This is the accessible text file for GAO report number GAO-07-336 
entitled 'Department of Energy: Major Construction Projects Need a 
Consistent Approach for Assessing Technology Readiness to Help Avoid 
Cost Increases and Delays' which was released on March 28, 2007. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to the Subcommittee on Energy and Water Development, and Related 
Agencies, Committee on Appropriations, House of Representatives: 

United States Government Accountability Office: 

GAO: 

March 2007: 

Department of Energy: 

Major Construction Projects Need a Consistent Approach for Assessing 
Technology Readiness to Help Avoid Cost Increases and Delays: 

GAO-07-336: 

GAO Highlights: 

Highlights of GAO-07-336, a report to the Subcommittee on Energy and 
Water Development, and Related Agencies, Committee on Appropriations, 
House of Representatives 

Why GAO Did This Study: 

The Department of Energy (DOE) spends billions of dollars on major 
construction projects that help maintain the nuclear weapons stockpile, 
conduct research and development, and process nuclear waste so that it 
can be disposed of. Because of DOE’s long-standing project management 
problems, GAO determined the extent to which (1) DOE’s major 
construction projects are having cost increases and schedule delays and 
the major factors contributing to these problems and (2) DOE ensures 
that project designs are sufficiently complete before construction 
begins to help avoid cost increases and delays. We examined 12 DOE 
major projects with total costs of about $27 billion, spoke with 
federal and contractor officials, and reviewed project management 
documents. 

What GAO Found: 

Of the 12 DOE major projects GAO reviewed, 9 exceeded their original 
cost or schedule estimates, principally because of ineffective DOE 
project oversight and poor contractor management. Specifically, 8 of 
the 12 projects experienced cost increases ranging from $79.0 million 
to $7.9 billion, and 9 of the 12 projects were behind schedule by 9 
months to more than 11 years. Project oversight problems included, 
among other things, inadequate systems for measuring contractor 
performance, approval of construction activities before final designs 
were sufficiently complete, ineffective project reviews, and 
insufficient DOE staffing. Furthermore, contractors poorly managed the 
development and integration of the technology used in the projects by, 
among other things, not accurately anticipating the cost and time that 
would be required to carry out the highly complex tasks involved. 

Even though DOE requires final project designs to be sufficiently 
complete before beginning construction, it has not systematically 
ensured that the critical technologies reflected in these designs have 
been demonstrated to work as intended (technology readiness) before 
committing to construction expenses. Specifically, only one of the five 
DOE project directors with projects that have recently begun or are 
nearing construction had systematically assessed technology readiness. 
The other four directors also told us that they have or will have 
completed prior to construction, 85 to 100 percent of their projects’ 
final design, but they had not systematically assessed technology 
readiness. Proceeding into construction without also demonstrating a 
technology’s readiness can lead to cost increases and delays. For 
example, one technology to be used in DOE’s Waste Treatment and 
Immobilization Plant was not sufficiently demonstrated—that is, shown 
to be technologically ready for its intended application—before 
construction began. Consequently, the technology did not perform as 
expected, which resulted in about $225 million in redesign costs and 
schedule delays of more than 1 year. To help avoid these problems, the 
National Aeronautics and Space Administration (NASA) pioneered and the 
Department of Defense (DOD) has adopted for its projects a method for 
measuring and communicating technology readiness levels (TRL). Using a 
scale from one (basic principles observed) through nine (total system 
used successfully in project operations), TRLs show the extent to which 
technologies have been demonstrated to work as intended in the project. 
DOE project directors agreed that such an approach would help make 
technology assessments more transparent and improve stakeholder 
communication prior to making critical project decisions, such as 
authorizing construction. 

Figure: Technology Readiness Levels: 

[See PDF for Image] 

Source: GAO analysis of DOD data. 

[End of figure] 

What GAO Recommends: 

GAO recommends that DOE develop a consistent approach for measuring the 
readiness of critical project technologies. DOE supports GAO’s 
recommendations but suggested revisions to allow it to first conduct a 
pilot application on selected projects to better understand the process 
and evaluate its potential use. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-07-336]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Gene Aloise at (202) 512-
3841 or aloisee@gao.gov. 

[End of section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

Most Major Projects Have Exceeded Original Costs and Are Years Late, 
Principally Because of Ineffective DOE Project Oversight and Contractor 
Management: 

DOE Does Not Consistently Measure Technology Readiness to Ensure That 
Critical Technologies Will Work as Intended before Construction Begins: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Information on the 12 Department of Energy Major Projects 
Reviewed: 

Appendix III: Independent Studies Reviewed: 

Appendix IV: Survey Results for Primary Factors Affecting Cost and 
Schedule on Nine Projects with Cost or Schedule Changes: 

Appendix V: Definitions of Technology Readiness Levels: 

Appendix VI: Comparison of DOD's Product Development Process with DOE's 
Project Management Process: 

Appendix VII: Comments from the Department of Energy: 

Appendix VIII: GAO Contact and Staff Acknowledgments: 

Tables: 

Table 1: Changes in Estimated Total Project Cost for DOE Major 
Construction Projects: 

Table 2: Changes in Estimated Project Schedules for DOE Major 
Construction Projects: 

Table 3: Reasons for Cost Increases and Schedule Delays: 

Abbreviations: 

DOD: Department of Defense: 

DOE: Department of Energy: 

EM: Office of Environmental Management: 

ITP: In-Tank Precipitation: 

NASA: National Aeronautics and Space Administration: 

NNSA: National Nuclear Security Administration: 

PDRI: Product Definition Rating Index: 

TPC: total project cost: 

TRL: technology readiness level: 

United States Government Accountability Office: 
Washington, DC 20548: 

March 27, 2007: 

The Honorable Peter J. Visclosky: 
Chairman: 
The Honorable David L. Hobson: 
Ranking Member: 
Subcommittee on Energy and Water Development, and Related Agencies: 
Committee on Appropriations: 
House of Representatives: 

The Department of Energy (DOE) spends billions of dollars on major 
construction projects that, among other things, are used to help 
maintain the nuclear weapons stockpile, conduct research and 
development in the areas of high-energy physics and nuclear physics, 
and process nuclear waste into forms suitable for longer-term storage 
or permanent disposal. DOE oversees the construction of facilities 
primarily at government-owned, contractor-operated sites throughout the 
nation. In July 2006, DOE revised its dollar threshold defining a 
construction project as "major"; it is now at $750 million, up from 
$400 million when we began our review in December 2005. The following 
12 projects included in our review had estimated project costs 
exceeding the original threshold.[Footnote 1] The total cost of these 
projects is currently estimated at about $27 billion.[Footnote 2] These 
12 projects and their locations are as follows: 

* Chemistry and Metallurgy Research Facility Replacement--Los Alamos 
National Laboratory, Los Alamos, New Mexico. 

* Depleted Uranium Hexafluoride 6 Conversion Facility--Portsmouth, 
Ohio, and Paducah, Kentucky. 

* Highly Enriched Uranium Materials Facility--Y-12 National Security 
Complex, Oak Ridge, Tennessee. 

* Linac Coherent Light Source--Stanford Linear Accelerator Center, 
Menlo Park, California. 

* Microsystems and Engineering Sciences Applications--Sandia National 
Laboratories, Albuquerque, New Mexico. 

* Mixed Oxide Fuel Fabrication Facility--Savannah River Site, Aiken, 
South Carolina. 

* National Ignition Facility--Lawrence Livermore National Laboratory, 
Livermore, California. 

* Pit Disassembly and Conversion Facility--Savannah River Site, Aiken, 
South Carolina. 

* Salt Waste Processing Facility--Savannah River Site, Aiken, South 
Carolina. 

* Spallation Neutron Source--Oak Ridge National Laboratory, Oak Ridge, 
Tennessee. 

* Tritium Extraction Facility--Savannah River Site, Aiken, South 
Carolina. 

* Waste Treatment and Immobilization Plant--Hanford Site, Richland, 
Washington. 

These major projects require the construction of large building 
complexes and the development of innovative cleanup and other 
technologies. Many of these technologies are developed for the project 
or are applied in a new way. DOE project directors are responsible for 
managing these major projects and overseeing the contractors that 
design and construct the facilities. In doing so, project directors 
follow specific departmental directives, policies, and guidance for 
project management. Among these are DOE Order 413.3A and Manual 413.3- 
1, which establish protocols for planning and executing a project. The 
protocols require DOE projects to go through a series of five critical 
decisions as they enter each new phase of work. Two of the decisions 
made before construction begins are key: (1) formally approving the 
project's definitive cost and schedule estimates as accurate and 
complete--an approval that is to be based on a review of the project's 
completed preliminary design, and (2) reaching agreement that the 
project's final design is sufficiently complete and that resources can 
be committed toward procurement and construction. To oversee projects 
and approve these critical decisions, DOE conducts its own reviews, 
often with the help of independent technical experts. In addition, 
projects are regularly subject to reviews by DOE's Office of 
Engineering and Construction Management and it's Office of Inspector 
General, the Department of Defense's (DOD) U.S. Army Corps of 
Engineers, the Defense Nuclear Facilities Safety Board, and the 
National Research Council, among others. 

We and others have reported over the past decade that project 
management weaknesses have impaired these projects. For example, for 
the Waste Treatment and Immobilization Plant, we reported that DOE's 
use of a "fast-track, design-build" approach to construction--in which 
design and construction activities overlap--has been problematic for 
highly complex, first-of-a-kind facilities. We found that the designs 
for these facilities were not sufficiently complete for construction to 
begin, which has resulted in significant cost increases and schedule 
delays.[Footnote 3] 

In this context, we determined the extent to which (1) DOE's active 
major construction projects are experiencing cost increases and 
schedule delays and the key factors contributing to these problems and 
(2) DOE ensures that project designs are sufficiently complete before 
construction begins to help avoid cost increases and schedule 
delays.[Footnote 4] 

To determine the extent to which DOE projects are experiencing cost 
increases or schedule delays and factors contributing to these 
problems, we sent a survey to the 12 DOE directors of major projects 
and reviewed the project management documents for these projects--6 
projects that were above the $750 million threshold, 2 estimated to 
cost between the previous $400 million threshold and $750 million, and 
4 estimated to cost between $300 million and $400 million. (App. II 
describes these projects.) These 12 projects are managed by DOE's 
Office of Science, Office of Environmental Management, or National 
Nuclear Security Administration (NNSA). We conducted site visits and 
analyzed independent project studies for the 9 projects that 
experienced cost increases or schedule delays. During the course of our 
review, we identified a method used by the DOE project director for the 
Pit Disassembly and Conversion Facility to systematically assess the 
extent to which a technology is sufficiently developed for its intended 
purpose. The project director based this method on a system developed 
by the National Aeronautics and Space Administration (NASA). We had 
previously reported on the use of a similar assessment system-- 
technology readiness levels (TRL), which DOD has adopted for its major 
projects.[Footnote 5] We obtained and reviewed documents regarding 
these two assessment systems. 

To determine the extent to which DOE ensures that project designs are 
sufficiently complete before construction, we reviewed in detail 5 of 
the 12 projects that were approaching or had recently begun 
construction. Specifically, we obtained information on the extent to 
which project designs were, or are expected to be, complete before 
beginning construction, and the actions DOE has taken to ensure that 
technologies used in these designs are sufficiently ready to begin 
construction. 

Because we and others have previously expressed concern about the data 
reliability of a key DOE project management tracking database--the 
Project Assessment and Reporting System--we did not develop conclusions 
or findings on the basis of information generated through that 
system.[Footnote 6] Instead, we collected information directly from 
project site offices. In addition, we spoke with officials from DOE 
program offices and DOE's Office of Engineering and Construction 
Management in Washington, D.C. We provided interim briefings to the 
Subcommittee on the status of our work in May and September, 2006. We 
performed our work between December 2005 and January 2007, in 
accordance with generally accepted government auditing standards. 
Appendix I contains a detailed description of our scope and 
methodology. 

Results in Brief: 

Nine of the 12 DOE major projects we reviewed have exceeded their 
original cost estimates and/or experienced schedule delays, principally 
because of ineffective DOE project oversight and poor contractor 
management, according to independent studies we reviewed and interviews 
we conducted with DOE and contractor project officials. Specifically, 8 
of the 12 projects experienced cost increases ranging from $79.0 
million to $7.9 billion, and 9 of the 12 projects are behind schedule 
by 9 months to more than 11 years. Major factors cited for these cost 
increases and delays included the following: 

* Ineffective DOE project oversight. For all 9 projects experiencing 
cost increases or schedule delays, poor DOE oversight was a key 
contributing factor. Project oversight problems included inadequate 
systems for measuring contractor performance, approval of construction 
activities before final designs were sufficiently complete, ineffective 
project reviews, and insufficient DOE staffing and project management 
experience. 

* Poor contractor management. Eight of the 9 major projects experienced 
cost increases and/or schedule delays, in part because contractors did 
not effectively manage the development and integration of the 
technology used in the projects, including not accurately anticipating 
the cost and time that would be required to carry out the highly 
complex tasks involved. For example, the National Ignition Facility has 
had over $1 billion in cost increases and years of schedule delays 
owing in part to technology integration problems, according to the DOE 
project director. Other examples of poor contractor performance 
included inadequate quality assurance for the Highly Enriched Uranium 
Materials Facility, which resulted in concrete work that did not meet 
design specifications. The subsequent suspension of construction 
activities and rework added to the project's estimated cost and 
schedule. 

DOE officials also explained that a now-defunct policy may have 
contributed to increased costs and delays for several projects we 
examined. Until 2000, DOE required contractors to prepare cost and 
schedule estimates early in the project, before preliminary designs 
were completed. These estimates were used to establish a baseline for 
measuring contractor performance and tracking any cost increases or 
schedule delays. However, these estimates often were based on early 
conceptual designs and, thus, were subject to significant change as 
more detailed designs were developed. To improve the reliability of 
these estimates, DOE issued a new order in October 2000 that required 
the preparation of a cost estimate range at the start of preliminary 
design, and delayed the requirement for a definitive cost and schedule 
baseline estimate until after preliminary design was completed. 
Consequently, DOE officials explained, the new policy should result in 
improved estimates and a more accurate measure of cost and schedule 
performance. 

Even though DOE requires final project designs to be sufficiently 
complete before beginning construction, it has not systematically 
ensured that the critical technologies reflected in these designs have 
been demonstrated to work as intended (technology readiness) before 
committing to construction expenses. Only one of the five DOE directors 
with projects that have recently begun, or are nearing construction, 
had systematically assessed technology readiness. The other four 
directors also told us that they have or will have completed prior to 
construction, 85 to 100 percent of their projects' final design, but 
they had not systematically assessed for technology readiness. Lack of 
technology readiness can result in cost overruns and schedule delays. 
For example, technology used in a subsystem intended to prepare 
radioactive material for processing in DOE's Waste Treatment and 
Immobilization Plant was not fully developed and did not work as 
expected after construction had already begun, resulting in redesign 
costs of about $225 million and over 1 year in schedule delays. 

To effectively assess technology readiness, NASA pioneered and DOD has 
adopted a process for measuring and communicating technology readiness 
for first-of-a-kind technology applications. This process uses a nine- 
point scale for assessing TRLs. Using this scale, a technology would 
receive a higher TRL value (e.g., TRL 7) if it has been successfully 
demonstrated in an operational environment, compared with a technology 
that has been demonstrated only in a laboratory test (e.g., TRL 4). 
Several DOE project directors we spoke with agreed that a consistent, 
systematic method for assessing technology readiness would help 
standardize terminology, make technology assessments more transparent, 
and help improve communication among project stakeholders before they 
make critical project decisions. 

To improve oversight and decision making for DOE's major construction 
projects, we are recommending that the Secretary of Energy evaluate and 
consider adopting a disciplined and consistent approach to assessing 
TRLs for projects with critical technologies. 

DOE provided comments to us based on a draft of the report. DOE agreed 
with our recommendations but suggested revisions that would first allow 
them to conduct a pilot application on selected projects to better 
understand the technology readiness assessment process and evaluate its 
potential use. We revised our recommendations as appropriate. DOE 
suggested that our report is too narrowly focused on technology 
assessment, and that we inappropriately calculated cost increases and 
schedule delays using preliminary estimates that were only intended for 
internal DOE planning. We believe that our recommendations were 
justifiably based on our finding that DOE has not systematically 
ensured that project designs, including critical technologies reflected 
in these designs, have been demonstrated to work as intended prior to 
construction. We also believe it was appropriate, when necessary, to 
measure cost and schedule changes using the initial estimates that were 
developed at the end of conceptual design, as specified in DOE's 
project management policy in effect prior to 2000. We note that these 
estimates were, in some instances, the only initial estimates available 
and had been used by DOE to inform the Congress of the estimated cost 
and schedule of the projects while it was seeking initial project 
funding. We also incorporated technical changes in this report where 
appropriate on the basis of detailed comments provided by DOE. 

Background: 

To meet its diverse missions, DOE pays its contractors billions of 
dollars each year to implement hundreds of projects, ranging from 
hazardous waste cleanups at sites in the weapons complex to the 
construction of scientific facilities. Many of these complex, unique 
projects are designed to meet defense, energy research, environmental, 
and fissile materials disposition goals. They often rely on 
technologies that are unproven in operational conditions. In recent 
years, DOE's budget has been dominated by the monumental task of 
environmental restoration and waste management to repair damage caused 
by the past production of nuclear weapons. 

DOE has long had a poor track record for developing designs and cost 
estimates and managing projects. We reported in 1997 that from 1980 to 
1996, 31 of DOE's 80 major projects were terminated prior to 
completion, after expenditures of over $10 billion; 15 of the projects 
were completed, but most of them were finished behind schedule and with 
cost overruns; and the remaining 34 ongoing projects also were 
experiencing schedule slippage or cost overruns.[Footnote 7] In 
addition, for over a decade, DOE's Office of Inspector General, the 
National Academy of Sciences, and others have identified problems with 
DOE's management of major construction projects. Projects were late or 
never finished; project costs increased by millions and sometimes 
billions of dollars; and environmental conditions at the sites did not 
significantly improve. According to the National Research 
Council,[Footnote 8] DOE's construction and environmental remediation 
projects take much longer and cost about 50 percent more than 
comparable projects by other federal agencies or projects in the 
private sector.[Footnote 9] A 2004 assessment of departmental project 
management completed by the Civil Engineering Research Foundation 
recommended, among other things, that DOE develop a core group of 
highly qualified project directors and require peer reviews for first- 
of-a-kind and technically complex projects when the projects' 
preliminary baselines are approved.[Footnote 10] 

To address project management issues, DOE began a series of reforms in 
the 1990s that included efforts to strengthen project management 
practices. To guide these reforms, the department formed the Office of 
Engineering and Construction Management in 1999. The reforms instituted 
to date have included planning, organizing, and tracking project 
activities, costs, and schedules; training to ensure that federal 
project managers had the required expertise to manage projects; 
increasing emphasis on independent reviews; and strengthening project 
reporting and oversight. 

Most Major Projects Have Exceeded Original Costs and Are Years Late, 
Principally Because of Ineffective DOE Project Oversight and Contractor 
Management: 

The estimated costs of many of the DOE major construction projects we 
reviewed have significantly exceeded original estimates and schedules 
have slipped. On the basis of our analysis of independent project 
studies and interviews with project directors, cost growth and schedule 
slippage occurred principally because of ineffective DOE project 
oversight and poor contractor project management. Furthermore, 
unreliable initial cost and schedule estimates resulting from a now- 
defunct policy may have been a contributing factor, according to DOE 
project officials. Although external factors, such as additional 
security and safety requirements, contributed to cost growth and 
delays, the management of these requirements was complicated by 
ineffective and untimely DOE communication and decision making. 

Eight of the 12 DOE projects we reviewed had increases in estimates of 
total project cost (TPC) ranging from $79.0 million to $7.9 billion. As 
table 1 shows, the percentage of cost increase for these 8 projects 
ranged from 2 percent to over 200 percent. 

Table 1: Changes in Estimated Total Project Cost for DOE Major 
Construction Projects: 

Dollars in millions. 

Project: Mixed Oxide Fuel Fabrication Facility[C]; 
Initial total project cost (TPC) estimate[A]: $1,400; 
Current TPC estimate: $4,699; 
Percentage increase[B]: 205%. 

Project: Waste Treatment and Immobilization Plant; 
Initial total project cost (TPC) estimate[A]: 4,350; 
Current TPC estimate: 12,263; 
Percentage increase[B]: 143. 

Project: Highly Enriched Uranium Materials Facility; 
Initial total project cost (TPC) estimate[A]: 251; 
Current TPC estimate: 549; 
Percentage increase[B]: 102. 

Project: National Ignition Facility; 
Initial total project cost (TPC) estimate[A]: 1,199; 
Current TPC estimate: $2,248; 
Percentage increase[B]: 59. 

Project: Salt Waste Processing Facility; 
Initial total project cost (TPC) estimate[A]: 440; 
Current TPC estimate: 680[D]; 
Percentage increase[B]: 50. 

Project: Pit Disassembly and Conversion Facility[C]; 
Initial total project cost (TPC) estimate[A]: 1,700; 
Current TPC estimate: 2,694; 
Percentage increase[B]: 40. 

Project: Tritium Extraction Facility; 
Initial total project cost (TPC) estimate[A]: 384; 
Current TPC estimate: 506; 
Percentage increase[B]: 15. 

Project: Spallation Neutron Source; 
Initial total project cost (TPC) estimate[A]: 1,333; 
Current TPC estimate: 1,412; 
Percentage increase[B]: 2. 

Project: Depleted Uranium Hexafluoride 6 Conversion Facility; 
Initial total project cost (TPC) estimate[A]: 346; 
Current TPC estimate: 346; 
Percentage increase[B]: 0. 

Project: Chemistry and Metallurgy Research Facility Replacement; 
Initial total project cost (TPC) estimate[A]: 837; 
Current TPC estimate: 837; 
Percentage increase[B]: 0. 

Project: Microsystems and Engineering Sciences Applications; 
Initial total project cost (TPC) estimate[A]: 518; 
Current TPC estimate: 518; 
Percentage increase[B]: 0. 

Project: Linac Coherent Light Source; 
Initial total project cost (TPC) estimate[A]: 379; 
Current TPC estimate: 379; 
Percentage increase[B]: 0. 

Source: GAO analysis of DOE data. 

[A] In 2000, DOE changed its requirements for establishing initial cost 
and schedule estimates. Prior to 2000, these estimates were established 
at the end of conceptual design. After 2000, DOE required initial 
estimates to be completed later in the project--at the end of 
preliminary design. For projects beginning prior to 2000, and for 
projects beginning after 2000 that had not yet completed preliminary 
design, we used the TPC estimates prepared after conceptual design. For 
additional details on our methodology, see appendix I. 

[B] We calculated the percentages of cost increases on the basis of 
constant 2007 dollars to make them comparable across projects and to 
show real increases in cost while excluding increases due to inflation. 

[C] NNSA officials, in commenting on our draft report, stated that 
initial and current cost estimates for the Mixed Oxide Fuel Fabrication 
Facility and the Pit Disassembly and Conversion Facility should not be 
used in this analysis because neither project has an approved budget 
quality baseline. Nevertheless, we included the estimates in this 
analysis because both projects have been in an extended period of 
project design, without an approved budget-quality baseline, for about 
10 years, and the estimates provided here are the only estimates 
available. 

[D] Estimate may change when DOE approves contractor's revised TPC in 
2007. 

[End of table] 

In addition, as shown in table 2, 9 of the 12 projects experienced 
schedule delays ranging from 9 months to more than 11 years. Of the 9 
projects, 7 had schedule delays of at least 2 years or more. 

Table 2: Changes in Estimated Project Schedules for DOE Major 
Construction Projects: 

Project: Pit Disassembly and Conversion Facility; 
Year mission need was approved: 1997; 
Initial completion date estimate: 06/2005; 
Current completion date estimate: 03/2017; 
Schedule delay as of February 2007: 11 years, 9 months. 

Project: Mixed Oxide Fuel Fabrication Facility; 
Year mission need was approved: 1997; 
Initial completion date estimate: 09/2004; 
Current completion date estimate: 03/2016; 
Schedule delay as of February 2007: 11 years, 6 months. 

Project: Waste Treatment and Immobilization Plant; 
Year mission need was approved: 1995; 
Initial completion date estimate: 07/2011; 
Current completion date estimate: 11/2019; 
Schedule delay as of February 2007: 8 years, 4 months. 

Project: National Ignition Facility; 
Year mission need was approved: 1993; 
Initial completion date estimate: 10/2003; 
Current completion date estimate: 03/2009; 
Schedule delay as of February 2007: 5 years, 5 months. 

Project: Depleted Uranium Hexafluoride 6 Conversion Facility[A]; 
Year mission need was approved: 2000; 
Initial completion date estimate: 03/ 2006; 
Current completion date estimate: 06/2008; 
Schedule delay as of February 2007: 2 years, 3 months. 

Project: Salt Waste Processing Facility; 
Year mission need was approved: 2001; 
Initial completion date estimate: 07/2009; 
Current completion date estimate: 09/2011[B]; 
Schedule delay as of February 2007: 2 years, 2 months. 

Project: Tritium Extraction Facility; 
Year mission need was approved: 1995; 
Initial completion date estimate: 06/2005; 
Current completion date estimate: 07/2007; 
Schedule delay as of February 2007: 2 years, 1 month. 

Project: Highly Enriched Uranium Materials Facility; 
Year mission need was approved: 1999; 
Initial completion date estimate: 04/2008; 
Current completion date estimate: 03/2010; 
Schedule delay as of February 2007: 1 year, 11 months. 

Project: Spallation Neutron Source; 
Year mission need was approved: 1996; 
Initial completion date estimate: 09/2005; 
Current completion date estimate: 06/2006[C]; 
Schedule delay as of February 2007: 9 months. 

Project: Chemistry and Metallurgy Research Facility Replacement; 
Year mission need was approved: 2002; 
Initial completion date estimate: 03/ 2014; 
Current completion date estimate: 03/2014; 
Schedule delay as of February 2007: Not applicable. 

Project: Microsystems and Engineering Sciences Applications; 
Year mission need was approved: 1999; 
Initial completion date estimate: 01/ 2009; 
Current completion date estimate: 01/2009; 
Schedule delay as of February 2007: Not applicable. 

Project: Linac Coherent Light Source; 
Year mission need was approved: 2001; 
Initial completion date estimate: 03/2009; 
Current completion date estimate: 03/2009; 
Schedule delay as of February 2007: Not applicable. 

Source: GAO analysis of DOE data. 

[A] This project reported a schedule delay but did not report an 
increase in the estimated total project cost (TPC). According to the 
DOE project director, the original cost estimate was probably too high 
and was not well supported. 

[B] According to DOE officials, schedule may slip further when the 
contractor submits its revised TPC to DOE in July 2007. 

[C] Project was completed on this date. Transition to operations has 
begun. 

[End of table] 

As table 3 shows, ineffective DOE project oversight and poor contractor 
management were frequently cited reasons for cost increases and 
schedule delays for the projects we reviewed, according to our review 
of independent studies of the 9 projects experiencing cost growth and 
schedule delays and our follow-up interviews with DOE project 
directors. Project officials, in commenting on our draft report, were 
concerned that table 3 might misrepresent the overall successful 
execution and completion of some projects, such as the Spallation 
Neutron Source, and that some problems may have already been addressed. 
Nevertheless, to clarify our main purpose for table 3, our intent is to 
show broad categories of major reasons for cost increases and schedule 
delays, regardless of when they occurred or whether they have been 
adequately addressed. 

Table 3: Reasons for Cost Increases and Schedule Delays: 

Project: Depleted Uranium Hexafluoride 6 Conversion Facility; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/security): X. 

Project: Highly Enriched Uranium Materials Facility; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/security): X. 

Project: Mixed Oxide Fuel Fabrication Facility; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/ security): X. 

Project: National Ignition Facility; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/security): [Empty]. 

Project: Pit Disassembly and Conversion Facility; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/security): X. 

Project: Salt Waste Processing Facility; 
DOE project oversight: X; 
Poor contractor management: [Empty]; 
External factors (e.g., safety/ security): X. 

Project: Spallation Neutron Source; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/security): [Empty]. 

Project: Tritium Extraction Facility; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/security): X. 

Project: Waste Treatment and Immobilization Plant; 
DOE project oversight: X; 
Poor contractor management: X; 
External factors (e.g., safety/security): X. 

Project: Total; 
DOE project oversight: 9; 
Poor contractor management: 8; 
External factors (e.g., safety/security): 7. 

Source: GAO analysis of independent project studies and interviews with 
DOE project directors (a list of the project studies we reviewed is 
included in app. III). 

[End of table] 

The DOE project oversight issues mentioned in table 3 include the 
following: 

* inadequate systems for measuring contractor performance; 

* approval of construction activities before final designs were 
sufficiently complete; 

* ineffective project reviews; 

* insufficient DOE staffing and experience; 

* inadequate use of project management controls; 

* lack of headquarters assistance and oversight support of field 
project directors; 

* failure to detect contractor performance problems, including 
inadequate federal inspection activities; and: 

* poor government cost estimates, including inadequate funding for 
contingencies. 

DOE's lack of adequate systems to measure contractor performance was 
cited in a December 2005 DOE Inspector General review of the Mixed 
Oxide Fuel Fabrication Facility. The Inspector General criticized DOE's 
NNSA for failing to approve a baseline against which to measure 
contractor performance and relying on outdated cost plans.[Footnote 11] 
According to the report, NNSA relied on confusing and misleading 
information detailed in the monthly project reports to monitor progress 
and track costs--reports that the contractor acknowledged as being 
"useless for evaluating performance or managing the project." 
Furthermore, although the contractor reported unfavorable cost and 
schedule variances for months, these variances were inaccurate and 
meaningless because performance was being compared against a 2-year-old 
plan. NNSA, in commenting on our draft report, stated that project 
oversight and contractor management problems identified in previous 
GAO, Inspector General, and other independent assessments have led to 
extensive improvements to the project, and that major findings 
identified during a recent independent review have been successfully 
addressed. 

Similarly, DOE's approval of construction activities before final 
designs were sufficiently complete has contributed significantly to 
project cost growth and schedule delays. As we have previously 
reported, the accelerated fast-track, design-build approach used for 
the Waste Treatment and Immobilization Plant, a highly complex first- 
of-a-kind nuclear facility, resulted in significant cost increases and 
schedule delays.[Footnote 12] DOE also allowed the contractor on 
another project, the Tritium Extraction Facility, to begin construction 
before the final design was completed to meet schedule commitments. 
According to a 2002 DOE Inspector General report on the 
project,[Footnote 13] this revised acquisition strategy of simultaneous 
design and construction directly resulted in at least $12 million in 
project overruns. 

The contractor management issues mentioned in table 3 include the poor 
management of technological challenges, among other contractor 
performance issues, according to DOE project directors. Cost increases 
and schedule delays for 6 of the 9 projects were due in part to 
contractors' poor management of the development and integration of 
technologies used in project designs by, among other things, not 
accurately anticipating the cost and time that would be required to 
carry out the highly complex tasks involved.[Footnote 14] For example: 

* The National Ignition Facility had over $1 billion in cost overruns 
and years of schedule delays, in large part because of technology 
integration problems. The requirements for the National Ignition 
Facility--the use of 192 high-power laser beams focused on a single 
target in a "clean room" environment--had not been attempted before on 
such a large scale. According to the DOE project director, early 
incorrect assumptions about the original facility design and the amount 
of work necessary to integrate the technologies and assemble the 
technical components contributed to about half of the project's cost 
increases and schedule delays. 

* The design of the Mixed Oxide Fuel Fabrication Facility has presented 
technical challenges in adapting the design of a similar plant in 
France to the design needs of this project. Although the technological 
challenge related to adopting the process designs from the French 
designs was not the primary contributor to the project's cost increases 
and schedule delays, according to NNSA officials, it has affected the 
project's complexity. The basic technology--combining plutonium oxide 
with depleted uranium to form fuel assemblies for use in commercial 
power reactors--has been previously demonstrated in France. However, 
the DOE project director told us that the DOE facility design must, 
among other things, account for processing surplus weapon-grade 
plutonium, a different type of material than processed in the French 
facility, and must be adapted to satisfy U.S. regulatory and other 
local requirements. In addition, the DOE facility faced the 
technological challenge of reducing the scale of components used in the 
French facility. Although definitive cost estimates are not yet 
available, expected costs for completing this project have grown by 
about $3.3 billion since 2002, and the schedule has been extended by 
more than 11 years, in part because the contractor did not initially 
understand the project's complexity and underestimated the level of 
effort needed to complete the work. NNSA explained that the capability 
of the reference plants currently in operation in France, and by 
extension, the Mixed Oxide Fuel Fabrication Facility process design, is 
currently being demonstrated by several prototype fuel assemblies 
manufactured with weapon-grade plutonium oxide, which are currently 
being successfully used in a reactor in South Carolina. 

* For the Waste Treatment and Immobilization Plant, a technology 
application used on the project had not been tested before 
construction. Filters, widely used in the water treatment industry, 
were being designed for the project to concentrate and remove 
radioactive particles in liquid waste, a new application for the 
filters. Although tests are currently under way to demonstrate the 
effectiveness of this application, project officials conceded that 
these filters may still not be appropriate for the project. 

Other contractor performance problems are illustrated by two examples. 
First, DOE cited the contractor working on the Highly Enriched Uranium 
Materials Facility for inadequate quality assurance that resulted in 
concrete work that did not meet design specifications. The subsequent 
suspension of construction activities and rework added to the project's 
estimated cost and schedule. Second, the DOE project director of the 
Depleted Uranium Hexafluoride 6 Conversion Facility told us that the 
project was delayed 2 years because the contractor (1) did not have 
experience in government contracts, (2) underestimated the design 
effort needed, and (3) failed to properly integrate the operations of 
three separate organizations it managed. 

As table 3 shows, external factors were cited as also contributing to 
cost growth and schedule delays, such as additional work to implement 
requirements for higher levels of safety and security in project 
operations, among other things. For example, design rework for 4 of the 
projects occurred in response to external safety oversight 
recommendations by the Defense Nuclear Facilities Safety Board that 
large DOE construction projects meet a certain level of personnel 
safety, and that their designs be robust enough to withstand certain 
seismic events. In addition, owing to new security requirements 
implemented after September 11, 2001, project officials on the Highly 
Enriched Uranium Materials Facility had to redesign some aspects of the 
project to ensure that heightened security measures were addressed. 

While DOE faced additional requirements for safety and security, it did 
not always reach timely decisions on how to implement these 
requirements, which contributed significantly to cost increases and 
schedule delays for the Salt Waste Processing Facility. The DOE project 
director for this project told us the Defense Nuclear Facilities Safety 
Board had expressed concerns in June 2004, 5 months after the 
preliminary design was started, that the facility design might not 
ensure nuclear wastes would be adequately contained in the event of 
earthquakes. However, DOE did not decide how to address this concern 
until 17 months later, as the project continued to move forward with 
the existing project design. According to the project director, better 
and more timely discussions between site officials and headquarters to 
decide on the actions needed to adequately address these safety and 
security requirements might have hastened resolution of the problem, 
and up to 1 year of design rework might have been avoided. The delay, 
the director told us, added $180 million to the total project cost and 
extended the schedule by 26 months. In commenting on our draft report, 
EM officials noted that it is now requiring a more rigorous safety 
analysis earlier in the decision-making process. 

Other external factors also contributed significantly to cost increases 
and delays for 2 interrelated projects we reviewed--the Mixed Oxide 
Fuel Fabrication Facility and the Pit Disassembly and Conversion 
Facility. Project officials for these projects told us that 25 to 50 
percent of the cost increases and over 70 percent of the schedule 
delays they experienced were the direct result of Office of Management 
and Budget funding constraints and restrictions resulting from 
international agreements with Russia. That is, work that is delayed to 
a subsequent year because of funding constraints and other work 
restrictions can delay project completion, which likely increases total 
project costs. Similarly, Office of Science officials, commenting on 
our draft report, stated that external factors caused the largest 
percentage cost increase and schedule delay for the Spallation Neutron 
Source, including a reduced level of funding appropriated at a time 
when project activities and costs were increasing considerably. 
However, congressional funding was reduced in fiscal year 2000 because 
of concerns about poor project oversight and management in the early 
stages of this project. 

DOE officials also explained that a now-defunct policy may have 
contributed to increased costs and delays for several projects we 
examined. Until 2000, DOE required contractors to prepare cost and 
schedule estimates early in the project, before preliminary designs 
were completed. These estimates were used to establish a baseline for 
measuring contractor performance and tracking any cost increases or 
schedule delays. However, these estimates often were based on early 
conceptual designs and, thus, were subject to significant change as 
more detailed designs were developed. To improve the reliability of 
these estimates, DOE issued a new order in October 2000 that required 
the preparation of a cost estimate range at the start of preliminary 
design, and delayed the requirement for a definitive cost and schedule 
baseline estimate until after the preliminary design was completed. 
Consequently, DOE officials explained, the new policy should result in 
improved estimates and a more accurate measure of cost and schedule 
performance. 

We also sent a survey to DOE project directors for all 12 projects 
asking them to identify key events that led to the greatest cost 
increases or schedule delays, and the major factors contributing to 
these key events. However, no individual factors were identified as 
being major contributors to the cost increases or schedule delays. In 
responding to our survey, DOE project directors cited several factors 
that affected changes in cost and schedule. However, when asked to rate 
the relative significance of these factors for their impact on cost and 
schedule changes, the project directors generally did not judge them to 
be significant contributors to the changes. The most frequently cited 
factors were: 

* an absence of open communication, mutual trust, and close 
coordination; 

* changes in "political will" during project execution (e.g., project 
changes resulting from political decisions, both internal and external 
to the project); 

* interruptions in project funding; and: 

* project managers' lack of adequate professional experience. 

(For detailed survey results covering these four factors, see app. IV.) 

In contrast to the cost increases and schedule delays incurred on most 
of the projects we reviewed, 3 projects had not yet experienced cost 
increases or schedule delays--Microsystems and Engineering Sciences 
Applications, the Linac Coherent Light Source, and the Chemistry and 
Metallurgy Research Facility Replacement. DOE project officials 
identified key conditions that they believed helped avoid those cost 
increases and delays. These conditions included: 

* active oversight--that is, the DOE project directors were never 
"blindsided" by contractor issues; 

* a lack of technological complexity; 

* an effective system to measure contractor performance; 

* reliable cost estimates; 

* effective communication with and integration of all stakeholders; 
and: 

* sustained leadership. 

However, we observed that the Linac Coherent Light Source and the 
Chemistry and Metallurgy Research Facility Replacement facilities are 
still in a relatively early stage in the project development process, 
and thus it may be too early to gauge the overall success of either 
project. Additionally, because none of these 3 projects are highly 
technologically complex, they may be less susceptible to the types of 
problems associated with other projects we reviewed that experienced 
cost increases and delays. 

DOE Does Not Consistently Measure Technology Readiness to Ensure That 
Critical Technologies Will Work as Intended before Construction Begins: 

Although DOE requires its final designs to be sufficiently complete 
before beginning construction, it has not systematically ensured that 
the critical technologies reflected in project designs are 
technologically ready. Recognizing that a lack of technology readiness 
can result in cost overruns and schedule delays, other federal 
agencies, such as NASA and DOD, have issued guidance for measuring and 
communicating technology readiness. 

DOE Does Not Consistently Assess Technology Readiness: 

Only 1 of the 5 projects we reviewed to determine how DOE ensures that 
project designs are sufficiently complete before construction-- 
projects that were approaching or had recently begun construction--had 
a systematic assessment of technology readiness to determine whether 
the project components would work individually or collectively as 
expected in the intended design.[Footnote 15] Specifically, the DOE 
project director for the Pit Disassembly and Conversion Facility 
systematically measured and assessed readiness levels for each critical 
component of the overall project.[Footnote 16] The assessment was based 
on a method developed by NASA, that is, rating each technology from 0 
to 10 in terms of relative maturity. Because the project has not yet 
begun construction, we could not determine whether the technology 
readiness assessment has helped project managers to avoid cost 
increases or schedule delays during construction. However, according to 
DOE and contractor officials responsible for the project, the 
assessment helped focus management attention during project design on 
critical technologies that may require additional resources to ensure 
that they are sufficiently ready before construction begins. In 
reviewing the assessment, however, we noted that project officials had 
not updated the assessment tool for this project for over 3 years. 
DOE's project director acknowledged the delay in updating the 
assessment and responded that he plans to begin updating the assessment 
annually. 

The other 4 projects did not have systematic assessments of 
technological readiness. Therefore, the risk associated with the 
technology may not be clearly and consistently understood across all 
levels of management. Formally approving the project's cost and 
schedule estimates as accurate and complete, or proceeding into 
construction, without having clearly assessed evidence of technology 
readiness can result in cost overruns and schedule delays. 

DOE's experience with the Waste Treatment and Immobilization Plant is a 
case in point. Specifically, technology known as "pulse jet 
mixers"[Footnote 17] was used in the design of a subsystem intended to 
prepare radioactive material for processing. However, this technology 
had not been used previously in this application, and it did not work 
in tests as expected, even after construction had already begun. 
Consequently, DOE incurred about $225 million in redesign costs and 
over 1 year in schedule delays, according to the DOE project director. 

Over the past several years, we and others have stressed the importance 
of assessing technology readiness to complete projects successfully, 
while avoiding cost increases and schedule delays. Specifically, by 
1999, we reported that organizations using best practices recognize 
that delaying the resolution of technology problems until production or 
construction can result in at least a 10-fold cost increase.[Footnote 
18] Furthermore, we reported that delaying the resolution until after 
the start of production could increase costs by 100-fold. Reporting on 
similar concerns, the National Research Council has identified factors 
common to large construction projects--in the areas of cost, schedule, 
and scope--that help to ensure projects are completed 
successfully.[Footnote 19] Among key technical conditions for defining 
project scope, the council stated, is a project plan that is based on 
employing the best available, state-of-the-art technology, but not 
experimental or unproven technology. As such, employing a consistent, 
systematic method for measuring the extent to which technology is still 
experimental or unproven is of critical importance. 

An assessment of technology readiness is even more crucial at certain 
points in the life of a project--particularly as DOE decides to accept 
a project's (1) preliminary design and formally approve the project's 
cost and schedule estimates as accurate and complete and (2) final 
design as sufficiently complete so that resources can be committed 
toward procurement and construction. Proceeding through these critical 
decision points without a credible and complete technology readiness 
assessment can lead to problems later in the project. Specifically, if 
DOE proceeds with the project when technologies are not yet ready, 
there is less certainty that the technologies specified in the 
preliminary or final designs will work as intended. Project managers 
may then need to modify or replace these technologies to make them work 
properly, which can result in costly and time-consuming redesign work. 

Moreover, modifying the design of a facility after construction has 
already begun can be expensive and time consuming. First, changes to an 
already designed work plan are not necessarily subject to competition 
because the new work can occur through "change orders"--that is, 
modifications to existing contracts. These change orders can be 
expensive, according to DOE project directors. Second, worker 
productivity can be lost if, for example, extra downtime results from 
delays to interrelated construction work. Finally, tearing down and 
rebuilding items already constructed, such as concrete floors, walls, 
and doors, might be necessary to accommodate a design change. 

DOE's experience in the predecessor project to the Salt Waste 
Processing Facility--the In-Tank Precipitation (ITP) project process-- 
at the Savannah River Site illustrates the potential consequences of 
proceeding with technology that is not sufficiently ready. As we 
reported in 2000, the ITP project was selected in 1983 as the preferred 
method for separating highly radioactive material from 34 million 
gallons of liquid stored at the Savannah River site--a step considered 
necessary to effectively handle this large quantity of waste.[Footnote 
20] A 1983 test using the ITP technology on a tank containing 500,000 
gallons of waste resulted in a significant buildup of benzene--a highly 
explosive and hazardous compound. The buildup of benzene was more than 
the tank instruments could register. Nevertheless, project managers 
decided to proceed with the project. In 1985, DOE estimated that it 
would take about 3 years and $32 million to construct the ITP facility. 
After a number of delays, the ITP facility was constructed and began 
start-up operations in 1995, which were halted because of safety 
concerns about the amount of benzene that the facility generated. In 
1998, after about a decade of delays and costs of almost $500 million, 
DOE suspended the project because it did not work as safely and 
efficiently as designed. This suspension put an effective remedy for 
treating high-level waste at the Savannah River Site years behind 
schedule. DOE then directed its contractor to begin a process to 
identify and select an alternative technology, which has developed into 
the current project intended to treat this waste--the Salt Waste 
Processing Facility project. 

In response to our concerns about the 4 projects without systematic 
assessments of technology readiness, DOE project directors explained 
that they have alternative methods for assessing readiness. They are 
required to submit a project execution plan, which includes an 
assessment of risks, including technological risks, and a plan for 
mitigating risks. They also rely upon independent reviews, including 
extensive design reviews, before making critical decisions to accept 
designs, and cost and schedule estimates, or to proceed with 
construction. For example, DOE's Office of Engineering and Construction 
Management formally reviews major projects in an effort to ensure that 
the designs are sufficiently complete to begin construction. 
Specifically, an external independent readiness review is performed, 
often using the services of various independent technical experts, 
that, at a minimum, is intended to verify the readiness of the project 
to proceed into construction or to identify remedial action. Finally, 
several DOE project directors stated that they intentionally have 
avoided using fast-track, design-build approaches because of the many 
problems it posed for the Waste Treatment and Immobilization Plant 
project. The DOE project directors of the 5 DOE projects that are 
nearing, or have recently begun construction, told us they have 
completed, or expect to complete prior to construction, 85 to 100 
percent of their projects' final design. 

In addition to following the more standard approaches for managing 
projects, such as preparing risk assessment plans, some DOE offices 
have developed their own tools for assessing the readiness of projects. 
For example, DOE's Office of Environmental Management (EM) uses a 
Product Definition Rating Index (PDRI) as a tool to assess how well a 
project is planned, and whether it is ready to proceed to the next 
project phase. Project elements rated include cost, schedule, scope/ 
technical, management planning and control, and external factors. Among 
the 77 project elements rated, 2 involve technology--the identification 
of technology development requirements, and the testing and evaluation 
of the technology to be used. While the project technologies are 
collectively given a ranking with this tool, the PDRI does not 
represent a rigorous examination of the demonstrated readiness of each 
critical technology for its application in the project. Furthermore, 
not all EM projects we examined were using this tool. 

DOE's design reviews, risk assessments, and other actions to monitor 
design completion are extensive and certainly have merit. However, we 
found that these actions alone do not provide consistent and 
transparent assurance that all technologies are sufficiently ready 
because they do not use a consistent and systematic method of 
measurement. DOE's project design reviews, for example, do not always 
clearly distinguish between technology that has been demonstrated to 
work as expected in the intended design versus a judgment that the 
technology has potential for reaching a specific level of readiness. 

The external review of the technologies for the Mixed Oxide Fuel 
Fabrication Facility illustrates the shortfalls in DOE's current 
approach to assessing technology readiness and communicating the 
results of those assessments.[Footnote 21] The report concluded, among 
other things, that the method chosen by the contractor is the most 
rigorous and comprehensive, and should result in the most successful 
technology transfer possible. Furthermore, the review team was very 
impressed with the rigor with which designs and design changes were 
being managed, finding ample evidence verifying that the exact design 
process used by the French was being transferred to the United States 
facility. Although the external reviewers seemed to be impressed with 
many aspects of the design transfer, and concluded that the 
technologies should not be problematic, they had identified some key 
concerns about technology readiness in the body of their final report. 
The reviewers did not explain how they reconciled their conclusion with 
their concerns. To reconcile these differences, we obtained several 
clarifying statements from DOE's project director, technical experts, 
and one of the study's authors. These clarifying statements appear to 
support the reviewers' conclusions. However, without these statements, 
the level of technological readiness was not readily evident because 
the independent review lacked consistent, systematic criteria and a 
method for measuring the degree of readiness or clearly communicating 
assessment results, and the review was not transparent. 

DOE does not consistently assess technology readiness of project 
technologies because its project management guidance lacks 
comprehensive standards for systematically measuring and communicating 
the readiness of project technologies. Specifically, DOE lacks 
consistent metrics for determining technology readiness departmentwide, 
terminology to facilitate effective communication, and oversight 
protocols for reporting and reviewing technology readiness levels. DOE 
project management guidance is contained in two key documents--DOE 
Order 413.3A and Manual 413.3-1. Although the manual requires final 
designs to be sufficiently complete before beginning construction, it 
does not specify how technologies reflected in project designs are to 
be assessed for readiness--to determine that they have been 
sufficiently demonstrated to work as intended. Consequently, critical 
decisions made without standard measures are susceptible to varying 
interpretations of the actual technology readiness attained and the 
level needed for a project to proceed, which can easily vary among 
projects and among officials within a single project. 

Other Federal Agencies Use a Standard Method for Measuring and 
Communicating Technology Readiness: 

Other federal agencies have recognized the importance of ensuring that 
technologies have been sufficiently demonstrated for their intended 
purpose and have issued standard guidance for measuring and 
communicating TRLs. In particular, recognizing the need to measure the 
readiness level of project technologies, NASA began using a systematic 
method of measurement in the mid-1990s. NASA incorporated a structured 
TRL approach into guidance on integrated technology planning. 

Similarly, to improve DOD management of risk and technology 
development, the Deputy Under Secretary of Defense (Science and 
Technology) officially endorsed, in a July 2001 memorandum, the use of 
TRLs in new major programs. In 2002, DOD issued mandatory procedures 
for major defense acquisition programs and major automated information 
system acquisition programs, which identified technology readiness as a 
principal element of program risk. The procedures require the military 
services' science and technology officials to conduct a systematic 
assessment of critical technologies that are identified in major weapon 
systems programs before starting engineering and manufacturing 
development and production. Using TRLs is the preferred method, and 
approval must be obtained from the Deputy Under Secretary if an 
equivalent alternative method is used, according to the Deputy Under 
Secretary's memorandum. Importantly, the procedures stated that TRLs 
are a measure of demonstrated technical maturity--they do not discuss 
the probability of occurrence (i.e., the likelihood of attaining 
required maturity) or the impact of not achieving technology maturity. 

Both NASA and DOD use a nine-point scale to measure technology 
readiness, from a low of TRL 1 (basic principles observed) to a high of 
TRL 9 (total system used successfully in project operations). (App. V 
contains the definitions of these nine TRLs.) For example, a subsystem 
prototype that has been successfully demonstrated in an operational 
environment would receive a higher TRL value (i.e., TRL 7) than a 
technological component that has been demonstrated in a laboratory test 
(i.e., TRL 4). In our previous work, we recommended to the Secretary of 
Defense that key project technologies used in weapons systems be 
demonstrated in an operational environment, reaching a high maturity 
level--analogous to TRL 7--before deciding to commit to a cost, 
schedule, and performance baseline for development and production of 
the weapon system.[Footnote 22] In response to our recommendation, DOD 
has agreed that if a technology does not achieve a score of TRL 6 or 7, 
project managers must develop a plan to bring the technology to the 
required readiness level before proceeding to the next project phase. 

Use of TRLs is not by itself a cure-all for managing critical 
technologies, but TRLs can be used in conjunction with other measures 
to improve the way projects are managed. For example, according to 
studies by NASA, DOD, and others, TRLs can: 

* provide a common language among the technology developers, engineers 
who will adopt/use the technology, and other stakeholders; 

* improve stakeholder communication regarding technology development-- 
a by-product of the discussion among stakeholders that is needed to 
negotiate a TRL value; 

* reveal the gap between a technology's current readiness level and the 
readiness level needed for successful inclusion in the intended 
product; 

* identify at-risk technologies that need increased management 
attention or additional resources for technology development to 
initiate risk-reduction measures; and: 

* increase transparency of critical decisions by identifying key 
technologies that have been demonstrated to work or by highlighting 
still immature or unproven technologies that might result in high 
project risk. 

Two DOE headquarters offices have attempted to systematically assess 
technology readiness. First, under the Office of Nuclear Energy, a DOE 
contractor preparing a congressional report used a TRL method to 
compare the maturity of advanced fuel cycle technologies. In addition, 
in 2000, DOE's Office of Science and Technology, under EM, issued a 
report that defined a process for assessing technology maturity of EM 
projects.[Footnote 23] However, according to an EM official, the office 
decided to discontinue using this assessment process because it was 
considered overly burdensome. As a result, DOE devolved responsibility 
for managing technology readiness to the contractor level. 

According to several DOE project directors we spoke with, a consistent, 
systematic method for assessing technology readiness would help achieve 
a number of objectives: that is, standardize terminology, make 
technology assessments more transparent, and improve communication 
among project stakeholders before they make critical project decisions. 
DOE project managers also acknowledged that TRLs could improve project 
management departmentwide, and some managers are now attempting to use 
this tool to assess technology maturity. The DOE project director for 
the Waste Treatment and Immobilization Plant told us that a senior DOE 
official encouraged him to begin using TRLs. He is consulting with DOD 
officials knowledgeable about using the TRL method and expects to 
develop a TRL tool and have TRL determinations for major parts of the 
project in 2007. (App. VI compares DOD's product development process 
with DOE's project management process for major projects.) 

Conclusions: 

The magnitude of the cost increases and schedule delays for DOE's major 
projects is cause for serious rethinking of how DOE manages them. To 
its credit, DOE has completed, or expects to complete prior to 
construction, 85 to 100 percent of project design work for the 5 
projects we reviewed that have recently begun or are nearing 
construction. However, DOE has not systematically addressed another key 
factor--the readiness level of the technologies it expects to use in 
these projects. DOE lacks comprehensive standards in DOE Order 413.3A 
and Manual 413.3-1 for systematically measuring and communicating the 
readiness of project technologies. Specifically, the department lacks 
consistent metrics for determining technology readiness departmentwide, 
terminology, and oversight protocols for reporting and reviewing TRLs. 
Without consistent measurement and communication of the readiness of 
technologies, DOE does not have a basis for defining the acceptable 
level of technological risk for each project, making critical decisions 
on accepting the validity of a project's total estimated cost and 
schedule, or proceeding with construction. 

Other federal agencies have recognized the need to consistently measure 
and communicate technology readiness to help avoid cost increases and 
delays that result from relying on immature technologies. DOD, for 
example, requires its managers to use a TRL process to measure 
technology readiness and generally requires a TRL 7 (as we had 
recommended) before system development and demonstration. In contrast, 
as DOE's poor track record for managing the technological complexity of 
major projects shows, DOE has not systematically measured the readiness 
of critical project technologies before it approves definitive cost and 
schedule estimates or begins construction. Furthermore, without a 
systematic method for measuring technological readiness, DOE cannot 
effectively communicate within the department and to the Congress 
whether projects are at risk of experiencing cost increases and 
schedule delays associated with technology problems. 

Recommendations for Executive Action: 

To improve decision making and oversight for major DOE construction 
projects, including how project technology readiness is measured and 
reported, we recommend that the Secretary of Energy evaluate and 
consider adopting a disciplined and consistent approach to assessing 
TRLs for projects with critical technologies that includes the 
following three actions: 

* Develop comprehensive standards for systematically measuring and 
communicating the readiness of project technologies. At a minimum, 
these standards should (1) specify consistent metrics for determining 
technology readiness departmentwide, (2) establish terminology that can 
be consistently applied across projects, and (3) detail the oversight 
protocols to be used in reporting and reviewing TRLs. In preparing 
these standards, DOE should consider lessons learned from NASA and DOD, 
and its own experience in measuring technology readiness. If DOE's 
evaluation results in the decision to adopt these standards, it should 
incorporate them into DOE Order 413.3A and Manual 413.3-1, and provide 
the appropriate training to ensure their proper implementation. 

* Direct DOE Acquisition Executives to ensure that projects with 
critical technologies reach a level of readiness commensurate with 
acceptable risk--analogous to TRL 7--before deciding to approve the 
preliminary design and commit to definitive cost and schedule 
estimates, and at least TRL 7 or, if possible, TRL 8 before committing 
to construction expenses. 

* Inform the appropriate committees and Members of Congress of any DOE 
decision to approve definitive cost and schedule estimates, or to begin 
construction, without first having ensured that project technologies 
are sufficiently ready (at TRL 7 or 8). This information should include 
specific plans for mitigating technology risks, such as developing 
backup technologies to offset the effects of a potential technology 
failure, and appropriate justification for accepting higher 
technological risk. 

Agency Comments and Our Evaluation: 

We provided a draft of this report to DOE for its review and comment. 
DOE's written comments are reproduced in appendix VII. DOE agreed with 
our recommendations but suggested revisions that would allow it to 
first conduct a pilot application on selected projects to better 
understand the technology readiness assessment process and evaluate its 
potential use. We revised our recommendations to give DOE this 
flexibility. DOE also provided detailed technical comments, which we 
have incorporated into our report as appropriate. 

DOE also expressed several specific concerns with our draft report. 
First, DOE stated that while our draft broadly asserts that DOE project 
management has led to increases in cost and schedule, our 
recommendations are narrowly focused on technology assessment. We agree 
that our draft states that DOE project management has led to cost 
increases and schedule delays, a conclusion we reached on the basis of 
our contact with DOE project directors and our review of numerous 
studies and reports on DOE major projects. Our recommendations address 
technology assessment, a critical project management activity, because 
they were developed primarily on the basis of our specific finding that 
DOE lacks a systematic approach to ensure that final project designs, 
including critical technologies reflected in these designs, have been 
demonstrated to work as intended prior to construction. This report 
explains that delaying resolution of technology problems until 
construction can potentially lead to significant cost increases and 
schedule delays. 

Second, DOE stated that our draft report inappropriately characterizes 
cost and schedule growth from a small sample of projects by using 
preliminary cost and schedule estimates that are intended for internal 
DOE planning. To clarify, the scope of our review included an 
evaluation of DOE's major construction projects. In addition, our 
report explains that DOE changed its project management policy in 2000 
to allow cost and schedule estimates to be prepared later in the 
project--at the end of preliminary design. Prior to this new policy, 
project directors submitted cost and schedule estimates earlier in the 
project development phase--at the end of conceptual design. For 
projects under way prior to the policy in 2000, we used post-2000 
validated baseline estimates, if available. Otherwise, we used earlier 
estimates since these were the only estimates available and had been 
previously used by DOE to inform Congress of the total expected project 
cost and schedule while seeking initial project funding. We also note 
that for the five projects that were started after the new policy in 
2000, we used the validated project baseline estimates recommended by 
DOE, if available. 

Third, DOE suggested we revise table 3 in our report to more clearly 
identify the correlation between cost and schedule growth and 
technology maturity. As our report states, the information in table 3 
was drawn from the results of our review of independent studies 
involving the projects we reviewed and the results of our interviews 
with DOE project directors. Our report explains that cost increases and 
schedule delays for 6 of the 9 projects shown in the table were due in 
part to contractors' poor management of the development and integration 
of technologies used in the project designs. 

Finally, DOE stated that it is unclear how the factors cited in 
appendix IV, such as communication, and changes in "political will," 
among other things, led to our recommendation to assess technology 
readiness. Although not all of the factors cited in our survey have a 
link to our recommendation on technology readiness, one factor in 
particular--absence of communication--is addressed in our 
recommendation. Specifically, we recommended that the Secretary of 
Energy consider developing comprehensive standards for systematically 
measuring and communicating the readiness of project technologies, 
including the establishment of terminology that is to be consistently 
applied across projects. 

We are sending copies of the report to interested congressional 
committees, the Secretary of Energy, and the Director of the Office of 
Management and Budget. We will make copies available to others on 
request. In addition, the report will also be available at no charge on 
the GAO Web site at http://www.gao.gov. 

If you or your staffs have any questions about this report, please 
contact me at (202) 512-3841 or aloisee@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. Other staff contributing to the report 
are listed in appendix VIII. 

Signed by: 

Gene Aloise: 
Director, Natural Resources and Environment: 

[End of section] 

Appendix I: Scope and Methodology: 

To determine the extent to which the Department of Energy's (DOE) major 
construction projects have experienced cost increases and schedule 
delays and the factors that have contributed to these problems, we 
identified (1) active DOE major line-item construction projects that 
have current total project cost estimates above the $750 million 
threshold--DOE's criteria for "major construction projects," and (2) 
the projects with estimates above $400 million--the DOE threshold for 
major projects until July 2006. We also identified those projects above 
$300 million to account for any projects that may pass the $400 million 
threshold.[Footnote 24] In all, we identified the following 12 
projects: 

* Five of these 12 projects began before DOE moved its requirement for 
firm cost and schedule estimates to later in the project: the National 
Ignition Facility, the Mixed Oxide Fuel Fabrication Facility, the Pit 
Disassembly and Conversion Facility, the Spallation Neutron Source, and 
the Tritium Extraction Facility. We used the estimates at the end of 
conceptual design, as reported by project directors, for the initial 
project cost and schedule estimates. 

* Four of the remaining 7 projects had cost and schedule estimates 
completed at the end of preliminary design, according to the new DOE 
guidelines: the Highly Enriched Uranium Materials Facility, 
Microsystems and Engineering Sciences Applications, the Depleted 
Uranium Hexafluoride 6 Conversion Facilities, and the Linac Coherent 
Light Source. For these projects, we considered the estimates as 
reported by project directors to be the initial cost and schedule 
estimates. 

* One project, the Waste Treatment and Immobilization Plant, began 
after DOE moved the requirement for firm cost and schedule estimates to 
later in the project. However, DOE initially exempted the contractor 
from submitting firm cost and schedule estimates. Therefore, we used 
the estimates reported by the project director to be the initial cost 
and schedule estimates. 

* The final 2 projects, although falling under the new DOE 
requirements, had yet to complete their preliminary design at the time 
of our review: the Chemistry and Metallurgy Research Facility 
Replacement and the Salt Waste Processing Facility. For these projects, 
we considered the cost and schedule estimates at the end of conceptual 
design reported by project directors to be the initial project cost and 
schedule estimates. 

Because we and others have previously expressed concern about the data 
reliability of a key DOE project management tracking database--the 
Project Assessment and Reporting System--we did not develop conclusions 
or findings based on information generated through that 
system.[Footnote 25] Instead, we collected information directly through 
surveys and interviews with project site officials. 

To identify cost increases and schedule delays, and the factors that 
may have contributed to these changes, we surveyed DOE project 
directors, interviewed DOE and contractor project personnel, and 
reviewed project management documents for 12 major projects. These 12 
projects are managed by DOE's Office of Science, Office of 
Environmental Management (EM), or National Nuclear Security 
Administration (NNSA). (See app. II for information on these projects.) 

Our survey asked DOE project directors of the 12 projects to identify 
the degree to which cost and schedule estimates may have changed and 
the reasons for these changes, and to describe the events and 
conditions that led to any changes. Eight of the 12 project directors 
responded that their projects had experienced cost increases and 
schedule delays, and 1 project director reported only a schedule delay. 
For these 9 projects, we asked project directors to (1) identify the 
top three events that led to the cost and schedule delays and (2) 
indicate to what extent certain factors may have contributed to the 
event that led to the largest percentage cost increase or schedule 
delay. The factors included in the survey instrument were based on the 
results of a National Research Council study that listed essential or 
important conditions needed for the successful completion of major 
projects.[Footnote 26] We asked project directors to identify the 
extent to which the lack of these conditions may have contributed to 
any cost and schedule delays. (App. IV shows key survey results for 
these 9 projects.) 

In addition to reviewing project documentation, we conducted site 
visits for the 9 projects that had experienced cost and schedule 
changes, and we analyzed (1) studies of these projects completed by 
DOE's Office of Inspector General and (2) external independent project 
reviews conducted under the direction of DOE's Office of Engineering 
and Construction Management in Washington, D.C. We interviewed federal 
project directors of the 3 projects that had not experienced cost 
increases or schedule delays to obtain information on factors they 
believe are important in avoiding such increases. 

To determine the extent to which DOE ensures that project designs are 
sufficiently complete before construction, we obtained additional 
information from project directors on 5 projects that were approaching, 
or had recently begun, construction. During our review, we obtained 
information on the extent project designs were, or are expected to be, 
complete before beginning construction, and the actions DOE had taken 
to ensure technologies used in these designs are sufficiently ready to 
begin construction. For 2 of these 5 projects, we applied a tool we 
previously had used to assess DOD programs--the tool enables project 
directors to characterize the readiness level of each technology being 
developed for use in aircraft and other military applications. In 
addition, we spoke with officials from DOE program offices and DOE's 
Office of Engineering and Construction Management in Washington, D.C. 

We provided interim briefings to the Subcommittee on Energy and Water 
Development, House Committee on Appropriations, on the status of our 
work in May and September, 2006. We performed our work between December 
2005 and January 2007, in accordance with generally accepted government 
auditing standards. 

[End of section] 

Appendix II: Information on the 12 Department of Energy Major Projects 
Reviewed: 

Table: 

Project: Chemistry and Metallurgy Research Facility Replacement; 
DOE program office: National Nuclear Security Administration; 
Project purpose/objectives: Relocate and consolidate mission-critical 
analytical chemistry, material characterization, and research and 
development capabilities to ensure continuous national security mission 
support beyond 2010. 

Project: Depleted Uranium Hexafluoride 6 Conversion Facility; 
DOE program office: Office of Environmental Management; 
Project purpose/ objectives: Design and construct facilities at 
Portsmouth, Ohio, and Paducah, Kentucky, to convert the Department of 
Energy's existing inventory of depleted uranium hexafluoride into a 
more stable form for disposal or beneficial reuse. 

Project: Highly Enriched Uranium Materials Facility; 
DOE program office: National Nuclear Security Administration; 
Project purpose/ objectives: Project will construct a highly secure, 
state-of-the-art facility for consolidating and storing highly enriched 
uranium, resulting in cost savings and an increased security posture. 

Project: Linac Coherent Light Source; 
DOE program office: Science; 
Project purpose/objectives: Provide laser-like radiation in the X-ray 
region of the spectrum that is 10 billion times greater in peak 
brightness than any existing X-ray light source. The project will apply 
these high-brightness X-rays to experiments in the chemical, material, 
and biological sciences. 

Project: Microsystems and Engineering Sciences Applications; 
DOE program office: National Nuclear Security Administration; 
Project purpose/objectives: Provide state-of-the-art national complex 
that will provide for the design, integration, prototyping, and 
qualification of microsystems into components, subsystems, and systems 
within the nuclear weapons stockpile. 

Project: Mixed Oxide Fuel Fabrication Facility; 
DOE program office: National Nuclear Security Administration; 
Project purpose/objectives: Facility will combine surplus weapon-grade 
plutonium oxide with depleted uranium to form mixed oxide fuel 
assemblies that will be irradiated in United States commercial nuclear 
reactors. Once irradiated and converted into spent fuel, the resulting 
plutonium can no longer be readily used for nuclear weapons. 

Project: National Ignition Facility; 
DOE program office: National Nuclear Security Administration; 
Project purpose/objectives: Provide experimental capability to assess 
nuclear weapons physics, providing critical data that will allow the 
United States to maintain its technical capabilities in nuclear weapons 
in the absence of underground testing, and to advance fusion as an 
energy source. 

Project: Pit Disassembly and Conversion Facility; 
DOE program office: National Nuclear Security Administration; 
Project purpose/objectives: Eliminate surplus Russian and United States 
plutonium and highly enriched uranium by disassembling surplus nuclear 
weapons pits and converting the resulting plutonium metal to a powder 
form that can later be fabricated into mixed oxide fuel to produce 
nuclear fuel assemblies for use in commercial nuclear reactors. 

Project: Salt Waste Processing Facility; 
DOE program office: Office of Environmental Management; 
Project purpose/objectives: Meet site cleanup goals and reduce 
significant environmental and health/safety risk by construction of a 
facility to treat large quantities of waste from reprocessing and 
nuclear materials production operations at the Savannah River Site. 
Process will separate waste, solidify it in glass, and send it to 
federal repositories for disposal. 

Project: Spallation Neutron Source; 
DOE program office: Science; 
Project purpose/objectives: Provide next generation, short-pulse 
spallation neutron source for neutron scattering, to be used by 
researchers from academia, national and federal labs, and industry for 
basic and applied research and technology development in the fields of 
condensed matter physics, materials sciences, magnetic materials, 
polymers and complex fluids, chemistry, biology, earth sciences, and 
engineering. 

Project: Tritium Extraction Facility; 
DOE program office: National Nuclear Security Administration; 
Project purpose/objectives: To replenish the tritium needs of the 
nuclear weapons stockpile, the facility will extract tritium produced 
in a commercial nuclear reactor for use in nuclear weapons development. 

Project: Waste Treatment and Immobilization Plant; 
DOE program office: Office of Environmental Management; 
Project purpose/objectives: The plant will separate high-level from low-
level radioactive waste currently stored in underground tanks, 
processing and solidifying all high-level waste and a substantial 
portion of the low-level waste, and will treat the remaining low-level 
waste. 

Source: DOE. 

[End of table] 

[End of section] 

Appendix III: Independent Studies Reviewed: 

National Ignition Facility: 

Department of Energy, Office of Inspector General. Audit Report: Status 
of the National Ignition Facility Project. DOE/IG-0598. Washington, 
D.C.: April 28, 2003. 

GAO. Department of Energy: Status of Contract and Project Management 
Reforms. GAO-03-570T. Washington, D.C.: March 20, 2003. 

GAO. Contract Reform: DOE Has Made Progress, but Actions Needed to 
Ensure Initiatives Have Improved Results. GAO-02-798. Washington, D.C.: 
September 13, 2002. 

GAO. Department of Energy: Follow-up Review of DOE's National Ignition 
Facility. GAO-01-677R. Washington, D.C.: June 1, 2001. 

GAO. National Ignition Facility: Management and Oversight Failures 
Caused Major Cost Overruns and Schedule Delays. GAO/RCED-00-141 and 
GAO/RCED-00-271. Washington, D.C.: August 8, 2000. 

The Mitre Corporation. NIF Ignition. JSR-05-340. McLean, VA: June 29, 
2005. 

Mixed Oxide Fuel Fabrication Facility: 

Burns and Roe Enterprises, Inc. External Independent Review of the 
Mixed Oxide Fuel Fabrication Facility (MFFF) Project Critical Decision 
(CD) 2/3 Baseline: Performance Baseline (CD-2) and Start of 
Construction (CD-3) Review. BREI-L-R-06-03. Oradell, NJ: July 7, 2006. 

Burns and Roe Enterprises, Inc. External Independent Review of the 
Basis of Design for the Aqueuous Polishing Process. BREI-SLP-R-06-01. 
Oradell, NJ: March 27, 2006. 

Civil Engineering Research Foundation. Independent Research Assessment 
of Project Management Factors Affecting Department of Energy Project 
Success. Washington, D.C.: July 12, 2004. 

Department of Energy, Office of Inspector General. Audit Report: Status 
of the Mixed Oxide Fuel Fabrication Facility. DOE/IG-0713. Washington, 
D.C.: December 21, 2005. 

Pit Disassembly and Conversion Facility: 

Department of Energy, Office of Inspector General. Audit Report: 
National Nuclear Security Administration's Pit Disassembly and 
Conversion Facility. DOE/IG-0688. Washington, D.C.: May 3, 2005. 

Los Alamos National Laboratory. Options for the Development and Testing 
of the Pit Disassembly and Conversion Facility Government-Furnished 
Design. LA-UR-03-3926. Los Alamos, NM: June 11, 2003. 

Waste Treatment and Immobilization Plant: 

Bechtel National, Inc. Hanford Tank Waste Treatment and Immobilization 
Plant, May 2006 Estimate at Completion. Hanford Site, WA: May 31, 2006. 

Bechtel National, Inc. Comprehensive Review of the Hanford Tank Waste 
Treatment and Immobilization Plant Estimate at Completion. CCN 132848. 
Hanford Site, WA: March 31, 2006. 

Bechtel National, Inc. Comprehensive Review of the Hanford Waste 
Treatment Plant Flowsheet and Throughput. CCN132846. Hanford Site, WA: 
March 17, 2006. 

Bechtel National, Inc. Hanford Tank Waste Treatment and Immobilization 
Plant, December 2005 Estimate at Completion Executive Summary. Hanford 
Site, WA: January 30, 2006. 

Department of the Army Corp of Engineers. Complete Statement of Kim 
Callan, to the Subcommittee on Energy and Water Development, Committee 
on Appropriations, United States House of Representatives. Washington, 
D.C.: April 6, 2006. 

Department of Energy. External Independent Review, Independent Cost 
Review, CD-3C Review of the Waste Treatment and Immobilization Plant 
Project. Hanford Site, WA: September 2002. 

Department of Energy. External Independent Review CD-3B Review of the 
Waste Treatment and Immobilization Plant Project. Hanford Site, WA: 
April 2002. 

GAO. Hanford Waste Treatment Plant, Contractor and DOE Management 
Problems Have Led to Higher Costs, Construction Delays, and Safety 
Concerns. GAO-06-602T. Washington, D.C.: April 6, 2006. 

GAO. Further Actions Are Needed to Strengthen Contract Management for 
Major Projects. GAO-05-123. Washington, D.C.: March 18, 2005. 

GAO. Nuclear Waste: Absence of Key Management Reforms on Hanford's 
Cleanup Project Adds to Challenges of Achieving Cost and Schedule 
Goals. GAO-04-611. Washington, D.C.: June 9, 2004. 

GAO. Status of Contract and Project Management Reforms. GAO-03-57T. 
Washington, D.C.: March 20, 2003. 

GAO. Contract Reform: DOE Has Made Progress, but Actions Needed to 
Ensure Initiatives Have Improved Results. GAO-02-798. Washington, D.C.: 
September 13, 2002. 

GAO. Nuclear Waste: Hanford Tank Waste Program Needs Cost, Schedule, 
and Management Changes. GAO/RCED-93-99. Washington, D.C.: March 8, 
1993. 

LMI Government Consulting. Hanford Waste Treatment and Immobilization 
Plant After-Action Fact-Finding Review. DE535T1. McLean, VA: January 
2006. 

LMI Government Consulting. External Independent Review, Follow-up 
Review, Waste Treatment and Immobilization Plant (WTP) Out Briefing. 
Washington, D.C.: March 14, 2003. 

Spallation Neutron Source: 

Civil Engineering Research Foundation. Independent Research Assessment 
of Project Management Factors Affecting Department of Energy Project 
Success. Washington, D.C.: July 12, 2004. 

Department of Energy, Office of Inspector General. Audit Report: 
Progress of the Spallation Neutron Source Project. DOE/IG-0532. 
Washington, D.C.: November 19, 2001. 

Department of Energy. Review Committee Report on the Baseline Review of 
the Spallation Neutron Source (SNS) Project. Washington, D.C.: July 15, 
1999. 

Department of Energy. Technical, Cost, Schedule, and Management Review 
of the Spallation Neutron Source Project. Washington, D.C.: January 28, 
1999. 

GAO. Department of Energy: Status of Contract and Project Management 
Reforms. GAO-03-570T. Washington, D.C.: March 20, 2003. 

GAO. Contract Reform: DOE Has Made Progress, but Actions Needed to 
Ensure Initiatives Have Improved Results. GAO-02-798. Washington, D.C.: 
September 13, 2002. 

GAO. Department of Energy: Challenges Exist in Managing the Spallation 
Neutron Source Project. GAO/T-RCED-99-103. Washington, D.C.: March 3, 
1999. 

Salt Waste Processing Facility: 

Department of Energy, Office of Inspector General. Audit Report: Salt 
Processing Project at the Savannah River Site. DOE/IG-0565. Washington, 
D.C.: August 27, 2002. 

Institute for Regulatory Science. Technical Peer Review Report of the 
Review Panel on Salt Waste Processing Facility Technology Readiness. 
CRTD-Vol. 75. Danvers, MA: October 31, 2003. 

Tritium Extraction Facility: 

Civil Engineering Research Foundation. Independent Research Assessment 
of Project Management Factors Affecting Department of Energy Project 
Success. Washington, D.C.: July 12, 2004. 

Department of Energy, Office of Inspector General. Audit Report: The 
Department of Energy's Tritium Extraction Facility. DOE/IG-0560. 
Washington, D.C.: June 24, 2002. 

GAO. Department of Energy: Further Actions Are Needed to Strengthen 
Contract Management for Major Projects. GAO-05-123. Washington, D.C.: 
March 18, 2005. 

GAO. Department of Energy: Status of Contract and Project Management 
Reforms. GAO-03-570T. Washington, D.C.: March 20, 2003. 

GAO. Contract Reform: DOE Has Made Progress, but Actions Needed to 
Ensure Initiatives Have Improved Results. GAO-02-798. Washington, D.C.: 
September 13, 2002. 

GAO. Nuclear Weapons: Design Reviews of DOE's Tritium Extraction 
Facility. GAO/RCED-98-75. Washington, D.C.: March 31, 1998. 

National Nuclear Security Administration. Program Review of the 
Estimate to Complete Tritium Extraction Facility (TEF) at Savannah 
River Site. Washington, D.C.: August 29, 2002. 

Highly Enriched Uranium Materials Facility: 

BWXT Y-12. Highly Enriched Uranium Materials Facility Project Causal 
Analysis Report. Oak Ridge, TN: March 6, 2006. 

Department of Energy. Limited External Independent Review for Baseline 
Change Proposal Review. Oak Ridge, TN: August 31, 2004. 

Department of Energy, Office of Inspector General. Audit Report, Design 
of the Uranium Storage Facility at the Y-12 National Security Complex. 
DOE/IG-0643. Washington, D.C.: March 19, 2004. 

Department of Energy, Office of Inspector General. Audit Report, 
Reestablishment of Enriched Uranium Operations at the Y-12 National 
Security Complex. DOE/IG-0640. Washington, D.C.: February 24, 2004. 

Department of Energy. External Independent Review - Performance 
Baseline Review of the Highly Enriched Uranium Materials Facility 
Project. Oak Ridge, TN: June 2003. 

Depleted Uranium Hexafluoride 6 Conversion Facility: 

Department of Energy. Report on the Independent Project Review of the 
Depleted Uranium Hexafluoride Conversion Project. Washington, D.C.: 
October 8, 2004. 

Department of Energy, Office of Inspector General. Audit Report: 
Depleted Uranium Hexafluoride Conversion. DOE/IG-0642. Washington, 
D.C.: March 18, 2004. 

GAO. Department of Energy: Status of Contract and Project Management 
Reforms. GAO-03-570T. Washington, D.C.: March 20, 2003. 

LMI Government Consulting. DUF6 Conversion Project CD-3 Corrective 
Action Plan Review. DE538T1. McLean, VA: October 2005. 

LMI Government Consulting. Construction Readiness EIR (for CD-3) of the 
Depleted Uranium Hexafluoride Conversion Project. DE534T1. McLean, VA: 
June 2005. 

LMI Government Consulting. DUF6 Conversion Project CD-3C Construction 
Readiness Review Preliminary Draft. Washington, D.C.: May 20, 2005. 

LMI Government Consulting. DUF6 Limited Conversion Plan Project 
External Independent Review for the Office of Engineering and 
Construction Management. DE428T1. McLean, VA: June 2004. 

Chemistry and Metallurgy Research Facility Replacement: 

Jupiter Corporation. External Independent Review of the Chemistry and 
Metallurgy Research Building Replacement Project. Approve Performance 
Baseline and Approve Start of Construction. CD-2A/CD-3A. Wheaton, MD: 
October 14, 2005. 

[End of section] 

Appendix IV: Survey Results for Primary Factors Affecting Cost and 
Schedule on Nine Projects with Cost or Schedule Changes: 

Table: 

Absence of open communication, mutual trust, and close coordination. 

Factor/Project: Depleted Uranium Hexafluoride 6 Conversion Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: X; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Highly Enriched Uranium Materials Facility; Survey 
results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: X; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Mixed Oxide Fuel Fabrication Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: X. 

Factor/Project: National Ignition Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Pit Disassembly and Conversion Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: X. 

Factor/Project: Salt Waste Processing Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Spallation Neutron Source; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: X; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Tritium Extraction Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: X; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Waste Treatment and Immobilization Plant; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: X; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Total; 
Survey results for primary factors: To no extent: 0; 
Survey results for primary factors: To a limited extent: 4; 
Survey results for primary factors: To a moderate extent: 2; 
Survey results for primary factors: To a great extent: 1; 
Survey results for primary factors: To a very great extent: 0; 
Survey results for primary factors: No answer: 2. 

Changes in "political will" during project execution (e.g., project 
changes resulting from political decisions--includes politics internal 
and external to the project ). 

Factor/Project: Depleted Uranium Hexafluoride 6 Conversion Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Highly Enriched Uranium Materials Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: X; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Mixed Oxide Fuel Fabrication Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: X. 

Factor/Project: National Ignition Facility; 
Survey results for primary factors: To no extent: X; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Pit Disassembly and Conversion Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: X; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Salt Waste Processing Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: X; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Spallation Neutron Source; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: X; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Tritium Extraction Facility; 
Survey results for primary factors: To no extent: X; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Waste Treatment and Immobilization Plant; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Total; 
Survey results for primary factors: To no extent: 2; 
Survey results for primary factors: To a limited extent: 2; 
Survey results for primary factors: To a moderate extent: 2; 
Survey results for primary factors: To a great extent: 0; 
Survey results for primary factors: To a very great extent: 2; 
Survey results for primary factors: No answer: 1. 

Interruptions in planning and committing budget funds. 

Factor/Project: Depleted Uranium Hexafluoride 6 Conversion; 
Survey results for primary factors: To no extent: X; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Highly Enriched Uranium Materials Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: X; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Mixed Oxide Fuel Fabrication Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: X; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: National Ignition Facility; 
Survey results for primary factors: To no extent: X; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Pit Disassembly and Conversion Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: X. 

Factor/Project: Salt Waste Processing Facility; 
Survey results for primary factors: To no extent: X; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Spallation Neutron Source; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: X; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Tritium Extraction Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Waste Treatment and Immobilization Plant; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: X; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Total; 
Survey results for primary factors: To no extent: 3; 
Survey results for primary factors: To a limited extent: 0; 
Survey results for primary factors: To a moderate extent: 1; 
Survey results for primary factors: To a great extent: 2; 
Survey results for primary factors: To a very great extent: 2; 
Survey results for primary factors: No answer: 1. 

Project managers did not have adequate professional experience. 

Factor/Project: Depleted Uranium Hexafluoride 6 Conversion; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Highly Enriched Uranium Materials Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Mixed Oxide Fuel Fabrication Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: X. 

Factor/Project: National Ignition Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Salt Waste Processing Facility; 
Survey results for primary factors: To no extent: X; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Spallation Neutron Source; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: X; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Tritium Extraction Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: X; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Pit Disassembly and Conversion Facility; 
Survey results for primary factors: To no extent: [Empty]; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: X. 

Factor/Project: Waste Treatment and Immobilization Plant; 
Survey results for primary factors: To no extent: X; 
Survey results for primary factors: To a limited extent: [Empty]; 
Survey results for primary factors: To a moderate extent: [Empty]; 
Survey results for primary factors: To a great extent: [Empty]; 
Survey results for primary factors: To a very great extent: [Empty]; 
Survey results for primary factors: No answer: [Empty]. 

Factor/Project: Total; 
Survey results for primary factors: To no extent: 2; 
Survey results for primary factors: To a limited extent: 1; 
Survey results for primary factors: To a moderate extent: 4; 
Survey results for primary factors: To a great extent: 0; 
Survey results for primary factors: To a very great extent: 0; 
Survey results for primary factors: No answer: 2. 

Source: GAO. 

[End of table] 

[End of section] 

Appendix V: Definitions of Technology Readiness Levels: 

Table: 

Technology readiness level(TRL): 1. Basic principles observed and 
reported; 
Level involved: Studies; 
Basic objective of TRLs: Research to prove feasibility; 
Components: None; 
Integration: None; 
Tests and Environment: Desktop "back of envelope" environment. 

Technology readiness level(TRL): 2. Technology concept and/or 
application formulated; 
Level involved: Studies; 
Basic objective of TRLs: Research to prove feasibility; 
Components: None; 
Integration: Paper studies indicate components ought to work together; 
Tests and Environment: Academic environment. The emphasis here is still 
on understanding the science but beginning to think about possible 
applications of the scientific principles. 

Technology readiness level(TRL): 3. Analytical and experimental 
critical function and/or characteristic proof or concept; 
Level involved: Pieces of components; 
Basic objective of TRLs: Research to prove feasibility; 
Components: No system components, just basic laboratory research 
equipment to verify physical principles; 
Integration: No attempt at integration; still trying to see whether 
individual parts of the technology work. Lab experiments with available 
components show they will work; 
Tests and Environment: Uses of the observed properties are postulated 
and experimentation with potential elements of subsystem begins. Lab 
work to validate pieces of technology without trying to integrate. 
Emphasis is on validating the predictions made during earlier 
analytical studies to ensure that the technology has a firm scientific 
underpinning. 

Technology readiness level(TRL): 4. Component and/or breadboard 
validation in lab environment; 
Level involved: Low fidelity breadboard; 
Basic objective of TRLs: Demonstrate technical feasibility and 
functionality; 
Components: Ad Hoc and available laboratory components are surrogates 
for system components that may require special handling, calibration, 
or alignment to get them to function. Not fully functional but 
representative of technically feasible approach; 
Integration: Available components assembled into subsystem breadboard. 
Interfaces between components are realistic; 
Tests and Environment: Tests in controlled laboratory environment. Lab 
work at less than full subsystem integration, although starting to see 
if components will work together. 

Technology readiness level(TRL): 5. Component and/or breadboard 
validation in relevant environment; 
Level involved: High fidelity breadboard/brass-board (e.g., nonscale or 
form components); 
Basic objective of TRLs: Demonstrate technical feasibility and 
functionality; 
Components: Fidelity of components and interfaces are improved from TRL 
4. Some special purpose components combined with available laboratory 
components. Functionally equivalent but not of same material or size. 
May include integration of several components with reasonably realistic 
support elements to demonstrate functionality; 
Integration: Fidelity of subsystem mock up improves (e.g., from 
breadboard to brassboard). Integration issues become defined; 
Tests and Environment: Laboratory environment modified to approximate 
operational environment. Increases in accuracy of the controlled 
environment in which it is tested. 

Technology readiness level(TRL): 6. System/Subsystem model or prototype 
demonstration in relevant environment; 
Level involved: Subsystem closely configured for intended project 
application. Demonstrated in relevant environment. (Shows will work in 
desired configuration); 
Basic objective of TRLs: Demonstrate applicability to intended project 
and subsystem integration.
(Specific to intended application in project.); 
Components: Subsystem is high fidelity functional prototype with (very 
near same material and size of operational system). Probably includes 
the integration of many new components and realistic supporting 
elements/subsystems if needed to demonstrate full functionality. 
Partially integrated with existing systems; 
Integration: Components are functionally compatible (and very near same 
material and size of operational system). Component integration into 
system is demonstrated; 
Tests and Environment: Relevant environment inside or outside the 
laboratory, but not the eventual operating environment. The testing 
environment does not reach the level of an operational environment, 
although moving out of controlled laboratory environment into something 
more closely approximating the realities of technology’s intended use. 

Technology readiness level(TRL): 7. Subsystem prototype demonstration 
in an operational environment; 
Level involved: Subsystem configured for intended project application. 
Demonstrated in operational environment; 
Basic objective of TRLs: Demonstrate applicability to intended project 
and subsystem integration.
(Specific to intended application in project.); 
Components: Prototype improves to preproduction quality. Components are 
representative of project components (material, size, and function) and 
integrated with other key supporting elements/subsystems to demonstrate 
full functionality. Accurate enough representation to expect only minor 
design changes; 
Integration: Prototype not integrated into intended system but onto 
surrogate system; 
Tests and Environment: Operational environment, but not the eventual 
environment. Operational testing of system in representational 
environment. Prototype will be exposed to the true operational 
environment on a surrogate platform, demonstrator, or test bed. 

Technology readiness level(TRL): 8. Total system completed, tested, and 
fully demonstrated; 
Level involved: Full integration of subsystems to show total system 
will meet requirements; 
Basic objective of TRLs: Applied/Integrated into intended project 
application; 
Components: Components are right material, size, and function 
compatible with operational system; 
Integration: Subsystem performance meets intended application and is 
fully integrated into total system; 
Tests and Environment: Demonstration, test, and evaluation completed. 
Demonstrates system meets procurement specifications. Demonstrated in 
eventual environment. 

Technology readiness level(TRL): 9. Total system used successfully in 
project operations; 
Level involved: System meeting intended operational requirements; 
Basic objective of TRLs: Applied/Integrated into intended project 
application; 
Components: Components are successfully performing in the actual 
environment—proper size, material, and function; 
Integration: Subsystem has been installed and successfully deployed in 
project systems; 
Tests and Environment: Operational testing and evaluation completed. 
Demonstrates that system is capable of meeting all mission 
requirements. 

Source: GAO analysis of DOD data. 

[End of table] 

[End of section] 

Appendix VI: Comparison of DOD's Product Development Process with DOE's 
Project Management Process: 

[See PDF for Image] 

Source: GAO analysis of DOD and DOE data. 

[End of section] 

Appendix VII: Comments from the Department of Energy: 

Department of Energy: 
Washington, DC 20585: 

Mar 7 2007: 

Mr. Gene Aloise: 
Director, Natural Resources and Environment: 
U.S. Government Accountability Office: 
441 G Street NW: 
Washington, DC 20548: 

Dear Mr. Aloise: 

The Department of Energy (DOE or Department) has reviewed the draft 
Government Accountability Office (GAO) report entitled "Major 
Construction Projects Need a Consistent Approach for Assessing 
Technology Readiness to Help Avoid Cost Increases and Delays" (GAO-07- 
336). 

The report asserts broadly that the Department's management of projects 
has led to growth in cost and schedules, but the report's 
recommendations focus only on implementing a technology assessment 
process. The Department agrees that appropriately assessing technology 
readiness can be a significant factor in successfully completing its 
projects. However, the Department has concerns with (1) the manner in 
which GAO characterizes cost and schedule growth from a small sample of 
our projects, and (2) the establishment of a standard for evaluating 
(and approving) technology readiness for all DOE projects without 
appropriate study. 

The report inappropriately characterizes the cost growth associated 
with DOE projects by using preliminary cost and schedule estimates 
intended for internal DOE planning rather than validated and approved 
baselines. These cost and schedule baselines are established at 
Critical Decision-2 after having been validated by the Department's 
Office of Engineering and Construction Management and approved by the 
applicable Acquisition Executive. Tables 1 and 2, which compare 
inconsistent combinations of preliminary and validated data, should be 
deleted from the report or revised using only validated data for 
initial and current baselines to allow for an accurate comparison. The 
findings and conclusions supported by these tables should also be 
corrected. While the report caveats the basis for cost and schedule 
growth in the tables, the explanation provided is not sufficient to 
prevent readers from reaching the wrong conclusions regarding cost and 
schedule growth for the sample of projects in the study. 

The report also attempts to identify the causes for the cost and 
schedule increases in Table 3. The information contained in Table 3 
should be revised to more clearly identify the correlation between cost 
and schedule growth and technology maturity. 

Additionally, GAO's data in Appendix IV, Survey Results, focuses on 
communication, changes in "political will", funding uncertainties, and 
project manager experience. It is unclear how these factors lead to the 
recommendation to assess technology readiness. 

Despite concerns with the study and report, the Department believes 
GAO's recommendation regarding technology readiness analysis has merit. 
The Department plans to pilot application of the technology readiness 
assessment process on selected projects in order to better understand 
the process and evaluate its potential use in its diverse portfolio of 
projects. If warranted, DOE could implement a consistent technology 
readiness assessment as part of its established project management 
system. The assessment process would likely be applied to projects on a 
case by case basis where critical technologies are being used. 

The Department suggests that GAO's recommendation be restated as 
follows: 

As one tool to improve project planning and execution, we recommend 
that the Secretary of Energy evaluate the use of a technology readiness 
assessment for projects that involve critical technologies. 

* The Department of Energy should consider lessons learned from NASA 
and DoD on the use of Technology Readiness Levels (TRLs), as well as 
the Department's own experience in determining technology readiness, as 
it evaluates protocols for assessing and communicating the readiness of 
critical project technologies. 

* The Acquisition Executive should consider project risk imposed by 
immature technology, and on a case by case basis, define an appropriate 
level of technology readiness prior to establishing the project's 
baseline. 

Additional project-specific comments and corrections are attached. The 
Department requests that this response letter be included in GAO's 
final report. 

Sincerely, 

Signed by: 

Ingrid Kolb: 
Director: 
Office of Management: 

Attachment: 

[End of section] 

Appendix VIII: GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Gene Aloise, (202) 512-3841: 

Staff Acknowledgments: 

In addition to the individual named above, Michaela Brown, Rudy 
Chatlos, James Espinoza, Daniel Feehan (Assistant Director), Joseph 
Keener, Thomas Kingham, Matthew Lea, Mehrzad Nadji, Omari Norman, 
Christopher Pacheco, Thomas Perry, and Carol Herrnstadt Shulman made 
key contributions to this report. 

FOOTNOTES 

[1] For this review, we lowered the threshold to $300 million out of 
concern that some projects not considered major could later be defined 
as major because of cost increases. 

[2] This estimate includes design and construction costs, but does not 
reflect the total life-cycle costs of the projects, such as operating 
and maintenance costs. 

[3] GAO, Hanford Waste Treatment Plant: Contractor and DOE Management 
Problems Have Led to Higher Costs, Construction Delays, and Safety 
Concerns, GAO-06-602T (Washington, D.C.: Apr. 6, 2006). 

[4] A forthcoming GAO report will address actions taken by DOE to 
improve overall project management. 

[5] GAO, Best Practices: Better Management of Technology Development 
Can Improve Weapon System Outcomes, GAO/NSIAD-99-162 (Washington, D.C.: 
July 30, 1999); Defense Acquisitions: Assessments of Selected Major 
Weapons Programs, GAO-06-391 (Washington, D.C.: Mar. 31, 2006); and 
Defense Acquisitions: Space-Based Radar Effort Needs Additional 
Knowledge before Starting Development, GAO-04-759 (Washington, D.C.: 
July 23, 2004). 

[6] GAO, Department of Energy: Further Actions Are Needed to Strengthen 
Contract Management for Major Projects, GAO-05-123 (Washington, D.C.: 
Mar. 18, 2005); and Civil Engineering Research Foundation, Independent 
Research Assessment of Project Management Factors Affecting Department 
of Energy Project Success (Washington, D.C: July 12, 2004). 

[7] GAO, Oversight of DOE's Major Systems, GAO/RCED-97-146R 
(Washington, D.C.: Apr. 30, 1997). 

[8] The National Research Council was organized by the National Academy 
of Sciences to advise the federal government on matters related to 
science and technology. 

[9] National Research Council, Improving Project Management in the 
Department of Energy (Washington, D.C.: July 1999). 

[10] Civil Engineering Research Foundation, Independent Research 
Assessment of Project Management Factors Affecting Department of Energy 
Project Success (Washington, D.C.: July 12, 2004). 

[11] Department of Energy, Office of Inspector General, Audit Report: 
Status of the Mixed Oxide Fuel Fabrication Facility, DOE/IG-0713 
(Washington, D.C.: December 2005). 

[12] GAO-06-602T. 

[13] Department of Energy, Office of Inspector General, Audit Report: 
The Department of Energy's Tritium Extraction Facility, DOE/IG-0560 
(Washington, D.C.: June 2002). 

[14] These 6 projects are the Mixed Oxide Fuel Fabrication Facility, 
National Ignition Facility, Pit Disassembly and Conversion Facility, 
Spallation Neutron Source, Tritium Extraction Facility, and Waste 
Treatment and Immobilization Plant. 

[15] These 5 projects are the Chemistry and Metallurgy Research 
Facility Replacement, Depleted Uranium Hexafluoride 6 Conversion 
Facility, Mixed Oxide Fuel Fabrication Facility, Pit Disassembly and 
Conversion Facility, and Salt Waste Processing Facility. 

[16] Los Alamos National Laboratory, Options for the Development and 
Testing of the Pit Disassembly and Conversion Facility Government- 
Furnished Design, LA-UR-03-3926 (Los Alamos, New Mexico: June 11, 
2003). 

[17] Pulse jet mixers, which do not have moving parts, use compressed 
air to continuously mix tank waste so that it can be properly prepared 
for further processing. While such devices have previously been used 
successfully in other applications, they have never been used for 
mixing wastes with high-solid content like those at the Waste Treatment 
and Immobilization Plant. 

[18] GAO/NSIAD-99-162 and GAO, Joint Strike Fighter Acquisition: Mature 
Critical Technologies Needed to Reduce Risks, GAO-02-39 (Washington, 
D.C.: Oct. 19, 2001). 

[19] Improving Project Management. 

[20] GAO, Department of Energy: Uncertainties and Management Problems 
Have Hindered Cleanup at Two Nuclear Waste Sites, GAO/T-RCED-00-248 
(Washington, D.C.: July 12, 2000). 

[21] Burns and Roe Enterprises, Inc., External Independent Review of 
the Basis of Design for the Aqueous Polishing Process for the Mixed 
Oxide Fuel Fabrication Facility at The Savannah River Site for the U.S. 
Department of Energy Office of Engineering and Construction Management 
and National Energy Technology Laboratory Report, BREI-LSP-R-06-01 
(Oradell, New Jersey: March 2006). 

[22] GAO/NSIAD-99-162. 

[23] Department of Energy, Tracking Technology Maturity in DOE's 
Environmental Management Science and Technology Program; Revision 1 
(Washington, D.C.: Jan. 1, 2001). 

[24] We excluded the Yucca Mountain Repository project, with a total 
estimated cost of $23 billion, from our review due to its uniqueness 
and the fact that we have recently reported on the project and 
currently have an ongoing review. Also, to review projects with 
sufficient maturity, we included only the projects that were at least 1 
year past completion of conceptual design. 

[25] GAO, Department of Energy: Further Actions Are Needed to 
Strengthen Contract Management for Major Projects, GAO-05-123 
(Washington, D.C.: Mar. 18, 2005); and Civil Engineering Research 
Foundation, Independent Research Assessment of Project Management 
Factors Affecting Department of Energy Project Success (Washington, 
D.C.: July 12, 2004). 

[26] National Research Council, Improving Project Management in the 
Department of Energy (Washington, D.C.: July 1999). 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site (www.gao.gov). Each weekday, GAO posts 
newly released reports, testimony, and correspondence on its Web site. 
To have GAO e-mail you a list of newly posted products every afternoon, 
go to www.gao.gov and select "Subscribe to Updates." 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 441 G Street NW, Room LM 
Washington, D.C. 20548: 

To order by Phone: Voice: (202) 512-6000 TDD: (202) 512-2537 Fax: (202) 
512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Gloria Jarmon, Managing Director, JarmonG@gao.gov (202) 512-4400 U.S. 
Government Accountability Office, 441 G Street NW, Room 7125 
Washington, D.C. 20548: 

Public Affairs: 

Paul Anderson, Managing Director, AndersonP1@gao.gov (202) 512-4800 
U.S. Government Accountability Office, 441 G Street NW, Room 7149 
Washington, D.C. 20548: