This is the accessible text file for GAO report number GAO-10-523 
entitled 'Defense Acquisitions: Navy's Ability to Overcome Challenges 
Facing the Littoral Combat Ship Will Determine Eventual Capabilities' 
which was released on August 31, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Requesters: 

United States Government Accountability Office: 
GAO: 

August 2010: 

Defense Acquisitions: 

Navy's Ability to Overcome Challenges Facing the Littoral Combat Ship 
Will Determine Eventual Capabilities: 

GAO-10-523: 

GAO Highlights: 

Highlights of GAO-10-523, a report to congressional requesters. 

Why GAO Did This Study: 

The Navy’s Littoral Combat Ship (LCS) is envisioned as a 
reconfigurable vessel able to meet three missions: surface warfare, 
mine countermeasures, and anti-submarine warfare. It consists of the 
ship (seaframe) and the mission package it carries and deploys. The 
Navy plans to invest over $25 billion through fiscal year 2035 to 
acquire LCS. However, recurring cost growth and schedule delays have 
jeopardized the Navy’s ability to deliver promised LCS capabilities. 

Based on a congressional request, GAO (1) identified technical, 
design, and construction challenges to completing the first four ships 
within current cost and schedule estimates, (2) assessed the Navy’s 
progress developing and fielding mission packages, and (3) evaluated 
the quality of recent Navy cost analyses for seaframes and their 
effect on program progress. GAO’s findings are based on an analysis of 
government and contractor-generated documents, and discussions with 
defense officials and key contractors. This product is a public 
version of a For Official Use Only report, GAO-10-1006SU, also issued 
in August 2010. 

What GAO Found: 

The Navy faces technical, design, and construction challenges to 
completing the first four seaframes within current cost and schedule 
estimates. The Navy and its shipbuilders have learned lessons from 
construction of the first two seaframes that have positioned them to 
more effectively construct future vessels. However, technical issues 
with the first two seaframes have yet to be fully resolved. Addressing 
these technical issues has required the Navy to implement design 
changes at the same time LCS 3 and LCS 4 are being built. 
Incorporating changes during this phase will likely require additional 
labor hours beyond current forecasts. Together, these challenges may 
hinder the ability of shipbuilders to apply lessons learned to follow-
on ships and could undermine anticipated benefits from recent capital 
investments in the LCS shipyards. 

Challenges developing mission packages have delayed the timely 
fielding of promised capabilities, limiting the ships’ utility to the 
fleet during initial deployments. Until these challenges are resolved, 
it will be difficult for the Navy to align seaframe purchases with 
mission package procurements and execute planned tests. Key mine 
countermeasures and surface warfare systems encountered problems in 
operational and other testing that delayed their fielding. For 
example, four of six Non-Line-of-Sight Launch System missiles did not 
hit their intended targets in recent testing, and the Department of 
Defense has since canceled the program. Further, Navy analysis of anti-
submarine warfare systems has shown the planned systems do not 
contribute significantly to the anti-submarine warfare mission. These 
combined challenges have led to procurement delays for all three 
mission packages. Mission package delays have also disrupted program 
test schedules—a situation exacerbated by early deployments of initial 
ships—limiting their availability for operational testing. In 
addition, these delays could disrupt program plans for simultaneously 
acquiring seaframes and mission packages. Until mission packages are 
proven, the Navy risks investing in a fleet of ships that does not 
deliver promised capability. 

The Navy entered contract negotiations in 2009 for fiscal year 2010 
funded seaframes with an incomplete understanding of LCS program 
costs. These contract negotiations proved unsuccessful, prompting the 
Navy to revise its acquisition strategy for the program. The 
contractors’ proposals for construction of the next three ships 
exceeded the approximate $1.4 billion in funds the Navy had allocated 
in its fiscal year 2010 budget. In response, the Navy revised its 
strategy to construct one seaframe design instead of two for fiscal 
year 2010 ships and beyond in an effort to improve affordability. Navy 
cost analyses completed prior to the failed negotiations in 2009 lack 
several characteristics essential to a high-quality cost estimate. 
These characteristics include the completion of sensitivity and 
uncertainty analyses and an independent review of the cost estimate. 
The Navy plans to complete a more comprehensive cost estimate before 
award of additional ship contracts in 2010. 

What GAO Recommends: 

GAO recommends the Secretary of Defense take actions to ensure more 
realistic cost estimates, timely incorporation of design changes, and 
coordination of seaframe and mission package acquisition. The 
Department of Defense concurred with each of these recommendations. 

View [hyperlink, http://www.gao.gov/products/GAO-10-523] or key 
components. For more information, contact Belva Martin at (202) 512-
4841 or martinb@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

Ongoing Development of Key Seaframe Systems Could Impede Efficient 
Construction of Initial Follow-On Ships: 

Mission Package Delays Limit Ship Capabilities in the Near Term and 
Pose Risk to Efficient Execution of Program Acquisition and Test Plans: 

Incomplete Cost Analyses in the LCS Program Have Undermined Program 
Progress: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: GAO Methodology Used to Perform Cost Estimating Analysis: 

Appendix III: Comments from the Department of Defense: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1: Systems Included in the Baseline LCS Mine Countermeasures, 
Surface Warfare, and Anti-Submarine Warfare Mission Packages: 

Table 2: Cost Growth on Initial LCS Seaframes: 

Table 3: Delays in Delivering Initial LCS Seaframes: 

Table 4: Navy's Progress Developing and Fielding Mine Countermeasures 
Mission Package Systems: 

Table 5: Navy's Progress Developing and Fielding Surface Warfare 
Mission Package Systems: 

Table 6: Navy's Progress Developing and Fielding Key Mission Package 
Support Aircraft: 

Table 7: Extent to Which the Navy's Total Ownership Cost Baseline 
Estimate for LCS Procurement Was Well-Documented, Comprehensive, 
Accurate, and Credible: 

Figures: 

Figure 1: LCS Seaframes: 

Figure 2: Operational Concept for LCS Mine Countermeasures Systems: 

Figure 3: Operational Concept for LCS Surface Warfare Systems: 

Figure 4: Recent Changes to Navy Mission Package Procurement Plans: 

Figure 5: Schedule of Key Near-term Events as Outlined in the LCS 
Program's 2009 and 2010 Acquisition Strategies: 

[End of section] 

United States Government Accountability Office:
Washington, DC 20548: 

August 31, 2010: 

The Honorable Solomon Ortiz:
Chairman:
The Honorable J. Randy Forbes:
Ranking Member:
Subcommittee on Readiness:
Committee on Armed Services:
House of Representatives: 

The Honorable Gene Taylor:
Chairman:
The Honorable W. Todd Akin:
Ranking Member:
Subcommittee on Seapower and Expeditionary Forces:
Committee on Armed Services:
House of Representatives: 

The Navy's Littoral Combat Ship (LCS) is envisioned as a vessel able 
to be reconfigured to meet three different mission areas: mine 
countermeasures, surface warfare, and anti-submarine warfare. Its 
design concept consists of two distinct parts--the ship itself 
(seaframe) and the mission package it carries and deploys. The Navy 
currently plans to invest over $25 billion to acquire LCS seaframes 
and mission packages through fiscal year 2035. However, recurring cost 
growth and schedule delays in the program have jeopardized the Navy's 
ability to deliver promised LCS capabilities. 

In light of these developments, you asked us to evaluate LCS planning 
and implementation efforts. In response to this request, we (1) 
identified technical, design, and construction challenges to 
completing the first four seaframes within current cost and schedule 
estimates; (2) assessed the Navy's progress developing and fielding 
mission packages; and (3) evaluated the quality of recent Navy cost 
analyses for seaframes and their effect on program progress. This 
product is a public version of a For Official Use Only report, GAO-10-
1006SU, also issued in August 2010. 

To identify challenges to completing the first four seaframes, we 
analyzed Department of Defense and contractor-generated documents that 
addressed technical challenges and cost and schedule performance for 
LCS seaframes including sea trial reports for the first two ships, 
construction progress briefings, and monthly contract performance 
reports. We corroborated this information through discussions with 
officials responsible for managing LCS design and construction 
activities including Navy program officials, technical authorities, 
and requirements officers; LCS prime contractors and shipbuilders; and 
the Office of the Secretary of Defense. To assess the Navy's progress 
developing and fielding mission packages, we reviewed documents that 
outline LCS mission package plans and performance including program 
schedules and recent test reports. We also held discussions with Navy 
program offices and Department of Defense agencies responsible for 
acquiring and testing key LCS mission systems to gather additional 
information on remaining risks to mission package development and 
integration. To evaluate the quality of recent Navy cost analyses, we 
compared the Navy's total ownership cost baseline estimate for the LCS 
program against the characteristics inherent in high-quality cost 
estimates as outlined in our cost estimating and assessment 
guide.[Footnote 1] In addition, we interviewed LCS cost analysts and 
program officials to supplement our analysis and gain additional 
visibility into the Navy's process for developing its cost estimate. A 
more detailed description of our scope and methodology is presented in 
appendix I. 

We conducted this performance audit from July 2009 to August 2010 in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

LCS is designed to move fast and transport manned and unmanned mine 
countermeasures, surface warfare, and anti-submarine warfare systems 
into theater. For LCS, the seaframe consists of the hull; command and 
control systems; automated launch, handling, and recovery systems; and 
certain core combat systems like an air defense radar and 57-
millimeter gun. The Navy is procuring the first four ships in two 
different designs from shipbuilding teams led by Lockheed Martin and 
General Dynamics. Lockheed Martin and General Dynamics currently build 
their designs at Marinette Marine and Austal USA shipyards, 
respectively. Figure 1 shows the first two LCS seaframes, USS Freedom 
(LCS 1) and USS Independence (LCS 2). 

Figure 1: LCS Seaframes: 

[Refer to PDF for image: 2 photographs] 

USS Freedom (LCS 1): 
USS Independence (LCS 2): 

Sources: Lockheed Martin (left); General Dynamics (right). 

Note: LCS 1 is a steel monohull while LCS 2 is an aluminum trimaran. 

[End of figure] 

The Navy is embedding LCS's mine countermeasures, surface warfare, and 
anti-submarine warfare capabilities within mission packages. These 
packages are comprised of unmanned underwater vehicles, unmanned 
surface vehicles, towed systems, and hull-and helo-mounted weapons. 
Table 1 identifies the systems included in the LCS mission packages. 

Table 1: Systems Included in the Baseline LCS Mine Countermeasures, 
Surface Warfare, and Anti-Submarine Warfare Mission Packages: 

Mine Countermeasures Mission Package: 

Airborne Laser Mine Detection System; 
Airborne Mine Neutralization System; 
AN/AQS-20A Sonar; 
Remote Minehunting System; 
Coastal Battlefield Reconnaissance and Analysis System; 
Organic Airborne and Surface Influence Sweep System; 
Rapid Airborne Mine Clearance System; 
Unmanned Surface Vehicle with Unmanned Surface Sweep System. 

Surface Warfare Mission Package: 

MK 46 30-Millimeter Gun System; 
Non-Line-Of-Sight Launch System and Missiles[B]; 
Maritime Security Module. 

Anti-Submarine Warfare Mission Package[A]: 

Multi-Function Towed Array; 
Remotely Towed Active Source; 
Multi-Static Off-Board Source; 
Remote Multi-Mission Vehicle; 
Unmanned Surface Vehicle; 
Unmanned Surface Vehicle Dipping Sonar; 
Unmanned Surface Vehicle Towed Array System. 

Source: Navy. 

Note: Aviation assets and support equipment including the MH-60R 
helicopter, MH-60S helicopter, MQ-8B Vertical Take-off and Landing 
Tactical Unmanned Aerial Vehicle, mission package computing 
environment, and stowage containers are not included. 

[A] The Navy is evaluating new configurations for future anti-
submarine warfare mission packages. 

[B] The Navy planned to employ the Army's Non-Line-of-Sight Launch 
System and Missiles to provide LCS with a small boat engagement 
capability, but the program was canceled in May 2010 because of 
performance and cost problems. The Navy is evaluating alternative 
weapon systems to replace the Non-Line-of-Sight Launch System and 
Missiles. 

[End of table] 

Fundamental to the capability of the LCS seaframe is its ability to 
move quickly ahead of other ships and deploy its offboard sensors to 
secure lanes of transit. To deploy LCS's mine countermeasures and anti-
submarine warfare systems, the Navy will rely extensively on (1) 
automated launch, handling, and recovery systems embedded in each 
seaframe and (2) helicopters and unmanned aerial vehicles. The Navy's 
acquisition approach is to populate initial versions of mission 
packages with a mixture of developmental and production-representative 
systems, gradually moving to all production-representative systems 
that constitute the baseline configuration for each package. The Navy 
plans to procure 55 seaframes and 64 mission packages (24 mine 
countermeasures, 24 surface warfare, and 16 anti-submarine warfare) as 
part of the LCS program. 

The Navy has required LCS seaframes to meet Level 1 survivability 
standards. Ships built to Level 1 are expected to operate in the least 
severe environment, away from the area where a carrier group is 
operating or the general war-at-sea region. These vessels should also 
maintain good handling in bad weather--including seas above 30 feet 
high (sea state 8)[Footnote 2]--and have systems for fighting fires on 
board the ships, hardening against electromagnetic pulses, and 
protection against chemical, biological, or radiological 
contamination. Unlike surface warships like cruisers and destroyers, 
Level 1 ships (including LCS) are not designed to maintain their 
mission capabilities after incurring substantive damage. Current ships 
in the fleet built to the Level 1 standard include material support 
ships, mine-warfare vessels, and patrol combatants. 

Two broad categories of contract types are available for government 
procurements, including ship procurement: fixed-price and cost- 
reimbursement. Fixed-price contracts provide for a firm price or, in 
appropriate cases, an adjustable price that may include a ceiling 
price, a target price, or both. This contract type places the risk on 
the contractor, who generally bears the responsibility of increased 
costs of performance. Cost-reimbursement contracts provide for payment 
of allowable incurred costs, to the extent prescribed in the contract. 
This contract type places most of the risk on the government, which 
may pay more than budgeted should incurred costs be more than expected 
when the contract was signed. 

The Navy awarded cost-reimbursable contracts for detail design and 
construction of the first two seaframes--LCS 1 and LCS 2--in December 
2004 and October 2005 for $188.2 million and $223.2 million, 
respectively. It later exercised options on each of these contracts in 
June and December 2006 for construction of the third and fourth ships 
(LCS 3 and LCS 4). However, changing technical requirements, evolving 
designs, and construction challenges increased the government's 
estimated prices at completion for the LCS 1 and LCS 2 seaframes to 
about $500 million each. This cost growth precipitated concern within 
the Navy that similar outcomes were possible for LCS 3 and LCS 4. In 
response, the Navy reassessed program costs and structure, revisited 
the acquisition strategy for future ships, and entered into 
negotiations with its shipbuilders to convert the LCS 3 and LCS 4 
contracts into fixed-price contracts. The Navy was unable to reach 
agreement with its shipbuilders on fixed-price terms for these ships, 
subsequently leading the Navy to terminate, in part, the LCS 3 and LCS 
4 contracts in April and November 2007 for the convenience of the 
government. In March and May 2009, the Navy awarded new fixed-price 
contracts for LCS 3 and LCS 4. According to the Navy, work completed 
and materials procured under the terminated original contract options 
for LCS 3 and LCS 4--totaling approximately $192 million--are not 
included in the current contract values for those ships. 

In our work on shipbuilding best practices, we found that achieving 
design stability before start of fabrication is a key step that 
leading commercial shipbuilders and ship buyers follow to ensure their 
vessels deliver on-time, within planned costs, and with planned 
capabilities.[Footnote 3] Leading commercial firms assess a ship 
design as stable once all basic and functional design activities have 
been completed. Basic and functional design refers to two-dimensional 
drawings and three-dimensional, computer-aided models (when employed) 
that fix the ship's hull structure; set the ship's hydrodynamics; 
route all major distributive systems including electricity, water, and 
other utilities; and identify the exact positioning of piping and 
other outfitting within each block of the ship. At the point of design 
stability, the shipbuilder has a clear understanding of both ship 
structure as well as ship electrical, piping, and other systems that 
traverse individual blocks of the ship. To achieve design stability, 
shipbuilders need suppliers (also called vendors) to provide complete, 
accurate system information prior to entering basic design. This 
vendor-furnished information describes the exact dimensions of a 
system or piece of equipment going into a ship, including space and 
weight requirements, and also requirements for power, water, and other 
utilities that will have to feed the system. 

As is typical for all ships, the LCS construction phase includes 
several steps: block fabrication, assembly and outfitting of blocks, 
block erection, launch, and delivery. During block fabrication, metal 
plates are welded together into elements called blocks. Blocks are the 
basic building units for a ship, and when completed they will form 
completed or partial compartments, including accommodation space, 
engine rooms, and storage areas. Blocks are generally outfitted with 
pipes, brackets for machinery or cabling, ladders, and any other 
equipment that may be available for installation at this early stage 
of construction. This allows a block to be installed as a completed 
unit when it is welded to the hull of the ship. Installing equipment 
at the block stage of construction is preferable because access to 
spaces is not limited by doors or machinery, unlike at later phases. 
Blocks are welded together to form grand blocks and then erected with 
other grand blocks in a drydock or, in the case of LCS, in a building 
hall. Finally, once the ship is watertight and the decision is made to 
launch--or float the ship in water--the ship is then towed into a quay 
or dock area where final outfitting and testing of machinery and 
equipment like main engines will occur. Afterwards, the ship embarks 
on sea trials where performance is evaluated against the contractually 
required specifications and overall quality is assessed. Following sea 
trials, the shipyard delivers the ship to the buyer. 

LCS 1 was delivered to the Navy in September 2008, with LCS 2 
following in December 2009. The Navy has also accepted delivery of 
five partial mission packages to date. Currently, LCS 1 is on 
deployment, LCS 2 is undergoing post-delivery work, and LCS 3 and LCS 
4 remain in different stages of construction. In addition, development 
and testing activities for the mine countermeasures, anti-submarine 
warfare, and surface warfare mission packages continue. The Navy 
deployed LCS 1 two years ahead of its previous schedule and prior to 
the ship completing initial operational test and evaluation. The Navy 
also stated that early deployment is possible for LCS 2. 

Initial operational test and evaluation is intended to assess a weapon 
system's capability in a realistic environment when maintained and 
operated by sailors, subjected to routine wear-and-tear, and employed 
in typical combat conditions against a simulated enemy who fights 
back. During this test phase, the weapon system is exposed to as many 
actual operational scenarios as possible--a process that reveals the 
weapon system's capabilities under stress. Once the fleet has attained 
the ability to effectively employ and operate the weapon system, 
initial operational capability is achieved. 

Until September 2009, the Navy planned to continue buying both ship 
designs. In September 2009, the Navy announced it was revising the LCS 
program's acquisition strategy and would select one seaframe design 
before awarding contracts for any additional ships. In the National 
Defense Authorization Act for Fiscal Year 2010, Congress mandated a 
$480 million cost cap for each LCS, starting with fiscal year 2011 
funded seaframes.[Footnote 4] In an effort to comply with this 
mandate, Navy officials have stated that a major program review 
(milestone B)--and completion of an independent cost estimate--will 
precede further contract awards in the program. 

Cost estimates are necessary for government acquisition programs, like 
LCS, for many reasons: to support decisions about funding one program 
over another, to develop annual budget requests, to evaluate resource 
requirements at key decision points, and to develop performance 
measurement baselines. A cost estimate is a summation of individual 
cost elements, using established methods and valid data, to estimate 
the future costs of a program, based on what is known today. The 
management of a cost estimate involves continually updating the cost 
estimate with actual data as they become available, revising the 
estimate to reflect changes, and analyzing differences between 
estimated and actual costs--for example, using data from a reliable 
earned value management system. 

Ongoing Development of Key Seaframe Systems Could Impede Efficient 
Construction of Initial Follow-On Ships: 

The Navy faces technical, design, and construction challenges to 
completing the first four seaframes within current cost and schedule 
estimates. The Navy and its shipbuilders have learned lessons from 
construction of the first two seaframes that can be applied to 
construction of future vessels. However, technical issues with the 
first two seaframes have yet to be fully resolved, posing risk of 
design changes to follow on ships already under construction. 
Addressing these technical issues has required the Navy to implement 
design changes at the same time LCS 3 and LCS 4 are being built. 
Incorporating changes during this phase may disrupt the optimal 
construction sequence for these ships, requiring additional labor 
hours beyond current forecasts. Together, these challenges may hinder 
the ability of shipbuilders to apply lessons learned to follow on 
ships and could undermine anticipated benefits from recent capital 
investments in the LCS shipyards. 

Cost Growth and Schedule Delays Have Hampered Construction of the 
First Four Ships: 

Initial LCS seaframes have required more funding and taken longer to 
construct than the Navy originally planned. The Navy has accepted 
delivery of the first two ships (LCS 1 and LCS 2), which, according to 
the Navy, reduces the likelihood of additional cost increases and 
schedule delays on those ships. Further, the Navy's decision to 
partially terminate, and later re-award, construction contracts for 
follow-on ships (LCS 3 and LCS 4) changed the planned delivery dates 
for those ships. Tables 2 and 3 highlight the cost growth and schedule 
delays associated with the first four ships of the class. 

Table 2: Cost Growth on Initial LCS Seaframes: Dollars in millions: 

LCS 1; 
Initial budget: $215.5; 
Fiscal year 2011 budget: $537.0; 
Total cost growth: $321.5; 
Cost growth as a percent of initial budget: 149.2%. 

LCS 2; 
Initial budget: $256.5; 
Fiscal year 2011 budget: $607.0[A]; 
Total cost growth: $350.5; 
Cost growth as a percent of initial budget: 136.6%. 

LCS 3-4; 
Initial budget: $1,260.7[B]; 
Fiscal year 2011 budget: $1,357.7; 
Total cost growth: $97.0; 
Cost growth as a percent of initial budget: 7.7%. 

Source: GAO analysis of President's budget data. 

Note: Fiscal year 2011 budget figures identified for LCS 1 and LCS 2 
exclude funding associated with certain design, planning, and program 
management activities for these ships. These funds total $170.0 
million and $177.0 million for LCS 1 and LCS 2, respectively. 

[A] Total excludes Department of Defense reprogramming actions in July 
2010 that added $5.256 million in funding to complete post-delivery 
work on LCS 2. 

[B] Initial budget figure for LCS 3 and LCS 4 reflects the total 
Shipbuilding and Conversion, Navy (SCN) funds the Navy requested in 
fiscal year 2009 to construct two LCS seaframes plus the value of 
funds and materials applied from the two canceled, fiscal year 2006 
funded LCS seaframes. Congress originally appropriated $440 million in 
fiscal year 2006 to construct these two ships. 

[End of table] 

Table 3: Delays in Delivering Initial LCS Seaframes: 

Ship: LCS 1; 
Initial planned delivery date: January 2007; 
Current estimated/actual delivery date: September 2008; 
Total construction delays: 20 months. 

Ship: LCS 2; 
Initial planned delivery date: October 2007; 
Current estimated/actual delivery date: December 2009; 
Total construction delays: 26 months. 

Ship: LCS 3; 
Initial planned delivery date: November 2012; 
Current estimated/actual delivery date: February 2012; 
Total construction delays: N/A. 

Ship: LCS 4; 
Initial planned delivery date: January 2013; 
Current estimated/actual delivery date: April 2012; 
Total construction delays: N/A. 

Source: GAO analysis of President's budget data. 

Note: Initial planned delivery dates for LCS 3 and LCS 4 reflect the 
planned schedules for two fiscal year 2009 funded LCS seaframes. 
Previously, the Navy funded these two ships in fiscal year 2006 and 
expected deliveries in October 2008. The Navy's decision to partially 
terminate construction contracts for the two fiscal year 2006 ships, 
coupled with Congress's decision to rescind appropriations for one 
fiscal year 2008 funded seaframe, account for several months of 
schedule gains realized for LCS 3 and LCS 4. 

[End of table] 

First Two Seaframes Delivered to the Fleet, but Technical Challenges 
Currently Limit Their Capabilities: 

The Navy accepted delivery of LCS 1 and LCS 2 with both seaframes in 
an incomplete state and with outstanding technical issues. After 
experiencing significant cost increases and schedule delays on these 
ships, the Navy judged it more cost efficient to accept the incomplete 
ships and resolve remaining issues post-delivery. According to Navy 
officials, this step afforded the Navy more control over remaining 
work and provided the ability to use repair yards that charge less 
than the builder in some instances. Although the ships are currently 
in service, the Navy continues to address technical issues on each 
seaframe. Addressing these issues has required the Navy to schedule 
extensive post-delivery work periods for each ship, which were not 
fully anticipated at the time of lead ship contract awards. For 
instance, to resolve the LCS 1 issues, the Navy allocated several 
months for two industrial post-delivery availability periods in 2009. 
A similar schedule is planned for LCS 2. 

The Navy has made significant progress resolving LCS 1 deficiencies. 
While challenges with several systems were identified at delivery, the 
Navy deferred testing of other systems until after delivery. The 
shipbuilder had not completed installation of several LCS 1 systems 
prior to delivery, contributing to Navy decisions to defer key 
elements of the ship's acceptance trials until later.[Footnote 5] Most 
notably, the Navy deferred testing of the ship's launch, handling, and 
recovery system--a system instrumental to deploying and recovering 
mission package elements that, if not performing adequately, will 
impair LCS capability. To date, a full demonstration of this system 
remains incomplete. Navy simulations to date have identified risks in 
safely launching and recovering mission systems that experience 
pendulous motion during handling--such as the remote multi-mission 
vehicle and unmanned surface vehicle systems. Navy officials stated, 
however, that the fleet successfully demonstrated operation and 
movement of an embarked 11-meter rigid-hull inflatable boat, having 
used one extensively for counterdrug operations in the Caribbean in 
March 2010. 

Another challenge for LCS 1 launch, handling, and recovery is the 
potential for unacceptably high water levels during high sea states in 
the waterborne mission zone--the area at the stern end of the ship 
designed to launch watercraft through stern doors and down a ramp 
directly into the water. Further, LCS 1's launch, handling, and 
recovery system has also experienced difficulty safely moving payloads 
on the ship. Most notably, payload handling cranes will not be 
installed until a future maintenance period in fiscal year 2013. 

Like LCS 1, the Navy identified several significant technical 
deficiencies on LCS 2 during that ship's acceptance trials. However, 
because LCS 2 was only recently delivered (December 2009), the Navy 
remains in the early stages of addressing the issues facing that ship. 
Similar to LCS 1, the Navy chose to accept delivery of LCS 2 prior to 
the shipbuilder completing installation of key systems. The incomplete 
condition of the ship contributed to Navy decisions to defer key 
elements of acceptance trials until after delivery. As was the case 
with LCS 1, these deferments included testing of the LCS 2 launch, 
handling, and recovery system for mission watercraft. 

LCS 2 is designed to employ a twin boom extensible crane system to 
launch, handle, and recover mission watercraft. This system includes 
the crane, synthetic lift lines, and a straddle carrier. The synthetic 
lift lines attach to the crane to retrieve watercraft, but remain an 
unproven, new capability to the Navy. Another risk to the system is 
the ability of the straddle carrier to interface with, maneuver, and 
return to stowage the rigid-hull inflatable boat, remote multi-mission 
vehicle, and unmanned surface vehicle systems--three of the largest 
watercraft the Navy plans to embark on LCS 2. According to the Navy, 
the straddle carrier was used to successfully move the remote multi- 
mission vehicle and unmanned surface vehicle during onboard trials in 
March 2010. 

Continuing Design Changes Could Hinder Efficient Construction of LCS 3 
and LCS 4: 

The Navy's efforts to resolve technical issues affecting LCS 1 and LCS 
2, implement cost reduction measures, and increase mission capability 
have led to design changes for LCS 3 and LCS 4, several of which are 
not yet complete. These design changes have affected the configuration 
of several major ship systems for LCS 3 and LCS 4 including 
propulsion, communications, electrical, and navigation. The Navy is 
working to implement these design changes concurrent with LCS 3 and 
LCS 4 construction activities. Incorporating design changes on the 
lead seaframes while the follow-on ships are under construction may 
disrupt the optimal construction sequence for LCS 3 and LCS 4, 
requiring additional labor hours beyond current forecasts. As we have 
previously reported, by delaying construction start until basic and 
functional design is completed and a stable design is achieved, 
shipbuilders minimize the risk of design changes and the subsequent 
costly rework and out-of-sequence work these changes can drive. 
[Footnote 6] 

Benefits Derived from Recent Process Improvements and Capital 
Investments in the LCS Shipyards May Not Be Fully Realized on Early 
Follow-On Ships: 

The Navy and its shipbuilders learned valuable lessons from the 
construction of the lead ships that can save time and money on the 
construction of follow-on ships. The shipbuilding teams have 
implemented process improvements based on these lessons and made 
capital investments in their yards in an effort to increase 
efficiency. Despite the various improvements to capacity and processes 
at the shipyards, capitalizing on these improvements might be 
challenging given the significant design changes still occurring in 
the program. As technical issues are resolved on the lead seaframes, 
this, in general, leads to redesign--and potentially costly rework--
for initial follow-on ships. Thus, while efficiencies will be gained 
as a result of the shipyards' improvement, remaining technical issues 
on the seaframes will likely continue to jeopardize the Navy's ability 
to complete the first four seaframes within planned cost and schedule 
estimates. 

Mission Package Delays Limit Ship Capabilities in the Near Term and 
Pose Risk to Efficient Execution of Program Acquisition and Test Plans: 

Challenges developing and procuring mission packages have delayed the 
timely fielding of promised capabilities, limiting the ships' utility 
to the fleet during initial deployments. Until these challenges are 
resolved, it will be difficult for the Navy to align seaframe 
purchases with mission package procurements and execute planned tests. 
Key mine countermeasures and surface warfare systems have encountered 
technical issues that have delayed their development and fielding. 
Further, Navy analysis of LCS anti-submarine warfare systems found 
these capabilities did not contribute significantly to the anti-
submarine warfare mission. These challenges have led to procurement 
delays for all three mission packages. For instance, key elements of 
the surface warfare package remain in development, requiring the Navy 
to deploy a less robust capability on LCS 1. Mission package delays 
have also disrupted program test schedules--a situation exacerbated by 
decisions to deploy initial ships early, which limit their 
availability for operational testing. In addition, these delays could 
disrupt program plans for simultaneously acquiring seaframes and 
mission packages. Until mission package performance is proven, the 
Navy risks investing in a fleet of ships that does not deliver 
promised capability. 

Challenges Developing LCS Mission Package Systems Have Delayed Their 
Planned Fielding Dates: 

Development efforts for most of these systems predate the LCS program--
in some cases by 10 years or more. Recent testing of mission package 
systems has yielded less than desirable results. To date, most LCS 
mission systems have not demonstrated the ability to provide required 
capabilities. Further, the Navy has determined that an additional 
capability will be incorporated into future anti-submarine warfare 
mission packages. The existing anti-submarine warfare mission package 
procurement is temporarily suspended, and performance will be assessed 
during at-sea testing in 2010. In addition to the sensors, vehicles, 
and weapons included in each mission package, each LCS will rely on 
aircraft and their support systems to complete missions. 

Mine Countermeasures: 

Mine countermeasures missions for LCS will involve detecting, 
classifying, localizing, identifying, and neutralizing enemy sea mines 
in areas ranging from deep water through beach zones.[Footnote 7] We 
have previously reported on challenges the Navy faces in transitioning 
the mine countermeasures mission to LCS.[Footnote 8] Figure 2 
illustrates how the Navy plans to employ the LCS mine countermeasures 
systems against mine threats. 

Figure 2: Operational Concept for LCS Mine Countermeasures Systems: 

[Refer to PDF for image: illustration] 

Depicted in the illustration: 

Mine threats: 
Near Surface mines (0’ to 30’ from surface); 
In Volume mines (30’ from surface to 150’ from bottom); 
Close-tethered mines (30’ to 150’ from bottom); 
Close-close tethered mines (<30’ from bottom). 

MH-60S Helicopter: 
MQ-8B Fire Scout Unmanned Aerial Vehicle: 
AN/AQS-20A Sonar; 
Remote mine-hunting system; 
Airborne Mine Neutralization System; 
Organic Airborne and Influence Sweep System; 
Unmanned Surface Vehicle with Unmanned Surface Sweep System; 
Airborne Laser Mine Detection System; 
Rapid Airborne Mine Clearance System; 
Coastal Battlefield Reconnaissance and Analysis System. 

Source: GAO analysis of Navy data. 

[End of figure] 

Table 4 shows the status of mine countermeasures mission package 
systems. 

Table 4: Navy's Progress Developing and Fielding Mine Countermeasures 
Mission Package Systems: 

Mission system: AN/AQS-20A Sonar; 
Capabilities description: Provides identification of bottom mines in 
shallow water and detection, localization, and classification of 
bottom, close-tethered, and volume mines in deep water; 
Development status: System has met performance requirements in 
developmental testing. Operational testing has been delayed, however, 
due to decertification of the system following integration problems 
with the common tow cable that connects it to the MH-60S helicopter; 
Estimated fielding date: 2011. 

Mission system: Airborne Laser Mine Detection System; 
Capabilities description: Detects, classifies, and localizes floating 
and near-surface moored mines in deep water; 
Development status: System has demonstrated partial capability during 
developmental testing. Current challenges include the ability to 
detect mines at the required maximum depth or classify mines at 
surface depths; 
Estimated fielding date: 2011. 

Mission system: Airborne Mine Neutralization System; 
Capabilities description: Identifies and neutralizes unburied bottom 
and moored sea mines in shallow water that are impractical or unsafe 
to counter using existing minesweeping systems; 
Development status: System has successfully streamed and deployed an 
inert neutralizer in developmental testing. The mount that connects 
the system to the MH-60S carriage, stream, tow, and recovery system is 
being redesigned following loss of a test unit; 
Estimated fielding date: 2011. 

Mission system: Coastal Battlefield Reconnaissance and Analysis System; 
Capabilities description: Provides intelligence preparation of the 
battlefield information, which accurately depicts tactical objectives, 
minefields, and obstacles in the surf zone, on the beach, and through 
the beach exit during amphibious and expeditionary operations; 
future increments planned will provide active (day/night), surf zone, 
buried minefield detection, and real-time processing capabilities; 
Development status: System has demonstrated capability to detect 
buried mines on the beach when flown from the MH-53 helicopter, but 
has yet to be integrated with its host platform, the MQ-8B Vertical 
Take-off and Landing Tactical Unmanned Aerial Vehicle; 
Estimated fielding date: 2012. 

Mission system: Organic Airborne and Surface Influence Sweep System; 
Capabilities description: Provides organic, high-speed magnetic/ 
acoustic influence minesweeping capability where mine hunting is not 
feasible (adverse environmental conditions); 
Development status: Engineering development model experienced 
excessive corrosion at its interface point with the common tow cable 
during testing from an MH-53E helicopter. The Navy has implemented a 
design solution, and new models are in production; 
Estimated fielding date: 2012. 

Mission system: Remote Minehunting System; 
Capabilities description: Underwater vehicle towing the AN/AQS-20A 
sonar used to detect, classify, locate, and identify minelike objects; 
Development status: The Navy abandoned initial operational test and 
evaluation of this system in June 2007 following reliability issues--
both software and hardware related--affecting the underwater vehicle. 
Subsequent plans for resuming this testing in September 2008 were 
deferred because of continuing concerns about the reliability of the 
underwater vehicle, and the scheduled test was downgraded to an 
operational assessment. Spurred by cost growth facing the system, the 
Office of the Secretary of Defense recently completed a review of the 
program, subsequently deciding to allow the system to continue 
development. The Navy is currently executing a reliability growth plan 
for the system; 
Estimated fielding date: 2015. 

Mission system: Unmanned Surface Vehicle with Unmanned Surface Sweep 
System; 
Capabilities description: Micro-turbine-powered magnetic towed cable 
and acoustical signal generator towed from an unmanned surface craft; 
Development status: Prototypes of the unmanned surface vehicle have 
experienced connectivity and communication issues at distance, 
reliability issues with their electrical generators, and software 
malfunctions. Additionally, the Navy is redesigning the cable planned 
to tow the unmanned surface sweep system due to durability concerns. 
The unmanned surface sweep system remains in early development; 
Estimated fielding date: 2015. 

Mission system: Rapid Airborne Mine Clearance System; 
Capabilities description: Mounted 30-millimeter gun firing 
supercavitating projectiles to neutralize near-surface and floating 
moored mines; 
Development status: Separate engineering development models of the gun 
and targeting pod have been tested with mixed results. Gun testing 
demonstrated the need to redesign the bushing (shock absorber). 
Targeting pod testing revealed problems reacquiring minelike objects 
and maintaining a gun lock on them. The Navy is rewriting software to 
address the targeting pod issues; 
Estimated fielding date: 2017. 

Source: GAO analysis of Navy data. 

[End of table] 

For two of the LCS mine countermeasures systems--the Remote 
Minehunting System and the Airborne Laser Mine Detection System--the 
Navy has delayed further production pending successful resolution of 
developmental challenges. These systems both entered production in 
2005. According to Navy officials, relaxing the performance 
requirements for the Remote Minehunting System and the Airborne Laser 
Mine Detection System is one option under consideration. 

* Airborne Laser Mine Detection System: Testing of this system has 
revealed problems detecting mines at the required maximum depth and 
classifying mines at surface depths. According to Navy officials, the 
system's required maximum detection depth could be reduced because the 
system can currently detect mine-like objects at depths that extend 
below the keels of all ships in the fleet. According to Director, 
Operational Test and Evaluation officials, however, the system is 
currently incapable of providing this capability with the required 
accuracy. Further, Navy officials report that the Remote Minehunting 
System could provide coverage in near-surface areas of the water that 
the Airborne Laser Mine Detection System currently cannot reach. 

* Remote Minehunting System: Operational testing of this system in 
2008 revealed significant reliability shortfalls associated with the 
underwater vehicle. Most notably, the system was only able to function 
for 7.9 hours before failing--far short of its minimum requirement. 
Director, Operational Test and Evaluation officials report that since 
the 2008 event, the Navy's estimated mean time between failures for 
the system has increased to 45 hours. According to Navy officials, 
testing and design changes are expected to last into 2011. While the 
Navy is actively exploring ways to improve Remote Minehunting System 
reliability, it is also considering reducing the reliability 
requirement by half. 

Surface Warfare: 

Surface warfare for LCS involves detecting, tracking, and engaging 
small boat threats; escorting ships; and protecting joint operating 
areas. Figure 3 illustrates how the surface warfare mission package 
functions. 

Figure 3: Operational Concept for LCS Surface Warfare Systems: 

[Refer to PDF for image: illustration] 

LCS: Maritime Security Module (on board): 
MH-60R Helicopter; 
MQ-8B Fire Scout Unmanned Aerial Vehicle; 
30 millimeter gun: 2.3 nautical miles; 
57 millimeter gun: 3.5 nautical miles; 
Non-Line-of-Sight Launch System: 21 nautical miles. 

Source: U.S. Navy. 

Note: The 57-millimeter gun is a core seaframe system. 

[End of figure] 

Table 5 shows the status of surface warfare mission systems. 

Table 5: Navy's Progress Developing and Fielding Surface Warfare 
Mission Package Systems: 

Mission system: MK 46 30-Millimeter Gun Module; 
Capabilities description: Two-axis stabilized chain gun that can fire 
up to 250 rounds per minute employing a forward-looking infrared 
sensor, camera, and laser rangefinder; 
Development status: Structural test firing completed from LCS 1 in 
September 2009. Currently, the system has not been fully integrated 
with the combat systems for either of the lead seaframes; 
Actual/estimated fielding date: 2010. 

Mission system: Maritime Security Module; 
Capabilities description: Complement of 19 personnel operating in two 
teams on LCS that provide capability to conduct visit, board, search, 
and seizure operations against potential threat vessels; 
Development status: The Navy installed a prototype Maritime Security 
Module in LCS 1 for the ship's early deployment that included 2 11-
meter rigid hull inflatable boats and two berthing/sanitation modules; 
Actual/estimated fielding date: 2010. 

Mission system: Non-Line-of-Sight Launch System; 
Capabilities description: Container launch unit and precision attack 
missile for use against moving and stationary targets; 
Development status: Testing in July 2009 intended to demonstrate the 
system's ability to neutralize a target while fired from a rolling 
platform (similar to a ship) proved unsuccessful due to a 
malfunctioning sensor and battery connector. During Army operational 
testing in January and February 2010, the precision attack missile 
failed to hit its intended target four out of six times. Recent 
cancellation of the Non-Line-of-Sight Launch System program has 
prompted the Navy to seek alternatives to include on LCS; 
Actual/estimated fielding date: 2014. 

Source: GAO analysis of Navy data. 

[End of table] 

The surface warfare package remains unproven as a key system, the Non- 
Line-of-Sight Launch System, was recently canceled prior to completing 
development. The system--developed under the Army's Future Combat 
System program--progressed slower than anticipated due to technical 
challenges and associated test failures. These issues--along with Army 
fiscal year 2011 budget estimates showing missiles could cost up to 
$466,000 each--prompted the Army to revisit its commitment to the 
program. In May 2010, this process culminated with the Under Secretary 
of Defense for Acquisition, Technology and Logistics approving the 
Army's request to cancel the program. In response, Navy officials 
report they are now evaluating potential alternatives to the Non-Line- 
of-Sight Launch System--including modifications to existing missile 
systems--to substitute into the surface warfare mission package. 

Support Aircraft: 

In addition to systems outlined above, the Navy plans to employ 
aircraft in different configurations to execute LCS missions. Table 6 
highlights the status of key mission package support aircraft. 

Table 6: Navy's Progress Developing and Fielding Key Mission Package 
Support Aircraft: 

Mission system: MH-60R Helicopter[A]; 
Capabilities description: Ship-based helicopter designed to operate 
from several types of Navy vessels. Key capabilities include dipping 
sonar and sonobuoy acoustic sensors, multi-mode radar, electronic 
warfare sensors, and a forward looking infrared sensor with laser 
designator. Employs torpedoes, Hellfire air-to-surface missiles, and 
crew-served mounted machine guns; 
Development status: Initial operational capability achieved in 2005. 
September 2009 testing revealed deficiencies associated with the data 
link (Link 16) and with the automatic video tracking feature of the 
helicopter's targeting system; 
Actual/estimated fielding date: 2005. 

Mission system: MQ-8B Vertical Take-off and Landing Tactical Unmanned 
Aerial Vehicle[B]; 
Capabilities description: Unmanned rotary wing air vehicle designed to 
provide intelligence, surveillance, reconnaissance, and targeting data 
to tactical users; 
Development status: Low-rate initial production units are scheduled to 
complete initial operational test and evaluation onboard a Navy 
frigate in 2010. The Navy plans to field the system exclusively 
onboard LCS, where it will connect with and deploy the Coastal 
Battlefield Reconnaissance and Analysis System. However, integration 
with the Coastal Battlefield Reconnaissance and Analysis System and 
LCS seaframes is not scheduled to occur until after the MQ-8B achieves 
initial operational capability; 
Actual/estimated fielding date: 2010. 

Mission system: MH-60S Helicopter[C]; 
Capabilities description: Helicopter modified into three variants 
(Fleet Logistics, Airborne Mine Countermeasures, and Armed Helicopter) 
and optimized for operation in the shipboard/marine environment. 
Installed systems differ by variant based on mission. The Navy is 
procuring the Airborne Mine Countermeasures variant in two increments 
of capability; 
Development status: Operational testing of the Airborne Mine 
Countermeasures variant in 2008 was unsuccessful due to reliability 
issues with the Carriage, Stream, Tow, and Recovery System used to 
deploy, tow, and retrieve several of the LCS mine countermeasures 
systems. Further, the on-board command and control console used to 
monitor and communicate with deployed airborne mine countermeasures 
systems required a series of software updates to fix computer freezes 
and other glitches that were degrading performance. The Navy has 
rescheduled initial operational test and evaluation events for this 
variant to December 2010; 
Actual/estimated fielding date: 2011[D]. 

Source: GAO analysis of Navy data. 

[A] MH-60R helicopter supports deployment of the surface warfare and 
anti-submarine warfare mission packages. 

[B] MQ-8B Vertical Take-off and Landing Tactical Unmanned Aerial 
Vehicle supports deployment of all three LCS mission packages. 

[C] MH-60S helicopter supports deployment of the mine countermeasures 
mission package. 

[D] Denotes estimated fielding date for the initial increment of the 
MH-60S airborne mine countermeasures variant. 

[End of table] 

In addition to these technical challenges, other factors may constrain 
availability of the three LCS support aircraft. 

* MH-60R Helicopter: According to Navy officials, while this system 
has completed its first deployment with a carrier strike group, the 
earliest possible date that it will deploy onboard an LCS is the end 
of fiscal year 2013. Navy officials reported that because of fleet 
demand for the helicopter, initial MH-60Rs will be assigned to the 
carrier strike group elements (e.g., destroyers, cruisers, and 
frigates) before deploying with an LCS. As of January 2010, the Navy 
had accepted delivery of 46 MH-60Rs of a planned quantity of 252. 

* MH-60S Helicopter: The Navy has certified flight operations of the 
armed variant of this helicopter from LCS 1. Previous plans called for 
only the mine countermeasures variant of the MH-60S to fly from the 
LCS. As of December 2009, 159 of 275 MH-60S helicopters had been 
delivered. 

* MQ-8B Vertical Take-off and Landing Tactical Aerial Vehicle (known 
as Fire Scout): The Navy is conducting operational testing of Fire 
Scout onboard a frigate, but intends to field the system with LCS 
exclusively. Reliability and availability issues uncovered during 
fiscal year 2010 testing have delayed the program's fielding schedule. 
Previously, the Navy expected to reach a full-rate production decision 
on Fire Scout in March 2010. The Navy has since deferred this decision 
to May 2011. 

Developmental Challenges with Individual Systems Have Contributed to 
Mission Package Procurement Delays: 

The Navy is buying mission packages through an incremental approach by 
incorporating systems into the respective mission packages when 
systems achieve minimum performance requirements. Figure 4 illustrates 
the effect that recent developmental challenges have had upon mission 
package procurement plans. 

Figure 4: Recent Changes to Navy Mission Package Procurement Plans: 

[Refer to PDF for image: stacked horizontal bar graph] 

2007 plan: Mine Countermeasures; 
Number of partial mission package deliveries through fiscal year 2012: 
3; 
Number of fully capable mission package deliveries through fiscal year 
2012: 1. 

2007 plan: Surface Warfare; 
Number of partial mission package deliveries through fiscal year 2012: 
6; 
Number of fully capable mission package deliveries through fiscal year 
2012: 3. 

2007 plan: Anti-Submarine Warfare; 
Number of partial mission package deliveries through fiscal year 2012: 
2; 
Number of fully capable mission package deliveries through fiscal year 
2012: 1. 

2007 plan: Total; 
Number of partial mission package deliveries through fiscal year 2012: 
11. 
Number of fully capable mission package deliveries through fiscal year 
2012: 5. 

2010 plan: Mine Countermeasures; 
Number of partial mission package deliveries through fiscal year 2012: 
3. 

2010 plan: Surface Warfare; 
Number of partial mission package deliveries through fiscal year 2012: 
4. 

2010 plan: Anti-Submarine Warfare; 
Number of partial mission package deliveries through fiscal year 2012: 
1. 

2010 plan: Total; 
Number of partial mission package deliveries through fiscal year 2012: 
8. 

Source: GAO analysis of Navy data. 

[End of figure] 

In 2007, the Navy anticipated that a total of 16 mission packages 
would be delivered by 2012 with all three types of mission packages 
reaching their full configuration by that date. In recent years, the 
Navy has deferred planned procurements of LCS mission packages due, in 
part, to developmental challenges facing mission systems. Under the 
Navy's 2010 plan, the Navy plans to acquire 8 mission packages by 2012 
with no mission package having achieved its full configuration of 
capabilities. 

To date, the Navy has taken delivery of five partial mission packages--
two surface warfare, two mine countermeasures, and one anti-submarine 
warfare. The Navy delayed procurement of the fiscal year 2009 funded 
mine countermeasures package due to technical issues and resulting 
operational testing delays. Delivery of the two partial surface 
warfare mission packages occurred in July 2008 and March 2010, 
respectively. The first surface warfare package included two 
engineering development models for the 30-millimeter gun, but did not 
include the launcher or missiles for the Non-Line-of-Sight Launch 
System. The second surface warfare mission package included the 30-
millimeter gun module and the launcher component--but no missiles--for 
the Non-Line-of-Sight Launch System. 

Because of planned configuration changes to the anti-submarine warfare 
mission package, the Navy does not plan to buy additional quantities 
of this package until the new configuration is settled. According to 
Navy officials, recent warfighting analyses showed that the baseline 
anti-submarine warfare package did not contribute significantly to the 
anti-submarine warfare mission. The first package will undergo 
developmental testing, with results used to inform decisions on future 
configuration. The Navy conducted end-to-end testing on the first anti-
submarine warfare mission package in April 2009 and plans to continue 
developmental testing in fiscal year 2010. During the 2009 end-to-end 
test, the Navy found that the unmanned surface vehicle and its 
associated sensors will require reliability and interface improvements 
to support sustained undersea warfare. 

Mission Package Procurement Delays Could Disrupt Program Plans for 
Simultaneously Acquiring Seaframes and Mission Packages and Will Limit 
the Ships' Utility During Initial Deployments: 

While the Navy now plans to purchase 17 ships and 13 mission packages 
between fiscal year 2011 and fiscal year 2015, developmental delays 
facing key mission package systems have positioned the Navy to acquire 
significant numbers of seaframes before mission packages are proven. 
This development represents a reversal for the LCS program. In prior 
years, the Navy deferred purchase of mission packages to account for 
delays in constructing seaframes. However, as key mission package 
systems entered operational testing--producing less than successful 
results--and seaframe design and construction progressed, planned 
alignment of seaframe and mission package purchases suffered further 
disruption. 

Until mission package performance is proven, the Navy risks investing 
in a fleet of ships that does not deliver its promised capability. As 
the Navy stated, the underlying strength of the LCS lies in its 
innovative design--interchangeable mission equipment that allows the 
ship to be used for different missions. Fundamental to this approach 
is the capability to rapidly install interchangeable mission packages 
into the seaframe. Absent significant capability within its mission 
packages, seaframe functionality is largely constrained to self-
defense as opposed to mission-related tasks. 

In addition, the Navy has deployed LCS 1 earlier than originally 
scheduled and is evaluating a similar course for LCS 2. For these 
deployments, the Navy is employing hybrid--limited and incomplete-- 
versions of mission packages. The package on LCS 1 includes one 
mission system (two 30-millimeter guns), the armed variant of the MH-
60S helicopter, and the maritime security module. According to Navy 
officials, deploying LCS 1 two years ahead of schedule allows them to 
incorporate lessons that can only be learned in a deployment setting. 
LCS 1 will conduct operations where it will be able to take advantage 
of its speed and will be equipped with an incomplete version of the 
surface warfare package. Because the surface warfare mission package 
is incomplete, the range of missions LCS 1 is capable of executing 
will be constrained during its initial deployment. 

Furthermore, the surface warfare mission package onboard LCS 1 has yet 
to be fully integrated with the seaframe and lacks key capabilities 
necessary to defeat surface threats. For example, the 30-millimeter 
guns have undergone testing with the LCS 1 seaframe, but have yet to 
be fully integrated with the ship's combat suite. Also, while the guns 
provide a close range self-defense capability, Navy officials report 
LCS 1 is currently unable to automatically transfer tracking data from 
the ship's radar to the 30-millimeter guns. In addition, because of 
excess MH-60R helicopter demands, the Navy has assigned the armed helo 
variant of the MH-60S helicopter to LCS 1 for its maiden deployment. 
Although this MH-60S variant carries air-to-surface missiles and crew- 
served side machine guns (among other offensive capabilities), it does 
not have the multi-mode radar found on the MH-60R--a shortfall that 
could constrain LCS 1's ability to execute surface warfare missions. 

Mission Package Delays Coupled with Early Deployment of LCS Seaframes 
Require Deferral of Key Test Events: 

Neither LCS seaframe design--nor any of the three LCS mission 
packages--has completed initial operational test and evaluation. 
Normally after a lead ship completes its post-delivery maintenance 
period, initial operational test and evaluation occurs--generally 
planned for within 1 year of ship delivery. In the case of LCS, 
initial operational test and evaluation will encompass both seaframes 
and mission packages. Under the program's 2008 Test and Evaluation 
Master Plan, LCS 1 was to begin operational testing with the initial 
systems in the mine countermeasures mission package in the second 
quarter of fiscal year 2010. The mission systems that were to be 
tested included the Remote Minehunting System, the MH-60S helicopter 
(mine countermeasures variant), AN/AQS-20A mine detecting sonar, 
Unmanned Surface Vehicle with Unmanned Surface Sweep System, Airborne 
Mine Neutralization System, and Airborne Laser Mine Detection System. 
However, as noted above, these mission systems have experienced 
developmental challenges and none are ready to be tested on the 
seaframe. The Navy has since postponed operational testing of the mine 
countermeasures mission package to the second quarter of fiscal year 
2013, now planned to occur onboard LCS 2. 

In addition, early deployments of seaframes postpone their 
availability to complete planned testing events. For example, although 
LCS 1 deployed 2 years earlier than scheduled, its first operational 
testing event with a mission package was delayed by 3 years.[Footnote 
9] The Navy faces several risks in deploying the LCS 1 before it has 
completed initial operational test and evaluation. For example, 
Department of Defense testing officials stated that because LCS 1 and 
LCS 2 are such revolutionary designs, the lead ships should be put 
through a rigorous testing and evaluation process--in a controlled 
environment--to best understand their capabilities and limitations. 
Additionally, the testing officials reported that the ship's 
maintenance and support strategy was of significant concern to them. 
According to the testing officials, LCS--more so than other ships--
will have to rely heavily on shore-based support, which is an unproven 
concept. 

Incomplete Cost Analyses in the LCS Program Have Undermined Program 
Progress: 

The Navy entered contract negotiations in 2009 for fiscal year 2010 
funded seaframes with an incomplete understanding of LCS program 
costs. These contract negotiations proved unsuccessful, prompting the 
Navy to revise its acquisition strategy for the program. The 
contractors' proposals for construction of the next three ships 
exceeded the approximate $1.4 billion in funds the Navy had allocated 
in its fiscal year 2010 budget. In response, the Navy revised its 
strategy to construct one seaframe design instead of two for fiscal 
year 2010 ships and beyond in an effort to improve affordability. Navy 
cost analyses completed prior to the failed negotiations in 2009 lack 
several characteristics essential to a high quality cost estimate. 
These characteristics include the completion of sensitivity and 
uncertainty analyses and an independent review of the cost estimate. 
The Navy plans to complete a more comprehensive cost estimate before 
award of additional ship contracts in 2010. 

Unsuccessful Contract Negotiations in Late 2009 Prompted the Navy to 
Restructure Its Acquisition Strategy for the LCS Program: 

The Navy budgeted $1.38 billion in fiscal year 2010 for construction 
of three ships (LCS 5, LCS 6, and LCS 7) at a cost of $460 million 
each. The Navy planned to award construction contracts for these ships 
in November 2009, to include the purchase of at least one ship of each 
LCS seaframe design. Navy officials were confident they had gained 
sufficient knowledge from construction activities associated with the 
first four seaframes to support a cost efficient, dual design strategy 
going forward. As part of this strategy, the Navy solicited proposals 
from each of the LCS prime contractors for construction of up to three 
ships on a fixed-price basis. The industry teams returned their 
proposals in August 2009 and, according to Navy officials, included 
pricing significantly above the Navy's expectations. Lockheed Martin 
and General Dynamics officials stated that the fixed-price terms the 
Navy sought prompted a forthright assessment of remaining program 
risks--including technical, design, and funding uncertainties--and 
subsequent pricing of that risk in their proposals. 

Due to the sharp differences between the Navy cost expectations and 
the contractor proposals with respect to LCS pricing, the Navy 
concluded the negotiations without awarding contracts for any new 
ships. Further, Navy leadership stated it had no reasonable basis to 
find that the LCS program would be executable going forward under the 
current acquisition strategy, which prompted the Navy to outline a new 
acquisition strategy in September 2009 aimed at improving program 
affordability by selecting one design for the fiscal year 2010 ships 
and beyond. Under the terms of the new strategy, the Navy will 
contract with a single source on a fixed-price basis for up to 10 
ships (2 ships awarded per year) through fiscal year 2014. The 
strategy also outlines plans to issue a second solicitation for up to 
another 5 ships to be constructed at a separate yard with awards 
planned between fiscal years 2012 and 2014. The first source will 
provide the combat systems for the 5 additional ships constructed by 
the second shipyard. Navy officials stated that the new acquisition 
approach will produce cost benefits attributable to near-term 
competitive pricing pressures between the two current LCS shipbuilding 
teams, economic order quantity purchases of key materials, 
efficiencies associated with potentially moving to a single, common 
combat system, and significantly reduced total ownership costs for the 
Navy. 

While the new acquisition strategy for the LCS program promises 
improved affordability, the Navy's failure to recognize the 
unexecutable nature of the previous strategy--before engaging in the 
costly, time consuming process of requesting proposals--has not come 
without penalty. Contract awards for LCS 5, LCS 6, and LCS 7 have been 
delayed by at least 9 months, subsequently disrupting planned 
workloads--and potentially increasing the overhead costs charged to 
existing Navy contracts--in the LCS shipyards. Most importantly, 
however, the unsuccessful negotiations and revised strategy represent 
the latest delay to delivery of promised capabilities to the fleet, 
which is depending heavily on LCS to take over several current and 
future missions. Figure 5 highlights the resequencing of key LCS 
program events following the revised acquisition strategy, which 
delayed contract awards for the fiscal year 2010 funded ships. 

Figure 5: Schedule of Key Near-term Events as Outlined in the LCS 
Program's 2009 and 2010 Acquisition Strategies: 

[Refer to PDF for image: time line] 

2009 plan: 

November 2009: 
Contract awards for LCS 5, LCS 6,and LCS 7. 

August 2010: 
LCS 5 construction start. 

October 2010: 
LCS 6 construction start. 

December 2010: 
LCS 7 construction start. 

June 2011: 
Milestone B. 

April 2013: 
LCS 5 delivery. 

June 2013: 
LCS 6 delivery. 

August 2013: 
LCS 7 delivery. 

2010 plan: 

August/September 2010: 
Milestone B and contract awards for LCS 5 and LCS 6. 

November 2010: 
Contract awards for LCS 7 and LCS 8. 

February 2011: 
LCS 5 construction start. 

April 2011: 
LCS 6 construction start. 

August 2011: 
LCS 7 construction start. 

October 2013: 
LCS 5 delivery. 

December 2013: 
LCS 6 delivery. 

April 2014: 
LCS 7 delivery. 

Source: GAO analysis. 

[End of figure] 

Under the new acquisition strategy, the LCS program must complete a 
major program review (milestone B) before award of fiscal year 2010 
ship contracts. The previous acquisition strategy deferred this review 
until June 2011--after award of the three fiscal year 2010 ship 
contracts. While holding the milestone B decision earlier than planned 
is an improvement, most ship programs align milestone B with the 
decision to authorize the start of detail design--a decision that 
dates back to 2004 in the LCS program. 

In support of the milestone B review, Department of Defense policy 
requires the Navy to provide its own cost estimate for the program. 
[Footnote 10] In response, the Navy plans to submit a program life 
cycle cost estimate, which will be completed by Naval Sea Systems 
Command's Cost Engineering and Industrial Analysis division. In 
addition, federal statute requires that for major defense acquisition 
programs (including LCS), an independent estimate of life cycle costs 
be prepared and provided to the milestone decision authority before 
the approval is given to proceed with Engineering and Manufacturing 
Development.[Footnote 11] The responsibility for the independent cost 
estimate is assigned to the Director, Cost Assessment and Program 
Evaluation within the Department of Defense. 

Navy Cost Analyses Completed Ahead of Contract Negotiations in 2009 
Lacked Key Elements Needed to Ensure High Quality: 

Because the Department of Defense has not yet completed a milestone B 
review of the LCS program--to include development and evaluation of a 
comprehensive Navy cost estimate and independent cost estimate--the 
typical mechanisms and processes for assessing program affordability 
were not carried out ahead of the Navy's 2009 contract negotiations, 
which turned out to be unsuccessful. Instead, Navy officials reported 
their cost expectations for fiscal year 2010 funded seaframes were 
largely framed by the pricing agreements reached with Lockheed Martin 
and General Dynamics for LCS 3 and LCS 4 construction, respectively. 
Apart from this data, the Navy had few alternative sources available 
that forecast LCS program costs. Most prominent of these sources was 
analysis completed in June 2009 as part of the LCS total ownership 
cost baseline estimate.[Footnote 12] The Navy chartered this estimate 
to investigate ways it could alter the LCS seaframe designs to reduce 
its total ownership cost in the program. The estimate reflected the 
life cycle costs of the proposed two-design, 55 ship LCS class--not 
including mission packages--and was divided into sections covering (1) 
research, development, testing, and evaluation; (2) procurement; and 
(3) operations and support costs. The estimate also updated a set of 
previous Navy and Department of Defense estimates for LCS 3 and LCS 4 
that were completed in November 2008 in support of the program's 
milestone A-Prime review[Footnote 13] and March and May 2009 contract 
awards for those ships. 

Our analysis of the procurement section of the LCS total ownership 
cost baseline found the estimate lacks several characteristics 
essential to a high-quality cost estimate.[Footnote 14] To complete 
this analysis, we compared the Navy's estimate to best practices 
criteria, as outlined in GAO's Cost Estimating and Assessment Guide 
and presented in appendix II.[Footnote 15] These criteria characterize 
high-quality cost estimates as those that are credible, comprehensive, 
well-documented, and accurate. Table 7 highlights the key findings of 
our analysis. 

Table 7: Extent to Which the Navy's Total Ownership Cost Baseline 
Estimate for LCS Procurement Was Well-Documented, Comprehensive, 
Accurate, and Credible: 

Four characteristics of high-quality cost estimates and 12 key 
steps[A]: 

Well-documented: Partially met. 

Well-documented: Define the estimate's purpose (Step 1);
Mostly met. 

Well-documented: Define the program characteristics (Step 3); 
Partially met. 

Well-documented: Identify ground rules and assumptions (Step 5); 
Minimally met. 

Well-documented: Obtain the data (Step 6); 
Mostly met. 

Well-documented: Document the estimate (Step 10); 
Minimally met. 

Well-documented: Present the estimate to management for approval (Step 
11); 
Partially met. 

Comprehensive: Partially met. 

Comprehensive: Develop the estimating plan (Step 2); 
Partially met. 

Comprehensive: Determine the estimating approach (Step 4); 
Mostly met. 

Comprehensive: Identify ground rules and assumptions (Step 5); 
Minimally met. 

Accurate: Partially met. 

Accurate: Develop the point estimate and compare to an independent 
cost estimate (Step 7); 
Partially met. 

Accurate: Update the estimate to reflect actual costs and changes 
(Step 12); 
Mostly met. 

Credible: Minimally met. 

Credible: Develop the point estimate and compare to an independent 
cost estimate (Step 7); 
Partially met. 

Credible: Conduct a sensitivity analysis (Step 8); 
Minimally met. 

Credible: Conduct risk and uncertainty analysis (Step 9); 
Not met. 

Source: GAO analysis of Navy data. 

[A] These 12 steps are outlined in additional detail in appendix II. 

Note: The ratings used in this analysis are as follows: "Not met" 
means that the Navy did not provide evidence that satisfied the 
criterion; "Minimally met" means that the Navy provided evidence that 
satisfies a small portion of the criterion; "Partially met" means that 
the Navy provided evidence that satisfies about half of the criterion; 
"Mostly met" means that the Navy provided evidence that satisfies a 
large portion of the criterion; "Fully met" means that the Navy 
provided complete evidence that satisfies the entire criterion. 

[End of table] 

In developing the LCS total ownership cost baseline estimate, the Navy 
excluded certain key costs, used overly optimistic assumptions, 
inadequately documented its analyses, and did not perform analyses 
needed to identify levels of confidence and certainty in the cost 
estimate. As a result of these weaknesses, the LCS program total 
ownership cost baseline estimate is not reliable for decision making. 

Well-documented: 

Cost estimates are well-documented when they can be easily repeated or 
updated and can be traced to original sources through auditing. 
Rigorous documentation increases the credibility of an estimate and 
helps support an organization's decision making process. The 
documentation should explicitly identify the primary methods, 
calculations, results, rationales, assumptions, and sources of the 
data used to generate each cost element. All the steps involved in 
developing the estimate should be documented so that a cost analyst 
unfamiliar with the program can recreate the estimate with the same 
result. 

The level of documentation detailing the Navy's LCS procurement cost 
model is insufficient for someone unfamiliar with the program to 
easily recreate the estimate. The level of detail in the total 
ownership cost estimate does not reflect the full level of detail 
available for the LCS program, leaving managers with incomplete 
information on which to base program decisions. The Navy documented 
the LCS technical baseline in a July 2006 report--the Cost Analysis 
Requirements Description--describing program requirements, purpose, 
technical characteristics, development plan, acquisition strategy, 
operational plan, and risks. Navy estimators, however, did not rely 
upon this document in developing their estimate because the Cost 
Analysis Requirements Document is out of date and does not reflect 
current program approaches, seaframe configurations, and developmental 
challenges. Alternatively, Navy cost estimators relied on the current 
LCS build specification, ship weight reports, and known design changes 
to inform their understanding of the ships' technical characteristics. 
Since then, the Navy reports it has updated the LCS Cost Analysis 
Requirements Document in anticipation of the program's milestone B 
review. 

In addition, the Navy divided the procurement content of its estimate 
into cost categories for plans, basic construction, change orders, 
government furnished equipment, other items, and outfitting and post- 
delivery. For most of these elements, Navy cost estimators relied on 
historical data and subject matter experts as sources of data. For the 
basic construction cost element, the Navy relied primarily on 
contractor cost proposals dating to May 2008 and November 2008. 
According to the Navy, the proposal data provided an accurate starting 
point for basic construction cost modeling because industry teams were 
instructed to base their proposals on their actual labor and material 
costs and/or estimates for lead ships. The Navy reports it traced the 
proposal data to November 2008 cost performance reports submitted by 
the contractors. The Navy then adjusted the proposals' estimates for 
labor hours and materials to reflect, for instance, known changes in 
pricing. 

However, as we recently reported, earned value management systems in 
each of the LCS shipyards do not meet Defense Contract Management 
Agency requirements for validation.[Footnote 16] Consequently, cost 
and schedule data reported by the prime contractors cannot be 
considered fully reliable.[Footnote 17] The LCS cost estimate does not 
include any evidence that the Navy adjusted its basic construction 
cost estimates to account for this uncertainty. 

Comprehensive: 

Estimates are comprehensive when they contain a level of detail that 
ensures that all pertinent costs are included and no costs are double- 
counted. It is important to ensure the completeness, consistency, and 
realism of the information contained in the cost estimate. 

The Navy chartered a working group at the outset of the total 
ownership cost baseline estimate. Group members included 
representatives from the Naval Center for Cost Analysis; Naval Sea 
Systems Command's Ship Engineering and Logistics, Maintenance, and 
Industrial Operations directorates; Chief of Naval Operations' Surface 
Warfare directorate, Space and Naval Warfare Systems Command; Program 
Executive Office for Integrated Warfare Systems; and the RAND 
Corporation. This group developed a study plan for the LCS estimate 
that identified goals, set deadlines for completing key tasks, and 
outlined required resources. In addition, the group met biweekly and 
provided cross-checks and verification to the Navy cost team's 
estimating assumptions and results. Upon completion of the procurement 
cost analysis, Navy estimators briefed out results to the Commander, 
Naval Sea Systems Command, in June 2009. 

Further, our analysis found that the Navy's LCS estimate identifies 
ground rules and assumptions from which the estimate is derived. 
However, it does not identify potential effects that changes to key 
assumptions--such as allocation of ships between contractors and 
changes to the technical baseline of the ship--could have upon the 
cost estimate. Also, the estimate does not identify how budget 
constraints could affect program plans or the potential effects that 
continued design refinements to the lead ships may have upon 
construction cost outcomes of follow-on ships. 

In addition, the Navy did not complete evaluations of risk 
distributions for its cost estimating assumptions. Alternatively, cost 
estimators relied on discussions with ship designers, engineers, and 
technicians from the Navy and contractors to identify the scope of 
certain procurement cost elements. Navy cost analysts report they will 
complete evaluations of risk distributions for assumptions used in the 
LCS program life cycle cost estimate being developed for the milestone 
B review. 

The Navy also relied upon industry-provided work breakdown structures 
for LCS 1, LCS 2, and LCS 3--that it then mapped to its own ship work 
breakdown structure--to identify the work tasks necessary to deliver 
LCS seaframes. Following completion of the total ownership cost 
estimate, the Navy received the LCS 4 work breakdown structure from 
industry, which it will use in developing the milestone B program life 
cycle cost estimate. 

Accurate: 

Estimates are accurate when they are based on an assessment of the 
costs most likely to be incurred. Therefore, when costs change, best 
practices require that the estimate be updated to reflect changes in 
technical or program assumptions and new phases or milestones. 

The total ownership cost baseline estimate discretely estimated LCS 3 
and LCS 4 basic construction costs separate from the cost performance 
outcomes being realized on LCS 1 and LCS 2. This approach was used 
because, according to Navy cost estimators, distinguishing 
nonrecurring work on the first two ships from work that would recur on 
future ships--a necessary step for deriving follow-on ship costs--was 
too challenging an undertaking given the major design changes and 
construction rework that occurred on the lead ships. Further, LCS 3 
and LCS 4 represented a slightly different technical baseline from LCS 
1 and LCS 2, leading the Navy to judge it more appropriate to use the 
initial follow-on ships as the basis of estimates for future ships. 

After developing their cost estimates for LCS 3 and LCS 4, the Navy 
estimators applied a 94 percent learning curve to the basic 
construction cost elements to arrive at construction estimates for 
future ships of each design. However, because Austal USA and Marinette 
Marine have only recently begun building complex Navy ships such as 
LCS, the historical data available to Navy cost analysts for deriving 
an accurate learning curve was constrained. As a result, the Navy 
developed its LCS learning curve based primarily on construction 
outcomes for alternative vessels and, in some cases, alternative 
shipyards including (1) 14 Coast Guard buoy tenders built at Marinette 
Marine, (2) 13 Cyclone-class coastal patrol ships built at Bollinger 
Shipyards, and (3) 10 patrol craft built at Austal facilities in 
Australia. According to the Navy, this data produced a widely varied 
range of potential LCS learning curves, which contributed to the 
Navy's decision to arrive at a curve for LCS that was toward the high 
end of the range (i.e., more conservative). 

Navy cost estimators stated that their current work to develop a 
program life cycle cost estimate for LCS precludes future updates to 
the total ownership cost baseline. Additional cost estimates post- 
milestone B in the program will rely on the program life cycle cost 
estimate--and corresponding independent cost analysis--as starting 
points. 

Credible: 

Estimates are credible when they have been cross-checked with an 
independent cost estimate and when a level of uncertainty associated 
with the estimate has been identified. An independent cost estimate 
provides the estimator with an unbiased test of the reasonableness of 
the estimate and reduces the cost risk associated with the project by 
demonstrating that alternative methods generate similar results. 

Our analysis found that the total ownership cost baseline was not 
compared to an independent cost estimate. Comparing against an 
independent cost estimate provides an unbiased test of whether a 
program office or service-level cost estimate is reasonable. It is 
also used to identify risks related to budget shortfalls or excesses. 
According to Navy officials, the total ownership cost estimate was not 
tied to a major program milestone. As such, development of a 
corresponding independent cost estimate was not required. The Navy 
did, however, complete peer reviews, engage in discussions with 
program officials for classes of ships used as analogies in the 
estimate, and utilize expert opinion and work groups to cross-check 
for accuracy and omissions. 

In addition, we found the Navy did not complete sensitivity or 
uncertainty analyses for LCS procurement cost elements. A sensitivity 
analysis provides a range of costs that span a best and worst case 
spread. In general, it is better for decision makers to know the range 
of potential costs that surround a point estimate and the reasons 
behind what drives that range than to just have a point estimate from 
which to make decisions. Sensitivity analysis can provide a clear 
picture of both the high and low costs that can be expected, with 
discrete reasons for what drives them. Uncertainty analysis provides 
the basis for adjusting estimates to reflect unknown facts and 
circumstances that could affect costs, and it identifies risk 
associated with the cost estimate. In order to inform decision makers 
about the likelihood of success, an uncertainty analysis should be 
performed for every cost estimate, as an organization varies the 
effects of multiple elements on costs, and as a result, can express a 
level of confidence in the point estimate. Further, because numerous 
risks can influence the estimate, they should be examined for their 
sources of uncertainty and potential effect, and they should be 
modeled to determine how they can affect the uncertainty of the cost 
estimate. 

Navy cost estimators identified major procurement cost drivers in the 
program, but do not plan to complete sensitivity or uncertainty 
analyses for those drivers until shortly before milestone B. Navy 
officials cited the change to the program's acquisition strategy 
shortly following completion of the total ownership cost estimate as 
their rationale for deferring these analyses. Without sensitivity and 
uncertainty analyses, the Navy cannot fully account for the effect 
various risks can have on the overall total ownership cost estimate. 

Conclusions: 

The Navy is counting on LCS as its primary means to defeat sea mines, 
counter low-end surface threats, and prosecute enemy submarines in 
coastal waters. Further, LCS--with its planned 55 seaframes and 64 
mission packages--represents a large component of the Navy's future 
surface fleet, making it key to the Navy's ability to maintain global 
presence. 

However, the Navy's ability to deliver a capable, affordable LCS 
remains unproven. Staying within budget will require the Navy to 
achieve design stability before beginning construction of future 
ships. Moreover, LCS testing remains in its infancy, as the first 
operational testing event involving a seaframe and partial mission 
package has been deferred to fiscal year 2013. In addition, the Navy 
now expects individual mission package systems to remain in 
development through 2017. Until LCS capabilities are demonstrated 
through operational testing, the Navy cannot be certain that the 
seaframes and mission packages it is buying will be able to execute 
the missions that the fleet plans to assign to LCS vessels. 

Further, decisions to deploy the lead ship early and complete 
previously unplanned maintenance periods have rendered current program 
test plans obsolete. Testing delays to key mission package elements-- 
followed by prudent Navy decisions to defer new procurements of these 
systems--have created an imbalance between seaframe and mission 
package acquisition plans. For example, the Navy now plans to fund 
construction of 17 seaframes between fiscal years 2011 and 2015--
whereas only 13 mission packages will be purchased during that time. 
This situation could be exacerbated should the Navy encounter 
additional difficulties resolving the substantial technical issues 
facing the mine countermeasures package. 

In addition, although the Navy has emphasized the importance of 
affordability to successful outcomes in the LCS program, it continues 
to make key investment decisions without a clear understanding of 
program costs. For LCS, the Navy determined it appropriate to award 
contracts for four ships and conduct negotiations for three more 
without completing a detailed, programwide, independent cost estimate--
a strategy that contributed to less than optimal results. High-quality 
cost estimates are well-documented, comprehensive, accurate, and 
credible--characteristics that are not fully embodied in the Navy's 
most recent cost estimate for LCS procurement. Shortfalls include the 
lack of sensitivity and uncertainty analyses and an independent review 
of the cost estimate. Continuing technical challenges and design 
changes on initial seaframes further complicate the Navy's efforts to 
identify future LCS costs. Until these issues are resolved, and a high-
quality estimate of program costs is developed, the Navy cannot be 
confident that the LCS capabilities it promises can be attained at 
prices it is willing to pay. 

Recommendations for Executive Action: 

We recommend the Secretary of Defense take the following four actions: 

To attain the level of knowledge needed to retire design risk and 
reduce construction disruptions, ensure changes identified in building 
and testing the first four ships are incorporated into the basic and 
functional design by the start of construction for future LCS 
seaframes. 

To provide a meaningful framework for evaluating seaframe and mission 
package performance, update the LCS test and evaluation master plan to 
(1) account for any early deployments of seaframes and the significant 
developmental challenges faced by key mission package systems and (2) 
identify alternative approaches for completing seaframe and mission 
package initial operational test and evaluation. 

To safeguard against excess quantities of ships and mission packages 
being purchased before their combined capabilities are demonstrated, 
update the LCS acquisition strategy to account for operational testing 
delays in the program and resequence planned purchases of ships and 
mission packages, as appropriate. 

To provide a sound basis for future LCS investment decisions, ensure 
that future LCS cost estimates--including the program life cycle cost 
estimate currently planned for milestone B--are well-documented, 
comprehensive, accurate, and credible. 

Agency Comments and Our Evaluation: 

The Department of Defense agreed with all of our recommendations. 
However, in responding to our recommendation to ensure changes 
identified in building and testing the first four ships are 
incorporated into the basic and functional design by the start of 
construction for future LCS seaframes, the department stated that the 
program can use existing ship and class design services contracts to 
execute additional changes after contract award. As our prior work has 
shown, however, this practice has been tried before in Navy 
shipbuilding programs and has consistently contributed to ship 
deliveries that are over cost and behind schedule. As such, we would 
expect the Navy to set the bar extremely high for making design 
changes to ships that are already under construction. 

The department's written comments can be found in appendix III of this 
report. The department also provided technical comments, which were 
incorporated into the report as appropriate. 

We are sending copies of this report to interested congressional 
committees, the Secretary of Defense, and the Secretary of the Navy. 
The report is also available at no charge on the GAO Web site at 
[hyperlink, http://www.gao.gov]. 

If you or your staff have any questions about this report, please 
contact me at (202) 512-4841 or martinb@gao.gov. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. GAO staff who made major 
contributions to this report are listed in appendix IV. 

Signed by: 

Belva M. Martin: 
Acting Director: 
Acquisition and Sourcing Management: 

[End of section] 

Appendix I: Scope and Methodology: 

This report evaluates Littoral Combat Ship (LCS) planning and 
implementation efforts. Specifically, we (1) identified technical, 
design, and construction challenges to completing the first four 
seaframes within current cost and schedule estimates, (2) assessed the 
Navy's progress developing and fielding mission packages, and (3) 
evaluated the quality of recent Navy cost analyses for seaframes and 
their effect on program progress. 

To identify challenges in completing the first four seaframes, we 
analyzed Department of Defense and contractor-generated documents that 
addressed technical challenges and cost and schedule performance for 
LCS seaframes including Navy test reports; Navy Supervisor of 
Shipbuilding reports; monthly contract performance reports; integrated 
baseline reviews; reports to Congress; sea trial reports for the first 
two ships; and construction progress briefings. To identify design 
changes and to understand the impact of these changes to the 
construction processes for seaframes, we reviewed LCS contracts and 
change orders; program schedules for LCS 3 and LCS 4; monthly contract 
performance reports; weekly Supervisor of Shipbuilding reports; and 
quarterly ship production progress conference briefings. We also 
reviewed information from contractors outlining process improvements 
and capital investments at each of the LCS shipyards aimed at 
increasing capability and capacity needed to support efficient 
construction of LCS seaframes. To further corroborate documentary 
evidence and gather additional information in support of our review, 
we conducted interviews with relevant Navy and industry officials 
responsible for managing the design and construction of LCS seaframes, 
such as the LCS Seaframe program office; Program Executive Office, 
Ships; Supervisor of Shipbuilding officials; Lockheed Martin and 
General Dynamics (LCS prime contractors); Marinette Marine and Austal 
USA (LCS shipbuilders); and MTU (LCS 2 and LCS 4 diesel engine 
vendor). We also held discussions with LCS technical authorities, 
testing agents, and requirements officers from Naval Sea Systems 
Command's Ship Engineering directorate; Director, Operational Test and 
Evaluation; American Bureau of Shipping; Commander, Navy Operational 
Test and Evaluation Force; Office of the Chief of Naval Operations' 
Surface Warfare directorate; and Naval Surface Warfare Center-Panama 
City division. 

To assess the Navy's progress developing and fielding mission 
packages, we analyzed documents outlining LCS mission package 
development plans and performance including program schedules, test 
reports, and budget submissions. In order to evaluate the realism of 
mission package testing and procurement plans, we analyzed and 
compared mission package development schedules and test reports 
against LCS seaframe construction, delivery, and testing schedules. To 
further corroborate documentary evidence and gather additional 
information in support of our review, we held discussions with Navy 
program offices and Department of Defense agencies responsible for 
acquiring and testing key LCS mission systems including the Program 
Executive Office for Littoral and Mine Warfare; LCS Mission Modules 
program office; Unmanned Maritime Vehicles program office; and the 
Mine Warfare program office; Director, Operational Test and 
Evaluation; Commander, Operational Test and Evaluation Force, Navy. To 
gather additional information on remaining risks to mission package 
development and integration, we interviewed relevant Navy officials 
from the MH-60R Helicopter program office, MH-60S Helicopter program 
office, Navy and Marine Corps Tactical Multi-Mission Unmanned Aerial 
Systems program office, and Naval Surface Warfare Center-Panama City 
division. 

To evaluate the quality of recent Navy cost analyses for LCS 
seaframes, we compared the Navy's total ownership cost baseline 
estimate for LCS procurement to best practices criteria as outlined in 
GAO's Cost Estimating and Assessment Guide. These criteria 
characterize high-quality cost estimates as those that are credible, 
comprehensive, well-documented, and accurate. To supplement our 
analysis and gain additional visibility into the Navy's process for 
developing its LCS estimate, we interviewed officials from Naval Sea 
Systems Command's Cost Engineering and Analysis directorate; LCS 
Seaframe program officials; and the Director, Cost Assessment and 
Program Evaluation. 

We conducted this performance audit from July 2009 to August 2010 in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: GAO Methodology Used to Perform Cost Estimating Analysis: 

To evaluate estimated Littoral Combat Ship (LCS) seaframe procurement 
costs as outlined in the Navy's total ownership cost baseline (August 
2009), GAO employed criteria from our Cost Estimating and Assessment 
Guide.[Footnote 18] In developing this guide, GAO cost experts 
identified 12 steps consistently applied by cost-estimating 
organizations throughout the federal government and industry and 
considered best practices for the development of reliable cost 
estimates. These 12 steps--and their related measures--are identified 
below. 

Step One: Define the Estimate's Purpose: 

* Are the purpose and scope of the cost estimate defined and 
documented? 

a. Is the level of detail the estimate is conducted at consistent with 
the level of detail available for the program? 

b. Have all applicable costs been estimated, including life cycle 
costs? 

c. Is the scope of the estimate defined and documented? 

Step Two: Develop the Estimating Plan: 

* Did the team develop a written study plan that: 

a. Determined the estimating team's composition and whether the team 
is from a centralized office; 

b. Identified which subject matter experts the team will rely on for 
information; 

c. Outlined the estimating approach (see Step four); 

d. Identified a master schedule for completing the estimate that 
provided adequate time to do the work. 

Step Three: Define the Program Characteristics: 

* Is there a documented technical baseline description that is 
contained in a single document? If yes, does it include the following: 

a. What the program is supposed to do--requirements; 

b. How the program will fulfill its mission--purpose; 

c. What it will look like--technical characteristics; 

d. Where and how the program will be built--development plan; 

e. How the program will be acquired--acquisition strategy; 

f. How the program will operate--operational plan; 

g. Which characteristics affect cost the most--risk. 

Step Four: Determine the Estimating Structure: 

* Is there a defined work breakdown structure (WBS) and/or cost 
element structure? 

a. Is the WBS product-oriented, traceable to the statement of work, 
and at an appropriate level of detail to ensure that cost elements are 
neither omitted nor double-counted? 

b. Is the WBS standardized so that cost data can be collected and used 
for estimating future programs? 

c. Does the cost estimate WBS match the schedule and earned value 
management (EVM) WBS? 

d. Is the WBS updated as the program becomes better defined and to 
reflect changes as they occur? 

e. Is there a WBS dictionary that defines what is included in each 
element and how it relates to others in the hierarchy? 

Step Five: Identify Ground Rules and Assumptions: 

* Are there defined ground rules and assumptions that document the 
rationale and any historical data to back up any claims? 

a. Have risks associated with any assumptions been identified and 
traced to specific WBS elements? 

b. Have budget constraints, as well as the effect of delaying program 
content, been defined? 

c. Have inflation indices and their source been identified? 

d. If the program depends on a participating agency or agency's 
equipment have the effects of these assumptions not holding been 
identified? 

e. Have items excluded from the estimate been documented and explained? 

f. If technology maturity has been assumed, does the estimate address 
the effect of the assumption's failure on cost and schedule? 

g. Did cost estimators meet with technical staff to determine risk 
distributions for all assumptions so they could use this information 
for sensitivity and uncertainty analysis? 

Step Six: Obtain the Data: 

* Was the data gathered from valid historical actual cost, schedule, 
and program and technical sources? 

a. Do the data apply to the program being estimated and have they been 
analyzed for cost drivers? 

b. Have the data been collected from primary sources and adequately 
documented as to the source, content, time, units, an assessment of 
the accuracy of the data and reliability, and any circumstances 
affecting the data? 

c. Are data continually collected and stored for future use? 

d. Did analysts meet with the data sources to better understand the 
program and ask them about the data? 

e. Were the data reviewed and benchmarked against historical data for 
reasonableness? 

f. Were the data analyzed using scatterplots and descriptive 
statistics and were they normalized to account for cost, sizing units, 
etc. so they are consistent for comparisons? 

Step Seven: Develop the Point Estimate and Compare It to an 
Independent Cost Estimate: 

* Did the cost estimator consider various cost estimating methods like 
analogy, engineering build up, parametric, extrapolating from actual 
costs, and expert opinion (if none of the other methods can be used)? 

a. If the parametric method was used as the estimating method, were 
the cost estimating relationships (CER) statistics examined to 
determine its quality? 

b. Were learning curves used if there was much manual labor associated 
with production and were production rate and breaks in production 
considered? 

c. Was the point estimate developed by aggregating the WBS cost 
estimates by one of the cost estimating methods? 

d. Were results checked for accuracy, double-counting, and omissions 
and were validated with cross checks and independent cost estimates? 

e. If software is a major component of the cost estimate were software 
estimating best practices from Chapter 12 of the Guide addressed? 

Step Eight: Conduct a Sensitivity Analysis: 

* Did the cost estimate include a sensitivity analysis that, using a 
range of possible costs, identified the effects of changing key cost 
driver assumptions or factors? Were the following steps taken: 

a. Key cost drivers were identified; 

b. Cost elements representing the highest percentage of cost were 
determined and their parameters and assumptions were examined; 

c. The total cost was reestimated by varying each parameter between 
its minimum and maximum range; 

d. Results were documented and the reestimate repeated for each 
parameter that was a key cost driver; 

e. Outcomes were evaluated for parameters most sensitive to change. 

Step Nine: Conduct Risk and Uncertainty Analysis: 

* Was a risk and uncertainty analysis conducted that quantified the 
imperfectly understood risks and identified the effects of changing 
key cost driver assumptions and factors? Were the following steps 
performed: 

a. A probability distribution was modeled for each cost element's 
uncertainty based on data availability, reliability, and variability; 

b. The correlation (i.e., relationship) between cost elements was 
accounted for to capture risk; 

c. A Monte Carlo simulation model was used to develop a distribution 
of total possible costs and an S curve showing alternative cost 
estimate probabilities; 

d. The probability associated with the point estimate was identified. 

e. Contingency reserves were recommended for achieving the desired 
confidence level; 

f. The risk-adjusted cost estimate was allocated, phased, and 
converted to then year dollars for budgeting, and high-risk elements 
were identified to mitigate risks; 

g. A risk management plan was implemented jointly with the contractor 
to identify and analyze risk, plan for risk mitigation, and 
continually track risk. 

Step Ten: Document the Estimate: 

* Did the documentation describe the cost estimating process, data 
sources, and methods step by step so that a cost analyst unfamiliar 
with the program could understand what was done and replicate it? 

a. Are supporting data adequate for easily updating the estimate to 
reflect actual costs or program changes and using them for future 
estimates? 

b. Did the documentation describe the estimate with narrative and cost 
tables and did it contain an executive summary, introduction, and 
descriptions of methods, with data broken out by WBS cost elements, 
sensitivity analysis, risk and uncertainty analysis, management 
approval, and updates that reflect actual costs and changes? 

c. Did the detail address best practices and the 12 steps of high-
quality estimates? 

d. Was the documentation mathematically sensible and logical? 

e. Did it discuss contingency reserves and how they were derived from 
risk and uncertainty analysis? 

f. Did the documentation include access to an electronic copy of the 
cost model and are both the documentation and the cost model stored so 
that authorized personnel can easily find and use them for other cost 
estimates? 

Step Eleven: Present the Estimate to Management for Approval: 

* Was there a briefing to management that included a clear explanation 
of the cost estimate so as to convey its level of competence? 

a. Did the briefing illustrate the largest cost drivers by presenting 
them logically with backup charts for responding to more probing 
questions? 

b. Did the briefing include an overview of the program's technical 
foundation and objectives, the life cycle cost estimate in time-phased 
constant year dollars, a discussion of ground rules and assumptions, 
the method and process for each WBS cost element estimate including 
data sources, the results of sensitivity and risk/uncertainty analysis 
along with a confidence interval, the comparison of the point estimate 
to an independent cost estimate with a discussion of any differences 
and whether the point estimate is reasonable, an affordability 
analysis based on funding and contingency reserves, a discussion of 
any concerns or challenges, conclusions, and recommendations for 
approval? 

c. Was any feedback from the briefing including management's 
acceptance of the estimate acted on and recorded in the cost estimate 
documentation? 

Step Twelve: Update the Estimate to Reflect Actual Costs and Changes: 

* Is there a process for the estimating team to update the estimate 
with actual costs as it becomes available? 

a. Was the estimate updated to reflect changes in technical or program 
assumptions and was there a discussion how these changes affected the 
cost estimate? 

b. Did the cost estimates get replaced with actual costs? Were the 
actual costs from an EVM system? 

c. Did the estimate discuss lessons learned for elements whose actual 
costs or schedules differed from the estimate? 

[End of section] 

Appendix III: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
Acquisition, Technology And Logistics: 
3000 Defense Pentagon: 
Washington, DC 20301-3000: 

August 24, 2010: 
	
Ms. Belva M. Martin: 
Acting Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street NW: 
Washington, DC 20548: 

Dear Ms. Martin: 

This is the Department of Defense (DoD) response to the GAO draft 
report 10-523 "Defense Acquisitions: Navy's Ability to Overcome 
Challenges Facing the Littoral Combat Ship Will Determine Eventual 
Capabilities" dated June 30, 2010, (GAO Code 120834). Detailed 
comments on the report recommendations are enclosed. 

The Department appreciates the opportunity to comment on the draft 
report. For further questions concerning this report, please contact 
Darlene Costello, Deputy Director, Naval Warfare, 703-697-2205. 

Sincerely, 

Signed by: 

David G. Ahern: 
Director: 
Portfolio Systems Acquisition: 

Enclosure: As stated: 

[End of letter] 

GAO Draft Report Dated June 30, 2010: 
GAO-10-523 (GAO Code 120834): 

"Defense Acquisitions; Navy's Ability To Overcome Challenges Facing 
The Littoral Combat Ship Will Determine Eventual Capabilities" 

Department Of Defense Comments To The GAO Recommendations: 

Recommendation 1: The GAO recommends that the Secretary of Defense 
ensure changes identified in building and testing the first four ships 
are incorporated into the basic and functional design by the start of 
construction for future Littoral Combat Ship (LCS) seaframes. (See 
page 36/GAO Draft Report.) 

DoD Response: Concur. The Navy has been operating both LCS designs and 
collecting design performance data. The Navy will continue to actively 
test and report on ship performance as the first two follow ships are 
delivered and operated in the Fleet so that the design performance of 
future ships is enhanced using empirical data. The Fiscal Year (FY) 
2010 solicitation uses the technical baseline of the FY 2009 ships, 
plus known government directed changes, to establish a stable baseline 
for the near term awards. The program can use existing ship and
class design services contracts to execute additional changes through 
the program's formal configuration management process after contract 
award. The Department also will review post-delivery test sequencing 
to ensure testing results can inform future purchases as early as 
practicable. 

Recommendation 2: The GAO recommends that the Secretary of Defense 
update the LCS test and evaluation master plan to (1) account for any 
early deployments of seaframes and the significant developmental 
challenges faced by key mission package systems and (2) identify 
alternative approaches for completing seaframe and mission package 
initial operational test and evaluation. (See page 36/GAO Draft Report.) 

DoD Response: Concur. The Navy will update the LCS Test and Evaluation
Master Plan (TEMP) after the down-select and the Milestone 13 decision 
to reflect the changes in the program. The updated TEMP will reflect 
the new LCS acquisition strategy approved in January 2010. In 
addition, it will address the test and evaluation strategy of 
Developmental Testing (DT) and Operational Testing (OT) for one 
mission package on each of the lead ships. This will support 
achievement of initial operational capability as defined in the Flight 
0 Capability Development Document. The remaining LCS mission packages 
are scheduled for DT/OT on LCS 3, 4, and 5. 

Recommendation 3: The GAO recommends that the Secretary of Defense 
update the LCS acquisition strategy to account for operational testing 
delays in the program and resequence planned purchases of ships and 
mission packages, as appropriate. (See page 36/GAO Draft Report.) 

DoD Response: Concur. The Navy understands that alignment of the 
seaframe and mission modules production milestones must occur to meet 
requirements for initial operational test and evaluation and further 
production decisions. An updated schedule is under development. The 
Navy will continue to deliver LCS seaframes as currently planned and 
to field mission module capability in a spiral fashion as new systems 
are matured, tested, and accepted by the Fleet. In addition, the 
Department will review post-delivery test sequencing to ensure testing 
results can inform future purchases as early as practicable. 

Recommendation 4: The GAO recommends that the Secretary of Defense 
ensure that future LCS cost estimates--including the program life 
cycle cost estimate currently planned for milestone B--are well-
documented, comprehensive, accurate, and credible. (See page 37/GAO 
Draft Report.) 

DoD Response: Concur. However, the cost analyses referenced in the 
draft GAO report were used to support investigatory trade studies and 
were not intended as a budget quality estimate, nor intended to inform 
contract negotiations. The estimate was developed to establish a cost 
baseline for the overall LCS program life cycle to be used as a point 
of departure for conducting cost trade-off analyses. In preparation 
for the program's Milestone B review, the Navy produced a complete 
cost estimate for the entire system lifecycle. This estimate fully 
incorporated cost estimating best practices, including cost risk, cost 
driver sensitivity analyses, and a fully documented Independent Cost 
Estimate (ICE), in accordance with NAVSEA 05C's 12-Step Cost 
Estimating Process. Additionally, NAVSEA 05C held discussions with 
OSD's Cost Assessment and Program Evaluation (CAPE) group. CAPE also 
prepared an ICE for the LCS program to support the Milestone B review. 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Belva M. Martin, (202) 512-4841 or martinb@gao.gov: 

Acknowledgments: 

In addition to the contact named above, key contributors to this 
report were Karen Zuckerstein, Assistant Director; Greg Campbell; 
Christopher R. Durbin; Kristine Hassinger; Jeremy Hawk; Jasmin 
Jahanshahi; Julia P. Jebo; Jason Kelly; and Amber N. Keyser. 

[End of section] 

Footnotes: 

[1] See GAO, GAO Cost Estimating and Assessment Guide: Best Practices 
for Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: Mar. 2009). 

[2] The Navy classifies sea states on a scale of 0 to 9 depending on 
the roughness of the water as caused by wind or other disturbances. 
Sea states 0 to 3 represent calm to slight seas of 4 feet or less. Sea 
state 4 is characterized by moderate seas of 4 to 8 feet. Sea states 5 
to 6 range from rough to very rough seas between 8 to 20 feet. Sea 
states 7 to 9--the most challenging marine conditions--reflect high to 
extremely rough seas, including seas above 20 feet. 

[3] See GAO, Best Practices: High Levels of Knowledge at Key Points 
Differentiate Commercial Shipbuilding from Navy Shipbuilding, 
[hyperlink, http://www.gao.gov/products/GAO-09-322] (Washington, D.C.: 
May 13, 2009). 

[4] Pub. L. No 111-84, § 121 (c). Section 121(d) also authorizes the 
Secretary of the Navy to waive and adjust provisions of the cost 
limitation upon making certain findings and other conditions. 

[5] In addition, Navy officials stated that environmental and treaty 
constraints prohibited testing of several ship systems within the 
confines of the Great Lakes. 

[6] See GAO, Best Practices: High Levels of Knowledge at Key Points 
Differentiate Commercial Shipbuilding from Navy Shipbuilding, 
[hyperlink, http://www.gao.gov/products/GAO-09-322] (Washington, D.C.: 
May 13, 2009). 

[7] While the Navy will use LCS systems to detect mines in the very 
shallow (40 feet to 30 feet water only), surf (less than 10 feet to 0 
feet water), and beach zones, other military assets will neutralize 
these mines. 

[8] See GAO, Defense Acquisitions: Overcoming Challenges Key to 
Capitalizing on Mine Countermeasures Capabilities, [hyperlink, 
http://www.gao.gov/products/GAO-08-13] (Washington, D.C.: Oct. 12, 
2007). 

[9] Under the LCS program's 2008 Test and Evaluation Master Plan, the 
Navy planned to conduct an operational assessment of LCS 1--employing 
elements of the first mine countermeasures mission package--beginning 
the second quarter of fiscal year 2010. The Navy's fiscal year 2011 
budget estimates show LCS 1 will now begin operational testing in the 
third quarter of fiscal year 2013 using the surface warfare mission 
package. 

[10] Department of Defense Instruction 5000.02, Operation of the 
Defense Acquisition System Enclosure 4 Table 3 (Dec. 8, 2008). 

[11] Engineering and manufacturing development has the same meaning as 
system development and demonstration as referred to in 10 U.S.C. § 
2434. 

[12] In June 2009, Navy cost estimators completed their preliminary 
analysis of LCS total ownership costs and briefed key findings to 
senior Navy leaders. The Navy later recorded this analysis in the LCS 
Total Ownership Cost Baseline Estimate Documentation (Aug. 25, 2009). 

[13] On December 18, 2008, the Defense Acquisition Board conducted a 
Milestone A-Prime review of the LCS program to determine the readiness 
of the program to continue the Technology Development phase and to 
procure fiscal year 2009 ships and mission packages. 

[14] We previously assessed the quality of the Navy's operating and 
support cost estimates for LCS. See GAO, Littoral Combat Ship: Actions 
Needed to Improve Operating Cost Estimates and Mitigate Risks in 
Implementing New Concepts, [hyperlink, 
http://www.gao.gov/products/GAO-10-257] (Washington, D.C.: Feb. 2, 
2010). 

[15] See GAO, GAO Cost Estimating and Assessment Guide: Best Practices 
for Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: Mar. 2009). 

[16] See GAO, Defense Acquisitions: Assessments of Selected Weapons 
Programs, [hyperlink, http://www.gao.gov/products/GAO-10-388SP] 
(Washington, D.C.: Mar. 30, 2010). 

[17] Under the terms of the LCS 3 and LCS 4 contracts, the shipyards 
must achieve earned value management system certification within 28 
months from the date of contract award. 

[18] See GAO, GAO Cost Estimating and Assessment Guide: Best Practices 
for Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: Mar. 2009). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: