This is the accessible text file for GAO report number GAO-10-689 
entitled 'New Embassy Compounds: State Faces Challenges in Sizing 
Facilities and Providing for Operations and Maintenance Requirements' 
which was released on July 20, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Committee on Foreign Relations, Senate and the Committee on 
Foreign Affairs, House of Representatives: 

United States Government Accountability Office: 
GAO: 

July 2010: 

New Embassy Compounds: 

State Faces Challenges in Sizing Facilities and Providing for 
Operations and Maintenance Requirements: 

GAO-10-689: 

GAO Highlights: 

Highlights of GAO-10-689, a report to Committee on Foreign Relations, 
Senate and the Committee on Foreign Affairs, House of Representatives. 

Why GAO Did This Study: 

In response to the 1998 bombings of two U.S. embassies, the Department 
of State (State) embarked on a multiyear, multibillion dollar program 
to replace insecure and dilapidated diplomatic facilities. Since 2001, 
State has constructed 52 new embassy compounds (NECs) under this 
program, and moved over 21,000 U.S. government personnel into more 
secure and safe facilities. GAO was asked to examine (1) the extent to 
which new facilities match the space and functionality needs of 
overseas missions and State’s actions to address space and 
functionality challenges; and (2) operations and maintenance 
challenges at these new facilities and State’s steps to address them. 
GAO analyzed staffing data and other documentation for 44 NECs built 
from 2001 to 2009 and interviewed State headquarters and embassy 
officials at 22 of these 44 NECs to obtain information on their 
functionality and operations and maintenance issues. 

What GAO Found: 

State has located nearly one-quarter of overseas staff in NECs, which 
posts said are an improvement over older facilities. However, NECs do 
not fully meet the space and functionality needs of overseas missions. 
Current staffing levels exceed the originally-built desk—or office—
space at over half of the 44 NECs GAO analyzed. Post management has 
dealt with space limitations by converting spaces, like conference 
rooms, into offices, but 4 posts have had to retain space outside the 
compound for staff that could not fit in the NECs. Also, officials at 
almost all of the 22 NECs that GAO reviewed in depth reported some 
spaces, like consular affairs spaces, did not fully meet their 
functional needs. According to State officials, it is difficult to 
predict changing foreign policy priorities that can affect staffing 
levels, and the process for planning NECs has been unable to fully 
account for these changes. Budget constraints also affected decisions 
about the size of NECs and types of features provided. State has taken 
some actions to improve NEC sizing, but does not have sufficient 
flexibility in its staffing projection and design processes to better 
address sizing challenges. To address problems with functionality, 
State implemented a lessons learned program to analyze issues in 
completed NECs and modify design criteria for future NECs, but State 
has not completed, in a timely manner, planned evaluations that are 
designed to identify such issues. 

While NECs are state-of-the-art buildings, they have presented 
operations and maintenance challenges, and the larger size and greater 
complexity of NECs, compared to facilities they replaced, have 
resulted in increased operations and maintenance costs. In 2010, State 
developed its first long-range maintenance plan that identifies $3.7 
billion in maintenance requirements over 6 years for all overseas 
facilities, but it does not include time frames for implementing 
identified maintenance projects or address increased operating costs. 
Problems with testing, or “commissioning,” new building systems have 
contributed to problems with building systems that do not function as 
they should, causing higher maintenance costs. State strengthened its 
commissioning process, though this change only applies to future NECs 
and does not address problems at existing NECs. Further, State does 
not currently recommission—or retest—NECs to ensure they are operating 
as intended. In addition, more than half of the 22 NECs that GAO 
reviewed in detail experienced problems with some building systems, 
resulting in the need for premature repair and replacement. Through 
its lessons learned program, State has changed some design criteria 
for future NECs to avoid problems with building systems. Finally, 
State has had problems hiring and training personnel who have the 
technical skills necessary to manage the complex NEC systems. State 
has taken initial steps to improve its staff hiring and training, but 
does not have an overall plan to establish its NEC human resource 
needs and the associated costs. 

What GAO Recommends: 

GAO recommends that the Secretary of State take several actions to (1) 
improve its processes for determining NEC size and ensuring that these 
facilities are fully functional, and (2) address challenges in meeting 
NECs' long-range operations and maintenance needs. 

GAO received comments from the Department of State, which agreed with 
our recommendations. State’s comments are reprinted in appendix II. 

View [hyperlink, http://www.gao.gov/products/GAO-10-689] or key 
components. For more information, contact Jess T. Ford (202) 512-4128, 
fordj@gao.gov or Terrell G. Dorn (202) 512-6923, dornt@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

NECs Do Not Fully Meet the Space and Functionality Needs of Overseas 
Posts and State Actions Have Addressed Some, but Not All, Challenges: 

NECs Are Challenging to Operate and Maintain; State Has Taken Steps to 
Address These Challenges, but Problems Remain: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments: 

Appendix I: Scope and Methodology: 

Appendix II: Comments from the Department of State: GAO comments: 

Appendix III: GAO Contacts and Staff Acknowledgments: 

Tables: 

Table 1: Reasons for Off-Site Employees at Four Posts: 

Table 2: Features Cited as Not Fully Meeting Posts' Functional Needs: 

Table 3: State's Recent Modifications to Address Functionality 
Challenges: 

Table 4: NEC Utility Costs Pre-and Post-Move for NECs Completed in 
2007 and 2008 (costs rounded to the nearest thousand): 

Table 5: Changes Made by State to the Standard Embassy Design to Avoid 
Problems with Building Systems on Future NECs: 

Table 6: Locations of 44 NECs within GAO's Scope: 

Figures: 

Figure 1: Percentage Difference between Current NEC Staffing Levels 
and As-Built Desks: 

Figure 2: Desk Differential in 25 NECs with Staffing Levels Exceeding 
As-Built Space by at Least 5 Percent: 

Figure 3: As-Built Desks versus Current Staffing Levels for State and 
other U.S. Government Agencies: 

Figure 4: Space Alterations in Kigali, Rwanda, and Belmopan, Belize: 

Figure 5: Issues with Warehouse Facilities: 

Figure 6: Issues with Maintenance Shops: 

Figure 7: Issues with Parking Areas: 

Figure 8: Issues with Quality-of-Life Amenities: 

Figure 9: Issues with Representational Space: 

Figure 10: Issues with Consular Affairs Section: 

Figure 11: Typical NEC Building Systems: 

Figure 12: Sofia, Bulgaria, the first LEED-Certified U.S. Embassy: 

Figure 13: Example of Condensation Causing Mold: 

Figure 14: Example of Inadequate Maintenance of Air Supply Diffuser 
and Cooling Units Added After System Failure: 

Figure 15: NEC Fire Panel in Kigali, Rwanda, with Trouble and 
Supervisory Lights Illuminated: 

Figure 16: NEC Sofia, Bulgaria: 

Figure 17: NECs Kigali, Rwanda, and Port-au-Prince, Haiti: 

Abbreviations: 

BME: Building Maintenance Expenses: 

BOE: Building Operating Expenses: 

DOE: Department of Energy: 

ICASS: International Cooperative Administrative Support Services: 

IG: Inspector General: 

LEED: Leadership in Energy and Environmental Design: 

LROMP: Long-Range Overseas Maintenance Plan: 

M/PRI: Office of Management Policy, Rightsizing, and Innovation: 

NEC: new embassy compound: 

OBO: Bureau of Overseas Buildings Operations: 

PEPFAR: President's Emergency Plan for AIDS Relief: 

SED: Standard Embassy Design: 

State: Department of State: 

USAID: U.S. Agency for International Development: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

July 20, 2010: 

Congressional Committees: 

In the wake of 1998 terrorist bombings of embassies in Dar es Salaam, 
Tanzania, and Nairobi, Kenya, that exposed the poor condition of and 
security vulnerabilities at U.S. diplomatic facilities overseas, the 
Department of State (State) began a multiyear, multibillion dollar 
program to replace insecure and aging diplomatic facilities worldwide. 
The goal of this program, the Capital Security Construction Program, 
is to construct safe, secure, functional, and modern diplomatic 
facilities at approximately 214 overseas posts as quickly as possible. 
The program incorporates the requirements of the Secure Embassy 
Construction and Counterterrorism Act of 1999[Footnote 1] that calls 
for new diplomatic facilities to be sufficiently sized to ensure that 
all U.S. government personnel at the post are located on-site. 
[Footnote 2] State's Bureau of Overseas Buildings Operations (OBO), 
which operates the program, also intends that these new embassy and 
consulate compounds are efficient, state-of-the-art office buildings. 

In 2006, we reported that State has made significant progress 
constructing new facilities but that better planning is needed for 
operations[Footnote 3] and maintenance[Footnote 4] requirements. 
[Footnote 5] State supported our recommendation that it should develop 
a plan that addressed the financial and human resources for meeting 
the immediate and long-term operations and maintenance requirements 
for new embassy compounds (NEC). Since 2001, OBO has completed 52 
NECs, and moved more than 21,000 United States government personnel--
about one-quarter of those employees working overseas--into more 
secure, safe, and functional facilities.[Footnote 6] OBO continues to 
manage ongoing construction and design of 33 additional facilities. 

In response to your request, we examined: (1) the extent to which NECs 
match the space and functionality needs of overseas posts and the 
actions State has taken to address any space and functionality 
challenges, and (2) operations and maintenance challenges at NECs and 
State's steps to address them. 

To address these objectives, we reviewed program, planning, budget, 
evaluation, and other analysis documents from State, as well as 
previous GAO reports on State's embassy construction program. To 
examine space needs, we analyzed data from State's capital security 
cost-sharing program for 44 of the 52 completed NECs. Our analysis 
does not include 8 completed NECs, which generally were excluded from 
our scope because they are unique projects, such as the NECs in 
Baghdad, Iraq, and Kabul, Afghanistan, or were recently completed in 
fiscal year 2010. We also reviewed 22 of the 44 NECs in greater depth, 
examining space, functionality, operations, and maintenance issues; we 
reviewed these NECs in more detail based on factors such as their 
geographic location and their history with staffing, functionality, 
operations, or maintenance challenges. For these 22 locations, we 
conducted site visits at 8 posts and teleconferences with 14 posts. As 
part of our review of operations and maintenance issues, we reviewed 
State documents and reports, including the Long-Range Overseas 
Buildings and Maintenance Plans. In addition, we discussed the embassy 
construction program with State officials in Washington, D.C.; from 
OBO; regional bureaus; and Office of Management Policy, Rightsizing 
and Innovation. Appendix I provides more information on our scope and 
methodology. 

We conducted this performance audit from February 2010 to July 2010 in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

The United States maintains facilities at more than 260 diplomatic 
missions, including embassies, consulates, and other diplomatic 
offices, located around the world. More than 80,000 U.S. government 
employees from 30 agencies depend on infrastructure that State 
provides and maintains. 

In 1998, terrorist bombings of embassies in Dar es Salaam, Tanzania, 
and Nairobi, Kenya, killed more than 220 people and injured 4,000 
others. In 1998, State formed the Accountability Review Boards to 
investigate the bombings. The Boards reported that unless security 
vulnerabilities at U.S. embassies and consulates were addressed, U.S. 
government employees and the public would remain at risk from 
terrorist attacks at many overseas facilities. In 1999, the Secretary 
of State formed the Overseas Presence Advisory Panel to appraise the 
condition of overseas facilities and consider the future of U.S. 
overseas representation. The Panel reported on the unsafe, 
overcrowded, deteriorating, and "shockingly shabby" conditions of U.S. 
embassies and consulates. Both the Boards and the Panel recommended 
that State replace insecure and aging diplomatic facilities worldwide. 
That same year, State embarked on a multiyear, multibillion dollar 
program to replace overseas facilities. Through its Capital Security 
Construction Program, administered by OBO, State intends to construct 
new facilities at 214 overseas posts with the goal of providing safe, 
secure, functional, and modern buildings as quickly as possible. The 
program incorporates the requirements of the Secure Embassy 
Construction and Counterterrorism Act of 1999 that calls for new 
diplomatic facilities to be sufficiently sized to ensure that all U.S. 
government personnel at the post are located on-site. In June 2006, we 
reported that State had made significant progress in completing new 
embassy and consulate compounds.[Footnote 7] As of April 2010, State 
has completed 52 NECs and placed over 21,000 U.S. government 
employees--or about one-quarter of the population working overseas--in 
more safe, secure, and functional facilities. 

To enable timely completion of its construction projects, OBO 
typically uses the design-build project delivery method[Footnote 8] 
and a Standard Embassy Design (SED) that can be adapted to accommodate 
conditions at each project site.[Footnote 9] NECs generally consist of 
a main office building (chancery), compound access control buildings, 
utility buildings for mechanical and electrical systems, and Marine 
Security Guard quarters (if a post has a Marine contingent). Depending 
on the site, the project budget, and the needs of the post, a new 
compound could also include a General Services support annex, a 
warehouse, maintenance shops, recreation facilities, and employee and 
public parking areas. Some compounds also include an annex building 
for USAID or other program or agency functions. In 2003, we found that 
staffing projections for NECs were developed without a systematic 
approach or comprehensive rightsizing analyses, potentially resulting 
in wrong-sized buildings, and recommended, among other things, that 
State provide overseas posts with comprehensive guidance on developing 
staffing projections for NECs.[Footnote 10] In 2004, State created the 
Office of Management Policy, Rightsizing, and Innovation (M/PRI), 
which now manages the process for developing NEC staffing projections. 
In establishing project requirements, OBO obtains information on a 
post's projected staffing from M/PRI, which works closely with 
officials at the post, State's regional bureau, and other U.S. 
government agencies to develop a 5-year projection of the post's 
staffing needs based on an assessment of mission priorities and the 
staffing levels required to pursue those priorities. With this 
information, OBO outlines space requirements that define functional 
needs for office (desks), common use (conference rooms, cafeteria), 
support (janitor closet, mechanical rooms), and future growth space. 
OBO uses this space requirements analysis to estimate the cost of each 
project, which forms the basis for State's Capital Security 
Construction Program budget request. At the time of State's budget 
submission, OBO considers project requirements to be "locked," meaning 
it intends to construct the facility according to the requirements 
that were used to set the budget request. OBO generally locks project 
requirements 2 years prior to awarding a contract for design-build 
services. 

In our June 2006 report on State's progress in constructing NECs, 
[Footnote 11] we noted the comparatively higher utility consumption of 
the new facilities caused, for example, by the need to continually 
operate heating, ventilation, and air conditioning systems--that may 
not have existed in former facilities--to adequately condition spaces 
in the sealed buildings.[Footnote 12] In addition, we reported that 
posts have had to hire additional maintenance staff with the skills 
and qualifications to maintain the state-of-the-art buildings. In 
consideration of these and other factors, we estimated that once all 
new diplomatic facilities were completed, total post-funded annual 
operations and maintenance costs, adjusted to 2006 constant dollars, 
could increase by at least $71 million and possibly by several times 
more over those posts' previous facilities. Because we found that 
State was slow to recognize the increased funding needed to operate 
and maintain its new facilities and had not developed a comprehensive 
plan that details long-term resource requirements necessary for 
protecting its investment in the facilities, we recommended that the 
Secretary of State develop an integrated and comprehensive facilities 
plan that clearly specifies the financial and human resources for 
meeting the immediate and long-term operations and maintenance 
requirements for NECs. State agreed with our findings and indicated it 
would take action to address the recommendation. 

NECs Do Not Fully Meet the Space and Functionality Needs of Overseas 
Posts and State Actions Have Addressed Some, but Not All, Challenges: 

State is making progress moving staff into more secure and functional 
facilities. However, we found that over half of the 44 NECs completed 
from 2001 through 2009 have staffing levels that exceed the number of 
desks originally provided by 5 percent or more. Additionally, 
officials at nearly all of the 22 NECs we reviewed in greater depth 
reported the design of some spaces--such as consular areas, 
warehouses, or maintenance shops--did not fully meet their functional 
needs. According to State officials, it is difficult to predict 
changes in foreign policy priorities that can affect overseas staffing 
levels, and the current process for planning NECs has been unable to 
fully account for these changing needs. State officials also indicated 
that budget constraints affected decisions about the overall size and 
types of features provided in NECs. In some cases, space and 
functionality challenges resulted in the need to conduct follow-on 
projects after posts occupied the NEC, resulting in millions of 
dollars of additional costs. State has taken steps to address some 
space and functionality challenges, such as creating M/PRI to 
standardize the process for projecting future staffing levels; 
incorporating some additional flexibility for future growth into NECs; 
and implementing a lessons learned program to analyze issues in 
completed NECs and modify design criteria for future NECs. However, 
sizing NECs remains challenging and State did not provide the 
analytical basis for determining how much growth space should be 
incorporated into an NEC. Additionally, State has not conducted 
planned evaluations of completed NECs to ensure timely identification 
of issues. 

State Is Making Progress Locating Staff in More Secure and Functional 
Facilities: 

As of April 2010, State has moved over 21,000 people--or about one- 
quarter of all overseas staff--into new facilities. State's Inspector 
General (IG) and OBO have reported that posts are satisfied with many 
aspects of their NECs, such as the improved security they provide. In 
2008, State's IG reported that posts commented favorably about their 
NECs and praised their design, space, and security.[Footnote 13] In 
2007, OBO surveyed officials at posts with NECs, and occupants 
responded positively about many aspects of their NECs, particularly 
when compared with old facilities. For example, 86 percent of 
respondents agreed or strongly agreed with the statement that "the 
layout of the NEC is well designed compared with the previous 
facility." Overall, respondents rated security improvements and the 
fact that personnel were all located on a single compound as NECs' two 
most important improvements to achieving their diplomatic mission. In 
many cases, posts moved from facilities that were in poor condition, 
insecure, and scattered throughout the city. State officials noted 
that, in general, NECs are a dramatic improvement over older 
facilities. For example, the former embassy in Sofia, Bulgaria, 
consisted of seven buildings spread throughout the city that did not 
meet current security standards and suffered from seismic and 
structural deficiencies. In comparison, officials in Sofia noted the 
NEC was one of the nicest buildings in Bulgaria. Additionally, 
officials at overseas posts and State's regional bureaus commented on 
the professional environment of the NECs. For example, officials at 
overseas posts stated that NECs were a positive representation of the 
United States' commitment to the host country. However, some officials 
also pointed out that the external appearance of NECs can be imposing 
and that increased security standards, including the fact that many 
NECs are located far from city centers, in part to meet more stringent 
security requirements, reduced the willingness of host government 
officials to hold meetings at NECs. 

As Originally Constructed, Over Half of NECs Did Not Have Enough Desks 
for Current Staffing Levels, Resulting in the Need to Add Desks, Which 
Has Had Some Negative Consequences: 

Over half of the 44 NECs we analyzed did not have enough desk space to 
meet current staffing needs. Post management has converted common 
spaces, such as conference rooms or training rooms, into offices in 
order to accommodate additional desks on the compound. However, 
actions taken to accommodate additional staff have had some negative 
consequences, such as the loss of common spaces. 

Current Staffing Levels Exceed Originally Constructed Desk Space at 
Over Half NECs: 

While NECs are a long-term investment that State intends to serve a 
post for decades, our analysis shows that most posts have filled their 
originally constructed space within just a few years of occupying the 
NEC. Over half (25 of 44) of the posts occupying NECs completed from 
2001 through 2009 currently have more staff requiring desks than were 
provided in the NEC's original construction.[Footnote 14] 
Specifically, as indicated in figure 1, our analysis of data for all 
44 posts in our scope shows that current staffing levels exceed as-
built desks--the number of desks provided when the NEC was 
constructed--by 10 percent or more at 21 of the 44 posts and exceed as-
built desks by at least 5 percent at 4 additional posts.[Footnote 15] 
Not all posts have exceeded the desk space initially provided. For 
example, our analysis also shows 13 posts have current staffing levels 
at least 5 percent below as-built desk space. However, officials at 
overseas posts noted that having some excess space can be helpful, as 
posts may require additional space over time and it provides 
flexibility for post management to adapt to changing circumstances. 

Figure 1: Percentage Difference between Current NEC Staffing Levels 
and As-Built Desks: 

[Refer to PDF for image: pie-chart] 

Total NECs = 44. 

Staffing levels higher than as-built desks: 
21 NECs: more than 10 percent higher: 48%; 
4 NECs: 5-10 percent higher: 9%. 

Staffing levels approximately equal to as-built desks: 
6 NECs: within 5 percent: 14%. 

Staffing levels under (less than) as-built desks: 
6 NECs: More than 10 percent under: 14%; 
7 NECs: 5-10 percent under: 16%. 

Source: GAO analysis of State data. 

Note: Numbers may not add to 100 percent due to rounding. 

[End of figure] 

As figure 2 demonstrates, our analysis shows a difference of more than 
50 desks for 11 of the 25 posts in which current staffing levels 
exceed as-built desk space by at least 5 percent.[Footnote 16] 

Figure 2: Desk Differential in 25 NECs with Staffing Levels Exceeding 
As-Built Space by at Least 5 Percent: 

[Refer to PDF for image: vertical bar graph] 

Current desk needs in excess of as-built desks: Staff levels exceed as-
built desks by 50 or fewer desk positions: 
20 or fewer: 5. 
21-50: 
51-100: 
More than 100: 

Current desk needs in excess of as-built desks: Staff levels exceed as-
built desks by 50 or fewer desk positions: 
21-50: 9. 
51-100: 
More than 100: 

Current desk needs in excess of as-built desks: Staff levels exceed as-
built desks by 51 or more desk positions: 
51-100: 8. 
More than 100: 

Current desk needs in excess of as-built desks: Staff levels exceed as-
built desks by 51 or more desk positions: 
More than 100: 3. 

Source: GAO analysis of State data. 

[End of figure] 

State typically plans NECs with some additional desk space for future 
growth, but the amount of growth space provided fluctuated over time 
and across posts. When the NECs we examined were designed, State 
typically budgeted for NECs to include from 5 percent to 10 percent 
additional desk space as future growth space.[Footnote 17] Some growth 
space is designed as office space, with desks or cubicles installed 
during construction, while other growth space may initially be 
designed as conference rooms or file rooms, with the intention that 
they can be converted to office space in the future, if needed. 
State's typical growth factor for NECs has fluctuated over time. Prior 
to 2003, OBO typically planned for growth space equivalent to 10 
percent of the projected desk space in an NEC. However, in 2003, due 
to concerns about the high cost of the embassy construction program, 
OBO reduced the growth space allowance to 5 percent of an NEC's 
projected desk space needs. In 2008, OBO returned to a 10 percent 
growth factor to provide a greater margin to accommodate unanticipated 
growth. These policies only serve as general guides, though, and some 
NECs received less growth space than is typically budgeted. For 
example, in Bamako, Mali, State eliminated growth space in the 
chancery in order to reduce total construction costs to meet 
construction contractor bids that were higher than anticipated. 

For the 25 posts in which current staffing levels exceed as-built 
space by at least 5 percent, we found that, in general, the number of 
State positions has grown more than the number of positions for all 
other agencies, including the U.S. Agency for International 
Development (USAID). As shown in figure 3, for the 25 posts 
collectively, the number of current State desk positions exceeds as-
built desk space by more than 1,400 desks, or 38 percent. 
Comparatively, the number of desk positions for all other U.S. 
government agencies combined exceeds as-built desk space by about 200 
desks, or 10 percent. Individually, we found a larger increase--both 
in terms of absolute numbers and percentage increase--in the number of 
State desk positions than in the number of other agency desk positions 
at 20 of the 25 posts. 

Figure 3: As-Built Desks versus Current Staffing Levels for State and 
other U.S. Government Agencies: 

[Refer to PDF for image: vertical bar graph] 

U.S. government agency: State; 
As-built desks: 3,795; 
Current desk positions: 5,237. 

U.S. government agency: Other agencies; 
As-built desks: 1,997; 
Current desk positions: 2,198. 

Source: GAO analysis of State data. 

[End of figure] 

Because our analysis groups all non-State agencies into a single 
category, it may not highlight the changing make up of overseas posts. 
While some non-State agencies have grown substantially, other agencies 
have reduced their overseas presence. For example, according to one 
State official, law enforcement agencies have increased their overseas 
presence since September 11, 2001, while the Departments of the 
Treasury and Transportation reduced their overseas staffing levels. 
Additionally, some of the growth within State may have resulted from 
consolidating administrative services once all agencies collocated at 
the NEC. State has taken on additional administrative responsibilities 
while other agencies were able to reduce administrative staff. 
[Footnote 18] 

Some State officials commented that the earliest-built NECs are more 
likely to have space shortages, since it is difficult to project 
staffing levels farther into the future and there has been more time 
for the post to outgrow the space originally provided. However, we 
found that the age of an NEC was not a major factor in explaining 
space shortages. For example, while 4 of the 6 NECs completed from 
2001 to 2003 have shortages of 5 percent or more, 8 of the 16 NECs 
occupied since 2007 also have shortages of 5 percent or more. 

Posts Have Used Growth Space, Converted Conference Rooms and Other 
Common Spaces, and Reduced Cubicle Size to Locate Staff On-Compound: 

We reviewed 22 posts in greater depth to determine how they found 
office space for additional staff. At most of the 22 posts we 
reviewed, State was able to find enough space on the new compound for 
all additional staff. Current staffing levels exceed as-built desk 
space by at least 5 percent in 15 of the 22 posts we reviewed. Eleven 
of those posts were able to accommodate all desk positions on compound 
by using growth space; converting common spaces, such as conference 
rooms or training rooms, into offices; or reducing cubicle sizes. 
Figure 4 provides examples of some spaces that posts have converted 
into office space. 

Figure 4: Space Alterations in Kigali, Rwanda, and Belmopan, Belize: 

[Refer to PDF for image: 3 photographs] 

Left photo to right photo, Kigali, Rwanda: File room converted to 
office space (before and after photos). 

Above photo, Belmopan, Belize: Kitchen converted to office space. 

Source: GAO. 

[End of figure] 

However, 4 of the posts we reviewed had to retain some office space 
off-site. Table 1 lists the posts that have office space off-site, as 
well as the reasons for doing so. 

Table 1: Reasons for Off-Site Employees at Four Posts: 

Post: Abuja, Nigeria; 
Reason(s) some employees are off-site: Staffing levels at the post 
outgrew the amount of space that was initially planned. Space 
constraints in Abuja have been exacerbated by substantial delays in 
construction of a USAID annex, which was planned concurrently with the 
chancery but not funded at that time.[A] Currently, the post leases 
off-site space for staff who cannot fit on-compound, including those 
who will be located in the USAID annex. Even once the USAID annex is 
completed, however, post management anticipates it will be too small 
for their current needs, and some agencies will likely have to remain 
off-site. 

Post: Beijing, China; 
Reason(s) some employees are off-site: Staffing levels at the post 
outgrew the NEC before construction was completed. The post retained 
one of the old embassy buildings to temporarily house the employees 
that cannot fit in the NEC, and OBO plans to construct an additional 
annex on the new compound. 

Post: Berlin, Germany; 
Reason(s) some employees are off-site: The size of the new chancery 
was reduced due to budget limitations, resulting in a new facility 
that could not accommodate all post staff. The post retained two old 
facilities--an office building and a warehouse/General Services Office 
annex building--to house staff and functions that could not fit in the 
new facility. 

Post: Kathmandu, Nepal; 
Reason(s) some employees are off-site: The NEC site is not large 
enough to accommodate a General Services Office annex and warehouse. 
State was required to retain some of the old facilities, so it opted 
to keep some functions, including a small number of desk positions, on 
the old compound. 

Source: GAO. 

[A] Prior to the creation of the Capital Security Cost Sharing 
program, which centralized funding for NEC construction, State built 
new embassy compounds in separate stages, typically constructing USAID 
annexes after construction began--or sometimes after construction was 
completed--on the rest of the compound. For additional information, 
see GAO, Embassy Construction: Achieving Concurrent Construction Would 
Help Reduce Costs and Meet Security Goals, GAO-04-925 (Washington, 
D.C.: Sept. 24, 2004). 

[End of table] 

In addition to potentially increasing the security risks for those 
employees not on-compound, State officials noted that having employees 
off-compound results in additional costs and can affect coordination 
across the mission and reduce the efficiency of posts' operations 
because embassy personnel have to spend more time in transit between 
facilities. In the cases in which posts have some staff working off- 
site, post management has had to either retain old facilities or lease 
additional office space. In the case of Berlin, the most cost-
effective option for locating staff off-site--at an estimated cost of 
$25 million--involved purchasing and renovating an office facility the 
post had formerly leased. In Abuja, leasing off-site office space 
costs over $800,000 per year. 

Space Constraints and Actions Taken to Add Desks Have Had Some 
Negative Consequences for Post Operations: 

State officials noted that, because post management often has to 
convert common areas, such as conference rooms or training rooms, into 
offices to accommodate additional staff, posts may not have sufficient 
meeting or training space. For example, regional bureau officials 
stated that dedicated training rooms in NECs are often converted into 
office space, but that having training space is important for embassy 
operations. Officials also noted that other actions, such as having 
staff share desks or locating new staff in available spaces far from 
the rest of their agency or section, can result in operational 
inefficiencies. For example, at one African post, some FBI staff have 
to work in shifts in order to share a limited number of classified 
computers. 

Additionally, officials at some of the posts we reviewed expressed 
concerns that space could increasingly become a consideration in 
approving requests for new overseas positions, potentially reducing 
the post's ability to execute its mission. In general, the vast 
majority of new position requests are approved--over 97 percent of all 
requests were approved in 2008 and 2009. In considering new position 
requests, State advises Chiefs of Mission to consider space 
availability, among other issues, and we found that a few position 
requests at posts with NECs have been denied, at least in part, 
because of space constraints. According to State data, in a few 
instances, posts have cited resource limitations, including space 
constraints, when denying requests for new overseas positions. Of the 
seven posts that cited resource limitations when denying requests for 
overseas positions in 2008 and 2009, three currently occupy NECs and 
one is scheduled to move into an NEC with known space shortages in 
2010. Some post officials also noted that space shortages can make it 
difficult to accommodate short-term, or temporary duty, positions. 
Officials noted that, in cases where the NEC has little or no 
available office space, it can be difficult to find places for short-
term staff to work. At some posts, the number of short-term positions 
can be quite large. For example, an official in Beijing, China, stated 
that the post can have up to 100 short-term staff at the NEC on any 
given day and finding desks for them can be challenging. 

Officials at Nearly All Posts We Reviewed Reported the Design of Some 
Spaces Did Not Fully Meet Their Functional Needs: 

Though staff at overseas posts noted many aspects of NECs function 
well, officials at 21 of the 22 posts we reviewed reported the design 
of some spaces within the NEC did not fully meet their functional 
needs, with an average of five functionality-related issues per post. 
While officials reported a variety of different concerns about each of 
the spaces, several officials noted an overarching concern that the 
design of some spaces in the NEC failed to take into account local 
conditions, such as weather or economic factors, or how the post would 
ultimately use the space. Table 2 shows the six most commonly cited 
issues. 

Table 2: Features Cited as Not Fully Meeting Posts' Functional Needs: 

Features commonly cited as not fully meeting posts' functional needs 
at 22 NECs: Warehouse; 
Number of posts reporting issues: 16. 

Features commonly cited as not fully meeting posts' functional needs 
at 22 NECs: Maintenance shops; 
Number of posts reporting issues: 16. 

Features commonly cited as not fully meeting posts' functional needs 
at 22 NECs: Parking; 
Number of posts reporting issues: 16. 

Features commonly cited as not fully meeting posts' functional needs 
at 22 NECs: Quality-of-life amenities (e.g., cafeteria, recreational 
facilities); 
Number of posts reporting issues: 14. 

Features commonly cited as not fully meeting posts' functional needs 
at 22 NECs: Atrium and other representational space; 
Number of posts reporting issues: 13. 

Features commonly cited as not fully meeting posts' functional needs 
at 22 NECs: Consular Affairs section; 
Number of posts reporting issues: 11. 

Source: GAO. 

[End of table] 

Figures 5 through 10 provide descriptions of some of the types of 
issues post officials reported with each of the above functional areas. 

Figure 5: Issues with Warehouse Facilities: 

[Refer to PDF for image: photograph and associated information] 

Size/No Warehouse: 
Officials reported that some on-compound warehouses are too
small, in some cases resulting in the need to rent an additional
warehouse off-site or to use supplemental storage, such as
shipping containers, on compound. Additionally, some NECs do
not have a warehouse on compound, which can be challenging,
according to some post officials. It can result in added costs to
lease off-site space and one official noted that, because security
requirements prohibit American officers from working full time
from an off-site warehouse, one official noted it can be more
difficult to oversee warehouse operations when they are off
compound. Post officials also said increased transportation time
between facilities can result in inefficiencies. 

Layout: 
The layout of some NEC warehouses, including the type of
shelving provided or the configuration of the shelves, did not
meet posts’ needs. 

To the right: In Nairobi, Kenya, it can take up to 2 hours for
staff to drive one way from the NEC to the off-site warehouse.
Consequently, post staff moved several shipping containers onto
the NEC (shown at right) to meet their more immediate storage
needs. 

Source: GAO. 

[End of figure] 

Figure 6: Issues with Maintenance Shops: 

[Refer to PDF for image: photograph and associated information] 

Size/Type of Shops: 
Officials reported issues relating to the size or types of shops
provided, often noting that shops are too small for their intended
purpose, or space was not provided for one or more shops
needed for the post’s operations. For example, officials in
Panama City, Panama, said that no vehicle maintenance shop
was provided in the NEC. Additionally, some post officials said
having no maintenance shops at the NEC can pose challenges,
such as having to lease off-site space, resulting in reduced
efficiency associated with traveling between locations. 

Design: 
The design of some shops does not meet posts’ needs. For
example, in Accra, Ghana, officials noted that the welding shop
was not outfitted with adequate ventilation, so maintenance staff
cannot use it for its intended purpose. 

To the right: The ceiling in the auto maintenance shop in
Port-au-Prince, Haiti, is too low to fully extend the vehicle lift for
large vehicles like trucks. 

Source: GAO. 

[End of figure] 

Figure 7: Issues with Parking Areas: 

[Refer to PDF for image: photograph and associated information] 

Staff/Visitor Parking: 
Some NECs do not have adequate parking for staff or visitors.
Some officials noted that, because many NECs are located far
from city centers where public transportation can be less
reliable, parking can take on an added importance. 

Covered Parking: 
Some officials reported their NEC has inadequate covered
parking for official armored vehicles. The vehicles’ armor coating
can be damaged by exposure to the intensive sun common at
some overseas posts. Having inadequate covered parking can
shorten the lifespan of the armor and result in costly
replacements or repairs. 

To the right: In Belmopan, Belize, the NEC has only two covered
parking spaces for five armored vehicles. 

Source: GAO. 

[End of figure] 

Figure 8: Issues with Quality-of-Life Amenities: 

[Refer to PDF for image: photograph and associated information] 

Size/Design:
In some cases, officials noted the size or design of one or more
quality-of-life amenities, such as cafeterias and gyms or other
recreational facilities, was inappropriate given the number of
staff at the post or the availability of alternatives in the vicinity of
the NEC. Some officials noted that design problems resulted in
amenities that, while nice, were largely unused. 

Features Not Provided: 
In other cases, officials stated that some features were not
provided in the NEC. For example, in Abuja, Nigeria, the NEC
does not have a cafeteria, so the post is currently using two
shipping containers as a temporary replacement. According to
State officials, many overseas posts are located in places that
provide few commercial recreational options, making
quality-of-life amenities important for staff morale. 

To the right: The commercial cafeteria in Belmopan, Belize,
which post staff estimated cost $1 million, has largely been
unused in the 3 years the NEC has been occupied. Post
management reported that the cafeteria is far too large for its
needs and that the relatively small size of the post, in
combination with its remote location, make it unlikely that the
post will be able to support a commercial vendor. 

Source: GAO. 

[End of figure] 

Figure 9: Issues with Representational Space: 

[Refer to PDF for image: photograph and associated information] 

Atrium: 
Until 2006, the SED included a three- or four-story atrium,
which was intended, in part, as space to host representational
functions. While officials at some posts commented that the
atrium space was useful for representational events, officials at
other posts reported challenges associated with the atrium,
including that it is expensive to heat and cool, difficult to
maintain, and its long, narrow layout and location inside the
embassy, which requires additional security procedures for
guests and caterers, can make it difficult to use for events. 

Other Representational Space: 
Some NECs, including some that were planned prior to the
development of the SED or special projects like the NEC in
Berlin, do not have an atrium. Officials at some of these posts
also reported difficulties with hosting representational
functions at the NEC. 

Executive Offices: 
Officials reported that offices for the Ambassador and Deputy
Chief of Mission can be too small, making it difficult to use the
space for meetings. 

To the right: Officials in Tashkent, Uzbekistan, reported that the
long, narrow layout of the atrium makes it difficult to host large
events in the space. 

Source: GAO. 

[End of figure] 

Figure 10: Issues with Consular Affairs Section: 

[Refer to PDF for image: photograph and associated information] 

Consular Interview Windows: 
Some posts reported concerns about either the layout or number of
consular interview windows in the NEC. For example, some officials said
the layout of the desk area on the teller side of the window provided 
little room for reviewing and processing papers and that poor acoustics
complicated transactions between consular staff and visitors. 

Waiting Areas: 
Officials reported issues with some consular waiting areas, such as
interior waiting areas that are too small or outdoor waiting areas that
have insufficient cover from sun or rain. 

Supervisory Line of Sight: 
Officials at four posts reported issues associated with consular
supervisors having a clear line of sight of the consular section.
According to a Consular Affairs official, a clear line of sight is 
intended to improve management controls and prevent visa malfeasance. 
Consular Affairs guidance notes that consular officers should be able 
to easily see all the print areas, most work areas, most of the 
interview windows, and have clear views from two or more angles into 
the cashier booth, from their desks. 

To the right: View from the office designed for the consular chief in
Belmopan, Belize, from which only two of the four consular windows and
none of the print areas or work areas are visible. As a result of this
obscured line of sight, the consular chief cannot use the office and,
instead, has moved to a cubicle in the main work area. 

Source: GAO. 

[End of figure] 

Challenges with Projecting Future Staffing Levels and Budget 
Constraints Have Resulted in the Need to Conduct Follow-on Work: 

According to State officials, it is difficult to predict changes to 
staffing levels associated with shifting foreign policy priorities, 
and the process for planning NECs has not been able to fully account 
for those changes. State officials also indicated that budget 
limitations contributed to decisions about the overall size and types 
of features provided in NECs. In some cases, space and functionality 
challenges resulted in the need to conduct follow-on projects, 
resulting in millions of dollars of additional costs. 

The Current Process for Sizing NECs Has Not Been Able to Fully Account 
for Changing Foreign Policy Priorities: 

According to State officials, the process for planning NECs has not 
been able to fully account for changing staffing levels associated 
with shifting foreign policy priorities. Because of the time required 
to plan and construct an NEC, there can be a lag of multiple years 
from the time staffing projections are finalized to the time a post 
moves into an NEC. The process for projecting future staffing needs 
starts with an assessment of mission priorities and the staffing 
levels necessary for carrying out those priorities. Therefore, State 
officials noted it can be very difficult to predict future staffing 
levels when changes occur as a result of unexpected events or 
initiatives. Officials at overseas posts, OBO, the regional bureaus, 
and M/PRI all agreed that changes in U.S. foreign policy priorities 
following the planning or construction of an NEC resulted in 
significant growth at many posts, contributing to the differences 
between current staffing levels and as-built desk space. According to 
State officials, some posts have had large increases in staffing due 
to recent initiatives, such as the President's Emergency Plan for AIDS 
Relief (PEPFAR) and recent State and USAID initiatives to 
substantially increase their Foreign Service presences. For example, 
according to officials in Kigali, Rwanda, the post's staffing 
projections predicted that the Centers for Disease Control and 
Prevention would have 18 desk positions at the time the NEC opened, 
but it actually had 34 desk positions when the NEC opened because of 
increases associated with PEPFAR. Staffing levels have also reflected 
changing needs in response to world events. For example, according to 
an M/PRI report, following the terrorist attacks of September 11, 
2001, many law enforcement, security, and military agencies increased 
their overseas presence. According to State officials, many of these 
initiatives were not anticipated when NECs were planned. 

Additionally, when staffing projections are prepared, an agency may 
not have clearly planned for or articulated future needs. According to 
State officials, some agencies have historically been better than 
others in developing staffing projections and articulating the policy 
justifications for staffing growth. However, other agencies have been 
less clear in their planning, complicating State's ability to plan an 
NEC. For example, State officials report that USAID frequently revises 
its projected staffing levels, sometimes even after construction of a 
facility has begun. Also, as our earlier analysis showed, at the posts 
that have exceeded as-built desk space by at least 5 percent, State 
has grown substantially more than other agencies, indicating it has 
also been challenging for State to predict its own future staffing 
levels. 

State officials also noted that the staffing projections that 
determine an NEC's size are not directly tied to the process for 
approving actual staffing levels at each post.[Footnote 19] OBO sizes 
NECs based on staffing projections provided in a post's rightsizing 
report. While posts, tenant agencies, and the regional bureaus all 
have input into the rightsizing process, M/PRI has final approval for 
these staffing projections. However, State officials noted that the 
Chief of Mission has authority over actual staffing levels at each 
post and may approve positions beyond the levels planned for in the 
NEC. According to State officials, in cases where M/PRI and the Chief 
of Mission do not agree on the appropriate staffing levels for a post, 
discrepancies can result between an NEC's planned size and the post's 
actual staffing levels. For example, in Addis Ababa, Ethiopia, the 
post's initial projections anticipated the post would expand and 
become a regional center. Both M/PRI and State's IG disputed the 
premise that Addis Ababa should be a regional center, noting that 
Nairobi, Kenya, already serves a regional role in East Africa. In 
addition, M/PRI found the post's initial projections included 
substantial growth even though the post had dozens of unfilled 
positions. Therefore, the rightsized staffing projections anticipated 
more limited growth, reducing the post's initial projections by 47 
desk positions. However, the Chief of Mission continued to add new 
positions at a rate even faster than the post initially projected and, 
in 2009, OBO had to initiate changes after construction of the Addis 
Ababa NEC had already begun in order to accommodate 96 additional desk 
positions at a cost of about $13 million. 

OBO officials report it is difficult to make changes to a project to 
accommodate changing needs after the staffing projections have been 
finalized. The NEC construction process typically requires a 2-year 
lag from the time staffing projections are initiated to the time a 
contract is issued and an additional 3-year lag between contract 
issuance and the time a post moves into the NEC. When changes are 
requested, State officials said State and other tenant agencies may 
reassess the project to determine whether the requirements are 
critical enough to warrant changing the project's planned schedule and 
budget. In some instances, State officials reported changes could be 
accommodated to the program and in other cases changes could not. OBO 
officials noted it is easier to make changes to a project before a 
contract has been awarded. While changes have been made to a few 
projects after a contract has been issued, OBO officials stated it is 
not preferable because it can increase costs and delay construction. 

Budget Limitations Also Contributed to Space Constraints and 
Functionality Issues: 

Budget limitations also contributed to space constraints and 
functionality issues in some NECs. According to OBO officials, 
congressional and executive concerns about the high cost of the 
embassy construction program were a primary reason for the 2003 
decision to reduce the NEC growth factor from 10 percent to 5 percent. 
Budget limitations also impacted decisions about the overall size of 
the NEC at some posts with significant desk shortages. For example, 
State officials noted that, the overall size of the NEC in Dushanbe, 
Tajikistan--where, according to our analysis, current staffing levels 
are more than double the number of desks initially provided--was 
largely based on the planned budget.[Footnote 20] We identified 10 
posts in which some spaces or features were reduced or eliminated 
between the initial planning and final construction of the NEC. Some 
NECs were significantly affected by budget limitations. In Berlin, 
Germany, for example, more than one-third of the originally planned 
space in the new facility was cut due to budget limitations.[Footnote 
21] In Conakry, Guinea, functional spaces--including the cafeteria, 
multipurpose room, and most conference rooms--were cut in order to 
meet the project's planned budget. According to OBO officials, 
programmatic support facilities, such as warehouses, recreational 
facilities, and cafeterias, were eliminated from a project's scope 
before any changes were made to office space. State officials noted 
that, in some cases, reducing the scope of a project may have been 
preferable to delaying the project. 

Space and Functionality Challenges Resulted in the Need for Follow-on 
Work at Some Posts: 

In some cases, problems with space and functionality resulted in the 
need to conduct follow-on work after the post moved into the NEC, such 
as planning for a major redesign of interior space or constructing an 
office annex or support facility, which has cost implications. 
[Footnote 22] In particular, State has completed or plans to complete 
new construction or major renovations in at least six of the 44 
completed NECs within our scope. For example, State is constructing an 
office annex in Beijing, China, to accommodate 318 additional desks at 
a cost of $103 million. In Dushanbe, Tajikistan, OBO developed a plan 
to rearrange space within the existing chancery to accommodate new and 
projected desk positions, as well as build a warehouse and maintenance 
shops on-compound. In total, OBO estimates the changes will cost about 
$7.5 million, but notes that, even with the recommended changes to add 
office space, there will be no available space for future growth 
beyond the staffing levels projected for 2013. Additionally, in its 
2010 Long Range Overseas Maintenance Plan, OBO identifies 96 needed 
projects for the 22 posts we reviewed in greater depth at a total cost 
of approximately $98 million. Most of the costs are attributable to 
major rehabilitation projects, including $42 million in Frankfurt, 
Germany, for renovations that were anticipated but not undertaken when 
the post originally moved into the new facilities in 2005.[Footnote 
23] Additionally, officials at 16 of the 22 posts we reviewed reported 
they have already undertaken follow-on projects of varying size and 
complexity to correct problems with their respective NEC. 

State Has Begun to Take Actions to Address Space and Functionality 
Challenges, but Not All Problems Have Been Fully Addressed: 

State has recognized many of the problems related to space and 
functionality and has taken actions that have resulted in 
improvements, but not all problems have been fully addressed. To 
improve NEC sizing, State created M/PRI to standardize the process for 
projecting future staffing levels. Additionally, OBO has taken some 
actions to incorporate additional flexibility for growth in NECs. 
However, accurately projecting future staffing needs remains 
challenging and State did not provide an analytical basis for 
determining how much growth space is appropriate. To address 
functionality challenges, OBO implemented a lessons learned program 
that analyzes issues in completed NECs and, as appropriate, modifies 
design criteria for future NECs. However, State has not ensured timely 
identification of problems in completed NECs through reviews, like 
post-occupancy evaluations. 

State Has Taken Actions to Improve Sizing of NECs, but Challenges 
Remain: 

Through its creation of M/PRI in 2004, State standardized the process 
for developing staffing projections for posts receiving an NEC. As we 
noted in 2003, under State's prior process, State's headquarters gave 
embassies little guidance on factors to consider in developing 
projections, and U.S. agencies therefore did not take a consistent or 
systematic approach to determining long-term staffing needs. M/PRI now 
directs the process and has developed formal guidance on developing 
staffing projections for posts. According to State officials, in 
combination with the 2005 establishment of the Capital Security Cost 
Sharing program, through which each agency with an overseas presence 
contributes funds for construction on the basis of its overseas 
staffing levels and the type of space occupied, changes made through 
the rightsizing process have brought greater discipline to the 
planning process and have provided greater incentive for State and 
other agencies operating overseas to seriously consider their long-
term staffing needs. State has also undertaken efforts to work more 
closely with tenant agencies to better understand their staffing 
needs. For example, State now meets with officials from USAID on a 
monthly basis to discuss future staffing needs. 

OBO has also taken actions to incorporate some additional flexibility 
for growth into NECs. According to OBO officials, the SED was changed 
to incorporate more flexibility after the first year of its use. For 
example, the first version of the SED included detailed floor plans 
that dictated where offices and open workstations would be located. 
However, in the SED's second year, OBO moved to a different approach 
that focused on the overall size of the NEC but left greater interior 
flexibility to rearrange office space. Recognizing the need to 
reassess the amount of growth space provided in NECs, in 2008 OBO 
increased the standard growth factor from 5 percent back to 10 
percent, which it had been prior to 2003, to provide a greater margin 
to accommodate unanticipated growth. According to State officials, OBO 
has made an effort to be more accommodating to changing post needs 
through the design and construction process, when possible. OBO 
officials noted four cases in which they made changes to add space to 
an NEC's design after the staffing projections were finalized. 
However, officials also stated that, while they want to accommodate 
posts' needs, OBO prefers to avoid making changes after the contract 
has been issued because it is costly and can cause substantial delays. 

While the implementation of a formal rightsizing process is an 
important step to improving projections for sizing NECs, accurately 
planning for future needs remains challenging. State officials 
acknowledged it remains difficult to accurately project future 
staffing needs. While only 6 of the 44 posts included in our scope 
underwent a thorough rightsizing review when planning their NEC, our 
analysis of staffing data at these posts suggests that accurately 
projecting future staffing needs can still be difficult. We found that 
current staffing levels exceed as-built desk space by at least 20 
percent at four of the six posts that underwent a rightsizing review, 
all of which were completed in 2008 or later. 

OBO, M/PRI, and regional bureau officials agreed that the NEC planning 
process should include a greater degree of flexibility to account for 
unanticipated changes. OBO officials indicated it may be more 
advantageous to plan buildings based on flexible bands that correspond 
to a post's general size--for example, posts with a need of 200 to 250 
desks might constitute one band--rather than focusing on a specific 
desk count. Officials noted construction costs tend to come in bands 
and such an approach could incorporate more flexibility than is 
allowed in the current process. M/PRI officials also said that placing 
less focus on a specific desk count in planning NECs could be 
beneficial, as it would allow them to focus more resources on 
assessing the potential for policy changes that could impact future 
staffing levels. 

Analytical Basis for Growth Factor Unclear: 

While State revised the growth factor for NECs in 2008, officials did 
not provide the analytical basis for determining how much growth space 
is appropriate. OBO officials stated that, while the growth factor was 
originally intended to provide space for future growth, even a 10 
percent growth factor can be exhausted very quickly at many posts, 
essentially providing some posts with no available growth space from 
the moment they occupy the NEC. As our earlier analysis showed, nearly 
half of all NEC posts have current staffing levels that exceed as-
built space by more than 10 percent, while some posts have staffing 
levels lower than the initial projections. However, while the amount 
of growth space provided is sometimes reduced based on budget or other 
considerations, officials noted that State essentially applies a 
uniform growth factor across all posts and does not adjust the growth 
factor based on post-specific characteristics, such as a post's 
geographic location or the presence of rapidly growing agencies or 
functions, that might help forecast growth not explicitly planned for 
in the staffing projections. State officials did not indicate they 
have conducted any analysis of characteristics associated with rapid 
growth at completed NECs, but officials from M/PRI acknowledged that 
examining such characteristics could improve the process for sizing 
NECs. OBO officials report they have considered changing the standard 
growth factor based on certain post characteristics, such as adding 5 
percent additional growth space at posts in which USAID has a 
presence. While we could not identify clear industry or government 
standards regarding how much growth space is appropriate, one agency--
the National Institutes of Health--recommends that in determining how 
much flexibility should be incorporated into a building, one should 
consider the cost of incorporating flexibility now compared with the 
cost of renovating space in the future, among other factors. However, 
according to State officials, State has no current plans to make any 
changes to the NEC growth factor. 

State Implemented a Lessons Learned Program to Improve Future NEC 
Design: 

In 2004, State implemented a formal lessons learned program that seeks 
to improve the design of future NECs. According to OBO officials, the 
program entails bringing together representatives from a variety of 
technical disciplines within OBO to systematically evaluate issues 
identified in completed NECs and, if appropriate, take action to 
modify NEC design criteria to avoid similar problems in future 
facilities. OBO identifies topics to evaluate through the lessons 
learned program through a variety of sources, including post-occupancy 
evaluations, contractor roundtables, and facilities management 
industry best practices. Through the lessons learned program, State 
identified many of the functionality issues at the posts we reviewed 
and has taken action to change the design criteria for a number of 
functional areas of future NECs. According to State officials, for 
fiscal years 2005 through 2008, OBO implemented changes to design 
criteria for over half of the issues identified through the lessons 
learned program. OBO officials noted that, on average, the program 
reviews about 500 issues of varying size and complexity per year. 
Table 3 lists certain recent modifications that have been made through 
the lessons learned program to address functionality challenges. 

Table 3: State's Recent Modifications to Address Functionality 
Challenges: 

Features cited as not fully functional: Warehouses and maintenance 
shops; 
Selected actions taken: Developed an assessment tool to improve 
planning of warehouses and maintenance shops; 
Fiscal year implemented: Currently in pilot phase. 

Features cited as not fully functional: Cafeterias; 
Selected actions taken: Incorporated a food service study into the 
planning phase to more accurately predict cafeteria needs; 
Fiscal year implemented: 2010. 

Features cited as not fully functional: Consular areas; 
Selected actions taken: Redesigning consular teller windows to address 
ergonomics and waiting area acoustics and improve microphone systems; 
Fiscal year implemented: Currently in pilot phase. 

Features cited as not fully functional: Atriums; 
Selected actions taken: Converted from a 3-to 4-story atrium to a 2-
story gallery to make it easier to maintain and less costly to heat 
and cool; 
Fiscal year implemented: 2006. 

Source: GAO analysis of State information. 

[End of table] 

Post-Occupancy Evaluations Provide a Useful Tool for the Lessons 
Learned Program, but State Has Not Ensured Timely Completion of 
Evaluations: 

Evaluations of completed NECs are one mechanism for obtaining 
information for the lessons learned program. State has undertaken post-
occupancy evaluations on some completed NECs to assess what aspects of 
the building worked well and what aspects need improvement. State 
officials reported post-occupancy evaluations are a very important 
tool for identifying issues and noted that some of the design changes 
they have initiated were based on issues identified through post-
occupancy evaluations. In conducting a post-occupancy evaluation on 
the NEC in Yerevan, Armenia, for example, State reported it identified 
a number of issues with the maintenance shops, which led to a 
recommendation to examine how State could improve maintenance shops in 
future NECs. In addition to post-occupancy evaluations, in 2008, OBO 
initiated a "look back" study to identify issues and problems for 
review through its lessons learned process with regard to the 
planning, design, construction, and maintenance of 55 NECs and office 
annexes completed from 2001 to 2007. For example, OBO officials report 
that the look back study found posts have had issues with consular 
windows, such as poor acoustics impacting the privacy afforded to visa 
applicants. While the look back study was an important tool for 
identifying issues in completed NECs, the study had some limitations. 
For example, according to an OBO official, it was completed in a very 
short time frame and the level of detail in its findings was 
inconsistent across posts. 

While State's efforts to implement the lessons learned program have 
resulted in improvements, State has not ensured that reviews of 
completed NECs are undertaken in a timely manner. Due to the time 
required to contract and construct NECs, it can take 4 years for an 
approved lessons learned recommendation to materialize as an 
improvement in future NECs. Therefore, according to State officials, 
timely identification of issues through OBO reviews, such as post- 
occupancy evaluations, is critical to ensure that problems are not 
repeated in future designs.[Footnote 24] We found that OBO has 
completed a post-occupancy evaluation for 10 of the 44 NECs completed 
since 2001 and has not completed any post-occupancy evaluations since 
2008. OBO officials reported that OBO intended to complete 17 post- 
occupancy evaluations of NECs in 2009, but did not complete any 
because staff were diverted to other priorities. OBO officials also 
report they plan to complete 9 post-occupancy evaluations of NECs in 
2010; however, as of May, 2010--almost halfway through the year--no 
evaluations have been completed. 

NECs Are Challenging to Operate and Maintain; State Has Taken Steps to 
Address These Challenges, but Problems Remain: 

State has constructed NECs that are state-of-the-art buildings, built 
in accordance with current building codes, security, and energy- 
efficiency standards. The comparatively larger size of NECs, relative 
to the facilities they replaced, and complexity of NEC building 
systems have resulted in increases to operations and maintenance 
costs. State has developed a plan that identifies future maintenance 
requirements to protect the investments made in NECs but the plan does 
not report on the increased operating costs, and likely future costs, 
to operate NECs. NECs have also presented challenges for some posts 
due to rushed testing of building systems--recognized in the industry 
as "commissioning"[Footnote 25]--or poorly coordinated transfer of the 
NEC from OBO to the post, which has contributed to operational issues 
affecting building cooling and fire protection systems. More than half 
of the 22 NECs we reviewed also have experienced problems operating 
building systems, which have resulted in the need for earlier-than- 
anticipated repair and replacement projects. State has made 
organizational changes, revised its commissioning process, and changed 
design criteria to avoid problems with future NECs. However, State has 
not developed a plan to recommission or retest completed NECs to 
ensure building systems are operating as efficiently as possible and 
that outstanding and potential problems with NEC building systems, 
such as the increased risk of failure of NEC cooling systems, are 
being fully addressed. In addition, State has had problems in hiring 
U.S. facility managers and hiring and training locally employed 
maintenance staff that have the necessary technical skills to operate 
and maintain an NEC's complex systems. 

State Is Making Progress in Constructing Facilities That Meet Building 
Codes and Security Standards and Support Federal Energy Reduction 
Goals: 

State constructs NECs in accordance with modern building codes, State 
security standards, and federal energy-efficiency goals. The new 
facilities are modern, state-of-the-art buildings that incorporate 
technologically sophisticated building systems and are more secure 
than the old embassies and consulates that would not meet current 
codes and standards. (Figure 11 shows examples of the equipment that 
support the sophisticated NEC building systems.) 

Figure 11: Typical NEC Building Systems: 

[Refer to PDF for image: 4 photographs] 

Source: GAO. 

Note: Power generation system (upper left); cooling system (upper 
right); fire suppression system (lower left); water treatment system 
(lower right). 

[End of figure] 

NECs are modern, state-of-the-art facilities designed and built in 
accordance with the International Building Code, which guides design 
of the facilities' structural components, fire and life safety 
features, and seismic engineering provisions, among other elements. 
For example, NECs have modern fire protection systems that require 
fire pumps to protect multiple buildings on a typical 10-acre 
compound. In addition, NECs are safer than older embassies because the 
designs for NECs consider the seismic conditions in local areas to 
enable the NECs to be constructed to withstand seismic events. The NEC 
in Port-au-Prince, Haiti, for example, was one of the few facilities 
to withstand the January 2010 earthquake in the country and was used 
in support of recovery operations. Meeting modern code requirements by 
including fire pumps and designing structural systems to withstand 
seismic events contribute to NECs being larger than the facilities 
they replaced. Additionally, NECs provide common areas (e.g., 
cafeterias, atriums, and recreational facilities) that also contribute 
to the larger size of NECs. 

NECs are constructed to meet security standards and, as a result, are 
more secure than the facilities they replace because the buildings' 
exteriors are hardened to provide blast protection, and windows and 
doors also are designed to meet forced-entry and ballistic-resistance 
standards. In addition, NECs' heating, ventilation, and air 
conditioning systems are equipped with larger, technologically 
sophisticated systems to filter potentially harmful airborne 
contaminants and effectively create an air-tight environment within 
the buildings. NECs also have redundant systems such as generators 
that operate in the event of local power loss and provide storage for 
water and fuel so that posts are capable of maintaining operations. 
Some NECs receive services from local utility systems while others 
must independently produce their own utility services. The NEC in Port-
au-Prince, Haiti, for example, operates its own utility systems that 
enable it to generate electricity, produce potable water on-site, and 
treat waste water. Constructing NECs to meet current security 
standards, such as hardening structures and having built-in system 
redundancies, contributes to NECs being more secure and larger than 
the old facilities. 

To meet federal energy mandates to reduce energy and water 
consumption, NECs contain technologically sophisticated building 
automation and energy management systems that control and monitor 
heating, cooling, ventilation, lighting, and power systems.[Footnote 
26] In addition, starting in 2008, State's goal is to design all new 
NECs to meet the U.S Green Building Council's Leadership in Energy and 
Environmental Design (LEED) certification requirements related to 
promoting energy efficiency and minimizing environmental impacts. 
[Footnote 27] To date, State has constructed LEED-certified NECs in 
Sofia, Bulgaria (see figure 12); Panama City, Panama; Brazzaville, 
Republic of Congo; and Johannesburg, South Africa. State officials 
report that the department has approximately 30 projects registered 
with the LEED program and they expect many of the projects will 
receive LEED certification over the next few years.[Footnote 28] 

Figure 12: Sofia, Bulgaria, the first LEED-Certified U.S. Embassy: 

[Refer to PDF for image: photograph] 

Source: GAO. 

[End of figure] 

Larger, More Technologically Complicated New Facilities Cost More to 
Operate and Maintain than Those They Replaced: 

The comparatively larger size of NECs and the complexity of their 
building systems have resulted in higher operations and maintenance 
costs than at the facilities they replaced. Costs of utilities, 
maintenance staff, and service contracts are contributing to the cost 
increases. In our review of 10 recently completed posts,[Footnote 29] 
we found that total post-managed operations and maintenance costs were 
about $12 million greater than at the facilities they replaced. 
[Footnote 30] Utility costs (e.g., electricity, gas, fuel oil, water, 
and sewer) increased on average $827,000--or about 250 percent--per 
post. Each of the 10 posts experienced at least a 75 percent increase 
in utility costs after moving into an NEC. Our analysis is consistent 
with a State 2009 benchmarking study of approximately 165 overseas 
posts that shows a trend of increasing operations and maintenance 
costs. In addition, State's report shows that four of the five posts 
with the highest utility costs (calculated on a gross square meter 
basis) were NECs.[Footnote 31] Table 4, for NECs completed in 2007 and 
2008, shows the pre-NEC utility costs approximately 1 year prior to 
the move into the NEC compared to posts' fiscal year 2009 utility 
costs. 

Table 4: NEC Utility Costs Pre-and Post-Move for NECs Completed in 
2007 and 2008 (costs rounded to the nearest thousand): 

NECs completed in 2007 and 2008: Accra, Ghana; 
Pre-NEC utility cost: $77,000; 
Post-NEC utility cost (FY 2009)[A]: $923,000; 
Percentage increase: 1,099%. 

NECs completed in 2007 and 2008: Kigali, Rwanda; 
Pre-NEC utility cost: $178,000; 
Post-NEC utility cost (FY 2009)[A]: $1,624,000; 
Percentage increase: 812%. 

NECs completed in 2007 and 2008: Beijing, China; 
Pre-NEC utility cost: $486,000; 
Post-NEC utility cost (FY 2009)[A]: $2,704,000[B]; 
Percentage increase: 456%. 

NECs completed in 2007 and 2008: Berlin, Germany; 
Pre-NEC utility cost: $324,000; 
Post-NEC utility cost (FY 2009)[A]: $1,373,000[C]; 
Percentage increase: 324%. 

NECs completed in 2007 and 2008: Algiers, Algeria; 
Pre-NEC utility cost: $96,000; 
Post-NEC utility cost (FY 2009)[A]: $375,000; 
Percentage increase: 291%. 

NECs completed in 2007 and 2008: Panama City, Panama; 
Pre-NEC utility cost: $620,000; 
Post-NEC utility cost (FY 2009)[A]: $1,489,000; 
Percentage increase: 140%. 

NECs completed in 2007 and 2008: Port-au-Prince, Haiti; 
Pre-NEC utility cost: $368,000; 
Post-NEC utility cost (FY 2009)[A]: $821,000; 
Percentage increase: 123%. 

NECs completed in 2007 and 2008: Managua, Nicaragua; 
Pre-NEC utility cost: $619,000; 
Post-NEC utility cost (FY 2009)[A]: $1,338,000; 
Percentage increase: 116%. 

NECs completed in 2007 and 2008: Kathmandu, Nepal; 
Pre-NEC utility cost: $234,000; 
Post-NEC utility cost (FY 2009)[A]: $425,000; 
Percentage increase: 82%. 

NECs completed in 2007 and 2008: Rangoon, Burma; 
Pre-NEC utility cost: $263,000; 
Post-NEC utility cost (FY 2009)[A]: $464,000; 
Percentage increase: 76%. 

NECs completed in 2007 and 2008: Total; 
Pre-NEC utility cost: $3,265,000; 
Post-NEC utility cost (FY 2009)[A]: $11,536,000; 
Percentage increase: 253%. 

Source: GAO analysis of costs, as reported by posts. 

[A] Posts were asked to report utility costs separate from lease costs 
for old facilities that were vacated as a result of consolidating onto 
a new compound. Posts may or may not have included utilities costs for 
leased facilities. 

[B] Beijing provided actual cost data for 11 months of operation in 
2009. 

[C] Berlin provided cost data based on extrapolating actual cost data 
for 10 months. 

[End of table] 

State officials noted that while building systems in NECs are more 
energy efficient compared to systems in buildings that were replaced, 
operating conditions cause them to consume a greater amount of energy 
due to, for example, additional security equipment such as security 
gates, lighting, cameras, and vehicle barriers that all require power. 
Further, NECs are physically larger than replaced facilities, meaning 
that costs to heat and cool the NECs will be greater. In addition, the 
air filtration equipment needed to maintain the sealed environment in 
NECs is about 50 percent larger in size and costs about 40 percent 
more to operate than if the filtration systems were not installed. 

Maintenance Staff Costs Are Increasing at NECs: 

The costs for maintenance staff increased by approximately $200,000 on 
average at the 10 posts for which we analyzed cost data because of the 
need to hire additional facilities staff to operate and maintain the 
NECs. For example, officials in Kigali, Rwanda, reported the size of 
its facilities staff prior to occupying the NEC was 20. Kigali now has 
50 facilities maintenance staff as a result of the larger chancery and 
increased staff housing. Fourteen of those staff are dedicated solely 
to the NEC operations and maintenance. The additional annual cost for 
those 14 positions solely dedicated to NEC maintenance in Kigali was 
approximately $236,000. 

Service Contracts Are Needed to Support Some NEC Maintenance: 

For fiscal year 2011, to ensure proper maintenance of systems and 
equipment at NECs, OBO estimates that posts would spend approximately 
$150,000, on average, to fund maintenance service contracts. Posts use 
service contracts to obtain technicians to maintain some systems, like 
elevators and building automation systems, that may not have existed 
at the older facilities. Some posts also use service contracts to 
obtain maintenance service from regional sources when they are unable 
to find skilled labor to hire locally. Because some posts' maintenance 
personnel may not be capable of fully addressing all maintenance 
requirements of an NEC's technically sophisticated systems, use of 
maintenance service contracts enables posts to obtain contractors that 
can perform specialized maintenance, such as conducting infrared 
testing on equipment temperatures. 

State Has Developed Its First Long-Range Overseas Maintenance Plan, 
but Plans Are Incomplete: 

State's Strategy to Maintain NECs Includes Revisions to Processes for 
Funding Routine Maintenance and Service: 

In fiscal year 2010, partly in response to our 2006 recommendation, 
OBO developed its first Long-Range Overseas Maintenance Plan (LROMP) 
to support State in budgeting for what OBO reports in the plan as an 
"investment protection" strategy for the multibillion dollar 
investment made in constructing NECs. The LROMP outlines facility 
maintenance needs--characterized as "non-capital projects"--over a 6-
year planning horizon for NECs as well as older facilities at posts 
not scheduled to move into an NEC.[Footnote 32] State intends to 
update the plan annually as a companion document to the Long-Range 
Overseas Buildings Plan which outlines State's capital construction 
plan for building new embassies over the same period. The plan is 
intended to inform State's budget requests beginning with the fiscal 
year 2011 budget request. The plan currently identifies over 3,300 
potential projects for the period from fiscal year 2010 through fiscal 
year 2015. Overall, the plan presents what State characterizes as "the 
universe of requirements" (i.e., based on approximately 5,200 
facilities located in over 260 locations) identified in fiscal year 
2010, which total just over $3.7 billion. State has also identified a 
number of areas where the LROMP needs to be improved in next year's 
edition, such as ensuring that posts have accurately identified all 
their maintenance requirements, better defining costs for major 
rehabilitation projects (e.g., costs to move staff into temporary 
space during a project), and better automating the process for 
escalating or reducing project costs as proposed projects move between 
fiscal years. 

In addition to identifying future maintenance projects, State has 
taken action to improve its processes for establishing budgets targets 
for (1) determining and allocating funding for posts' routine 
maintenance and repair and (2) setting funding targets for posts' 
maintenance service contracts. The LROMP reports that starting with 
its fiscal year 2011 budget request, State changed its approach for 
setting posts' annual routine maintenance and repair budgets that fund 
maintenance activities that are considered routine, recurring, and 
minor, and that are managed by posts, such as painting and weather 
stripping. Historically, routine maintenance and repair funds were 
allocated to posts by simply escalating prior year funding levels 
without consideration for factors such as the age of posts' 
facilities. Under a new approach, a more objective determination of 
posts' budget levels is made based upon factors such as the age and 
current condition of posts' facilities, the amount of space needed to 
be maintained, and an index for geographic costs considerations, such 
as the costs to procure or ship maintenance materials in the region. 
Under this new approach, State identified a requirement of $98 million 
for fiscal 2011 to support routine maintenance and repair at overseas 
posts, more than double the amount of State's 2009 budget of $44.5 
million for routine maintenance and repair. The LROMP also reports 
that, starting in fiscal year 2009, State took action to establish a 
new cost category for Building Maintenance Expenses (BME)[Footnote 33] 
in order to improve how it budgets, funds, and captures costs for 
preventative maintenance service contracts (e.g., service contracts 
for elevators, generators, fire protection systems, and building 
automation systems) at overseas posts. The new process places the 
responsibility for setting State's budget targets for maintenance 
service contracts with OBO as opposed to posts and other agencies; 
other agencies at posts are still required to fund their share of the 
maintenance service contracts. State made the decision to fund its 
agency's share of the maintenance service contracts out of existing 
OBO funding in order to protect the investment made in NECs. According 
to a senior State official, development of the LROMP, as well as the 
shifting of responsibilities to OBO for setting funding targets for 
State's share of posts' maintenance service contracts, should be seen 
as moving State toward clarifying at least the maintenance 
requirements for overseas posts. 

State's Plan Does Not Provide Planning Time Frames to Implement 
Projects: 

While the LROMP has begun to outline maintenance requirements, and 
does prioritize projects, our analysis of the plan found it does not 
provide an indication as to when projects would be executed over the 6-
year period and the likely implications of delaying projects due to 
lower-than-anticipated budgets. Rather, the plan outlines the 
"universe of requirements" of 3,300 potential projects at a cost of 
nearly $3.7 billion over a 6-year period. A senior State official 
acknowledged the plan does not indicate in what specific fiscal years 
projects are planned to be implemented.[Footnote 34] He noted that 
undertaking the first edition of the LROMP was itself a major 
undertaking and getting posts to identify maintenance requirements was 
challenging. Without some detail on the planned time frames to 
implement some of the maintenance projects, for at least the current 
fiscal year and pending budget year, the usefulness of the plan in 
supporting State's budget requests is diminished. 

State's Plan Does Not Address Increasing Costs to Operate NECs: 

While the LROMP is a step toward providing insight into the 
maintenance resources needed to protect the investment in NECs, we 
found it does not provide insight into operating costs, such as the 
costs for utilities.[Footnote 35] In 2007, OBO took action to create a 
utility database to capture some of posts' annual operating costs as 
well as posts' energy and water consumption data; however, our review 
of database reports shows that many posts have reported incomplete or 
missing data for recent years, including data for some of the NECs we 
reviewed. OBO prepared a 2009 benchmarking study that may enable State 
to focus on reducing operating expenses at posts with high costs. 
[Footnote 36] However, according to OBO, except for providing posts 
with first-year operating cost estimates for individual NECs, planning 
for operations is not an area that OBO officials feel they can address 
directly, as it is outside OBO's program area of responsibility. 
[Footnote 37] State and other agencies at overseas posts are 
responsible for funding operations through the International 
Cooperative Administrative Support Services (ICASS) process,[Footnote 
38] while OBO is responsible for funding maintenance. Following 
State's briefing of the LROMP to its Industry Advisory Panel, one of 
the panel members representing a leading international facilities 
management organization commented that he felt that State's plan was 
missing the "operations piece." He reported that his organization 
found that building owners must plan for both operations and 
maintenance and remarked that, while the LROMP does outline future 
maintenance budget needs, it does not provide insight into future 
operations costs. 

Problems in Commissioning and Transferring the Early NECs from OBO to 
Post Posed Potential Safety Risks and Hindered Efficient Operations: 

NECs have presented operations and maintenance challenges for posts 
due to problems, in part, related to the inspection, testing, and 
documentation of building systems--recognized in the construction 
industry and by the federal government as "commissioning." In 13 of 
the 22 posts we reviewed, we found problems that were linked, in part, 
to commissioning. State's Inspector General identified significant 
problems with the commissioning process in its 2008 report on OBO's 
operations, citing it as the most maligned issue raised by posts with 
NECs.[Footnote 39] Officials at NECs report they have had to contend 
with operational issues, including some systems not functioning 
properly due to commissioning-related issues. Officials' concerns 
regarding commissioning relate to operational issues they have 
experienced with critical systems, such as NEC cooling, building 
automation, and fire protection systems. Prior to September 2008, the 
commissioning agents did not work for State directly, but rather were 
hired by the construction contractors. Furthermore, we found there 
were problems when NECs were transferred from OBO to post, such as the 
facility managers not receiving accurate drawings of the NEC to 
support maintenance. 

Commissioning of Critical NEC Building Systems Has Been Challenging: 

At more than half the posts we reviewed, we found problems related, in 
part, to the commissioning of heating, ventilation, and cooling 
systems and the building automation systems controlling those systems. 
For example, in Berlin, Germany, the facility manager told us that, 
nearly a year after taking occupancy, the embassy's building 
automation system has had ongoing operational problems, resulting in 
it not being able to fully control NEC mechanical systems. He believes 
these problems should have been identified during commissioning. He 
further noted that OBO is providing funding for a contractor to 
continue to work on the programming of the building automation system. 
In Sofia, Bulgaria, one official noted the building automation system 
as commissioned and transferred by OBO was not programmed to provide 
for the most efficient operation of heating and cooling systems and 
that it took time for maintenance staff to learn how to adjust the 
system and achieve energy savings by optimizing the system. Similarly, 
in Yaoundé, Cameroon, officials reported that the building automation 
system was only recently programmed--nearly 4 years after the NEC was 
completed--to run the NEC's cooling system at a reduced level during 
periods of low occupancy such as during nights and on weekends. Post 
officials reported this change allowed them to save $4,000 per month 
($48,000 per year) in utility costs. In addition, the embassy in 
Kathmandu, Nepal, reported that systems were not commissioned for 
efficient operation and that maintenance staff had to undertake their 
own efforts to optimize operations of the new chancery's building 
automation, cooling, and power generator systems, resulting in reduced 
energy consumption and savings of approximately $58,000 in electrical 
energy costs and $84,000 in diesel fuel costs between approximately 
November 2008 and May 2009. 

Prior to 2009, commissioning responsibilities for fire protection 
systems resided with OBO's Office of Design and Engineering, rather 
than OBO's Office of Fire Protection, which is largely responsible for 
inspections of existing fire protection systems, supporting posts in 
maintaining those systems, and investigating fires. While OBO's Office 
of Design and Engineering had fire protection engineers verifying 
compliance with contract documents in an effort to ensure fire systems 
were commissioned before NECs were occupied, OBO officials reported 
those staff engineers did not have the direct authority to prevent 
occupancy of NECs. Also, while commissioning of fire protection 
systems may have been conducted before post personnel moved into the 
NECs, post officials reported many problems with those systems shortly 
after commissioning, including false alarms, problems with fire alarm 
panels, and some fire devices (e.g., smoke detectors) not being 
connected. In its written responses to our questions, OBO's Office of 
Fire Protection reported that some early NECs were occupied without 
the correction of critical deficiencies. 

In its review of OBO and its survey of overseas NECs, the State IG 
also reported there were numerous comments about NEC fire systems not 
being fully ready at occupancy.[Footnote 40] Embassy officials in 
Panama City, Panama, reported to us that when post personnel moved 
into the NEC, the fire alarm system in the warehouse was not hooked 
up, some smoke detectors were not installed, and the fire alarm panels 
were problematic. They believe that schedule pressures led to 
occupying the NEC before issues were fully resolved. Officials at 3 
NECs we reviewed told us that OBO's fire engineers, or its 
contractors, had visited their post to help fix problems that occurred 
after moving into the NECs. 

State's Commissioning Approach Lacked Independence: 

State reported that until 2008 the testing and commissioning of NECs 
was largely an activity controlled by OBO's project director and the 
construction contractor who employed the commissioning agent, rather 
than a third-party independent entity working for State. Department of 
Energy (DOE) federal facilities commissioning guidance states that the 
use of independent third-party commissioning agents is the most common 
option used by federal agencies for conducting commissioning.[Footnote 
41] The guidance also states that for large projects with highly 
sophisticated systems, the savings to the government by employing an 
independent agent typically outweigh the government's cost to obtain 
those commissioning services. DOE further reports that using an 
independent commissioning agent provides an independent judge, with a 
minimum possible conflict of interest, and avoids instances when 
contractors perform commissioning activities on their projects and 
evaluate their own work. Some State officials further stated that the 
completion of the commissioning tests may have been subject to 
pressures driven by OBO officials wanting to complete projects on 
schedule and that in some cases commissioning was not completed before 
staff moved into the NECs. OBO officials reported that starting in 
2008, State generally extended the duration of NEC project schedules 
by 4 to 5 months, in part, to allow more time for commissioning and 
transfer activities at the end of projects.[Footnote 42] 

Some posts questioned the independence of commissioning agents that 
were working for the construction contractor.[Footnote 43] Officials 
at the NEC in Managua, Nicaragua, believe that OBO's former 
commissioning process resulted in many problems that post officials 
have had to resolve. For example, they said post had to hire a 
contractor to fix problems with air pressurization controlled by the 
building's air handling and ventilation system, which they said is due 
to the incorrect set up of the building automation system. They 
believe there would have been fewer problems after moving into the 
building had OBO used an independent commissioning agent. In addition, 
in response to our written questions on what could have been done 
differently to eliminate operations and maintenance problems that 
occurred, embassy officials in Belmopan, Belize, indicated that OBO 
should have hired an independent commissioning agent, which they 
believe would have resulted in OBO identifying many of the problems 
that post staff identified on their own after occupying the NEC. 

Several Posts Reported the Transfer of an NEC from OBO to the Post 
Resulted in a Lack of Information: 

In addition to commissioning issues, we found that at 11 of 22 NECs, 
transferring[Footnote 44] of completed facilities from OBO's on-site 
project director, who managed the construction of the NEC, to posts 
and their facility managers was not always well coordinated or without 
problems, resulting in some information--such as preventative 
maintenance plans, operations and maintenance manuals for building 
systems, and as-built drawings--either not being turned over to the 
maintenance staff or being incomplete. In addition, officials at many 
posts reported that the training for NEC maintenance staff to support 
effective operations and maintenance activities is inadequate. OBO 
officials acknowledged there has been a wide variance in the 
completeness and accuracy of construction contractors' turnover 
documents. In particular, we found: 

* 6 of 22 posts had not received preventive maintenance plans; 

* 8 of 22 posts did not receive as-built drawings that accurately 
reflect details of the final construction; and: 

* 16 of 22 posts thought that the basic familiarization training on 
new building systems provided by construction contractors to local 
facilities staff, by itself, is insufficient to fully train staff. 

Among the problems reported by post officials were cases when 
maintenance plans were not fully loaded into the NEC's computerized 
maintenance management system.[Footnote 45] As a result of not having 
complete information about system components (e.g., equipment make and 
model, required maintenance, and location in the facility), facilities 
staff at three posts we visited reported staff had to populate the 
incomplete maintenance databases, an effort that required posts' 
maintenance staff to populate the databases themselves with 
information such as the location of equipment, the manufacturer, and 
the required preventative maintenance that needed to be undertaken on 
the systems. In Belmopan, Belize, for example, post officials said 
that wiring diagrams for the building automation system showing the 
connections between it and the NEC building systems it controlled were 
not provided with the as-built drawings. As a result, the facilities 
staff must use a trial-and-error approach to determine how the system 
is configured, which makes it difficult for them to respond in 
emergency situations. 

State Revised Its Commissioning and Transfer Processes for Future 
NECs, but Issues with Completed NECs Remain: 

State Strengthened Its Processes for Commissioning and Transferring 
NECs and Made Organizational Improvements: 

OBO has recognized and taken action to address posts' concerns 
regarding issues related to past commissioning and turnover of the 
early NECs. Senior OBO officials emphasize that while they believe 
that on-site project directors fully enforced contract requirements 
related to commissioning, there may have been some instances when 
commissioning by the construction contractor was rushed. In 2008, OBO 
changed its process for commissioning NECs; OBO now contracts with 
independent commissioning agents to oversee the commissioning process 
on behalf of the government and provide a more independent assessment 
of the testing of building systems than State had in the past. In 
2009, in briefing its Industry Advisory Panel, OBO's Director reported 
there was a disconnect between OBO's on-site project directors, who 
oversaw construction, and posts' facility managers with regard to 
expectations on system performance and turnover documentation that 
resulted in instances of each blaming the other for building systems' 
problems. In recognition of the organizational disconnect between 
those constructing the NECs and those maintaining them, the OBO 
Director combined OBO's Office of Construction Management and its 
Office of Facility Management under a single managing director to 
improve communication, coordination, and efficiency related to both 
commissioning and turnover of completed projects from OBO's 
construction project directors to posts and their facility managers. 
In addition, given issues with commissioning and maintenance of fire 
protection systems, OBO's Director removed the fire engineers from 
OBO's Office of Design and Engineering and assigned them to OBO's 
Office of Fire Protection. In written comments to us, OBO officials 
reported those staff engineers did not have the direct authority to 
prevent occupancy of NECs. According to the director of the Office of 
Fire Protection, starting in January 2009, that office now has full 
authority for overseeing commissioning tests of the fire protection 
systems in NECs and provides the final approval authority on 
acceptance of those systems prior to issuance of a certificate of 
occupancy that allows post to move into the NEC. Furthermore, that 
office is organized so that staff conducting and overseeing 
commissioning reviews and testing are fully independent of the fire 
protection engineers who conduct the design and construction reviews 
of the fire protection systems to support the on-site construction 
project director. This is to ensure OBO's fire commissioning officials 
are not pressured by project director concerns related to completion 
schedules and that they have an independent perspective on the project. 

OBO has also made changes to the process it uses to transfer a 
completed NEC to post. For example, in 2009 it established an NEC 
Transition Program and a new Transition Division, with the intent to 
assign an on-site Operations and Maintenance Transition Coordinator--6 
months before, and 6 months after an NEC opens--to assist posts, the 
project director, and the incoming facility manager during the 
turnover to ensure, among other things, that maintenance staff receive 
required maintenance manuals, maintenance plans, and as-built 
drawings. The individual will also serve as coordinator with OBO 
headquarters to assist post management and the facility manager in 
resolving contractor punch lists and warranty issues that may still be 
at issue after a post has moved into the NEC and OBO's project 
director has departed.[Footnote 46] 

In 2009, OBO also updated its standard operating procedures governing 
the responsibilities of all parties involved in the transfer of NECs 
from the project director to the post facility manager and provided 
additional guidance to smooth the transition process of NECs. OBO 
officials also reported they now conduct a warranty inspection site 
visit approximately 8 to 11 months after construction to ensure all 
warranty-related issues have been addressed before the contractor's 1- 
year warranty period expires. OBO officials report that NECs that are 
completed in fiscal year 2010 would be the first set of projects where 
the changes made to the commissioning process should be evident and 
result in fewer issues after posts move into the NECs. 

Changes to the Commissioning and Transfer Processes Do Not Address 
Completed NECs: 

While OBO has taken action to change its commissioning process, the 
changes do not address problems that resulted at NECs completed under 
the old process. We note that DOE's commissioning guide for federal 
agencies states that federal facilities should be recommissioned every 
3 to 5 years and that the costs associated with commissioning the 
systems again--effectively a tune-up of the building--will typically 
be recaptured in about 2 years as the tune-up results in energy cost 
savings. More than a third of completed NECs are now nearly 5 years 
old, but OBO has not undertaken any complete recommissioning of NECs 
despite the many reported issues with some NECs' building cooling, 
fire protection, and other systems. While OBO has undertaken some 
limited recommissioning on individual systems--such as systems in 
Beijing, China; Conakry, Guinea; and Phnom Penh, Cambodia--one 
official noted that the problems with one system sometimes have 
linkages to others. Industry commissioning experts cite that, while 
some building owners (e.g., the federal government) do undertake 
limited commissioning on existing building systems, focusing on a 
single system does not typically result in a facility that operates 
optimally overall; an integrated approach maximizes positive results 
to ensure the building is operating efficiently and safely.[Footnote 
47] For example, the building cooling system may be affected by 
electrical power conditioning problems. One OBO management official 
indicated that he would like State's goal to be to recommission NECs 
every 5 years but further noted there is no established budget for 
recommissioning. In our review of State's Long-Range Overseas 
Maintenance Plan, we found the plan did not include any proposed 
prioritization, schedule, or costs for recommissioning completed NECs. 
OBO officials affirmed they are not performing recommissioning on a 5-
year basis and do not have a formal plan to recommission NECs. 
[Footnote 48] 

Several NECs Had Problems with Building Systems, Including Failures 
That Disrupted NEC Operations: 

More than half of the 22 NECs we reviewed have experienced problems 
with operating critical building systems, which have resulted in the 
need for projects to repair or replace some systems. The problems 
involved three building systems, including NEC cooling systems, fire 
alarm systems, and security doors and windows, and were common across 
many of the NECs we reviewed. In particular, we found that: 

* 14 of 22 NECs had problems with their cooling systems--specifically 
the chillers[Footnote 49]--not performing as intended, including 
failing completely; 

* 16 of 22 NECs had false alarms or other recurring problems with the 
fire alarm systems; and: 

* 16 of 22 NECs had problems with their forced-entry and ballistic- 
resistant security doors or windows. 

These problems, some that should have been caught during 
commissioning, have caused varying levels of disruption to post 
operations, ranging from nuisances caused by false fire alarms to 
substantial disturbance resulting from chiller failures that have 
caused flooding with damage to property and equipment. 

Posts Have Had Numerous Problems with NEC Building Cooling Systems: 

According to a 2007 OBO study, NECs have experienced numerous failures 
with the buildings' cooling systems that are due to problems with the 
air conditioning chiller units. The report shows that over 100 
chillers, installed since 2001, have either failed or experienced 
serious operating problems. OBO identified 22 completed NECs that have 
experienced problems that affected the proper operation of the units, 
including chiller failures. At the NEC in Panama City, Panama, for 
example, post officials noted that one of the chillers failed on 
several occasions, resulting in critical spaces being flooded with 
water used within the cooling system and causing damage to equipment. 
One post official further noted that to adequately address the 
problem, major portions of the cooling system had to be redesigned and 
that OBO is planning to replace the system in 2010. In 2009, OBO 
funded emergency repairs of two chillers that failed in Conakry, 
Guinea, at a reported cost of $250,000. In 2008, State's IG reported 
that in Abuja, Nigeria, chillers did not work properly for at least 2 
years after the post opened. One OBO official reported that a new 
chiller is planned to be installed in Abuja sometime in 2010. 

OBO officials identified that most chiller problems are associated 
with a single manufacturer's units and characterized some problems as 
"latent defects," meaning that the problems were not detectable at the 
time of inspection and acceptance. Circuit board burn outs, 
refrigerant loss or leakage, defective refrigerant valves, and 
compressor failures have led to failures of the chillers. OBO reports 
that the manufacturer has addressed some of the problems with the 
chillers during the one year warranty period. However, our review of 
OBO reports found that some chillers have been replaced prior to the 
units' expected useful life, which is estimated to be at least 25 
years. Our review found that OBO has already identified a need to 
replace chillers in Yaoundé, Cameroon (completed in 2005), and 
Kathmandu, Nepal (completed in 2007). In interviews with OBO, the 
chief of the mechanical engineering branch reported that OBO is 
starting to develop a program to replace chillers where critical 
problems exist; however, OBO does not yet have a clear idea of which 
posts will definitively need their chillers replaced. OBO's 2007 study 
estimated the cost to replace a single post's chillers to range from 
$500,000 to over $1 million. 

Our review of OBO's study on chillers found OBO's mechanical 
engineering branch was neither fully involved in the selection and 
approval of chillers as proposed by the contractor nor the 
commissioning of building cooling systems. In addition, OBO's 
mechanical engineering branch chief noted the NEC design 
specifications for chillers were "not as tight as they perhaps could 
have been." In some instances, he noted the building cooling systems 
were oversized resulting in chillers not operating properly. Those 
issues reveal that some problems State experienced were not due solely 
to problems with the units but rather were also due, in part, to 
problems with OBO's internal processes. In addition, both OBO and post 
officials have reported that local facilities staff at some posts may 
not have the requisite technical skills to adequately maintain the 
chillers and could have also contributed to problems posts 
experienced. An OBO official reported that the design criteria for 
NECs prior to 2007 allowed contractors to install either water-cooled 
or air-cooled chillers based on life-cycle cost 
considerations.[Footnote 50] They further reported that maintaining 
water-cooled chillers is challenging due to technical issues, such as 
having to treat the water-cooled systems by using potentially 
hazardous chemicals. In 2007, after learning of the problems that 
facilities staff had maintaining the water-cooled systems, OBO changed 
its design criteria to require air-cooled chillers to be installed in 
future NECs. OBO based its decision on its conclusion that the units 
are less difficult to operate, in part, due to not having cooling 
towers to maintain. OBO reported that water-cooled systems will no 
longer be used in NECs, despite being generally more cost effective 
with regard to energy use. OBO officials believe there is no case 
where energy savings of using water cooled chillers would outweigh the 
costs of maintaining those systems. 

In addition to problems with chillers, we found evidence of other 
issues related to the NECs cooling systems, including temperature 
control problems, building air pressure issues, condensation on pipes 
and in ductwork, mold, and inadequate cooling of computer server 
rooms. Some of the contributing factors include design and 
installation issues and lack of required preventative maintenance on 
the systems. (See figs. 13 and 14 for examples of problems we found 
that are related to the design, installation, operation, or 
maintenance of the NEC cooling systems.) 

Figure 13: Example of Condensation Causing Mold: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

Note: Condensation from chilled water piping (left) causes mold to 
grow on ceiling tiles (right). 

[End of figure] 

Figure 14: Example of Inadequate Maintenance of Air Supply Diffuser 
and Cooling Units Added After System Failure: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

Note: Inadequate maintenance of an air supply diffuser (left) and two 
supplemental cooling units (right) added by post maintenance staff to 
the computer server room after the NEC cooling system failed. 

[End of figure] 

Fire Alarm Systems at Many Posts Have Been Problematic: 

Several posts we reviewed have experienced false alarms or other 
repeated problems with operations of their fire alarm systems. These 
alarms disrupt operations--particularly consular services and 
classified operations--when post personnel need to cease activities 
and secure classified materials and workspaces prior to evacuating the 
building in the event of an alarm. Embassy officials in Sofia, 
Bulgaria, reported, for example, repeated false alarms during the 
first 4 years of occupancy that took several visits from OBO and 
contractor teams to troubleshoot and resolve.[Footnote 51] In Yaoundé, 
Cameroon, officials reported they experienced four false alarms per 
week and that OBO spent $120,000 on repairs to the NEC fire alarm 
system.[Footnote 52] At one NEC, officials said the ambassador would 
advise people he was meeting with that the NEC fire alarm system had 
problems and they need not evacuate the building unless the public 
address system indicated there was an actual fire incident. 

In addition to false alarms, several NECs have had repeated problems 
with fire alarm control panels, with illuminated "trouble" or 
"supervisory" lights, or the sounding of an alarm on the panel that 
signals a problem with the system.[Footnote 53] OBO fire officials 
report that the problems with the fire alarm control panels are 
related to one manufacturer's products that are complex to operate and 
cannot easily be corrected by the maintenance staff because of special 
tools and programming codes from the manufacturer that are needed to 
troubleshoot and fix the problems. These alarms can cause disruptions. 
For example, in Kigali, Rwanda, the General Service Officer who 
oversees warehouse operations commented that the fire alarm control 
panel in the warehouse routinely sounds an audible alarm. The alarm is 
very loud and disturbing to warehouse staff. While the alarm has been 
reset many times, she noted it has been an issue since the facility 
was completed in 2008. During our visit, we found the panel had both 
trouble and supervisory lights lit. Post facilities personnel noted 
they have been waiting for nearly 8 months for OBO to find a solution. 
Figure 15 shows the fire alarm control panel at Kigali, Rwanda, which 
we observed had warning lights indicating a condition in the system 
that requires attention. Similar trouble and supervisory conditions 
were found at some of the other posts we visited as well. 

Figure 15: NEC Fire Panel in Kigali, Rwanda, with Trouble and 
Supervisory Lights Illuminated: 

[Refer to PDF for image: photograph] 

Source: GAO. 

[End of figure] 

OBO fire officials report that while they assess most problems as 
being minor in nature, they report there are some problems that are 
more significant and require extensive troubleshooting by trained 
technicians. Fixing the problems is complicated by most posts' lack of 
qualified and experienced staff to perform testing and maintenance of 
the complex fire protection systems. As a result, OBO staff or 
contractors must be sent to posts to resolve the problems. In 
discussions with OBO's fire officials, they noted they are aware of 
many of the past problems with false alarms and are trying to address 
them; however, higher priorities to conduct final acceptance testing 
on NECs under construction has slowed their ability to respond to the 
problems as quickly as they would like. 

NEC Security Doors and Windows Had Problems and Replacements Are Under 
Way: 

More than half the posts we reviewed have encountered problems with 
their security forced-entry and ballistic-resistant doors and windows, 
including problems with doors malfunctioning and window glass 
cracking. State officials reported, as the NEC program grew and the 
demand for security doors and windows increased, recurring problems 
with the doors and windows became evident as projects were completed. 
Problems with doors and windows relate to a combination of design, 
manufacturing, and installation defects. For example, doors used in 
early NECs were fitted with hinges that were incapable of supporting 
the door's weight and prone to premature failure, especially in high-
traffic areas such as main lobbies and the consular applicant waiting 
areas. Doors installed at NECs built prior to 2005 also presented 
maintenance challenges because their design specifications did not 
adequately allow for adjustment to keep doors properly aligned in 
relation to the door frame and building structure. State has revised 
its specifications to ensure the doors are installed correctly and 
that they allow for future adjustment to properly maintain the doors. 
Similarly, windows used at early NECs exhibited manufacturing defects 
that contributed to their cracking, especially in locations with high 
temperatures. Also, because some contractors were not experienced with 
these products, doors and windows were not always installed correctly, 
and as a result, did not operate properly after the facilities were 
occupied. 

While OBO expects fewer problems with security doors and windows in 
the future because of improvements made to design specifications, 
manufacturing processes, and installation techniques, it is 
systematically managing efforts to repair or replace defective doors 
and windows at several existing NEC locations.[Footnote 54] For 
example, in Yaoundé, Cameroon, OBO reports that it funded a project to 
replace 24 doors at a cost of approximately $840,000. In Kathmandu, 
Nepal, 30 windows cracked shortly after the NEC opened in 2007, and 
post officials report OBO is planning to replace them. Going forward, 
our review shows that OBO plans to repair or replace security doors 
and windows in at least 16 additional NEC locations at a total 
estimated cost of $25 million (see figs. 16 and 17).[Footnote 55] 
While some replacements are reported by OBO officials as being driven 
by an increase in the security standards since the NECs were 
completed, it is unclear the extent to which replacements are also due 
to poor performance of those products or deficiencies in the design 
criteria for the doors in early NECs.[Footnote 56] 

Figure 16: NEC Sofia, Bulgaria: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

Note: New security doors being installed (left) and old security doors 
removed (right) at the time of our visit. 

[End of figure] 

Figure 17: NECs Kigali, Rwanda, and Port-au-Prince, Haiti: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

Note: Cracked security windows at NEC Kigali, Rwanda (left), and Port- 
au-Prince, Haiti, prior to 2010 earthquake (right) at the time of our 
visits. 

[End of figure] 

State Has Taken Steps to Avoid Future Problems with Building Systems: 

As previously discussed, State has a lessons learned process that 
examines issues and problems with past projects so as to inform future 
designs of NECs. OBO officials have acknowledged the numerous issues 
posts reported, such as problems with building cooling systems, fire 
alarm panels, and security doors and windows. We found that OBO has 
taken action to change the SED design and contract requirements that 
govern future NECs with regard to all three of those building systems. 
Table 5 outlines some of the changes that have been made through the 
lessons learned program to avoid the problems that exist with the 
underperformance or failure of building systems in earlier NECs; 
however, due to the time required to contract and construct NECs, it 
typically takes 4 years before these changes are evident in completed 
NECs. While changes to SED design criteria for future projects do not 
resolve problems with completed NECs, interviews with OBO officials 
and our review of State's LROMP show evidence that OBO is trying to 
address some of the problems with chillers and security windows and 
doors through planned replacement projects, a few of which have 
already been completed. OBO fire officials are also working with posts 
to develop maintenance contracts to assist in troubleshooting 
maintenance problems with NEC fire alarm systems. 

Table 5: Changes Made by State to the Standard Embassy Design to Avoid 
Problems with Building Systems on Future NECs: 

Problem area: Building cooling systems; 
Selected actions taken: Changed requirements to require contractors to 
provide only air-cooled, rather than water-cooled, chillers. OBO staff 
report that while less energy efficient, air-cooled chillers will be 
easier to operate and maintain and will reduce water consumption; 
Fiscal year implemented[A]: 2007. 

Problem area: Fire alarm control panels; 
Selected actions taken: Changed the requirements for fire alarm 
panels, removing language that may have restricted contractors to 
procuring units from one manufacturer. OBO staff report that other 
manufacturers' units may be less difficult to maintain; 
Fiscal year implemented[A]: 2008. 

Problem area: Security doors and windows; 
Selected actions taken: Instituted a Government Procured Equipment 
program for security doors and windows with the intent to improve 
performance of those products in more recent NECs. Modified 
requirements to require contractors to provide a certified installer 
to train installation crews on job sites; 
Fiscal year implemented[A]: 2005. 

Source: GAO analysis of State information. 

[A] While changes to the design requirements have been made, due to 
the time required to contract for and construct NECs, it typically 
takes 4 years before results are evident in completed NECs. 

[End of table] 

State Faces Challenges in Hiring and Training NEC Facilities Staff and 
Lacks a Plan to Fully Address Challenges: 

State has experienced problems in hiring U.S. Foreign Service facility 
managers and the locally employed maintenance staff that possess 
needed technical skills to operate and maintain the NECs. In addition, 
the local maintenance staff need more training on operating the 
sophisticated NEC building systems. As a result, facilities may be 
operating suboptimally and important maintenance activities may be 
compromised, leaving NECs at risk of not performing as expected. We 
found that State's LROMP does not identify costs or a schedule to 
address the training needs of local maintenance staff to ensure the 
investment in NECs is protected. If State cannot hire enough facility 
managers and local maintenance staff with the technical skills and 
qualifications needed to understand the NEC building systems and also 
train the local facilities staff responsible for operating and 
maintaining those sophisticated systems, State puts at risk the 
investment made in those NECs, the safety of the people operating and 
working in the facilities, and the ability of U.S. government 
employees to conduct their work. 

State Faces Challenges Hiring Qualified U.S. Foreign Service Facility 
Managers and Local Maintenance Staff: 

State officials reported that, based on sophisticated building systems 
installed in NECs, State's hiring criteria needed to be strengthened 
for U.S. facility managers and, further, hiring appropriate staff has 
proven to be a slow process. Specifically, State now requires that 
newly hired facility managers have a degree in facilities management 
or a related engineering field. OBO currently has approximately 170 
facility managers, of which approximately 145 are assigned to overseas 
posts and some facility managers have regional duties supporting more 
than one post; however, to meet its intent of placing specially 
qualified facility managers at every large embassy and consulate 
worldwide, OBO is undertaking a long-term recruitment and hiring 
effort. OBO officials reported a goal to hire 20 facility managers in 
fiscal year 2009, 20 in fiscal year 2010, and 24 total for fiscal 
years 2011 to 2015.[Footnote 57] However, OBO has fallen short of 
achieving its hiring goals. In fiscal year 2009, for example, OBO 
reported that it hired 11 facility managers (i.e., just over half of 
its goal), and as of May 2010, OBO had hired a total of 6 facility 
managers relative to its fiscal year 2010 goal of 20. Some of the 
challenges and delays in hiring were due to the process of developing 
new position descriptions that require facility managers to have a 
degree in facilities management or a related engineering field, and 
working with State's human resources department to get those new 
qualifications requirements approved. 

Overseas posts are responsible for hiring locally employed maintenance 
staff and sometimes face challenges hiring individuals with the 
technical skills and experience required to operate NECs' complex 
systems. OBO officials report a key issue with NEC maintenance, which 
they believe has contributed to the problems with some systems, is 
that posts have not been able to hire appropriately qualified local 
staff. OBO provides individual posts with a recommended maintenance 
staffing plan and advises posts that, because NECs are large and have 
sophisticated building systems, posts should be prepared to hire 
additional staff to properly support the maintenance needs when an NEC 
opens. State's IG, in surveying posts with NECs about whether they had 
hired the required maintenance staff, found that several did not hire 
the required maintenance staff due to budget constraints or had not 
hired them by the time the NEC initially opened.[Footnote 58] 

As noted previously, local staffing costs at NECs increased by 
approximately $200,000, on average, at 10 posts we reviewed because of 
the need to hire additional local maintenance staff.[Footnote 59] 
State's Inspector General reported that the level and quality of 
maintenance services appears to be determined by available ICASS funds 
rather than need, and a few posts reported concerns that ICASS budgets 
did not keep pace with increased NEC staff needs. Some posts also 
reported that it can be difficult in some less developed countries to 
find qualified maintenance technicians to hire. OBO officials reported 
to us that part of the reason why posts face problems hiring local 
maintenance staff in a timely manner is these additional positions 
must be approved by other agencies located at the post through ICASS. 
OBO officials also indicated that in some cases, the salaries needed 
to get qualified technical staff--such as a building automation 
operator--have created difficulties for posts when it would require 
paying the new hire more than senior local staff in other offices 
within the embassy. 

To address hiring challenges related to facility manager positions, 
OBO officials report they are reaching out to industry facilities 
management associations and universities to increase the number of 
potential applicants that apply for the positions. As we reported, 
State did not meet its fiscal year 2009 goal for hiring new facility 
managers and may not meet its goal for fiscal year 2010. Starting in 
2009, OBO reports that the new Operations and Maintenance Transition 
Coordinators assigned to each project will assist posts' management 
officials in hiring additional local maintenance staff as needed; 
however, OBO officials reported that the approval and hiring of local 
facilities staff, to include setting salaries, remains an ICASS 
decision and is not under OBO's control. 

State Faces Challenges in Training Maintenance Staff to Operate and 
Maintain the NECs: 

State officials report that prior to 2008, the department had not 
focused on training and career development needed for its facilities 
maintenance personnel. While State had provided training in the areas 
of management and leadership for facility managers, there was no 
formal training program available that provided technical training on 
the sophisticated NEC systems and State policies governing overseas 
facility management in an embassy environment. In addition, there were 
no training programs for local maintenance staff. State has started to 
take action to address some of the challenges, but OBO officials 
report those actions will not fully address the needs of local 
maintenance personnel. In 2008, OBO developed a training program for 
State's facility managers. Unlike local maintenance staff, OBO 
officials report they are directly responsible for training and career 
development for facility managers. OBO officials recognized the need 
to provide more training for facility managers and report that newly 
hired facility managers now attend courses at the Foreign Service 
Institute and receive specialized training in areas such as (1) 
building automation systems; (2) heating, cooling, and ventilation 
systems; and (3) fire protection systems. In addition, facility 
managers receive training on overseas facilities management related to 
specific State regulations governing maintenance budgets and the 
maintenance protocols for classified areas. 

Training of the local maintenance staff remains a problem.[Footnote 
60] As noted earlier, the basic familiarization training provided by 
the NEC construction contractor during the time of commissioning and 
prior to transfer is not sufficient by itself to fully train the local 
maintenance staff on the building systems. As a result, operation of 
building automation systems, in particular, has been challenging for 
posts. Our review of OBO reports and interviews with posts show that 
14 of the 22 NECs we reviewed encountered problems with operating 
building automation systems.[Footnote 61] For example, embassy 
officials in Kigali, Rwanda, report that personnel will have 
difficulty learning enough programming on the system to facilitate 
programming replacement components in the event the original 
components fail; they report that emergencies may not enable post to 
wait for a service contractor or OBO to travel to post to troubleshoot 
or fix problems. One of State's contractors noted that sufficiently 
operating and maintaining the building automation system is 
challenging, since it requires training and knowledge of both 
mechanical engineering and advanced computer programming. He reported 
that at some NECs he finds sensors, controllers, and equipment that 
have been shut off by facilities staff who have not had adequate 
training on the systems and may not understand the implications when 
components are merely turned off. For example, shutting a component 
down may restrict fresh air being provided to a closed office. 

We found that State's LROMP does not identify needed resources and 
costs to meet the training needs of local maintenance staff at NECs. 
OBO officials recognize that NEC building systems require extensive 
training to operate. OBO officials also recognize that if the local 
maintenance staff are not trained properly, the condition and 
operation of the NECs will be affected; however, OBO officials report 
they do not receive funding to train overseas maintenance staff, as it 
is an ICASS responsibility. Regardless, in 2009, OBO took some initial 
action to address some of the training deficiencies of local 
maintenance personnel and reported that it would be providing posts' 
local staff with access to online training in areas such as water and 
wastewater treatment, environmental security protection systems, 
building automation systems, and work order management. However, two 
of these courses came online only recently and one is still in 
development; therefore, the action is too recent to assess in terms of 
the number of staff trained and the effectiveness of the training. 
[Footnote 62] OBO officials also reported that they have just begun 
discussions with a facility management training provider to explore if 
they can develop facility maintenance courses that could be made 
available to posts' local staff. Again, the actions are too recent to 
assess in terms of their effectiveness. 

According to State officials, they are trying to compensate for the 
lack of technical skills of the local staff through the use of 
regional maintenance programs and posts' maintenance service 
contracts;[Footnote 63] however, that may not be the most cost- 
effective solution. For example, State's IG reported that the U.S. 
embassy in Abidjan, Cote d'Ivoire, did not have trained personnel to 
maintain the critical elements of the NEC's heating and cooling 
systems and that post had to bring in a contractor from South Africa 
for emergency repairs at a cost of about $9,000 per visit. OBO 
officials reported they are exploring the idea of making use of OBO's 
facility managers to act as trainers to control costs as OBO does not 
have dedicated funding to train posts' local maintenance staff. 
According to OBO officials, some of OBO's efforts to provide more 
training to local maintenance staff are being funded out of existing 
NEC project funds. Starting in 2009, OBO began to set aside 0.1 
percent of NEC project funding--which would equate to $100,000 on a 
$100 million NEC project--to provide additional training, but OBO 
officials acknowledged it alone will not be sufficient to fully train 
local maintenance staff. OBO officials further noted that, while ICASS 
should normally fund the training of local staff, OBO is funding what 
it can to try to address some of the local staff training needs. 

Conclusions: 

State has built 52 NECs that are more secure, safe, and functional for 
U.S. government personnel working overseas. Constructing such 
facilities that meet stringent requirements, such as building codes, 
security standards, and energy-efficiency goals, has been a 
significant undertaking requiring billions of dollars and sustained 
effort over nearly 10 years. However, State has encountered a number 
of challenges in building NECs that are the appropriate size for 
immediate and long-term staffing levels and in planning for the 
increased operational and maintenance needs of these new, 
technologically sophisticated buildings. As a result, State has had to 
build additional office space at some locations, and may need to 
construct more, and has also faced higher operating, maintenance, and 
repair costs. Currently, the process to determine the size of an NEC 
does not allow enough flexibility to ensure that NECs have sufficient 
space to accommodate staffing changes related to ever-shifting foreign 
policy priorities. State has not analyzed post-specific 
characteristics in completed projects that have been associated with 
rapid staff growth, such as geographic location, nor have officials 
been able to explain the analytical basis for determining the amount 
of growth space to include in building an NEC. In addition, overseas 
officials have found that the design of some spaces does not fully 
meet functional needs. While State has been able to identify and 
address certain design issues, identifying these design problems 
earlier, by, for example, conducting timely post-occupancy evaluations 
in accordance with State's plans, is crucial to avoid similar problems 
in future NECs. Since State expects NECs to support U.S policy efforts 
for several decades, it is important that the facilities are large 
enough to safely and securely house the changing number of overseas 
staff in a manner in which staff are able to effectively carry out 
their missions. 

State has not fully addressed the increased operations and maintenance 
requirements of the more technologically sophisticated NECs. Problems 
with commissioning and transferring the NECs from the contractors to 
the posts have resulted in some building systems that do not function 
as they should and led to added costs to repair and replace systems, 
contributed to higher operating costs, and created potential safety 
risks for staff. State has made changes to building design 
requirements to avoid future problems with NEC building systems. 
However, since changes can take at least 4 years to materialize in 
completed NECs, due to time to contract for and construct NECs, the 
changes are too recent to assess. State does not have a formal plan to 
recommission, or retest, the building systems at NECs that have 
already been completed. Recommissioning NECs would help ensure that 
the systems operate as efficiently as possible and that the problems 
with building systems are being fully addressed. State's recent LROMP 
outlines--for the first time--NEC maintenance costs over a number of 
years and identifies the need for improvements in future editions, but 
it does not establish a time table for when specific projects should 
be completed which would help to further strengthen the planning 
process. In addition, the LROMP is focused solely on maintenance costs 
and does not address operating costs, resulting in an incomplete 
assessment of all costs associated with the functioning of NECs. 
Finally, without a plan that comprehensively outlines all human 
resources required to operate and maintain NECs, including identifying 
hiring and training needs, State will have difficulty ensuring NECs 
operate in an efficient and cost-effective manner. As State continues 
building NECs and strives to maintain those already constructed, 
addressing these challenges is important to provide U.S. employees 
with a secure and dependable working environment and ensure that State 
protects the country's investment in these facilities. 

Recommendations for Executive Action: 

In order to strengthen the operations of the extensive U.S. program 
that provides for new embassy compounds around the world, we recommend 
that the Secretary of State take the following six actions. 

* Take steps to improve the process for determining the appropriate 
size for an NEC, including reassessing the analytical basis for 
projecting future staffing levels and determining how much growth 
space is allocated. 

* Ensure that OBO conducts post-occupancy evaluations of completed 
NECs as planned. 

* Develop a plan to recommission those NECs completed before 2008 to, 
for example, resolve any problems posts may still have with building 
systems, and ensure that the operating costs are not being incurred 
unnecessarily as a result of building systems that are not operating 
as efficiently as intended. 

* Identify time frames for implementing the maintenance projects that 
are outlined in the LROMP. 

* Expand on future editions of the LROMP to include reporting on 
operating costs to allow for a more complete assessment of the costs 
to maintain and operate NECs. 

* Develop a human resource plan that addresses the requirements and 
cost implications for hiring required NEC facilities maintenance staff 
and sufficiently training the local maintenance staff. 

Agency Comments: 

We received written comments on a draft of this report from the 
Department of State. State said that the report contains helpful input 
about its program to build NECs which State will use to further its 
efforts to improve the efficiency and effectiveness of its operations. 
State concurred with our principle findings, conclusions, and 
recommendations. For example, State wrote it will work to identify 
time frames for implementing the LROMP maintenance projects, develop a 
system to compile and report on operating costs, and undertake human 
resource planning to hire and train local maintenance staff. State 
further outlined specific actions that begin to address our 
recommendations in a few instances. For example, State said it is 
currently conducting post-occupancy evaluations at three posts and 
plans to evaluate at least six more by the end of 2010. In addition, 
State said it is conducting two pilot recommissioning studies, and 
plans to conduct two more studies in fiscal year 2011 if funding is 
available. State provided additional clarifying and technical comments 
on a number of points, which we have incorporated throughout the 
report, as appropriate. Many of State's comments we had already 
acknowledged in our report. State's complete comments, along with our 
responses to specific points, are reprinted in appendix II. 

We are sending copies of this report to interested congressional 
committees. We are also sending copies of this report to the Secretary 
of State. In addition, this report will be available at no charge on 
the GAO Web site at [hyperlink, http://gao.gov]. 

If you or your staff have any questions about this report, please 
contact Jess T. Ford at (202) 512-4268, fordj@gao.gov, or Terrell G. 
Dorn at (202) 512-6923, dornt@gao.gov. Contact points for our Offices 
of Congressional Relations and Public Affairs may be found on the last 
page of this report. Other GAO contact and staff acknowledgments are 
listed in appendix IV. 

Signed by: 

Jess T. Ford: 
Director, International Affairs and Trade: 

Signed by: 

Terrell G. Dorn, PE: 
Director, Physical Infrastructure: 

List of Requesters: 

The Honorable John F. Kerry:
Chairman:
The Honorable Richard G. Lugar:
Ranking Member:
Committee on Foreign Relations:
United States Senate: 

The Honorable Howard L. Berman:
Chairman:
The Honorable Ileana Ros-Lehtinen:
Ranking Member:
Committee on Foreign Affairs:
House of Representatives: 

[End of section] 

Appendix I: Scope and Methodology: 

The objectives of this report were to examine (1) the extent to which 
new diplomatic facilities match the space and functionality needs of 
overseas posts and the actions State has taken to address any space 
and functionality challenges; and (2) operations and maintenance 
challenges at these new facilities and State's steps to address them. 

Our scope included new facilities at 44 posts that State's Bureau of 
Overseas Buildings Operations (OBO) refers to as New Embassy Compounds 
(NEC), New Consulate Compounds, and New Office Buildings. In addition, 
we included any facility OBO refers to as a Newly Acquired Building if 
the purchase and renovation of such a facility were intended to locate 
all U.S. government employees at a new and single location.[Footnote 
64] We included all posts for which construction began in or after 
fiscal year 1999 and were completed by September 30, 2009.[Footnote 65] 

To obtain information on space, functionality, and operations and 
maintenance challenges identified at NECs within our scope, we 
reviewed State's 2008 Revalidation Look Back Study, which identified 
issues and problems, as well as successes, with regard to the 
planning, design, construction, and maintenance of the new facilities. 
The study took place between August and October 2008 and identified 23 
challenges as frequently occurring throughout completed NECs. We also 
conducted interviews with officials at OBO and State's regional 
bureaus and reviewed other documentation, including the State 
Inspector General's (IG) inspection of OBO;[Footnote 66] IG post 
inspection reports; posts' responses to a March 2008 IG satisfaction 
survey; posts' lessons learned cables; rightsizing reports; and post-
occupancy evaluations of some completed projects. 

To obtain more detailed information on space, functionality, and 
operations and maintenance challenges, we reviewed 22 NECs, or one-
half of the posts within our scope, in greater depth. We selected 
these posts based on interviews with regional bureau officials, 
reviews of rightsizing reports and 2008 staffing data, OBO and OIG 
reports on embassy operations and maintenance issues, OBO's 
Revalidation Look Back study, and past GAO reviews of the NEC program. 
In addition to selecting posts with many identified space, 
functionality, and operations and maintenance problems, we also 
selected some posts with few identified problems to be able to analyze 
a range of experiences. Geographical diversity of posts and project 
type[Footnote 67] were also factors in determining which posts to 
contact. 

Of the 22 posts we reviewed in greater depth, we conducted site visits 
at 8 posts and conducted teleconference interviews with 14 posts. In 
addition to contacting officials at each post, we interviewed 
officials at the regional bureaus in Washington to obtain information 
on space, functionality, and operations and maintenance challenges at 
posts that we were unable to contact, as well as to gain further 
insight on how these challenges affect their respective regions as a 
whole. 

Table 6 lists all 44 NECs within our scope and identifies those we 
visited or interviewed via teleconference. 

Table 6: Locations of 44 NECs within GAO's Scope: 

Region: Africa; 

New Embassy Compound: 
Abidjan, Cote d'Ivoire.
Abuja, Nigeria (Visited by GAO).
Accra, Ghana (Visited by GAO).
Bamako, Mali.
Brazzaville, Republic of the Congo.
Cape Town, South Africa.
Conakry, Guinea.
Dar es Salaam, Tanzania.
Freetown, Sierra Leone.
Johannesburg, South Africa.
Kampala, Uganda (Visited by GAO).
Kigali, Rwanda (Visited by GAO).
Lome, Togo (Visited by GAO).
Luanda, Angola.
Nairobi, Kenya (Visited by GAO).
Yaoundé, Cameroon (Visited by GAO). 

Region: East Asia and the Pacific: 

New Embassy Compound: 
Beijing, China (Visited by GAO).
Phnom Penh, Cambodia (Visited by GAO).
Rangoon, Burma (Visited by GAO). 

Region: The Americas: 

New Embassy Compound: 
Belmopan, Belize.
Bridgetown, Barbados.
Ciudad Juarez, Mexico.
Kingston, Jamaica.
Managua, Nicaragua (Visited by GAO).
Panama City, Panama (Visited by GAO).
Port-Au-Prince, Haiti (Visited by GAO).
Quito, Ecuador.
Sao Paulo, Brazil. 

Region: Middle East and North Africa: 

New Embassy Compound: 
Abu Dhabi, United Arab Emirates.
Algiers, Algeria (Visited by GAO).
Tunis, Tunisia. 

Region: South and Central Asia: 

New Embassy Compound: 
Astana, Kazakhstan (Visited by GAO).
Dushanbe, Tajikistan.
Kathmandu, Nepal (Visited by GAO).
Tashkent, Uzbekistan (Visited by GAO). 

Region: Europe and Eurasia: 

New Embassy Compound: 
Berlin, Germany (Visited by GAO).
Bern, Switzerland.
Frankfurt, Germany.
Istanbul, Turkey.
Skopje, Macedonia.
Sofia, Bulgaria (Visited by GAO).
Tbilisi, Georgia (Visited by GAO).
Yerevan, Armenia.
Zagreb, Croatia. 

Source: GAO. 

[End of table] 

To assess the extent to which initially constructed desk space matched 
posts' current desk space needs, we compared State data on the number 
of desks originally built at each post with current authorized 
collocated desk positions, as reported in each post's 2009 submission 
of staffing data for the purposes of determining each overseas 
agency's charges for the Capital Security Cost Sharing program for all 
44 posts within our scope. We interviewed knowledgeable State 
officials and reviewed our analysis with the 22 posts we interviewed, 
OBO, and each of the regional bureaus and determined that both data 
sources were sufficiently reliable for our purposes. However, we 
identified a few limitations to our analysis, including: (1) in a 
small number of cases, current staffing data for other agencies, 
particularly the U.S. Agency for International Development, may not be 
completely accurate; (2) the data are based on a single point in time 
and subsequent changes may have occurred that altered the conditions 
at posts; (3) the as-built data may not have captured all changes made 
during construction and do not include planned growth space; and (4) 
the current staffing data report authorized positions representing the 
post's total need if all positions were filled, but some positions may 
not be filled. However, our checks found only a small number of 
inaccuracies in either source, most of which, in our judgment, had 
little impact on our overall findings. In addition, we interviewed 
officials at State's Office of Management Policy, Rightsizing, and 
Innovation (M/PRI) and OBO to discuss their respective roles in 
planning for the space needs of NECs. 

To examine functionality challenges, we asked officials at the 22 
posts we contacted open-ended questions about functionality concerns. 
We then summarized functionality challenges that were commonly 
identified during our interviews and site visits. These ranged from 
the amount of controlled access and noncontrolled access space 
available at NECs to issues with the NEC's quality-of-life facilities. 
Our methodology may not have captured all challenges experienced at 
all of the posts we reviewed, as post officials might have only 
reported the challenges they deemed to be most significant. 

To analyze challenges found in operating and maintaining NECs, we 
quantified common challenges found across the 22 posts we contacted, 
based on officials' responses to open-ended questions in our 
interviews and site visits, as well as our review of documentation, 
including State IG reports and the Revalidation Look-Back study. These 
challenges ranged from problems with forced-entry and ballistic-
resistant doors and windows to the process of turning over the NEC 
from the construction contractor and OBO to the posts. Our methodology 
may not have captured all challenges experienced at all of the posts 
we reviewed, as post officials might have only reported the challenges 
they deemed to be most significant. 

In addition, we analyzed operations and maintenance cost data from 10 
NECs opened in fiscal years 2007 and 2008. We asked officials to 
provide fiscal year 2009 data on operating expenses (e.g. cost for 
utilities such as electric, gas, water, and sewer as well as other 
costs like grounds keeping and janitorial services), costs for 
maintenance service contracts (e.g. elevator service contract), and 
the cost of hiring additional facilities maintenance staff (e.g. 
building automation system operator) for the NEC. We also asked for 
data on each of these expenses for the last full fiscal year in which 
the post operated from its previous facilities. Because these NECs 
were completed recently, inflation and other time-related issues, such 
as price changes, did not play a significant factor in our comparison 
of 2009 costs at the NECs with the last full year of operation in the 
previous facilities, and thus the reported cost are not adjusted for 
inflation or currency fluctuations. We discussed potential 
discrepancies in the data with post officials and tested the data for 
internal consistency. Although in some cases, posts may or may not 
have included utilities costs for leased facilities, we determined 
that unreported utility costs for leased facilities would not 
materially impact our findings. We determined the data were 
sufficiently reliable for the purpose of demonstrating that the 
operating costs of the 10 NECs were substantially higher than the 
costs of the facilities they replaced.[Footnote 68] Due to concerns 
about OBO having complete and accurate data on posts' expenses, we 
obtained the cost data directly from posts. 

Finally, to identify actions State has taken to address space, 
functionality and operations and maintenance challenges, we 
interviewed State officials at OBO, the regional bureaus, and M/PRI. 
In addition, we reviewed documentation of programs or initiatives that 
State has developed to address identified challenges. 

[End of section] 

Appendix II: Comments from the Department of State: 

Note: GAO comments supplementing those in the report text appear at 
the end of this appendix. 

United States Department of State: 
Chief Financial Officer: 
Washington, D.C. 20520: 

June 28, 2010: 

Ms. Jacquelyn Williams-Bridgers: 
Managing Director: 
International Affairs and Trade: 
Government Accountability Office: 
441 G Street, N.W. 
Washington, D.C. 20548-0001: 

Dear Ms. Williams-Bridgers: 

We appreciate the opportunity to review your draft report, "New 
Embassy Compounds: State Faces Challenges in Sizing Facilities and 
Planning for Operations and Maintenance Requirements," GAO Job Code 
320750. 

The enclosed Department of State comments are provided for 
incorporation with this letter as an appendix to the final report.
If you have any questions concerning this response, please contact 
Christina Maier, Program Analyst, Office of Overseas Building s 
Operations at (202) 875-5752. 

Sincerely, 

Signed by: 

James L. Millette: 

cc: GAO — Jess Ford: 
OBO — Adam Namm (Acting): 
State/OIG — Tracy Burnett: 

[End of letter] 

Department of State Comments on GAO Draft Report: 

New Embassy Compounds: 

State Faces Challenges in Sizing Facilities and Planning for 
Operations and Maintenance Requirements (GAO-10-689, GAO Code 320750): 

Introduction: 

The Department of State appreciates the opportunity to review the 
subject draft report. Overall, the report contains helpful input about 
the Department's ongoing Capital Security Construction Program to 
build New Embassy Compounds (NECs) and New Consulate Compounds (NCCs). 
We will use GAO's findings to further our efforts to improve the 
efficiency and effectiveness of the Department's operations. We offer 
the following comments: 

Construction Progress: 

The Department is pleased that GAO acknowledges State's progress in 
constructing NECs, NCCs, and annexes — 72 since 2001 — and moving over 
21,000 staff into safer, more secure, and functional facilities. GAO 
also reiterates the findings of a State Office of Inspector General 
study where posts with NECs praised their design, space, and security, 
and found NECs to be a dramatic improvement over older facilities. 

Other Comments: 

Planning for Maintenance: The Bureau of Overseas Buildings Operations 
(OBO) believes it has made measurable progress in planning for 
maintenance and operations since GAO's 2006 study.{Footnote 1] 

In March 2010, OBO issued the first Long-Range Overseas Maintenance 
Plan (LROMP). The inaugural LROMP is a comprehensive strategic 
planning document, focused on the management of $3.7 billion in 
deferred and planned maintenance, repair, and rehabilitation needs. 
The plan aims to ensure the $10+ billion invested in constructing new 
facilities since 2001 is protected through proper maintenance as well 
as ensure legacy facilities not planned for replacement receive 
appropriate maintenance and operations funding. The LROMP identifies 
post-by-post prioritized needs for more than 3,500 projects and is a 
companion publication to the Long-Range Overseas Buildings Plan 
(LROBP). 

We have also accomplished the following: 

* Studied and refined our estimates of future NEC operating costs; 

* Enhanced the qualifications needed to become a Facility Manager 
(FM), including requiring an engineering or facility management degree; 

* Instituted a new training curriculum for FMs at the Foreign Service 
Institute; 

* Hired 11 new FMs who have completed the new curriculum, 6 are 
currently enrolled, 20 will begin class in August 2010 and there are 
10 slots for a class in March 2011; 

* Realigned the FM reporting structure at post in that FMs now report 
to management; 

* Developed on-line training courses for locally employed maintenance 
staff at post and are developing an augmented, blended learning 
program; 

* Improved our NEC staffing studies to provide post with guidance on 
hiring and training appropriate staff to maintain the NECs; 

* The Lessons Learned Program has shortened the period for including 
changes into the program; and; 

* Adjusted the parametric model for estimating costs by including FY 
09 construction award and project closeout data. 

While the Department realizes that there is still room for improvement 
in our maintenance planning, we believe we have made substantial 
progress in this area. We will work to address GAO's recommendations 
on identifying time frames for implementing the LROMP maintenance 
projects, developing a system to compile and report on operating 
costs, and undertake human resource planning to hire and train local 
maintenance staff. 

Increased Maintenance Costs: [See comment 1] OBO is aware that posts 
with NECs are experiencing increased operating costs because the 
facilities are often larger to accommodate a growing overseas civilian 
USG presence, and are equipped with state-of-the art building systems 
and environmental security protection. While it may appear that costs 
are higher, they can actually be less on a per square meter basis, 
which is the standard industry measure. Using the industry recognized 
Whitestone Facility Maintenance and Repair Cost Reference 2009 — 2010, 
the maintenance costs for a medium sized NEC (approximately 11,600 
gross square meters) have been precisely defined. Maintenance costs 
were carefully estimated, using the Standard Embassy Design drawings 
and specifications for a medium-sized NEC with the following building 
sizes: 

* New Office Building: 7,555 GSM; 
* Marine Security Guard Quarters: 721 GSM; 
* Utility Building: 698 GSM; 
* Warehouse: 2,071 GSM; 
* 3 Compound Access Control Units 566 GSM. 

The results for the maintenance cost per gross square meter are: 

* $26.10 per gross square meter for an NEC; 
* $29.50 per gross square meter for the equivalent Washington DC-area 
buildings as noted above. 

While maintenance costs have increased at NECs, maintenance has 
historically not been funded at a level to thoroughly address all 
needs. It is possible that the percent increase in maintaining NECs 
might have been less if the old facilities had been fully maintained. 
In addition, some maintenance funding intentionally decreases toward 
the end of occupancy of the older facilities, as OBO and post decide, 
for cost savings, to not fully maintain or upgrade systems in a 
building about to be vacated, thus making the NEC maintenance costs 
seem comparatively higher. 

NECs are Safer: [See comment 2] On page 42 of the draft report, GAO's 
subheading notes that problems in NEC commissioning "posed potential 
safety risks." State notes that any safety risks discussed by GAO 
would have been much less in the NEC than the safety risks posed by 
the aging, deteriorated facilities that the NEC replaced. For example, 
as GAO reports, the fire alarm systems at posts were problematic with 
false indicator lights, etc.; however, the NEC buildings were also 
equipped with fully operational fire sprinkler systems, which most of 
the previous embassy buildings did not have. Thus, the NEC provided a 
much improved level of safety. We are concerned that this subheading 
would lead a reader to conclude that we moved staff into unsafe 
facilities, and request that GAO delete the phrase [Posed Potential 
Safety Risks and]. 

GAO's Recommendations: 

The GAO recommends that the Secretary of State take the following six 
actions: 

1. Improve the process for determining the appropriate size for an 
NEC, including reassessing the analytical basis for projecting future 
staffing levels and determining how much growth space is allocated. 

Response: The Department agrees with this recommendation and has 
evaluated both staffing projections and the development of growth 
factors for office space. 

The Office of Management Policy, Rightsizing, and Innovation (M/PRI) 
has reviewed the posts with capital security projects that began after 
the inception of the Office of Rightsizing. The analysis includes 
sixteen posts with OBO projects that will be completed by the end of 
2010 and shows a narrower margin of error--between the rightsized 
number and the staff actually moved into the building--1.2 percent for 
U.S. direct-hire positions in aggregate. For all types of positions, 
the data show an average discrepancy of only 3.4 percent, well within 
OBO's ten percent growth margin. [See comment 3] 

We view this as a success, a validation of the Department's 
rightsizing efforts and an indication that the problem of inadequate 
office space is gradually being resolved. However, we also note that 
the effort to predict future office space needs will always contain 
some uncertainties, that staffing projection discrepancies will 
occasionally exceed ten percent, as they have in four of the sixteen 
"rightsized" posts included in the above-referenced analysis. The 
discrepancies at these four posts were wide enough to skew the 
standard deviation for all positions beyond the 10 percent range-- 
12.5% for posts with staffing overages and 14.8% for all posts. NECs 
are being built in the most volatile areas of the world which makes it 
more difficult to plan for future needs — mission priorities can 
change and programs can expand or contract in a short period of time. 
Dramatic changes at a minority of posts will affect our overall 
success rate at all posts. 

M/PRI's strategic plan for the next five years includes a greater 
emphasis on pro-active analysis and objective comparisons. We also 
hope to move from our current focus on individual posts towards 
analyzing and projecting global staffing trends. 

OBO has recently increased the amount of growth factored into its 
space programs. While OBO still utilizes a 10-percent growth factor 
(i.e. taking the approved desk total and adding an additional 10-
percent of space to the total required for the number of desks), it 
has changed the formula so that each desk position creates 25 usable 
square meters of growth space (vice the previous factors of 6.5 or 
10.8 net square meters). This is in recognition that growth desk 
positions have a ripple effect across the entire space program, and 
this change will provide more flexibility to posts. This change will 
be applied to all projects in FY11 and beyond and for FY10 projects as 
budget and schedule permits. The growth space will be allocated 
proportionally to include basic desk space, designated support space, 
and common areas. We note that because this change is being made for 
projects in FY 2011 (and beyond) and possibly some FY 2010 projects, 
the impact of this increase cannot be evaluated until FY 2014 at the 
earliest. However, as new information comes to light from the Lessons 
Learned Program (to include the Post Occupancy Evaluation process), 
OBO will continue to evaluate the results and determine whether this 
should be refined further. OBO remains aware that the fluidity in 
staffing projections creates a risk that some facilities may end up 
with excess space, as GAO found in its recent study of courthouses. 
[Footnote 2] This would appear to be validated by the GAO's finding 
that only 13 of the 44 NECs they surveyed were under-occupied by five 
percent or more; however, it should be noted that this would allow for 
future growth space. [See comment 4] 

2. Ensure that OBO conducts post-occupancy evaluations of completed 
NECs as planned. 

Response: The Department agrees with this recommendation. As of the 
date of these comments, an OBO team is in the field conducting post-
occupancy evaluations (POEs) at three Western Hemisphere posts. We 
plan to conduct two more POE trips — to Western Hemisphere and African 
regions — to evaluate 6 to 8 more posts by the end of calendar year 
2010. OBO envisions conducting 9 to 12 POEs per year, and accelerating 
the schedule to conduct additional POEs depends on the availability of 
resources. 

Prior to 2008, available resources allowed 0130 to perform on average 
four POEs per year. In 2008, OBO undertook a "Revalidation Look-Back" 
of the 55 NECs, NCCs, annexes, and other diplomatic facilities that 
had been completed between 2001 and 2006. This look-back provided a 
valuable overview of some overarching issues being encountered by 
posts as they occupied their new facilities, and allowed OBO to 
implement improvements in areas such as consular operations, food 
service, warehouses, and maintenance shops. Much of 2009 was directed 
toward integrating the Revalidation Look-Back into the first edition 
of the LROMP (produced in March 2010), and conducting in-depth studies 
of the maintenance shop and warehouse issues identified during the 
look-back. In late 2009 and early 2010, OBO developed enhanced survey 
questionnaires and a new web-based application to facilitate 
communication with post and improve upcoming POEs. 

3. Develop a plan to recommission those NECs completed before 2008 to, 
for example, resolve any problems posts may still have with building 
systems, and ensure that the operating costs are not being incurred 
unnecessarily as a result of buildings systems that are not operating 
as efficiently as intended. 

Response: The Department agrees with this recommendation and will 
conduct recommissioning studies as resources allow. OBO is currently 
conducting two pilot recommissioning studies, and plans to conduct two 
more studies in FY 2011, if funding is available. We estimate that 
each initial study will cost approximately $150,000 to $200,000. 
Current plans are to seek funding in FY 2012 and beyond to conduct 10 
recommissioning studies each fiscal year. 

4. Identify time frames for implementing the maintenance projects that 
are outlined in the LROMP. 

Response: The Department agrees with this recommendation. Upon 
receiving funding for requirements set out in the LROMP, the program 
will be executed similarly to the implementation of the LROBP. The 
timeline for implementing projects will be established concurrent with 
availability of funds. 

5. Expand on future editions of the LROMP to include reporting on 
operating costs to allow for a more complete assessment of the costs 
to maintain and operate NECs. [See comment 5] 

Response: OBO provides estimated costs to operate a NEC to the regional
bureaus before each new facility opens. Three major cost components 
are used in the development of the Building Operating Expense (BOE) 
estimates for NEC/NCCs:[Footnote 3] [See comment 6] 

* Locally Employed (LE) Staff Maintenance Labor Costs — Posts' labor 
costs to maintain equipment within the embassy compound;[Footnote 4] 
(costs assume that all equipment is installed and commissioned per the 
design intent); cost of providing proper preventative maintenance (90% 
of available work hours for the first year); and the cost of training 
facility management LE Staff. 

* Local Service Contract Costs - includes local service maintenance 
contracts for grounds maintenance and landscaping; solid waste 
removal; custodial services; pest control; and pavement and sidewalk 
maintenance (sweeping and snow removal, if applicable). Contracts are 
dependent upon approval of funding by the post ICASS (International 
Cooperative Administrative Support Services) council. 

* Utility Cost - estimates depend on local climate data; number, type, 
and size of the compound's buildings; includes heating and cooling 
loads, water use. Calculated to include variables such as inflation; 
utility rates, and average power and water consumption by NEC occupants.
After the NEC opens, the actual operating costs are tracked by the 
post, the regional bureau, and ICASS. However, limitations on the 
availability of actual cost data, due in part to the complexities of 
the multi-agency ICASS structure, makes the tracking of actual 
operating costs a challenge. The Department is reviewing options for 
efficiently capturing these costs currently resident in multiple data 
systems. 

6. Develop a human resource plan that addresses the requirements and 
cost implications for hiring required NEC facilities maintenance staff 
and sufficiently training the local maintenance staff. 

Response: The Department agrees with this recommendation. The 
Department has not been as diligent as necessary in hiring and 
training local maintenance staff. For NECs, OBO develops a staffing 
plan that details the number of staff and type of skills needed, which 
is provided to post and the Regional Bureau 15 to 18 months before the 
NEC opens. Post then hires the needed staff, which is funded by ICASS 
and D&CP funds. Because of resource limitations, staffing needs can go 
unfulfilled. This issue will be further addressed by OBO, the Regional 
Bureaus, ICASS, and the Bureau of Resource Management. 

In FY 2009, the Senate Appropriations Committee in S. Rept. 110-425, 
accompanying S. 3288, cited GAO's 2006 report on NEC construction and 
its finding that State does not clearly identify the projected 
operations and maintenance costs for NECs. The Committee directed 
State to report on this issue, including whether ICASS is effective in 
supporting post maintenance, given that it is a voluntary system. The 
Committee also considered how a dedicated funding system for 
maintenance, akin to the cost-sharing program for construction, could 
be adapted to fully fund necessary maintenance. OMB and the Department 
have begun working on a possible cost-sharing mechanism for 
maintenance costs. Such a cost-sharing scheme would necessitate 
developing a comprehensive human resources plan for hiring and 
training maintenance staff, as well as the universe of other 
maintenance requirements. [See comment 7] 

As GAO reports, OBO has enhanced its qualifications for Foreign 
Service FMs, requiring them to have an engineering or facility 
management degree. OBO is making progress in recruiting and hiring 
new, degreed FMs. Eleven have completed the FM training course at the 
Foreign Service Institute established in 2009, and six more are 
currently enrolled. There will be 20 more FMs in the September 2010 
training course, 10 expected in the February 2011 course, and 10 per 
year in the following years. This influx should allow posting FMs at 
all of our NECs/NCCs and many legacy facilities, with posts not having 
a resident FM serviced by a regional FM. Addressing increased demands 
for emerging posts in Iraq and Afghanistan continues to be a challenge 
in balancing resources. 

As GAO reports, OBO has developed and is developing on-line training 
courses intended to assist maintenance staff at post in carrying out 
their duties. We are also working with a contractor on a proposal to 
further augment our training program. As is standard practice, the OBO 
Project Director on each NEC project will continue to provide system-
specific familiarization training for the LE Staff, in addition to 
basic training on mechanical and electrical principles and systems 
provided by the engineers on the OBO Project Director's staff. 

Rightsizing Projections Versus June 2010 Staffing: 
(Capital Security Projects Completed As OF CY-2010): 
									
Post: Panama[A]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Oct-03; 
U.S. Direct-Hire Positions: Project Completion Date: Jun-07; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 175; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 164; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -6.3%; 
All Positions: Original Rightsized Projections: 412; 
All Positions: Current	Positions in Chancery: 420; 
All Positions: Percent Difference (+/-): 1.9%. 

Post: Kigali; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Mar-05; 
U.S. Direct-Hire Positions: Project Completion Date: Jan-08; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 61; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 49; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -19.7%; 
All Positions: Original Rightsized Projections: 244; 
All Positions: Current	Positions in Chancery: 254; 
All Positions: Percent Difference (+/-): 4.1%. 

Post: Tbilisi; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Oct-05; 
U.S. Direct-Hire Positions: Project Completion Date: Jul-08; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 104; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 112; 
U.S. Direct-Hire Positions: Percent Difference (+/-): 7.7%; 
All Positions: Original Rightsized Projections: 668; 
All Positions: Current	Positions in Chancery: 641; 
All Positions: Percent Difference (+/-): -4.0%. 

Post: Brazzaville; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Mar-05; 
U.S. Direct-Hire Positions: Project Completion Date: Nov-08; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 11; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 15; 
U.S. Direct-Hire Positions: Percent Difference (+/-): 36.4%; 
All Positions: Original Rightsized Projections: 145; 
All Positions: Current	Positions in Chancery: 185; 
All Positions: Percent Difference (+/-): 27.6%. 

Post: Johannesburg; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Jan-05; 
U.S. Direct-Hire Positions: Project Completion Date: Dec-08; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 43; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 30; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -30.2%; 
All Positions: Original Rightsized Projections: 143; 
All Positions: Current	Positions in Chancery: 110; 
All Positions: Percent Difference (+/-): -23.1%. 

Post: Skopje; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Nov-05; 
U.S. Direct-Hire Positions: Project Completion Date: Mar-09; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 66; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 74; 
U.S. Direct-Hire Positions: Percent Difference (+/-): 12.1%; 
All Positions: Original Rightsized Projections: 304; 
All Positions: Current	Positions in Chancery: 324; 
All Positions: Percent Difference (+/-): 6.6%. 

Post: Ouagadougou[D]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Nov-06; 
U.S. Direct-Hire Positions: Project Completion Date: Jan-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 31; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 25; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -19.4%; 
All Positions: Original Rightsized Projections: 146; 
All Positions: Current	Positions in Chancery: 159; 
All Positions: Percent Difference (+/-): 8.9%. 

Post: Antananarivo[B]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: May-07; 
U.S. Direct-Hire Positions: Project Completion Date: Mar-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 49; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 40; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -18.4%; 
All Positions: Original Rightsized Projections: 253; 
All Positions: Current	Positions in Chancery: 249; 
All Positions: Percent Difference (+/-): -1.6%. 

Post: Khartoum[C]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Aug-05; 
U.S. Direct-Hire Positions: Project Completion Date: Mar-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 82; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 75; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -8.5%; 
All Positions: Original Rightsized Projections: 305; 
All Positions: Current	Positions in Chancery: 322; 
All Positions: Percent Difference (+/-): 5.0%. 

Post: Sarajevo[D]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Oct-06; 
U.S. Direct-Hire Positions: Project Completion Date: May-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 92; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 102; 
U.S. Direct-Hire Positions: Percent Difference (+/-): 10.9%; 
All Positions: Original Rightsized Projections: 331; 
All Positions: Current	Positions in Chancery: 346; 
All Positions: Percent Difference (+/-): 4.5%. 

Post: Mumbai[B]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Oct-06; 
U.S. Direct-Hire Positions: Project Completion Date: Jun-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 74; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 69; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -6.8%; 
All Positions: Original Rightsized Projections: 340; 
All Positions: Current	Positions in Chancery: 306; 
All Positions: Percent Difference (+/-): -10.0%. 

Post: Karachi[B]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Mar-06; 
U.S. Direct-Hire Positions: Project Completion Date: Jun-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 32; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 49; 
U.S. Direct-Hire Positions: Percent Difference (+/-): 53.1%; 	
All Positions: Original Rightsized Projections: 204; 
All Positions: Current	Positions in Chancery: 247; 
All Positions: Percent Difference (+/-): 21.1%. 

Post: Addis Ababa[D]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Jul-06; 
U.S. Direct-Hire Positions: Project Completion Date: Jul-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 153; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 147; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -3.9%; 	
All Positions: Original Rightsized Projections: 679; 
All Positions: Current	Positions in Chancery: 732; 
All Positions: Percent Difference (+/-): 7.8%. 

Post: Riga[B]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Feb-07; 
U.S. Direct-Hire Positions: Project Completion Date: Jul-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 50; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 39; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -22.0%; 	
All Positions: Original Rightsized Projections: 168; 
All Positions: Current	Positions in Chancery: 165; 
All Positions: Percent Difference (+/-): -1.8%. 

Post: Lusaka; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Jul-06; 
U.S. Direct-Hire Positions: Project Completion Date: Nov-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 76; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 94; 
U.S. Direct-Hire Positions: Percent Difference (+/-): 23.7%; 	
All Positions: Original Rightsized Projections: 359; 
All Positions: Current	Positions in Chancery: 373; 
All Positions: Percent Difference (+/-): 3.9%. 

Post: Suva[B]; 
U.S. Direct-Hire Positions: Rightsizing Review Date: Apr-05; 
U.S. Direct-Hire Positions: Project Completion Date: Nov-10; 
U.S. Direct-Hire Positions: Original Rightsized Projections: 20; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 22; 
U.S. Direct-Hire Positions: Percent Difference (+/-): 10.0%; 	
All Positions: Original Rightsized Projections: 78; 
All Positions: Current	Positions in Chancery: 110; 
All Positions: Percent Difference (+/-): 41.0%. 

Post: Totals:	
U.S. Direct-Hire Positions: Original Rightsized Projections: 1,119; 
U.S. Direct-Hire Positions: Current Positions in Chancery: 1,106; 
U.S. Direct-Hire Positions: Percent Difference (+/-): -1.2%; 
All Positions: Original Rightsized Projections: 4,779; 
All Positions: Current	Positions in Chancery: 4,943; 
All Positions: Percent Difference (+/-): 3.4%. 

Projected completion later in CY-2010, current staffing includes OBO 
construction managers (Data source: original rightsizing reviews, Jun 
2010 post profiles data; rev. 6-23-2010) 

[A] Rightsizing review clone by WID before current rightsizing program 
began. 

[B] Temporary OBO construction teams not counted. 

[C] Government employee guard force positions not counted (other 
missions have contract guards.) 

[D] Temporary OBO construction teams and guard positions not counted. 

The above figures do not include Peace Corps, whose offices are never 
co-located in the chancery. 

Standard deviation (posts with staffing overages):	
U.S. Direct-Hire Positions: 17.1%; 
All Positions: 12.5%. 

Standard deviation (all posts):	
U.S. Direct-Hire Positions: 22.8%; 
All Positions: 14.8%. 

Footnotes: 

[1] Embassy Construction: State Has Made Progress Constructing New 
Embassies, but Better Planning Is Needed for Operations and 
Maintenance Requirements; GAO-06-641, June 30, 2006. 

[2] Federal Courthouse Construction: Preliminary Results Show Be 
Planning, Oversight, and Courtroom Sharing Could Help Control Future 
Costs; GAO-10-753T, May 25, 2010. 

[3] 6 FAH-5 H-405.1-11 defines BOE as "Expenses incident to occupying 
buildings and grounds, but not including improvements. repair or 
maintenance costs beyond those minor operating system repairs and 
preventive maintenance identified in the ICASS Handbook." 

[4] To obtain a total post operations and maintenance (O&M) cost, 
additional maintenance labor costs, utility costs, and maintenance 
spare parts costs must be added to the O&M cost estimates listed for 
all posts that have GO and LTL properties outside the NEC/NCC walls. 

The following are GAO's comments to the Department of State's letter 
dated June 28, 2010. 

GAO comments: 

1. We do not dispute that NEC maintenance costs may be in line with 
those for similar facilities as suggested by OBO's analysis. Rather, 
our intent in comparing operations and maintenance costs of NECs to 
those at the facilities they replaced is to show that because of their 
larger size and the increased complexity of building systems, among 
other factors, NEC operations and maintenance costs are higher. Our 
analysis of utility costs indicates, for example, that NECs have a 
comparatively higher utility demand than previous facilities and pay 
correspondingly higher amounts for utilities. As the higher costs to 
operate and maintain NECs present long-term budget implications, we 
believe it is important for State to continue its efforts, as it has 
begun to do with the recent development of its Long Range Overseas 
Maintenance Plan (LROMP), to comprehensively plan for the long-term 
resource requirements necessary for protecting its investment in NECs. 

2. We acknowledge that NECs provide an improved level of safety 
compared to the facilities they replaced. However, the intent of our 
discussion is to convey that safety concerns, particularly concerning 
the operation of fire protection systems, were apparent at some of the 
earlier NECs as a result of deficiencies with the commissioning 
process. For example, OBO's Office of Fire Protection reported that 
some early NECs were occupied without the correction of critical 
deficiencies affecting operation of their fire protection systems, a 
situation that we believe would not have occurred if commissioning had 
been properly conducted. Because of the paramount importance of 
safety, we believe it is necessary to report on issues that 
potentially result in reduced safety levels. 

3. We support State's intention to place greater emphasis on proactive 
analysis and objective comparison. State concludes that its analysis 
of the 16 NECs planned since the inception of M/PRI, many of which are 
still under construction, indicates that "the problem of inadequate 
office space is gradually being resolved." However, State's analysis 
does not clearly demonstrate whether these NECs match the space needs 
of overseas posts. For example, State's analysis includes all 
positions at overseas posts and does not distinguish between those 
positions that require office space in the NEC (referred to in our 
report as "desk" positions) and those, such as warehouse or 
maintenance personnel, that do not. While such an analysis could be 
appropriate for determining whether the rightsizing process is 
resulting in greater accuracy projecting overall staffing levels, it 
is does not provide a clear picture of whether the amount of office 
space that was planned for the NECs is adequate for current office 
space needs. 

In addition to having concerns that State's analysis may not provide a 
clear assessment of space requirements, we also believe that the 
results of State's analysis do not indicate that NECs planned under 
rightsizing will face fewer space challenges than their predecessors. 
For example, State's analysis of all positions shows that 7 of the 16 
(44 percent) NECs planned under rightsizing have at least 5 percent 
more staff than were included in the initial projections, even though 
none of the NECs planned under rightsizing is more than 3 years old 
and many are still under construction. Our analysis of 44 completed 
NECs showed that over half have current desk space needs that exceed 
the amount of desk space constructed by at least 5 percent. 
Additionally, we found that 4 of the 6 NECs completed since the 
inception of M/PRI had current staffing levels that exceeded 
constructed desk space by more than 20 percent. We believe that both 
our analysis and State's analysis support our finding that many NECs 
have already run out of desk space and, therefore, the planning 
process might benefit from additional analysis of the relationship 
between post-specific characteristics and staffing growth. 

4. We acknowledge OBO's intention to revise the growth factor formula, 
which would provide additional space in NECs. However, this does not 
address our concern that OBO has not provided any analytical basis to 
demonstrate that a growth factor of 10 percent, applied uniformly 
across all projects, is appropriate. 

5. We support State's initial effort in taking action to identify and 
prioritize its maintenance needs as documented in its first edition of 
the LROMP. Establishing a timeline concurrent with availability of 
funds would provide greater transparency for projects to be initiated 
during a specific funding period. However, we also believe State 
should consider outlining notional implementation time frames for 
requirements identified over each of the future budget years covered 
by the LROMP, including those years for which future funding is not 
certain. By identifying notional time frames, based on forecasted 
budget scenarios and not solely on available funds, we believe State 
will be better able to demonstrate whether the plan can effectively be 
resourced by future anticipated budget scenarios or whether 
maintenance requirements potentially exceed likely funding scenarios. 
We believe such an approach would strengthen State's efforts to show 
how timely investments in maintenance can protect the multibillion 
dollar investment State is making in constructing NECs. 

6. We support OBO's efforts in developing first-year operating cost 
estimates for NECs when they open. However, we still maintain State 
needs to develop an assessment of future operating costs that is 
included in the LROMP. A plan that outlines future operating costs is 
particularly important since, as our analysis shows, the operating 
costs at NEC posts have clearly increased relative to the facilities 
they replaced. By developing estimates of future years' operating 
costs and combining those with estimates of future maintenance costs 
that State has already outlined in its LROMP, we believe State will 
have a more complete assessment of the financial resources that State 
and other contributing agencies will need in future budget years to 
operate and maintain overseas facilities. 

7. We maintain that State needs a human resources plan for NEC 
facilities maintenance staff, regardless of the funding mechanism. 
Such a plan, that addresses cost implications for hiring and training 
necessary staff, could assist State in better identifying the 
necessary financial resources and planning to address resource 
limitations. 

[End of section] 

Appendix III: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Jess T. Ford, Director, International Affairs and Trade, (202) 512-
4268 or fordj@gao.gov: 

Terrell G. Dorn, Director, Physical Infrastructure, (202) 512-6923 or 
dornt@gao.gov. 

Staff Acknowledgments: 

In addition to the individuals named above, Leslie Holen, Assistant 
Director; Michael Armes, Assistant Director; John Bauckman; Sam 
Bernet; Raj Chitikila; Kalvin Jenhung Lo; Kara Marshall; Christina 
Werth; and Richard Winsor made key contributions to this report. In 
addition, Joe Carney, Martin de Alteriis, Mark Dowling, and Faye 
Morrison provided technical or legal assistance. 

[End of section] 

Footnotes: 

[1] H.R. 3427 (106th Cong.), Title VI (H.R. 3427 was incorporated by 
cross-reference in the conference report to H.R.3194 [Div. B]. H.R. 
3194, the Fiscal Year 2000 Consolidated Appropriations bill, became 
Public Law 106-113 on Nov. 29, 1999). State elaborates on these 
requirements in the U.S. Department of State Foreign Affairs Handbook, 
12 FAH-5. 

[2] Agencies may request a waiver to the collocation requirement if 
security conditions permit and it is determined that U.S. national 
interests are best served by locating personnel outside new facilities. 

[3] Within the Department of State, Operations and Maintenance (O&M) 
falls under two main categories of funding: (1) Building Operating 
Expenses (BOE) and (2) Maintenance and Repair (M&R). The term 
"operations and maintenance" is used to describe both aspects of 
running a facility. BOE (i.e., operations) includes costs associated 
with occupying a facility to include utilities, janitorial services, 
trash collection, grounds care, the labor costs of locally employed 
maintenance staff, and maintenance service contracts (i.e., Building 
Maintenance Expenses) for building systems (e.g., elevators, 
generators, etc.). BOE costs, for facilities shared by State and other 
agencies, are funded through posts' International Cooperative 
Administrative Support Services (ICASS) system. 

[4] Maintenance and Repair (M&R), which is funded by OBO, includes 
those maintenance activities that a landlord would take to maintain a 
property in acceptable condition. M&R funds services and materials for 
items of a recurring nature such as painting and minor repairs to 
building systems. 

[5] GAO, Embassy Construction: State Has Made Progress Constructing 
New Embassies, but Better Planning Is Needed for Operations and 
Maintenance Requirements, [hyperlink, 
http://www.gao.gov/products/GAO-06-641] (Washington, D.C.: June 30, 
2006). 

[6] The term "NEC" refers to all new facilities--including new embassy 
compounds, new consulate compounds, new office buildings, and newly 
acquired buildings--constructed for the purposes of locating all U.S. 
government employees at a new and single location. Further, for the 
purposes of this report, the term "post" refers to the entirety of the 
U.S. government's operations in an overseas location. 

[7] [hyperlink, http://www.gao.gov/products/GAO-06-641]. 

[8] The design-build project delivery method reduces project cycle 
time by combining design and construction in a single contract award 
and allows contractors to begin construction before the building 
design is complete. 

[9] In 2002, OBO implemented the SED to expedite the planning, design, 
and construction of NECs. The SED is a template that standardizes the 
basic plans for the structural, spatial, safety, and security 
requirements for each NEC. Since 2002, there have been three primary 
SED classes--small, medium, and large--based on the size and cost of 
the facility. Each size has a predefined project schedule and 
duration. In 2004, State introduced a fourth class of SED, called 
Extra Large or Special SEDs, for construction that generally exceeds 
the size and cost of large SEDs. Finally, in 2007, State introduced 
the Standard Secure Mini Compound, which is generally smaller and less 
costly than a small SED. See GAO, Embassy Construction: Additional 
Actions Are Needed to Address Contractor Participation, [hyperlink, 
http://www.gao.gov/products/GAO-09-48] (Washington, D.C.: Jan. 16, 
2009) for additional information on SED. 

[10] GAO, Embassy Construction: Process for Determining Staffing 
Requirements Needs Improvement, [hyperlink, 
http://www.gao.gov/products/GAO-03-411] (Washington, D.C.: Apr. 7, 
2003). 

[11] [hyperlink, http://www.gao.gov/products/GAO-06-641]. 

[12] NEC windows are nonoperable and thus cannot be opened to allow 
fresh air in, and the security requirements to filter and pressurize 
the air within an NEC effectively creates a sealed building. 

[13] U.S. State Department, Office of the Inspector General, Report of 
Inspection: Bureau of Overseas Buildings Operations, Report Number: 
ISP-I-08-34 (Washington, D.C., August 2008). 

[14] State plans NECs based on projections of the number of "desk" 
positions--or positions that will require an assigned office or 
workspace--that will occupy the facility. 

[15] "Current staffing levels" refers specifically to authorized 
positions at overseas posts that post management indicated required a 
desk on the compound in 2009 staffing data. There may be a discrepancy 
between the number of positions that are authorized and the number of 
positions that are actually filled; however, State's staffing data do 
not provide sufficient detail for us to distinguish between the two. 
Some positions at overseas posts, such as guards or some facilities 
maintenance positions, do not require a desk and, therefore, are not 
included in our analysis of current staffing levels. 

[16] The 11 posts with a difference of more than 50 desks are Abu 
Dhabi, United Arab Emirates; Abuja, Nigeria; Beijing, China; Berlin, 
Germany; Dar es Salaam, Tanzania; Dushanbe, Tajikistan; Frankfurt, 
Germany; Nairobi, Kenya; Skopje, Macedonia; Tblisi, Georgia; and 
Tunis, Tunisia. 

[17] Growth space is not included in our analysis of as-built desk 
space. 

[18] Administrative support services are primarily provided through 
the International Cooperative Administrative Support Services (ICASS) 
system. ICASS functions are most commonly covered by State and, 
therefore, most ICASS positions are listed under State. As staffing 
levels at a post increase, there is often a corresponding increase in 
ICASS positions, which accounts for some of the increase in State 
positions. 

[19] The precise structure of a mission is determined by the Chief of 
Mission through the National Security Decision Directive 38 (NSDD-38) 
process, which provides authority for the Chief of Mission to 
determine the size, composition, or mandate of personnel operating at 
the mission. 

[20] OBO officials noted that OBO received the amount of money it 
requested for the facility. 

[21] As a result of these space reductions, some staff are located off-
site in Berlin. Post management noted that the most cost-effective 
option for locating staff off-site--at an estimated cost of $25 
million--involved purchasing and renovating an office facility the 
post had formerly leased. 

[22] While OBO has not conducted a formal study comparing the costs of 
initially building a larger space with building an annex at a later 
date, OBO officials noted it is generally cheaper to increase the size 
of a single building than build a separate building because of the 
fixed costs that come with each building. 

[23] In Frankfurt, Germany, State rehabilitated an old military 
hospital for use as the new Consulate, rather than construct a new 
facility. OBO officials noted that State undertook the initial 
renovation project in Frankfurt with the knowledge that additional 
work would be required following the post's move-in. 

[24] Some other U.S. government agencies, such as the National 
Institutes of Health (NIH) and the Naval Facilities Engineering 
Command (NAVFAC), require post-occupancy evaluations for all 
facilities above a certain cost threshold--$10 million for NIH and $5 
million for NAVFAC. Additionally, the proposed Embassy Design and 
Security Act, (S. 3210, introduced in the Senate on April 15, 2010), 
would require that State conduct post-occupancy evaluations of each 
completed facility. 

[25] Commissioning is a process of assuring by testing, verification, 
and documentation that systems perform according to the design and the 
building owner's operational needs, including the preparatory training 
of facilities personnel. Commissioning is generally performed by a 
third party. If commissioning is improperly performed, the owner 
(i.e., State) is at risk of taking possession of a facility with 
building systems that may not be installed correctly, are defective, 
or are not integrated to operate optimally and efficiently. In 
addition, essential training and documentation on the systems might 
not be provided to operations and maintenance staff. In such cases of 
improperly performed commissioning, energy efficiency is reduced and 
the performance of the facility fails to meet owner and occupant 
expectations. 

[26] Building automation systems (BAS), also known as energy 
management control systems, provide centralized control--through the 
use of BAS software and hardware (e.g., computer, modems, sensors, 
controllers, and printers)--to monitor and adjust building systems 
(e.g., temperature settings and schedules for running equipment)--such 
as a building's cooling systems. A BAS is intended to optimize the 
integrated performance of the individual equipment components that 
comprise the system. Data can be recorded so they can be analyzed. The 
Department of Energy's Federal Energy Management Program indicates 
that the objective of a BAS is to achieve an optimal level of occupant 
comfort while minimizing energy use. 

[27] The U.S. Green Building Council's Leadership in Energy and 
Environmental Design green building rating system defines sustainable 
features for buildings and includes a set of performance standards 
that can be used to certify the design and construction of buildings. 
By meeting the standards during facility design and construction, 
builders can earn credits and become certified in accordance with an 
established four-level scale--certified, silver, gold, and platinum. 

[28] Projects registered include both completed projects and projects 
where construction has not yet been completed. 

[29] For projects completed in 2007 or 2008, we compared operations 
and maintenance costs for the last full year of operation in the old 
facility with NEC operations and maintenance costs for fiscal year 
2009. 

[30] The total reported is the aggregate nominal cost increase 
associated with operating and maintaining NECs and is not adjusted for 
inflation due to the short time frames involved. OBO officials report 
that the maintenance of older facilities may not have been fully 
funded at appropriate levels and that there might not have been such a 
large cost increase with the NECs if the old facilities had been 
properly maintained 

[31] U.S. State Department, Benchmarking: Operations and Maintenance 
Costs (Sept. 1, 2009). The four posts identified are Beijing, China; 
Belmopan, Belize; Bridgetown, Barbados; and Panama City, Panama. 
Beijing's cost did not fully reflect 1 full year of occupancy as the 
NEC did not open until August 2008. 

[32] State's LROMP also outlines a "legacy maintenance strategy" for 
maintaining older facilities that will not be replaced by an NEC in 
the near future. 

[33] BME is a category of cost within Building Operating Expenses 
(BOE) that is used to capture costs attributable to occupying 
buildings and grounds. BOE includes costs for facilities maintenance 
staff, custodial and trash services, fuel, utilities, applicable 
government assessments and taxes, insurance on real property, and 
service contracts on building systems (i.e., BME). 

[34] One member of OBO's Industry Advisory Panel suggested State 
consider examining the sequencing of projects relative to other 
requested projects in a given facility, as it could affect when a 
building owner (e.g., State) funds and executes projects. For example, 
he stated that an owner may want to fund projects to replace windows 
and lighting first before upgrading the building's mechanical plant; 
otherwise, the owner may overdesign the mechanical components being 
replaced by failing to have considered performance efficiencies 
resulting in reduced heating and cooling needs that would be gained by 
replacing the other two systems. 

[35] Executive Order 13327, Federal Real Property Asset Management 
(signed in 2004) established a Federal Real Property Council (FRPC) 
that requires agencies to report the annual operating costs, among 
other data, for their real property assets. In 2008, State's Inspector 
General reported that the Department's reporting of annual operating 
costs to the FRPC was inaccurate. See ISP-08-34. 

[36] State's 2009 benchmarking study examined operating and 
maintenance costs at overseas posts (both NEC and non-NEC posts); 
however, the study looked at just over 160 posts (out of over 240 
posts) due, in part, to data on costs not being reported by some posts. 

[37] OBO prepares first-year operating cost estimates for individual 
NECs based on when an NEC is expected to be completed. Those operating 
cost estimates are provided to posts and also reported in State's Long-
Range Overseas Buildings Plan. In its 2008 review of OBO, State's IG 
reported that 12 of 17 posts (that took occupancy of an NEC after 
January 2005) stated that either no estimates were provided, or if 
they were, the estimates were not accurate. See ISP-08-34. 

[38] The funding responsibilities for the NEC operating costs (i.e., 
BOE) at posts are not an OBO responsibility but rather are shared 
costs paid by State's regional bureaus, diplomatic security and 
consular programs, and other government agencies at post through 
ICASS. OBO staff characterized the ICASS system as providing each 
agency at post with a vote, which may make it difficult for OBO and 
the facilities managers to convince the ICASS council to approve the 
funding for additional maintenance staff. 

[39] ISP-I-08-34. 

[40] ISP-08-34. 

[41] The DOE, Federal Energy Management Program (FEMP) mission is to 
facilitate the federal government's implementation of sound, cost- 
effective energy management and investment practices to enhance the 
nation's energy security and environmental stewardship. DOE/FEMP 
prepared: Commissioning for Federal Facilities - A Practical Guide to 
Building Commissioning, Recommissioning, Retro-Commissioning, and 
Continuous Commissioning (Washington, D.C.). 

[42] In previous GAO work examining embassy construction, we found 
that 7 of 15 State construction contractors reported to us that 
getting a timely response from OBO on final commissioning approvals 
was a major or moderate challenge. See [hyperlink, 
http://www.gao.gov/products/GAO-09-48]. 

[43] OBO officials indicate OBO's construction contracts did call for 
an "independent" agent to do commissioning; however, because those 
commissioning services were obtained by the construction contractor 
under contract to OBO, posts felt those agents were not independent of 
the construction contractors. 

[44] The "transfer" of an NEC is commonly referred to in OBO guidance 
as the "turnover" of the NEC. 

[45] DOE reports computerized maintenance management systems (CMMS) 
automate many functions performed by facilities staff, such as 
maintenance work order generation and tracking, inventory control, 
document storage, warranty management, maintenance management, and 
tracking costs. DOE reports that benefits of a CMMS include achieving 
a higher level of maintenance, more efficient use of staff, and 
maintaining optimal equipment performance to include reducing downtime 
and extending equipment life. DOE reports that one common pitfall 
associated with CMMS is inadequate training of staff on the CMMS. 

[46] A punch list identifies tasks, usually minor, to be completed by 
the construction contractor at the end of a project. 

[47] Building Commissioning Association, Best Practices in 
Commissioning Existing Buildings, August 18, 2008. 

[48] State officials report they anticipate requesting funding for 
recommissioning NECs in their fiscal year 2012 budget request. OBO 
officials noted that such a plan would require approval by State and 
the Office of Management and Budget. 

[49] A chiller is a refrigeration system that cools water similar to 
an air conditioner. Once cooled, chilled water has a variety of 
applications such as cooling the air within a facility. Two to three 
chillers, associated piping, cooling towers (if installed), and water 
pumps make up a typical NEC chiller plant. 

[50] Two common methods used to provide air conditioning are "water- 
cooled" chillers that use water towers, recirculated water, and 
compressors to condense refrigerant fluid, and "air-cooled" chillers 
that use compressors and fans to draw air over finned coils to 
condense refrigerant. 

[51] Post officials noted that while the situation has improved and 
alarms have not been triggered recently, the fire panel indicates 
there is still a problem with the system. 

[52] OBO officials reported that both Sofia (fiscal year 2001 
contract) and Yaoundé (fiscal year 2005 contract) were two of State's 
earlier projects. 

[53] The main fire alarm control panels are typically installed within 
NEC's main security post and subordinate panels are installed in other 
locations like the warehouse. Trouble lights could signify a 
relatively minor problem with the fire alarm system, like a dirty 
smoke detector, or a more serious problem such as the loss of power to 
a smoke detector that may prevent it from working. Supervisory lights 
are generally more serious indicators of a problem within the fire 
suppression system such as the fire pump running or a closed sprinkler 
valve. An audible alarm sounding at the panel gives post personnel 
another indication that there is a condition within the system that 
should be examined. 

[54] Some doors and windows have been replaced under warranty at 
contractors' expense, while others have been replaced via follow-on 
projects at government expense. 

[55] Estimated costs are based on data within OBO's Long-Range 
Overseas Maintenance Plan, for fiscal years 2010 to 2015. 

[56] In 2006, the security requirements for Marine Security Guard 
Quarters were strengthened. In 2007, the security requirements for 
Compound Access Control facilities were strengthened. 

[57] OBO officials report that they estimate the average cost for 
hiring an additional overseas facility manager is approximately 
$330,000 annually. Costs generally include salary, benefits, overseas 
housing costs, travel and moving expenses, training, and education 
allowances for dependents. Based on OBO's stated goal of hiring 20 
additional facility managers in fiscal year 2009, that added cost 
would amount to $6.6 million annually for just those additional U.S. 
facility managers. Costs for State's overseas facility managers are 
directly funded by OBO and not by posts or ICASS. 

[58] ISP-I-08-34. 

[59] Costs for locally employed facilities staff are funded through 
ICASS as a shared cost paid by State and other federal agencies. 

[60] State reports that the facility manager courses are available to 
locally employed staff on a space available basis but that the first 
priority is newly hired facility managers. According to a State 
official, the Foreign Service Institute will initiate additional 
sessions if the number of waitlisted requests justifies the need. 
However, funding to pay for the costs of travel and training of posts' 
local staff may still need to be identified. 

[61] DOE reports that building automation system operators must be 
fully trained on the system's capabilities in order to optimize and 
realize energy efficiency of the new system and that refresher 
training is needed. 

[62] In May 2010, State officials reported that development of online 
facilities training for work order management and environmental 
security protection systems was completed and is now available to 
overseas posts staff. 

[63] State's International Maintenance Assistance Program and its 
recently created African Regional Maintenance Program (ARMP) dispatch 
maintenance contractors to support overseas posts maintenance needs. 
ARMP is uniquely focused on support for 15 NEC posts in Africa. 

[64] In this report, we use the term NEC to universally include NEC, 
New Consulate Compound, New Office Building, and Newly Acquired 
Building projects. 

[65] The following posts that met our definition of an NEC were 
excluded from our review: 1) Posts, such as Doha, Qatar, where 
construction began and/or funding was provided before 1999; 2) 
Embassies Baghdad, Iraq and Kabul, Afghanistan, where operations are 
not reflective of normalized post operations and/or funding was 
obtained entirely through supplemental appropriations; 3) Facilities 
referred to by OBO as Standard Secure Mini Compounds (SSMC) or unique, 
small compounds that were precursors to the SSMC design (Koror, Palau 
and Kolonia, Federated States of Micronesia); and 4) NECs in which the 
post moved into the new facilities after September 30, 2009 
(Ouagadougou, Burkina Faso; Antananarivo, Madagascar, and Khartoum, 
Sudan). Additionally, we excluded posts in Lima, Peru; Athens, Greece; 
Bogota, Columbia; and Tirana, Albania where annexes were built on or 
adjacent to facilities built prior to 1999; and an Interim Office 
Building in Dili, Timor-Leste. 

[66] United States Department of State and the Broadcasting Board of 
Governors Office of Inspector General, Report of Inspection: Bureau of 
Overseas Buildings Operations, ISP-I-08-34, (Washington, D.C., August 
2008). 

[67] Project type refers to the type of design and construction 
contracts, such as design-bid-build or design-build, which may make 
use of a standard embassy design. 

[68] OBO officials report that the maintenance of older facilities may 
not have been fully funded at appropriate levels and that there might 
not have been such a large cost increase with the NECs if the old 
facilities had been properly maintained. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: