This is the accessible text file for GAO report number GAO-09-99 
entitled 'International Environmental Oversight: U.S. Agencies Follow 
Certain Procedures Required by Law, but Have Limited Impact' which was 
released on November 20, 2008.

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Chairman, Committee on Foreign Relations, U.S. Senate: 

United States Government Accountability Office: 
GAO: 

November 2008: 

International Environmental Oversight: 

U.S. Agencies Follow Certain Procedures Required by Law, but Have 
Limited Impact: 

GAO-09-99: 

GAO Highlights: 

Highlights of GAO-09-99, a report to the Chairman, Committee on Foreign 
Relations, U.S. Senate. 

Why GAO Did This Study: 

The World Bank Group lends about $40 billion annually to developing 
countries. Critics have claimed that some projects have harmed the 
environment and the local population. Title XIII of the International 
Financial Institutions Act of 1977 outlines in part the U.S. 
government’s requirements for reviewing potential environmental and 
social impacts of proposed multilateral development bank projects. GAO 
was asked to assess the U.S. government’s international environmental 
oversight efforts by examining (1) how U.S. agencies implement 
legislative requirements to review the potential environmental concerns 
associated with proposed World Bank Group projects, and (2) agencies’ 
ability to identify and address these concerns. GAO reviewed Title 
XIII, World Bank Group reports, and U.S. agency documents and met with 
representatives from U.S. government agencies, the World Bank Group, 
and nongovernmental organizations. 

What GAO Found: 

U.S. agencies take various approaches to meet legal requirements for 
reviewing World Bank Group proposals likely to have significant adverse 
environmental impacts. The Treasury Department (Treasury), which leads 
these efforts, generally focuses on fulfilling the law’s largely 
procedural requirements, such as ensuring that the project’s 
environmental assessment is made publicly available by the project 
sponsor 120 days before it is voted on by the Group’s board. The 
reviews usually occur from 1 to 3 weeks prior to such a vote. Treasury 
also engages in required consultations by leading a weekly interagency 
working group. Some participants stated that, because of limited time 
and the volume of proposals, they rely on Treasury to identify 
proposals of concern to facilitate the discussions. However, Treasury 
has not routinely done so. For a selected few projects, Treasury and 
the U.S. Agency for International Development analyze in more depth a 
proposal’s potential environmental and social impacts. Both agencies 
learn about many such projects through regular interaction with 
nongovernmental organizations. 

Figure: Timeline of Events Related to U.S. Government Review of 
Proposed World Bank Group Projects: 

[Refer to PDF for image] 

This figure contains a timeline depicting the following information: 

* 120 days before board vote: U.S. government cannot support project 
unless environmental assessment is disclosed 120 days before the World 
Bank Group board vote; 

* 1-3 weeks before board vote: Project notification and Treasury 
review; 

* ~1 week before interagency meeting: Interagency meeting agenda sent 
out by Treasury; 

* ~1 week before board vote: Interagency meeting/consultation; 

* World Bank Group board vote. 

Source: GAO analysis of Department of Treasury data. 

[End of figure] 

Time constraints limit the U.S. government’s ability to identify 
environmental and social concerns associated with World Bank Group 
projects before a vote on the proposal, and projects with potentially 
significant adverse impacts proceed with or without U.S. government 
support. The compressed review time frame makes it difficult for U.S. 
officials to examine proposal documentation and solicit information 
from knowledgeable parties (see fig.) In addition, by the time of the 
vote, a project is often already in its final design stage or even 
under construction, which limits U.S. agencies’ ability to identify 
ways to mitigate the concerns. Furthermore, proposals with potentially 
significant adverse impacts proceed with or without U.S. government 
support. The board consistently approves proposals that lack U.S. 
support; between January 2004 and May 2008, all 34 of the proposals the 
United States did not support because they did not meet legislative 
requirements were still approved by the board. Finally, the U.S. 
government occasionally supports proposals with significant 
environmental impacts, due to competing priorities, including economic 
and other considerations. 

What GAO Recommends: 

To maximize interagency contributions to evaluating World Bank Group 
proposals, GAO recommends that the Secretary of the Treasury routinely 
identify all proposals of concern in advance of interagency working 
group meetings. Treasury agreed with the recommendation, whereas USAID 
suggested that it may warrant further guidance to more clearly address 
short lead times. 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-09-99]. For more 
information, contact Thomas Melito, 202-512-9601, melitot@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

U.S. Agencies Take Various Approaches to Meet Legal Requirements for 
Reviewing World Bank Group Proposals Likely to Impact the Environment: 

U.S. Government Ability to Identify Environmental Concerns Is Limited, 
and World Bank Group Projects with Potentially Significant Adverse 
Impacts Proceed with or without U.S. Government Support: 

Conclusion: 

Recommendation for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: Comments from the Department of the Treasury and GAO's 
Evaluation: 

Appendix III: Comments from the United States Agency for International 
Development and GAO's Evaluation: 

Appendix IV: GAO Contact and Staff Acknowledgments: 

Table: 

Table 1: World Bank Group Project Categories Based on Potential 
Environmental Impact: 

Figures: 

Figure 1: Timeline of Events Related to U.S. Government Review of 
Proposed World Bank Group Projects: 

Figure 2: Number of World Bank Group Proposals That Treasury Has not 
Supported due to Lack of Compliance with the Pelosi Amendment, January 
2004 through May 2008: 

Abbreviations: 

CEQ: Council on Environmental Quality: 

EIA: Environmental Impact Assessment: 

EPA: Environmental Protection Agency: 

IBRD: International Bank for Reconstruction and Development: 

IDA: International Development Association: 

IFC: International Finance Corporation: 

MIGA: Multilateral Investment Guarantee Agency: 

NEPA: National Environmental Policy Act of 1969, as amended: 

Title XIII: Title XIII of the International Financial Institutions Act 
of 1977, as amended: 

USAID: U.S. Agency for International Development: 

[End of section] 

United States Government Accountability Office:
Washington, DC 20548: 

November 20, 2008: 

The Honorable Joseph R. Biden, Jr. 
Chairman: 
Committee on Foreign Relations United States Senate: 

Dear Mr. Chairman: 

The World Bank Group[Footnote 1] lends about $40 billion annually to 
developing countries, and while its projects can provide significant 
benefits, some, particularly those involving natural resource 
management, rural development, energy, and other infrastructure 
projects, can adversely impact the physical environment and the lives 
of indigenous people in the project area. Critics of the World Bank 
Group, as well as oversight entities within the World Bank Group, have 
claimed that many of these projects have harmed the environment and the 
local population. For example, some road projects have led to 
deforestation caused by clear-cutting, and artificial lakes created by 
large dam projects have forced thousands of local inhabitants to leave 
their homes and communities and resettle elsewhere. In 1989, the World 
Bank established policies that require project sponsors to prepare 
assessments that would identify environmental and social impacts 
associated with the projects it finances. The World Bank Group also 
established policies guiding the disclosure of this information to the 
public. However, concerns persist about the implementation of these 
policies as well as the quality of the environmental assessments 
associated with the projects. For example, according to a 2008 World 
Bank Group Internal Evaluations Group report, World Bank Group staff 
have not consistently applied its environmental assessment standards 
across regions and countries, partly due to unclear guidance. 

Title XIII of the International Financial Institutions Act of 1977, as 
amended (Title XIII) outlines the U.S. government's basic requirements 
for reviewing the potential environmental and social impacts of 
proposed multilateral development bank projects, including those of the 
World Bank Group. This legislation was enacted to strengthen the 
environmental performance of multilateral development banks, which 
includes promoting the use of environmental assessments to identify and 
address harmful environmental and social impacts of multilateral 
development bank projects. It requires, in part, that the U.S. 
government review proposed World Bank Group and other multilateral 
development bank-funded projects with the potential for such impacts. 
To do so, U.S. government agencies examine project-specific 
environmental assessments prior to project approval and ensure that 
these assessments were made available to the public by the project 
sponsors at least 120 days before the project is voted on by the World 
Bank Group Board of Directors. The Department of the Treasury 
(Treasury) instructs the U.S. Executive Director on the U.S. position 
for each proposed project based on its review; the legislation 
specifically precludes the U.S. Executive Director from supporting 
projects that do not meet the 120-day public disclosure requirement. 

For this report, you asked us to assess (1) how U.S. agencies implement 
their legislative requirements to review the potential environmental 
and social concerns associated with proposed World Bank Group projects, 
and (2) agencies' ability to identify and address these concerns. 
Although this legislation applies to all multilateral development 
banks, we have limited the scope of our review to the World Bank Group 
organizations because their environmental policies are generally 
considered to be international good practice among multilateral 
organizations and private-sector entities. Also, this report is the 
first in a two-part review: it focuses on U.S. government oversight of 
the World Bank Group's environmental assessment processes; the second 
report will focus on World Bank Group environmental assessment policies 
and their implementation. 

To address these objectives, we reviewed portions of Title XIII and its 
relevant amendments, as well as agency documents such as periodic 
reports to Congress and position papers. We also interviewed U.S. 
government officials from the Council on Environmental Quality, the 
Environmental Protection Agency (EPA), the U.S. Agency for 
International Development (USAID), and the Departments of Commerce, 
State, and the Treasury. In addition, we reviewed World Bank Group 
reports and studies and interviewed relevant World Bank Group officials 
from the International Bank for Reconstruction and Development (IBRD), 
the International Development Association (IDA), the International 
Finance Corporation (IFC), and the Multilateral Investment Guarantee 
Agency (MIGA), as well as environmental experts from nongovernmental 
organizations, and the private sector. 

We conducted this performance audit from October 2007 to November 2008, 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. Appendix I provides detailed 
information on our methodology. 

Results in Brief: 

U.S. agencies take various approaches to meet legal requirements for 
reviewing World Bank Group proposals likely to have significant adverse 
environmental and social impacts. Treasury, which leads these efforts, 
reviews proposals that it determines are likely to have significant 
adverse environmental and social impacts. These reviews are generally 
focused on fulfilling requirements in the law, which are largely 
procedural, such as ensuring that sponsors of World Bank Group projects 
make environmental assessments publicly available 120 days before a 
vote by the World Bank Group's Board of Directors. The reviews 
generally occur anywhere from 1 to 3 weeks prior to board vote. 
Treasury also engages in required interagency consultations by leading 
a weekly interagency working group. Officials from some of the 
participating agencies stated that because of the volume of proposals 
to review and the short time span in which to discuss them, they rely 
on Treasury to identify proposals of concern to facilitate the 
discussions. However, Treasury has not routinely done so. For example, 
of over 95 project proposals in 2007 categorized by the World Bank 
Group as being likely to have significant adverse environmental 
impacts, Treasury identified only 14 in advance of the interagency 
meeting. For a selected few controversial projects, USAID and Treasury 
analyzed in more depth the potential environmental and social impacts. 
Because they have different statutory responsibilities and flexibility 
within their statutory requirements, the agencies conduct the reviews 
and apply criteria differently. Both agencies learn about many such 
projects through regular interaction with nongovernmental 
organizations. 

Time constraints limit the U.S. government's ability to identify 
environmental and social concerns associated with World Bank Group 
projects before the Group's board votes on them, and projects with 
significant adverse impacts proceed with or without U.S. government 
support. The compressed time frame between World Bank Group 
notification of projects, interagency meetings to discuss the projects, 
and the board vote date makes it difficult for U.S. agency officials to 
review project documentation and solicit information from knowledgeable 
parties. In addition, by the time a project is ready for a board vote, 
it is often already in its final design stage or, in some cases, under 
construction, which limits U.S. agencies' ability to identify ways to 
mitigate environmental and social issues associated with these 
projects. For example, construction on a mine project in Guatemala 
began a month before it received approval for IFC financing. 
Furthermore, the World Bank Group consistently approves projects with 
potentially significant adverse impacts without U.S. government 
support; between January 2004 and May 2008, all 34 of the projects the 
U.S. Executive Director did not support because they did not meet the 
law's public disclosure requirements were still approved by the board 
of directors and moved forward.[Footnote 2] In addition, the U.S. 
government occasionally supports projects with significant adverse 
environmental impacts, due to competing priorities. For example, when 
reviewing an environmental assessment and associated documentation for 
a hydroelectric project in Uganda, USAID and EPA raised environmental 
concerns and recommended that Treasury instruct the U.S. Executive 
Director not to support the project, but Treasury ultimately supported 
the project with State's concurrence due to a balance of economic and 
other considerations and a belief that potential impacts can be 
mitigated. 

To improve U.S. agencies' ability to effectively contribute to the 
interagency effort to evaluate World Bank Group proposals that are 
likely to have significant adverse environmental and social impacts, we 
are recommending that the Secretary of the Treasury, in his capacity as 
the chair of the Working Group on Multilateral Assistance, routinely 
identify all proposals of concern in advance of working group meetings 
with other agencies in order to maximize the ability of all 
participants to contribute to the evaluation of World Bank Group 
proposals. 

In commenting on a draft of this report, Treasury agreed with the 
recommendation and noted in technical comments submitted separately 
that it is already taking a number of measures to comply with the 
recommendation. We also incorporated Treasury's technical comments as 
appropriate in the report. Treasury disputed our finding that their 
efforts have had little impact, because they believed we did not 
adequately note Treasury's behind the scenes efforts to influence 
project design. While we have added language to the report to reflect 
some of these efforts, Treasury did not provide us with information to 
gauge the impact of these communications. Treasury also believed that 
we characterized the interagency process as limited to weekly meetings. 
While we disagree with Treasury's interpretation, we added language to 
clarify the extent of interagency communication. In its comments on the 
draft report, USAID suggested that the recommendation may warrant 
further guidance to more clearly address very short lead times. It also 
noted that sections of Title XIII, such as those calling for a system 
for information exchange with other interested member countries, were 
not addressed in the report. These sections were not addressed because 
we focused the scope of our review on those sections of Title XIII that 
directly addressed U.S. government oversight of the potential 
environmental and social concerns associated with proposed World Bank 
Group projects. USAID made additional comments on more specific topics, 
which we address more fully in the agency comments section of this 
report. 

Background: 

The World Bank Group's member countries collectively determine policy 
and make investment decisions. Its board of directors is made up of 24 
executive directors who represent all 185 member countries.[Footnote 3] 
The U.S. Executive Director is the main liaison between the United 
States and the World Bank Group. Treasury has the lead role in working 
with the U.S. Executive Director to determine the U.S. position on 
proposed World Bank Group projects. As a member country of the World 
Bank Group, the United States may support, abstain from voting, or vote 
against a proposed project. However, no single member country can veto 
a proposed project. 

In 1989, the World Bank established social and environmental 
guidelines, or Safeguard Policies, to identify and address potentially 
significant negative environmental and social impacts. In 2006, IFC 
developed its own distinct performance standards for assessing the 
environmental and social impact of its projects, and MIGA introduced 
its own standards, which were largely based on IFC's, in 2007. The 
World Bank, IFC, and MIGA have also established policies guiding the 
disclosure of project information to the public. IFC and MIGA 
guidelines state that proposed project documents, including 
environmental assessments, should be released 60 days prior to a board 
vote on projects with potential, significant adverse impacts. The World 
Bank disclosure guidelines do not specify a number of days. 

World Bank Group entities screen project proposals for potential 
environmental impacts and assign one of four categories to determine 
the type of environmental assessment needed. See table 1. 

Table 1: World Bank Group Project Categories Based on Potential 
Environmental Impact: 

Category: A; 
Definition: Projects with potential, significant adverse impacts that 
are diverse, irreversible, or unprecedented; 
Examples: Large dams, mining activities, new roads; 
Environmental Assessment (EA) requirements: Requires full EA. 

Category: B; 
Definition: Projects with potential, limited adverse impacts that are 
few in number, site-specific, largely reversible, and readily addressed 
through mitigation measures; 
Examples: Rural electrification, smaller scale irrigation, 
rehabilitation, and maintenance projects; 
Environmental Assessment (EA) requirements: Requires less comprehensive 
EA. 

Category: C; 
Definition: Projects that are expected to have minimal or no adverse 
impacts; 
Examples: Health, education, and family planning projects; 
Environmental Assessment (EA) requirements: No EA required. 

Category: FI; 
Definition: Projects in which funds are channeled through a financial 
intermediary; 
Examples: Support to a local development investment fund to finance 
municipal infrastructure; 
Environmental Assessment (EA) requirements: No EA required. 

Source: GAO analysis of World Bank Group documents. 

[End of table] 

Title XIII outlines the U.S. government's basic requirements for 
reviewing the potential environmental and social impacts of proposed 
multilateral development bank projects, including those of the World 
Bank Group. The overall purpose of the legislation is to ensure that 
U.S. assistance to multilateral development banks promotes sustainable 
use of natural resources and the protection of the environment, public 
health, and the status of indigenous people in developing countries. In 
1989, Congress amended Title XIII to include Section 1307, commonly 
referred to as the Pelosi Amendment. The Pelosi Amendment directly 
affects whether the U.S. government will support a proposed project. It 
directs the U.S. government to ensure that a proposed project with 
potentially significant negative impacts meets certain requirements, 
such as making publicly available an assessment of the project's 
environmental impact 120 days before the World Bank Group's Board of 
Directors votes on the project. If the World Bank Group's project 
sponsor does not make the assessment or a summary of the assessment 
publicly available within this time frame, the law instructs the U.S. 
government not to vote in favor of the proposal. The law also requires 
that the assessment include an analysis of the project's cumulative and 
associated impacts, as well as alternatives to the proposed project. As 
a result of the Pelosi Amendment, the World Bank Group and other major 
multilateral development banks began requiring project sponsors to 
prepare environmental impact assessments and make them available to 
affected groups, according to representatives from U.S. government 
agencies and nongovernmental organizations, as well as a 1998 U.S. 
Congressional Research Service report determining the impact of the 
Pelosi Amendment.[Footnote 4] 

Both the Pelosi Amendment and other sections of Title XIII specify the 
responsibilities of several U.S. agencies in monitoring proposed 
multilateral development bank projects with the potential for 
significant environmental and social impacts. As the lead U.S. agency 
interacting with the multilateral development banks, Treasury is to 
take the following actions: 

* ensure that an environmental impact assessment or a comprehensive 
summary accompanies project proposals, 

* consult with and consider recommendations from other federal agencies 
and interested members of the public regarding this assessment, 

* determine whether an environmental assessment has been made publicly 
available at least 120 days prior to the board vote on the proposal, 

* instruct the U.S. Executive Director on the U.S. position for each 
proposed project, 

* consult with other U.S. agencies to develop environmental impact 
review procedures for proposed multilateral development bank projects 
and assist in implementing these procedures,[Footnote 5] and: 

* provide an annual report to Congress on the environmental 
sustainability of multilateral development banks' operations and the 
efficacy of U.S. efforts in this process. 

Title XIII also requires USAID to work with Treasury and the Department 
of State (State) to analyze, where feasible, the environmental, social, 
and other[Footnote 6] impacts of proposed multilateral development bank 
projects "well in advance" of the projects' board vote date, and to 
ensure that investigations are undertaken for proposals that are likely 
to have substantial adverse impacts. USAID is also required to provide 
its own report to Congress that identifies proposals likely to have 
adverse impacts on the environment, natural resources, public health, 
or indigenous peoples. State and Treasury are to work with USAID to 
vigorously promote mechanisms to strengthen the environmental 
performance of multilateral development banks. 

U.S. Agencies Take Various Approaches to Meet Legal Requirements for 
Reviewing World Bank Group Proposals Likely to Impact the Environment: 

Treasury addresses Pelosi Amendment requirements for assessing World 
Bank Group projects by conducting reviews that focus on procedural 
requirements such as whether the project's environmental assessment is 
made publicly available by the project sponsor 120 days before the 
World Bank Group's board vote date. Treasury also engages in required 
interagency consultations by leading a weekly interagency working 
group. However, Treasury does not always identify projects with 
potentially significant environmental and social impacts in advance of 
the interagency meetings, making it difficult for participants to 
provide effective input. Because they have different responsibilities 
and flexibility within their statutory requirements, USAID and Treasury 
take different approaches to analyzing in more depth the environmental 
and social impacts of a few controversial projects. The agencies learn 
about many such projects through regular interaction with 
nongovernmental organizations. 

Treasury Addresses Pelosi Amendment Requirements by Conducting 
Procedural Reviews and Engaging in Interagency Consultations: 

Treasury Reviews of World Bank Group Projects Generally Focus on 
Procedural Requirements: 

As required by the Pelosi Amendment, Treasury conducts reviews of 
environmental documentation for World Bank Group proposals that could 
have significant environmental or social impacts. Treasury's efforts 
generally focus on fulfilling the requirements of the legislation, 
which are largely procedural; specifically, Treasury staff review 
documentation on World Bank Group projects to ensure that procedural 
requirements specified in the legislation are met. These requirements 
include ensuring that an environmental impact assessment or a 
comprehensive summary of the assessment is made publicly available 120 
days prior to the World Bank Group's Board of Executive Directors vote 
date[Footnote 7] and that the summary contains items such as 
discussions of alternatives to the proposed project and the project's 
direct and indirect environmental impacts. A Treasury Department 
official who reviews project documentation stated that the review 
process involves attempting to ascertain the actual disclosure date, 
which is not necessarily the date or dates listed on the documents. 
[Footnote 8] The Treasury reviews generally take place once the World 
Bank Group's Board of Executive Directors schedules a vote for the 
proposed project. In practice, this can be anywhere from 1 to 3 weeks 
prior to the scheduled vote date. In calendar year 2007, Treasury 
officials estimated that they reviewed over 95 projects that they 
determined could have significant environmental or social impacts. 
[Footnote 9] 

The Pelosi Amendment requires that Treasury consider, among other 
things, associated and cumulative environmental impacts in its review 
of World Bank Group project documentation but does not specify what 
criteria should be used to determine these considerations. As a result, 
one Treasury economist said she uses professional judgment to determine 
if the evidence "seems reasonable" when reviewing environmental 
assessments for compliance with the Pelosi Amendment's requirement 
regarding associated and cumulative environmental impacts. Since the 
amendment does not require Treasury to review proposals to determine if 
they meet the World Bank Group's environmental and social safeguard 
policies, Treasury generally does not evaluate proposals for compliance 
with these policies. Treasury officials stated that they do not do this 
because the multilateral development banks have their own procedures, 
staff, and accountability mechanisms for ensuring compliance with bank 
policies. Treasury officials noted that they occasionally may closely 
review the analysis contained in the environmental assessment or other 
project documentation if they have concerns about the environmental and 
social impact of the project. However, these officials told us that 
they rarely instruct the U.S. Executive Director not to support a 
proposal because of deficiencies with the assessment's technical 
analysis.[Footnote 10] 

Because Treasury is only required by law to review proposals on which 
the World Bank Group board votes, a subset of proposals, specifically, 
umbrella proposals, are not always reviewed by Treasury for compliance 
with the Pelosi Amendment. These proposals, which are presented to the 
World Bank Group's board for approval, contain an environmental 
assessment that represents a framework for multiple sub-projects. 
Although the board must approve the proposal as a whole, future sub- 
projects--some of which could have significant adverse impacts--are not 
subject to board approval. Since the board does not vote on 
subprojects, the Pelosi Amendment does not require Treasury to review 
them. Instead, Treasury reviews these types of proposals on a case-by- 
case basis. According to Treasury officials, they use professional 
judgment to determine if the intended sub-projects are likely to have 
significant adverse environmental and social impacts and, therefore, 
whether they review environmental documents associated with the sub- 
projects. 

Treasury reports its findings to Congress, as required by law,[Footnote 
11] but does not provide these reports in a timely manner. Federal law 
requires Treasury to provide an annual report to Congress summarizing 
the environmental performance of the multilateral development banks, 
including the World Bank Group. Treasury's most recent report is for 
fiscal year 2005. Treasury officials told us in October 2007 and again 
in August 2008 that they were still preparing the report for fiscal 
year 2006. 

Treasury Engages in Interagency Consultations to Address Pelosi 
Amendment Requirements: 

Treasury addresses the Pelosi Amendment's requirement that it consult 
with other agencies[Footnote 12] by leading an interagency working 
group on multilateral assistance that meets once a week for about an 
hour to discuss U.S. agencies' concerns regarding proposed World Bank 
Group projects. This group discusses political, economic, 
environmental, social, and other concerns related to proposed 
multilateral development bank projects, including those of the World 
Bank Group.[Footnote 13] The purpose of these discussions is to solicit 
agency input as to whether Treasury should instruct the U.S. Executive 
Director to support the projects. In addition to Treasury, State, 
USAID, and the Commerce Department are regular participants at the 
meeting. Other agencies such as EPA have attended in the past. 

According to participants, the volume of proposals and brief discussion 
time at the working group meetings has limited the quality of 
discussion on proposals with potentially significant environmental and 
social impacts. Approximately 1 week prior to each working group 
meeting, Treasury distributes an agenda containing a list of all 
multilateral development bank proposals that are scheduled for a vote 
over the next several weeks. The number of proposals to be discussed in 
the hour-long meeting each week varies, averaging about 60, but in some 
weeks, such as near the end of the World Bank Group's fiscal year, it 
has been about 150. Treasury officials told us they assume the agencies 
will review the proposals in advance and inform Treasury of any 
concerns they may have. They said that if an agency does have an issue 
with a proposal, Treasury staff will informally discuss the concern 
with the agency and attempt to resolve it prior to the meeting. 
Officials from participating agencies we met with stated that because 
of the volume of proposals to review and the short time span in which 
to discuss them, they rely on Treasury to identify in the meeting 
agenda proposals that it believes to be of concern, to facilitate the 
discussion. However, Treasury has not routinely done so. For example, 
of over 95 World Bank Group proposals in 2007 considered by Treasury as 
being likely to have significant adverse environmental impacts, the 
agency identified only 14 in the agendas it sent out in advance of the 
working group meetings. Treasury officials stated that, given all their 
other responsibilities and limited resources, they had not been focused 
on identifying proposals likely to have significant adverse 
environmental impact for the weekly working group meeting agendas. 

USAID and Treasury Analyze a Selected Few Controversial Projects in 
More Depth, and Learn about Many Such Projects through Regular 
Interaction with Nongovernmental Organizations: 

USAID and Treasury Are Governed by Different Statutory Responsibilities 
for Analyzing the Impacts of Controversial Projects: 

Title XIII does not specify a particular process that USAID and 
Treasury should use when considering environmental assessments, and the 
agencies use different standards when assessing the sufficiency of 
environmental impact assessments. Though USAID and Treasury are charged 
with different statutory responsibilities, each agency may evaluate 
environmental impact assessments on proposed projects during its review 
process. Neither federal law nor agency regulations specify one 
standard to be used across the federal government when considering 
proposals or environmental impact assessments. 

Section 1303 of Title XIII requires USAID to ensure that other U.S. 
agencies and overseas USAID missions analyze, where feasible, the 
environmental impacts of multilateral development loans well in advance 
of the loans' approval to determine whether the proposals will 
contribute to the sustainable development of the borrowing country. 
USAID is also required to ensure that investigations of proposed 
projects with "substantial adverse impacts" are conducted. Because the 
law contains no prescriptive requirements for how to ensure that 
investigations of projects with likely substantial adverse impacts are 
conducted, USAID has taken various approaches to fulfilling this 
requirement. In previous years, the agency conducted a brief annual 
review of a large number of proposed projects; in contrast, its current 
approach is to conduct a thorough analysis of a much smaller number of 
proposed projects. For example, USAID's 1999 report to Congress briefly 
highlighted environmental concerns in 29 projects. In contrast, the 
latest report, from April 2008, provides an in-depth analysis of nine 
projects. 

According to the official responsible for conducting the 
investigations, USAID reviews the project's environmental assessment, 
as well as related studies, such as the environmental management plan. 
To perform its analyses, USAID employs a technical expert, who 
evaluates proposals' environmental and social impacts against USAID 
standards as well as other guidance, such as that developed by the 
Council on Environmental Quality (CEQ).[Footnote 14] This technical 
expert told us she uses certain criteria when determining whether a 
proposed project should be investigated and applies them at her 
discretion. These criteria include, among others, the significance and 
potential of adverse cumulative impacts, the ability of the proposal to 
serve as a model for similar proposals within a particular sector, and 
the potential for the proposal to undermine USAID's sustainable 
development activities. USAID may also perform site visits to the 
proposed project location. During these visits, USAID and other U.S. 
government officials, including those from Treasury and State, may meet 
with stakeholders such as the project sponsor, World Bank Group staff, 
host-country government officials, and local communities affected by 
the proposal. In addition, USAID may continue to monitor and report on 
the project if the World Bank Group board approves it once financing 
and construction begin. 

Treasury, in determining the U.S. position on proposed actions to be 
taken by the World Bank Group, is required to develop and prescribe 
procedures that consider environmental impact assessments, the 
interagency and public review of these assessments, and other 
environmental reviews and consultations required by law. Treasury 
issued regulations in 1992 to fulfill this requirement; however, the 
regulations do not specify criteria to be used in the interagency 
process that measure the sufficiency of the environmental assessments. 
While these regulations address how Treasury will instruct the U.S. 
Executive Director to proceed at the World Bank Group when an 
environmental analysis is determined to be insufficient, the 
regulations do not identify a set of criteria or standard against which 
to measure sufficiency. While USAID uses guidance and regulations 
issued by the Council for Environmental Quality when reviewing 
different aspects of environmental assessments, Treasury often uses 
internal requirements issued by the World Bank. 

Although not required to do so by law, Treasury occasionally conducts 
additional, more in-depth investigations of a few World Bank Group 
proposals that it determines to be controversial, such as mining or oil 
and gas projects, or that present opportunities for reducing adverse 
impacts.[Footnote 15] Unlike its more procedural reviews of proposals 
for compliance with the Pelosi Amendment, Treasury officials said they 
may evaluate these proposals' documentation for compliance with the 
multilateral development banks' internal requirements for assessing 
environmental and social impacts.[Footnote 16] However, they do not 
necessarily determine, for example, whether the World Bank's "good 
practices" have been followed. The World Bank's good practices, 
compiled in its Environmental Assessment Sourcebook, give examples of 
practices that the World Bank considers models for project managers to 
emulate, such as establishing project supervision and monitoring 
programs.[Footnote 17] 

U.S. Government Agencies Focus Attention Predominantly on Projects 
Identified by Nongovernmental Organizations: 

According to officials from U.S. agencies, of the few proposed projects 
that Treasury and USAID select for in-depth analysis, many come to 
their attention through regular interaction with nongovernmental 
organizations. To foster dialogue with interested non-governmental 
organizations and to fulfill legislative requirements, Treasury and 
USAID meet with nongovernmental organizations in a forum commonly 
referred to as the Tuesday Group, since it generally meets on the first 
Tuesday of each month.[Footnote 18] At this forum, the agencies often 
obtain leads on potentially controversial projects through discussions 
of planned and ongoing multilateral development bank projects that may 
have significant adverse environmental and social impacts. 

In mid-2008, Treasury informally proposed changing the structure of 
these meetings. Specifically, Treasury's proposal establishes a 
steering committee consisting of a representative from Treasury, USAID, 
and two nongovernmental organizations[Footnote 19] for the purpose of 
reviewing and selecting submitted discussion topics for subsequent 
meetings, which would then focus the discussion on those issues that 
the steering committee identifies. Treasury officials said that this 
proposal is meant to make the meetings more efficient, since the 
officials have many responsibilities and can devote only a small share 
of their time to assessing the environmental impacts of multilateral 
development bank projects. We discussed this proposal with the Bank 
Information Center in September 2008; the Center and Treasury are 
considering a compromise proposal that would have an agreed-upon agenda 
while setting aside some time for open-ended discussion.[Footnote 20] 

U.S. Government Ability to Identify Environmental Concerns Is Limited, 
and World Bank Group Projects with Potentially Significant Adverse 
Impacts Proceed with or without U.S. Government Support: 

Time constraints limit the U.S. government's ability to identify the 
environmental and social concerns associated with World Bank Group 
projects before the World Bank Group board votes on them, and projects 
with potentially significant adverse impacts proceed with or without 
U.S. government support. By the time a project is ready for board vote, 
it is often in its final design stage or, in some cases, already under 
construction, which limits U.S. agencies' ability to identify ways to 
mitigate environmental and social issues associated with the project. 
Furthermore, the World Bank Group consistently approves projects with 
potentially significant adverse impacts without U.S. government 
support; between January 2004 and April 2008, all 34 of the projects 
the U.S. Executive Director did not support because they did not meet 
the Pelosi Amendment requirements were still approved by the World Bank 
Group's Board of Directors and moved forward. In addition, the U.S. 
government occasionally supports projects with significant 
environmental impacts, due to competing priorities and a belief that 
potential impacts can be mitigated. 

The U.S. Government's Ability to Identify Environmental and Social 
Issues Associated with Most World Bank Group Projects Is Limited by 
Review Time Frames: 

Officials from agencies that participate in the interagency working 
group told us that they usually do not have sufficient time to identify 
environmental and social issues associated with projects in the few 
weeks encompassing the World Bank Group's notification of a proposed 
project scheduled for a vote, the working group meeting at which the 
project could be discussed, and the date the board votes on the 
project. Figure 1 shows the timeline of events related to the U.S. 
government's review of proposed World Bank Group projects. 

Figure 1: Timeline of Events Related to U.S. Government Review of 
Proposed World Bank Group Projects: 

[Refer to PDF for image] 

This figure contains a timeline depicting the following information: 

* 120 days before board vote: U.S. government cannot support project 
unless environmental assessment is disclosed 120 days before the World 
Bank Group board vote; 

* 1-3 weeks before board vote: Project notification and Treasury 
review; 

* ~1 week before interagency meeting: Interagency meeting agenda sent 
out by Treasury; 

* ~1 week before board vote: Interagency meeting/consultation; 

* World Bank Group board vote. 

Source: GAO analysis of Department of Treasury data. 

[End of figure] 

Treasury officials said that they are notified about projects when they 
receive a project appraisal document, which describes the project and 
is what the board reviews when it votes on a project. They said they 
generally receive this document about 1 to 3 weeks before the board is 
scheduled to vote on the project.[Footnote 21] They then put these 
projects on the working group meeting agenda. The working group 
meetings generally take place approximately 1 or 2 weeks before the 
board votes on projects, and Treasury e-mails a list of projects and 
estimated board vote dates to relevant U.S. agencies about 1 week 
before each meeting. State and USAID officials noted that this 
compressed time frame makes it difficult to review project 
documentation and solicit input from relevant officials from other 
offices within their agencies. Furthermore, USAID staff in countries 
where projects are being proposed have limited time to review project 
documentation because they do not have access to the necessary project 
documents and depend on staff in Washington to make this information 
available to them, according to USAID officials. Even when U.S. 
agencies are able to identify project-related issues, the U.S. 
government has little time to discuss these issues with the World Bank 
Group. USAID officials stated that project stakeholders are unlikely to 
alter the project without sufficient time for discussion before a vote. 
[Footnote 22] 

Even when agencies can identify issues before the board vote, the 
project is often in its final design stage or, in some cases, already 
under construction, so the extent to which the World Bank Group can 
mitigate the issues is limited. Treasury officials stated that there is 
little opportunity to influence project design once the World Bank 
Group has released the project appraisal document shortly before the 
board votes on the project. In addition, an April 2008 USAID report to 
Congress stated that there are inadequate opportunities to identify, 
avert, or mitigate adverse environmental and social impacts associated 
with the projects even when the multilateral development banks release 
the environmental documents 120 days before the board votes, as the 
Pelosi Amendment requires. In some instances, projects may already be 
under construction. For example, construction began on an IFC-financed 
gold mine in Guatemala a month before the project went to the board for 
a vote,[Footnote 23] despite problems associated with the project, 
including inadequate consultations with the affected community and 
potential water contamination, according to a USAID report. In its 2005 
annual report to Congress, Treasury noted that, while the timeliness 
and quality of environmental impact assessments of World Bank Group 
projects had improved, the agency remained concerned about the need to 
determine appropriate interventions if projects had already begun 
construction or suffered from a legacy of unaddressed environmental 
damage. 

The World Bank Group Consistently Approves Projects That Lack U.S. 
Government Support: 

Since 2004, the World Bank Group has always approved proposals that 
lack U.S. support, even if they have potentially significant adverse 
environmental and social impacts. A lack of U.S. government support for 
proposals that do not comply with the Pelosi Amendment does not prevent 
the board from approving such proposals because one member country's 
vote cannot prevent approval. Between January 2004 and May 2008, 
[Footnote 24] all 34 of the proposed projects the U.S. Executive 
Director did not support because they did not meet the Pelosi Amendment 
requirements were still approved by the World Bank Group Board of 
Directors and moved forward. (See fig. 2 for the number of proposals 
Treasury has not supported due to lack of compliance with the Pelosi 
Amendment.) 

Figure 2: Number of World Bank Group Proposals That Treasury Has not 
Supported due to Lack of Compliance with the Pelosi Amendment, January 
2004 through May 2008: 

[Refer to PDF for image] 

This figure illustrates the following information, using interlocking 
circles: 

About 180 World Bank Group Category A proposed projects; 

23 Category A proposed projects: 
Treasury may review for compliance with the Pelosi Amendment proposed 
projects that are classified by the World Bank Group as Category A—that 
is, likely to have significant adverse environmental and social 
impacts. Of the approximately 180 proposed projects categorized as such 
from January 2004 through May 2008, Treasury identified 23 that did not 
meet the requirements of the Pelosi Amendment and recommended that the 
U.S. Executive Director abstain from voting for them. 

11 non-Category A proposed projects: 
Treasury may also review for compliance with the Pelosi Amendment 
proposed projects that are not classified by the World Bank Group as 
Category A, if it determines these proposed projects are still likely 
to have significant adverse environmental and social impacts. Because 
the agency does not maintain an ongoing database of its reviews, we 
could not obtain the exact number of these proposed projects. From 
January 2004 through May 2008, Treasury determined that 11 of these 
proposed projects did not meet the requirements of the Pelosi Amendment 
and recommended that the U.S. Executive Director abstain from voting 
for them. 

Source: GAO analysis of Department of Treasury and World Bank Group 
data. 

[End of figure] 

Treasury officials told us that overall U.S. interests are sometimes 
served when the board approves projects that the Pelosi Amendment 
prevents the United States from supporting. For example, in one case, 
the board approved a proposal for a development project in Iraq that 
the U.S. government would have otherwise wanted to support, but could 
not because it did not meet the amendment's 120-day disclosure 
deadline. 

Furthermore, once proposed projects are approved by the board, they are 
unlikely to be modified to address U.S. concerns about adverse 
environmental and social impacts. U.S. government officials informed us 
that changes are seldom made to a project as a result of the U.S. 
Executive Director not supporting it.[Footnote 25] According to 
Treasury officials, once the board has approved the proposal and the 
World Bank Group has funded the project, Treasury has little leverage 
in influencing any changes to mitigate adverse environmental or social 
impacts. 

The United States Occasionally Supports Projects with Significant 
Environmental Impacts, Due to Competing Priorities: 

In some cases, Treasury recommends that the U.S. Executive Director 
support projects with significant adverse impacts. Some U.S. agencies 
may want to oppose these projects because of environmental concerns, 
but Treasury sometimes recommends that the U.S. Executive Director vote 
in favor of the project if it determines that it is in compliance with 
the Pelosi Amendment and that potential impacts can be mitigated. As 
the lead U.S. agency in formulating the U.S. government's position on 
proposed multilateral development bank projects, Treasury's 
determination takes into account competing priorities--such as economic 
development--as well as environmental concerns and, therefore, does not 
always reflect consensus either among agencies or among units of the 
same agencies. For example, when reviewing an environmental assessment 
and associated documentation for a hydroelectric dam project in Uganda, 
USAID and EPA raised environmental concerns and recommended that 
Treasury instruct the U.S. Executive Director not to support the 
project. USAID and EPA officials opposed the project because, among 
other things, they believed the environmental analysis was incomplete 
and the analysis of the impact of the dam on endangered species was 
inadequate. However, Treasury ultimately supported the project due to 
economic considerations, having determined that the measures the 
project sponsor would take to mitigate the adverse impacts were 
sufficient. In its memo to instruct the U.S. Executive Director to 
support the project, Treasury stated that the project would help reduce 
Uganda's electricity shortage and, thereby, lower an obstacle to 
economic growth and development. State also ultimately supported the 
project because it brought an acceptable balance across multiple 
issues, including clean energy, economic development, and political 
support for the Ugandan government, according to State officials. 

We could not determine the extent to which the U.S. government balances 
competing priorities for projects with potentially significant adverse 
environmental and social impacts that are compliant with the Pelosi 
Amendment. Between January 2004 and July 2008, Treasury supported 17 
World Bank Group proposals for which it determined that significant 
environmental impacts would occur, but be mitigated. However, because 
Treasury does not generally write memos to the U.S. Executive Director 
for projects it supports, it does not maintain documentation to show to 
what extent other issues may have outweighed environmental and social 
concerns in these cases.[Footnote 26] Treasury officials responsible 
for conducting environmental reviews stated that for controversial 
projects, decisions are made by senior-level administration officials. 

Conclusion: 

Given the potential consequences of World Bank Group projects with 
significant environmental and social impacts, the overriding 
constraints posed by the World Bank Group's project development and 
approval process, and the restrictions the Pelosi Amendment imposes on 
the U.S. government's decision-making, U.S. agencies must coordinate 
efficiently to maximize their resources within the very limited time 
they have available to review upcoming projects. However, Treasury is 
not maximizing the effectiveness of a major mechanism for gathering 
interagency views on projects--the weekly interagency working group it 
leads. The working group meetings, which Treasury uses to meet its 
legal requirement to consult with other agencies on the possible 
impacts of World Bank Group proposals, are meant to provide an 
opportunity for all participants to utilize their expertise and discuss 
their perspectives and concerns as part of the vetting process to 
determine a U.S. position on the proposals. Prior to the meetings, 
Treasury's staff flag those projects that they believe have potentially 
significant environmental and social impacts. Treasury has not, 
however, been routinely passing this information on to the other 
participants of the working group in advance of group meetings. For 
example, Treasury only identified about 15 percent of such projects in 
working group agendas in 2007. Without this identification, working 
group agencies have been limited in their ability to effectively 
contribute to the interagency effort to evaluate proposed World Bank 
Group projects. 

Recommendation for Executive Action: 

In order to improve U.S. agencies' ability to effectively contribute to 
the interagency effort to evaluate World Bank Group proposals that are 
likely to have significant adverse environmental and social impacts, we 
recommend that the Secretary of the Treasury, in his capacity as the 
chair of the Working Group on Multilateral Assistance, routinely 
identify all proposals of concern in advance of working group meetings 
with other agencies in order to maximize the ability of all 
participants to contribute to the evaluation of World Bank Group 
proposals. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to Treasury and USAID for their 
review and comment. Treasury and USAID provided written comments, which 
are reprinted in appendix II and III respectively. Treasury also 
provided technical comments, which are incorporated as appropriate 
throughout the report. 

Treasury agreed with our recommendation and noted in its technical 
comments that it welcomes this recommendation and is already taking a 
number of measures to comply with it. Treasury also disagreed with two 
of our findings. First, Treasury disputed our finding that its efforts 
had little impact, because it believed we did not adequately note 
Treasury's behind the scenes efforts to influence project design. In 
response, we have added language to the report to reflect some of these 
efforts. However, Treasury did not provide us with information to gauge 
the impact of these communications and Treasury officials also told us 
they could not determine what impact these communications have on 
project design. Second, Treasury also believed that we characterized 
the interagency process as limited to weekly meetings. While we 
disagree with Treasury's interpretation, we added language to clarify 
the extent of interagency communication. 

In its comments, USAID suggested that the recommendation may warrant 
further guidance to more clearly address very short lead times for 
notice to other agencies. We did not, however, revise this 
recommendation because we believe it is up to Treasury to determine how 
best to implement the recommendation. USAID's comments also raised 
several issues, including that our report title was overly expansive. 
In response, we modified the title to clarify that the report addresses 
certain procedures required by U.S. law. USAID was also concerned that 
our report did not address all provisions in Title XIII, such as 
creating a system for information exchange with other interested member 
countries. These were not within the scope of this report because we 
focused our review on those sections of Title XIII that directly 
address U.S. government oversight of the potential environmental and 
social concerns associated with proposed World Bank Group projects. 
USAID was also concerned that we did not address whether Treasury has 
sufficient expertise to evaluate measures to mitigate environmental 
damage. However, it is beyond the scope of this report to determine 
whether mitigation measures have been effective; we anticipate 
addressing this issue in our next report, which will focus on project 
implementation. More detail on USAID's comments and our evaluation can 
be found in appendix III. 

We are sending copies of this report to interested congressional 
committees, the Secretary of the Treasury, and the Administrator of 
USAID. The report is available at no charge on the GAO Web site at 
[hyperlink, http://www.gao.gov]. 

If you or your staff have any questions about this report, please 
contact me at (202) 512-9601. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this report. GAO staff who made major contributions to this 
report are listed in appendix IV. 

Sincerely, 

Signed by: 

Thomas Melito: 
Director, International Affairs and Trade: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

Our objectives were to assess (1) how U.S. agencies implement their 
legislative requirements to review the potential environmental and 
social concerns associated with proposed World Bank Group projects, and 
(2) agencies' ability to identify and address these concerns. 

To assess how U.S. agencies implement their legislative requirements, 
we reviewed environmental legislation, including: Title XIII of the 
International Financial Institutions Act of 1977, as amended; the 
procedures for the environmental review of proposed projects of 
multilateral development banks in 31 C.F.R. Part 26; as well as the 
U.S. Agency for International Development's (USAID) Environmental 
Procedures contained in 22 C.F.R. Part 216. We also reviewed 
legislation governing U.S. environmental assessments, such as the 
National Environmental Policy Act of 1969 (NEPA) and Council on 
Environmental Quality Regulations for Implementing the Procedural 
Provisions of NEPA, 40 C.F.R. Parts 1500-1508; and, Council on 
Environmental Quality guidance on implementing 40 C.F.R. Part 1500- 
1508. To determine how agencies implement their legislative 
requirements, we interviewed U.S. government officials from the 
Environmental Protection Agency (EPA), USAID, and the Departments of 
State and the Treasury (Treasury), as well as expert staff from 
environmental non-governmental organizations. Because not every agency 
keeps complete records of its environmental oversight activities or has 
internal policies governing such actions, certain procedural 
documentation could not be provided. In such cases, we relied on agency 
officials' testimonial evidence. 

To examine agencies' ability to identify and address environmental 
concerns of proposed World Bank Group projects, we reviewed agency 
documents such as periodic reports to Congress, agency decision memos, 
and the U.S. government's voting record on World Bank Group proposals. 
We also interviewed U.S. government officials from EPA, USAID, and the 
Departments of Commerce, State, and Treasury. In addition, we 
interviewed relevant World Bank Group officials from the International 
Bank for Reconstruction and Development, the International Development 
Association, the International Finance Corporation, and the 
Multilateral Investment Guarantee Agency, as well as environmental 
experts from nongovernmental organizations, and the private sector. 

To determine the number of World Bank Group projects that the U.S. 
Executive Director abstained from voting on due to the requirements of 
the Pelosi Amendment, we collected data from Treasury on the U.S. 
Executive Director's voting record from January 2004 through May 2008. 
We also used these data to identify projects supported by the U.S. 
Executive Director that Treasury determined may have significant 
environmental impacts, but that the U.S. Executive Director supported 
based on Treasury's determination that such impacts have been addressed 
and mitigated in the design of the project. 

To assess the reliability of Treasury's data on the U.S. Executive 
Director's voting record, we (1) interviewed the Treasury official 
responsible for managing the team of analysts who record data on the 
status of multilateral development bank projects; and (2) reviewed the 
voting record data. During the course of our review, we identified 
incomplete data fields and manual data entry errors, such as duplicate 
entries of the same project. However, based on our intended use of the 
data--to identify how the U.S. Executive Director voted on particular 
World Bank Group projects--and the results of our assessment, we 
determined that the data provided were sufficiently reliable for the 
this purpose. 

Because Treasury does not maintain a database of the projects it 
reviews for compliance with the Pelosi Amendment, we requested that the 
agency create a list of projects receiving such a review for calendar 
years 2006 through 2008. The Treasury analyst conducting these reviews 
compiled for us an estimate of the projects she reviewed during this 
time frame. She stated that she compiled the list from a manual log she 
keeps along with archived emails. Although the analyst stated that the 
list was generally accurate it is possible that a few projects may not 
have been captured. We determined, however, that the data provided were 
sufficiently reliable for the purposes of this report. 

To determine the total number of projects the World Bank Group 
identified as (1) having the potential for significant adverse impacts; 
(2) having the potential for limited adverse impacts; or (3) having 
funds channeled through a financial intermediary, we extracted data 
from the World Bank's and IFC's project Web sites from January 2004 
through May 2008. Since the World Bank Group has not completed vetting 
its response to our request to conduct a review of World Bank Group 
environmental assessment policies and their implementation, it 
therefore did not allow us to assess the reliability of World Bank and 
IFC data. Although we used this data to identify an approximate number 
of projects that were categorized by the World Bank and IFC as likely 
to have significant adverse environmental impacts, the reliability of 
those data are undetermined. 

Due to the nature of the Multilateral Investment Guarantee Agency's 
(MIGA) business model (providing political risk insurance and project 
guarantees), it was not feasible for us to collect project-related 
data, since MIGA's tracking and monitoring activities are different 
than those of the IFC or the World Bank. For example, MIGA does not 
categorize its support in terms of individual projects, but rather in 
terms of individual guarantees from distinct investors. Therefore, 
there may be more than one investor who has applied for and obtained 
MIGA insurance and, thus, more than one guarantee for a given project. 

We conducted this performance audit from October 2007 to November 2008, 
in accordance with generally accepted government auditing standards. 
Those standards require that we plan and perform the audit to obtain 
sufficient, appropriate evidence to provide a reasonable basis for our 
findings and conclusions based on our audit objectives. We believe that 
the evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the Department of the Treasury and GAO's 
Evaluation: 

Note: GAO comments supplementing those in the report text appear at the 
end of this appendix. 

Department Of The Treasury: 
Washington, D.C. 20220: 

November 7, 2008: 

Mr. Thomas Melito: 
Director, International Affairs and Trade: 
Government Accountability Office: 
441 G St., NW: 
Washington, D.C. 20548: 

Dear Mr. Melito: 

I welcome the opportunity to comment, on behalf of the Treasury 
Department, on the Government Accountability Office's report on 
International Environmental Oversight. We found it to be a useful 
presentation, and we appreciate the effort your staff put into this 
report. 

We fully agree with the report's assessment that Treasury has followed 
the procedures required by Title XIII of the International Financial 
Institutions Act of 1977 through the establishment of a rigorous loan 
review process. However, we dispute your claim that our efforts have 
little impact. This finding is based on the fact that U.S. opposition 
at the World Bank Board is insufficient to block projects from going 
forward. However, the report does not take into account Treasury's 
efforts behind the scenes to influence project design, which we believe 
have yielded benefits. In this regard, we look forward to your second 
report on this topic, and anticipate that you will find that U.S.-led 
efforts have had a significant impact on the World Bank's environmental 
due diligence over the past twenty years. [See comment 1] 

We also disagree with your characterization of the interagency process 
as one that is limited to weekly meetings, an assertion which does not 
reflect the dynamic nature of the process. In fact, the process of 
consultations and coordination with other agencies can be quite 
intensive, and includes regular engagement among staff. [See comment 2] 

That said, your point that the sheer volume of projects and limited 
review time review strains USG analytical resources is a valid one. To 
manage these strains, Treasury is committed to increased efforts to 
provide agencies with earlier warning on environmentally significant 
projects. We already provide a 6-12-month pipeline of upcoming MDB 
projects to all agencies, but going forward we will incorporate the 
pipeline into the weekly discussions. We also now include in the agenda 
for the weekly meetings the environment category for each project, in 
conformity with your recommendation. 

Thank you for the opportunity to review and comment on the draft 
report. 

Sincerely, 

Signed by: 

Illegible, for: 

Karen Mathiasen: 
Acting Deputy Assistant Secretary: 
International Finance Development and Debt: 

The following are GAO's comments on the U.S. Department of Treasury's 
letter dated November 7, 2008. 

GAO Comments: 

1. Treasury disputed our finding that their efforts have little impact. 
While Treasury officials did note that they communicate with World Bank 
Group officials informally about projects, Treasury did not provide us 
with information to gauge the impact of these communications. 
Furthermore, Treasury officials also told us they could not determine 
what impact these communications have on project design. 

2. Treasury asserted that we characterized the interagency process as 
limited to weekly meetings. While we did not specifically state that 
the interagency process is limited to the weekly interagency working 
group meetings, we have added language to clarify the extent of 
interagency communication. 

[End of section] 

Appendix III: Comments from the United States Agency for International 
Development and GAO's Evaluation: 

Note: GAO comments supplementing those in the report text appear at the 
end of this appendix. 

USAID: 
From The American People: 
U.S. Agency for International Development: 
1300 Pennsylvania Avenue, NW: 
Washington, DC 20523: 
[hyperlink, http://www.usaidgov]: 

November 13, 2008: 

Mr. Thomas Melito: 
Director: 
International Affairs and Trade: 
U.S. Government Accountability Office: 
441 G Street, N.W. 
Washington, D.C. 20548: 

Dear Mr. Melito: 

I am pleased to provide the U.S. Agency for International Development's 
(USAID) formal response on the draft GAO report entitled "International 
Environmental Oversight: U.S. Agencies Follow Procedures Required By 
Law, But Have Limited Impact" (Nov 2008) (09-99). 

USAID appreciates the opportunity to comment on the GAO's draft report. 
In general, while it is clear a great deal of work went into this 
report and GAO has identified some important issues, several key 
sections of Title XIII do not appear to have been evaluated or, if they 
were, they were not discussed in the report. For example, Section 1304 
requires Treasury, in consultation with State and USAID to create a 
system for cooperative exchange of information with other interested 
member countries on assistance proposals. The overarching objective of 
the International Financial Institutions Act (Title XIII) and relevant 
sections is "to vigorously promote mechanisms to strengthen the 
environmental performance of these banks". The creation or 
effectiveness of this system was not discussed, including 
recommendations or corrective measures to improve the process to 
increase potential impact. [See comment 1] 

Detailed commentary on the draft report with proposed recommendations 
covering the following areas is enclosed: 

* Report Title; 
* Timing Constraints; 
* Mitigation Measures; 
* Section 1307; 
* Reviews and Standards of Reviews; 
* Tuesday Group; 
* GAO draft report recommendation. 

Thank you for the opportunity to respond to the GAO draft report and 
for the courtesies extended by your staff in the conduct of this 
review. 

Sincerely, 

Signed by: 

Sean R. Mulvaney: 
Assistant Administrator: 
Bureau for Management: 

Enclosure: a/s: 

Detailed Commentary: 

Report Title: The report title is overly expansive since the report 
only covers USG oversight of Multilateral Development Banks (MDBs) and 
not "international environmental oversight," which is a far broader 
issue. In addition, this report focuses only on the World Bank group, 
while Title XIII of the International Financial Institutions Act (Title 
XIII) applies to all eleven MDBs. [See comment 2] 

Timing constraints: The timeline on which GAO bases a number of its 
findings starts when the Project Appraisal document is released, which 
is usually 1-3 weeks before the Board vote. USAID agrees that this 
short timeline is a serious problem for engaging effectively with the 
MDBs, especially for loans where a project is already underway and 
construction has begun long before the loan comes to a vote. In such 
"after the fact" loans, there is limited ability to affect the 
environmental impacts of a project. 

However, the single focus and reference to this timeline is misleading. 
It does not take into consideration the time period leading up to 
release of the Project Appraisal document when the project 
Environmental Impact Assessment (EIA) has been released to the public 
120 days prior to Board vote for World Bank (Bank) projects. Although 
it is ideal to engage with the Bank and project sponsors prior to the 
finalization of the EIA, USAID believes it is possible to conduct a 
worthwhile investigation of the project during the time immediately 
following the initial EIA release. This would include review and 
analysis of environmental documentation, as well as conducting site 
visits and meetings with stakeholders to develop recommendations for 
USG engagement with Bank management on project improvements. Obviously 
the final USG position would have to wait until the Project Appraisal 
document is released, but by engaging earlier, the USG could have a 
greater opportunity to discuss recommendations with the Bank. The 
Project Appraisal document would then form the basis to determine the 
extent to which the recommendations have been considered and integrated 
into the project. This early upstream approach has been recommended by 
USAID since 2002 with the initial restructuring of Tuesday Group (the 
monthly meeting of non-governmental organizations (NGOs) and U.S. 
Government agencies, co-chaired by USAID and Bank Information Center to 
address MDB project loans and policies). [See comment 3] 

Mitigation measures: In several places, the report states that Treasury 
supports projects with significant adverse environmental impacts due to 
competing priorities and based on the belief that potential impacts can 
be mitigated (pages 5, 17, 21). The report implies that Treasury has 
the expertise to review the EIAs and determine if the mitigation 
measures are appropriate. For example, the report states that "... 
USAID and Treasury analyzed in more depth the potential environmental 
and social impacts. Because they have different statutory 
responsibilities and flexibility within their statutory requirements, 
the agencies conduct the reviews and apply criteria differently" (page 
4). Without a substantive assessment of the EIA and clear standards of 
review it is difficult to determine whether credible analysis was 
established against which to determine the scope and scale of 
environmental and social impacts and what measures might be needed to 
avoid or mitigate impacts. In many cases, information on funding and 
third party responsibilities and/or commitments to implement the 
mitigation plan are not available as part of the Board's project review 
process. Therefore, there is no way to determine if the mitigation plan 
will be viable. 

These concerns could be addressed on projects that rely on mitigative 
measures to reduce environmental impacts to an acceptable level by 
requiring that the full funding and commitments for the EIA monitoring 
and mitigation plan be made an integral part of the loan amount and the 
Bank's internal management plan for the loan. This would also be a 
required part of the standard Board review process. [See comment 4] 

Section 1307: USAID strongly believes that the intent of the Section 
1307 (Pelosi Amendment) is more than just a procedural process. The 120-
day public disclosure period prior to Board vote should be the 
opportunity where a fully developed environmental impact assessment, 
including adequate alternatives analyses and cumulative and associated 
effects analyses, is available to both the public and the member 
countries of the MDB to engage in an informed discussion that results 
in concrete improvements to the final design. The broader objective of 
Title XIII is to improve the environmental performance of the MDBs and 
to have EIAs account for cumulative and associated impacts. The EIA is 
the foundation for improving environmental performance of bank projects 
and by not "vigorously promoting mechanisms to strengthen the 
environmental performance of these banks," the intent of Title XIII is 
not being achieved. [See comment 5] 

The report cited the Uganda (Bujagali) Hydropower project as a project 
Treasury supported contrary to USAID's recommendation. Among USAID's 
concerns was that the environmental analysis included an inadequate 
cumulative impact analysis required under Section 1307 (Pelosi 
Amendment) (page 21). It should be noted that the USAID finding that 
the environmental analysis was incomplete has since been supported by 
the African Development Bank's own Compliance Review and Mediation 
Unit. 

An example was provided to demonstrate that the Pelosi Amendment can 
prevent the US from supporting projects it would otherwise want to 
support (page 21). This example was a development project in Iraq which 
the USG wanted to support but could not because it did not meet the 120 
day disclosure period. This example also illustrates the intent of the 
Pelosi amendment to require public disclosure of EIAs in sufficient 
time to ensure that affected groups and local nongovernmental 
organizations have access to available information. 

Reviews and Standards of Review: The report states that Treasury is to 
consult with other US agencies to develop environmental impact review 
procedures for proposed MDB projects (Section 1307(d)) (page 8). To 
USAID's knowledge this has not occurred, as evidenced in the report's 
statement that US agencies take various approaches (page 3) and have 
different environmental standards when assessing the sufficiency of 
environmental impact assessments (page 13). 

USAID has found that some EIAs issued by the Banks do not meet any 
international standards for EIAs, or domestic ones applied by the 
Executive Branch to its own projects, nor even the Banks' own 
standards. Omissions of such basic EIA elements as cumulative impacts, 
associated facilities impacts, baseline studies, no-action 
alternatives, consultation with the affected public including 
indigenous peoples, and adaptive management are highly significant and 
not merely matters of EIA style. 

The report states that USAID may evaluate the environmental impact 
assessments of a project during its review (page 13). The majority of 
reviews that USAID undertakes are considered under Section 1303 (a), 
and as such USAID would like to clarify that it always evaluates the 
EIA. 

The report states that USAID may meet with stakeholders when performing 
site visits (page 14). When USAID undertakes an affirmative 
investigation it always meets with as many stakeholders as possible in 
order to gain a more complete understanding of the project to be able 
to make informed recommendations. 

USAID notes that in practice, Title XIII analysis is applied to a 
limited number of proposed MDB loans - essentially ones with the 
greatest potential for significant adverse environmental and social 
impacts. The purpose is to focus finite resources to achieve in-depth 
analysis of projects that can serve as examples for the rest of the MDB 
projects to follow. Consequently, no conclusions should be drawn from 
the numbers in this report on the overall percentage of MDB projects 
having significant environmental problems. 

We also believe that the report should include recommendations on ways 
to harmonize the seemingly disparate review standards being used. [See 
comment 6] 

Tuesday Group: There are factual errors in the report with respect to 
the Tuesday Group (TG). First, Treasury is not a co-chair of Tuesday 
Group. USAID and the Bank Information Center (a non-governmental 
organization) are the co-chairs. Second, the proposal attributed to 
Treasury is inaccurate. The proposal described in the draft report was 
agreed upon in 2004 based on consultations with NGOs and U.S. 
Government agencies, and was first reported in USAID's MDB Report to 
Congress 2002-2004. Please see attachment. Treasury did submit a 
different proposal recently, and USAID has provided comments to 
Treasury on it. [See comment 7] 

GAO draft report recommendation: The recommendation that "the Secretary 
of the Treasury, in his capacity as the chair of the Working Group on 
Multilateral Assistance, routinely identify all proposals of concern in 
advance of working group meetings" may warrant further guidance to more 
clearly address the very short lead times for notice to other agencies. 
[See comment 8] 

Section 5: Annex A: 

Reorganization Of Tuesday Group: 

Complementing the U.S. government interagency review process is the 
Tuesday Group (TG) which is comprised of concerned NGOs and U.S. 
Federal agencies. Meeting monthly for more than a decade, it addresses 
policies, macroeconomic and project loans of the MDBs. Meetings are 
held in Washington and attended by representatives of several agencies 
and about 25 NGOs as well as guests from around the world. USAID and 
the Bank Information Center (BIC), an NGO serving citizens groups 
concerned about MDBs, co chair the meetings. Minutes from the meetings 
are shared with about 165 NGOs worldwide. 

Proposal for Restructuring Tuesday Group (adopted June 2004): 

The objective for restructuring is to ensure TG is a vehicle for 
substantive input on the policies and projects of the MDBs. The 
restructuring proposal seeks to address several issues raised by TG 
participants: informed discussion at TG requires advance circulation of 
information; many important MDB issues that deserve TG attention 
require more proactive identification and preparation; agenda items 
often require more structure to ensure full discussion. The new TG 
format will be reviewed after several meetings and is open for further 
refinement. 

A Steering Committee comprised of USAID, Bank Information Group, the 
Department of the Treasury and an NGO to be determined, will confer 
monthly to plan the ensuing TG meeting: 

* Set agenda for following TG via submitted proposals (NGOs or U.S. 
Federal agencies) and by proactively identifying issues and relevant 
presenters/responders; 

* Use Chatham House Rule; 

* Operate via meetings, calls and emails Any differences will be 
resolved by the co-chairs (USAID and BIC). 

Criteria used by the Steering Committee for determining which submitted 
issues are prioritized for in-depth discussion or only as an 
announcement: 

* Identifiable environmental and social impacts; 

* Sustained engagement by project proposer to help achieve objectives; 

* Importance of potential implications of the project/policy; 

* Leverage TG can bring towards contributing to positive changes with 
respect to project/policy. 

NGOs and U.S. Federal agencies are to submit a one-page outline of 
proposed project/policy issue for initial discussion to TG co-chairs at 
least three weeks prior to TG meeting (see timeline below). Format for 
one-page submission should identify: 

* Project/policy/issue; 

* Potential environmental and social impacts; 

* Importance of potential implications of the project/policy (e.g. why 
discuss this project versus the 1004-category A projects per year that 
need to be reviewed?); 

* Decision points/timeline for proposed intervention(s); 

* Objectives of proposed intervention(s): 
- Note: Proposed interventions are directed towards U.S. government or 
NGOs and may be different depending on U.S. government entity. 

* Groups working on issue. 

Presenters of accepted agenda items are to prepare a 2-3 page (maximum) 
presentation and submit to TG co-chairs no later than one full week 
prior to TG meeting. This will enable TG co-chairs to distribute agenda 
and submissions to TG participants at least one full week prior to next 
TG meeting. Suggested format for Tuesday Group presentation: 

* Background; 

* Key Issues; 

* Proposed intervention(s)/timeline, including objectives of proposed 
intervention(s); 

* Proposer's contribution and sustained engagement to help achieve 
objectives (i.e. project specific analyses, field outreach, time 
commitment). 

Supporting documents can also be submitted for distribution. 

TG meeting format and discussion: 

* Last minute agenda items for emerging issues (for flagging important 
developments, not for in-depth discussion); 

* Follow up items from previous meetings; 

* Discussion moderated by TG co-chairs (BIC or USAID). Purpose of 
discussion is to clarify points made in presentation, to offer 
additional information, and to facilitate follow-up; 

* Minutes will be taken and circulated of meeting. 

Follow-up after TG presentation: 

* Relevant organizations will communicate among themselves to determine 
response to presentation. 

* Appropriate organization will inform TG of decision at the next 
meeting. 

* As required, relevant organization will host separate project 
specific meetings. 

* As required, project updates will be provided during future TG 
meetings. 

- Note; TG co-chairs will provide an example of follow-up submission (1 
page maximum). Supporting documents can also be submitted for 
distribution. 

One project will be selected for discussion under Chatham House Rule as 
a test case for determining practicality and receptivity for a blanket 
adoption of Chatham House Rule at TG. This will require an explicit 
agreement by all participants. 

Timeline for setting agenda: 

* Week 1 -TG meeting; 

* Week 2 - Proposed agenda items submitted and Steering Committee makes 
decisions; 

* Week 3 - Notify presenters so they can prepare document and submit to 
TG co-chairs; 

* Week 4 - Send out agenda and documents - at least one full week prior 
to next TG meeting. 

The following are GAO's comments on the U.S. Agency for International 
Development letter dated November 13, 2008. 

GAO Comments: 

1. USAID commented that several sections of Title XIII are not 
discussed in the report, such as creating a system for information 
exchange with other interested member countries. This is outside the 
scope of our report, which focuses on U.S. government efforts to review 
the World Bank Group's process for assessing the environmental impact 
of projects. We have added language to the report to clarify this 
point. 

2. USAID commented that our draft report title was overly expansive. In 
response, we have changed the title to clarify that our report 
addresses certain procedures required by U.S. law. 

3. USAID commented that the focus on a short timeline is misleading 
because it does not take into consideration the time period leading up 
to the release of the project appraisal document. However, Title XIII 
does not provide a timeline for when U.S. government agencies should 
begin reviewing World Bank Group or other multilateral development bank 
proposals. By not specifying a timeline, the legislation leaves it up 
to the agencies to determine when they should begin reviewing 
proposals. We do note that an April 2008 USAID report to Congress 
stated that there are inadequate opportunities to identify, avert, or 
mitigate adverse environmental and social impacts associated with 
projects even when the banks release the environmental documents 120 
days before the board votes. USAID has acknowledged that it can only 
use the early, upstream approach to provide a more intensive look at a 
limited number of projects. 

4. USAID commented that our report implies that Treasury has the 
expertise to review environmental impact assessments and determine if 
mitigation measures are appropriate. However, we do not comment on 
Treasury expertise. Rather, we acknowledge that USAID and Treasury 
review documentation for different purposes. We also state that 
Treasury is the lead agency in formulating the U.S. government's 
position on proposed multilateral development projects, and that its 
decisions do not always reflect consensus among agencies or even among 
units of the same agencies. While the Pelosi Amendment (Section 1307) 
requires that environmental impact assessments contain associated and 
cumulative impacts and alternatives to the proposal in order for 
Treasury to support a project in a board vote, Treasury is not required 
to consider specific mitigating measures in determining how to instruct 
the U.S. executive director to vote. Section 1306, a separate law in 
Title XIII, requires Treasury to instruct the U.S. Executive Director 
to vigorously urge the multilateral development banks to consider other 
environmental factors and to circulate to the bank board documents that 
include these factors, including mitigating measures. It is beyond the 
scope of this report to determine whether mitigation measures have been 
effective; we anticipate addressing this issue in our next report, 
which will focus on project implementation. 

5. USAID strongly believes that the intent of Section 1307 of Title 
XIII is to be more than just a procedural process. However, the 
specific provisions of Section 1307 that require U.S. government 
oversight of the potential environmental and social concerns associated 
with proposed World Bank Group projects are primarily procedural in 
nature. We revised the report as appropriate in response to this 
comment. 

6. USAID states that Treasury has not consulted with other U.S. 
agencies to develop environmental impact review procedures for 
multilateral development bank projects. USAID believes that our report 
should include recommendations to harmonize disparate review standards. 
However, the law does not require agencies to harmonize review 
standards. Therefore, we did not address this issue in this report. 

7. USAID commented on several factual errors in the report with respect 
to the Tuesday Group. We have revised the report to incorporate the 
first point regarding Tuesday Group co-chairs. Regarding the second 
point, we characterized the proposal, dating from mid-2008, as it was 
described to us by Treasury and the Bank Information Center. Moreover, 
in a technical comment regarding this proposal, Treasury did not 
dispute its timing. We have added a sentence to an existing footnote 
stating that this proposal is very similar to one described in section 
5, annex A of USAID's 2002-2004 report to Congress. 

8. USAID commented that our recommendation may warrant further guidance 
to more clearly address the very short lead times for notice to other 
agencies. However, we did not change our recommendation, which was made 
to the Secretary of the Treasury. We believe it is up to Treasury to 
determine how best to implement the recommendation. 

[End of section] 

Appendix IV: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Thomas Melito (202) 512-9601 or melitot@gao.gov: 

Staff Acknowledgments: 

Anthony Moran, Assistant Director; Kay Halpern; Chris Kunitz; RG 
Steinman; Christina Werth; and Linda Wong made key contributions to 
this report. In addition, Ashley Alley, Debbie Chung, Etana Finkler, 
and Joel Grossman provided technical or legal assistance. 

[End of section] 

Footnotes: 

[1] The World Bank Group is comprised of several affiliated but 
distinct institutions: (1) the World Bank, which consists of the 
International Bank for Reconstruction and Development and the 
International Development Association and provides funding primarily to 
governments to aid public-sector development; (2) the International 
Finance Corporation, which provides financing to the private sector for 
projects in developing and transitioning countries; and (3) the 
Multilateral Investment Guarantee Agency, which provides political risk 
and other insurance to foreign investors in developing countries. 

[2] Each member country's vote is weighted according to the country's 
contribution to the Bank. While the United States has 16.41 percent of 
the vote at IBRD, a majority of all votes is required for a proposal to 
pass (IBRD Article V, Section 3). 

[3] The executive directors of IBRD serve ex-officio as directors of 
IDA and IFC, provided that the country that appoints them or any one of 
the countries that elects them is also a member of IDA and IFC. It is 
customary for the directors of MIGA also to serve as executive 
directors of the World Bank. IFC and MIGA each have slightly fewer 
member countries than the World Bank; IFC has 179; MIGA 172. 

[4] U.S. Congressional Research Service, Multilateral Development 
Banks' Environmental Assessment and Information Policies: Impact of the 
Pelosi Amendment (98-180F) (February 1998). 

[5] The other U.S. agencies Treasury consults with include the 
Department of State, USAID, the Environmental Protection Agency, the 
Council on Environmental Quality, the Department of the Interior, and 
the National Oceanic and Atmospheric Administration. 

[6] These include the extent to which the proposal will contribute to 
the sustainable development of the borrowing country, the economic 
viability of the proposal, and its impact on public health. 

[7] According to Treasury officials, for World Bank projects, once 
board documents have been distributed, board procedures provide for a 
delay of up to one board meeting, which could be useful in meeting 
Pelosi Amendment requirements only if the public disclosure period 
falls short by a day or two. For IFC projects, where the IFC-required 
disclosure period is 60 days, Treasury officials told us the client's 
financing needs typically prohibit shifting from 60 to 120 days to meet 
the Pelosi Amendment requirements. 

[8] According to this official, the disclosure date is the date the 
documentation is posted on the World Bank's Web site. Treasury 
officials obtain this date from the Web site, the board document, the 
World Bank's Integrated Safeguards Data Sheet, or World Bank Group 
staff. They will also look at the local disclosure date, if there is 
one. However, since Treasury generally conducts the review shortly 
before the board vote, Treasury officials told us they do not have a 
way to verify whether the date on the documentation is the date the 
documents were actually posted on the Web site. 

[9] Treasury officials could not provide the exact number of proposals 
they review for the Pelosi Amendment because they do not keep an 
ongoing database of Pelosi Amendment reviews. 

[10] Treasury officials said they rarely do this because such 
deficiencies are seldom identified. 

[11] Section 539(e) of Title V of Public Law 99-591 and Section 
1303(b)(3) of Title XIII require Treasury to provide an annual report 
to Congress on the environmental sustainability of multilateral 
development bank operations and the efficacy of U.S. efforts in this 
process. 

[12] The law requires Treasury to consult with U.S. agencies such as 
State, EPA, and USAID in determining whether multilateral development 
banks or the borrower provide an environmental assessment or summary 
thereof for a proposed project that is likely to have significant and 
adverse environmental impacts (22 U.S.C. § 262m-7). In addition, 
Treasury regulations specify the actions Treasury and the working group 
should take if U.S. government agencies or members of the public have 
specific comments on proposed multilateral development projects (31 
C.F.R. § 26.4). Such actions include considering whether the 
multilateral development bank has assigned the proposed project the 
appropriate environmental category, and considering the U.S. 
government's position on the project. 

[13] These meetings are for U.S. government agencies to address all 
mandates and concerns associated with multilateral development bank 
projects, not just those associated with the environment. 

[14] See USAID's Environmental Procedures, 22 C.F.R. Part 216; The 
National Environmental Policy Act of 1969 (NEPA), as amended; CEQ 
Regulations for Implementing the Procedural Provisions of NEPA, 40 
C.F.R. parts 1500-1508; and CEQ guidance on implementing 40 C.F.R. Part 
1500-1508: [hyperlink, http://www.nepa.gov/nepa/regs/guidance.html]. 

[15] The Treasury official responsible for performing these analyses 
stated she may initiate the analyses many months to years before the 
proposed project is scheduled for a board vote. She provided 
information indicating that Treasury performed four such analyses in 
2006 and 2007. 

[16] The World Bank, IFC and MIGA each has its own requirements, which 
project sponsors must follow when preparing environmental assessments. 
For example, the World Bank lays out its requirements for environmental 
assessments in its Operational Directive 4.01. The World Bank also has 
an environmental assessment guidebook, the Environmental Assessment 
Sourcebook, which contains advisable practices that could be employed 
when preparing an environmental assessment. The World Bank recommends, 
but does not require, that environmental assessments conform to these 
advisable practices. 

[17] World Bank Environmental Assessment Sourcebook, rev. 1999. 

[18] The Tuesday Group is chaired by USAID and the Bank Information 
Center, a nongovernmental organization. Treasury regulations require 
Treasury to consider all comments made from any member of the public 
during the periodic meetings convened by the Bank Information Center 
and present summaries to other U.S. government agencies participating 
in an interagency working group led by Treasury (31 C.F.R. § 
26.4(a)(2)). 

[19] In its proposal, Treasury has named only one nongovernmental 
organization, the Bank Information Center. A Treasury official said the 
agency has yet to identify a second organization to participate in the 
proposed steering committee. This proposal is very similar to one 
described in section 5, annex A of USAID's 2002-2004 report to 
Congress. 

[20] In commenting on this report, Treasury officials noted that, as of 
October 2008, an open discussion period has been part of the Tuesday 
Group meeting format. 

[21] Treasury officials noted that, while they do not have the fully 
appraised project proposal until about 3 weeks before the board vote 
date, they do receive some project information much earlier, through a 
6-month "pipeline" notification system that they have asked each 
multilateral development bank to prepare. They also stated that they 
share this information with other agencies in an ongoing consultation 
process prior to the interagency meeting. 

[22] According to some agency officials, the board vote date might be 
postponed to allow more time for discussion, although this is rare. For 
example, according to Treasury officials, IFC management delayed voting 
on a paper mill project in Uruguay to allow for an analysis of 
cumulative impacts of the two mills that were planned in the project. 
However, this was a highly unusual case that was brought to the U.S. 
government's attention by a high-level delegation from Argentina, which 
would have been affected by the project. According to Treasury 
officials, if they need clarification about a project while conducting 
a review before a board vote, they will contact World Bank Group 
officials to discuss the project. However, if they do not obtain a 
response from World Bank Group officials before the board vote date, 
Treasury must make a decision based on the information it already has. 

[23] According to an expert on the environmental impacts of World Bank 
Group projects who worked for several decades as an Environmental 
Advisor to the World Bank Group, IFC projects often have additional 
financing from the private sector, which allows construction to begin 
before the project sponsor applies for or is approved to receive IFC 
financing. 

[24] This was the most complete data at the time of our analysis. 

[25] In commenting on this report, Treasury officials stated that, 
while this situation is rare, there have been two multilateral 
development bank projects over the past year that were changed 
following the circulation of a U.S. statement to the board the night 
before the vote indicating that the United States would vote no. These 
projects were a World Bank road project in the Philippines and an Asian 
Development Bank technical assistance proposal for a feasibility study 
of roads through Indonesian national parks. 

[26] Treasury officials noted that their agency generally prepares 
decision memos for support for highly controversial projects, very 
large projects, and all China projects. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: