory requirement. 

Property was eligible for all relevant NSP 1 activities; 
NSP 1 statutory or regulatory requirement. 

Property address was included in grantee’s Quarterly Performance 
Report in DRGR, where applicable; 
Other requirement or control[A]. 

Grantee had relevant procedures and checklists; 
Other requirement or control[A]. 

Acquisition: 

Acquisition price was at least 1 percent below the appraised value; 
NSP 1 statutory or regulatory requirement. 

Appraisal was conducted no more than 60 days prior to purchase offer; 
NSP 1 statutory or regulatory requirement. 

Proof of purchase and title transfer; 
Other requirement or control[A]. 

Documentation of title insurance; 
Other requirement or control[A]. 

Documentation that the required environmental review process was 
completed prior to acquisition and had been certified by the 
responsible official; 
Other requirement or control[A]. 

Rehabilitation: 

Documentation of work write-ups and appropriate approvals; 
Other requirement or control[A]. 

Documentation of estimated and final rehabilitation costs; 
Other requirement or control[A]. 

Final inspection reports documented that all rehabilitation work was 
completed in a satisfactory manner; 
Other requirement or control[A]. 

Demolition: 

Documentation indicating the structure met the grantee’s definition of 
blighted; 
NSP 1 statutory or regulatory requirement. 

Evidence of the structure prior to demolition; 
Other requirement or control[A]. 

Documentation of estimated and final demolition costs; 
Other requirement or control[A]. 

Resale: 

Provisions for primary residence and continued affordability were in 
place[B]; 
NSP 1 statutory or regulatory requirement. 

Property was resold at a price lower than the sum of the acquisition 
and rehabilitation costs; 
NSP 1 statutory or regulatory requirement. 

Proof of purchase and title transfer; 
Other requirement or control[A]. 

Income eligibility of homebuyers was determined and documented; 
NSP 1 statutory or regulatory requirement. 

Evidence that homebuyers attended at least 8 hours of homebuyer 
counseling; 
NSP 1 statutory or regulatory requirement. 

Homebuyers obtained a traditional mortgage product; 
NSP 1 statutory or regulatory requirement[C]. 

Financing (assistance provided to homebuyers for purchase or 
rehabilitation): 

Provisions for primary residence and continued affordability were in 
place; 
NSP 1 statutory or regulatory requirement. 

In cases where down payment assistance was provided, the assistance 
was less than 50 percent of the home’s sale price; 
NSP 1 statutory or regulatory requirement. 

Income eligibility of homebuyers was determined and documented; 
NSP 1 statutory or regulatory requirement. 

Evidence that the homebuyers attended at least 8 hours of homebuyer 
counseling; 
NSP 1 statutory or regulatory requirement. 

Homebuyers obtained a traditional mortgage product; 
NSP 1 statutory or regulatory requirement[C]. 

Source: GAO. 

[A] Other requirements and controls are based on those from other 
relevant HUD programs (e.g., the CDBG and HOME Investment Partnerships 
programs) or are practices consistent with federal internal control 
standards. 

[B] Some grantees addressed the primary residence requirement and 
continued affordability restrictions by inserting clauses in purchase 
and loan contracts. Under the continued affordability requirement for 
NSP 1, grantees must ensure, to the maximum extent practicable and for 
the longest feasible term, that the sale, rental, or redevelopment of 
abandoned and foreclosed-upon homes and residential properties remain 
affordable to individuals or families whose incomes do not exceed 120 
percent (or 50 percent if property qualifies as low income) of area 
median income. 

[C] NSP 1 grantees are required to ensure that homebuyers obtain 
mortgage loans from lenders that agree to comply with federal banking 
regulator guidance for nontraditional mortgages. (Nontraditional 
mortgages include loan products that allow borrowers to defer payment 
of principal and, in some cases, interest. These features create the 
potential for "payment shock" when the monthly payments adjust to a 
fully amortized amount.) We did not review compliance with this 
requirement directly because of potential variation in what would 
constitute such assurance. However, we did determine whether 
homebuyers obtained traditional mortgage products (e.g., 30-year fixed-
rate loans). For the 10 properties in our sample that had been 
purchased by a homebuyer (either directly or from the grantee), the 
homebuyer obtained a 30-year fixed-rate mortgage. 

[End of figure] 

We found no instances of significant noncompliance with the key NSP 1 
requirements we reviewed for the 32 properties in our nonstatistical 
sample.[Footnote 46] The results of our review cannot be generalized 
to the total population of NSP 1 activities or grantees. 

Table 1 shows the types of activities that had been completed at the 
properties we reviewed. Seventeen of the 32 properties we reviewed had 
been acquired and undergone rehabilitation. Six of those 17 properties 
were resold by the grantees, and a seventh property was directly 
acquired and rehabilitated by the homebuyer with NSP 1 assistance. 

Table 1: Activities Reviewed for 32 NSP 1 Properties: 

Activities reviewed: Acquisition by grantee; 
Number of properties: 7; 
Number of properties with homebuyer assistance: n/a[A]. 

Activities reviewed: Acquisition and rehabilitation by grantee; 
Number of properties: 10; 
Number of properties with homebuyer assistance: n/a[A]. 

Activities reviewed: Acquisition, rehabilitation, and resale by 
grantee; 
Number of properties: 6; 
Number of properties with homebuyer assistance: 6. 

Activities reviewed: Demolition by grantee[B]; 
Number of properties: 5; 
Number of properties with homebuyer assistance: n/a[A]. 

Activities reviewed: Acquisition by homebuyer; 
Number of properties: 3; 
Number of properties with homebuyer assistance: 3. 

Activities reviewed: Acquisition and rehabilitation by homebuyer; 
Number of properties: 1; 
Number of properties with homebuyer assistance: 1. 

Activities reviewed: Total; 
Number of properties: 32; 
Number of properties with homebuyer assistance: 10. 

Source: GAO. 

[A] The properties in these categories were not yet at the resale 
stage (or in the case of demolitions not intended for resale) when 
homebuyer assistance is provided. 

[B] Of the five demolished properties, only one was acquired using NSP 
1 funds. The others were donated or blighted structures. 

[End of table] 

HUD Adapted an Information System for NSP 1, but Data on Program 
Outputs Have Limitations: 

HUD Modified DRGR and Provided Training and Guidance: 

HUD made several modifications to DRGR--a system that was designed to 
assist in managing Disaster Recovery grants--in order to collect 
information for NSP 1 and subsequent rounds of the program. For 
example, HUD modified system menus to include items unique to NSP, 
such as land banks; removed inapplicable items; and enabled grantees 
to designate whether properties had been sold or rented or were single-
or multifamily. HUD also provided training and technical assistance to 
HUD field staff and NSP grantees that were unfamiliar with DRGR. These 
efforts included one-on-one troubleshooting workshops, online 
information, and a help desk. In addition, HUD technical assistance 
providers held 10 joint sessions for HUD field staff and grantees on 
DRGR. 

As we have seen, grantees established action plans in DRGR, creating 
projects and linking activities to them. For activities, HUD required 
detailed information, including: 

* a national objective (e.g., targeting low-, moderate-, and middle- 
income persons),[Footnote 47] 

* an activity type (e.g., acquisition, rehabilitation, demolition, 
homeownership assistance, land banking, administration),[Footnote 48] 

* a responsible organization (grantee or subrecipient carrying out the 
activity), and: 

* performance measures (e.g., output measures such as the number of 
properties, housing units, or households or persons benefiting). 
[Footnote 49] 

In addition, HUD instructed grantees to enter projected and actual 
output measures for each activity in DRGR and provided a predetermined 
list of outputs for each activity type. HUD officials said they 
considered the number of households benefiting to be the primary 
output measure for NSP 1. Under each activity, HUD also required 
grantees to enter a property address at the point they obligated funds 
for a property. 

HUD headquarters developed training and checklists for CPD field 
office staff to use in reviewing the information grantees entered in 
DRGR, including action plans and QPRs.[Footnote 50] The action plan 
checklist required field offices to ensure that (1) grantees 
established an activity for each responsible organization, (2) 
activities met income-based national objectives, (3) every activity 
type had a corresponding NSP eligible use, and (4) each multifamily 
project had its own activity. The QPR checklist covers these areas and 
requires field staff to monitor grantees' progress in meeting their 
obligation deadlines and projected outputs. 

HUD uses DRGR for a number of monitoring and reporting purposes. As 
discussed earlier, HUD uses information grantees enter into DRGR to 
monitor grantees' progress in meeting obligation deadlines and set- 
aside requirements for low-income households. HUD also has put program-
wide and grantee-specific "snapshot" reports on its NSP Resource 
Exchange Web site to provide financial and other information about NSP 
1 to the public. In addition, the Administration has included DRGR-
generated information on NSP 1 in its monthly housing 
scorecard.[Footnote 51] Thus far, the scorecard has reported three 
output measures: (1) number of housing units constructed or 
rehabilitated, (2) number of housing units demolished or cleared, and 
(3) number of housing units for which direct homeownership assistance 
was provided. In the October housing scorecard, HUD reported that by 
March 2013, about 36,000 units would be rehabilitated or constructed; 
8,000 units would be demolished; and direct homeownership assistance 
would be provided for about 18,000 units.[Footnote 52] For reasons 
described in the next section, it is difficult to know the number of 
unique housing units or benefiting households these data represent, 
and the data may tend to understate activity-specific outputs. 

Reporting Flexibilities and Shortcomings in HUD Guidance Have Limited 
the Usefulness of Output Data in DRGR: 

Although DRGR has been a useful tool for monitoring grantees' 
obligations, variation in the way grantees were allowed to classify 
certain activities and select output measures in DRGR complicates the 
analysis of program outputs. As under the CDBG program---which was 
designed to give grantees substantial flexibility---HUD officials said 
they permit NSP 1 grantees to group activities in different ways. For 
example, HUD officials told us they instructed grantees to enter 
information for property acquisitions under a rehabilitation activity 
if the acquisition and rehabilitation are to be carried out by the 
same responsible organization and are to be rehabilitated within a 
short time frame. Accordingly, our review of DRGR information for 18 
grantees identified a number of variations, including: (1) one 
activity (classified as "rehabilitation") covering both the 
acquisition and rehabilitation of housing units; (2) two activities 
(one classified as "acquisition" and the other as "rehabilitation") 
for acquiring and rehabilitating units; and (3) one activity 
(classified as "acquisition for land banking") for acquiring, 
demolishing, and land-banking housing units.[Footnote 53] Due to these 
variations, totaling outputs for individual activity types can result 
in undercounting program outputs (because grantees that combine two or 
more activities report the associated outputs under a single activity 
type) and totaling outputs across multiple activity types can result 
in double counting program outputs (because grantees that do not 
combine activities may report the same outputs under multiple activity 
types).[Footnote 54] 

HUD officials said that the variation did not affect their ability to 
monitor grantees' compliance with program requirements but 
acknowledged that it complicated analysis of program outputs. HUD 
officials said they were in the process of identifying duplicate 
property addresses in DRGR, which will allow them to report total 
numbers of NSP 1 housing units and benefiting households without 
double counting these outputs. Undercounting is likely primarily an 
issue with the acquisition activity type, because, as previously 
noted, HUD allows grantees to combine acquisition and rehabilitation 
under a rehabilitation activity in some circumstances. Additionally, 
HUD officials said they were more focused on reporting outputs for 
"end uses" of NSP 1 funds, such as the number of housing units 
rehabilitated and demolished and the number of benefiting households. 

However, we found that grantees did not always group acquisition and 
rehabilitation under a rehabilitation activity. For instance, contrary 
to HUD's instructions, we identified several instances in which 
grantees combined acquisition and rehabilitation under an acquisition 
activity. HUD officials indicated they had found similar cases in 
their reviews of DRGR information. As a result, totaling output data 
for rehabilitation activities may understate actual outputs. HUD 
training and its QPR review checklist developed for CPD field staff 
responsible for reviewing activity data in DRGR do not adequately 
address this issue. In particular, the checklist that field staff use 
to review grantees' QPRs does not require field staff to determine 
whether grantees grouped activities in accordance with HUD guidance. 
As a result, HUD staff may not be detecting errors in how grantees are 
classifying activities, which can negatively affect the accuracy and 
reliability of NSP 1 output data and therefore the usefulness of these 
data for monitoring program progress and results. 

We also found variation in how grantees selected output measures for 
different activity types. For example, one grantee selected "number of 
properties" as its sole output measure for the majority of its 
activities (including acquisition and rehabilitation) and did not 
select numbers of households benefiting, which HUD told us it 
considers the program's primary output measure. For the same 
activities, another grantee selected multiple output measures--number 
of properties, housing units, households benefiting, and persons 
benefiting. HUD officials said they explained the output measures 
grantees should input into DRGR as part of DRGR training and strongly 
encouraged grantees to select all applicable output measures. However, 
the documentation HUD staff cited as guidance for grantees, including 
the NSP 1 Notice, did not provide specific instructions on which 
output measures should be linked to each activity type. Additionally, 
while HUD's QPR checklist requires field staff to determine whether 
grantees used the "right" output measures for each activity, it does 
not specify which output measures should be entered for each activity 
type. As a result, HUD may not be collecting consistent output data 
for each activity, which impairs the agency's ability to summarize and 
report on program outputs in an accurate and consistent manner. 

GAO's Standards for Internal Control emphasizes the need for federal 
agencies to collect reliable information with which to manage their 
programs and to review the integrity of performance measures.[Footnote 
55] Due to limitations in HUD guidance to grantees and field office 
staff, HUD lacks assurance that these standards are being met. 

A Planned Assessment of NSP Outcomes Will Focus on NSP 2 but Will Also 
Include NSP 1-assisted Areas: 

HUD is in the process of contracting for an assessment of NSP that 
will evaluate the impact of the program by tracking outcomes in the 
neighborhoods where NSP-assisted activities took place.[Footnote 56] 
HUD's Office of Policy Development and Research (PD&R) is overseeing 
the assessment in collaboration with CPD. The assessment will focus 
primarily on the impacts of NSP 2--which funds the same types of 
activities as NSP 1--but will also incorporate the results of NSP 1 
where the two rounds of the program overlap. According to PD&R staff, 
many neighborhoods receiving NSP 2 funds also received NSP 1 funds. 
HUD does not plan to conduct a separate assessment of NSP 1 outcomes, 
in part because HERA did not provide funding for an evaluation. 
However, ARRA, which authorized NSP 2, did provide funds for program 
evaluation. 

HUD has established outcome measures for NSP. In its May 2009 Notice 
of Funding Availability (NOFA) for NSP 2, HUD established short- and 
long-term outcome measures as guidance for grantees in their 
application process. CPD staff said they would also apply these 
measures to NSP 1. The outcome measures are: 

* short-term: (1) arrest decline in home values and (2) reduce or 
eliminate vacant and abandoned properties; and: 

* long-term: (1) increase sales in target areas and (2) increase 
median property values. 

PD&R staff said they have been working closely with CPD to develop the 
objectives and scope of the assessment. They said the assessment will 
track conditions and trends in NSP-assisted neighborhoods in relation 
to the short-and long-term outcome measures. They also will attempt to 
identify suitable comparison areas (e.g., similar areas that did not 
receive assistance) to demonstrate the impact of NSP, but expect this 
to be more challenging. Additionally, PD&R staff noted that DRGR was 
structured to track spending by DRGR activity rather than by property, 
making it difficult to determine the amount of NSP 1 funds that were 
spent in a particular geographic area. PD&R staff plan to obtain and 
review additional records from NSP 2 grantees to determine the amount 
of funds spent on NSP 2 properties and may collect similar information 
for NSP 1 properties in areas served by both rounds of the program. 
HUD is anticipating that the assessment will be completed no earlier 
than January 2014. Given that NSP 1 and NSP 2 share a common set of 
eligible activities, the results of the assessment should be useful 
for understanding the impact of both rounds of the program on assisted 
neighborhoods. 

Conclusions: 

NSP 1 provided a mechanism for state and local governments to mitigate 
the destabilizing effects of mortgage foreclosures, but HUD and 
grantees faced a number of implementation challenges, including the 
program's tight time frames and the limited capacity of some grantees 
to undertake real estate activities. HUD took actions to help grantees 
meet these challenges though guidance, training, and technical 
assistance. Additionally, HUD established internal control procedures 
to mitigate risks and promote compliance with program requirements. 
Our work suggests that these efforts helped grantees obligate funds in 
a timely manner, adopt strategies appropriate to their communities, 
and follow program rules. Nevertheless, because many NSP 1 activities 
have not been completed, continued HUD oversight will be required to 
ensure that any implementation and compliance problems are identified 
and addressed in an effective manner. In particular, HUD will need to 
follow through on its efforts to ensure that grantees are taking 
corrective actions on findings from on-site monitoring visits. 

As NSP 1 and other rounds of NSP progress, assessing program outputs 
and outcomes will become increasingly important. HUD took a number of 
important steps to collect key program data in DRGR, including 
information on grantees' activities and performance measures. However, 
variation in how grantees entered this information make it difficult 
to accurately summarize program outputs without undercounting (in the 
case of activity-specific outputs) or overcounting (in the case of 
program-wide outputs). While HUD has developed a method to resolve the 
overcounting issue, limitations in HUD's written guidance to grantees 
and field staff may be contributing to variation in data entry and 
impairing HUD's ability to accurately summarize program outputs. 
Existing guidance does not require field staff to review whether 
grantees properly grouped activities and does not specify which output 
measures grantees should select for each type of activity. Similarly, 
HUD has not provided grantees with written guidance specifying the 
output measures they should select for different activity types. In 
the absence of such guidance, HUD lacks assurance that it is 
collecting consistent information from NSP 1 grantees and that it is 
summarizing and reporting program outputs in an accurate manner. 
Because grantees involved in NSP 2 and 3 also are using DRGR, 
addressing limitations in written guidance would benefit HUD's 
analysis of output data for all rounds of NSP. 

Recommendations for Executive Action: 

To ensure the consistency of data collection in DRGR and enhance the 
reporting of program outputs for all rounds of NSP, we recommend that 
the Secretary of HUD take the following two actions: 

* Update the QPR review checklist to include reviews of whether 
grantees are (1) grouping activities in accordance with HUD 
instructions and (2) selecting the appropriate output measures for 
different activities. 

* Issue written guidance to NSP grantees on the output measures they 
should select for different activities. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to HUD for its review and comment. 
We received written comments from the Deputy Assistant Secretary for 
Grant Programs, CPD, that are reprinted in appendix II. We also 
received technical comments from HUD that we incorporated into the 
final report as appropriate. In its written comments, HUD stated that, 
in general, the draft report accurately represented its efforts to 
implement NSP 1. HUD also agreed to implement both of the report's 
recommendations in the first half of 2011. 

We are sending copies of this report to the appropriate congressional 
committees, the Secretary of Housing and Urban Development, and other 
interested parties. In addition, the report will be available at no 
charge on GAO's Web site at [hyperlink, http://www.gao.gov]. 

If you or your staffs have questions about this report, please contact 
me at (202) 512-8678 or sciremj@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. GAO staff who made key contributions to 
this report are listed in appendix III. 

Signed by: 

Mathew J. Scirè: 
Director, Financial Markets and Community Investment: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

Congress created the Neighborhood Stabilization Program (NSP), which 
is administered by the Department of Housing and Urban Development 
(HUD), to help reduce the number of foreclosed and abandoned 
properties and restore depressed local housing markets. The Housing 
and Economic Recovery Act of 2008 (HERA) authorized the first phase of 
this program (NSP 1), providing $3.92 billion in grant funds to states 
and local governments.[Footnote 57] HERA mandated that GAO report on 
whether NSP 1 funds were being used in a manner consistent with 
criteria set forth in the act. To respond to this mandate we examined 
(1) grantees' progress and challenges in meeting NSP 1 obligation time 
frames and income-targeting criteria, (2) HUD's actions to mitigate 
program risks and ensure grantees' compliance with key NSP 1 
requirements, and (3) HUD's efforts to collect program data and assess 
program performance. 

Grantee Progress and Challenges: 

To examine NSP 1 grantees' progress and challenges in meeting HERA 
obligation time frames and income-targeting criteria, we reviewed data 
from HUD's Disaster Recovery Grant Reporting (DRGR) system on grantee 
obligations, analyzed states' methods for distributing funds to other 
entities for obligation, and interviewed representatives from selected 
NSP 1 grantees (see selection criteria below). We also reviewed 
relevant HERA provisions and program guidance from the Department of 
Housing and Urban Development (HUD), including the NSP 1 Notice. 

We analyzed DRGR data as of June 24, 2010, and October 1, 2010, to 
calculate the percentage of their grant allocation each grantee had 
obligated at both points in time. Using the October data, we also 
calculated the overall percentage of NSP 1 funds obligated by grantees 
and the proportion of funds obligated for different activities. To do 
these calculations, we used the approach set forth in the NSP 1 
Notice, which does not differentiate between obligation of grant funds 
and program income in assessing progress toward obligation deadlines. 
[Footnote 58] For the analysis of obligations by activity type, we 
combined the data for acquisition, rehabilitation, and disposition 
because--as described in the body of this report--grantees sometimes 
group two or more of these activities together under a single activity 
in DRGR. 

Because state grantees could reallocate their funds to other entities 
(e.g., local governments) for obligation as long as the funds targeted 
areas of greatest need, we examined the methods states used to 
distribute their NSP 1 funds. We did this by analyzing information in 
DRGR on states' HUD-approved NSP 1 action plans to determine whether 
the states used required criteria for determining areas of greatest 
need and the types of distribution methods they used, including 
reallocation by competition, reallocation by formula, and through 
state-administered programs. Additionally, by analyzing DRGR data as 
of June 24, 2010, we also determined the number of states that 
reallocated funds to local governments that had also received NSP 1 
funds directly from HUD. We also determined the number of local 
governments that received NSP 1 funds both directly from HUD and from 
state reallocations, as well as the amount and percentage of program 
funds this represented. The funding amounts and percentages are 
approximate because in two states it was unclear from HUD data how 
reallocations were divided between two recipients, only one of which 
was a direct grantee. We included the entire reallocations for these 
two cases ($3.6 million in total) in our nationwide total of $175.8 
million as it seemed likely that the funds were used by the direct 
grantee. 

We also assessed the reliability of the DRGR information (discussed 
later in this section). We concluded that the data we used were 
sufficiently reliable for our purposes. 

We interviewed 11 grantees to discuss their approaches to implementing 
NSP 1, the progress they had made, and challenges they faced in 
meeting obligation time frames and income-targeting criteria. We 
selected these grantees to cover areas with substantial foreclosure 
problems and provide some variation in geographic location, housing 
market conditions, and grantee types. We also focused on grantees that 
had made some progress in implementing their NSP 1 programs. The 
grantees were: State of Indiana, City of Fort Wayne, and City of 
Indianapolis (Indiana); Lee County, Orange County, and City of Tampa 
(Florida); and State of Nevada, Clark County, City of Henderson, City 
of Las Vegas, and City of North Las Vegas (Nevada). We had previously 
spoken with these grantees during the first phase of our work, which 
we conducted in April through December 2009. 

We also interviewed officials from four HUD field offices about 
grantees' progress and challenges in implementing NSP 1. We selected 
these field offices to provide some geographic variation and because 
they were responsible for overseeing some of the grantees that we 
visited on-site. The field offices were located in Columbus, Ohio; 
Miami, Florida; Philadelphia, Pennsylvania; and San Francisco, 
California. 

We also spoke with staff from NeighborWorks® America and the National 
Community Stabilization Trust to obtain their perspectives on 
grantees' progress and challenges. 

HUD's Actions to Mitigate Risks and Ensure Compliance: 

To examine the steps HUD has taken to ensure grantees' compliance with 
key NSP 1 requirements and mitigate program risks, we reviewed NSP 1 
statutes and regulations and HUD's front-end risk assessment (FERA) 
for the program. We reviewed relevant documentation and interviewed 
HUD officials about the agency's efforts to hire additional staff to 
address gaps in capacity to oversee NSP 1 grantees (a program risk 
identified in the FERA) and to provide training and technical 
assistance to grantees. Additionally, we interviewed staff from the 11 
grantees described above about HUD's training, technical assistance, 
and oversight processes for NSP 1 to obtain their perspectives on 
these efforts. 

We reviewed HUD's internal controls for NSP 1, including HUD's 
guidance and procedures for monitoring grantee compliance with key 
program requirements. In addition, we reviewed results of on-site 
monitoring of NSP 1 grantees conducted by the four field offices we 
contacted. More specifically, we reviewed the results for the 40 
grantees for which the field offices had completed monitoring letters 
as of September 15, 2010.[Footnote 59] In addition, we interviewed HUD 
headquarters and field office officials on the status and results of 
their on-site monitoring. 

Additionally, we visited 8 grantees to conduct limited tests of 
compliance with key program requirements. We purposefully selected the 
grantees to cover different eligible NSP 1 activities, types of 
grantees, and geographic areas where characteristics of housing 
markets may vary. The grantees we selected were: Collier County and 
Lee County (Florida); City of Columbus and City of Dayton (Ohio); 
Maricopa County and City of Phoenix (Arizona); Philadelphia, 
Pennsylvania; and Prince William County, Virginia. We primarily 
focused on grantees with completed activities, which intentionally 
overrepresented grantees that had made the most progress in 
implementing NSP 1 at the time of our review and ensured we would 
review a variety of activities for compliance with NSP 1 key 
requirements. Further, to avoid overburdening grantees, we focused our 
site visits on grantees that, on the basis of information from HUD, 
were not receiving extensive technical assistance or being monitoring 
on-site by HUD staff. 

At each grantee, we reviewed records for four properties, for a total 
of 32 properties in our sample. To select the four properties to be 
reviewed at each grantee, we obtained a list of NSP 1 properties with 
completed activities and applied the following steps: (1) We 
identified the group of properties with the largest number of 
completed activities (e.g., acquisition, rehabilitation, resale, 
etc.). We grouped the remaining properties by type of activity. (2) We 
allocated the number of properties to be selected from the different 
groupings to intentionally capture properties with the most completed 
activities, while also covering the grantee's full range of 
activities. (3) We randomly selected properties from each group up to 
the predetermined allocation. 

We developed a checklist to review compliance with program 
requirements and internal controls for the following types of 
activities for each property: acquisition, rehabilitation, demolition, 
financing, and resale. We selected the checklist components by 
reviewing federal internal control standards and analyzing NSP 1 
requirements in statutes, regulations, and relevant HUD program 
guidance. Figure 8 in the body of this report includes the 
requirements and controls we reviewed. 

We are not able to generalize the results of our compliance testing to 
all NSP 1 grantees or activities. We did not conduct financial audits 
of the 8 grantees or the 32 properties. 

HUD Data Collection and Performance Assessment: 

To examine HUD's efforts to collect program data and assess the 
reliability of NSP data, we reviewed HUD Office of Inspector General 
(OIG) audits of the DRGR system. We interviewed OIG staff about these 
audits and reviewed documentation on HUD's actions to address the 
OIG's recommendations. We also reviewed documentation on HUD's 
modifications to DRGR and efforts to train system users. This 
information included HUD training materials and guidance to grantees 
and field staff on entering and reviewing data on program activities 
and output measures. We also interviewed HUD headquarters, HUD field 
office, and grantee staff with responsibilities for inputting or 
monitoring DRGR data. We also conducted reasonableness checks of DRGR 
data to identify any missing or erroneous data and by interviewing 
knowledgeable HUD officials to ensure we interpreted the data 
correctly. For the purpose of this and the first objective, we 
concluded that the data we used were sufficiently reliable for our 
purposes. 

Additionally, we reviewed the NSP output data that HUD posted on its 
NSP Web site and included in the Administration's monthly housing 
scorecard. Furthermore, we examined DRGR action plans and Quarterly 
Performance Reports (for the second quarter of calendar year 2010) for 
18 grantees--the 11 cited previously plus others we visited on-site 
(described in the previous section of this appendix). Our examination 
focused on the consistency with which grantees set up activities and 
selected program output measures in DRGR when entering their action 
plans and performance reports, and the extent to which they followed 
applicable HUD guidance. Finally, we reviewed federal internal control 
standards relevant to data quality and controls. 

To obtain information on HUD's plans to assess NSP 1, we reviewed the 
scope of work for a planned HUD study of NSP program outcomes. In 
addition, we interviewed HUD staff knowledgeable of the study, 
including officials from HUD's Office of Policy Development and 
Research and Office of Community Planning and Development. 

We conducted this performance audit from January to December 2010, in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the Department of Housing and Urban 
Development: 

U.S. Department Of Housing And Urban Development: 
Office Of Community Planning And Development: 
Washington, DC 20410-7000: 

December 6, 2010: 

Mr. Matthew J. Scirè: 	
Director, Financial Markets and Community Investment: 
US Government Accountability Office: 
441 G St., NW: 
Washington, DC 20548: 

Dear Mr. Scirè: 
	
Thank you for the opportunity to comment on the draft report entitled 
"Neighborhood Stabilization Program — HUD and Grantees Are Taking 
Actions to Ensure Program Compliance but Data on Program Outputs Could 
be Improved." 

In general, the Department finds that the draft report accurately 
represents the Department's efforts to implement the Neighborhood 
Stabilization Program (NSPI) since its enactment as part of the 
Housing and Economic Recovery Act of 2008 (HERA). Editorial comments 
on the draft report have been informally conveyed to your staff via a 
conference call on December 2, 2010. This letter provides a response 
to the Recommendations for Executive Action identified in the draft 
report. 

The first recommendation calls for HUD to "Update the QPR review 
checklist to include reviews of whether grantees are (1) grouping 
activities in accordance with HUD instructions and (2) selecting the 
appropriate output measures for different activities." The Department 
will revise the QPR checklist in draft format and issue it to 
Community Planning and Development (CPD) field staff for testing by 
March 31, 2011. Based on comments received from the field testing 
effort, HUD intends to issue a final revised QPR checklist not later 
than June 30, 2011. 

The second recommendation call for HUD to "issue written guidance to 
NSP grantees on the output measures they should select for different 
activities." The Department concurs with the recommendation and will 
issue guidance on this point not later than March 31, 2011. 

The Department appreciates the willingness of your staff to 
accommodate CPD staff schedules and workload considerations over the 
duration of this engagement as we have worked to implement not only 
NSP I but also NSP2 and NSP3. Please contact me at (202) 708-2111 if 
you have any questions regarding this matter. 

Sincerely, 

Signed by: 

Yolanda Chavez: 
Deputy Assistant Secretary for Grant Programs: 

[End of section] 

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Mathew J. Scirè, (202) 512-8678 or sciremj@gao.gov: 

Staff Acknowledgments: 

In addition to the individual named above, Steven Westley, Assistant 
Director; Allison Abrams; Emily Chalmers; Mya Dinh; Ying Long; John 
McGrail; Meredith Moore; Jasminee Persaud; and Carl Ramirez made key 
contributions to this report. 

[End of section] 

Footnotes: 

[1] P.L. 110-289. The American Recovery and Reinvestment Act of 2009 
(P.L. 111-5) provided an additional $2 billion in NSP funds (referred 
to as NSP 2) and changed several aspects of the program. Later, the 
Dodd-Frank Wall Street Reform and Consumer Protection Act (P.L. 111- 
203) enacted in July 2010 provided an additional $1 billion in funding 
for the program (referred to as NSP 3). This report focuses on NSP 1. 

[2] The CDBG program was first established in 1974 and is one of the 
federal government's largest and most flexible community and economic 
development programs. CDBG funds may be used to rehabilitate housing, 
improve infrastructure, provided job training, and fund other 
community-determined projects. 

[3] Funds went to 50 states, 4 insular areas, Puerto Rico, the 
District of Columbia, and 253 county and city governments. The four 
insular areas are American Samoa, Guam, Northern Marianas, and the 
Virgin Islands. 

[4] One grantee was included in both of these groups. 

[5] NSP 1 grantees may redevelop demolished or vacant properties for 
residential and nonresidential uses, commercial use, or mixed 
residential and commercial use. The American Recovery and Reinvestment 
Act limits redevelopment of such properties under NSP 2 and NSP 3 to 
residential purposes. 

[6] 73 Fed. Reg. 58330 (Oct. 6, 2008). 

[7] 74 Fed. Reg. 29225 (June 19, 2009). 

[8] CPD requires grantees to submit consolidated plans covering up to 
four of its major grant programs: CDBG, HOME Investment Partnerships, 
Emergency Shelter Grants, and Housing Opportunities for Persons with 
AIDS. 

[9] Generally, entitlement communities are (1) principal cities of 
metropolitan areas, (2) other metropolitan cities with populations of 
at least 50,000, and (3) qualified urban counties with populations of 
at least 200,000 (excluding the population of entitled cities). 

[10] Some examples include the building of community centers or 
firehouses, or repairing sewage treatment plants. 

[11] HERA required HUD to establish a formula for allocating NSP 1 
funds to states and eligible local governments no later than 60 days 
after the law's enactment and to distribute these funds no later than 
30 days after establishing the formula. 

[12] For details on HUD's methodology for allocating funds to state 
and local governments, see 73 Fed. Reg. 58343-9 (Oct. 6, 2008). 

[13] In response to disasters, Congress may appropriate additional 
funding for CDBG to provide disaster recovery grants to rebuild 
affected areas and provide seed money to start the recovery process. 

[14] Under the CDBG program, grantees' activities must meet one of 
three national objectives. They must either (1) benefit low-and 
moderate-income persons, (2) eliminate slums or blight, or (3) meet 
urgent needs. Under NSP, there is one national objective grantees' 
activities must meet--they must benefit low-, moderate-, and middle- 
income persons. Low-income is defined as 50 percent of AMI or lower, 
moderate-income as 51 percent to 80 percent of AMI, and middle-income 
as 81 percent to 120 percent of AMI. The middle-income category 
applies to NSP but not CDBG, which defines low-and moderate-income 
persons as those being at or below 80 percent of AMI. 

[15] HUD Office of Inspector General (OIG), HUD's Disaster Recovery 
Grant Reporting System Can Collect the Basic Information Needed to 
Monitor the Neighborhood Stabilization Program, 2009-FW-0001 
(Amended), June 25, 2009. 

[16] HUD OIG, Review of Selected Controls within the Disaster Recovery 
Grant Reporting System, 2009-DP-0007, September 30, 2009. 

[17] As discussed previously, a grantee's deadline depended on the 
date it received NSP 1 grant funds from HUD, so obligation deadlines 
varied among grantees. HUD officials confirmed that the majority of 
obligation deadlines expired in September 2010. 

[18] HUD made NSP 1 grant allocations to 309 units of state and local 
government. However, there are only 307 grant agreements because the 
State of Colorado and City of Colorado Springs (Colorado) entered into 
a cooperative grant agreement, as did Clark County and the City of Las 
Vegas (Nevada). 

[19] As indicated in the NSP 1 Notice, HUD did not distinguish between 
obligation of grant funds and program income (e.g., income a grantee 
received from reselling a property) in assessing compliance with the 
18-month requirement. Therefore, grantees met the requirement as long 
as they obligated grant funds and program income in an aggregate 
amount equal to their NSP 1 allocation. HUD officials said they took 
this approach so as not to penalize grantees that progressed faster in 
implementing NSP 1, potentially resulting in larger amounts of program 
income. 

[20] In its audits of the State of Kansas and the City and County of 
Denver, the OIG concluded that these grantees had improperly obligated 
NSP 1 funds by reporting its funds as obligated without linking these 
funds to a specific address or household, as required. See HUD OIG, 
The State of Kansas Did Not Properly Obligate Its Neighborhood 
Stabilization Program Funds, 2010-KC-1006, August 20, 2010; and HUD 
OIG, The City and County of Denver Did Not Properly Obligate and 
Report NSP 1 Funding, 2010-DE-1006, September 17, 2010. However, 
several other OIG compliance audits found that the grantees generally 
complied with NSP 1 requirements. 

[21] Depending on the grantee's NSP 1 performance and the amount of 
unobligated funds, HUD may enter into a memorandum of agreement with 
the grantee designed to enable use of the funds for the purposes 
intended in the NSP 1 Notice. See 75 Fed. Reg. 52772 (Aug. 27, 2010). 

[22] Under CDBG, HUD provides funds to metropolitan cities and urban 
counties, known as entitlement communities, and provides funds to 
states for distribution to nonentitlement communities. States may not 
use CDBG funds directly. However, the NSP 1 Notice spells out the 
various ways in which states may use NSP 1 funds directly for 
activities, including using their own employees, procuring 
contractors, or providing grants through nonprofit subrecipients, 
among other direct uses. In prior work, we examined how the states 
distribute CDBG funds. See GAO, Community Development Block Grants: 
Entitlement Communities' and States' Methods of Distributing Funds 
Reflect Program Flexibility, [hyperlink, 
http://www.gao.gov/products/GAO-10-1011] (Washington, D.C.: Sept. 15, 
2010). 

[23] The percentage (9) and dollar amount ($176 million) are estimates 
because in two cases it was unclear exactly how much NSP 1 funds were 
reallocated to direct local government NSP 1 grantees. However, we 
included the amount in the estimates--totaling $3.6 million--as it 
seemed likely that the funds were used by the direct grantee. 

[24] For 3 states, it was unclear from their action plans which method 
was used to distribute funds within the state. Our review of states' 
NSP action plans included all 50 states and the District of Columbia 
but did not include Puerto Rico. 

[25] A soft second loan is a second mortgage with payments that are 
forgiven, deferred, or subsidized in some fashion, generally until 
resale of the mortgaged property. 

[26] As discussed in appendix I, we spoke with 18 grantees (2 states, 
6 counties, and 10 cities). 

[27] The two grantees that did not obligate their total grant amounts 
by October 1 had obligated 94 percent and 97 percent, respectively. 

[28] Harriet Newburger, Federal Reserve Bank of Philadelphia, 
"Acquiring Privately Held REO Properties with Public Funds: The Case 
of the Neighborhood Stabilization Program." REO & Vacant Properties: 
Strategies for Neighborhood Stabilization, A Joint Publication of the 
Federal Reserve Banks of Boston and Cleveland and the Federal Reserve 
Board, 2010. 

[29] HUD Secretary Announces National First Look Program To Help 
Communities Stabilize Neighborhoods Hard-Hit By Foreclosure, September 
1, 2010. 

[30] 75 Fed. Reg. 41225 (July 15, 2010). 

[31] The purpose of a FERA is to detect conditions that may adversely 
affect the achievement of program objectives and to provide reasonable 
assurance that program goals, including compliance with applicable 
laws and regulations, will be met. The FERA is mandatory for any new 
HUD program with a funding level totaling $10 million or more and for 
certain substantially revised programs. HUD uses the FERA in 
accordance with principles of risk assessment outlined in OMB Circular 
A-123, to identify and analyze risks, from both internal and external 
sources, which may affect the ability of the agency to meet objectives. 

[32] The eight modules were: (1) Eligible Uses, Activities, and 
Properties; (2) Pre-Acquisition Considerations; (3) Post-Acquisition 
Considerations; (4) Disaster Recovery Grant Reporting System; (5) 
Financing Issues; (6) Program Administration; (7) Land Banking and 
Demolition; and (8) Eligible Use Scenarios. They are available at 
[hyperlink, 
http://www.hud.gov/offices/cpd/communitydevelopment/programs/neighborhoo
dspg/training/index.cfm]. 

[33] Aggregate purchases for NSP are defined as all of the properties 
that an NSP grantee purchases with its NSP funds. 

[34] We spoke with a number of grantees we contacted during our review 
about the impact of HUD's definition changes on their NSP programs. 
This work was done in coordination with another GAO team reviewing 
issues of incomplete or "abandoned" foreclosures. See GAO, Mortgage 
Foreclosures: Additional Mortgage Servicer Actions Could Help Reduce 
the Frequency and Impact of Abandoned Foreclosures, GAO-11-93 
(Washington, D.C.: Nov. 15, 2010). 

[35] The term "abandoned" was originally defined as a property that 
had been foreclosed upon and was vacant for at least 90 days. However, 
HUD explained that this definition limited opportunities for acquiring 
properties in a strategic and timely manner. For example, the 
requirement that the property had to be vacant for at least 90 days 
left out properties abandoned by owners, but where tenants were still 
in place. Therefore, HUD expanded the definition of abandoned to 
include vacant and nonvacant properties (a) for which no mortgage or 
tax payments have been made by the property owner for at least 90 
days, (b) for which a code enforcement inspection determined that the 
property is not habitable and the owner has taken no corrective 
actions within 90 days of the notification of the deficiencies, or (c) 
subject to a court-ordered receivership or nuisance abatement related 
to abandonment. 

[36] Local technical assistance providers serviced the following 
locations: Northern and Southern California, Northern and Southern 
Florida, Illinois, Indiana, Ohio, Georgia, New England, and Michigan. 
HUD news release: HUD No. 09-159 on August 26, 2009. 

[37] The field offices are in Jacksonville and Miami, Florida; 
Columbus, Ohio; Detroit, Michigan; San Francisco and Los Angeles, 
California; and Las Vegas, Nevada. The Las Vegas field office reports 
to the San Francisco regional office. 

[38] The HUD OIG identified some inconsistency in the way HUD field 
offices applied the special conditions. While some field offices 
considered past performance only in the CDBG program, others also 
considered grantees' performance in other HUD programs--for example, 
HOME Investment Partnerships and the Supportive Housing Program. See 
HUD Office of the Inspector General Audit Report 2010-CH-0001, March 
29, 2010. 

[39] HUD officials told us that HUD headquarters staff reverified 
compliance with the checklist for the vast majority of grantees. 

[40] HUD Notice CPD-09-04: Implementing Risk Analyses for Monitoring 
Community Planning and Development Grant Programs in FY 2010 and 2011, 
Issued 8-24-2009. 

[41] As of the end of September 2010, the OIG had issued capacity 
audits of 22 NSP 1 grantees and found that 12 grantees generally had 
sufficient capacity, while 8 grantees needed to improve their capacity 
to administer the program. Further, 2 grantees did not have the 
capacity to effectively and efficiently administer NSP funding. 
Examples of lack of capacity included inadequate staffing levels and 
policies, procedures, and internal controls. 

[42] In total, the four field offices are responsible for overseeing 
86 NSP 1 grantees, 50 of which they monitored on-site. We reviewed the 
monitoring results for the 40 grantees for which the field offices had 
completed "monitoring letters" as of September 15, 2010. Sixty days 
after completing an on-site visit, HUD field staff send a monitoring 
letter to the grantee discussing, among other things, the field 
staff's conclusions, any monitoring findings, and any corrective 
actions required. 

[43] Monitoring letters containing findings specify corrective actions 
the grantee should take and the time frame in which the grantee should 
respond. 

[44] See appendix I for a detailed description of our methodology. 

[45] By focusing on grantees with completed activities, our sample 
intentionally overrepresented those grantees that had made the most 
progress in implementing NSP 1 at the time of our review. Also, while 
our methodology for selecting properties at each grantee focused on 
properties with the most completed activities, some planned activities 
for some of the properties in our sample had yet to be completed. We 
did not include those planned activities in our compliance review. 

[46] For one property, however, the grantee did not receive final 
supervisory approval of an otherwise complete environmental review 
until after the property had been acquired. 

[47] As previously noted, under the CDBG program, grantees' activities 
must meet one of three national objectives, but under NSP grantees' 
must meet one national objective--they must benefit low-, moderate-, 
and middle-income persons. 

[48] The activity type menu in DRGR includes a number of variations of 
acquisition, rehabilitation, and other major activity types. For ease 
of presentation, we generally refer only to the major activity type 
(e.g., "acquisition" or "rehabilitation"). 

[49] Outputs are the products and services delivered by a program. 

[50] HUD headquarters staff set policy for managing and monitoring NSP 
1 activities, and CPD field staff conduct the actual oversight of 
individual grantees under their purview. 

[51] The scorecard contains data on key housing market indicators and 
includes performance metrics for the Administration's housing recovery 
efforts. Data are presented by HUD and the Department of the Treasury 
in "The Obama Administration's Efforts to Stabilize the Housing Market 
and Help American Homeowners" brochure, October 2010. 

[52] HUD data indicate that the number of rehabilitated units is 
greater than the number of newly constructed units. 

[53] We reviewed action plans and QPRs for the second quarter of 
calendar year 2010 for the 18 grantees we interviewed or visited on- 
site. (See appendix I for a list of these grantees and our selection 
criteria.) 

[54] To illustrate, for a grantee that used a "rehabilitation" 
activity to report outputs for the acquisition and rehabilitation of 
five housing units, DRGR would show no properties under "acquisition" 
(understating the actual number of acquisitions by five). For a 
grantee that set up both "acquisition" and "rehabilitation" activities 
for acquiring and rehabilitating five units, DRGR would show five 
units under each activity. Consequently, totaling across these 
activities would result in double counting. 

[55] See GAO, Standards for Internal Control in the Federal 
Government, [hyperlink, 
http://www.gao.gov/products/GAO/AIMD-00-21.3.1] (Washington, D.C.: 
November 1999). 

[56] Outcomes describe the intended result of carrying out a program 
or activity. 

[57] P.L. 110-289. The American Recovery and Reinvestment Act of 2009 
(P.L. 111-5) provided an additional $2 billion in NSP funds (referred 
to as NSP 2) and changed several aspects of the program. The Dodd-
Frank Wall Street Reform and Consumer Protection Act (P.L. 111-203), 
enacted in July 2010, provided an additional $1 billion for the 
program (referred to as NSP 3). This report focuses on NSP 1. 

[58] That is, we considered grantees to have met the obligation 
requirement as long as they obligated grant funds and program income 
in an aggregate amount equal to their NSP 1 allocation. HUD officials 
said they took this approach so as not to penalize grantees that 
progressed faster in implementing NSP 1, potentially resulting in 
larger amounts of program income. 

[59] In total, the four field offices are responsible for overseeing 
86 NSP 1 grantees, 50 of which they monitored on-site. Sixty days 
after completing an on-site visit, HUD field staff send a monitoring 
letter to the grantee discussing, among other things, the field 
staff's conclusions, any monitoring findings, and any corrective 
actions required. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: