This is the accessible text file for GAO report number GAO-10-784 
entitled 'Recovery Act: Most DOE Cleanup Projects Appear to Be Meeting 
Cost and Schedule Targets, but Assessing Impact of Spending Remains a 
Challenge' which was released on July 29, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Requesters: 

United States Government Accountability Office: 
GAO: 

July 2010: 

Recovery Act: 

Most DOE Cleanup Projects Appear to Be Meeting Cost and Schedule 
Targets, but Assessing Impact of Spending Remains a Challenge: 

GAO-10-784: 

GAO Highlights: 

Highlights of GAO-10-784, a report to congressional requesters. 

Why GAO Did This Study: 

The American Recovery and Reinvestment Act of 2009 aims to stimulate 
the economy, including funding for environmental cleanup projects. The 
Department of Energy (DOE) receives annual appropriations of $6 
billion to support the cleanup of radioactive and hazardous wastes 
resulting from decades of nuclear weapons research and production. 

GAO was asked to examine (1) how DOE selected projects for funding and 
developed cost and schedule targets, (2) project status and extent to 
which projects are achieving these targets, and (3) key challenges 
faced and efforts to address them. GAO reviewed Recovery Act project 
documentation, including cost, schedule, and performance data for 84 
projects at 17 sites; visited the 4 sites receiving most of the 
funding; and interviewed headquarters and site officials. 

What GAO Found: 

DOE’s Office of Environmental Management generally chose to use 
Recovery Act funds for cleanup projects that could be quickly started 
and finished. Most projects also had existing contracts, which allowed 
DOE to update and validate cost and schedule targets within a short 
time. DOE generally funded four types of projects: decontaminating or 
demolishing facilities, removing contamination from soil and 
groundwater, packaging and disposing of transuranic and other wastes, 
and supporting the maintenance and treatment of liquid tank wastes. In 
all, DOE selected 84 projects at 17 DOE sites in 12 states for 
Recovery Act funding, with 4 sites receiving most of the money. 

As of May 2010, DOE had begun work on all Recovery Act projects and 
reported creating about 5,600 full-time equivalent jobs at the 17 
sites during the first quarter of 2010. Spending on Recovery Act 
projects has been slower than planned. DOE had obligated about $5.5 
billion of the $6 billion in Recovery Act cleanup funding and spent 
about $1.9 billion of those funds. This sum is less than the $2.3 
billion DOE had expected to spend by that time. DOE reported that most 
Recovery Act projects were achieving cost and schedule targets, 
although a third of projects were not. 

DOE has faced familiar challenges in both managing Recovery Act 
projects and measuring how Recovery Act funding has affected cleanup 
and other goals. According to DOE officials, a third of projects did 
not meet cost and schedule targets for some of the same reasons that 
have plagued DOE in the past: technical, regulatory, safety, and 
contracting issues. DOE has taken steps aimed at strengthening project 
management and oversight for Recovery Act projects, such as increasing 
project reporting requirements and placing tighter controls on when 
funds are disbursed to sites, but it is uncertain how these steps will 
ultimately affect Recovery Act project performance, or whether they 
hold the potential to be useful for cleanup work funded under annual 
appropriations. Measuring the impact of Recovery Act funding on job 
creation and DOE’s cleanup goals has also been a challenge for DOE, in 
particular, providing an accurate assessment of the act’s impact on 
jobs, environmental risk reduction, and the life-cycle costs of its 
cleanup program. DOE has used three different methodologies to assess 
and report jobs created, which provide very different and potentially 
misleading, pictures of jobs created. For example, the calculations 
ranged from about 5,700 jobs to 20,200, depending on the methodology 
used. Also, DOE has not developed a clear means of measuring how 
cleanup work funded by the act will affect environmental risk or 
reduce its footprint—the land and facilities requiring DOE cleanup. 
Further, it is unclear to what extent Recovery Act funding will reduce 
the costs of cleaning up the DOE complex over the long term. DOE’s 
estimate of $4 billion in life cycle cost savings resulting from 
Recovery Act funding was not calculated in accordance with federal 
guidance. GAO’s analysis indicates that those savings could be 80 
percent less than DOE estimated. Without clear and consistent 
measures, it will be difficult to say whether or how Recovery Act 
funding has affected DOE’s cleanup goals. 

What GAO Recommends: 

GAO recommends four actions for DOE to improve project management and 
reporting: (1) determine whether project management and oversight 
steps adopted for Recovery Act projects would benefit other cleanup 
projects, (2) clarify the methodology used to calculate jobs created, 
(3) develop clear and quantifiable measures for determining the impact 
of Recovery Act funding, and (4) ensure that cost savings are 
calculated according to federal guidance. DOE agreed with the 
recommendations. 

View [hyperlink, http://www.gao.gov/products/GAO-10-784] or key 
components. For more information, contact Gene Aloise at (202) 512-
3841 or aloisee@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

For Recovery Act Funding, DOE Generally Selected "Shovel-Ready" 
Projects Whose Cost and Schedule Targets Had Been Developed and Needed 
Minimal Work to Finalize: 

DOE Has Begun Work on All Projects, Most Appear to Be Meeting Cost and 
Schedule Targets, and Spending Overall Has Been Slower Than Planned: 

DOE Has Taken Steps to Help Address Potential Problems but Continues 
to Face Key Challenges in Managing Projects and Measuring Their Impact: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Description of Four Projects Reviewed in Depth: 

Appendix III: Recovery Act Project Cost Data through March 2010: 

Appendix IV: Recovery Act Project Performance through March 2010: 

Appendix V: Comments from the Department of Energy: 

Appendix VI: GAO Contact and Staff Acknowledgments: 

Related GAO Products: 

Tables: 

Table 1: Spending on Recovery Act Cleanup Projects through May 2010: 

Table 2: Number of Recovery Act Cleanup Jobs Created by DOE, as 
Calculated According to OMB and DOE Guidance, as of March 31, 2010: 

Figures: 

Figure 1: Sites Selected to Receive Recovery Act Funding: 

Figure 2: Aerial and Interior View of Building K-33, East Tennessee 
Technology Park, Oak Ridge Reservation: 

Figure 3: Workers Packaging Transuranic Waste, Savannah River Site: 

Figure 4: Selected Performance Measures for Environmental Management's 
Recovery Act Projects, Reported by DOE, as of March 2010: 

Figure 5: Performance of Recovery Act Projects, as of March 31, 2010: 

Abbreviations: 

CERCLA: Comprehensive Environmental Response, Compensation, and 
Liability Act: 

DOE: Department of Energy: 

EPA: Environmental Protection Agency: 

FTE: full-time equivalent: 

OMB: Office of Management and Budget: 

[End of section] 

United States Government Accountability Office:
Washington, DC 20548: 

July 29, 2010: 

The Honorable Joe Barton: 
Ranking Member: 
Committee on Energy and Commerce: 
House of Representatives: 

The Honorable Peter J. Visclosky: 
Chairman: 
The Honorable Rodney P. Frelinghuysen: 
Ranking Member: 
Subcommittee on Energy and Water Development: 
Committee on Appropriations: 
House of Representatives: 

The Honorable Michael C. Burgess: 
Ranking Member: 
Subcommittee on Oversight and Investigations: 
Committee on Energy and Commerce: 
House of Representatives: 

The Honorable Greg Walden: 
House of Representatives: 

In response to what is generally reported to be the most serious 
economic crisis since the Great Depression, the American Recovery and 
Reinvestment Act of 2009 (Recovery Act) was enacted on February 17, 
2009.[Footnote 1] The purposes of the act, among other aims, are to 
preserve and create jobs, to promote economic recovery, and to provide 
investments to increase economic efficiency by spurring technological 
advances in science and health. Initially estimated to cost $787 
billion, the Recovery Act includes an estimated $580 billion in 
spending, including for environmental protection. One of the 
departments the act directs funds to--the Department of Energy (DOE)-- 
received appropriations of $6 billion to expand and accelerate its 
efforts to clean up numerous contaminated sites across the country, 
where decades of nuclear weapons research, development, and production 
left a legacy of dangerously radioactive, chemical, and other 
hazardous wastes. 

DOE's Office of Environmental Management directs the cleanup of this 
contamination across the DOE complex. The sites contain nuclear 
reactors; chemical processing buildings; and plants, laboratories, and 
maintenance facilities once used to manufacture thousands of nuclear 
warheads. Cleanup activities include treating and permanently 
disposing of millions of gallons of radioactive and chemical waste 
stored in large underground tanks; disposing of spent nuclear fuel; 
removing contaminated soil; treating contaminated groundwater; 
packaging and shipping solid wastes infused with synthetic radioactive 
elements like plutonium and americium for permanent disposal to a deep 
geologic repository; and eliminating excess facilities, which may 
include decontaminating, decommissioning, deactivating, and 
demolishing obsolete structures or a combination of these activities. 
DOE has estimated that the cost of this cleanup may approach $300 
billion[Footnote 2] over the next several decades. 

Recovery Act funding, which DOE intends to spend over 2.5 years, 
substantially boosts the Office of Environmental Management's annual 
appropriation for cleanup, of between $6 and $7 billion. DOE 
designated the bulk of this new funding--almost 80 percent--to speed 
cleanup activities at four large sites: the Hanford Site in Washington 
State; Idaho National Laboratory in Idaho; the Oak Ridge Reservation 
in Tennessee; and the Savannah River Site in South Carolina. As we 
have previously reported,[Footnote 3] most of these sites have 
contended with various contract or project management challenges in 
the past, which have resulted in significant cost overruns or delays 
lasting years for some projects. 

You asked us to examine (1) how DOE selected projects for Recovery Act 
funding and developed cost and schedule targets, (2) the status of 
Recovery Act projects and the extent to which the projects are 
achieving cost and schedule targets and performance measures, and (3) 
key challenges DOE has faced in carrying out these projects and its 
efforts to address them. 

To conduct our work, we reviewed pertinent provisions of the American 
Recovery and Reinvestment Act of 2009; federal regulations guiding 
government acquisition of goods and services; Office of Management and 
Budget (OMB) and DOE policies, procedures, and guidance on Recovery 
Act implementation; and relevant studies of Recovery Act 
implementation. To determine how DOE selected projects and developed 
cost and schedule targets, we reviewed relevant project documentation, 
including project operating plans, DOE assessments of proposed cost 
and schedule targets, and project risk assessments. We obtained data 
on costs, schedules, and jobs created as of March 2010, the most 
recent data available, from DOE's Environmental Management Recovery 
Act Program office. We also interviewed DOE headquarters and federal 
project and contractor officials at each of the 17 sites receiving 
Recovery Act funding.[Footnote 4] We interviewed officials at 13 sites 
by phone and visited the 4 DOE cleanup sites receiving the bulk of the 
$6 billion in Recovery Act funding for environmental cleanup: (1) the 
Hanford Site, (2) Idaho National Laboratory, (3) the Oak Ridge 
Reservation, and (4) the Savannah River Site. At each site, we 
reviewed project documentation, interviewed officials, and observed 
Recovery Act work under way. In addition, at the Hanford and Savannah 
River sites, we also selected a nonrandom sample of four of the 
costliest projects--two projects involving demolition of facilities, a 
project to remediate soil and groundwater, and a project to package 
and dispose of waste--to better understand how cost and schedule 
estimates were developed and to assess the reliability of estimates 
for these projects. Two projects were located at the Hanford Site and 
two at the Savannah River Site. To assess to what extent projects were 
meeting cost and schedule targets, we reviewed March 2010 data, the 
most recent available, from DOE's system for tracking project 
performance, called an earned value management system, and also 
reviewed data on project-related performance measures that refer to 
specific cleanup activities. To determine what key challenges DOE 
faced and the steps officials took to address these challenges, we 
reviewed pertinent Recovery Act project guidance and DOE project 
documents and reports, and interviewed headquarters officials and 
federal and contractor officials at all 17 sites. We also conferred 
with staff from DOE's Office of Inspector General. To assess the 
reliability of data we reviewed, we sent out questionnaires to DOE 
headquarters and site officials regarding the steps taken to ensure 
the accuracy of data related to measuring progress toward cost and 
schedule targets, jobs created, and other project outcomes. We 
determined that the data were sufficiently reliable for the purposes 
of our report. Appendix I presents a more detailed description of our 
scope and methodology. Appendix II provides more information on the 
four projects reviewed in depth. 

We conducted this performance audit from June 2009 to July 2010, in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

Since the 1940s, DOE and its predecessor agencies have operated a 
nationwide complex of facilities used to research, design, and 
manufacture nuclear weapons and related technologies. DOE also 
conducts research in energy and sciences ranging from harnessing 
geothermal power as a renewable resource to the behavior of subatomic 
particles colliding at nearly the speed of light. Organizationally, 
DOE supports this broad range of activities with a diverse group of 
mission-based program elements. These include the Office of Science, 
charged with conducting basic science and technology research; the 
National Nuclear Security Administration, which oversees the nation's 
nuclear weapons stockpile; and the Office of Environmental Management, 
which leads the department's often complex and challenging effort to 
clean up nuclear, chemical, and other hazardous wastes. Environmental 
Management carries out its work at numerous DOE sites and facilities 
around the country, primarily through private entities that manage the 
facilities and work under contract to DOE. About 90 percent of DOE's 
annual budget (which totaled about $27 billion in fiscal year 2010) 
goes to contracts with private firms. An extensive network of site 
offices directly oversees the work of these contractors. 

In 1990, GAO designated DOE's contract management, including both 
contract administration and project management, at high risk for 
fraud, waste, abuse, and mismanagement. In the following two decades, 
continued ineffective oversight and poor contract management led to 
substantial cost overruns and lengthy delays on many projects overseen 
by DOE, in particular, the Office of Environmental Management. DOE has 
faced difficulties in developing realistic cost and schedule targets 
and then achieving them, in part because of challenges addressing 
complex technical issues, negotiating contracts, complying with 
regulatory issues, and ensuring safety.[Footnote 5] Recently, for 
example, factors such as these have delayed completion of Hanford's 
Waste Treatment and Immobilization Plant in Washington State. The 
project has been delayed by 8 years, while costs have escalated, more 
than doubling the initial estimate, from $4.3 to $12.2 billion. The 
treatment plant was one of nine major DOE construction projects, 
collectively valued at about $14 billion, that as of 2009 had exceeded 
both their original cost and schedule estimates. As we recently 
reported, DOE has taken steps to improve its contract and management 
activities, including in 2000 issuing its order 413.3A, which 
established a process for managing projects, from beginning to end. 
[Footnote 6] The order established five major milestones--or "critical 
decision points"--that span a project's life, beginning with approval 
of need and ending with project completion. Order 413.3A specifies the 
requirements that must be met, along with the documentation necessary, 
to move past each milestone, including when a variety of independent 
reviews should occur to assess progress. Other steps DOE has taken 
include developing a root-cause analysis, a corrective action plan, 
and performance measures intended to help assess progress. 
Nevertheless, Environmental Management's contract and project 
management activities remain on GAO's list of programs or agencies at 
high risk for fraud, waste, abuse, and mismanagement. 

The Recovery Act is intended to promote economic recovery, make 
investments, and minimize or avert reductions in state and local 
government services. The Congressional Budget Office estimated that 
the Recovery Act would increase employment by about 1.2 million to 3.6 
million jobs by the end of 2010. Enacted on February 17, 2009, the act 
directed that priority be given to projects that could be started 
quickly. The administration referred to such projects as "shovel- 
ready." Projects funded by the Recovery Act must comply with section 
1512 of the act, which requires funding recipients to report quarterly 
on a number of measures, including the amount of funds expended or 
obligated to projects or activities, and the number of jobs created. 
The act generally requires that all awarded funding must be obligated 
by September 30, 2010. Funds must be expended by September 30, 2015. 

In implementing environmental cleanup work under the Recovery Act, 
Environmental Management established several goals. These goals 
included creating jobs; reducing DOE's "footprint," or area with 
ongoing cleanup activity; reducing the life-cycle costs associated 
with hazardous waste cleanup; completing cleanup activities at three 
small sites; and meeting a number of regulatory cleanup deadlines that 
it might not otherwise meet. In addition, Environmental Management set 
an internal deadline to expend all Recovery Act funds and complete 
Recovery Act work by the end of fiscal year 2011. 

For Recovery Act Funding, DOE Generally Selected "Shovel-Ready" 
Projects Whose Cost and Schedule Targets Had Been Developed and Needed 
Minimal Work to Finalize: 

DOE generally chose to use Recovery Act funds for cleanup projects 
that could be quickly started and finished. The majority of the 
projects selected also had existing contracts, which allowed the 
department to update and validate new cost and schedule targets within 
a short time frame. 

Recovery Act Funding Enabled DOE to Implement Shovel-Ready Projects It 
Had Identified in Recent Planning Efforts: 

At the time the Recovery Act was passed, DOE was well positioned to 
select projects that could be implemented quickly with Recovery Act 
funding. DOE officials said they had planning efforts under way since 
2006, which were aimed at identifying relatively low-risk cleanup 
projects that could reduce DOE's cleanup footprint and speed overall 
site remediation. Such projects included, for example, facility 
demolition, groundwater or soil remediation, or finishing work that 
could help accelerate site closure. These projects generally had 
contracts, including cost and schedule targets, in place; they used 
proven technologies, had secured needed regulatory approvals, and were 
therefore considered "shovel-ready." (According to DOE officials, this 
focus on discrete, low-risk projects stemmed in part from lessons 
learned during a 2002 cleanup acceleration attempt, which ultimately 
did not work well for complex and costly projects.[Footnote 7]) In 
addition to its internal deadline to expend all Recovery Act funds and 
complete work by the end of fiscal year 2011, other criteria--
including job creation and reducing environmental risk--also 
influenced DOE's selection. DOE officials said that in selecting these 
projects, they had to balance competing goals. For example, to begin 
and complete work quickly, they chose a portfolio of cleanup projects 
that may ultimately reduce DOE's footprint--its physical presence--on 
the national landscape by 372 square miles (approximately 40 percent) 
but would not address the most dangerously radioactive and hazardous 
wastes and the environmental risks these wastes present. 

In all, DOE selected 84 projects at 17 DOE sites in 12 states for 
Recovery Act funding (see figure 1) with the majority of the money 
going to four sites--Hanford, Idaho National Laboratory, the Oak Ridge 
Reservation, and Savannah River (see appendix III). 

Figure 1: Sites Selected to Receive Recovery Act Funding: 

[Refer to PDF for image: illustrated U.S. map] 

Hanford Site: Richland Operations Office; 
10 projects, $1,635 million. 

Hanford Site: Office of River Protection; 
5 projects,$326 million. 

Idaho National Laboratory: 
8 projects, $468 million. 

SLAC Accelerator Laboratory: 
1 project, $8 million. 

Nevada Test Site: 
1 project, $44 million. 

Moab UMTRA Site: 
1 project, $108 million. 

Energy Technology Engineering Center: 
2 projects, $54 million. 

Los Alamos National Laboratory: 
4 projects, $212 million. 

Waste Isolation Pilot Plant: 
3 projects, $172 million. 

Argonne National Laboratory: 
4 projects, $79 million. 

Mound Site: 
1 project, $20 million. 

West Valley Demonstration Project: 
3 projects, $74 million. 

Paducah Site: 
3 projects, $80 million. 

Oak Ridge Reservation: 
14 projects, $755 million. 

Savannah River Site: 
14 projects, $1,615 million. 

Portsmouth Site: 
5 projects, $120 million. 

Brookhaven National Laboratory: 
3 projects, $62 million. 

Separations Process Research Unit: 
2 projects, $52 million. 

Sources: DOE; Map Resources (map). 

[End of figure] 

The vast majority of projects had been included in the sites' own work 
plans, such as groundwater remediation at Los Alamos National 
Laboratory, but some projects also represented work newly transferred 
from other program offices, such as remediation and demolition of a 
former weapons facility at Oak Ridge Reservation. In general, projects 
chosen for Recovery Act funding fell into four main categories of work: 

* Decontaminating and demolishing facilities: for example, 
decontaminating and demolishing the K-33 building at the Oak Ridge 
Reservation.[Footnote 8] A two-level structure that covers 32 acres 
(see figure 2) was constructed in 1954 to process and enrich uranium 
for use in nuclear weapons. Although uranium enrichment operations 
ceased in 1985, the building's piping and other equipment were not 
removed completely until 2005, and radiological and chemical 
contamination remains throughout the building. DOE had initially 
selected a different building for demolition, K-27, which was also 
used to process and enrich uranium, but it found unexpectedly high 
levels of mercury contamination, complicating that cleanup. So in 
February 2010, DOE decided to instead demolish the K-33 building--a 
much larger building but a less-contaminated and less-complex cleanup 
project--at a cost of $65 million. Work began in April 2010. Given the 
delay in starting the project, site officials expect the project to be 
completed in 2012. 

Figure 2: Aerial and Interior View of Building K-33, East Tennessee 
Technology Park, Oak Ridge Reservation: 

[Refer to PDF for image: 2 photographs] 

Source: DOE. 

[End of figure] 

* Removing contamination from soil and groundwater: for example, 
removing and disposing of radioactive and hazardous contaminants from 
soil and groundwater at the Mound Site, a former production site for 
explosives and other weapons' components. Production at the site 
ceased in 1995. The site's contractor declared the physical completion 
of environmental cleanup of the site in July 2006, although a landfill 
remained, which DOE planned to monitor for contamination. Congress, 
however, directed further remediation of the landfill at the site. The 
project includes excavating and disposing of contaminated soils and 
backfilling the site. Although work began with base funding, the 
funding was insufficient to complete removal of the contamination. 
Recovery Act funding of $19.7 million was applied to the project to 
complete remaining work, with an expected site closure date of 
September 2010.[Footnote 9] 

* Packaging and disposing of transuranic and other wastes: for 
example, characterizing and packaging transuranic wastes at multiple 
DOE sites for shipment to the department's deep geologic repository 
for permanent disposal. (See figure 3.) Transuranic wastes are 
typically discarded rags, tools, equipment, soils, or other solid 
materials that have been contaminated by radioactive elements, such as 
plutonium or americium.[Footnote 10] About 110,000 cubic meters of 
these wastes were generated mostly after 1970 and then stored at 
various DOE sites. Because these wastes remain radioactive for 
extremely long periods--hundreds of thousands of years in some cases--
most are headed for disposal at the Waste Isolation Pilot Plant, a 
deep geologic repository near Carlsbad, New Mexico, designed for 
transuranic waste disposal. Idaho National Laboratory plans to ship 
160 transuranic waste containers--those containers that because of 
their high radioactivity, must be handled remotely--to the Waste 
Isolation Pilot Plant. 

Figure 3: Workers Packaging Transuranic Waste, Savannah River Site: 

[Refer to PDF for image: photograph] 

Source: DOE. 

[End of figure] 

* Supporting the maintenance and treatment of liquid tank waste: for 
example, upgrading the infrastructure used to stabilize and maintain 
the tanks that store chemical and radioactive waste at the Hanford 
Site. Projects funded through the Recovery Act are accelerating 
specific upgrades, such as installing new ventilation systems to 
prevent the buildup of hazardous and volatile gases produced in the 
tanks. The waste is gradually being transferred from the oldest, 
deteriorating underground tanks to larger, newer tanks in preparation 
for processing in the waste treatment plant, which is expected to 
start operating in 2019. 

DOE Updated and Validated Cost and Schedule Targets for Recovery Act 
Projects: 

To implement Recovery Act work, DOE updated (or, for new work, 
developed) cost and schedule targets for each project. Once these 
targets were established, DOE followed the process established by 
order 413.3A for reviewing and assessing the targets' validity and the 
reasonableness of the price of the associated contract. Reviews fell 
into two general categories: 

* Program reviews: Performed by DOE officials with no vested interest 
in a project, such reviews are to determine if a project's scope, cost 
and schedules, safety, and technology are valid and appropriate. 
Program reviews for projects estimated to cost no more than $100 
million are known as independent project reviews. Program reviews for 
projects estimated to cost $100 million or more are known as external 
independent reviews. 

* Cost reviews: These reviews verify that the contractors' price 
estimates adequately reflect the programs' scope and are reasonable 
for the work to be accomplished. Cost reviews for projects valued at 
$100,000 or more are known as independent government cost estimates. 
Cost reviews for projects valued at $5 million or more are known as 
independent reviews and validations. 

Both of these categories of reviews serve to highlight any potential 
issues or problems with contracts, as well as offer an opportunity for 
DOE and its contractors to define and perform any needed corrective 
action. For example, the Savannah River Site's external independent 
review to assess cost and schedule estimates and readiness to begin 
construction found that the contractor had not produced sound cost and 
schedule estimates or risk management plans nor clearly defined the 
scope of Recovery Act work to decommission certain buildings. The 
site's contractor responded with a corrective action plan that spelled 
out actions to remedy these shortcomings. Reviews have also found 
contracts where information was missing. At Hanford, for example, the 
external independent review found that some of the Recovery Act 
projects had not fully defined the scope of their work or established 
cost and schedule targets at the time of the review. In other cases, 
the reviews found contracts that lacked sufficient "contingencies," 
that is, sufficient cushions built into the cost and schedule 
estimates in case of unforeseen technical or programmatic problems. 
For example, Idaho National Laboratory did not initially include a 
contingency estimate in its schedule for the site's Recovery Act 
activities. Reviews also uncovered concerns about project 
implementation, such as contractors' inability to start work as 
quickly as planned. For instance, at the Moab Site, Utah, an initial 
program review found that the contractor's procurement office was 
unable to acquire needed equipment to operate at full capacity, 
slowing work at the site. 

In addition, DOE decided to disburse funding for Recovery Act cleanup 
projects in phases, requiring site officials to complete a series of 
steps before releasing the funds. For example, initial funding--equal 
to 30 percent of obligated funds--was released only after sites had 
certified that contracts were finalized for the Recovery Act projects. 

DOE Has Begun Work on All Projects, Most Appear to Be Meeting Cost and 
Schedule Targets, and Spending Overall Has Been Slower Than Planned: 

DOE has begun work on all of its Recovery Act projects, spent over 
$1.9 billion of its $6 billion in Recovery Act funding, and created 
more than 5,600 jobs at the 17 cleanup sites selected for funding. DOE 
reported that the majority of Recovery Act projects were achieving 
cost and schedule targets, although about one-third were not.[Footnote 
11] In addition, inconsistencies exist between some projects' cost and 
schedule performance and progress shown by other performance measures, 
such cubic meters of soil remediated. 

DOE Reported All 84 Recovery Act Projects Are Under Way, Creating 
About 5,600 Jobs, but Overall Spending Has Been Slower Than Planned: 

Work has begun on each of DOE's 84 Recovery Act cleanup projects and, 
as of May 2010, each of the projects was still in progress. The first 
project planned for completion--an effort to remove contaminated soil 
and groundwater at the Mound Site in Ohio--is scheduled to finish in 
September 2010, according to DOE. According to DOE monthly reports, 
most of the other 83 projects are expected to be completed by 
September 2011, DOE's internal target for completing all Recovery Act 
work. DOE's monthly project reports from early 2010 indicated that 20 
projects were scheduled for completion after fiscal year 2011, 
including 11 of the 14 projects at the Savannah River Site. More 
recently, however, DOE headquarters officials said that at least nine 
projects would not be completed before the September 2011 deadline. 
These projects include: 

* a project at Savannah River to clean up transuranic waste, which was 
delayed as the site awaited approval to ship its waste to the Waste 
Isolation Pilot Plant for permanent disposal, according to DOE; 
[Footnote 12] 

* a project to demolish a uranium enrichment and processing facility 
at the Oak Ridge Reservation, which began late, according to DOE; and; 
[Footnote 13] 

* a facility-decommissioning project at Idaho National Laboratory, 
which was delayed because of technical difficulties.[Footnote 14] 

In March 2010, DOE reported that Recovery Act cleanup work had 
resulted in more than 5,600 full-time-equivalent jobs at all 17 sites 
in 12 states.[Footnote 15] Over 80 percent of these jobs were located 
at the four sites--Hanford, Idaho National Laboratory, the Oak Ridge 
Reservation, and Savannah River--that together received 80 percent of 
Recovery Act funding. The number of full-time jobs created varied from 
site to site. For example, DOE reported that 5 jobs were created at 
the Energy Technology Engineering Center in California, a 90-acre site 
currently engaged in deactivation and decommissioning activities to 
clean up the nuclear waste generated during years of nuclear research, 
and nearly 1,400 jobs were created at Savannah River, a 310-square-
mile site where a number of DOE cleanup activities are taking place, 
including the stabilization, treatment, and disposal of nuclear waste 
generated during decades of development and production of nuclear 
weapons and materials. 

DOE's spending on Recovery Act projects has been slower than the 
department had planned. As of May 2010, a little over a year into the 
program, DOE had obligated about $5.5 billion (92 percent) of the $6 
billion in Recovery Act cleanup funding and had spent about $1.9 
billion of those funds--slightly less than the $2.3 billion DOE had 
expected to spend through May 2010. Spending rates varied across 
sites, from 76 percent of obligated funds spent at the Energy 
Technology Engineering Center in California to 23 percent at Argonne 
National Laboratory in Illinois. On a project-by-project basis, as of 
March 2010, amounts spent ranged from less than 1 percent of total 
estimated project cost (a $142 million project to decommission a 
reactor at Savannah River[Footnote 16]) to 84 percent of estimated 
project cost (a $17 million project to decommission a reactor at 
Brookhaven National Laboratory[Footnote 17]). In some cases, according 
to DOE officials, the slower spending at a site or on a given project 
resulted from technical and management challenges that may have slowed 
progress. In other cases, however, DOE had planned to spend less money 
early on: for example, DOE estimated slower spending during the first 
several months of a project to remediate contaminated soil and 
groundwater at Hanford because fewer workers were needed for the 
work's first, less complex phase, according to a site official. DOE's 
plans for that project show an increase in the rate of spending 
Recovery Act funds beginning in May 2010, once excavating the 
contaminated soil is under way.[Footnote 18] Table 1 shows Recovery 
Act spending on DOE cleanup projects through May 2010. In commenting 
on a draft of this report, DOE stated that the initial project spend 
plans for the Recovery Act were developed prior to finalizing the 
contracts for the work. Now, with the exception of nine projects for 
which the scope of work changed, DOE officials expect to spend over 95 
percent of project funds by the end of fiscal year 2011. 

Table 1: Spending on Recovery Act Cleanup Projects through May 2010: 

Dollars in thousands: 

Total Recovery Act funds allotted: [Empty]. 

Site: 1. Argonne National Laboratory (IL); 
Total Recovery Act funds allotted: $79,000; 
Allotted funds that have been obligated: Amount: $79,000; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $17,843; 
Allotted funds that have been spent: Percentage: 23%. 

Site: 2. Brookhaven National Laboratory (NY); 
Total Recovery Act funds allotted: $61,855; 
Allotted funds that have been obligated: Amount: $61,855; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $29,636; 
Allotted funds that have been spent: Percentage: 48%. 

Site: 3. Energy Technology Engineering Center (CA); 
Total Recovery Act funds allotted: $54,175; 
Allotted funds that have been obligated: Amount: $54,162; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $41,202; 
Allotted funds that have been spent: Percentage: 76%. 

Site: 4. Hanford Site (WA): Office of River Protection; 
Total Recovery Act funds allotted: $326,035; 
Allotted funds that have been obligated: Amount: $325,935; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $85,962; 
Allotted funds that have been spent: Percentage: 26%. 

Site: 4. Hanford Site (WA): Richland Operations Office; 
Total Recovery Act funds allotted: $1,634,500; 
Allotted funds that have been obligated: Amount: $1,633,993; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $476,258; 
Allotted funds that have been spent: Percentage: 29%. 

Site: 5. Idaho National Laboratory (ID); 
Total Recovery Act funds allotted: $467,875; 
Allotted funds that have been obligated: Amount: $423,775; 
Allotted funds that have been obligated: Percentage: 91%; 
Allotted funds that have been spent: Amount: $184,126; 
Allotted funds that have been spent: Percentage: 39%. 

Site: 6. Los Alamos National Laboratory (NM); 
Total Recovery Act funds allotted: $211,775; 
Allotted funds that have been obligated: Amount: $211,775; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $64,234; 
Allotted funds that have been spent: Percentage: 30%. 

Site: 7. Moab UMTRA Site (UT); 
Total Recovery Act funds allotted: $108,350; 
Allotted funds that have been obligated: Amount: $108,350; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $35,654; 
Allotted funds that have been spent: Percentage: 33%. 

Site: 8. Mound Site (OH); 
Total Recovery Act funds allotted: $19,700; 
Allotted funds that have been obligated: Amount: $19,700; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $8,975; 
Allotted funds that have been spent: Percentage: 46%. 

Site: 9. Nevada Test Site (NV); 
Total Recovery Act funds allotted: $44,325; 
Allotted funds that have been obligated: Amount: $44,300; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $21,795; 
Allotted funds that have been spent: Percentage: 49%. 

Site: 10. Oak Ridge Reservation (TN); 
Total Recovery Act funds allotted: $755,110; 
Allotted funds that have been obligated: Amount: $657,563; 
Allotted funds that have been obligated: Percentage: 87%; 
Allotted funds that have been spent: Amount: $193,340; 
Allotted funds that have been spent: Percentage: 26%. 

Site: 11. Paducah Site (KY); 
Total Recovery Act funds allotted: $80,400; 
Allotted funds that have been obligated: Amount: $80,400; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $24,871; 
Allotted funds that have been spent: Percentage: 31%. 

Site: 12. Portsmouth Site (OH); 
Total Recovery Act funds allotted: $119,800; 
Allotted funds that have been obligated: Amount: $119,800; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $38,430; 
Allotted funds that have been spent: Percentage: 32%. 

Site: 13. Savannah River Site (SC); 
Total Recovery Act funds allotted: $1,615,400; 
Allotted funds that have been obligated: Amount: $1,363,924; 
Allotted funds that have been obligated: Percentage: 84%; 
Allotted funds that have been spent: Amount: $563,292; 
Allotted funds that have been spent: Percentage: 35%. 

Site: 14. Separations Process Research Unit (NY); 
Total Recovery Act funds allotted: $51,775; 
Allotted funds that have been obligated: Amount: $51,775; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $16,202; 
Allotted funds that have been spent: Percentage: 31%. 

Site: 15. SLAC National Accelerator Laboratory (CA); 
Total Recovery Act funds allotted: $7,925; 
Allotted funds that have been obligated: Amount: $7,925; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $5,351; 
Allotted funds that have been spent: Percentage: 68%. 

Site: 16. Waste Isolation Pilot Plant (NM); 
Total Recovery Act funds allotted: $172,375; 
Allotted funds that have been obligated: Amount: $172,344; 
Allotted funds that have been obligated: Percentage: 100%; 
Allotted funds that have been spent: Amount: $58,394; 
Allotted funds that have been spent: Percentage: 34%. 

Site: 17. West Valley Demonstration Project (NY); 
Total Recovery Act funds allotted: $73,875; 
Allotted funds that have been obligated: Amount: $62,875; 
Allotted funds that have been obligated: Percentage: 85%; 
Allotted funds that have been spent: Amount: $22,889; 
Allotted funds that have been spent: Percentage: 31%. 

Site: Other[A]; 
Total Recovery Act funds allotted: $99,650; 
Allotted funds that have been obligated: Amount: $64,237; 
Allotted funds that have been obligated: Percentage: 64%; 
Allotted funds that have been spent: Amount: $57,177; 
Allotted funds that have been spent: Percentage: 57%. 

Site: Unapportioned[B]; 
Total Recovery Act funds allotted: $16,100; 
Allotted funds that have been obligated: Amount: 0; 
Allotted funds that have been obligated: Percentage: 0; 
Allotted funds that have been spent: Amount: N/A; 
Allotted funds that have been spent: Percentage: [Empty]. 

Site: Total; 
Total Recovery Act funds allotted: $6,000,000; 
Allotted funds that have been obligated: Amount: $5,543,688; 
Allotted funds that have been obligated: Percentage: 92%; 
Allotted funds that have been spent: Amount: $1,945,629; 
Allotted funds that have been spent: Percentage: 32%. 

Source: GAO analysis of DOE data. 

[A] Includes management costs, as well as DOE's Title X uranium and 
thorium reimbursement program funded with Recovery Act dollars. 

[B] Refers to money held in reserve by OMB. 

[End of table] 

A Majority of Recovery Act-Funded Projects Appear to Be Meeting Cost 
and Schedule Targets, Although Inconsistencies Exist between Some 
Targets and Performance Measures: 

A key set of metrics DOE uses to determine whether projects, including 
those funded by the Recovery Act, are meeting their cost and schedule 
targets comes from DOE contractors' earned value management system. 
Earned value is a project management tool that combines measurements 
of scope, schedule, and cost in a single integrated system that can be 
used by DOE contractors to manage programs.[Footnote 19] According to 
DOE headquarters and site officials, DOE monitors this earned value 
information monthly from headquarters, as well as weekly or daily at 
some sites. Using these data, DOE reported that, as of March 2010, 57 
of the 84 Recovery Act projects--about two-thirds--were meeting both 
cost and schedule targets. About 20 percent of projects were meeting 
either their cost or schedule target, but not both, and the remaining 
11 percent had missed both targets altogether. Projects meeting and 
missing targets spanned the range of project types, including facility 
demolitions, groundwater remediation, and infrastructure upgrades. 
Appendix IV provides performance information by project number for 
Recovery Act projects. 

In addition to tracking earned value metrics, DOE also evaluates 
project performance by reviewing project-specific performance 
measures. As of March 2010, DOE reported that across the complex, 
progress on five of seven selected performance measures was meeting or 
exceeding targets (see figure 4). These measures relate to the 
specific cleanup activities under way at a given site, such as cubic 
meters of waste disposed of or the number of radioactive facilities 
decommissioned. Historically, DOE has used such measures to track 
cleanup progress complexwide. DOE developed several new performance 
measures specific to Recovery Act projects. These include, for 
example, cubic meters of transuranic waste that have been prepared and 
certified for shipment to the Waste Isolation Pilot Plant, a measure 
that supplements existing measures tracking only the amount of 
transuranic waste actually disposed of. Some sites have also developed 
site-or project-specific cleanup measures, such as the Savannah River 
Site, which is measuring cubic yards of grout (a cementlike material) 
poured into decommissioned reactor facilities, and the Hanford Site, 
which is measuring the number of waste tank systems that are upgraded. 

Figure 4: Selected Performance Measures for Environmental Management's 
Recovery Act Projects, Reported by DOE, as of March 2010: 

[Refer to PDF for image: horizontal bar graph] 

Performance measures: Facility square footage demolished (ft2); 
Overall goal: 3,144,981; 
Target to date: 405,636; 
Actual to date: 456,778. 

Performance measures: Demolition debris and soil permanently disposed 
of (m3); 
Overall goal: 1,217,177
Target to date: 381,368; 
Actual to date: 277,765. 

Performance measures: Mill tailings disposed of (tons); 
Overall goal: 2,004,035; 
Target to date: 465,155; 
Actual to date: 614,295. 

Performance measures: Transuranic waste packaged for disposal (m3); 
Overall goal: 6,657; 
Target to date: 1,799; 
Actual to date: 1,928. 

Performance measures: Transuranic waste characterized for final 
disposal (m3); 
Overall goal: 10,045; 
Target to date: 1,970; 
Actual to date: 1,259. 

Performance measures: Transuranic waste permanently disposed of (m3); 
Overall goal: 8,398; 
Target to date: 744; 
Actual to date: 878. 

Performance measures: Low-level and mix low-level waste permanently 
disposed of (m3); 
Overall goal: 72,687; 
Target to date: 13,069; 
Actual to date: 13,666. 

Source: DOE. 

Note: Demolition debris and soil permanently disposed of represents a 
planning estimate rather than a performance measure, according to DOE. 
For Recovery Act projects, DOE's goal is to generate and dispose of 
less than the total estimated volume of such debris--1.2 million cubic 
meters--shown in the figure. 

[End of figure] 

While DOE is using performance measures to track progress on most of 
its 84 Recovery Act projects, progress on 31 projects has not been 
tracked using any performance measures, for two main reasons. First, 
18 of the 31 projects do not yet have any corresponding performance 
measures assigned. According to a DOE Recovery Act Program official, 
performance measures are being developed for most of these 18 
projects. Five of the 18 projects will not be assigned any performance 
measures, however, because the work does not lend itself to meaningful 
performance measures, the work is almost complete, or earned value 
data are deemed sufficient to track the projects' progress, according 
to DOE. For example, DOE will rely primarily on earned value measures 
to track progress on a project to maintain and monitor the physical 
condition of inactive facilities at the Savannah River Site.[Footnote 
20] Second, the remaining 13 of 31 projects currently have performance 
measures assigned for tracking progress, but the planned work 
associated with those measures has not begun. For example, for a 
particular project at the Hanford Site to identify and dispose of 
contaminated soil, the performance measure is cubic meters of soil 
disposed of.[Footnote 21] But because work during the project's first 
several months involved identifying the extent of the contamination 
(before beginning actual excavation of contaminated soil), this 
particular performance measure will not be useful for tracking 
progress until the first planned disposal of contaminated soil in 
October 2010. 

For the remaining 53 projects that had performance measures in place 
as of March 2010, results were mixed. Of these projects, DOE reported 
in its monthly reports that 38 were meeting all their performance 
measure targets, and 15 were missing some or all of their targets (see 
fig 5). For example, a project at the Savannah River Site to treat and 
dispose of several types of solid waste had five performance measures 
tracking progress, as of March 2010, including metric tons of depleted 
uranium packaged for disposal, number of waste drums disposed of, and 
cubic meters of debris and soil disposed of.[Footnote 22] As of March 
2010, the project was falling short on three of its five performance 
measures. Among other aims, the project was supposed to prepare about 
11,600 metric tons of depleted uranium for disposal, but only about 
4,000 metric tons had actually been prepared because of a delayed 
start on the project, according to site officials. 

In reviewing projects' earned value cost and schedule target data and 
projects' associated performance measures, we found that the results 
as assessed by performance measures were sometimes inconsistent with 
the results shown by earned value data for cost and schedule targets. 
A given project might have met cost and schedule targets but have 
nevertheless fallen short in meeting performance measure targets. For 
example, at the Hanford Site, a project to dispose of contaminated 
soil and debris met or bettered its cost and schedule targets, but a 
related performance measure showed that none of the contaminated 
material had been disposed of as planned.[Footnote 23] Conversely, 
earned value data for a project to demolish contaminated buildings at 
Idaho National Laboratory showed that the project was not meeting its 
cost and schedule targets but was meeting all of its performance 
measures, such as square footage of facilities demolished.[Footnote 
24] In commenting on a draft of this report, DOE officials stated that 
earned value scores and other project performance information are 
intended to provide complementary insights into overall performance. 
Officials said that when differences among the indicators arise, 
headquarters officials follow up with federal and contractor officials 
at the site to determine the reasons for these differences. 

Figure 5: Performance of Recovery Act Projects, as of March 31, 2010: 

[Refer to PDF for image: 2 pie-charts] 

Projects not meeting both cost and schedule targets: 9 (11%); 
Projects meeting either cost or schedule targets (but not both): 18 
(21%); 
Projects meeting both cost and schedule targets: 57 (68%). 

Projects not meeting any performance targets: 4 (5%); 
Projects meeting some performance targets, missing others: 11 (13%); 
Projects not currently being tracked with performance measures: 31[B] 
(37%); 
Projects meeting all performance targets: 38[A] (45%). 

Source: GAO analysis of DOE data. 

[A] DOE considers performance to be meeting targets until it drops 
below 90 percent of the target. That is, work could be slightly under 
expectations--but not less than 90 percent of the target--and still be 
considered as meeting its target. 

[B] Some of these projects have performance measures in place, but 
those measures did not show any planned work through March 2010. 

[End of figure] 

DOE Has Taken Steps to Help Address Potential Problems but Continues 
to Face Key Challenges in Managing Projects and Measuring Their Impact: 

DOE's Recovery Act work is well into its second year, and the 
department faces familiar challenges. While DOE has taken steps to 
strengthen project management activities, as of March 2010, about one- 
third of projects did not achieve cost or schedule targets, or both. 
According to DOE officials, many schedule delays and cost problems 
could be traced to the same types of issues that have troubled DOE in 
the past--technical challenges, regulatory issues, and contracting 
delays. In addition, it is unclear how Recovery Act funding has 
affected job creation and the department's environmental cleanup goals 
or, in particular, to what degree this additional funding will reduce 
DOE's footprint, related environmental risks, and future cleanup costs. 

DOE Has Taken Steps to Help Projects Achieve Cost and Schedule 
Targets, Although Some Project Management Issues Remain: 

To help Recovery Act projects achieve their cost and schedule targets, 
DOE has taken steps to strengthen project management and oversight, 
such as adding federal oversight staff, increasing project reporting 
requirements, and placing tighter controls on when and how funds are 
disbursed to cleanup sites. First, DOE created a management structure 
to oversee Recovery Act projects separately from its cleanup projects 
funded by annual appropriations. At the headquarters level, DOE 
created an Environmental Management Recovery Act program office, where 
experienced DOE staff oversee site reporting and project review 
requirements for Recovery Act work. In addition, DOE assigned a 
certified on-site federal project director to oversee each Recovery 
Act project. All federal project directors for Recovery Act projects 
are senior managers certified by the Project Management Career 
Development Program Certification Review Board.[Footnote 25] DOE also 
created a new position for cleanup sites--a Recovery Act site 
representative--who reports project status to DOE's headquarters' 
Recovery Act program office and the Office of Environmental 
Management's Consolidated Business Center. Recovery Act site 
representatives are expected to monitor and report to the Recovery Act 
program office on technical, programmatic, regulatory, environmental, 
safety and health, and fiscal issues and concerns. The business center 
provides project management support, such as assistance in cost 
estimating and analysis. 

Second, DOE increased oversight via new and more frequent reporting 
requirements for Recovery Act work. In addition to reporting the 
number of jobs funded by the act, sites report to Environmental 
Management's Recovery Act program office--on a monthly, rather than 
quarterly, basis--projects' progress toward cost and schedule targets, 
as well as progress on performance measures. Sites also are to report 
whether contractors are completing certain tasks (milestones) on time, 
or whether contractors have missed their targets. Third, DOE has 
disbursed Recovery Act funding to sites in phases and required site 
officials to complete and document a series of tasks before funding 
can be released at each phase. For those cases where a site does not 
satisfactorily complete these tasks, DOE officials said they are 
prepared to withhold additional funding until the site has complied 
with the requirements. For example, one of the requirements for 
receiving funding is that a project receives a favorable project 
review, which involves an assessment of cost and schedule targets and 
project management plans. At the Savannah River Site, because a July 
2009 external independent review of a decontamination and decommission 
project found that the contractor had failed to produce sound cost and 
schedule estimates or risk management plans as required, DOE shifted 
$200 million it had intended to allocate to that contractor to a 
different project managed by a second contractor at the site. DOE 
subsequently implemented corrective actions at the site, including 
management changes. DOE has not taken similar steps to increase 
oversight of projects within its broader environmental cleanup 
program, and it is uncertain how or whether the actions taken to 
strengthen project management and oversight of Recovery Act projects 
will benefit management of DOE's larger portfolio of cleanup projects. 

As of March 2010, nearly one-third of Recovery Act projects were 
facing cost or schedule difficulties or both--despite DOE's efforts to 
choose low-risk, straightforward, shovel-ready projects for funding 
and to increase oversight--and overall spending was somewhat slower 
than expected. About halfway through DOE's planned Recovery Act 
program, slightly less than one-third of the department's $6 billion 
allocation had been spent. Officials attributed these difficulties to 
technical, regulatory, safety, and contracting problems--some of the 
same issues that have challenged DOE's project management in the past. 
For instance: 

* Technical challenges: Some Recovery Act projects faced technical 
problems, such as the discovery of unanticipated wastes that require 
additional time and effort to remediate or an inability to obtain 
necessary materials or equipment in a timely manner. For example, 
unexpected levels of contamination--discovered after cost and schedule 
targets under the Recovery Act had been established--have delayed the 
decommissioning and demolition of the former Experimental Breeder 
Reactor II (one of 52 nuclear reactors at Idaho National Laboratory). 
[Footnote 26] In determining the extent of contamination at the 
facility and planning the decommissioning effort, DOE discovered that 
a portion of the reactor contained a layer of asbestos insulation 
between the reactor's outer steel shell and its inner concrete lining 
and that the concrete lining was also filled with asbestos. As of May 
2010, according to DOE officials, the contractor had to slow the work 
to figure out how to best address this unexpected contamination, and 
as a result, this $118 million project is not expected to be completed 
by September 2011. At the Savannah River Site, a $304 million project 
to accelerate disposal of 5,000 cubic meters of transuranic 
waste[Footnote 27] cannot be completed until 2012 because of problems 
obtaining the proper containers for shipping the waste to the Waste 
Isolation Pilot Plant. When the site could not obtain large containers 
in a timely manner, workers instead packaged the waste into smaller 
containers--a process that was time-consuming and costly, officials 
said. In early June 2010, DOE officials said the Nuclear Regulatory 
Commission issued a certification of compliance for the large 
containers. According to a Savannah River Site official, the new 
containers will enable workers to package the waste more efficiently 
and at lower cost. Still, as a result of this delay, the project is 
expected to be completed in 2012, later than planned. 

* Regulatory issues: Some sites have also faced regulatory issues that 
require additional time to address. For example, DOE is working on a 
$38 million Recovery Act cleanup project at the Energy Technology 
Engineering Center[Footnote 28]--which was once involved in nuclear 
reactor development and testing--in partnership with the Environmental 
Protection Agency (EPA). Under an interagency agreement between EPA 
and DOE, EPA has responsibility for conducting a comprehensive 
characterization of radioactivity at the site, in accordance with 
Comprehensive Environmental Response, Compensation, and Liability Act 
(CERCLA) processes.[Footnote 29] When this CERCLA characterization is 
completed, DOE can develop an environmental impact statement and 
proceed with facility demolition and groundwater and soil cleanup. 
[Footnote 30] According to site officials, however, EPA's 
characterization activities are taking longer than expected. 

* Safety issues: Safety concerns also affected project progress. For 
example, a project at the West Valley Demonstration Project in New 
York[Footnote 31] to process transuranic wastes for disposal is not 
meeting either cost or schedule expectations, according to site 
officials, because of safety issues that have slowed progress. DOE 
site officials said that after work started on the project, air 
monitors showed that contamination in the work area exceeded allowable 
limits. Although the workers were already wearing respirators, the air 
monitors' warning prompted site officials to require workers to wear 
additional protective gear to complete the work. This additional gear, 
which includes bubble suits, is more cumbersome and contributed to 
slower-than-expected progress. Nevertheless, DOE expects the $4.2 
million effort to be completed by December 2010 as planned. 

* Contracting delays: Delays in finalizing new contracts or contract 
modifications have also led to cost and schedule difficulties. For 
example, three of the four indefinite-delivery/indefinite-quantity 
contracts[Footnote 32] at the Oak Ridge site in Tennessee have not 
been finalized. (Such contracts constitute standing arrangements for 
goods and services and introduce greater flexibility into the 
contracting process.) The four projects involve cleaning up 
contaminated soil and decontaminating or demolishing excess 
facilities, including demolishing a radioisotope development 
laboratory, a wooden building originally constructed in the 1940s for 
a variety of processing and research activities. Unoccupied since 
1998, the dilapidated building contains both radioactive and hazardous 
materials. The contract has not been finalized for this project and, 
as a result, work cannot begin. Site officials at Oak Ridge 
Reservation said that finalizing this type of contract often takes 
longer than they expect or plan for. In addition, one of the contracts 
for the Oak Ridge site was protested by prospective contractors, also 
delaying the projects. 

Recovery Act Impact on Job Creation and Environmental Cleanup Goals Is 
Unclear: 

In reporting the number of jobs created as a result of Recovery Act 
spending, DOE has reported three substantially different figures, 
which can be confusing and potentially misleading. Also unclear is how 
much impact Recovery Act spending will have on the department's 
environmental cleanup goals, such as reducing environmental risks from 
nuclear and hazardous wastes and long-term costs of maintaining excess 
facilities and monitoring stored wastes and contaminated soil and 
groundwater. 

Determining Impact of Recovery Act Spending on Job Creation Is 
Problematic Because DOE Calculates Jobs Created Using Three Different 
Methodologies: 

DOE has wrestled with calculating and reporting jobs created--a 
requirement of the Recovery Act--publicly reporting three vastly 
different figures. Recovery Act reporting requirements direct agencies 
to count hours worked under a prime contractor--the nonfederal entity 
that receives Recovery Act funding directly from the federal 
government.[Footnote 33] OMB guidance states that agencies are to 
report jobs created as full-time equivalents (FTE) calculated by 
totaling the number of hours charged by workers to Recovery Act 
projects in a given quarter and dividing the sum by the total number 
of work hours representing a full work schedule. 

While DOE has used this required figure, it has also chosen to 
calculate and publicize two additional figures that represent jobs 
created: (1) the sum of both prime contractor and subcontractor FTEs 
and (2) the number of people who have charged time to Recovery Act 
activities--without regard to the number of hours worked--which DOE 
refers to as "head count" or "lives touched." DOE officials stated 
that because the department relies largely on subcontractors to carry 
out the cleanup work, reporting only prime contractor FTEs 
substantially understates the employment impact of DOE's Recovery Act 
program. The number of prime contractor FTEs DOE reported to OMB as of 
March 2010 was 5,655, while the sum for both prime contractors and 
subcontractors for the same period was nearly twice that, at 10,018. 
The head count, or number of workers engaged for any length of time in 
Recovery Act work, was substantially higher still (see table 2). 

Table 2: Number of Recovery Act Cleanup Jobs Created by DOE, as 
Calculated According to OMB and DOE Guidance, as of March 31, 2010: 

Site: 1. Argonne National Laboratory (IL); 
OMB-required calculation (prime contractor FTEs): 93; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 129; 
DOE's additional calculations: Cumulative head count: 264. 

Site: 2. Brookhaven National Laboratory (NY); 
OMB-required calculation (prime contractor FTEs): 18; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 93; 
DOE's additional calculations: Cumulative head count: 172. 

Site: 3. Energy Technology Engineering Center (CA); 
OMB-required calculation (prime contractor FTEs): 5; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 15; 
DOE's additional calculations: Cumulative head count: 248. 

Site: 4. Hanford Site (WA): Office of River Protection; 
OMB-required calculation (prime contractor FTEs): 187; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 414; 
DOE's additional calculations: Cumulative head count: 1,235. 

Site: 4. Hanford Site (WA): Richland Operations Office; 
OMB-required calculation (prime contractor FTEs): 1,116; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 2,486; 
DOE's additional calculations: Cumulative head count: 5,197. 

Site: 5. Idaho National Laboratory (ID); 
OMB-required calculation (prime contractor FTEs): 760; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 786; 
DOE's additional calculations: Cumulative head count: 1,902. 

Site: 6. Los Alamos National Laboratory (NM); 
OMB-required calculation (prime contractor FTEs): 120; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 296; 
DOE's additional calculations: Cumulative head count: 653. 

Site: 7. Moab UMTRA Site(UT); 
OMB-required calculation (prime contractor FTEs): 148; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 227; 
DOE's additional calculations: Cumulative head count: 229. 

Site: 8. Mound Site (OH); 
OMB-required calculation (prime contractor FTEs): 7; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 42; 
DOE's additional calculations: Cumulative head count: 50. 

Site: 9. Nevada Test Site (NV); 
OMB-required calculation (prime contractor FTEs): 67; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 110; 
DOE's additional calculations: Cumulative head count: 545. 

Site: 10. Oak Ridge Reservation (TN); 
OMB-required calculation (prime contractor FTEs): 1,141; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 1,886; 
DOE's additional calculations: Cumulative head count: 3,749. 

Site: 11. Paducah Site (KY); 
OMB-required calculation (prime contractor FTEs): 165; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 253; 
DOE's additional calculations: Cumulative head count: 626. 

Site: 12. Portsmouth Site (OH); 
OMB-required calculation (prime contractor FTEs): 142; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 464; 
DOE's additional calculations: Cumulative head count: 794. 

Site: 13. Savannah River Site (SC); 
OMB-required calculation (prime contractor FTEs): 1,389; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 2,258; 
DOE's additional calculations: Cumulative head count: 3,356. 

Site: 14. Separations Process Research Unit (NY); 
OMB-required calculation (prime contractor FTEs): 32; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 119; 
DOE's additional calculations: Cumulative head count: 219. 

Site: 15. SLAC National Accelerator Laboratory (CA); 
OMB-required calculation (prime contractor FTEs): 32; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 42; 
DOE's additional calculations: Cumulative head count: 146. 

Site: 16. Waste Isolation Pilot Plant (NM); 
OMB-required calculation (prime contractor FTEs): 150; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 270; 
DOE's additional calculations: Cumulative head count: 504. 

Site: 17. West Valley Demonstration Project (NY); 
OMB-required calculation (prime contractor FTEs): 84; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 128; 
DOE's additional calculations: Cumulative head count: 377. 

Site: Total; 
OMB-required calculation (prime contractor FTEs): 5,655; 
DOE's additional calculations: Prime contractor plus subcontractor 
FTEs: 10,018; 
DOE's additional calculations: Cumulative head count: 20,266. 

Source: DOE. 

[End of table] 

DOE's job creation calculations are problematic because they are 
confusing and potentially misleading. DOE frequently publicizes all 
three figures to represent the employment impact of Recovery Act 
funding on communities near DOE cleanup sites, without explaining how 
the figures were calculated. But only FTEs for prime contractors are 
counted in a manner that can be compared with other federal recipients 
of Recovery Act funds. It is this number that DOE reports on the 
federal Web site FederalReporting.gov. DOE officials said they had 
tried to gain permission from OMB to include subcontractor FTEs in 
this official count, but OMB has not changed its guidance. In 
commenting on a draft of this report, however, DOE stated that federal 
acquisition regulations have changed and, effective with the third 
quarter of fiscal year 2010, DOE will report both prime contractor and 
subcontractor FTEs. Further, DOE's calculation of head count is 
potentially misleading for two reasons. First, counting the number of 
people carrying out Recovery Act work, rather than the time they have 
actually spent in such work, implies that one person engaged in 2 
hours of work per week is equivalent to one person engaged in 40 hours 
of work per week. The economic benefits to the worker, however, differ 
significantly. Second, the estimate includes a count of those people 
who contributed to the manufacture of materials or equipment purchased 
by prime contractors and subcontractors to support Recovery Act work, 
an estimate that is difficult to verify, according to site officials. 

The Impact of Recovery Act Spending on Cleanup and Other Goals Remains 
Unclear: 

In addition to inconsistencies in how the department measures job 
creation, DOE has no clear means of determining how cleanup work 
funded by the act will reduce environmental risk, if at all. While a 
key departmental goal for the funding is to reduce DOE's footprint, or 
area of ongoing cleanup activity, just what this goal entails is 
unclear. DOE is using a comprehensive list of existing measures to 
assess environmental cleanup performance, including additional 
measures developed under its Recovery Act program. Existing measures 
include such metrics as amount of hazardous material packaged or 
disposed of, number of facilities demolished, number of sites for 
which remediation has been completed, and number of sites closed. 
Recovery Act project-specific measures are similar to department 
measures, although more specific, such as number of groundwater wells 
installed or square feet of facilities demolished. These project-
specific performance measures, however, focus on outputs and are not 
directly linked to long-term outcomes such as reducing risks. For 
example, the performance measures do not indicate what impact 
installing groundwater wells or demolishing facilities will have on 
reducing risks to human health and the environment. Moreover, the way 
progress is measured is sometimes inconsistent, and many projects have 
no performance measures established to date. As a result, project-
specific performance measures reveal very little about the outcomes 
DOE intends to achieve with Recovery Act funding, in particular, how 
DOE will measure the impact that Recovery Act funding will have on the 
long-term condition of large tracts of land under DOE management or on 
DOE's footprint. Headquarters officials defined footprint reduction as 
"physical completion of activities with petition for regulatory 
approval to follow." Some federal cleanup site officials, however, 
said they were confused by DOE's footprint reduction goal and 
uncertain how they are to take credit for having achieved it. For 
example, it is not clear whether footprint reduction includes total 
square footage of facilities owned by DOE, acres of land surrounding 
those facilities and owned or controlled by DOE, contaminated soil and 
groundwater beneath the facilities, some combination of all of these 
things, or something else entirely. Without a clearly defined and 
consistent measure of its footprint, it will be difficult for DOE to 
report whether or how Recovery Act funding has affected progress 
toward this key DOE cleanup goal. 

Furthermore, it is also uncertain how much DOE can expect to save in 
life-cycle costs of its environmental cleanup program as a result of 
Recovery Act funding. DOE Recovery Act program officials estimated 
that as much as $4 billion in life-cycle savings would be realized by 
doing the work under Recovery Act funding sooner rather than later, as 
originally planned.[Footnote 34] Officials stated that savings are to 
be achieved by avoiding costs such as those for long-term maintenance, 
security, and waste monitoring. DOE's $4 billion estimate, however, 
includes an estimate for savings that could be achieved because of 
inflation--by avoiding the higher costs of materials and labor in the 
future. In addition, DOE's estimates do not take into account the time 
value of money. That is, they do not account for the fact that costs 
incurred in the future are worth less than costs incurred sooner. 
According to standard economic analysis, OMB guidance on benefit-cost 
analysis, as well as DOE's guidance on life-cycle cost analysis, life- 
cycle analyses should be based on cost adjusted for both inflation and 
the time value of money--that is, on cost in present-value dollars. In 
contrast, DOE's comparison of its base program life-cycle cost 
estimate and its Recovery Act program estimate is based on current 
dollars and does not correct for either the effect of inflation on 
prices or the time value of money. Our analysis of DOE's cost savings, 
taking the appropriate factors into account, found that DOE's $4 
billion savings estimate may be overstated by as much as 80 percent. 
GAO has previously taken issue with DOE's method of calculating 
savings in life-cycle costs.[Footnote 35] DOE officials have said that 
when estimating life-cycle cost savings from Recovery Act work, they 
prefer to use current dollars, which take into account increasing 
costs due to inflation. An official said that using current dollars 
provides for a more direct comparison with DOE's budget submission to 
Congress. 

Conclusions: 

DOE expected that Recovery Act funding would help it achieve several 
goals, including accelerating the cleanup effort and reducing the 
footprint of facilities and contamination at 17 of its sites, creating 
jobs, and reducing total remaining cleanup costs. As the halfway mark 
in DOE's Recovery Act work approaches, the department has made 
progress toward completing cleanup projects and the majority, although 
not all, of these projects appear to be meeting cost and schedule 
targets. In carrying out its Recovery Act work, DOE has implemented 
additional steps to address familiar contract and project management 
challenges, by providing stricter controls over how and when funds are 
disbursed to cleanup sites, increasing reporting requirements, and 
paying greater attention to project oversight. Although we do not yet 
know what effects each of these additional steps to improve project 
management and increase oversight of Recovery Act projects will 
ultimately have on DOE's ability to meet projects' cost and schedule 
targets, some of the steps could be found useful for Recovery Act 
cleanup work, as well as carry the potential to be beneficial for 
projects funded under annual appropriations. The department has been 
less successful in implementing steps to better assess the results of 
its Recovery Act work. Specifically, DOE faces challenges in 
accurately assessing the effects of Recovery Act spending on job 
creation, environmental risk, footprint reduction, and long-term 
cleanup costs. Regarding jobs created, OMB requires that job creation 
figures be calculated and reported using a standard methodology. DOE, 
however, has chosen to also use two additional methodologies to 
calculate and publicly report job creation figures, which potentially 
provides a misleading picture of actual jobs created. DOE sites also 
do not have a means of determining how cleanup funded by the act will 
reduce environmental risk, if at all, or how DOE will measure progress 
toward its goals for footprint reduction. Further, DOE is not 
following OMB's or its own internal guidance in calculating cost 
savings that might accrue from completing cleanup projects sooner 
using Recovery Act funding. The methodology chosen by the department 
appears to significantly overstate savings from Recovery Act spending. 
Without clear performance goals and consistent and meaningful 
methodologies for measuring outcomes stemming from Recovery Act 
spending, it will be difficult for the department or others to 
accurately assess the benefits gained from the $6 billion of Recovery 
Act funding directed to the department. 

Recommendations for Executive Action: 

To help ensure successful completion of Recovery Act projects and 
apply lessons learned to DOE's larger cleanup effort, we recommend 
that the Secretary of Energy direct the Assistant Secretary of 
Environmental Management to take the following four actions: 

* Determine whether additional project management and oversight steps 
adopted for Recovery Act projects, such as more frequent reporting, 
have proven beneficial and whether these steps would be effective and 
appropriate for DOE's cleanup projects funded under annual 
appropriations. 

* Clarify the methodology used to calculate any supplemental job 
creation figures in addition to prime contractor and subcontractor 
FTEs, such as head count--that is workers who have charged any amount 
of time to Recovery Act projects--so that users of this information 
fully understand what each number represents and its significance and 
limitations. 

* Develop clear, quantifiable, and consistent measures for determining 
the impact of Recovery Act funding on environmental risk. As part of 
this effort, clearly define what the DOE footprint consists of, 
determine how changes to the footprint will be measured, and ensure 
that all DOE sites report changes to their footprint in a consistent 
and comparable manner. 

* Ensure that savings estimates over the life of the cleanup projects 
are calculated according to OMB and DOE guidance, so that these 
estimates accurately represent potential savings and reflect costs 
adjusted for both inflation and the time value of money. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to DOE for its review and comment. 
In written comments, the Assistant Secretary for Environmental 
Management stated that DOE concurred with our four recommendations 
contained in the report and indicated that some of the actions we are 
recommending have already been taken. Regarding the first 
recommendation--to evaluate the effectiveness of additional project 
management and oversight steps adopted for Recovery Act projects and 
determine if these steps would be effective for projects funded under 
annual appropriations--DOE indicated that some steps had been taken. 
These include requiring more frequent reviews of projects. DOE stated 
it is still evaluating the potential benefit to the base program of 
other steps taken to manage Recovery Act projects. In responding to 
the second recommendation on the methods used to calculate job 
creation figures, DOE stated that a recent change to federal 
acquisition regulations, which will result in the reporting of both 
prime contractor and subcontractor jobs in FederalReporting.gov, will 
negate GAO's concern on the matter. Our concern, however, centered on 
ensuring that users of DOE's three job creation figures--prime 
contractor FTEs, prime contractor and subcontractor FTEs, and head 
count--understand exactly what the figures represent. The head count 
figure is not reported into FederalReporting.gov and, as we note in 
our report, was a significantly higher figure than prime contractor or 
subcontractor job figures. In its detailed comments, DOE stated that 
it has posted guidance on its Web site regarding the methodologies 
used to calculate job creation figures and will also include a one-
page explanation sheet with job numbers presented to stakeholders or 
the public. We have reworded this recommendation to enhance its 
clarity. Third, DOE stated that it agreed with GAO's recommendation to 
have clear, quantifiable, and consistent measures of footprint 
reduction and has taken steps to better define this concept and 
communicate the definition to all its sites. While we agree that DOE 
has made progress on defining footprint reduction, the focus of our 
recommendation was broader, emphasizing the development of clear, 
quantifiable, and consistent measures for determining the impact of 
Recovery Act funding on environmental risk. While we recognize that 
DOE collects information related to project risks, as it stated in its 
response, the information collected concerns risks associated with 
successfully carrying out a project, not quantifying the reduction in 
environmental risks themselves. DOE went on to point out that its 
performance measures are focused on outputs that are directly tied to 
cleanup of the site. Outputs, such as cubic meters of soil remediated, 
do provide a measure of work performed, but they may not easily 
translate into the outcome in terms of environmental risk reduction 
due to Recovery Act funds spent at each site. We maintain that DOE 
needs to continue to develop measures for determining the impact of 
Recovery Act funding on reducing environmental risks. DOE also 
expressed concern over the method we used to determine project 
performance, as well as our assessment that inconsistencies exist 
between some projects' cost and schedule performance and other 
measures. We modified the draft to address these concerns. In 
responding to our recommendation on calculating life-cycle cost 
savings, DOE agreed stating that it is currently following OMB and DOE 
guidance. As we noted in our report, however, the $4 billion in 
savings that DOE has stated will result from Recovery Act projects 
could be overstated by as much as 80 percent because the calculation 
does not take into account the time value of money and inflation. 

DOE's written comments are presented in appendix V. In addition, DOE 
provided detailed technical comments, which we incorporated as 
appropriate. 

We are sending copies of this report to the appropriate congressional 
committees, the Secretary of Energy, and other interested parties. The 
report is also available at no charge on the GAO Web site at 
[hyperlink, http://www.gao.gov]. 

If you or your staff members have any questions regarding this report, 
please contact me at (202) 512-3841 or aloisee@gao.gov. Contact points 
for our Offices of Congressional Relations and Public Affairs may be 
found on the last page of this report. GAO staff who made major 
contributions to this report are listed in appendix VI. 

Signed by: 

Gene Aloise: 
Director, Natural Resources and Environment: 

[End of section] 

Appendix I: Scope and Methodology: 

To determine how the Department of Energy (DOE) selected projects for 
funding under the American Recovery and Reinvestment Act of 2009 
(Recovery Act) and developed cost, schedule, and performance targets, 
we reviewed key provisions of the Recovery Act and Office of 
Management and Budget (OMB) guidance regarding the act. We also 
reviewed various DOE guidance documents regarding project management 
and project reviews (orders 413.3A, 413.3-8 and 413.3-9), cost-
estimating procedures (order 430.1-1), and the use of earned value 
management techniques (order 413.3-10). In addition, we reviewed key 
project planning and management documents. These included project 
operating plans, DOE assessments of project cost and schedule targets, 
and earned value management system certifications. We also reviewed 
OMB and DOE guidance on collecting and reporting data on jobs created 
and DOE's most recent performance accountability annual reports. To 
gain a better understanding of how projects were selected and the 
steps officials took to develop cost and schedule targets, we 
interviewed DOE headquarters officials and officials at each of the 17 
sites receiving Recovery Act funding--once after initial project 
implementation, and again several months later. We visited the four 
DOE cleanup sites receiving the bulk of the $6 billion in Recovery Act 
funding for environmental cleanup: (1) the Hanford Site, (2) Idaho 
National Laboratory, (3) the Oak Ridge Reservation, and (4) the 
Savannah River Site. For each site, we reviewed project documentation, 
interviewed officials, and observed Recovery Act work under way. We 
also selected a nonrandom sample of four of the costliest projects--
including soil and groundwater remediation, facility demolition, and 
disposal of waste--to better understand how the cost estimates were 
developed and to assess the reliability of the estimates for these 
projects. Two projects were at the Hanford Site and two at the 
Savannah River Site. Further information on the four projects appears 
in appendix II. 

To determine the status of the Recovery Act projects and the extent to 
which projects are achieving cost and schedule targets and performance 
measures, we used contractor data submitted to the Office of 
Environmental Management and assembled under its integrated planning, 
accounting, and budgeting system. Information we reviewed from this 
database consisted of cost and schedule targets; monthly cost and 
schedule performance; earned value management system data; and key 
agencywide, site, and project performance metrics. To assess the 
reliability of data we reviewed, we sent out questionnaires to DOE 
headquarters and site officials regarding the steps taken to ensure 
the accuracy of data related to measuring progress in meeting project 
cost and schedule targets, jobs created, and other project outcomes. 
Although in a few instances we found data of questionable reliability 
at some of the sites, we determined that, overall, these data were 
sufficiently reliable for the purposes of our report. 

To determine what key challenges DOE faced and the steps officials 
have taken to address these challenges, we reviewed independent 
internal and external project reviews, program reviews, and corrective 
action plans. We attended an April 2010 Environmental Management 
conference at which site officials exchanged information on their 
experiences implementing Recovery Act cleanup projects. We reviewed 
DOE Office of Inspector General reports on the Recovery Act and 
conferred with Inspector General staff. We interviewed headquarters 
officials and officials at all 17 sites and reviewed responses to the 
data reliability questionnaires sent to and completed by contractor 
and federal project management officials for all 84 projects. To 
recalculate the life-cycle cost savings that would result from the 
Recovery Act, we obtained DOE's life-cycle cost estimates for each 
project before and after the Recovery Act. We converted these 
estimates to constant dollars using the appropriate inflation factors 
for each project provided to us by DOE. We then converted those 
estimates to present value using real discount rates from OMB. For 
each project, we used the discount rate for the time period that most 
closely corresponded with the length of the project under 
consideration. 

We conducted this performance audit from June 2009 to July 2010, in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: Description of Four Projects Reviewed in Depth: 

We selected four Recovery Act projects for an in-depth review of their 
cost and schedule estimates and the reliability of these estimates. 
These projects came from the list of projects funded at the two DOE's 
sites receiving the most Recovery Act funding--the Hanford and 
Savannah River sites. 

Hanford: 

DOE's Hanford Site in southeastern Washington State was established in 
1943 to produce nuclear materials for the nation's defense. Although 
DOE stopped producing nuclear material at Hanford in 1989, millions of 
gallons of high-level radioactive waste from production still remain 
on site. The primary mission at Hanford is site cleanup, including 
waste removal and containment and soil and groundwater remediation to 
protect the nearby Columbia River. The Richland Operations Office at 
the Hanford Site received $1.6 billion from the Recovery Act for 
cleanup activities and is funding 10 projects.[Footnote 36] The 
projects are to demolish nuclear and support facilities, clean up 
waste sites and contaminated groundwater, and retrieve solid waste 
from burial grounds. Recovery Act funding to accelerate cleanup of 
facilities, waste sites, and groundwater along the Columbia River will 
help the site decrease its active area of cleanup from 586 to 75 
square miles or less by 2015, which is more than 5 years ahead of the 
current schedule. We selected the following two Hanford projects for 
in-depth cost and schedule reliability review: 

* U Plant D&D:[Footnote 37] The U Plant is a former processing 
facility on the site's Central Plateau, where special nuclear 
materials were recovered and converted for shipment to other sites for 
weapons manufacture and assembly. Plant facilities were built in 1944 
and operated until 1964. Other than minor decontamination work, the 
facility has been unused and deserted since operations ceased. The 
Recovery Act project's scope includes preparing the U Plant for 
decommissioning by clearing the facility of equipment and grouting the 
reactor's cells, as well as deactivating, decommissioning, 
decontaminating, and demolishing 16 ancillary facilities. The project 
is expected to be completed by September 2011, at a cost of $257 
million. 

* 100 K Area remediation:[Footnote 38] The 100 K Area comprises two 
former plutonium production reactors along the Columbia River. None of 
the reactors is still operational, and contamination from the former 
production processes and facilities is a key cleanup objective. The 
scope of this Recovery Act project includes decontaminating and 
demolishing 30 industrial and radiological facilities associated with 
the reactors within the 100 K area, as well as cleaning up or 
characterizing 23 waste sites. The project is expected to be completed 
by September 2011, at a cost of $203 million. 

On the basis of our in-depth reviews, DOE partially met industry best 
practices for ensuring that the estimates were accurate, 
comprehensive, well documented, and credible as detailed in GAO cost 
estimating guide.[Footnote 39] While DOE carried out many best 
practices for developing its estimates, in some instances, it did not. 
For example, when preparing estimates for both of these projects, DOE 
did not create a plan to ensure that the estimates were developed by 
people with expertise in cost and schedule estimating and did not test 
the reasonableness of its estimates against known costs for similar 
activities. 

Savannah River: 

The Savannah River Site was constructed in the early 1950s to produce 
tritium and plutonium for use in nuclear weapons. Historically the 
site has supported five nuclear reactors, two chemical separation 
plants, a heavy-water extraction plant, a nuclear fuel and target 
fabrication facility, a tritium extraction facility, and waste 
management facilities. Although the site no longer produces plutonium, 
some of its missions continue, such as the extraction of tritium for 
nuclear warheads. The site received $1.6 billion under the Recovery 
Act, which is funding 14 projects. Overall, Recovery Act projects at 
Savannah River are expected to accelerate transuranic waste disposal 
by 4 years, and the decommissioning of the nuclear facilities by at 
least 5 years. We selected two of Savannah River's Recovery Act 
projects for in-depth cost and schedule estimate and reliability 
review: 

* Accelerated transuranic waste disposition:[Footnote 40] The purpose 
of this project is to accelerate the characterization, packaging, and 
disposal of 4,200 cubic meters of transuranic waste from the site's 
former production of nuclear weapons. The waste will then be shipped 
to DOE's Waste Isolation Pilot Plant for permanent disposal. In 
addition, the project's current scope includes repackaging of 800 
cubic meters of transuranic waste into smaller containers in 
preparation for shipment. The project is expected to be completed in 
September 2012, at a cost of $304 million.[Footnote 41] 

* P&R Area completion general plant projects and operations:[Footnote 
42] "P&R Area" refers to the P and R reactors, two of the site's first 
nuclear production reactors, which started operating in 1953 and 1954, 
respectively. The buildings and associated infrastructure, such as 
railroad tracks used to transfer radioactive material from the 
reactors to other site facilities, have remained unused since the 
facilities ceased operations in 1964 (R reactor) and 1988 (P reactor). 
The scope of the Recovery Act project includes decommissioning the two 
reactors, as well as removing the railroad tracks. The project also 
includes remediation of contaminated soil under the tracks. The 
project is expected to advance completion of the P and R area cleanup 
by 5 to 6 years. 

On the basis of our in-depth reviews of these two projects, DOE 
partially met best practices for ensuring that the estimates were 
credible, comprehensive, and well documented and minimally met best 
practices associated with ensuring that the estimates were accurate. 
For example, DOE did not compare its cost and schedule estimates to an 
independent cost estimate, a step that helps ensure accuracy. Instead, 
the department relied on internal project reviews, which were not as 
rigorous. 

[End of section] 

Appendix III: Recovery Act Project Cost Data through March 2010: 

Dollars in thousands: 

Argonne National Laboratory (IL): 

Project number: 1. CH-ANLE-0040.NEW.R1.1; 
Project description: D&D:[B] Building 310; 
Total estimated project cost[A]: $14,017; 
Cumulative spent (percentage of total cost): $1,602 (11%). 

Project number: 2. CH-ANLE-0040.NEW.R1.2; 
Project description: D&D: Building 330; 
Total estimated project cost[A]: $34,200; 
Cumulative spent (percentage of total cost): $2,459 (7%). 

Project number: 3. CH-ANLE-0040.NEW.R1.3; 
Project description: D&D: Alpha-Gamma Hot Cell Facility; 
Total estimated project cost[A]: $26,482; 
Cumulative spent (percentage of total cost): $4,042 (15%). 

Project number: 4. CH-ANLE-0040.NEW.R1.4; 
Project description: TRU[C] waste processing; 
Total estimated project cost[A]: $23,567; 
Cumulative spent (percentage of total cost): $7,458 (32%). 

Argonne National Laboratory (IL): Total; 
Total estimated project cost[A]: $98,266; 
Cumulative spent (percentage of total cost): $15,561 (16%). 

Brookhaven National Laboratory (NY): 

Project number: 5. BRNL-0040.R1; 
Project description: D&D: Brookhaven Graphite Research Reactor; 
Total estimated project cost[A]: $17,208; 
Cumulative spent (percentage of total cost): $14,378 (84%). 

Project number: 6. BRNL-0041.R1; 
Project description: D&D: High Flux Beam Reactor; 
Total estimated project cost[A]: $20,932; 
Cumulative spent (percentage of total cost): 8,842 $(42%). 

Project number: 7. BRNL-0041.NEW.R1; 
Project description: D&D: High Flux Beam Reactor; 
Total estimated project cost[A]: $4,215; 
Cumulative spent (percentage of total cost): $3,469 (82%). 

Brookhaven National Laboratory (NY): Total; 
Total estimated project cost[A]: $42,355; 
Cumulative spent (percentage of total cost): $26,689 (63%). 

Energy Technology Engineering Center (CA): 

Project number: 8. CBC-ETEC-0040.R1.1; 
Project description: D&D: EPA radiological characterization; 
Total estimated project cost[A]: $38,300; 
Cumulative spent (percentage of total cost): $2,775 (7%). 

Project number: 9. CBC-ETEC-0040.R1.2; 
Project description: Soil and groundwater cleanup; 
Total estimated project cost[A]: $15,875; 
Cumulative spent (percentage of total cost): $3,332 (21%). 

Energy Technology Engineering Center (CA): Total; 
Total estimated project cost[A]: 54,175; 
Cumulative spent (percentage of total cost): 6,107 (11%). 

Hanford Site: Office of River Protection (WA): 

Project number: 10. ORP-0014.R1.1; 
Project description: Tank waste support: Tank farm infrastructure 
upgrades; 
Total estimated project cost[A]: $100,983; 
Cumulative spent (percentage of total cost): $20,968 (21%). 

Project number: 11. ORP-0014.R1.2; 
Project description: Tank waste support: Other infrastructure upgrades; 
Total estimated project cost[A]: $26,089; 
Cumulative spent (percentage of total cost): $3,473 (13%). 

Project number: 12. ORP-0014.R1.3; 
Project description: Tank waste support: Facility upgrades; 
Total estimated project cost[A]: $92,786; 
Cumulative spent (percentage of total cost): $13,808 (15%). 

Project number: 13. ORP-0014.R1.4; 
Project description: Tank waste support: Waste feed infrastructure 
upgrades; 
Total estimated project cost[A]: $62,351; 
Cumulative spent (percentage of total cost): $9,093 (15%). 

Project number: 14. ORP-0014.R1.5; 
Project description: Tank waste support: SY transfer line upgrade; 
Total estimated project cost[A]: $17,900; 
Cumulative spent (percentage of total cost): $988 (6%). 

Hanford Site: Office of River Protection (WA): Total; 
Total estimated project cost[A]: $300,109; 
Cumulative spent (percentage of total cost): $48,330 (16%). 

Hanford Site: Richland Operations Office (WA): 

Project number: 15. RL-0011.R1; 
Project description: D&D: Plutonium Finishing Plant; 
Total estimated project cost[A]: $330,200; 
Cumulative spent (percentage of total cost): $79,470 (24%). 

Project number: 16. RL-0013C.R1.1; 
Project description: Solid waste disposal: Mixed low-level waste 
treatment; 
Total estimated project cost[A]: $50,389; 
Cumulative spent (percentage of total cost): $20,873 (41%). 

Project number: 17. RL-0013C.R1.2; 
Project description: TRU waste processing; 
Total estimated project cost[A]: $178,110; 
Cumulative spent (percentage of total cost): $57,159 (32%). 

Project number: 18. RL-0030.R1; 
Project description: Soil and groundwater cleanup: Treatment and 
monitoring; 
Total estimated project cost[A]: $145,771; 
Cumulative spent (percentage of total cost): $44,267 (30%). 

Project number: 19. RL-0040.R1.1; 
Project description: D&D: U Plant/other; 
Total estimated project cost[A]: $256,500; 
Cumulative spent (percentage of total cost): v70,579 (28%). 

Project number: 20. RL-0040.R1.2; 
Project description: D&D: Outer Zone; 
Total estimated project cost[A]: $114,900; 
Cumulative spent (percentage of total cost): $15,222 (13%). 

Project number: 21. RL-0041.R1.1; 
Project description: D&D: 100 K Area; 
Total estimated project cost[A]: $266,417; 
Cumulative spent (percentage of total cost): $44,293 (17%). 

Project number: 22. RL-0041.R1.2; 
Project description: D&D: Disposal facility expansion; 
Total estimated project cost[A]: $36,683; 
Cumulative spent (percentage of total cost): $25,412 (69%). 

Project number: 23. RL-0041.R1.3; 
Project description: D&D: Remedial action/footprint reduction; 
Total estimated project cost[A]: $139,117; 
Cumulative spent (percentage of total cost): $7,896 (6%). 

Project number: 24. RL-0041.R2; 
Project description: D&D: 618-10 burial grounds; 
Total estimated project cost[A]: $77,814; 
Cumulative spent (percentage of total cost): $11,345 (15%). 

Hanford Site: Richland Operations Office (WA): Total; 
Total estimated project cost[A]: 1,595,901; 
Cumulative spent (percentage of total cost): 376,516 (24%). 

Idaho National Laboratory (ID): 

Project number: 25. ID-0013.R1; 
Project description: TRU waste processing; 
Total estimated project cost[A]: $30,000; 
Cumulative spent (percentage of total cost): $16,935 (56%). 

Project number: 26. ID-0013.NEW.R1; 
Project description: TRU waste processing; 
Total estimated project cost[A]: $100,000; 
Cumulative spent (percentage of total cost): $39,501 (40%). 

Project number: 27. ID-0030B.R1.1; 
Project description: Soil and groundwater cleanup: Buried waste; 
Total estimated project cost[A]: $75,428; 
Cumulative spent (percentage of total cost): $13,860 (18%). 

Project number: 28. ID-0030B.R1.2; 
Project description: Soil and groundwater cleanup: In-situ grouting; 
Total estimated project cost[A]: $22,666; 
Cumulative spent (percentage of total cost): $1,693 (7%). 

Project number: 29. ID-0030B.R1.3; 
Project description: Soil and groundwater cleanup: Operations; 
Total estimated project cost[A]: $21,900; 
Cumulative spent (percentage of total cost): $17,520 (80%). 

Project number: 30. ID-0040B.R1.1; 
Project description: D&D: 39 facilities; 
Total estimated project cost[A]: $47,969; 
Cumulative spent (percentage of total cost): $30,314 (63%). 

Project number: 31. ID-0040B.R1.2; 
Project description: D&D: 29 facilities; 
Total estimated project cost[A]: v53,481; 
Cumulative spent (percentage of total cost): $18,518 (35%). 

Project number: 32. ID-0040B.NEW.R1.3; 
Project description: D&D: Nuclear Energy facilities; 
Total estimated project cost[A]: $118,061; 
Cumulative spent (percentage of total cost): $21,110 (18%). 

Idaho National Laboratory (ID): Total; 
Total estimated project cost[A]: $469,505; 
Cumulative spent (percentage of total cost): $159,451 (34%). 

Los Alamos National Laboratory (NM): 

Project number: 33. VL-LANL-0030.R1.1; 
Project description: Soil and groundwater cleanup: Material Disposal 
Area B; 
Total estimated project cost[A]: $93,988; 
Cumulative spent (percentage of total cost): $17,820 (19%). 

Project number: 34. VL-LANL-0030.R1.2; 
Project description: Soil and groundwater cleanup: Groundwater wells; 
Total estimated project cost[A]: $44,977; 
Cumulative spent (percentage of total cost): $16,272 (36%). 

Project number: 35. VL-LANL-0040-D.R1; 
Project description: D&D: Defense-related facilities; 
Total estimated project cost[A]: $58,022; 
Cumulative spent (percentage of total cost): $11,681 (20%). 

Project number: 36. VL-LANL-0040-N.R1; 
Project description: D&D: Nondefense-related facilities; 
Total estimated project cost[A]: $14,775; 
Cumulative spent (percentage of total cost): $4,315 (29%). 

Los Alamos National Laboratory (NM): Total; 
Total estimated project cost[A]: $211,762; 
Cumulative spent (percentage of total cost): $50,088 (24%). 

Moab UMTRA Site (UT): 

Project number: 37. CBC-MOAB-0031.R1; 
Project description: Soil and groundwater cleanup: Mill tailings; 
Total estimated project cost[A]: $108,350; 
Cumulative spent (percentage of total cost): $38,214 (35%). 

Moab UMTRA Site (UT): Total; 
Total estimated project cost[A]: 108,350; 
Cumulative spent (percentage of total cost): 38,214 (35%). 

Mound Site (OH): 

Project number: 38. OH-MB-0031.NEW.R1; 
Project description: Soil and groundwater cleanup: Operable Unit 1; 
Total estimated project cost[A]: $19,700; 
Cumulative spent (percentage of total cost): $9,242 (47%). 

Mound Site (OH): Total; 
Total estimated project cost[A]: $19,700; 
Cumulative spent (percentage of total cost): $9,242 (47%). 

Nevada Test Site (NV): 

Project number: 39. VL-NV-0030.R1; 
Project description: Soil and groundwater cleanup; 
Total estimated project cost[A]: $45,069; 
Cumulative spent (percentage of total cost): $20,024 (44%). 

Nevada Test Site (NV): Total; 
Total estimated project cost[A]: $45,069; 
Cumulative spent (percentage of total cost): $20,024 (44%). 

Oak Ridge Reservation (TN): 

Project number: 40. OR-0013B.R1.1; 
Project description: TRU waste processing; 
Total estimated project cost[A]: $124,500; 
Cumulative spent (percentage of total cost): $31,578 (25%). 

Project number: 41. OR-0040.R1; 
Project description: D&D: East Tennessee Technology Park; 
Total estimated project cost[A]: v118,000; 
Cumulative spent (percentage of total cost): $18,885 (16%). 

Project number: 42. OR-0041.R1.1; 
Project description: D&D: Y-12 facility; 
Total estimated project cost[A]: $5,000; 
Cumulative spent (percentage of total cost): $2,417 (48%). 

Project number: 43. OR-0041.R1.2; 
Project description: D&D: Y-12 remediation preparation; 
Total estimated project cost[A]: $43,000; 
Cumulative spent (percentage of total cost): $14,326 (33%). 

Project number: 44. OR-0041.R1.3; 
Project description: D&D: Disposal facility expansion; 
Total estimated project cost[A]: $45,000; 
Cumulative spent (percentage of total cost): $16,026 (36%). 

Project number: 45. OR-0041.NEW.R1.1; 
Project description: D&D: Y-12 excess material; 
Total estimated project cost[A]: $147,000; 
Cumulative spent (percentage of total cost): $41,025 (28%). 

Project number: 46. OR-0041.NEW.R1.2; 
Project description: D&D: Y-12 biology complex; 
Total estimated project cost[A]: $29,853; 
Cumulative spent (percentage of total cost): $7,224 (24%). 

Project number: 47. OR-0041.NEW.R1.3; 
Project description: D&D: Y-12 9206 filter house; 
Total estimated project cost[A]: $7,000; 
Cumulative spent (percentage of total cost): $3,503 (50%). 

Project number: 48. OR-0042.R1.1; 
Project description: D&D: Defense legacy material removal; 
Total estimated project cost[A]: $10,450; 
Cumulative spent (percentage of total cost): $170 (2%). 

Project number: 49. OR-0042.R1.2; 
Project description: D&D: Defense facility demolition; 
Total estimated project cost[A]: $38,922; 
Cumulative spent (percentage of total cost): $12,366 (32%). 

Project number: 50. OR-0042.R1.3; 
Project description: D&D: Defense remedial actions; 
Total estimated project cost[A]: $83,100; 
Cumulative spent (percentage of total cost): $7,868 (9%). 

Project number: 51. OR-0042.NEW.R2.1; 
Project description: D&D: Nondefense legacy material removal; 
Total estimated project cost[A]: $35,769; 
Cumulative spent (percentage of total cost): $649 (2%). 

Project number: 52. OR-0042.NEW.R2.2; 
Project description: D&D: 2000 complex; 
Total estimated project cost[A]: $12,968; 
Cumulative spent (percentage of total cost): v4,968 (38%). 

Project number: 53. OR-0042.NEW.R2.3; 
Project description: D&D: Misc. facility demolition; 
Total estimated project cost[A]: $22,000; 
Cumulative spent (percentage of total cost): $3,493 (16%). 

Oak Ridge Reservation (TN): Total; 
Total estimated project cost[A]: $722,562; 
Cumulative spent (percentage of total cost): $164,498 (23%). 

Paducah Site (KY): 

Project number: 54. PA-0040.R1.1; 
Project description: D&D: C-410; 
Total estimated project cost[A]: $11,040; 
Cumulative spent (percentage of total cost): $3,001 (27%). 

Project number: 55. PA-0040.R1.2; 
Project description: D&D: C-340; 
Total estimated project cost[A]: $36,301; 
Cumulative spent (percentage of total cost): $8,319 (23%). 

Project number: 56. PA-0040.R1.3; 
Project description: D&D: C-746-A; 
Total estimated project cost[A]: $31,500; 
Cumulative spent (percentage of total cost): $9,212 (29%). 

Paducah Site (KY): Total; 
Total estimated project cost[A]: $78,841; 
Cumulative spent (percentage of total cost): $20,532 (26%). 

Portsmouth Site (OH): 

Project number: 57. PO-0013.R1; 
Project description: Solid waste disposal: UMC disposition; 
Total estimated project cost[A]: $15,700; 
Cumulative spent (percentage of total cost): $4,767 (30%). 

Project number: 58. PO-0040.R1.1; 
Project description: D&D: X-701B plume remediation; 
Total estimated project cost[A]: $48,600; 
Cumulative spent (percentage of total cost): $15,191 (31%). 

Project number: 59. PO-0040.R1.2; 
Project description: D&D: X-533; 
Total estimated project cost[A]: $20,600; 
Cumulative spent (percentage of total cost): $5,456 (26%). 

Project number: 60. PO-0040.R1.3; 
Project description: D&D: X-633; 
Total estimated project cost[A]: $17,400; 
Cumulative spent (percentage of total cost): $6,381 (37%). 

Project number: 61. PO-0040.R1.4; 
Project description: D&D: X-760; 
Total estimated project cost[A]: 15,900; 
Cumulative spent (percentage of total cost): 2,282 (14%). 

Portsmouth Site (OH): Total; 
Total estimated project cost[A]: $118,200; 
Cumulative spent (percentage of total cost): $34,077 (29%). 

Savannah River Site (SC): 

Project number: 62. SR-0011C.R1.1; 
Project description: TRU waste processing: Canyon complex support; 
Total estimated project cost[A]: $33,974; 
Cumulative spent (percentage of total cost): $25,692 (76%). 

Project number: 63. SR-0013.R1.1; 
Project description: Solid waste disposal; 
Total estimated project cost[A]: $324,469; 
Cumulative spent (percentage of total cost): $167,678 (52%). 

Project number: 64. SR-0013.R1.2; 
Project description: TRU waste processing; 
Total estimated project cost[A]: $303,596; 
Cumulative spent (percentage of total cost): $82,830 (27%). 

Project number: 65. SR-0014C.R1.1; 
Project description: Tank waste support: Waste systems 
recapitalization; 
Total estimated project cost[A]: $174,000; 
Cumulative spent (percentage of total cost): $24,958 (14%). 

Project number: 66. SR-0014C.R1.PEN; 
Project description: Tank waste support: Contractor pension payment; 
Total estimated project cost[A]: $26,000; 
Cumulative spent (percentage of total cost): $4,919 (19%). 

Project number: 67. SR-0030.R1.1; 
Project description: D&D: P and R Area completion; 
Total estimated project cost[A]: $165,490; 
Cumulative spent (percentage of total cost): $85,393 (52%). 

Project number: 68. SR-0030.R1.2; 
Project description: D&D: P reactor; 
Total estimated project cost[A]: $142,200; 
Cumulative spent (percentage of total cost): $1,052 (1%). 

Project number: 69. SR-0030.R1.3; 
Project description: D&D: P ash basin; 
Total estimated project cost[A]: $30,000; 
Cumulative spent (percentage of total cost): $5,188 (17%). 

Project number: 70. SR-0030.R1.4; 
Project description: D&D: R reactor; 
Total estimated project cost[A]: $149,200; 
Cumulative spent (percentage of total cost): $3,727 (2%). 

Project number: 71. SR-0030.R1.5; 
Project description: D&D: R ash basin; 
Total estimated project cost[A]: $11,800; 
Cumulative spent (percentage of total cost): v3,668 (31%). 

Project number: 72. SR-0030.R2.1; 
Project description: D&D: M and D Area completion; 
Total estimated project cost[A]: v17,070; 
Cumulative spent (percentage of total cost): $8,255 (48%). 

Project number: 73. SR-0030.R3.1; 
Project description: D&D: Sitewide completion; 
Total estimated project cost[A]: $220,704; 
Cumulative spent (percentage of total cost): $94,260 (43%). 

Project number: 74. SR-0030.R3.2; 
Project description: D&D: Test reactor decommissioning; 
Total estimated project cost[A]: $10,720; 
Cumulative spent (percentage of total cost): $708 (7%). 

Project number: 75. SR-0040.R1.1; 
Project description: D&D: Surveillance and maintenance; 
Total estimated project cost[A]: $5,846; 
Cumulative spent (percentage of total cost): $2,567 (44%). 

Savannah River Site (SC): Total; 
Total estimated project cost[A]: $1,615,069; 
Cumulative spent (percentage of total cost): $510,895 (32%). 

Separations Process Research Unit (NY): 

Project number: 76. VL-SPRU-0040.R1.1; 
Project description: D&D: Building G2 and H2; 
Total estimated project cost[A]: $37,000; 
Cumulative spent (percentage of total cost): $13,274 (36%). 

Project number: 77. VL-SPRU-0040.R1.2; 
Project description: D&D: Contaminated soil removal, North Field; 
Total estimated project cost[A]: v14,775; 
Cumulative spent (percentage of total cost): $4,829 (33%). 

Separations Process Research Unit (NY): Total; 
Total estimated project cost[A]: $51,775; 
Cumulative spent (percentage of total cost): $18,103 (35%). 

SLAC National Accelerator Laboratory (CA): 

Project number: 78. CBC-SLAC-0030.R1; 
Project description: Soil and groundwater cleanup; 
Total estimated project cost[A]: $7,925; 
Cumulative spent (percentage of total cost): $5,225 (66%). 

SLAC National Accelerator Laboratory (CA): Total; 
Total estimated project cost[A]: $7,925; 
Cumulative spent (percentage of total cost): $5,225 (66%). 

Waste Isolation Pilot Plant (NM): 

Project number: 79. CB-0080.R1; 
Project description: Operate waste disposal facility; 
Total estimated project cost[A]: $53,287; 
Cumulative spent (percentage of total cost): $17,953 (34%). 

Project number: 80. CB-0081.R1; 
Project description: Waste characterization; 
Total estimated project cost[A]: $102,868; 
Cumulative spent (percentage of total cost): $31,660 (31%). 

Project number: 81. CB-0090.R1; 
Project description: TRU waste processing; 
Total estimated project cost[A]: $16,200; 
Cumulative spent (percentage of total cost): $2,248 (14%). 

Waste Isolation Pilot Plant (NM): Total; 
Total estimated project cost[A]: $172,355; 
Cumulative spent (percentage of total cost): $51,861 (30%). 

West Valley Demonstration Project (NY): 

Project number: 82. OH-WV-0013.R1; 
Project description: TRU waste processing; 
Total estimated project cost[A]: $4,200; 
Cumulative spent (percentage of total cost): $2,234 (53%). 

Project number: 83. OH-WV-0040.R1.1; 
Project description: D&D: Main plant; 
Total estimated project cost[A]: $42,400; 
Cumulative spent (percentage of total cost): $11,802 (28%). 

Project number: 84. OH-WV-0040.R1.2; 
Project description: D&D: Other facilities; 
Total estimated project cost[A]: $27,300; 
Cumulative spent (percentage of total cost): $7,961 (29%). 

West Valley Demonstration Project (NY): Total; 
Total estimated project cost[A]: $73,900; 
Cumulative spent (percentage of total cost): $21,997 (30%). 

Complexwide total; 
Total estimated project cost[A]: $5,785,819; 
Cumulative spent (percentage of total cost): $1,577,410 (27%). 

[End of table] 

[A] Total estimated and cumulative project cost does not generally 
include contractor fee, management reserve, or contingency funds. As a 
result, these totals may not equal the amounts of Recovery Act funds 
allocated and costed overall to each site. 

[B] D&D = deactivation, decommissioning, decontamination, demolition, 
or a combination of these activities. 

[C] TRU = transuranic. 

Source: GAO analysis of DOE data. 

[End of section] 

Appendix IV: Recovery Act Project Performance through March 2010: 

Argonne National Laboratory (IL): 

Project number: 1. CH-ANLE-0040.NEW.R1.1; 
Project description: D&D: Building 310; 
Cost target: Positive; 
Schedule target: [Empty]; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work. 

Project number: 2. CH-ANLE-0040.NEW.R1.2; 
Project description: D&D: Building 330; 
Cost target: Positive; 
Schedule target: [Empty]; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work. 

Project number: 3. CH-ANLE-0040.NEW.R1.3; 
Project description: D&D: Alpha-Gamma Hot Cell Facility; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Negative. 

Project number: 4. CH-ANLE-0040.NEW.R1.4; 
Project description: TRU waste processing; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive; Performance 
measure with no planned work. 

Brookhaven National Laboratory (NY): 

Project number: 5. BRNL-0040.R1; 
Project description: D&D: Brookhaven Graphite Research Reactor; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work; Performance measure 
with no planned work. 

Project number: 6. BRNL-0041.R1; 
Project description: D&D: High Flux Beam Reactor; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive; Performance 
measure with no planned work. 

Project number: 7. BRNL-0041.NEW.R1; 
Project description: D&D: High Flux Beam Reactor; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive. 

Energy Technology Engineering Center (CA): 

Project number: 8. CBC-ETEC-0040.R1.1; 
Project description: D&D: EPA radiological characterization; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 9. CBC-ETEC-0040.R1.2; 
Project description: Soil and groundwater cleanup; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work. 

Hanford Site: Office of River Protection (WA): 

Project number: 10. ORP-0014.R1.1; 
Project description: Tank waste support: Tank farm infrastructure 
upgrades; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive; Positive; 
Positive; Positive. 

Project number: 11. ORP-0014.R1.2; 
Project description: Tank waste support: Other infrastructure upgrades; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work. 

Project number: 12. ORP-0014.R1.3; 
Project description: Tank waste support: Facility upgrades; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive; Positive; 
Positive; Positive; Positive. 

Project number: 13. ORP-0014.R1.4; 
Project description: Tank waste support: Waste feed infrastructure 
upgrades; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work. 

Project number: 14. ORP-0014.R1.5; 
Project description: Tank waste support: SY transfer line upgrade; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: [Empty]. 

Hanford Site: Richland Operations Office (WA): 

Project number: 15. RL-0011.R1; 
Project description: D&D: Plutonium Finishing Plant; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Negative. 

Project number: 16. RL-0013C.R1.1; 
Project description: Solid waste disposal: Mixed low-level waste 
treatment; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive. 

Project number: 17. RL-0013C.R1.2; 
Project description: TRU waste processing; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: Positive; Positive; Positive. 

Project number: 18. RL-0030.R1; 
Project description: Soil and groundwater cleanup: Treatment and 
monitoring; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive. 

Project number: 19. RL-0040.R1.1; 
Project description: D&D: U Plant/other; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Negative; Negative; 
Performance measure with no planned work; Performance measure with no 
planned work. 

Project number: 20. RL-0040.R1.2; 
Project description: D&D: Outer Zone; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: Positive; Positive; Positive; Positive; 
Positive; Positive; Negative; Performance measure with no planned work; 

Project number: 21. RL-0041.R1.1; 
Project description: D&D: 100 K Area; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Negative; Negative; Negative. 

Project number: 22. RL-0041.R1.2; 
Project description: D&D: Disposal facility expansion; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive. 

Project number: 23. RL-0041.R1.3; 
Project description: D&D: Remedial action/footprint reduction; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Negative; Negative; Performance measure with 
no planned work. 

Project number: 24. RL-0041.R2; 
Project description: D&D: 618-10 burial grounds; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work. 

Idaho National Laboratory (ID): 

Project number: 25. ID-0013.R1; 
Project description: TRU waste processing; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive. 

Project number: 26. ID-0013.NEW.R1; 
Project description: TRU waste processing; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive. 

Project number: 27. ID-0030B.R1.1; 
Project description: Soil and groundwater cleanup: Buried waste; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: [Empty]. 

Project number: 28. ID-0030B.R1.2; 
Project description: Soil and groundwater cleanup: In-situ grouting; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: [Empty]. 

Project number: 29. ID-0030B.R1.3; 
Project description: Soil and groundwater cleanup: Operations; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive. 

Project number: 30. ID-0040B.R1.1; 
Project description: D&D: 39 facilities; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive; Positive. 

Project number: 31. ID-0040B.R1.2; 
Project description: D&D: 29 facilities; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive; Positive. 

Project number: 32. ID-0040B.NEW.R1.3; 
Project description: D&D: Nuclear Energy facilities; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: Positive; Positive; Positive; Performance 
measure with no planned work. 

Los Alamos National Laboratory (NM): 

Project number: 33. VL-LANL-0030.R1.1; 
Project description: Soil and groundwater cleanup: Material Disposal 
Area B; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work. 

Project number: 34. VL-LANL-0030.R1.2; 
Project description: Soil and groundwater cleanup: Groundwater wells; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive. 

Project number: 35. VL-LANL-0040-D.R1; 
Project description: D&D: Defense-related facilities; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive. 

Project number: 36. VL-LANL-0040-N.R1; 
Project description: D&D: Nondefense-related facilities; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: Positive; Positive; Performance measure with 
no planned work. 

Moab UMTRA Site (UT): 

Project number: 37. CBC-MOAB-0031.R1; 
Project description: Soil and groundwater cleanup: Mill tailings; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive. 

Mound Site (OH): 

Project number: 38. OH-MB-0031.NEW.R1; 
Project description: Soil and groundwater cleanup: Operable Unit 1; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work. 

Nevada Test Site (NV): 

Project number: 39. VL-NV-0030.R1; 
Project description: Soil and groundwater cleanup; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Negative; Performance measure with 
no planned work; Performance measure with no planned work; Performance 
measure with no planned work. 

Oak Ridge Reservation (TN): 

Project number: 40. OR-0013B.R1.1; 
Project description: TRU waste processing; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Positive; Negative. 

Project number: 41. OR-0040.R1; 
Project description: D&D: East Tennessee Technology Park; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 42. OR-0041.R1.1; 
Project description: D&D: Y-12 facility; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work. 

Project number: 43. OR-0041.R1.2; 
Project description: D&D: Y-12 remediation preparation; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Performance measure with 
no planned work; Performance measure with no planned work. 

Project number: 44. OR-0041.R1.3; 
Project description: D&D: Disposal facility expansion; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 45. OR-0041.NEW.R1.1; 
Project description: D&D: Y-12 excess material; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Negative; Negative; Performance 
measure with no planned work. 

Project number: 46. OR-0041.NEW.R1.2; 
Project description: D&D: Y-12 biology complex; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Negative; Performance measure with no planned 
work; Performance measure with no planned work; Performance measure 
with no planned work. 

Project number: 47. OR-0041.NEW.R1.3; 
Project description: D&D: Y-12 9206 filter house; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive. 

Project number: 48. OR-0042.R1.1; 
Project description: D&D: Defense legacy material removal; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 49. OR-0042.R1.2; 
Project description: D&D: Defense facility demolition; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: Positive; Negative; Negative. 

Project number: 50. OR-0042.R1.3; 
Project description: D&D: Defense remedial actions; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: Negative; Performance measure with no planned 
work; Performance measure with no planned work; Performance measure 
with no planned work; Performance measure with no planned work; 
Performance measure with no planned work. 

Project number: 51. OR-0042.NEW.R2.1; 
Project description: D&D: Nondefense legacy material removal; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 52. OR-0042.NEW.R2.2; 
Project description: D&D: 2000 complex; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Negative; Performance measure with 
no planned work; Performance measure with no planned work. 

Project number: 53. OR-0042.NEW.R2.3; 
Project description: D&D: Misc. facility demolition; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Paducah Site (KY): 

Project number: 54. PA-0040.R1.1; 
Project description: D&D: C-410; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work; Performance measure with no planned work. 

Project number: 55. PA-0040.R1.2; 
Project description: D&D: C-340; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work; Performance measure with no planned work; Performance 
measure with no planned work. 

Project number: 56. PA-0040.R1.3; 
Project description: D&D: C-746-A; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work; Performance measure with no planned work. 

Portsmouth Site (OH): 

Project number: 57. PO-0013.R1; 
Project description: Solid waste disposal: UMC disposition; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive. 

Project number: 58. PO-0040.R1.1; 
Project description: D&D: X-701B plume remediation; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work. 

Project number: 59. PO-0040.R1.2; 
Project description: D&D: X-533; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work. 

Project number: 60. PO-0040.R1.3; 
Project description: D&D: X-633; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work; Performance measure 
with no planned work. 

Project number: 61. PO-0040.R1.4; 
Project description: D&D: X-760; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work. 

Savannah River Site (SC): 

Project number: 62. SR-0011C.R1.1; 
Project description: TRU waste processing: Canyon complex support; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 63. SR-0013.R1.1; 
Project description: Solid waste disposal; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Positive; Negative; Negative; 
Negative; Performance measure with no planned work. 

Project number: 64. SR-0013.R1.2; 
Project description: TRU waste processing; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: Positive; Positive; Positive; Positive. 

Project number: 65. SR-0014C.R1.1; 
Project description: Tank waste support: Waste systems 
recapitalization; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 66. SR-0014C.R1.PEN; 
Project description: Tank waste support: Contractor pension payment; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 67. SR-0030.R1.1; 
Project description: D&D: P and R Area completion; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: [Empty]. 

Project number: 68. SR-0030.R1.2; 
Project description: D&D: P reactor; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work; Performance measure with no planned work; Performance 
measure with no planned work. 

Project number: 69. SR-0030.R1.3; 
Project description: D&D: P ash basin; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: [Empty]. 

Project number: 70. SR-0030.R1.4; 
Project description: D&D: R reactor; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work; Performance measure 
with no planned work; Performance measure with no planned work. 

Project number: 71. SR-0030.R1.5; 
Project description: D&D: R ash basin; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Project number: 72. SR-0030.R2.1; 
Project description: D&D: M and D Area completion; 
Cost target: Negative; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work. 

Project number: 73. SR-0030.R3.1; 
Project description: D&D: Sitewide completion; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: Positive; Positive; Positive; Positive; 
Positive; Performance measure with no planned work; Performance 
measure with no planned work; Performance measure with no planned 
work; Performance measure with no planned work. 

Project number: 74. SR-0030.R3.2; 
Project description: D&D: Test reactor decommissioning; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work. 

Project number: 75. SR-0040.R1.1; 
Project description: D&D: Surveillance and maintenance; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: [Empty]. 

Separations Process Research Unit (NY): 

Project number: 76. VL-SPRU-0040.R1.1; 
Project description: D&D: Building G2 and H2; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work. 

Project number: 77. VL-SPRU-0040.R1.2; 
Project description: D&D: Contaminated soil removal, North Field; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work. 

SLAC National Accelerator Laboratory (CA): 

Project number: 78. CBC-SLAC-0030.R1; 
Project description: Soil and groundwater cleanup; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: [Empty]. 

Waste Isolation Pilot Plant (NM): 

Project number: 79. CB-0080.R1; 
Project description: Operate waste disposal facility; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: [Empty]. 

Project number: 80. CB-0081.R1; 
Project description: Waste characterization; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Negative. 

Project number: 81. CB-0090.R1; 
Project description: TRU waste processing; 
Cost target: Positive; 
Schedule target: Positive; 
Performance measures[A]: Positive; Performance measure with no planned 
work; Performance measure with no planned work. 

West Valley Demonstration Project (NY): 

Project number: 82. OH-WV-0013.R1; 
Project description: TRU waste processing; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: Positive. 

Project number: 83. OH-WV-0040.R1.1; 
Project description: D&D: Main plant; 
Cost target: Positive; 
Schedule target: Negative; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work. 

Project number: 84. OH-WV-0040.R1.2; 
Project description: D&D: Other facilities; 
Cost target: Negative; 
Schedule target: Negative; 
Performance measures[A]: Performance measure with no planned work; 
Performance measure with no planned work; Performance measure with no 
planned work; Performance measure with no planned work. 

Source: GAO analysis of DOE data. 

Notes: 

Positive cost performance means that the value of work performed is 
greater than what the work actually cost to accomplish. For example, 
if the earned value of work completed by a contractor is $5 million, 
and the work actually cost $5 million or less to complete, then cost 
performance is considered positive. Schedule performance is also 
measured in dollars, but in this case, positive performance means that 
the value of the work completed in a given period is greater than what 
had been planned. For example, if the contractor is given 1 month to 
complete $5 million of work and completes that earned value of work by 
that deadline or earlier, then schedule performance is considered 
positive. DOE considers cost and schedule targets to be positive until 
they drop below 90 percent of the target. That is, work could come 
slightly under expectations--but not less than 90 percent of the 
target--and still be considered positive. 

Negative cost performance means that the value of work performed is 
less than what the work actually cost to accomplish. For example, if 
the earned value of work completed by a contractor is $5 million, but 
the work actually cost $6.7 million, cost performance would be 
considered negative. Schedule performance is also measured in dollars, 
but in this case, negative performance means that the value of the 
work completed in a given period is less than what had been planned. 
For example, if the contractor is given 1 month to complete $10 
million of work but completes only $5 million in earned value of work 
by that deadline, then schedule performance is considered negative. 

Performance measures are currently in place for the associated 
projects, but the planned work associated with these measures has not 
yet begun. As a result, these measures do not yet provide a meaningful 
way to monitor progress made on the projects. DOE considers 
performance targets to be positive until they drop below 90 percent of 
the target. That is, work could come slightly under expectations--but 
not less than 90 percent of the target--and still be considered 
positive. 

[A] Number of performance measures per project. 

[End of table] 

[End of section] 

Appendix V: Comments from the Department of Energy: 

Department of Energy: 
Washington, DC 20585: 

July 16, 2010: 

Mr. Gene Aloise, Director: 
Natural Resources and Environment: 
U.S. Government Accountability Office: 
Washington, DC 20548: 

Dear Mr. Aloise: 

Thank you for your effort in reviewing and reporting on Recovery Act 
work by the Department of Energy's (DOE) Office of Environmental 
Management (EM) and the opportunity to review your draft report: 
Recovery Act, Most DOE Cleanup Projects Appear to be Meeting Cost and
Schedule Targets, but Assessing Impact of Spending Remains a Challenge 
(GAO 10-784). DOE appreciates the opportunity to provide feedback on 
the statements, conclusions, and recommendations in the report.
DOE responses to the report recommendations and divergent statements 
are summarized below: 

Project Management - DOE concurs with GAO recommendations regarding 
evaluating the effectiveness of additional project management and 
oversight steps adopted for Recovery Act projects and determining if 
these steps would be effective for the EM Base Program funded under 
annual appropriations. EM has already evaluated and taken several 
steps to more broadly implement Recovery Act initiatives beginning as 
early as June 2009. These include increased review and engagement by 
management; and restructuring the EM portfolio of programs, projects 
and activities into more appropriate and manageable sizes. Other steps 
are still being developed and evaluated. As Recovery Act work 
continues, more data will be available upon which to base quantitative 
analysis of Recovery Act practices. 

Jobs Creation — EM agrees with GAO's recommendation to ensure 
methodology for calculating job creation is clear and will articulate 
this to the public. EM communicates three figures when presenting the 
number of workers impacted with Recovery Act funding. These three are 
prime contractor full time equivalents (FTEs), prime contractor and 
subcontractor FTEs, and total headcount. 

Both prime contractor and subcontractor FTEs are calculated strictly 
in accordance with Office of Management and Budget guidance, and 
therefore there is no ambiguity in the methodologies employed between 
prime and subcontractor FTE data. Changes to Federal Acquisition
Regulation (FAR) clause 52.204-11 will result in both prime and 
subcontractor jobs being reported in FederalReporting.gov, thus 
negating GAO's concern on the matter. 

It is also important to note that a number of EM Recovery Act workers 
may not be employed full-time nor for the full duration of the EM 
Recovery Act program. Headcount is the method employed by EM to 
account for these workers. Headcount is the cumulative number of 
workers, full-time, part-time, and temporary workers that benefited 
from Recovery Act with direct labor charges to Recovery Act funds. 
EM's collection and reporting of this figure augments and facilitates 
transparency and accountability of Recovery Act job creation. 

Footprint Reduction — DOE agrees with GAO's recommendation to have in 
place clear, quantifiable and consistent measures for footprint 
reduction, which, as a brand new measure, has taken some time to fully 
define. Footprint reduction is a measure intended to objectively track 
incremental progress (number of square miles cleaned up) toward 
completing DOE's large site remediation effort that will not be 
totally finished for many years. Footprint reduction has now been 
defined, communicated with all the sites, and is being reported to 
show progress on a regular basis. 

Successful site cleanup, area closure, and footprint reduction as a 
result of soil and groundwater remediation and facility 
decontamination and decommissioning meets DOE's long term goals by 
maximizing the reduction of environmental, safety, and health risks. 
EM measures its success in reducing these risks by tracking 
quantifiable outputs of its cleanup process. Among others, these 
include installing groundwater wells for remediation systems, 
decontaminating, decommissioning, and demolishing contaminated 
facilities, disposing of contaminated debris piles, and remediating 
soil units. 

Life-Cycle Cost - EM agrees with the GAO's recommendation and will 
continue to use the DOE and OMB guidance to calculate cost savings and 
to develop and portray life-cycle cost estimates. EM develops life-
cycle cost, scope, and schedule estimates for projects in accordance 
with DOE Order 413.3A. The Order specifies that cost estimates include 
escalation and therefore are in current year dollars. Current 
(escalated) dollars are used in DOE's budget requests and within 
reports provided to Congress and our stakeholders. Therefore in order 
to remain consistent with our Orders and our entire budget reporting, 
any cost savings or reductions to our life-cycle cost estimates that 
are achieved because of Recovery Act Funding are also reported in 
current dollars. 

Spending Versus Spend Plans - The initial project spend plans for the 
EM Recovery Act were developed prior to contracts being finalized. 
After pricing and technical proposals were negotiated and approved 
between the Department of Energy and the Prime Contractors affiliated 
with each of the EM sites, Recovery Act projects baselines were 
adjusted to reflect the approved contracts. The current project spend 
plans reflect an overall "spend rate" of approximately $200M per 
month, which the program is achieving. EM's internal goal established 
at the beginning of the Recovery Act was to have a majority of 
Recovery Act funds spent by the end of Fiscal Year 2011. With the 
exceptions of 9 projects, due to scope changes, EM is on-track to 
spend over 95 percent of project funds per the original goal. 

Performance Measures - DOE has concern over the method GAO appears to 
be using to determine project cost and schedule status. It appears 
that GAO is classifying performance as negative unless measure actual 
are "exactly" equal to or greater than the planned target. This is 
inconsistent with DOE and consensus project management best practices. 

Project Metrics — DOE has concerns with GAO statements such as 
"inconsistencies exist between some projects' cost and schedule 
performance and progress shown by other performance measures..." and 
"...we found that the results as assessed by performance measures were 
sometimes inconsistent with the results shown by earned value data..." 
DOE uses Earned Value Measurement Systems (EVMS) and performance 
metrics as important components of a tool kit which includes numerous 
performance indicators (milestones, project risk status, use of 
management reserve and contingency, etc.) in assessing project health 
and performance. Project performance information provides different, 
but complementary insight into essential aspects of overall project 
performance. EM project managers and senior program managers take in 
all available information to arrive at a complete picture of project 
health. 

DOE's review has identified several statements and text corrections 
that should be addressed prior to release of the GAO report. 

Attachment 1 provides DOE's detailed response to GAO's recommendations 
and statements, and Attachment 2 provides a summary of DOE review 
comments discovered in the draft reports. 

EM remains committed to the objectives of the Recovery Act program — 
to create jobs and accelerate cleanup of legacy waste sites from the 
nuclear weapons production program. 

If you have any further questions, please contact Cynthia Anderson, 
Director, EM Recovery Act Program, at 202-586-2083. 

Sincerely, 

Signed by: 

Ines R. Triay: 
Assistant Secretary for Environmental Management: 

Attachments: 

[End of letter] 

Attachment 1: 

Department of Energy: 
Comments on the Draft Government Accountability Office (GAO) Report 
GA0-10-784: 

DOE Responses to GA0-10-784 Recommendations for Executive Action: 

GAO Recommendation 1: Determine whether additional project management 
and oversight steps adopted for the Recovery Ad projects, such as more 
frequent reporting, have proven beneficial and whether these steps 
would be effective and appropriate for DOE's cleanup projects funded 
under annual appropriations. 

DOE Response 1: The Office of Environmental Management (EM) 
fundamentally agrees with the recommended action. The increased review 
and engagement by EM senior management for Recovery Act work provided 
an opportunity for early qualitative evaluation of the success of 
Recovery Act initiatives, and EM has already taken several steps to 
more broadly implement Recovery Act initiatives beginning as early as 
June 2009. As Recovery Act work continues, more data will be available 
upon which to base quantitative analysis of Recovery Act practices. 

The budget and management structure of the EM portfolio of programs, 
projects, and activities (PPA) is fundamental to the management and 
oversight of the EM mission work. The EM Recovery Act Program, 
Portfolio Management Framework (July 10, 2009), was developed to 
provide a structure to enable greater review, oversight, and control 
of Recovery Act projects. While this Framework was still draft, EM 
signaled the intent to utilize this Framework for the entire EM 
portfolio (also referred to as the Base program) via the distribution 
of a memo from Dr. Ines Triay, dated June 5, 2009. Additional memos 
and guidance to the field from Dr. Triay and senior managers in June 
2009, November 2009, and April 2010 have continued the evolution of 
the EM portfolio toward a clear definition of capital projects and 
operations activities, and a decomposition of large projects into more 
appropriate and manageable sizes. 

The evolution of the EM portfolio described above is being 
complemented by a reworking of the reporting and review mechanisms. 
Quarterly Project Reviews (QPRs) were the standard for review of the 
EM projects. The Recovery Act began with monthly project reviews which 
provided for more direct and immediate EM oversight and corrective 
action. Monthly reviews which included the Base program capital 
projects which utilized back-to-back reporting, Recovery Act and Base 
program, began in March 2010. In May 2010 these reviews advanced to a 
combined Recovery Act/Base program monthly review. Efforts continue to 
refine the data analysis and formatting to provide for a full monthly 
review of the entire EM portfolio, including capital projects and 
operations activities for both, Recovery Act and Base program, to 
begin in October 2010. 

The tighter control of funds for Recovery Act work was necessitated by 
the nature of the Recovery Act funding and additional Office of 
Management and Budget restrictions. The new EM management portfolio of 
projects and operations activities inherently will provide more 
discreet funding control because of the smaller size of individual 
budget elements. Whether the controls for release of spending 
authority to the field used for Recovery Act will provide additional 
benefit to the Base program is still under evaluation. 

Additional Federal oversight staff, particularly in the form of 
Recovery Act Site Representatives (RASRs) physically located at the 
largest Recovery Act sites, has been a very successful practice for 
the Recovery Act. The RASR role in the monthly evaluation and review 
process, as well as providing immediate feedback on site challenges 
and opportunities, has allowed EM senior management to shorten the 
analysis and decision cycle on field issues, thus being more 
responsive. The EM Office of Program and Site Support has similar 
oversight staff assigned to liaison with field locations for the Base 
program, but these staff are located in EM headquarters and thus do 
not have the same direct access and oversight as the RASRs for the 
Recovery Act work. An opportunity is being evaluated to merge these 
oversight efforts to capture the best features of both. 

Finally, EM notes that the GAO report and recommendation only mentions 
a few of the management and oversight steps which EM has employed 
under Recovery Act. EM has developed Lessons Learned guidance which 
has been issued to the field sites. EM has developed a path forward 
and template which has been issued to the sites to capture Lessons 
Learned on Recovery Act Projects. EM is also in the process of 
developing Lessons Learned guidance which will first be implemented on 
Recovery Act Projects and then evaluated and modified if necessary, 
for use within the Base Program. Lessons learned on the Recovery Act 
Program initiation and contract management are also being captured for 
incorporation where applicable into the EM Base program and other DOE 
programs as deemed applicable. Lessons learned will be tracked in a 
searchable and reportable database that has been used and been proven 
to be an effective tool in tracking lessons learned for health and 
safety issues. EM has conducted two lessons learned information 
exchanges, in November 2009 and April 2010, to further advance the 
knowledge exchange. 

EM views the Recovery Act Program as a rare opportunity to accelerate 
completion of EM work, to reduce risk and reduce the footprint of EM, 
but also as an incubator for focused and responsive management and 
oversight practices. EM has already put some lessons from the Recovery 
Act in place for the Base program, and, as the Recovery Act work 
continues to completion, EM is fully committed to making full use of 
the future lessons. 

GAO Recommendation 2: When reporting the impact of Recovery Act 
funding on job creation, clearly indicate the methodology used to 
calculate each of the figures reported: prime contractor FTEs, 
subcontractor and prime contractor FTEs combined, or head count. 

DOE Response 2: EM agrees with the recommendation to ensure the 
methodology for calculating job creation is clear. EM communicates 
three figures when presenting the number of workers impacted with 
Recovery Act funding. These three include prime contractor full time 
equivalents (FTEs), prime contractor and subcontractor FTEs, and 
headcount. 

Prime contractor FTEs are reported into FederalReporting.gov on a 
quarterly basis and are calculated in accordance with the Office of 
Management and Budget (OMB) M-10-08, "Updated Guidance on the American 
Recovery and Reinvestment Act — Data Quality, Non-Reporting 
Recipients, and Reporting of Job Estimates," issued December 18, 2009. 
Basically, this calculation takes into account the total number of 
hours worked that are funded by the Recovery Act divided by the number 
of hours in a full-time schedule. 

Subcontractor FTEs are calculated in accordance with the same OMB 
guidance and are reported together with prime contractor FTEs by EM in 
newsletters, new flashes, press releases, monthly reviews, and public 
presentations to stakeholders. To date, subcontractor FTEs have not 
been required to be reported into FederalReporting.gov and as noted in 
the GAO report account for as much as 50% of EM Recovery Act total job 
creation. However, subcontractor FTE figures will begin being reported 
in the third quarter 2010 in accordance with recent changes to the FAR 
clause 52.204-11 to implement section 1512 reporting requirements of 
the Recovery Act. 

The intent of EM's initiative to collect and report both prime and 
subcontractor FTEs has always been to reflect a more accurate figure 
for the total number of FTEs saved or created under EM Recovery Act 
funds. This represents a more credible total number of EM Recovery Act 
full-time jobs. 

In regards to the EM headcount figure, a significant number of EM 
Recovery Act workers will work on projects or subprojects that will 
not last the entire duration of the EM Recovery Act program. However, 
these workers's have benefited from EM Recovery Act funding. Therefore 
a headcount figure of number of the workers, full-time, part-time and 
temporary workers compensated with Recovery Act funding has been 
collected and reported by EM communication venues noted above. The 
methodology EM utilizes to determine headcount is a cumulative number 
of workers who have benefited from Recovery Act funds. 

The change to the FAR clause will result in both prime and 
subcontractor (combined) jobs being reported in FederalReporting.gov 
thus negating GAO's concern on the matter. As for the EM headcount, 
collection and reporting of this figure continues to facilitate 
transparency and accountability of EM Recovery Act funded impact on 
job creation. 

To more clearly articulate the methodologies for calculating EM job 
creation, the EM guidance for calculating jobs has been posted on the 
EM Recovery Act website. In addition, a one-page explanation sheet 
will be included whenever job numbers are presented to stakeholders 
and/or the public. 

GAO Recommendation 3: Develop clear, quantifiable, and consistent 
measures for determining the impact of Recovery Act funding on 
environmental risk. As part of this effort, clearly define what the 
DOE footprint consists of determine how changes to the footprint will 
be measured, and ensure that all DOE sites report changes to their 
footprint in a consistent and comparable manner. 

DOE Response 3: Prior to initiation of any Recovery Act field 
activities, EM required all sites to develop a project-specific risk 
register for each project. Identification and quantification of risks 
were developed consistent with applicable DOE risk management guides 
and with guidance provided by both OMB and the office of the DOE Chief 
Financial Officer (CFO). This guidance required that all projects 
receiving Recovery Act funding to identify risks for each of the 
following category and/or sub-categories: 

Category: People; 
Sub-Category: Human capital; 
Sub-Category: Organizational structure. 

Category: Processes; 
Sub-Category: Procedures; 
Sub-Category: Funds control; 
Sub-Category: Reporting. 

Category: Governance; 
Sub-Category: Project structure; 
Sub-Category: Administration and management; 
Sub-Category: Monitoring; 
Sub-Category: Special concerns; 
Sub-Category: Performance metrics. 

Category: Technology; 
Sub-Category: Systems. 

Category: Project Specific; 
Sub-Category: Regulatory; 
Sub-Category: Conflict of interest; 
Sub-Category: Safety & health; 
Sub-Category: Other special concerns. 

[End of table] 

EM also implemented a system to store/sort all project related risks 
from all sites in a headquarters controlled risk repository. As a 
follow-up to the original site-provided risk registers, EM also 
initiated a detailed review and update at each site during late June 
and through the month of July 2010. During this review, sites had the 
opportunity to update previously reported risks and the inclusion of 
new risks from recently added projects. Each site received training 
and software licenses to allow input to be provided to the repository 
directly by the site for those projects located at the specific site. 
This repository provides EM Headquarters the ability to review the 
disposition of risks by site; types of risks; and potential 
magnitude/impact of risks by site or category of risks, including 
appropriate mitigation strategies. EM uses this ongoing valuation of 
risks to monitor the use of project-specific management reserve and 
DOE contingency. 

Following completion of the July site training and update, EM will 
post the top-25 risks on the portal. 

EM agrees with this GAO recommendation and has implemented a system 
that clearly defines EM's cleanup mission/scope through a number of 
processes, including agreements with regulatory agencies. This scope 
is defined through EM's life-cycle performance metrics (Base scope 
plus ARRA scope), which quantify the measurable and necessary steps in 
the cleanup process and have been in place for nearly 15 years. These 
performance measures are focused on outputs. The specific outputs 
chosen are directly tied to cleanup of the site, which results in 
environmental risk reduction. Therefore, as we measure achievement of 
cleanup steps, we are thereby measuring progress toward cleanup and 
reducing overall environmental risks. 

Historically, EM has tracked area closures in terms of the number of 
geographic sites completed. EM's responsibility has included 107 
geographic sites, and through 2010 has closed 89 of these sites. Since 
EM's ARRA work scope is largely centered on the largest sites, the 
Hanford and Savannah River Sites, where the cleanup mission will not 
be completed for many years, EM adopted a footprint reduction tracking 
system in order to measure incremental progress in completing these 
large sites. 

EM has established footprint reduction as a High Priority Performance 
Goal (HPPG) for the department to demonstrate progress. Specifically, 
EM has committed to a 40% footprint reduction in the square mileage 
under EM control by September 30, 2011 (i.e., reducing footprint from 
900 square miles to 540 square miles). Performance against the HPPG is 
reported to OMB and is updated on a quarterly basis. Specific measures 
tracked by EM for the performance of this goal includes number of 
soils units remediated and debris piles removed, and number of 
industrial/radioactive facilities decontaminated and decommissioned. 
OMB will make the HPPG performance available through its release of 
Performance.gov by the fall of 2010. 

Footprint reduction is a high-level benefit to the nation and the 
respective communities. Achieving EM footprint reduction as a result 
of soil and groundwater remediation and facility decontamination and 
decommissioning maximizes the reduction of environmental, safety, and 
health risks in a safe, secure, compliant, and cost-effective manner. 
Removal of contamination also reduces monitoring and maintenance life-
cycle costs and liabilities. 

GAO Recommendation 4: Ensure that savings estimates over the life of 
the cleanup projects are calculated according to OMB and DOE guidance, 
so that those estimates accurately represent potential savings and 
reflect cost adjusted for both inflation and the time value of money. 

DOE Response 4: 

EM agrees with the GAO's life-cycle cost calculation recommendation 
and will continue to utilize the Department's and OMB's guidance to 
calculate cost savings, and develop and portray life-cycle cost 
estimates where applicable. 

EM develops the life-cycle cost, scope and schedule required to 
complete specific cleanup projects captured in a Project Baseline 
Summary (PBS) in accordance with DOE Order 413.3A, Program and Project 
Management for the Acquisition of Capital Assets. The Order and 
supporting Guides specify that project cost estimates include 
escalation and, therefore, are in current year dollars. These cost 
estimates are utilized to portray the life-cycle cost associated with 
the cleanup of the Cold War legacy. 

EM recognizes the importance of taking into account the time value of 
money when comparing specific projects or activities. EM will continue 
to use OMB Circular A-94, Guidelines and Discount Rates for Benefit-
Cost Analysis of Federal Programs, when conducting alternative 
analysis to determine the cost/benefit and return on investment 
associated with project activities. In fact, EM utilized this 
methodology to determine candidates for receipt of ARRA funding. 

In addition, EM will continue to portray its life-cycle cost based on 
the life-cycle cost estimates developed in accordance with DOE Order 
413.3A. EM reports its life cycle cost in current (escalated) dollars 
in its annual Congressional Budget Request and other congressionally 
mandated reports to Congress such as the January 2009 Status of 
Environmental Management Initiatives to Accelerate the Reduction of 
Environmental Risks and Challenges Posed by the Legacy of the Cold War 
and the June 2010 updated appendices to this report which included a 
listing of life-cycle cost by Site and PBS. 

To be consistent with the life-cycle cost projections Congress and our 
stakeholders are seeing in our budget requests and Congressional 
Reports, any reduction in the life cycle cost is also reported in 
current dollars. Our life cycle cost reported in the June 2010 update 
to Status of Environmental Management Initiatives to Accelerate the 
Reduction of Environmental Risks and Challenges Posed by the Legacy of 
the Cold War factored in the $4B in cost savings attributed to the 
acceleration of cleanup work as a result of ARRA funding. 

In addition to the $4B in life-cycle cost savings, EM has also 
estimated cost avoidances of more than $3 billion that have resulted 
from the receipt of Recovery Act funding. These cost avoidances should 
also be accounted for in the final report. For example ARRA funding at 
Idaho, Oak Ridge, Savannah River Site, and Hanford has enabled these 
transuranic waste generator sites to accelerate shipments to the Waste 
Isolation Pilot Plant (WIPP) by many years, avoiding a schedule 
extension and continued operating costs. The reduced operating time 
resulting in an estimated cost avoidance of $2.5 billion at WIPP, 
compared to what the cost would have been had ARRA funding not been 
received. 

GAO Statements: 

DOE Response to GAO 2012 Spending Statements - The initial EM Recovery 
Act spend plans were developed prior to contract definitization. As 
project price and technical proposals were negotiated and approved, EM 
re-baselined spending plans. As project price and technical proposals 
were negotiated and approved, EM revised these spending plans. The 
current plans reflect an overall "burn rate" of approximately $200M 
per month, which the program is achieving. With the following 
exceptions (due to scope changes), EM expects Recovery Act projects 
will be complete (and funds expended) by the end of FY 2011. 

* INL D&D of EBR II (June 2012); 
* Title X Uranium/Thorium Reimbursements (April 2013); 
* OR Y-12 D&D (December 2011); 
* ORNL Defense D&D (December 2011); 
* ORNL Non-Defense D&D (Defense 2011); 
* OR Uranium Enrichment Facility D&D (December 2011); 
* SRS Solid Waste and Accelerated TRU Disposition (December 2012); 
* SRS P and R Area Completions (September 2012); 
* EPA's Radioactive Site Characterization of Area IV of the Santa 
Susana Field Lab (December 2011). 

Fluctuations in the total amount of allotted funds that are obligated 
arc due to downward adjustments to make obligation authority available 
for OMB re-apportionment. These re-apportionments primarily occur 
within site allocations to realign funding between projects when cost 
efficiencies are realized or scope additions/deletions are required. 
The de-obligation process must he followed before reapportionment 
action can be approved at OMB. When all de-obligation and re-
obligation actions are completed, there will be a net effect of zero 
to EM's allocation of $6 billion. 

DOE Response to GAO Project Metrics Statements — DOE has concerns with 
GAO statements such as "...inconsistencies exist between some 
projects' cost and schedule performance and progress shown by other 
performance measures..." (bottom of pg 12) and "...we found that the 
results as assessed by performance measures were sometimes 
inconsistent with the results shown by earned value data..." (top of 
pg 19) Project performance information, including such data elements 
as EVMS, performance metrics, milestones, project risk status, use of 
management reserve and contingency, etc., each provide different, but 
complementary, insight into different aspects of overall project 
performance. EM project managers and senior program managers take in 
all available information to arrive at a complete picture of project 
health, before rendering an assessment. Performance measures were 
selected to provide visibility into a distinct but important aspect of 
the project, in some cases, a relatively minor percentage of the 
project cost value; Earned Value (EV), on the other hand, typically 
encompasses the entire scope basis. While the last sentence in the 
paragraph on page 19 is the most important and reflects a more 
accurate response, the term "inconsistencies" is still inappropriate 
and should be replaced with "differences in indicators". 

At the bottom of page 16, the GAO report states that as of March of 
2010, "DOE reported that across the complex, progress on five of seven 
selected performance measures was meeting or exceeding targets..." DOE 
believes strongly this should read "five out of six" performance 
measures are meeting or exceeding their targets. As previously 
explained to GAO, "Demolition debris and soil permanently disposed" 
was specifically not established as a performance measure, but rather 
as a measurable unit useful in planning and estimating, as well as in 
conveying overall progress against cleanup (e.g., when rolled up to 
the site or complex-wide level). Using waste minimization best 
practices and avoiding generation and disposal of wastes is in the 
best interest of the government and overall project performance is 
actually improved when these estimates arc NOT realized; for actual 
values to be lower than original estimates is a good outcome. So to 
include this metric in the same category as the other true performance 
measures is misleading and understates the actual performance. While 
the footnote in Figure 5 recognizes this, the accompanying text should 
be accurate as well. 

As a demonstration of the overall health of the EM project portfolio, 
many sites are beginning to realize efficiencies and have brought 
forth additional scope that may be completed within the FY2011 
timeframe. 

[End of section] 

Appendix VI: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Gene Aloise, (202) 512-3841, aloisee@gao.gov: 

Staff Acknowledgments: 

In addition to the individual named above, Janet Frisch, Assistant 
Director; Antoinette Capaccio; Ellen W. Chu; Heather Dowey; Jennifer 
Echard; Jeff Larson; Mehrzad Nadji; John G. Smale Jr.; Stacey Steele; 
Kiki Theodoropoulos; and Ginny Vanderlinde made key contributions to 
this report. 

[End of section] 

Related GAO Products: 

Department of Energy: Actions Needed to Develop High-Quality Cost 
Estimates for Construction and Environmental Cleanup Projects. 
[hyperlink, http://www.gao.gov/products/GAO-10-199]. Washington, D.C.: 
January 14, 2010. 

Nuclear Waste: Uncertainties and Questions about Costs and Risks 
Persist with DOE's Tank Waste Cleanup Strategy at Hanford. [hyperlink, 
http://www.gao.gov/products/GAO-09-913]. Washington, D.C.: September 
30, 2009. 

Department of Energy: Contract and Project Management Concerns at the 
National Nuclear Security Administration and Office of Environmental 
Management. [hyperlink, http://www.gao.gov/products/GAO-09-406T]. 
Washington, D.C.: March 4, 2009. 

Nuclear Waste: Action Needed to Improve Accountability and Management 
of DOE's Major Cleanup Projects. [hyperlink, 
http://www.gao.gov/products/GAO-08-1081]. Washington, D.C.: September 
26, 2008. 

Nuclear Waste: DOE Lacks Critical Information Needed to Assess Its 
Tank Management Strategy at Hanford. [hyperlink, 
http://www.gao.gov/products/GAO-08-793]. Washington, D.C.: June 30, 
2008. 

Department of Energy: Office of Science Has Kept Majority of Projects 
within Budget and on Schedule, but Funding and Other Challenges May 
Grow. [hyperlink, http://www.gao.gov/products/GAO-08-641]. Washington, 
D.C.: May 30, 2008. 

Hanford Waste Treatment Plant: Department of Energy Needs to 
Strengthen Controls over Contractor Payments and Project Assets. 
[hyperlink, http://www.gao.gov/products/GAO-07-888]. Washington, D.C.: 
July 20, 2007. 

Department of Energy: Consistent Application of Requirements Needed to 
Improve Project Management. [hyperlink, 
http://www.gao.gov/products/GAO-07-518]. Washington, D.C.: May 11, 
2007. 

Department of Energy: Major Construction Projects Need a Consistent 
Approach for Assessing Technology Readiness to Help Avoid Cost 
Increases and Delays. [hyperlink, 
http://www.gao.gov/products/GAO-07-336]. Washington, D.C.: March 27, 
2007. 

Hanford Waste Treatment Plant: Contractor and DOE Management Problems 
Have Led to Higher Costs, Construction Delays, and Safety Concerns. 
[hyperlink, http://www.gao.gov/products/GAO-06-602T]. Washington, 
D.C.: April 6, 2006. 

Nuclear Waste: Better Performance Reporting Needed to Assess DOE's 
Ability to Achieve the Goals of the Accelerated Cleanup Program. 
[hyperlink, http://www.gao.gov/products/GAO-05-764]. Washington, D.C.: 
July 29, 2005. 

Department of Energy: Further Actions Are Needed to Strengthen 
Contract Management for Major Projects. [hyperlink, 
http://www.gao.gov/products/GAO-05-123]. Washington, D.C.: March 18, 
2005. 

Nuclear Waste: Absence of Key Management Reforms on Hanford's Cleanup 
Project Adds to Challenges of Achieving Cost and Schedule Goals. 
[hyperlink, http://www.gao.gov/products/GAO-04-611]. Washington, D.C.: 
June 9, 2004. 

[End of section] 

Footnotes: 

[1] Pub. L. No. 111-5 (2009). 

[2] This figure includes about $83 billion in actual costs from 1997 
to 2009, according to DOE. 

[3] GAO has found these sites to have had problems with rising costs, 
schedule delays, and contract and project management. See GAO, 
Department of Energy: Contract and Project Management Concerns at the 
National Nuclear Security Administration and Office of Environmental 
Management, [hyperlink, http://www.gao.gov/products/GAO-09-406T] 
(Washington, D.C.: Mar. 4, 2009); GAO, Hanford Waste Treatment Plant: 
Department of Energy Needs to Strengthen Controls over Contractor 
Payments and Project Assets [hyperlink, 
http://www.gao.gov/products/GAO-07-888] (Washington, D.C.: July 20, 
2007); GAO, Nuclear Waste: Better Performance Reporting Needed to 
Assess DOE's Ability to Achieve Goals of the Accelerated Cleanup 
Program, [hyperlink, http://www.gao.gov/products/GAO-05-764] 
(Washington, D.C.: July 29, 2005); GAO, Nuclear Waste: Department of 
Energy's Project to Clean Up Pit 9 at Idaho Falls Is Experiencing 
Problems, [hyperlink, http://www.gao.gov/products/GAO/RCED-97-180] 
(Washington, D.C.: July 28, 1997). A list of GAO related products 
appears at the end of this report. 

[4] The 17 sites were Argonne National Laboratory (IL), Brookhaven 
National Laboratory (NY), Energy Technology Engineering Center (CA), 
Hanford Site Office of River Protection and Richland Operations Office 
(WA), Idaho National Laboratory (ID), Los Alamos National Laboratory 
(NM), Moab UMTRA Site (UT), Mound Site (OH), Nevada Test Site (NV), 
Oak Ridge Reservation (TN), Paducah Site (KY), Portsmouth Site (OH), 
Savannah River Site (SC), Separations Process Research Unit (NY), SLAC 
National Accelerator Laboratory (CA), Waste Isolation Pilot Plant 
(NM), and West Valley Demonstration Project (NY). 

[5] GAO, Department of Energy: Major Construction Projects Need a 
Consistent Approach for Assessing Technology Readiness to Help Avoid 
Cost Increases and Delays, [hyperlink, 
http://www.gao.gov/products/GAO-07-336] (Washington, D.C.: Mar. 27, 
2007); GAO, Department of Energy: Further Actions Are Needed to 
Strengthen Contract Management for Major Projects, [hyperlink, 
http://www.gao.gov/products/GAO-05-123] (Washington, D.C.: Mar. 18, 
2005); GAO, Hanford Waste Treatment Plant: Contractor and DOE 
Management Problems Have Led to Higher Costs, Construction Delays, and 
Safety Concerns, [hyperlink, http://www.gao.gov/products/GAO-06-602T] 
(Washington, D.C.: Apr. 6, 2006). 

[6] GAO, Department of Energy: Actions Needed to Develop High-Quality 
Cost Estimates for Construction and Environmental Cleanup Projects, 
[hyperlink, http://www.gao.gov/products/GAO-10-199] (Washington, D.C.: 
Jan. 14, 2010). 

[7] Our prior work found that technical problems (such as developing 
sophisticated waste separation technologies) or legal and regulatory 
issues (such as determining when a waste tank was clean enough to 
close) handicapped acceleration of complex and costly projects; see 
[hyperlink, http://www.gao.gov/products/GAO-05-764]. 

[8] To track projects, DOE assigns each project a number, which 
corresponds to project baseline information. A complete list of DOE 
Recovery Act projects, organized by site and project number appears in 
appendix III. Project number OR-0040.R1 (see appendix III and IV). 

[9] Project number OH-MB-0031.NEW.R1 (see appendix III and IV). 

[10] Transuranic waste is waste containing more than 100 nanocuries of 
alpha-emitting transuranic elements (radiation) per gram with half- 
lives greater than 20 years with certain exceptions. A half-life is 
the amount of time required for an element to decay by half, and 
nanocuries are a measure of radioactivity. Alpha-emitting radiation 
cannot pass through objects, including human skin, but is extremely 
dangerous if inhaled or ingested. 

[11] In this report, references to a project achieving its cost and 
schedule targets means that the project is demonstrating an earned 
value metric that shows positive cost and schedule performance as 
assessed by the contractor's earned value management system. See 
appendix IV for further information on how this metric is used. 

[12] Project number SR-0013.R1.2 (see appendix III and IV). 

[13] Project number OR-0040.R1 (see appendix III and IV). 

[14] Project number ID-0040B.NEW.R1.3 (see appendix III and IV). 

[15] This jobs number reflects reporting by DOE contractors and 
represents a count of full-time equivalents for DOE's prime 
contractors only. Per OMB guidance, this number represents jobs 
created during the previous quarter (January through March 2010). 

[16] Project number SR-0030.R1.2 (see appendix III and IV). 

[17] Project number BRNL-0040.R1 (see appendix III and IV). 

[18] Project number RL-0041.R2 (see appendix III and IV). 

[19] DOE has certified that the earned value system used by its 
contractors is reliable for all but one Recovery Act contractor 
(Savannah River's liquid tank waste contractor). DOE does not require 
contractors at three of the sites--Argonne National Laboratory, 
Paducah, and SLAC National Accelerator Laboratory--to have their 
earned value systems certified. 

[20] Project number SR-0040.R1 (see appendix III and IV). 

[21] Project number RL-0041.R2 (see appendix III and IV). 

[22] Project number SR-0013.R1.1 (see appendix III and IV). 

[23] Project number RL-0041.R1.3 (see appendix III and IV). 

[24] Project number ID-0040B.NEW.R1.3 (see appendix III and IV). 

[25] In 2001, DOE established DOE's Project Management Career 
Development Program, which defines a project management career path 
that includes certification, minimum training and continuing education 
requirements, and project management responsibilities that are 
commensurate with clearly defined qualifications. According to DOE 
officials, all project directors overseeing Recovery Act projects are 
certified at, or greater than, the level appropriate for the project 
they are managing, which means that they have the qualifications to 
oversee projects valued at more than $100 million. The requirements 
are articulated in DOE order 361.1B, Acquisition Career Management 
Program. 

[26] Project number ID-0040B.NEW.R1.3 (see appendix III and IV). 

[27] Project number SR-0013.R1.2 (see appendix III and IV). 

[28] Project number CBC-ETEC-0040.R1.1 (see appendix III and IV). 

[29] 42 U.S.C. 9601-9675 (2006). 

[30] Project number CBC-ETEC-0040.R1.2 (see appendix III and IV). 

[31] Project number OH-WV-0013.R1 (see appendix III and IV). 

[32] Indefinite-delivery/indefinite-quantity contracts allow the 
government to contract for indefinite quantities of supplies or 
services during a fixed period. The government places delivery orders 
(for supplies) or task orders (for services) in a base contract and 
specifies minimum and maximum quantity limits, then places individual 
orders as needed. 48 C.F.R.§§ 16.501-1,504(a) (2009). 

[33] Federal Acquisition Regulations 52.204-11 governing the reporting 
of job creation figures have changed, and, beginning with the third 
quarter of fiscal year 2010, subcontractor FTEs will also be reported. 

[34] DOE also estimated more than $3 billion in costs that would be 
avoided because of Recovery Act funding. These include, for example, 
accelerated shipments to the Waste Isolation Pilot Plant, which would 
avert a schedule extension and continued operating costs. 

[35] GAO, Nuclear Waste: Absence of Key Management Reforms on 
Hanford's Cleanup Project Adds to Challenges of Achieving Cost and 
Schedule Goals, [hyperlink, http://www.gao.gov/products/GAO-04-611] 
(Washington, D.C.: June 9, 2004), and GAO-05-764. 

[36] This $1.6 billion went solely to Hanford's Richland Operations 
Office, one of two DOE administrative units at Hanford. 

[37] Project number RL-0040.R1.1 (see appendix III and IV). Projects 
labeled D&D by DOE generally consist of deactivation, decommissioning, 
decontamination, demolition, or a combination of these activities. 

[38] Project number RL-0041.R1.1 (see appendix III and IV). 

[39] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C. Mar. 2, 
2009). 

[40] Project number SR-0013.R1.2 (see appendix III and IV). 

[41] As of June 2010, DOE is updating this project's cost and schedule 
targets because of changes to the allowable container size for 
shipping and disposing of transuranic waste. 

[42] Project number SR-0030.R.1.1 (see appendix III and IV). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: