This is the accessible text file for GAO report number GAO-11-112 
entitled 'Defense Acquisitions: DOD Needs to Reassess Joint Cruise 
Missile Costs before Starting New Production Phase' which was released 
on October 13, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office:
GAO: 

October 2010: 

Defense Acquisitions: 

DOD Needs to Reassess Joint Cruise Missile Costs before Starting New 
Production Phase: 

GAO-11-112: 

GAO Highlights: 

Highlights of GAO-11-112, a report to congressional committees. 

Why GAO Did This Study: 

Over the past two and a half decades, the Department of Defense (DOD) 
has invested heavily to acquire a cruise missile capable of attacking 
ground targets stealthily, reliably, and affordably. After abandoning 
an earlier, more expensive missile and a joint service effort, the Air 
Force began producing the Joint Air-to-Surface Standoff Missile 
(JASSM) in 2001. After that, the program (1) encountered many flight 
test failures, (2) decided to develop an extended range version, and 
(3) recognized significant cost growth. The production decision for 
the JASSM-ER is planned for November 2010. Also, the Secretary of 
Defense has recently announced a major initiative to restore 
affordability and productivity in defense spending. This initiative is 
expected to, among other things, identify savings by conducting needed 
programs more efficiently. 

As DOD faces the initial production decision on JASSM-ER, GAO was 
asked to assess (1) most recent test results, correction of causes of 
previous flight test failures, and efforts to improve JASSM’s 
reliability; and (2) JASSM cost changes, efforts to control costs, and 
additional cost risks for the program. 

What GAO Found: 

Since 2007, design changes and other corrective actions by the Air 
Force have improved the baseline JASSM’s test results significantly—
the missile has now demonstrated 85 percent success versus 58 percent 
achieved previously and before the corrections. The JASSM-ER variant 
has done well thus far, with no failures during the first seven flight 
tests. These results reflect the Air Force’s enhanced oversight of the 
program and significant investments made to improve reliability. These 
efforts also identified many of the root causes for flight test 
failures. While baseline JASSM missile reliability has improved, it is 
not expected to achieve the Under Secretary of Defense for 
Acquisition, Technology and Logistics’ required level of 90 percent 
until 2013. Tests conducted thus far of the improved baseline JASSM 
and the JASSM-ER variants have been developmental—or controlled—in 
nature. Neither the improved JASSM baseline missile nor the JASSM-ER 
has been demonstrated in operationally realistic testing or in a 
combat operation. 

Table: JASSM Estimated Costs and Quantities Through 2025: 

Quantities to be produced: 
December 1998: 2,400; 
May 2008: 4,900; 
December 2009: 4,900. 

Total Program Cost (millions): 
December 1998: $2,232.5; 
May 2008: $6,641.4; 
December 2009: $7,129.4. 

Program Unit Cost (thousands): 
December 1998: $907.0; 
May 2008: $1,327.0; 
December 2009: $1,421.0. 

Procurement Unit Cost (thousands): 
December 1998: $515.0; 
May 2008: $1,073.0; 
December 2009: $1,160.0. 

Source: GAO analysis of Department of Defense data. 

Note: Fiscal year 2010 dollars. 

[End of table] 

JASSM costs have increased by over seven percent since the program was 
restructured in 2008. As the table shows, since 1998, JASSM quantities 
have more than doubled and estimated program costs have grown from 
$2.2 billion to a $7.1 billion. The Air Force has taken several steps 
to control JASSM costs, but options to reduce costs at this point 
appear limited. In fact, several factors suggest additional cost 
growth is likely. First, the Air Force has not been able to provide 
enough funding to produce the missiles at planned rates. That has led 
to a less efficient production process, a longer production period, 
and higher costs that have not yet been reflected in the $7.1 billion 
estimate. Second, the Air Force’s potential plans to retrofit existing 
missiles with the reliability improvements may not be feasible, given 
the missile’s sensitivity to being reopened. If retrofits prove 
infeasible, new replacements may have to be purchased; if they are 
feasible, the Air Force may have to provide additional funding to 
retrofit all existing missiles. Finally, since the Air Force last 
compared JASSM to possible alternatives, the unit cost was assumed to 
be about 40 percent less than currently expected and that now could 
make alternatives more competitive in terms of cost and/or 
capabilities. A reevaluation of the JASSM program, given that most of 
its costs have yet to be incurred, is warranted before the decision to 
produce the JASSM-ER is made. 

What GAO Recommends: 

GAO recommends that the Secretary of Defense reevaluate the JASSM 
program’s affordability and cost-effectiveness before making the 
decision to produce the JASSM-ER. DOD partially concurred with GAO’s 
assessment, but believes the JASSM-ER should begin production in 
November 2010. GAO believes that it is incumbent upon the department 
to reexamine JASSM before making the production decision to ensure 
that the program is structured as efficiently as possible and is still 
a good investment given the other demands DOD faces. 

View [hyperlink, http://www.gao.gov/products/GAO-11-112] or key 
components. For more information, contact Mike Sullivan at (202) 512-
4841 or sullivanm@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

Corrective Actions Have Led to Improved JASSM Test Results but 
Operational Effectiveness Is Still to Be Demonstrated: 

Several Areas of Potential Cost Risk Could Further Increase JASSM 
Program Costs: 

Conclusions: 

Recommendation for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: Comments from the Department of Defense: 

Appendix III: JASSM Baseline and JASSM-ER Cost Estimates Met Most Best 
Practices, but the Risk Analyses Did Not Consider Reliability or 
Extending the Production Schedule: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1: Changes Since 2008 in JASSM Estimated Cost, Schedule, and 
Quantities through 2025: 

Table 2: Flight Test Cost to Increasing Reliability: 

Table 3: Extent to Which the Cost Estimating Practices for JASSM 
Baseline and JASSM-ER Reflect GAO Best Practices: 

Figures: 

Figure 1: JASSM Missile Reliability Assessment Flight Test: 

Figure 2: Initial JASSM Program Schedule: 

Figure 3: JASSM's Original Acquisition Strategy: 

Figure 4: JASSM Subsystems Involved in Flight Test Failures: 

Figure 5: JASSM Baseline Missile Test Results: 

Figure 6: Comparison of JASSM's Original and 2009 Total Acquisition 
Funding Profiles: 

Figure 7: JASSM Baseline and JASSM-ER Cost Estimate Trend Analysis 
1997 through 2009: 

Abbreviations: 

CARD: Cost Analysis Requirements Document: 

CAIG: Cost Analysis Improvement Group: 

DOD: Department of Defense: 

JASSM: Joint Air-to-Surface Standoff Missile: 

JASSM-ER: Joint Air-to-Surface Standoff Missile Extended Range: 

OSD: Office of Secretary of Defense: 

TSPR: Total System Performance Responsibility: 

TSSAM: Tri-Service Standoff Attack Missile: 

U.S.C. United States Code: 

USD/ATL: Under Secretary of Defense for Acquisition, Technology, and 
Logistics: 

WBS: Work Breakdown Structure: 

[End of section] 

United States Government Accountability Office:
Washington, DC 20548: 

October 13, 2010: 

Congressional Committees: 

Over the past two and a half decades, the Department of Defense (DOD) 
has invested heavily to acquire an Air Force air-to-ground cruise 
missile capable of stealthy flight and reliable performance at 
affordable costs. The Air Force invested in the Tri-Service Standoff 
Attack Missile (TSSAM) from 1986 through 1994 but ended the program 
once the unit costs exceeded $2 million per missile and as testing 
issues surfaced. The Air Force is currently in production for the 
Joint Air-to-Surface Standoff Missile (JASSM). This program is 
intended to provide a next-generation cruise missile capable of 
striking high-value, highly defended targets from outside the enemy's 
air defenses launched from a variety of aircraft, including the B-1, B-
2, B-52, and F-16. Over the first several years of the program, the 
Air Force (1) encountered many flight test failures, (2) decided to 
develop an extended range version, and (3) recognized significant cost 
growth which led to a critical Nunn-McCurdy unit cost breach in 2006. 
[Footnote 1] The Air Force is about to begin producing the extended 
range version (JASSM-ER) that will more than double the range of the 
baseline missile. The two variants of JASSM are approximately 70 
percent common in hardware and 95 percent common in software. 

As DOD approaches the production decision on JASSM-ER, you asked us 
(1) to assess the results of testing, whether the causes of previous 
flight test failures have been corrected, and Air Force initiatives to 
improve JASSM's reliability; and (2) to identify the extent JASSM 
costs have changed over time, the steps the Air Force is taking to 
control costs, and additional cost risks, if any, for the program. We 
note that the production decision on JASSM-ER is being made shortly 
after the Secretary of Defense announced a major initiative to improve 
the cost efficiency of weapon systems acquisition. 

To determine JASSM's current costs and the extent they have changed, 
we analyzed JASSM's contracts, budgets, and selected acquisition 
reports. We compared the cost estimating practices of Office of 
Secretary of Defense (OSD) cost analysts in the development of the 
life-cycle cost estimates for JASSM and JASSM-ER to our Cost 
Estimating and Assessment Guide.[Footnote 2] To assess the results of 
the most recent tests and to determine if corrective actions have been 
implemented, we analyzed JASSM flight test results and the results of 
the failure review boards to determine scoring criteria and results 
and what corrective actions were implemented. We interviewed officials 
with the JASSM joint program office, Lockheed Martin--the prime 
contractor, the Air Force, and Office of Secretary of Defense. We 
interviewed a former Air Force official who was an early JASSM program 
manager to better understand the program's objectives and original 
acquisition strategy. We also reviewed our prior work on best 
acquisition practices which established a set of evaluation criteria 
for a knowledge-based acquisition approach.[Footnote 3] We conducted 
this performance audit from November 2009 through October 2010 in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

The JASSM program began in 1995 and was to be an affordable, joint 
program between the Air Force and the Navy to meet an urgent need with 
a streamlined acquisition strategy. JASSM predecessor TSSAM was also 
planned to be a low-cost cruise missile able to deliver several 
different munitions. However, after several unsuccessful flight tests, 
the lead contractor for TSSAM initiated a reliability improvement 
program to address higher reliability requirements, but demonstration 
of whether problems had been resolved would have taken several years 
and cost more than $300 million. As costs for TSSAM increased, the 
Army ended its participation in the program and after a period of 
declining budgets and changes to threat scenarios, a cost and 
operational effectiveness analysis was completed, which showed that 
other options might be adequate to meet national security 
requirements. In 2004, the Navy left the JASSM program citing it as a 
redundant capability to other systems in its inventory. JASSM was 
expected to require minimal maintenance while in storage and life-
cycle cost was to be controlled through improved reliability and 
supportability achieved during development. 

Figure 1: JASSM Missile Reliability Assessment Flight Test: 

[Refer to PDF for image: photograph] 

Source: JASSM program office. 

[End of figure] 

To execute the acquisition strategy and meet cost and schedule goals, 
the Air Force used Total System Performance Responsibility (TSPR). 
[Footnote 4] TSPR generally gives the contractor total responsibility 
for the entire weapon system and for meeting DOD requirements, with 
minimum government oversight. The Air Force made initial JASSM 
requirements flexible to allow Lockheed Martin to have clear control 
of the design and product baseline. Program officials stated this 
strategy was based on other successful programs, such as the Joint 
Direct Attack Munition program, and would allow the contractor 
flexibility to make changes to meet cost and schedule deadlines 
without having to consult with the government. An example of this 
flexibility was the mission missile effectiveness requirement. The 
effectiveness requirement is the minimum number of missiles required 
to kill specified targets and was named as a key performance 
parameter, allowing trades between reliability, survivability, and 
lethality. In other words, if the program was successful at achieving 
high levels of survivability and lethality, reliability could remain 
low, even fluctuate, and still meet the stated parameters. Quantities 
for JASSM were established by reviewing the threshold targets and 
determining the number of missiles necessary to meet operational 
damage criteria, based on missile performance using the effectiveness 
requirement. Therefore, changes to reliability would affect the 
quantities necessary to meet requirements. 

Figure 2: Initial JASSM Program Schedule: 

[Refer to PDF for image: illustrated schedule] 

FY 1994, Q4: TSSAM termination. 

FY 1995, Q4-FY 1996 Q3: Proposal. 

FY 1995, Q3: Milestone A. 

FY 1995, Q4-FY 1998 Q4: Risk reduction (24 months). 

FY 1998, Q3: MIlestone B. 

FY 1998, Q4-FY 2001, Q2: Development (32 months). 

FY 1999, Q4-FY 2000, Q4: 4 flight tests. 

FY 2000, Q3: Low-rate production. 

FY 2001, Q3: Milestone C. 

FY 2001, Q3: Lot 1, 87. 

FY 2002, Q3: Lot 2, 91. 

FY 2003, Q3: Lot 3, 242. 

FY 2004, Q3: Lot 4, 340. 

FY 2005, Q3: Lot 5, 346. 

FY 2006, Q3: Lot 6, 360. 

FY 2007, Q3: Lot 7, 360. 

FY 2008, Q3: Lot 8, 360. 

FY 2009, Q3: Lot 9, 214. 

Source: GAO analysis of DOD data. 

[End of figure] 

As part of the program's 1995 acquisition strategy, the Air Force 
received five proposals for JASSM and in 1996 selected Lockheed Martin 
and McDonnell Douglas to begin a 24-month risk-reduction phase. 
Following the risk-reduction phase, the Air Force planned 32 months 
for development and a total of 56 months from program start to full-
rate production in 2001. The program planned for concurrent 
developmental and operational testing and evaluation with four flight 
tests planned before initial production. The Air Force planned to have 
nine fixed-price production lots from 2001 through 2009 totaling 2,400 
baseline missiles with an initial program cost estimate of $2.2 
billion (fiscal year 2010 dollars). 

A former Air Force official who was an early JASSM program manager 
stated the Air Force accepted Lockheed Martin's proposal, which 
included favorable fixed-price contract prices for production lots 1 
through 5 with the understanding that the prices would increase after 
Lot 5. JASSM's acquisition strategy planned for a 74 percent unit cost 
increase between Lots 5 and 6. The cost increase between Lots 5 and 6 
was to occur at a time when quantities were increasing. Despite this 
planned cost increase, the production unit costs would have remained 
within the Air Force's acceptable range established before the 
competition and at much less cost than TSSAM. Further, the prices 
offered by Lockheed Martin for the first five production lots were 
below the Air Force's desired cost range for the system. Air Force 
officials said the low costs contributed to Lockheed Martin's 
selection. However, to maintain the benefits of this pricing, the 
quantities purchased by the Air Force had to remain within a certain 
range for each of the first 5 years. 

Figure 3: JASSM's Original Acquisition Strategy: 

[Refer to PDF for image: illustrated line graph] 

Air Force planned range for unit cost projection: $500,000-$900,000. 

Fiscal year: 2001	
Unit cost projection: $395,000; 
Lot: 1; 
Quantity: 87. 

Fiscal year: 2002	
Unit cost projection: $397,000; 
Lot: 2; 
Quantity: 91. 

Fiscal year: 2003	
Unit cost projection: $354,000; 
Lot: 3; 
Quantity: 242. 

Fiscal year: 2004	
Unit cost projection: $355,000; 
Lot: 4; 
Quantity: 340. 

Fiscal year: 2005	
Unit cost projection: $357,000; 
Lot: 5; 
Quantity: 346. 

Fiscal year: 2006	
Unit cost projection: $620,000; 
Lot: 6; 
Quantity: 360. 

Fiscal year: 2007	
Unit cost projection: $606,000; 
Lot: 7; 
Quantity: 360. 

Fiscal year: 2008	
Unit cost projection: $606,000; 
Lot: 8; 
Quantity: 360. 

Fiscal year: 2009	
Unit cost projection: $594,000; 
Lot: 9; 
Quantity: 214. 

Source: GAO analysis of DOD data. 

Notes: The increase between Lot 5 and Lot 6 represents a 74 percent 
increase in unit costs. Fiscal year 2010 dollars. Quantities are all 
Air Force. 

[End of figure] 

While the Air Force planned for some cost growth in the original 
acquisition strategy, the program's cost grew much more than expected. 
For the first four production lots, the Air Force benefited from the 
favorable prices in the original contract. However, because of funding 
limitations, it was not able to procure the minimum missile purchase 
in Lot 5 and had to renegotiate this lot with Lockheed Martin. In 
doing so, Lockheed Martin was able to renegotiate Lot 5 prices based 
on its actual production costs--at over $1 million per missile. Air 
Force documentation indicates that previously negotiated unit prices 
for Lot 1 through Lot 5 were as much as 45 percent less than Lockheed 
Martin's actual costs. Subsequent lots that had not been negotiated 
under the original contract similarly reflected an increase in price. 

Most of this cost growth took place prior to 2006, culminating in a 
critical Nunn-McCurdy unit cost breach late in 2006. According to 
program documents, several causes have been cited for the critical 
Nunn-McCurdy unit cost breach: an unrealistic cost estimate resulting 
from a flawed acquisition strategy; the addition of 2,500 more 
expensive JASSM-ER variants; the costly efforts to overcome 
reliability problems; and reduced annual production rates for a longer 
period. Following the critical Nunn-McCurdy unit cost breach, the Air 
Force halted production of the missiles until DOD certified that the 
program should continue. The Under Secretary of Defense for 
Acquisition, Technology, and Logistics (USD/ATL) found no lower cost 
alternatives and certified the program in 2008, despite the missile's 
higher than projected production costs. 

Since operational testing began in 2001, the reliability of the JASSM 
missile has been inconsistent. The Air Force flight-tested 62 baseline 
missiles from January 2001 through May 2007, resulting in 25 failures 
and 3 "no tests," which was a 58 percent reliability success rate. 
However, because the program's strategy allowed for the contractor to 
manage to mission effectiveness by combining reliability with other 
factors, the 58 percent reliability rate was sufficient to meet 
mission effectiveness criteria. The Air Force tracked reasons for 
flight test failures, but was not part of the failure review boards 
until production Lot 5, 5 years after the start of operational 
testing. Air Force officials stated that until 2006, Lockheed Martin 
handled all flight test failure review determinations and made 
corrective actions internally and the government was not heavily 
involved. During the Nunn-McCurdy certification process, USD/ATL 
directed the JASSM program to develop a reliability growth plan that 
would achieve 90 percent reliability for the baseline missile. The 
program set a goal of achieving this reliability rate by Lot 11, or 
fiscal year 2013. In addition, the JASSM-ER program set a reliability 
goal of 85 percent by Lot 4, or fiscal year 2014. 

In our 2000 report on JASSM, we recommended the Secretary of Defense 
revise its acquisition strategy for the JASSM program to be more 
closely linked to demonstrating that the missile design is stable and 
can meet performance requirements before making the production 
decision.[Footnote 5] DOD partially concurred with our recommendation 
stating that its acquisition strategy is directly linked to knowledge 
points, that it is linked to specific criteria established for making 
the low-rate initial production decision, and that the contractor is 
required to meet these criteria. We concluded that, while the Air 
Force had taken steps to link production decisions for JASSM to 
knowledge, we did not believe that the specific criteria established 
to support a production decision were sufficient to minimize cost and 
schedule risk. 

In June 2010, the Secretary of Defense announced an initiative to 
restore affordability and productivity in defense spending. He stated 
that there is a need to abandon inefficient practices accumulated in a 
period of budget growth and learn to manage defense dollars in a 
manner that is "respectful of the American taxpayer at a time of 
economic and fiscal stress." He set a goal to save $100 billion over 
the course of the 5 year defense planning period. Subsequently, 
USD/ATL has issued guidance on delivering better value to the taxpayer 
and improving the way DOD does business. That guidance indicated that 
budget savings could be found by eliminating unneeded and costly 
programs and activities as well as by conducting needed programs and 
activities more efficiently, such as by stabilizing production rates. 
Subsequently, in a September 14, 2010, memorandum, USD/ATL provided 
specific guidance to acquisition professionals to achieve this 
mandate. That guidance included 23 principle actions to improve 
efficiency, including "Mandate affordability as a requirement" and 
"Drive productivity growth through Will Cost/Should Cost management." 

Corrective Actions Have Led to Improved JASSM Test Results but 
Operational Effectiveness Is Still to Be Demonstrated: 

Since 2007, the Air Force has enhanced its oversight of the JASSM 
program and made significant investments to improve its reliability as 
directed by USD/ATL. As a result of increased reliability testing and 
investments in reliability initiatives, the Air Force has identified 
many of the root causes for flight test failures. Since then, design 
changes and other corrective actions have improved JASSM baseline's 
test results significantly--now demonstrating 85 percent success. The 
JASSM-ER variant has done well thus far, with no scored failures 
during the first seven flight tests. However, while JASSM baseline 
missile reliability has improved, it is not expected to achieve the 
USD/ATL-required level of 90 percent until 2013, and its operational 
effectiveness has not yet been demonstrated either through operational 
testing or use in a combat operation. 

Enhanced Oversight and Increased Investments Have Led to Corrective 
Actions and Improved JASSM Reliability: 

In 2004, after two back-to-back flight test failures, the Air Force 
formed a reliability enhancement team to address what it considered 
the loss of confidence in JASSM's performance, OSD's concerns about 
the program, and budget reductions. The team's report stated that 
while JASSM's development and reliability were within acceptable 
ranges when compared to other cruise missiles, the JASSM program 
should increase testing to discover additional weaknesses in design or 
production as well as increase confidence in the level of reliability 
achieved and tie those results to contractor incentives. In 2007, 
after direction from USD/ATL and the Air Force during the Nunn-McCurdy 
certification process, the program office updated the Joint 
Reliability and Maintainability Evaluation Team and Test Data Scoring 
Board charters to significantly expand their role in management of 
system development, manufacturing, configuration changes, and testing. 
Since 2007, as a result of the Air Force's increased attention to 
reliability testing and investments in reliability initiatives, the 
program has identified many of the root causes for reliability 
failures. While there is no single cause behind JASSM flight test 
failures, common failures occurred across JASSM subsystems including 
navigation, flight control, and propulsion. 

Figure 4: JASSM Subsystems Involved in Flight Test Failures: 

[Refer to PDF for image: pie-chart] 

Payload: 21.0%; 
Navigation: 16.1%; 
Flight Control: 14.0%; 
Propulsion: 14.0%; 
Other: 9.8%; 
Unverified: 6.3%. 
Missile: 4.9%. 

Source: GAO analysis of DOD data. 

Notes: Other includes airplane, power, and missile control unit. 
Unverified is due to ongoing investigations. 

[End of figure] 

Most of the corrective actions to address the causes of the flight 
test failures affect missile hardware and many have been implemented 
in the current configuration for new production missiles. However, 
some flight test failure investigations are still ongoing. Those 
investigations are often difficult because of the lack of physical 
evidence after the flight test missile detonates on the White Sands 
missile range. As a result, identifying the root causes for failures 
were based on very extensive component testing at supplier facilities. 
Additionally, the root causes for several test failures were never 
conclusively determined as the failures may have resulted from 
aircraft or user malfunctions. Efforts to address significant 
reliability problems found during testing have contributed greatly to 
JASSM's cost growth and schedule delays since the beginning of 
development. The Air Force has estimated that it may ultimately spend 
about $400 million through fiscal year 2025 on its reliability 
improvement initiatives. 

The Air Force has also increased lot acceptance testing of the fuses 
and implemented high-speed photography and screening improvements. In 
addition to forensic evaluation of the missile impact area, the Air 
Force also employs visual inspections and a built-in-test.[Footnote 6] 
The Air Force has also taken a variety of actions, in addition to 
flight testing, to improve JASSM's reliability, including the 
following initiatives. 

* Increased Oversight: The Air Force and Lockheed Martin have begun a 
process verification program to ensure suppliers follow prime 
contractor specifications. According to Air Force officials, the 
process verification program has allowed the Air Force to avoid 
unforeseen costs as some missile parts have become obsolete. Further, 
officials stated that it allows the JASSM program to catch problems 
earlier and plan on how to replace parts sooner. According to a 
program official, one process verification program team caught an 
obsolescence issue with a global positioning satellite receiver and 
was able to minimize the cost and production effect on the program. 

* Missile Redesign: Program officials state that while wholesale 
missile redesign is not considered a cost-effective option, they are 
considering design changes and improvements at the component level. 

* Increased Personnel: The program office has increased the number of 
government personnel supporting the process verification program and 
corrective action efforts. During Lot 1, the program had two staff 
members with production and manufacturing engineering expertise--by 
Lot 7, 22 staff members had such expertise. 

* Improved Quality Assurance: In August 2006, the Air Force and 
Lockheed Martin implemented a quality assurance program. Lockheed 
Martin has implemented tests and improvement programs to increase user 
confidence in reliability and control costs. For example, Lockheed 
Martin officials stated that, to improve reliability, they have begun 
using a test that exposes electrical connections to higher voltages 
than they usually encounter during flight to make sure the wiring can 
handle a surge. Additionally, Lockheed Martin has increased the sample 
sizes of certain components they inspect and test. 

Recent JASSM Testing Has Shown Improved Results: 

Recent tests of JASSM have demonstrated increased reliability. Since 
the Air Force's reliability initiatives began in fiscal year 2007, the 
JASSM program has conducted 48 missile flight tests and 39 have been 
successful (2 were characterized as "no-test") for a reliability rate 
of 85 percent. 

Figure 5: JASSM Baseline Missile Test Results: 

[Refer to PDF for image: stacked vertical bar graph] 

Number of tests: 

Fiscal year: 2001; 
Successful: 4; 
Failures: 2. 

Fiscal year: 2002; 
Successful: 6; 
Failures: 1. 

Fiscal year: 2003; 
Successful: 7; 
Failures: 7. 

Fiscal year: 2004; 
Successful: 3; 
Failures: 4. 

Fiscal year: 2005; 
Successful: 8; 
Failures: 3. 

Fiscal year: 2006; 
Successful: 6; 
Failures: 3. 

Fiscal year: 2007; 
Successful: 0; 
Failures: 5. 

Fiscal year: 2008; 
Successful: 17; 
Failures: 2. 

Fiscal year: 2009; 
Successful: 17; 
Failures: 5. 

Fiscal year: 2010; 
Successful: 5v
Failures: 0. 

Source: GAO analysis of DOD data. 

[End of figure] 

The current focus of JASSM baseline testing has been on improving the 
reliability of the missile. In the most recent tests of the JASSM 
baseline missiles produced in 2008, 15 of 16 flight tests were 
considered successful. In the one failure, the warhead did not 
detonate and the program is awaiting fuse recovery to make a 
determination of the root cause. The JASSM-ER is in developmental 
testing. Developmental testing of JASSM-ER is primarily addressing the 
differences of JASSM-ER from the baseline system (i.e., larger engine 
and fuel tanks) and will verify integration on the B-1 aircraft. All 
seven test flights of JASSM-ER have been successful.[Footnote 7] The 
program office is planning three additional integrated JASSM-ER tests 
to be flown before a production decision is made. 

Uncertain If Improved Missile Reliability Will Result in Improved 
JASSM Operational Effectiveness: 

In 2007, after USD/ATL's decision to enhance JASSM reliability, the 
Air Force and Lockheed Martin agreed to focus on the inherent 
reliability of the missile and not take into account user error or 
platform malfunctions (i.e., carrier aircraft, aircrew 
instrumentation, range safety, etc.). Whereas operational testing is 
designed to evaluate the ability of JASSM to execute a mission, 
reliability testing is more narrowly focused on evaluating the 
missile's performance during the mission. While mission failures were 
counted against the program during initial testing, more recent 
mission test failures have been declared "no tests." For example, in 
early testing when a B-52 software issue resulted in an aborted 
mission and it was scored a test failure, this event would have been 
declared a no test under current missile reliability definitions. 

While recent flight testing of the baseline missile has shown improved 
missile reliability, the Air Force has not yet evaluated the 
operational effectiveness and suitability of the baseline JASSM with 
all corrective actions implemented.[Footnote 8] The JASSM program 
assesses operational effectiveness through operational testing, follow-
on testing, and the weapon system evaluation program (routine tests of 
inventory assets). These flight test scenarios assess operational 
effectiveness in realistic combat scenarios against targets by 
determining reliability, evaluating capability and limitations by 
identifying deficiencies, and recommending corrective actions. In 
operational testing, the JASSM baseline program flight tested 38 
missiles from June 2002 through May 2007 resulting in 19 failures and 
two no tests. While these tests identified issues with missile 
reliability, they also identified issues related to the B-52 aircraft, 
aircraft software, and fuse issues which negatively affected the 
operational effectiveness of the missile. This led to a 9-month 
suspension of testing in 2004 to address these issues. The improved 
JASSM baseline missile's suitability was assessed by Air Force testers 
in 2008 and it was characterized as suitable and likely to meet 
reliability goals; however, operational testing of the effectiveness 
of the improved missile has not yet been scheduled. 

Several Areas of Potential Cost Risk Could Further Increase JASSM 
Program Costs: 

Current projections of JASSM costs have increased by over 7 percent 
since the Nunn-McCurdy certification in 2008. When taking into 
consideration the pre-2008 cost growth, which included the cost of 
adding the JASSM-ER variant, JASSM has grown from a $2.2 billion to a 
$7.1 billion program. In addition, while it has initiated several cost 
control measures, the Air Force appears to have limited options to 
reduce JASSM costs. Moreover, several areas of risk could add to those 
costs. First, the Air Force has not been able to provide enough annual 
funding to support the annual procurement levels used as the basis for 
its 2008 program cost estimate. That has led to a less efficient 
production process and a longer production period (most recently 
extended 5 years to 2025). Second, until the Air Force evaluates the 
effectiveness of the inventory JASSM baseline missiles with corrective 
actions for previously identified hardware and software issues, 
[Footnote 9] their viability and military utility is in question. If 
inventory missiles are found not to have utility, they may need to be 
replaced. If retrofitted missiles are found to be effective, the Air 
Force may still have to find additional funding to complete the 
retrofit process. Third, the Air Force plans to conduct many more 
flight tests to improve JASSM reliability from 85 to 90 percent. 
Finally, in comparing the capabilities and cost of JASSM to several 
domestic and international missile systems in 2008, the Air Force 
assumed that JASSM would cost about $1 million per unit, which is 
about 40 percent less than currently expected. 

JASSM Costs Are Much Higher Than Originally Anticipated: 

Compared to original program estimates, JASSM's currently projected 
costs are much higher because of (1) higher than anticipated 
production costs, (2) longer production period, (3) the addition of 
the JASSM-ER variant, and (4) reliability improvement efforts. Through 
fiscal year 2010, about 75 percent of the planned JASSM quantities 
have yet to be procured and, as a result, most of the program costs 
have yet to be incurred. 

Figure 6: Comparison of JASSM's Original and 2009 Total Acquisition 
Funding Profiles: 

[Refer to PDF for image: multiple line graph] 

Fiscal year: 1996; 
December 1988 selected acquisition report: $34.4 million; 
December 2009 selected acquisition report: $34.4 million. 

Fiscal year: 2000; 
December 1988 selected acquisition report: $200.7 million; 
December 2009 selected acquisition report: $188.2 million. 

Fiscal year: 2004; 
December 1988 selected acquisition report: $166.9 million; 
December 2009 selected acquisition report: $164 million. 

Fiscal year: 2008; 
December 1988 selected acquisition report: $192.3 million; 
December 2009 selected acquisition report: $173.4 million. 

Fiscal year: 2012; 
December 1988 selected acquisition report: $0; 
December 2009 selected acquisition report: $231.2 million. 

Fiscal year: 2016; 
December 2009 selected acquisition report: $380.8 million. 

Fiscal year: 2020; 
December 2009 selected acquisition report: $335.2 million. 

Fiscal year: 2024; 
December 2009 selected acquisition report: $326.5 million. 

Fiscal year: 2028; 
December 2009 selected acquisition report: $0. 

Source: GAO analysis of DOD data. 

Notes: Fiscal year 2010 dollars. The $7.1 billion includes 2,500 JASSM-
ER missiles. 

[End of figure] 

Following the critical Nunn-McCurdy unit cost breach, the Air Force 
halted production of the missiles until USD/ATL certified that the 
program should continue. USD/ATL found no lower cost alternatives and 
certified the program in 2008, despite the missile's higher than 
projected production costs. As a part of our review, we examined the 
cost estimates used by OSD to certify the program following the 
critical Nunn-McCurdy unit cost breach. This estimate used the actual 
costs of the missile since JASSM was well into the production phase at 
the time. Overall, the Air Force's cost estimate substantially met our 
best practice standards in our Cost Guide. For a more in-depth 
discussion of our review of this JASSM cost estimate, see appendix III. 

Since the Nunn-McCurdy certification in 2008, the growth in JASSM's 
projected program cost has moderated, rising about $500 million (from 
$6.6 billion to $7.1 billion) through 2025. Reliability enhancements 
to the JASSM missile instituted in 2007 and additional reliability 
testing have added the majority of the increase in program costs. 
These enhancements were implemented to meet USD/ATL's 90 percent 
reliability goal which was set during the Nunn-McCurdy certification. 
Also, the Air Force decided to lengthen the program's procurement 
schedule by another 5 years, buying the same number of missiles over a 
longer time period. That reduces the efficiency of the production 
processes and adds inflation to the cost estimate. Currently, on a per 
unit basis, the average procurement unit cost of a JASSM missile is 
projected to be about $1.2 million. JASSM-ER is expected to cost about 
$200,000 more than the average, about $1.4 million per unit.[Footnote 
10] 

Table 1: Changes Since 2008 in JASSM Estimated Cost, Schedule, and 
Quantities through 2025: 

Expected quantities: Development quantities; 
May 2008 (Nunn-McCurdy certification): 106; 
December 2009 (selected acquisition report): 118; 
Percentage Change (2008 to 2009): 11.3%. 

Expected quantities: Procurement quantities; 
May 2008 (Nunn-McCurdy certification): 4,900; 
December 2009 (selected acquisition report): 4,900; 
Percentage Change (2008 to 2009): 0.0. 

Expected quantities: Total quantities; 
May 2008 (Nunn-McCurdy certification): 5,006; 
December 2009 (selected acquisition report): 5,018; 
Percentage Change (2008 to 2009): 0.2%. 

Cost estimates (dollars in millions): Development; 
May 2008 (Nunn-McCurdy certification): $1,383.5; 
December 2009 (selected acquisition report): $1,447.8; 
Percentage Change (2008 to 2009): 4.6%. 

Cost estimates (dollars in millions): Procurement; 
May 2008 (Nunn-McCurdy certification): $5,257.9; 
December 2009 (selected acquisition report): $5,681.6; 
Percentage Change (2008 to 2009): 8.1%. 

Cost estimates (dollars in millions): Total program acquisition; 
May 2008 (Nunn-McCurdy certification): $6,641.4; 
December 2009 (selected acquisition report): $7,129.4; 
Percentage Change (2008 to 2009): 7.3%. 

Unit cost estimates (dollars in thousands): Program acquisition; 
May 2008 (Nunn-McCurdy certification): $1,327; 
December 2009 (selected acquisition report): $1,421; 
Percentage Change (2008 to 2009): 7.1%. 

Unit cost estimates (dollars in thousands): Average procurement; 
May 2008 (Nunn-McCurdy certification): $1,073; 
December 2009 (selected acquisition report): $1,160; 
Percentage Change (2008 to 2009): 8.1%. 

Estimated delivery dates: Production length (years); 
May 2008 (Nunn-McCurdy certification): 20; 
December 2009 (selected acquisition report): 25; 
Percentage Change (2008 to 2009): 25.0%. 

Source: GAO analysis of DOD data. 

Note: Fiscal year 2010 dollars. 

[End of table] 

Since 2008, the Air Force has added several measures to control costs 
in the JASSM program, but the effect of these measures is not yet 
clear. Examples of these measures include the following. 

* Contract Incentives: The Air Force has begun using fixed-price 
incentive (firm target) contracts for each lot to produce the missiles 
for less than projected.[Footnote 11] 

* Greater Insight into Actual Costs: Air Force officials have 
increased insight into Lockheed Martin's actual costs, which may make 
them more informed when negotiating new contracts. Program officials 
stated that, for example, they now know how many engineers are needed 
to perform a certain task and the number of hours it takes to assemble 
a missile. The Air Force can directly verify the costs charged by 
subcontractors. 

* Increased Authority over Design: In recent contract negotiations, 
the Air Force gained approval authority over certain design changes 
that may affect current and future lots, including those that may 
increase cost, require retrofit, or affect safety. Previously, 
Lockheed Martin had full authority over most design changes. 

While the effectiveness of the cost control measures is not yet known, 
the Air Force appears to have limited options to actually reduce those 
costs. For example, annual production rates are expected to remain 
well below the levels projected at the start of the program. The 2008 
Air Force cost estimate was based on an annual production rate of 280 
missiles per year. However, that cost estimate may now be understated 
because the program has not produced that many missiles in a single 
year since 2005. For example, the Air Force's procurement quantities 
for production Lot 7 and Lot 8 were 111 and 80 units, respectively, 
well below the economic order quantity of 175 missiles per year. 
Program officials stated that annual quantities below the economic 
order quantity will result in an increasingly inefficient production 
process and some key suppliers may shift from continuous to limited 
production. Further, Lockheed Martin officials stated that low 
production rates could cause skilled labor to look elsewhere for work 
and JASSM reliability could be adversely affected. The contractor has 
been able to maintain some level of production efficiency because of 
foreign military sales that make up for the reduced Air Force 
procurements. However, lower than projected annual procurement levels 
will increase production costs. A further challenge is the fact that 
JASSM's design is mostly complete and there may be few opportunities 
to reduce production costs through redesign. As a result, average 
JASSM unit costs may remain in excess of $1.2 million indefinitely. 

Effectiveness of Retrofitting Corrective Actions into JASSM Inventory 
Is Uncertain: 

The Air Force has plans to address the low reliability of missiles in 
its inventory by retrofitting some of its 942 missiles with hardware 
and software corrective actions. Program officials state the retrofit 
costs will be shared between Lockheed Martin and the Air Force, but 
the total cost to retrofit the missiles in inventory has not been 
calculated. However, previous efforts to retrofit JASSM missiles have 
proven to be problematic. An example of challenges associated with 
retrofitting missiles is adding telemetry instrumentation kits after 
the missiles have been produced and are in the inventory. Those kits 
are added to all missiles to be flight tested.[Footnote 12] This 
requires opening up the missile to insert telemetry after the stealth 
coating has been applied and increasing the number of electrical 
connections as compared to a production missile.[Footnote 13] Air 
Force officials stated the kit could add some reliability concerns 
when it is added to test missiles because the missiles were not 
designed to be opened after they were completed. Air Force officials 
also stated that workers have to reroute wires and remove the engine 
so that the self-destruct mechanism can be installed and all of this 
rework inside the missile has the potential to lead to more errors and 
cause additional reliability issues. 

The impact of retrofitting missiles has become evident in the weapon 
system evaluation program, which is operationally representative 
flight testing run by users of the system and focuses on the 
performance of missiles in the inventory. JASSM's performance in this 
evaluation program has not been good, with 7 failures in 12 tests from 
2006 through 2007, and with at least some of the failures attributable 
to the retrofit process. The addition of telemetry kits has also 
contributed to 3 no tests during other JASSM flight testing. The Air 
Force has not yet flight tested any of the JASSM inventory missiles 
that have been retrofitted with all of the corrective actions to 
address reliability issues. This type of test would be important in 
determining the viability of the current inventory of JASSM missiles 
and would be a key input in the Air Force deciding whether or not to 
retrofit the entire inventory of missiles. 

Additional Flight Testing to Further Improve Reliability Will Be 
Costly: 

The Air Force plans more flight tests in the next few years of new 
production missiles to meet missile reliability goals. For the JASSM 
baseline missile to meet its reliability requirement, the Air Force is 
planning to conduct up to 48 additional flight tests, at a cost of 
about $120 million. In addition, most reliability issues with the 
baseline variant will directly affect the progress of the JASSM-ER 
variant as the missiles are at least 70 percent common in hardware and 
95 percent common in software. Anything learned during these flight 
tests about the baseline applies to JASSM-ER. According to the Air 
Force, as many as 20 additional flight tests may be needed to fully 
demonstrate JASSM-ER's reliability goal of 85 percent.[Footnote 14] 

Table 2: Flight Test Cost to Increasing Reliability: 

Variant of JASSM: Baseline; 
Additional flight tests required to reach reliability requirement: 
48[A]; 
Current cost per flight test: $2.5 million; 
Additional flight test costs to reach reliability requirement: $120 
million. 

Variant of JASSM: Extended range; 
Additional flight tests required to reach reliability requirement: 20; 
Current cost per flight test: $3.5 million; 
Additional flight test costs to reach reliability requirement: $70 
million. 

Source: GAO analysis of DOD data. 

[A] The JASSM baseline program can achieve its missile reliability 
goal with either (1) 21 successful reliability test shots, or (2) 3 
more sets of reliability tests with 16 test shots each--with no more 
than two failures in 1 set of reliability tests and not more than 1 
failure in each of the other 2 sets of reliability tests. 

[End of table] 

The $190 million cost to achieve the final percentages of missile 
reliability reflects the fact that problems or weaknesses become 
harder to find and correct as the more obvious issues are corrected. 
Program officials are considering alternative means to meet user needs 
for a more reliable missile while reducing the cost of JASSM flight 
testing. 

Previous Analysis of Alternatives Assumed Much Lower Costs of JASSM 
Missile: 

As part of the Nunn-McCurdy certification process in fiscal years 2007 
through 2008, DOD assessed whether there were readily available 
alternatives that provided as much or more capability as JASSM at 
lower cost. DOD assessed programs ranging from direct attack munitions 
to intercontinental range missiles. For the JASSM baseline missile, 
all of DOD's existing programs were found to be less effective in 
terms of lethality, survivability, or capacity. The Navy's Tomahawk 
missile was the closest alternative to meeting JASSM's capability but 
it is not as lethal as JASSM. Also, the Tomahawk is launched from 
ships and not from aircraft, as the Air Force plans to use the 
capability. 

DOD also evaluated new or modified programs as possible alternatives 
to JASSM and JASSM-ER. The Air Force evaluated 12 domestic and 
international missile systems with projected unit production costs 
ranging from $600,000 to $2.8 million. JASSM-ER, estimated at the time 
of this evaluation to cost $1 million per unit, was more expensive 
than 5 alternative systems under consideration. In terms of 
performance, some alternatives were more capable than JASSM and some 
were not. All of the alternative systems were expected to require some 
up-front investment. Based on this analysis, no other alternative was 
found to provide greater or equal military capability at less cost 
than JASSM-ER. 

Later in the Nunn-McCurdy process, however, OSD cost analysts found 
that the costs of JASSM-ER would likely be at least $1.4 million per 
missile. That continues to be the projected unit cost of JASSM-ER and, 
as we discussed earlier in this report, there are cost risks that may 
drive that unit cost higher. Despite the higher production unit costs 
for JASSM-ER, the Air Force has not revisited the results of its 
assessment of alternatives. In light of the current cost projections, 
which are 40 percent higher than assumed in the previous assessment, 
JASSM-ER would be equal to the cost of an additional alternative. 
Further, the unit cost differential between JASSM-ER and the lower- 
priced alternatives may now be large enough to make those alternatives 
more competitive in terms of cost or capabilities. 

Conclusions: 

DOD's 25-year history to acquire and field an affordable air-to- 
ground cruise missile has been a difficult one. After abandoning the 
expensive TSSAM program, the Air Force conceived the JASSM program 
using an acquisition strategy that minimized government oversight. 
After restructuring the program in 2008 and after considerable effort 
to improve reliability, the JASSM program as it exists today is much 
different than originally envisioned. A $2.2 billion, 11-year program 
to produce 2,400 missiles has become a $7.1 billion, 28-year program 
to produce 4,900 missiles. From a technical and capability standpoint, 
the program offers more now than the baseline missile did before 2008. 
Yet, the effectiveness of the new missiles remains to be demonstrated 
in operational testing, and low production rates, retrofit costs, and 
additional reliability testing could drive program costs higher. 

At this point, about 70 percent of the projected JASSM costs have not 
yet been incurred. In November 2011, DOD will decide whether to 
approve the Air Force's request to start low-rate initial production 
of the JASSM-ER variant. Low-rate initial production is normally the 
last major milestone decision for an acquisition program. With the 
JASSM program now expected to extend through 2025 and about $5 billion 
yet to be spent, a reevaluation of its cost-effectiveness is warranted 
before such a commitment is made. This is particularly true given the 
Secretary of Defense's recent initiative to improve the cost-
efficiency of defense acquisition programs. At this juncture, the 
JASSM program would seem to be an excellent opportunity for DOD and 
Air Force leadership to take a hard look at the cost-effectiveness and 
efficiency of this important but costly defense program. 

Recommendation for Executive Action: 

We recommend that the Secretary of Defense defer the production 
decision for JASSM-ER until (1) the program's likely costs and 
affordability are reassessed to take into account the feasibility and 
cost of retrofitting JASSM baseline missiles or replacing them, the 
cost of additional reliability testing against the likely improvement, 
and the effect of sustained low production rates; and (2) the results 
of the previous analysis of alternatives are reassessed in light of 
the likely costs of the JASSM program. 

Agency Comments and Our Evaluation: 

In its comments on our draft report, DOD partially concurred with our 
recommendation. DOD stated that JASSM-ER is on track for a Milestone C 
low-rate initial production decision in November 2010. DOD also agreed 
that the rate of JASSM production has not been optimum and that it 
plans to address efficient production rates as part of the JASSM-ER 
Milestone C decision. DOD also stated that (1) there are no additional 
plans (nor is there a need) to retrofit fielded JASSMs above what has 
already been accomplished or is under way; (2) it has revisited 
various alternatives and reaffirms the continued validity of its 2008 
conclusion that none of the alternative concepts provide comparable 
operational utility at or near a similar cost or schedule to JASSM; 
and (3) in the absence of viable alternatives, delaying the program 
further will increase costs and further postpone delivering a vital 
capability to the warfighter. DOD's response is reprinted in appendix 
II. 

In concluding that retrofits to the inventory missiles may not be 
necessary, DOD does not address the viability of the current inventory 
of JASSM baseline missiles or the need to replace some or all of them. 
Until the Air Force evaluates the effectiveness of the inventory of 
JASSM baseline missiles with corrective actions for previously 
identified hardware and software issues, their viability and military 
utility will still be in question. In addition, DOD states that the 
Air Force has revisited its earlier assessment of alternatives to 
JASSM and again found that there are none with comparable utility, 
cost, or schedule. This is new information and DOD did not provide 
details for us to assess, including whether the Air Force factored in 
the higher current projections of JASSM costs. Finally, DOD did not 
address the part of our recommendation dealing with the cost of 
additional reliability testing against the likely improvement. 

To the extent DOD has made decisions on retrofits and reconsideration 
of alternatives, these are positive signs, as is its agreement to 
address the efficiency of production rates. At this point, it is not 
clear whether the reliability of the existing baseline inventory 
missiles is acceptable or whether additional reliability testing is 
warranted. These determinations are necessary to establish the full 
value and cost of the JASSM program. 

Beyond these steps, it is incumbent upon the department to reexamine 
JASSM before making the production decision to ensure that the program 
is structured as efficiently as possible and is still a good 
investment given the other demands DOD faces. DOD's agreement to 
address the efficiency of JASSM production rates is a positive step. 
This is particularly important given the Secretary's current 
efficiency and affordability initiative. DOD needs to ensure that it 
has the information available to fully assess the JASSM investment 
before making the production decision. If DOD needs more time, then we 
believe the decision could be delayed. 

We also received several technical comments from DOD and the Air Force 
and have made other changes to our report. 

We are sending copies of this report to the Secretary of Defense and 
interested congressional committees. In addition, this report will be 
made available at no charge on the GAO Web site at [hyperlink, 
http://www.gao.gov]. If you or your staff have any questions about 
this report or need additional information, please contact me at (202) 
512-4841 or sullivanm@gao.gov. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. GAO staff who made major contributions to this 
report are listed in appendix IV. 

Signed by: 

Michael J. Sullivan, Director: 
Acquisition and Sourcing Management: 

List of Congressional Committees: 

The Honorable Joseph Lieberman: 
Chairman: 
The Honorable John Thune: 
Ranking Member: 
Subcommittee on Airland: 
Committee on Armed Services: 
United States Senate: 

The Honorable Daniel K. Inouye: 
Chairman: 
The Honorable Thad Cochran: 
Ranking Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
United States Senate: 

The Honorable Adam Smith: 
Chairman: 
The Honorable Roscoe Bartlett: 
Ranking Member: 
Subcommittee on Air and Land Forces: 
Committee on Armed Services: 
House of Representatives: 

The Honorable Norm Dicks: 
Chairman: 
The Honorable C.W. Bill Young: 
Ranking Member: 
Subcommittee on Defense: 
Committee on Appropriations: 
House of Representatives: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

To determine Joint Air-to-Surface Standoff Missile's (JASSM) current 
production unit costs and the extent they have grown, we analyzed 
JASSM's contracts, budgets, and compared the program's selected 
acquisition reports. We analyzed Nunn-McCurdy documentation and 
certification criteria as well as Air Force and Lockheed Martin data 
to determine the causes for the cost growth and critical breaches. We 
interviewed officials with the JASSM joint program office; Lockheed 
Martin; the Office of Secretary of Defense Cost Assessment and Program 
Evaluation; and a former program official. 

To determine the extent to which Department of Defense's (DOD) cost 
estimating policies and guidance support the development of high- 
quality cost estimates, we analyzed the cost estimating practices of 
the Cost Analysis Improvement Group (CAIG), now known as the Cost 
Analysis and Process Evaluation (CAPE), in the development of life- 
cycle cost estimates for the Air Force's Joint Air-to-Surface Standoff 
Missile Program (baseline and JASSM-ER variants), against the 12 best 
practices of a high-quality cost estimate as defined in our Cost 
Estimating and Assessment Guide.[Footnote 15] 

We assessed each cost estimate, used in support of the critical Nunn- 
McCurdy unit cost breach, against these 12 key practices associated 
with four characteristics of a reliable estimate. As defined in the 
guide, these four characteristics are comprehensive, well-documented, 
accurate, and credible, and the practices address, for example, the 
methodologies, assumptions, and source data used. We also interviewed 
program officials responsible for the cost estimate about the 
estimate's derivation. We then characterized the extent to which each 
of the four characteristics was met; that is, we rated each 
characteristic as being either Not Met, Minimally Met, Partially Met, 
Substantially Met, or Fully Met. To do so, we scored each of the 12 
individual key practices associated with the four characteristics on a 
scale of 1-5 (Not Met = 1, Minimally Met = 2, Partially Met = 3, 
Substantially Met = 4, and Fully Met = 5), and then averaged the 
individual practice scores associated with a given characteristic to 
determine the score for that characteristic. 

To determine the results of the most recent tests and if corrective 
actions have been implemented for previous test failures, we analyzed 
JASSM flight test results and failure review board findings to 
determine scoring criteria and results to determine what corrective 
actions were implemented. We determined whether recent flight test 
results are representative of the entire fleet by comparing and 
evaluating the lot-by-lot missile configuration changes and retrofit 
activities. We interviewed officials with the JASSM joint program 
office; Lockheed Martin; Office of Under Secretary of Defense for 
Acquisition, Technology, and Logistics; Director, Operational Test and 
Evaluation; Air Combat Command; Secretary of the Air Force for 
Acquisition; Office of Secretary of Defense Cost Assessment and 
Program Evaluation; Joint Staff; Air Force Directorate of Test and 
Evaluation; and a former Air Force official who was an early JASSM 
program manager to better understand the program's objectives and 
original acquisition strategy. We discussed recent DOD reliability 
initiatives with Office of the Director, Operational Test and 
Evaluation officials. 

To determine what the Air Force has done to control and reduce 
production costs while improving reliability, we examined JASSM's 
contracts to see what provisions have been added as well as Air Force 
and Lockheed Martin data. We interviewed officials with the JASSM 
joint program office; Lockheed Martin; and Office of Secretary of 
Defense (OSD) test organizations to determine if testing reflects the 
current effectiveness of the missile. We reviewed our prior work on 
best practices for a knowledge-based approach for acquisition programs 
in determining if the Air Force's approach to beginning the JASSM-ER 
program meets best practices. We compared requirements and other 
documents to see if the JASSM-ER missile reflects lessons learned from 
the baseline variant as well as increased knowledge and oversight from 
the government. We compared the baseline design with JASSM-ER to 
determine commonality. We interviewed officials with the JASSM joint 
program office; Lockheed Martin; Office of Under Secretary of Defense 
for Acquisition, Technology, and Logistics; Office of Secretary of 
Defense Cost Assessment and Program Evaluation; Director of 
Operational Test and Evaluation; Air Combat Command; Secretary of the 
Air Force for Acquisition; Joint Staff; and a former program official 
to the determine acquisition planning leading up to JASSM-ER's 
production decision and what initiatives have been taken to control 
costs. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
Acquisition, Technology And Logistics: 
3000 Defense Pentagon: 
Washington, DC 20301-3000: 

September 30, 2010: 
	
Mr. Michael J. Sullivan: 
Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20548: 

Dear Mr. Sullivan: 

This is the Department of Defense (DoD) response to the GAO draft 
report, GAO-10-573, "Defense Acquisitions: DoD Needs to Reassess Joint 
Cruise Missile Costs Before Starting New Production Phase," dated 
August 25, 2010 (GAO Code 120868). 

The DoD partially concurs with the recommendation. The rationale for 
our position is enclosed. 

We appreciate the opportunity to comment on the draft report. My point 
of contact for this effort is Mr. Ron Woods, Ronald.Woods@osd.mil, 703-
697-8183. 

Sincerely, 

Signed by: 

David G. Ahern: 
Director: 
Portfolio Systems Acquisition: 

Enclosure: As stated: 

[End of letter] 

GAO Draft Report Dated August 25, 2010: 
GAO-10-573 (GAO 120868): 

"Defense Acquisitions: DoD Needs to Reassess Joint Cruise Missile 
Costs Before Starting New Production Phase" 

Department Of Defense Comments To The GAO Recommendation: 

Recommendation 1: We recommend that the Secretary of Defense defer the 
production decision for JASSM-ER until (1) the program's likely costs 
and affordability are reassessed to take into account the feasibility 
and cost of retrofitting JASSM baseline missiles or replacing them, 
the cost of additional reliability testing against the likely 
improvement, and the effect of sustained low production rates; and (2) 
the results of the previous analysis of alternatives are reassessed in 
light of the likely costs of the JASSM program. 

DOD Response: Partial-concur. Having passed all qualification testing 
and production readiness reviews, JASSM-ER is on track for a Milestone 
C Low Rate Initial Production decision in November 2010. JASSM-ER 
Flight test results have met expectations. 

The Department agrees with GAO's assessment that the rate of JASSM 
production has not been optimum. Lower than optimum production rates 
in Lots 5 through 8 were driven by the need to restructure the program 
to address reliability concerns resulting from Weapon System 
Evaluation Program failures in 2006-2007 and Lot 5 test results. The 
Department accepted the near-term cost impacts of the production 
delays to lay a solid foundation for production of a more reliable 
baseline JASSM and future JASSMER low-rate production. Baseline JASSM 
has been in production since December 2001. JASSM-ER has demonstrated 
readiness for a production decision. The Department plans to address 
efficient production rates as part of the JASSM-ER Milestone C 
decision. 

Lot 5 and 6 missiles have successfully been retrofitted with new 
fuzes, cabling and other corrective actions to increase their 
reliability. Below a minimum acceptable level, the prime contractor 
continues to bear responsibility for determining, validating and 
implementing all fixes to return the missile to a specified 
reliability level. The Air Force has also accomplished retrofits and 
additional screening on previous blocks of missiles (Lot 1 and part of 
Lot 2) since 2007. There are no additional plans (nor need) to 
retrofit currently fielded JASSMs above what has already been 
accomplished or is under way. 

The Air Force issued a Request for Information (RFI) on alternate 
cruise missile concepts and completed an associated analysis in 2007-
2008. The Air Force recently reviewed this analysis and affirmed the 
continued validity of the 2008 conclusion that none of the alternative 
concepts provide comparable operational utility at or near a similar 
cost or schedule. In the absence of viable alternatives (i.e., no 
other concepts offer similar capability at or near same cost), 
delaying the program further will increase costs and further postpone 
delivering a vital stand-off capability to the warfighter. 

[End of section] 

Appendix III: JASSM Baseline and JASSM-ER Cost Estimates Met Most Best 
Practices, but the Risk Analyses Did Not Consider Reliability or 
Extending the Production Schedule: 

After reviewing documentation submitted by the JASSM program office, 
conducting interviews, and reviewing relevant sources, we determined 
the CAIG's life-cycle cost estimate's totaling $7.1 billion for both 
programs--the JASSM baseline cost estimate was $3.4 million while the 
JASSM-ER variant cost estimate of $3.7 million--Fully Met one and 
Substantially Met the other three characteristics of a reliable cost 
estimate, as shown in Table 3 below. We assessed 12 measures 
consistently applied by cost estimating organizations throughout the 
federal government and industry and considered best practices for the 
development of reliable cost estimates. We analyzed the cost 
estimating practices used by CAIG in developing the life-cycle cost 
estimates for both programs against these 12 best practices and the 
findings are documented in table 3 below. 

Table 3: Extent to Which the Cost Estimating Practices for JASSM 
Baseline and JASSM-ER Reflect GAO Best Practices: 

Best practice: Comprehensive; 
Explanation: The cost estimates should include both government and 
contractor costs of the program over its full life-cycle, from 
inception of the program through design, development, deployment, and 
operation and maintenance to retirement of the program. They should 
also provide a level of detail appropriate to ensure that cost 
elements are neither omitted nor double-counted, and they should 
document all cost-influencing ground rules and assumptions; 
Satisfied?: Substantially Met. 

Best practice: Well documented; 
Explanation: The documentation should addresses the purpose of the 
estimate, the program background and system description, its schedule, 
the scope of the estimate, the ground rules and assumptions, all data 
sources, estimating methodology and rationale, the results of the risk 
analysis, and a conclusion about whether the cost estimate is 
reasonable. Therefore, a good cost estimate--while taking the form of 
a single number--is supported by detailed documentation that describes 
how it was derived and how the expected funding will be spent in order 
to achieve a given objective. Finally, the cost estimate should be 
reviewed and accepted by management to ensure that there is a high 
level of confidence in the estimating process and the estimate itself; 
Satisfied?: Fully Met. 

Best practice: Accurate; 
Explanation: The cost estimate should provide for results that are 
unbiased and should not be overly conservative or optimistic. Among 
other things, the estimate should be grounded in a historical record 
of cost estimating and actual experiences on comparable programs. 
Estimates are accurate when they are based on an assessment of most 
likely costs, adjusted properly for inflation, updated regularly, and 
contain few, if any, minor mistakes; 
Satisfied?: Substantially Met. 

Best practice: Credible; 
Explanation: The cost estimates should discuss any limitations of the 
analysis because of uncertainty or biases surrounding data or 
assumptions. Major assumptions should be varied, and other outcomes 
recomputed to determine how sensitive they are to changes in the 
assumptions. Risk and uncertainty analysis should be performed to 
determine the level of risk associated with the estimate. Further, the 
estimate's results should be crosschecked, and an independent cost 
estimate conducted by a group outside the acquiring organization 
should be developed to determine whether other estimating results 
produce similar results; 
Satisfied?: Substantially Met. 

Source: GAO analysis of DOD data. 

[End of table] 

The following explains the definitions we used in assessing CAIG's 
cost estimating methods used in support of the critical Nunn-McCurdy 
unit cost breach: 

* Fully Met--JASSM program office provided complete evidence that 
satisfies the entire criterion; 

* Substantially Met--JASSM program office provided evidence that 
satisfies a large portion of the criterion; 

* Partially Met--JASSM program office provided evidence that satisfies 
about half of the criterion; 

* Minimally Met--JASSM program office provided evidence that satisfies 
a small portion of the criterion; and: 

* Not Met--JASSM program office provided no evidence that satisfies 
any of the criterion. 

The sections that follow highlight the key findings of our assessment. 

JASSM Baseline and JASSM-ER Estimates Substantially Met 
Characteristics for Comprehensiveness: 

Though the cost estimates accounted for all possible costs and were 
structured in such a manner that would ensure that cost elements were 
omitted or double-counted, neither the JASSM baseline nor JASSM-ER had 
a Work Break Down Structure (WBS) dictionary that defined each 
element.[Footnote 16] In addition, the JASSM baseline variant provided 
no evidence that risks associated with the ground rules and 
assumptions were traced back to specific cost elements. 

* All applicable costs including government and contractor costs were 
included in the estimates--The cost estimates included sunk costs such 
as contractor program management, overhead, system design, and 
development and testing. In addition, the program office outlined the 
cost estimating methodology, basis of the costs, as well as 
development costs for JASSM-ER and other government costs. 

* The cost estimates' level of detail ensure that no costs were 
omitted or double-counted--The cost estimates are based on a product-
oriented WBS which is in line with best practices. For example, the 
cost estimate is broken down into various components such as the 
propulsion, payload, airframe, and guidance and control and also 
includes supporting cost elements such as systems engineering, program 
management, and system test and evaluation. As a result, all of the 
system products are visible at lower levels of WBS providing us with 
confidence that no costs were omitted or double-counted. WBS has been 
updated as the JASSM baseline and JASSM-ER programs have evolved; 
however, there is not an accompanying dictionary that defines each 
element and how it relates to others in the hierarchy. 

* Ground rules and assumptions were largely identified and documented--
The JASSM baseline cost estimate documentation included a list of risk 
model inputs based on WBS elements. Although WBS elements such as 
engineering support, subcontractor, and warranty were identified, 
there was no discussion of risk upon assumptions that drive costs such 
as product reliability, sustainability of subcontractors, or schedule 
variability. Like the JASSM baseline cost estimate documentation, the 
JASSM-ER cost estimate documentation also included a list of ground 
rules and assumptions; however, there was evidence that risk 
associated with the fuel tank assumption was traceable to a specific 
WBS element. In separate documentation, we were able to identify where 
the program office considered risks for the JASSM baseline estimate. 

JASSM Baseline and JASSM-ER Estimates Fully Met Characteristics for 
Being Well Documented: 

Both cost estimates were documented in enough detail that would allow 
an analyst unfamiliar with the program to recreate the estimate and 
get the same result. In addition, the briefing to management was 
detailed enough to show that the estimates were credible and well 
documented. 

* The cost estimate is fully documented--For the JASSM baseline and 
JASSM-ER, the cost estimate documentation included a report 
documentation page identifying the report date, title, contract 
number, report authors, and other information. The documentation also 
included a table of contents, introduction, purpose, and structure of 
the document as well as the scope of the estimate, a list of team 
members, the cost methodology, and a system description. The 
documentation discussed a risk and sensitivity analysis, costs broken 
out by WBS elements including data sources and estimating method and 
rationale, and provided evidence that the estimates were updated using 
actual costs. In a separate briefing, the program office outlined the 
cost estimating methodology, basis of the costs, as well as 
development costs for JASSM-ER and other government costs. The program 
office also provided a copy of the cost sufficiency review of the 
estimate, which included the estimate's purpose and scope, technical 
description and schedule, ground rules and assumptions, data sources 
and analysis, and methodology. For both programs, the estimate 
documentation and the cost analysis requirements document (CARD) 
addressed best practices and the 12 steps of a high-quality estimate. 
Contingency reserves and the associated level of confidence for the 
risk-adjusted cost estimate were also documented. Electronic versions 
of the cost estimates were also provided. 

* The estimate documentation describes how the estimate was derived-- 
The point estimate was developed primarily using actual costs, with a 
few cost elements estimated based on learning curves method.[Footnote 
17] Actual sunk costs for prior years were presented and remaining 
production lot costs were based on a labor staffing assessment and the 
latest contractor labor rates. Cross-checks were performed and no 
instances of double-counting were visible. A separate document was 
provided that showed in detail how the cost estimate was developed, 
what data were used to create the cost estimate, and how risks were 
quantified to determine a level of confidence in the cost estimate. 

* The estimates were reviewed and approved by management--The 
estimates were presented by OSD CAIG to the OSD overarching integrated 
product team for consideration as the new acquisition program 
baseline. In November 2009, the team provided a detailed overview of 
the JASSM program which addressed the major cost growth factors, such 
as the addition of the JASSM-ER variant, reliability enhancements, and 
the reduction in missile purchases. 

JASSM Baseline and JASSM-ER Variant Estimates Substantially Met 
Characteristics for Accuracy: 

Both cost estimates were unbiased and represented most likely costs. 
For example, the estimates were adjusted to reflect risks and the 
program office also included requirements in the new Lot 8 contract 
that would allow them to update the cost estimates with actual data. 

* The cost estimates were adjusted for inflation--The JASSM program 
office used the February 2009 version of the OSD inflation rates 
provided by the Secretary of the Air Force/Financial Management Cost 
and Economics. The estimates were developed and documented in base 
year 1995 dollars and inflated using the weighted rates applicable to 
the appropriations in the estimate. Base year 1995 is the program's 
designated base year. 

* The cost estimates included most likely costs--Per the Nunn-McCurdy 
certification process, the CAIG developed independent cost estimates 
for the JASSM baseline and JASSM-ER development and procurement costs 
as well as future-year resource requirements for the baseline and 
JASSM-ER variants. Operating and support costs as well as software 
costs were also included in the estimates. The JASSM baseline life- 
cycle cost estimate of $3.4 billion, which spans a period of time from 
2001 through 2015, was estimated at the 77 percent confidence level, 
while the JASSM-ER life-cycle cost estimate of $3.7 billion spans the 
period from 2011 through 2025 and was estimated at the 73 percent 
confidence level. 

* The cost estimates have not been updated to reflect current costs-- 
Though the JASSM baseline estimate dated April 2008 was updated to 
reflect new program changes, the CARD has not been updated since May 
2003. Examples of JASSM baseline changes include additional 
reliability enhancement team improvements and additional testing, 
which are not reflected in the 2003 CARD. However, when comparing the 
JASSM WBS dated January 1999 and the Lot 8 contract dated January 
2010, it is evident that WBS has been updated as changes have 
occurred. On the other hand, the CARD for the JASSM-ER was updated as 
of August 2009. Updates to the JASSM-ER CARD include a new, more 
powerful engine than the baseline variant. As part of the Milestone C 
process, work is currently under way by CAPE to update the JASSM-ER 
cost estimate. The program office said that the JASSM-ER cost model 
will include updated costs based on the Lot 8 proposal data, updated 
quantity profiles, and January 2010 revised inflation rates. The 
program office is in the process of updating labor rates and overhead 
rates and is reexamining all component prices. 

* The cost estimates were based on historical costs--The JASSM 
baseline and JASSM-ER share 70 percent building materials and 95 
percent software design; therefore, the WBS is virtually the same. As 
such, the JASSM baseline and JASSM-ER share many of the same costs. As 
outlined in both the JASSM baseline and JASSM-ER cost estimate 
documentation, the cost estimates were based on actual labor costs 
from JASSM baseline production Lot 1 through Lot 4, actual material 
and subcontractor costs from JASSM production Lot 1 through Lot 4, and 
estimated labor costs for JASSM production Lot 5 and Lot 6. Also, 
costs were estimated for the total JASSM program by fiscal year, and 
then allocated to both programs based on the associated number of 
missiles produced. The program office also used data from similar 
programs such as the HARPOON Missile, Advanced Medium Range Air-to-Air 
Missile, and Joint Standoff Weapon. 

JASSM Baseline and JASSM-ER Estimates Substantially Met Criteria for 
Credibility: 

While the cost estimates addressed risk and uncertainty as well as 
sensitivity, the estimates failed to address the risks regarding 
reliability and changes to the production schedule. By not doing so, 
the program office may not have a full understanding of the future 
effects to the overall cost position of these two programs. 

* The estimates were assessed for risk and uncertainty--Both programs 
identified engineering and test support, subcontractors, and warranty 
as major risk elements. However, the analysis did not identify 
reliability or an increase in the production schedule as possible risk 
factors. During the Nunn-McCurdy certification process, the DOD's 
analyses found that the cost breach was driven by four primary 
factors, two of which focused on reliability. As a result, the program 
office instituted a reliability enhancement program directed to 
address reliability concerns. An indirect effect of the enhancement 
program was an increase in the overall missile costs. The December 
2009 selected acquisition report identified increases to the missile 
hardware cost due to reduced annual quantities, missile production 
breaks, and increased test requirements and reliability programs. The 
combined cost estimate, for the JASSM baseline and JASSM-ER variants, 
has grown significantly over time. By not including reliability and 
the extension of the production schedule as possible risk factors, 
cost growth could continue to occur in future production lots. As a 
result, the programs' calculated point estimate confidence level of 77 
percent for baseline and 73 percent for the JASSM and JASSM-ER 
variants may be overstated. 

Figure 7: JASSM Baseline and JASSM-ER Cost Estimate Trend Analysis 
1997 through 2009: 

[Refer to PDF for image: multiple line graph] 

Fiscal year: 1997	
Current estimate: $602 million; 
Selected acquisition report for the JASSM baseline production 
estimate: $3.03 billion. 

Fiscal year: 1998	
Current estimate: $201 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $3.03 billion. 

Fiscal year: 1999	
Current estimate: $2.10 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $2.07 billion. 

Fiscal year: 2001	
Current estimate: $3.12 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $2.07 billion. 

Fiscal year: 2002	
Current estimate: $4.05 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $2.07 billion. 

Fiscal year: 2003	
Current estimate: $4.0 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $2.07 billion. 

Fiscal year: 2004	
Current estimate: $4.64 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $4.98 billion. 

Fiscal year: 2005	
Current estimate: $4.91 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $4.98 billion. 

Fiscal year: 2006	
Current estimate: $5.80 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $4.98 billion. 

Fiscal year: 2007	
Current estimate: $6.07 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $4.98 billion. 

Fiscal year: 2009	
Current estimate: $7.71 billion; 
Selected acquisition report for the JASSM baseline production 
estimate: $4.98 billion. 

Source: GAO analysis of DOD data. 

Note: DOD did not issue selected acquisition reports in December for 
fiscal years 2000 and 2008. 

[End of figure] 

* The estimates were assessed for sensitivity--For both the JASSM 
baseline and JASSM-ER estimates, key cost drivers were identified. The 
cost estimators examined eight cost factors for the JASSM baseline 
estimate and 13 cost factors for the JASSM-ER estimate. For the JASSM 
analysis, engineering support, testing support, other subcontractors, 
and Teledyne propulsion had the greatest impact on the total variance 
in the estimate. Engineering support showed a 14 percent impact, 
followed by test support with a 13 percent impact, other 
subcontractors with a 12 percent impact, and Teledyne propulsion with 
a 9 percent impact. These four elements account for 68 percent of the 
total cost before risk was applied. For the JASSM-ER analysis, the 
Williams propulsion, other subcontractors, engineering support, and 
testing support showed the greatest impact on the total cost variance 
in the estimate. The Williams propulsion had a 15 percent impact, 
followed by a 15 percent impact for other subcontractors, an 11 
percent impact for engineering support, and a 9 percent impact for 
test support. These four elements account for 76 percent of the total 
cost before risk was applied. 

* The cost estimates were checked for errors--Cross-checks were 
performed and no instances of double-counting were visible. The Lot 5 
and Lot 6 estimates were compared back to Lot 1 through Lot 4 for 
consistency and reasonableness. Also, multiple row and column 
summation cross-checks were performed to avoid duplication and 
omission errors. Upon review of the electronic cost model, GAO found 
no instances of double-counting and the spreadsheet calculations are 
accurate given the input parameters and assumptions. 

* The cost estimates were validated against an independent cost 
estimate--The CAIG estimate is the independent cost estimate. As part 
of the Nunn-McCurdy certification process, the CAIG developed an 
independent cost estimate for the development and procurement costs as 
well as future-year resource requirements for the baseline and JASSM-
ER variants. This new independent estimate was a joint effort by the 
OSD CAIG, the program office, and the Financial Management Center of 
Expertise, so there was no other estimate for comparison. Per the Nunn-
McCurdy JASSM certification package dated April 30, 2008, the CAIG 
estimate of the acquisition costs for the restructured JASSM program 
is $7.1 billion, which is directly comparable to the $6 billion 
estimate reported in the quarterly selected acquisition report dated 
December 2007. 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Michael J. Sullivan, (202) 512-4841 or sullivanm@gao.gov. 

In addition to the contact name above, the following individuals made 
key contributions to this report: William Graveline (Assistant 
Director), John Crawford, Morgan DelaneyRamaker, Tisha Derricotte, 
Michael J. Hesse, Karen Richey, Hai Tran, and Alyssa Weir. 

[End of section] 

Footnotes: 

[1] 10 U.S.C. § 2433 establishes the requirement for DOD to prepare 
unit cost reports on major defense acquisition programs or designated 
major defense subprograms. If a program exceeds cost growth thresholds 
specified in the law, this is known as a Nunn-McCurdy breach. The law 
describes two types of cost growth thresholds that can be breached; 
the "significant cost growth threshold" and the "critical cost growth 
threshold." A breach of the critical cost growth threshold occurs when 
a major defense acquisition program or designated major defense 
subprogram experiences at least a 25 percent increase over either the 
program acquisition unit cost (total cost of development, procurement, 
and system-specific military construction divided by the number of 
fully configured end items to be procured) or over the procurement 
unit cost (total funds programmed for procurement divided by the total 
number of fully configured end items to be procured) in the current 
baseline estimate or at least a 50 percent increase over the program 
acquisition unit cost or the procurement unit cost in the original 
baseline estimate. DOD is also required to report breaches to 
Congress. At the time of JASSM's breach, section 2433 also required 
DOD to, in certain circumstances, reassess the program and submit a 
certification to Congress in order to continue the program. Currently, 
these and other requirements are found in 10 U.S.C. § 2433a. 

[2] GAO, GAO Cost Estimating and Assessment Guide, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 2009). 

[3] GAO, Defense Acquisitions: Strong Leadership is Key to Planning 
and Executing Stable Weapon Programs, [hyperlink, 
http://www.gao.gov/products/GAO-10-522] (Washington, D.C.: May 6, 
2010). 

[4] In May 2003, a report of the Defense Science Board/Air Force 
Scientific Advisory Board Joint Task Force stated that the TSPR policy 
marginalized the government program management role and replaced 
traditional government "oversight" with "insight." It further stated 
that the authority of program managers and other working-level 
acquisition officials subsequently eroded to the point where it 
reduced their ability to succeed on development programs. We have also 
found that the use of TSPR in government oversight and involvement led 
to major reductions in various government capabilities, including cost-
estimating and systems-engineering staff. The loss of cost-estimating 
and systems-engineering staff in turn led to a lack of technical data 
needed to develop sound cost estimates. GAO, Space Acquisitions: 
Actions Needed to Expand and Sustain Use of Best Practices, GAO-07-
730T (Washington, D.C.: Apr. 19, 2007). 

[5] GAO, Defense Acquisitions: Need to Revise Acquisition Strategy to 
Reduce Risk for Joint Air-to-Surface Standoff Missile, [hyperlink, 
http://www.gao.gov/products/GAO/NSIAD-00-75] (Washington, D.C.: Apr. 
26, 2000). 

[6] A built-in-test provides fault detection to assess operational 
availability of the missile. The test is conducted on the ground or 
via aircraft interface and evaluates at least 95 percent of the 
missile components. It does not assess one-shot devices such as fuse, 
wing retention, and warhead. 

[7] OSD and Lockheed Martin officials have not officially scored the 
two most recent tests of JASSM-ER conducted in September 2010. 
Contractor officials stated that one test was fully successful while 
the other experienced an in-flight anomaly. Contractor officials 
stated that issues with the electronic control unit for the new engine 
are being evaluated as a possible root cause for the anomaly. 

[8] The program office provided technical comments stating that while 
operational effectiveness has not been evaluated since 2007, testing 
has been more operationally oriented since 2008. 

[9] Currently, the Air Force has about 942 JASSM baseline missiles in 
its inventory. 

[10] In May 2008, USD/ATL required the program to prepare a new 
acquisition program baseline within 90 days that separates JASSM and 
JASSM-ER costs. The certification of a new acquisition program 
baseline was originally delayed pending the analysis of flight test 
failures and recently delayed until the JASSM-ER requirements had been 
validated by the Joint Requirements Oversight Council. Program 
officials stated that the acquisition program baseline will be 
completed to support an initial production decision for JASSM-ER in 
November 2011. 

[11] Under this type of contract, there is a target cost, a target 
profit, and a price ceiling. After performance, the government and the 
contractor negotiate the final cost. If the final negotiated cost is 
over the target cost, then the contractor may realize a profit less 
than the target profit, or even a net loss. If the negotiated final 
cost is less than the target cost, then the contractor may realize a 
profit greater than the target profit. If the final cost exceeds the 
price ceiling, the contractor absorbs the difference. 

[12] The telemetry kit is added during the production process for 
newly produced missiles to be tested. 

[13] Air Force officials state that because of the cost of the 
telemetry kits, about $350,000, or 30 percent to 40 percent of the 
total production unit cost, it is cost prohibitive to add telemetry 
kits to every missile produced. Therefore, the Air Force has decided 
against changing the design of the missile to be more testable, and 
adds telemetry after fabrication. However, this requires additional 
retrofitting if the missiles do not have telemetry kits installed 
while still on the production line. 

[14] OSD and Air Force officials were not able to provide an 
analytical explanation for why the JASSM baseline and JASSM-ER 
variants have different reliability goals--90 percent and 85 percent, 
respectively. 

[15] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: March 
2009), p. 71). 

[16] A work breakdown structure is the cornerstone of every program 
because it defines in detail the work necessary to accomplish a 
program's objectives. WBS reflects the requirements, resources, and 
tasks that must be accomplished to develop a program. 

[17] Learning curve theory is based on the premise that people and 
organizations learn to do things better and more efficiently when they 
perform repetitive tasks. Learning curves assume that as the quantity 
of units to be produced doubles the amount of effort declines by a 
constant percentage. GAO, GAO Cost Estimating and Assessment Guide: 
Best Practices for Developing and Managing Capital Program Costs, 
[hyperlink, http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: 
March 2009), p. 137. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: