This is the accessible text file for GAO report number GAO-06-692 
entitled 'Cooperative Threat Reduction: DOD Needs More Reliable Data to 
Better Estimate the Cost and Schedule of the Shchuch'ye Facility' which 
was released on June 1, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 

GAO: 

Report to the Chairman, Subcommittee on Federal Financial Management, 
Government Information, and International Security, Committee on 
Homeland Security and Governmental Affairs, U.S. Senate: 

Cooperative Threat Reduction: 

DOD Needs More Reliable Data to Better Estimate the Cost and Schedule 
of the Shchuch’ye Facility: 

GAO-06-692: 

GAO Highlights: 

Highlights of GAO-06-692, a report to the Chairman, Subcommittee on 
Federal Financial Management, Government Information and International 
Security, Committee on Homeland Security and Governmental Affairs, U.S. 
Senate. 

Why GAO Did This Study: 

Until destroyed, Russia’s stockpile of chemical weapons remains a 
proliferation threat, vulnerable to theft and diversion. Since 1992, 
Congress has authorized the Department of Defense (DOD) to provide more 
than $1 billion for the Cooperative Threat Reduction (CTR) program to 
help the Russian Federation construct a chemical weapons destruction 
facility (CWDF) at Shchuch’ye to eliminate about 14 percent of its 
stockpile. Over the past several years DOD has faced numerous 
challenges that have increased the estimated cost of the facility from 
about $750 million to more than $1 billion and delayed the facility’s 
operation from 2006 until 2009. DOD has attributed the increase cost 
and schedule to a variety of factors. In this report we (1) assess the 
facility’s progress, schedule, and cost and (2) review the status of 
Russia’s efforts to destroy all of its chemical weapons. 

What GAO Found: 

Although DOD has made visible progress over the past 2 years in 
constructing the chemical weapons destruction facility at Shchuch’ye, 
it continues to face numerous challenges that threaten the project’s 
schedule and cost. Primarily, key buildings on the site have fallen 
behind schedule due to difficulties working with Russian 
subcontractors. Such delays have been costing DOD more than $3 million 
per month since October 2005 and will continue until the award of a 
crucial subcontract, possibly in June 2006. Uncertain progress of 
Russian construction on the site, unpredictable Russian regulatory 
requirements, and various technical issues, such as testing the 
facility, could cause further schedule delays and increase costs. Also, 
DOD lacks a reliable earned value management (EVM) system to record, 
predict, and monitor the project’s progress. DOD allocated $6.7 million 
to the project’s contractor in September 2004 to establish an EVM 
system and expected to have a validated EVM system in place by March 
2005. DOD cannot use the current EVM system to assess the final 
schedule and cost for completing the Shchuch’ye facility because it 
contains flawed and unreliable data. In addition, the contractor has 
not yet conducted an integrated baseline review of the Shchuch’ye 
project. 

Furthermore, it remains uncertain whether the Russian government can 
destroy its entire chemical weapons stockpile by the Chemical Weapons 
Convention (CWC) extended deadline of 2012. As of March 2006, Russia 
had destroyed about 3 percent of its 40,000 metric tons of chemical 
weapons at two completed destruction facilities. To eliminate the 
remainder of its chemical weapons over the next six years, the Russian 
government must construct and operate five additional destruction 
facilities, including Shchuch’ye. The Russian government has indicated 
that it will need continued international assistance to destroy the 
remaining stockpile. 

Figure: Site Map of the Planned Chemical Weapons Destruction Facility 
at Shchuch’ye: 

[See PDF for Image] 

[End of Figure] 

What GAO Recommends: 

GAO recommends that the Secretary of Defense direct the Defense Threat 
Reduction Agency and the U.S. Army Corps of Engineers to (1) ensure 
that the EVM system contains valid and reliable data, (2) set aside a 
portion of the contractor’s award fee until the EVM system produces 
reliable data, and (3) require the contractor to perform an integrated 
baseline review after awarding the contract for completing Building 
101. DOD concurred with our recommendation. 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-06-692]. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Joseph Christoff at (202) 
512-8979 or christoffj@gao.gov. 

[End of Section] 

Contents: 

Letter: 

Results in Brief: 

Background: 

Construction Has Progressed, but Project Is behind Schedule and Faces 
Substantial Challenges: 

Russia Has Developed a Destruction Plan and Increased Funding but May 
Not Meet Its Destruction Deadlines: Conclusion: 

Recommendations for Executive Action: Agency Comments and Our 
Evaluation: 

Appendix I: Scope and Methodology: 

Appendix II: Lack of Reliable EVM Data Limits DOD’s Ability to Estimate 
Schedule and Cost for Constructing the CWDF: 

Appendix III: Comments from the Department of Defense: Appendix IV: GAO 
Contact and Staff Acknowledgments: 

Tables:

Table 1: Schedule for Russian CWDFs: 

Table 2: International Assistance for Russian Destruction, as of April 
2006: 

Table 3: Examples of Accounting System Errors Understating the Variance 
at Completion from January 2006 Report: 

Figures:

Figure 1: Russian Chemical Weapons Stockpile: 

Figure 2: Completed Firehouse at Shchuch’ye, November 2005: 

Figure 3: Administration/Cafeteria Building under Construction, 
November 2005:

Figure 4: Construction Progress on Building 101 in November 2003 and 
November 2005: 

Figure 5: U.S. Construction Status of Key Structures at Shchuch’ye, 
March 2006: 

Figure 6: Status of Key CWDF Milestones, as of May 2006: 

Abbreviations 

CTR: Cooperative Threat Reduction: 

CWC: Chemical Weapons Convention: 

CWD: Chemical Weapons Destruction: 

CWDF: chemical weapons destruction facility: 

DCAA: Defense Contract Audit Agency: 

DCMA: Defense Contract Management Agency: 

DOD: Department of Defense: 

DTRA: Defense Threat Reduction Agency: 

EVM: Earned Value Management: 

FAR: Federal Acquisition Regulations: 

IBR: integrated baseline review: 

RFP: Requests for Proposal: 

Rostekhnadzor: Federal Service for Ecological, Technological, and 
Nuclear Oversight: 

VAT: Value Added Tax: 

May 31, 2006: 

The Honorable Tom Coburn: 
Chairman: 
Subcommittee on Federal Financial Management, 
Government Information, and International Security: 
Committee on Homeland Security and Governmental Affairs: 

United States Senate: 

Dear Mr. Chairman: 

Russia possesses the world's largest declared chemical weapons 
stockpile. Since 1992, Congress has authorized the Department of 
Defense (DOD), through its Cooperative Threat Reduction (CTR) program 
to provide the Russian Federation more than $1 billion to eliminate 
these weapons. The majority of these funds support the construction of 
a chemical weapons destruction facility (CWDF) at Shchuch'ye, Russia. 
The facility is designed to destroy about 14 percent of Russia's 
chemical weapons stockpile. In 1999, DOD estimated that the destruction 
facility would cost about $750 million and could begin destroying 
chemical weapons in 2006. However, by 2003, DOD determined that the 
facility would cost more than $1 billion and would not be operational 
until 2009. DOD has attributed the increased cost and schedule to a 
variety of risk factors, including changing requirements and 
congressional restrictions on construction funding. 

In this report, we (1) assess the facility's progress, schedule, and 
cost and (2) review the status of Russia's efforts to destroy all its 
chemical weapons. To assess the progress of the facility, we obtained 
information from U.S. government officials and representatives of 
Parsons Global Services, Inc., (Parsons) the contractor managing the 
construction at Shchuch'ye. We also collected and analyzed DOD and 
contractor documents and met with relevant officials. Furthermore, we 
analyzed the reliability of Parsons' Earned Value Management (EVM) 
system data for the facility. A DOD-required management tool, an EVM 
system measures performance by comparing the value of work accomplished 
with work scheduled and thereby provides early warning of schedule 
delays and cost overruns. To obtain information on Russia's chemical 
weapons destruction efforts, we met with Russian government and 
international donor officials and reviewed copies of pertinent 
documents, including the Russian chemical weapons destruction plan. We 
performed our work from June 2005 through May 2006 in accordance with 
generally accepted government auditing standards. (See app. 1 for 
details on our scope and methodology.) 

Results in Brief: 

Since our last visit to the site in November 2003, DOD and Parsons have 
made progress in constructing the CWDF at Shchuch'ye. For example, 
several buildings are at or near completion, including the fire 
station, housing complex, and warehouse. However, DOD faces substantial 
challenges that could threaten the project's cost and schedule. First, 
the construction of key buildings is behind schedule. The construction 
of the main destruction building is delayed due to subcontractor bids 
that were incomplete or excessively high. The control building is 
behind schedule because a major Russian subcontractor went bankrupt. As 
of February 2006, DOD estimated that the construction of the entire 
CWDF was about 40 percent complete, compared with the more than 52 
percent scheduled for completion at that time. Second, uncertain 
progress of Russian construction of utilities (electricity, water, and 
gas) required to operate the facility could delay the destruction 
process. Third, a new Russian regulatory agency has levied additional 
and unplanned safety and administrative requirements on the project. In 
addition, potential difficulties in implementing the next critical 
step--systemization--in which all of the facility's components 
(destruction, electrical, water, etc.) are tested to ensure 
interoperability and performance--could impact cost and schedule. While 
DOD estimates that it will turn over the Shchuch'ye facility to the 
Russian government in May 2009, such an estimate appears optimistic 
given the construction and other unknown delays DOD may encounter. 
Furthermore, the EVM system that Parsons is using to record, predict, 
and monitor progress contains flawed and unreliable data. Our analysis 
revealed serious discrepancies in the data, such as improper 
calculations and accounting errors. For example, we found that from 
September 2005 through January 2006 Parsons' EVM reports did not 
capture almost $29 million in actual costs for the CWDF project. In 
addition, we found that DOD and Parsons have not yet conducted an 
integrated baseline review for the Shchuch'ye project. 

To improve DOD's efforts to accurately measure progress on the 
Shchuch'ye project and estimate its final completion date and cost, we 
are recommending that the Secretary of Defense ensure that Parsons' EVM 
system contains valid, reliable data and that it reflects actual cost 
and schedule conditions. Until Parsons' system produces reliable EVM 
data, we are also recommending that the Secretary of Defense withhold a 
portion of Parsons' award fee. Finally, we are recommending that the 
Secretary of Defense require Parsons to perform an integrated baseline 
review of the Shchuch'ye project once the contract for completing 
Building 101 has been awarded. 

DOD concurred with our recommendation regarding the improvement of 
Parsons' EVM system data and provided technical comments that we 
incorporated where appropriate. The Department of State did not provide 
comments. 

In addition to the Shchuch'ye project, the Russian government has 
ambitious plans to eliminate its chemical weapons stockpile. Since 
2002, Russia has destroyed about 3 percent of its declared 40,000 
metric tons of chemical weapons at two completed destruction 
facilities. To eliminate the remaining stockpile and meet the Chemical 
Weapons Convention (CWC) extended deadline of 2012, the Russian 
government will have to destroy about 38,000 metric tons of chemical 
weapons. The Russian government's destruction plan to eliminate all 
chemical weapons by 2012 may be unrealistic as it depends on the 
construction of seven destruction facilities--two have been built, two 
are under construction, and three have not been started. Furthermore, 
the Russian government's priority is to destroy nerve agents contained 
in large munitions, because destroying the larger-sized munitions first 
would allow Russia to meet its CWC destruction deadlines faster. 
Accordingly, the destruction of smaller munitions at Shchuch'ye may 
become less of a priority for the Russian government. In addition, the 
Russian government has indicated that it will need continued 
international assistance to destroy the remaining stockpile. Its 
destruction plan estimates that about $5.6 billion is needed to 
eliminate the entire Russian stockpile. Since 2002, international 
donors, including the United States, have committed almost $2 billion 
for Russian chemical weapons destruction efforts. 

Background: 

Russia possesses the world's largest declared chemical weapons 
stockpile, which is stored at seven sites across the country (see fig. 
1). When declared in 1998, the Russian stockpile included 32,500 metric 
tons of nerve agents and 7,500 metric tons of blister agents.[Footnote 
1] As of March 2006, Russia had destroyed about 1,158 metric tons of 
blister agents, about 3 percent of its stockpile. Under the CWC, Russia 
must destroy all of its chemical weapons by the extended deadline of 
2012.[Footnote 2] The CWC is a multilateral arms control treaty that 
bans the development, production, stockpiling, transfer, and use of 
chemical weapons and requires the destruction of existing chemical 
weapons stocks. Until destroyed, chemical weapons remain a 
proliferation threat. 

Figure 1: Russian Chemical Weapons Stockpile: 

[See PDF for Image] 

[End of Figure] 

In 1992, the United States agreed to assist the Russian government in 
eliminating its chemical weapons stockpile. The United States has 
committed to fund the design, construction, equipment acquisition and 
installation, systems integration, training, and start-up of the 
Shchuch'ye facility. When completed, the facility will house about 100 
buildings and structures, including the destruction buildings where 
chemical munitions are destroyed; the administration building where the 
destruction process is controlled; and support buildings such as the 
boiler house, which provides heat to the entire facility. As originally 
planned, the facility's construction was expected to begin in March 
2001 and to be completed in 2005. However, a 2-year congressional 
freeze on funding postponed the start of construction until March 2003. 

DOD's Defense Threat Reduction Agency (DTRA) manages the implementation 
of the CTR program. To construct the Shchuch'ye facility, DTRA--- 
through the U.S. Army Corps of Engineers, the contract manager for the 
project--has contracted with Parsons, which in turn subcontracts the 
design and construction work to Russian contractors. Contracts are 
executed, managed, and reviewed in accordance with DOD and Federal 
Acquisition Requirements (FAR). Subcontractors submit bids in response 
to Requests for Proposal (RFP) issued by Parsons. Parsons then awards 
the subcontract on the basis of safety records, past performance, 
quality of work, price, and other factors. After awarding these 
packages, Parsons works with the subcontractors to conduct technical 
evaluations of the schedule and cost of the work. CTR assistance will 
finance the construction of all buildings and structures on site, 
except for one. The Russian Federation has agreed to fund the 
construction of a second destruction building (Building 101A) nearly 
identical to Building 101, the U.S. funded destruction structure. 
Russia is also funding the construction of utilities (gas, electricity, 
water) needed to operate the facility and to support the local 
community. 

Since 1992, Congress has passed 27 laws addressing the CTR 
program.[Footnote 3] The legislation includes various DOD requirements 
for CTR funding, conditions on CTR expenditures, and mandates to report 
on the implementation of the CTR program. Some legislative provisions 
apply to the entire CTR program; others are directed at the Shchuch'ye 
project, including a requirement for a presidential certification that 
the project is in the U.S. national security interest.[Footnote 4] The 
President's certification authority and the waiver of a prior 
prohibition on funding chemical weapons destruction in Russia expire on 
December 31, 2006.[Footnote 5] In addition, Congress has conditioned 
funding for the Shchuch'ye facility on the Secretary of Defense's 
certification that, among other conditions, Russia has allocated at 
least $25 million to eliminating chemical weapons and has developed a 
practical plan for destroying its chemical weapons stockpile.[Footnote 
6] 

Construction Has Progressed, but Project Is behind Schedule and Faces 
Substantial Challenges: 

Since our last visit to the Shchuch'ye site in 2003, we found that 
Parsons and DOD had made progress in constructing the facility. Several 
support buildings such as the fire station, worker housing, and 
warehouse had been completed; and many of the other structures, 
including the administration/cafeteria building, the processing 
building, and storage buildings were well under construction. However, 
key buildings had fallen behind schedule, affecting the facility's 
overall cost and schedule. Uncertain progress of Russian construction 
at the facility and on its infrastructure, an unpredictable Russian 
operating environment, and assorted technical issues could continue to 
impact the project's cost and schedule. Furthermore, the failure of 
Parsons to develop and implement a usable EVMS has limited DOD's 
efforts to oversee project schedule and cost. 

DOD Has Made Progress but Is Experiencing Delays: 

During our visit to the Shchuch'ye site in November 2005, we observed 
substantial construction progress compared with our visit in November 
2003. In 2003, the site consisted mainly of concrete foundations for 
the destruction buildings, with only the specialist camp[Footnote 7] 
and warehouse under construction. By 2005, however, the support 
structures of many buildings had been built, and several buildings were 
at or near completion, including the specialist camp, warehouse, gas 
rescue station,[Footnote 8] and fire station. (Fig. 2 shows the 
completed fire station.) 

Figure 2: Completed Firehouse at Shchuch'ye, November 2005: 

[See PDF for Image] 

[End of Figure] 

Also under construction were the boiler house and the administration/ 
cafeteria building, seen in figure 3. 

Figure 3: Administration/Cafeteria Building under Construction, 
November 2005: 

[See PDF for Image] 

[End of Figure] 

The concrete outer shells of Building 101 and the administration/ 
control building had been completed. While Building 101 was still open 
to the elements and contained no inner walls, Russian subcontractors 
were installing outlets and control panels inside the drywall of the 
administration building. (See fig. 4 for a comparison of the 
construction work completed on Building 101 in November 2003 and 
November 2005.) We also observed piping and wiring being installed 
above ground for site wide electrical, heat, and water utilities. 

Figure 4: Construction Progress on Building 101 in November 2003 (left) 
and November 2005 (right): 

[See PDF for Image] 

[End of Figure] 

Despite such progress, the CWDF project has not met scheduled 
milestones, primarily because of a delay in awarding the contract for 
the completion of the CTR-funded destruction building (Building 101), 
pictured in figure 4. In January 2005, DOD estimated that the CWDF 
would cost $1.039 billion and be transferred to the Russian Federation 
by July 2009. However, in March 2006, DOD officials stated that they 
were unable to estimate when the entire facility will be completed and 
at what cost until they award a contract for the completion of Building 
101. As of February 2006, DOD estimated that the construction of the 
entire CWDF was about 40 percent complete, compared with the more than 
52 percent scheduled for completion at that time. As indicated in 
figure 5, the construction of certain key structures is behind 
schedule, including the destruction building (Building 101), the 
control building (administration building), the boiler house, and the 
water circulation building. 

Figure 5: U.S. Construction Status of Key Structures at Shchuch'ye, 
March 2006: 

[See PDF for Image] 

[A] Building schedule modified by Parsons to reflect longer timelines. 

[End of Image] 

Building 101 is on the "critical path" --that is, delays in finishing 
the building will prolong construction on other parts of the Shchuch'ye 
facility. Although the exterior shell of Building 101 is on schedule, 
the award of the construction contract for the remainder of Building 
101 is behind schedule. Parsons had planned to award the subcontract 
for the balance of the building in June 2005, but it may not be awarded 
until summer 2006. Since October 2005, Parsons has incurred costs for 
personnel salaries, rent, and transportation of more than $3 million 
per month, which will continue until the subcontract is awarded. Where 
possible, Parsons has reduced or delayed recruitment of personnel 
planned for management of Building 101. Construction activity is still 
ongoing at other buildings throughout the site. 

The delay in awarding the contract for the remainder of Building 101 
has impacted the overall schedule for completing the facility's 
construction. As part of its program management, DOD estimates dates 
for key project milestones at Shchuch'ye. These include a milestone 
schedule with objective (ideal) completion dates, threshold (latest 
acceptable) dates, and estimated completion dates for key activities. 
As of May 2006, however, DOD does not expect to meet key milestone 
dates for the CWDF. According to this schedule (as shown in fig. 6), 
construction of the facility will be delayed by about 1 year, testing 
using simulated nerve agent will begin some 15 months later than 
planned, and live agent demonstration will be delayed by about 8 
months. While DOD estimates that it will turn over the Shchuch'ye 
facility to the Russian government in December 2009, such an estimate 
appears optimistic given the construction and other unknown delays that 
DOD may encounter in testing the facility with simulated and live nerve 
agent. DOD officials stated that these milestones may slip even 
further. 

Figure 6: Status of Key CWDF Milestones, as of May 2006: 

[See PDF for Image] 

[End of Figure] 

Shchuch'ye CWDF Delayed Due to Difficulties Working with Russian 
Subcontractors: 

The delays in constructing key buildings at the CWDF result from 
problems Parsons and DOD have had with Russian subcontractors, 
including the bankruptcy of one major subcontractor, problems in 
soliciting adequate bids, and difficulty maintaining a competitive- 
bidding process. 

First, the 2005 bankruptcy of the Russian construction subcontractor 
Magnitostroy delayed construction of key buildings. This company was 
cited during the initial source selection process during 2000 to 2001 
for its technical abilities, logistical capability, competitive 
pricing, and financial responsibility and was the first construction 
subcontractor to work on the Shchuch'ye project. According to DOD and 
Parsons officials, Magnitostroy enjoyed the strong support of the 
Russian government. However, it was discovered in 2005 that a senior 
executive embezzled millions of dollars from the company in 2003. As a 
result, the company was unable to afford sufficient labor to complete 
its work at the site, according to DOD and Parsons officials. The most 
serious delay involved the construction of the administration building-
-the command building that will control the destruction process. 
Although scheduled to be complete at the time of our visit in November 
2005, construction of the administration building was only about 36 
percent complete. By January 2006, Parsons had assumed direct 
responsibility for the construction of the building and had divided 
most of the remaining work among Magnitostroy's subcontractors. 
Similarly at that time, two other Magnitostroy buildings were behind 
schedule, requiring Parsons to extend their completion dates. Given 
these delays, Parsons has not provided Magnitostroy with RFPs on any 
new construction packages. 

Second, DOD and Parsons officials stated that Russian subcontractors 
had not provided detailed cost and scheduling information in their 
bids. Although Parsons cited incomplete bids as the cause of the delay, 
DOD criticized Parsons for a "lack of urgency" in resolving the 
Building 101 bid issue. Parsons had particular difficulty soliciting 
adequate bids on the construction package for the work remaining on 
Building 101.[Footnote 9] This construction package will complete the 
building's physical structure and install the equipment and processing 
systems needed to destroy the chemical munitions. According to DOD and 
Parsons officials, it is the largest, most complex construction package 
of the CWDF project. After Magnitostroy's bankruptcy, two other 
contractors, Spetztroy and Stroytransgaz, bid on the remaining Building 
101 construction package. According to DOD officials, their bids 
arrived after the June 2005 deadline and did not include adequate cost 
and schedule data. Despite a deadline extension, neither subcontractor 
submitted a complete bid until the end of December 2005. At that time, 
only Spetzstroy submitted a responsive bid. Its bid price, however, was 
$239 million over DOD's budget. 

Third, the small pool of approved Russian subcontractors has made it 
difficult to maintain a competitive-bidding process. According to DOD, 
the subcontractors for the CWDF are selected through a series of joint 
selection committees. The Russian government develops a list of 
approved companies that Parsons and a joint commission comprising DOD 
and Russian government officials examine. In the initial round of 
subcontractor selections in 2000 to 2001, Magnitostroy was the first 
CWDF subcontractor chosen. A second round of selections in 2003 added 
four more subcontractors: Promstroy, Spetztroy, Stroyprogress, and 
Stroytransgaz. According to DOD officials, before Magnitostroy's 2005 
bankruptcy, Magnitostroy, Stroytransgaz, and Spetztroy were the only 
subcontractors that were capable of completing larger construction 
efforts. The small number of Russian contractors discouraged effective 
competition and limited the number of construction packages that could 
be awarded. 

In March 2005, DOD requested that the Russian Federation expand the 
subcontractor pool to ensure completion of the Shchuch'ye facility on 
time and within budget. The Russian government added one small 
specialty subcontractor, Vneshstrojimport, but did not restart the 
selection process to find a replacement for Magnitostroy. In December 
2005, Stroytransgaz withdrew from competition, and the sole remaining 
contractor, Spetztroy, submitted a bid for $310 million to complete 
Building 101. However, DOD had budgeted only $71 million for the 
construction package. To reconcile the cost difference, DOD paid for an 
independent cost analysis that validated the original Parsons estimate 
of $56 million. Parsons and DOD also sought the assistance of the 
Russian government to negotiate with Spetzstroy to lower its bid. When 
negotiations failed to produce a compromise, Parsons canceled the RFP 
for the balance of Building 101 on March 2, 2006. 

In March 2006, DOD resubmitted a request for more subcontractors and 
provided the Russian government with a list of five potential 
companies, three of which were added to the pool. In April 2006, 
Parsons issued a new RFP for the remainder of Building 101. According 
to DOD officials, Parsons has and will continue to conduct weekly 
meetings with the bidders and make personnel available for questions 
and clarifications regarding the RFP. 

Cost and Schedule Subject to Uncertain Progress of Russian 
Construction, an Unpredictable Russian Operating Environment, and 
System Testing Issues: 

The cost and schedule of the Shchuch'ye facility are subject to 
continuous risks. The Russian Federation's uncertain progress in 
completing work on Building 101A and required utilities could delay the 
final system testing for the CWDF. The Russian government's failure to 
complete promised social infrastructure could generate local opposition 
to the CWDF. DOD and Parsons must also operate in an unpredictable 
Russian environment with changing legal and technical requirements that 
could directly affect schedule and cost. 

Uncertain Russian Progress in Completing Facility and Infrastructure: 

Russian Federation progress in completing Building 101A, as well as the 
industrial and social infrastructure surrounding the CWDF, remains 
uncertain. According to DOD officials, the Russian government's method 
of construction scheduling contains few itemized tasks, making it 
difficult to accurately gauge construction progress and uncover issues 
that could cause delays. Although DOD and Parsons monitor Russian 
Federation construction progress through monthly progress reports and 
project site visits, the Russian government has not always followed 
jointly agreed upon schedules. DOD and Parsons officials remain 
concerned that systemization timelines could be affected if both 
destruction buildings are not completed at the same time. Furthermore, 
Russian progress in constructing utilities for the CWDF and the local 
community has produced mixed results. For instance, we observed that 
the Russian government has installed only one of three power lines 
needed to operate the CWDF. According to Parsons and DOD officials, 
although the Russian government completed the new water line to the 
CWDF and the town of Shchuch'ye in 2004, the more water the CWDF uses, 
the less the town has available. This may lead to a competition for 
water when the facility begins consuming substantially more water when 
testing of the facility's systems begins, and during operation. 
Furthermore, when the Russian government constructed a new gas line to 
the CWDF and through the town of Shchuch'ye, it did not connect the 
line to local homes as promised. A local Shchuch'ye official stated 
that most local residents cannot afford to pay for connection to the 
main gas line and expressed concerns that the Russian government will 
not fulfill its obligations to the local population. To allay public 
concerns that may impact the CWDF, DOD uses public outreach offices to 
conduct opinion polls and educate the local populace on the 
CWDF.[Footnote 10] 

Russia's Operating Environment Is Unpredictable: 

DOD and Parsons must contend with an unpredictable Russian business 
environment that can affect cost and schedule through unexpected 
changes in Russian legal, technical, and administrative 
requirements.[Footnote 11] New regulatory requirements have impacted 
the CWDF; in one case, stopping work on a building until it could be 
redesigned to comply with new Russian electrical codes. In November 
2005, a new Russian regulatory agency---the Federal Service for 
Ecological, Technological and Nuclear Oversight (Rostekhnadzor)--- 
performed a surprise audit at the Shchuch'ye CWDF. The agency cited 
Parsons with noncompliance in several areas, including environmental 
and industrial safety reviews, permits, licenses, and certifications. 
While Parsons and DOD officials were not aware of these requirements, 
they agreed to implement corrective actions. As of March 2006, Parsons 
had resolved 82 percent of the Rostekhnadzor audit findings and was 
working to mitigate the remainder. DOD continues to negotiate with 
Rostekhnadzor to meet the requirements of Russian law and is working 
with the Russian government to identify feasible solutions. 
Additionally, Parsons has contracted with consultants that specialize 
in helping companies conform to Russian fire, ecological, and 
industrial safety regulations at the local and national levels. 

Furthermore, DOD and Parsons must review new technical requirements 
raised by Russian government officials. According to DOD officials, 
some new requirement requests are justified as they relate to the 
operation of the CWDF, while most others are attempts to transfer cost 
and risk from Russia to the United States. For example, as a result of 
code and space deficiencies, DOD accepted the Russian requirement for 
an additional laboratory building on site, construction of which will 
increase the project's cost by an additional $12 million. However, DOD 
officials have resisted approving Russian requests that they believe 
are unnecessary or that fall within Russian responsibilities at the 
site. DOD refused to allow the Russian government to incorporate a new 
machine into the destruction process, which would have required 
significant redesign and testing of the process, and led to schedule 
delays and increased project costs. 

Russian requirements for long-term visas and value added tax (VAT) 
exemptions for equipment have affected cost and schedule. The Russian 
government provides most DOD and Parsons personnel with only 6-month 
visas, requiring workers to temporarily leave the country while their 
visas are reissued. One DOD official estimated that transportation 
costs associated with this practice totaled approximately $3 million as 
of November 2005. However, DOD officials have noticed improvement in 
how quickly the Russian Federation processes visas. In addition, when 
the Russian government reorganized in early 2004, the office in charge 
of Russian customs was dissolved, leaving no agency able to approve the 
VAT exemptions for more than 6 months. During that time, all equipment 
shipped from the United States was halted, causing a 3-month slip in 
the CWDF construction schedule. In late 2004, the Russian Federation 
eventually reestablished a new VAT office, and equipment delivery was 
resumed. Since that time, DOD has encountered no VAT-related delays. 

Testing Issues Could Delay Destruction Process: 

Issues associated with the testing of the CWDF's utilities and 
automated destruction system (systemization) could further delay the 
schedule and increase costs. DOD officials identified systemization of 
the CWDF as the next major challenge after resolving the bid issue for 
Building 101. Systemization consists of a series of tests to ensure the 
safety, function, and interoperability of the CWDF internal systems-- 
i.e., water, gas, electric, heat, and the chemical munitions 
destruction process. Such testing could be delayed if either 
destruction building (101 or 101A) or essential utilities are not 
completed on time. The automated destruction process is complex, 
involving the drilling, draining, and decontamination of various sizes 
and types of munitions, and the neutralization and bituminization of 
the nerve agent they contain. Ensuring that this system works and 
interfaces properly with the rest of the facility will require the 
testing and calibrating of roughly 1,000 different processes, according 
to a DOD official. DOD officials noted that U.S. experiences with 
destroying chemical weapons found that systemization often encounters 
difficulties and delays and has the potential to increase costs. 
Furthermore, DOD and Parsons must compete the systemization contract 
between two Russian subcontractors, Redkino and Giprosintez, selected 
by the Russian government. Given previous difficulties working with 
subcontractors, Parsons may experience delays in obtaining adequate and 
reasonably priced bids. 

DOD is attempting to mitigate systemization risk by exploring options 
to test the CWDF's systems using Russian rather than U.S. methods. 
Although the Shchuch'ye facility is a Russian design, it is currently 
planned to undergo testing procedures similar to those DOD uses in the 
United States. According to DOD officials, Russian systemization 
methods are less involved than U.S. processes, which must adhere to 
stringent environmental and operating regulations and can take 16 to 18 
months to complete. The Russian government, however, systemized its 
CWDF at Kambarka within 6 to 9 months. While DOD officials caution that 
each CWDF is unique, given the types of munitions to be destroyed, they 
have begun exploring whether Russian methods may allow for streamlining 
and compression of the systemization schedule at Shchuch'ye, while 
still maintaining acceptable safety levels. Parsons and its 
subcontractors are also testing the automated destruction system 
equipment before it is installed in Building 101. 

EVM System Has Not Been Effectively Implemented and Contains Flawed 
Data: 

DOD policy and guidance[Footnote 12] require the use of EVM to measure 
program performance. EVM uses contractor reported data to provide 
program managers and others with timely information on a contractor's 
ability to perform work within estimated cost and schedule. It does so 
by examining variances reported in contractor performance reports 
between actual cost and time of performing work tasks and the budgeted 
or estimated cost and time. In September 2004, DOD modified its 
contract with Parsons, allocating about $6.7 million and requiring the 
company to apply EVM to the Shchuch'ye project. Parsons was expected to 
have a validated EVM system by March 2005.[Footnote 13] As of April 
2006, Parsons had not developed an EVM system that provided useful and 
accurate data to CWDF program managers. In addition, our analysis found 
that the project's EVM data are unreliable and inaccurate. According to 
DOD officials, these problems stem in part from Parsons' outdated 
accounting system. EVM guidance states that surveillance[Footnote 14] 
of an EVM system should occur over the life of the contract. DOD has 
not yet conducted an integrated baseline review (IBR)[Footnote 15] for 
the Shchuch'ye project and does not plan to do so until after Parsons 
awards the subcontract to complete Building 101, possibly in June 2006. 

Parsons' EVM System Is Not Yet Useful to DOD Managers: 

In December 2005 a Parsons' self-evaluation[Footnote 16] stated that 
the EVM system for the CWDF was "fully implemented." In contrast, DOD 
characterized Parsons' EVM implementation as a "management failure," 
citing a lack of experienced and qualified Parsons staff. DOD withheld 
approximately $162,000 of Parsons' award fee due to concerns over the 
EVM system. In March 2006, DOD officials stated that at that point in 
implementation, EVM was not yet a useable tool in managing the 
Shchuch'ye project. DOD officials stated that Parsons needs to 
demonstrate that it incorporates EVM into project management rather 
than simply fulfilling a contractual requirement. DOD expects Parsons 
to use EVM to estimate cost and schedule impacts and their causes and, 
most importantly, to help eliminate or mitigate identified risks. 

Parsons' EVM staff stated that they underestimated the effort needed to 
incorporate EVM data into the system, train staff, and develop EVM 
procedures. Parsons officials were also surprised by the number of man- 
hours required to accomplish these tasks, citing a high level of staff 
turnover as contributing to the problem. According to the officials, 
working in a remote and isolated area caused many of the non-Russian 
employees to leave the program rather than extend beyond their initial 
tour of duty. 

Parsons' EVM Data Are Inaccurate and Unreliable: 

Based on our review of Parsons' monthly EVM data for September 2005 
through January 2006, we found that the data are inaccurate and 
unreliable and that Parsons is exercising poor quality control over its 
EVM data. Specifically, we discovered numerous instances where data 
were not added properly for scheduled work; Parsons' EVM reports, 
therefore, did not accurately capture data needed by project management 
to make informed decisions about the Shchuch'ye facility. For example, 
we found that from September 2005 through January 2006, Parsons' EVM 
reports contained addition errors that did not capture almost $29 
million in actual costs for the CWDF project. Such cost omissions and 
other errors may cause DOD and Parsons project officials to 
overestimate the amount of project funding available. 

Moreover, we found several instances where the accounting data were not 
allocated to the correct cost accounts, causing large cost over-runs 
and under-runs. This problem occurred because the accounting data were 
placed in the wrong account or Parsons' accounting system was unable to 
track costs at all levels of detail within EVM. A Parsons official 
stated that the company was taking measures to identify these 
inaccuracies and allocate the accounting data to the proper cost 
accounts. These problems, however, have led to numerous accounting 
errors in the EVM reports. Such mistakes underestimate the true cost of 
the CWDF project by ignoring cost variances that have already occurred. 
Cost variances compare the earned value of the completed work with the 
actual cost of the work performed. Until Parsons fixes its accounting 
system, manual adjustments will have to be made monthly to ensure that 
costs are properly aligned with the correct budget. Such continuous 
adjustments mean that the system is consistently reflecting an 
inaccurate status of the project for Parsons and DOD managers. (For 
specific examples of our findings regarding Parsons' EVM data, see app. 
II.) 

EVM guidance states that surveillance of an EVM system should occur 
over the life of the contract to guarantee the validity of the 
performance data provided to the U.S. government. Initial surveillance 
activities involve performing an IBR of a project within 6 months of 
awarding a contract and as needed throughout the life of a project. DOD 
and Parsons have not yet conducted an IBR for the Shchuch'ye project. 
Program managers are expected to use EVM reports that have been 
validated by an IBR. Without verifying the baseline, monthly EVM 
reporting, which tracks project work against a set budget and schedule, 
is neither meaningful nor valid. Parsons and DOD officials explained 
that while an IBR has been discussed, one will not be conducted until 
Parsons awards a contract for completing Building 101. DOD officials 
estimate that the award process for this contract may not be completed 
until summer 2006, approximately a year later than planned. According 
to Parsons, as of January 2006, about $66 million of scheduled work has 
not been completed as planned, due to the delay in awarding the 
subcontract for the balance of Building 101. DOD officials stated that 
while they recognize the importance of conducting surveillance over an 
EVM system, they currently are focused on the immediate need of 
establishing a usable EVM system on which to perform surveillance. 

Furthermore, DOD requires all EVM systems to undergo a compliance audit 
or "validation" conducted by the Defense Contract Management Agency 
(DCMA) with assistance from the Defense Contract Audit Agency (DCAA). 
DCAA found that Parsons' accounting process was inadequate. A DCAA 
official on the validation team stated that Parsons is relying on an 
outdated accounting system that has difficulty capturing actual costs 
for the Shchuch'ye project and placing them into appropriate cost 
categories. The DCAA official stated that Parsons management should 
have discovered such accounting errors before the EVM report was 
released to DOD. DCAA therefore questioned whether Parsons can generate 
correct accounting data and recommended that Parsons update its 
accounting system. As of April 2006, DCMA and DCAA had not yet 
validated Parsons' EVM system. (For more information regarding DCMA and 
DCAA's assessments of Parsons' EVM system see app. II.) 

Russia Has Developed a Destruction Plan and Increased Funding but May 
Not Meet Its Destruction Deadlines: 

Since our report in March 2004,[Footnote 17] the Russian government has 
approved a plan to destroy its chemical weapons stockpile and has begun 
financing significantly more of its own destruction activities. 
However, as of April 2006, the Russian government's progress in 
destroying its chemical weapons stockpile has been limited, and the 
Russian government's destruction plan may be overly ambitious and 
reliant on international assistance. 

Russia Has Developed a Destruction Plan That May Prove Overly 
Ambitious: 

We reported in early 2004 that Russia's lack of a credible chemical 
weapons destruction (CWD) plan had hindered destruction activities. 
However, in October 2005, the Russian government approved a plan for 
destroying its entire chemical weapons stockpile by the CWC-established 
deadline of 2012.[Footnote 18] The October 2005 plan calls for using 
seven destruction facilities to eliminate the entire chemical weapons 
stockpile. Destruction of the chemical weapons stockpile at Gorniy was 
completed in December 2005. As of March 2006, only the facility at 
Kambarka is operational. The plan outlines the construction of the 
remaining five sites, including Shchuch'ye, where nerve agent is to be 
eliminated. 

According to the Russian plan, the blister agents stored at Gorniy and 
Kambarka were to be destroyed first. In December 2005, the Russian 
government completed its destruction efforts at Gorniy and began 
destroying chemical weapons at Kambarka. In accordance with the plan, 
destruction will next be focused on nerve agents. The storage sites 
near Leonidovka, Maradykovskiy, and Pochep house large nerve-agent 
munitions, while those near Shchuch'ye and Kizner store smaller 
munitions. Table 1 depicts the schedule for Russian chemical weapons 
destruction facilities. 

Table 1: Schedule for Russian CWDFs: 

Russian destruction facility site: Gorniy; 
Actual or estimated date of operation: December 2002; 
Actual or estimated completion date for destroying weapons: December 
2005; 
Type of chemical weapons: Bulk blister; 
Quantity of agent to be destroyed (metric tons): 0; 
Amount of declared stockpile (metric tons): 1,120. 

Russian destruction facility site: Kambarka; 
Actual or estimated date of operation: December 2005; 
Actual or estimated completion date for destroying weapons: 2010; 
Type of chemical weapons: Bulk blister; 
Quantity of agent to be destroyed (metric tons): 6,347; 
Amount of declared stockpile (metric tons): 6,360. 

Russian destruction facility site: Maradykovskiy; 
Actual or estimated date of operation: 2006; 
Actual or estimated completion date for destroying weapons: 2012; 
Type of chemical weapons: Large nerve munitions; 
Quantity of agent to be destroyed (metric tons): 6,960; 
Amount of declared stockpile (metric tons): 6,960. 

Russian destruction facility site: Shchuch'ye; 
Actual or estimated date of operation: 2008; 
Actual or estimated completion date for destroying weapons: 2012; 
Type of chemical weapons: Small nerve munitions; 
Quantity of agent to be destroyed (metric tons): 5,440; 
Amount of declared stockpile (metric tons): 5,440. 

Russian destruction facility site: Leonidovka; 
Actual or estimated date of operation: 2008; 
Actual or estimated completion date for destroying weapons: 2012; 
Type of chemical weapons: Large nerve munitions; 
Quantity of agent to be destroyed (metric tons): 6,960; 
Amount of declared stockpile (metric tons): 6,960. 

Russian destruction facility site: Pochep; 
Actual or estimated date of operation: 2008; 
Actual or estimated completion date for destroying weapons: 2012; 
Type of chemical weapons: Large nerve munitions; 
Quantity of agent to be destroyed (metric tons): 7,520; 
Amount of declared stockpile (metric tons): 7,520. 

Russian destruction facility site: Kizner; 
Actual or estimated date of operation: 2009; 
Actual or estimated completion date for destroying weapons: 2012; 
Type of chemical weapons: Small nerve munitions; 
Quantity of agent to be destroyed (metric tons): 5,640; 
Amount of declared stockpile (metric tons): 5,640. 

Source: GAO analysis of Russian government and DOD data. 

[End of table] 

While the Russian plan indicates that the CWDF at Shchuch'ye will be 
operational by 2008, DOD estimates that the facility may not be 
operational until 2009. Furthermore, the Russian government's priority 
is to destroy nerve agents contained in large munitions, because 
destroying the larger-sized munitions first would allow Russia to meet 
its CWC destruction deadlines faster. Accordingly, the destruction of 
smaller munitions at Shchuch'ye[Footnote 19] may become less of a 
priority for the Russian government. 

However, the Russian government's destruction plan to eliminate all 
chemical weapons by 2012 may be unrealistic. It depends on the 
construction of seven facilities, but only two have been built, two are 
under construction, and three have not been started. Although the CWDF 
at Maradykovskiy may be operational in mid-2006, the Shchuch'ye 
facility is still under construction, and only minimal work has begun 
at the three remaining sites of Kizner, Leonidovka, and Pochep. 
According to its CWC destruction schedule, Russia must eliminate 20 
percent of its chemical weapons stockpile by April 2007. As of March 
2006, it had eliminated about 3 percent at Gorniy and Kambarka. Between 
April 2007 and April 2012, Russia must eliminate the remainder of its 
chemical weapons stockpile (about 80 percent) at five destruction 
facilities that have yet to be completed. It will be extremely 
difficult for the Russian government to complete and operate the last 
three facilities by its proposed schedule and meet its CWC commitment 
to destroy all stockpiles at these sites by the extended deadline of 
April 2012. 

Similarly, as of April 2006, DOD announced that the United States will 
not be able to meet the CWC extended destruction deadline of 2012. DOD 
estimates indicate that about 66 percent of the U.S. declared chemical 
weapons stockpile will be destroyed by April 2012. As of March 2006, 
the United States had destroyed about 36 percent of its declared 
stockpile. In the United States, DOD had five operating chemical 
weapons destruction facilities as of March 2006, and two additional 
facilities were being designed.[Footnote 20] 

Russia Has Significantly Increased Funding, but Destruction Efforts 
Need International Assistance: 

According to the Russian destruction plan, the estimated cost for 
eliminating the entire Russian chemical weapons stockpile is more than 
160 billion rubles--about $5.6 billion. 

Over the past 6 years, Russia has substantially increased its annual 
funding for its chemical weapons destruction efforts. In 2000, the 
Russian government spent about $16 million for chemical weapons 
destruction. By 2005, it had spent almost $400 million. For 2006, the 
Russian government plans to spend more than $640 million. For chemical 
weapons elimination at Shchuch'ye, the Russian government has budgeted 
about $144 million since fiscal year 2000. Russian funding at the site 
supports construction of one of the two destruction buildings (Building 
101A), as well as the industrial and social infrastructure (utilities, 
roads, schools, etc.) needed to support the facility's operations. 

The Russian government will need continued international assistance to 
complete destruction of its chemical weapons stockpile. The United 
States, Canada, Germany, Italy, United Kingdom, and other donors have 
committed almost $2 billion in assistance, with the United States 
committing the largest amount, about $1.039 billion. The Russian 
government estimates it will need about $5.6 billion to eliminate its 
entire stockpile. All U.S. assistance for destroying Russian chemical 
weapons is being provided to the CWDF at Shchuch'ye.[Footnote 21] As of 
March 2006, other international donors, such as Canada and the United 
Kingdom, are also providing significant assistance to Shchuch'ye to 
help fund the Russian destruction building (Building 101A) and the 
infrastructure needed to support the facility's operation.[Footnote 22] 
Although Italy is providing some funding for Shchuch'ye infrastructure, 
most of its contributions are committed to the construction of the CWDF 
at Pochep. Russia has been relying on German assistance to destroy its 
stockpile of blister agents at the Gorniy and Kambarka destruction 
facilities. Table 2 describes the commitments and types of assistance 
provided by international donors. 

Table 2: International Assistance for Russian CWD, as of April 2006: 

International donors: Belgium; 
Committed funding for Russian CWD (U.S. dollars)[A]: $100,000; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: To be determined. 

International donors: Canada; 
Committed funding for Russian CWD (U.S. dollars)[A]: $89,150,537; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: Industrial infrastructure, railway, and 
equipment for Building 101A. 

International donors: Czech Republic; 
Committed funding for Russian CWD (U.S. dollars)[A]: $232,458; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: Industrial infrastructure (electrical 
substations). 

International donors: Denmark; 
Committed funding for Russian CWD (U.S. dollars)[A]: $117, 970; 
Areas to receive international assistance: Various locations; 
Types of projects being funded: Public outreach efforts. 

International donors: European Union; 
Committed funding for Russian CWD (U.S. dollars)[A]: $14,156,452; 
Areas to receive international assistance: Gorniy, Kambarka, and 
Shchuch'ye; 
Types of projects being funded: Equipment at Gorniy and Kambarka, and 
industrial infrastructure at Shchuch'ye (electrical substation). 

International donors: Finland; 
Committed funding for Russian CWD (U.S. dollars)[A]: $871,771; 
Areas to receive international assistance: Gorniy and other locations; 
Types of projects being funded: Equipment at Gorniy and public outreach 
efforts. 

International donors: France; 
Committed funding for Russian CWD (U.S. dollars)[A]: $7,077,976; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: Environmental surveys and other 
projects to be determined. 

International donors: Germany; 
Committed funding for Russian CWD (U.S. dollars)[A]: $233,573,198; 
Areas to receive international assistance: Gorniy and Kambarka; 
Types of projects being funded: Equipment for the construction and 
operation of both facilities. 

International donors: Ireland; 
Committed funding for Russian CWD (U.S. dollars)[A]: $94,376; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: To be determined. 

International donors: Italy; 
Committed funding for Russian CWD (U.S. dollars)[A]: $439,660,257; 
Areas to receive international assistance: Shchuch'ye and Pochep; 
Types of projects being funded: Infrastructure (gas pipeline) at 
Schuch'ye and the construction of the Pochep CWDF. 

International donors: Netherlands; 
Committed funding for Russian CWD (U.S. dollars)[A]: $9,028,325; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: Equipment for Building 101A. 

International donors: New Zealand; 
Committed funding for Russian CWD (U.S. dollars)[A]: $1,158,433; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: Industrial infrastructure (electrical 
substation). 

International donors: Norway; 
Committed funding for Russian CWD (U.S. dollars)[A]: $3,250,969; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: Industrial Infrastructure (electrical 
substation) and other projects to be determined. 

International donors: Nuclear Threat Initiative; 
Committed funding for Russian CWD (U.S. dollars)[A]: $1,000,000; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: Infrastructure (railway bridge). 

International donors: Sweden; 
Committed funding for Russian CWD (U.S. dollars)[A]: $952,988; 
Areas to receive international assistance: Shchuch'ye; 
Types of projects being funded: To be determined. 

International donors: Switzerland; 
Committed funding for Russian CWD (U.S. dollars)[A]: $6,984,707; 
Areas to receive international assistance: Kambarka, Shchuch'ye, and 
other locations; 
Types of projects being funded: Sanitary and hygiene monitoring system 
at Shchuch'ye, equipment at Kambarka, and public outreach efforts. 

International donors: United Kingdom; 
Committed funding for Russian CWD (U.S. dollars)[A]: $141,196,728; 
Areas to receive international assistance: Shchuch'ye and other 
locations; 
Types of projects being funded: Industrial infrastructure, equipment 
for Building 101A, and public outreach efforts. 

International donors: United States; 
Committed funding for Russian CWD (U.S. dollars)[A]: $1,039,200,000; 
Types of projects being funded: Shchuch'ye; 
Types of projects being funded: Construction of the destruction 
facility. 

International donors: Total; 
Committed funding for Russian CWD (U.S. dollars)[A]: $1,987,807,145; 
Types of projects being funded: [Empty]; 
Types of projects being funded: [Empty]. 

Source: GAO analysis of data from DOD, State, and international donors. 

[A] Donor commitments converted from foreign currencies to U.S. dollars 
using the annual 2005 exchange rate. 

[End of table] 

To facilitate additional international contributions, the Russian 
government has provided potential donors a list of CWDF projects 
requiring assistance. Primarily, assistance is needed for the 
construction of the destruction facilities at Kizner, Leonikovka, and 
Pochep, as well as related infrastructure support. The Russian 
government is also seeking international funding to support operations 
at the Kambarka and Maradykovskiy facilities. 

Conclusion: 

Until destroyed, Russia's stockpile of chemical weapons--especially 
nerve agents contained in small munitions, such as those stored at 
Shchuch'ye--remain a proliferation threat, vulnerable to diversion and 
theft. Since 1992, the United States has been providing CTR assistance 
for the CWDF at Shchuch'ye to help reduce the threats posed by these 
weapons. Originally designed as a pilot facility to "jump start" 
Russian chemical weapons destruction efforts, Shchuch'ye may no longer 
be a priority for the Russian government. Delays in implementing the 
Shchuch'ye project over the past 14 years led the Russian government to 
begin destruction efforts at other sites. Disagreements between the 
United States and Russia over the types of munitions to destroy and how 
to destroy them, negotiations to resolve outstanding issues, 
restrictions on U.S. funding, and difficulties with Russian 
subcontractors, among other factors, have delayed the Shchuch'ye 
facility's completion and increased its costs. Although progress has 
been made on the physical construction of the facility over the past 3 
years, DOD continues to encounter numerous challenges that affect the 
completion of the Shchuch'ye CWDF. Furthermore, DOD currently cannot 
reliably estimate when the Shchuch'ye facility will be completed and at 
what cost. Parsons' EVM system, implemented to help manage the schedule 
and cost of the Shchuch'ye project, contains unreliable and inaccurate 
data; thus, DOD cannot use it as a management tool. Even with 
significant international assistance at Shchuch'ye and other 
destruction facility sites, the Russian government will likely fail to 
destroy its entire chemical weapons stockpile by the CWC extended 
deadline of 2012. 

Recommendations for Executive Action: 

Unreliable EVM data limit DOD's efforts to accurately measure progress 
on the Shchuch'ye project and estimate its final completion date and 
cost. As such, we recommend that the Secretary of Defense direct the 
Defense Threat Reduction Agency, in conjunction with the U.S. Army 
Corps of Engineers, to take the following three actions: 

* ensure that Parsons' EVM system contains valid, reliable data and 
that the system reflects actual cost and schedule conditions; 

* withhold a portion of Parsons' award fee until the EVM system 
produces reliable data; and: 

* require Parsons to perform an integrated baseline review after 
awarding the contract for completing Building 101. 

Agency Comments and Our Evaluation: 

DOD provided comments on a draft of this report, which are reproduced 
in appendix III. DOD concurred with our recommendation that DTRA in 
conjunction with the U.S. Army Corps of Engineers ensure that Parsons' 
EVM system contains valid, reliable data and reflects actual cost and 
schedule conditions, and require that Parsons perform an integrated 
baseline review after awarding the contract for completing Building 
101. DOD partially concurred with our recommendation that a portion of 
Parsons' award fee be withheld until the EVM system produces reliable 
data. DOD stated that it had withheld a portion of Parson's award fee 
in a previous period. DOD further noted that an award fee must be based 
on the merits of the contractor's performance and until the performance 
period is completed, it cannot prejudge Parsons' performance and 
predetermine the withholding of award fees based on our recommendation. 
DOD also provided technical comments, which we have incorporated where 
appropriate. The Department of State was provided a draft of this 
report but did not provide comments. 

We are providing copies of this report to the Secretaries of Defense 
and State and interested congressional committees. We will also make 
copies available to others upon request. In addition, this report will 
be available on the GAO Web site at [Hyperlink, http://www.gao.gov]. 

If you or your staff have any questions concerning this report, please 
contact me at (202) 512-8979 or christoffj@gao.gov. Contact points for 
our Offices of Congressional Relations and Public Affairs may be found 
on the last page of this report. GAO staff who made major contributions 
to this report are listed in appendix IV. 

Sincerely yours, 

Signed by: 

Joseph A. Christoff: 
Director, International Affairs and Trade: 

Appendix I: 
Scope and Methodology: 

To assess the progress of the Shchuch'ye facility, we collected and 
analyzed Department of Defense (DOD) and Parsons Global Services, Inc. 
(Parsons) contractor documents and met with relevant officials. 
Specifically, we met with officials from the Cooperative Threat 
Reduction (CTR) Policy Office, the office of the Assistant to the 
Secretary of Defense for Nuclear and Chemical and Biological Defense 
Programs, the Defense Threat Reduction Agency (DTRA), and the U.S. Army 
Corps of Engineers. Within DTRA, we obtained information from the 
Director of the Cooperative Threat Reduction Directorate, as well as 
the program and project managers, for chemical weapons elimination. We 
also met with officials from the Threat Reduction Support Center in 
Springfield, Virginia. In addition, we met with officials from the DTRA 
office and the Chemical Weapons Destruction Support Office in Moscow. 

We traveled to the Russian Federation to observe construction of the 
CTR-funded chemical weapons destruction facility at Shchuch'ye. At 
Shchuch'ye and Chelyabinsk, we met with personnel from Parsons and the 
U.S. Army Corps of Engineers. In Moscow, we met with Russian government 
officials at the Federal Agency for Industry, the Ministry of Foreign 
Affairs, the Duma, and the Accounts Chamber of the Russian Federation. 
We also analyzed the reliability of the earned value management (EVM) 
data for the Shchuch'ye project. Specifically, we examined Parsons' EVM 
reports for a 5-month period from, September 2005 to January 2006, to 
assess the Shchuch'ye destruction facility's cost and schedule. We 
checked the EVM data to see if there were any mathematical errors or 
inconsistencies that would lead to the data being unreliable. We 
interviewed officials from the Defense Contract Management Agency 
(DCMA), the Defense Contract Audit Agency (DCAA), and Parsons officials 
to better understand the anomalies in Parsons' EVM data and determine 
what outside surveillance was being done to ensure the validity of the 
EVM data. We also used a data collection instrument to obtain detailed 
information from DOD on the Shchuch'ye project, including the contract, 
program management activities, independent cost estimates, risk 
analysis, and award fees. 

To obtain information on Russian elimination efforts and international 
donor assistance for Russian chemical weapons destruction, we met with 
U.S., Russian, and international donor officials and obtained copies of 
pertinent documents, including the Russian chemical weapons destruction 
plan. We obtained information from officials in the Bureau of European 
and Eurasian Affairs and the Bureau of International Security and 
Nonproliferation at the Department of State. At DOD, we met with 
officials and acquired documents from the Office of the Secretary of 
Defense for Cooperative Threat Reduction Policy. In Moscow, we obtained 
information from Russian government officials at the Accounts Chamber, 
the Federal Agency for Industry, the Ministry of Foreign Affairs, and 
the Duma. At Shchuch'ye, we spoke with a local government official 
involved with public outreach efforts. We obtained data from the U.S., 
Russian, British, Canadian, and German governments as well as the G-8 
Global Partnership on the assistance committed and provided for Russian 
chemical weapons destruction efforts. To assess the reliability of 
these data, we corroborated other nations' data wherever possible, 
comparing and cross-checking documents and information. We interviewed 
officials from the United States, Canada, Germany, the United Kingdom, 
and the Russian Federation. We determined that data on funding and 
assistance provided for Russian chemical weapons destruction were 
sufficiently reliable for the purposes of this report. We also 
determined that data on the status of Russian and U.S. chemical weapons 
elimination were sufficiently reliable for the purposes of this report. 

The information on Russian law in this report does not reflect our 
independent legal analysis but is based on interviews and secondary 
sources. We performed our work from June 2005 through May 2006 in 
accordance with generally accepted government auditing standards. 

Appendix II: 

Lack of Reliable EVM Data Limits DOD's Ability to Estimate Schedule and 
Cost for Constructing the CWDF at Shchuch'ye: 

Measuring and reporting progress against cost and schedule commitments 
is vital to effective program management. To measure program 
performance, DOD requires the use of EVM, a concept that has been used 
by DOD since the 1960s for measuring program performance. Through EVM, 
program offices can determine a contractor's ability to perform work 
within cost and schedule estimates by examining variances between the 
actual and estimated costs and time to perform work tasks. EVM offers 
many benefits when done properly and serves as a means to measure 
performance and identify deviations from planned activities, allowing 
program managers to mitigate risks. Based on our analysis of Parsons' 
EVM data, and the findings of the Defense Contract Management Agency 
(DCMA) and Defense Contract Audit Agency (DCAA), the data are 
inaccurate and unreliable. Without reliable schedule and cost 
estimates, DTRA has limited means to accurately assess when the 
Shchuch'ye facility will be completed and at what cost. 

GAO's Analysis Reveals Parsons' EVM Data are Unreliable and Require 
Surveillance: 

In reviewing Parsons' monthly EVM data for September 2005 through 
January 2006, we discovered numerous instances of data not adding 
properly for scheduled work. Further, Parsons' EVM reports are not 
capturing all of the data needed by project management to make informed 
decisions about the Shchuch'ye facility. Such errors may cause DOD and 
Parsons project officials to overestimate the amount of funding 
available to cover future risks, such as the systemization of the 
Shchuch'ye facility. Moreover, we found several instances where the 
accounting data were not allocated to the correct cost accounts causing 
large cost over-runs and under-runs. In these cases, the accounting 
data were placed in the wrong account, or Parsons' accounting system 
was unable to track costs at the level of detail EVM as requires. 
Parsons officials stated that measures are being taken to identify 
these inaccuracies and allocate the accounting data to the proper cost 
accounts. These problems, however, have led to numerous accounting 
errors in Parsons' EVM reports. 

Furthermore, in reviewing Parsons' EVM reporting data, we found several 
errors that a Parsons' official attributes to the company's accounting 
system. For instance, current EVM period data are not accurate due to 
historical data corruption, numerous mistakes in accounting accruals, 
and manual budget adjustments. Such mistakes underestimate the true 
cost of the CWDF project by ignoring cost variances that have already 
occurred. For example, the Moscow project management task was budgeted 
at a cost of $100,000. According to the January 2006 EVM report, the 
work has been completed but the actual cost was $2.6 million, resulting 
in an overrun of approximately $2.5 million. The EVM report, however, 
fails to capture the expected $2.5 million overrun. Such data are 
misleading and skew the project's overall performance. As indicated in 
table 3, this is just one example of accounting system errors. In the 
case of the Moscow project management task, Parsons officials explained 
that this error occurred because the budget for this account was 
misaligned and, therefore, caused a false cost variance. Parsons 
officials stated they would be issuing an internal change order to 
correct this mistake. 

Table 3: Examples of Accounting System Errors Understating the Variance 
at Completion from January 2006 Report: 

Dollars in Millions: 

Estimate at completion: 


Design task (27); task management; 
Work scheduled: $2.1; 
Work performed: $2.1; 
Actual costs: $5.5; 
Budget at completion: $2.1; 
Estimate at completion: $2.1; 
GAO analysis of variance at completion understated by: $3.4. 

Work scheduled: Design task (27); project management, Moscow; 
Work scheduled: $0.1; 
Work performed: $0.1; 
Actual costs: $2.6; 
Budget at completion: $0.1; 
Estimate at completion: $0.1; 
GAO analysis of variance at completion understated by: $2.5. 

Work scheduled: Design task (27); construction packages; 
Work scheduled: $9.4; 
Work performed: $9.0; 
Actual costs: Budget at completion: $20.2; 
Budget at completion: $9.9; 
Estimate at completion: $9.9; 
GAO analysis of variance at completion understated by: $11.0. 

Construction task (33); Parsons purchased equipment Building 101; 
Work scheduled: $48.6; 
Work performed: $36.1; 
Actual costs: Budget at completion: $10.4; 
Budget at completion: $80.7; 
Estimate at completion: $52.3; 
GAO analysis of variance at completion understated by: $28.3. 

Source: GAO analysis of Parsons data. 

[End of table] 

Until Parsons' management updates the company's accounting system, 
these types of manual adjustments will have to be made through monthly 
change orders to ensure that costs are properly aligned with the 
correct budget. Such continuous adjustments do not allow the EVM system 
to provide timely and accurate information to Parsons and DOD managers. 

In addition, DOD guidance and best practices require program managers 
to conduct an integrated baseline review (IBR) as needed to ensure that 
the baseline for tracking cost, technical information, and schedule 
status reflects (1) all tasks in the statement of work, (2) adequate 
resources in terms of staff and materials to complete the tasks, and 
(3) integration of the tasks into a well-defined schedule. Program 
managers are required to use EVM reports that have been validated by an 
IBR. Without verifying the baseline, monthly EVM reporting--which 
tracks project work against a set budget and schedule--is insufficient 
and invalid. 

Parsons and DOD officials explained that while an IBR has been 
discussed, one will not be conducted until the contract for completing 
Building 101 has been awarded. DOD officials estimate that the contract-
award process may not be completed until June 2006, resulting in a 1 
year delay. Such a delay not only prevents Parsons from holding an IBR, 
but it also jeopardizes DOD's ability to accurately estimate the cost 
and schedule to complete the CWDF program. Until the costs have been 
negotiated for building the remainder of Building 101, it is unclear 
whether the CWDF at Shchuch'ye will be completed on time and within 
budget. DTRA officials explained that if the costs for this effort 
exceed the original estimate, they will have to cover the shortfall 
using management reserve funds. Using management reserve funds for 
construction leaves less contingency funding available to complete and 
test the Shchuch'ye facility. 

DCMA and DCAA Have Concerns with Parsons' EVM Implementation: 

Until December 2004, DTRA was using EVM data from a simplified Parsons 
EVM process. In September 2004, DTRA directed Parsons to implement a 
complete EVM system that was capable of being validated by DCMA. 
Although Parsons' EVM validation was originally scheduled for March 
2005, Parsons was unable to meet this deadline and requested a series 
of extensions. In September 2005, DCMA officials visited the Shchuch'ye 
site for a program assistance visit and then returned in mid-November 
2005 to conduct the formal validation review, 8 months later than 
planned. 

DOD requires all EVM systems to go through a compliance audit or 
"validation" conducted by DCMA, with assistance from DCAA. The 
evaluation team looks for proof that the system meets the 32 
criteria[Footnote 23] for a good EVM system, as well as 2 to 3 months 
of reliable EVM data. While the DCMA official who led the validation 
team saw much improvement in Parsons' EVM system from September to 
November 2005, he stipulated that an EVM compliance audit only tests 
whether the contractor has a good, capable EVM system and knows how to 
use it. A compliance audit does not identify whether the system is used 
properly, the data are reliable, or the products of the system are read 
and acted upon by management. The DCMA official stated that continual 
surveillance of Parsons' EVM system would be necessary to ensure these 
actions were occurring. According to the official, DCMA does not expect 
to perform surveillance for the Shchuch'ye project. 

DCAA also participated in Parsons' EVM validation and produced a 
corrective action report stating that its EVM accounting process was 
inadequate. Specifically, Parsons did not provide adequate 
documentation that direct costs of almost $300,000 were based on 
accurate and reliable accounting data. The source of the accounting 
data used by Parsons may be unreliable, causing actual costs for 
September 2005 to be significantly understated. For September 2005, 
Parsons subtracted almost $1 million without providing sufficient data 
that the adjustment was reasonable and allowable. A DCAA official 
stated that these findings are the result of Parsons' reliance on an 
outdated accounting system that has difficulty capturing actual costs 
for the Shchuch'ye project into a proper cost ledger. The official 
noted that the software Parsons uses to query the accounting system and 
pull data into the EVM reports also caused errors. DCAA was also 
concerned with Parsons' ability to apply effective EVM data quality 
control. According to DCAA officials, Parsons' management should have 
discovered such accounting errors before the EVM report was released to 
DOD. DCAA therefore questioned whether Parsons can generate correct 
accounting data and recommended that Parsons update its accounting 
system. 

Appendix III: 

Comments from the Department of Defense: 

Nuclear And Chemical And Biological Defense Programs: 
Assistant To The Secretary Of Defense: 
3050 Defense Pentagon Washington, DC 20301-3050: 

May 19, 2006: 

Mr. Joseph A Christoff: 
Director, International Affairs and Trade: 
U.S. Government Accountability Office (GAO): 
441 G Street N.W. 
Washington, DC 20548: 

Dear Mr. Christoff: 

This is the Department Of Defense (DOD) response to the GAO draft 
report 06-692, "COOPERATIVE THREAT REDUCTION: DOD Needs More Reliable 
Data to Better Estimate the Cost and Schedule Of the Shchuch'ye 
Facility," dated May 3, 2006 (GAO Code 320363). 

The Department concurs with the report. Suggested technical and 
editorial corrections to the report were provided separately. The 
detailed comments to each report recommendation are provided in the 
enclosure. 

The Department appreciates the opportunity to review and comment On the 
draft report.  

Signed by: 

Dale Klein: 

Enclosure: 
As stated: 

cc: 
DIR DTRA: 
DASD NP: 

GAO DRAFT REPORT DATED MAY 3, 2006 GAO-06-692 (GAO CODE 320363): 

"COOPERATIVE THREAT REDUCTION: DOD NEEDS MORE RELIABLE DATA TO BETTER 
ESTIMATE THE COST AND SCHEDULE OF THE SHCHUCH'YE FACILITY" 

DEPARTMENT OF DEFENSE COMMENTS TO THE GAO RECOMMENDATIONS: 

RECOMMENDATION (A): The GAO recommended that the Secretary of Defense 
direct the Defense Threat Reduction Agency, in conjunction with the 
U.S. Army Corps of Engineers to ensure that the Parsons' Earned Value 
Management (EVM) system contains valid, reliable data and that it 
reflects actual cost and schedule conditions. 

DOD RESPONSE: (DOD) concurs. The Defense Threat Reduction Agency 
(DTRA), the U.S. Army Corps of Engineers (COE), the Defense Contract 
Management Agency (DCMA), and the Defense Contract Audit Agency ("CAA) 
continue to work collaboratively with Parsons to ensure that the 
Parsons' Earned Value Management (EVM) system contains valid, reliable 
data and that it reflects actual cost and schedule conditions. Parsons' 
EVM data continues to improve and is now being used by Parsons, COE, 
and DTRA managers to manage the program. However, more work will be 
done to improve its quality. For example, over the next few months, 
software upgrades will be made to make the EVM data more user friendly. 
(DOD) surveillance and improvement of the EVM system will Continue 
using its own technical experts and assistance from DCMA/DCAA. DCMA 
validation of the EVM system is pending the resolution of DCAA 
identified faults in Parsons' accounting system. 

RECOMMENDATION (B): The GAO recommended that the Secretary of Defense 
direct the Defense Threat Reduction Agency, in conjunction with the 
U.S. Army Corps of Engineers, to withhold a portion of Parsons' award 
fee until the PATNA system produces reliable data. 

DOD RESPONSE: (DOD) partially concurs. No direction from the Secretary 
of Defense is required. (DOD) already withheld a portion of Parsons' 
award fee in a previous period based on the EVM system. This is a 
standard management technique practiced by (DOD) However, (DOD) cannot 
prejudge Parsons and predetermine an award fee based on a GAO 
recommendation. An award fee must be based on the merits of the 
performance, according to the contract's award fee criteria. 

RECOMMENDATION (C): The GAO recommended that the Secretary of Defense 
direct the Defense Threat Reduction Agency, in conjunction with the 
U.S. Army Corps of: 

Engineers to require Parsons to perform an integrated baseline review 
after awarding the contract for completing Building 101. 

DOD RESPONSE: (DOD) Concurs. (DOD) and Parsons always intended to 
conduct an integrated baseline review of the project after Parsons 
awarded the contract for completing building 101. 

Appendix IV: 

GAO Contact and Staff Acknowledgments: 

GAO Contact: 

Joseph Christoff (202) 512-8979 or christoffj@gao.gov: 

Acknowledgments: 

In addition to the individual named above, Muriel Forster (Assistant 
Director), Jerome Brown, Lynn Cothern, Jennifer Echard, David Hancock, 
Beth Hoffman León, and Karen Richey contributed to this report. Joanna 
Chan, Martin DeAlteriis, Mark Dowling, Jennifer Mills, and Jena 
Sinkfield also provided assistance. 

(320363): 

FOOTNOTES 

[1] Nerve agents affect the transmission of nerve impulses in the 
nervous system. Nerve agents are easily dispersed and highly toxic when 
absorbed through the skin or via respiration. Blister agents, which can 
be lethal if inhaled, generally cause burns on contact with skin. The 
blister agents include mustard gas and lewisite. 

[2] The CWC requires the destruction of existing chemical weapons 
stocks and production facilities by 2007 with a possible extension to 
2012. 

[3] For a summary of the legislation, see appendix II of GAO, 
Cooperative Threat Reduction: DOD Has Improved Its Management and 
Internal Controls, but Challenges Remain, GA0-05-329 (Washington, D.C.: 
June 30, 2005). Since publication of that report, Congress has passed 
two laws containing measures addressing CTR. Pub. L. 109-103, Div A 
(The National Defense Authorization Act for Fiscal Year 2006) and Pub. 
L. 139-148, Div A (The Department of Defense Appropriations Act of 
2006). 

[4] Pub. L. 108-375, sec. 1303 (amending Pub. L. 108-136, sec. 1306). 

[5] See Pub. L. 106-65, sec. 1305. 

[6] See Pub. L. 107-107, sec. 1308. The Secretary of Defense must 
certify that there has been (1) information provided by Russia, that 
the United States assesses to be full and accurate, regarding the size 
of the chemical weapons stockpile of Russia; (2) a demonstrated annual 
commitment by Russia to allocate at least $25 million to chemical 
weapons elimination; (3) development by Russia of a practical plan for 
destroying its stockpile of nerve agents; (4) enactment of a law by 
Russia that provides for the elimination of all nerve agents at a 
single site; (5) an agreement by Russia to destroy or convert its 
chemical weapons production facilities at Volgograd and Novocheboksark; 
and (6) a demonstrated commitment from the international community to 
fund and build infrastructure needed to support and operate the 
facility. 

[7] The specialist camp is the building to house contractors working on 
site. 

[8] The gas rescue station will serve as a training center and 
equipment depot for dealing with hazardous materials on site. 

[9] Construction packages are "mini contracts" for completing specific 
tasks associated with buildings and infrastructure that are awarded to 
subcontractors on a competitive basis. 

[10] The Green Cross public outreach offices are located in Shchuch'ye, 
Chelyabinsk, and Kurgan. 

[11] According to its agreement with DOD, the Russian government must 
identify and obtain all legal permits, licenses, and certifications 
required to design, construct, equip, commission, and operate the 
Shchuch'ye CWDF. 

[12] Defense Contract Management Agency, Department of Defense Earned 
Value Management Implementation Guide, (Washington, D.C.: Apr. 7, 
2005). See also DOD Memorandum: Revision to DOD Earned Value Management 
Policy, (Washington, D.C.: Mar. 7, 2005). 

[13] According to DOD, a validated EVM system was not required at the 
time the Parsons contract was awarded. A modified EVM system, 
implemented in September 1998, was maintained and used until December 
2004. 

[14] Surveillance is the process of reviewing the health of the EVM 
system process. The purpose of surveillance is to focus on using EVM 
system effectively to manage cost, schedule, and technical performance. 
An effective surveillance process ensures that the key elements of the 
process are maintained over time. 

[15] An IBR verifies the technical content of the baseline. It also 
ensures that contractor personnel understand and have been adequately 
trained to collect EVM data. The review also verifies the accuracy of 
the related budget and schedule to ensure that risks have been properly 
identified, and it also assesses whether the contractor meets the 
program's objectives. 

[16] Award fee contracts allow government agencies to adjust the amount 
of fee paid to contractors based on the contractor's performance. 
Parsons is required to do a self assessment of its performance at the 
end of each award fee evaluation period. 

[17] GAO, Nonproliferation: Delays in Implementing the Chemical Weapons 
Convention Raise Concerns About Proliferation, GAO-04-361 (Washington, 
D.C.: Mar. 31, 2004). 

[18] The Government of the Russian Federation Resolution, No. 639 (Oct. 
24, 2005). On Amendments to the Federal Target-Oriented Program, 
"Chemical Weapons Stockpiles Destruction in the Russian Federation." 

[19] The nerve agents to be destroyed at the Shchuch'ye CWDF are stored 
at the Planovy arsenal located about 10 miles away. 

[20] The U.S. facilities operational as of March 2006 include Umatilla, 
Ore; Newport, Ind; Deseret, Utah; Pine Bluff, Ark; and Anniston, Ala. 
The facilities at Blue Grass, Ky; and Pueblo, Colo., remain in the 
design phase. In February 2006, the facility at Edgewood, Md., began 
closing procedures. As of November 2003, all chemical weapons at 
Johnston Atoll were destroyed and the destruction facility dismantled. 

[21] In addition to funds for destroying Russian chemical weapons, 
other CTR assistance is being provided to help eliminate former Russian 
chemical weapons production facilities at Volgograd and 
Novocheboksarsk. 

[22] The United States, the United Kingdom, and Canada, in conjunction 
with the Russian Federation, formed a working group in November 2003 to 
coordinate all international assistance to the Shchuch'ye site. 

[23] The American National Standards Institute/Electronic Industries 
Alliance guidance identifies 32 criteria that reliable EVM systems 
should meet. The criteria are organized into five categories: 
organization, planning and budgeting; accounting; analysis; and 
revisions and data maintenance. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: