This is the accessible text file for GAO report number GAO-10-625 
entitled 'High Speed Rail: Learning From Service Start-ups, Prospects 
for Increased Industry Investment, and Federal Oversight Plans' which 
was released on June 17, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Committees: 

United States Government Accountability Office: 
GAO: 

June 2010: 

High Speed Rail: 

Learning From Service Start-ups, Prospects for Increased Industry 
Investment, and Federal Oversight Plans: 

GAO-10-625: 

GAO Highlights: 

Highlights of GAO-10-625, a report to congressional committees. 

Why GAO Did This Study: 

The American Recovery and Reinvestment Act (Recovery Act) and 
subsequent appropriations have dramatically increased federal funds 
available for high speed intercity passenger rail from $120 million in 
fiscal year 2008 and fiscal year 2009 combined to $10.5 billion 
available in fiscal year 2010. Other issues, such as developing 
industry capacity to supply rail equipment and fostering multiyear 
public support for such systems must be resolved. 

As part of its efforts to assess Recovery Act initiatives, GAO 
reviewed (1) how states started or improved passenger rail services in 
the recent past, (2) rail industry plans to accommodate the increased 
passenger rail investments, and (3) Federal Railroad Administration 
(FRA) plans to oversee the use of federal intercity passenger rail 
funds. GAO reviewed federal legislation; interviewed state, industry 
and federal officials; and reviewed selected literature. 

GAO is not making any recommendations. The Department of 
Transportation did not express an overall opinion on a draft of this 
report. It did provide technical and clarifying comments, which GAO 
incorporated. 

What GAO Found: 

State successes to initiate or improve intercity passenger rail 
services in the recent past (the last 15 years), hinged largely on 
their abilities to build public and political support, secure funding, 
obtain equipment, and manage their services. Public and political 
support and funding provided a foundation for these services. States 
acquired equipment by using collaborative and cost-saving approaches. 
Further, states managed their rail services by building consensus with 
stakeholders, borrowing expertise, and developing state capacity. All 
of these activities will be important for states that seek to initiate 
or improve services in the future, including developing conventional 
passenger rail (operating at speeds up to 79 miles per hour), higher 
speed passenger rail (operating at speeds up to 150 miles per hour), 
and even high speed rail services (operating at speeds of 150 miles 
per hour or more). 

Rail industry stakeholders are optimistic that they can meet increased 
public investment in intercity passenger rail; however, they are 
looking for (1) federal leadership in setting safety standards for 
high speed rail and in promoting interstate cooperation for service 
across state lines, among other things, and (2) stable funding to 
create a structure for developing a passenger rail marketplace. 
Additionally, stakeholders said that a stable federal funding stream 
would encourage firms to enter and invest in the intercity passenger 
rail marketplace. However, even with strong federal leadership and 
funding it could take several years to provide the necessary 
infrastructure, such as for building new passenger rail cars, 
potentially making it difficult to spend some Recovery Act high speed 
rail funds by 2017, as required by law. 

As a result of Recovery Act funding and the Passenger Rail Investment 
and Improvement Act of 2008, FRA has had to develop a rail program and 
an oversight approach. Among other things, FRA had to quickly draft a 
preliminary national rail plan and a high speed rail strategic vision, 
as well as develop a program to distribute Recovery Act funds. As a 
result, FRA officials stated that they concentrated their efforts on 
meeting these requirements and they are currently designing their 
oversight program. FRA is in its early stages of setting up agreements 
with its state grantees and hiring both FRA and contractor personnel 
to oversee how the federal funds are used. FRA is planning to release 
another version of its national rail plan in September 2010 which it 
expects to discuss issues such as the roles of federal, state, and 
local governments in rail transportation and public and private 
funding sources. The strategic vision did not define the goals, 
stakeholder roles, or objectives for federal involvement in high speed 
intercity passenger rail and the preliminary national rail plan did 
not have any recommendations for future action. While states will be 
the recipients of Recovery Act funds, many states do not have state 
rail plans that would establish strategies and priorities, capital 
investments, and public benefits of rail investments in the state. To 
try to stimulate the economy quickly, Congress exempted projects 
funded by the Recovery Act and recent appropriations from being in 
state rail plans. 

View [hyperlink, http://www.gao.gov/products/GAO-10-625] or key 
components. For more information, contact Susan Fleming at (202) 512-
2834 or flemings@gao.gov. 

[End of section] 

Contents: 

Letter: 

Background: 

States Developed Services by Generating Support, Securing Funding, 
Obtaining Equipment, and Managing Services: 

Industry Stakeholders View Federal Leadership as Important in Creating 
a Robust Intercity Passenger Rail Market: 

FRA's New Responsibilities Have Held Back Developing a National Rail 
Plan, Strategic Vision, and Grant Oversight Plan: 

Concluding Observations: 

Agency Comments: 

Appendix I: Scope and Methodology: 

Tables: 

Table 1: New or Improved Service Sponsored by States, 1995-Present: 

Table 2: Annual State Operating Support: 

Table 3: Issues Identified by Rail Industry Stakeholders for Federal 
Action: 

Table 4: FRA's Oversight Plan in Relation to Selected Grant Oversight 
Principles: 

Table 5: Organizations Contacted: 

Figures: 

Figure 1: Recovery Act High Speed Rail Awards: 

Figure 2: Stages of New Rail Car Development and Manufacturing: 

Abbreviations: 

Amtrak: National Railroad Passenger Corporation: 

FRA: Federal Railroad Administration: 

FTA: Federal Transit Administration: 

PRIIA: Passenger Rail Investment and Improvement Act of 2008: 

Recovery Act: American Recovery and Reinvestment Act of 2009: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

June 17, 2010: 

The Honorable Christopher Bond: 
Ranking Member: 
Subcommittee on Transportation, Housing and Urban Development, and 
Related Agencies: 
Committee on Appropriations: 
United States Senate: 

The Honorable Corrine Brown: 
Chair: 
Subcommittee on Railroads, Pipelines, and Hazardous Materials: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

Interest in passenger rail service in the United States is high. 
Recent legislation, especially the American Recovery and Reinvestment 
Act of 2009 (Recovery Act), has established a new federal role in and 
provided an unprecedented amount of federal funds for intercity 
passenger rail. Thirty-seven states and the District of Columbia 
submitted 259 applications totaling approximately $57 billion for the 
$8 billion that the Recovery Act made available for new passenger rail 
corridors or improvements to existing service. Passenger rail 
operators and suppliers from around the world are showing interest in 
making and operating high speed passenger trains for a possible 
emerging U.S. market. In addition, prominent statements by the 
President, the Vice President, the Secretary of Transportation, and 
others have elevated the profile of intercity passenger rail service 
and promoted its possible public benefits including energy efficiency, 
reductions in greenhouse gas emissions, and road and airport 
congestion reduction. 

However, while there is a palpable excitement created by the Recovery 
Act's funding for new high speed rail service, establishing new 
service is a difficult, multiyear effort. This effort hinges on, among 
other things, the availability of federal capital and state operating 
funds to build and operate systems that go far beyond the funds 
provided by the Recovery Act in a time of continuing federal and state 
deficits; the ability of states to work together for service that 
crosses state lines; gaining the cooperation from private railroads 
which own most of the rail infrastructure in the United States; and 
obtaining equipment, such as rail cars, which can take years to 
design, test, and build. In addition, the Federal Railroad 
Administration (FRA) recognizes that it has to transform itself from 
essentially a rail safety organization to one that can make 
multibillion dollar investment choices while simultaneously carrying 
out its safety mission. 

To provide some insight into these issues, this report, as part of our 
overall effort to assess Recovery Act spending, focuses on (1) how 
states started or improved passenger rail services in the recent past; 
[Footnote 1] (2) rail industry's plans to accommodate increased 
passenger rail investments; and (3) FRA's plans to oversee the use of 
federal intercity passenger rail funds. 

Our overall approach to addressing these topics was to (1) review 
federal legislation, regulations, plans, and other guidance; (2) 
interview a broad cross-section of intercity passenger rail 
stakeholders, including FRA, states that have established or improved 
intercity passenger rail service, freight railroads, the National 
Railroad Passenger Corporation (Amtrak), and other potential operators 
of intercity passenger rail service; passenger rail car manufacturers; 
railroad construction contractors; and industry and transportation 
associations; and (3) review studies by various organizations, 
including the American Association of State Highway and Transportation 
Officials, the Transportation Research Board, and the Congressional 
Research Service, as well as our reports on high speed rail. To gain 
some insight into the types of infrastructure improvements necessary 
to increase speeds and improve the performance of intercity passenger 
rail service, we visited railroad projects in Indiana, Michigan, and 
Illinois designed to reduce rail congestion and increase train speeds. 
To provide principles of grants oversight that could be used by FRA as 
it formulates its grants management program, we identified important 
elements of an effective grants oversight program from information 
provided by the Comptroller General's Domestic Working Group and 
contained in our reports evaluating various federal grants programs. 
[Footnote 2] 

We conducted this performance audit from June 2009 to June 2010 in 
accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe 
that the evidence obtained provides a reasonable basis for our 
findings and conclusions based on our audit objectives. 

Background: 

Since Amtrak started operations in 1971, federal involvement in 
funding intercity passenger rail has mainly consisted of capital and 
operating subsidies to Amtrak annually appropriated from general 
funds. However, recent legislation has vastly increased the federal 
role in and federal funds for developing intercity passenger rail 
service, making the federal government a major investor with state 
governments in passenger rail service. The Passenger Rail Investment 
and Improvement Act (PRIIA), enacted in October 2008, authorized over 
$3.7 billion for three different federal programs for high speed rail, 
intercity passenger rail congestion, and capital grants. PRIIA 
required that projects funded through two of these three programs be 
included in a state rail plan.[Footnote 3] A state rail transportation 
authority would develop a statewide rail plan coordinated with other 
state transportation planning programs that, among other things, must 
include an explanation of the state's passenger rail service 
objectives; an analysis of rail's transportation, economic, and 
environmental impacts in the state; and a long-range investment 
program for current and future freight and passenger infrastructure in 
the state. PRIIA also called for the Department of Transportation to 
establish minimum standards for the preparation and periodic revision 
of state rail plans. It also called for FRA to create a preliminary 
national rail plan within 1 year of passage of the law as well as a 
long-range national rail plan that is consistent with approved state 
rail plans. FRA released a preliminary national rail plan in October 
2009. 

The Recovery Act appropriated $8 billion for the three PRIIA- 
established intercity passenger rail programs.[Footnote 4] This 
funding represented a dramatic increase in federal funding for 
intercity passenger rail projects. The Recovery Act provided up to 100 
percent federal funding available for expenditure until 2017 and 
exempted projects from having to be included in a state rail plan; 
however, it did require, by incorporating the programs and the 
requirements of PRIIA, that the funds be competitively awarded and 
that the Department of Transportation develop a strategic plan to use 
these funds. The department released its strategic plan to use these 
funds in April 2009.[Footnote 5] In December 2009, the Department of 
Transportation's fiscal year 2010 appropriation also included $2.5 
billion for high speed rail and intercity passenger rail projects. 
These funds are subject to a 20 percent nonfederal matching 
requirement and the law also exempted these projects from having to be 
included in a state rail plan. The fiscal year 2011 budget proposal 
includes another $1 billion in intercity passenger rail funding. 
[Footnote 6] 

Amtrak, the nation's only intercity passenger rail operator, currently 
carries about 28 million passengers per year, which amounts to less 
than 1 percent of the country's total intercity passenger miles, 
although Amtrak's market share when compared to air service is higher 
in certain corridors. Amtrak operates long and short distance routes, 
as well as provides some commuter rail service through contracts with 
transit providers.[Footnote 7] Most of the nation's railroad network 
is owned by private, for-profit freight railroads with the primary 
exception of the Amtrak and state-owned Northeast Corridor from 
Washington, D.C., to Boston[Footnote 8] and almost 100 miles in 
southwest Michigan. As a result, about 70 percent of Amtrak's train 
miles are over tracks owned by other railroads.[Footnote 9] Top speeds 
are limited by track conditions. Amtrak's trains are generally limited 
to top speeds of 79 miles per hour off the Northeast Corridor and up 
to 150 miles per hour on the corridor.[Footnote 10] 

States provide financial support to certain intercity passenger rail 
corridors. In fiscal year 2010, 14 states funded short distance 
service in their states or between states by contract with Amtrak. 
Between 1995 and 2009, states initiated six new services and improved 
or increased the speed on seven existing intercity passenger rail 
services. (See table 1.) 

Table 1: New or Improved Service Sponsored by States, 1995-Present: 

New service: 

Service: Lynchburg Service; 
State: Virginia; 
Year(s) service initiated or improved: 2009. 

Service: Downeaster; 
State: Maine; 
Year(s) service initiated or improved: 2001. 

Service: Heartland Flyer; 
State: Oklahoma; 
Year(s) service initiated or improved: 1999. 

Service: Ethan Allen; 
State: Vermont; 
Year(s) service initiated or improved: 1996. 

Service: Piedmont; 
State: North Carolina; 
Year(s) service initiated or improved: 1995. 

Service: Vermonter; 
State: Vermont; 
Year(s) service initiated or improved: 1995. 

Improved service: 

Service: Lincoln Service; 
State: Illinois; 
Year(s) service initiated or improved: 2006. 

Service: Keystone Corridor; 
State: Pennsylvania; 
Year(s) service initiated or improved: 2006. 

Service: San Joaquin, Capitol Corridor, and Pacific Surfliner 
Corridors; 
State: California; 
Year(s) service initiated or improved: 1998-present. 

Service: Cascades Service; 
State: Washington; 
Year(s) service initiated or improved: 1999-2000. 

Higher speed on existing corridor: 

Service: Keystone Corridor; 
State: Pennsylvania; 
Year(s) service initiated or improved: 2006. 

Source: GAO. 

[End of table] 

Domestic passenger rail car manufacturing capacity has been in 
decline, along with the decline in intercity passenger rail service, 
since the 1950s. Foreign passenger rail car manufacturers have 
established factories in the United States--although mainly for the 
domestic rail transit market as Amtrak has not made a large capital 
purchase of passenger rail cars since the Acela trains in the late 
1990s. 

FRA is the primary federal agency responsible for formulating and 
enforcing railroad safety regulations and for distributing federal 
funds for intercity passenger rail service. The agency sets 
regulations for railroad safety, including rail car maintenance 
standards and track standards for operating passenger and freight 
trains at various speeds. Through grant agreements, FRA administers 
federal operational and capital grants to Amtrak, which have averaged 
between $1 billion and $1.3 billion per year since fiscal year 2003. 
FRA also approves Railroad Rehabilitation and Improvement Financing 
loans and Rail Line Relocation and Improvement Capital Grants, and is 
the granting agency for the $120 million in fiscal year 2008 and 
fiscal year 2009 capital funds to states for intercity passenger rail 
projects. 

In addition to the increase in federal funds, PRIIA and the Recovery 
Act have created new responsibilities for FRA to plan, award, and 
oversee the use of federal funds for intercity passenger rail. After 
passage of the Recovery Act, FRA officials said that they set their 
priorities to meet these responsibilities. According to these 
officials, FRA's immediate priorities included quickly awarding the 
funds responsibly and getting all of the Recovery Act funds obligated 
within 2 years. They also stated that their intermediate and long-term 
priorities included helping states advance their corridors and 
projects and gauging the effectiveness of the federal investments, 
respectively. FRA staff and management worked to meet these priorities 
by releasing a notice of funding availability and interim guidance on 
the high speed rail program,[Footnote 11] creating an overall 
strategic plan for implementing federal grants for high speed rail 
[Footnote 12] and releasing a preliminary national rail plan.[Footnote 
13] FRA staff and management held informational sessions with states 
and other stakeholders across the country and worked with state 
applicants to answer questions, evaluate, and provide feedback on 
preapplications for these funds. In the 5 months between the 
application deadlines and the grant award announcement, FRA and other 
department staff used criteria such as public return on investment, 
economic recovery benefits, and timeliness to completion to evaluate 
259 grant applications from 37 states and the District of Columbia. 

In January 2010, FRA announced that 62 projects in 23 states and the 
District of Columbia would receive approximately $8 billion in 
Recovery Act funds.[Footnote 14] (See figure 1.) The announced awards 
went to several types of intercity passenger rail projects--including 
almost $2.3 billion for initial investments in the planned over 200 
miles per hour service between Los Angeles and San Francisco and, 
eventually, Sacramento and San Diego; $1.1 billion to increase top 
speeds to 110 miles per hour for existing service between Chicago and 
St. Louis; $400 million for new service with a top speed of 79 miles 
per hour between Cincinnati and Cleveland; and $4 million for signal 
timing improvements in Texas to benefit Amtrak's existing Heartland 
Flyer service. All of the states that have initiated or improved 
services over the last 15 years were awarded about 62 percent of all 
Recovery Act high speed rail funds (about $4.9 billion of the $8 
billion available). 

Figure 1: Recovery Act High Speed Rail Awards: 

[Refer to PDF for image: map of the continental United States and 
accompanying data table] 

State: California; 
Award: $2,343 billion; 
Project details: For new high speed rail service, purchase right-of-
way, construct track, signaling systems, and stations, and complete 
environmental reviews and engineering. To improve conventional 
services, track improvements, and new equipment emissions controls. 

State: Connecticut; 
Award: $40 million; 
Project details: To improve existing conventional service, construct 
new track. 

State: District of Columbia; 
Award: $3 million; 
Project details: To improve existing passenger rail service. 

State: Florida; 
Award: $1.25 billion. 
Project details: For new high speed rail, construct track, build and 
improve stations, purchase equipment. 

State: Illinois; 
Award: $1.233 billion; 
Project details: For higher speed service, improve track, improve 
signal systems, improve stations, implement positive train control, 
conduct planning studies. 

State: Indiana; 
Award: $71 million; 
Project details: To improve existing conventional service, signal, and 
track improvements. 

State: Iowa; 
Award: $17 million; 
Project details: To improve existing conventional service, signal, and 
track improvements. 

State: Maine; 
Award: $35 million; 
Project details: To expand existing conventional service, track, and 
crossing improvements. 

State: Maryland; 
Award: $69 million; 
Project details: To improve existing passenger rail service. 

State: Massachusetts; 
Award: $70 million; 
Project details: To improve existing conventional service, track, 
station, and signal improvements. 

State: Michigan; 
Award: $40 million; 
Project details: To improve existing conventional service, station 
improvements, and build a new station. 

State: Missouri; 
Award: $31 million; 
Project details: To improve existing conventional service, track, and 
crossing improvements. 

State: New Jersey; 
Award: $39 million; 
Project details: To improve existing passenger rail service. 

State: New York; 
Award: $150 million; 
Project details: To improve existing conventional service, construct 
new track, improve signals, crossings, and stations. 

State: North Carolina; 
Award: $545 million; 
Project details: To improve existing conventional service, acquire 
rolling stock, improve track and stations, mitigate congestion. 

State: Ohio; 
Award: $400 million; 
Project details: For new conventional service, improve track, 
crossings, stations, and maintenance facilities. 

State: Oregon; 
Award: $8 million; 
Project details: To improve existing conventional service, upgrade 
station, and engineering and environmental work for track and signal 
improvements. 

State: Pennsylvania; 
Award: $26 million; 
Project details: To improve existing higher speed service, eliminate 
grade crossings, study extending service. 

State: Rhode Island; 
Award: $1 million; 
Project details: To improve existing passenger rail service. 

State: Texas; 
Award: $4 million; 
Project details: To improve existing conventional service, final 
design, and grade and crossing improvements. 

State: Vermont; 
Award: $50 million; 
Project details: To improve existing conventional service, and 
infrastructure improvements. 

State: Virginia; 
Award: $75 million; 
Project details: To improve existing conventional service, and 
construct track. 

State: Washington; 
Award: $590 million; 
Project details: To improve existing conventional service; construct 
track; and track, signal, and safety improvements. 

State: Wisconsin; 
Award: $822 million; 
Project details: To expand existing conventional service and to 
improve existing conventional service to higher speed service; track, 
signal, and station improvements; a new station, and positive train 
control technology. 

Sources: GAO analysis of FRA data; Map Resources (map). 

[End of figure] 

States Developed Services by Generating Support, Securing Funding, 
Obtaining Equipment, and Managing Services: 

Officials from states that initiated or improved intercity passenger 
rail services in the recent past told us that their ability to start 
or upgrade their services largely hinged on their ability to resolve a 
number of issues. First, public and political support and funding 
provided a foundation for initiating and improving their services. 
Second, states acquired equipment for their services through 
collaborative and cost-saving approaches. States also built consensus 
with stakeholders, borrowed expertise, and developed state capacity to 
effectively manage their rail services. 

The activities that helped states initiate and improve their services 
will be important for states seeking to initiate or improve services 
in the future--including developing conventional passenger rail, 
higher speed passenger rail, and high speed rail.[Footnote 15] 
Learning ways to build support, secure funding, obtain equipment, and 
effectively manage rail services will be even more crucial to states 
developing high speed rail because they will face long time frames, 
high costs, and a lack of experience in the U.S. passenger rail market 
for all stages of developing and managing these new passenger rail 
services. While other countries have experience with high speed 
passenger rail service, no state currently supports high speed 
intercity passenger rail service.[Footnote 16] While there are 
differences between conventional passenger and high speed passenger 
rail services, some of the lessons learned by states apply to both. As 
such, our review of state experiences with conventional passenger rail 
service could provide some insight into how states might accomplish 
both initiating and improving conventional passenger rail services, as 
well as developing higher and high speed passenger rail services. 

Public and Political Support and Funding Provided a Foundation for 
States to Develop Passenger Rail Services: 

State officials favoring investment in intercity passenger rail 
services secured funding to initiate or expand such services by 
achieving public and political support and by using innovative 
approaches for funding both capital and operating costs. Support from 
passenger rail proponents including governors, state legislators, 
passenger rail advocacy groups, and communities helped develop public 
and political support for committing state funds to capital and 
operating costs of passenger rail services. For example, corridor 
coalitions of grassroots supporters, advocates, and elected officials 
aided Illinois' efforts to gain support for making improvements and 
operating a new service. 

Infrastructure improvements for these services required significant 
investments from states to upgrade track, signals, crossings, and 
stations. The costs of these improvements varied, from small 
individual projects costing several million dollars to more extensive 
projects totaling more than $100 million. States drew upon a range of 
sources to supplement limited general funding available for capital 
improvements. Four states we interviewed established dedicated funding 
sources for capital improvements or acquired flexible federal funds to 
develop infrastructure.[Footnote 17] For example, Virginia used its 
rail enhancement fund, funded in part from a state rental car tax, in 
cooperation with a freight railroad to make $33 million in capacity 
improvements to initiate a new service. North Carolina used a 
combination of federal transportation enhancement funds,[Footnote 18] 
congressional directives (commonly called earmarks), and the state's 
share of a federal Congestion Mitigation and Air Quality Improvement 
Program grant for investments in capital improvements.[Footnote 19] 

Some states shared costs or offered incentives to Amtrak, freight 
railroads, and local governments to attract nonstate funds to support 
intercity passenger rail service. For example, North Carolina 
partnered with communities to redevelop train stations and Washington 
state recently established grant and loan incentive programs for 
public agencies and private right-of-way owners to help fund 
improvements on railroad infrastructure to improve the passenger and 
freight rail services in the state. 

The capital costs of high speed rail systems are expected to be of a 
magnitude far greater than for initiating or improving conventional 
and higher speed passenger rail services.[Footnote 20] Based on 
reported projections, construction costs to initiate new conventional 
service on existing right-of-way between Cleveland, Columbus, and 
Cincinnati, Ohio, would be about $1.4 million per mile.[Footnote 21] 
Similarly, improving existing services to higher speeds could cost 
about $1.9 million per mile for services in both Pennsylvania and 
Michigan;[Footnote 22] $11.8 million per mile for service from New 
York City to Niagara Falls, New York;[Footnote 23] and $15.2 million 
per mile to establish higher speed service from Charlotte, North 
Carolina, to Washington, D.C.[Footnote 24] These estimates are lower 
than projections to develop new high speed rail services in Florida 
and California, which would both require building new dedicated track 
instead of using existing infrastructure. Based on reported 
projections, final design and construction for high speed rail service 
between Tampa and Orlando, Florida, would cost approximately $36.7 
million per mile,[Footnote 25] and capital costs for high speed rail 
between Los Angeles and Anaheim, California, would be about $75.5 
million per mile.[Footnote 26] 

To secure annual operating subsidies, state rail officials gained 
support for their passenger rail services. According to state rail 
officials, this reporting, as well as support from governors, 
legislators, metropolitan planning organizations, or public grassroots 
efforts helped rail proponents obtain operating funds for passenger 
rail services. States reported performance indicators and other 
metrics such as ridership, on-time performance, and customer 
satisfaction to communicate the value of their services. A few states 
reported these indicators on an annual basis. 

States use state funds to support passenger rail operations, ranging 
from $1.5 million to $32.2 million per service annually. Support from 
these states covers 26 percent to 100 percent of the annual operating 
costs for these services. (See table 2.) Three states established 
dedicated state funding sources, and another two states used flexible 
federal transportation funds to overcome funding limitations to 
operate their services. For example, Pennsylvania established a public 
transportation trust fund with a set-aside for passenger rail 
operating expenses to avoid obtaining funding each year from the state 
legislature, and California derives operating support from a portion 
of the state sales tax on diesel fuel (with a portion of the state gas 
tax supporting capital expenditures). In addition, Vermont and Maine 
drew upon flexible federal funding from their states' Congestion 
Mitigation and Air Quality Improvement Program allocation, which 
provided 80 percent of initial operating costs. To meet its $13.5 
million operating budget, Maine contributes $1.2 million from general 
revenues and draws upon $4.8 million in federal Congestion Mitigation 
and Air Quality Improvement Program funds. 

Table 2: Annual State Operating Support: 

State: California; 
Service: Capitol Corridor; 
Type of state funding: Dedicated fund; 
Annual state operating support: $29.3 million; 
Total annual operating cost: $29.3 million; 
Percentage of annual operating cost supported by state: 100%. 

State: California; 
Service: Pacific Surfliner; 
Type of state funding: Dedicated fund; 
Annual state operating support: $24.9 million; 
Total annual operating cost: $35.5 million; 
Percentage of annual operating cost supported by state: 70%. 

State: California; 
Service: San Joaquin; 
Type of state funding: Dedicated fund; 
Annual state operating support: $32.2 million; 
Total annual operating cost: $32.2 million; 
Percentage of annual operating cost supported by state: 100%. 

State: Illinois; 
Service: Lincoln; 
Type of state funding: General fund; 
Annual state operating support: $11.9 million; 
Total annual operating cost: $20.7 million; 
Percentage of annual operating cost supported by state: 57%. 

State: Maine; 
Service: Downeaster; 
Type of state funding: General fund and flexible federal funds; 
Annual state operating support: $7.9 million; 
Total annual operating cost: $15.1 million; 
Percentage of annual operating cost supported by state: 52%. 

State: North Carolina; 
Service: Piedmont and Carolinian; 
Type of state funding: Combination of dedicated funds; 
Annual state operating support: $5.0 million; 
Total annual operating cost: $19.0 million; 
Percentage of annual operating cost supported by state: 26%. 

State: Pennsylvania; 
Service: Keystone; 
Type of state funding: Dedicated fund; 
Annual state operating support: $9.3 million; 
Total annual operating cost: $17.1 million; 
Percentage of annual operating cost supported by state: 54%. 

State: Vermont; 
Service: Ethan Allen; 
Type of state funding: General fund and flexible federal funds; 
Annual state operating support: $1.5 million; 
Total annual operating cost: $3.7 million; 
Percentage of annual operating cost supported by state: 41%. 

State: Vermont; 
Service: Vermonter; 
Type of state funding: General fund and flexible federal funds; 
Annual state operating support: $3.4 million; 
Total annual operating cost: $7.6 million; 
Percentage of annual operating cost supported by state: 45%. 

State: Washington; 
Service: Cascades; 
Type of state funding: Combination of dedicated funds; 
Annual state operating support: $14.3 million; 
Total annual operating cost: $31.2 million; 
Percentage of annual operating cost supported by state: 46%. 

Source: GAO analysis of best available data provided by states. 

[End of table] 

States Used Collaborative and Cost-saving Approaches to Acquire 
Equipment for Their Services: 

To secure passenger rail cars, states worked with Amtrak to use 
existing passenger rail cars efficiently or refurbished older 
equipment. Several states partnered with Amtrak during early stages of 
planning their services, which led to agreements for equipment and 
operations. For example, Illinois developed agreements in which Amtrak 
reallocated its equipment on other corridors to commit rail cars to 
the state's service, and Virginia and Amtrak jointly developed an 
operating service and capital improvement agreement in which Amtrak 
committed out-of-service passenger rail cars to the state's new 
service for which Virginia shared in the rehabilitation cost. 

Refurbishing old equipment and pooling equipment orders were other 
ways that states managed equipment costs. North Carolina officials 
said that although purchasing used equipment and refurbishing it was 
not the state's preferred approach, it reduced the cost of rail cars 
by 50 percent and gave the state more control over the amenities and 
appearance of its passenger rail cars. Additionally, some states 
reduced their procurement costs by pooling equipment orders. For 
example, California left options open on an order for new locomotives, 
which allowed other states and commuter agencies to obtain locomotives 
at a reduced per unit cost. 

Procuring equipment for high speed rail systems will also be 
difficult, in part because no equipment or specifications are 
currently available for these systems in the United States. According 
to FRA's High Speed Passenger Rail Safety Strategy, as a general best 
practice, to travel at speeds exceeding 150 miles per hour, passenger 
trains should operate on dedicated right-of-way.[Footnote 27] To 
achieve these high speeds, rail cars are designed to weigh much less 
than conventional intercity passenger rail equipment and are powered 
by electric locomotives, which are much lighter than diesel 
locomotives.[Footnote 28] Based on weight estimates from two 
manufacturers, a high speed rail car could weigh as much as 29 percent 
less than a conventional passenger rail car, depending on safety 
standards and design factors, and an electric locomotive could weigh 
as much as 33 percent less than a diesel locomotive. The cost of high 
speed rail cars and locomotives would also depend on safety and design 
factors that have not been defined by FRA. 

States Managed Services by Building Consensus with Stakeholders, 
Borrowing Expertise, and Developing State Capacity: 

States developed a variety of planning processes and approaches to 
stakeholder involvement as a way to build consensus among freight 
railroads, Amtrak, and other states. For example, California works 
with railroads to ensure freight capacity is maintained and 
accommodates projected freight growth through appropriate capital 
improvements. Additionally, Virginia worked for 5 months with diverse 
stakeholders such as Amtrak, freight railroads, a commuter rail 
operator, and local communities to agree to memoranda of understanding 
for using right-of-way and operating new services. Pennsylvania 
developed a Web site, held public meetings, and used other outreach 
activities to educate stakeholders about station area planning and 
redevelopment processes to bridge potential communication gaps between 
state passenger rail staff and public participants. In addition to 
these approaches to working with stakeholders, states leveraged 
outside expertise and built their own capacity to manage their 
services. For example, Illinois obtained support from Amtrak, which 
worked on the state's behalf to negotiate use agreements with freight 
railroads; Pennsylvania received planning assistance from FTA and FRA 
for its service; and Virginia worked with a freight railroad to 
develop a technical model for forecasting the impacts of its new 
passenger rail service on affected stakeholders. 

Developing high speed rail systems would involve long time frames, in 
part because acquiring dedicated right-of-way could involve many more 
local communities and private interests, lengthy environmental 
approval, and would require states to build consensus among a greater 
number of stakeholders than developing conventional passenger rail 
services on existing rights-of-way. We have reported that coordinating 
high speed rail projects among numerous stakeholders without an 
established institutional framework would make developing high speed 
rail difficult.[Footnote 29] 

Several states initiated their services with support from consultants 
and later developed management capacity within their state departments 
of transportation. These states developed their services by changing 
their management approaches and by building technical expertise. For 
example, Washington state revamped its passenger rail programs to 
facilitate communication with freight railroads and reorganized its 
rail division to more actively manage relationships with freight 
railroads and Amtrak. Additionally, California rail officials learned 
over time how to work most effectively with freight railroads on 
passenger rail projects and developed their own technical expertise 
and modeling knowledge over time. In addition to these approaches, two 
states established independent authorities to oversee their intercity 
passenger rail operations as a way to focus on the management needs of 
their services. For example, Maine created an independent authority to 
focus resources on managing its passenger rail service as well as 
managing relationships with multiple states, Amtrak, and a commuter 
railroad. Washington state rail officials reported that the state 
department of transportation's management change was successful and 
resulted in growth, improved on-time performance, and projects 
completed on time and under budget. 

Similarly, states that develop high speed rail services would need to 
build capacity to manage their programs. The administrative structures 
and technical expertise needed to manage these services would require 
consideration from states and affected stakeholders. Several state 
officials said that state departments of transportation would need 
additional technical expertise and staff resources to develop new high 
speed rail. 

Industry Stakeholders View Federal Leadership as Important in Creating 
a Robust Intercity Passenger Rail Market: 

Rail industry stakeholders, such as passenger rail operators, freight 
rail right-of-way owners, passenger rail car manufacturers, and 
general contractors are optimistic that they can meet increased public 
investment in intercity passenger rail, but they are looking for 
federal leadership and funding to create a structure for developing 
high speed rail. Additionally, stakeholders said that a stable federal 
funding stream would encourage firms to enter and invest in the 
intercity passenger rail marketplace. However, even after guidance is 
given on the application of federal laws and states advertise 
contracts, it could take several years to provide the necessary 
infrastructure such as new passenger rail cars, potentially making it 
difficult to spend Recovery Act high speed rail funds by September 30, 
2017, as required by law. 

Industry Stakeholders Are Optimistic They Can Meet Increased Public 
Investment in Intercity Passenger Rail Given Federal Leadership: 

Industry stakeholders said that the rail industry is in decline due to 
the recession; however, once the federal government distributes 
funding and establishes standards, rail industry stakeholders stated 
that they can begin to increase capacity to meet the increased 
investments. Stakeholders we interviewed stated that they are ready to 
increase capacity because several rail industry companies have been 
forced to lay off workers. 

While industry stakeholders are optimistic, it may take some time to 
build products and develop services to meet the increased public 
investment. For example, passenger rail car manufacturers, the 
Secretary of Transportation, and the FRA Administrator have stated 
that the Recovery Act funding could revive the U.S. market for these 
rail cars. Foreign passenger rail cars could not be used in this 
country because U.S. safety standards focus more on crash survival 
rather than crash avoidance, which is the norm for other countries' 
safety standards. Most manufacturers we spoke with said that the 
capacity to design and manufacture intercity passenger rail equipment 
existed in the United States and that they were eager to have orders 
placed. However, they also advised that it could take years to design 
and test new rail cars before they can be manufactured.[Footnote 30] 
(See figure 2.) For example, industry stakeholders told us that 
design, testing, and production of new passenger rail cars can take 
anywhere from almost 2.5 years to almost 9 years. Consequently, if 
states do not place rail car orders relatively soon, it could be 
difficult to spend Recovery Act funds before 2017. Some states that 
were awarded funding may be able to spend these funds before 2017 more 
easily than others. For example, Illinois' Chicago to St. Louis 
corridor already has project plans and agreements with freight 
railroads in place to use their federal funds to improve the rail 
infrastructure, whereas Ohio's "3-C" corridor is still in the 
preliminary planning stages.[Footnote 31] 

Figure 2: Stages of New Rail Car Development and Manufacturing: 

[Refer to PDF for image: illustrated timeline] 

Phase: Design; 
Minimum number of months: 12; 
Potential additional months: 12; 
Potential total: 25 months. 

Phase: Prototype development; 
Minimum number of months: 6; 
Potential additional months: 14; 
Potential total: 20 months. 

Phase: Testing; 
Minimum number of months: 3; 
Potential additional months: 18; 
Potential total: 21 months. 

Phase: Production; 
Minimum number of months: 8.5; 
Potential additional months: 33.5; 
Potential total: 42 months. 

Total time: 
Minimum number of months: 29.5; 
Potential additional months: 77.5; 
Potential total: 107 months. 

Source: GAO interviews with rolling stock manufacturers. 

[End of figure] 

In addition, it may take some time for potential passenger rail 
operators to build the capacity to operate services. With the 
exception of Amtrak, potential U.S. passenger rail operating companies 
only have experience operating commuter rail services, not intercity 
or high speed passenger rail services. Potential foreign passenger 
rail operating companies have extensive experience in operating 
intercity passenger rail and even high speed intercity passenger rail 
service, but they do not have experience operating those trains in the 
U.S. market with its unique operating conditions, legal environment, 
and infrastructure. Even Amtrak, with already established operations 
and agreements with freight railroads and other railroads, may have to 
amend its existing agreements or negotiate new agreements with each 
state and freight right-of-way owner for any new service it operates. 
The time required to negotiate these agreements can range from a few 
months to several years.[Footnote 32] Some stakeholders stated that 
Amtrak has advantages that might make it difficult for other potential 
operators to compete in the intercity passenger rail market. For 
example, Amtrak has three statutory rights that no other operator has: 
(1) access to tracks and facilities of privately owned railroads and 
regional transportation authorities, (2) access to that railroad 
infrastructure at incremental cost, and (3) priority over freight 
trains.[Footnote 33] 

Stakeholders are looking for federal leadership and funding to create 
a structure for high speed rail development, among other things. 
[Footnote 34] Federal leadership is important as most passenger trains 
operate over the national rail network and federal involvement could 
help states work cooperatively to develop routes that cross state 
lines. Aside from funding, stakeholders said that they were looking 
for a stronger federal policy and programmatic role. For example, 
stakeholders mentioned the need for a federal role in promoting 
interagency and interstate cooperation, and identified other potential 
federal roles, such as setting additional safety standards, promoting 
intermodal models of transportation, and assisting with right-of-way 
acquisition. The Recovery Act will provide a one-time infusion of 
federal funds, and PRIIA, among other things, provided the basis for a 
federal structure by mandating a national rail plan. However, 
stakeholders suggested that more funding and structure is needed. 

Although industry stakeholders are optimistic regarding intercity 
passenger rail implementation, they told us federal guidance could 
help provide structure to the intercity passenger rail market. 
According to industry stakeholders, there are several areas where 
federal guidance could help provide that structure: liability laws, 
safety regulations, Buy America requirements,[Footnote 35] and 
equipment standardization. (See table 3.) For example, industry 
stakeholders cited liability against accident and other train-related 
risks as a major challenge to high speed intercity passenger rail. 
This is a challenge because federal law provides limited protection to 
the operator or right-of-way owner since it only covers the claims of 
passengers, not third-party claims.[Footnote 36] 

Table 3: Issues Identified by Rail Industry Stakeholders for Federal 
Action: 

Issue: Liability; 
Stakeholder concern: Potential passenger rail operators said they 
might not bid on projects because: 
* Operator liability increases at higher speeds; 
* Uncertainty about and limitations of the federal $200 million 
liability limit; 
* Potential of states to seek additional liability coverage for 
intercity passenger rail operators; 
Stakeholder-identified federal solution: Industry stakeholders 
proposed a variety of solutions including: 
* public insurance; 
* public funding for insurance; 
* pooled insurance; and; 
* additional liability caps; 
FRA told us that the Administration has not yet taken a position on 
these liability issues. 

Issue: Safety standards; 
Stakeholder concern: Manufacturers may wait to design passenger rail 
cars because: 
* There are no standards for intercity passenger rail cars to operate 
at speeds greater than 125 miles per hour; 
* Designs may be discarded if they do not meet future regulations; 
Stakeholder-identified federal solution: FRA should establish the 
safety standards for high speed passenger rail service. FRA is 
developing guidance to be provided by June 2011 that will involve a 
series of several different passenger rail car and other safety 
standards. 

Issue: Buy America; 
Stakeholder concern: Industry stakeholders may be unable to enter the 
marketplace because: 
* FRA does not have a passenger rail car exemption similar to FTA's 
exemption; 
* They might be unable to meet the 100 percent manufactured in the 
United States requirement; 
Stakeholder-identified federal solution: FRA should issue guidance 
related to passenger rail cars in accordance with the FTA 
requirements. FRA has stated that it will only fund projects for which 
the steel, iron, and manufactured goods used in the project are 
produced in the United States--unless a waiver justification applies, 
is submitted, and approved. 

Issue: Equipment standardization; 
Stakeholder concern: Industry stakeholders generally agreed that 
standardization of design would be beneficial to the industry because 
it would allow them to quickly and easily fill orders; 
Stakeholder-identified federal solution: FRA should establish a 
standard design requirement and conduct an oversight and approval 
process to ensure that all vehicles met these requirements. FRA 
officials told us that they are working with other stakeholders to 
develop specifications for new passenger rail equipment. 

Source: GAO interviews with various rail industry stakeholders and FRA. 

[End of table] 

Freight railroads, for example, do not want to allow such service on 
their rights-of-way unless they are protected from liability. Freight 
railroads' liability insurance policies cover accidents related to 
their freight operations; however, when a freight railroad allows 
passenger rail service to operate over its right-of-way, it is exposed 
to additional risks as passengers may sue the passenger rail operator, 
as well as the right-of-way owner. As a result, freight railroad 
officials believe that passenger rail operators must contractually 
indemnify freight railroads against all liability and obtain insurance 
as a guarantee that payments will be made for any damages. The costs 
of providing this coverage could present a hurdle for new passenger 
rail operators. 

Potential operators were also concerned that Congress might be willing 
to raise the $200 million per accident federal liability limit which 
could make it even more expensive for new passenger rail operating 
firms to enter the marketplace. Because the application of this 
liability cap has been untested in court, many freight and passenger 
railroads are hesitant to rely upon this statute to cover the full 
extent of their potential liability. In addition, the federal 
liability limit does not cover third-party claims, such as from 
bystanders or property owners along the rights-of-way. As a result, 
liability agreements between freight railroads and commuter rail 
operators can range from $75 million to $500 million per accident. 
[Footnote 37] 

The proposed high speed rail corridors also present new liability 
issues that will increase costs as, according to one right-of-way 
owner, operator risk and damage will likely increase at higher speeds. 
In addition, some freight railroads are requesting that operator 
agreements include covering third parties (such as bystanders) which 
would also increase operator costs. For example, CSX Corporation and 
Norfolk Southern Corporation have requested liability insurance of 
$500 million per incident as an element of new access agreements with 
Virginia Railway Express commuter rail service in the Washington, 
D.C., area. Furthermore, changes in state liability law may influence 
negotiations between passenger rail operators and freight rail right- 
of-way owners. Commuter railroads face similar issues to intercity 
passenger rail operators because they run trains over the same rail 
network and have to negotiate with the same freight railroads. Options 
for facilitating negotiations on liability and indemnity provisions 
could include amending current law; exploring alternatives to 
traditional commercial insurance; providing commuter rail agencies 
with more leverage in negotiations; and separating passenger and 
freight traffic, either physically or by time of day. With regard to 
high speed rail, some stakeholders suggested a variety of solutions to 
this issue, including (1) publicly provided passenger rail insurance 
coverage, (2) government funding of passenger rail insurance to 
provide an additional layer of protection to railroad-purchased 
insurance, (3) pooled insurance across railroads,[Footnote 38] and (4) 
additional liability caps. 

Industry Stakeholders Noted the Importance of a Stable Public Funding 
Source for a Robust Intercity Passenger Rail Marketplace: 

Industry stakeholders agreed that the time frame for building more 
intercity passenger rail capacity in the United States depends upon 
the level of public funding committed. They further stated that a 
stable federal funding stream would encourage firms to enter the 
marketplace and to make investments. For example, passenger rail car 
manufacturers discussed the time commitment involved in designing, 
testing, and manufacturing passenger rail cars. As a result, they 
stated that they need to ensure that funding will be available 
throughout the entire process. While the Recovery Act funding waives 
the PRIIA nonfederal match requirements for capital investments, the 
fiscal year 2010 appropriation for intercity passenger rail projects 
requires at least 20 percent of the project's capital costs to come 
from nonfederal funding sources. If states or other grantees do not 
come up with their share, they will be unable to use the federal 
funds. Industry stakeholders stated that, in order to be successful, 
intercity passenger rail service would need stable state operating 
support in addition to capital funding provided by the federal 
government because all of the passenger rail systems we studied 
required some level of public operational and capital 
subsidy.[Footnote 39] One freight railroad official noted that, 
historically, state fluctuations in ridership and inaccurate ridership 
and revenue predictions have resulted in a financial shortfall that 
put private railroads at risk, leaving right-of-way owners concerned 
about the potential sunk costs of underutilized passenger rail 
equipment and higher speed rail infrastructure. However, during the 
current economic environment, it is uncertain the extent to which 
states will be able to provide funding support--capital or operating--
as simulations show near-term projected state and local deficits 
continuing for several years into the future.[Footnote 40] 

Industry stakeholders said that it is important to recognize that 
effective high speed rail operations will require a long-term 
investment of resources for ongoing maintenance and operations. 
Without long-term public funding commitments for capital investments 
and operations, projects may not be completed and the intercity 
passenger rail market may not stabilize. The current level of public 
funding for high speed rail is not as stable as industry stakeholders 
said it would need to be to create a robust industry. For example, 
after the initial one-time $8 billion infusion of Recovery Act 
funding, $2.5 billion was appropriated in fiscal year 2010 and, most 
recently, the administration's fiscal year 2011 budget proposed $1 
billion for high speed rail. These funds are derived from general 
funds rather than a dedicated funding source. Future federal 
appropriations for intercity passenger rail projects from general 
funds will have to compete annually with other transportation and 
nontransportation expenditures, such as national defense and health 
care. Industry stakeholders did not view this level of funding as 
enough to sustain a high speed passenger rail system. However, 
industry stakeholders commented that, although small, the Recovery Act 
funding for high speed rail has created an interest in the U.S. 
passenger rail market. 

Both current and former domestic high speed rail project sponsors have 
sought private financing but found it difficult to obtain private 
sector participation, given the significant financial risks high speed 
rail projects pose. Other countries have had success implementing 
public-private partnerships in which foreign governments' shared the 
financial risks of their expanding high speed rail systems with 
private partners.[Footnote 41] Some state officials said there was 
greater interest in entering public-private partnerships with regard 
to station development, train operation, and track maintenance before 
the economic downturn. In addition, a potential passenger rail 
operator said that the private sector could not provide enough money 
to meet the initial capital costs of starting intercity passenger rail 
service; the vast majority of funding would have to come from the 
public sources. 

FRA's New Responsibilities Have Held Back Developing a National Rail 
Plan, Strategic Vision, and Grant Oversight Plan: 

FRA's responsibilities and federal funding for intercity passenger 
rail investments significantly increased under PRIIA and the Recovery 
Act--posing risks for the use of federal intercity passenger rail 
funds. Among other things, recent legislation required FRA to draft a 
preliminary national rail plan and quickly develop a strategic vision 
for high speed rail while creating a new federal program to distribute 
and oversee a large increase in federal funds. A national rail plan, 
consistent with state rail plans, as required in federal law, that 
defines goals, roles for stakeholders, and objectives for federal 
investment in rail projects could help FRA develop an oversight 
program that would ensure accountability for these funds. Inclusion of 
sound grants management principles could also enhance FRA's grant 
oversight program to ensure grantees use federal funds effectively, 
measure and demonstrate success, and regularly assess and enhance 
program performance. 

Federal and State Capacity to Accommodate Dramatically Increased Funds 
and New Responsibilities Poses Risks for the Use of High Speed Rail 
Funds: 

The confluence of several factors resulting from the Recovery Act's 
funding for intercity passenger rail projects pose risks for the use 
of federal funds for investments in high speed rail projects. First, 
the act dramatically and quickly increased the amount of funds 
available for federal investment in high speed rail projects. The $8 
billion in funding along with the $2.5 billion fiscal year 2010 
appropriation for intercity passenger rail projects represent an 
increase of over 87 times the $120 million appropriated for intercity 
passenger rail projects in fiscal years 2008 and 2009 combined. 

Second, FRA officials have been simultaneously carrying out several 
new responsibilities, including: 

* developing a preliminary national rail plan and strategic vision for 
high speed rail service; 

* creating a rail development program to use Recovery Act funds; 

* soliciting and evaluating applications and making award decisions; 

* negotiating letters of intent and cooperative agreements with states 
awarded grants; 

* creating a grants oversight plan; 

* hiring new personnel for grants oversight; and: 

* determining awards for fiscal year 2010 high speed rail capital 
grants. 

As a result, FRA officials stated that they have been working to meet 
these new responsibilities and have had personnel from other 
Department of Transportation agencies, such as FTA and the Research 
and Innovative Technology Administration, help them review state 
applications for Recovery Act funds. 

Third, while federal law requires a project management oversight 
program be in place for one of the three federal intercity passenger 
rail grant programs, the other two federal rail grant programs do not 
have this requirement.[Footnote 42] However, according to FRA 
officials, its high speed rail program will outline how the agency 
will administer and oversee all federal high speed rail grants. FRA 
officials stated that they are drawing from a number of resources in 
developing a robust oversight and monitoring program for high speed 
rail projects, including existing agency procedures and new high speed 
intercity passenger rail program-specific protocols. For example, FRA 
is planning to use letters of intent with grantees which will define 
milestones and conditions that must be satisfied prior to the 
obligation and disbursement of federal funds. FRA is also planning to 
use cooperative agreements with its grantees which will allow for 
greater federal participation in risk management, oversight, and 
technical assistance than under standard grant agreements. 

In addition, FRA is planning to incorporate best practices and lessons 
learned from other major federal transportation investment programs in 
its oversight program, including those employed by FTA and the Federal 
Highway Administration. FRA is adopting several project oversight 
tools similar to those employed by FTA's New Starts Program--
specifically through the required development of Project Management 
Plans for major capital projects, and the use of project management 
oversight contractors to aid FRA staff in project oversight.[Footnote 
43] FRA officials stated that they are planning to hire consultants to 
provide on-site, day-to-day project management oversight and to ensure 
that the development and implementation of each project complies with 
all applicable statutes, regulations, and FRA guidance. FRA will 
establish a point of contact for each state for additional oversight 
and to provide coordination for any other federal funds for these 
projects. FRA will also adopt the Federal Highway Administration's 
Major Projects risk management approach, using three primary risk 
management tools: a project management plan, a financial plan, and a 
comprehensive risk-based cost-estimate review. FRA anticipates its 
internal grant management manual describing this program to be ready 
in June 2010. This program's development is critical as it is 
important to hold grantees accountable by verifying that they are 
making progress toward stated objectives and ensuring that grant funds 
are used efficiently to support the program's objectives. 

FRA officials stated that as FRA strives to meet these new 
responsibilities, it is increasing its staff dedicated to high speed 
passenger rail. Before the Recovery Act, FRA officials said that it 
had 23 staff dedicated to passenger rail activities. FRA officials 
stated that FRA received funding for 20 additional personnel, for its 
passenger rail program in fiscal year 2010. FRA will need to dedicate 
resources over the next months and years to hire and train these 
additional personnel as well as find and acclimate the project 
management consultant firms it plans to retain to oversee the day-to- 
day project management for each state grantee or large project. 

Other federal agencies have faced a similar increase in new 
responsibilities in critical situations or in quickly handling 
unprecedented amounts of federal funds. For example, as the federal 
Office of Financial Stability's assumed responsibility for the $700 
billion Troubled Asset Relief Program, it faced a key challenge of 
developing comprehensive oversight procedures as it had to quickly 
react to financial market events, increase staff at the newly created 
agency, and attempt to develop and communicate a strategy for the 
federal role in the financial marketplace while simultaneously 
developing and implementing a program to carry out the strategy. 
[Footnote 44] Similar issues existed at the Department of Commerce and 
the Department of Agriculture as they hired contractors to handle 
their multiple new award and oversight responsibilities that 
accompanied a Recovery Act increase in funding of 97 times the 
previous annual average amount for broadband infrastructure grants. 
[Footnote 45] FRA's efforts to meet these responsibilities could also 
be complicated in the near term. Although funds available for 
oversight of Recovery Act projects expire in September 2014, FRA funds 
for projects funded with fiscal year 2010 appropriations are available 
until expended. 

Finally, according to FRA officials, no state or federal agency 
currently has the management capability to oversee such a large 
passenger rail program so recently established. They noted that while 
FRA is building its own capacity to initiate and sustain this program, 
some state departments of transportation are even further behind in 
developing their capacity to apply for grants and manage passenger 
rail projects. While they found that some states are more advanced in 
their planning for passenger rail projects than others, some have no 
state resources dedicated to rail and many do not have a state rail 
plan to guide their efforts. 

Development of a National Rail Plan Consistent with State Rail Plans 
Could Increase the Accountability and Transparency of Federal High 
Speed Rail Funds: 

FRA's Preliminary National Rail Plan recognizes the importance of 
these state rail plans and anticipates coordinating its National Rail 
Plan with them into an "efficient national system…meeting both 
regional and national goals." However, FRA officials stated that as 
the agency is developing its capacity and processes to manage this new 
intercity passenger rail program, some states are further behind in 
developing their capacity and processes to apply for passenger rail 
funds. For example, a California department of transportation official 
stated that it has been planning for and running its intercity 
passenger rail service since 1976. In contrast, Ohio commissioned 
Amtrak to conduct a feasibility study for its "3-C" service in late 
2008 and received it in late 2009. As a result, Congress specifically 
exempted projects funded with Recovery Act funds and fiscal year 2010 
appropriations from this requirement to speed their distribution and 
use. In addition, this exemption allowed those states without state 
rail plans to apply for and receive federal funding awards without 
establishing statewide strategies, priorities, capital investments, or 
possible public benefits for rail service. 

Due to the pace and scale of the Recovery Act grants, FRA officials 
have not been able to develop a detailed strategic plan for how high 
speed rail fits into the national transportation system or the federal 
role in high speed intercity passenger rail, as required in the act. 
FRA has published a strategic vision and a preliminary national rail 
plan as it concentrated on preparing for and then awarding the 
Recovery Act funds. The strategic vision outlined FRA's proposed 
strategy to implement the act's funding for high speed rail corridors; 
however, it did not define the goals, roles of stakeholders, or 
objectives for federal involvement in high speed intercity passenger 
rail. The Preliminary National Rail Plan, while offering broad 
objectives for high speed intercity passenger rail, did not offer 
specific recommendations for future action and is designed to serve as 
a "springboard for further discussion" with states and freight 
railroads. 

We have reported that the United States is not well positioned to 
reform its intercity passenger rail system as the goals and expected 
outcomes of U.S. rail policy are ambiguous, stakeholder roles are 
unclear, and funding is limited.[Footnote 46] A national rail plan 
could define several important aspects of such a rail policy by 
describing: 

* the vision and goals for U.S. high speed rail; 

* how passenger rail might fit into the national transportation 
system; and: 

* the appropriate federal role in achieving the established goals. 
[Footnote 47] 

As a result, we recommended that the Department of Transportation 
prepare a strategic vision for high speed rail, particularly in 
relation to the role that high speed rail can play in the national 
transportation system, that clearly identifies potential objectives 
and goals for high speed rail systems and the roles that the federal 
government and others can play in achieving each objective and goal. 
With the federal interest clearly defined, policymakers can clarify 
the goals for federal involvement and the roles of all stakeholders 
toward those goals.[Footnote 48] FRA officials stated that the 
National Rail Plan to be released in September 2010 will attempt to 
better define the role of passenger and freight rail in the national 
transportation system, as well as appropriate roles for rail 
stakeholders. 

Sound Grants Management Practices Could Also Help FRA in Developing 
Its Oversight Efforts: 

A well-designed and implemented grant oversight program is critical to 
ensuring effective use of federal grant funds. In addition to meeting 
agency and congressional goals and providing public benefits, 
effective use of federal funds is important in light of the federal 
government's long-term fiscal imbalance. Simply monitoring and 
reporting performance may encourage accountability and grant 
guidelines can establish uniform outcome measures for evaluating 
grantees' performance toward specific goals.[Footnote 49] Incentives 
or penalties in the grant agreements can also create clear links 
between performance and funding which help hold grantees accountable 
for achieving desired results. 

Some grants management practices identified by the Comptroller 
General's Domestic Working Group could help FRA in developing these 
aspects of its grant management program.[Footnote 50] The Domestic 
Working Group identified several promising practices which could 
improve grants management including: managing grantee performance, 
using results of the grant program, and assessing and developing 
performance measures for grantees.[Footnote 51] These specific 
principles will become important as FRA transitions from awarding 
grants to overseeing their performance. FRA is planning to address 
these principles in its grant oversight approach. (See table 4.) 

Table 4: FRA's Oversight Plan in Relation to Selected Grant Oversight 
Principles: 

Principle: Managing grantee performance; 
GAO Grants Working Group description: Agencies need to ensure grants 
are used for the intended purposes by: 
* monitoring the grants' financial status; 
* monitoring performance of grantees and subgrantees; and; 
* using audits to gain information about grantees; 
FRA's planned oversight approach: FRA is planning to incorporate 
programmatic, financial, and administrative reviews of grantee reports 
and documentation, as well as perform site visits. Audits will be used 
to identify project-specific corrective actions. 

Principle: Assessing and using results of the grant program; 
GAO Grants Working Group description: Agencies should be able to: 
* demonstrate grants' successes by surveying grantees or inspecting 
projects; and; 
* identify ways to improve program performance using outside experts 
to assess and evaluate programs; 
FRA's planned oversight approach: FRA is planning to aggregate its 
project reviews and site visits to identify trends and to preempt 
potential issues and concerns with the program. 

Principle: Measuring performance; 
GAO Grants Working Group description: Agencies should develop outcome-
related performance measures with its grantees; 
FRA's planned oversight approach: FRA officials stated that they are 
developing tools to measure these outcomes. FRA officials stated that 
they will require time and focused resources to fully develop accurate 
and useful metrics to measure public benefits. 

Source: Guide to Opportunities for Improving Grant Accountability and 
GAO analysis of FRA information. 

[End of table] 

As FRA is working on agreements with states to monitor their 
performance on Recovery Act projects, FRA officials have stated that 
their grant oversight program will incorporate reviews and site visits 
to measure grantees' performance; the development of a tool to track 
grantees' performance; and processes to use the results of the 
reviews, site visits, and tracking tool to improve the overall 
program. Although some performance measures, such as ridership, 
revenue, and revenue-to-cost metrics exist, FRA officials told us that 
they are developing more robust metrics for accurately measuring the 
public benefits of passenger rail investments. FRA's high speed rail 
interim program guidance includes such potential benefits as 
congestion reduction, environmental quality, safety, energy 
efficiency, and the creation of livable communities. We have 
recognized that the valuation of public benefits is difficult and have 
recommended that the Department of Transportation develop specific 
policies that include performance measures of public benefits in its 
intercity passenger rail grant award decisions.[Footnote 52] In 
addition, assessing the grant program and incorporating the results of 
that assessment could be critical as FRA gains experience with this 
new program and as future federal funds are appropriated for high 
speed intercity passenger rail projects. 

Concluding Observations: 

The federal government has embarked on a new role in transportation by 
designating an unprecedented amount of federal funds for high speed 
passenger rail. Federal, state, and local officials have welcomed the 
investment and have cited the possible public benefits of passenger 
rail service for the nation, regions, states, and communities. 
However, this new opportunity will come with many years of planning, 
testing, and construction, and brings new concerns. While the rail 
industry and some states are ready to take advantage of this 
opportunity, the federal government and many states do not have any 
experience in contracting for intercity passenger rail service. States 
that have established intercity passenger rail service have taken 
years to build public support, secure funding, obtain equipment, and 
manage their services. More passenger rail service, especially 
services at higher and high speeds, will require new safety rules, 
constant public capital investment and operating subsidies, and 
balance with freight rail service and the rest of the national 
transportation system--and currently only some of these elements are 
in place. 

While the recent federal funds may serve as a catalyst for many 
projects and have generated high public expectations, the planning 
necessary to meet the many concerns outlined above has not yet 
occurred. In particular, some states do not have a state rail plan 
that identifies the states' strategies, priorities, and possible 
public benefits of public investment in rail transportation. While it 
is understandable that Congress exempted projects funded by the 
Recovery Act from this requirement to stimulate the economy, it 
remains nonetheless important to know how states plan to use federal 
funds for passenger rail projects over the long term. PRIIA 
established that states should plan how they use federal passenger 
rail funds and we believe this kind of planning can provide the basis 
for sound investment of federal funds. Additionally, on a national 
level, FRA's definition of federal role, goals, and objectives, in 
conjunction with a robust grant oversight program, are critical to 
making sound federal investments. These elements will become even more 
important as more federal funds are appropriated and distributed and 
as states and the federal government gain experience in investing and 
managing intercity passenger rail service. We are not recommending 
that FRA include these elements in its next version of its National 
Rail Plan at this time, as the agency appears to be on a path to doing 
so. We will continue to monitor FRA's efforts in this regard. 

Agency Comments: 

We provided a draft of this report to the Department of Transportation 
for review and comment. The department did not express an overall view 
on the draft report. It did provide technical comments and 
clarifications, which we incorporated. 

We are sending copies of this report to congressional subcommittees 
with responsibilities for surface transportation issues; the Director, 
Office of Management and Budget; the Secretary of Transportation; and 
the Administrator of the Federal Railroad Administration. In addition, 
this report will be available at no charge on GAO's Web site at 
[hyperlink, http://www.gao.gov]. 

If you or your staff have any questions regarding this report, please 
contact me at (202) 512-2834 or flemings@gao.gov. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. GAO staff who made key contributions 
to this report are Heather Chartier, Gregory Hanna, James 
Ratzenberger, and Caitlin Tobin. 

Signed by: 

Susan A. Fleming: 
Director, Physical Infrastructure Issues: 

[End of section] 

Appendix I: Scope and Methodology: 

To report on how states successfully initiated or improved their 
intercity passenger rail services over the past 15 years, we reviewed 
documentation about states that provided operational support to 
intercity passenger rail services; interviewed state, association, and 
industry officials; and identified parallels between developing 
conventional passenger rail and higher and high speed passenger rail 
services. (For a list of the organizations interviewed, see table 5 at 
the end of this appendix.) We identified states that initiated or 
improved intercity passenger rail services over the last 15 years by 
reviewing reports and background information about recent intercity 
passenger rail services, as well as by conducting interviews with the 
Federal Railroad Administration (FRA), National Railroad Passenger 
Corporation (Amtrak), and association officials knowledgeable of state-
supported passenger rail services. We conducted semistructured 
interviews with state rail officials from 8 states, including 4 states 
that initiated new services and 4 states that improved existing 
services, including 1 state that improved an existing service to 
higher speeds. We also reviewed documentation provided by states about 
these passenger rail systems and conducted semistructured interviews 
with industry officials about these state-supported services. 

To gain some insight into the types of infrastructure improvements 
states would need to invest in to increase speeds and improve the 
performance of intercity passenger rail service, we visited railroad 
projects in Indiana, projects on Amtrak-owned infrastructure in 
Michigan which will soon allow a top speed for passenger trains of 110 
miles per hour, and projects on various freight railroad rights-of-way 
in Illinois designed to reduce rail congestion and increase train 
speeds, respectively. Additionally, we reviewed information about 
states and projects awarded Recovery Act funding and reviewed our 
previous work about intercity passenger rail and high speed rail to 
determine how state experiences developing intercity passenger rail 
can be applied to developing conventional intercity passenger rail and 
high speed rail services. 

We met with industry stakeholders to obtain their views regarding how 
the rail industry plans to accommodate the increased investment in 
passenger rail service. To identify these stakeholders, we met with 
railroad associations, attended rail conferences, and drew upon 
internal and external subject matter experts to identify companies in 
each area. We conducted semistructured interviews with potential 
operators, right-of-way owners, passenger rail car manufacturers, and 
general rail industry contractors to obtain their views on the 
capacity of the rail industry to accommodate the increased public 
investment and to identify issues related to this increased 
investment. We reviewed and analyzed federal laws and regulations such 
as the Buy America provision in the Recovery Act, and FRA's Passenger 
Rail Safety Study, to describe the rules that govern the industry. We 
reviewed information from our reports related to stakeholder-
identified rail industry challenges to see if these challenges have 
changed with the onset of the Recovery Act funding. 

We reviewed federal laws including the Recovery Act and the Passenger 
Rail Investment and Improvement Act of 2008 to describe FRA's new 
responsibilities regarding passenger rail investment. To provide grant 
oversight principles that could be used by the FRA in its grants 
management program, we identified important grant oversight elements 
from the Comptroller General's Domestic Working Group report on grants 
management and from our reports evaluating various federal grant 
programs. We compared them to statements made by FRA officials 
regarding their oversight program. We analyzed FRA's strategic vision 
for high speed rail, its preliminary national rail plan, and its 
interim guidance for its high speed passenger rail program for 
information on the stated federal role in intercity passenger rail and 
how it fits within the national transportation system. We also 
interviewed FRA officials responsible for passenger rail development 
to determine how FRA is planning to oversee the use of Recovery Act 
and other federal funds for intercity passenger rail investments. 

We focused on the state, industry, and federal efforts to fund capital 
investments in state-supported intercity passenger rail corridors and 
projects as these projects were the types of projects eligible for 
Recovery Act and subsequent federal funding. 

Table 5: Organizations Contacted: 

Federal agency: 
Department of Transportation, Federal Railroad Administration. 

State departments of transportation: 
California; 
Illinois; 
Maine; 
North Carolina; 
Pennsylvania; 
Vermont; 
Virginia; 
Washington. 

Passenger rail operators: 
Amtrak; 
Herzog; 
JR Central (Central Japan Railway Company); 
SNCF; 
Veolia. 

Freight railroads: 
BNSF Railway Company; 
Canadian National Railway Company; 
Canadian Pacific Railway; 
CSX Transportation Incorporated; 
Union Pacific Railroad. 

Rail car manufacturers and rail industry firms: 
Alstom Transport; 
Bombardie; 
Kawasaki Rail Car; 
Parsons Brinckerhoff; 
Talgo; 
URS Corporation. 

Associations: 
American Association of State Highway and Transportation Officials; 
Association of American Railroads; 
Coalition of Northeastern Governors; 
States for Passenger Rail Coalition. 

Source: GAO. 

[End of table] 

[End of section] 

Footnotes: 

[1] For the purpose of our work, we considered the recent past as the 
15-year period between 1995 and 2009 so that we could concentrate on 
those states that established intercity passenger rail service during 
and after the most recent changes in Amtrak and freight railroad 
policies toward expanding intercity passenger rail. 

[2] Domestic Working Group, Grant Accountability Group, Guide to 
Opportunities for Improving Grant Accountability (Washington, D.C., 
October 2005). This group consisted of 19 federal, state, and local 
audit organizations to identify current and emerging challenges of 
mutual interest and explore opportunities for greater collaboration 
within the intergovernmental audit community. 

[3] These three programs are Section 301-Capital Assistance for 
Intercity Passenger Rail Service Grants, Section 302-Congestion 
Grants, and Section 501-High Speed Rail Corridor Program. State rail 
plans are required for Sections 301 and 501, but not mentioned in 
Section 302. 

[4] By comparison, the fiscal year 2008 and fiscal year 2009 
appropriations for the department included $30 million and $90 million 
respectively for intercity passenger rail grants to states. 

[5] Department of Transportation, Vision for High-Speed Rail in 
America (Washington, D.C., April 2009). 

[6] This proposal also includes $4 billion for a national 
infrastructure fund that could also be used for intercity passenger 
rail projects. 

[7] As per 49 U.S.C. 24102(5)(C) and (D), Amtrak defines short 
distance routes as being 750 miles or less in length and routes 750 
miles or more to be long distance. Commuter rail service is generally 
defined as regional service between a central city and its suburbs. 

[8] Amtrak owns tracks connected to the corridor between Philadelphia 
and Harrisburg, Pennsylvania, and between New Haven, Connecticut, and 
Springfield, Massachusetts. 

[9] In addition, several transit authorities have purchased rights-of- 
way on which to operate their commuter rail service. For more 
information, see GAO, Commuter Rail: Many Factors Influence Liability 
and Indemnity Provisions and Options Exist to Facilitate Negotiations, 
[hyperlink, http://www.gao.gov/products/GAO-09-282] (Washington, D.C.: 
Feb. 24, 2009). 

[10] However, Amtrak's fastest scheduled Acela Express service takes 2 
hours and 42 minutes to go 225 miles between Washington, D.C., and New 
York City for an average of 84 miles per hour. 

[11] 74 Fed. Reg. 29900, June 23, 2009. 

[12] Department of Transportation, Vision for High-Speed Rail in 
America (Washington, D.C., April 2009). 

[13] FRA, Preliminary National Rail Plan (Washington, D.C., October 
2009). 

[14] For ease of presentation, we combined the individual Recovery Act 
awards by state. In addition to the Recovery Act awards, another 20 
projects in 15 states and the District of Columbia were also awarded 
$27 million in fiscal year 2008 and 2009 funds for intercity passenger 
rail assistance grants in January 2010. 

[15] We considered conventional passenger rail service to include 
trains traveling up to 79 miles per hour; higher speed passenger rail 
service to include trains traveling up to 150 miles per hour; and high 
speed passenger rail service to include trains traveling 150 miles per 
hour or more. In PRIIA, Congress defined high speed rail service as 
intercity passenger rail service that is reasonably expected to reach 
speeds of at least 110 miles per hour. We are making this additional 
differentiation to show the different levels of planning, investment, 
and safety considerations required to achieve these top speeds. 

[16] GAO, High Speed Passenger Rail: Future Development Will Depend on 
Addressing Financial and Other Challenges and Establishing a Clear 
Federal Role, [hyperlink, http://www.gao.gov/products/GAO-09-317] 
(Washington, D.C.: Mar. 19, 2009). 

[17] Flexible funds are federal funds that, by statute, may be used 
for transit or highway purposes. They allow a local area to choose to 
use certain federal surface transportation funds--including from the 
Surface Transportation Program, the Congestion Mitigation and Air 
Quality Improvement Program, and through Urban Formula funding--based 
on local planning priorities, not on a restrictive definition of 
program eligibility. The Federal Highway Administration and the 
Federal Transit Administration (FTA) administer these programs. 

[18] The Transportation Enhancement Program, administered by the 
Federal Highway Administration and first authorized by the Intermodal 
Surface Transportation Efficiency Act of 1991, provides funding 
opportunities to states to help expand transportation choices and 
enhance the transportation experience through 12 eligible activities, 
including the rehabilitation and operation of historic transportation 
buildings, structures, or facilities. 

[19] The Congestion Mitigation and Air Quality Improvement Program is 
jointly administered by the Federal Highway Administration and FTA. 
The program provides funding to state departments of transportation, 
metropolitan planning organizations, and transit agencies to invest in 
projects that reduce regulated air pollutants from transportation- 
related sources. 

[20] These cost estimates can include several different types of 
investments, such as constructing stations and platforms, acquiring 
locomotives and passenger rail cars, improving existing railroad 
rights-of-way, and building new railroad rights-of-way. The types and 
mixtures of investments may vary across corridors and some investments 
may be less variable than others due to the length of the corridor. 
Nonetheless, expressing cost estimates using route miles as a common 
denominator helps show how costs for higher and high speed service are 
significantly greater than for conventional service. 

[21] Ohio Rail Development Commission, High Speed Intercity Passenger 
Rail Track 2 Application: OH-3C-QuickStart (October 2009). 

[22] Pennsylvania Department of Transportation, High Speed Intercity 
Passenger Rail Track 2 Application: PA - Keystone Corridor - High 
Speed (October 2009), and Michigan Department of Transportation, High 
Speed Intercity Passenger Rail Track 2 Application: MI-CHI Hub, CHI-
DET/PNT (October 2009). 

[23] New York State Department of Transportation, High Speed Intercity 
Passenger Rail Track 2 Application: NY-EC2-Empire Corridor-NYC-NFL 
(October 2009). 

[24] North Carolina Department of Transportation, High Speed Intercity 
Passenger Rail Track 2 Application: NCT2.4 - SEHSR - Charlotte to DC/ 
NEC (October 2009). 

[25] Florida Department of Transportation, High Speed Intercity 
Passenger Rail Track 2 Application: Florida High Speed Rail Express: 
Tampa-Orlando (October 2009). 

[26] California High Speed Rail Authority, Report to the Legislature 
(December 2009). 

[27] Dedicated rail right-of-way refers to railroad track reserved for 
the exclusive use of high speed rail passenger trains, whereas shared 
rail right-of-way refers to track used by both passenger and freight 
trains. 

[28] Conventional passenger rail trains and higher speed passenger 
rail trains are usually powered by diesel locomotives and operate over 
rail right-of-way shared with freight trains. Of the states we 
interviewed, only Pennsylvania improved service on an electrified, 
rail right-of-way in the recent past. 

[29] [hyperlink, http://www.gao.gov/products/GAO-09-317]. 

[30] However, one passenger rail car manufacturer stated that there 
are many factors that affect the time it takes to deliver rail cars, 
such as, the type of equipment, whether there are new design features 
that require extensive testing, and requirements in the customer's 
technical specifications. 

[31] Ohio's "3-C" corridor is approximately 256 miles long and will 
connect Cleveland, Columbus, and Cincinnati. 

[32] GAO, Intercity Passenger Rail: National Policy and Strategies 
Needed to Maximize Public Benefits from Federal Expenditures, 
[hyperlink, http://www.gao.gov/products/GAO-07-15] (Washington, D.C.: 
Nov. 13, 2006). 

[33] For these reasons, Amtrak's access costs cannot be directly 
compared with any other potential intercity passenger rail operator. 
However, commuter rail costs are the same as to as much as 10 times as 
much as Amtrak pays for rail infrastructure access. 

[34] [hyperlink, http://www.gao.gov/products/GAO-09-317]. 

[35] The Buy America provisions set forth in 49 U.S.C. 24405(a) 
provides that the Secretary of Transportation may obligate Recovery 
Act funds for a High Speed Rail/Intercity Passenger Rail or congestion 
project only if the steel, iron, and manufactured goods used in the 
project are produced in the United States. The Secretary has the 
authority to waive this requirement under certain circumstances and 
the requirement is only applicable to projects which exceed $100,000. 

[36] Federal law limits overall damages from passenger claims to $200 
million and explicitly authorized passenger rail providers to enter 
into indemnification agreements. For more information, see [hyperlink, 
http://www.gao.gov/products/GAO-09-282]. 

[37] [hyperlink, http://www.gao.gov/products/GAO-09-282]. 

[38] A liability insurance pool can be described as a group of 
organizations with similar characteristics, such as a group of 
commuter rail agencies that pool their assets to obtain a single 
commercial insurance policy, rather than obtaining individual 
commercial insurance policies. 

[39] In 2006, we studied the passenger rail systems of Canada, France, 
Germany, Japan, and the United Kingdom. We selected these systems as 
they had reformed to try to become more cost-effective and value-added 
for the level of subsidies spent. For more information, see 
[hyperlink, http://www.gao.gov/products/GAO-07-15]. 

[40] GAO, State and Local Governments' Fiscal Outlook: March 2010 
Update, [hyperlink, http://www.gao.gov/products/GAO-10-358] 
(Washington, D.C.: Mar. 2, 2010). 

[41] [hyperlink, http://www.gao.gov/products/GAO-09-317]. 

[42] One of the federal grant programs established in PRIIA that will 
be used to distribute Recovery Act high speed rail funds has a project 
management oversight requirement (Section 301-Capital Assistance for 
Intercity Passenger Rail Service Grants); whereas the other two 
programs do not (Section 302-Congestion Grants and Section 501-High 
Speed Rail Corridor Program). However, FRA is requiring all 
construction projects funded under the Recovery Act or with future 
federal passenger rail funds to develop an FRA-approved project 
management plan prior to awarding the funds. 

[43] Through its New Starts program, FTA identifies and recommends, 
based on financial and programmatic criteria, new fixed-guideway 
transit projects, including heavy, light, and commuter rail projects, 
for federal capital funding. 

[44] GAO, Troubled Asset Relief Program: Status of Efforts to Address 
Transparency and Accountability Issues, [hyperlink, 
http://www.gao.gov/products/GAO-09-296] (Washington, D.C.: Jan. 30, 
2009). 

[45] GAO, Recovery Act: Agencies Are Addressing Broadband Program 
Challenges, but Actions Are Needed to Improve Implementation, 
[hyperlink, http://www.gao.gov/products/GAO-10-80] (Washington, D.C.: 
Nov. 16, 2009). 

[46] GAO, Intercity Passenger Rail: National Policy and Strategies 
Needed to Maximize Public Benefits from Federal Expenditures, 
[hyperlink, http://www.gao.gov/products/GAO-07-15] (Washington, D.C.: 
Nov. 13, 2006). 

[47] [hyperlink, http://www.gao.gov/products/GAO-09-317]. 

[48] [hyperlink, http://www.gao.gov/products/GAO-09-317]. The 
Department of Transportation did not take a position on this 
recommendation and stated that the Recovery Act accelerated its work 
on high speed intercity passenger rail. At the time, the department 
indicated that its upcoming strategic plan may include its vision on 
implementing high speed intercity passenger rail services. 

[49] GAO, Grants Management: Enhancing Performance Accountability 
Provisions Could Lead to Better Results, [hyperlink, 
http://www.gao.gov/products/GAO-06-1046] (Washington, D.C.: Sept. 29, 
2006). 

[50] We have also reported on oversight of several federal grant 
programs such as: Department of Justice juvenile justice grants, GAO, 
Juvenile Justice: A Time Frame for Enhancing Grant Monitoring 
Documentation and Verification of Data Quality Would Help Improve 
Accountability and Resource Allocation Decisions, [hyperlink, 
http://www.gao.gov/products/GAO-09-850R] (Washington, D.C.: Sept. 22, 
2009); Transportation Security Agency and Federal Emergency Management 
Agency first responder grants, GAO, Transit Security Grant Program: 
DHS Allocates Grants Based on Risk, but Its Risk Methodology, 
Management Controls, and Grant Oversight Can Be Strengthened, 
[hyperlink, http://www.gao.gov/products/GAO-09-491] (Washington, D.C.: 
June 8, 2009); overall grant performance management, GAO, Grants 
Management: Enhancing Performance Accountability Provisions Could Lead 
to Better Results, [hyperlink, 
http://www.gao.gov/products/GAO-06-1046] (Washington, D.C.: Sept. 29, 
2006); and Environmental Protection Agency grant oversight, GAO, 
Grants Management: EPA Needs to Strengthen Efforts to Address 
Persistent Challenges, [hyperlink, 
http://www.gao.gov/products/GAO-03-846] (Washington, D.C.: Aug. 29, 
2003). 

[51] Domestic Working Group, Grant Accountability Project, Guide to 
Opportunities for Improving Grant Accountability, October 2005. This 
guide states that it is designed to provide government executives at 
the federal, state, and local levels with ideas for better managing 
grants. The guide focuses on specific steps taken by various agencies. 
The intent is to share useful and innovative approaches taken, so that 
others can consider using them. 

[52] [hyperlink, http://www.gao.gov/products/GAO-09-317]. The 
Department of Transportation did not take a position on this 
recommendation and stated that the Recovery Act accelerated its work 
on high speed intercity passenger rail. At the time, the department 
indicated that its upcoming strategic plan may include its criteria 
for selecting projects and an evaluation process that will be used to 
measure effectiveness. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: