This is the accessible text file for GAO report number GAO-08-759 
entitled 'Telecommunications: Agencies Are Generally Following Sound 
Transition Planning Practices, and GSA Is Taking Action to Resolve 
Challenges' which was released on July 28, 2008. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Committee on Homeland Security and Governmental Affairs, 
U.S. Senate: 

United States Government Accountability Office: 

GAO: 

June 2008: 

Telecommunications: 

Agencies Are Generally Following Sound Transition Planning Practices, 
and GSA Is Taking Action to Resolve Challenges: 

GAO-08-759: 

GAO Highlights: 

Highlights of GAO-08-759, a report to the Committee on Homeland 
Security and Governmental Affairs, U.S. Senate. 

Why GAO Did This Study: 

The General Services Administration (GSA) is responsible for ensuring 
that federal agencies have access to the telecommunications needed to 
meet mission requirements. GSA’s current telecommunications program, 
called FTS2001, has contracts in place that will expire by June 2010. 
Thus, agencies face the difficult task of transitioning their services 
to a successor program, known as Networx. GAO was asked to determine 
(1) the extent to which agencies are following sound transition 
planning practices and (2) the actions GSA is taking to identify and 
resolve common transition challenges affecting agencies. In performing 
this work, GAO selected six agencies based on, among other things, 
their FTS2001 charges; reviewed transition planning at these agencies 
and GSA; and analyzed GSA documentation of actions to address 
transition challenges. 

What GAO Found: 

Selected agencies—the Departments of Homeland Security, Commerce, and 
Agriculture and the Small Business Administration, U.S. Army Corps of 
Engineers, and the U.S. Nuclear Regulatory Commission—are generally 
following sound transition planning practices previously identified by 
GAO (see table below). For example, all have established 
telecommunications inventories, and most have established transition 
plans that include transition preparation tasks and time lines. 
However, other key practices are not being fully implemented at three 
agencies. For example, Commerce does not plan to clearly define all key 
transition roles and responsibilities, Homeland Security does not plan 
to identify local and regional points of contact, and the Nuclear 
Regulatory Commission does not plan to establish measures of success 
based on its transition objectives. With limited time available to 
finalize planning and begin transitions, agencies that do not address 
gaps in their planning or follow through on plans risk delaying their 
transitions and increase the likelihood of incurring unnecessary costs. 

As facilitator for all transition management activities, GSA has 
identified numerous common challenges that agencies face in making the 
transition to Networx, and it is taking action to resolve them. GSA 
uses various forums to identify these challenges, which include 
ensuring cooperation from incumbent contractors, defining agencies’ 
responsibilities for information security during the transition, and 
the use of a transition inventory application developed by GSA. To 
resolve these challenges, GSA has, among other things, modified FTS2001 
contracts to help ensure contractor cooperation, developed guidance to 
clarify information security responsibilities, and established support 
teams to assist agencies in using the inventory application developed 
by GSA. GSA’s actions should reduce the likelihood that these 
challenges will hinder transition efforts. 

Table: Sound Transition Planning Practices: 

1. Establish an accurate telecommunications inventory and an inventory 
maintenance process. 

2. Identify strategic telecommunications requirements and use this to 
shape the agency’s management approach and guide efforts when 
identifying resources and developing a transition plan. 

3. Establish a structured management approach that includes a dedicated 
transition management team, key management processes (project 
management, configuration management, and change management), and clear 
lines of communication. 

4. Identify the funding and human capital resources that the transition 
effort will require. 

5. Develop a transition plan that includes transition objectives, 
measures of success, a risk assessment, and a detailed time line. 

Source: GAO. 

[End of table] 

What GAO Recommends: 

GAO recommends that Commerce, Homeland Security, and the Nuclear 
Regulatory Commission address gaps in transition planning. Commenting 
on a draft, Commerce agreed with the report, Homeland Security 
disagreed with five of seven recommendations, while the Nuclear 
Regulatory Commission agreed with one of two. However, failure to 
follow sound planning practices could put agency transitions at risk. 

To view the full product, including the scope and methodology, click on 
[hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-08-759]. For more 
information, contact Linda Koontz at (202) 512-6240 or KoontzL@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

Selected Agencies Are Generally Following Sound Transition Planning 
Practices: 

GSA Is Taking Action to Identify and Resolve Common Transition 
Challenges: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope, and Methodology: 

Appendix II: Comments from the General Services Administration: 

Appendix III: Comments from the Department of Commerce: 

Appendix IV: Comments from the U.S. Nuclear Regulatory Commission: 

Appendix V: Comments from the Department of Homeland Security: 

Appendix VI: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1: Telecommunications Inventory: 

Table 2: Strategic Analysis of Telecommunications Requirements: 

Table 3: Structured Transition Management Approach: 

Table 4: Resource Identification: 

Table 5: Transition Plan: 

Figures: 

Figure 1: Expiration of FTS2001 Contracts: 

Figure 2: Transition Time Line: 

Abbreviations: 

ACE: U.S. Army Corps of Engineers: 

DHS: Department of Homeland Security: 

DOC: Department of Commerce: 

FAR: Federal Acquisition Regulation: 

GSA: General Services Administration: 

IMC: Interagency Management Council: 

IT: Information Technology: 

NRC: U.S. Nuclear Regulatory Commission: 

OMB: Office of Management and Budget: 

SBA: Small Business Administration: 

TWG: Transition Working Group: 

USDA: U.S. Department of Agriculture: 

United States Government Accountability Office: 

Washington, DC 20548: 

June 27, 2008: 

The Honorable Joseph Lieberman: 
Chairman: 
The Honorable Susan M. Collins: 
Ranking Member: 
Committee on Homeland Security and Governmental Affairs: United States 
Senate: 

The General Services Administration (GSA) is responsible for ensuring 
that federal agencies have access to the telecommunications services 
and solutions that they need to meet mission requirements. As federal 
agencies have evolved in their use of telecommunications, so too has 
GSA's development of contracts to help support their needs. Currently, 
these telecommunications contracts not only support agencies' basic 
telephony needs, but also provide an acquisition vehicle for wireless 
and satellite services, as well as managed network services and 
information technology (IT) security services. In fiscal year 2007 
alone, federal agencies spent approximately $960 million on services 
acquired through the contracts under GSA's current telecommunications 
program, known as FTS2001. The FTS2001 contracts are set to expire by 
June 2010. 

In preparation for the end of its current telecommunications contracts, 
GSA developed a successor program, known as Networx, and awarded 
telecommunications contracts under this program in March and May 2007. 
Agencies must now undertake the difficult task of transitioning their 
telecommunications services to the Networx contracts. This transition 
will involve more than 135 agencies, about 50 types of services, and 
thousands of voice and data circuits. It could be the largest 
telecommunications services transition ever undertaken by the federal 
government and will require coordination among agencies, GSA, and a 
host of telecommunications contractors. 

This report responds to your request that we determine (1) the extent 
to which federal agencies are following sound transition planning 
practices and (2) the actions GSA is taking to identify and resolve 
common transition challenges affecting agencies. 

To determine the extent to which agencies are following sound 
transition planning practices, we selected six agencies for review from 
those that incurred FTS2001 charges in excess of $1 million for fiscal 
year 2006. We selected agencies that would ensure a representation of 
(1) executive departments, subagencies, and independent agencies; (2) 
varying levels of attendance in the Transition Working Group, an agency 
forum that is assisting GSA in its efforts to plan for the transition; 
and (3) a range of agency spending for FTS2001 in excess of $1 million. 
Based on these criteria, we selected the Departments of Homeland 
Security, Commerce, and Agriculture and the Small Business 
Administration, U.S. Army Corps of Engineers, and U.S. Nuclear 
Regulatory Commission. We then obtained and reviewed documentation 
(including strategic plans, telecommunications inventories, and 
transition-related plans) and interviewed officials from each of the 
selected agencies. We assessed this agency information against sound 
telecommunications transition planning practices that we identified in 
a report issued in 2006.[Footnote 1] In that report, we stated that 
organizations preparing for a telecommunications transition should: 

* establish a telecommunications inventory, 

* perform a strategic analysis of telecommunications requirements, 

* establish a structured transition management approach, 

* identify resources, and: 

* develop a transition plan. 

Each of these sound planning practices consists of various components 
(for example, developing a transition plan consists of (1) identifying 
and documenting objectives and measures of success, (2) determining 
risks that could affect success, and (3) defining transition 
preparation tasks and developing a time line for these tasks). For the 
current report, we classified the status of agency transition planning 
efforts to address the practice components as "fully implemented," if 
the agency has fully implemented the sound practice component; "plans 
to fully implement," if the agency has plans to fully implement the 
component; or "no plans to fully implement," if the agency does not 
have plans to fully implement it. We discussed our assessments with 
agency officials and made adjustments as appropriate. 

To determine actions that GSA is taking to identify and resolve 
challenges, we analyzed transition guidance and other Networx 
documentation developed by GSA and the Interagency Management Council's 
Transition Working Group, such as presentations, meeting minutes, 
projected time lines, and a pre-award transition guide. We also 
interviewed officials from GSA, FTS2001 incumbent vendors, Networx 
vendors, and the six agencies selected for review. 

We conducted this performance audit from September 2007 through June 
2008, in accordance with generally accepted government auditing 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives. A detailed 
discussion of our objectives, scope, and methodology can be found in 
appendix I. 

Results in Brief: 

The selected agencies are generally following sound telecommunications 
transition planning practices that we previously identified. For 
example, all have established telecommunications inventories for 
conducting their transitions, and all have ensured that identified 
telecommunications needs and opportunities are aligned with their 
respective missions, long-term IT plans, and enterprise architecture 
plans. Further, most have established transition plans that include 
transition preparation tasks and a time line that allows for periodic 
reporting. However, three agencies are not fully implementing other key 
practices and do not plan to do so. For example, Commerce does not plan 
to define all key transition roles and responsibilities, Homeland 
Security does not plan to identify local and regional points of 
contact, and the U.S. Nuclear Regulatory Commission does not plan to 
establish measures of success based on transition objectives--all of 
which activities are components of the sound management practices that 
we identified. Agency officials provided various reasons for not 
following these practices, including reliance on other entities and 
processes to carry them out. For example, Commerce officials stated 
that the department did not plan to define all responsibilities for the 
transition because the department's transition manager and each of its 
components will be responsible for undefined roles. Homeland Security 
officials stated that they do not plan to identify local contacts 
because they believe the department's current process for communicating 
telecommunications changes will be adequate for the transition. U.S. 
Nuclear Regulatory Commission officials stated that instead of 
establishing measures to assess progress toward the agency's transition 
goals, they plan to use GSA-established measures related to transition 
progress. Nonetheless, the time remaining for agencies to conduct their 
telecommunications transitions is limited; thus, agencies that do not 
address gaps in transition planning and follow through on their plans 
risk delaying their transitions and increase the likelihood that the 
government will incur unnecessary costs. 

GSA has identified a number of challenges facing agencies in making the 
transition to Networx contracts, and it is taking actions to resolve 
them. Through the use of various forums, such as the Interagency 
Management Council's Transition Working Group, GSA has identified 
challenges such as ensuring cooperation from incumbent contractors, 
defining agencies' responsibilities for information security during the 
transition, and using a transition inventory application developed by 
GSA. To resolve the challenges identified, GSA has taken a number of 
actions, including modifying FTS2001 contracts to help ensure 
contractor cooperation, developing guidance to clarify information 
security responsibilities, and establishing support teams to assist 
agencies in using the inventory application. GSA's actions should 
reduce the likelihood that these challenges will affect transition 
efforts. 

To reduce the risk that transition delays could lead to disruptions in 
agency telecommunications services or increased costs, we are making 
recommendations to the Secretaries of Commerce and Homeland Security 
and the Chairman of the U.S. Nuclear Regulatory Commission aimed at 
addressing gaps in their agencies' transition planning. 

We received comments on a draft of our report from five of the seven 
agencies reviewed. GSA, Commerce, the Nuclear Regulatory Commission, 
and Homeland Security provided written comments (which are reproduced 
in apps. II through V), and the Small Business Administration provided 
comments via e-mail. Two agencies, Agriculture and U.S. Army Corps of 
Engineers, indicated via e-mail that they had no comments. 

Three of the agencies generally agreed with our report, and two 
partially agreed. Agencies generally agreeing were GSA, the Department 
of Commerce, and the Small Business Administration. The Nuclear 
Regulatory Commission and the Department of Homeland Security disagreed 
with aspects of our findings and recommendations. 

* The Nuclear Regulatory Commission indicated that our report generally 
reflects the issues surrounding agency preparedness for transition. 
However, the responding official suggested that we remove our 
recommendation for the Commission to evaluate the costs and benefits of 
new technology or alternatives, because such an evaluation had been and 
would be conducted as part of its normal planning processes. 
Nonetheless, our recommendation remains because the Commission did not 
perform this activity for the transition to Networx. Commission 
officials also provided technical comments, which we incorporated into 
our report as appropriate. 

* Homeland Security agreed with two and disagreed with five of the 
seven recommendations directed toward the department, and it did not 
concur with one finding. The department agreed with our recommendations 
that it establish goals and measures of success and perform a 
transition risk assessment for the department's transition. It 
disagreed with the remaining recommendations, indicating that it was 
already taking actions in these areas. However, these actions are 
already reflected in our assessment and do not meet the sound practice 
standards on which we based our recommendations. For example, regarding 
telecommunications inventory maintenance, the department's comments 
acknowledged that it has not published a process document for 
maintaining its inventory of telecommunications service assets, but 
stated that it instructed its components to use documented GSA 
procedures to maintain their inventories. However, sound practices call 
for the agency to document the process to be used by its components for 
inventory maintenance to lessen the risk that changes to the inventory 
during and after transition would not be consistently and accurately 
captured. Finally, the department stated that it does not concur with a 
finding related to defining communications plans, indicating that the 
charter for its transition working group defines essential 
communications responsibilities and activities. Our report acknowledges 
that lines of communication have been established; however, the 
department's communications planning is incomplete because Homeland 
Security did not identify local and regional points of contact, as 
advocated by sound practices. 

Background: 

GSA's existing FTS2001 program is the successor to a line of programs 
that have provided long-distance telecommunications to the federal 
government. Made up of two large governmentwide contracts--one awarded 
to Sprint[Footnote 2] in December 1998 and one awarded to MCI[Footnote 
3] in January 1999--the program is designed to meet agency needs for 
various telecommunication services. It also includes contractors that 
had been awarded local telecommunications contracts for selected 
metropolitan areas. GSA allowed these contractors to also offer long-
distance services on the FTS2001 contracts--termed "crossover 
contracts."[Footnote 4] 

The original terms of the two FTS2001 contracts were set to expire in 
December 2006 and January 2007. However, to give itself time to 
finalize the contracts intended to succeed the FTS2001 contracts and to 
provide its customer agencies additional time to complete their 
transitions once the Networx contracts were awarded, GSA negotiated 
sole-source contracts (termed FTS2001 bridge contracts) with Sprint and 
MCI to provide continuity of service for agencies. These bridge 
contracts, which extend the terms of the FTS2001 contracts for no more 
than 42 months,[Footnote 5] began in December 2006 and January 2007 and 
are to expire at the end of May and June 2010, respectively. 

In October 2003, GSA announced its plans for the Networx program. In 
conjunction with a group of senior federal information resource 
officials known as the Interagency Management Council (IMC),[Footnote 
6] GSA identified eight strategic goals for the program: 

* Service continuity--Contracts should include all services currently 
available under FTS2001 to facilitate a smooth transition. 

* Competitive prices--Prices should be better than those available 
elsewhere in the telecommunications marketplace. 

* High-quality service--Contracts should ensure a high quality of 
service throughout the life of the contracts using enforceable 
agreements. 

* Full service vendors--Vendors should be capable of providing a broad 
array of services and provide follow-on services to avoid duplication 
of administrative and contracting costs. 

* Alternative services--Agencies should be able to choose from a 
greater number of competing vendors that provide new, enhanced services 
and emerging technologies. 

* Transition support--Contracts should include provisions that 
facilitate transition coordination and support. 

* Performance-based contracts--Contracts should be performance based 
and include service-level agreements where possible. 

* Operations support--GSA should provide fully integrated ordering, 
billing, and inventory management. 

In addition, GSA identified goals specific to the Networx transition 
and indicated that the ability of GSA and the Networx contractors to 
deliver against these goals is essential to the overall success of the 
transition effort. These goals include: 

- minimizing service impact, 

- transitioning telecommunications services before the FTS2001 
contracts expire, 

- expediting the availability of new services, and: 

- minimizing transition expenses. 

Under the Networx program, GSA awarded two multiple-award task and 
delivery order contracts--Networx Universal and Networx Enterprise-- 
having a combined estimated value of $20 billion. The contracts were 
awarded in March and May 2007, respectively. 

* GSA awarded Networx Universal contracts to AT&T, Verizon Business 
Services, and Qwest Government Services. Networx Universal offers voice 
and data services, wireless services, and management and application 
services, including video and audio conferencing, as well as mobile and 
fixed satellite services, with national and international coverage. 

* GSA awarded Networx Enterprise contracts to AT&T, Verizon Business 
Services, Qwest Government Services, Level 3 Communications, and Sprint 
Nextel. Networx Enterprise offers services similar to those of Networx 
Universal, with a focus on those that are Internet-based, and does not 
require coverage of as large a geographic area as does Networx 
Universal. 

Transition Responsibilities: 

Central to the successful transition from FTS2001 to Networx are 
transition planning and execution activities that involve GSA, the 
agencies, and FTS2001 and Networx contractors. GSA serves as a 
facilitator for all transition management activities and is using 
contracted support to assist in tracking transition activities in order 
to avoid delays and other problems that can arise throughout the 
process. 

GSA's primary responsibility is program management of both the FTS2001 
and Networx programs. As part of this, GSA is responsible for: 

* providing guidance and assistance to agencies for the transition to 
Networx to ensure that unnecessary delays in agency transitions are 
avoided; 

* developing an overall Networx transition strategy, minimizing agency 
transition costs, and ensuring that all telecommunications services are 
transitioned in a timely manner; and: 

* tracking daily progress of transition efforts, performing program-
level analysis to support transition goals and objectives, and 
resolving transition issues. 

The GSA organization carrying out these responsibilities is the Federal 
Acquisition Service, an organization formed in 2006 from the merger of 
GSA's Federal Technology Service, which had managed the FTS2001 
program, and GSA's Federal Supply Service. 

To assist agencies with their transitions from the FTS2001 contracts, 
GSA is working with representatives of federal agencies, both directly 
and through the IMC. A subgroup of the IMC, the Transition Working 
Group (TWG), was established in May 2004 to assist with developing a 
consensus on common transition issues that affect multiple agencies. 
The TWG coordinates with GSA, agencies, and industry partners to ensure 
thorough advance planning and preparation efforts for the transition to 
Networx. The TWG also serves as a conduit for communications among GSA 
and its customer agencies. 

GSA's customer agencies--those federal agencies acquiring services 
through the FTS2001 program--have principal responsibility for the 
transition. These agencies are responsible for coordinating transition 
efforts with the incumbent and Networx contractors to ensure that 
existing services under FTS2001 are disconnected and that new services 
are ordered. GSA and the IMC have requested each of the customer 
agencies to appoint a transition manager and establish a transition 
team that will: 

- manage the agency's internal transition planning, preparation, and 
execution efforts and: 

- be responsible for interfacing with GSA, the IMC, and officials 
within the agency. 

Both the Networx contractors and incumbent FTS2001 contractors are 
responsible for supporting agencies in their transition planning and 
execution efforts: 

* Networx contractors will be responsible for delivering services 
ordered, developing program-level and agency-level transition plans, 
and communicating the status of transition activities with scheduled 
notices and reports. 

* Incumbent FTS2001 contractors are expected to complete all FTS2001 
service disconnect orders requested by agencies and assist agency 
efforts to prepare for the transition by, for example, helping to 
identify inventory information and system requirements. 

GSA and Agencies Have Taken Steps to Address Difficulties Encountered 
in a Previous Transition: 

The previous transition of federal telecommunications services was a 
large and complex task that underscored the importance of proper 
transition management practices. In 2001, we reported[Footnote 7] that 
the transition to the current FTS2001 federal telecommunications 
contracts encountered delays and took more than 24 months, which 
hindered the timely achievement of program goals. We also reported that 
transition delays resulted in raised telecommunications costs. In 
total, an estimated $74 million in savings was lost due to delays in 
completing the transition to FTS2001. 

Subsequently, the TWG, in conjunction with GSA, identified 27 lessons 
learned from the previous transition. For example, lessons learned 
include (1) the need for GSA and agencies to identify funding for the 
transition early to ensure that resources are available and (2) the 
need to ensure that local agency sites are not responsible for delays 
due to access issues. Of the 27 lessons learned, 13 related to 
transition planning, 11 to transition execution, and 3 to transition 
monitoring. Together, the lessons learned affirmed that applying 
adequate transition practices--including planning, executing, and 
monitoring the transition--increases the likelihood of a successful 
transition from FTS2001 contracts to Networx. 

GSA and representatives of its customer agencies have taken actions to 
address these lessons learned. For example, to address funding for the 
transition, GSA and the TWG developed a Taxonomy and Allocation of 
Transition Costs document, which the IMC approved, that describes each 
type of transition cost and whether GSA or the agency would be 
responsible. And to help ensure that local agency sites are not 
responsible for delays, GSA has provided guidance to agencies on 
creating staffing and training plans to better ensure that those 
involved are prepared for the transition effort. 

GSA has also developed numerous guidance documents and presentations 
related to the transition, as well as several tools. Much of this 
information is maintained by GSA in two locations on the Internet--its 
public Web site at [hyperlink, http://www.gsa.gov/networx] and a Web 
site accessible only to agency transition managers and TWG members. 
Documentation developed includes, for example, a guide to assist 
agencies in selecting the vendor best suited to provide required 
services while giving all vendors fair opportunity to be considered for 
each order--known as the fair opportunity process[Footnote 8]. GSA has 
also developed numerous presentations on the transition from FTS2001 
and briefings presented to agency transition managers. Further, GSA has 
developed tools specifically designed to aid agencies as they 
transition to Networx, such as a transition inventory application to 
help agencies identify and validate their transition inventories and a 
tool that agencies can use to price their services against the various 
Networx contract offerings. 

GSA Has Provided Agencies Incentives to Transition Early: 

With GSA's FTS2001 contracts set to expire by June 2010--within the 
next 2 years--agencies have a limited time frame within which to 
complete their transitions (see fig. 1). As mentioned earlier, the 
FTS2001 bridge contracts expire in May and June 2010. In addition, 
GSA's FTS2001 crossover contracts with Qwest, Verizon, AT&T, Winstar 
Communications, and SBC will expire between January 2008[Footnote 9] 
and May 2010. Therefore, agencies have approximately 2 years to 
transition all FTS2001 services before all FTS2001 contracts expire. 
Figure 1 depicts these expiration dates. 

Figure 1: Expiration of FTS2001 Contracts: 

This figure is a timeline of expiration of FTS2001 contracts. 

[See PDF for image] 

Source: GAO analysis of GSA data. 

[A] Upon contract expiration or termination, a continuity of service 
period provides an agency additional time to use FTS2001 services until 
the agency is able to transition to a successor contract. 

[End of figure] 

To address the approaching expirations, GSA is taking several actions. 
First, to provide an incentive to transition early, GSA and the IMC 
agreed upon milestones and associated criteria that, if met, would 
allow agencies to be reimbursed by GSA for certain transition-related 
costs. Second, in meetings with agency Chief Information Officers, GSA 
has emphasized the importance of conducting an efficient and timely 
transition as well as garnering executive-level buy-in for transition 
support. Third, GSA's Technology Service Managers have been in contact 
with agencies to ensure that they are working toward transitioning 
their FTS2001 services. Fourth, the collection of GSA documents, 
presentations, and tools is geared toward assisting agencies in 
planning and executing their transitions. 

Specifically, to qualify for reimbursements, an agency must comply with 
the following milestones (fig. 2 depicts these milestones against the 
transition time line): 

* By September 30, 2008, agencies are to complete "fair opportunity" 
decisions--that is, select their vendors--for all services to be 
transitioned from FTS2001 telecommunications contracts. 

* By January 1, 2010, agencies must submit all transition orders that 
will incur costs related to parallel operations. GSA will not reimburse 
any costs for parallel operations an agency orders after this date. 

* By April 1, 2010, agencies must submit all transition orders. GSA 
will not reimburse any costs for transition orders an agency places 
after this date. 

Figure 2: Transition Time Line: 

This figure is a timeline showing transition. 

[See PDF for image] 

Source: GAO analysis of GSA data. 

[End of figure] 

Our Prior Work Has Addressed Telecommunications Transition Planning: 

We have issued several reports on issues surrounding GSA's FTS2001 and 
Networx telecommunications programs. Specifically, we reported on 
difficulties encountered during the previous transition, agency 
preparation for the transition to Networx, sound transition planning 
practices, and GSA's cost estimation for the transition to Networx. 

In 2001, we reported on difficulties encountered during the transition 
to the FTS2001 program.[Footnote 10] We found that the collective 
effect of delays encountered during this complex transition jeopardized 
the timely achievement of FTS2001's program goals. Delays occurred for 
several reasons. For example, delays occurred because agency efforts to 
order services were impeded by the inability of GSA and the long- 
distance contractors to rapidly add, through a contract modification 
process, transition-critical services to the FTS2001 contracts. Other 
identified reasons for transition delays included that agencies were 
slow to place orders for transition services and that contractors had 
issues with staffing and billing that impaired their efforts to support 
agencies' transition activities. We also reported that encountered 
delays would, among other things, cause agency telecommunications costs 
to rise. 

In 2006, we reported on sound transition planning practices that 
agencies could use to improve the likelihood of a smooth 
transition.[Footnote 11] These planning practices are to: 

* establish a telecommunications inventory, 

* perform a strategic analysis of telecommunications requirements, 

* establish a structured transition management approach, 

* identify resources, and: 

* develop a transition plan. 

Each of these sound planning practices consists of various components 
(for example, developing a transition plan consists of (1) identifying 
and documenting objectives and measures of success; (2) determining 
risks that could affect success; and (3) defining transition 
preparation tasks and developing a time line for these tasks). 

We assessed the progress of six agencies in preparing for the 
transition and reported that although agencies were early in the 
planning process, they were generally planning to employ sound 
transition planning practices in their transition management efforts. 
However, officials at two of the agencies stated that they did not plan 
to fully identify necessary resources. Specifically, officials at the 
Department of Justice indicated that they would not need additional 
financial resources, even though they could not provide an analytical 
basis for their decision, and officials from the Department of Energy 
believed that because the agency's transition would be straightforward, 
identifying human capital needs would not be necessary. We also 
reported that GSA had provided agencies with guidance on performing 
some but not all of the sound transition planning practices we 
identified. 

As a result, we recommended that: 

* the Attorney General ensure that the Department of Justice's planning 
efforts include an analysis of the extent to which current financial 
resources would be sufficient to conduct an effective transition; 

* the Secretary of Energy ensure that the department's planning efforts 
included identification of human capital resources needed to conduct an 
effective transition; and: 

* the Administrator of General Services, in working with the IMC, 
develop and distribute guidance to ensure that our identified sound 
practices for transition planning were used. 

In response, the three agencies took action or indicated that they 
planned to take action to implement our recommendations. The Department 
of Justice's Chief Information Officer indicated that the department 
intended to analyze and determine its financial and other resource 
requirements for transition in the near future. However, as of April 1, 
2008, it had not yet done so. The Department of Energy provided a 
transition plan that indicated that the need for human capital 
resources for the transition would be dependent on the Networx 
contractor or contractors chosen; once contractors were selected, the 
agency planned to re-examine its human capital needs to ensure that 
adequate support would be provided for transition execution. Finally, 
GSA provided guidance to agencies that addresses our identified sound 
transition planning practices. 

In 2007, we reported on GSA's development of cost estimates for the 
transition to Networx, stating that while it had adequate funding to 
support its anticipated transition costs, it did not use sound analysis 
when developing its estimate.[Footnote 12] Accordingly, to ensure that 
future cost estimates by GSA were sound and could be used as a reliable 
basis for decisions, we recommended that the Administrator of General 
Services establish an agencywide policy requiring that cost estimates 
be developed using best practices. In addition, we recommended that the 
Administrator revise the transition cost estimate for Networx using 
best practices after the award of contracts under the Networx program. 

To address these recommendations, GSA established an agencywide policy 
requiring that its cost estimates be developed using best practices. 
Regarding the revision of its transition cost estimate, GSA officials 
indicated that once a significant number of agencies have made their 
fair opportunity decisions, it will recalculate the transition cost 
estimate, brief the IMC, and provide the results to us. Officials 
stated that GSA will brief the IMC in June 2008 on the revised 
transition estimate. 

Selected Agencies Are Generally Following Sound Transition Planning 
Practices: 

The selected agencies are generally following the sound 
telecommunications transition planning practices that we identified in 
our 2006 report.[Footnote 13] For example, all have established 
telecommunications inventories for conducting their transitions, and 
all have ensured that identified telecommunications needs and 
opportunities are aligned with their respective missions, long-term IT 
plans, and enterprise architecture plans. However, key practices are 
not being fully implemented at three agencies: Commerce, Homeland 
Security, and the U.S. Nuclear Regulatory Commission. Officials of 
these agencies provided various reasons for not following these 
practices, including reliance on other entities and processes to carry 
them out. For example, for the key practice of establishing a 
structured transition management approach, one of the practice 
components is identifying key local and regional transition officials 
and points of contact who are responsible for disseminating 
information. Homeland Security did not plan to identify such local and 
regional points of contact; officials stated that when 
telecommunications changes occur, the department will rely on processes 
already in place to convey information through departmental channels to 
local contacts. However, in view of the potentially large number of 
locations and short time frames involved in the transition, relying on 
the standard process could be risky. If Homeland Security does not 
identify all of its local points of contact before it begins 
transitioning services, communication difficulties could produce delays 
in providing the required site access for vendors (such delays occurred 
during the previous transition). Agencies that do not address such gaps 
in transition planning and follow through on their plans risk delaying 
their transitions and increase the likelihood that the government will 
incur unnecessary costs. 

Agencies Have Identified Transition Inventories, but Processes for 
Maintaining Them Are Not Yet in Place: 

As described in our 2006 report, sound transition planning practices 
include establishing an accurate inventory of current 
telecommunications assets and services. First, agencies should have a 
detailed and complete transition inventory that represents all of their 
facilities, components, field offices, and any other managed sites. It 
should include information such as telecommunications services, traffic 
volumes, equipment, and applications being used. Second, agencies 
should have a documented inventory maintenance process that can be used 
to ensure that inventories remain current and reflect changes leading 
up to, during, and after the transition. Once established, an inventory 
maintenance process can ensure that changes are captured and allow 
agencies to audit vendor bills against their inventories throughout the 
life of the contract. 

Agencies should begin efforts to establish a telecommunications 
inventory early because the development of an accurate and reliable 
inventory is important to ensuring that the agency will be prepared to 
transition quickly. Agencies can use their transition inventories to 
identify opportunities for optimizing their current technology during 
strategic planning and to help determine areas for optimization and/or 
sharing of IT resources across the agency. 

Table 1 summarizes the extent to which transition planners have 
established telecommunications inventories at the U.S. Army Corps of 
Engineers (ACE), Department of Homeland Security (DHS), Department of 
Commerce (DOC), U.S. Nuclear Regulatory Commission (NRC), Small 
Business Administration (SBA), and U.S. Department of Agriculture 
(USDA). 

Table 1: Telecommunications Inventory: 

Sound practice components: The agency has identified complete 
telecommunications inventories at every site, facility, and component 
for the transition from FTS2001; 
ACE: Practice component has been fully implemented; 
DHS: Practice component has been fully implemented; 
DOC: Practice component has been fully implemented; 
NRC: Practice component has been fully implemented; 
SBA: Practice component has been fully implemented; 
USDA: Practice component has been fully implemented. 

Sound practice components: The agency has a documented process for 
updating and maintaining its inventories; 
ACE: Practice component has been fully implemented; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency plans to fully implement practice component; 
SBA: Practice component has been fully implemented; 
USDA: Agency plans to fully implement practice component. 

Source: GAO analysis. 

[End of table] 

As the table shows, all agencies have addressed the first of the two 
components of this practice. All six identified telecommunications 
inventories that are sufficient for conducting their 
transitions.[Footnote 14] Those agencies with established 
telecommunications transition inventories are likely to be better 
prepared to address strategic considerations and avoid unnecessary 
transition delays associated with inventory identification. 

However, four of the six agencies had not documented a process to 
maintain their inventories to ensure that they remain current, although 
three had developed plans to do so: 

* Agriculture and Commerce have drafted inventory maintenance 
processes. 

* NRC's transition manager stated that the agency plans to develop a 
maintenance process as part of its efforts to establish an expense 
management system. 

Homeland Security does not plan to develop such a process. Homeland 
Security's transition manager stated that the department did not have a 
documented inventory maintenance process or policy at its headquarters 
or any of its components. The transition manager stated that the 
department has instructed its components to maintain their inventories. 
However, there was no documentation of this instruction, and the 
department did not have plans to document a maintenance process. 
Without a documented inventory maintenance process, agencies may not 
consistently and accurately capture the changes to their 
telecommunications inventories during and after transition, hindering 
their ability to ensure that they are billed appropriately by the 
vendor or to determine areas for optimization and sharing of 
telecommunications and IT resources across the agency. 

Half of the Agencies Have Incorporated Strategic Needs into Transition 
Planning: 

Sound transition planning practices, as described in our earlier work, 
include identifying strategic telecommunications requirements and 
incorporating them into transition planning. To accomplish this, 
agencies should use an inventory of existing services to determine 
current and future telecommunications needs. Agencies should also use 
the transition as an opportunity to identify areas for optimization or 
sharing of telecommunications and IT resources across the agency. The 
costs and benefits of introducing new technology and alternatives for 
meeting the agency's telecommunications needs should be evaluated. 
Further, the identified needs and opportunities should be aligned with 
the agency's mission, long-term IT plans, and enterprise architecture 
plans.[Footnote 15] The agency's telecommunications requirements should 
shape the agency's management approach to the transition and guide 
other efforts, such as identifying and allocating resources and 
developing a transition plan. 

Table 2 summarizes the extent to which the six agencies have performed 
a strategic analysis of telecommunications requirements. 

Table 2: Strategic Analysis of Telecommunications Requirements: 

Sound practice components: The agency has identified current and future 
telecommunications needs, areas for optimization and sharing, and the 
costs and benefits of any options; 
ACE: Practice component has been fully implemented; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency does not plan to fully implement practice component; 
SBA: Practice component has been fully implemented; 
USDA: Practice component has been fully implemented. 

Sound practice components: The agency has determined that needs and 
opportunities are aligned with its mission, long-term IT plans, and 
enterprise architecture plans; 
ACE: Practice component has been fully implemented; 
DHS: Practice component has been fully implemented; 
DOC: Practice component has been fully implemented; 
NRC: Practice component has been fully implemented; 
SBA: Practice component has been fully implemented; 
USDA: Practice component has been fully implemented. 

Source: GAO analysis. 

[End of table] 

As the table shows, all six agencies have addressed the second of the 
two components of this practice: all have determined that needs and 
opportunities are aligned with their missions, long-term IT plans, and 
enterprise architecture plans. However, only half (Agriculture, ACE, 
and SBA) have fully implemented the other component: identifying 
current and future telecommunications needs, areas for optimization and 
sharing, and the costs and benefits of any options. One agency 
(Commerce) has plans to fully implement this component. That is, 
Commerce has determined its current and future telecommunications needs 
and, according to officials, plans to identify areas for optimization 
and sharing, as well as costs and benefits, before completing the fair 
opportunity process. 

However, two agencies (NRC and Homeland Security) do not have plans to 
fully implement this practice: 

* NRC had identified current and future needs and established long-term 
plans to meet those needs, but it does not plan to evaluate the costs 
and benefits of alternatives to meeting its telecommunications needs 
for this transition. NRC officials stated that they plan to transition 
only existing services, and alternatives would not be evaluated until 
after transition. 

* Although Homeland Security's transition plans address strategic 
needs, the department did not evaluate the costs and benefits of new 
technology or alternatives for meeting its telecommunications needs. 
Homeland Security officials stated that they felt this activity was not 
appropriate because they did not have the choice not to transition to 
Networx. 

Without assessing the costs and benefits of alternatives for meeting 
their needs, NRC and Homeland Security may not be taking full advantage 
of the transition as an opportunity to optimize their 
telecommunications services, such as by upgrading and optimizing their 
telecommunications services, or shifting service to more cost-effective 
technology. Further, if agencies do not incorporate strategic 
requirements into their planning, they risk making decisions that are 
not aligned with their long-term goals. 

Most Agencies Have Developed or Plan to Develop a Structured Transition 
Management Approach: 

The sound transition planning practices that we identified in our 
earlier work include establishing a structured transition management 
approach. This entails establishing a transition management team 
involved in all phases of the transition and clearly defining 
responsibilities for key transition activities, such as project 
management, asset management, contract and legal expertise, human 
capital management, and information security management. The agency 
should also ensure a comprehensive understanding of the transition by 
identifying those who will be involved and how transition plans, 
including transition objectives, will be communicated. This also 
involves communicating what is going to happen and when, such as the 
frequency of status updates and meetings, and should include alerting 
and educating end users to changes or disruptions. Key local and 
regional transition officials and points of contact should be 
identified who are responsible for disseminating information to 
employees and working with the vendor to facilitate transition 
execution. 

In addition, the agency should ensure that it uses established project 
management, configuration management, and change management processes 
during the transition. Project management processes can be used to plan 
and manage transition-related activities, providing a structure that 
incorporates performance measurement and project-level control. 
Configuration management processes help ensure integrity and 
traceability as change occurs. Change management processes help 
employees prepare for the procedure and technology changes that may 
accompany a transition, reducing the risk that improvement efforts will 
fail. 

Table 3 summarizes the extent to which the six agencies have 
established a structured transition management approach. 

Table 3: Structured Transition Management Approach: 

Sound practice components: The agency has established a transition 
management team and clearly defined responsibilities for key transition 
roles; 
ACE: Practice component has been fully implemented; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Agency does not plan to fully implement practice component; 
NRC: Agency plans to fully implement practice component; 
SBA: Agency plans to fully implement practice component; 
USDA: Agency plans to fully implement practice component. 

Sound practice components: The agency has identified communication 
plans in order to facilitate information sharing during transition 
planning and execution; 
ACE: Agency plans to fully implement practice component; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency plans to fully implement practice component; 
SBA: Practice component has been fully implemented; 
USDA: Agency plans to fully implement practice component. 

Sound practice components: The agency is using project management, 
configuration management, and change management processes in the 
management of its transition planning efforts; 
ACE: Practice component has been fully implemented; 
DHS: Agency plans to fully implement practice component; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency plans to fully implement practice component; 
SBA: Agency plans to fully implement practice component; 
USDA: Agency plans to fully implement practice component. 

Source: GAO analysis. 

[End of table] 

With regard to the first component of this practice, one agency (ACE) 
established a transition management team and defined all key transition 
roles and responsibilities; the remaining five agencies have 
established management teams, but have yet to define all roles and 
responsibilities. Specifically, three agencies had not yet defined 
responsibilities for certain roles, but planned to do so: 

* Agriculture had not defined the role of legal expertise in its 
transition efforts, but it has requested support and was awaiting a 
response from its Office of General Counsel. 

* SBA had yet to define responsibility for asset management, but 
officials indicated that they plan to do so. 

* NRC had yet to define responsibility for information security 
management, but officials indicated that they planned to do so. 

The remaining two agencies did not plan to fully implement this sound 
practice component: 

* Commerce officials stated that the responsibilities for asset and 
human capital management will rest with the department's transition 
manager and each individual component; therefore, the department did 
not plan to define responsibilities for these roles. 

* Homeland Security officials stated that roles such as asset 
management, legal expertise, human capital management, and information 
security management would not be assigned by name because expertise in 
these areas would be available as needed. 

However, by not defining key roles and responsibilities for the 
transition, these agencies risk extending their transition period as 
they attempt to assign appropriate personnel and update them on 
transition progress and issues. 

With regard to the second component of this practice, one agency (SBA) 
identified communications plans and local and regional points of 
contact. Four additional agencies plan to fully address this sound 
practice component. Specifically: 

* Agriculture developed a communications plan, and its transition plans 
indicated that it will identify transition points of contact by the end 
of fiscal year 2008. 

* Commerce officials stated that they plan to develop transition and 
communications plans that will include transition points of contact. 

* A contractor supporting ACE's transition is required to develop a 
communications plan, and the ACE transition plan indicates that the 
contractor is in the process of identifying transition points of 
contact. 

* NRC officials stated that they plan to develop a communications plan 
as part of the agency's transition plan, which is to include transition 
points of contact. 

However, one agency (Homeland Security) does not plan to fully 
implement this sound practice component. Specifically, although it has 
established lines of communication, it had not identified local and 
regional points of contact to facilitate transition execution, because, 
according to department officials, when telecommunications changes 
occur, the department has a process in place to convey information 
through departmental channels to local contacts, and officials believe 
that this process will be adequate for any changes that are part of the 
transition. However, in view of the potentially large number of 
locations and short time frames involved in the transition, relying on 
the standard process could be risky. If Homeland Security does not 
identify all of its local points of contact before it begins 
transitioning services, communication difficulties could produce delays 
in providing the necessary site access for vendors (such delays 
occurred during the previous transition). 

With regard to the third component of this practice, ACE is the only 
agency currently using all three key management processes--project 
management, configuration management, and change management processes-
-in the management of its transition, but the other five agencies were 
using at least one of these management processes and planned to use all 
three. Officials at the five agencies generally provided policies or 
other documents indicating that all three processes would be used or 
stated that they planned to implement those not yet in use.[Footnote 
16] 

Agencies that do not use a sound management approach risk additional 
financial costs, extended time lines, and disruptions to the continuity 
of their telecommunication systems. Further, without establishing lines 
of communication and identifying local and regional points of contact, 
agencies may lack the quality of information that is necessary for 
comprehensive understanding, accountability, and shared expectations at 
all levels. 

Most Agencies Have Identified or Plan to Identify Resources Necessary 
for the Transition: 

Our sound transition planning practices include ensuring that the 
resources required to successfully plan for the transition are 
identified. To do so, the agency should identify any funding 
requirements for its transition planning efforts to ensure that 
resources needed are available. The organizational need for investments 
should be identified and the agency should assess benefits versus costs 
to justify any resource requests. Cost-benefit analyses and return-on- 
investment calculations are common methods used to justify requests. 
Transition planning costs that should be considered include transition 
project management, software and hardware upgrades, and establishing 
reliable inventories. 

The agency should also determine staffing levels that may be required 
throughout the transition effort, as well as ensure that personnel with 
the right skills are in place to support the transition effort. As 
mentioned earlier, some of the skills needed are project management, 
asset management, contract and legal expertise, human capital 
management, and information security expertise. Further, the agency 
should require training for those carrying out the transition or 
operating and maintaining newly transitioned technology. 

Identifying the need for resources early in the planning process is 
likely to help to avoid unnecessary spending and delays during the 
transition. Further, the resources allocated to the transition effort 
should reflect the level of change identified in the agency's strategic 
analysis of telecommunications requirements; that is, if the agency 
chooses to implement new technology, it must budget resources 
accordingly. 

Table 4 summarizes the extent to which the six agencies have identified 
resources for their transitions. 

Table 4: Resource Identification: 

Sound practice components: The agency has identified the level of 
funding needed to support transition planning, and justified 
organizational resource requests; 
ACE: Agency does not plan to fully implement practice component; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Practice component has been fully implemented; 
NRC: Agency does not plan to fully implement practice component; 
SBA: Practice component has been fully implemented; 
USDA: Practice component has been fully implemented. 

Sound practice components: The agency has identified human capital 
needs for the entire transition effort; 
ACE: Agency plans to fully implement practice component; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency plans to fully implement practice component; 
SBA: Practice component has been fully implemented; 
USDA: Practice component has been fully implemented. 

Sound practice components: The agency has required training for the 
transition; 
ACE: Practice component has been fully implemented; 
DHS: Practice component has been fully implemented; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency plans to fully implement practice component; 
SBA: Practice component has been fully implemented; 
USDA: Agency plans to fully implement practice component. 

Source: GAO analysis. 

[End of table] 

As table 4 shows, three agencies addressed the first component of this 
practice, having identified the level of funding needed to support 
transition planning efforts and justified organizational resource 
requests. However, three did not: Homeland Security, NRC, and ACE did 
not address funding requirements for their transition planning efforts 
before planning their transitions and, among other things, identifying 
inventories. Instead, the three agencies moved forward with performing 
transition planning using existing resources without having analyzed 
the sufficiency of these resources. At this late point in the planning 
process, performing such an analysis is no longer feasible. 

With regard to the second component, two agencies (SBA and Agriculture) 
have identified staffing levels that will be needed throughout the 
transition, and three plan to do so. ACE and Commerce provided evidence 
of efforts under way to identify staffing resources that will be 
needed, and NRC officials stated that they plan to address staffing 
levels in the agency's transition plan. 

Homeland Security indicated that although staffing specific to the 
transition effort was not identified, staffing for the transition was 
taken into consideration as part of the department's acquisition for a 
wide-area network under Networx. However, Homeland Security did not 
provide documentation to demonstrate that this sound practice component 
had been addressed. Without determining staffing needs for its 
transition effort, Homeland Security risks underestimating the 
complexity and demands of the transition, which may lead to delays and 
unexpected costs. 

As the table shows, three agencies have fully implemented the third 
component: Homeland Security, ACE, and SBA have required training for 
those involved in the transition. Of the remaining agencies, Commerce 
has a draft policy requiring those involved with the transition to meet 
certain training requirements, and a draft Agriculture transition plan 
indicated that training requirements will be addressed. NRC officials 
stated that they plan to identify training requirements in the agency's 
transition plan. 

As illustrated by lessons learned from the previous transition, 
agencies that do not fully analyze their transition-related resource 
needs may be underestimating the complexity and demands of the 
transition effort. Further, unexpected costs may arise that lead to 
delays and unnecessary spending that could have been avoided. 

The Agencies Have Generally Established Transition Plans, but None Have 
Established Measures of Success: 

The sound transition planning practices we identified include 
developing a transition plan that identifies transition objectives, 
measures of success, and risks, and that approaches the transition 
planning process as a critical project with a detailed time line. To 
facilitate this practice, agencies' transition management teams should 
undertake the following three activities: 

* The agency should identify transition objectives and measures of 
success. Transition objectives should be based on the agency's 
strategic analysis of telecommunications requirements and aligned with 
the agency's overall mission and business objectives. Measures of 
success should be based on these transition objectives. They are a key 
tool to help managers assess progress. 

* The agency should identify agency-specific risks that could affect 
transition success. The importance of the risks should be evaluated 
relative to the agency's mission-critical systems and continuity of 
operations plans. Knowing what risks exist and how to mitigate them 
appropriately will lessen problems and delays during the transition. 
This risk assessment should also include an analysis of information 
security risks to determine what controls are required to protect 
networks and what level of resources should be expended on controls. 

* The agency should develop a transition plan that depicts a management 
strategy with clearly defined transition preparation tasks and includes 
a time line that allows for periodic reporting. This time line should 
take into account priorities relative to the agency's mission-critical 
systems, contingency plans, and identified risks. 

Table 5 identifies the extent to which the agencies have developed 
plans for the transition. 

Table 5: Transition Plan: 

Sound practice components: The agency has identified and documented 
agency-specific transition objectives and measures of success; 
ACE: Agency plans to fully implement practice component; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency does not plan to fully implement practice component; 
SBA: Agency plans to fully implement practice component; 
USDA: Agency plans to fully implement practice component. 

Sound practice components: The agency has identified agency-specific 
risks that could affect transition success including information 
security risks; 
ACE: Agency plans to fully implement practice component; 
DHS: Agency does not plan to fully implement practice component; 
DOC: Agency plans to fully implement practice component; 
NRC: Agency plans to fully implement practice component; 
SBA: Agency plans to fully implement practice component; 
USDA: Agency plans to fully implement practice component. 

Sound practice components: The agency has clearly defined transition 
preparation tasks and developed a time line; 
ACE: Agency plans to fully implement practice component; 
DHS: Practice component has been fully implemented; 
DOC: Practice component has been fully implemented; 
NRC: Agency plans to fully implement practice component; 
SBA: Practice component has been fully implemented; 
USDA: Practice component has been fully implemented. 

Source: GAO analysis. 

[End of table] 

Four of the agencies have plans to fully implement the first component 
of this sound practice, with three having documented agency-specific 
transition objectives and the remaining planning to do so. And while 
none had yet established measures of success, officials at all four 
stated that they plan to do so. However, NRC and Homeland Security do 
not plan to fully address this component. 

* Although NRC officials stated that they plan to establish transition 
objectives, they do not plan to establish measures of success. Instead 
of establishing measures to assess progress toward agency goals, NRC 
officials stated that they plan to use GSA-established measures related 
to governmentwide transition progress. 

* Homeland Security officials stated that transition goals were 
discussed, but evidence was not provided, and the department had no 
plans to establish measures of success. Without documenting objectives 
for the transition, Homeland Security may find it difficult to provide 
those involved in the transition with clear expectations. 

Those agencies that do not establish measures of success based on 
documented objectives will lack information that could be used to track 
progress toward transition objectives and inform management decisions. 

Five agencies plan to fully implement the second component of this 
sound practice: identifying agency-specific risks that could affect 
transition success. Specifically, for ACE, Agriculture, and Commerce, 
the agencies' transition plans indicate that agency-specific transition 
risks will be identified. For SBA, a memorandum indicated that a formal 
risk assessment will be performed before the transition to Networx. For 
NRC, officials stated that risks will be addressed in the agency's 
transition plan and that information security risks will be addressed 
during the agency's fair opportunity process. 

One agency, however, did not have plans to fully address this sound 
practice component. Homeland Security performed a high-level risk 
assessment, but this assessment did not address risks to mission- 
critical systems, continuity of operations plans, or information 
security risks, which are key components of this practice. Homeland 
Security officials stated that information security risk assessments 
will be performed in accordance with federal requirements, but they do 
not intend to identify information security risks specific to their 
transition effort. If they do not analyze risks relevant to the 
transition, agencies may encounter problems and delays during the 
transition because they are not adequately prepared to mitigate risks. 

Four of the agencies fully implemented the third step of this practice, 
having transition plans that depicted a management strategy with 
clearly defined transition preparation tasks and included a time line 
that allowed for periodic reporting. The remaining two agencies' 
transition plans indicate that they will fully implement this sound 
practice component. 

Agencies that do not document measurable objectives and clearly define 
transition tasks that take into account agency priorities and risks may 
find it difficult to provide those involved in the transition with 
clear expectations or gauge transition success. Specifically, without 
measurable objectives, managers will lack information that could be 
used to track progress toward transition objectives and inform 
management decisions. 

GSA Is Taking Action to Identify and Resolve Common Transition 
Challenges: 

GSA is working with agencies and various forums to identify and resolve 
transition challenges facing agencies in making the transition to the 
Networx contracts. In working with agencies and vendors through such 
forums as the Interagency Management Council's Transition Working 
Group, and a transition help desk, GSA has identified challenges 
related to incumbent contractor support during the transition, defining 
responsibilities of agencies during the transition to ensure 
information security compliance, and use of a transition inventory 
application developed by GSA. To resolve the challenges, GSA has, among 
other things, modified incumbent FTS2001 contracts to help ensure 
contractor support during the transition, developed guidance to clarify 
agencies' information security responsibilities, and established 
support teams to assist agencies in using the inventory application 
developed by GSA. 

GSA Is Working through Various Forums to Identify Common Transition 
Challenges: 

As the lead agency for the Networx transition, GSA is responsible for 
ensuring that unnecessary delays in agency transitions are avoided, as 
well as minimizing agency transition costs and ensuring that all 
telecommunications services are transitioned in a timely manner. As 
part of its efforts to address its transition responsibilities, GSA is 
using various forums to identify transition challenges: 

* Transition Working Group (TWG)--A subgroup of the Interagency 
Management Council, TWG was created in May 2004 and serves as the 
primary avenue through which common transition challenges affecting 
agencies are identified. TWG is a bi-weekly forum for agency 
representatives. It promotes collective government planning related to 
the transition and assists with developing a consensus on common issues 
that affect multiple agencies. 

* Direct interaction with individual agencies--GSA interacts directly 
with agencies to provide them with individual assistance related to its 
various contract offerings, including FTS2001 and Networx. GSA has 
Technology Service Managers who are assigned to specific agencies to 
serve as single points of contact for GSA's contract offerings and 
provide support to agencies for, among other things, selection, 
ordering, implementation, and maintenance of FTS2001 and Networx 
services. GSA indicated that agencies can contact their Technology 
Service Managers to raise challenges specific to their agency. In 
addition to the Technology Service Managers, GSA's Director of Network 
Services Programs has been meeting individually with agency Chief 
Information Officers and other executive-level leadership to educate 
them on the benefits of Networx and prepare for the transition from 
FTS2001. 

* Regular interaction with vendors--GSA interacts with vendors in a 
number of ways, including regular meetings, vendor-required reporting 
to GSA, and GSA-initiated information requests. Specifically, GSA meets 
regularly with FTS2001 and Networx vendors (as often as weekly) to 
facilitate information sharing and to identify and resolve concerns or 
challenges. Vendors are also required to submit monthly status reports 
to GSA as well as provide quarterly program reviews. GSA has also 
requested information from its vendors to address specific issues. For 
example, GSA recently sent a request for information to the vendors to 
solicit strategies for enabling agency compliance with a recent 
initiative by the Office of Management and Budget (OMB) to improve 
governmentwide information security by reducing the number of Internet 
connections. 

* Networx Help Desk--The help desk is a resource for agencies and GSA 
to track and resolve agency-reported issues such as transition planning 
concerns, assistance with GSA tools, and identification of transition 
inventories. This help desk is part of GSA's Transition Coordination 
Center, a GSA-established team of GSA personnel and contractors tasked 
with facilitating the transition to Networx. The help desk addresses 
individual agency concerns or questions and develops weekly reports of 
help desk tickets that are reviewed and tracked by GSA. Using these 
tickets, GSA has created a knowledge database and identified frequently 
asked questions that are available for review by agencies. GSA 
officials stated that through the help desk they could likely identify 
vendors who deliver services late or provide inadequate support during 
the transition. As a result of GSA's efforts, a number of challenges 
have been identified: 

* Incumbent contractor cooperation--The FTS2001 contracts lacked 
requirements for the incumbent vendors to provide a certain level of 
support to meet agencies' needs during the transition to Networx. 

* Organizational conflicts of interest--Agencies found that they were 
unable to use current contractors providing telecommunications support 
to assist with the transitions to Networx if the particular contractors 
were also subcontractors of a Networx vendor. 

* Information security compliance--Agencies did not have a clear 
understanding of their responsibilities during the transition related 
to existing information security requirements. 

* GSA transition inventory application--Agencies encountered 
difficulties using an application developed by GSA to assist agencies 
in identifying their transition inventories. 

* Agencies' statements of work--Delays in the transition process could 
result from statements of work developed by agencies that include 
unclear requirements. 

* Contract modification process--Modifications to the Networx contracts 
require time and effort of both GSA and the vendors and may extend the 
amount of time required for an agency to transition. 

* OMB security initiative--The OMB initiative to reduce the number of 
government Internet connections (mentioned previously) may require 
agencies to revisit their Networx transition planning efforts. 

* Expansion of protest rights--Recent legislation permits protests of 
orders above $10 million under multiple-award task and delivery order 
contracts such as Networx; if an order is protested, it may delay an 
agency's transition. 

More detail on these challenges is presented in the discussion 
following. 

GSA Has Taken Action to Resolve Common Transition Challenges: 

GSA has taken various actions to resolve the identified common 
transition challenges. 

Incumbent Contractor Cooperation: 

In September 2006, TWG members expressed concern that FTS2001 incumbent 
vendor contracts did not include certain transition-related provisions. 
Specifically, the contracts did not require FTS2001 incumbent vendors 
to assist in the transition process by providing the ability for 
agencies to "fall back" on the incumbent vendors' services if a 
specific transition effort encountered difficulties. Agencies requested 
clarification on the level of effort required of the incumbent vendor 
to reestablish agency telecommunications services until transition 
issues could be remedied. 

GSA modified the FTS2001 contracts, including the FTS2001 crossover 
contracts, to address these issues. Specifically, all but two FTS2001 
crossover contracts were modified to include requirements for incumbent 
vendors to restore agency services in the event of problems with 
transition to new services. (GSA officials indicated that the remaining 
two contracts already included language to address this concern.) 
Modifications included provisions for the incumbent contractors to make 
a reasonable effort to promptly reactivate service if there was a 
problem with the successor contractor's service and it was necessary to 
fall back to the incumbent's service. In addition, modifications state 
that the incumbent contractor's point of contact should be available 
during scheduled cutovers to handle fallback requests. The inclusion of 
these terms in the FTS2001 contracts should help to reduce the risk 
that agencies' telecommunications transitions will be disrupted by the 
lack of cooperation by incumbent contractors, as well as help to ensure 
that unnecessary delays are avoided if agencies encounter difficulties 
in transitioning to a new contractor. 

Organizational Conflicts of Interest: 

During a September 2007 meeting, TWG members identified a concern 
regarding contractor organizational conflicts of interest.[Footnote 17] 
Specifically, agencies found that they were unable to use certain 
current contractors providing telecommunications support to assist with 
the transition to Networx because these contractors were also 
subcontractors of Networx vendors, and the agencies' use of such a 
subcontractor could give a Networx vendor an unfair competitive 
advantage. The Federal Acquisition Regulation (FAR) calls for the 
exercise of good judgment to resolve a potential organizational 
conflict of interest and requires appropriate action to avoid, 
neutralize, or mitigate the potential conflict.[Footnote 18] 

To address this challenge, GSA has modified Networx contracts to allow 
agencies to use their existing contractor support within defined 
boundaries. For example, the modification requires contractors 
supporting an agency to (1) avoid situations with the risk of 
unauthorized disclosure of information, (2) refuse to divulge 
information about the agency's program, and (3) report conflicts of 
interest. The modification also calls for contractors to train their 
employees on the Procurement Integrity Act[Footnote 19] and its 
penalties. Thus, GSA has established a framework for agencies and 
contractors to follow that is intended to address potential or actual 
organizational conflicts of interest. Agencies remain responsible for 
taking steps to avoid, neutralize, and mitigate conflicts of interest 
in using contractors. 

Information Security Compliance: 

The TWG expressed concern that responsibilities related to the Federal 
Information Security Management Act of 2002[Footnote 20] were unclear. 
Specifically, agencies were unsure of their responsibilities for 
information security under Networx versus those of GSA and the vendors. 
For example, agencies requested clarification on government 
responsibility to certify and accredit[Footnote 21] the public network 
during transition and GSA's information security responsibilities as 
the agency providing the contract vehicle for telecommunications 
services. 

GSA, in consultation with OMB, has provided guidance to agencies that 
addresses information security concerns for transition. Specifically, a 
GSA briefing to agencies clarifies that agencies are responsible for 
determining the impact of the transition on the certification and 
accreditation of their systems. In addition, GSA clarified that its 
responsibilities, as the manager of the contract vehicle, includes, 
among other things, reviewing contractor security plans and reports in 
accordance with the provisions of the contract; monitoring and 
resolving security issues during the life of the contract; conducting 
post-award certification and accreditation of contract awardees' 
support systems; and conducting certification and accreditation on 
GSA's billing system related to Networx. GSA's actions should help 
ensure that information security during the transition will be 
adequately addressed. 

GSA Transition Inventory Application: 

The TWG indicated that agencies were having difficulties using an 
application developed by GSA to validate their telecommunications 
inventories for the transition. In January 2007, GSA created an initial 
governmentwide inventory using FTS2001 vendor billing reports, with the 
intention of using it to track transition status and aid agencies in 
planning for their transitions. To assist in this effort, GSA required 
agencies to validate their inventory using a GSA inventory application. 
As agencies worked to validate these inventories, the TWG indicated 
that agencies encountered difficulties with the application and that 
the process for validating their inventories was not clearly defined. 

To address this challenge, GSA has taken several actions. GSA has 
issued user guidance for its inventory application and has briefed the 
TWG on the inventory validation process. GSA has also established 
inventory assistance teams to work with agencies to identify and 
validate their inventories. These inventory assistance teams are 
assigned at the request of an agency and include GSA personnel and 
contracted support staff. From September to December 2007, inventory 
assistance teams worked with 43 agencies to provide assistance with 
validating their inventories. As a result, when GSA established a 
baseline in January 2008 of the government's inventory to be used to 
measure transition progress, federal agencies had validated about 92 
percent of the almost 4.1 million records in the inventory. As a result 
of its actions, GSA has increased the chances of a successful 
transition by helping to ensure that agencies have available to them 
accurate inventory information. 

Agencies' Statements of Work: 

GSA and several of the Networx vendors identified concerns about the 
quality of agency statements of work and possible delays as a result of 
unclear statements of work. An agency will develop a statement of work 
when its telecommunications requirements cannot be met using existing 
offerings in the Networx contract. Since statements of work are 
particular, those with unclear requirements could extend the time 
required for GSA to review and determine whether a modification is 
necessary. According to Networx vendors, an unclear statement of work 
may also require additional time as they review it to clarify and 
understand agency requirements. Lack of clarity may also result in an 
agency receiving disparate proposals from vendors, which may not all 
meet the agency's particular needs. Finally, GSA officials stated that 
there are fewer contracting staff (the personnel responsible for 
reviewing agency statements of work) assigned to Networx than were 
assigned to FTS2001. A limited number of staff may increase the amount 
of time needed for GSA's review of agency statements of work. 

GSA is taking action to address concerns related to the quality of 
statements of work. First, GSA has developed a "Fair Opportunity and 
Statement of Work Guide," intended to provide agencies with a set of 
uniform ordering guidelines to obtain services under the Networx 
contacts. This guide addresses the definition and documentation of 
agency requirements, describes how to determine if a statement of work 
is needed, and states that GSA has advisory and consulting services 
available to agencies. Second, GSA officials stated that after an 
agency submits its finalized statement of work to GSA, it is reviewed 
for possible legal, pricing, contracting, management, and technical 
issues, as well as to determine whether there are opportunities for the 
agency's needs to be met using existing Networx service offerings. If 
concerns or errors are identified, the statement of work is rejected, 
the agency is briefed on the cause of rejection, and the agency must 
revise its statement of work. Finally, to address the limited number of 
contracting staff, GSA officials stated that they plan to add 
additional staff to better facilitate the contract review process. The 
actions being taken by GSA should help address issues regarding the 
quality of statements of work developed by agencies and submitted to 
vendors. 

Contract Modification Process: 

Contract modifications require time and effort, from both GSA and the 
vendors, to negotiate the terms of the modification and eventually 
extend the amount of time required for an agency to transition. In 
addition to its responsibility for overseeing the transition, GSA has 
administrative responsibility for processing and authorizing contract 
modifications. Modifications to the Networx contract are essential to 
allow agencies to place orders against requirements that are within the 
scope of the Networx contract, but that are not currently available as 
fixed price contract items. Contract modifications can also be 
initiated (1) by a vendor desiring to add or change specific service 
offerings or (2) as a result of a Networx program need determined by 
GSA. Also, as previously discussed, GSA officials stated that they have 
fewer personnel assigned to Networx who are responsible for reviewing 
and incorporating contract modifications than were assigned to the 
transition to FTS2001. 

To address concerns with the contract modification process, GSA 
identified existing and planned actions. First, the initial review of 
agencies' statements of work is, in part, designed to identify whether 
a modification is necessary. Second, GSA developed a contract 
modification guide to inform those involved of the process for 
modifying contracts. Third, in April 2008, it took steps to automate 
certain aspects of the contract modification process. For example, 
contractors can now draft, submit, and update contract modifications 
using an Internet-based application. In addition, according to GSA 
officials, contractors can also use this application to track the 
modification throughout the process. Last, the previously mentioned 
planned increase in contract review staff will also be used to 
facilitate the processing of contract modifications. 

As a result of actions taken, GSA is making progress in meeting its 
goals for processing contract modifications. Its "Fair Opportunity and 
Statement of Work Guide" indicates that the majority of modifications 
should be completed within 30 business days. As of May 2008, the time 
to complete a contract modification varied from 1 business day to more 
than 106 business days; about 49 percent of its modifications had been 
made within 30 days. However, many of these took place before GSA had 
implemented its automated contract modification tools. These tools and 
the other actions GSA has taken have the potential to minimize contract 
modification delays. 

OMB Security Initiative: 

In November 2007, OMB issued a memorandum to improve governmentwide 
information security. This initiative, called the Trusted Internet 
Connections initiative, seeks to lessen information security risks by 
reducing the number of Internet connections maintained by the 
government. OMB has asked agencies to analyze and resolve any effects 
of this initiative on, among other things, planning related to the 
agencies' use of the Networx contracts. Therefore, agencies may have to 
revisit their Networx transition planning efforts if, for example, they 
find it necessary to reconfigure their networks to enable the use of 
fewer Internet connections. 

In response to this initiative, GSA asked Networx vendors to identify 
(1) how they can help agencies to meet the goals of the initiative and 
(2) any concerns. GSA summarized the vendors' feedback and on February 
25, 2008, it presented the results to OMB, which is leading the 
initiative in conjunction with Homeland Security. The summary indicated 
multiple areas of support that vendors are willing to provide agencies, 
such as assisting agencies in performing a complete inventory and 
discovery of all agency Internet connections. In addition, it indicated 
that the Networx contracts may need to be modified to allow vendors to 
offer several of these services. GSA stated that detailed requirements 
for this initiative have yet to be fully developed by Homeland Security 
and that, as of May 2, 2008, no specific modifications to existing 
Networx contract offerings have been identified as necessary. GSA is, 
however, working with Homeland Security to define detailed requirements 
for a new service offering under Networx to provide a trusted Internet 
portal service; it expects this service to be available to the agencies 
by November 2008. The actions GSA is taking and has planned should help 
to ensure that the Networx contracts can be used by agencies to address 
OMB's Trusted Internet Connections initiative. 

Expansion of Protest Rights: 

Recent legislation permits protests of orders above $10 million under 
multiple-award task and delivery order contracts such as 
Networx.[Footnote 22] Beginning May 27, 2008, the recently enacted 
National Defense Authorization Act for Fiscal Year 2008 authorizes bid 
protests of such orders; previously, protests were authorized only when 
an order increased the scope, period, or maximum value of the contract 
under which the order was issued. The protest of an agency's order may 
affect the time available to the agency to complete its transition. 

Although officials stated that the impact of this legislation on agency 
transitions cannot be known at this time, GSA has briefed IMC members, 
TWG members, and agency transition managers on this legislation. The 
briefing provided information on the terms of the legislation, and 
informed agencies of their expected responsibilities as well as GSA's 
expected role. For example, the briefing indicated that GSA may be 
asked to provide input in the event of a protest, but the agency that 
issued the order would have primary responsibility to defend the 
protest. In addition, GSA revised its "Fair Opportunity and Statement 
of Work Guide" to reflect this new legislation. Further, officials 
stated that they are responding to agency questions, through the 
Networx help desk, regarding the bid protest process. GSA's actions 
have helped to inform agency transition officials of their 
responsibilities and the impact this legislation may have on their 
ordering process. 

Conclusions: 

Transitioning federal telecommunications services is a large and 
complex undertaking. The previous transition resulted in significant 
delays and increased costs, taking more than 2 years to complete, which 
underscores the importance of making necessary preparations before 
starting such an effort. For the current transition, selected agencies 
are generally following our sound transition practices, which should 
help them avoid some of the delays experienced previously. However, 
Homeland Security, Commerce, and NRC are not planning to fully 
implement key sound practices. Because the period to conduct their 
telecommunications transitions is limited, agencies will be better 
prepared if they consistently implement all of the sound practices. If 
they do not, they risk being unable to complete their transitions 
before the expiration of the FTS2001 contracts and increase the 
likelihood that the government will incur unnecessary costs. 

In managing its $20 billion Networx program, GSA has taken actions to 
identify and resolve common transition challenges, including developing 
guidance for agency statements of work and creating teams to assist 
agencies in establishing transition inventories. These actions should 
help to reduce the risk that challenges will lead to unnecessary 
transition delays and costs for agencies. Going forward, GSA's 
responsibility as facilitator for the Networx transition will continue 
to require it to proactively identify and resolve common transition 
challenges, complete actions planned to resolve already identified 
challenges, and monitor transition progress. 

Recommendations for Executive Action: 

To reduce the risk that transition delays could lead to disruptions in 
service and increased costs, we are making the following 10 
recommendations: 

We recommend that the Secretary of Commerce direct the department's 
Chief Information Officer to define the roles of asset and human 
capital management for the department's transition. 

We recommend that the Chairman of the U.S. Nuclear Regulatory 
Commission direct the commission's Chief Information Officer to: 

* establish measures of success based on the transition objectives that 
the agency plans to develop and: 

* evaluate the costs and benefits of new technology or alternatives to 
meeting its telecommunications needs. 

We recommend that the Secretary of Homeland Security direct the 
department's Chief Information Officer to address the gaps in its 
transition planning. Specifically, the Chief Information Officer 
should: 

* document the department's processes for maintaining 
telecommunications inventories; 

* evaluate the costs and benefits of new technology or alternatives to 
meeting its telecommunications needs; 

* clearly define the roles of asset management, legal expertise, human 
capital management, and information security expertise for the 
department's transition; 

* identify local and regional points of contact; 

* include in the department's planning efforts the identification of 
human capital resources needed to conduct an effective transition; 

* establish goals and measures of success for the department's 
transition efforts to help managers assess progress; and: 

* perform a transition risk assessment that addresses risks to mission- 
critical systems, continuity of operations plans, and risks to 
information security. 

Agency Comments and Our Evaluation: 

In commenting on a draft of our report, three of the seven agencies 
reviewed generally agreed with our report, and two agencies partially 
agreed. GSA, Commerce, NRC, and Homeland Security provided written 
comments (which are reproduced in apps. II through V), and SBA provided 
comments via e-mail. Two agencies, Agriculture and U.S. Army Corps of 
Engineers, indicated via e-mail that they had no comments. 

Officials from GSA, Commerce, and SBA generally agreed with our 
findings: 

* The Acting Administrator of GSA concurred with the information 
pertaining to GSA and expressed appreciation for our acknowledgment of 
the actions the agency had taken. 

* Commerce's Chief Information Officer indicated that the report 
provided a fair assessment of the department's progress and status to 
date. 

* A program manager in SBA's Office of Congressional and Legislative 
Affairs indicated that SBA was satisfied with our findings regarding 
the agency. 

NRC and the Department of Homeland Security partially agreed with our 
report. NRC's Executive Director for Operations indicated that our 
report generally reflects the issues surrounding agency preparedness 
for transition. However, the official suggested that we remove our 
recommendation that the Commission evaluate the costs and benefits of 
new technology or alternatives because such an evaluation had been and 
would be conducted as part of the agency's normal planning processes. 
However, our recommendation remains because the Commission did not 
perform this activity specifically for the transition to Networx. 
Performing such an analysis would provide the Commission with the 
opportunity to optimize its telecommunications services in the light of 
its present and projected needs. The Executive Director also provided 
technical comments, which we incorporated into our report as 
appropriate; our assessment of these comments is contained in appendix 
IV. 

The Acting Director of Homeland Security's Departmental Audit Liaison 
Office indicated partial agreement with our report. In particular, 
regarding our recommendations that Homeland Security establish goals 
and measures of success and perform a transition risk assessment, the 
department agreed that a more structured communication of transition 
objectives and a specific risk management process for transition would 
be beneficial. However, this official indicated that the department 
disagreed with five of our recommendations and with a finding regarding 
its transition communications planning. The department's comments 
reiterated information on actions that it had taken in these areas that 
it considered to meet the goals of the sound practices. However, these 
actions are already reflected in our assessment. The specific areas of 
disagreement are as follows: 

* Regarding our recommendation that the department document its 
processes for maintaining telecommunications inventories, the official 
acknowledged that the department does not have a documented inventory 
maintenance process, but stated that our observation was in conflict 
with our finding that it had identified a complete telecommunications 
inventory. The official added that the department has instructed its 
components to maintain their inventories using a GSA tool and 
documented GSA procedures. However, our finding that the department had 
established an inventory for transition is not in conflict with the 
recommendation. While the department had addressed one component of 
this sound practice by establishing an inventory for transition, it had 
not taken the necessary action to address the other component; it had 
not documented the process to be used by its components for inventory 
maintenance. Specifically, this sound practice component calls for a 
documented inventory maintenance process to lessen the risk that 
changes to the inventory during and after transition would not be 
consistently and accurately captured. 

* Regarding our recommendation that the department evaluate the costs 
and benefits of new technology or alternatives to meeting its 
telecommunications needs, the official indicated that this was in 
conflict with our related finding that the department had aligned needs 
and opportunities with its mission, long-term IT plans, and enterprise 
architecture plans. The official added that its fair opportunity 
efforts will include service and cost analyses. However, our 
recommendation is not in conflict with the identified finding. 
Specifically, although the department's transition plans addressed 
strategic needs, it had not performed an analysis of costs and benefits 
of new technology or alternatives for meeting those needs. Regarding 
decisions made during the fair opportunity process, our recommendation 
refers to the sound transition practice of performing a strategic 
analysis based on agencywide telecommunications needs, with the results 
of this analysis being used to shape the agency's transition management 
approach, transition plan development, and allocation of resources. In 
contrast, the fair opportunity process involves selecting a vendor for 
the agency's service orders; at that point in the process, the agency 
should have already identified services to order. Therefore, to be 
effective, an agency's evaluation of costs and benefits of new 
technology and alternatives would need to take place before the 
department's fair opportunity efforts. 

* Regarding our recommendation that the department clearly define the 
roles of asset management, legal expertise, human capital management, 
and information security expertise, the official indicated that the 
department can call upon these specialty disciplines as needed. 
However, by taking this approach, Homeland Security risks encountering 
delays as officials attempt to assign personnel in a time of need and 
bring them up to date on transition progress and issues. Defining such 
roles at the outset, as advocated by sound transition planning 
practices, would help avoid such delays. 

* Regarding our recommendation that the department identify local and 
regional points of contact, the official stated that we had suggested 
that the department should identify all personnel that might be 
involved in any kind of telecommunication change and stated that such 
an effort would include thousands of individuals across the department 
and all IT field support personnel. Rather than contacting all these 
personnel, the Acting Director indicated that the department had taken 
steps to alert key managers at each component. However, this sound 
practice does not involve identifying all personnel that might be 
involved in any telecommunications change, but rather only identifying 
those contacts that will be responsible for facilitating the 
transition. For example, a contact is needed for each location where 
service is provided to facilitate physical access to equipment during a 
transition. Homeland Security's decision to not identify all contacts 
responsible for facilitating the transition does not follow sound 
transition planning practices and increases the risk that it will 
experience delays in providing the necessary site access for vendors. 

* Regarding our recommendation that the department identify human 
capital resources needed to conduct an effective transition, the 
official indicated the department did identify funding and staffing for 
transition planning. However, our recommendation is that Homeland 
Security determine human capital resources needed throughout the entire 
transition effort--not simply the planning effort. 

* The official acknowledged that Homeland Security had not published a 
Networx transition communications plan, but stated that the charter for 
its transition work group defined essential communications and 
activities. Our report indicates that the department has established 
lines of communication in its charter, but as previously discussed, it 
had not identified local and regional points of contact. Thus, the 
department's communications planning is incomplete. If Homeland 
Security does not identify all of its local points of contact before it 
begins transitioning services, communication difficulties could produce 
delays in providing the necessary site access for vendors. 

As agreed with your staff, unless you publicly announce the contents of 
this report earlier, we plan no further distribution of this report 
until 30 days from the report date. At that time, we will send copies 
of this report to other interested congressional committees, the 
Administrators of General Services and the Small Business 
Administration; the Chairman of the U.S. Nuclear Regulatory Commission; 
and the Secretaries of Agriculture, Commerce, Defense, and Homeland 
Security. We will also make copies available to others upon request. In 
addition, the report will be available at no charge on the GAO Web site 
at [hyperlink, http://www.gao.gov]. 

If you or your staff have any questions about this report, please 
contact me at (202) 512-6240 or by e-mail at koontzl@gao.gov. Contact 
points for our Offices of Congressional Relations and Public Affairs 
may be found on the last page of this report. Key contributors to this 
report are listed in appendix VI. 

Signed by: 

Linda D. Koontz: 

Director, Information Management Issues: 

[End of section] 

Appendix I: Objectives, Scope, and Methodology: 

Our objectives were to determine (1) the extent to which federal 
agencies are following sound transition planning practices and (2) the 
actions the General Services Administration (GSA) is taking to identify 
and resolve common transition challenges affecting agencies. 

To determine the extent to which agencies are following sound 
transition planning practices, we selected six agencies for review. 
Using FTS2001 billing data provided by GSA, we identified total charges 
for each agency for fiscal year 2006. These totals ranged from over 
$145,000,000 to as low as $28 for 127 separate entities. We then 
reduced the number of entities under consideration to a more manageable 
number by identifying agencies with total charges in excess of $1 
million for fiscal year 2006. From this group of agencies, we made a 
judgmental selection of six agencies that were representative of (1) 
varying types of organization, including executive departments, 
subagencies, and independent agencies; (2) varying levels of attendance 
in the Transition Working Group, an agency forum that is assisting GSA 
in its efforts to plan for the transition; and (3) the entire range of 
agency charges in excess of $1 million. The departments and agencies 
selected for review were the Department of Homeland Security; 
Department of Commerce; U.S. Department of Agriculture; Small Business 
Administration; U.S. Army Corps of Engineers, a component of the 
Department of Defense; and U.S. Nuclear Regulatory Commission. 

Because we judgmentally selected the agencies in our review, we cannot 
conclude that our results represent the entire federal government's 
level of preparation. However, the six cases studied illustrate various 
challenges that agencies may face in planning for the transition to 
Networx. 

To determine the extent to which the selected agencies have made 
adequate preparations for their upcoming transitions, we obtained and 
reviewed agency documentation, including but not limited to strategic 
plans, telecommunications inventories, and transition-related plans, 
and interviewed agency officials. We then assessed this information 
against the five sound transition planning practices identified in our 
prior report on agency transition planning.[Footnote 23] These 
practices are (1) establish a telecommunications inventory, (2) perform 
a strategic analysis of telecommunications requirements, (3) establish 
a structured transition management approach, (4) identify resources, 
and (5) develop a transition plan. Each of these sound planning 
practices consists of various components (for example, developing a 
transition plan consists of (1) identifying and documenting objectives 
and measures of success; (2) determining risks that could affect 
success; and (3) defining transition preparation tasks and developing a 
time line for these tasks). 

Based on our assessment, we classified the status of agency transition 
planning efforts to address each sound practice component as "fully 
implemented," if the agency has fully implemented the sound practice 
component; "plans to fully implement," if the agency has plans to fully 
implement the component; or "no plans to fully implement," if the 
agency does not have plans to fully implement it. We discussed our 
assessments with agency officials and made adjustments as appropriate. 

To evaluate one of the sound practices, establishing a 
telecommunications inventory, we developed criteria to assess the 
extent to which agencies had identified complete transition 
inventories. First, based on data provided by GSA, we determined 
whether each agency had validated 90 percent or more of its inventory. 
Second, we administered a questionnaire to determine whether each 
agency had adequate quality control mechanisms in place to identify and 
maintain its inventory.[Footnote 24] If these two criteria were met, we 
considered the inventory to be sufficient for a telecommunications 
transition. 

To determine the actions that GSA is taking to identify and resolve 
common transition challenges affecting agencies, we reviewed transition 
guidance and other Networx documentation developed by GSA and the 
Transition Working Group (TWG) of the Interagency Management Council 
(IMC), including presentations, meeting minutes, projected time lines, 
GSA's "Fair Opportunity and Statement of Work Guide," and the TWG's 
"Networx Transition Guide (Pre-Award)"; interviewed FTS2001 incumbent 
vendors and Networx vendors (AT&T, Level3 Communications, Qwest, 
Sprint, and Verizon Business) and the six agencies selected for review; 
and interviewed GSA officials to identify challenges, guidance, and GSA 
current and planned actions for the Networx transition. We assessed 
GSA's efforts to resolve identified challenges by analyzing 
documentation and testimonial evidence from GSA on any actions taken to 
address them. 

We performed our work at the Washington, D.C., area offices of the 
Department of Homeland Security, Department of Commerce, Department of 
Defense, Small Business Administration, U.S. Army Corps of Engineers, 
U.S. Department of Agriculture, U.S. Nuclear Regulatory Commission, and 
the General Services Administration. We conducted this performance 
audit from September 2007 through June 2008, in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

[End of section] 

Appendix II: Comments from the General Services Administration: 

GSA: 
U.S. General Services Administration: 
1800 F Street. NW: 
Washington, DC 20405-0002: 
Telephone (202) 501.0800 Fax: (202) 2t9-1243
[hyperlink, http://www.gsa.gov]: 

GSA Administrator: 

June 11, 2008: 

The Honorable Gene L. Dodaro: 
Acting Comptroller General of the United States: 
U.S. Government Accountability Office: 
Washington, DC 20548: 

Dear Mr. Dodaro: 

The U.S. General Services Administration (GSA) thanks you for the 
opportunity to review and comment on the draft report, 
"Telecommunications: Agencies Are Generally Following Sound Transition 
Planning Practices, and GSA Is Taking Action to Resolve Challenges" 
(GAO-08-759). We concur with the information pertaining to GSA and 
appreciate your acknowledgement of the actions we have taken. 

If you have any questions, please contact me. Staff inquiries may be 
directed to Mr. Kevin Messner, Associate Administrator, Office of 
Congressional and Intergovernmental Affairs, at (202) 501-0563. 

Sincerely, 

Signed by: 

David L. Bibb: 
Acting Administrator: 

cc:
Ms. Linda Koontz: 
Director: 
Information Management Issues: 
U.S. Government Accountability Office: 
Washington, DC 20548: 

[End of section] 

Appendix III: Comments from the Department of Commerce: 

United States Department Of Commerce: 
Chief Information Officer: 
Washington, D.C. 20230: 

June 12, 2008:

Ms. Linda Koontz: 
Director, Information Management Issues: 
Government Accountability Office: 
441 G. Street, N.W.: 
Washington, D.C. 20548: 

Dear Ms. Koontz: 

Thank you for the opportunity to review the draft report, GAO 08-729 – 
Telecommunications: Agencies Are Generally Following Sound Transition 
Planning Practices, and GSA Is Taking Action to Resolve Challenges, 
dated June 2008. 

The report provides a thorough examination and assessment of Federal 
government activities, and procedures to support the transition from 
the GSA's Telecommunications program, FTS2001 to the successor program, 
Networx. The report provides a fair assessment of the Department of 
Commerce progress and status to date. 

We have no substantial comments or changes to recommend at this time. 
Please let us know if you have questions or need additional 
information. Our Department of Commerce point of contact is Ms. 
Demetria Blyther, she can be reached at (202) 482-0267 or at 
DBlytheru@doc.gov. 

Sincerely, 

Signed by: 

Suzanne Hilding: 
Chief Information Officer: 

[End of section] 

Appendix IV: Comments from the U.S. Nuclear Regulatory Commission: 

Note: GAO comments supplementing those in the report text appear at the 
end of this appendix. 

United States Nuclear Regulatory Commission: 
Washington 20555-0001: 

June 13, 2008: 

Ms. Linda Koontz, Director: 
Information Management Issues: 
Government Accountability Office: 
441 G Street, NW: 
Washington, D.C. 20548: 

Dear Ms. Koontz: 

The U.S. Nuclear Regulatory Commission (NRC) appreciates the 
opportunity to provide comments on the draft report entitled, 
"Telecommunications: Agencies Are Generally Following Sound Transition 
Planning Practices, and GSA Is Taking Action to Resolve Challenges" 
(GAO-08-759). The NRC's comments are enclosed for your consideration 
and inclusion in the final report as mentioned in your letter of May 
27, 2008. 

Please direct any questions or concerns that you may have on NRC's 
comments to Mr. Jesse Arildsen, at (301) 415-1785 or email to 
Jesse.Arildsen@nrc.gov. 

Sincerely,

Signed by: 

R. W. Borchardt: 
Executive Director for Operations: 

Enclosure: As stated: 
cc: J. Sweetman, GAO: 

U.S. Nuclear Regulatory Commission Comments on GAO Draft Report, 
"Telecommunications: Agencies Are Generally Following Sound Transition 
Planning Practices, And GSA is Taking Action To Resolve Challenges" 
(GAO-08-759): 

In general, the document reflects the issues surrounding agency 
preparedness to transition from the existing FTS 2001 Bridge contracts 
to the new Networx contracts provided by the General Services 
Administration (GSA). However, additional credit could be given to the 
Interagency Management Council (IMC) for solving agency problems. Many 
of the solutions that were put in place by GSA were as a result of a 
collegial effort between the IMC member agencies and the GSA Networx 
Program Management Office. (Reference Page 6, second paragraph first 
sentence) 

(See comment 1.): 


The U.S. Nuclear Regulatory Commission's (NRC) telecommunications 
infrastructure requirements are driven by the Information Technology 
requirements in support of the agency mission and goals. The FTS 2001 
and FTS 2001 Bridge contracts offered many full service features which 
allowed the NRC to expand its telecommunications infrastructure in 
support of agency requirements. NRC has been able to realize cost 
avoidance measures and other benefits while participating in the 
program. As NRC infrastructure and application requirements mature, the 
agency will evaluate the Networx advanced offerings which may prove 
beneficial. The telecommunications infrastructure at the NRC is planned 
as a component of the overall agency Enterprise Architecture and future 
enhancements will be vetted through our Capital Planning and Investment 
Control processes. (Reference Page 24, second paragraph). 

(See comment 2.): 

The GSA Networx Program Management Office in conjunction with the IMC 
Transition Working Group (TWG) spent a considerable amount of time and 
effort to define how the Government would monitor, track, collate, and 
report Transition status and progress. Tools were developed such as the 
Transition Management Portal (TMP) to allow both GSA and the Agencies 
to view the status of transition from both a government wide 
perspective as well as individual agency perspective. This tool along 
with others (i.e. Transition Baseline Inventory (TBI)) was developed in 
order to conform to previous GAO guidance with respect to the 
transition. (Reference Page 32, second paragraph.) 

(See comment 3.): 

The introduction of the Office of Management and Budget (OMB) Trusted 
Internet Connection (TIC) as a "transition" challenge is not 
categorized correctly. The transition of services as defined by GSA is, 
". as the movement of services from the FTS2001 contracts to Networx 
and continues until the disconnection of all services from the FTS2001 
contracts." Since the TIC is not a current service offering under 
either the FTS 2001 or the Networx contracts, it should be considered 
as an implementation rather than a transition issue. An agency that 
takes time to consider the TIC alternatives as part of their transition 
will experience delays in their Fair Opportunity selections and 
execution of transition tasks. (Reference Page 36, fifth paragraph.) 

(See comment 4.): 

Two recommendations are made to the NRC in the report. It is suggested 
that the first suggestion be modified to say: 

* establish measures of success based upon agency specific transition 
objectives that the agency plans to develop using the tools provided by 
GSA and the IMC as source data 

It is further suggested that the second suggestion be removed, since an 
evaluation of costs and benefits of new technology or alternatives to 
meet the agency telecommunications needs has been and will be conducted 
as a part of NRC's normal planning processes. (Reference Page 45 
"Recommendations", third paragraph.) 

(See comment 5.): 

Enclosure: 

The following is GAO's response to the U.S. Nuclear Regulatory 
Commission's letter dated June 13, 2008. 

GAO Comments: 

1. We clarified our report to better reflect the role of the IMC. 

2. NRC's comment references our statement that it did not plan to 
evaluate the costs and benefits of alternatives to meeting its 
telecommunications needs. The official stated that, as its requirements 
mature, the agency will evaluate the Networx advanced offerings that 
may prove beneficial. However, sound transition planning calls for 
performing a cost benefit and analysis specifically for the agency's 
transition effort as part of a strategic analysis that should be used 
to shape the agency's transition management approach, transition plan 
development, and allocation of resources. NRC has not performed this 
activity for the transition. 

3. NRC's comment references our statement that it did not plan to 
establish measures of success to assess progress toward its goals. NRC 
indicated that it plans to use GSA-established measures related to 
transition progress and identified various tracking tools. However, NRC 
has not established agency-specific objectives for its transition and, 
by limiting measures of success to those established by GSA, NRC may 
lack information that could be used to track its progress in achieving 
its own goals and to inform its own management decisions. 

4. We disagree with NRC's statement that the introduction of the Office 
of Management and Budget's Trusted Internet Connection (TIC) initiative 
should not be characterized as a transition issue. As NRC goes on to 
state, agencies that take time to address considerations relative to 
TIC may experience delays in their efforts to transition. We consider 
this a challenge that may affect agency transitions. 

5. We do not agree with the suggested modification to our 
recommendation. NRC's suggestion would limit its measures of success to 
those emphasized by GSA, such as measures of transition progress. 
However, sound practices call for agencies to establish measures for 
each of its transition objectives to help managers assess the extent to 
which those objectives are achieved. 

[End of section] 

Appendix V: Comments from the Department of Homeland Security: 

U.S. Department of Homeland Security: 
Washington, DC 20528: 

Homeland Security: 

June 16, 2008: 

Ms. Linda D. Koontz: 
Director, Information Management Issues: 
United States Government Accountability Office: 
Washington, DC 20548: 

Dear Ms. Koontz: 

Thank you for the opportunity to review and comment on the Government 
Accountability Office's (GAO's) Draft Report GAO-08-759 entitled 
Telecommunications: Agencies are Generally Following Sound Transition 
Planning Practices, and GSA Is Taking Action to Resolve Challenges. In 
regard to the recommendations in the draft report, the Department has a 
few concerns regarding GAO's portrayal of the state of the Department 
of Homeland Security's (DHS's) Networx transition activities. 

Recommendation #1— DHS does not concur: 

* document the department's processes for maintaining 
telecommunications inventories; 

Response: 

GAO indicated that DHS has not published a process document for 
inventory of telecommunications service assets. This observation is in 
conflict with the related finding that we have identified a complete 
telecommunications inventory. It is true the DHS HQ has not published a 
process document for inventory of telecommunications service assets. 
Instead, via our Networx Transition Work Group (NTWG), DHS has 
instructed all components to maintain the GSA Transition Baseline 
Inventory, housed at GSA, using documented GSA procedures for doing so. 
DHS HQ, with GSA input, monitors and reports the degree to which 
components comply with this inventory methodology. DHS provided 
artifacts of the monitoring effort, hence the finding that DHS has a 
complete telecommunications inventory. 

Recommendation #2 - DHS does not concur: 

* evaluate the costs and benefits of new technology or alternatives to 
meeting its telecommunications needs; 

Response: 

This observation is in conflict with a related finding that DHS has 
aligned needs, opportunities and plans. DHS briefed the GAO audit team 
on several occasions regarding the enabling role that Networx 
transition plays in our Infrastructure Transformation Program. GAO 
representatives were also briefed and provided artifacts regarding the 
fair opportunity efforts for OneNet and non-OneNet telecommunication 
services. DHS fair opportunity efforts represent service and cost 
analyses which are subject to formal contracting officer approval. 

Recommendation #3 - DHS does not concur: 

* clearly define the roles of asset, legal, human capital, and 
information security management for the department's transition; 

Response: 

GAO indicated that DHS has not established a transition management team 
and has not assigned, by name, key transition roles. DHS has formally 
chartered the NTWG with membership from all major components. The NTWG 
meets biweekly and artifacts of meeting proceedings were provided to 
GAO. DHS provided names for those responsible for managing the 
telecommunications service inventory (NTWG members), the name of the 
contracting officer assigned to the OneNet fair opportunity and the 
name of the attorney that was consulted on the OneNet fair opportunity, 
and the name of the Chief Information Security Officer. It is true that 
DHS did not provide the name of a member of the Chief Human Capital 
Officer's staff, as the Networx transition effort had not required such 
services. All specialty disciplines (legal, contracting, human capital, 
information security) are available to the NTWG as needed and have been 
called upon where needed. DHS has demonstrated the ability to draw upon 
these services where needed. 

Recommendation # 4 - DHS does not concur: 

* identify local and regional points of contact; 

Response: 

GAO indicated that DHS had not properly identified local and regional 
points of contact for transition efforts. GAO has requested we identify 
the national, regional and local telecommunications ordering officials 
involved in the transition effort. GAO subsequently clarified this 
request to be all personnel that might be involved in any kind of 
telecommunication change. We advised GAO that this would be thousands 
of individuals across the Department and, most notably, all the IT 
field support personnel. The draft report fails to recognize that 
implementation of telecommunication changes, as entailed in the 
Transition to Networx, is executed by individual components of the 
Department, with each component having a differing command and control 
infrastructure. The Department has taken proactive steps to engage, 
alert and inform the key managers at each component and is tracking 
overall migration progress.

Recommendation #5 - DHS does not concur: 

* include in the department's planning efforts the identification of 
human capital resources needed to conduct an effective transition; 

Response: 

GAO indicated that DHS did not identify funding for transition planning 
and did not identify funding for human capital needs. It is a 
meaningful clarification that GAO queries in this area are not 
associated with the transition work itself, but are instead focused on 
the exactitude to which DHS planned to plan. DHS did identify funding 
and staffing for OneNet transition planning as part of the 
Infrastructure Transformation Program. DHS offered artifacts to this 
effect, but was advised such artifacts were not applicable. It is true 
that DHS did not identify funding or staffing for the planning of non-
OneNet services (e.g., switched voice, calling cards, etc.), but 
execution of the transition activities (e.g., an effective working 
group, a complete inventory, fair opportunity decisions, etc.) are 
clear indicators of success.

Recommendation #6 & #7 - DHS concurs: 

* establish goals and measures of success for the department's 
transition efforts to help managers assess progress; 

* perform a transition risk assessment that addresses risks to mission-
critical system systems, continuity of operations plans, and risks to 
information security. 

Response: 

Transition objectives are defined as part of the Infrastructure 
Transformation Program in the form of wide area network consolidation 
goals and the project plan for OneNet. Transition objective for non- 
OneNet services (i.e., transfer of all FTS2001 services to Networx 
before FTS2001 contract expiration) was set at initial NTWG meeting. 
Meeting minutes for this initial NTWG session did not clearly 
articulate this goal. Risk management is a key element in the OneNet 
solicitation, which was provided as an artifact. Risk management is 
also inherent in the OneNet, and all information systems, certification 
and accreditation processes, dictated under the Federal Information 
Security Management Act, with which DHS complies. DHS agrees that more 
structured communication of transition objectives and a specific risk 
management process for transition would be beneficial. 

GAO Finding (pages 25 and 27) - DHS does not concur: 

* lack of a communications plan; 

Response: 

While it is true the DHS has not published a Networx transition 
communications plan, the NTWG charter, provided to GAO, defines 
essential communications responsibility and activities. 

Thank you again for the opportunity to comment on this draft report and 
we look forward to working with you on future homeland security issues. 

Penelope G. McCormack: 
Acting Director: 
Departmental Audit Liaison Office: 

[End of section] 

Appendix VI: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Linda D. Koontz (202) 512-6240 or koontzl@gao.gov: 

Staff Acknowledgments: 

In addition to the individual named above, key contributions were made 
to this report by James R. Sweetman, Jr., Assistant Director; Gerard 
Aflague; Barbara Collier; Jamey A. Collins; Eric Costello; Joel 
Grossman; Amos Tevelow; Hai V. Tran; and Merry Woo. 

[End of section] 

Footnotes: 

[1] GAO, Telecommunications: Full Adoption of Sound Transition Planning 
Practices by GSA and Selected Agencies Could Improve Planning Efforts, 
GAO-06-476 (Washington, D.C.: June 6, 2006). 

[2] Sprint Corporation merged with Nextel Communications, Inc., to form 
Sprint Nextel Corporation in August 2005. 

[3] MCI merged with Verizon to form Verizon Business in January 2006. 

[4] In August 2001, GSA allowed contractors that had been awarded local 
telecommunications contracts in selected metropolitan areas, through 
GSA's Metropolitan Area Acquisition program, to offer long-distance 
services on the FTS2001 contracts. This process is termed "crossover." 

[5] GSA negotiated sole-source contracts for a 24-month period with 
three 6-month optional periods, for a total of 42 months. 

[6] The council was established in 1992 to provide a forum and focal 
point for agency participation in planning and overseeing GSA's long- 
distance telecommunications services. 

[7] GAO, FTS2001: Transition Challenges Jeopardize Program Goals, GAO-
01-289 (Washington, D.C.: Mar. 30, 2001). 

[8] 41 U.S.C. § 253j(b) requires civilian agencies to provide all 
contractors awarded multiple award task-and-delivery order contracts a 
fair opportunity to be considered for each order in excess of $2,500 
that is to be issued under any of the contracts, unless one of the 
statute's exceptions applies. As recently amended, subsection 253j(d) 
establishes enhanced competition requirements for this process 
applicable to orders over $5 million. Similar requirements apply to the 
Department of Defense under 10 U.S.C. § 2304c. In addition, section 803 
of the National Defense Authorization Act for Fiscal Year 2002 requires 
that an order for services in excess of $100,000 issued under a 
multiple award contract by or on behalf of the Department of Defense be 
made on a competitive basis unless a contracting officer justifies an 
exception in writing. Pub. L. No. 107-107 (Dec. 28, 2001). 

[9] Verizon's FTS2001 crossover contract is currently operating under a 
continuity of service clause that provides an additional 24 months for 
agencies to transition to a new contract. 

[10] GAO-01-289 and GAO, FTS2001: Contract Transition Delays and Their 
Impact on Program Goals, GAO-01-544T (Washington, D.C.: Apr. 26, 2001). 

[11] GAO, Telecommunications: Full Adoption of Sound Transition 
Planning Practices by GSA and Selected Agencies Could Improve Planning 
Efforts, GAO-06-476 (Washington, D.C.: June 6, 2006). 

[12] GAO, Telecommunications: GSA Has Accumulated Adequate Funding for 
Transition to New Contracts but Needs Cost Estimation Policy, GAO-07-
268 (Washington, D.C.: Feb. 23, 2007). 

[13] GAO-06-476. 

[14] In determining the extent to which agencies had established 
transition inventories, we reviewed agency data quality controls in 
place as well as the extent to which each agency had validated its 
transition inventory. If an agency had sufficient controls in place and 
had validated at least 90 percent of its inventory, its inventory was 
considered sufficient for conducting a transition. See appendix I for a 
complete description of our methodology. 

[15] An enterprise architecture is an institutional blueprint that 
defines how an enterprise operates today, in both business and 
technology terms, and how it intends to operate in the future. 

[16] Specifically, Agriculture and Homeland Security are currently 
using certain management processes, and agency policies indicate that 
all will be used. SBA is currently using project management, and 
officials stated they plan to use change and configuration management 
processes. Commerce provided a draft policy and evidence of contractor 
support to indicate that project, configuration, and change management 
processes will be used in its management of the transition. NRC 
provided agency policy requiring the use of these processes and 
officials stated that they plan to use them. 

[17] "Organizational conflicts of interest" means that because of other 
activities or relationships with other persons, a person is unable or 
potentially unable to render impartial assistance or advice to the 
government, or the person's objectivity in performing the contract work 
is or might be otherwise impaired, or a person has an unfair 
competitive advantage. FAR 2.101. 

[18] FAR 9.505. 

[19] Among its requirements, the Procurement Integrity Act prohibits 
the disclosure of source selection and contractor bid or proposal 
information before the award of a federal agency procurement contract 
to which the information relates. 41 U.S.C. § 423. 

[20] The Federal Information Security Management Act of 2002 (FISMA) 
sets forth a comprehensive framework for ensuring the effectiveness of 
information security controls over information resources that support 
federal operations and assets. E-Government Act of 2002, Title III, 
Pub. L. No. 107-347 (Dec. 17, 2002). 

[21] Certification and accreditation is the requirement that agency 
management officials formally authorize information systems to process 
information, thereby accepting the risk associated with their 
operation. 

[22] Pub. L. No. 110-181, § 843 (Jan. 28, 2008) (to be codified in 
relevant part at 10 U.S.C. § 2304c (defense) and 41 U.S.C. § 253j 
(civilian)). 

[23] GAO-06-476. 

[24] In one case in which the GSA was not able to provide inventory 
information (NRC), we used that agency's responses to the questionnaire 
on quality control to determine whether both criteria were met. 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability.  

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates."  

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:  

U.S. Government Accountability Office: 
441 G Street NW, Room LM: 
Washington, D.C. 20548:  

To order by Phone: 
Voice: (202) 512-6000: 
TDD: (202) 512-2537: 
Fax: (202) 512-6061:  

To Report Fraud, Waste, and Abuse in Federal Programs:  

Contact:  

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470:  

Congressional Relations:  

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548:  

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: