This is the accessible text file for GAO report number GAO-09-50 
entitled 'Defense Acquisitions: Timely and Accurate Estimates of Costs 
and Requirements Are Needed to Define Optimal Future Strategic Airlift 
Mix' which was released on November 21, 2008.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Subcommittee on Air and Land Forces, Committee on Armed 
Services, House of Representatives: 

United States Government Accountability Office: 
GAO: 

November 2008: 

Defense Acquisitions: 

Timely and Accurate Estimates of Costs and Requirements Are Needed to 
Define Optimal Future Strategic Airlift Mix: 

GAO-09-50: 

GAO Highlights: 

Highlights of GAO-09-50, a report to the Subcommittee on Air and Land 
Forces, Committee on Armed Services, House of Representatives. 

Why GAO Did This Study: 

The Department of Defense’s (DOD) C-5 Galaxy and C-17 Globemaster III 
aircraft play key roles in transporting weapons and other cargo. Since 
September 2001, these aircraft have delivered over 2.4 million tons of 
cargo to staging and operating bases in Iraq and Afghanistan. Yet 
determining the number and mix to meet current and future airlift 
requirements has become increasingly challenging given distinct 
differences between the two aircraft. While the C-5 can carry more 
cargo, the newer C-17 is more flexible since it can deliver to forward-
deployed bases and has a higher mission capable rate. 

GAO was asked to identify the impact C-5 modernization cost increases 
have had on the mix of aircraft; assess the current C-5 modernization 
cost estimate; and identify C-17 production plans and issues related to 
production line shutdown. To conduct its work, GAO reviewed options DOD 
considered to meet its current and future strategic airlift 
requirements, and evaluated C-5 modernization and C-17 production line 
shut down cost estimates. 

What GAO Found: 

The Air Force has cut the number of C-5s it plans to fully modernize by 
more than half because of substantial cost increases in the C-5 
Reliability Enhancement and Reengining Program (RERP) and plans to 
acquire more C-17s, with additional congressional funding. Currently, 
the Air Force plans to provide avionics upgrades to all 111 C-5s, limit 
RERP to 52 C-5s, and acquire 205 C-17s. However, this mix may change 
again, based in part on the results of a new mobility capabilities 
study, the findings of which DOD plans to release in May 2009. While 
the new study is expected to consider transport needs for the future 
force, DOD has not identified specific metrics it will use to make 
strategic airlift decisions—a concern GAO raised about DOD’s previous 
mobility capabilities study and one DOD agreed to address in future 
studies. 

The Air Force currently estimates it will spend $9.1 billion on 
upgrading the C-5s. However, this estimate may be understated because 
DOD did not apply risk or uncertainty analyses to its RERP major cost 
drivers. Moreover, the current RERP is underfunded by almost $300 
million and may be unachievable if the engine production schedule is 
not met. At the same time, the Air Force has not priced or budgeted for 
a new upgrade program it plans to begin in fiscal year 2010 to address 
certain modernization deficiencies and to add new capabilities. Some 
future costs, however, may be avoided should the Air Force justify 
retirement of some older C-5s and forego planned modifications. 

Careful planning is needed to ensure C-17 production is not ended 
prematurely and later restarted at substantial cost. Current production 
plans call for shutting down the C-17 production line in September 
2010. However, results from the new mobility capabilities studies and 
potential C-5 retirements could lead to decisions to extend C-17 
production beyond the 205 now authorized. Both the manufacturer and Air 
Force agree that shutting down and restarting production would not be 
feasible or cost effective due to the costs to reinstate a capable 
workforce, reinstall tooling, and reestablish the supplier base. At 
some point, the C-17 production line will shut down, and DOD will have 
to pay substantial costs that have not yet been budgeted. The 
manufacturer and Air Force shutdown estimates differ significantly 
—about $1 billion and $465 million, respectively—in large part because 
the manufacturer’s estimate included assumptions about demolishing 
facilities and environmental remediation, while the Air Force’s did 
not. 

Comparison of C-5 and C-17 Capabilities and Characteristics: 

Loads: 
C-5: 270,000 pounds of cargo; 
C-17: 170,900 pounds of cargo. 

Range (unrefueled): 
C-5: 6,320 miles; 
C-17: 2,700 miles. 
Minimum runway length: 
C-5: 6,000 feet; 
C-17: 3,500 feet. 
Crew: 
C-5: 7; 
C-17: 3. 

Mission capable rate: 
C-5: 53 percent; 
C-17: 86 percent. 
Cost per flying hour: 
C-5: $23,100; 
C-17: $11,300. 

[End of table] 

What GAO Recommends: 

GAO is making recommendations to help DOD identify the appropriate 
strategic airlift mix and improve cost estimates for the C-5 program 
and C-17 production shutdown. DOD concurred with one recommendation and 
partially concurred with another, but believes updated C-5 cost 
estimates are not warranted. GAO believes this recommendation is still 
valid. 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.gao.gov/products/GAO-09-50]. For more 
information, contact Michael J. Sullivan at (202) 512-4841 or 
sullivanm@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

Mix of C-5s and C-17s Needed to Meet DOD's Strategic Airlift 
Requirement Continues to Evolve: 

C-5 Modernization Costs Have Not Been Fully Identified: 

The Air Force Must Make a Decision Soon Regarding C-17 Acquisition and 
Eventual Shutdown of the Production Line: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: Comments from the Department of Defense: 

Tables: 

Table 1: C-5 RERP Quantity and Cost Changes: 

Table 2: Estimated Million Ton-Mile per Day Capability Comparison: 

Table 3: Comparison of a Modernized C-5 and C-17 Equivalent Airlift 
Capabilities: 

Table 4: Comparison of Boeing and Air Force Cost-estimating Assumptions 
for C-17 Production Line Shutdown and Restart: 

Table 5: Comparison of Cost and Assumptions Included in C-17 Production 
Line Shutdown Cost Estimates: 

Figures: 

Figure 1: Comparison of C-5 and C-17 Capabilities and Characteristics: 

Figure 2: Annual Funding Requirements for the C-5 RERP: 

Abbreviations: 

AMP: Avionics Modernization Program: 

CAIG: Cost Analysis Improvement Group: 

DOD: Department of Defense: 

RERP: Reliability Enhancement and Reengining Program: 

[End of figure] 

United States Government Accountability Office:
Washington, DC 20548: 

November 21, 2008: 

The Honorable Neil Abercrombie: 
Chairman: 
The Honorable Jim Saxon: 
Ranking Member: 
Subcommittee on Air and Land Forces: 
Committee on Armed Services: 
House of Representatives: 

Strategic airlift provides the capability to rapidly deploy, supply, 
and sustain U.S. combat forces worldwide. The Air Force's C-5 Galaxy 
and C-17 Globemaster III aircraft, supported by aerial refueling 
tankers and the civil reserve air fleet, provide the "air bridge" to 
transport weapon systems, equipment, cargo, and personnel from the 
United States and staging bases to overseas locations in support of 
military and humanitarian operations. Demands on strategic airlift have 
increased since the end of the Cold War and subsequent closure of about 
two-thirds of U.S. overseas bases, requiring more frequent deployment 
of U.S. forces over greater distances. The two airlifters continue to 
play a key role in supporting combat operations in the Middle East, 
collectively delivering more than 2.4 million tons of equipment and 
cargo to Iraq and Afghanistan in over 330,000 airlift sorties. 

While there is a broad consensus for sustaining a robust and effective 
strategic airlift capability, determining current and future airlift 
requirements--and the specific numbers and optimal mix of aircraft 
needed to meet those requirements--has become increasingly challenging 
given affordability concerns and changes in threats, missions, and 
future force structure. The 2006 Quadrennial Defense Report identified 
plans to acquire and modernize a fleet of 292 strategic airlifters, 
comprised of 180 C-17s and 112 modernized and reliability enhanced C- 
5s. Subsequently, Congress provided additional funding that the Air 
Force plans to use to procure 25 more C-17s for a future force of 205, 
and 1 C-5 crashed, leaving 111 aircraft.[Footnote 1] However, the 
Department of Defense (DOD) is currently rethinking its strategic 
airlift plans, due in part to significant cost growth for modernizing C-
5 aircraft and a subsequent scaling back of modernization efforts. New 
mobility requirements studies now under way and pending decisions on C-
17 acquisitions will further influence the department's airlift 
investment strategy. In this context, you asked us to (1) identify the 
impact C-5 modernization cost increases have had on the mix of aircraft 
DOD needs to meet its strategic airlift requirement, (2) assess the 
current C-5 modernization cost estimate, and (3) identify C-17 
production plans and issues related to production line shutdown. 

In conducting our work, we collected information on options DOD 
considered to meet its strategic airlift requirement and on DOD's 
efforts to determine its future airlift needs. We evaluated DOD and 
contractor cost estimates for the C-5 Avionics Modernization Program 
(AMP) and the Reliability Enhancement and Reengining Program (RERP), 
and the report by the Institute for Defense Analyses to assess the 
underlying assumptions and differences between various RERP cost 
estimates. We compared the practices used by DOD's Cost Analysis 
Improvement Group (CAIG) to develop the RERP cost estimate with 
practices described in GAO's cost assessment guide to evaluate the 
overall reliability of the new estimate. We discussed and evaluated C- 
17 production plans, costs, and issues related to work force, tooling, 
and suppliers for both a shutdown and a shutdown/restart scenario with 
DOD and contractor officials. 

We conducted this performance audit from February 2008 to November 2008 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. Appendix I includes 
additional details about our scope and methodology. 

Results in Brief: 

The Air Force has cut the number of C-5s it plans to fully modernize by 
more than half because of substantial cost increases in the 
modernization effort and will acquire a total of 205 C-17s--25 more 
than planned at the time of the Quadrennial Defense Review--with funds 
added by the Congress. All 111 C-5s will receive the avionics upgrade, 
while only 52 will receive the reliability enhancement and reengining 
upgrade. This mix may change again, based on the results of DOD's new 
mobility capabilities studies, possible C-5 retirements, and a revised 
cost estimate for C-5 modernization.[Footnote 2] DOD's previous 
mobility capabilities study, which was completed in December 2006, was 
found by GAO to be inadequate, in part because it did not base the 
number and mix of strategic airlift on a specific ton-mile[Footnote 3] 
mobility requirement metric, a metric commonly used to quantify the 
optimal mix of aircraft needed to meet a desired capability. DOD's new 
study--the findings of which it plans to release in May 2009--is 
expected to encompass transport needs for the future force. However, as 
of this writing DOD officials have not decided what specific metrics 
the department will use to make strategic airlift decisions. 

The costs to modernize C-5 aircraft have not been fully identified and 
are likely to increase. While the Air Force now estimates it will spend 
$9.1 billion to modernize C-5s, the costs may be underestimated because 
DOD did not apply risk or uncertainty analysis to its reliability 
enhancement and reengining program major cost drivers. Moreover, that 
particular effort is underfunded by almost $300 million and costs may 
escalate if the Air Force has to stretch the program schedule to stay 
within funding targets. At the same time, the Air Force has not fully 
priced or budgeted for a new C-5 upgrade program it plans to begin in 
fiscal year 2010 to address current avionics deficiencies and to add 
new capabilities. Some future costs, however, may be avoided should the 
Air Force justify retirement of some older C-5s and forego planned 
modifications. 

Results from the new mobility studies and potential C-5 retirements 
could lead to decisions to extend C-17 production beyond the 205 now 
authorized. According to current production plans, shutdown of the C-17 
production line will occur in September 2010. Careful planning to avoid 
shutting down the C-17 line prematurely is important. Both the Air 
Force and the manufacturer believe that shutting down the line and 
restarting production in the future would not be feasible or cost 
effective because of the substantial costs to hire and train a new 
workforce, reinstall tooling to proper working condition, and 
reestablish the supplier base. Nonetheless, at some point the C-17 
production line will shut down, and DOD estimates it will have to pay 
substantial costs for the shutdown. However, DOD has not yet budgeted 
for these costs. The manufacturer and Air Force developed significantly 
different estimates for shutdown of about $1 billion and $465 million, 
respectively. A large part of the difference can be attributed to the 
assumptions related to facilities demolition and environmental 
remediation, which the manufacturer included in its estimate but which 
the Air Force did not. 

To bring clarity to strategic mobility requirements, we recommend that 
the ongoing mobility capabilities study specifically identify ton-mile 
requirements, as well as other metrics, to quantify the number and mix 
of C-17 and C-5 aircraft needed and to inform decisions on potential C- 
5 retirements, the number of C-17s needed for both strategic and 
tactical roles, and future procurement and modernization needs. We also 
recommend updated, comprehensive, and fully funded estimates for C-5 
modernization efforts and for C-17 production line shutdown. DOD 
commented on a draft of this report and concurred with the 
recommendation to update the C-17 production shutdown cost estimate. 
DOD partially concurred with the recommendation to include a ton-mile 
metric and other relevant metrics in its mobility capabilities study 
effort because the department identified other offices responsible for 
implementing this recommendation; accordingly, we redirected the 
recommendation to the appropriate offices. DOD does not believe there 
is a compelling need to update its C-5 modernization cost estimates and 
therefore did not concur with that recommendation. We believe this 
recommendation remains valid as it provides DOD leaders better 
information to consider when making future budget decisions related to 
the number and mix of strategic airlifters. 

Background: 

The Air Force's C-5 and C-17 strategic airlifters both possess 
intercontinental range with aerial refueling and can carry weapons and 
equipment too large for any other DOD aircraft. Each also has some 
complementary characteristics that favor a mixed fleet. The larger C-5 
can carry more cargo than the C-17 and is the only aircraft capable of 
handling some equipment, such as the Army's 74-ton mobile scissors 
bridge. The C-17 is more modern, has a higher mission capable rate, 
[Footnote 4] and is more flexible in that it also provides tactical 
(intratheater) airlift to austere, forward-deployed bases. Figure 1 
compares the two strategic airlifters. 

Figure 1: Comparison of C-5 and C-17 Capabilities and Characteristics: 

[Refer to PDF for image] 

This figure contains drawing of both aircraft, as well as the following 
information: 

Loads: 
C-5: 270,000 pounds of cargo, (36 pallets), 81 troops; 
C-17: 170,900 pounds of cargo, (18 pallets),102 troops. 

Wingspan: 
C-5: 223 feet; 
C-17: 170 feet. 

Length: 
C-5: 247 feet; 
C-17: 174 feet. 

Maximum take-off weight: 
C-5: 840,000 pounds; 
C-17: 585,000 pounds. 

Range: 
C-5: 6,320 miles, (unrefueled); Unlimited (air refueled); 
C-17: 2,700 miles (unrefueled); Unlimited (air refueled). 

Speed: 
C-5: 518 mph; 
C-17: 572 mph. 

Minimum runway length: 
C-5: 6,000 feet; 
C-17: 3,500 feet. 

Crew: 
C-5: 7; 
C-17: 3. 

Mission capable rate: 
C-5: 53 percent; 
C-17: 86 percent. 

Cost per flying hour: 
C-5: $23,100; 
C-17: $11,300. 

Source: GAO analysis of DOD data; graphics by Lockheed Martin 
Corporation. 

[End of figure] 

The Air Force acquired the C-5 fleet in two production batches. 
Aircraft designated C-5A were built between 1969 and 1974 and given new 
wings in the 1980s.[Footnote 5] Aircraft designated C-5B were built in 
a second production run in the 1980s. In 1999, the Air Force began 
modernizing its C-5 aircraft to improve fleet reliability and mission 
capable rates. The modernization is being done in two phases. 

* The Avionics Modernization Program (AMP) upgrades capabilities, 
including Global Air Traffic Management, navigation and safety 
equipment, modern digital equipment, and an all-weather flight control 
system. 

* The Reliability Enhancement and Reengining Program (RERP) replaces 
engines and modifies electrical, fuel, and other subsystems. 

Together, these two upgrades were expected to improve the fleet's 
mission capable rate to at least 75 percent, thereby increasing payload 
capability and transportation throughput, and to reduce total ownership 
costs over the life cycle by about $14 billion in 2008 dollars. 
[Footnote 6] 

DOD initially expected to spend about $12 billion on the C-5 AMP and 
RERP efforts. However, both modernization efforts experienced cost 
problems. AMP development costs increased by approximately 20 percent 
and would have been higher had the Air Force not reduced requirements 
and deferred some development activities to other programs. Officials 
waived 14 operational requirements and deferred the correction of 250 
deficiencies identified during testing, many of which will be addressed 
and funded in RERP or future efforts. In 2007, DOD reported that RERP 
average procurement unit costs grew more than 50 percent from the 
original baseline estimate. 

C-17 procurement began in 1988 and the Air Force's current plan is to 
acquire a total of 205 C-17s for $66 billion. The first production C-17 
aircraft was delivered to the Air Force in June 1993 and the service 
has accepted delivery of 178 aircraft through October 2008. Delivery of 
the 205th aircraft is projected in August 2010. One aircraft is 
dedicated to provide airlift capabilities to the North Atlantic Treaty 
Organization, effectively setting the Air Force's operational force at 
204. 

DOD periodically assesses global threats, the national military 
strategy, and its force structure to determine future airlift 
requirements and to judge the sufficiency of its acquisition and 
modernization plans. The analytical basis for DOD's current airlift 
requirements is the mobility capabilities study completed in December 
2005. Officials used the study results to report in the 2006 
Quadrennial Defense Review that 180 C-17s and 112 fully modernized C- 
5s--i.e., those receiving both the AMP and RERP modification--would be 
sufficient to meet national military strategy with acceptable risk. The 
Air Force is now engaged in a new mobility capabilities study, the 
results of which will be briefed in May 2009. A final written report is 
expected to be issued in November 2009. According to Air Force 
officials, the new study will take into account a variety of changes 
that have occurred since the last mobility study was completed in 2005, 
including the following: 

* Addition of over 92,000 Marines and Army soldiers and their equipment 
that will need to be transported to locations across the United States 
and around the world. 

* Establishment of a new African Command that will require the movement 
of troops and equipment to a variety of locations around the second 
largest continent in the world. 

* Introduction of Mine Resistant Ambush Protected vehicles, which are 
being used in Iraq to provide enhanced protection for U.S. troops. 

* Increase in weight of the Army's Future Combat System vehicles, which 
makes it no longer possible to transport some vehicles with C-130 
aircraft (DOD's primary tactical airlifter). 

In addition to the new mobility capabilities study, Congress in 2008 
directed the Secretary of Defense to conduct a requirements-based study 
on alternatives for the proper size and mix of fixed-wing strategic and 
tactical airlift to meet the national military strategy for the 2012, 
2018, and 2024 time frames.[Footnote 7] The study, accomplished by the 
Institute for Defense Analysis, is due in January 2009. 

Mix of C-5s and C-17s Needed to Meet DOD's Strategic Airlift 
Requirement Continues to Evolve: 

The numbers and specific mix of strategic airlifters continues to be in 
a state of flux as DOD struggles to define and control costs and to 
establish firm requirements. Over the past several years, DOD has made 
changes in the number of C-5s and C-17s it says it needs to meet its 
strategic airlift requirement. C-5 modernization cost increases 
prompted DOD to reduce the number of C-5s it plans to fully modernize. 
Subsequently, Congress provided additional funding that the Air Force 
is using to procure more C-17s, which would offset the loss in 
capability of modernizing fewer C-5s. While officials believe this mix 
will allow DOD to meet its strategic airlift requirement, the number of 
C-5s DOD modernizes and C-17s it procures may change again, pending the 
results of ongoing mobility studies, potential C-5 retirements, and the 
eventual cost estimates of C-5 modernization. Past efforts to identify 
the appropriate mix have been hampered by the lack of sufficient 
metrics, such as a million ton-mile metric, that quantify specific C-5 
and C-17 needs. At this time, DOD officials have not determined what 
metrics it will use to make strategic airlift decisions. 

Fewer C-5s Will Be Fully Modernized Due to Significant RERP Cost 
Increases: 

C-5 modernization cost increases caused DOD to change its approach for 
meeting its strategic airlift requirements. DOD had planned to meet the 
requirements with 112 fully modernized C-5s--i.e., those receiving both 
the AMP and RERP modifications--and 180 C-17 aircraft. The cost for the 
C-5 modernization efforts was estimated to be approximately $12 
billion--about $900 million for the AMP program and $11.1 billion for 
the RERP program. 

However, just prior to the RERP production decision in February 2007, 
the prime contractor, Lockheed Martin, indicated that RERP costs 
related to labor and supplier parts had significantly increased, 
prompting new cost estimates. The Air Force's estimate of $17.5 billion 
was $4.2 billion more than Lockheed Martin's estimate of $13.3 billion 
at that time. The new estimate increased projected average procurement 
unit costs by more than 50 percent compared to the original baseline 
and triggered a statutory requirement for review and certification of 
the program.[Footnote 8] 

Following notification to Congress of the cost increase, the Under 
Secretary of Defense for Acquisition, Technology and Logistics 
requested that the CAIG estimate the cost of various options for DOD to 
meet its strategic airlift mission. The CAIG analyzed 14 options 
covering a range of scenarios for the RERP program in three broad 
categories: modifying all C-5 aircraft, partially modifying the C-5 
fleet, and canceling the C-5 RERP program. Each option also assumed 
that the department would have at least 203 C-17 aircraft, 14 more than 
the program planned to acquire at that time. The CAIG estimated the 
cost of providing the RERP modification to all 111 aircraft to be $15.4 
billion, halfway between the contractor's and the Air Force's 
estimates. Based on this analysis, the Under Secretary of Defense for 
Acquisition, Technology and Logistics concluded that the cost to RERP 
all C-5 aircraft was unaffordable and opted to limit full modification 
to 52 aircraft--47 C-5 Bs, both C-5 Cs, and 3 system development and 
demonstration aircraft. While the Air Force is expected to spend $3.4 
billion less under the restructured program, ultimately less than one- 
half of the 111 aircraft will be modernized and at a much higher unit 
cost than originally estimated (see table 1). 

Table 1: C-5 RERP Quantity and Cost Changes: 

Number of aircraft: 
Initial estimate: 126[A]; 
Current estimate: 52; 
Percentage change: -59. 

Total cost: 
Initial estimate: $11.1 billion; 
Current estimate: $7.7 billion; 
Percentage change: -31. 

Program acquisition unit cost: 
Initial estimate: $88 million; 
Current estimate: $148 million; 
Percentage change: 68. 

Source: DOD selected acquisition reports. 

[A] Since the initial estimate, the Air Force retired 14 C-5 aircraft 
and 1 crashed, leaving a current fleet of 111. 

[End of table] 

Additional C-17s Offset Capability Loss from Modifying Fewer C-5s: 

As part of the C-5 RERP restructuring, U.S. Transportation Command 
identified a need for 205 C-17s, 25 more than were authorized at the 
time the 2005 mobility capabilities study was completed. Subsequent to 
the study, Congress provided additional funding that the Air Force used 
to procure 10 more C-17s in 2007 and 15 more in 2008. The following 
table shows the changes in the strategic airlift mix over the past 3 
years and the impact the mixes have had on DOD's ability to meet its 
strategic airlift mission (see table 2). While DOD did not use a 
million ton-mile per day metric to determine how many C-5s and C-17s it 
needed in its December 2005 mobility study, officials were able to 
quantify for us the million ton-mile per day capabilities of the 
scenarios identified below. 

Table 2: Estimated Million Ton-Mile per Day Capability Comparison: 

Strategic airlifters: Number of C-17; 
December 2005: 180; 
July 2007: 190; 
February 2008: 190; 
September 2008: 205. 

Strategic airlifters: Number of C-5s; 
December 2005: 112 fully modernized; 
July 2007: 112 fully modernized; 
February 2008: 59 avionics only; 52 fully modernized; 
September 2008: 59 avionics only; 52 fully modernized. 

Strategic airlifters: Estimated million ton-miles per day capability; 
December 2005: 33.09; 
July 2007: 33.95; 
February 2008: 33.05; 
September 2008: 34.80. 

Source: GAO analysis of DOD data. 

[End of table] 

The fiscal year 2009 National Defense Authorization Act authorizes 
procurement of 6 more C-17s, which will bring the total number to 211 
aircraft.[Footnote 9] 

Forthcoming Decisions Could Lead to a Change in the Strategic Airlift 
Mix in the Near Future: 

The number and mix of aircraft needed to support DOD's strategic 
airlift mission could change again based on the results of ongoing 
mobility studies, possible C-5 retirements, and the eventual cost of C- 
5 modernization efforts. However, DOD's ability to make sound strategic 
airlift portfolio decisions, including the number of C-5s to retire and 
the number of additional C-17s that should be procured, may be hampered 
if appropriate metrics are not included in the study efforts. 

Mobility Requirements Studies: 

DOD is currently studying its future mobility requirements. The 
congressionally directed requirements study by the Institute of Defense 
Analysis is due in January 2009, followed by the Air Force's mobility 
capabilities study in May 2009. Some expect the studies will identify 
increased demands on airlift, particularly for the C-17 since it can 
perform both a strategic and tactical role. As Army equipment becomes 
heavier and/or bulkier, the C-17 may be the only aircraft capable of 
delivering major weapon systems to the front lines and to more austere 
bases in the theater of combat. The results of both studies, if done 
accurately and comprehensively, should provide the analytical 
foundation for the future airlift force structure. 

We previously reported on shortcomings in the Institute for Defense 
Analysis' study plan that could make it difficult for decision makers 
to know how much strategic airlift is needed. For example, the study 
plan did not provide details on assumptions and the measures of 
effectiveness, or metrics, the command officials would be using in 
their evaluation. Measures of effectiveness are considered to be 
especially important when evaluating alternatives, such as comparing 
the results of two analyses that measure different airlift force mixes. 
We recommended in April 2008 that DOD take action to ensure that the 
final study plan included sufficient details to address all the 
elements specified in the law and needed to inform decision makers on 
airlift issues.[Footnote 10] DOD concurred with our recommendation. 

We also identified shortcomings in DOD's 2005 mobility capabilities 
study approach that, if not addressed, could be repeated again in the 
current study. Unlike prior studies, the 2005 study did not recommend a 
specific airlift requirement expressed in million ton-miles per day--a 
common metric integral to prior capability studies that defines and 
quantifies airlift requirements as a basis for computing the size and 
optimal mix of airlift forces. Instead, DOD officials stated that it 
expressed its airlift requirement in terms of specific numbers and 
types of aircraft needed to meet the national defense strategy to take 
into account real-world operating parameters that may cause aircraft 
payloads to vary significantly from standard planning factors. Later, 
in response to congressional direction, DOD translated the requirements 
into a million ton-mile requirement. We also found the study did not 
identify the operational impact of increased or decreased strategic 
airlift on achieving warfighting objectives that would be associated 
with different mixes of C-5 and C-17 aircraft. As a result, we could 
not determine how the study concluded that the mix of C-5s and C-17s at 
that time was adequate for meeting mobility requirements and for 
supporting strategic airlift portfolio investment decisions. In 2006, 
we recommended that DOD include mobility metrics, along with 
warfighting metrics to determine air superiority, when completing 
future mobility capabilities studies. DOD concurred with this 
recommendation.[Footnote 11] 

Although DOD concurred with the recommendation, a Transportation 
Command official stated that a decision has not yet been made on what 
specific metrics will be used to determine the number and mix of 
strategic airlifters in the current mobility capabilities study. At the 
time of this writing, the study plan had not been finalized and it is 
unclear whether a million ton-miles metric will be used, though it is 
being considered. DOD often uses the million ton-mile metric as an easy 
way to compare the capacity of different fleet mixes. For example, 
according to a DOD official, since C-130s, C-130Js, C-17s, C-5As, C- 
5Bs, and C-5Ms all have different capabilities when it comes to payload 
and range, it is difficult to compare different mixes of them without 
using this metric. 

Potential C-5 Retirements: 

Congressional legislation would allow the Air Force to begin to retire 
some C-5s, if appropriate, beginning October 1, 2008, as long as the 
Air Force maintains a strategic airlift fleet of 299 aircraft.[Footnote 
12] Prior to retiring any aircraft, DOD's Director of the Operational 
Test and Evaluation must complete its assessment of a C-5A that had 
received RERP modification.[Footnote 13] According to an Air Force 
official, testing of a C-5A will begin in August 2009 and the final 
report will be released in February 2010. 

Air Mobility Command officials told us that while they are concerned 
about the emerging global threats and requirements, fiscal and 
personnel demands require that the command limit overall fleet size 
once warfighting risk is reduced to a reasonable level. Therefore, the 
Air Mobility Command will consider retiring C-5s, as the law and 
requirements allow, on a one-for-one basis after 205 C-17s have been 
procured to ensure the right combination of aircraft and capability is 
balanced against cost and risk. A decision on whether and when to 
retire C-5s will not likely be made until after the mobility study has 
been completed. 

Relative Capability Increases from Modernized C-5s and New C-17 
Aircraft: 

Finally, if the cost for C-5 modernization continues to increase, Air 
Force officials may have to reconsider the mix within its airlift 
portfolio or request additional funding. Additional investments in C-17 
aircraft may become more attractive. Currently, a new C-17 would cost 
about $276 million compared to $132 million to fully modernize a C-5. 
Each new C-17 potentially adds 100 percent of its cargo capacity toward 
meeting the total airlift requirement. Because the C-5s are already 
part of the operational force, each aircraft's current capacity is 
already counted toward the total requirement. Consequently, according 
to DOD data, the C-5 modernization programs only provide a marginal 
increase of 14 percent in capability over nonmodernized aircraft. Using 
DOD's million ton-mile per day planning factors, we, working in 
collaboration with DOD, calculated that DOD would need to fully 
modernize 7 C-5s to attain the equivalent capability achieved from 
acquiring 1 additional C-17 and the costs would be over 3 times more 
(see table 3). 

Table 3: Comparison of a Modernized C-5 and C-17 Equivalent Airlift 
Capabilities: 

C-5 fully modernized: 
Unit cost[A]: $132 million; 
Aircraft needed to provide equivalent capabilities: 7; 
Total cost of equivalent capability: $924 million. 

C-17 new: Unit cost[A]: $276 million; 
Aircraft needed to provide equivalent capabilities: 1; 
Total cost of equivalent capability: $276 million. 

Source: GAO analysis of DOD data. 

[A] Unit costs reflect procurement costs only. Data are rounded for 
presentation purposes. 

[End of table] 

The analysis does not include the life-cycle costs of adding more C-17s 
to DOD's airlift portfolio. However, previous DOD analysis indicated 
that the life-cycle costs would be approximately the same if DOD 
replaced 30 C-5s with 30 C-17s. 

C-5 Modernization Costs Have Not Been Fully Identified: 

The Air Force has not fully identified the funding needed to modernize 
the C-5 aircraft, and costs are likely to increase. The current cost 
estimate is $9.1 billion to AMP the entire fleet of 111 aircraft and 
RERP 52 aircraft. However, we believe this is understated. The current 
budget does not fully fund the revised RERP program and the CAIG's cost 
estimate does not adequately address risk and uncertainty. Further, the 
cost estimate does not include the costs for a new modernization 
upgrade program slated to begin in fiscal year 2010 that would fix AMP 
deficiencies and add new capabilities. Alternatively, some future 
modification costs may be avoided should the Air Force justify 
retirement of some older C-5s. 

Current Estimate for C-5 Modernization Costs Is Questionable: 

The current budget does not sufficiently fund the revised RERP program. 
According to the CAIG's analysis, the C-5 RERP is underfunded by about 
$294 million across the Future Years Defense Plan for fiscal years 2009-
2013. Approximately $250 million less is needed in fiscal years 2009 
through 2011, and $544 million more is needed in fiscal years 2012 and 
2013. According to program officials, the Air Force is committed to 
fully funding the CAIG RERP cost estimate in the fiscal year 2010 
President's budget yet to be submitted. However, program officials 
could not identify sources for the additional funding needed in fiscal 
years 2012 and 2013. Figure 2 provides the funding estimate developed 
by the CAIG to support the restructured RERP program compared to the 
fiscal year 2009 budget. 

Figure 2: Annual Funding Requirements for the C-5 RERP: 

[Refer to PDF for image] 

This figure is a combination vertical bar and line graph depicting the 
following data: 

Fiscal year: 2009; 
Fiscal year 2009 budget: $561.9 million; 
CAIG estimate: $511.2 million. 

Fiscal year: 2010; 
Fiscal year 2009 budget: $866 million; 
CAIG estimate: $711.5 million. 

Fiscal year: 2011; 
Fiscal year 2009 budget: $975.2 million; 
CAIG estimate: $930.2 million. 

Fiscal year: 2012; 
Fiscal year 2009 budget: $936.9 million; 
CAIG estimate: $1170.2 million. 

Fiscal year: 2013; 
Fiscal year 2009 budget: $932 million; 
CAIG estimate: $1242.7 million. 

Source: CAIG and DOD budget data, GAO analysis. 

[End of figure] 

While our review of the CAIG's cost-estimating methodology found it 
generally well documented, comprehensive, and accurate, we found some 
weaknesses that impair the credibility and overall reliability of the C-
5 cost estimate.[Footnote 14] Specifically, the CAIG did not take risk 
or uncertainty into account for some major cost drivers, in particular 
the propulsion system and labor. Because cost estimates predict future 
program costs, uncertainty is always associated with them. For example, 
there is always a chance that the actual cost will differ from the 
estimate because of a lack of knowledge about the future as well as 
errors resulting from historical data inconsistencies, assumptions, 
cost-estimating equations, and factors that are typically used to 
develop an estimate. Quantifying that risk and uncertainty is 
considered to be a cost estimating best practice because it captures 
the cumulative effect of risks and recognizes the potential for error. 

In a memo documenting its independent cost estimate, the CAIG stated 
that the biggest risk to the cost estimate was the purchase agreement 
between Lockheed Martin and General Electric for the propulsion system 
that is conditioned on specific annual procurement quantities. The CAIG 
had estimated that the Air Force could save 18 percent by meeting the 
quantity and schedule identified in the revised RERP. However, CAIG 
officials stated that if the budget is not sufficient to meet these 
agreed-to quantities, then anticipated price breaks would not occur, 
resulting in increased costs of the C-5 RERP to the government. Despite 
this significant risk, the CAIG did not perform a risk/uncertainty 
analysis to determine the extent to which costs would increase should 
the buy quantity be cut. CAIG officials stated that they believe 
propulsion system procurement risk has been mitigated because they have 
identified the quantities necessary to meet the conditions of the 
purchase agreement and the Air Force plans to fully fund to this 
estimate. Despite these assurances, however, we have found that DOD 
often changes procurement quantities and there is a risk that 
quantities for the C-5 RERP program may change. For example, DOD's 
Selected Acquisition Report summary shows that of the 56 programs 
currently in production, 38 (or 68 percent), have experienced a 
quantity change since their production decisions. 

In addition, the CAIG did not quantify or address uncertainty with its 
$2.1 billion labor cost estimate associated with the installation of 
the RERP on C-5 production aircraft. The RERP program experienced a 29- 
month break in production between the last system development and 
demonstration unit and the first production unit. As such, the CAIG had 
to estimate inefficiencies due to loss of learning and how it would 
affect the costs of future production. The CAIG's assumptions differed 
from those used by the Air Force and Lockheed Martin, which caused the 
CAIG estimate to be about $200 million more than Lockheed Martin's 
estimate and about $400 million less than the Air Force's labor 
estimate. As a result of the weaknesses discussed above, the Air 
Force's basis for making strategic airlift portfolio investment 
decisions is impaired, and the RERP program is at increased risk of 
experiencing cost overruns. 

A New Modernization Program for the C-5 Will Add Further Costs: 

Additional modernization efforts not yet budgeted will add to future C- 
5 costs. Air Force officials stated that a new C-5 upgrade program is 
slated to begin in fiscal year 2010. The initial funding requirement is 
$65 million--$40 million in research, development, test, and evaluation 
funds and $25 million in procurement funds--to migrate all C-5s toward 
a standard software configuration, based on changes made in the AMP and 
RERP programs. Requirements previous waived on the AMP may also be 
addressed in the initial block of this program. Additional funding will 
be requested in 2012 and beyond to provide additional capabilities. 
According to a program official, the total requirements and funding 
needs for this modernization program have not been finalized. However, 
at this time it is not expected to be as costly as the C-5 AMP or RERP. 

The eventual costs for modernizing C-5 aircraft hinge upon the 
decisions DOD officials make about the number and mix of strategic 
airlifters DOD needs in the future. If additional C-5 capability is 
needed, more C-5 aircraft may need to receive the RERP modification and 
costs will increase. On the other hand, if decision makers believe 
additional C-17 capability is needed in lieu of the C-5, the Air Force 
may be able to reduce the number of aircraft that need the AMP 
modification and additional modifications slated to begin in fiscal 
year 2010. 

The Air Force Must Make a Decision Soon Regarding C-17 Acquisition and 
Eventual Shutdown of the Production Line: 

Results from the two mobility studies, potential C-5 retirements, and 
future modernization cost increases could lead to a decision to extend 
C-17 production beyond the 205 now authorized. The production line is 
currently scheduled to close in September 2010 with the supplier base 
and portions of the line closing sooner. A well-reasoned near-term 
decision on the final force size could avoid substantial future costs 
from ending C-17 production prematurely and later restarting 
production. Eventually, the Air Force is responsible for providing the 
substantial funding for shutdown expenses. Contractor and Air Force 
cost estimates vary widely, ranging up to $1 billion and more, and need 
to be reconciled. Only $37 million has been budgeted thus far. 

Careful Planning Needed to Avoid Shutting Down and Restarting the 
Production Line: 

Two alternatives to completely shutting down the C-17 production line 
would be to slow down the rate of production or to close out current 
production while preserving some ability to restart the line should 
conditions change and additional C-17s are needed. Both options are not 
attractive. Slowing down production raises unit costs due to smaller 
annual quantities. Analysis indicates that, once closed, it would not 
be feasible or cost effective to restart production due to costs for 
hiring and training a new workforce, reinstalling tooling, and 
reestablishing the supply base. Therefore, careful planning to firmly 
and timely establish future C-17 fleet requirements is important to 
avoid unnecessary costs associated with a slowdown or a premature 
shutdown. 

Our review of contractor and Air Force plans identified the following 
major challenges and substantial costs for restarting production: 

* A workforce of nearly 3,100 people would have to be hired and trained 
following a complete shutdown. Boeing officials believe that the vast 
majority of its current workforce will not be available for 
reemployment 1 year after the shutdown. A union representative stated 
that workers, whose average age is around 57 years, will either retire 
or find other jobs during the shutdown period. Boeing does not have the 
ability to move its workers to other production lines at its Long 
Beach, California, plant because the C-17 is the last aircraft being 
built at that facility.[Footnote 15] 

* Production tooling would need to be dismantled, stored, and 
maintained for the entire length of the shutdown. Tooling would then 
have to be reinstalled and restored to its original working condition, 
which officials believe would be no small feat considering the 
significant amount of automation involved in the production process. In 
addition, new tooling may need to be procured depending on design 
changes that may occur during the shutdown period. 

* Suppliers would have to be identified and their processes and parts 
would have to be qualified. Boeing officials stated that some suppliers 
it deals with now may not be available and many other suppliers may not 
participate in the C-17 production program because they may develop 
alternative business ventures following the shutdown. Suppliers of 
certain specialty parts are of utmost concern. 

Cost estimates to shut down and restart the C-17 production line are 
very substantial. In 2006, when various shutdown options were being 
evaluated, Boeing estimated that the cost to shut down and restart 
would be about $918 million; the Air Force estimated $2 billion. Table 
4 shows the main assumptions used to develop these estimates. 

Table 4: Comparison of Boeing and Air Force Cost-estimating Assumptions 
for C-17 Production Line Shutdown and Restart: 

Then-year dollars: 

Boeing estimate $918 million: 
* 5-year production shutdown period, estimate only covers 24-month 
shutdown period, a new contract would be required for the remaining 36 
months; 
* Includes 30 percent factor to cover risk; 
* Did not include restart cost in the estimate. 

Air Force estimate $2 billion: 
* Restart spans 3 years and shutdown spans 48-month period and assumes 
production restart decisions in October 2010.
* Includes 20 percent risk in the estimate; 
* Includes restart cost in the estimate. 

Source: GAO analysis of Boeing and C-17 Program Office data. 

[End of table] 

Boeing and the Air Force used different cost-estimating assumptions 
when completing their production shutdown and restart estimates, and 
neither estimate reflects all potential costs. For example, Boeing's 
estimate only addresses mothballing the production facility in 
anticipation of restarting production, whereas the Air Force's estimate 
includes the costs to stop and restart production as well as a final 
shutdown that would occur after a second production run is completed. 
Neither Boeing nor the Air Force included costs to hire and train 
approximately 3,100 workers or to make configuration changes that may 
have occurred to the aircraft during the time period when the line was 
shut down. According to Boeing and Air Force officials, these two cost 
categories could add millions of dollars to their production shutdown 
and restart estimates. 

Air Force Has Not Budgeted Sufficient Funds for the C-17 Production 
Shutdown: 

At this writing, the Air Force has allocated $37 million in its 
outyears budget for C-17 production shutdown, far less than what is 
believed to be needed. As above, cost estimates vary and were not 
consistently derived. Identifying and reconciling the full costs of 
shutdown is needed. The Air Force plans to negotiate and issue a 
postproduction contract to Boeing to identify the disposition of 
tooling and other production assets and to ensure that a viable 
sustainment supplier base has been established when production has 
ended. 

In 2006, Boeing and the Air Force developed considerably different 
estimates of about $1 billion and $465 million, respectively, for the 
cost of shutting down production completely. Table 5 below compares the 
two cost estimates developed in 2006 and the underlying assumptions 
that contributed most significantly to the differences. 

Table 5: Comparison of Cost and Assumptions Included in C-17 Production 
Line Shutdown Cost Estimates: 

Then-year dollars: 

Boeing estimate $1 billion: 
* 5-year shutdown schedule beginning in 2006; 
* Buildings would be demolished; 
* Environmental remediation needed. 

Air Force estimate $465 million:
* 4-year shutdown schedule beginning in 2008; 
* No costs for demolishing facilities; 
* No environmental remediation needed. 

Source: GAO analysis of Boeing and C-17 Program Office data. 

[End of table] 

Differences between the two estimates can largely be attributed to the 
underlying assumptions used. For example, in assessing alternatives for 
shutting down the C-17 production facility at Long Beach, California, 
Boeing considered three options for the site: redeploy the property to 
Boeing for reuse, treat the property as an operating asset, or sell the 
property. Boeing officials concluded that the current production 
facility would not be used for future business and should be sold. 
Therefore, they included costs to demolish facilities and for 
environmental remediation in their estimate. Air Force officials 
believe demolition and environmental remediation costs should not be 
part of the shutdown costs and did not include them. 

Since 2006, Congress has provided additional funding that the Air Force 
is using to procure additional C-17s. Thus, DOD officials stated that 
the requirement to shut down the production has been delayed 1 year and 
now estimate the shutdown costs to be $505 million, due to inflation. 
Boeing has not updated its estimate. 

Conclusions: 

Strategic airlift is an essential, key enabler of U.S. military 
capability to rapidly project forces worldwide. The C-5 and C-17 
provide complementary capabilities. However, DOD continues to struggle 
with identifying the specific quantities and determining the optimal 
mix of aircraft needed. Clarity is needed before committing additional 
billions of dollars to C-5 modernization programs, establishing C-5 
retirement schedules, and/or acquiring additional C-17 aircraft. 
Careful planning is also important to avoid the costs of shutting down 
the C-17 line prematurely and later deciding to restart the production. 
The new mobility studies, if done correctly, could bring clarity to 
strategic airlift capabilities needed to support the future force and 
changed threats, as well as inform future tactical airlift requirements 
because of the C-17's dual role. Important metrics left out of the 2005 
capabilities study--such as specific ton-mile mobility requirements and 
relative reliability rates--are considered critical factors in 
quantifying and analyzing cost-effective force mixes. DOD concurred 
with our prior recommendation to use mobility metrics to inform future 
mobility capabilities studies. However, at this writing, it is unclear 
whether DOD will use a million ton-mile metric in its current analysis 
to determine the cost-effective mix of aircraft and guide important 
investment decisions related to the expenditure of billions of dollars. 
Until comprehensive requirements--supported by appropriate, 
quantifiable metrics--and the full costs for alternate courses of 
action are identified, DOD decision making on the future size and mix 
of strategic airlift is hampered, thus increasing the risk of incurring 
unnecessary costs and establishing a less than optimal mix of strategic 
and tactical airlift forces. 

Recommendations for Executive Action: 

To better inform decision makers and provide improved and quantifiable 
projections of airlift mobility requirements and investment needs, we 
recommend that the Secretary of Defense direct the Office of the 
Secretary of Defense (Program Analysis and Evaluation) and U.S. 
Transportation Command to take the following action: 

* Ensure that the new mobility capabilities study specifies the ton- 
mile per day metric and other relevant metrics to support sound 
strategic airlift decisions, including (1) the cost-effective mix of C- 
5 and C-17 aircraft consistent with national security strategy; (2) the 
number of C-5s required to airlift equipment that can only be carried 
by that aircraft; (3) C-5A retirement schedules, if warranted by 
analysis; (4) the number of C-17s needed to accomplish both its 
strategic and tactical roles; and (5) future procurement and 
modernization needs. 

We also recommend that the Secretary of Defense direct the Secretary of 
the Air Force to take the following two actions: 

* Prepare updated, reliable, and comprehensive cost estimates for C-5 
modernization to include risk and sensitivity analyses on major cost 
drivers for the RERP, the costs of a new modernization program, and 
potential savings should some C-5A retirements be warranted. 

* Identify and budget for the full costs to shut down the C-17 
production line in the time frame consistent with final decisions on 
the future size of the C-17 fleet. 

Agency Comments and Our Evaluation: 

DOD provided us with written comments on a draft of this report. DOD 
concurred with one recommendation, partially concurred with another, 
and did not concur with one recommendation. DOD's comments appear in 
appendix II. DOD also provided technical comments on our draft report 
which we incorporated as appropriate in the report. 

In its comments, DOD partially concurred with the draft recommendation 
to ensure that the current mobility capabilities study specifies a ton- 
mile per day metric and other relevant metrics to support sound 
strategic airlift decisions. The department stated that the Office of 
the Secretary of Defense (Program Analysis and Evaluation) and U.S. 
Transportation Command, offices that are jointly working on the 
mobility capabilities study, will specify metrics, including a ton- 
miles per day metric, for the study. Accordingly, we redirected our 
recommendation to these offices instead of the Air Force. 

DOD did not concur with the recommendation to prepare updated C-5 
modernization cost estimates. DOD stated that the modernization is 
being accomplished in two phases--the AMP and RERP--and that the third 
modernization effort we identified that is slated to begin in fiscal 
year 2010 is a sustainment program that would fall below the ACAT II 
threshold. Further, department officials believe that the most recent 
cost estimates for the AMP and RERP are sufficient and areas of concern 
and mitigating factors related to the RERP estimate were identified 
during the Nunn-McCurdy process. 

We continue to believe updated estimates are warranted. We are not 
suggesting that the department revisit its RERP Nunn-McCurdy decision. 
For the most part, we believe the CAIG did an adequate job identifying 
the costs associated with 14 different RERP options, especially given 
the short time frame in which the estimates had to be completed. 
However, the CAIG did not perform risk or uncertainty analysis, which 
is considered to be a cost-estimating best practice. Since the program 
is not fully funded and the Air Force has not yet completed its 
analysis of mobility requirements, there remains significant risk that 
funding will not be available in outyears or that the quantities of C- 
5s and C-17s could change. Therefore, we believe it is important that 
DOD identify a range of potential costs based on different quantities, 
so that decision makers will have adequate information for future 
budget decisions related to the number and mix of strategic airlifters. 

DOD concurred with our recommendation to identify and budget for the 
full costs to shut down the C-17 production line consistent with final 
decisions on the future size of the C-17 fleet. 

We are sending copies of this report to the Secretary of Defense and 
interested congressional committees. The report is also available at no 
charge on the GAO Web site at [hyperlink, http://www.gao.gov]. 

If you have any questions about this report or need additional 
information, please contact me at (202) 512-4841 or sullivanm@gao.gov. 
Contact points for our Offices of Congressional Relations and Public 
Affairs may be found on the last page of this report. Key contributors 
to this report were Bruce Fairbairn, Assistant Director; Cheryl Andrew; 
Marvin Bonner; John Crawford; Karen Sloan; Karen Richey; and Marie 
Ahearn. 

Signed by: 

Michael Sullivan: 
Director: 
Acquisition and Sourcing Management: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

This report examines the Department of Defense's (DOD) efforts to meet 
its strategic airlift requirements. Specifically, we (1) identify the 
impact C-5 modernization cost increases have had on the mix of aircraft 
DOD needs to meet its strategic airlift requirement, (2) assess the 
current C-5 modernization cost estimate, and (3) identify C-17 
production plans and issues related to a production line shutdown. 

To determine the impact C-5 modernization cost increases have on the 
mix of aircraft DOD needs to meet its strategic airlift requirement, we 
compared the mix of aircraft DOD planned to use to meet the strategic 
airlift requirements identified in a 2005 mobility study to the mix of 
aircraft DOD currently plans to use. We collected information on the 14 
options DOD considered to meet its strategic airlift requirements 
following the C-5 Reliability Enhancement and Reengining Program (RERP) 
cost breach notification to Congress. We also obtained cost data from 
the Cost Analysis Improvement Group (CAIG) related to the 14 options. 
We met with appropriate officials from the Office of the Secretary of 
Defense, the Office of the Secretary of the Air Force, and Air Mobility 
Command to obtain their opinions on the mix of C-5 and C-17 aircraft 
needed to meet the current mobility requirement. When available, we 
obtained analytical documentation supporting the views of these 
officials. 

We also considered the impact decisions related to the current, ongoing 
mobility studies, pending congressional legislation, and further C-5 
cost increases could have on the future mix of C-5 and C-17s. We 
identified issues related to DOD's 2005 mobility study and discussed 
DOD's efforts to address these same issues in the current study with 
DOD officials. 

To determine the current cost estimates for the C-5 modernization 
efforts, we collected cost estimates for the C-5 Avionics Modernization 
Program (AMP) and C-5 RERP. We also gathered preliminary cost data for 
the modernization program slated to begin in fiscal year 2010 from 
program officials. We used C-5 AMP cost data from the December 2007 
Selected Acquisition Report and C-5 RERP cost data from the June 2008 
Selected Acquisition Report. The CAIG identified funding shortfalls for 
the C-5 RERP program. 

During our examination of C-5 RERP costs, we collected various cost 
estimates and supporting documentation developed by Lockheed Martin, 
the DOD CAIG, and the Air Force. We met with appropriate officials from 
each of these organizations to determine the underlying assumptions of 
their respective estimates and to understand key differences between 
the estimates. Since the CAIG's estimate serves as DOD's official 
estimate for the restructured C-5 RERP program, we compared how that 
estimate was developed to GAO's guide for estimating and managing 
program costs[Footnote 16] to determine the reliability of the DOD's 
cost estimate. We also interviewed officials from the Institute for 
Defense Analysis to discuss their analysis and findings related to the 
various C-5 RERP cost estimates.[Footnote 17] 

To identify C-17 production plans and issues related to the C-17 
production line shutdown, we collected information on the number of C- 
17s DOD is currently authorized to procure and discussed production 
shutdown time frames with Boeing, the prime contractor. We collected 
cost estimates and underlying assumptions Boeing and the Air Force made 
in 2006 for shutting down the production line completely and shutting 
down and restarting the production line at a later time. Additionally, 
we obtained the opinions of Boeing and Air Force program officials 
about the costs and challenges associated with shutting down and 
restarting the production line. Our discussions with both of these 
organizations focused on potential personnel, supplier, and tooling 
issues. We also discussed this topic with Boeing union officials who 
have dealt with downsizing efforts at Boeing's Long Beach, California, 
facility and Lockheed Martin officials who were involved with shutting 
down and restarting the C-5 production line during the 1970s and 1980s 
at the Marietta, Georgia, plant. Finally, we reviewed DOD budget 
documents to determine how much had been budgeted for the C-17 
production line shutdown. 

We conducted this performance audit from February 2008 to November 2008 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the Department of Defense: 

Office Of The Under Secretary Of Defense: 
Acquisition, Technology And Logistics: 
3000 Defense Pentagon: 
Washington, DC 20301-3000 

November 14, 2008: 

Mr. Michael J. Sullivan: 
Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, DC 20548: 

Dear Mr. Sullivan: 

This is the Department of Defense (DoD) response to the GAO draft 
report, GAO-09-50, "Defense Acquisitions: Timely and Accurate Estimates 
of Costs and Requirements Are Needed to Define Optimal Future Strategic 
Airlift Mix," dated October 15, 2008, (GAO Code 120718). DoD's 
responses to the report's recommendations are enclosed. 

The GAO draft report contains misleading information that leads one to 
believe the Department did not apply proper rigor in its strategic 
airlift cost-benefit analysis. The Department stands by the 
restructured C-5 Reliability Enhancement and Re-enginning Program 
following Nunn-McCurdy re-certification and the analysis behind that 
decision. The Department's Cost Analysis Improvement Group properly 
analyzed all 14 of the options proposed during the Nunn-McCurdy process 
and identified areas of concern and mitigating factors. Additionally, 
the Department found many of the GAO report's analyses and supporting 
tables to be misleading and over-simplified. 

The Department understands the criticality of its strategic airlift 
capability in today's global environment. Proper stewardship of 
resources is essential in ensuring we maintain this capability. The 
upcoming Mobility Capabilities and Requirements Study will apply the 
proper metrics necessary to aide the Department in determining the most 
capable and cost-effective fleet to meet our global commitments. My 
point of contact for this matter is Col AJ Murch, at 703-695-7565, e-
mail Anthony.Murch@osd.mil. 

Sincerely, 

Signed by: 
David G. Ahern: 
Director: 
Portfolio Systems Acquisition: 

Enclosure: As stated: 

GAO Draft Report Dated October 15, 2008: 
GAO-09-50 (GAO Code 120718): 

"Defense Acquisitions: Timely And Accurate Estimates Of Costs And 
Requirements Are Needed To Define Optimal Future Strategic Airlift Mix" 

Department Of Defense Comments To The GAO Recommendations: 

Recommendation 1: The GAO recommends that the Secretary of Defense 
direct the Secretary of the Air Force to ensure that the new mobility 
capability study specifies the ton-miles per day metric and other 
relevant metrics to support sound strategic airlift decisions, 
including (1) the cost-effective mix of C-5 and C-17 aircraft 
consistent with national security strategy; (2) the number of C-5s 
required to airlift equipment that can only be carried by the aircraft; 
(3) C-5A retirement schedules, if warranted by analysis; (4) the number 
of C-17s needed to accomplish both its strategic and tactical roles; 
and (5) future procurement and modernization needs. (p. 19/GAO Draft 
Report) 

DOD Response: Partially concur. The Mobility Capabilities and 
Requirements Study - 2016 (MCRS-16) is a joint Office of the Secretary 
of Defense (Program Analysis and Evaluation)/U.S. Transportation 
Command effort. These offices, with support from the US Air Force, will 
specify appropriate metrics (to include ton-miles per day) to support 
sound strategic airlift decisions. The study will identify: (1) an 
appropriate mix of C-5 and C-17 aircraft that is consistent with 
national security strategy; (2) the number of C-5s required to airlift 
equipment that can only be carried by the aircraft; and (3) the number 
of C-17s needed to accomplish both its strategic and tactical roles. 
The MCRS will set the stage to address the cost-effectiveness of the 
strategic airlift mix, recommend C-5A retirements, and identify future 
procurement and modernization needs. Any capability gaps in the 
strategic airlift fleet identified in MCRS-16 will be addressed during 
ensuing program and budget development processes. 

Recommendation 2: The GAO recommends that the Secretary of Defense 
direct the Secretary of the Air Force to prepare updated, reliable, and 
comprehensive cost estimates for C-5 modernization to include risk and 
sensitivity analyses on major cost drivers for the RERP, the costs of a 
new modernization program, and potential savings should some C-5A 
retirements be warranted. (p. 19/GAO Draft Report) 

DOD Response: Non-concur. Modernization of the C-5 fleet will be 
accomplished in two phases, each of which is a separate Major Defense 
Acquisition Program (MDAP). The C-5 Avionics Modernization Program 
(AMP) represents the first phase. AMP is a mature program well into its 
production phase, with no future acquisition milestones and only one-
third of the required total procurement funding remaining in FY 2010-
2015. The C-5 Reliability Enhancement and Re-enginning (RERP) Program 
represents the second phase of the C-5 fleet modernization. In 
preparation for its Milestone C, the Air Force cost estimate revealed a 
critical breach of the unit cost metrics requiring the Department to 
review and recertify the program to Congress under the Nunn-McCurdy 
statute. A restructured RERP program excluding the older C-5A model 
aircraft was certified to Congress in February 2008 and Milestone C 
approval was granted in March 2008. The OSD Cost Analysis Improvement 
Group (CAIG) developed an independent cost estimate of the restructured 
program, to include areas of concern and mitigating factors, to support 
its certification and its subsequent Milestone C. Finally, the "new 
modernization upgrade program" referenced in the report is primarily a 
sustainment effort which will initially focus on correcting 
deficiencies in the software of the current C-5 AMP program. This 
software block cycle sustainment program is common to many weapons 
systems and should not be mistaken for a Major Defense Acquisition 
Program (MDAP). The cost for this sustainment effort is currently 
projected to fall below the ACAT II threshold. Given C-5 AMP's program 
maturity, RERP's lack of technology elements which will become cost 
drivers, and the block sustainment program being a "level of effort" 
program, there is no compelling need for a new comprehensive cost 
estimate of the C-5 fleet modernization efforts. 

Recommendation 3: The GAO recommends that the Secretary of Defense 
direct the Secretary of the Air Force to identify and budget for the 
full costs to shut down the C-17 production line in the time frame 
consistent with final decisions on the future size of the C-17 fleet. 
(p. 19/GAO Draft Report) 

DOD Response: Concur. The future size of the C-17 fleet and 
accompanying shutdown decisions will be addressed once the results of 
the MCRS are available and additional analysis is completed. 

[End of section] 

Footnotes: 

[1] While this report was out to DOD for comment, the President signed 
the fiscal year 2009 National Defense Authorization Act, which 
authorizes the procurement of 6 more C-17s, bringing the total number 
of C-17s authorized to 211 aircraft. Accordingly, throughout this 
report we refer to the 205 C-17s previously authorized. Duncan Hunter 
National Defense Authorization Act for Fiscal Year 2009, Pub. L. No. 
110-417, § 1501(b) (2008). 

[2] National Defense Authorization Act for Fiscal Year 2004, Pub. L. 
No. 108-136, § 132 (2003) includes provisions that DOD must meet before 
it can retire C-5 aircraft. 

[3] The million ton-mile measure is a common metric integral to prior 
capability studies that defines and quantifies airlift requirements as 
a basis for computing the size and optimal mix of airlift forces. 

[4] Mission capable rate is a measure of an aircraft's readiness to 
perform its missions. 

[5] Two C-5As were later modified to carry National Aeronautics and 
Space Administration components and other outsized cargo and were 
redesignated C-5Cs. 

[6] Throughput is defined as the amount of work that can be performed 
or the amount of output that can be produced by a system or component 
in a given period of time. For airlifters, it refers to the amount of 
freight or passengers that can be carried by an aircraft during a 
specified time period. 

[7] National Defense Authorization Act for Fiscal Year 2008, Pub. L. 
110-181, § 1046 (2008). 

[8] 10 U.S.C. § 2433 establishes the requirement for unit cost reports. 
If certain cost thresholds are exceeded (known as unit cost or Nunn- 
McCurdy breaches), DOD is required to report to Congress and, in 
certain circumstances, certify the program to Congress. 

[9] Pub. L. No. 110-417, § 1501(b) (2008). 

[10] GAO, Defense Transportation: DOD Should Ensure that the Final Size 
and Mix of Airlift Force Study Plan Includes Sufficient Detail to Meet 
the Terms of the Law and Inform Decision Makers, [hyperlink, 
http://www.gao.gov/products/GAO-08-704R] (Washington, D.C.: Apr. 28, 
2008). 

[11] GAO, Defense Transportation: Study Limitations Raise Questions 
about the Adequacy and Completeness of the Mobility Capability Study 
and Report, [hyperlink, http://www.gao.gov/products/GAO-06-938] 
(Washington, D.C.: Sept. 20, 2006). 

[12] John Warner National Defense Authorization Act for Fiscal Year 
2007, Pub. L. No. 109-364, § 132 (2006). 

[13] National Defense Authorization Act for Fiscal Year 2004, Pub. L. 
No. 108-136, § 132 (2003). 

[14] Our prior research has identified a number of practices for 
effective program cost estimating. We have issued guidance that 
associates these practices with four characteristics of a reliable cost 
estimate--well documented, comprehensive, accurate, and credible. GAO, 
Cost Assessment Guide: Best Practices for Estimating and Managing 
Program Costs, Exposure Draft, GAO-07-1134SP (Washington, D.C.: July 
2007). 

[15] This is a different situation than that experienced by Lockheed 
Martin when it shut down and later restarted the C-5 production line. 
When the C-5A line was closed in the 1970s, the company was able to 
move C-5 workers to the ongoing C-130 production line at the same 
facility. When the C-5B production line opened in the 1980s, company 
officials were able to bring many of those experienced workers back, 
thus minimizing hiring and training costs for the program. 

[16] GAO, Cost Assessment Guide: Best Practices for Estimating and 
Managing Program Costs - Exposure Draft, [hyperlink, 
http://www.gao.gov/products/GAO-07-1134SP] (Washington, D.C.: July 
2007). GAO was seeking input and feedback on the exposure draft from 
August 13, 2007, through July 14, 2008, which was during the time frame 
of our audit. GAO worked closely with experts throughout the cost 
community to develop the draft. 

[17] Institute for Defense Analysis: Review of Cost Estimates for the C-
5 Reliability Enhancement and Re-engining Program (RERP), IDA Paper P-
4336 (Alexandria, Va.: March 2008). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: