This is the accessible text file for GAO report number GAO-10-417 
entitled 'Federal Courthouse Construction: Better Planning, Oversight, 
and Courtroom Sharing Needed to Address Future Costs' which was 
released on June 22, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 
GAO: 

June 2010: 

Federal Courthouse Construction: 

Better Planning, Oversight, and Courtroom Sharing Needed to Address 
Future Costs: 

GAO-10-417: 

GAO Highlights: 

Highlights of GAO-10-417, a report to congressional committees. 

Why GAO Did This Study: 

The federal judiciary and the General Services Administration (GSA) 
are in the midst of a multibillion-dollar courthouse construction 
initiative, which has since faced rising construction costs. As 
requested, for 33 federal courthouses completed since 2000, GAO 
examined (1) whether they contain extra space and any costs related to 
it; (2) how their actual size compares with the congressionally 
authorized size; (3) how their space based on the judiciary’s 10-year 
estimates of judges compares with the actual number of judges; and (4) 
whether the level of courtroom sharing supported by the judiciary's 
data could have changed the amount of space needed in these 
courthouses. GAO analyzed courthouse planning and use data, visited 
courthouses, modeled courtroom sharing scenarios, and interviewed 
judges, GSA officials, and other experts. 

What GAO Found: 

The 33 federal courthouses completed since 2000 include 3.56 million 
square feet of extra space consisting of space that was constructed 
(1) above the congressionally authorized size, (2) due to 
overestimating the number of judges the courthouses would have, and 
(3) without planning for courtroom sharing among judges. Overall, this 
space represents about 9 average-sized courthouses. The estimated cost 
to construct this extra space, when adjusted to 2010 dollars, is $835 
million, and the annual cost to rent, operate and maintain it is $51 
million. 

Twenty-seven of the 33 courthouses completed since 2000 exceed their 
congressionally authorized size by a total of 1.7 million square feet. 
Fifteen exceed their congressionally authorized size by more than 10 
percent, and 12 of these 15 also had total project costs that exceeded 
the estimates provided to congressional committees. However, there is 
no requirement to notify congressional committees about size overages. 
A lack of oversight by GSA, including not ensuring its space 
measurement policies were understood and followed and a lack of focus 
on building courthouses within the congressionally authorized size, 
contributed to these size overages. 

For 23 of 28 courthouses whose space planning occurred at least 10 
years ago, the judiciary overestimated the number of judges who would 
be located in them, causing them to be larger and costlier than 
necessary. Overall, the judiciary has 119, or approximately 26 
percent, fewer judges than the 461 it estimated it would have. This 
leaves the 23 courthouses with extra courtrooms and chamber suites 
that, together, total approximately 887,000 square feet of extra 
space. A variety of factors contributed to the judiciary’s 
overestimates, including inaccurate caseload projections, difficulties 
in projecting when judges would take senior status, and long-standing 
difficulties in obtaining new authorizations and filling vacancies. 
However, the degree to which inaccurate caseload projections 
contributed to inaccurate judge estimates cannot be measured because 
the judiciary did not retain the historic caseload projections used in 
planning the courthouses. 

Using the judiciary’s data, GAO designed a model for courtroom 
sharing, which shows that there is enough unscheduled time for 
substantial courtroom sharing. Sharing could have reduced the number 
of courtrooms needed in courthouses built since 2000 by 126 courtrooms—
about 40 percent of the total number—covering about 946,000 square 
feet of extra space. Some judges GAO consulted raised potential 
challenges to courtroom sharing, such as uncertainty about courtroom 
availability, but others indicated they overcame those challenges when 
necessary, and no trials were postponed. The judiciary has adopted 
policies for future sharing for senior and magistrate judges, but 
GAO’s analysis shows that additional sharing opportunities are 
available. For example, GAO’s courtroom sharing model shows that there 
is sufficient unscheduled time for 3 district judges to share 2 
courtrooms and 3 senior judges to share 1 courtroom. 

What GAO Recommends: 

Among other things, GSA should: (1) ensure that courthouses are within 
their authorized size or notify congressional committees; and the 
Judicial Conference of the United States should: (2) retain caseload 
projections to improve the accuracy of its 10-year judge planning; and 
(3) establish and use courtroom sharing policies based on scheduling 
and use data. GSA and the judiciary agreed with most of the 
recommendations, but expressed concerns with GAO’s methodology and key 
findings. GAO believes these to be sound, as explained in the report. 

View [hyperlink, http://www.gao.gov/products/GAO-10-417] or key 
components. For more information, contact Mark L. Goldstein at (202) 
512-2834 or goldsteinm@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

Extra Space in Courthouses Cost an Estimated $835 Million in Constant 
2010 Dollars to Construct and $51 Million Annually to Rent, Operate, 
and Maintain: 

Most Courthouses Exceed Congressionally Authorized Size Due to a Lack 
of Oversight by GSA: 

Estimated Space Needs Exceeded Actual Space Needs, Resulting in 
Courthouses That Were Larger than Necessary: 

Low Levels of Use Show That Judges Could Share Courtrooms, Reducing 
the Need for Future Courtrooms by More Than One-Third: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: Comments from the U.S. General Services Administration:
GAO Comments: 

Appendix III: Comments from the Federal Judiciary:
GAO Comments: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1:The Different Types of Federal Judges: 

Table 2: Estimated Construction and Annual Operations and Maintenance 
Costs of Building Extra Space in Seven Case Study Courthouses: 

Table 3: Square Footage Over Authorized and Efficiency of Seven 
Courthouses: 

Table 4: Comparison of 10-Year Judge Estimates and the Actual Number 
of Judges After 10 Years or More for Case Study Courthouse Locations 
and Related Space Consequences: 

Table 5:Dedicated Courtroom-Sharing Possibilities Based on GAO Model: 

Table 6: District, Senior, and Magistrate Judge Courtroom Sharing That 
Could Occur in Selected Courthouses Based on the Judiciary's Data: 

Table 7: The 33 Courthouses Completed from 2000 through March 2010: 

Table 8: Courtroom Sharing for District Judges Based on Centralized 
Sharing: 

Table 9:Courtroom Sharing for Senior District Judges Based on 
Centralized Sharing: 

Table 10: Courtroom Sharing for Magistrate Judges Based on Centralized 
Sharing: 

Table 11: Courtroom Sharing for Courthouses Using Nationwide Ratio of 
District Judges to Senior and Magistrate Judges Based on Centralized 
Sharing: 

Figures: 

Figure 1: Extra Federal Courthouse Space Constructed Since 2000 and 
the Estimated Construction and Annual Costs: 

Figure 2: Extra Federal Courthouse Space Constructed Since 2000 Due to 
Exceeding Congressionally Authorized Square Footage: 

Figure 3: Percentage Difference in Size of Federal Courthouses as 
Congressionally Authorized and as Built: 

Figure 4: Example of a Mechanical Room on a Courtroom Floor of the 
Eagleton U.S. Courthouse in St. Louis, Missouri, and on the Top Level 
of the Coyle U.S. Courthouse, in Fresno, California: 

Figure 5: D'Amato U.S. Courthouse Atrium Map and Pictures: 

Figure 6: Atrium in Ferguson, Jr., U.S. Courthouse in Miami, Florida, 
and Entry Space in DeConcini U.S. Courthouse in Tucson, Arizona: 

Figure 7: Extra Federal Courthouse Space Constructed Since 2000 Due to 
Overestimating the Number of Judges: 

Figure 8: Unassigned Chamber Suites in the Coyle Courthouse in Fresno, 
California: 

Figure 9: Total District Court Case Filings for the Eastern District 
of Missouri: 

Figure 10: Unassigned District Courtroom and Chamber in the Ferguson 
Courthouse, Miami, Florida: 

Figure 11: Extra Federal Courthouse Space Constructed Since 2000 Due 
to Judges Not Sharing Courtrooms: 

Figure 12: Representation of an Average 8 Hour Day for a Courtroom by 
Type of Judge as of July 2007: 

Abbreviations: 

ADR: Alternative Dispute Resolution: 

BOMA: Building Owners and Managers Association: 

Design Guide: The U.S. Courts Design Guide: 

FJC: Federal Judicial Center: 

GSA: General Services Administration: 

judiciary: federal judiciary: 

Marshals: U.S. Marshals: 

OMB: Office of Management and Budget: 

[End of section] 

United States Government Accountability Office:
Washington, DC 20548: 

June 21, 2010: 

The Honorable James L. Oberstar: 
Chairman: 
The Honorable John L. Mica: 
Ranking Member: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

The Honorable Eleanor Holmes Norton: 
Chair: 
The Honorable Mario Diaz-Balart: 
Ranking Member: 
Subcommittee on Economic Development, Public Buildings, and Emergency 
Management: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

Since the early 1990s, the General Services Administration (GSA) and 
the federal judiciary (judiciary) have undertaken a multibillion-
dollar courthouse construction initiative that has resulted in 66 new 
courthouses or annexes,[Footnote 1] with 29 additional projects in 
various stages of development. However, rising costs and other federal 
budget priorities threaten to stall the initiative. In 2008, for 
example, we found that increases in construction cost estimates for 
the Los Angeles, California, courthouse had led to an impasse that has 
yet to be resolved.[Footnote 2] Over the last 15 years, we have raised 
concerns about GSA's and the judiciary's process for planning new 
courthouses, including concerns over limited controls and oversight 
over courthouse construction costs.[Footnote 3] We have also raised 
questions about the accuracy of the judiciary's long-term caseload 
projections--projections used to estimate the number of judges who 
will be located in new courthouses in 10 years, often under a policy 
that provided one courtroom for each estimated judge. Furthermore, we 
and some members of Congress have raised concerns that some courtrooms 
are underutilized; that more courtrooms than needed have been, and 
continue to be, constructed; and that increased courtroom sharing by 
judges--an option that the judiciary studied for district courtrooms 
in 2008[Footnote 4]--could reduce the number of new courtrooms needed 
and therefore the size and cost of new courthouse projects. As a 
result of this study, the judiciary recently established some new 
policies that incorporate more sharing of courtrooms for senior judges 
[Footnote 5] and magistrate judges. 

To assist you in your oversight of the courthouse construction 
initiative, you asked us to review courthouse planning and 
construction, including the initiative's management and costs. 
Accordingly, for 33 federal courthouses completed since 2000, we 
examined (1) whether the courthouses contain extra space and any costs 
related to it, (2) how the actual size of the courthouses compares 
with the congressionally authorized size, (3) how courthouse space 
based on the judiciary's 10-year estimates of judges compares with the 
actual number of judges; and (4) whether the level of courtroom 
sharing supported by data from the judiciary's 2008 study of district 
courtroom sharing could have changed the amount of space needed in 
these courthouses. To address these objectives, we analyzed planning, 
construction, and budget documents associated with all 33 federal 
courthouses or major annexes completed from 2000 through March 2010. 
For the names and locations of these courthouses, see table 7 in 
appendix I. In addition, we selected seven of the federal courthouses 
in our scope to analyze more closely as case studies: the Bryant U.S. 
Courthouse Annex in Washington, D.C.; the Coyle U.S. Courthouse in 
Fresno, California; the D'Amato U.S. Courthouse in Central Islip, New 
York; the DeConcini U.S. Courthouse in Tucson, Arizona; the Eagleton 
U.S. Courthouse in St. Louis, Missouri; the Ferguson U.S. Courthouse 
in Miami, Florida; and the Limbaugh, Sr., U.S. Courthouse in Cape 
Girardeau, Missouri. We chose these courthouses because they represent 
a wide distribution of sizes, dates of completion, and locations and 
their gross square footage exceeds their congressionally authorized 
size. 

To estimate the cost of any extra courthouse space, we added together 
any extra square footage due to an increase in the courthouse's gross 
square footage over the congressional authorization, inaccurate 10-
year judge estimates, and less sharing than is supported by the 
judiciary's data, as described below in the methodology for the other 
objectives. We then calculated the extra cost to construct, and rent 
or operate and maintain this space based on the actual construction 
costs and the fiscal year 2009 rent and operations and maintenance 
costs. We developed this methodology after discussing and validating 
the approach with outside construction experts. To determine how the 
size of courthouses compares with the authorized size, we compared 
each courthouse's congressionally authorized gross square footage 
[Footnote 6] with the gross square footage of the courthouse as 
measured by GSA's space measurement program. To learn how the 
judiciary's 10-year judge estimates compared with the actual number of 
judges in service, we used courthouse planning documents to determine 
how many judges the judiciary estimated it would have in each 
courthouse in 10 years and compared that number with the judiciary's 
data showing how many judges or authorized vacancies are located there. 

To learn more about the level of courtroom sharing that the 
judiciary's data support, we used the judiciary's 2008 district 
courtroom scheduling and use data to model courtroom sharing 
scenarios. Working with a contractor, we designed this sharing model 
in conjunction with a specialist in discrete event simulation and the 
company that designed the simulation software to ensure that the model 
conformed to generally accepted simulation modeling standards and was 
reasonable for the federal court system. We determined that the 
judiciary's courtroom data were sufficiently reliable for our purposes 
by conducting checks on the data, reviewing the judiciary's validation 
techniques, and interviewing staff who collected the data at both the 
national and the local levels. We also visited courthouses in 
Philadelphia, Pennsylvania, and Manhattan, New York, to observe and 
discuss sharing experiences with judges and judicial staff. We chose 
these courthouses because the judges in them have experience with 
sharing courtrooms. We convened a panel of judicial experts and 
conducted structured interviews with numerous other district and 
magistrate judges about the challenges and opportunities related to 
courtroom sharing. 

We conducted this performance audit from September 2008 to June 2010 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. A detailed 
discussion of our scope and methodology appears in appendix I. 

Background: 

Federal courthouses vary in size and scope. While typically, one to 
five district court judges are located in small-to medium-sized 
courthouses, in several large metropolitan areas, 15 or more district 
judges are located in a single courthouse. Courthouses may also 
include space for appellate, bankruptcy, and magistrate judges, as 
well as other tenants. The U.S. district courts are the trial courts 
of the federal court system. There are 94 federal judicial districts--
at least 1 for each state--organized into 12 regional circuits, each 
of which has a court of appeals whose jurisdiction includes appeals 
from the district courts located within the circuit, as well as 
appeals from decisions of federal administrative agencies. Each 
district includes a U.S. bankruptcy court as a unit of the district 
court.[Footnote 7] Table 1 identifies the term, role, and numbers of 
the different types of federal judges. 

Table 1: The Different Types of Federal Judges: 

Judge type: Appeals; 
Appointment: Life term; 
Role: Hears appeals from district courts located within its circuit 
and appeals from decisions of federal administrative agencies.; 
Authorized number: 179; 
Actual number (authorized number less vacancies): 159 plus 93 senior 
judges. 

Judge type: District; 
Appointment: Life term; 
Role: Exercises jurisdiction over nearly all categories of federal 
cases, including both civil and criminal matters; 
Authorized number: 678; 
Actual number (authorized number less vacancies): 603 plus 347 senior 
judges. 

Judge type: Magistrate; 
Appointment: 8-year term; 
Role: Exercises jurisdiction over matters assigned by statute as well 
as those delegated by the district judges; 
Authorized number: 567; 
Actual number (authorized number less vacancies): Actual number not 
listed plus 43 recalled judges. 

Judge type: Bankruptcy; 
Appointment: 14-year term; 
Role: Exercises jurisdiction over bankruptcy cases; 
Authorized number: 352; 
Actual number (authorized number less vacancies): 332 plus 22 recalled 
judges. 

Source: Federal Judiciary; authorized and actual numbers from Judicial 
Business of the United States Courts: 2009 Annual Report of the 
Director. 

Note: Court of appeals and district judges who are eligible to retire 
may continue to hear cases on a full-or part-time basis as senior 
judges. 

[End of table] 

The Administrative Office of the U.S. Courts is an agency within the 
judicial branch and serves as the central support entity for federal 
courts, providing a wide range of administrative, legal, financial, 
management, and information technology functions. The Director of the 
Administrative Office of the U.S. Courts is supervised by the Judicial 
Conference. The Judicial Conference of the United States serves as the 
judiciary's principal policy-making body and recommends national 
policies and legislation on all aspects of federal judicial 
administration. The Judicial Conference of the United States 
periodically assesses the need for additional judgeships for the 
nation's appellate, district, and bankruptcy courts and recommends 
additional judgeships to Congress, specifying the circuit or district 
for which the additional judgeship is requested--for example, the 
eastern district of California. The additional requested and 
authorized judgeships may be permanent or temporary.[Footnote 8] 

Since fiscal year 1996, the judiciary has used a 5-year plan to 
prioritize new courthouse construction projects, taking into account a 
court's projected need for space related to caseload and estimated 
growth in the number of judges and staff, security concerns, and any 
operational inefficiencies that may exist. Under current practices, 
GSA and the judiciary plan new federal courthouses based on the 
judiciary's projected 10-year space requirements. To develop these 
projections, the judiciary evaluates historical caseload data, 
[Footnote 9] among other factors, to estimate how many weighted 
filings[Footnote 10] the court will have 10 years later. It then uses 
this information to determine how many judges to plan for. Currently, 
the judiciary uses a threshold of 500 adjusted annual appeals case 
filings per three-judge appellate panel, 430 to 500 weighted annual 
filings per authorized district judgeship,[Footnote 11] and 1,500 
annual weighted filings per bankruptcy judgeship. Magistrate judge 
positions are created based on an analysis of various factors, 
including the weighted caseload of the court, the ratio of magistrate 
judges to district judges, the workload of the magistrate judges, and 
the utilization of magistrate judges in the district. Except for 
appeals court judges, who sit on panels of three or more, the 
judiciary requested one courtroom per estimated judge for courthouses 
built from 2000 through 2009, although it occasionally planned for 
senior judges to share courtrooms. 

The U.S. Courts Design Guide (Design Guide) specifies the judiciary's 
criteria for designing new court facilities and sets the space and 
design standards for court-related elements of courthouse 
construction. In 1993, the judiciary also developed a space planning 
program called AnyCourt to determine the amount of court-related space 
the court will request for a new courthouse based on Design Guide 
standards and estimated staffing levels. GSA develops requests to 
congressional authorizing committees for both new courthouses and 
expanded court facilities. These requests are based on input from the 
judiciary and are reviewed by the Office of Management and Budget 
(OMB) before they are submitted to the congressional committees. GSA 
also serves as the central point of contact for the judiciary and 
other stakeholders throughout the construction process. 

For courthouses that are selected for construction, GSA typically 
submits two detailed project descriptions, or prospectuses, for 
congressional authorization. The first prospectus, often called the 
site and design prospectus, outlines the scope, size, and estimated 
costs of the project at the outset and typically requests 
authorization and funding to purchase the site and design the 
building. The second prospectus, often called the construction 
prospectus, outlines the scope, size, and estimated costs of the 
project as it enters the construction phase and typically requests 
authorization and funding for construction, as well as additional 
funding if needed for site and design work. GSA may also provide 
additional prospectuses or less formal materials that contain 
information on the project's size and estimated total cost to the 
authorizing committees. 

Typically, the total gross square footage of the courthouses depicted 
in the construction prospectus or fact sheet is based on the following: 

* The judiciary's projected need for space, based on 10-year judge 
estimates. 

* Projected space to be built for other tenants, such as the U.S. 
Marshals (Marshals) and U.S. Attorneys. 

* Gross square footage reserved for building common and other space, 
such as public lobbies and hallways, atriums, elevators, and 
mechanical rooms. The amount of gross square footage estimated for 
this space is based on GSA's specification that a courthouse should be 
67 percent efficient, meaning that 67 percent of the total gross 
square footage, excluding parking, should consist of tenant space 
(space assigned to the courts and other tenants)[Footnote 12] and the 
rest should be building common and other space.[Footnote 13] 

* Space needed for interior parking. 

Congressional committees authorize and Congress appropriates funds for 
courthouse projects, often at both the design and construction phases. 
Congressional authorizations of courthouse projects typically include 
the gross square footage of the planned courthouse as described in the 
prospectus and the funding requested. After funds have been 
appropriated, GSA selects private-sector firms for the design and 
construction work through a competitive procurement process. GSA also 
manages the construction contract and oversees the work of the 
construction contractor. 

After courthouses are occupied, GSA charges each tenant agency, 
including the judiciary, rent for the space it occupies and for its 
respective share of common areas, including mechanical spaces. GSA 
considers some space in buildings, such as vertical penetrations, 
including the upper floors of atriums, nonrentable space. In fiscal 
year 2009, the judiciary's rent payments totaled over $970 million. 
The judiciary has sought to reduce the payments through requests for 
rent exemptions from GSA and Congress and internal policy changes, 
such as annually capping rent growth and validating rental rates. 

Extra Space in Courthouses Cost an Estimated $835 Million in Constant 
2010 Dollars to Construct and $51 Million Annually to Rent, Operate, 
and Maintain: 

The 33 federal courthouses completed since 2000 include 3.56 million 
square feet of extra space consisting of space that was constructed 
above the congressionally authorized size, due to overestimating the 
number of judges the courthouses would have, and without planning for 
courtroom sharing among judges.[Footnote 14] Overall, this space 
represents about 9 average-sized courthouses. The estimated cost to 
construct this extra space, when adjusted to 2010 dollars, is $835 
million,[Footnote 15] and the annual cost to rent, operate, and 
maintain it is $51 million. More specifically, the extra space and its 
causes are as follows: 

* 1.7 million square feet caused by construction in excess of 
congressional authorizations; 

* 887,000 extra square feet caused by the judiciary overestimating the 
number of judges the courthouses would have in 10 years; and: 

* 946,000 extra square feet caused by district and magistrate judges 
not sharing courtrooms. 

Thirty-two of the 33 courthouses include extra space attributable to 
at least one of these three causes and 19 have extra space 
attributable to all three causes. This extra 3.56 million square feet 
cost an estimated $835 million in constant 2010 dollars to construct 
based on the cost per square foot to construct each courthouse (see 
figure 1). 

Figure 1: Extra Federal Courthouse Space Constructed Since 2000 and 
the Estimated Construction and Annual Costs: 

[Refer to PDF for image: pie-chart] 

Courthouses built since 2000: 13 million gross square feet (GSF); 
1.7 million extra square feet due to exceeding congressionally 
authorized gross square footage; 
887,000 extra square feet due to over-estimating number of judges; 
946,000 extra square feet due to judges not sharing courtrooms. 

3.56 million total extra square feet. 
Costing an estimated: $835 million to construct, and $51 million 
annually to rent, operate and maintain. 

Sources: GAO analysis of GSA data. 

Note: Numbers in figure 1 do not add up due to rounding. 

[End of figure] 

In addition to the one-time construction cost increase, the extra 
square footage in these 32 courthouses causes higher annual operations 
and maintenance costs, which are largely passed on to the judiciary 
and other tenants as rent. According to our analysis of the 
judiciary's rent payments to GSA for these courthouses at fiscal year 
2009 rental rates, the extra courtrooms and other judiciary space 
increase the judiciary's annual rent payments by $40 million. In 
addition, our analysis indicates that other extra space cost $11 
million in fiscal year 2009 to operate and maintain.[Footnote 16] 
Typically, operations and maintenance costs represent from 60 to 85 
percent of the costs of a facility over its lifetime, while design and 
construction costs represent about 5 to 10 percent of these costs. 
[Footnote 17] Therefore, the ongoing operations and maintenance costs 
for the extra square footage are likely to total considerably more in 
the long run than the construction costs for this extra square 
footage. Table 2 identifies the amount of extra space and associated 
costs for our seven case study courthouses.[Footnote 18] 

Table 2: Estimated Construction and Annual Operations and Maintenance 
Costs of Building Extra Space in Seven Case Study Courthouses: 

Courthouse: Bryant U.S. Courthouse Annex, Washington, D.C.; 
Estimated extra square feet constructed: 218,000; 
Estimated annual rent, operations, and maintenance costs for extra 
space: $4.0 million; 
Estimated extra construction costs in constant 2010 dollars: $56.5 
million. 

Courthouse: Coyle U.S. Courthouse, Fresno, California; 
Estimated extra square feet constructed: 131,000; 
Estimated annual rent, operations, and maintenance costs for extra 
space: $2.2 million; 
Estimated extra construction costs in constant 2010 dollars: $34.9 
million. 

Courthouse: D'Amato U.S. Courthouse, Islip, N.Y.; 
Estimated extra square feet constructed: 282,000; 
Estimated annual rent, operations, and maintenance costs for extra 
space: $3.8 million; 
Estimated extra construction costs in constant 2010 dollars: $74.7 
million. 

Courthouse: DeConcini U.S. Courthouse, Tucson, Arizona; 
Estimated extra square feet constructed: 78,000; 
Estimated annual rent, operations, and maintenance costs for extra 
space: $1.3 million; 
Estimated extra construction costs in constant 2010 dollars: $17.2 
million. 

Courthouse: Eagleton U.S. Courthouse, St. Louis, Missouri; 
Estimated extra square feet constructed: 398,000; 
Estimated annual rent, operations, and maintenance costs for extra 
space: $2.8 million; 
Estimated extra construction costs in constant 2010 dollars: $88.8 
million. 

Courthouse: Ferguson U.S. Courthouse, Miami, Florida; 
Estimated extra square feet constructed: 238,000; 
Estimated annual rent, operations, and maintenance costs for extra 
space: $3.8 million; 
Estimated extra construction costs in constant 2010 dollars: $48.5 
million. 

Courthouse: Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Missouri; 
Estimated extra square feet constructed: 26,000; 
Estimated annual rent, operations, and maintenance costs for extra 
space: $0.2 million; 
Estimated extra construction costs in constant 2010 dollars: $7.4 
million. 

Source: GAO. 

[End of table] 

Most Courthouses Exceed Congressionally Authorized Size Due to a Lack 
of Oversight by GSA: 

Twenty-seven of the 33 federal courthouses constructed since 2000 
exceed their congressionally authorized size,[Footnote 19] and 15 of 
the 33 courthouses exceed their congressionally authorized size by 10 
percent or more. Most of the courthouses that exceed the 
congressionally authorized size by 10 percent or more also had total 
project costs that exceeded the estimated budget provided to 
congressional authorizing committees. All seven courthouses we 
examined as case studies had increases in size made up at least in 
part of increases in building common and other space.[Footnote 20] 
Five of the seven courthouses also had increases in tenant space. In 
all seven of the case study courthouses, the increases in building 
common and other space were proportionally larger than the increases 
in tenant space, leading to a lower efficiency than GSA's target of 67 
percent.[Footnote 21] Efficiency is important because, for a given 
amount of tenant space, meeting the efficiency target helps control a 
courthouse's gross square footage and therefore its costs.[Footnote 
22] According to GSA officials, controlling the gross square footage 
of a courthouse is the best way to control construction costs. 
However, GSA lacked sufficient controls to ensure that courthouses 
were planned and built according to authorized gross square footage, 
initially because it had not established a consistent policy for how 
to measure gross square footage. GSA established a policy for 
measuring gross square footage by 2000, but GSA has not demonstrated 
it is enforcing this policy because the most recently completed 
courthouses continue to exceed the congressionally authorized size. 

Most Federal Courthouses Constructed Since 2000 Exceed Authorized 
Size, Some by Substantial Amounts: 

Twenty-seven of the 33 federal courthouses built since 2000 are larger 
than the congressionally authorized gross square footage. As shown in 
figure 2, altogether, these 27 courthouses have about 1.7 million more 
square feet than authorized. 

Figure 2: Extra Federal Courthouse Space Constructed Since 2000 Due to 
Exceeding Congressionally Authorized Square Footage: 

[Refer to PDF for image: pie-chart] 

Courthouses built since 2000: 13 million gross square feet (GSF); 
1.7 million extra square feet due to exceeding congressionally 
authorized gross square footage. 

Sources: GAO analysis of GSA data. 

[End of figure] 

Fifteen of these 33 courthouses are over 10 percent larger than 
authorized, and 3 of the federal courthouses built since 2000--the 
O'Connor U.S. Courthouse in Phoenix; the U.S. Courthouse in Hammond, 
Indiana; and the Arnold U.S. Courthouse Annex in Little Rock, 
Arkansas--are at least 50 percent larger than congressionally 
authorized.[Footnote 23] For example, the O'Connor Courthouse in 
Phoenix was congressionally authorized at 555,810 gross square feet 
but is 831,604 gross square feet, an increase of 50 percent. 

On the other hand, 6 of the 33 courthouses are smaller than 
congressionally authorized, as shown in figure 3, and 3 of these are 
more than 5 percent smaller. For example, the Arraj U.S. Courthouse in 
Denver, Colorado, is 6 percent smaller than authorized. We reported in 
2005 that, according to GSA's construction manager, construction price 
increases caused GSA to implement cost-saving measures that included 
cutting one floor from the design.[Footnote 24] According to a GSA 
official, it was possible to delete this floor because two judges 
retired instead of taking senior status. In spite of this and other 
cost-saving measures, according to GSA's project manager, the 
competition in the local construction market contributed to actual 
costs that were 6 percent higher than the estimated costs submitted 
with the construction funding request. 

In addition, 8 courthouses are within 5 percent of their authorized 
gross square footage. Courthouses from 0 to 5 percent below their 
authorized square footage include: 

* the U.S. Courthouse in Laredo, Texas; 

* the U.S. Courthouse Annex in London, Kentucky; and: 

* the Hruska U.S. Courthouse, in Omaha, Nebraska. 

Courthouses from 0 to 5 percent above their authorized gross square 
footage include: 

* the Federal Building and U.S. Courthouse in Wheeling, West Virginia; 

* the King U.S. Courthouse in Albany, Georgia; 

* the Quillen U.S. Courthouse, in Greeneville, Tennessee; 

* the George U.S. Courthouse in Las Vegas, Nevada; and: 

* the DeConcini U.S. Courthouse, in Tucson, Arizona. 

Figure 3: Percentage Difference in Size of Federal Courthouses as 
Congressionally Authorized and as Built: 

[Refer to PDF for image: U.S. map with associated data] 

0-15 percent smaller than Congressionally authorized square footage: 
Denver, Colorado; 
Gulfport, Mississippi; 
Laredo, Texas; 
London, Kentucky; 
Omaha, Nebraska; 
Tallahassee, Florida. 

0-9 percent larger than authorized: 
Albany, Georgia; 
Brooklyn, New York; 
Cleveland, Ohio; 
Columbia, South Carolina; 
Greenville, Tennessee; 
Jacksonville, Florida; 
Las Vegas, Nevada; 
Montgomery, Alabama; 
Seattle, Washington; 
Tucson, Arizona; 
Youngstown, Ohio; 
Wheeling, West Virginia. 

10-20 percent larger than authorized: 
Cape Girardeau, Missouri; 
Central Islip, New York; 
Erie, Pennsylvania; 
Eugene, Oregon; 
Fresno, California; 
Miami, Florida; 
Richmond, Virginia; 
Springfield, Massachusetts. 

25 percent or more larger than authorized: 
Corpus Christi, Texas; 
Hammond, Indiana; 
Little Rock, Arkansas; 
Orlando, Florida; 
Phoenix, Arizona; 
St. Louis, Missouri; 
Washington, D.C. 

Source: GAO presentation of GSA data; Map Resources (map). 

[End of figure] 

Most of the Courthouses That Exceeded Authorized Size by 10 Percent or 
More Also Exceeded Budget Estimates: 

Twelve of the 15 courthouses that exceeded the congressionally 
authorized gross square footage by 10 percent or more also had total 
project costs that exceeded the total project cost estimate provided 
to congressional authorizing committees. There is a 10 percent 
statutory cap in the authorizing language on the estimated maximum 
cost increase of a project. GSA's annual appropriations acts include a 
provision stating that GSA may increase spending for a project in an 
approved prospectus by more than 10 percent if GSA obtains advance 
approval from the Committee on Appropriations.[Footnote 25] There is 
no statutory requirement for GSA to notify congressional authorizing 
or appropriations committees if the size exceeds the congressionally 
authorized square footage. Four of the 15 courthouses had total 
project costs that exceeded the estimate provided to congressional 
authorizing committees at the construction phase by about 10 percent 
or more.[Footnote 26] The construction industry commonly uses 10 
percent as a benchmark for the expected variance between the actual 
cost and the construction estimate. However, while GSA sought approval 
from the appropriations committees for the cost increases incurred for 
these 4 courthouses, GSA did not explain to these committees that the 
courthouses were larger than authorized and therefore did not 
attribute any of the cost increase to this difference. 

For example, the total project cost of the Coyle U.S. Courthouse in 
Fresno, California, (about $133 million) was about $13 million over 
the estimate provided to congressional authorizing committees before 
construction (an increase of 11 percent), while the courthouse is 
about 16 percent larger than its authorized gross square footage. In 
requesting approval from the appropriations committees for additional 
funds for the Coyle U.S. Courthouse, GSA stated that, among other 
things, additional funds were needed for fireproofing and electrical 
and sewer line revisions--but did not mention that the courthouse was 
16 percent larger than authorized. Because the construction costs of a 
building increase when its gross square footage increases, the cost 
overruns for this courthouse would have been smaller or might have 
been eliminated if GSA had built the courthouse to meet the authorized 
square footage. 

Increase in Overall Size Consisted of Increases in Building Common and 
Tenant Spaces: 

We found that in five of the seven courthouses we examined as case 
studies, the size increase over the congressionally authorized gross 
square footage consisted of increases in both tenant space and 
building common and other space over the space that was 
congressionally authorized. Two of the seven had decreases in tenant 
space, while all seven had increases in the building common and other 
space compared with the congressionally authorized sizes for these 
spaces. In the two with decreases in tenant space, the increase in the 
building common and other space more than offset the decreases, so 
that the gross square footage of all seven exceeded the 
congressionally authorized gross square footage. In addition, for all 
seven courthouses, the increase in building common and other space was 
proportionally larger than the increase (if any) in tenant space, and 
the efficiency of all seven courthouses was below GSA's target, as 
stated in the judiciary's Design Guide, of 67 percent. According to 
GSA officials, a building's efficiency is important because, as it 
declines, less of the building's space directly contributes to the 
tenant's mission-related activities. In addition, for a given amount 
of tenant space, meeting the efficiency target helps control a 
courthouse's gross square footage and therefore its costs. The 
efficiency of five of our seven case study courthouses fell at least 5 
percentage points below GSA's efficiency target of 67 percent. 
[Footnote 27] (see table 3). 

Table 3: Square Footage Over Authorized and Efficiency of Seven 
Courthouses: 

Gross square footage over authorized; 
Bryant U.S. Courthouse Annex, Washington, D.C.: 82,374; 
Coyle U.S. Courthouse, Fresno, Calif.: 67,536; 
D'Amato U.S. Courthouse, Central Islip, N.Y.: 156,031; 
DeConcini U.S. Courthouse, Tucson, Ariz.: 20,075; 
Eagleton U.S. Courthouse, St. Louis, Mo.: 273,244; 
Ferguson, Jr., U.S. Courthouse, Miami, Fla.: 97,477; 
Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Mo.: 18,982. 

Actual gross square footage, including parking; 
Bryant U.S. Courthouse Annex, Washington, D.C.: 409,974; 
Coyle U.S. Courthouse, Fresno, Calif.: 495,912; 
D'Amato U.S. Courthouse, Central Islip, N.Y.: 1,014,031; 
DeConcini U.S. Courthouse, Tucson, Ariz.: 439,817; 
Eagleton U.S. Courthouse, St. Louis, Mo.: 1,310,876; 
Ferguson, Jr., U.S. Courthouse, Miami, Fla.: 605,800; 
Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Mo.: 173,392. 

Authorized gross square footage for construction, including parking; 
Bryant U.S. Courthouse Annex, Washington, D.C.: 327,600; 
Coyle U.S. Courthouse, Fresno, Calif.: 428,376; 
D'Amato U.S. Courthouse, Central Islip, N.Y.: 858,000; 
DeConcini U.S. Courthouse, Tucson, Ariz.: 419,742; 
Eagleton U.S. Courthouse, St. Louis, Mo.: 1,037,632; 
Ferguson, Jr., U.S. Courthouse, Miami, Fla.: 508,323; 
Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Mo.: 154,410. 

Actual tenant space square footage[A]; 
Bryant U.S. Courthouse Annex, Washington, D.C.: 188,955; 
(38,722 over planned); 
Coyle U.S. Courthouse, Fresno, Calif.: 278,654; 
(21,658 over planned); 
D'Amato U.S. Courthouse, Central Islip, N.Y.: 416,827; 
(33,173 under planned); 
DeConcini U.S. Courthouse, Tucson, Ariz.: 255,225; 
(2,285 over planned); 
Eagleton U.S. Courthouse, St. Louis, Mo.: 671,050; 
(73,696 over planned)[B]; 
Ferguson, Jr., U.S. Courthouse, Miami, Fla.: 366,924; 
(46,924 over planned); 
Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Mo.: 96,025; 
(998 under planned). 

Actual building common and other space square footage[A]; 
Bryant U.S. Courthouse Annex, Washington, D.C.: 149,628; 
(75,633 over planned); 
Coyle U.S. Courthouse, Fresno, Calif.: 173,157; 
(46,577 over planned); 
D'Amato U.S. Courthouse, Central Islip, N.Y.: 468,411; 
(185,411 over planned); 
DeConcini U.S. Courthouse, Tucson, Ariz.: 148,015; 
(23,433 over planned); 
Eagleton U.S. Courthouse, St. Louis, Mo.: 518,006; 
(224,865 over planned)[B]; 
Ferguson, Jr., U.S. Courthouse, Miami, Fla.: 188,766; 
(44,443 over planned); 
Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Mo.: 68,008; 
(20,221 over planned). 

Actual Efficiency; 
Bryant U.S. Courthouse Annex, Washington, D.C.: 56%; 
Coyle U.S. Courthouse, Fresno, California: 62%; 
D'Amato U.S. Courthouse, Central Islip, N.Y.: 47%; 
DeConcini U.S. Courthouse, Tucson, Arizona: 63%; 
Eagleton U.S. Courthouse, St. Louis, Missouri: 56%; 
Ferguson, Jr., U.S. Courthouse, Miami, Florida: 66%; 
Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Missouri: 59%. 

Source: GAO. 

[A] The square footage for tenant space and building common and other 
space does not include indoor parking and, thus, does not add up to 
the actual gross square footage, which includes indoor parking. 

[B] While the square footage to be used for tenant space and building 
common and other space is not specifically congressionally authorized, 
GSA provides congressional committees with plans it has developed with 
the judiciary that show how much of the gross square footage not 
including parking (which is congressionally authorized) is to be used 
for tenant space, with the rest of the square footage planned for 
building common and other space. 

[End of table] 

GSA Lacked Sufficient Oversight and Controls to Ensure That 
Courthouses Were Planned and Built According to Authorized Size: 

GSA lacked sufficient control activities to ensure that the 33 
courthouses were constructed within the congressionally authorized 
gross square footage, initially because it had not established a 
consistent policy for how to measure gross square footage. GSA 
established a policy for measuring gross square footage by 2000, but 
has not ensured that this space measurement policy was understood and 
followed. Moreover, GSA has not demonstrated it is enforcing this 
policy because all 6 courthouses completed since 2007 exceed their 
congressionally authorized size. According to GSA officials, the 
agency did not focus on ensuring that the authorized gross square 
footage was met in the design and construction of courthouses until 
2007. Our Standards for Internal Control in the Federal Government 
define control activities as the policies, procedures, techniques, and 
mechanisms that enforce management's directives, such as the process 
of adhering to requirements and budget execution.[Footnote 28] GSA 
lacked such policies, procedures, techniques, or mechanisms to enforce 
adherence to the authorized square footage in the design and 
construction of these federal courthouses. GSA lacked such mechanisms 
even though, according to GSA officials, controlling the gross square 
footage of a building is important to controlling its construction 
costs because when the gross square footage of a building increases, 
construction costs increase as well. This lack of oversight and 
controls contributed to the increase over the congressionally 
authorized size in some courthouses built since 2000. 

Lack of GSA Oversight Contributed to More Building Common Space Than 
Planned: 

All seven of the courthouses we examined in our case studies had 
increases in building common and other space--such as mechanical 
spaces and atriums--as compared with the square footage planned for 
these spaces within the congressionally authorized gross square 
footage. The percentage of increase over the planned space ranged from 
19 percent to 102 percent. According to a GSA official, at times, 
courthouses were designed to meet various design goals without an 
attempt to limit the size of the building common or other space to the 
square footage allotted in the plans provided to congressional 
authorizing committees--and these spaces may have become larger to 
serve a design goal as a result. Regional GSA officials involved in 
the planning and construction of several courthouses we visited stated 
that they were unaware until we told them that the courthouse was 
larger and less efficient than authorized. 

For example, the building common and other space in the Eagleton U.S. 
Courthouse in St. Louis is 77 percent larger than planned, and the 
courthouse has an efficiency of 56 percent. While we could not 
determine the cause of all of this additional space, all courtroom 
floors of the St. Louis courthouse have mechanical rooms near the 
courtrooms, and in total, the mechanical space in the St. Louis 
courthouse takes up proportionally more space than it does in the 
DeConcini U.S. Courthouse, in Tucson, Arizona. In addition, the 
Eagleton U.S. Courthouse in St. Louis has two empty elevator shafts-- 
rising all 33 floors--that were built but are not used. Together, the 
mechanical space and the elevator shafts bring the efficiency of the 
Eagleton U.S. Courthouse well below GSA's target of 67 percent and 
limit the proportion of the building's total space that contributes to 
mission-related activities. However, regional GSA officials stated 
that they were unaware until we told them that the courthouse was 
larger and less efficient than authorized. 

Similarly, according to GSA officials, some of the mechanical space in 
the Coyle U.S. Courthouse in Fresno, California, was enclosed to serve 
the design of the courthouse. Specifically, the top level of the 
courthouse could have been left unenclosed except for the elevator 
tower, but to prevent the elevator tower from marring the line of 
vision of the roof, the architect enclosed a larger-than-necessary 
space, which became mechanical space (see figure 4). The efficiency of 
the Coyle U.S. Courthouse in Fresno is 62 percent. In addition, the 
DeConcini U.S. Courthouse in Tucson, which has an efficiency of 63 
percent, several percentage points below the target of 67 percent, has 
public hallways on every floor with large open areas, which increase 
the size of the hallways. GSA officials stated that these areas were 
created to meet the architect's vision for the building's façade, 
which did not consider how the space would work inside the building. 

Figure 4: Example of a Mechanical Room on a Courtroom Floor of the 
Eagleton U.S. Courthouse in St. Louis, Missouri, and on the Top Level 
of the Coyle U.S. Courthouse, in Fresno, California: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

[End of figure] 

Another element of GSA's lack of oversight in this area was that GSA 
relied on the architect to validate that the courthouse's design was 
within the authorized gross square footage without ensuring that the 
architect followed GSA's policies for how to measure certain commonly 
included spaces, such as atriums. Although GSA officials emphasized 
that open space for atriums would not cost as much as space completely 
built out with floors, these officials also agreed that there are 
costs associated with constructing and operating atrium space. In 
fact, the 2007 edition of the Design Guide, which reflects an effort 
to impose tighter constraints on future space and facilities costs, 
emphasizes that courthouses should have no more than one atrium. 

According to GSA officials, a primary reason why the Limbaugh, Sr., 
U.S. Courthouse in Cape Girardeau, Missouri, and the Bryant U.S. 
Courthouse Annex in Washington, D.C., exceeded their congressionally 
authorized square footage is that the architect did not consider the 
upper atrium levels as part of the gross square footage of the 
courthouse--in conflict with GSA's standards for measuring atrium 
space. In GSA's policy for determining a building's gross square 
footage, the atrium space is counted on all floors because multifloor 
atriums increase a building's volume and thus its costs. However, 
according to GSA officials, GSA's practice in the early 2000s--when 
the Limbaugh, Sr., and Bryant Courthouses were under design--was to 
rely on the architect to measure and validate the plans for the 
courthouse, and GSA did not expect its regional or headquarters 
officials to monitor or check whether the architect was following 
GSA's policies. The D'Amato U.S. Courthouse in Central Islip, New 
York, was also larger than congressionally authorized, according to a 
regional GSA official, because in designing this courthouse, the 
square footage of the air space of three large atriums was not 
included as part of the gross square footage (see figure 5). In our 
visits to courthouses, we found that some GSA regional staff were 
still unclear about GSA's policy for measuring atrium space. 

Figure 5: D'Amato U.S. Courthouse Atrium Map and Pictures: 

[Refer to PDF for image: map and 3 photographs] 

Sources: GSA (floor map); Scott Frances/Esto (wall atrium photograph); 
and GAO. 

[End of figure] 

According to GSA officials, GSA's current policy on how to count the 
square footage of atriums and the target of 67 percent efficiency for 
federal courthouses should make it difficult, if not impossible, for a 
courthouse project to include large atriums spanning many floors-- 
although relatively modest atriums should still be feasible. For the 
Bryant U.S. Courthouse Annex and Limbaugh, Sr., U.S. Courthouse, a 
result of GSA not providing oversight to ensure that the architect's 
measurement of the courthouse followed GSA's standards for measuring 
atrium space was that the courthouses were built larger than 
authorized. Moreover, these courthouses include larger atriums than 
would likely have been feasible within the authorized gross square 
footage if the atrium space had been measured according to GSA's 
standards. 

The Design Guide states that courthouses must provide a civic presence 
and that the architecture must promote respect for the tradition and 
purpose of the American judicial process. While some GSA officials we 
met with suggested that atriums were part of what provided this civic 
presence, we found evidence that courthouses could be built with 
relatively small atriums or other elements to create a grand entrance 
without causing low building efficiency. The Ferguson, Jr., U.S. 
Courthouse in Miami, for example, which has an efficiency of 66 
percent, close to GSA's target of 67 percent, has a public atrium that 
is not a major contributor to the courthouse being larger than 
authorized, and the DeConcini U.S. Courthouse in Tucson has a grand 
entrance without a multistory atrium (see figure 6.) 

Figure 6: Atrium in Ferguson, Jr., U.S. Courthouse in Miami, Florida, 
and Entry Space in DeConcini U.S. Courthouse in Tucson, Arizona: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

[End of figure] 

A Lack of GSA Oversight Contributed to Some Courthouses Being Built 
with Larger Tenant Spaces: 

GSA's lack of focus on meeting authorized square footage also 
contributed to increases in the size of tenant spaces in five of our 
seven case study courthouses. For example, the Ferguson, Jr., U.S. 
Courthouse in Miami has about 46,924 more square feet of tenant space 
than planned. The district court has about 20,768 more square feet of 
space in this courthouse than planned. Among other things, the 14 
regular district courtrooms built in this courthouse are each about 
2,800 square feet--17 percent larger than the Design Guide standard of 
2,400 square feet--while the two special proceedings courtrooms on the 
13th floor are each about 3,200 square feet, about 7 percent larger 
than the Design Guide standard of 3,000 square feet. GSA officials 
stated that courtroom space is among the most expensive of courthouse 
spaces to construct and the Design Guide's criteria are in part meant 
to help ensure that courthouses are built to be cost-effective as well 
as functional. 

The Coyle U.S. Courthouse, in Fresno, California, and the Bryant U.S. 
Courthouse Annex in Washington, D.C., also have more tenant space than 
planned, in part because the design of these courthouses led to the 
construction of more space than planned for U.S. marshals. According 
to regional GSA officials, both of these courthouses needed additional 
marshal space to accommodate the movement of prisoners from the 
courthouse entrances into the holding cells via secured passageways. 
As a result, the U.S. marshal space in the Coyle U.S. Courthouse 
almost doubled, and in the Bryant U.S. Courthouse Annex, it more than 
doubled. GSA and court officials said that for the Bryant U.S. 
Courthouse Annex, an additional subterranean floor had to be built 
beneath the basement parking levels to accommodate the passageway. 
According to GSA officials, because of the security elements necessary 
for U.S. marshal space, this space is among the most expensive types 
of courthouse space to construct. Therefore, design decisions that 
create a need for more U.S. marshal space than planned may have a 
significant impact on the cost of constructing the courthouse. 

In addition, some courthouses encompass more courtroom space than 
planned because during the planning stages, neither the judiciary nor 
GSA took into account the possibility that the design of the 
courthouse could double the size of each courtroom. Under Design Guide 
standards in effect when these courthouses were designed, courtroom 
ceilings were to be at least 16 feet high,[Footnote 29] while judges' 
chambers and other court-related spaces did not have ceiling height 
requirements. Courthouses have been designed in various ways to 
address the height requirement for courtroom ceilings. For example, in 
a collegial floor plan, courtroom floors alternate with floors for 
judicial chambers and other spaces that do not need higher ceilings, 
so that each floor can be built to a height that is suitable for the 
rooms it contains. However, because federal courthouses have typically 
been built with judges' chambers on the same floors as the courtrooms, 
some courthouses have courtrooms on floors designed to hold rooms with 
10-foot ceilings, and the ceiling of each courtroom is cut out so that 
each courtroom takes up two floors. For example, Eagleton U.S. 
Courthouse in St. Louis and the Bryant U.S. Courthouse Annex in 
Washington, D.C., were constructed with courtrooms that span two 
floors. According to GSA's policy, when a courthouse is designed so 
that a courtroom takes up two floors, the space on the second floor--
referred to as a tenant floor cut--is considered part of the gross 
square footage of the building and--if it would otherwise be usable 
space--is also considered to be court-occupied space. Therefore, in 
this type of courthouse, each courtroom is counted as having double 
the square footage of the courtroom floor. Although the extra square 
footage in this type of courtroom is multistory space, like the extra 
square footage in atria, and therefore, according to GSA, costs less 
than square footage that is completely built out, nevertheless there 
are costs associated with this space. 

Judiciary officials said that space planning is done well before they 
know if they will need to incorporate additional space for tenant 
floor cuts in courtrooms. Under the judiciary's current automated 
space planning tool, AnyCourt, which the judiciary uses to determine 
how much court-related space to request for a new courthouse, the 
Design Guide's standard of 2,400 square feet is provided for each 
district courtroom planned for a new courthouse. However, because the 
gross square footage requirements that GSA identifies in the 
prospectus to congressional committees are based on AnyCourt's output 
for the amount of space needed by the courts, for courthouses designed 
with district courtrooms that have tenant floor cuts, the AnyCourt 
program identifies only half of the square footage the courtroom will 
take up when calculating the courthouse's gross square footage 
following GSA's standards. If GSA requests court space based on the 
AnyCourt model, it therefore may not be requesting sufficient space 
for courtrooms to account for courtrooms that are designed with tenant 
floor cuts. 

Recently, GSA Has Taken Some Steps to Improve Oversight of Courthouse 
Size: 

Recently, GSA has taken some steps to improve its oversight of the 
courthouse construction process by clarifying its space measurement 
policies and increasing efforts to monitor the size of courthouse 
projects during the planning stages. In May 2009, GSA published a 
revised space assignment policy to clarify and emphasize its policies 
on counting the square footage of atria and tenant floor cuts, among 
other things. In addition, according to GSA officials, to avoid 
further inconsistencies between its policies and the process for 
measuring courthouses during the planning stages, GSA established a 
collaborative effort in 2008 between its Office of Design and 
Construction and its Real Estate Portfolio Management to establish 
policy and practices for avoiding inconsistencies. This effort 
includes, among other things, using data management software to ensure 
that space guidelines are followed in the early planning phases of 
courthouse projects. It is not yet clear whether these steps will 
establish sufficient oversight to ensure that courthouses are planned 
and constructed within the congressionally authorized square footage. 

Estimated Space Needs Exceeded Actual Space Needs, Resulting in 
Courthouses That Were Larger than Necessary: 

Because the Judiciary Overestimated the Number of Judges, Courthouses 
Have Much Extra Space After 10 Years: 

Our analysis of construction plans for the 33 courthouses built since 
2000 shows that 28 have reached or passed their 10-year planning 
period[Footnote 30] and 23 of those 28 courthouses have fewer judges 
than estimated.[Footnote 31] Overall, the judiciary has 119, or 
approximately 26 percent, fewer judges than the 461 it estimated it 
would have. As a result, these 23 courthouses have extra courtrooms, 
chamber suites, and related support, building common, and other spaces 
covering approximately 887,000 square feet (see figure 7). A variety 
of factors led the judiciary to overestimate the number of judges it 
would have after 10 years, including inaccurate caseload projections, 
challenges associated with estimating when judges will take senior 
status, and not factoring in the time associated with obtaining new 
judgeship authorizations. 

Figure 7: Extra Federal Courthouse Space Constructed Since 2000 Due to 
Overestimating the Number of Judges: 

[Refer to PDF for image: pie--chart] 

Courthouses built since 2000: 13 million gross square feet (GSF); 
887,000 extra square feet due to over-estimating number of judges. 

Sources: GAO analysis of GSA data. 

[End of figure] 

Six of the seven case study courthouses we reviewed have reached the 
end of their 10-year planning period and were designed for more judges 
than they actually have.[Footnote 32] Table 4 compares the estimated 
and actual numbers of judges for each of these courthouses and the 
space consequences of overestimating the number of judges. 

Table 4: Comparison of 10-Year Judge Estimates and the Actual Number 
of Judges After 10 Years or More for Case Study Courthouse Locations 
and Related Space Consequences: 

Year estimate was made; 
Bryant Courthouse, Washington, D.C.: 2000; 
Coyle Courthouse, Fresno, California: 2000; 
D'Amato Courthouse, Central Islip, N.Y.: 1995; 
DeConcini Courthouse, Tucson, Arizona: 1995; 
Eagleton Courthouse, St. Louis, Missouri: 1994; 
Ferguson Courthouse, Miami, Florida: 2000. 

10-year judge estimate; 
Bryant Courthouse, Washington, D.C.: 49; 
Coyle Courthouse, Fresno, California: 18; 
D'Amato Courthouse, Central Islip, N.Y.: 25; 
DeConcini Courthouse, Tucson, Arizona: 15; 
Eagleton Courthouse, St. Louis, Missouri: 29; 
Ferguson Courthouse, Miami, Florida: 33. 

Current judges, including vacancies; 
Bryant Courthouse, Washington, D.C.: 39; 
Coyle Courthouse, Fresno, California: 10; 
D'Amato Courthouse, Central Islip, N.Y.: 15; 
DeConcini Courthouse, Tucson, Arizona: 12; 
Eagleton Courthouse, St. Louis, Missouri: 20; 
Ferguson Courthouse, Miami, Florida: 27. 

Judges short of estimate; 
Bryant Courthouse, Washington, D.C.: 10; 
Coyle Courthouse, Fresno, California: 8; 
D'Amato Courthouse, Central Islip, N.Y.: 10; 
DeConcini Courthouse, Tucson, Arizona: 3; 
Eagleton Courthouse, St. Louis, Missouri: 9; 
Ferguson Courthouse, Miami, Florida: 6. 

Estimated extra square footage built because of incorrect judge 
estimates; 
Bryant Courthouse, Washington, D.C.: 62,000; 
Coyle Courthouse, Fresno, California: 52,000; 
D'Amato Courthouse, Central Islip, N.Y.: 89,000; 
DeConcini Courthouse, Tucson, Arizona: 25,000; 
Eagleton Courthouse, St. Louis, Missouri: 76,000; 
Ferguson Courthouse, Miami, Florida: 57,000. 

Source: GAO. 

Note: Our analysis includes judges who are located in the new 
courthouse and authorized vacancies not covered by recalled judges. 

[End of table] 

Extra space includes courtroom suites,[Footnote 33] ranging in size 
from 3,500 to 5,000 square feet, and chamber suites, ranging in size 
from 1,500 to 2,400 square feet, as specified in the Design Guide (see 
figure 8). In addition to the court space, these spaces require a 
proportional allocation of additional public and mechanical spaces, 
and judges are generally provided with secure, inside parking space in 
new courthouses. These additional spaces are also not needed if 
estimates exceed authorized judges. 

Figure 8: Unassigned Chamber Suites in the Coyle Courthouse in Fresno, 
California: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

[End of figure] 

Judiciary Planning Overstated the Need for Space through Inaccurate 
Caseload Projections and Allocations of Space for Visiting Judges: 

Inaccurate caseload growth projections and inconsistent application of 
planning guidelines led the judiciary to estimate a need for more 
judges, and subsequently overestimate the need for space, for some 
courthouse projects. In a 1993 report, we questioned the reliability 
of the caseload projection process the judiciary used.[Footnote 34] In 
that report, we showed that the judiciary's estimates of future space 
needs exceeded estimates made using a standard statistical method by 
about 3.6 million square feet. For this report, we were not able to 
determine the degree to which inaccurate caseload projections 
contributed to inaccurate judge estimates because the judiciary did 
not retain the historic caseload projections used in planning the 
courthouses. Judiciary officials said that the judiciary does not 
typically review the accuracy of the caseload and judge estimates for 
courthouse construction projects. However, judiciary officials at 
three of our site visit courthouses indicated that the estimates used 
in planning for these courthouses inadvertently overstated the growth 
in district case filings and, hence, the need for additional judges. 
For example, for the Eagleton Courthouse in St. Louis, judiciary 
officials said the district estimated that it would need four 
additional district judges by 2004 to handle a high level of estimated 
growth in case filings; however, that case filing growth never 
materialized and the Eagleton Courthouse has the same number of 
authorized judges that it had in 1994 when the estimates were made. 
Specifically, the Eastern District of Missouri, in which the Eagleton 
Courthouse is located, had 3,182 case filings in 1994 and 3,241 case 
filings in 2008 (see figure 9). 

Figure 9: Total District Court Case Filings for the Eastern District 
of Missouri: 

[Refer to PDF for image: line graph] 

Year: 1994; 
Total filings: 3,182. 

Year: 1995; 
Total filings: 3,081. 

Year: 1996; 
Total filings: 3,410. 

Year: 1997; 
Total filings: 3,346. 

Year: 1998; 
Total filings: 3,046. 

Year: 1999; 
Total filings: 2,871. 

Year: 2000; 
Total filings: 2,993. 

Year: 2001; 
Total filings: 2,949. 

Year: 2002; 
Total filings: 3,079. 

Year: 2003; 
Total filings: 3,010. 

Year: 2004; 
Total filings: 3,070. 

Year: 2005; 
Total filings: 3,564v 

Year: 2006; 
Total filings: 3,474. 

Year: 2007; 
Total filings: 3,415. 

Year: 2008; 
Total filings: 3,241. 

Year: 2009; 
Total filings: 3,501. 

Source: Administrative Office of the U.S. Courts. 

[End of figure] 

Planning for nonresident judges, or visiting judges, is another reason 
of overestimating the 10-year need for judges and space. Our analysis 
of courthouse space planning documents showed that 5 courthouses 
included courtrooms for visiting district judges, which is a way of 
building extra space into courthouses above the estimated number of 
judges expected to be permanently located in the courthouse. The 
judiciary indicated that its guidance has since been revised to 
exclude estimates of space needs for visiting judges. These five 
courthouses contain a total of six courtrooms allocated for visiting 
district judges, totaling approximately 30,000 extra square feet, 
which are not assigned to a specific judge. For example, when planning 
the Perry, Jr., Courthouse in Columbia, South Carolina, the judiciary 
estimated a need for two visiting district courtrooms--one in a new 
courthouse and one in an existing space. As a result, the number of 
district courtrooms in the courthouse exceeds the estimated number of 
judges by two, and these two courtrooms account for approximately 
15,000 extra square feet, including court, support, and public spaces. 

The Judiciary's Method of Estimating Judges Does Not Account for 
Uncertainty in When Judges Will Take Senior Status and in How Many New 
Judgeships Will Be Authorized: 

Limitations of the judiciary's 10-year judge estimates are also due, 
in part, to the challenges associated with predicting how many judges 
will be located in a courthouse in 10 years. Such challenges include 
predicting when judges will take senior status, how many requested 
judgeships will be authorized, and where newly authorized judges will 
be seated. By not accounting for the outcomes of these challenges-- 
which is that the actual number of judges was smaller than the 
estimated number--the judiciary overestimated how many judges it would 
have in courthouses after 10 years or more. 

Predicting when district judges will assume senior status is 
challenging because judges are not required to take senior status when 
they become eligible. For example, the judiciary estimated that the 
Washington, D.C., district court would have 14 senior judges by the 
end of the 10-year planning period; however, because some judges left 
the bench, died, or remained active after they became eligible for 
senior status, the court currently has 9 fewer senior judges than 
estimated. 

Determining how many requested judgeships will be authorized and how 
many judicial vacancies will be filled is also challenging for several 
reasons. First, Congress has authorized fewer positions than the 
judiciary has requested over the years. It has been 20 years since 
Congress passed comprehensive judgeship legislation. Yet, the 
judiciary did not incorporate historic trends into its planning for 
new courthouses. Instead, it requested new courthouses that could 
accommodate the number of judges it would have if all of its estimated 
judgeships were approved, and some of the excess space in new 
courthouses reflects the judiciary's receipt of fewer judgeships than 
it requested. Problems with the reliability of the weighted caseload 
data--the workload indicator that the judiciary uses to decide when a 
new judge is needed--can undermine the credibility of the judiciary's 
requests for new judgeships. For example, in a 2009 hearing, a member 
of Congress cited a lack of reliability in weighted caseloads to 
question if all of the requested judgeships are necessary. In a 2008 
report, we found that a weighted caseload is not reliable because its 
accuracy for district and appeals courts cannot be tested. [Footnote 
35] 

A second challenge the judiciary faces in estimating how many judges 
it will need for specific courthouses is that judgeships are requested 
and thus authorized at the district or circuit levels as a whole, 
rather than for a specific courthouse. Hence, it is hard to predict 
which courthouses the additional judgeships requested in the Federal 
Judgeship Act of 2009,[Footnote 36] if enacted, would be assigned to 
if the positions were authorized. However, the judiciary's estimation 
process does not take this uncertainty into account. For example, in 
2009, the judiciary requested 18 judgeships for districts that contain 
courthouses built since 2000, but not all of the judges for these 
requested judgeships, if approved by Congress, would necessarily be 
placed in those courthouses. For example, in the Eastern District of 
California where the Coyle Courthouse in Fresno is located, the 
average weighted caseload is 1,095 weighted filings per district 
judge, well above the 430 weighted filings outlined in the judiciary's 
guidelines and the highest in the nation according to the judiciary. 
The judiciary estimated that the Coyle Courthouse would have 6 more 
district judges than it currently has, and it has requested 4 
additional district judgeships for the Eastern District of California. 
However, these judgeships, if approved, could be located at other 
locations in the district. In addition, the Ferguson Courthouse in 
Miami has space reserved for 4 extra district courtrooms (see figure 
10), yet Southern District of Florida officials said they anticipate 
that the next new authorized judgeship in the district will be 
allocated to the courthouse in Fort Lauderdale. 

Figure 10: Unassigned District Courtroom and Chamber in the Ferguson 
Courthouse, Miami, Florida: 

[Refer to PDF for image: 2 photographs] 

Source: GAO. 

[End of figure] 

Low Levels of Use Show That Judges Could Share Courtrooms, Reducing 
the Need for Future Courtrooms by More Than One-Third: 

Most courthouses constructed since 2000 have enough courtrooms for all 
of the district and magistrate judges to have their own courtrooms. 
According to the judiciary's data,[Footnote 37] courtrooms are used 
for case-related proceedings only a quarter of the available time or 
less, on average. Furthermore, no event was scheduled in courtrooms 
for half the time or more, on average. Using the judiciary's data, we 
designed a model for courtroom sharing that shows sufficient amounts 
of unscheduled time for judges to share courtrooms at high levels. 
Specifically, it shows that 3 district judges could share 2 
courtrooms, 3 senior judges could share 1 courtroom, and 2 magistrate 
judges could share 1 courtroom with time to spare. This level of 
sharing would reduce the number of courtrooms the judiciary requires 
by a third for district judges and by more for senior district and 
magistrate judges. For example, courtroom sharing could have reduced 
the number of courtrooms needed in 27 of the 33 district courthouses 
built since 2000 by a total of 126 courtrooms--about 40 percent of the 
total number of district and magistrate courtrooms constructed since 
2000.[Footnote 38] In total, not building these courtrooms and their 
associated support, building common, and other spaces would have 
reduced construction by approximately 946,000 square feet [Footnote 
39] (see figure 11). During our interviews and convening of an expert 
panel on courtroom sharing, some judges raised potential challenges to 
courtroom sharing, such as uncertainty about courtrooms' availability, 
but other judges with sharing experience have overcome those 
challenges when necessary and no trials have been postponed. The 
judiciary has adopted sharing policies for senior and magistrate 
judges in the future, but our analysis shows that additional sharing 
opportunities are available. 

Figure 11: Extra Federal Courthouse Space Constructed Since 2000 Due 
to Judges Not Sharing Courtrooms: 

[Refer to PDF for image: pie-chart] 

Courthouses built since 2000: 13 million gross square feet (GSF); 
946,000 extra square feet due to judges not sharing courtrooms. 

Sources: GAO analysis of GSA data. 

[End of figure] 

Courtrooms Assigned to One Judge Are Used a Quarter of the Time or 
Less for Case Proceedings: 

In 1997, we reported that the district courtrooms in seven locations 
were unused for 115 of 250 federal days in 1995 and recommended that 
the judiciary gather data to determine how much courtroom sharing was 
possible.[Footnote 40] The judiciary implemented this recommendation 
by hiring a consultant to examine space use issues, including 
courtroom utilization. A more recent 2008 study commissioned by the 
judiciary contains the data necessary to determine the level of 
sharing possible for district and magistrate judges.[Footnote 41] The 
study shows that, as of July 2007, on average, a courtroom is 
scheduled to be used 4.1 hours a day for active district judge 
courtrooms, 2 hours a day for senior judge courtrooms, and 2.6 hours a 
day for magistrate judge courtrooms. Beyond that, only half of the 
scheduled courtroom time is actually spent on case-related 
proceedings. Specifically, the 4.1 hours scheduled for the use of 
courtrooms assigned to district judges includes about 1 hour, on 
average, for scheduled events that are subsequently canceled or 
postponed and about 1 hour for events that are not related to case 
proceedings. Events not related to case proceedings include set-up and 
take-down time for attorneys, maintenance, education, ceremonies, and 
other uses. For example, judges said that they would allow their 
courtrooms to be used for public tours and by law schools, and local 
bar associations when available. Figure 12 illustrates the average 
daily uses of courtrooms assigned to single district, senior district, 
or magistrate judges. 

Figure 12: Representation of an Average 8 Hour Day for a Courtroom by 
Type of Judge as of July 2007: 

[Refer to PDF for image: stacked vertical bar graph] 

Type of courtroom: District Judge Courtroom; 
Case proceeding: 1.9 hours; 
Other use: 1 hours; 
Event canceled or postponed: 1.2 hours; 
No event scheduled: 3.9 hours. 

Type of courtroom: Senior District Judge Courtroom; 
Case proceeding: 1 hours; 
Other use: 0.5 hours; 
Event canceled or postponed: 0.5 hours; 
No event scheduled: 6 hours. 

Type of courtroom: Magistrate Judge Courtroom; 
Case proceeding: 1.2 hours; 
Other use: 0.7 hours; 
Event canceled or postponed: 0.7 hours; 
No event scheduled: 5.4 hours. 

Source: GAO analysis of Judiciary data. 

[End of figure] 

These low levels of courtroom usage are consistent across courthouses 
regardless of case filings. Specifically, the judiciary's data showed 
no correlation between the number of weighted and unweighted cases 
filed in a courthouse and the amount of time courtrooms are in use. 
Although the judiciary uses weighted case filings as the measurement 
criteria for requesting additional judgeships, this representation of 
higher levels of activity does not translate into higher courtroom 
usage rates, according to the judiciary's courtroom use data. 
According to the data, courthouses located on the nation's border and 
those with higher pending caseloads do make greater-than-average use 
of their courtrooms, but other courthouses in the same districts 
offset that higher use for district and senior district judges' 
courtrooms. 

There is some consensus in federal court-related literature, and among 
federal judges we interviewed, that there has been a trend toward 
decreasing time spent on trials--the main use of a courtroom. For 
example, some trials have been replaced with other types of case 
resolution, including Summary judgment, settlements, and alternative 
dispute resolution (ADR) that require less use of a courtroom. Court- 
related literature indicates that the use of courtrooms for trials has 
declined since the mid-1960s and the role of judges has changed with 
the changes in case resolution.[Footnote 42] A judge said that the 
decrease in the number of trials does not mean that cases are not 
being resolved--it means they are being resolved through other means, 
including settlement, dismissal, and pleas. Other judges said that 
there has been an increased emphasis on ADR, which is done outside of 
a courtroom by a third-party mediator, as well as an increase in 
Summary judgments, a written procedure that allows speedy disposition 
of a controversy without the need for a trial or a courtroom. 

Increased Courtroom Sharing Is Feasible and Could Reduce the Need for 
Courtrooms By More Than One-Third: 

Based on the low levels of use indicated by the judiciary's data, we 
found that sharing is feasible in 27 of the 33 district courthouses 
built since 2000 and could have resulted in the construction of 126 
fewer courtrooms--40 percent of all district and magistrate courtrooms 
in those courthouses.[Footnote 43] The Design Guide in place when 
these courthouses were built encouraged judicial circuits to adopt 
courtroom-sharing policies for senior judges. However, most of the 
courthouses constructed since 2000 provided enough courtrooms for all 
district and magistrate judges to have their own courtrooms. 

The 2008 study by the judiciary states that the data collected during 
the study could be used with computer modeling to determine how levels 
of use might translate into potential sharing opportunities for 
judges, but that such a determination was outside the scope of the 
study. As a result, we applied generally accepted modeling techniques 
to the judiciary's data to develop a computer model for sharing 
courtrooms. The model ensures sufficient courtroom time for: 

* all case-related activities; 

* all time allotted to noncase-related activities, such as preparation 
time, ceremonies, and educational purposes; and: 

* all events canceled or postponed within a week of the event. 

Under our model, the remainder of time remains unscheduled-- 
approximately 18 percent of the time for district courtrooms and 22 
percent of the time for magistrate courtrooms on average. In this way, 
our model includes substantial time when the courtroom is not in use 
for case proceedings. Some noncase-related events could be held 
outside of normal business hours, and 60 percent of events are 
canceled or postponed within 1 week of the event's original date, 
according to the judiciary's data. Not allocating time in the model 
for these purposes would create even more opportunity for sharing; 
however, we chose to include these data, keep the model conservative, 
and allow for unpredictability. 

The judiciary's report also included a section of case studies based 
on in-depth interviews with judges at courthouses where judges share 
courtrooms. These interviews suggested that courtrooms can be shared 
in two ways(1) through dedicated sharing, in which judges are assigned 
to share specific courtrooms, and (2) through centralized sharing, in 
which all courtrooms are available for assignment to any judge based 
on need. Our model shows the following possibilities for dedicated 
courtroom sharing, with additional unscheduled time to spare (see 
table 5). 

Table 5: Dedicated Courtroom-Sharing Possibilities Based on GAO Model: 

Judges: 3 district judges; 
Dedicated courtrooms needed: 2 district courtrooms. 

Judges: 3 senior district judges; 
Dedicated courtrooms needed: 1 district courtroom. 

Judges: 1 district and 1 senior judge; 
Dedicated courtrooms needed: 1 district courtroom. 

Judges: 2 magistrate judges; 
Dedicated courtrooms needed: 1 magistrate courtroom. 

Source: GAO. 

[End of table] 

Our model shows that centralized sharing improves efficiency by 
increasing the number of courtrooms each judge can access, whereas in 
dedicated sharing judges only use the shared courtroom assigned to 
them. We used the model to estimate how the courtrooms in one 
courthouse could be shared both ways. Specifically, to illustrate the 
increased efficiency of centralized sharing over dedicated sharing, we 
applied the two types of sharing to the current district and 
magistrate judges in the Ferguson Courthouse in Miami, Florida. 
Currently, the Ferguson Courthouse has 26 courtrooms for 26 judges, 
including 12 district judges, 3 senior district judges and 11 
magistrate judges (two of whom are recalled). Under a dedicated 
sharing model, the Ferguson Courthouse could accommodate these judges 
in 15 courtrooms. Under a centralized sharing model, in which all 
district judges have access to all district judge courtrooms and all 
magistrate judges have access to all magistrate courtrooms, the number 
of needed courtrooms is reduced to 14. Table 6 shows the levels of 
sharing possible and the amount of space that could be eliminated for 
all of our seven case study courthouses through centralized sharing. 

Table 6: District, Senior, and Magistrate Judge Courtroom Sharing That 
Could Occur in Selected Courthouses Based on the Judiciary's Data: 

Courthouses: Bryant Courthouse Annex, Washington, D.C.; 
Current number of courtrooms by type with one courtroom per judge: 
District: 20; Magistrate: 3; 
Number of courtrooms needed under centralized sharing: District: 11; 
Magistrate: 2; 
Number of extra courtrooms under centralized sharing: 10; 
Square footage of extra courtroom and associated support and public 
spaces: 74,000. 

Courthouses: Coyle Courthouse, Fresno, Calif.; 
Current number of courtrooms by type with one courtroom per judge: 
District: 3; Magistrate: 4[A]; 
Number of courtrooms needed under centralized sharing: District: 2; 
Magistrate: 2; 
Number of extra courtrooms under centralized sharing: 3; 
Square footage of extra courtroom and associated support and public 
spaces: 20,000. 

Courthouses: D'Amato Courthouse, Islip, N.Y.; 
Current number of courtrooms by type with one courtroom per judge: 
Active District: 7; Magistrate: 4; 
Number of courtrooms needed under centralized sharing: District: 4; 
Magistrate: 2; 
Number of extra courtrooms under centralized sharing: 5; 
Square footage of extra courtroom and associated support and public 
spaces: 35,000. 

Courthouses: DeConcini Courthouse, Tucson, Ariz.; 
Current number of courtrooms by type with one courtroom per judge: 
Active District: 5; Magistrate: 7; 
Number of courtrooms needed under centralized sharing: District: 4; 
Magistrate: 3; 
Number of extra courtrooms under centralized sharing: 5; 
Square footage of extra courtroom and associated support and public 
spaces: 33,000. 

Courthouses: Eagleton Courthouse, St. Louis, Mo.; 
Current number of courtrooms by type with one courtroom per judge: 
Active District: 9; Magistrate: 6; 
Number of courtrooms needed under centralized sharing: District: 5; 
Magistrate: 3; 
Number of extra courtrooms under centralized sharing: 7; 
Square footage of extra courtroom and associated support and public 
spaces: 49,000. 

Courthouses: Ferguson Courthouse, Miami, Fla.; 
Current number of courtrooms by type with one courtroom per judge: 
Active District: 15; Magistrate: 11; 
Number of courtrooms needed under centralized sharing: District: 9; 
Magistrate: 5; 
Number of extra courtrooms under centralized sharing: 12; 
Square footage of extra courtroom and associated support and public 
spaces: 83,000. 

Courthouses: Limbaugh Courthouse, Cape Girardeau, Mo.; 
Current number of courtrooms by type with one courtroom per judge: 
Active District: 2; Magistrate: 1; 
Number of courtrooms needed under centralized sharing: District: 1; 
Magistrate: 1; 
Number of extra courtrooms under centralized sharing: 1; 
Square footage of extra courtroom and associated support and public 
spaces: 7,500. 

Source: GAO analysis of the judiciary's data. 

[A] There are 5 magistrate judges in the Coyle Courthouse, including 1 
vacancy, but only 4 courtrooms. The model was run for 5 magistrate 
judges and the result was that there would need to be 2 magistrate 
courtrooms--eliminating the need for 2 magistrate courtrooms. 

[End of table] 

Some Judges Said They Could Overcome the Challenges to Courtroom 
Sharing: 

We solicited expert views on the challenges related to courtroom 
sharing through interviews with judges and court administrators on 
site visits to courts with sharing experience and assistance from the 
National Academy of Sciences in assembling a panel of judicial 
experts.[Footnote 44] While some judges remained skeptical that 
courtroom sharing among district judges could work on a permanent 
basis, judges with experience in sharing courtrooms said that they 
overcame the challenges when necessary and trials were never postponed 
because of sharing. 

The primary concern judges cited was the possibility that a courtroom 
might not be available. They stated that the certainty of having a 
courtroom available encourages involved parties to resolve cases more 
quickly. They further noted that courtroom sharing could be a 
disservice to the public if it meant that an event had to be 
rescheduled for lack of a courtroom; in that case, defendants, 
attorneys, families, and witnesses would also have to reschedule, 
costing the public time and money. To address the concern that a 
courtroom would not be available when needed, we programmed our model 
to provide more courtroom time than necessary to conduct court 
business. As stated earlier, the model includes time for all case- 
related events, all noncase-related events, all canceled events, all 
postponed events, and approximately 18 percent to 22 percent of 
courtroom time remained unscheduled. Most judges with experience 
sharing courtrooms agreed that court staff must work harder than in 
nonsharing arrangements to coordinate with judges and all involved 
parties to ensure that everyone is in the correct courtroom at the 
correct time, but that such coordination is possible as long as people 
remain flexible and the lines of communication remain open. 
Additionally, some judges said that sharing increased the need for 
coordination, not space. However, one district court official 
cautioned that other indicators of courthouse efficiency were 
negatively affected by sharing; including the time it takes from the 
day a case is filed to when it is resolved. 

Judges who share courtrooms in one district also said that 
coordination is easier when there is a great deal of collegiality 
among judges. A few panel members noted that the design of many 
courthouses today, with judges' chambers located adjacent to 
courtrooms, is not conducive to collegiality or courtroom sharing. 
While this design is convenient for judges who are assigned 
exclusively to the adjacent courtroom, it leads to isolation from 
other judges. Alternative courtroom designs, such as that of the 
Roosevelt Courthouse in Brooklyn, New York, may be more conducive to 
collegiality and sharing. In this courthouse, the chamber and court 
floors alternate so that judges' chambers are not located on the same 
floor as the courtrooms. The chamber floors are completely secure 
because the public does not need direct access to them, and chambers 
are grouped so that judges have greater opportunities to interact. 
This design breaks the apparent association of chambers with specific 
courtrooms without significantly increasing the distance from chambers 
to courtrooms. Another judge suggested perimeter chambers around 
several courtrooms of varying sizes to make courthouses more conducive 
to sharing. 

Another concern about sharing courtrooms was how the court would 
manage when judges have long trials. Judges noted that long trials 
present logistical challenges requiring substantial coordination and 
continuity, which could be difficult when sharing courtrooms. However, 
when the number of total trials is averaged across the total number of 
judges, each judge has approximately 15 trials per year, with the 
median trial lasting 1 or 2 days.[Footnote 45] Hence, it is highly 
unlikely that all judges in a courthouse will simultaneously have long 
trials. Also, a centralized sharing arrangement would allow for those 
who need a courtroom for multiple days to reserve one. 

Panelists' concern about sharing courtrooms between district and 
magistrate judges stems in part from differences in responsibilities, 
which can affect courtroom design and could make formal courtroom 
sharing inappropriate. For example, district judges are 
constitutionally empowered to handle all types of federal cases, 
whereas magistrate judges are hired by the court and are not 
constitutionally empowered to try felony criminal cases. Although 
magistrate judges can try all civil cases with the consent of the 
parties, civil cases do not require as much courtroom space because 
the jury box for civil cases is smaller. Accordingly, the Design Guide 
allots smaller courtrooms with smaller jury boxes to magistrate 
judges. In addition, judges we interviewed said that it would be 
highly unusual for district judges to routinely share courtrooms with 
magistrate judges. To address this concern, our model separated 
district and magistrate judges for sharing purposes, reducing the 
potential for sharing that could occur through cross scheduling in 
courthouses with both district and magistrate judges. 

Judges expressed concern about the compatibility of the current 
scheduling system with courtroom sharing. Most judges keep their own 
schedules through their personal staff, making centralized sharing 
difficult. For example, one concern raised by the panel was that 
sharing was very difficult because judges were unable to access one 
another's calendars or see if a courtroom had been reserved for 
another event. According to panelists, a new calendar system approved 
by the judiciary is also not conducive to sharing because it shows 
judges' Products, but not courtroom Products. One courthouse we 
visited that has a courtroom sharing arrangement overcame this 
challenge by assigning courtrooms centrally through the Clerk of 
Court's office. 

Finally, judges said that increasing the use of technology could help 
overcome some of the challenges to courtroom sharing. Panel judges 
agreed that increased technology saves money; it expedites general 
processing because documents can be submitted to the court 
electronically. Technology makes certain conferences easier through 
the use of teleconferences and videoconferencing. One judge said that 
videoconferencing with a defendant who was being held in a prison 
hundreds of miles away potentially saved thousands of dollars. Another 
judge said that if less money were spent on space, more could be spent 
on technological upgrades to increase flexibility and increase the 
ability to share space among judges. 

The Judiciary Has Taken Some Steps to Increase Sharing in Future 
Courthouse Projects: 

In 2008 and 2009, the Judicial Conference adopted sharing policies for 
future courthouses under which senior district and magistrate judges 
will share courtrooms at a rate of two judges per courtroom plus one 
additional duty courtroom for courthouses with more than two 
magistrate judges. Additionally, the conference recognized the greater 
efficiencies available in courthouses with many courtrooms and 
recommended that in courthouses with more than 10 district judges, 
district judges also share. Our model's application of the judiciary's 
data shows that more sharing opportunities are available. 
Specifically, sharing between district judges could be increased by 
one-third in all but the largest courthouses by having three district 
judges share two courtrooms in all-sized courthouses. Sharing between 
senior district judges could also be increased by having three senior 
judges--instead of two--share one courtroom. If implemented, these 
opportunities could further reduce the need for courtrooms, thereby 
decreasing the size of future courthouses. 

To date, the Judicial Conference has made no recommendations for 
bankruptcy judges to share courtrooms. However, the judiciary is 
conducting a study for bankruptcy courtrooms similar to the 2008 
district court study and expects to complete it in 2010. 

Conclusions: 

It is important for the federal judiciary to have adequate, 
appropriate, modern facilities to carry out judicial functions. 
However, the current process for planning and constructing new 
courthouses has resulted in the 33 federal courthouses built since 
2000 being overbuilt by more than 3.6 million square feet--the size of 
9 average-sized courthouses. This extra space not only cost $843 
million in constant 2010 dollars to construct, but has additional 
annual costs of $52 million in operations and maintenance and rent 
that will continue to strain GSA's and the judiciary's resources for 
years to come. This extra space exists because the courthouses, as 
built, are larger than those congressionally authorized; contain space 
for more judges than are in the courthouses at least 10 years after 
the space was planned, and, for the most part, were not planned with a 
view toward judges sharing courtrooms. 

GSA has not exercised sufficient oversight to ensure that regional GSA 
staff and architects focused on designing courthouses within the 
congressionally authorized gross square footage, as measured according 
to GSA's space measurement policies--and this lack of oversight 
contributed to the construction of courthouses that are larger than 
congressionally authorized. While GSA's appropriations acts include a 
provision stating GSA is to obtain advance approval from the 
Committees on Appropriations if the expenditures for a project will 
exceed the amount included in an approved prospectus by more than 10 
percent, there is no statutory requirement for GSA to notify the 
congressional authorizing or appropriations committees if the size of 
a courthouse project exceeds the congressionally authorized gross 
square footage. Without such a requirement, GSA did not notify 
congressional committees that four courthouses that had cost increases 
of about 10 percent or more were also more than 10 percent larger than 
authorized. In addition, GSA did not focus on avoiding such increases 
during the design and construction of these courthouses--to the extent 
that regional GSA officials involved in the planning and construction 
of several courthouses we visited were unaware until we told them that 
the courthouse projects they worked on were larger than 
congressionally authorized. GSA lacked such mechanisms even though, 
according to GSA officials, controlling the efficiency and gross 
square footage of a building is important to control construction 
costs. One additional contributor to the construction of more tenant 
space than planned is the judiciary's automated space planning tool, 
AnyCourt, which incorporates a standard square footage requirement for 
each district courtroom. However, according to GSA's space measurement 
policy, the amount of a courtroom's square footage doubles if the 
courtroom is designed with a tenant floor cut. Without a mechanism to 
adjust AnyCourt's calculation of a planned courthouse's square footage 
to reflect GSA's space measurement policy when the design includes 
tenant floor cuts, GSA may not request sufficient gross square footage 
to build a courthouse with tenant floor cuts that falls within the 
authorized gross square footage. Further, it is not yet clear whether 
GSA's recent steps to better monitor the size of courthouse projects 
provide sufficient oversight to ensure that courthouses are 
constructed within the congressionally authorized square footage. The 
ongoing confusion that we identified among some GSA regional staff 
about GSA's policies for measuring atriums and the gross square 
footage of courthouses--and the fact that the six most recently 
completed courthouses exceeded the congressionally authorized size--
raise questions about the sufficiency of GSA's oversight improvement 
steps to date. 

The judiciary's inaccurate estimates of future numbers of judges 
further contributed to the size and cost of these courthouses. 
Estimating the number of judges that will be stationed a specific 
location in the future is challenging for a number of reasons, but the 
judiciary usually overestimated the number of judges. Overly 
optimistic projections of growing caseloads, combined with unsupported 
assumptions about the amount of time it would take to obtain 
authorizations for new judgeships, led the judiciary to estimate it 
would have 120 more judges than it actually has at courthouses built 
since 2000. The full extent to which the overly optimistic caseload 
projections contributed to the inaccurate judge estimates is unknown, 
because the judiciary has not analyzed and does not retain its 
caseload projection data. Without analyzing the accuracy of its 
caseload estimates, the judiciary cannot determine what changes to its 
planning for 10-year needs would yield more accurate estimates. 
Furthermore, the interplay between the judiciary's policy of 
authorizing judges districtwide and its need to estimate how many 
judges will be needed at specific locations creates additional 
challenges to accurately estimating future numbers of judges. 

The third major contributor to the extra space in most of the 33 
courthouses built since 2000, the judiciary's one-judge, one-courtroom 
policy--which the judiciary's data show is inefficient--has undergone 
some initial changes, but considerably more efficiencies are possible. 
As our computer modeling has shown, higher levels of courtroom sharing 
would not jeopardize the availability of courtrooms or delay trials, 
and even with the modeled level of sharing, the courtrooms would be 
dark much of the time because of frequent cancellations. Yet, given 
the challenges to effective courtroom sharing raised by some judges we 
spoke with, the transition could be difficult without an effort by the 
judiciary to promote practices that have helped other judges overcome 
the challenges to sharing courtrooms. Such an effort, while a 
challenge to the status quo, could reap long-term benefits for 
taxpayers and the judiciary, since further courtroom sharing could 
significantly reduce the size of new courthouses--as well as the costs 
associated with constructing and renting them. 

While it is too late to reduce the extra space in the 33 courthouses 
constructed since 2000, for at least some of the 29 additional 
courthouse projects underway and for all future courthouse 
construction projects not yet begun, GSA and the judiciary have an 
opportunity to align their courthouse planning and construction with 
the judiciary's real need for space. Such changes would greatly reduce 
construction, operations and maintenance, and rent costs. 

Recommendations for Executive Action: 

In order to improve the planning and oversight for future courthouse 
construction projects and to increase the efficiency of courtroom 
usage through courtroom sharing, we are making six recommendations. 

To ensure that future courthouses are built within the congressionally 
authorized gross square footage, we recommend that the Administrator 
of GSA take the following three actions: 

* Establish sufficient internal control activities to ensure that 
regional GSA officials understand and follow GSA's space measurement 
policies throughout the planning and construction of courthouses. 
These control activities should allow for accurate comparisons of the 
size of a planned courthouse with the congressionally authorized gross 
square footage throughout the design and construction process. 

* To avoid requesting insufficient space for courtrooms based on the 
AnyCourt model's identification of courtroom space needs, establish a 
process, in cooperation with the Director of the Administrative Office 
of the U.S. Courts, by which the planning for the space needed per 
courtroom takes into account GSA's space measurement policy related to 
tenant floor cuts if a courthouse may be designed with courtrooms that 
have tenant floor cuts. 

* Report to congressional authorizing committees when the design of a 
courthouse exceeds the authorized size by more than 10 percent, 
including the reasons for the increase in size. 

In planning for future space needs, we recommend that the Director of 
the Administrative Office of the U.S. Courts, on behalf of the 
Judicial Conference of the United States, improve the accuracy of its 
10-year estimation of judges by taking the following action: 

* Retain caseload projections for at least 10 years for use in 
analyzing their accuracy and incorporate additional factors into the 
judiciary's 10-year judge estimates, such as past trends in obtaining 
judgeships. 

To increase the efficiency of courtroom use, we recommend that the 
Director of the Administrative Office of the U.S. Courts, on behalf of 
the Judicial Conference of the United States, take the following two 
actions: 

* Expand nationwide courtroom sharing policies to more fully reflect 
the actual scheduling and use of district courtrooms. 

* Distribute information to judges on positive practices judges have 
used to overcome challenges to courtroom sharing. 

Agency Comments and Our Evaluation: 

We provided copies of a draft of this report to GSA and AOUSC for 
review and comment and received written comments from both. GSA agreed 
with our recommendation to inform congressional committees when 
courthouses exceed their authorized size by more than 10 percent. 
However, GSA indicated that it has serious concerns with the report 
and takes exception to much of our methodology and many of the 
report's conclusions, commenting that much of the information in the 
report is misleading. GSA's complete comments are contained in 
appendix II, along with our response to specific issues raised. AOUSC 
commented that it has serious concerns about the accuracy of key data, 
the way in which information is presented, and the methodologies 
employed, but indicated that it welcomes constructive and feasible 
recommendations and will implement them as it has in the past. AOUSC's 
complete comments are contained in appendix III, along with our 
response to specific issues raised. In general, we believe our 
methodology, analysis, findings, and conclusions are sound. In 
response to AOUSC's comments, we made some technical clarifications, 
none of which materially affected our findings, conclusions, or 
recommendations. 

GSA Comments: 

In commenting on a draft of our report, GSA cited serious concerns 
with our methodology and many of the report's conclusions and stated 
that much of the information in the report is misleading. As detailed 
below, our methodology applied GSA's policies and data directly from 
original documents and sources. Our conclusions address the 
opportunity to improve courthouse planning and construction for future 
courthouses by quantifying the costs of GSA's lack of oversight on 
past courthouse projects. We believe that our findings are presented 
in a fair and accurate way. 

Regarding our methodology, GSA stated that we assume that upper-level 
space in building atriums is included in the gross square footage of 
an asset. This is true. We included this space in the gross square 
footage calculation because that is GSA's space measurement policy. 
Since at least August 2000, GSA's explicit policy has been and remains 
today to include all levels of atriums and tenant floor cuts in 
measuring the gross square footage of a building. GSA also states that 
we mistakenly ascribed normal operating and construction costs to the 
upper-level space in atriums. This is an oversimplification of our 
cost estimation methodology, which balanced higher cost space, such as 
courtroom and marshal space, with lower cost space, such as the upper 
floors of atriums to create a conservative estimate of the costs 
associated with the extra space in courthouses. Our report indicates 
that, according to GSA, the upper floors of atriums are less expensive 
to construct. However, these spaces represent only a portion of the 
1.7 million square feet built above congressional authorization and 
none of the 1.8 million extra square feet due to overestimating the 
number of judges and not sharing courtrooms. Furthermore, GSA states 
that we retroactively apply courtroom sharing policies to courthouses. 
Our congressional requesters specifically asked that we consider how a 
courtroom sharing policy could have changed the amount of space needed 
in these courthouses. However, our draft and final reports indicate 
that the judiciary's policy at the time was largely to provide one 
courtroom per judge. 

GSA also stated that (1) our cost estimates for the extra space are 
contrived and (2) the final construction costs for 32 of the 33 
exceeded appropriations by $269 million. Our cost estimates were based 
on GSA data and generally accepted construction cost estimation 
methods, and appropriation levels are not relevant to this discussion. 
We validated our cost estimation approach with a number of 
construction industry experts. All agreed that in order to develop an 
order of magnitude estimate for such cost implications, determining 
the cost per square foot of constructing the building was the best 
methodology. GSA's approach of comparing costs with appropriations is 
not relevant because there are numerous reasons why projects can go 
over or under budget. Appropriation levels did not take into account 
that these courthouses could have been much smaller than authorized 
with improved judge estimates and courtroom sharing, and previous 
appropriation levels were not adjusted for inflation. 

AOUSC Comments: 

In commenting on a draft of our report, AOUSC cited concerns about our 
data, presentation, and methodologies but effectively concurred with 
our recommendations and said it will implement them as it has in the 
past. Specifically, AOUSC disputed our conclusion that the 33 
courthouses completed since 2000 have 3.56 million extra square feet. 
In AOUSC's view, it was misleading to conclude that space is extra 
because the actual number of judges in courthouses is smaller than the 
number the judiciary estimated. According to AOUSC, this conclusion 
does not provide a complete picture of the judiciary's need for 
courthouse space, and the shortfall in the actual number of judges has 
occurred, in part, because Congress has not approved all needed new 
judgeships. AOUSC also stated that it was not appropriate for us to 
retroactively apply courtroom sharing policies that were not in effect 
at the time the courthouses were planned. AOUSC further questioned the 
soundness of our courtroom sharing model and maintained that the 
report did not describe the model in enough detail to permit a 
complete analysis of its sufficiency. AOUSC also disputed our 
characterization of the views of the experts who participated in our 
panel on courtroom sharing, in part because of the objections of a 
U.S. District Judge, who participated in the 1-day portion of the 
expert panel. 

We believe our findings, analysis, conclusions, and recommendations 
are well supported by the facts. GAO adheres to generally accepted 
government auditing standards, which ensure the accuracy and relevance 
of the facts within this report. These standards include a layered 
approach to fact validation that includes supervisory review of all 
work papers, independent verification of the facts within the report, 
and the judiciary's review of the facts prior to our release of the 
draft report for agency comment. We also believe that our estimation 
of the extra space in courthouses is appropriate. Our congressional 
requesters specifically asked that we consider how a courtroom sharing 
policy could have changed the amount of space needed in these 
courthouses. However, our draft and final reports indicate that the 
judiciary's policy at the time was largely to provide one courtroom 
per judge. Our report acknowledges the challenges associated with 
estimating future needs for judges, and we continue to believe that 
the judiciary could overcome some of those challenges and improve 
courtroom planning by increasing the accuracy of its caseload 
projections and by being more realistic about the number of authorized 
judgeships it is likely to have after 10 years. 

With regard to our courtroom sharing model, the report contains 
sufficient detail so that anyone with access to the judiciary's data 
and familiarity with discrete event simulation modeling techniques 
could replicate our model. We developed our model to demonstrate the 
benefits of the judiciary developing a policy for courtroom sharing 
based on courtroom scheduling and usage data, not to provide a 
specific model for the judiciary's use. Our analysis of the views of 
the expert panel were based on the results of a 1-day panel session 
with 7 participants and subsequent interviews with 5 additional 
experts who could not attend the 1-day session. We used an official 
transcript of the statements from the 1-day panel to support the facts 
in our report, but none of the experts who participated in the 1-day 
session participated in the individual interviews with experts who 
could not attend the 1-day session. As a result, none of the 
individual experts had the opportunity to hear all experts' views. Our 
report notes that some judges remained skeptical that courtroom 
sharing could work on a permanent basis, but not all the experts held 
that view. In response to AOUSC's comments, we clarified the report 
and added detail to our methodology in appendix I as appropriate. 

We are sending copies of this report to the Director of the 
Administrative Office of the U.S. Courts, the Director of the Federal 
Judicial Center, the Administrator of GSA, and interested 
congressional committees. The report is also available at no charge on 
GAO's Web site at [hyperlink, http://www.gao.gov]. 

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-2834 or goldsteinm@gao.gov. Contact points for 
our offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. GAO staff who made major 
contributions to this report are listed in appendix IV. 

Signed by: 

Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

For the 33 federal courthouses completed since 2000, we examined (1) 
whether the courthouses contain extra space and any costs related to 
it; (2) how the actual size of the courthouses compares with the 
congressionally authorized size; (3) how courthouse space based on the 
judiciary's 10-year estimates of judges compares with the actual 
number of judges; and (4) whether the level of courtroom sharing 
supported by data from the judiciary's 2008 study of district 
courtroom sharing could have changed the amount of space needed in 
these courthouses. The 33 courthouses in our scope included the 
courthouses in table 7. 

Table 7: The 33 Courthouses Completed from 2000 through March 2010: 

Year completed: 2000; 
Courthouse: George U.S. Courthouse, Las Vegas, Nevada; 
Eagleton U.S. Courthouse, St. Louis, Missouri; 
D'Amato U.S. Courthouse, Central Islip, New York; 
DeConcini U.S. Courthouse, Tucson, Arizona; 
Hruska U.S. Courthouse, Omaha, Nebraska; 
U.S. Courthouse Annex, Tallahassee, Florida; 
O'Connor U.S. Courthouse, Phoenix, Arizona. 

Year completed: 2001; 
Courthouse: U.S. Courthouse, Corpus Christi, Texas; 
Johnson U.S. Courthouse Annex, Montgomery, Alabama; 
Quillen U.S. Courthouse, Greeneville, Tennessee. 

Year completed: 2002; 
Courthouse: U.S. Courthouse Annex, London, Kentucky; 
U.S. Courthouse, Hammond, Indiana; 
King U.S. Courthouse, Albany, Georgia; 
Stokes U.S. Courthouse, Cleveland, Ohio; 
Jones Federal Building & U.S. Courthouse, Youngstown, Ohio; 
Simpson U.S. Courthouse, Jacksonville, Florida. 

Year completed: 2003; 
Courthouse: Arraj U.S. Courthouse, Denver, Colorado; 
Perry, Jr., U.S. Courthouse, Columbia, South Carolina. 

Year completed: 2004; 
Courthouse: Russell, Jr., U.S. Courthouse, Gulfport, Mississippi; 
Federal Building & U.S. Courthouse, Wheeling, West Virginia; 
U.S. Courthouse Annex, Erie, Pennsylvania; 
U.S. Courthouse, Laredo, Texas; 
U.S. Courthouse, Seattle, Washington. 

Year completed: 2005; 
Courthouse: Coyle U.S. Courthouse, Fresno, California. 

Year completed: 2006; 
Courthouse: Bryant U.S. Courthouse Annex, Washington, D.C.; 
Roosevelt U.S. Courthouse Annex, Brooklyn, New York; 
Morse U.S. Courthouse, Eugene, Oregon. 

Year completed: 2007; 
Courthouse: Arnold U.S. Courthouse Annex, Little Rock, Arkansas; 
U.S. Courthouse Annex, Orlando, Florida; 
Ferguson, Jr., U.S. Courthouse, Miami, Florida; 
Limbaugh, Sr., U.S. Courthouse, Cape Girardeau, Missouri. 

Year completed: 2008; 
Courthouse: Robinson, III, and Merhige, Jr., U.S. Courthouse, 
Richmond, Virginia; 
U.S. Courthouse, Springfield, Massachusetts. 

Source: GSA. 

[End of table] 

To meet all four objectives, for each of the 33 courthouses in our 
scope, we reviewed the site and design prospectuses, construction 
prospectus, and other relevant fact sheets and housing plans provided 
by the General Services Administration (GSA) to congressional 
authorizing committees to support the request, as well as the 
congressional authorizations provided at the construction phase of the 
project. To understand how much square footage is allocated to 
different types of court space and the process for determining how 
much space is requested for a new courthouse, we reviewed the 1997 and 
2007 editions of the judiciary's Design Guide and examples of the 
judiciary's space program model, AnyCourt, for those courthouse 
projects in our scope for which an AnyCourt model had been developed. 
We discussed verbally and in writing with GSA officials GSA's and the 
judiciary's processes for planning and constructing courthouses, and 
we requested and received written responses to questions related to 
the judiciary's process for determining its space needs. We also 
reviewed prior GAO work on courthouse construction and rent paid by 
the judiciary to GSA, and we researched relevant laws. Furthermore, to 
meet all four objectives, we selected 7 federal courthouses in our 
scope to analyze more closely as case studies. We chose the 7 case 
studies because they provided examples of courthouses that are larger 
than congressionally authorized. In addition, we chose these sites to 
represent a wide distribution of courthouse sizes, dates of 
completion, and geographical locations. Our analysis of courthouse 
size and cost is based on data for all courthouses and major annexes 
completed from 2000 through March 2010. The information specifically 
from our site visits cannot be generalized to that population. These 
case studies included the following courthouses(1) Bryant U.S. 
Courthouse Annex in Washington, D.C.; (2) Coyle U.S. Courthouse in 
Fresno, California; (3) D'Amato U.S. Courthouse in Central Islip, New 
York; (4) DeConcini U.S. Courthouse in Tucson, Arizona; (5) Eagleton 
U.S. Courthouse in St. Louis, Missouri; (6) Ferguson, Jr., U.S. 
Courthouse in Miami, Florida; and (7) Limbaugh, Sr., U.S. Courthouse 
in Cape Girardeau, Missouri. For these courthouses, we analyzed 
blueprints labeled with size and tenant allocations for each space, 
which we requested and received from GSA. For all of these courthouses 
except the DeConcini Courthouse in Tucson, we visited the courthouse, 
where we toured the courthouse and met with court officials, including 
judges, circuit executives, and others involved in planning for 
judicial space needs and requesting and using courthouse space; and we 
met with GSA officials involved in planning, constructing, and 
operating the courthouse. For the DeConcini Courthouse, we reviewed 
workpapers from a prior GAO engagement that included a December 2005 
visit to the Tucson courthouse that involved a tour of the courthouse 
and discussions with court and GSA staff. During our meetings with 
court officials, we discussed issues pertaining to all four of our 
objectives, including the process for determining the size of the 
courthouse needed, the planning and construction of the courthouse, 
and the current uses of courthouse space, including courtrooms and 
chambers, and we sought the officials' views on the potential for more 
than one judge to share a courtroom. 

In addition to these activities, we performed the following work 
related to each specific objective: 

To determine whether the courthouses contain extra space and any costs 
related to it, we added together any extra square footage due to an 
increase in the courthouse's gross square footage over the 
congressional authorization, inaccurate judge estimates, and less 
sharing than is supported by the judiciary's data, as described below 
in the methodology for the other objectives. We consider the sum of 
the extra space as calculated according to the method described in our 
discussion of the following objectives to be the extra space for each 
courthouse. We then discussed how to calculate an order of magnitude 
estimate for the cost of increasing a courthouse's square footage with 
construction experts within GAO, at the Construction Institute of 
America, and at a private sector firm that specializes in developing 
cost estimates for the construction of buildings. All agreed that in 
order to develop with an order of magnitude estimate for such cost 
implications, determining the cost per square foot for constructing 
the building was the best methodology. Based on these conversations, 
we estimated the cost per square foot through the following method: 

* To determine the total construction cost of each courthouse, we 
obtained from GSA the total net obligations, excluding claims, for 
each of the 33 courthouses through September 11, 2009, and determined 
that these data, which equal the total cost of each project as of 
September 11, 2009, were sufficiently reliable for our purposes 
through discussions with GSA officials and by reviewing information 
related to the reliability of these data from a previous GAO 
engagement. GSA officials told us that GSA could not break out the 
construction costs from the total costs of courthouse projects. 
Therefore, except for most annexes, we then subtracted from the total 
project costs the estimates GSA had provided for site, design, and 
management and inspection costs in its construction prospectuses to 
congressional authorizing committees. We consider the resulting figure 
to be an estimate for the total construction cost for each courthouse. 

* We then calculated the construction cost per square foot by dividing 
the construction cost of each courthouse, as calculated above, by the 
gross square footage, as measured using ESmart and reported by GSA, 
for each courthouse. For annex projects that involved substantial work 
on older buildings, we used a different method to determine the 
construction cost per square foot. GSA officials told us that for 
those annexes that involved substantial costs both to renovate an 
older building and to construct a new annex, they could not separate 
the costs of work done on the annex from the costs of any work done on 
the older building. Therefore, we used GSA's estimated cost per square 
foot for constructing the annex, which was reported in the 
construction prospectus, as our figure for the construction cost per 
square foot. 

* We then reduced the construction cost per square foot of each 
courthouse or annex by 10 percent based on discussions with 
construction experts to account for the economies of scale that cause 
the construction cost per square foot to decrease slightly in larger 
buildings. 

* We removed the effect of inflation from the estimates by applying 
two sources of information on annual increases in construction costs--
the Bureau of Economic Analysis's Office Construction Series for years 
up through 2008 and the Global Insight Projections on Commercial 
Construction Costs for 2009 to the present based on each courthouse's 
completion date. 

* Then, we multiplied the sum of the extra square footage by the 
construction cost per square foot for each courthouse to estimate the 
total construction cost implications for each courthouse. 

To estimate the annual costs to rent or operate and maintain the extra 
space, we took the following steps. To the extent practical, we 
determined whether the costs of the extra space were directly passed 
on to the judiciary as rent. If the costs of the space are passed on 
to the judiciary as rent, such as for extra courtrooms, we calculated 
the annual rental costs for the space to the judiciary. To do so, we 
obtained information on the rent payments that the judiciary made to 
GSA for fiscal year 2009, which we determined was reliable for our 
purposes. Then, we multiplied the annual rent per square foot for each 
courthouse by any extra square footage. If the costs of the space are 
not directly passed on to the judiciary as rent (including the costs 
of all the extra space, if any, due to construction above the 
congressional authorization, which we did not attempt to allocate 
between the judiciary, other tenants, and GSA), we calculated the 
annual operations and maintenance costs of the space. To do so, we 
obtained from GSA the total operations and maintenance costs for each 
of the 33 courthouses for fiscal year 2009 and determined that these 
data were sufficiently reliable for our purposes. For each courthouse, 
we divided these costs by the actual gross square footage to come up 
with an operations and maintenance cost per square foot. We then 
multiplied the cost per square foot by any extra square feet. Finally, 
we summed the extra operations and maintenance costs with the extra 
rent costs for all 33 courthouses built since 2000. 

To determine how the actual size of the courthouses compares with the 
congressionally authorized size, we compared the congressionally 
authorized gross square footage of each courthouse with the gross 
square footage of the courthouse as measured by GSA's space 
measurement program, ESmart. We determined that these data were 
sufficiently reliable for our purposes through discussions with GSA 
officials on practices and procedures for entering data into ESmart, 
including GSA's efforts to ensure the reliability of these data. To 
determine the extent to which a courthouse that exceeded its 
authorized size by 10 percent or more had total project costs that 
exceeded the total project cost estimate provided to the congressional 
authorizing committees, we used the same information obtained from GSA 
on the total net obligations (i.e., total project costs), excluding 
claims, for each of these courthouses through September 11, 2009, as 
described above. We compared the total project cost for each 
courthouse to the total project cost estimate provided to the 
congressional authorizing committees in the construction prospectus or 
related fact sheets. We also examined GSA's communications to the 
committees on appropriations for four courthouses that we found 
exceeded the authorized size and estimated total budget by about 10 
percent or more. To increase our understanding of how and why 
courthouse size exceeds congressional authorized size, we reviewed 
GSA's space measurement policy and guidance and discussed these 
documents with GSA officials. We also discussed the reasons that some 
courthouses are larger than congressionally authorized with GSA 
headquarters and regional officials and reviewed written comments on 
the size and space allocations for some of our case study courthouses. 
In addition, for two of the case study courthouses, we contracted with 
an engineer and architect to advise us on analyzing the extra space in 
these courthouses. 

To determine how courthouse space based on the judiciary's 10-year 
estimates of judges compares with the actual number of judges, we used 
courthouse planning documents to determine how many judges the 
judiciary estimated it would have in each courthouse in 10 years. We 
then compared that estimate with the judiciary's data showing how many 
judges are located there including authorized vacancies identified for 
specific courthouses and interviewed judiciary officials. We 
determined that these data were sufficiently reliable for our 
purposes. To determine the effects of any differences, we calculated 
how much excess space exists in courthouses that were estimated to 
have more judges than are currently seated there at least 10 years 
after the 10-year estimates were made. We also discussed challenges 
associated with accurately estimating the number of judges in a 
courthouse with judicial officials and analyzed judiciary data where 
available. 

To determine whether the level of courtroom sharing supported by data 
from the judiciary's 2008 study of district courtroom sharing could 
have changed the amount of space needed in these courthouses, we also 
took the following steps. We created a simulation model to determine 
the level of courtroom sharing supported by the data. The data used to 
create the simulation model for courtroom usage were collected by the 
Federal Judicial Center (FJC)--the research arm of the federal 
judiciary--for its Report on the Usage of Federal District Court 
Courtrooms, published in 2008. The data collected by FJC were a 
stratified random sample of federal court districts to ensure a 
nationally representative sample of courthouses--that is, FJC sampled 
from small, medium, and large districts, as well as districts with 
low, medium, and high weighted filings. Altogether, there were 23 
randomly selected districts and 3 case study districts, which included 
91 courthouses, 602 courtrooms, and every circuit except that of the 
District of Columbia. The data sample was taken in 3-month increments 
over a 6-month period in 2007 for a total of 63 federal workdays, by 
trained court staff who recorded all courtroom usage, including 
scheduled but unused time. These data were then verified against three 
independently recorded sources of data about courtroom use. 
Specifically, the sample data were compared with JS-10 data routinely 
recorded for courtroom events conducted by district judges, MJSTAR 
data routinely recorded for courtroom events conducted by magistrate 
judges, and data collected by independent observers in a randomly 
selected subset of districts in the sample. We verified that these 
methods were reliable and empirically sound for use in simulation 
modeling. 

To create a simulation model, we contracted for the services of a firm 
with expertise in discrete event simulations modeling. This 
engineering services and technology consulting firm uses advanced 
computer modeling and visualization as well as other techniques to 
maximize throughput, improve system flow, and reduce capital and 
operating expenses. Working with the contractor, we discussed 
assumptions made for the inputs of the model and verified the output 
with in-house data experts. We designed this sharing model in 
conjunction with a specialist in discrete event simulation and the 
company that designed the simulation software to ensure that the model 
conformed to generally accepted simulation modeling standards and was 
reasonable for the federal court system. The model was also verified 
with the creator of the software to ensure proper use and model 
specification. Simulation is widely used in modeling any system where 
there is competition for scarce resources. The goal of the model was 
to determine how many courtrooms are required for courtroom 
utilization rates similar to that recorded by FJC. This determination 
is based on data for all courtroom use time collected by FJC, 
including time when the courtroom was scheduled to be used but the 
event was canceled within one week of the scheduled date. 

The completed model allows, for each courthouse, user input of the 
number and types of judges and courtrooms, and the output states 
whether the utilization of the courtrooms does not exceed the 
availability of the courtrooms in the long run. When using the model 
to determine the level of sharing possible at each courthouse based on 
scheduled courtroom availability on weekdays from 8 a.m. to 6 p.m., we 
established a baseline of one courtroom per judge to the extent that 
this sharing level exists at the 33 courthouses built since 2000. In 
selecting the 8 a.m. to 6 p.m. time frame for courtroom scheduling, we 
used the courtroom scheduling profile that judges currently use, 
reflecting the many uses and flexibility needed for a courtroom. 
Judges stated that during trials courtrooms may be needed by attorneys 
before trial times in order to set up materials. This set up time was 
captured in the FJC data; other uses of a courtroom captured by FJC 
are time spent on ceremonies, education, training, and maintenance. We 
differentiated events and time in the model by grouping them as case- 
related events, nonjudge-related events, and unused scheduled time, 
and we allotted enough time for each of these events to occur without 
delay. Then we inputted the number of judges from each courthouse and 
determined the fewest number of courtrooms needed for no backlog in 
court proceedings. 

To understand judges' views on the potential for, and problems 
associated with, courtroom sharing, we contracted with the National 
Academy of Sciences to convene a panel of judicial experts. This 
panel, which consisted of seven federal judges, three state judges, 
one judicial officer, one attorney, and one law professor and scholar, 
discussed the challenges and limitations to courtroom sharing. Not all 
panelists invited were able to attend the 1-day panel, and these 
panelists were individually contacted and interviewed separately. We 
also conducted structured interviews either in person or via telephone 
with 14 federal judges, 1 court staff, 1 state judge, 2 D.C. Superior 
Court judges, 1 lawyer, and 1 academic, during which we discussed 
issues related to the challenges and opportunities associated with 
courtroom sharing. Additionally, we used district courtroom scheduling 
and use data to model courtroom sharing scenarios. We determined that 
these courtroom data were sufficiently reliable for our purposes by 
analyzing the data, reviewing the data collection and validation 
methods, and interviewing staff that collected and analyzed the data. 
Besides the 7 courthouses we selected as case studies, we visited 2 
district courthouses that have experience with sharing--the Moynihan 
U.S. Courthouse in Manhattan, New York, and the Byrne U.S. Courthouse 
in Philadelphia, Pennsylvania. In addition, we visited the Roosevelt 
U.S. Courthouse Annex in Brooklyn, New York, as an example of a 
courthouse with a collegial floor plan. 

We conducted this performance audit from September 2008 to June 2010 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the U.S. General Services Administration: 

Note: GAO comments supplementing those in the report text appear at 
the end of this appendix. 

GSA Administrator: 
U.S. General Services Administration: 
1800 F Street, NW: 
Washington, DC 20405-0002: 
Telephone: (202) 501-0800: 
Fax (209) (210-1243): 
[hyperlink,http://www.gsa.gov] 

June 3 2010: 

The Honorable Gene L. Dodaro: 
Comptroller General of the United States: 
Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20548: 

Dear Mr. Dodaro: 

The U.S. General Services Administration (GSA) appreciates the 
opportunity to review and comment on the draft report, "Federal 
Courthouse Construction: Better Planning, Oversight, and Courtroom 
Sharing Needed to Address Future Costs" (GAO-10-417). 

GSA has serious concerns with this draft report and takes exception to 
much of GAO's methodology and many of the report's conclusions. We 
welcome the opportunity to clarify and correct the information 
presented in this report, as much of this information is misleading: 
[See comment 1] 

* GAO has used a space measurement that assumes upper space in 
building atriums is included in the gross square footage of an asset; 
[See comment 2] 

* GAO compounded this erroneous assumption by mistakenly ascribing 
normal operating and construction costs to these empty volumes; {See 
comment 3] and, 

* GAO retroactively applies a methodology of "courtroom sharing" to 
buildings designed in some cases more than a decade ago, prior to the 
creation of the courtroom sharing policy, and then claims that the 
buildings thus previously designed and built somehow violate this 
retroactive standard. [See comment 4] 

In the enclosed document, we address these concerns in greater detail 
for your consideration in composing the final report. If you have any 
questions or concerns, please contact me. Staff inquiries may be 
directed to Mr. Ralph Conner, Acting Associate Administrator, Office 
of Congressional and Intergovernmental Affairs. He can be reached at 
(202) 501-0563. 

Sincerely, 

Signed by: 

Martha Johnson: 	
Administrator: 

Enclosure: 

[End of letter] 

U.S. General Services Administration's Response to the Government 
Accountability Office's Draft Report: 

Federal Courthouse Construction: Better Planning, Oversight, and
Courtroom Sharing Needed to Address Future Costs: 

The GAO's draft report, titled "Federal Courthouse Construction: 
Better Planning Oversight, and Courtroom Sharing Needed to Address 
Future Costs" (GA0-10-417), determines that GSA has constructed 3.56 
million square feet of extra and unauthorized courthouse space, 
totaling $835 million in construction costs and $51 million annually 
to rent, operate and maintain. GSA strongly disagrees with and 
disputes most of the significant findings in this draft report. 

The dollar amounts are contrived, largely based on phantom space and 
faulty cost calculations. In fact, for 32 of the 33 courthouses 
studied by GAO, total construction costs originally appropriated by 
Congress were $3.05 billion; final costs were $3.32 billion. And the 
additional $269 million was due largely to historically high 
construction cost inflation. The remaining courthouse studied by GAO, 
in Little Rock. Arkansas, is not yet completed. [See comment 5] 

Most egregious is the report's suggestion that GSA and the Courts 
flouted the intentions of Congress. On the contrary, all the spending 
described above was approved in advance by Congress pursuant to 
longstanding procedures. including the additional 258 million. [See 
comment 6] 

It is true that the courthouses built contained more square footage 
than was originally requested by GSA in authorizing prospectuses. 
However, those prospectuses are submitted when only a generic 
courthouse program exists, prior to the detailed architectural and 
engineering design that is necessary to flesh out the program and fit 
it to a particular site. Still, the courthouses were built within 
their authorized cost limits. Moreover, our courthouse projects are 
managed to meet functional needs within budget limitations. [See 
comment 7] 

Background on the Courthouse Construction and Renovation Program - The 
Federal Courts play a critical role in the constitutional framework of 
American democracy. Local, state and Federal courthouses are a 
traditional landmark, dating back to the founding of the Nation. As 
the steward of federally owned buildings, GSA is proud to build 
courthouses worthy of that role. GSA has compiled a solid track record 
of delivering high quality buildings that support the Courts' unique 
needs while enhancing the buildings' surroundings. We do so within 
carefully considered design and budgetary guidelines and pursuant to 
Congressional authorization and appropriations. 

In this draft report, GAO asserts that GSA has constructed additional 
space, costing taxpayers millions of dollars. GSA disagrees with GAO's 
methodology and manner in which the auditors calculated extra space 
built and the associated cost to construct, operate, and maintain this 
space. GAO's assessment of these additional costs misleads Congress 
and the American public. 

Measuring Space - The amount of extra courthouse space constructed, as 
cited in the GAO report, counted all of the square feet in the 
building, including tenant floor cuts and vertical floor penetrations 
[Footnote 1] in multi-story atriums and double height courtrooms that 
are, in reality, "phantom floors." GAO used this phantom square 
footage to calculate additional costs supposedly incurred to complete 
the building. GAO divided the total cost of the facility, excluding 
site costs, design fees and other soft costs, by the gross square 
footage (GSF) of the building. GAO then used this grossly inflated GSF 
number and multiplied it by the alleged amount of additional space GSA 
constructed to determine the cost of the alleged overbuilt space. 
These assertions and calculations are inaccurate and grossly 
misleading. [See comment 8] 

GAO assumes the costs to build and maintain tenant floor cuts and 
multi-story atriums are the same as other building space, such as 
hallways, courtrooms, Marshals holding facilities, or general office 
space. This is an incorrect assumption and significantly overstates 
the cost of constructing and maintaining this phantom floor space in a 
building. Obviously, a square foot of air inside an atrium costs less 
to build, maintain, and operate than a square foot of floor space 
inside an office, courtroom or holding cell. [See comment 9] 

The cost of constructing phantom space in an atrium or double height 
courtroom is only a fraction of the cost of constructing occupied 
space in the building. These phantom spaces do not require slabs of 
concrete, nor do they have finishes such as carpeting or wood 
paneling. The cost of maintaining and operating this type of space is 
less compared to the rest of the facility. For example, the O'Connor 
Courthouse in Phoenix, Arizona and referenced in the report, has an 
atrium that is not air conditioned, so it is fallacious to assume 
these operating costs are the same as the occupied space inside the 
building. This type of space also requires little cleaning, repair or 
maintenance, so operating costs are also minimal. 

Alleged Cost Overruns — GAO also suggests that cost overruns were a 
direct result of constructing this additional 1.7 million square feet 
of space. The increases in construction costs were primarily due to 
unprecedented increases in construction costs during GAO's audited 
time period. This phenomenal cost growth was well documented and was 
due to an industry worldwide building boom that resulted in acute 
material and labor shortages. [See comment 10] 

The Construction Cost Index, as published annually by RS Means, 
reflects a cumulative escalation of 58 percent from October 1, 2000 to 
October 1, 2008, which is during GAO's audit time period. GSA prepares 
cost information years in advance of actual construction. The budget 
inflation factors used to project future costs simply did not keep 
pace with the real inflation happening across the globe. This was a 
common occurrence across the construction industry and was not due to 
a lack of planning foresight on the part of GSA. This too is well 
documented. This industry cost increase, not the design and layout of 
the courthouses, was the major driver for the increase in construction 
costs found by GAO. 

In addition to the unprecedented increase in construction costs, 
during the period covered by the audit, the U.S. was attacked by both 
domestic and international terrorism. As a result of those attacks, 
both our building designs and projects under construction received a 
tremendous increase in security requirements which had a direct impact 
on construction costs and the resultant cost increases associated with 
our projects. 

Congressional Authorization of Additional Space —The GAO report 
implies that GSA has willfully neglected Congressional direction in 
the courthouse program. On the contrary, GSA has scrupulously sought 
and followed regular Congressional authorizations and appropriations 
and has been subject to strict Congressional oversight of the 
courthouse program. We built only courtrooms requested by the 
Judiciary and authorized by Congress. GSA has been forthright and 
transparent in all of our documents, testimony, and briefings to 
Congress throughout the history of our courthouse program. [See 
comment 11] 

GAO asserts that 27 out of the 33 Federal courthouses built since 2000 
are larger than authorized by Congress. GSA disagrees with GAO's claim 
that this additional space contributes considerably to the increase in 
project costs since approximately 50 percent of the supposedly 
additional 1.7 million square footage cited in this report is due to 
vertical floor penetrations associated with atriums, according to 
GSA's estimates. [See comment 12] For example, GAO stated that the 
Springfield Courthouse in Massachusetts exceeded Congressional 
authorization by 17,299 GSF, or 11 percent. GSA disagrees with this 
assertion because 17,606 GSF of this courthouse is associated with 
phantom floors or void space. [See comment 13] 

Reasons for the remaining 50 percent of the alleged 1.7 million square 
feet above authorized amount can be attributed to: 

1) Site limitations and restrictions, such as site configurations and 
grading, can result in less than optimal building construction, 
resulting in design responses that provide less than optimal layout 
for space; 

2) Constructing connections for annexes. One third of the audited 
projects were annexes connected to existing buildings; and; 

3) New requirements not included in the space programming due to new 
design standards, such as LEED and security requirements, as well as 
expanding customer requirements. 

GAO also suggests that GSA should notify Congressional authorizing and 
appropriation committees if the size of a courthouse exceeds the 
Congressional authorized GSF. GSA notifies the appropriate 
Congressional committees when the cost of a project exceeds 10 percent 
of the maximum identified in the prospectus and seeks further approval 
in accordance with 40 U.S.C. § 3307(c). We have multiple levels of 
management and system controls to ensure costs do not exceed this 
threshold without Congressional approval. 

When the original gross square footage is exceeded, GSA often has 
pressing and logical reasons for doing so. For example, during design, 
architects can develop more energy-efficient methods, such as creating 
atriums or light wells to bring natural light into interior windowless 
space within the building that could increase the building's total 
square footage. GSA will ensure that Congress is notified of these 
increases in The future, along with the rationale for the increase. 

In estimating the cost of this additional space, GAO applies current 
GSA policy retroactively in its analysis. Although GSA adopted the 
American National Standards Institute and the Building Owners and 
Managers Association (BOMA) measurement standards in 1997, GSA did not 
establish formal national guidance to include atrium space in the 
gross area calculation until fiscal year 2005. The 33 courthouse 
projects under review by GAO were authorized prior to this policy, so 
applying this policy retroactively inflates the gross area of the 
building during the time of the projects. [See comment 14] 

As discussed in 2009 in the BOMA publication of The Gross Areas of a 
Building: Methods of Measurement, current industry standards exclude 
atrium space in the gross square foot calculation. If GAO were to 
apply this BOMA standard or analyze the 33 projects in context prior 
to the issuance of the formal GSA guidance in 2005, the atrium voids 
would be excluded from the gross square feet, resulting in more than a 
50 percent decrease in square footage above authorized prospectus 
levels. Courthouses such as Greeneville, Laredo, Wheeling, Springfield 
and Richmond would be at or below the square footage given in the 
authorized prospectus by approximately 10,000 — 20,000 square feet. 
[See comment 15] 

Oversight and Controls — GAO asserts that GSA needs additional 
oversight and controls over the management of our courthouse program. 
GSA has implemented additional oversight and controls. Policies are in 
place that require GSA's Central Office and GSA's Regional Offices, 
during the design process, to approve the facilities' measurements and 
ensure they are in line with the appropriation and authorized 
prospectus. Additionally, we have measurement experts, who provide an 
independent evaluation of the design. This evaluation is done during 
the development of the design and compliance with the square footage 
given in the authorized prospectus is necessary to proceed with the 
project. GSA continues to educate our project teams on these policies 
and ensure our measurement experts are involved throughout the 
project's phases to continually review the design and ensure the size 
remains within the authorized amount. [See comment 16] 

Judgeship Projections and Courtroom Sharing — GAO also discusses 
overestimating judgeship projections and courtroom sharing in this 
report. GAO recommends that the Judicial Conference of the United 
States through the Administrative Office of the United States Courts 
improve the accuracy of the planning currently done to estimate 
courtroom needs over a 10-year time horizon. GSA agrees this issue 
warrants further review, since these projections have been 
overestimated in the past. GSA, the Judiciary, and Congress should 
discuss a realistic approach for the future. 

Regarding courtroom sharing, GSA works closely with the Judiciary to 
develop their courthouse requirements. The Judiciary has developed and 
implemented policies that require courtrooms to be shared among 
judges. We commend the Courts for developing these new courtroom 
sharing models, which were developed in recent years. GSA will 
continue to work with the Judiciary on courtroom sharing alternatives. 

GAO audited courthouses that were, in most cases, designed and built 
before the Judiciary and GSA implemented the sharing models. Thus. GAO 
retroactively applies a methodology of "courtroom sharing" to 
buildings designed in some cases more than a decade ago and then 
claims that the buildings thus previously designed and built somehow 
violate this retroactive standard. [See comment 17] 

The current sharing requirement, included initially in the 2007 design 
guide, requires one courtroom for every two senior judges. In 2009, it 
was updated further to require one courtroom for every two magistrate 
judges. The Judiciary and GSA also implemented additional sharing 
policies that were included for the first time for projects funded by 
the American Recovery and Reinvestment Act of 2009. These new 
courtroom sharing policies state that there should be no more than one 
courtroom for every two district judges who are within 10 years of 
their senior eligibility date. Additionally, GSA makes every effort to 
more fully utilize any vacant space in a courthouse previously built. 
GSA and the Judiciary are committed to the courtroom sharing policies 
for current and future courthouse projects. 

In conclusion, GSA will continue to work with the Judiciary in 
designing Federal courthouses that meet the Courts' needs. GSA helps 
the Judiciary shape their requirements and ensure buildings are 
constructed efficiently, considering cost, space, and energy needs, 
with sufficient controls and oversight. Working with the Courts, GSA 
will use courtroom sharing practices and review judgeship projections. 
As recommended by GAO, GSA will also notify the appropriate 
Congressional committees when the square footage increase exceeds by 
10 percent or more the maximum identified in the prospectus. [See 
comment 18] 

Footnote: 

[1] Vertical floor penetrations are air space within a building 
created by the absence of a floor slab Tenant floor cuts are the upper 
portion of a tenant space that expands into the floor above, if a 
floor were present in this upper area, it could be used for office 
space. This space could also be the upper air space of a double-height 
courtroom. 

The following are GAO's comments on the U.S. General Services 
Administration letter dated June 3, 2010. 

GAO Comments: 

1. GSA stated that it has serious concerns with much of our 
methodology and many of the report's conclusions and that much of the 
information in the report is misleading. As detailed in the next three 
comments, our methodology applied GSA's policies and data directly 
from original documents and sources. Our conclusions were meant to 
improve courthouse planning and construction for future courthouses by 
quantifying the costs related to GSA's lack of oversight on past 
courthouse projects, not to suggest the methodology should have been 
applied retroactively. We believe that our information is presented in 
a fair and accurate way in illustrating how past problems with the 
courthouse program could affect future courthouse projects. 

2. GSA stated that GAO assumes that upper-level space in building 
atriums is included in the gross square footage of an asset. This is 
true. We included this space in the gross square footage calculation 
because that is GSA's space measurement policy. Since at least August 
2000, GSA's written policy has been and remains today to include all 
levels of atriums and tenant floor cuts in measuring the gross square 
footage of a building. 

3. GSA stated that we mistakenly ascribed normal operating and 
construction costs to the upper-level space in atriums. This is an 
oversimplification of our cost estimation methodology, which balanced 
higher cost space, such as courtroom and marshal space, with lower 
cost space, such as the upper floors of atriums, to create a 
conservative estimate of the costs associated with the extra space in 
courthouses. Our report indicates that according to GSA, the upper 
floors of atriums are less expensive to construct and operate. 
However, these spaces represent only a portion of the 1.7 million 
square feet built above congressional authorization and none of the 
1.8 million extra square feet due to overestimating judges and not 
sharing courtrooms. For example, GSA's analysis that appears later in 
its comments on our report (see p. 61) indicate that about 850,000 
square feet of the space constructed in excess of the congressionally 
authorized gross square footage is upper-level space in atriums--
meaning that 2.7 million square feet--or about 75 percent--of the 
extra space in courthouses may be higher-cost space. 

4. GSA stated that we retroactively applied courtroom sharing policies 
to courthouses. Our congressional requesters specifically asked that 
we consider how a courtroom sharing policy could have changed the 
amount of space needed in these courthouses. However, our draft and 
final reports indicate that the judiciary's policy at the time was 
largely to provide one courtroom per judge. 

5. GSA stated that (1) our cost estimates for the extra space are 
contrived and (2) the final construction costs for 32 of the 33 
courthouses exceeded appropriations by $269 million. Our cost 
estimates were based on GSA data and generally accepted construction 
cost estimation methods, and appropriation levels are not relevant to 
this discussion. We validated our cost estimation approach with a 
number of construction industry experts. All agreed that in order to 
develop an order of magnitude estimate for such cost implications, 
determining the cost per square foot of constructing the building was 
the best methodology. GSA's approach of comparing costs with 
appropriations is not relevant for the following reasons: 

* There are numerous reasons why construction projects can go over or 
under budget. For this report, we did not conduct a detailed 
examination of GSA's process of estimating courthouse construction 
costs. However, it does stand to reason that the cost overruns would 
have been lower or nonexistent if the courthouses had been constructed 
within the congressionally authorized gross square footage limits. For 
example, our report states that because the construction costs of a 
building increase when its gross square footage increases, cost 
overruns for the Coyle U.S. Courthouse in Fresno would have been 
smaller or might have been eliminated if the courthouse had been built 
within the authorized square footage. As discussed in the report, the 
courthouse is about 16 percent larger than authorized and cost about 
$13 million, or 11 percent, more than estimated when congressionally 
authorized its construction. 

* We suggest that the extra square footage due to GSA constructing the 
courthouses larger than authorized may have contributed to cost 
overages. However, about half of the extra square footage we found--
and therefore about half of our estimated construction costs--are 
attributable to over estimating the number of judges and not sharing 
courtrooms. This extra space was factored into the plans and, thus, 
would be factored in to the appropriations, for the courthouses. 
Reducing this space would, therefore, be likely to have led to a 
corresponding reduction in the courthouses' appropriations. 

* Even if relevant, GSA's estimate of $269 million spent over 
congressional appropriations does not appear to have been adjusted for 
inflation. Adjusting GSA's cost estimate for inflation would most 
likely increase it significantly, since the courthouses we reviewed 
were completed up to 10 years ago. 

6. According to GSA, our report suggests that GSA and the judiciary 
purposefully disregarded the intentions of Congress. This is not the 
case. While it is unclear to what extent GSA was aware that the 
courthouses we reviewed exceeded their authorized gross square 
footage, the report does not indicate that GSA or the judiciary 
purposefully disregarded congressional authorizations. Instead, we 
found that GSA lacked sufficient oversight and controls to ensure that 
courthouses were planned and built as authorized. 

7. GSA acknowledged that the courthouses built since 2000 contain more 
square footage than GSA requested in the prospectuses and 
congressionally authorized. We understand that prospectuses are 
submitted for courthouses before their detailed architectural and 
engineering designs are completed, but the congressionally authorized 
gross square footage is to be the maximum allowable gross square 
footage. As we reported, GSA lacked the oversight and controls to 
ensure that 27 of the 33 courthouses we reviewed were designed and 
constructed within the authorized gross square footage. 

8. GSA described the upper-level floors of atriums and "double-height 
courtrooms" as "phantom floors" and stated that the incorporation of 
these spaces grossly inflates the gross square footage amounts for 
courthouses. These spaces are not phantom floors--they increase the 
volume and cost of buildings, and it is GSA--not GAO--that chose to 
count them as part of a building's gross square footage. As discussed 
in comment 2, our calculations are based entirely on GSA's 
longstanding space measurement policy. 

9. See comment 3. 

10. See the first bullet of comment 5. 

11. See comment 6. 

12. GSA questioned our finding that 27 of the 33 federal courthouses 
built since 2000 are larger than congressionally authorized and that 
this extra square footage has significant cost implications. The extra 
1.7 million square feet of extra space built above congressional 
authorization is substantial, representing 13 percent of all 
courthouse space built since 2000, and was also expensive to construct 
because gross square feet is a key construction cost driver. See 
comments 2 and 3 for additional discussion of these issues. 

13. Our report does not provide any data on the square footage of the 
Springfield courthouse, other than its inclusion in Figure 3 as being 
10-20 percent larger than authorized, because it was not one of the 7 
courthouses we selected for case studies. GSA appears to have 
calculated the overage for this courthouse as we did for the 
courthouses in our review by comparing the congressional authorization 
with the gross square footage measurement in GSA's ESmart database. 
GSA's calculation of the overage--17,299 gross square feet, or 11 
percent more than authorized--includes the square footage of the upper 
levels of the atrium and tenant floor cuts, consistent with GSA's 
policy. Moreover, the total project cost of the Springfield Courthouse 
was about $65 million, more than 20 percent over the estimated total 
project cost of about $53 million provided to congressional 
committees. As discussed in comment 5, we did not fully analyze the 
reasons for cost overruns in the courthouses we reviewed, including 
the Springfield Courthouse. But because a building's construction 
costs increase with its gross square footage, cost overruns for the 
Springfield Courthouse would likely have been reduced if it had been 
built with a smaller atrium or less void space. The extent to which 
GSA overbuilt the public and nontenant spaces becomes clear through 
the efficiency rating. GSA specifies that 67 percent of the space in 
courthouses should be tenant spaces--or 67 percent efficient--but only 
50 percent of the Springfield Courthouse is tenant space. In other 
words, half of the courthouse's space is dedicated to public 
circulation, mechanical, and other nonmission-related spaces. 

14. GSA stated that we applied current GSA policy retroactively in 
estimating the costs of additional courthouse space and maintained 
that it did not establish formal national guidance to include atrium 
space in the gross area calculation until fiscal year 2005. GSA 
incorrectly represents the evolution of its policy. GSA's policy 
manual dating from August 2000 instructs that all levels of atriums 
and tenant floor cuts be included in the gross square footage of a 
building. In our report, consistent with this evidence, we state that 
GSA had this space measurement policy since at least 2000, but did not 
ensure that it was understood and followed. Moreover, GSA has not 
demonstrated it is enforcing this policy because all 6 courthouses 
completed since 2007 exceed their congressionally authorized size. 

15. GSA suggested that we should have applied 2009 Building Owners and 
Managers Association (BOMA) standards to measure the gross square 
footage of the courthouses we reviewed. We believe it is appropriate 
to apply GSA's own policies to develop our estimates, and we, 
therefore, used the square footage numbers GSA provided us from its 
ESmart program and in blueprints. 

16. GSA commented that it has implemented additional oversight and 
controls over its courthouse program. However, as we state in our 
report's conclusion, it is not yet clear whether GSA's recent steps to 
better monitor the size of courthouse projects provide sufficient 
oversight to ensure that courthouses are constructed within the 
congressionally authorized square footage. The ongoing confusion that 
we identified among some GSA regional staff about GSA's policies for 
measuring atriums and the gross square footage of courthouses--and the 
fact that the six most recently completed courthouses exceeded the 
congressionally authorized size--raise questions about the sufficiency 
of the steps GSA has taken to date to improve its oversight. Our 
recommendation for GSA to establish sufficient internal control 
activities to ensure that GSA space measurement policies are followed, 
therefore, remains unchanged at this time. 

17. See comment 4. 

18. GSA agreed with our recommendation to notify congressional 
authorizing committees when the design of a courthouse exceeds the 
authorized size by more than 10 percent, including the reasons for the 
increase in size. However, to ensure that future courthouses are built 
within the congressionally authorized gross square footage, it is 
important that GSA also implement our other two recommendations: to 
establish sufficient internal control activities to ensure that 
regional GSA officials understand and follow GSA's space measurement 
policies throughout the planning and construction of courthouses; and 
to establish a process, in cooperation with the Director of the 
Administrative Office of the U.S. Courts, by which the planning for 
the space needed per courtroom takes into account GSA's space 
measurement policy related to tenant floor cuts if a courthouse is 
designed with courtrooms that have tenant floor cuts. 

[End of section] 

Appendix III: Comments from the Federal Judiciary: 

Note: GAO comments supplementing those in the report text appear at 
the end of this appendix. 

Administrative Office Of The United States Courts: 
James C. Duff, Director: 
Washington, D.C. 20544: 

June 1, 2010: 

Mr. Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Dear Mr. Goldstein: 

I write on behalf of the Federal Judiciary in response to the draft 
report entitled, Federal Courthouse Construction. Better Planning, 
Oversight, and Courtroom Sharing Needed to Address Future Costs (GAO-
10-417). The Judiciary takes its stewardship responsibilities 
seriously and would welcome a fact-based and objective analysis as 
well as constructive suggestions for improving our facilities planning 
approach. It is regrettable at a time when the General Services 
Administration (GSA) and the Federal Judiciary arc working closely and 
effectively to control courthouse costs — including current and 
planned courtroom-sharing measures adopted by the Judiciary — that GAO 
has produced a misinformed report that distorts both the current 
facilities planning process and prior projects. 

In short, we have serious concerns about the accuracy of key data, the 
misleading way in which information is presented, and the soundness of 
methodologies employed to substantiate the draft report's conclusions. 
We emphatically dispute the draft report's contention that the 33 
federal courthouses completed since 2000 have 3.56 million square feet 
of unnecessary and wasted space; and we have grave doubts about the 
validity and viability of the courtroom-sharing model developed by 
GAO. [See comment 1] 

We are also deeply troubled that the draft report issued by the GAO 
under strict disclosure restrictions was released to the public by GAO 
as its testimony to Congress on May 25, 2010, before Judiciary and GSA 
officials had provided comments. Additionally, after hearing GSA's and 
the Judiciary's testimony before the House Subcommittee on Economic 
Development, Public Buildings and Emergency Management of the 
Committee on Transportation and Infrastructure disputing key facts 
underlying the draft report's conclusions, you nevertheless discussed 
those conclusions on Federal News Radio. [See comment 2] 

This letter describes concerns related to those aspects of the draft 
report that pertain directly to the Federal Judiciary's programs and 
policies. A companion Judiciary response is enclosed in the form of a 
letter from the Honorable Loretta A. Preska, Chief Judge. United 
States District Court for the Southern District of New York. Chief 
Judge Preska's letter decries GAO's misleading characterization of her 
district's temporary experience with courtroom sharing as proof of the 
long-term efficacy of sharing by district judges (as asserted by GAO 
obliquely in the draft report and explicitly at the May 25 hearing); 
and it refutes the accuracy of the draft report's portrayal of an 
expert-panel discussion in which she participated. The draft report 
also covers important issues that are under the purview of the GSA, 
which will be responding separately. [See comment 3] 

We appreciate that the internal review process within GAO strives to 
ensure the objectivity and fairness of reports as well as the accuracy 
of facts and analyses. It is worrisome, however, that a senior member 
of the GAO audit team disclosed a predilection for a particular 
outcome when he told a group of Judiciary officials that more 
courtroom sharing would be coming and there would be no point in 
arguing against it. It appears that the audit team's zeal to meet 
certain objectives may have compromised its ability to be entirely 
objective and fair. It may be too late to change false impressions 
already generated by the premature disclosure and discussion of an 
unreviewed draft report, but it is not too late to make corrections 
and you expressed a willingness to do this during the May 25 hearing. 
We hope these comments will be helpful to GAO to produce a final 
product that will satisfy its high standards of quality. objectivity, 
and fairness. Primary issues are outlined below, followed by more 
detailed analysis. [See comment 4] 

* For the 33 courthouses studied by GAO, the Judiciary's courtroom 
policies in effect at that time were used to determine the number of 
courtrooms needed in each facility and these numbers were authorized 
by Congress. Those policies provided a courtroom for each judge. 
Auditors typically review actions and operations against the policies 
and rules in effect at the time. Instead, GAO has manufactured its own 
rules in the course of this study regarding how many courtrooms it 
thinks should be provided to judges, and it has applied these untested 
and unapproved rules retroactively to the 33 courthouses that were 
already built. The report attributes to this made-up concept 946,000 
excess square feet. [See comment 5] 

* Because of GAO's retroactive application of its notion about 
courtroom sharing, this draft has defined as excess and wasted space 
courtrooms that currently are assigned to and used daily by federal 
judges. This is not reasonable. [See comment 6] 

* It is misleading to suggest that 887,000 extra square feet exist 
because of inaccurate estimates of judges for the 33 courthouses 
studied. GAO's snapshot approach to counting heads simply does not 
provide a complete picture. For example, the draft report supports
its conclusion that the Judiciary's planning process overstates the 
need for judges by showing photographs of unassigned chambers' suites 
in the Coyle Courthouse in Fresno, California (on p. 29). The Eastern 
District of California is desperately in need of additional judges. 
Its caseload per judge is the highest in the nation (with over 1000 
cases per district judge, it has twice the national average caseload), 
and additional judgeships arc currently pending approval by Congress. 
To suggest that those empty chambers are because of poor planning or 
are unneeded is absurd. [See comment 7] 

* The draft report focuses a great deal of attention on courtrooms, 
but nowhere in the report is a table indicating the numbers of 
courtrooms and judges in the courthouses studied. [See comment 8] For 
a fact-based analysis of courtrooms, the absence of such vital data is 
surprising. The facts present a different picture than what has been 
suggested. Our analysis of facts (actual data on courtroom numbers, 
current judges, existing vacancies, soon-to-be vacant authorized 
positions, and pending new judgeships) indicates that for most of the 
33 courthouses studied, either all courtrooms are assigned now, or 
they will be shortly or n the next few years. Moreover, these 
courthouses must suffice for many decades of occupancy. [See comment 9] 

* Based on the limited information provided about the simulation 
model, it is highly doubtful that GAO's courtroom-sharing model is 
sufficiently sound to he worthy of publishing, much less touted as an 
alternative to the carefully studied courtroom-sharing policies that 
have been promulgated over the last few years by the Judiciary. 
Running a simulation model for courtroom sharing requires making a 
large number of assumptions about case processing. It appears that the 
model was developed without the involvement of any experts in the 
judicial process and included some invalid assumptions. The draft 
report does not describe this model in the level of detail typically 
presented in research products to enable its assumptions and methods 
to be critically scrutinized. GAO has steadfastly refused to provide 
this information. Minutes after the May 25 hearing concluded, despite 
the Subcommittee's request that the GAO work collaboratively with the 
Judiciary and GSA and make available these assumptions, GAO pointedly 
refused to share them. If the model is well-grounded, why has GAO 
withheld this critical information? [See comment 10] 

* GAO has suggested that a one-day confidential meeting of an expert 
panel convened by GAO and the National Academy of Sciences helped to 
develop assumptions used for the simulation model. All of the 
Judiciary's participants in that panel have repudiated the 
representation of the panel discussion that appears in the draft 
report. A panel member's comprehensive and detailed critique is 
enclosed with this response. [See comment 11] 

* GAO's conclusions about feasible courtroom-sharing formulas do not 
appear to be supported by the source data. For example, courtroom-
usage data provided by the Federal Judicial Center and used by GAO to 
develop the model showed that courtrooms in the top quartile of use 
during the study period had an average 6.6 hours of use per day. This 
level of usage would appear to leave approximately one hour free in a 
typical workday for other use. In a three-judge courthouse, for 
example, if the judges each needed to use a courtroom for 6.6 hours 
each day but had to share one or two courtrooms as suggested by GAO, 
there clearly would be insufficient courtroom availability, and this 
would result in serious delays in the administration of justice.
Additional details about these and other issues are provided below. 
[See comment 12] 

Evolution of the Judiciary's Facilities Planning Process: 

The GAO report is critical of the Judiciary's planning process. 
Predicting what will happen in the future is, to say the least, 
challenging, and the GAO has recognized these challenges. A 1993 GAO 
report titled, Federal Judiciary Space: Long-Range Planning Process 
Needs Revision (GAO/GGD-93-132, Sept. 28, 1993), also noted that: 

GAO recognizes that it is difficult to project future space needs with 
precision. The projection of needs is not an exact science, and in the 
final analysis, it is reasonable to expect some variation between the 
estimate and what is actually needed. Space estimates are particularly 
challenging for the judiciary because there are numerous factors that 
cause changes in the workload, and therefore space needs, which are 
beyond its control. 

It can take upwards of 15-20 years from the time of initial planning 
to occupancy of new federal courthouses. During that time 
circumstances change: judgeship hills are not passed when anticipated, 
judges do not take senior status when planned, and judges retire or 
die. In addition, caseloads can fluctuate, prosecutorial policies 
change, and federal jurisdiction can expand — all impacting the 
workload of the federal courts. But once the decision is made to size 
a building based on a certain set of assumptions, it becomes very 
difficult and costly to change course mid-stream. To do so results in 
expensive change orders and a building that is not likely to meet 
longer-term needs. 

The Judiciary was one of the first entities in government to establish 
a systematic approach to space and facilities planning. In the mid-
1980s, the Judiciary began its formal facilities program to address 
problems associated with outdated and antiquated courthouses, the need 
for additional space to accommodate a growing Judiciary, and security 
issues. We have continued to improve and refine our space-planning 
process as additional data have been gathered and analyzed. Thus, the 
methodologies used in planning the courthouses studied by GAO have 
changed.
The Judiciary has been open to suggestions for improvements made by 
outside entities, and has adopted recommendations previously made by 
GAO and by private-sector consultants. Some of the improvements 
include use of multiple forecasting methods, review of the accuracy of 
the prior year's forecasts, and re-instituting the on-site planning 
sessions in each district and comprehensive facility evaluations of 
each courthouse. Perhaps most dramatically, the Judiciary stopped its 
space planning process entirely in 2004 so that it could, once again, 
re-evaluate its planning methodology with a view toward cost 
containment. The Judicial Conference, the Judiciary's policymaking 
body, determined that the long-range planning process should be 
modified to ensure that the courts with the most urgent space needs 
were highlighted. The courts now employ a new long-range facilities 
management process known as Asset Management Planning to assess 
facilities needs on a go-forward basis. The process was developed as 
an objective methodology that identifies costs and benefits for 
alternative housing solutions such as renovating existing space. We 
have worked with the GSA to contain costs, including implementing cost 
controls for the approval of deviations from space standards. 

Amount of Excess Space: 

The draft GAO report asserts that many courthouses have not been fully 
occupied and it suggests that what it then deems to be "excess" space 
constitutes a waste of funding. There arc several reasons to question 
the validity of these conclusions. One key question concerns the 
number of courtrooms and judges in these facilities. We analyzed the 
33 buildings identified by GAO and found that in most of these 
buildings, the number of courtrooms is either equal to the number of 
judges in the building, or will be equal to or be very close to the 
number of judges to be housed in the building once vacancies are 
filled and required new judgeships are approved. [See comment 13] It 
also appears from the draft report that GAO did not always take into 
account congressionally authorized vacant judgeship positions in its 
analysis. The building sizes authorized by Congress assumed that 
vacant, congressionally authorized judgeship positions would be filled 
at these locations, that senior district judges and magistrate judges 
would not be sharing courtrooms, and that space would be provided for 
future new judgeship positions. It is more appropriate to apply the 
planning policies in place at the time to determine whether we met or 
came close to our projections. [See comment 14] 

Out of the 33 courthouses studied, GAO chose to highlight six (p. 28) 
to demonstrate what appear to be large differences between planned and 
actual numbers. It is not clear how GAO calculated the numbers in this 
table. To provide a much simpler and understandable assessment of 
whether there is excess space in these courthouses, we have produced a 
table below that indicates for each courthouse the number of district, 
magistrate and bankruptcy judges compared to the number of courtrooms 
for these judges. The table below shows a very different picture. All 
of the courtrooms in these facilities are expected to be assigned 
within the next few years, and in three of the six courthouses there 
will be fewer courtrooms than judges. 

Table: Number of District and Bankruptcy Judges & Courtrooms at GAO's 
Selected Courthouses (By 2016): [See comment 15] 

Bryant/Prettyman CHs Washington, DC: 
Current Number of Judges & Vacancies: 24; 
Pending New Judgeships Anticipated: 0; 
Judges Eligible for Senior Status by 2016: 9; 
Possible Number of Judges by 2016: 33; 
Current Number of Courtrooms: 27; 
Surplus/Deficit Number of Courtrooms by 2016: (6). 
						
Coyle CH, Fresno, CA: 
Current Number of Judges & Vacancies: 10; 
Pending New Judgeships Anticipated: 3; 
Judges Eligible for Senior Status by 2016: 1; 
Possible Number of Judges by 2016: 14; 
Current Number of Courtrooms: 14; 
Surplus/Deficit Number of Courtrooms by 2016: 0. 

D'Amato CH Central Islip, NY: 
Current Number of Judges & Vacancies: 15; 
Pending New Judgeships Anticipated: 2; 
Judges Eligible for Senior Status by 2016: 2; 
Possible Number of Judges by 2016: 19; 
Current Number of Courtrooms: 19; 
Surplus/Deficit Number of Courtrooms by 2016: 0. 

DeConcini CH Tucson, AZ: 
Current Number of Judges & Vacancies: 12; 
Pending New Judgeships Anticipated: 1; 
Judges Eligible for Senior Status by 2016: 3; 
Possible Number of Judges by 2016: 16; 
Current Number of Courtrooms: 14; 
Surplus/Deficit Number of Courtrooms by 2016: (2). 

Eagleton CH St. Louis, MO: 
Current Number of Judges & Vacancies: 19; 
Pending New Judgeships Anticipated: 0; 
Judges Eligible for Senior Status by 2016: 1; 
Possible Number of Judges by 2016: 20; 
Current Number of Courtrooms: 20; 
Surplus/Deficit Number of Courtrooms by 2016: 0. 

Ferguson/King Atkins CHs Miami, FL: 
Current Number of Judges & Vacancies: 25; 
Pending New Judgeships Anticipated: 1; 
Judges Eligible for Senior Status by 2016: 7; 
Possible Number of Judges by 2016: 33; 
Current Number of Courtrooms: 27; 
Surplus/Deficit Number of Courtrooms by 2016: (6). 
						
Note: Our analysis includes all district, magistrate and bankruptcy 
judge types and authorized vacancies not covered by recalled judges. 

[End of table] 

There are factual corrections previously provided to GAO in response 
to a "Statement of Facts" that should be made. For example, GAO states 
(on p. 31) that the U.S. District Court for the District of Columbia 
had projected 14 senior judges by the end of the 10-year planning 
period. [See comment 16] The correct projected number of senior 
district judges is 7. Also, GAO incorrectly reports that the district 
court currently has 9 fewer senior judges than estimated. The correct 
number is I. Within the next 6 years, that district court will have 9 
additional judges who will be eligible for senior status. On page 32, 
the draft reports an incorrect figure. There are 5 not 4 pending new 
district judgeships in the Eastern District of California. [See 
comment 17] 

As noted in the draft report, there are locations where we did not 
meet our projections. Several of these buildings were planned at the 
inception of our planning process -- a process that has evolved over 
time. With the adoption of courtroom sharing policies for senior 
district judges and magistrate judges approved by the Judicial 
Conference in 2008 and 2009, many of these locations will now be able 
to support the operations of the Judiciary and the U.S. Marshals
Service well beyond the initially planned 10-year time frame. It is 
misleading to say that the space is "extra" because of incorrect judge 
estimates. The space will be needed at some point in the
near future. It may not be needed until the 12th year or the 14th year 
from the time design of the building started, but it will be needed. 
[See comment 18] 

The draft report charges that "the Judiciary's method of estimating 
judges does not account for uncertainty in when judges will take 
senior status and in how many new judgeships will be authorized." To 
account accurately for "uncertainty" would seem to he an oxymoron. The 
draft report states that the Judiciary's estimates were based on 
"unsupported assumptions about the amount of time it would take to 
obtain authorizations for new judgeships." This is false. When the 
courthouses studied by GAO were planned, Congress regularly enacted 
new judgeship legislation. In fact, up until 1990, Congress had passed 
comprehensive judgeship legislation about every six years, including 
1978, 1984, and 1990: These hills added hundreds of new judgeships to 
the courts, and this history formed a reasonable basis for the 
planning assumptions. Likewise, history regarding when eligible 
judges, on average, tended to take senior status formed the basis for 
the planning assumptions. [See comment 19] 

Although Congress has not passed regular comprehensive judgeship 
legislation in recent years, in the past two decades, the Judiciary 
has gained 103 district judgeships, 61 bankruptcy judges, and 210 
magistrate judges. The draft GAO report criticizes the Judiciary for 
continuing to plan space for new judgeships — however, if Congress had 
enacted our requests, as they had historically done, and we had not 
planned chambers and courtrooms for these judges, there would have 
been a critical shortfall of space around the country. 

The draft report incorrectly characterizes space provided for visiting 
judges by stating that it is a way of building "extra" space (p. 30). 
In smaller courts with few judges, it is not unusual to have all the 
Article III judges recuse themselves because of a connection or 
conflict with one of the parties. In other courts, judges are assigned 
from other districts or circuits to assist with a surge in workload. 
And, in some courts, judges travel from one division within a district 
to another because there are not enough judges at any one location to 
handle the caseload. When these circumstances exist, smaller chambers 
and sometimes a courtroom dedicated to use by visiting judges is 
provided. Characterizing this space as "extra" space because it is not 
assigned to a specific judge demonstrates a fundamental 
misunderstanding of how the judicial system operates at some 
locations. [See comment 20] 

We are sensitive to the costs of constructing courthouses, and we are 
willing to consider reasonable changes to our planning assumptions to 
reduce the risk of significant over-projections of future needs. 
Failing to take into account requested judgeships that are already 
needed because of existing caseload, but that have not yet been 
authorized by Congress, would he imprudent.
Most courthouses are occupied for many decades. To employ a planning 
process that could never result in unassigned space would be extremely 
shortsighted, would risk having inadequate capacity to house needed 
judges and staff for the future, and would therefore reduce the useful 
life of these courthouses. [See comment 21] 

Courtroom Sharing: 

The Judicial Conference has adopted several significant policy changes 
that included a policy to provide one courtroom for every two senior 
judges, and a policy to provide one courtroom for every two magistrate 
judges. In addition, a courtroom usage study of bankruptcy courts is 
currently underway and after a determination is made regarding the 
bankruptcy courts, the Judiciary will consider a courtroom sharing 
policy for courthouses with more than 10 active district judges. These 
are major changes to the courtroom allocation policies for the Federal 
Judiciary, which were made only after a great deal of consideration of 
their impact on the litigation process and the delivery of justice. 

While these policies were not in effect at the time the 33 courthouses 
were planned, the Judiciary now applies its courtroom-sharing policies 
to new planning efforts. These policies will result in substantial 
cost savings. The draft GAO report proposes senior district judges and 
magistrate judges sharing policies that differ from those endorsed by 
the Judicial Conference. The draft GAO report also proposes a sharing 
ratio for active district judges, a matter that the Judiciary is still 
working on. The report provides practically no information about the 
assumptions used to produce these results and nothing to support the 
contention that a single ratio could apply in districts of all sizes. 
Experience demonstrates that this cannot possibly work. [See comment 
22] 

The GAO proposals — articulated in a scant seven pages — are based on 
two sources of information. One source is interviews of court 
officials and an expert panel convened by GAO and the National Academy 
of Sciences, which included federal judges and a court clerk who had 
experience with courtroom sharing. GAO mischaracterizes many of the 
participants' comments. [See comment 23] For example, the draft 
asserts that a district court official said that "indicators of 
courthouse efficiency ... increased when the judges of the court were 
sharing." As noted in the enclosed comments from Chief Judge Loretta 
A. Preska, this statement is completely contrary to what was said. 
Chief Judge Preska's letter contains numerous examples of GAO's 
misrepresentation of the panelists' views and GAO's interviews in that 
district court. [See comment 24] 

The other source of information is a computer model of the Federal 
Judicial Center's study data that was developed for the GAO by a 
contractor with no apparent claim to any particular expertise in 
courts or the judicial system. As a result, the model does not reflect 
the reality of what happens in the courtroom or the litigation 
process. As with any type of modeling effort, the courtroom model must 
be based on certain assumptions, the formulation of which requires 
significant expertise and understanding of how courts actually work. 
and the consideration of possible impacts on litigants, parties, 
jurors and judges. The only key assumption identified by GAO in its 
report that may have radically affected the outcome of the modeling is 
noted in the appendix, i.e., that every courtroom should be in use for 
10 hours every day. This is unrealistic and virtually impossible. It 
inflates the work day by 25 percent. [See comment 25] 

Federal employees of the court and DOJ are dedicated and may well work 
long hours on a regular basis, but jurors, litigants, witnesses, 
family members, and other parties would have trouble arranging their 
schedules for the extra hours and may have difficulties arranging for 
child care, or meeting other commitments that would be necessary if 
normal work hours of 8:00 a.m. to 6:00 p.m. are assumed. This I 0-hour-
a-day assumption alone would have grossly distorted the resulting 
courtroom sharing ratios. The draft report also contains incorrect 
statements about trials (p. 42). Average trials per judge in 2008 were 
20 trials.[Footnote 1] The median length of a trial was 3 days. 
[Footnote 2] [See comment 26] 

A courtroom is not simply a facility but an essential tool for the 
delivery of justice. The application of courtroom usage data to 
construct a simulation model may give the appearance of authentic 
analysis, but the approach has serious logical and conceptual flaws, 
primarily through what appears to be simplistic and unrealistic 
assumptions. [See comment 27] An assessment of the need for courtrooms 
was completed by Ernst & Young in 2000 as part of an Independent 
Assessment of the Judiciary's Space and Facilities Program. That 
report noted: 

Planning for courtrooms and the impact of courtroom sharing is more 
complex than a simple assessment of actual courtroom use would indicate.
Understanding the dynamics of the judicial process is fundamental to 
any attempt to anticipate courtroom needs accurately and to use 
courtrooms effectively. [See comment 28] 

In describing factors that affect courtroom usage and needs, the 2000 
Ernst & Young study concluded that it would be wrong to assume that 
all of the hours spent by judges in a courthouse can be perfectly 
redistributed across fewer courtrooms without adding a generous 
allowance for flexibility. They indicated that such a factor is needed 
because scheduling full utilization of courtrooms would require 
conditions that do not exist in the judicial environment, namely, 
greater certainty that scheduled events will occur; greater certainty 
about event duration; adequate notice of all events; and the ability 
to reschedule events to fill open courtroom time. [See comment 29] 

As noted by Ernst &Young, it would be a false premise to assume that 
judicial events are largely knowable and predictable. They are not. It 
is one thing to plug into a mathematical model statistics about events 
that have already occurred, but it is another matter altogether to 
predict the duration of these events in advance. This would be 
difficult, even for experts, because of the
inherent variability and uncertain nature of the judicial process. 
Trial times can range significantly in length, and juries may 
deliberate for minutes or many days. Not only is the duration of many 
proceedings unpredictable, but only in a simulation model and not in 
reality can a suddenly available courtroom be readily used for another 
case. After the fact, one may know that a case concluded at noon and 
the courtroom was free in the afternoon, but how foreseeable was that 
circumstance? Perhaps it could have been foreseen the day before, but 
probably not a month earlier. An average trial for a particular type 
of case may take three or four days, but others will not. There is 
considerable variability. A 1998 study by the National Center for 
State Courts entitled On Trial: the Length of Civil and Criminal 
Trials, demonstrated there were substantial differences in experienced 
state court judges' and attorneys' estimates of trial length compared 
to the actual length of the trials. 

The draft report does not describe in any sufficient detail the 
methodology and assumptions used to determine its recommended ratio of 
judges to courtrooms. GAO did not provide the draft report to the 
Federal Judicial Center, which is the Judiciary's research and 
education entity, although GAO used the Federal Judicial Center's data 
to develop its simulation model. [See comment 30] After review of 
GAO's draft report, the Federal Judicial Center has provided the 
following response: 

The GAO's draft report provides little or no information about most of 
the model elements....Thus, there is not enough information or details 
about the simulation model, in general, or about the components of the 
simulation, in particular, to allow the Center to make a constructive 
technical assessment of the GAO's efforts to model and simulate 
courtroom use in the district courts. It is possible, however, to 
identify instances where this lack of detail raises questions about 
the completeness and adaptability of the model and therefore the 
ability of GAO's simulation to provide useful guidance for the 
judiciary. 

* According to the draft report (page 56 of Appendix l), the GAO used 
discrete event simulation techniques, such as those discussed above, 
to develop their simulation model of courtroom use. From the limited 
information the report provides about the simulation, however, it is 
difficult to determine exactly what elements were included in the GAO's
model. It is unclear, for example, what entities were defined (e.g., 
case proceedings, sessions of court) and whether different types of 
entities were represented (e.g., were case proceedings differentiated 
into trials and hearings). Decisions made about the elements of the 
model are critical for the outcome of the modeling effort. The GAO 
report provides little information about those decisions. [See comment 
31] 

* From the information given, it does not appear that the model 
included the concept of cases or a caseload, either as a specific 
entity of the model or as a parameter that could be varied in each 
simulation. If the model does not include cases and caseloads, then 
the simulation cannot estimate how changes in the model affect the 
time to disposition for individual cases or how changes in caseload 
affect courtroom use. The GAO report notes that the Center's study 
"...showed no correlation between the number of weighted and un-
weighted cases filed in a courthouse and the amount of time courtrooms 
are in use" (page 36). The study did, however, show a statistically 
significant correlation between pending caseloads and courtroom use, 
suggesting that cases and caseloads are important elements of a model. 
(See the continuation of the Executive Summary table on page 4 of the 
Center's report.) [See comment 32] 

* The draft report notes that the model allowed for "...user input of 
the number and types of judges and courtrooms," (page 56) so it seems 
that both judges and courtrooms were identified as resources in the 
model. But it is not clear how the coordination of judge and courtroom 
availability was handled. In particular the report mentions that the 
model was "...based on scheduled courtroom availability on weekdays 
from 8 a.m. to 6 p.m." (page 56), but it does not mention what 
schedules were used for judges. It also doesn't mention if those hours 
of operation are typical for the federal courthouses they studied or 
what the results would be if a typical operating schedule of less than 
10 hours per day were assumed (e.g., if 8 hours per day were used). 
[See comment 33] 

* The draft report does not provide details on what processing 
statistics were gathered during the simulation runs and only describes 
the output measures of the simulation broadly ("...the output states 
whether the utilization of the courtrooms does not exceed the 
availability of the courtrooms in the long run." (page 56)). It is 
unclear whether this means that all scheduled events were processed 
each day as expected, or if it implies that events were sometimes 
"bumped" from the day they were scheduled, but over the course of a 
week or a month all events were eventually processed. Whether events 
are processed on the same day as scheduled or over some longer period 
is an important distinction decision makers would want to take into 
account when determining the impact of changing the system. [See 
comment 34] 

* The draft report seems to imply that simulation runs were made for 
different courthouse configurations and that these runs resulted in 
different outcomes ("When using the model to determine the level of 
sharing possible at each courthouse...(page 56)), but it provides no 
specific information about what those outcomes were. The report also 
recommends a single sharing configuration for each type of judge e.g., 
3 district judges to 2 district courtrooms — suggesting that level was 
sufficient in every modeled situation. The report does not, however, 
provide details that support a recommendation that a single ratio can 
apply in districts of all sizes. [See comment 35] 

* The draft report states that "The goal of the model was to determine 
how many courtrooms are required for courtroom utilization rates 
similar to that recorded by FJC." (page 56) The level of utilization 
it seems to be referring to is the average use of a courtroom per day 
based on actual use and unused scheduled time combined (e.g., 4.1 
hours for courtrooms assigned to individual active district judges 
(page 35)) reported by the Center in our report on Courtroom Use. The 
average time per courtroom is not the only level of courtroom use that 
was reported for the Center's study, however. In particular, 
courtrooms in the upper quartile of use reported 6.6 hours per day on 
average. (See the Executive Summary table on page 3 of the Center's 
report on courtroom use.) [See comment 36] The draft report does not 
appear to take into account the impact of a 3-to-2 courtroom sharing 
ratio in situations where use is different than the average level of 
use. 

* The draft report describes GAO's efforts, with the assistance of the 
National Academy of Sciences, to assemble a panel of judicial experts 
to discuss the challenges to courtroom sharing (pages 40-41). However, 
it does not appear that the expert panel had an opportunity to review 
the GAO's model assumptions, decisions about entities and resources, 
decisions about the processing statistics that should be collected and 
reported, and so on. In other words, it does not appear that the 
expert panel had an on-going role in development of the model. [See 
comment 37] 

Conclusion: 

The Judiciary has already made great strides to reduce construction 
and rent costs. We understand that we must use limited resources 
wisely. The Judiciary and GSA will continue to work collaboratively as 
we plan new court facilities with an emphasis on cost and function. We 
will continue to look for ways to improve our planning methodologies. 
We welcome constructive and feasible recommendations from the GAO and 
will implement them as we have in the past. Also, the Judiciary will 
continue to examine seriously courtroom needs based On a thorough and 
considered analysis of data and its potential impact on the 
administration of justice and the Judiciary's responsibility to 
provide an impartial forum in which criminal prosecutions and civil 
cases can be resolved in a just, speedy, and inexpensive manner. 

GAO should consider carefully the Judiciary's comments (including 
those of Chief Judge Preska and the Federal Judicial Center) as well 
as those to be provided by the General Services Administration, to 
make substantial, realistic, and informed modifications to the report. 

Sincerely, 

Singed by: 

James C. Duff: 
Director: 

Enclosure: 

Footnotes: 

[1] Administrative Office of the United States Courts. 2008 Federal 
Court Management Statistics, Washington, D.C., March 2009. 

[2] Administrative Office of the United States Courts. 2008 Annual 
Report of the Director: Judicial Business of the United States Courts, 
Washington, D.C.: U.S. Government Printing Office, 2009. 

United States District Court: 
Southern District Of New York: 
500 Pearl Street: 
New York, New York 10007-1312: 
Loretta A. Preska, Chief Judge: 
212-805-0240: 
Fax: 805-7941: 

June 1, 2010: 

Mr. Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Re: Federal Courthouse Construction Draft: 

Dear Mr. Goldstein: 

Please accept this as a formal response to the draft report on Federal 
Courthouse Construction (GA0-10-417) (the "Draft"). I request that 
this letter be published in the final report. I participated in both 
the Government Accountability Office ("GAO") visit to my courthouse 
and the GAO/National Academy of Science panel discussion of September 
14 on courtroom sharing ("Panel"). 

The Draft is disappointing in that it mischaracterizes, over-
simplifies, and omits important parts of the discussions that took 
place at the Panel and at the meeting at the Moynihan Courthouse with 
the GAO and members of the Third Branch. That the Draft relies on 
those inaccuracies in reaching its conclusions is, I suggest, reason 
to reject those conclusions. [See comment 38] 

Panel of Experts: 

As noted above, I participated in the "panel" of experts held in 
Washington on September 14, 2009. I understand that the judiciary 
panelists were selected as experts because of our practical experience 
with courtroom sharing. 

The Draft states as facts and relies on matters that, at least in this 
district, are demonstrably incorrect. The Draft states at page 42 that 
the median trial lasts one or two days. Using our district's jury 
statistics for the six-month period from November, 2009 to April, 
2010, the median civil trial lasted four days, and the median criminal 
trial lasted seven days. The average civil trial lasted almost five-
and-a-half days, and the average criminal trial lasted eight days. 
Indeed, trials in our district often last for weeks or months. 
Statistics aside, in my seventeen years experience as a trial judge, 
it takes a total of more than a full day to select a jury, sum up and 
charge in the most simple criminal or civil case. Thus, the numbers 
relied on in the Draft allow no time at all for the taking of evidence 
in single-day jury cases and less than a day for the taking evidence 
in two-day jury cases. For both reasons, these supposed statistics 
about median trial length are demonstrably incorrect and thus provide 
adequate grounds for rejecting the Draft. [See comment 29] 

Even if these statistics were correct, the Draft oversimplifies the 
facts by implying that trials are the only use for courtrooms. It 
ignores conferences, oral arguments, evidentiary hearings, pleas and 
sentencings. It is beyond peradventure that all these non-trial 
activities, conducted in the courtroom, are necessary to the 
disposition of any case. The incorrect implication that these 
activities are not conducted in the courtroom infects the entire 
analysis of the Draft. [See comment 40] 

The Draft oversimplifies the disservice to the public of rescheduling 
court proceedings by saying only that it costs the public time and 
money (Draft at 41). While that is correct as far as it goes; it 
ignores the severe difficulty, discussed at the Panel; that 
rescheduling presents to our pro se litigants. Those litigants 
generally are not easily reachable for notification of the 
rescheduling and often must plan ahead to take a day off from work to 
attend court proceedings. Rescheduling on the short notice apparently 
contemplated by the "modeling techniques" employed by the Draft would 
likely result in litigants' not receiving timely notice and thus being 
required to take an additional day off. Unexpected changes in location 
of a proceeding, even if on the same day at the same time, would 
certainly result in pro se litigants' missing proceedings, causing 
delay of the case and increasing the amount of pay lost to litigants 
due to court appearances. On the criminal side, the Draft also omits 
the damage (discussed at the Panel) that such rescheduling would cause 
to transparency of criminal proceedings when a defendant's family and 
friends are prevented from witnessing a trial, plea or sentencing. 
[See comment 41] 

The supposed mitigating effect of "coordination...as long as people 
remain flexible and the lines of communication remain open" (Draft at 
41) oversimplifies facts and ignores discussion at the Panel. It also 
reflects a lack of understanding (or, in light of the specific 
discussion at the Panel of these issues, a refusal to acknowledge) the 
realities of what district judges do. As discussed at the Panel, a 
great deal of time is expended in district judges' chambers attending 
to scheduling and rescheduling of proceedings. Indeed, that activity 
consumes much of the ordinary courtroom deputy's time—even without 
courtroom sharing. What is unmentioned in the Draft, however, is the 
unanimous view of the judges present at the Panel and at the Moynihan 
Courthouse meeting that the kind of scheduling coordination that would 
be necessary for substantial courtroom sharing would be entirely 
unworkable and would result in serious disservice to the judicial 
process and to the public we serve. While an easy palliative to 
invoke, the call for increased coordination (and the observation at 
page 41 that "court staff [in sharing arrangements] must work harder 
than in non-sharing arrangements to coordinate with judges and all 
involved parties to ensure that everyone is in the correct courtroom 
at the correct time") fails (or refuses) to acknowledge the opinion of 
the experienced judges in the trenches that it is easily said but 
impossible to achieve on a long term basis. It is also remarkable that 
factual information provided by a Clerk of Court on the Panel about 
the negative effect of courtroom sharing on case disposition times has 
been described in the Draft (at page 41) as an efficiency improvement. 
The Draft cites only those "facts" that support the desired outcome 
and ignores the impossibility imposed by reality and brought to the 
drafters' attention by the judges who do this every day. [See comment 
42] 

The supposed mitigating effect of technology discussed at page 43 
misstates what was said at the Panel and relates "facts" that show a 
Serious lack of understanding of what goes on in a trial in a district 
court. At the Panel, the participants discussed greater use of
videoconferencing in non-jury matters as a way to save courthouse 
construction costs. For example, it was discussed that some courts 
have eliminated the need for an additional place of holding bankruptcy 
court by use of videoconferencing from a normal room in a remote 
location to the bankruptcy courthouse. The Panel mentioned, as does 
the Draft,[Footnote 1] the cost savings associated with conferences, 
including Rule 16 conferences and other pretrial conferences with 
incarcerated parties (although these savings are in time and travel 
costs because these conferences also take place from the courtroom). 
So far, so good. The unremarkable observation in the Draft that 
"increased technology saves money, it expedites general processing 
because documents can be submitted to the court electronically" (at 
page 43) has nothing whatsoever to do with courtroom sharing. The 
final observation in the Draft on this topic (at page 43) is "Another 
judge said that if less money were spent on space, more could be spent 
on technological upgrades to increase flexibility and increase the 
ability to share space among judges." First, I do not recall hearing 
that comment, but, of course, it could have been made at a session 1 
did not attend. Second, the comment is a meaningless non-sequitur. 
Third, and most importantly, by implying that technology will decrease 
courtroom usage, the Draft is seriously misleading. The Draft fails to 
mention that Rule 43 of the Rules of Criminal Procedure specifically 
requires that the defendant be present in the courtroom at the initial 
appearance, initial arraignment and every trial day. Indeed, in the 
'Second Circuit, a plea and a sentencing NOT held in a courtroom (but 
in the adjacent robing room) Were reversed. See United States v. 
Alcantara, 396 F.3d 189 (2d Cir. 2005). Thus, the technology section 
of the Draft is at least irrelevant and at worst misleading. [See 
comment 43] 

Discussion at the Moynihan Courthouse The Draft states categorically 
that "judges with experience in sharing courtrooms said that they 
overcame the challenges when necessary and trials were never postponed 
because of sharing." I suggest that the authors are cherry-picking the 
facts here. For example, the reason my court, the Southern District of 
New York, was chosen for a site visit is that our court is
currently engaged in limited courtroom sharing (about ten judges 
total) because of the on-going renovation of our second courthouse at 
Foley Square, the Thurgood Marshall Courthouse, with the resulting 
scarcity of courtrooms. Both at the Panel and during the interview GAO 
personnel conducted in New York with judges who are sharing (at which, 
as noted above, I was present), it was stated that this limited 
sharing is only workable because of collegiality, that is, the sharing 
pairs were carefully chosen for compatibility of workload and 
personality. While the Draft does mention the word "collegiality," 
stating at page 41 that "[judges that share courtrooms in one district 
also said that coordination is easier when there is a great deal of 
collegiality among judges," it omits the point made at the discussion 
in the Moynihan Courthouse. Perhaps the Draft is making reference to 
remarks made in some other district, but, even if it is, it fails to 
convey accurately the statements of judges in our district who 
actually do share courtrooms and the statement that I made at the 
Panel. The careful pairing of judges on which the temporary sharing in 
the Moynihan Courthouse is proceeding cannot be replicated in the 
widespread sharing urged in the Draft. 

The Draft discusses alternating chambers with courtroom floors (Draft 
at 41-42) stating that such design "may be more conducive to 
collegiality and sharing." First, collegiality is not the issue here. 
Second, courtroom floors and chambers floors DO alternate in the 
Moynihan courthouse, and that has no effect on our view that courtroom 
sharing to the extent contemplated in the Draft is not a viable option 
among active judges and should be subject to local exemption for 
senior judges. While some designs might, in fact, be more conducive to 
courtroom sharing without unduly increasing security risks (for 
example, perimeter chambers around several courtrooms of varying 
sizes), alternating courtroom and chambers floors is not one of them. 
The observation that "this design breaks the apparent association of 
chambers with specific courtrooms without significantly increasing the 
distance from chambers to courtrooms" is simply irrelevant. [See 
comment 44] 

The Model: 

In support of its conclusion that "GAO's courtroom sharing model shows 
that there is sufficient unscheduled time for 3 district judges to 
share two courtrooms and 3 senior judges to share 1 courtroom" (Draft 
at 1), the Draft relies on a computer simulation model. In describing 
the creation of that Model, the Draft states: 

To create a simulation model, we contracted for the services of a firm 
with expertise in discrete events simulations modeling. This 
consulting engineering services and technology firm uses advanced 
computer modeling and visualization and other techniques to maximize 
throughput, improve system flow, and reduce capital and operating 
expenses. Working with the contractor, we discussed assumptions made 
for the inputs of the model and verified the output with in-house data 
experts. We designed this sharing model in conjunction with a 
specialist in discrete event simulation and the company that designed 
the simulation software to ensure that the model conformed to 
generally accepted simulation modeling standards and was reasonable 
for the federal court system. The model was also verified with the 
creator of the software to ensure proper use and model specification. 
Simulation is widely used in modeling any system where there is 
competition for scarce resources. The goal of the model was to 
determine how many courtrooms are required for courtroom utilization 
rates similar to that recorded by FJC. This determination is based on 
data for all courtroom use time collected by FJC, including time when 
the courtroom was scheduled to be used but the event was canceled 
within 1 week of the scheduled date. (Draft at 56.) 

This description is, I suggest, merely gibberish and fails to inform 
the reader about precisely what assumptions were made and the method 
employed. To the extent that any assumptions are stated, the Draft 
states that it is "based on scheduled courtroom availability on 
weekdays from 8 a.m. to 6 p.m." (Draft at 56). First, these hours of 
operation are wholly unrealistic. Assuming that jurors would not be 
required to serve from 8 a.m. to 6 p.m., but only during a portion of 
that time, it is unrealistic to expect any juror to appear ready to 
start a trial by 8 a.m or to serve until 6 p.m. Many jurors have 
children who need to be attended to and cannot appear in Court by 8 
a.m. or sit until 6 p.m.[Footnote 2] [See comment 45] 

Assuming that the Model contemplates jury trials running in shifts, 
for example, 8 a.m. to 1 p.m. and I p.m. to 6 p.m., such shifts would 
close to double the time it takes to try any case, thus vastly 
increasing the cost to the litigants. There is already public outcry 
over the cost of litigation,[Footnote 3] and doubling the cost of 
trial would be a severe injustice to the public we serve. [See comment 
46] 

Finally, from the scant description of the Model presented in the 
Draft and from the conversation at the Panel, I infer that the Model 
assumes all court proceedings arc the same in kind and manner. Such 
treatment is directly contrary to fact and, more importantly for these 
purposes, contrary to the specific discussion at the Panel. 
Participants of the Panel specifically stated that courtroom 
proceedings are not interchangeable, especially trials and other 
evidentiary proceedings. A preliminary injunction hearing, for 
example, is by definition of great urgency and ordinarily must proceed 
from day to day until complete. Also, considering all trials as 
portable—subject to movement from courtroom to courtroom—is 
inaccurate. Even the Draft acknowledges (at page 35) that some 
courtroom use involves attorney set-up and break-down time (although 
the Draft incorrectly considered this as an "event not related to case 
proceedings"). These days, almost all trials involve the presentation 
of some evidence by electronic means, and lawyers (more likely 
computer contractors) spend time in advance of trial setting up their 
equipment for presentation of evidence electronically and time after 
trial taking it down. Most trials also involve boxes of files and 
other materials that are stored in the courtroom or in the hall 
outside the courtroom for ready access by counsel throughout the 
trial. Counsel's need for electronic equipment for presentation of 
evidence and for access to hard copy materials cannot be accommodated 
when the courtroom changes during a trial. [See comment 47] 

Conclusion: 

The authors of the Draft have not reported accurately the statements 
of even those they recognize as experts—the members of the Panel and 
the participants in the site visit to the Moynihan Courthouse. To the 
extent that the assumptions and techniques used in the modeling were 
disclosed, they are counter-factual, according to the same experts. 
Thus, the Draft is without foundation and, I suggest, should be 
rejected. 

Moreover, the Draft relics on only one metric—efficiency. While 
efficiency is a fair factor to be considered, it is only one. Less 
susceptible to quantitative measurement, however, is a more important 
consideration—delivery of justice to the citizens of this country. 1 
suggest that doing so in a user-friendly manner is inherently 
inefficient and thus that efficiency is only one of many factors to he 
considered. [See comment 48] 

Very truly yours, 

Signed by: 

Loretta A. Preska: 

Footnotes: 

[1] On this topic, the Draft states: "Technology makes certain 
conferences easier through the use of teleconferences and 
videoconferencing. One judge said that videoconferencing with a 
defendant who was being held in prison hundreds of miles away saved 
potentially thousands of dollars." (Draft at 43). 

[2] In New York State Courts, jurors generally commence service 
between 8:30 and 9:00 a.m. and are generally dismissed between 4:00 
and 4:30 p.m. The State Courts only draw jurors from a single county, 
however, while the SDNY draws jurors from eight counties, including 
from the cities of Poughkeepsie (85 miles) and Monticello (94 miles). 

[3] See Institute For The Advancement Of The American Legal System, 
Civil Litigation Survey Of Chief Legal Officers And General Counsel 
Belonging To The Association Of Corporate Counsel 17 (2010), available 
at [hyperlink, http://www.du.edu/legalinstitutelformchieflegal.html] 
("An astonishing 97% of respondents responded that the system is 'too 
expensive,' with 78% expressing strong agreement."). 

The following are GAO's comments on the Federal Judiciary letters 
dated June 1, 2010. stated: 

GAO Comments: 

1. In commenting on our draft report, the Administrative Office of the 
U.S. Courts (AOUSC) stated that it has concerns about the accuracy of 
key data, the presentation of information, and the soundness of the 
methodologies used. We drew the key facts in our report--the size of 
courthouses, the number of judges estimated, and the number of current 
judges--from judiciary and GSA documents. In this report and all of 
its Products, GAO adheres to generally accepted government auditing 
standards, which ensure the accuracy and relevance of the facts within 
this report. These standards include a layered approach to fact 
validation that includes supervisory review of all work papers, 
independent verification of the facts within the report, and the 
judiciary's review of the facts prior to the draft report's release 
for agency comment. For example, our conclusion that the 33 
courthouses completed since 2000 contain 3.56 million extra square 
feet was based on our analysis of the original documents related to 
all 33 courthouses. The data supporting our analysis were traced and 
verified, independently checked by analysts who were not part of the 
engagement team, and reviewed and approved by experts in the relevant 
methodologies. As a result of this strong fact checking and review 
process, we are confident in our presentation of the facts in this 
report. We will address AOUSC's additional points in the pages that 
follow. However, we did not refer to this extra space as "wasted" in 
our draft report as AOUSC indicates in its letter. 

2. AOUSC indicated that it was troubled by our release of the report's 
preliminary findings at a May 25, 2010, hearing and in a related media 
report before the judiciary and the General Services Administration 
(GSA) could comment. We were asked to testify on our preliminary 
findings by the same committee that requested the report, which is 
well within the committee's purview under GAO's Congressional 
Protocols. We made it clear that these findings were preliminary 
because AOUSC and GSA had not yet had an opportunity to comment on 
them. We provided the draft report to the judiciary and GSA on April 
29--almost a month before the hearing--and we notified them of the 
hearing and invited the judiciary and GSA to provide comments before 
the hearing. Both the judiciary and GSA declined. Responding to press 
inquiries following a hearing is also a standard part of our work, and 
in doing so we stated that our findings were preliminary at that time. 
We do not have control over what media outlets choose to report. 

3. AOUSC noted that Chief District Judge Loretta Preska indicated in 
an attached letter that GAO misleadingly characterized her experiences 
and the statements of the expert panel in which she participated. We 
visited numerous courthouses in addition to the judge's, and Judge 
Preska was present only for the 1-day portion of our panel, not the 
subsequent interviews with experts who could not attend the 1-day 
panel. As stated in the report, some experts were unable to attend the 
1-day session, and we interviewed them separately. 

4. AOUSC stated that a senior GAO team member revealed his bias toward 
courtroom sharing with a group of judiciary officials (which was 
during the 1-day portion of the expert panel). This is not the case. 
In framing the discussion surrounding the issue of courtroom sharing 
at the 1-day panel discussion, the GAO team member correctly cited the 
Judicial Conference's new policy requiring courtroom sharing in future 
courthouses, not his own views on the subject. 

5. AOUSC said that at the time the 33 courthouses we reviewed were 
planned, the judiciary's policy was for judges not to share courtrooms 
and that it would be more appropriate for us to apply that policy. Our 
congressional requesters specifically asked that we consider how a 
courtroom sharing policy could have changed the amount of space needed 
in these courthouses. However, our draft and final reports indicate 
that the judiciary's policy at the time was largely to provide one 
courtroom per judge. 

6. AOUSC suggested that our report describes the extra space we 
identified as wasted--a term that does not appear in either the draft 
or the final report. We also indicated in the report that we did not 
evaluate how much of the extra space was unused. We used judiciary- 
generated data on courtroom scheduling and use to determine how many 
courtrooms the judiciary actually needed in order to illustrate how 
courthouses could support the same number of judges with fewer 
courtrooms. 

7. AOUSC indicated that some extra courtrooms exist because the 
judiciary did not receive all the new judge authorizations it 
requested. We recognize, and our draft and final reports indicate, 
that some of the extra courtrooms reflect the historic trend that the 
judiciary has not received all the additional authorized judges it has 
requested. 

8. According to AOUSC, the draft report does not indicate how many 
courtrooms are in the courthouses we reviewed. This is correct. Our 
report instead focuses on the number of square feet in the 
courthouses, which includes all space, not just courtroom space. 

9. AOUSC drew conclusions related to the accuracy of its judge 
estimates that are very different from ours in several key ways and 
may partly illustrate why the judiciary consistently overestimates its 
need for judges. 

* The judiciary used "soon-to-be vacant authorized positions" in its 
analysis but provides no criteria for what constitutes such a 
position. However, the judiciary's previous estimates showed that all 
of the 28 courthouses that have met or exceeded their 10-year planning 
window should now be fully occupied. 

* The judiciary also included "additional pending judgeships" in its 
count, which assumes immediate congressional approval of all requested 
judgeships. Moreover, the judiciary inappropriately made assumptions 
about where the new judgeships will be located. However, Congress has 
not passed comprehensive judgeship legislation in 20 years, and new 
judges are authorized for a district, not for a specific courthouse. 

* The judiciary also implied that having a vacancy is equivalent to 
having an authorized judgeship, which is not the case. The nomination 
and confirmation process, as the judiciary agrees, can be lengthy. 

10. AOUSC questioned the development of our courtroom sharing model 
and what it said was our refusal to release critical elements for 
review. Early in the engagement, we spoke with officials from the 
Federal Judicial Center (FJC) about how FJC's data could be used to 
develop a courtroom sharing model. Contrary to the judiciary's 
contention, we have not withheld any information critical to 
understanding or replicating the model. We carefully documented the 
data and parameters throughout our report so that our model could be 
replicated by anyone with access to the judiciary's data and 
familiarity with discrete event simulation modeling techniques. We 
confirmed this was the case with simulation model experts. We do not 
recommend that the judiciary use our model, but, instead, institute 
courtroom sharing policies that more fully reflect the actual 
scheduling and use of district courtrooms. Our model provides one 
option for how to accomplish this. In doing so, our model incorporates 
the judiciary's courtroom sharing and usage data, and the model's 
parameters are based on detailed discussions with judges, other 
judicial experts whose views we obtained through a 1-day panel or 
additional interviews, and visits to districts with experience in 
sharing courtrooms. To date, the judiciary has not applied computer 
modeling techniques for courtroom sharing in developing its sharing 
policies, even though it gathered the data on courtroom scheduling 
with that purpose in mind. 

11. AOUSC questioned our characterization of the expert panel convened 
by the National Academy of Sciences and their contribution to the 
courtroom sharing model. As stated earlier, the panel consisted of a 1-
day session with experts and individual interviews with the remaining 
experts who could not attend. We used an official transcript of the 
statements from the 1-day panel to support the facts in our report, 
and none of the experts at the 1-day session participated in the 
individual interviews. As a result, none of the individual experts can 
draw conclusions about our overall characterization of all panelists' 
views. 

12. AOUSC questioned the feasibility of our courtroom sharing model 
based on the level of use of courtrooms in the top quartile of use. As 
we state in the report, we did not analyze the usage data by 
courtroom, but rather by courthouse, since courtrooms are used to 
varying degrees. In that way, our model is based on the real use of 
courtrooms in the courthouses where they are located and not on an 
artificial collection of the most-used individual courtrooms 
nationwide. In addition, the judiciary data incorporated variations 
across the country and included some sensitivity analysis as noted in 
our report. 

13. AOUSC noted that it conducted its own analysis of the numbers of 
courtrooms and judges in the 33 courthouses completed since 2000. The 
judiciary's analysis was very different from ours and highlighted some 
of the reasons the judiciary may overestimate the number of judges it 
will have in a courthouse after 10 years. 

* The judiciary counts judgeships that have not yet been authorized by 
Congress. We chose to count only the judgeships that are currently 
authorized because the judiciary has historically not received many of 
the judgeships it has requested and new judges are authorized for 
districts, which include multiple locations, not for individual 
courthouses. 

* The judiciary appears to count vacancies that are not linked to a 
specific location. We chose to count only the vacancies that the 
judiciary's data indicated were assigned to a specific courthouse 
because the other vacancies are districtwide, making it inappropriate 
to assume which specific courthouse a new judge would be assigned to 
once the judge was appointed and confirmed. 

14. See comment 5. 

15. AOUSC produced a table showing that, according to its projections, 
the six case study courthouses that have met or exceeded their 10-year 
planning period will be fully utilized by 2016. AOUSC's analysis is 
flawed in several important ways. 

* The judiciary extended its own 10-year planning period to 2016--a 
date that is 16 to 25 years after the planning of each courthouse. The 
judiciary had projected, as part of its justification for a new 
courthouse, that each of these courthouses would already be fully 
utilized. Moving the deadline out to 2016 more than doubles the number 
of years that the judiciary indicated it needed to fill some of these 
courthouses. 

* The judiciary counted judgeships that have not yet been authorized 
by Congress. We chose to count only the judgeships that are currently 
authorized because the judiciary has historically not received many of 
the judgeships it has requested and new judges are authorized for 
districts, which include multiple locations, not for individual 
courthouses. 

* The judiciary appeared to count vacancies that are not linked to a 
specific location. We chose to count only the vacancies that the 
judiciary's data indicated were assigned to a specific building. The 
judiciary's data show that several vacancies are districtwide, making 
it inappropriate to assume which specific courthouse a new judge would 
be assigned to once the judge was appointed and confirmed. 

* The judiciary assumed that all judges would take senior status as 
soon as they were eligible, that no current senior judges would leave 
the bench, and that all vacancies would be immediately filled by newly 
appointed and confirmed judges. These assumptions are unlikely. As the 
judiciary has told us, many judges do not take senior status 
immediately, others leave the bench, and the nomination and 
confirmation processes can take years. 

The judiciary's methodological decisions led to counting the maximum 
number of judges a courthouse could have by a certain date, not the 
number it is likely to have by that date. As a result, the judiciary 
has overestimated by 26 percent the number of judges it should have in 
the courthouses completed since 2000. 

16. AOUSC noted that it suggested changing the number of judges the 
District of Columbia projected from 14 to 7 when it was planning what 
would become the Bryant Courthouse Annex. However, we did not make 
that change because the planning documents used to justify the new 
building clearly indicate that the number of senior judges used to 
develop the 10-year estimate for that location was 14, and the 
judiciary did not provide any documentary evidence to support its 
contention that the number was actually 7. 

17. According to AOUSC, we incorrectly identified the number of 
pending district judgeships in the Eastern District of California as 4 
when, AOUSC says, the actual number is 5. AOUSC is incorrect. The 2009 
Federal Judgeship Bill includes language that would, if passed as 
currently written, increase the number of authorized judgeships in the 
Eastern District of California by 4. The other judgeship, if approved, 
would be temporary and would not increase the number of authorized 
permanent judgeships in the district. We chose not to count temporary 
judgeships as permanent, in part because the judges in the Eastern 
District of California told us during our visit that the last 
temporary judgeship in the district was lost because it was not 
converted into a permanent judgeship through an act of Congress. 

18. AOUSC noted that judges will eventually fill the vacancies within 
the courthouses we identified. This may be the case, but the judiciary 
has established the 10-year planning period as a reasonable time frame 
for estimating its new courthouse needs. Many of the courthouses in 
our study are well past the 10-year period and have still not met 
their 10-year estimate for judges. For example, planning for the 
Eagleton U.S. Courthouse in St. Louis, Missouri, began 16 years ago, 
but the courthouse remains 9 authorized judgeships short of the 
judiciary's 10-year estimate. 

19. AOUSC stated that it expected Congress to approve new judgeships 
on a regular basis because it had done so in previous years. Our 
report acknowledges the challenges associated with estimating 
judgeships and suggests that the judiciary incorporate some of the 
realities of the current process into its estimates. One of those 
realities is that Congress has not passed comprehensive judgeship 
legislation for 20 years. The judiciary has, instead, planned for the 
maximum number of possible judges after 10 years, which has led it to 
overestimate the number of judges by 26 percent and to construct far 
more courthouse space than needed. 

20. AOUSC stated that we incorrectly characterize space for visiting 
judges as extra. Our decision to refer to this space as extra is based 
on the judiciary's policy, which is to exclude estimates of space 
needs for visiting judges in courthouse planning. 

21. AOUSC stated that it is prudent to plan for unauthorized 
judgeships when caseloads support the need for a new judge. Our 
conclusion is that the judiciary can improve its judge estimation 
process for three reasons stated in our report: First, the judiciary's 
caseload projections have not always been correct. Second, Congress 
has not passed comprehensive judgeship legislation in the last 20 
years and has recently questioned the reliability of weighted caseload 
as a workload indicator. Third, in measuring the effectiveness of the 
judiciary's space planning, we applied the judiciary's criteria, which 
includes the number of authorized judgeships and senior judges that 
will be located in a facility after 10 years. 

22. According to AOUSC, our report provides practically no information 
about the assumptions we used to produce the results of our sharing 
scenarios. However, the report provides information about the 
assumptions used to create the model in sufficient detail to replicate 
the model. Both a senior methodologist and the contractor hired to 
develop the model stated that the model could be replicated by an 
expert in discrete event simulation with the information included in 
the report. 

* As noted in the report, we used data that were nationally 
representative of courtroom use and scheduling, which the Federal 
Judicial Center (FJC) collected for a discrete event simulation model. 
When creating the simulation model, we used all data capturing the 
time a courtroom was actually used, including time for education, 
training, set-up and take-down, and maintenance, as well as for all 
case proceedings. Above and beyond modeling all the time the 
courtrooms were reported to be used, we also incorporated all unused 
scheduled time. Thus, if an event was scheduled to take place over 4 
days, but lasted only 2 days, the remaining unused scheduled time was 
still included in the model as time a courtroom was not available for 
other events. This was done in recognition of the experts' concerns 
about the uncertainty involved in the judiciary's scheduling. 

* As noted in the report, when modeling, we allowed the courtroom to 
be in use for 10 hours a day. We do not presume that people could or 
should work 10 hours a day, but rather that the courtroom is available 
for a variety of uses between 8:00 a.m. and 6:00 p.m. We recognize 
that judges hold events at various times throughout the day to best 
serve the interests of parties and the public, and assuming that 
courtrooms are available for 10 hours a day allows for activities in 
addition to judicial proceedings. For example, materials may be 
brought into a courtroom before trial, staff training and educational 
tours may take place, and maintenance may be performed. We did not cut 
the time in which a courtroom was in use for these types of activities 
and, therefore, it would have been unrealistic to limit the time a 
courtroom can be used to less than the 10 hours. 

* For modeling purposes, we also developed two different sharing 
scenarios. In the first scenario, dedicated sharing, specific judges 
are assigned to courtrooms. In applying the model under dedicated 
sharing, we considered several base levels of sharing that work in all 
instances, according to the data. Please see table 5 in the report for 
a list of these results. In the second scenario, centralized sharing, 
all courtrooms are open to all judges, and significant efficiencies 
are gained. We have included the following tables (tables 8-11) to 
illustrate these efficiencies. The tables were prepared using our 
courthouse sharing model at the request of the House Transportation 
and Infrastructure Committee Subcommittee on Economic Development, 
Public Buildings, and Emergency Management following a hearing on May 
25, 2010. They show the efficiencies gained through centralized 
sharing based on increases in the numbers of district judges, senior 
judges, and magistrate judges, respectively. Table 11 provides the 
results of our model for entire hypothetic courthouses, based on the 
nationwide ratios of district judges to senior and magistrate judges, 
when all judges have centralized access to all courtrooms. The tables 
illustrate the potential of courtroom sharing to reduce the number of 
courtrooms needed. It is up to the judiciary to determine how much 
sharing is possible as indicated in our recommendation. 

Table 8: Courtroom Sharing for District Judges Based on Centralized 
Sharing: 

Number of district judges: 3; 
Number of district courtrooms needed: 2; 
Courtrooms per judge: 0.67; 
Per-room utility[A]: 89%. 

Number of district judges: 4; 
Number of district courtrooms needed: 3; 
Courtrooms per judge: 0.75; 
Per-room utility[A]: 78%. 

Number of district judges: 5; 
Number of district courtrooms needed: 4; 
Courtrooms per judge: 0.80; 
Per-room utility[A]: 74%. 

Number of district judges: 6; 
Number of district courtrooms needed: 4; 
Courtrooms per judge: 0.67; 
Per-room utility[A]: 88%. 

Number of district judges: 7; 
Number of district courtrooms needed: 5; 
Courtrooms per judge: 0.71; 
Per-room utility[A]: 84%. 

Number of district judges: 8; 
Number of district courtrooms needed: 5; 
Courtrooms per judge: 0.63; 
Per-room utility[A]: 94%. 

Number of district judges: 9; 
Number of district courtrooms needed: 6; 
Courtrooms per judge: 0.67; 
Per-room utility[A]: 89%. 

Number of district judges: 10; 
Number of district courtrooms needed: 7; 
Courtrooms per judge: 0.70; 
Per-room utility[A]: 85%. 

Number of district judges: 11; 
Number of district courtrooms needed: 7; 
Courtrooms per judge: 0.64; 
Per-room utility[A]: 92%. 

Number of district judges: 12; 
Number of district courtrooms needed: 8; 
Courtrooms per judge: 0.67; 
Per-room utility[A]: 88%. 

Number of district judges: 13; 
Number of district courtrooms needed: 8; 
Courtrooms per judge: 0.62; 
Per-room utility[A]: 95%. 

Number of district judges: 14; 
Number of district courtrooms needed: 9; 
Courtrooms per judge: 0.64; 
Per-room utility[A]: 91. 

Number of district judges: 15; 
Number of district courtrooms needed: 10; 
Courtrooms per judge: 0.67; 
Per-room utility[A]: 89%. 

Number of district judges: 16; 
Number of district courtrooms needed: 10; 
Courtrooms per judge: 0.63; 
Per-room utility[A]: 93%. 

Number of district judges: 17; 
Number of district courtrooms needed: 11; 
Courtrooms per judge: 0.65; 
Per-room utility[A]: 91%. 

Number of district judges: 18; 
Number of district courtrooms needed: 12; 
Courtrooms per judge: 0.67; 
Per-room utility[A]: 89%. 

Number of district judges: 19; 
Number of district courtrooms needed: 12; 
Courtrooms per judge: 0.63; 
Per-room utility[A]: 93%. 

Number of district judges: 20; 
Number of district courtrooms needed: 13; 
Courtrooms per judge: 0.65; 
Per-room utility[A]: 90%. 

Source: GAO. 

[A] 100 percent is full use. 

[End of table] 

Table 9: Courtroom Sharing for Senior District Judges Based on 
Centralized Sharing: 

Number of senior judges: 3; 
Number of senior courtrooms needed: 1; 
Courtrooms per judge: 0.33; 
Per-room utility[A]: 81%. 

Number of senior judges: 4; 
Number of senior courtrooms needed: 2; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 52%. 

Number of senior judges: 5; 
Number of senior courtrooms needed: 2; 
Courtrooms per judge: 0.40; 
Per-room utility[A]: 67%. 

Number of senior judges: 6; 
Number of senior courtrooms needed: 2; 
Courtrooms per judge: 0.33; 
Per-room utility[A]: 81%. 

Number of senior judges: 7; 
Number of senior courtrooms needed: 2; 
Courtrooms per judge: 0.29; 
Per-room utility[A]: 94%. 

Number of senior judges: 8; 
Number of senior courtrooms needed: 3; 
Courtrooms per judge: 0.38; 
Per-room utility[A]: 72%. 

Number of senior judges: 9; 
Number of senior courtrooms needed: 3; 
Courtrooms per judge: 0.33; 
Per-room utility[A]: 81%. 

Number of senior judges: 10; 
Number of senior courtrooms needed: 3; 
Courtrooms per judge: 0.30; 
Per-room utility[A]: 91%. 

Number of senior judges: 11; 
Number of senior courtrooms needed: 4; 
Courtrooms per judge: 0.36; 
Per-room utility[A]: 75%. 

Number of senior judges: 12; 
Number of senior courtrooms needed: 4; 
Courtrooms per judge: 0.33; 
Per-room utility[A]: 82%. 

Number of senior judges: 13; 
Number of senior courtrooms needed: 4; 
Courtrooms per judge: 0.31; 
Per-room utility[A]: 86%. 

Number of senior judges: 14; 
Number of senior courtrooms needed: 4; 
Courtrooms per judge: 0.29; 
Per-room utility[A]: 95%. 

Number of senior judges: 15; 
Number of senior courtrooms needed: 5; 
Courtrooms per judge: 0.33; 
Per-room utility[A]: 81%. 

Number of senior judges: 16; 
Number of senior courtrooms needed: 5; 
Courtrooms per judge: 0.31; 
Per-room utility[A]: 86%. 

Number of senior judges: 17; 
Number of senior courtrooms needed: 5; 
Courtrooms per judge: 0.29; 
Per-room utility[A]: 91v. 

Number of senior judges: 18; 
Number of senior courtrooms needed: 6; 
Courtrooms per judge: 0.33; 
Per-room utility[A]: 80%. 

Number of senior judges: 19; 
Number of senior courtrooms needed: 6; 
Courtrooms per judge: 0.32; 
Per-room utility[A]: 85%. 

Number of senior judges: 20; 
Number of senior courtrooms needed: 6; 
Courtrooms per judge: 0.30; 
Per-room utility[A]: 90%. 

Source: GAO. 

[A] 100 percent is full use. 

[End of table] 

Table 10: Courtroom Sharing for Magistrate Judges Based on Centralized 
Sharing: 

Number of magistrate judges: 2; 
Number of magistrate courtrooms needed: 1; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 75%. 

Number of magistrate judges: 3; 
Number of magistrate courtrooms needed: 2; 
Courtrooms per judge: 0.67; 
Per-room utility[A]: 55%. 

Number of magistrate judges: 4; 
Number of magistrate courtrooms needed: 2; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 76%. 

Number of magistrate judges: 5; 
Number of magistrate courtrooms needed: 2; 
Courtrooms per judge: 0.40; 
Per-room utility[A]: 92v. 

Number of magistrate judges: 6; 
Number of magistrate courtrooms needed: 3; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 75%. 

Number of magistrate judges: 7; 
Number of magistrate courtrooms needed: 3; 
Courtrooms per judge: 0.43; 
Per-room utility[A]: 86%. 

Number of magistrate judges: 8; 
Number of magistrate courtrooms needed: 4; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 75%. 

Number of magistrate judges: 9; 
Number of magistrate courtrooms needed: 4; 
Courtrooms per judge: 0.44; 
Per-room utility[A]: 85%. 

Number of magistrate judges: 10; 
Number of magistrate courtrooms needed: 4; 
Courtrooms per judge: 0.40; 
Per-room utility[A]: 93%. 

Number of magistrate judges: 11; 
Number of magistrate courtrooms needed: 5; 
Courtrooms per judge: 0.45; 
Per-room utility[A]: 83%. 

Number of magistrate judges: 12; 
Number of magistrate courtrooms needed: 5; 
Courtrooms per judge: 0.42; 
Per-room utility[A]: 88%. 

Number of magistrate judges: 13; 
Number of magistrate courtrooms needed: 6; 
Courtrooms per judge: 0.46; 
Per-room utility[A]: 79%. 

Number of magistrate judges: 14; 
Number of magistrate courtrooms needed: 6; 
Courtrooms per judge: 0.43; 
Per-room utility[A]: 86%. 

Number of magistrate judges: 15; 
Number of magistrate courtrooms needed: 6; 
Courtrooms per judge: 0.40; 
Per-room utility[A]: 92%. 

Number of magistrate judges: 16; 
Number of magistrate courtrooms needed: 7; 
Courtrooms per judge: 0.44; 
Per-room utility[A]: 85%. 

Number of magistrate judges: 17; 
Number of magistrate courtrooms needed: 7; 
Courtrooms per judge: 0.41; 
Per-room utility[A]: 89%. 

Number of magistrate judges: 18; 
Number of magistrate courtrooms needed: 7; 
Courtrooms per judge: 0.39; 
Per-room utility[A]: 95%. 

Number of magistrate judges: 18; 
Number of magistrate courtrooms needed: 8; 
Courtrooms per judge: 0.44; 
Per-room utility[A]: 83%. 

Number of magistrate judges: 19; 
Number of magistrate courtrooms needed: 8; 
Courtrooms per judge: 0.42; 
Per-room utility[A]: 88%. 

Number of magistrate judges: 20; 
Number of magistrate courtrooms needed: 8; 
Courtrooms per judge: 0.40; 
Per-room utility[A]: 93%. 

Source: GAO. 

[A] 100 percent is full use. 

[End of table] 

Table 11: Courtroom Sharing for Courthouses Using Nationwide Ratio of 
District Judges to Senior and Magistrate Judges Based on Centralized 
Sharing: 

District judges: 2; 
Senior judges: 1; 
Magistrate judges: 1; 
Total judges: 4; 
Number of district courtrooms needed: 2; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 92%. 

District judges: 3; 
Senior judges: 1; 
Magistrate judges: 2; 
Total judges: 6; 
Number of district courtrooms needed: 3; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 93%. 

District judges: 4; 
Senior judges: 2; 
Magistrate judges: 3; 
Total judges: 9; 
Number of district courtrooms needed: 5; 
Courtrooms per judge: 0.56; 
Per-room utility[A]: 80%. 

District judges: 5; 
Senior judges: 2; 
Magistrate judges: 4; 
Total judges: 11; 
Number of district courtrooms needed: 6; 
Courtrooms per judge: 0.55; 
Per-room utility[A]: 82%. 

District judges: 6; 
Senior judges: 3; 
Magistrate judges: 4; 
Total judges: 13; 
Number of district courtrooms needed: 7; 
Courtrooms per judge: 0.54; 
Per-room utility[A]: 83%. 

District judges: 7; 
Senior judges: 3; 
Magistrate judges: 5; 
Total judges: 15; 
Number of district courtrooms needed: 8; 
Courtrooms per judge: 0.53; 
Per-room utility[A]: 84%. 

District judges: 8; 
Senior judges: 4; 
Magistrate judges: 6; 
Total judges: 18; 
Number of district courtrooms needed: 9; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 88%. 

District judges: 9; 
Senior judges: 4; 
Magistrate judges: 7; 
Total judges: 20; 
Number of district courtrooms needed: 10; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 89%. 

District judges: 10; 
Senior judges: 5; 
Magistrate judges: 7; 
Total judges: 22; 
Number of district courtrooms needed: 11; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 89%. 

District judges: 11; 
Senior judges: 5; 
Magistrate judges: 8; 
Total judges: 24; 
Number of district courtrooms needed: 12; 
Courtrooms per judge: 0.50; 
Per-room utility[A]: 90%. 

District judges: 12; 
Senior judges: 6; 
Magistrate judges: 9; 
Total judges: 27; 
Number of district courtrooms needed: 13; 
Courtrooms per judge: 0.48; 
Per-room utility[A]: 92%. 

District judges: 13; 
Senior judges: 6; 
Magistrate judges: 10; 
Total judges: 29; 
Number of district courtrooms needed: 14; 
Courtrooms per judge: 0.48; 
Per-room utility[A]: 92%. 

District judges: 14; 
Senior judges: 7; 
Magistrate judges: 10; 
Total judges: 31; 
Number of district courtrooms needed: 15; 
Courtrooms per judge: 0.48; 
Per-room utility[A]: 92%. 

District judges: 15; 
Senior judges: 7; 
Magistrate judges: 11; 
Total judges: 33; 
Number of district courtrooms needed: 16; 
Courtrooms per judge: 0.48; 
Per-room utility[A]: 92%. 

District judges: 16; 
Senior judges: 8; 
Magistrate judges: 12; 
Total judges: 36; 
Number of district courtrooms needed: 17; 
Courtrooms per judge: 0.47; 
Per-room utility[A]: 94%. 

District judges: 17; 
Senior judges: 8; 
Magistrate judges: 13; 
Total judges: 38; 
Number of district courtrooms needed: 18; 
Courtrooms per judge: 0.47; 
Per-room utility[A]: 95%. 

District judges: 18; 
Senior judges: 9; 
Magistrate judges: 13; 
Total judges: 40; 
Number of district courtrooms needed: 19; 
Courtrooms per judge: 0.48; 
Per-room utility[A]: 94%. 

District judges: 19; 
Senior judges: 9; 
Magistrate judges: 14; 
Total judges: 42; 
Number of district courtrooms needed: 20; 
Courtrooms per judge: 0.48; 
Per-room utility[A]: 94%. 

District judges: 20; 
Senior judges: 10; 
Magistrate judges: 15; 
Total judges: 45; 
Number of district courtrooms needed: 21; 
Courtrooms per judge: 0.47; 
Per-room utility[A]: 95%. 

Source: GAO. 

[A] 100 percent is full use. 

[End of table] 

* For the outcomes we reported, we also modeled centralized sharing 
for magistrate judges separately because expert panel members stated 
that magistrate courtrooms differ in size from district courtrooms and 
would not be appropriate for district judges to use. 

* As we stated in the report, our sharing model resulted in 
approximately 18 to 22 percent of unused courtroom time. Our levels of 
sharing resulted in events being completed as scheduled with extra 
time to spare. 

23. AOUSC highlighted Judge Preska's contention that the draft report 
misrepresented panelists' views and included a partial quote from the 
draft report. However, the whole quote was in agreement with Judge 
Preska's view that the panelist was indicating it took longer to 
resolve cases when judges were sharing courtrooms. We revised the 
report to make this clearer. 

24. We addressed Judge Preska's statements about our characterization 
of the experts' views in our comments on her letter that is attached 
to AOUSC's letter. 

25. AOUSC indicated that an effective courtroom sharing model requires 
an understanding of the litigation process. We incorporated these 
elements into our model to the fullest extent possible. However, we 
recognize that there are different approaches to computer modeling of 
courtroom use and recommend that the courts expand nationwide 
courtroom sharing policies to more fully reflect the actual and 
scheduled use of courtrooms as demonstrated with the comprehensive 
data collected by FJC. 

26. See comment 22. 

27. We clarified the report to indicate that there are different 
definitions of what constitutes a trial; however, the median length of 
trials identified in our report was taken from the 2008 Annual Report 
of the Director: Judicial Business of the United States Courts, 
published by AOUSC. Furthermore, this number was not inputed into the 
model; the percentage of time spent on trials incorporated into the 
model was taken directly from the specific courtroom scheduling and 
use data gathered by FJC. 

28. AOUSC cited a 2000 Ernst & Young report in describing the 
complexities of courtroom sharing. In a 2001 report,[Footnote 46] we 
assessed the sufficiency of Ernst & Young's data and analysis in 
determining the feasibility of courtroom sharing and found that Ernst 
& Young did not gather sufficient data or conduct the needed analysis 
to resolve the courtroom sharing issue. 

29. According to AOUSC, it is difficult to model judicial processes 
because of its inherent variability and uncertain nature. Our model 
addresses the uncertainty of courtroom scheduling by accounting for 
unused scheduled time (see bullet 1, comment 22). We also note in our 
report that, according to our model, the average time that remained 
unscheduled for the mix of judges from the 27 courthouses was between 
18 and 22 percent. 

30. AOUSC questioned why we did not provide the draft report to FJC 
for comment. We coordinated with FJC beforehand and agreed that we 
would provide the draft report to our judiciary liaison and that, as 
part of the judiciary, FJC would obtain a copy of the report and 
provide comments through the central judiciary liaison, which they did. 

31. FJC stated that it is unclear how we differentiated events in our 
model. This information is not relevant, since we ensure that all 
events are able to occur as scheduled. Nonetheless, we added the 
following information to our report. We differentiated events and time 
in the model by grouping them as case-related events, nonjudge-related 
events, and unused scheduled time, and we allotted enough time for 
each of these events to occur without delay (for further assumptions 
in the model, see comment 22). 

32. FJC stated that we did not incorporate caseload data into our 
model. The data FJC provided to us did not include any additional 
details about caseload, and FJC removed the identifiers from the data 
as a condition of providing the data to us, precluding any caseload 
analysis. However, we did note when the data were correlated and not 
correlated to different caseload and case-filing measures, as FJC 
noted. 

33. For information on why we assumed a 10-hour work day, see bullet 2 
of comment 22. 

34. FJC noted that our model output might suggest that some events may 
get bumped from their scheduled day. This is not the case. Our model 
allows us to determine the fewest number of courtrooms needed for no 
backlog in court proceedings. 

35. FJC indicated that we provided little information on the outcomes 
of our model. The dedicated sharing ratios identified in table 5 
represent a lowest common denominator that can be calculated for 
courthouses with any number of judges, and our model results under 
centralized sharing are identified in table 6 for our case study 
courthouses. However, we did not recommend the judiciary implement our 
courtroom sharing model, but expand sharing based on actual courtroom 
scheduling and use data. For additional model output for centralized 
sharing, see the tables in comment 22. 

36. FJC stated that we seem to use only average levels of courtroom 
use in our model. This is not the case. We modeled the actual and 
scheduled usage levels for all assigned courtrooms. Our statement 
meant that our model assumes the data provided are representative of 
the actual demand for courtrooms, which FJC indicated that it tried to 
accomplish in its data collection. 

37. FJC stated that our expert panel did not have an ongoing role in 
the development of our model. We did develop the model, but the expert 
panel provided input into the parameters of the model, as appropriate, 
throughout our engagement. 

38. Judge Preska indicated that our report mischaracterizes, 
oversimplifies, and omits important parts of the discussions that took 
place during our expert panel and at our visit to the Moynihan U.S. 
Courthouse. We disagree. Our standards of evidence detailed in 
generally accepted government auditing standards and outlined in 
comment 1, ensure that our facts are sound. We visited numerous 
courthouses, in addition to the judge's, and Judge Preska was present 
only for the 1-day portion of our panel. As stated in our draft and 
final reports, some of the invited experts were unable to attend the 1-
day session, and we interviewed them separately. Their views and our 
analysis of all the experts' views were not available to Judge Preska. 

39. Judge Preska disagreed with the statistics we used related to the 
length of trials. We do not dispute that trial frequency and length 
may differ across districts and Judge Preska's personal experience may 
differ from other judges. However, we use AOUSC's statistics as cited 
in the report. See comment 27 for additional information related to 
this point. 

40. Judge Preska stated that our model implies courtrooms are used 
only for trials. This is incorrect. As noted in both the draft and 
final versions of the report, all used and unused scheduled time 
documented by FJC were considered use of a courtroom and included in 
our model, not just trial time. 

41. Judge Preska stated that our model contemplates rescheduling 
events on short notice. Our model does not reschedule any unused time 
for events canceled or postponed within a week of the event. 

42. Judge Preska stated that our report does not cite the expert 
panel's unanimity that courtroom sharing was unworkable. We believe 
that our report does reflect the accurate views of the entire experts' 
panel. In the report, we note that some judges remain skeptical that 
sharing could work on a permanent basis. Nonetheless, all judges that 
we spoke with who had sharing experience stated that a trial had never 
been delayed because a courtroom was not available. Additionally, as 
noted in comment 38, Judge Preska was only present for the 1-day 
portion of our panel. Some experts were unable to attend the 1-day 
panel session and were interviewed individually. Judge Preska did not 
participate in these interviews. 

43. Judge Preska stated that our discussion of the use of technology 
in the judicial process demonstrates our lack of understanding of the 
judicial process. In terms of increased technology, we reported what 
the expert panel and other judges told us and our report consequently 
reflects the expert panel's knowledge of the judicial process. 

44. Judge Preska stated that designs of courthouses may be more or 
less conducive to courtroom sharing, but disagreed with the 
alternating courtroom and chamber floors that we present in the 
report. We revised the report to include the idea that perimeter 
chambers around several courtrooms of varying sizes could facilitate 
courtroom sharing. 

45. Judge Preska stated that courtroom availability from 8 a.m. to 6 
p.m. is wholly unrealistic. See bullet 2 of comment 22 for our 
discussion of why we assumed courtrooms would be available for 
scheduling from 8:00 a.m. to 6:00 p.m. 

46. Judge Preska stated that we assume that trials would run in 
shifts. This is not the case. All that we assume is that the courtroom 
is available for the 10 hours. According to judges we spoke with early 
morning and late afternoon hours during trial time are used for set up 
and take down. Other possible uses for hours judges do not wish to 
hold case events are ceremonies, education, training, and maintenance. 
How courts choose to use that time in practice is not addressed in our 
report. 

47. Judge Preska represented our model as treating all court 
proceedings the same. We gave all scheduled events top urgency and 
made time for all events because we did not have criteria for 
prioritizing some areas over others. A different model could establish 
a priority ranking for events and might allow for even more efficient 
courtroom use. We recommended that the judiciary expand nationwide 
courtroom sharing policies to more fully reflect the actual scheduling 
and use of district courtrooms. 

48. Judge Preska stated that our model relies on only one metric-- 
efficiency--at the expense of the delivery of justice. We understand 
that providing one courtroom per judge is convenient for scheduling 
purposes, but we remain confident that our model shows that the 
efficiency of courtroom use can be improved through sharing without 
harming the delivery of justice. We designed our courtroom sharing 
model specifically to ensure more than sufficient court space would be 
available to deliver justice. For example, not treating courtrooms as 
available after events have been canceled or postponed greatly reduces 
the amount of time courtrooms can be scheduled by leaving courtrooms 
dark much of the time. Also, our model includes all of the time for 
noncase-related uses, such as tours and other educational events that 
could be scheduled on weekends and after 6 p.m. In addition, not 
requiring district judges to share courtrooms with magistrate judges 
reduces opportunities for efficiencies that could otherwise be 
achieved (see table 11 in comment 22). That said, we continue to 
believe that efficiency must enter into the equation of courtroom use. 
Otherwise, the practices that resulted in the construction of 3.56 
million square feet of extra courthouse space at a cost of $835 
million will continue. 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Mark L. Goldstein (202) 512-2834 or goldsteinm@gao.gov: 

Staff Acknowledgments: 

In addition to the contact named above, Tammy Conquest (Assistant 
Director), Keith Cunningham, Bess Eisenstadt, Brandon Haller, William 
Jenkins, Susan Michal-Smith, Steve Rabinowitz, Alwynne Wilbur, Jade 
Winfree, and Sarah Wood made key contributions to this report. 

[End of section] 

Footnotes: 

[1] An annex is an addition to an existing building. 

[2] GAO, Federal Courthouse Construction: Estimated Costs to House the 
L.A. District Court Have Tripled and There Is No Consensus on How to 
Proceed, [hyperlink, http://www.gao.gov/products/GAO-08-889] 
(Washington, D.C.: Sept. 12, 2008). 

[3] See, for example, GAO, Federal Courthouse Construction: More 
Disciplined Approach Would Reduce Costs and Provide for Better 
Decision-making, [hyperlink, 
http://www.gao.gov/products/GAO/T-GGD-96-19] (Washington, D.C.: Nov. 
19, 1995) and GAO, Courthouse Construction: Information on Project 
Cost and Size Changes Would Help to Enhance Oversight, [hyperlink, 
http://www.gao.gov/products/GAO-05-673] (Washington, D.C.: June 30, 
2005). 

[4] An independent and comprehensive study of courtroom use in 
district courts was conducted by the Federal Judicial Center (FJC) at 
the request of the Judicial Conference of the United States, which, 
after the study was completed, issued a report on the study. See 
Judicial Conference of the United States, Report on the Usage of 
Federal District Court Courtrooms, Sept. 16, 2008. The study served as 
a basis for the Judicial Conference's adoption of several policy 
changes related to the sharing of courtrooms by judges, which are 
described later in this report. 

[5] District judges who are eligible to retire may continue to hear 
cases on a full-or part-time basis as senior judges. 

[6] Before Congress makes an appropriation for a proposed project, GSA 
submits to the Senate Committee on Environment and Public Works and 
the House Committee on Transportation and Infrastructure detailed 
project descriptions, called prospectuses, for authorization by these 
committees when the proposed construction, alteration, or acquisition 
of a building to be used as a public building exceeds a specified 
threshold. For purposes of this report, we refer to these committees 
as "authorizing committees" when discussing the submission of the 
prospectuses and providing additional information relating to 
prospectuses to these committees. Furthermore, for purposes of this 
report, we refer to approval of these projects by these committees as 
"congressional authorization." See 40 U.S.C. § 3307. 

[7] There are also two trial courts (the Court of International Trade 
and the United States Court of Federal Claims) and one court of 
appeals (the Court of Appeals for the Federal Circuit) with nationwide 
jurisdiction over certain types of cases. 

[8] Temporary judgeships are those created by statute for a specified 
minimum period of time because of an increase in workload that is 
expected to be temporary (such as a large number of asbestos filings). 
Temporary judgeships are temporary to the district court, not to the 
judge. Judges appointed to temporary district judgeships hold lifetime 
appointments. At the end of the period for which the temporary 
judgeship was authorized, the temporary judgeship expires unless 
Congress either extends the authorization or converts the position to 
a permanently authorized one. If the temporary judgeship expires, the 
judge who occupied that position does not leave the bench, and until 
the next vacancy in that court occurs, the number of judges exceeds 
the number of permanently authorized judgeships. When the next 
judicial vacancy in that court occurs, the position is not filled and 
the number of judges is thus reduced to the number of permanently 
authorized judgeships. 

[9] In these data, the judiciary includes the total numbers of civil 
cases, criminal cases, and defendants; civil and criminal weighted 
filings; weighted and unweighted bankruptcy filings; and appeals. 

[10] Weighted filings statistics account for the different amounts of 
time district judges take to resolve various types of civil and 
criminal actions. Types of civil cases or criminal defendants whose 
cases typically take an average amount of time to resolve each receive 
a weight of approximately 1.0; for more time-consuming cases, higher 
weights are assigned (e.g., a death-penalty habeas corpus case is 
assigned a weight of 12.89); and cases demanding relatively little 
time from judges receive lower weights (e.g., overpayment and recovery 
cases, such as a defaulted student loan case, are assigned a weight of 
0.10). 

[11] The Judicial Conference standard for district court judgeships is 
430 weighted filings per judgeship, except in the case of small courts 
with fewer than five authorized judgeships, in which case the standard 
is 500 weighted filings per judgeship. 

[12] For the purposes of this report, we are referring to space 
assigned both to a specific tenant and to joint use as tenant space. 

[13] In line with GSA's method of calculating efficiency, this 
category includes the space GSA categorizes as building common, floor 
common, and unmarketable space. 

[14] We did not evaluate how much of the extra space was unused. 

[15] The estimated construction cost of the extra space was $640 
million in nominal (unadjusted) dollars. We adjusted for inflation 
using a price index for construction costs from the Bureau of Economic 
Analysis and Global Insights. We adjusted expenditures to 2010 
constant dollars. 

[16] We did not attempt to calculate the rent attributable to the 
extra square footage due to exceeding congressionally authorized gross 
square footage because some of this extra square footage is for 
tenants other than the judiciary or occurs in building common or other 
space, the costs of which are not directly passed on to the judiciary 
in rent. We therefore calculated the annual operations and maintenance 
costs for all extra space due to exceeding congressionally authorized 
gross square footage and for the extra building common and other space 
due to overestimating the number of judges and judges not sharing 
courtrooms. 

[17] The remaining lifetime costs include land acquisition, planning, 
renewal/revitalizations, and disposal. 

[18] We chose the seven courthouses for case studies because they 
provided examples of courthouses that exceeded the congressionally 
authorized size and represented a wide distribution of courthouse 
sizes, dates of completion, and geographical locations. 

[19] For all 33 courthouses in our scope, we used the congressionally 
authorized gross square footage for the construction of the 
courthouse. We compared the authorized gross square footage, including 
inside parking, with the actual gross square footage, including inside 
parking. 

[20] For the purposes of this report, we are using the term building 
common and other space to include GSA's categories of building common, 
floor common, and unmarketable space and the term tenant space to 
include GSA's categories of tenant space, joint use space, and vacant 
space. 

[21] In a building with 67 percent efficiency, 67 percent of the total 
gross square footage, excluding parking, consists of tenant space and 
the remainder consists of building common and other space. 

[22] GSA defines the gross square footage of a building as the total 
constructed area of a building, which includes tenant spaces and 
building common and other spaces, such as lobbies and mechanical 
rooms--as well as indoor parking. 

[23] The O'Connor Courthouse is 831,604 gross square feet (275,794 
square feet over its authorized 555,810 gross square feet), the 
Hammond, Indiana, Courthouse is 315,978 gross square feet (104,778 
square feet over its authorized 211,200 gross square feet), and the 
Arnold Courthouse Annex is 254,911 gross square feet (99,594 square 
feet over its authorized 155,317 gross square feet). 

[24] [hyperlink, http://www.gao.gov/products/GAO-05-673]. 

[25] See GSA's 2010 Fiscal Year Appropriations Act, Pub. L. No. 111- 
117, Div. C. Title V, 123 Stat. 3034, 3187-3188 (2009). Every year 
from fiscal year 1995 through fiscal year 2010, the GSA appropriations 
act has contained this requirement except for fiscal year 1998, when 
no appropriation was made for new construction or acquisition. For 
fiscal years 1990 through 1994, the GSA appropriations acts stated 
that these projects could not exceed their authorized cost by more 
than 10 percent. 

[26] For 8 of these 15 courthouses, the total project cost increased 
by about 1 to 9 percent over the cost estimate provided to 
congressional authorizing committees at the construction phase, while 
for 3 of the 15 courthouses, the total project cost was at or slightly 
under budget. 

[27] According to GSA, the 67 percent efficiency target is intended 
for application to standalone new courthouses, and application to an 
annex is impractical because of the need for connections between the 
courthouse and the annex. However, we consider the efficiency of the 
Bryant Annex to be relevant because in the plans for this annex 
provided to congressional committees for authorization, GSA based its 
request for total gross square footage on an annex that would be 67 
percent efficient. 

[28] GAO, Internal Control: Standards for Internal Control in the 
Federal Government, [hyperlink, 
http://www.gao.gov/products/GAO/AIMD-00-21.3.1] (Washington, D.C.: 
November 1999.) 

[29] The ceilings of special proceedings courtrooms and appellate en 
banc courtrooms (in which all the circuit's judges sit together on a 
panel and decide a case) were to be 18 feet high. 

[30] The judiciary makes the 10-year estimates during the planning 
stages of new courthouses and major annexes. We did not include 5 
courthouses in this section because they have not yet reached the end 
of their 10-year planning period. 

[31] Each of the five courthouses that met or exceeded their 10-year 
estimates for judges projected increases of zero or one judge for 
planning periods ending from 2004 to 2006. 

[32] The Limbaugh, Sr., Courthouse in Cape Girardeau, Missouri, is not 
included as a case study in this analysis because it has not reached 
the end of its 10-year planning period. 

[33] Courtroom space calculations include square footage for spaces 
that are necessary for courtroom use, such as soundlocks (an entryway 
designed to reduce sound), audiovisual storage space, and public 
waiting areas. Additional spaces associated with courtrooms vary by 
courtroom type and may include, among other things, coat closets, 
judges' conference rooms, judges' robing rooms, exhibit storage 
spaces, and offices for court reporters. 

[34] GAO, Federal Judiciary Space: Long-Range Planning Process Needs 
Revision, [hyperlink, http://www.gao.gov/products/GAO/GGD-93-132] 
(Washington, D.C.: Sept. 28, 1993). 

[35] GAO, Federal Judgeships: General Accuracy of District and 
Appellate Judgeship Case-Related Workload Measures, [hyperlink, 
http://www.gao.gov/products/GAO-08-928T] (Washington, D.C.: June 17, 
2008). 

[36] H.R. 3662, 111th Cong. (2009) and S. 1653, 111th Cong. (2009). 

[37] Federal Judicial Center, The Use of Courtrooms in U.S. District 
Courts: A Report to the Judicial Conference Committee on Court 
Administration & Case Management, (Washington, D.C.: July 18, 2008). 

[38] Our model does not reduce the number of courtrooms in six 
courthouses for the following reasons: four already had sharing 
between judges and the model did not find increased sharing 
possibilities and therefore imposed no reduction in courtrooms; one 
has only one district and one magistrate judge; and one courthouse has 
only bankruptcy judges and is out of our scope for district and 
magistrate sharing opportunities. 

[39] This number also includes the support spaces directly related to 
a courtroom, as applicable, such as jury rooms, evidence closets, and 
lawyer conference rooms. 

[40] GAO, Courthouse Construction: Better Courtroom Use Data Could 
Enhance Facility Planning and Decisionmaking, [hyperlink, 
http://www.gao.gov/products/GGD-97-39] (Washington, D.C.: May 19, 
1997). 

[41] Federal Judicial Center, The Use of Courtrooms in U.S. District 
Courts: A Report to the Judicial Conference Committee on Court 
Administration & Case Management (Washington, D.C., July 18, 2008). 

[42] Marc Galanter, "The Vanishing Trial: An Examination of Trials and 
Related Matter in Federal and State Courts," Journal of Empirical 
Legal Studies, Vol. 1, Issue 3 459-570, November 2004. 

[43] Sharing was not possible in some courthouses because there were 
only one or two district and/or magistrate judges. 

[44] The panel consisted primarily of judges and included other 
judicial experts with experience in or knowledge of courtroom sharing. 
Judges who were chosen for the panel but were unable to take part in 
the 1-day discussion were contacted separately, and semistructured 
interviews were conducted with them via telephone or in person. 

[45] There are different definitions of what constitutes a trial. The 
median trial length reported here reflects Table C-8 from the 
Administrative Office of the United States Courts, 2008 Annual Report 
of the Director: Judicial Business of the United States Courts. 
(Washington, D.C., U.S Government Printing Office, 2009. 

[46] GAO, Courthouse Construction: Sufficient Data and Analysis Would 
Help Resolve the Courtroom-Sharing Issue, [hyperlink, 
http://www.gao.gov/products/GAO-01-70] (Washington, D.C.: Dec. 14, 
2000). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: