This is the accessible text file for GAO report number GAO-05-369 
entitled 'Smithsonian Institution: Facilities Management Reorganization 
Is Progressing, but Funding Remains a Challenge' which was released on 
May 25, 2005. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Requesters: 

April 2005: 

Smithsonian Institution: 

Facilities Management Reorganization Is Progressing, but Funding 
Remains a Challenge: 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-05-369]

GAO Highlights: 

Highlights of GAO-05-369, a report to congressional requesters: 

Why GAO Did This Study: 

The Smithsonian is the world’s largest museum complex and research 
organization, with 18 museums and galleries, 10 science centers, and a 
zoological park. The age of the structures, past inattention to 
maintenance needs, and high visitation have left its facilities in need 
of revitalization and repair. Currently, the Smithsonian estimates $2.3 
billion in costs for revitalization, construction, and maintenance 
projects between 2005 and 2013. This report addresses (1) how the 
current condition of the Smithsonian’s facilities has affected access 
to the collections, and the collections themselves; (2) what changes 
the Smithsonian has made to its organization, practices, and 
prioritization processes to improve its facilities management; and (3) 
the estimated costs and status of the Smithsonian’s facilities projects 
and their funding sources. 

What GAO Found: 

To date, facilities-related problems at the Smithsonian have resulted 
in a few building closures and access restrictions and some cases of 
damage to the collections. For example, structural deterioration has 
caused closure of the 1881 Arts and Industries Building on the National 
Mall pending major repair and revitalization, as well as some 
facilities at the National Zoo. Concern over asbestos in a number of 
storage buildings has led to restricted access to the items within 
them. Some artifacts, such as two historic aircraft, have been damaged 
by water leaks from deteriorated pipes and roofing elements. Stopgap 
measures, such as draping plastic sheeting over artifacts in areas 
experiencing leaks, have prevented or minimized damage in other cases. 
Maintaining desired humidity and temperature levels for conserving the 
collections is a pervasive problem in some older Smithsonian 
facilities. These problems are indicative of a broad decline in the 
Smithsonian’s aging facilities and systems that pose a serious long-
term threat to the collections. 

The Smithsonian recently centralized its facilities organization, 
adopted industry best practices to maximize the effectiveness of its 
resources, reviewed its operating procedures, standardized its cost-
estimating practices, and established processes for prioritizing work 
and allocating funds. These changes resulted from an internal review 
and a 2001 report by the National Academy of Public Administration, 
which recommended that the Smithsonian centralize its then highly 
decentralized approach to facilities management and budgeting in order 
to promote uniform policies and procedures, improve accountability, and 
avoid duplication. The Smithsonian created the Office of Facilities 
Engineering and Operations (OFEO) in 2003 to assume responsibility for 
all facilities-related programs and budgets--formerly divided among 
four administrative offices and the individual museums and centers. 
Most of the museum and center directors were either positive or neutral 
about the effectiveness of the reorganization so far. Overall, the 
reorganization appears to be moving in the right direction, though it 
has been hindered by reductions in OFEO’s staffing and budget. 

The Smithsonian currently estimates that its planned capital and 
maintenance projects for 2005 through 2013 will cost about $2.3 
billion, though this could grow because it is largely based on 
preliminary assessments. Of 13 revitalization and construction projects 
active during our review, most were on time and within budget. The 
Smithsonian’s annual operating and capital program revenues come from 
its own trust fund assets and its federal appropriation (totaling 
$904.0 million in fiscal year 2004, with $184.4 million for 
facilities). Funding at this level would not be sufficient to cover the 
facilities projects planned for the next 9 years. Ensuring credible, 
long-term budget planning for sustaining and modernizing facilities 
involves the Smithsonian, the Office of Management and Budget, and the 
Congress in examining viable funding options. While Smithsonian 
officials have discussed funding options internally and with various 
stakeholders, no consensus has emerged on how to deal with this funding 
challenge. 

What GAO Recommends: 

We are recommending that the Smithsonian establish a process for 
exploring funding options with the Administration and the Congress, 
leading to the development and implementation of a strategic funding 
plan to address the Smithsonian’s revitalization, construction, and 
maintenance needs. In commenting on our report, the Smithsonian 
concurred with our findings and recommendation. 

www.gao.gov/cgi-bin/getrpt?GAO-05-369.
To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Mark Goldstein at (202) 
512-8022 or goldsteinm@gao.gov. 

[End of section]

Contents: 

Letter: 

Results in Brief: 

Background: 

Facility Conditions Have Generally Had Limited Effects on Access and 
Collections, but Some Chronic Problems Present Ongoing Risks: 

Smithsonian Has Centralized Its Facilities Management Organization and 
Budget to Improve the Efficiency and Effectiveness of Its Operations: 

Estimated Costs of Facilities Projects Have Grown, Posing Serious 
Funding Challenge: 

Conclusion: 

Recommendation for Executive Action: 

Agency Comments: 

Appendixes: 

Appendix I: Funding Sources and Statutes Related to the Smithsonian's 
Revitalization, Construction, and Minor Repair and Maintenance 
Programs: 

Appendix II: Smithsonian Institution's Status on the Implementation of 
the National Academy of Public Administration's Recommendations: 

Appendix III: Organization and Responsibilities of the Smithsonian's 
Office of Facilities Engineering and Operations: 

Appendix IV: Smithsonian's Efforts to Implement Leading Practices in 
Capital Decision-Making: 

Appendix V: Facility Revitalization and Construction Project Code 
Assignment Matrix: 

Appendix VI: Flow Chart of the Prioritization Decision-Making Process 
for Minor Repair and Maintenance: 

Appendix VII: Scope and Methodology: 

Appendix VIII: Comments from the Smithsonian Institution: 

Appendix IX: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Staff Acknowledgments: 

Tables: 

Table 1: Appropriated and Estimated Costs of Smithsonian Capital and 
Maintenance Programs, Fiscal Years 2005-2013: 

Table 2: Estimated Costs for Major Revitalization Projects as Reported 
by NAPA in 2001 and Identified by the Smithsonian in 2005: 

Table 3: Status of Fiscal Year 2004 Funded or Completed Major Projects 
as of April 2005: 

Figures: 

Figure 1: Location of Smithsonian Institution Facilities: 

Figure 2: Growth in Major Facilities Owned by the Smithsonian, in 
Square Feet: 

Figure 3: Arts and Industries Building, 1977 (left) and February 2005 
(right): 

Figure 4: Sloth Bear Facility, National Zoo: 

Figure 5: Measures to Shield Collections from Asbestos, Garber 
Facility, Suitland, MD: 

Figure 6: Water Stain on Wing of Lilienthal Hang Glider, National Air 
and Space Museum: 

Figure 7: Rust on Fuselage of Douglas Skyrocket, D558, Caused by Water 
Leak, National Air and Space Museum: 

Figure 8: Flooded Mechanical Room at the National Zoo: 

Figure 9: Alcohol-Preserved Specimens Stored on Open Shelves at the 
National Museum of Natural History: 

Figure 10: Nonexplosion Proof Lighting Fixtures and Switches in Alcohol 
Storage Rooms at the National Museum of Natural History: 

Figure 11: Organization of Smithsonian's New Office of Facilities 
Engineering and Operations: 

Figure 12: Failing Heating, Ventilation and Air Conditioning System at 
National Air and Space Museum: 

Figure 13: Antiquated Fire Suppression System, National Air and Space 
Museum: 

Figure 14: Flooding in High-Voltage Room, National Museum of American 
History: 

Figure 15: Leak in the Room 4303 (History Storage Room) at the National 
Museum of American History: 

Figure 16: Site Footprint of Planned Alcohol Storage Unit (Pod 5) to be 
added to the Museum Support Center, Suitland, MD: 

Figure 17: Estimated Maintenance Project Costs, by Type (dollars in 
millions): 

Abbreviations: 

CII: Construction Industry Institute: 

COTS: Commercial Off the Shelf: 

CPPB: Capital Program Planning Board: 

ERP: Enterprise Resource Planning: 

FONZ: Friends of the National Zoo: 

FY: Fiscal year: 

HVAC: Heating, ventilation and air conditioning: 

Maintenance: Minor repair and maintenance: 

Mall: National Mall: 

NAPA: National Academy of Public Administration: 

National Zoo: National Zoological Park: 

NHPA: National Historic Preservation Act: 

NMAH: National Museum of American History: 

NMNH: National Museum of Natural History: 

NRC: National Research Council: 

OFEO: Office of Facilities Engineering and Operations: 

OMB: Office of Management and Budget: 

OPP: Office of Physical Plant: 

PC: Priority Code: 

PFITS: Capital program cuff system: 

PT&I: Predictive testing and inspection: 

RCM: Reliability Centered Maintenance: 

RR&A: Renovation, repair and alteration: 

S&E: Salary and expenses: 

SAO: Smithsonian Astrophysical Observatory: 

SFS: Smithsonian Financial System: 

Smithsonian: Smithsonian Institution: 

VERITAS: Very Energetic Radiation Imaging Telescope Array System: 

Letter April 25, 2005: 

The Honorable Bill Shuster: 
Chairman, Subcommittee on Economic Development, Public Buildings, and 
Emergency Management: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

The Honorable Eleanor Holmes Norton: 
Ranking Democratic Member, Subcommittee on Economic Development, Public 
Buildings, and Emergency Management: 
Committee on Transportation and Infrastructure: 
House of Representatives: 

In January 2004, the Smithsonian Institution (the Smithsonian) closed 
its 1881 Arts and Industries Building to the public over concern about 
its deteriorating roof structure. During 2003, the roofs of two 
historic buildings of similar age and design had partially collapsed 
under heavy snowfall.[Footnote 1] Arts and Industries--used most 
recently for special exhibits and administrative offices--will need 
major renovation and revitalization work, including the replacement of 
its aging electrical, plumbing, and heating and cooling systems, before 
it can be returned to service. The failing condition of this National 
Mall (the Mall) landmark is the most extreme example of what a 
Smithsonian official has characterized as a "broad decline" in its 
extensive physical plant. 

This decline can, paradoxically, be linked to the Smithsonian's 
remarkable success in carrying out its mission: "the increase and 
diffusion of knowledge among men." In the years since its founding in 
1846, the Smithsonian Institution has preserved--and shared--our 
nation's most precious objects and become an international leader in 
scholarship and scientific discovery. From its original building on the 
Mall (commonly known as "the Castle"), the Smithsonian has evolved into 
the world's largest museum complex and research organization, with 18 
museums and galleries, 10 science centers, a zoological park, and 
various other facilities--in total, more than 660 owned and leased 
buildings and other structures, with an estimated replacement value of 
about $4.7 billion for owned space as of June 2004. About 143.7 million 
objects and specimens are safeguarded, studied, and displayed within 
its facilities, including research collections in natural history and 
biology, as well as icons of our national history such as the Fort 
McHenry "Star Spangled Banner" and the Apollo 11 command 
module.[Footnote 2] Two of the Smithsonian's museums on the Mall are 
the most visited in the world, with a third rivaling visitation at the 
British Museum and the Louvre. 

With this tremendous physical expansion and popularity, however, have 
come related facilities problems that include the structural 
deterioration of aging buildings; heating, cooling and electrical 
systems that are well past their normal life expectancy; leaks from 
roofs and pipes that jeopardize the collections; inadequate exhibition 
and storage space; and maintenance levels that have not kept pace with 
the wear and tear from millions of visitors each year. A 2001 report by 
the National Academy of Public Administration (NAPA)--based on a review 
requested by the Congress--highlighted the need for major changes in 
the Smithsonian's facilities management practices to help address these 
problems. In response to NAPA's recommendations, as well as its own 
internal review, the Smithsonian has been transforming its approach to 
facilities management. The NAPA report also found that, prior to 2000, 
the Smithsonian underestimated its revitalization needs, which were 
significantly larger than were identified in its budget requests. The 
Smithsonian has updated its funding requirements and has a 9-year 
estimate for the revitalization of its older buildings, new 
construction, and minor repair and maintenance (maintenance)[Footnote 
3] work that now stands at about $2.3 billion.[Footnote 4]

In light of ongoing concerns over the state of its facilities, you 
asked us to review the Smithsonian's facilities management. 
Accordingly, we addressed the following questions: 

* How does the current condition of the Smithsonian's facilities affect 
public and scientific access to the collections, and the collections 
themselves?

* What changes to its organizational structures and practices has the 
Smithsonian put in place to manage its facilities, and how does the 
Smithsonian now prioritize its revitalization, construction, and 
maintenance projects?

* What are the estimated costs and status of the Smithsonian's major 
revitalization, construction, and maintenance projects, including those 
that have been deferred, and what are the funding sources for these 
projects?

In addition, you asked us to provide information on how the Smithsonian 
uses its trust fund resources and federal appropriations to fund its 
operations, as well as information on the basic legal authorities under 
which the Smithsonian runs its revitalization, construction, and 
maintenance programs. This information is included as appendix I of 
this report. 

To address these issues, we visited 11 Smithsonian facilities to view 
and discuss problem areas with staff from the Smithsonian's Office of 
Facilities Engineering and Operations (OFEO) and the directors of the 
individual facilities. The Smithsonian identified these facilities as 
having significant facilities-related problems. Several facilities that 
we visited consisted of multiple buildings, such as the National 
Zoological Park (the National Zoo), which has more than 40 buildings. 
We interviewed the OFEO director and other appropriate OFEO staff, 
project executives, and project managers, as well as the Smithsonian's 
chief financial officer, associate general counsel, and 16 directors of 
museums, galleries, the National Zoo, a program and a research center 
(all internal customers of OFEO). We reviewed a variety of Smithsonian 
handbooks and guidance related to facilities project management, 
prioritization criteria, decision-making processes, and best practices. 
We also reviewed the NAPA report, the Smithsonian inspector general's 
reports, and other appropriate reports. We researched the Smithsonian's 
enabling legislation, the statutes under which it currently operates, 
including appropriations acts and numerous statutes authorizing 
Smithsonian Institution facilities from the 1950s. We also reviewed the 
Smithsonian's congressional budget requests and audited financial 
statements for fiscal years 2002, 2003, and 2004. The information we 
gathered was sufficiently reliable for the purposes of our review. We 
conducted our work between April 2004 and April 2005 in accordance with 
generally accepted government auditing standards. See appendix VII for 
a more detailed explanation of our scope and methodology. 

Results in Brief: 

Facilities-related problems at the Smithsonian have resulted in a few 
building closures and access restrictions, and some cases of harm to 
the collections. The problems range from major structural deterioration 
to chronic leaks that have damaged a few collections and threatened 
others. While the impact of these problems thus far has been limited, 
ongoing deterioration continues to present serious long-term risks to 
the collections' accessibility and safety. A few facilities have 
deteriorated to the point where access must be denied or limited. The 
1881 Arts and Industries Building on the Mall was closed to the public 
in 2004 for an indefinite period, pending repair of its weakened roof 
panels, renovation of its interior (which has been damaged by water 
intrusion), and replacement of aging systems such as heating and 
cooling. Another example is the National Zoo, where deterioration has 
led to closures, such as the sloth bear facility and the flight cage 
for birds of prey, and problems with major systems could jeopardize the 
operation of other zoo facilities. In addition, concern over asbestos 
in some Smithsonian storage buildings has led to restrictions on access 
to the collections kept inside them. Water leaks caused by deteriorated 
piping and roofing elements, along with humidity and temperature 
problems in buildings with aging systems, pose perhaps the most 
pervasive threats to artifacts in the museums and storage facilities. 
For example, leaks have damaged two historic aircraft at the National 
Air and Space Museum. Quick action by staff and stopgap measures, such 
as draping plastic sheets over materials exposed to leaks, has helped 
to prevent or minimize damage in other cases. For example, Smithsonian 
Institution Archives staff told us that they have had to deal with 19 
"water emergencies" since June 2002; some of their materials have been 
damaged by mold. 

The Smithsonian has taken steps to improve its facilities management in 
response to recommendations by NAPA in 2001 and its own internal 
review. At that time, the Smithsonian's facilities management was 
highly decentralized, with a complex, multilayered management structure 
and multiple budgets. Noting that this decentralization had a direct 
and sometimes adverse impact on effective management, NAPA recommended 
that the Smithsonian centralize its facilities-related functions, 
including the budgets for capital (revitalization and new construction) 
and maintenance programs in order to promote uniform policies and 
procedures, improve accountability, and avoid duplication. In 2001, the 
Smithsonian began developing OFEO, which assumed responsibility for all 
facilities-related programs and budgets previously divided among four 
administrative offices, individual museums and science centers and the 
National Zoo. This office is also adopting a variety of recognized 
industry best practices for managing facilities projects, such as the 
use of benchmarking and metrics recommended by the Construction 
Industry Institute and leading capital decision-making 
practices.[Footnote 5] In addition, the office has assigned 
responsibility for prioritizing projects to two offices under its 
direction--one for capital projects and the other for maintenance 
projects. Each of these offices follows a defined, consistent priority- 
setting process for projects under its jurisdiction at all Smithsonian 
facilities. Because the newly centralized facilities management 
organization has been in place with its own budget for only about a 
year, it is too early to assess its full impact. However, the process 
appears to be moving in the right direction. Of the 16 directors of 
museums, galleries, research centers, the National Zoo, and a program 
office that we contacted (all internal customers of OFEO), 5 said that 
facilities services had substantially improved, and 9 others were 
generally positive or neutral about the reorganization. Two directors 
said that services had deteriorated since the reorganization. Various 
directors, including the 2 who expressed negative views noted that 
OFEO's funding and staffing have been reduced due to budget constraints 
and a Smithsonian-wide staff "buy out," thereby hindering full 
implementation of the reorganization. Also, several directors, 
including some with positive reactions to the reorganization, noted 
that communications from OFEO to its internal customers could be 
improved. 

The Smithsonian currently estimates that it will need about $2.3 
billion through fiscal year 2013 for its currently identified 
revitalization, construction, and maintenance programs. This estimate 
exceeds NAPA's 2001 estimate of $1.2 billion because it reflects more 
recent and comprehensive assessments of the Smithsonian's 
revitalization needs, covers new construction (including about $103 
million to address security requirements),[Footnote 6] and incorporates 
more complete information about the maintenance projects. The 
Smithsonian is also standardizing its cost estimation process. 
Estimated costs could increase, since they are largely based on 
preliminary needs assessments and early design documents. A big 
"unknown" is the timing and cost of the recently authorized National 
Museum of African American History and Culture, which is likely to cost 
hundreds of millions of dollars.[Footnote 7] Recent additions to the 
Smithsonian's building inventory--the National Museum of the American 
Indian and the Steven F. Udvar-Hazy Center--and the planned 2006 
reopening of the revitalized Patent Office Building will add to the 
Smithsonian's annual maintenance costs. Of 13 major revitalization and 
construction projects (those in excess of $5 million) being funded at 
the time of our review, most were on time and within budget. Finding 
the funding needed for the full range of planned capital and 
maintenance projects is an imposing challenge for the Smithsonian. The 
institution's annual operating and capital programs revenue, which 
comes from a percentage of its trust assets and its federal 
appropriation, amounted to $904 million in fiscal year 2004,[Footnote 
8] with about $184.4 million of this total for facilities. Revenues at 
this level would not be sufficient to cover the $2.3 billion in 
estimated costs for the institution's planned facilities projects and 
maintenance needs over the next 9 years. Officials told us that various 
funding approaches and options have been discussed by the staff, the 
Board of Regents, and with congressional leaders, but that no consensus 
for dealing with this issue has emerged. It remains unclear at this 
time the extent to which the Smithsonian will secure the funding to 
carry out all of its planned facilities projects. 

We are recommending that the Secretary of the Smithsonian establish a 
process for exploring options for funding its facilities needs and 
engaging the key stakeholders--the Smithsonian Board of Regents, the 
Administration, and the Congress--in the development and implementation 
of a strategic funding plan to address the revitalization, 
construction, and maintenance projects identified by the Smithsonian. 
We provided a draft of this report to the Smithsonian for comment. The 
Smithsonian concurred with our findings and recommendation and offered 
some technical comments and updates that were incorporated where 
appropriate. 

Background: 

The Congress established the Smithsonian Institution in 1846 to 
administer a large bequest left to the United States by James Smithson, 
an English scientist, for the purpose of establishing in Washington, 
D.C., an institution "for the increase and diffusion of knowledge among 
men." In accepting Smithson's bequest on behalf of the nation, the 
Congress pledged the "faith of the United States" to carry out the 
purpose of the trust.[Footnote 9] To that end, the act establishing the 
Smithsonian provided for the administration of the trust, independent 
of the government itself, by a Board of Regents and a Secretary, who 
were given broad discretion in the use of the trust funds. The board 
was composed of both private citizens and members of all three branches 
of the federal government, in order to ensure "the wise and faithful 
use" of the Institution's funds.[Footnote 10] The trust funds were 
permanently loaned to the Treasury to be maintained in a separate 
account; and the principal was to be maintained and the interest from 
that money used for the operation of the Institution. Although the 
Smithsonian has grown greatly since its founding nearly 160 years ago, 
it retains its essential character as a trust establishment of the 
United States. 

Over the last 150 years, the Smithsonian's facilities inventory has 
expanded to include 18 museums and galleries, 10 science centers, a 
zoo, and other facilities--most located in or near Washington, D.C., 
with others in Massachusetts, New York, Florida, Arizona, Hawaii, and 
the Republic of Panama. (See fig. 1.) These facilities include about 
660 buildings and structures, owned and leased, ranging from major 
museum buildings to storage buildings and storage sheds. There are 
about 8.6 million square feet of owned space and 1 million square feet 
of leased space. The Smithsonian has estimated the replacement value 
for owned space at about $4.7 billion as of June 2004. In 2003, an 
estimated 25 million people visited Smithsonian museums, and 
researchers made 39,000 visits to use its facilities. 

Figure 1: Location of Smithsonian Institution Facilities: 

[See PDF for image] 

[End of figure] 

The major buildings owned by the Smithsonian range in age from about 
160 years old to less than a year old, with most of the facilities 
growth occurring since the 1960s. (See fig. 2.) More than half of these 
buildings are more than 25 years old, 6 are designated as National 
Historic Landmarks, and about 40 are listed on the National Register of 
Historic Places or otherwise eligible for special consideration under 
federal guidelines for historic buildings.[Footnote 11] Not all of 
these buildings involved new construction. For example, the Patent 
Office Building, Renwick Gallery, and Cooper-Hewitt Museum were 
transferred to the Smithsonian after they were built, and the Victor 
Building was purchased for use as administrative offices. The two 
latest additions to the Smithsonian are the Steven F. Udvar-Hazy Center 
(phase I), which is part of the National Air and Space Museum and 
opened in December 2003, and the National Museum of the American 
Indian, which opened in September 2004. The Smithsonian's growth will 
continue with the construction of an aircraft restoration area at the 
Udvar-Hazy Center (phase II), which the Smithsonian plans to complete 
in 2008,[Footnote 12] and the design and construction of a National 
Museum of African American History and Culture, authorized by the 
Congress in 2003. Beyond this, some members in both houses of Congress 
have expressed interest in developing a National Museum of the American 
Latino Community.[Footnote 13]

Figure 2: Growth in Major Facilities Owned by the Smithsonian, in 
Square Feet: 

[See PDF for image] 

Note: This figure tracks the square footage for all owned buildings as 
they were added to the inventory over time. Only the major facilities 
are named in the figure, although the square footage of smaller 
buildings is included. 

[End of figure] 

In 1995, a commission established by the Smithsonian's Board of Regents 
reported that the Institution's facilities were deteriorating at an 
accelerated rate because of their age, the large number of visitors, 
and the Smithsonian's failure to invest sufficient resources to repair, 
revitalize, and maintain them. The commission concluded that over the 
next decade, a total of $50 million a year would be needed to restore 
the Institution's facilities (excluding the National Zoo) to the point 
of being safe for people and appropriate for collections.[Footnote 14] 
This estimated annual need was more than double the fiscal year 1995 
appropriation for these purposes. 

Generally, the Congress provided increased funding in the late 1990s, 
but in 2000 the newly appointed Secretary of the Smithsonian testified 
that he believed the Smithsonian's buildings were in poor condition and 
that the cost to restore them would be substantially more than 
previously identified.[Footnote 15] The Secretary stated that the 
Smithsonian "has hesitated to represent to Congress the full scale of 
the need. Instead, we've tried to make do." In response, the Congress 
directed the Smithsonian to contract with NAPA for a review to obtain a 
better understanding of the use of funds that had been provided to 
date. Specifically, NAPA was to determine (1) how the Smithsonian had 
expended federal funds for repair and restoration of its facilities, 
(2) what progress had been made in restoring the facilities, and (3) 
what tasks lay ahead.[Footnote 16]

NAPA reported in July 2001 that the federal funds appropriated for the 
Smithsonian's facilities had been used properly; the Smithsonian's 
facility requirements exceeded the amounts provided in the 
institution's annual budgets; and the Smithsonian's 2000 estimates were 
based on a reasonable, building-by-building approach and were more 
realistic than previous estimates.[Footnote 17] NAPA found that the 
Smithsonian had used the funds for high-priority repair and restoration 
projects but that its needs were far greater than those identified in 
its budget requests. While validating the Smithsonian's 10-year 
estimate of about $1.2 billion in repair and revitalization projects, 
NAPA noted that this estimate could increase to at least $1.5 billion 
because it was not adjusted for the effects of inflation and reflected 
only rough "orders of magnitude" estimates for later-year 
requirements.[Footnote 18] The report also recommended management 
improvements, including centralizing the Smithsonian's decentralized 
facilities management under a single organization and implementing a 
more structured maintenance program. At the beginning of our review, 
the Smithsonian had implemented 25 of the 30 recommendations, including 
a fundamental reorganization of its facilities management organization, 
funding, and staffing and the other 5 recommendations were in the 
process of being implemented. (See app. II for a listing of NAPA's 
recommendations and the status of the Smithsonian's implementation of 
them.) In addition to the need for management improvements, NAPA 
highlighted the importance of a "continuing and substantial infusion of 
funds" to address facilities needs. 

We alluded to the Smithsonian's facilities problems in our High Risk 
Series report on federal real property. The Smithsonian is one example 
of the problem facing agencies across the federal government, which 
have accumulated significant backlogs of maintenance and renovation 
needs and face serious deterioration problems. Overall, we found that 
the condition of federal facilities is one of alarming and accelerating 
deterioration.[Footnote 19]

Facility Conditions Have Generally Had Limited Effects on Access and 
Collections, but Some Chronic Problems Present Ongoing Risks: 

Facilities-related problems at the Smithsonian have resulted in a few 
building closures and access restrictions and, in some cases, harm to 
the collections. The problems range from major structural deterioration 
to chronic leaks that have damaged a few collections and threatened 
others. While the impact of these problems thus far has been limited, 
ongoing deterioration continues to present serious long-term risks to 
collections' accessibility and safety. 

Restrictions on Access: 

Serious structural problems have led to the closure of the third-oldest 
building in the Smithsonian's inventory, the Arts and Industries 
Building, as well as several buildings at the National Zoo. The roof 
panels of the Arts and Industries Building, which opened in 1881, have 
deteriorated to the point where they are considered unsound. The 
building was closed to the public in 2004 and will be closed to staff 
in 2005. Prior to its public closure, the Arts and Industries Building 
housed collections and received more than 900,000 visitors annually. 
The building also provided the Smithsonian with a venue for functions 
related to fund-raising. No date has been set for reopening this 
museum. Figure 3 shows a comparison of the North Hall of the Arts and 
Industries building in 1977 and February 2005. 

Figure 3: Arts and Industries Building, 1977 (left) and February 2005 
(right): 

[See PDF for image] 

[End of figure] 

At the National Zoo, facilities such as the sloth bear enclosure and 
the flight cage for birds of prey have been rendered unusable because 
of deterioration. In 2002, the National Zoological Park Director 
testified to the Congress that over half of the National Zoo's 
buildings have seriously compromised structural, mechanical, 
electrical, and fire and life-safety systems. The National Zoo has 
begun a revitalization program that currently is being funded. Figure 4 
shows the deterioration at the zoo's sloth bear facility. 

Figure 4: Sloth Bear Facility, National Zoo: 

[See PDF for image] 

[End of figure] 

In addition to structural deterioration, problems with asbestos have 
restricted researchers' access to certain collections. At the Garber 
Facility, a complex used for storage and other support purposes, 
researchers' access to 5 of the complex's 40 buildings has been 
restricted because of asbestos. In these 5 buildings, the stored items 
must be covered with plastic, and access is limited to a few staff. 
Figure 5 shows the interior of building 16 at the Garber Facility, 
which provides storage for artifacts for the National Museum of 
American History. 

Figure 5: Measures to Shield Collections from Asbestos, Garber 
Facility, Suitland, MD: 

[See PDF for image] 

[End of figure] 

Both public and researchers' access to facilities and collections also 
can be temporarily restricted by revitalization projects. For example, 
the Patent Office Building, the second oldest building in the 
Smithsonian's inventory, has been closed to the public since 2000 for 
revitalization.[Footnote 20] This building is the home of the National 
Portrait Gallery and Smithsonian American Art Museum. The Smithsonian 
has tried to limit the impact of the closure for revitalization by 
loaning art work from these collections to other museums or having 
traveling exhibits. Parts of the National Museum of American History, 
the National Museum of Natural History, and the National Zoo also have 
been closed to the public during revitalization projects. At the 
National Museum of Natural History, the mammal collection was closed to 
researchers for 2 years while the exhibit hall was undergoing 
revitalization. 

Damage and Threats to Collections: 

Besides affecting access to the collections, the condition of 
Smithsonian buildings can also affect the collections themselves. The 
greatest dangers to the collections to date have been posed by water. 
For example, at the National Air and Space Museum, Smithsonian 
officials showed us that leaks have damaged both the Lilienthal Hang 
Glider, which helped pioneer early flight design by influencing the 
Wright Brothers, and the Douglas Skyrocket, D558, the first airplane to 
break Mach 2. (See figs. 6 and 7.) Water also damaged 200 books at the 
Smithsonian Institution Archives due to a drain back-up. 

Figure 6: Water Stain on Wing of Lilienthal Hang Glider, National Air 
and Space Museum: 

[See PDF for image] 

[End of figure] 

Figure 7: Rust on Fuselage of Douglas Skyrocket, D558, Caused by Water 
Leak, National Air and Space Museum: 

[See PDF for image] 

[End of figure] 

Smithsonian officials identified several incidents and vulnerabilities 
related to water, including: 

* In February 2005, a broken pipe at the National Zoo's mechanical room 
that supports the pools for the seals and sea lions flooded the room 
with 8 feet of water and damaged controls, pumps, and motors. The pipes 
were scheduled for replacement this spring. See figure 8. 

Figure 8: Flooded Mechanical Room at the National Zoo: 

[See PDF for image] 

[End of figure] 

* At the Smithsonian Institution Archives, 19 water emergencies have 
occurred since June 2002, and the facility has formed an emergency 
response team to deal with them. "We are excellent drapers of plastic," 
according to an Archives official. Some of the leaks were directly 
above collections, but quick action by the staff averted damage to the 
collections. 

* At the National Museum of African Art, breaches in the roof membrane, 
malfunctioning valves, and clogged pipes often leak over galleries, 
collection storage areas, and offices. Replacing the roof and the water 
condensate system could address these problems, but other, higher 
priorities have received funding instead. 

* At the Renwick Gallery, gutters have leaked into the Grand Salon and 
adjacent gallery, but damage to artwork has been avoided. Repairs are 
scheduled for fiscal year 2005. 

* At the Freer and Sackler Galleries, water has leaked many times in 
storage areas and the library, and condensation poses a serious problem 
in the Freer Gallery's exhibition areas. To date, no major damage to 
the collections has occurred. 

Another area of concern is related to fluctuating temperature and 
humidity, particularly in a museum setting where collections must be 
stored and displayed in precise ways. While we toured various 
facilities, operations and maintenance managers showed us aging 
heating, ventilation, and air-conditioning systems that, the managers 
said, were no longer consistently maintaining the temperature and 
humidity needed to protect collections from deterioration. At the 
Renwick Gallery, for example, fluctuations in temperature and humidity 
produced by steam outages have caused weeping of the plaster on the 
gallery walls and could potentially damage art work. Poor ventilation 
at the Smithsonian Institution Archives caused high humidity, resulting 
in mold damage that made some records unreadable. 

Lastly, safety concerns and hazardous materials also threaten some 
collections. For example, at both the National Museum of Natural 
History and the Smithsonian Environmental Research Center, biological 
specimen collections are preserved in an alcohol solution that poses a 
safety risk from fire or explosive vapor that has to be controlled. 
Additionally, at the Smithsonian Environmental Research Center, 
collections are stored in deteriorating surplus trailers, many of them 
over 20 years old. Figures 9 and 10 depict problems with the storage of 
specimens stored in alcohol-filled containers of various sizes at the 
National Museum of Natural History. Several large rooms of about 10,000 
square feet are used to store these containers, though current code 
limits such rooms to 500 square feet for safety purposes. Figure 9 
shows that the storage containers are not enclosed, and figure 10 shows 
alcohol storage rooms that do not have current code-required explosion 
proof electrical equipment and fixtures. 

Figure 9: Alcohol-Preserved Specimens Stored on Open Shelves at the 
National Museum of Natural History: 

[See PDF for image] 

[End of figure] 

Figure 10: Nonexplosion Proof Lighting Fixtures and Switches in Alcohol 
Storage Rooms at the National Museum of Natural History: 

[See PDF for image] 

[End of figure] 

The Smithsonian is working to address these situations. Containment for 
these collections that is up to code is costly and will require new 
construction, which is currently under way. 

Smithsonian Has Centralized Its Facilities Management Organization and 
Budget to Improve the Efficiency and Effectiveness of Its Operations: 

The Smithsonian has recently reorganized its facilities management 
function to improve its operational effectiveness and make more 
efficient use of limited staffing and funding resources. In July 2001, 
NAPA reported that the Smithsonian's decentralized organizational 
structure and management practices, in some cases, had a direct and 
adverse effect on the planning, design, and construction activities 
that were integral to the institution's revitalization, construction, 
and maintenance programs. In response to NAPA's recommendations for 
improvement and its own internal review, the Smithsonian began in 
fiscal year 2001 to centralize its facilities management, adopted a 
variety of industry best practices for managing facilities projects, 
and established a priority process for facilities management. Because 
of the relative newness of the reorganization, it is too early to 
assess its effectiveness, though it appears to be moving in the right 
direction. Smithsonian museum, program, and center directors (the 
internal customers directly affected by the reorganization) had 
generally positive or neutral reactions to the reorganization, although 
several directors believed that OFEO needed to improve communications 
with them. Many of the directors, as well as OFEO officials, noted that 
reductions in OFEO's staffing and budget have hindered fully 
implementing the reorganization. 

Smithsonian Has Centralized the Responsibility for Facilities 
Management: 

At the time of NAPA's 2001 report, the Smithsonian's facilities 
operations were decentralized. Three distinct organizations--the 
offices of Physical Plant, Environmental Management and Safety, and 
Protection Services--were loosely integrated under the central Office 
of Facilities Services, but each organization had its own director and 
budget. The Office of Physical Plant was further divided into 14 
different divisions and offices. These organizations were responsible 
for facility planning, design, construction, and maintenance activities 
for the museums and research facilities. However, the National Zoo had 
its own budget and on-site staff to perform these functions for itself 
and for its Conservation and Research Center at Front Royal, Virginia. 
In addition, each museum or other major facility had its own separate 
funding and organization for providing custodial services, loading dock 
management, trash collection, and minor maintenance. 

In its 2001 report, NAPA found that the sheer size of the Office of 
Physical Plant (with a span of control encompassing 14 different units) 
and the wide diversity of its functions (operations, repair, 
restoration, planning, design, and maintenance) led to a hybrid 
organization that was awkward to manage, diffused responsibility and 
accountability, and did not facilitate a focus on the office's three 
primary responsibilities: (1) operation and maintenance of the physical 
plant; (2) repair and restoration of facilities; and (3) new 
construction. NAPA also noted that the functions and tasks associated 
with operating and maintaining facilities were common to all of the 
Smithsonian buildings and that overlap and duplication were likely when 
more than one organization was responsible for carrying out the same 
functions. NAPA concluded that centralizing facilities management 
should enable the Smithsonian to provide more efficient and effective 
services by putting a single organization in charge. According to NAPA, 
this centralization would promote uniform policies and procedures, 
improve accountability, and avoid overlap and duplication. 

In March 2001, before NAPA issued its report, the Smithsonian hired the 
former director of Facilities Engineering at the National Aeronautics 
and Space Administration to lead the reorganization of the facilities 
program and to head the new organization. The Director met with the 
NAPA team and studied its findings and recommendations. He also met 
with the Smithsonian's senior leadership and, with the help of a small 
internal team, listened to priorities and suggestions from various 
customers, stakeholders, and other Smithsonian staff in developing a 
plan for the reorganization.[Footnote 21]

The result of this effort was the creation, in fiscal year 2004, of the 
Office of Facilities Engineering and Operations (OFEO), a new, flatter 
facilities management organization. OFEO assumed responsibility for all 
facility-related programs and budgets that had been divided among four 
offices the National Zoo, and each museum or other major facility. OFEO 
consists of eight offices--Project Management; Facilities Planning and 
Resources; Engineering, Design, and Construction; Facilities 
Reliability; Facilities Management; Protection Services; Safety and 
Environmental Management; and the Smithsonian Tropical Research 
Institute Facilities Operations--all reporting directly to the OFEO 
director and funded through one budget (see fig. 11). OFEO received its 
first budget in fiscal year 2004. 

Figure 11: Organization of Smithsonian's New Office of Facilities 
Engineering and Operations: 

[See PDF for image] 

[End of figure] 

Appendix III provides a detailed description of the responsibilities of 
each OFEO office. While all eight OFEO offices play a role in the 
facilities program, the Office of Project Management oversees all 
revitalization and construction projects, and two offices--Facilities 
Management and Facilities Reliability--manage maintenance projects. The 
Office of Project Management develops preliminary project scopes, 
schedules, and budgets; monitors, directs, and reports on updated 
scopes, schedules and budgets for projects; and coordinates the efforts 
of stakeholders, designers, and construction execution.[Footnote 22] 
Major projects (in excess of $5 million) are overseen by project 
executives, small projects ($5 million and less.) by project managers. 
For major projects, such as the construction of the National Museum of 
the American Indian and the revitalization of the Patent Office 
Building, monthly reports indicate the status of each project's cost 
and schedule. The OFEO director attends a monthly operational review of 
major revitalization and construction projects with museum directors, 
and the Smithsonian's deputy secretary/chief operating officer, general 
counsel, and chief financial officer are briefed approximately 
quarterly on the major projects. The Office of Project Management is 
also responsible for the initial prioritization of revitalization and 
construction projects. 

The Office of Facilities Management provides day-to-day facilities 
maintenance services, including preventive maintenance, janitorial and 
grounds maintenance, transportation and mail delivery, building 
management for leased facilities, landscaping, and system start-ups for 
newly completed facilities. The responsibility for maintenance is 
divided among eight zones. A zone may consist of one or more buildings. 
Each zone has a manager who is responsible for maintenance in that 
zone. If Facilities Management staff cannot perform the work, then the 
work is sent to the Office of Facilities Reliability. 

The Office of Facilities Reliability provides strategic planning and 
oversight for maintenance, manages the Reliability-Centered Maintenance 
program,[Footnote 23] develops tasks and processes and then monitors 
work efforts, collects and analyzes data and metrics on the maintenance 
program, purchases utilities, manages agencywide service contracts, 
operates building automation services, and repairs large equipment in 
central shops. The office uses both in-house and contractor personnel 
to accomplish its objectives. When a minor repair is too large for 
Facilities Management, Facilities Reliability uses its staff or 
contracts out the work. About 15 percent of minor repairs are performed 
in-house, and about 85 percent are contracted out. Working with 
Facilities Management and others, Facilities Reliability is responsible 
for prioritizing minor repair projects. When we concluded our review in 
April 2005, the offices of Facilities Management and Facilities 
Reliability were being consolidated into one office that will be 
responsible for all maintenance projects.[Footnote 24]

Smithsonian Has Adopted Industry Best Practices to Improve Its 
Management of Facilities Projects: 

In reorganizing its facilities management, the Smithsonian is 
incorporating recognized industry best practices so that its resources 
would go as far as possible toward addressing its rapidly growing 
revitalization, new construction, and maintenance workload. 

For example, OFEO's framework for project management is considered a 
best practice, according to an independent review of an OFEO project by 
a contractor working for the Smithsonian Inspector General. OFEO also 
has been developing several handbooks to establish procedures and 
provide guidance on various aspects of facilities management. Its 
Facilities Project Management Handbook specifically addresses the 
Construction Industry Institute's (CII) practices of benchmarking and 
metrics, partnering, and preproject planning.[Footnote 25] OFEO has 
begun to implement these practices by, for example, establishing and 
tracking metrics, such as holding contract schedule growth to 10 
percent or less and contract cost growth to 2 percent or less. Both 
Facilities Management and Facilities Reliability periodically survey 
their internal customers to determine their level of satisfaction with 
the services provided to them. Furthermore, OFEO has adopted CII's Pre-
Project Planning Handbook and uses CII's Project Definition Rating 
Index[Footnote 26] to evaluate the progress of projects at various 
stages--both tools recommended by CII to support the best practice of 
preproject planning. OFEO has also just begun to use CII's Estimate 
Score Program,[Footnote 27] a tool designed to enhance the accuracy of 
early estimates. CII's best practices form the core of the practices 
taught to OFEO staff, and according to OFEO officials, these practices 
are routinely used in various phases of projects. In addition, staff 
participate in CII committees and teams, including those that develop 
best practices and participate in Federal Facilities Council 
committees.[Footnote 28]

The Smithsonian has also adopted leading practices in capital decision 
making, such as identifying its inventory of assets, determining their 
condition and the gap between current and needed capabilities, and 
ranking and selecting projects according to their priority, type of 
work, and fiscal year.[Footnote 29] (See app. IV for more detail on how 
the Smithsonian is implementing these practices.) Other industry 
practices that OFEO has adopted include reliability-centered 
maintenance, which covers predictive testing and inspection, and 
preventive maintenance. 

Smithsonian Has Established a Prioritization Process for Allocating 
Limited Funds to Revitalization, Construction, and Maintenance 
Projects: 

OFEO's Offices of Project Management and Facilities Reliability share 
responsibility for prioritizing projects--Project Management for 
revitalization and construction projects and Facilities Reliability for 
maintenance projects. Other organizations throughout the Smithsonian 
have input into these decisions. The Smithsonian's Capital Planning 
Board,[Footnote 30] Secretary, and Board of Regents approve 
prioritizations of revitalization and construction projects in the 
institution's 5-year capital program, and the OFEO director approves 
prioritizations of maintenance projects. 

The Office of Project Management, working with the museums and other 
facility groups, develops an annual list of new and previously 
submitted projects to be prioritized for inclusion in the annual 5-year 
capital plan. Using OFEO's priority code assignment matrix, the office 
assigns each project one of four condition levels (catastrophic, 
critical, routine, and can defer) and one of five project types (shell/ 
system failure, code compliance/security, nonroutine capital repairs, 
energy/operational efficiency, and alterations and modifications). This 
assignment determines the project's priority code, which may be from 
one to five. For example, a shell/system failure project assigned a 
catastrophic condition level would receive a top priority code of "one" 
for the budget year in which funding is sought. (See app. V for the 
priority code assignment matrix and definitions of its elements.) After 
Project Management completes the prioritized list, it sends the list to 
the Smithsonian under secretaries and directors for review and 
approval. Project Management then uses the approved list to update the 
5-year capital plan and sends the updated plan to the Smithsonian's 
Capital Planning Board for review. The Capital Planning Board reviews 
the plan in the context of the Smithsonian's guidelines and needs. Only 
projects supported by this review and then by the Smithsonian 
Secretary's review are included in the updated 5-year capital plan, 
which accompanies the annual budget submission to the Office of 
Management and Budget. The Board of Regents approves the Smithsonian's 
annual budget submission, including the 5-year capital plan. According 
to Smithsonian officials, this process ensures that the institution's 
limited capital funding is allocated to the highest priority needs. 

The Office of Facilities Reliability, in conjunction with the museums 
and other facility groups, identifies maintenance projects, taking into 
account customer input; annual safety, health and environmental 
inspections; code and regulatory requirements; and facility 
assessments. Facilities Reliability then ranks these projects on a 
scale from 1 to 10. For example, a project to address an imminent 
facility failure that poses a potential safety, health, or 
environmental issue is ranked as a 1, the highest priority; a project 
to address a moderate disruption to a facility's functions is ranked as 
a 6, and a project that involves no expectation of failure or effect on 
safety or health is ranked as a 10, the lowest priority. Facilities 
Reliability then uses a funding matrix to determine which projects will 
be funded. Any projects that cannot be funded go into the office's 
inventory of projects. (See app. VI for the priority decision-making 
flowchart and maintenance ranking scale.) According to Facilities 
Reliability officials, if facilities-related emergencies occur during a 
year, funds obligated for other projects may have to be deobligated. 

Directors Generally Expressed Positive or Neutral Reactions to OFEO but 
Noted That Restructuring Has Been Hindered by Staffing and Budget 
Reductions: 

The 16 Smithsonian directors of museums, galleries, research centers, 
the National Zoo, and a program office that we interviewed expressed a 
range of opinions about the reorganization's impact on facilities 
services. Five directors said that services had improved substantially 
and 9 others were generally positive or neutral about the 
reorganization. Two directors said that services had deteriorated since 
the reorganization. Various directors, including the 2 that had 
expressed negative views, pointed out that after OFEO was reorganized, 
the Smithsonian had a staff buyout[Footnote 31] that led to staffing 
and funding reductions in OFEO. In total, OFEO lost 109 of about 1,750 
staff and the funding for their positions--59 in maintenance, 39 in 
security, and 11 in other OFEO offices, according to a Smithsonian 
official. These reductions, together with the recent opening of the 
National Museum of the American Indian, have negatively affected both 
maintenance and security services, according to various directors. 
Also, several directors, including some with positive reactions to 
OFEO, noted that communications from OFEO to its internal customers 
could be improved. 

Although implementation of the centralization effort is still a work in 
progress, senior OFEO officials believe the reorganization is 
progressing well. While full implementation has been hindered by both 
staffing shortages and budget constraints, OFEO has obtained permission 
to fill 19 of these positions in crucial areas.[Footnote 32]

Estimated Costs of Facilities Projects Have Grown, Posing Serious 
Funding Challenge: 

The Smithsonian currently estimates that it will need about $2.3 
billion for fiscal years 2005 through 2013 for its planned 
revitalization, construction, and maintenance projects, but this 
estimate could change as information is updated and new facilities are 
opened or authorized. As of April 2005, of the 13 funded major 
revitalization and construction projects that are active or were 
completed in fiscal year 2004, most were on time and within budget. 
Given its level of annual operating and capital program revenues (about 
$904 million in fiscal year 2004, including about $184.4 million for 
the facilities) for all of its activities, it is unclear how the 
Smithsonian's planned facilities needs will be funded over the next 9 
years. 

Current $2.3 Billion Estimate Reflects Updates but Could Change: 

The Smithsonian's $2.3 billion estimate for the next 9 years includes 
about $1.43 billion for revitalization projects (including facilities 
planning and design), about $136.2 million for construction projects, 
and about $713.9 million for its maintenance program. Table 1 breaks 
down these estimates by project and year. Like all estimates, these are 
based on the information that is available at the time they are made, 
and they are subject to change as new information becomes available. 
Additionally, the estimates for revitalization and construction, which 
total almost $1.57 billion, are largely based on preliminary planning 
documents, such as master plans and facility assessments, (some still 
in progress), and on preliminary designs. According to Smithsonian 
documents, about 86 percent of the estimates for revitalization and 
construction projects, which account for about $1.27 billion--or nearly 
81 percent--of the $1.57 billion total, are "order-of-magnitude" 
estimates. Such estimates have a range of accuracy of plus or minus 30 
to 50 percent. Thus, the $1.57 billion estimate for revitalization and 
construction projects could fall as low as about $875 million or rise 
as high as about $2.3 billion.[Footnote 33] The cost estimates for 
maintenance projects are based on facility assessments, guidance issued 
by the National Research Council and the Federal Facilities Council, 
and a formula Facility Reliability has developed for estimating 
maintenance costs. 

Table 1: Appropriated and Estimated Costs of Smithsonian Capital and 
Maintenance Programs, Fiscal Years 2005-2013: 

Dollars in millions. 

CAPITAL PROJECTS: 

Major revitalization: 

Arts and Industries Building; 
Appropriated funds: Prior funding[B]: $13.2; 
Appropriated funds: 2005: $23.4
Estimated costs for fiscal year(s)[A]: 2006: $5.8; 
Estimated costs for fiscal year(s)[A]: 2007: $11.3; 
Estimated costs for fiscal year(s)[A]: 2008: $57.0; 
Estimated costs for fiscal year(s)[A]: 2009: $61.0; 
Estimated costs for fiscal year(s)[A]: 2010: $64.0; 
Total: 2005 - 2013: $222.5. 

Freer Gallery; 
Estimated costs for fiscal year(s)[A]: 2010: $1.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $10.0;
Total: 2005 - 2013: $11.0. 

Hirshhorn Museum; 
Estimated costs for fiscal year(s)[A]: 2009: $2.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $20.0;
Total: 2005 - 2013: $22.0. 

Museum Support Center; 
Estimated costs for fiscal year(s)[A]: 2007: $1.0; 
Estimated costs for fiscal year(s)[A]: 2009: $10.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $24.0;
Total: 2005 - 2013: $35.0. 

National Air and Space Museum; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $59.0;
Total: 2005 - 2013: $59.0. 

National Museum of American History; 
Appropriated funds: Prior funding[B]: $4.8; 
Appropriated funds: 2005: $10.0
Estimated costs for fiscal year(s)[A]: 2006: $18.4; 
Estimated costs for fiscal year(s)[A]: 2007: $13.1; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $50.0;
Total: 2005 - 2013: $91.5. 

National Museum of Natural History; 
Appropriated funds: Prior funding[B]: $101.4; 
Appropriated funds: 2005: $10.0
Estimated costs for fiscal year(s)[A]: 2006: $15.8; 
Estimated costs for fiscal year(s)[A]: 2007: $33.2; 
Estimated costs for fiscal year(s)[A]: 2008: $34.0; 
Estimated costs for fiscal year(s)[A]: 2009: $32.0; 
Estimated costs for fiscal year(s)[A]: 2010: $33.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $125.5;
Total: 2005 - 2013: $283.5. 

National Zoological Park; 
Appropriated funds: Prior funding[B]: $43.9; 
Appropriated funds: 2005: $21.4
Estimated costs for fiscal year(s)[A]: 2006: $14.0; 
Estimated costs for fiscal year(s)[A]: 2007: $28.9; 
Estimated costs for fiscal year(s)[A]: 2008: $23.5; 
Estimated costs for fiscal year(s)[A]: 2009: $24.1; 
Estimated costs for fiscal year(s)[A]: 2010: $25.6; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $107.6;
Total: 2005 - 2013: $245.1. 

Patent Office Building; 
Appropriated funds: Prior funding[B]: $121.0; 
Appropriated funds: 2005: $44.4
Total: 2005 - 2013: $44.4. 

Quadrangle; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $60.0;
Total: 2005 - 2013: $60.0. 

Renwick Gallery; 
Estimated costs for fiscal year(s)[A]: 2010: $4.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $25.0;
Total: 2005 - 2013: $29.0. 

Smithsonian Institution Building (the "Castle"); 
Appropriated funds: Prior funding[B]: $1.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $87.0;
Total: 2005 - 2013: $87.0. 

Silver Hill/Suitland Facility; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $23.0;
Total: 2005 - 2013: $23.0. 

Smithsonian Tropical Research Institute; 
Estimated costs for fiscal year(s)[A]: 2007: $3.2; 
Estimated costs for fiscal year(s)[A]: 2008: $6.0; 
Estimated costs for fiscal year(s)[A]: 2009: $1.2; 
Estimated costs for fiscal year(s)[A]: 2010: $1.8; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $1.8;
Total: 2005 - 2013: $14.0. 

Other revitalization[C,D]: 

Appropriated funds: Prior funding[B]: $63.2; 
Appropriated funds: 2005: $6.0
Estimated costs for fiscal year(s)[A]: 2006: $15.0; 
Estimated costs for fiscal year(s)[A]: 2007: $37.0; 
Estimated costs for fiscal year(s)[A]: 2008: $23.5; 
Estimated costs for fiscal year(s)[A]: 2009: $15.1; 
Estimated costs for fiscal year(s)[A]: 2010: $16.1; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $51.7;
Total: 2005 - 2013: $164.4. 

Other revitalization[C,D]: Facilities Planning and Design[E]; 
Appropriated funds: 2005: $3.0; 
Estimated costs for fiscal year(s)[A]: 2006: $4.0; 
Estimated costs for fiscal year(s)[A]: 2007: $7.8; 
Estimated costs for fiscal year(s)[A]: 2008: $6.0; 
Estimated costs for fiscal year(s)[A]: 2009: $4.6; 
Estimated costs for fiscal year(s)[A]: 2010: $4.5; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $8.9;
Total: 2005 - 2013: $38.8. 

Subtotal revitalization; 
Appropriated funds: 2005: $118.2
Estimated costs for fiscal year(s)[A]: 2006: $73.0; 
Estimated costs for fiscal year(s)[A]: 2007: $135.5; 
Estimated costs for fiscal year(s)[A]: 2008: $150.0; 
Estimated costs for fiscal year(s)[A]: 2009: $150.0; 
Estimated costs for fiscal year(s)[A]: 2010: $150.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $653.5;
Total: 2005 - 2013: $1,430.2. 

Construction: 

Museum Support Center Pod 5; 
Appropriated funds: Prior funding[B]: $12.3; 
Appropriated funds: 2005: $6.9
Estimated costs for fiscal year(s)[A]: 2006: $9.0; 
Estimated costs for fiscal year(s)[A]: 2007: $14.5; 
Total: 2005 - 2013: $30.4. 

SAO - VERITAS Control Building (Arizona); 
Appropriated funds: 2005: $1.0
Total: 2005 - 2013: $1.0. 

National Museum of African American History and Culture (planning and 
design); 
Estimated costs for fiscal year(s)[A]: 2007: $2.0; 
Total: 2005 - 2013: $2.0. 

Antiterrorism protection[D]; 
Estimated costs for fiscal year(s)[A]: 2006: $8.9; 
Estimated costs for fiscal year(s)[A]: 2007: $15.6; 
Estimated costs for fiscal year(s)[A]: 2008: $14.2; 
Estimated costs for fiscal year(s)[A]: 2009: $15.3; 
Estimated costs for fiscal year(s)[A]: 2010: $23.8; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $25.0;
Total: 2005 - 2013: $102.8. 

Subtotal construction; 
Appropriated funds: 2005: $7.9
Estimated costs for fiscal year(s)[A]: 2006: $17.9; 
Estimated costs for fiscal year(s)[A]: 2007: $32.1; 
Estimated costs for fiscal year(s)[A]: 2008: $14.2; 
Estimated costs for fiscal year(s)[A]: 2009: $15.3; 
Estimated costs for fiscal year(s)[A]: 2010: $23.8; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $25.0;
Total: 2005 - 2013: $136.2. 

Subtotal capital projects[F]; 
Appropriated funds: 2005: $126.1
Estimated costs for fiscal year(s)[A]: 2006: $90.9; 
Estimated costs for fiscal year(s)[A]: 2007: $167.6; 
Estimated costs for fiscal year(s)[A]: 2008: $164.2; 
Estimated costs for fiscal year(s)[A]: 2009: $165.3; 
Estimated costs for fiscal year(s)[A]: 2010: $173.8; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $678.5;
Total: 2005 - 2013: $1,566.4. 

MINOR REPAIR AND MAINTENANCE PROJECTS[G]: 

Appropriated funds: 2005: $38.2
Estimated costs for fiscal year(s)[A]: 2006: $45.7; 
Estimated costs for fiscal year(s)[A]: 2007: $90.0; 
Estimated costs for fiscal year(s)[A]: 2008: $90.0; 
Estimated costs for fiscal year(s)[A]: 2009: $90.0; 
Estimated costs for fiscal year(s)[A]: 2010: $90.0; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $270.0;
Total: 2005 - 2013: $713.9. 

Total; 
Appropriated funds: 2005: $164.3
Estimated costs for fiscal year(s)[A]: 2006: $136.6; 
Estimated costs for fiscal year(s)[A]: 2007: $257.6; 
Estimated costs for fiscal year(s)[A]: 2008: $254.2; 
Estimated costs for fiscal year(s)[A]: 2009: $255.3; 
Estimated costs for fiscal year(s)[A]: 2010: $263.8; 
Estimated costs for fiscal year(s)[A]: 2011 - 2013: $948.5;
Total: 2005 - 2013: $2,280.3. 

Source: Smithsonian Institution. 

[A] These estimates are in current 2004 dollars. 

[B] These amounts are in year-appropriated dollars. 

[C] Includes funding for 95 other revitalization projects. Projects in 
this category are smaller in scale than major projects, usually involve 
systems or pieces of equipment for a single building, and typically 
cost between $100,000 and $5 million. 

[D] The funding for two categories--other revitalization projects and 
antiterrorism protection--is planned for projects at multiple 
Smithsonian sites. 

[E] Includes cost estimates for the design of other revitalization 
projects and master planning. 

[F] Includes funding for major revitalization, other revitalization, 
facility planning and design projects, and construction. 

[G] Represents total funding for maintenance program, including staff 
costs, minor repair and maintenance projects, and other contracts, 
supplies, materials and equipment. For fiscal year 2005, this is the 
amount appropriated for the program, according to the Smithsonian. For 
fiscal year 2006, this is the amount in the Smithsonian's fiscal year 
budget submitted to Congress, according to the Smithsonian. 

[End of table]

The revitalization and new construction costs presented in table 1 are 
driven, in part, by the need to modernize or add systems--fire 
detection and alarm; security; electrical; heating, ventilation, and 
air-conditioning (including environmental ventilation) systems, and 
elevators and escalators--and to comply with newer code requirements, 
such as those for air pressurization to keep stairwells clear of 
smoke[Footnote 34] and handicapped accessibility to buildings and 
restrooms. Figures 12 through 15 show revitalization projects that are 
included in the Smithsonian's estimate of $1.43 billion. Figure 16 
illustrates new construction planned to address the safety problems 
with alcohol storage depicted in figures 9 and 10 that are included in 
the Smithsonian's estimate of $136.2. 

Figure 12: Failing Heating, Ventilation and Air Conditioning System at 
National Air and Space Museum: 

[See PDF for image] 

[End of figure] 

Figure 13: Antiquated Fire Suppression System, National Air and Space 
Museum: 

[See PDF for image] 

[End of figure] 

Figure 14: Flooding in High-Voltage Room, National Museum of American 
History: 

[See PDF for image] 

[End of figure] 

Figure 15: Leak in the Room 4303 (History Storage Room) at the National 
Museum of American History: 

[See PDF for image] 

[End of figure] 

Figure 16: Site Footprint of Planned Alcohol Storage Unit (Pod 5) to be 
added to the Museum Support Center, Suitland, MD: 

[See PDF for image] 

[End of figure] 

Smithsonian Has Updated NAPA's Estimate and Implemented Other 
Recommendations to Improve Cost Estimation: 

The Smithsonian's current $2.3 billion estimate exceeds NAPA's $1.2 
billion estimate because it reflects more recent and comprehensive 
assessments of the Smithsonian's revitalization needs, covers new 
construction (including about $103 million to address security 
requirements),[Footnote 35] and incorporates more complete information 
about the maintenance program. After NAPA issued its July 2001 report, 
the Smithsonian implemented NAPA's recommendations that it revalidate 
its revitalization requirements and separate its maintenance budget 
from its revitalization budget. In September 2001, the Smithsonian 
issued a report outlining its revitalization objectives,[Footnote 36] 
and it has since been updating facility assessments and completing 
master plans to identify further revitalization costs. It has also 
taken other steps to improve its cost estimation, including 
establishing a cost-engineering unit and attempting to implement a NAPA 
recommendation that calls for linking requests for construction funding 
to progress in completing design drawings. Table 2 provides the 
Smithsonian's January 2005 cost estimates for major revitalization 
projects, NAPA's July 2001 estimates, and summaries of the reasons for 
differences between the estimates. Further discussion of the 
Smithsonian's cost estimation methods follows the table. 

Table 2: Estimated Costs for Major Revitalization Projects as Reported 
by NAPA in 2001 and Identified by the Smithsonian in 2005: 

Dollars in millions. 

Arts and Industries Building; 
2001 NAPA estimate: $105.0; 
2005 Smithsonian estimate: $235.7; ($36.6 funded); 
Difference: $130.7; 
Reasons for difference: Continuing deterioration, particularly of the 
roof, prompted a decision to close the building and move tenants 
instead of allowing them to occupy the building during a phased 
renovation. Of the $131 million difference, $34 million is for 
permanently relocating the staff and $10 million is for replacing the 
roof--originally a separate project, but now included in the overall 
renovation. Design development has revealed more substantial systems 
replacement and structural reinforcement needs; substantial work is 
also needed to restore the building to its original state. 

Freer Gallery; 
2001 NAPA estimate: $3.5; 
2005 Smithsonian estimate: $11.0; 
Difference: $7.5
Reasons for difference: Further investigation has revealed needs for 
modifying the courtyard to improve accessibility, modifying the fire 
protection systems, adding shade structures for the skylights, and 
installing new gallery lighting. 

Hirshhorn Museum; 
2001 NAPA estimate: $11.0; 
2005 Smithsonian estimate: $22.0; 
Difference: $11.0
Reasons for difference: Further investigation has revealed the need for 
additional work on the building envelope to stop water intrusion. 

Museum Support Center; 
2001 NAPA estimate: $16.0; 
2005 Smithsonian estimate: $35.0; 
Difference: $19.0
Reasons for difference: Further investigation has revealed the need for 
additional work on the electrical system and one emergency generator. 
The revalidated estimate also includes funding for a new requirement to 
renovate Pod 3, once alcohol-preserved collections are relocated to Pod 
5. The renovation will include the construction of two floors to 
replace the steel system now in place. 

National Air and Space Museum; 
2001 NAPA estimate: $45.0; 
2005 Smithsonian estimate: $59.0; 
Difference: $14.0
Reasons for difference: Design development has revealed the need for 
more extensive systems replacement. The project has also been postponed 
several years, adding a minimum of $5 million in escalation cost to the 
NAPA report's estimate. 

National Museum of American History; 
2001 NAPA estimate: $35.0; 
2005 Smithsonian estimate: $96.3; ($4.8 funded); 
Difference: $61.3
Reasons for difference: Further investigation has revealed the need for 
more extensive systems replacement. The fire-detection and alarm 
system, elevators and escalators, and security system need upgrading. 
Stair pressurization and restrooms must also comply with newer code 
requirements. Extensive renovation of the public areas, not included in 
the original project, is also needed to accommodate an exhibit 
replacement program funded by the Behring Foundation. 

National Museum of Natural History; 
2001 NAPA estimate: $200.0; 
2005 Smithsonian estimate: $387.9; ($111.4 funded); 
Difference: $187.9
Reasons for difference: The NAPA report's estimate was based on a 
1980's estimate, which projected a 10-year construction period. Lack of 
funding has extended the project, causing its costs to escalate. 
Furthermore, the project's scope has changed. The plans now call for a 
more comprehensive renovation of the entire building, including 
modifying the interior to provide refurbished space for museum 
activities. New requirements for environmental ventilation, additional 
fire protection, and lighting have also increased the estimate. 

National Zoological Park; 
2001 NAPA estimate: $171.0; 
2005 Smithsonian estimate: $289.0; ($65.3 funded); 
Difference: $118.0
Reasons for difference: Investigation of building and utility 
distribution systems was just beginning in 2001, and little was known 
about the magnitude of the deficiencies. A 2003 study by a contractor 
updated the cost to restore the National Zoo to at least $250 million 
over the next 10 years. Also, systems have continued to deteriorate, 
and the estimated costs to replace them have increased. The current 
estimate will change further as specific studies of individual 
buildings progress over the next 5 years. Finally, a catastrophic fire 
in the wetlands exhibit that occurred after the contractor's 2003 study 
has added about $10 million in estimated restoration costs. 

Patent Office Building; 
2001 NAPA estimate: $151.0; 
2005 Smithsonian estimate: $166.0; ($165.7 funded); 
Difference: $14.4
Reasons for difference: A design development and scope change to 
convert about 60,000 square feet of administrative space to public 
space required modifications to building systems and architectural 
finishes. 

Quadrangle; 
2001 NAPA estimate: $44.0; 
2005 Smithsonian estimate: $60.0; 
Difference: $16.0
Reasons for difference: The original estimate covered replacement of 
the roof structure, but since the project has been delayed, replacement 
of the mechanical systems has been added to the project. 

Renwick Gallery; 
2001 NAPA estimate: $23.0; 
2005 Smithsonian estimate: $29.0; 
Difference: $6.0
Reasons for difference: Costs have escalated with delays in starting 
the project due to lack of funding. 

Smithsonian Institution Building (the "Castle"); 
2001 NAPA estimate: $57.0; 
2005 Smithsonian estimate: $88.0; ($1.0 funded); 
Difference: $31.0
Reasons for difference: The master plan for the complete renovation of 
the "Castle" building and systems and finishes has progressed to the 65-
percent level, giving better cost data than when the NAPA report was 
done. 

Silver Hill/Suitland Facilities; 
2001 NAPA estimate: New; 
2005 Smithsonian estimate: $23.0; 
Difference: $23.0
Reasons for difference: New requirements have been identified since the 
NAPA report. 

Smithsonian Tropical Research Institute; 
2001 NAPA estimate: New; 
2005 Smithsonian estimate: $14.0; 
Difference: $14.0
Reasons for difference: New requirements have been identified since the 
NAPA report. 

Source: Smithsonian Institution. 

[End of table]

To estimate the costs of its revitalization projects and construction, 
the Office of Project Management may use facility assessments, fire and 
safety inspections, customer input, contracted cost estimates of 
projects, feasibility studies, design documents at various stages 
(preliminary, 35 percent, or 100 percent), and the input of the various 
experts in OFEO, according to OFEO officials. The developmental phase 
of a project determines the types of information that are available for 
use in estimating its cost. Depending on the types of information used, 
Project Management can assign a range of accuracy to an estimate, 
applying a four-class system that the Construction Industry Institute 
(CII) uses to categorize cost estimates.[Footnote 37] Estimates in each 
class--order of magnitude, factored, control, and detailed/definitive-
-are based on different, increasingly reliable documents and have 
increasingly narrow ranges of accuracy. Whereas an order-of-magnitude 
estimate could be based on a feasibility study alone and would have an 
range of accuracy of plus or minus 30 to 50 percent, a detailed/ 
definitive estimate could be based on detailed drawings and could have 
a narrower accuracy range of plus or minus less than 10 percent. As 
discussed, the majority of the Smithsonian's estimates for 
revitalization and construction projects are order-of-magnitude 
estimates. 

To provide better estimates of its future needs, OFEO has established a 
Cost Engineering Division, which recently has been fully staffed. This 
division is to provide revitalization and construction cost estimates 
for projects at the project development stage.[Footnote 38] The 
division is also to revise construction cost estimates for each project 
throughout its life cycle to reflect changes and current market 
conditions. The recently hired associate division director has 
developed a draft Cost Management Guide that is currently being 
reviewed. According to the associate division director, the guide is to 
standardize the estimating process throughout OFEO, including the 
process for developing cost estimates for the Smithsonian's 5-year 
capital plan, and to provide an audit trail for estimates. He is also 
introducing CII's Estimate Score Program to enhance the accuracy of 
early estimates. He expects his division to have a major role in 
developing all future project estimates. 

NAPA recommended that, to improve its cost estimates, the Smithsonian 
not request construction funding from the Congress until it has 
completed partial (35 percent) design drawings for its projects. 
According to the OFEO director, OFEO is having difficulty meeting this 
recommendation because of chronic underfunding in the design category. 
OFEO currently can barely keep up with the requirements for complete 
(100 percent) design drawings for the next year's capital program, the 
director said, and little funding is available to meet the longer-term 
requirements for partial (to 35 percent) designs. Ideally, the 35- 
percent design drawings should be complete before OFEO develops the 
request for construction funding to the Office of Management and 
Budget. The director believes that if OFEO had a larger pool of design 
funds, he could provide the Congress with more accurate information for 
making funding decisions and develop projects in a timely manner. 

Smithsonian Now Tracks Maintenance Project Costs Separately from 
Revitalization and Construction Project Costs: 

As NAPA recommended, the Smithsonian separated maintenance costs from 
revitalization and construction costs and now tracks and manages them 
through separate offices. Using facility assessments, the Office of 
Facilities Reliability determined an inventory of about $329 million in 
deferred maintenance projects as of October 2004. Figure 17 shows the 
breakdown of the inventory by type and total dollar value. 

Figure 17: Estimated Maintenance Project Costs, by Type (dollars in 
millions): 

[See PDF for image] 

[End of figure] 

According to Facilities Reliability officials, the yearly cost 
estimates for maintenance projects in table 1 provide for maintaining 
facilities at their current levels in fiscal years 2005 and 2006 as 
well as reducing the inventory of deferred maintenance in fiscal years 
2007 through 2013 if funded at these levels. To calculate these 
estimates, Facilities Reliability first (1) considers the building's 
condition, as measured against a facility condition index that ranges 
from 1 (the worst condition) to 5 (the best condition); (2) determines 
an allowance (between 2 percent and 6 percent, depending on the 
building's condition) of the building's current replacement value; and 
(3) applies a formula that includes the building's total square 
footage.[Footnote 39] Facilities Reliability then adjusts the results 
of its calculations according to the type of maintenance work and the 
input of staff. Finally, Facilities Reliability combines the estimated 
maintenance costs for all the buildings to determine the estimated 
maintenance needs for a fiscal year. The deferred maintenance inventory 
rises and falls as maintenance projects are completed, new projects are 
identified, and the estimated replacement value of the facility 
inventory changes. Underfunding maintenance needs in a given year 
increases the deferred maintenance inventory. 

Cost Estimates Could Change: 

For a variety of reasons, the Smithsonian's cost estimates for 
revitalization, construction, and maintenance could change. First, as 
noted, the estimates for about 86 percent of the revitalization and 
construction projects are order-of-magnitude estimates with an accuracy 
range of plus or minus 30 to 50 percent. An OFEO official pointed out 
that the costs are not likely to fall unless the projects are reduced 
in scope. Additionally, the estimates could increase further because 
assessments for the National Museum of Natural History, the National 
Zoo, and the Smithsonian Astrophysical Observatory are still in 
progress and could identify new needs. Moreover, as other facilities 
continue to deteriorate, additional revitalization needs could arise. 

Second, the annual costs for maintenance are expected to increase due 
to the addition of the National Museum of the American Indian and the 
Steven F. Udvar-Hazy Center to the Smithsonian's building inventory in 
fiscal year 2004, and with the planned completion of the Patent 
Office's revitalization in 2006. According to the National Research 
Council's standards for maintenance, the Smithsonian's maintenance 
budget should increase by at least 2 percent of these buildings' 
current replacement value to cover their maintenance. However, a 
Smithsonian official told us that the Smithsonian received an increase 
in maintenance funding for fiscal year 2005 to provide for the National 
Museum of the American Indian of only $700,000 of the $2.5 million 
needed. Unfunded maintenance costs increase the Smithsonian's deferred 
maintenance inventory. 

Third, the estimated costs for both construction and maintenance do not 
include the National Museum of African American History and Culture, 
which Congress authorized in 2003. This new museum is in its planning 
stage, and the timing and cost of its construction are still unknown, 
though it is likely to be several hundreds of millions of dollars. In 
addition, some members of Congress have expressed interest in 
developing a National Museum of the American Latino Community. 

Most Funded Major Revitalization and Construction Projects Are on Time 
and Within Budget: 

The Smithsonian has 13 funded major revitalization and construction 
projects that are currently active or were completed in fiscal year 
2004. As table 3 indicates, 8 of the 13 projects were within budget and 
on time (or were completed on time) as of April 2005.[Footnote 40] Of 
the remaining 5 projects, 1 was both over budget and behind schedule 
(Museum Support Center, Pod 5); 2 had increases in their budgets, but 
were on schedule (Ocean Exhibit and Patent Office Building, Phase II); 
2 were behind schedule, but within their budgets (Patent Office 
Building Phase I and Mall-wide Permanent Security Barriers). For each 
major project, table 3 identifies the budget, current working estimate, 
schedule, and comments. 

Table 3: Status of Fiscal Year 2004 Funded or Completed Major Projects 
as of April 2005: 

Dollars in millions. 

Revitalization projects. 

Arts and Industries Building; 
Project budget: $44; 
Current working estimate (CWE): $34; 
Schedule: On time; 
Comments: 
* This project covers closure, staff relocation and chilled water 
connection to GSA system; 
* Two leases for space signed; 
* Relocated Discovery Theater opened on time; 
* North hall tarp removed, structural investigation and implementation 
of temporary repairs completed; 
* Relocated Smithsonian Early Enrichment Center opened on schedule; 
* Federally funded through Smithsonian's capital program. 

National Museum of American History (NMAH); 
Comments: 
* This public space renewal project is being done in four phases, or 
"packages"; only the first two phases are supported by federal 
appropriations. 

Package I (supports Price of Freedom Exhibit); 
Project budget: $4.5; 
Current working estimate (CWE): $4.47; 
Schedule: On time; 
Comments: 
* Construction is complete and the exhibit opened on time. The cost 
indicated reflects only the federal appropriation component. 

Package II (supports Star Spangled Banner Exhibit); 
Project budget: $80.0; ($45.5 capital funds); 
Current working estimate (CWE): $80.0; ($45.37 capital funds); 
Schedule: 65 percent design delivered 3/28/05, three days ahead of 
schedule; 
Comments: 
* Design development under SD-410 review (Smithsonian internal review); 
* Notice to proceed given to contractor for value engineering on parts 
of the project; 
* Scope of work for construction documents (up to 65 percent) under 
development; 
* Construction documents (up to 65 percent) to be funded from federal 
funds in hand; 
* $45.5 million is to be federally funded through Smithsonian's capital 
program. The remainder is to be funded through the Smithsonian trust 
funds. 

National Museum of Natural History (NMNH): Ocean Exhibit; 
Project budget: $34.11; ($16.0 capital funds); 
Current working estimate (CWE): $40.47; ($18.27 capital funds); 
Schedule: On time; 
Comments: 
* Renovation costs have grown by $2.2 million because HVAC requirements 
have increased. The museum is using funds from other projects to cover 
the additional costs; 
* Exhibit costs have grown by $4.2 million to include specific projects 
of interest to the donor. The donor may cover the additional costs; 
if not, the additional exhibits will not be included; 
* $18.27 million is to be federally funded through Smithsonian's 
capital program. The remainder is to be funded through the Smithsonian 
trust funds. 

National Zoological Park: Asia Trail I; 
Project budget: $48.44; ($41.59 capital funds); 
Current working estimate (CWE): $50.44; ($43.6 capital funds); 
Schedule: On time; 
Comments: 
* Asia Trail II otter exhibit scope added to Asia Trail I project for 
construction. Asia Trail I construction budget increased by otter 
construction budget ($2 million); 
total project budget increased from $48.44 million to $50.44 million; 
* $43.6 million is to be federally funded through Smithsonian's capital 
program. The remainder is to be funded through the Smithsonian trust 
funds. 

National Zoological Park: Asia Trail II; 
Project budget: $62.71; ($37.85 capital funds); 
Current working estimate (CWE): $60.71; ($35.85 capital funds); 
Schedule: Design is on time; 
Comments: 
* Otter exhibit moved to Asia Trail I project. Asia Trail II budget 
reduced by otter construction budget of $2.0 million; 
* Friends of the National Zoo (FONZ) is evaluating feasibility of 
raising $30 million matching funds for elephant facility; 
* Architect/engineer responding to 35 percent design review; 
* $35.85 million is to be federally funded through Smithsonian's 
capital program. The remainder is to be funded through the Smithsonian 
trust funds. 

National Zoological Park: Kids Farm; 
Project budget: $5.193; 
Current working estimate (CWE): $5.193; 
Schedule: Opened on time; 
Comments: 
* $4.989 million federally funded through Smithsonian's capital 
program. $204,000 in trust funds of which $82,000 was funded by FONZ. 

Patent Office Building: Phase I; 
Project budget: $166.0; 
Current working estimate (CWE): $166.0; 
Schedule: 99 days behind schedule due to unexpected construction 
problems found during the renovation; 
Comments: 
* CWE within $166 million after executing scope reductions (security, 
exterior signage, furniture, elevator maintenance, and lighting) and 
transferring approved costs to trust fund budgets (wireless, build-out, 
collection move, Lunder Visible Conservation Center equipment); 
* Substantial completion projected to April 2006 (99-day delay) for a 
limited number of specific areas. Working to isolate delays and 
minimize overall impact to exhibit effort; 
* National Capital Planning Commission Submission anticipated on 
4/15/05 for hearing on 5/5/05; 
* Federally funded through Smithsonian's capital program. 

Patent Office Building: Phase II; 
Project budget: $50.0; 
Current working estimate (CWE): $51.7; 
Schedule: On time; 
Comments: 
* Funding is from trust funds; 
* Working on strategy that maintains $44.3 million budget and 
completion date 1/31/07. Smithsonian decision pending next contract 
funding increment; 
* Increased cost reflects potential desired enhancements. 

New construction: 

Museum Support Center, Pod 5; 
Project budget: $30; 
Current working estimate (CWE): $42.7; 
Schedule: Design is 4 months behind schedule; 
Comments: 
* The schedule and funding have been adjusted to address this design 
delay; 
* The Smithsonian is including an option for a laboratory in the 
contract documents for Pod 5 for an estimated $9.8 million. This $9.8 
million plus an increase in design cost of $400,000 accounts for $10.2 
million between the budget and the current working estimate; 
* Review of cost estimates resulted in a $2.5 million increase due to 
longer contract period and later separate contract awards; 
* Federally funded through Smithsonian's capital program. 

National Museum of the American Indian; 
Project budget: $219.3; 
Current working estimate (CWE): $219.3; 
Schedule: Opened on time, on Sept. 22, 2004; 
Comments: 
* About $119 million was federally funded through Smithsonian's capital 
program. The remainder was funded through the Smithsonian trust funds. 

Steven F. Udvar-Hazy Center; 
Project budget: $219.8; 
Current working estimate (CWE): $218.3; 
Schedule: Opened on time, in December 2003; 
Comments: 
* Does not include funding provided by Commonwealth of Virginia for 
site improvements; 
* The $210.3 million was funded through the Smithsonian trust funds. 
About $8 million in design funds was federally funded through 
Smithsonian's capital program. 

Mall-wide Permanent Security Barriers; 
Project budget: $0; 
Current working estimate (CWE): $33; 
Schedule: Phase 1 National Air and Space Museum construction contract 
awarded 2 months behind schedule; 
Comments: 
* Smithsonian needs to resolve Mall- wide 35-percent design issues; 
* Funding requested in fiscal year 2006 to design & construct barriers 
at NMNH; 
* Funding projected in fiscal year 2007 to complete barriers at NMAH; 
* Federally funded through Smithsonian's capital program. 

Smithsonian Institution Building (the "Castle"), National Air and Space 
Museum, Freer Gallery, Hirshhorn Museum, Quadrangle, Renwick Gallery; 
Comments: 
* No major projects are planned until 2011 to 2013. 

Source: Smithsonian Institution. 

[End of table]

* The current working estimate of the National Museum of Natural 
History's Ocean exhibit increased from about $34.1 million to $40.5 
million. This $6.4 million increase reflects higher costs for 
renovations ($2.2 million for heating, ventilation, and air- 
conditioning [HVAC] work required to support the planned exhibits' 
advanced technology and more interactive components) and $4.2 million 
for specific additional exhibits that the donor has suggested. The 
National Museum of Natural History is reprioritizing its capital 
projects to cover the higher HVAC costs. The donor will provide the 
$4.2 million in additional funds for the specific exhibits requested, 
or the additional exhibits will not be included in the project. 

* The current working estimate of Phase II of the Patent Office 
Building renovation was increased to reflect desired enhancements 
should additional trust fund monies become available. The current 
courtyard enclosure is within the original target. 

* The current working estimate of the Museum Support Center Pod 5 
project increased from $30.0 million to $42.7 million. The additional 
costs include $9.8 million for a laboratory, $400,000 for further 
design work, and $2.5 million[Footnote 41] due to a longer contract 
period,[Footnote 42] delays in obtaining program funds,[Footnote 43] 
and later separate contract awards. The purpose of this Pod is to store 
collection specimens preserved in alcohol-filled containers in a code- 
compliant building. According to the project manager, the design costs 
were higher than expected because it is difficult to design a storage 
facility to contain such a large quantity of alcohol. 

Delays in the three projects that were behind schedule were due to 
unexpected construction problems during renovation (Patent Office 
Building, Phase I), a design problem (Museum Support Center, Pod 5), 
and the late award of a construction contract (Mall-wide Permanent 
Security Barriers). According to a Smithsonian official, they are 
trying to minimize the impact of the construction delay on the Patent 
Office Building so that the public spaces can be opened on time. The 
project manager for the Museum Support Center believes that they can 
make up the delay. The project manager for the Mall security barriers 
is still working to determine the potential effects of the delay. 

In fiscal years 2002 and 2003, the Smithsonian's Office of Inspector 
General completed management reviews of three Smithsonian projects--the 
construction of National Museum of the American Indian, the Steven F. 
Udvar-Hazy Center, and the revitalization of the Patent Office 
Building. The reviews of the National Museum of the American Indian and 
of the Steven F. Udvar-Hazy Center showed that, overall, project 
management practices were effective and financial management controls 
were adequate to ensure compliance with contract terms.[Footnote 44] 
The third review, on the Patent Office Building, was performed by a 
contractor for the Office of Inspector General who found that adequate 
controls were in place to oversee the project's management and the 
existing cost-accounting system was effective in tracking the project's 
execution costs, which were managed by OFEO.[Footnote 45] While all 
three reports were generally positive, they included recommendations on 
how OFEO could improve its operations. OFEO has taken actions to adopt 
the recommendations. 

Funding Its Planned Revitalization, Construction, and Maintenance 
Remains a Key Challenge for the Smithsonian: 

NAPA's report focused strongly on improvements to the Smithsonian's 
facilities management. But the report also drew attention to the need 
for a substantial and ongoing infusion of funds to deal with the 
deterioration of the physical plant. Funding the $2.3 billion in 
planned facilities programs is an imposing challenge for the 
Smithsonian, the Administration, the Congress, and private sector 
supporters of the institution. 

Funding for the Smithsonian's annual operations and capital programs 
comes from two general sources: its trust funds and federal 
appropriations. Trust funds are used to carry out innovative research, 
expand the national collections, fund new exhibits, and support 
outreach activities to communities. The Smithsonian has been successful 
in attracting substantial philanthropic contributions to its trust fund 
that have been critical to the development and construction of new 
facilities. For example, most of the Udvar-Hazy Center's $218 million 
construction cost and $100 million of the $219 million of the National 
Museum of the American Indian's construction cost were funded through 
the trust funds. Smithsonian officials noted, however, that it is 
difficult to attract donor support for general revitalization and 
maintenance projects. Therefore, in these types of efforts, federal 
appropriations have been important. According to the Smithsonian, 
Congress first began to provide the Smithsonian with annual federal 
funding in 1858 to cover the cost of caring for objects of art and 
natural history belonging to the United States. Today, federal 
appropriations are used to operate, maintain, and protect the 
Smithsonian's facilities; conserve the national collections; sustain 
basic research; educate the public; provide administrative and support 
services; and support revitalization and construction. (See app. I for 
additional details on the Smithsonian's trust funds and appropriations.)

For fiscal year 2004, about 34 percent of Smithsonian's $904 million in 
revenues for operations and capital programs came from its trust fund 
assets, with the remainder coming from direct federal appropriations. 
Of this total amount, about $184.4 million was designated for 
facilities revitalization, construction and maintenance. While 
recognizing that future funding decisions could result in different 
levels of funding, annual revenues at the 2004 level would fall well 
short of the $2.3 billion estimate for the revitalization, 
construction, and maintenance needs identified for the next 9 years. In 
our High Risk Series report on federal real property, we highlighted 
the importance of ensuring credible, long-term budget planning for 
sustaining and modernizing facilities.[Footnote 46] Such planning 
involves key stakeholders in government--the property-holding agency, 
the Office of Management and Budget, and the Congress--in examining 
viable funding options. In the case of the Smithsonian, the importance 
of this approach is underlined by the trust-trustee relationship that 
defines the relationship between the institution and the federal 
government. We asked Smithsonian officials if a strategic approach had 
been developed for funding the planned facilities work. Officials told 
us that various funding approaches and options have been discussed by 
the staff, the Board of Regents, and with congressional leaders but 
said that no consensus for dealing with this issue has emerged. 

Conclusion: 

As an organization that relies heavily on federal support to maintain 
its facilities, the Smithsonian Institution is part of the general 
challenge facing the federal government in real property management. As 
we noted in our 2003 High Risk Series report on federal real property, 
the overall condition of the federal facilities portfolio is one of 
alarming deterioration, with the problem accelerating in recent years 
due to the age of the buildings. Greatly improved management processes 
and tens of billions of dollars will be needed to restore federal real 
property assets and make them fully functional. At stake with the 
Smithsonian are not just the buildings themselves, but the 
irreplaceable scientific and cultural assets that they contain. 

To address its own set of problems, the Smithsonian has taken major 
steps, in line with NAPA's 2001 recommendations, to reorganize its 
facilities management structure to achieve improved accountability and 
operational efficiency. OFEO is incorporating industry best practices 
for facilities management and has established processes for 
prioritizing work with the aim of leveraging its limited staffing and 
funding resources to the institution's best advantage. OFEO has also 
put processes in place to develop more accurate estimates of its 
facilities funding needs. The reorganization appears to be going in the 
right direction, though it is still in an early stage of implementation 
and its long-term effectiveness has yet to be determined. Full 
implementation of the restructuring effort has been hindered by 
staffing and funding reductions that have occurred throughout the 
Smithsonian due to budget constraints. 

Along with recommending management improvements, NAPA pointed to the 
need for a continuing and substantial infusion of funds for maintaining 
and improving existing and new facilities. The federal government has 
responded in recent years with increased levels of appropriations for 
the Smithsonian's facilities needs, and the Smithsonian itself has 
successfully raised its share of private sector funding for the 
construction of its two newest museums. Still, the estimated $2.3 
billion in costs for facilities needs over the next 9 years is beyond 
the current level of the Smithsonian's annual operating revenues from 
its trust funds and federal appropriations. At present, it is unclear 
how, when, or to what extent the planned projects will be funded. 

Recommendation for Executive Action: 

Given the critical importance of correcting the deteriorating condition 
of the Smithsonian's facilities, we recommend that the Secretary of the 
Smithsonian Institution establish a process for exploring and 
analyzing, in a structured and reportable manner, various options for 
funding its facilities needs (including options that may require 
legislative authorization), together with the advantages and 
disadvantages of each. This process would culminate with a method and 
time frame for engaging the key stakeholders--the Smithsonian Board of 
Regents, the Administration, and the Congress--in the development and 
implementation of a strategic funding plan to address the 
revitalization, construction, and maintenance projects identified by 
the Smithsonian. 

Agency Comments: 

We provided a draft of this report to the Smithsonian for comment. In 
response, the Smithsonian provided us with both oral and written 
comments, indicating that it concurred with our findings. In oral 
comments, the Director of Government Relations stated that the 
Smithsonian agreed with our recommendation. The Smithsonian also 
offered some technical comments and updates that we incorporated where 
appropriate. A letter from the Secretary of the Smithsonian commenting 
on our report is included as appendix VIII. 

As agreed with your office, unless you publicly announce its contents 
earlier, we plan no further distribution of this report until 30 days 
after the date of this letter. At that time, we will send copies of 
this report to the appropriate congressional committees, the Secretary 
of the Smithsonian Institution, and the Director of the Office of 
Management and Budget. We will make copies available to others upon 
request. In addition, this report will be available at no cost on the 
GAO Web site at [Hyperlink, http://www.gao.gov]. If you have any 
questions about this report, please contact me at (202) 512-2834 or 
[Hyperlink, goldsteinm@gao.gov]. Key contributors to this report are 
listed in appendix IX. 

Signed by: 

Mark L. Goldstein: 
Director, Physical Infrastructure Issues: 

[End of section]

Appendixes: 

Appendix I: Funding Sources and Statutes Related to the Smithsonian's 
Revitalization, Construction, and Minor Repair and Maintenance 
Programs: 

The Smithsonian uses funding from a variety of public and private 
sources for revitalization, construction, and minor repair and 
maintenance (maintenance) of its facilities. Currently, maintenance is 
funded primarily through appropriations, according to a Smithsonian 
official. The Smithsonian's funding can be classified into two broad 
categories: trust funds and congressional appropriations. 

Trust Funds: 

Unrestricted trust funds--These funds are not subject to any donor- 
imposed or legal restrictions on the use of the monies. The Board of 
Regents may expend these funds in any manner they deem appropriate in 
promoting the Smithsonian's mission. The unrestricted trust fund 
includes income from investment earnings; income from Smithsonian 
Business Ventures, which includes revenue from the Smithsonian's 
magazines and other publications, museum stores, mail-order catalogs, 
concessions, IMAX theater, and licensing and media enterprises; and 
income from government grants and contracts. Unrestricted trust funds 
are often devoted to programs, collections, and general administration, 
but could be used for revitalization, construction, and minor repair 
and maintenance. Various government agencies and departments provide 
grants and contracts for projects that only the Smithsonian can conduct 
because of its expertise in a particular area of science, history, art, 
or education and because of its ability to respond quickly to certain 
needs. At the end of fiscal year 2004, government grants and contracts 
accounted for about 12 percent of the Smithsonian's revenue. At the end 
of fiscal year 2004, the Smithsonian's unrestricted operating revenues 
totaled $399.4 million, of which $173.1 million was spent to operate 
the Smithsonian's businesses that generated $195.0 million in revenues, 
according to its audited financial statement. 

Temporarily restricted trust funds--These funds include donations, 
earnings on endowments, and private grants that are subject to donor- 
imposed stipulations on how the money is spent. The types of 
restrictions imposed by donors include limitations on the use of funds 
for the construction or renovation of a specific museum or facility or 
support for a specific program or exhibit. For example, the 
construction of the Steven F. Udvar-Hazy Center was funded by numerous 
private contributions that were classified as temporarily restricted 
and could only be spent on construction of the Hazy Center. At the end 
of fiscal year 2004, the Smithsonian's temporarily restricted operating 
revenues totaled $83.9 million, according to its audited financial 
statement. 

Permanently restricted trust funds--These funds include donations, 
earnings on endowments, and bequests that are subject to donor-imposed 
stipulations that the principal be maintained permanently. Donors of 
these funds permit the Smithsonian to use all or part of the income 
earned from these funds for either general or donor-specified purposes. 
James Smithson's original bequest is included within this category. At 
the end of fiscal year 2004, the Smithsonian's permanently restricted 
operating revenues totaled $0.5 million, according to its audited 
financial statement. 

Direct Federal Appropriations: 

Regular congressional appropriations for the Smithsonian began in 1858, 
according to a Smithsonian official. In 1879, the Congress authorized 
and appropriated $250,000 for construction of a National Museum (now 
known as the Arts and Industries Building). Today, 20 U.S.C. § 53(a) 
provides that appropriations are authorized for repairs and alterations 
of the Smithsonian's buildings and grounds. According to a Smithsonian 
official, this is the authority the Smithsonian uses to perform 
revitalizations and major repairs when there is no specific 
congressional authorization for a project. For fiscal year 2004, 
federal appropriations were $596.3 million, according to the audited 
financial statement. 

We were told by a Smithsonian official that major Smithsonian 
facilities (those that represent national landmarks or are otherwise 
significant) have all been legislatively authorized by the Congress. 
According to a Smithsonian official, it has built or replaced 
facilities without congressional authorization, but those projects did 
not exceed a $1 million cost ceiling agreed to with congressional staff 
and primarily have consisted of administrative, utility, and laboratory 
facilities. Further, recent appropriation acts have required the 
Smithsonian to consult with the Appropriations Committees before 
planning or commencing any construction projects, according to the same 
official. While the Congress has authorized major new museums and 
facilities, the Congress has moved away from fully funding the 
construction of these facilities beginning in 1982, when authorizing 
the construction of a building for the National Museum of African Art 
and a Center for Eastern Art. The Congress limited the federal funding 
to $36.5 million--just less than half of the estimated $75 million 
total cost of the project. The legislation directed that no 
appropriated funds be obligated or expended except for planning, 
administration, management expenses, and architectural or consulting 
services until the Smithsonian had sufficient private funding in hand 
which, when combined with federal funding, could complete the project. 

More recently, the Congress required that not more than two-thirds of 
the total cost of planning, designing, and constructing the National 
Museum of the American Indian come from federal appropriations. The 
Congress authorized the Udvar-Hazy Center and appropriated money for 
the design, but it did not allow any appropriations to be used for 
construction. The Smithsonian built the facility with private donations 
and a $78 million general obligation bond. In 2003, the Congress 
authorized the Smithsonian to plan, design, and construct a building 
for a National Museum of African American History and Culture. The 
authorization provided that half of the costs are to come from 
nonfederal sources. 

Currently, maintenance projects are funded primarily through 
appropriations, although the maintenance staff are funded by both 
appropriations and trust monies according to a Smithsonian official. A 
Smithsonian official also told us that the institution is moving toward 
trying to get private donors to allow part of their donations to be set 
aside for repair and maintenance of exhibits. Exhibits such as America 
on the Move and The Price of Freedom have planned maintenance budgets 
of about $1 million each, some of which has already been raised from 
the private sector. For The Star Spangled Banner, the Smithsonian is 
planning an endowment fund of $4 million for maintenance. One donor has 
agreed to let the Smithsonian use $1 million of his original gift for 
this exhibit to help fund the endowment. 

Selected Smithsonian Institution Legal Authorities Relating to 
Construction and Revitalization of Facilities: 

Enabling Laws: 

Act of 1836[Footnote 47] - Accepted James Smithson's bequest of his 
property to the United States for the purpose of founding in 
Washington, D.C., the Smithsonian Institution, an establishment for the 
increase and diffusion of knowledge among men. Among other things, the 
act required the Treasurer of the United States to account separately 
from all other accounts of his office all sums received by virtue of 
Smithson's bequest and for the funds to be spent in such manner as the 
Congress later directed. 

Act of 1846[Footnote 48] - Established the Smithsonian Institution in 
its present form and provided for the administration of the Smithsonian 
Institution trust by a Board of Regents. The act appropriated from 
federal funds an amount from the interest on Smithson's bequest for the 
erection of suitable buildings and other expenses of the institution. 
The act stated that all appropriations and expenditures that would be 
made for the purpose of the institution would be from the interest 
accrued and not from the principal of the fund. The act authorized the 
Board of Regents to select a suitable site for a building and contract 
for the construction of a suitable building necessary for the 
institution. The act authorized the Secretary of the Board of Regents 
to take charge of the building and property of the institution. The act 
also reiterated that all money recovered by, or accruing to the 
institution, would be paid into the United States Treasury and 
separately accounted for as provided by the 1836 act.[Footnote 49]

Current Statues: 

20 U.S.C. § 41 - Establishes the Smithsonian Institution for the 
increase and diffusion of knowledge among men, with the powers, 
limitations, and restrictions contained in the act. 

20 U.S.C. § 42 - Establishes the members of the Board of Regents. 

20 U.S.C. § 46 - Provides for the Secretary of the Board of Regents to 
take charge of the buildings and property of the Institution. 

20 U.S.C. § 53 - Provides that all laws relating to the protection of 
public property in the District of Columbia shall apply to the lands, 
buildings, and other property of the Smithsonian Institution. Also 
provides that all money recovered by or accruing to the Smithsonian 
Institution shall be paid into the Treasury of the United States, to 
the credit of the Smithsonian bequest, and separately accounted for. 

20 U.S.C. § 53a - Provides that appropriations are authorized for 
repairs and alterations of buildings and grounds occupied by the 
Smithsonian Institution in the District of Columbia and elsewhere. 

20 U.S.C. § 54 - Provides that interest is appropriated for perpetual 
maintenance and support of the institution. Also provides that all 
expenditures and appropriations made from the Smithsonian Institution 
treasury account for the purposes of the institution are to be made 
from the interest and not the principal in the account. 

20 U.S.C. § 55 - Provides that the Secretary is authorized to receive 
and deposit in the Treasury on the same terms as the original bequest 
of James Smithson's, such sums that the Regents see fit to deposit. 
This section specifically states that this shall not operate as a 
limitation on the power of the Smithsonian Institution to receive money 
or property by gift, bequest, or devise, and to hold or dispose of the 
same to promote the purposes of the institution. 

20 U.S.C. § 56 - Authorizes the Smithsonian Institution Board of 
Regents to dispose of any money which has accrued as interest on the 
Smithsonian fund, or not appropriated, as they deem best suited for the 
promotion of the purpose of James Smithson's bequest. 

Annual Appropriations Acts - Appropriates funds for maintenance, 
alteration, repair, revitalization, lease, and construction of 
facilities.[Footnote 50]

Selected Statutes Enacted Since 1955 Authorizing Smithsonian 
Institution Facilities: 

An Act to Authorize the Construction of a Building for the Museum of 
History and Technology Including the Plans and Specifications[Footnote 
51]

* Authorized the Board of Regents to prepare drawings and 
specifications for, and to construct a suitable building for, a Museum 
of History and Technology. Authorized to be appropriated such sums not 
to exceed $36,000,000 as may be necessary to carry this out. 

An Act to Authorize the Plans and Specifications for the Construction 
of a Building for a National Air Museum[Footnote 52]

* Authorized the Board of Regents to prepare plans, including drawings 
and specifications, for the construction of a suitable building for a 
National Air Museum and authorized to be appropriated such sums as may 
be necessary to carry this out. 

An Act for the Establishment of the Joseph H. Hirshhorn Museum and 
Sculpture Gardens[Footnote 53]

* Authorized the Board of Regents to remove any existing structure, 
prepare architectural and engineering designs, plans, and 
specifications and to construct a suitable museum and sculpture garden 
for the use of the Smithsonian Institution within the area designated 
within the act for the establishment of the Joseph H. Hirshhorn Museum 
and Sculpture Garden. Pledged the faith of the United States to provide 
such sums as may be necessary for the upkeep, operation, and 
administration of the Joseph H. Hirshhorn Museum and Sculpture Garden. 
Authorized to be appropriated not to exceed $15,000,000 for the 
planning and construction of the Joseph H. Hirshhorn Museum and 
Sculpture Garden and such additional sums as may be necessary for the 
maintenance and operation of the museum and sculpture garden. 

An Act to Authorize the Smithsonian Institution to Plan Museum Support 
Facilities[Footnote 54]

* Authorized the Board of Regents to prepare plans for museum support 
facilities to be used for (1) the care, curation, conservation, 
deposit, preparation, and study of the national collections of 
scientific, historic, and artistic objects, specimens, and artifacts; 
(2) the related documentation of such collections of the Smithsonian 
Institution; and (3) the training of museum conservators. Authorized to 
be appropriated such sums as may be necessary to carry this out. 
Provided that the museum shall be located on federally owned land 
within the metropolitan area of Washington, D.C., and authorized any 
federal agency to transfer land under its jurisdiction to the 
Smithsonian Institution for the site without reimbursement. 

An Act to Authorize the Smithsonian Institution to Construct Museum 
Support Facilities[Footnote 55]

* Amended an Act to Authorize the Smithsonian Institution to Plan 
Museum Support Facilities, P.L. 94-98, to authorize the Smithsonian 
Institution to construct museum support facilities. Authorized to be 
appropriated $21,500,000 to carry this out. 

An Act to Authorize the Smithsonian Institution to Plan for Development 
of the Area South of the Original Smithsonian Institution 
Building[Footnote 56]

* Authorized the Board of Regents to plan for the development of the 
area south of the original Smithsonian Institution Building adjacent to 
Independence Avenue at Tenth Street, Southwest, in Washington, D.C. 
Authorized to be appropriated $500,000 to carry this out. 

An Act to Authorize the Smithsonian Institution to Construct a Building 
for the National Museum of African Art and a Center for Eastern 
Art[Footnote 57]

* Authorized the Board of Regents to construct a building for the 
National Museum of African Art and a Center for Eastern Art together 
with structures for related educational activities and authorized to be 
appropriated $36,500,000 to carry this out. Provided that only funds 
appropriated pursuant to this act may be obligated or expended for 
planning, administration, management expenses, and architectural or 
other consulting services, and no other funds appropriated pursuant to 
this act shall be obligated or expended until such time as there is 
available to the Board of Regents, from private donation or other 
nonfederal sources, a sum combined with any appropriated funds in an 
amount sufficient to carry this out. 

An Act to Authorize the Smithsonian Institution to Purchase Land in 
Santa Cruz County, Arizona[Footnote 58]

* Authorized the Smithsonian Institution to purchase land in Santa Cruz 
County, Arizona, for the permanent headquarters of the Fred Lawrence 
Whipple Observatory and authorized to be appropriated $150,000 to carry 
this out. 

An Act to Authorize the Administrator of General Services to Transfer 
to the Smithsonian Institution Without Reimbursement the General Post 
Office Building and the Site Located in Washington, D.C.[Footnote 59]

* Authorized the Administrator of General Services to transfer to the 
Smithsonian Institution, without reimbursement, for use for art 
galleries and related functions the General Post Office Building with 
any attached underground structures and the site of the building 
located between Seventh and Eighth Streets Northwest and E and F 
Streets Northwest, in Washington, D.C. Authorized to be appropriated to 
the Board of Regents of the Smithsonian Institution $40,000,000 for 
renovation and repair after the transfer of the building is made to the 
Smithsonian Institution. 

An Act to Authorize the Smithsonian Institution to Plan and Construct 
Facilities for Certain Science Activities[Footnote 60]

* Authorized the Board of Regents to plan and construct facilities for 
the Smithsonian Astrophysical Observatory and the Smithsonian Tropical 
Research Institute. Authorized to be appropriated $4,500,000 for the 
Smithsonian Astrophysical Observatory and $11,100,000 for the 
Smithsonian Tropical Research Institute. 

An Act to Authorize the Smithsonian Institution to Construct the 
Charles McC. Mathias, Jr., Laboratory for Environmental 
Research[Footnote 61]

* Authorized the Board of Regents to construct the Charles McC. 
Mathias, Jr., Laboratory for Environmental Research in Edgewater, 
Maryland. Authorized to be appropriated $1,000,000 to carry this out. 

An Act to Establish the National Museum of the American Indian within 
the Smithsonian Institution[Footnote 62]

* Authorized the Board of Regents to plan, design, and construct a 
facility to house the portion of the National Museum to be located in 
Washington, D.C. at a site specified in the act. Provided that the 
Board of Regents shall pay not more than two-thirds of the total cost 
of planning, designing, and constructing the facility from funds 
appropriated to the board with the remainder of the costs coming from 
nonfederal sources. 

* Authorized the Administrator of General Services to lease to the 
Smithsonian Institution, at a nominal charge, space in the Old U. S. 
Custom House in New York to house the portion of the National Museum to 
be located in New York and designated as the "George Gustav Heye Center 
of the National Museum of the American Indian." Authorized the Board of 
Regents to plan, design, and construct a facility for the National 
Museum in the Old U. S. Custom House in New York and authorized the 
Administrator of General Services to plan, design, and construct an 
auditorium and loading dock for the shared use of all the occupants of 
the Old U. S. Custom House in New York. The act provided that the Board 
of Regents shall pay one-third of the costs of planning, designing, and 
constructing the National Museum in New York from funds appropriated to 
the board with the remainder of the costs coming from nonfederal 
sources. The act limited the obligation of federal funds for 
construction of the National Museum in New York in any fiscal year, 
until nonfederal sources have paid to the Board of Regents the 
nonfederal share of the costs which the board estimated will be 
incurred in any such year. The act noted that New York City and New 
York State each agreed to pay $8,000,000 or an amount equal to one- 
third of the costs for planning, designing, and constructing the 
facility, whichever is less. The act provided that after construction 
of the National Museum in New York is completed that repairs and 
alterations of the facility shall be the Board of Regents 
responsibility. 

* Authorized the Board of Regents to plan, design, and construct a 
facility for the conservation and storage of the collections of the 
National Museum at the Museum Support Center of the Smithsonian 
Institution with a total aggregate square footage of at least 400,000 
square feet. 

* Authorized to be appropriated to the Administrator of General 
Services from the Federal Buildings Fund $25,000,000 to carry out the 
plan, design, and construction of the auditorium and loading dock and 
to make repairs and alterations to the portion of the Old U. S. Custom 
House that is not leased to the Board of Regents. 

* Authorized to be appropriated to the Board of Regents such additional 
sums as may be necessary to carry out the planning, design, and 
construction of the National Museum to be located in Washington, D.C., 
the National Museum to be located in New York, and the Museum Support 
Center for the collections of the National Museum. 

An Act to Authorize the Smithsonian Institution to Plan, Design, 
Construct, and Equip Space in the East Court of the National Museum of 
the Natural History Building[Footnote 63]

* Authorized the Board of Regents to plan, design, construct, and equip 
approximately 80,000 square feet of space in the East Court of the 
National Museum of the Natural History Building. Authorized to be 
appropriated $30,000,000 to carry this out. 

An Act to Provide for Planning and Design of a National Air and Space 
Museum Extension[Footnote 64]

* Authorized the Board of Regents to plan and design an extension of 
the National Air and Space Museum at Washington Dulles International 
Airport and authorized to be appropriated $8,000,000 to carry this out. 

An Act to Authorize the Smithsonian Institution to Plan, Design, and 
Construct the West Court of the National Museum of the Natural History 
Building[Footnote 65]

* Authorized the Board of Regents to plan, design, and construct the 
West Court of the National Museum of the Natural History Building. 
Provided that no appropriated funds may be used to pay any expense for 
the planning, design, and construction of the West Court. 

An Act to Authorize Construction of a National Air and Space Museum 
Dulles Center at Washington Dulles International Airport[Footnote 66]

* Authorized the Board of Regents to construct the Smithsonian 
Institution National Air and Space Museum Dulles Center at Washington 
Dulles International Airport. Provided that no appropriated funds may 
be used to pay for any expenses of construction. 

An Act to Authorize the Smithsonian Institution to Plan, Design, 
Construct, and Equip Laboratory, Administrative, and Support Space for 
the Smithsonian Astrophysical Observatory Submillimeter Array[Footnote 
67]

* Authorized the Board of Regents to plan, design, construct, and equip 
laboratory, administrative, and support space to house base operations 
for the Smithsonian Astrophysical Observatory Submillimeter Array in 
Hilo Hawaii. Authorized to be appropriated specific amounts in various 
fiscal years to carry this out. 

Smithsonian Facilities Authorization Act[Footnote 68]

* Authorized the Board of Regents to plan, design, construct, and equip 
additional special use storage and laboratory space at the museum's 
support facility in Suitland, Maryland. Authorized to be appropriated 
specific amounts in various fiscal years and such additional sums as 
necessary to carry this out. 

* Authorized the Board of Regents to plan, design, and construct 
improvements to the interior and exterior of the Patent Office 
Building, including the construction of a roof covering for the 
courtyard. Provided that funds to carry this out will be from 
nonappropriated sources. 

National Museum of African American History and Culture Act[Footnote 
69] 

* Authorized the Board of Regents, in consultation with the National 
Museum of African American History and Culture Council, to plan, 
design, and construct a building for the museum. Provided that 50 
percent of the costs to carry this out will be from federal funds and 
50 percent of the costs to be from nonfederal sources. Authorized to be 
appropriated such sums as necessary to carry this out. 

An Act to Authorize Construction and Related Activities for Support of 
the VERITAS on Kitt Peak, Arizona[Footnote 70]

* To authorize the Board of Regents of the Smithsonian Institution to 
carry out construction and related activities in support of the 
collaborative Very Energetic Radiation Imaging Telescope Array System 
(VERITAS) project on Kitt Peak near Tucson, Arizona. Authorized to be 
appropriated $1,000,000 to carry this out. 

[End of section]

Appendix II: Smithsonian Institution's Status on the Implementation of 
the National Academy of Public Administration's Recommendations: 

Recommendations by area: 1. Evaluation of the renovation, repair and 
alteration (RR&A) requirements. 

Recommendations by area: 1.1. Revalidate the total backlog of RR&A 
requirements. This revalidation should include completing detailed 
facilities condition assessments for all museums and other major 
facilities that have not been surveyed for this purpose within the 
preceding 3 years. In-house capability should be supplemented with 
contract assistance, if necessary, to expedite completion; 
Status of implementation plans: Implemented; 
Smithsonian comments: Completed September 2001 with publication of 
Museums and Facilities: Critical Assessment and Improvement Objectives. 

Recommendations by area: 1.2. Develop a fully integrated and 
prioritized 10-year plan for executing the revalidated backlog of 
requirements and brief the Office of Management and Budget (OMB) 
examiners and congressional staffs on the total facilities 
requirements, even though the annual budget constraints may preclude 
requesting the full amount of funding actually needed; 
Status of implementation plans: Implemented; 
Smithsonian comments: Briefings with OMB and congressional staff held 
Spring 2002 based on Museums and Facilities: Critical Assessment and 
Improvement Objectives; subsequent briefings held annually to apprise 
of progress. 

Recommendations by area: 1.3. Cost estimates for all the capital 
improvements projects that are included in the Smithsonian's annual 
budget requests to OMB and Congress should be based on the completion 
of at least 35 percent of final design, with cost escalation included 
to improve the accuracy and reliability of the estimates; 
Status of implementation plans: Implementation under way; 
Smithsonian comments: Project Management Handbook includes this 
provision. Discussions have already taken place with OMB on this topic. 
Additional funding in Facilities Planning and Design will be required 
before the Smithsonian can consistently complete 35-percent design of 
future year projects before requesting construction funding. 

Recommendations by area: 1.4. Implement and adhere to strict control 
measures over project scope and cost increases. For selected major 
capital improvement projects, such as the Patent Office Building, 
consider establishing a formal review group to help control increases 
in project scope and cost; 
Status of implementation plans: Implemented; 
Smithsonian comments: Implemented. 

Recommendations by area: 1.5. The budget format for the RR&A program 
should be changed and simplified to succinctly state the actual 
requirements, estimated costs, and construction schedules; 
Status of implementation plans: Implemented; 
Smithsonian comments: Fiscal Year (FY) 2003 and 2004 budgets reflect 
new format of project descriptions. New structure for entire facilities 
program budget request implemented with FY 2004 request. 

Recommendations by area: 2. Responsiveness to Congress and OMB. 

Recommendations by area: 2.1. Place significantly increased emphasis on 
responding to congressional questions and requests in a timely and 
accurate manner; 
Status of implementation plans: Implemented; 
Smithsonian comments: All requests since 2002 have been dealt with 
expeditiously. 

Recommendations by area: 3. Facilities maintenance. 

Recommendations by area: 3.1. Develop and implement a well-structured 
maintenance program that includes preventive maintenance, periodic 
testing and inspection, and programmed maintenance; 
Status of implementation plans: Implemented; 
Smithsonian comments: Plan provided to OMB and Congress January 2002. 
Funds received in FY 2004 and requested for FY 2006 will begin to 
address capability to focus on planned maintenance activities, as 
guided by Reliability Centered Maintenance (RCM). 

Recommendations by area: 3.2. Reorder budget priorities to provide for 
an increase to at least $10 to $15 million annually in a preventive 
maintenance category; 
Status of implementation plans: Implementation under way; 
Smithsonian comments: Increase of $5.4 million received in FY 2004 
Salaries and Expenses (S&E) appropriation as an initial increment of 
increase. Additional increase of $4.7 million included in FY 2006 
request to Congress. Estimate of total requirement revised upward to 
reflect National Research Council (NRC) guidelines of 2-4 percent of 
physical plant Current Replacement Value. 

Recommendations by area: 3.3. Consider budgeting all maintenance and 
minor repair requirements, excluding personnel costs, in one separate 
account in the RR&A budget to provide improved visibility and funds 
control; 
Status of implementation plans: Implemented; 
Smithsonian comments: Budget restructured to create Facilities 
Maintenance line item in the S&E portion of the Smithsonian's FY 2004 
budget request. Decision to include in S&E rather than Capital portion 
of the budget discussed with OMB and congressional staff. 

Recommendations by area: 3.4. Consider adopting the RCM approach that 
many federal agencies use. RCM is a maintenance philosophy that 
incorporates an effective mix of proactive, preventive, predictive 
testing and inspection, and reactive maintenance practices that focus 
on reliability and risk management; 
Status of implementation plans: Implemented; 
Smithsonian comments: Associate Director for Reliability hired in 
August 2002. Implementation plan developed and Office Facilities 
Engineering and Operations (OFEO) staff trained. Predictive testing and 
inspection (PT&I) equipment purchased for vibration analysis, 
thermography, and ultrasonic thickness. Performance metrics identified 
and key processes are being revised and validated. PT&I tests were 
added as part of acceptance testing to Hazy, National Museum of the 
American Indian, and Patent Office Building projects. 

Recommendations by area: 4. Smithsonian "backlog". 

Recommendations by area: 4.1. Use commonly accepted definitions for 
facilities maintenance and repair as spelled out in the numerous NRC 
reports on this subject; 
Status of implementation plans: Implemented; 
Smithsonian comments: The engineering study Museums and Facilities: 
Critical Assessment and Improvement Objectives contains specific 
definitions that are in accord with NRC. 

Recommendations by area: 4.2. Properly identify the Smithsonian's very 
significant backlog of specific major repair and restoration 
requirements and refrain from attempting to identify all facilities 
deficiencies and needs under the misleading term "maintenance backlog"; 
Status of implementation plans: Implemented; 
Smithsonian comments: The Smithsonian no longer uses the term 
"maintenance backlog," and appropriately defines major repair and 
restoration requirements under "Facilities Capital--Revitalization 
Requirements.". 

Recommendations by area: 5. Facilities management organization. 

Recommendations by area: 5.1. Centralize facilities management 
functions, including the National Zoo, under a single facilities 
organization. This change would improve operational efficiency and 
effectiveness, cost control, quality control, and accountability; 
Status of implementation plans: Implemented; 
Smithsonian comments: Office of Facilities Engineering and Operations 
established. 

Recommendations by area: 5.2. Director of OFEO should be designated the 
principal Smithsonian official for managing the facilities maintenance 
activities, the RR&A program, and the construction program; 
Status of implementation plans: Implemented; 
Smithsonian comments: Director of OFEO has been given these 
responsibilities by the Secretary. 

Recommendations by area: 5.3. The Office of Physical Plant (OPP) should 
be restructured to place a stronger emphasis and focus on its three 
primary responsibilities: (1) operation and maintenance of the 
Smithsonian's physical plant, (2) repair and restoration of facilities 
to reduce the extensive backlog, and (3) construction of new 
facilities; 
Status of implementation plans: Implemented; 
Smithsonian comments: Former Office of Physical Plant has been 
reorganized into three separate entities to focus upon specific 
facilities management functions. 

Recommendations by area: 5.4. If the Smithsonian's RR&A program is 
substantially increased, the OFEO staffing should accordingly be 
increased to effectively manage the larger program; 
Status of implementation plans: Implementation under way; 
Smithsonian comments: The Smithsonian received some staff to support 
the capital program in FY 2003 and FY 2004; construction supervision 
and administration staff has been paid with project funding since FY 
2003. Remaining staffing requirements for a larger capital program will 
be requested in future budgets as the program increases. 

Recommendations by area: 6. Contracting out considerations. 

Recommendations by area: 6.1. Conduct a comprehensive and detailed 
analysis to determine whether or not the facilities operations and 
maintenance functions that are performed by the OFEO in-house workforce 
could be accomplished more efficiently and cost effectively if they 
were contracted out; 
Status of implementation plans: Implementation under way; 
Smithsonian comments: In FY 2003, the Smithsonian awarded a contract 
for operations and maintenance of the Hazy Center in lieu of adding new 
staff, and contracted out Heating, Ventilation and Air Conditioning 
(HVAC) maintenance at Smithsonian Environmental Research Center. 
Maintenance resources added in FY 2004 are being used primarily to 
augment staff capacity with contracts for inspection, testing, and 
preventive maintenance of automatic doors; electrical panels; fire 
alarm systems and fire sprinklers; testing and cleaning of cooling 
towers; and thermographic and vibration analysis. More analysis of 
contracting opportunities will be conducted upon completion of 
reorganization and filling of new positions in OFEO. 

Recommendations by area: 6.2. Conduct a similar analysis of the 
facilities operations and maintenance functions for the National 
Zoological Park (National Zoo); 
Status of implementation plans: Implementation under way; 
Smithsonian comments: The Smithsonian contracts for a number of 
maintenance activities at the National Zoo, including HVAC maintenance. 
More analysis of contracting opportunities will be conducted upon 
completion of reorganization and filling of new positions in OFEO. 

Recommendations by area: 7. Capital Program Planning Board (CPPB). 

Recommendations by area: 7.1. The CPPB membership should be realigned 
and updated to accommodate the Smithsonian's current organization; 
Status of implementation plans: Implemented; 
Smithsonian comments: A new charter for the board, now named the 
Capital Planning Board, reflects the current Smithsonian organization. 

Recommendations by area: 7.2. The Director of OFEO should be designated 
the Smithsonian's principal and lead official for developing, 
presenting, and defending all facilities programs and budgets to the 
CPPB and to external organizations, such as OMB and Congressional 
staffs, where required; 
Status of implementation plans: Implemented; 
Smithsonian comments: The board's charter assigns overall 
responsibility for the board to the Chief Financial Officer. The 
Director, OFEO, has been directed to lead the board's deliberations for 
facilities capital programs. 

Recommendations by area: 7.3. The CPPB should meet on a regularly 
scheduled basis to review and recommend approval of the annual budget 
request for the RR&A program, the maintenance program, and the 
construction program, as well as the 5-year plans for each of these 
facilities programs. Minutes of each meeting should be recorded and 
provided to board members; 
Status of implementation plans: Implemented; 
Smithsonian comments: The board meets on a regular basis. 

Recommendations by area: 7.4. Board review results should be provided 
in the form of formal written recommendations to the Secretary of the 
Smithsonian Institution; 
Status of implementation plans: Implemented; 
Smithsonian comments: Board recommendations are incorporated into 
overall budget recommendations made to the Secretary. 

Recommendations by area: 8. Budgeting and financial management. 

Recommendations by area: 8.1. Routinely include specific data in annual 
budget requests on how the Smithsonian applied its RR&A funding from 
the prior year; 
Status of implementation plans: Implemented; 
Smithsonian comments: The Smithsonian budget requests since FY 2003 
include this prior year information in summary and by major project. 

Recommendations by area: 9. More effective financial system. 

Recommendations by area: 9.1. The current Smithsonian Financial System 
(SFS) should be replaced with an updated system. The Smithsonian should 
ensure that the updated system is fully compatible with the standards 
set by the Joint Financial Management Improvement Program and reports 
obligations and outlays at the program and project level. The 
Smithsonian should ensure that program and major-unit managers, as well 
as working-level fund-control personnel, are consulted in the process 
of defining requirements for the new system; 
Status of implementation plans: Implemented; 
Smithsonian comments: Phase I of the Institution's new Enterprise 
Resource Planning (ERP) PeopleSoft implemented October 1, 2002. Capital 
Program managers are participating in planning for Phase II 
implementation, which will include the Asset Management Module. 

Recommendations by area: 9.2. In the interim, terminology used in the 
SFS reports should be clarified. If practical, SFS reports should be 
revised to provide actual obligation data. Key personnel should be 
trained to correctly apply the terms used in the federal appropriation 
process and those used in internal operations; 
Status of implementation plans: Implemented; 
Smithsonian comments: Terminology clarified as part of ERP development. 

Recommendations by area: 9.3. Recognize that managers will continue to 
rely on separate cuff systems unless and until a new system is in place 
that provides managers with the program and project-level information 
they need and in which the managers have confidence; 
Status of implementation plans: Implemented; 
Smithsonian comments: Capital Program cuff system (PFITS) will be 
retained and has been updated to match new PeopleSoft coding structure. 
Commercial Off The Shelf (COTS) project management software systems are 
being evaluated for potential use in the future. 

Recommendations by area: 9.4. The cuff records used by the National Zoo 
should be modified to more readily provide a basis for tracking 
obligations as well as commitments; 
Status of implementation plans: Implemented; 
Smithsonian comments: Merger of National Zoo PFITS with PFITS was 
completed in September 2003. All National Zoological Park PFITS 
obligations, commitments and expenses are now being tracked. 

Recommendations by area: 9.5. Survey managers to determine which SFS 
reports are actually providing useful data, which should be changed 
with the current system's capabilities, and which should be 
discontinued; 
Status of implementation plans: Implemented; 
Smithsonian comments: Information on reporting requirements gathered as 
part of new financial system (ERP) development. 

Recommendations by area: 9.6. Modify SFS basic reports to provide 
separate reporting for OPP and National Zoo transactions; 
Status of implementation plans: Implemented; 
Smithsonian comments: Separate codes have been established to 
distinguish between OFEO and National Zoo Facilities Capital financial 
activity. 

Recommendations by area: 9.7. Until a unified system is available, a 
sufficient number of people should be trained to operate the various 
cuff systems the Smithsonian uses so that the absence of any one 
individual does not hamper operations; 
Status of implementation plans: Implemented; 
Smithsonian comments: Backups have been trained to support the OFEO 
cuff system for the Capital Program (PFITS). 

Source: Smithsonian Institution. 

[End of table]

[End of section]

Appendix III: Organization and Responsibilities of the Smithsonian's 
Office of Facilities Engineering and Operations: 

Office/Sub-offices: Office of Facilities Engineering and Operations; 
Responsibilities: The office is responsible for facilities planning, 
master planning, and resource management including facility project 
budget advocacy, development, policy and standards, fiduciary 
accountability, program oversight and analysis. The office is also 
responsible for architectural history and historic preservation and 
real estate policy utilization, guidance, and reporting, as well as 
facilities management systems. 

Office/Sub-offices: 1. Office of Project Management; 
Responsibilities: The office provides comprehensive management of the 
Smithsonian's facilities revitalization and construction. It develops 
preliminary project scopes, schedules, and budgets; monitors, directs, 
and reports on the updated scope budget and schedule of individual 
projects and major construction; and coordinates the efforts of 
stakeholders, designers and construction execution on multiple 
projects. 

Office/Sub-offices: 2. Office of Facilities Planning and Resources; 
Responsibilities: The office serves as the focal point for facilities 
master planning and space-management issues and efforts. It advises 
management on architectural history and historic preservation, conducts 
historic preservation reviews, comprehensive facilities master planning 
studies, and space utilization studies, space inventories and analysis 
of these issues. It also coordinates with government and community 
groups on facilities planning, space management, and preservation 
matters and provides financial and administrative services regarding 
facilities issues. 

Office/Sub-offices: 3. Office of Engineering, Design and Construction; 
Responsibilities: With oversight from the Office of Project Management, 
this office is responsible for project design and construction 
oversight for all new construction and revitalization contracts. 

Office/Sub-offices: 3.1 Engineering and Design Division; 
Responsibilities: The office administers architectural and engineering 
services for facility construction, revitalization and repair that 
include developing design scopes for projects. It oversees contracted 
design efforts, provides limited in-house architectural and engineering 
design services, and is responsible to provide and ensure thorough 
project reviews and code compliance. 

Office/Sub-offices: 3.2 Construction Management Division; 
Responsibilities: The office provides construction administration 
services and operates field offices (resident engineer) at large 
project sites. It directs and oversees contract services of 
construction contractors and construction managers and is responsible 
for contract change order negotiations. 

Office/Sub-offices: 3.3 Cost Engineering Division; 
Responsibilities: The office provides construction cost estimates for 
projects at the project development stage. It provides revised 
construction cost estimates throughout the project life cycle to 
reflect changes and current market conditions. 

Office/Sub-offices: 3.4 Geo-Spatial Conversions; 
Responsibilities: The office consolidates and maintains a comprehensive 
Geographical Information System database that includes computer-aided 
drawings for Smithsonian facilities. It provides a central archive for 
facility documentation, project files, drawings, specifications, 
operations and maintenance, equipment and shop drawings files, as-built 
drawings and an improved as-built drawing capability for facilities 
management and project development. 

Office/Sub-offices: 4. Office of Facilities Reliability; 
Responsibilities: The office provides strategic planning and oversight 
to facilities operations and maintenance efforts. Its goal is to reduce 
breakdowns and increase planned maintenance. It runs the Reliability 
Centered Maintenance program utilizing predictive testing and 
inspection tools to manage facility equipment. It develops tasks and 
processes then monitors work efforts, collects and analyzes data and 
metrics of the maintenance programs, and adjusts the operation and 
maintenance process to gain further efficiencies. It also purchases 
utilities, manages agency-wide service contracts, operates building 
automation services, and repairs large equipment in central shops. It 
uses both in-house and contractor personnel to accomplish its 
objectives. It is directly involved with new facility design inputs, 
new system start-ups and commissioning efforts. 

Office/Sub-offices: 5. Office of Facilities Management; 
Responsibilities: The office performs day-to-day facilities maintenance 
services, including preventive maintenance, janitorial and grounds 
maintenance; transportation and mail delivery services, building 
management services for leased facilities; landscape services and is 
involved in new facility system start-ups upon completion. It 
accomplishes its work through in-house; and contracted services. 
Currently comprised of seven zones, due to its visibility it plays a 
critical role as ambassadors for OFEO. 

Office/Sub-offices: 6. Office of Protection Services; 
Responsibilities: The office ensures the safety and security of staff, 
visitors, properties, and collections through the use of security 
forces, technology, and facility design and construction. 

Office/Sub-offices: 7. Office of Safety and Environmental Management; 
Responsibilities: The office ensures the Smithsonian provides safe 
spaces for employees and visitors, oversees fire prevention and 
protection, industrial hygiene and occupational health, environmental 
management, and radiation safety. Conducts all safety, environmental, 
industrial hygiene, and occupational health compliance audits for the 
Institution. 

Office/Sub-offices: 8. Smithsonian Tropical Research Institute; 
Responsibilities: The office is responsible for both capital projects 
and operations, and minor repair and maintenance. 

Source: Smithsonian Institution. 

[End of table]

[End of section]

Appendix IV: Smithsonian's Efforts to Implement Leading Practices in 
Capital Decision-Making: 

Principles and practices: I. Integrate organizational goals into the 
capital decision-making process. 

Principles and practices: 1. Conduct comprehensive assessment of needs 
to meet results-oriented goals and objectives; 
Smithsonian's efforts: Secretary's Strategic Plan provides goals and 
specific objectives for all areas of the Institution. Annually, OFEO 
aligns its goals with the strategic plan. These goals include targets 
for percentage completion on particular projects, overall program 
performance, and targets for cost growth. 

Principles and practices: 2. Identify current capabilities, including 
the use of an inventory of assets and their condition, and determine if 
there is a gap between current and needed capabilities; 
Smithsonian's efforts: In September 2001, OFEO did a study Critical 
Assessment and Improvement Objectives, which provides an inventory of 
assets and a comprehensive list of all the studies, design, and 
construction to that date, along with a cost estimate for outstanding 
work and the basis for the estimates. Every 2 to 3 years facility 
assessments--in-depth condition reviews of a facility--are performed by 
the Facility Assessment Branch. Zone Managers consolidate and advocate 
all facility requirements, including noncapital minor repairs and 
maintenance. 

Principles and practices: 3. Decide how best to meet the gap by 
identifying and evaluating alternative approaches (including noncapital 
approaches); 
Smithsonian's efforts: OFEO has engaged in several noncapital 
approaches designed to maximize the buying power of the funding 
received. Among these approaches is the use of continuing contract 
authority. This permits multiyear funded major revitalization projects, 
such as the restoration of the Patent Office Building, to proceed in a 
measured way in partnership with the contractor, so that current year 
funds can be efficiently used, while not holding up the project until 
all funding is received. OFEO employees at all levels are members and 
active participants in both the Federal Facilities Council and the 
Construction Industry Institute. Both organizations promote best 
practices such as comprehensive preproject planning, value engineering 
and constructability reviews that ensure the best use of available 
dollars through project team alignment and technical innovation and 
flexibility. 

Principles and practices: II. Evaluate and select capital assets using 
an investment approach. 

Principles and practices: 4. Establish review and approval framework 
supported by analyses; 
Smithsonian's efforts: OFEO's Office of Project Management leads the 
annual formulation and revision of the Smithsonian's capital design and 
construction program. The process of evaluation and selection of 
projects begins with consultation with all Smithsonian Institution 
units, in conjunction with the Office of Facilities Reliability and the 
Office of Facilities Management. The staff of the Smithsonian units and 
the staff of the Offices of the Deputy Secretary, the Under Secretary 
for Science and the Under Secretary for Art participate in this 
process. Projects are rated and ranked according to criteria based on 
health and safety concerns first, code compliance and security, and the 
need for repairs and operational efficiency. 

Principles and practices: 5. Rank and select projects based on 
established criteria; 
Smithsonian's efforts: Once the cross- functional teams working at each 
facility rate and rank their projects by priority, type of work and 
fiscal year, the plan is presented to the Smithsonian's Capital 
Planning Board. The board under the direction of the Chief Financial 
Officer meets throughout the year to consider capital requests and 
balance needs of the design and construction program against other 
capital investments. 

Principles and practices: 6. Develop a long-term capital plan that 
defines capital asset decisions; 
Smithsonian's efforts: A 5-year Facilities Capital Program Summary for 
funding is developed. The combined efforts of OFEO and the Capital 
Planning Board ensure that the capital program receives wide-ranging 
review and approval from all areas of the Smithsonian. The Audit and 
Review Committee of the Board of Regents reviews the institution's 
finances and the Board of Regents authorizes the submission of the 
budget, which includes the 5-year plan to Congress. 

Principles and practices: III. Balance budgetary control and managerial 
flexibility when funding capital projects. 

Principles and practices: 7. Budget for projects in useful segments; 
Smithsonian's efforts: As previously mentioned, continuing contract 
authority is used for multiyear funded major revitalization, which 
allows for phased funding of projects and allows a project to proceed 
in a measured way in partnership with the contractor. This process is 
also used for new construction such as the recently completed National 
Museum of the American Indian on the Mall. The vast majority of the 
Smithsonian's Capital projects are under $1 million in cost, so the 
need for phased work is only present in the very largest capital 
projects. A goal of OFEO, given adequate resources in the Facilities 
Planning and Design account, is to have designs funded 2 years in 
advance of project execution, and to have at least 35 percent of the 
design complete prior to final funding decisions. 

Principles and practices: 8. Consider innovative approaches to full up- 
front funding; 
Smithsonian's efforts: Within the recent environment of constrained 
funding for the capital program, the Smithsonian has engaged in 
unprecedented fund-raising for design and construction. Fully one third 
of the total project costs of the National Museum of the American 
Indian on the Mall come from privately raised funds, as does the entire 
construction of the National Air and Space Museum's Steven F. Udvar-
Hazy Center. This kind of partnership with the private sector will 
continue to be an important source of support in the completion of the 
Patent Office Building revitalization, the overhaul of the major 
exhibitions halls at the National Museum of American History, and the 
future construction of the National Museum of African American History 
and Culture. 

Principles and practices: IV. Use project management techniques to 
optimize project success. 

Principles and practices: 9. Monitor project performance and establish 
incentives for accountability; 
Smithsonian's efforts: Monitoring project performance is the 
fundamental responsibility of OFEO's project, design and construction 
managers. The requirements for project schedules, cost estimates, 
milestone submissions and regular project meetings are outlined fully 
in the Project Management Handbook. In addition, on the largest 
projects, monthly executive meetings with museum directors and the OFEO 
director are held, as well as quarterly oversight meetings with the 
deputy secretary/chief operating officer and chief financial officer. 
There are two primary incentives for accountability: project status is 
reported regularly to individuals outside the project authority, as 
noted above; and, project managers' performance evaluations are based 
on qualitative and quantitative execution of their individual capital 
programs. 

Principles and practices: 10. Use cross-functional teams to plan for 
and manage projects; 
Smithsonian's efforts: OFEO project teams consist of a lead project 
manager, design manager, resident engineer, client representatives, and 
contracting specialists and, during design reviews, representatives of 
the Offices of Safety and Environmental Management, Protection 
Services, Facilities Planning and Resources, Information Technology and 
others. Also see items II. 4. and IV. 9. above. 

Principles and practices: V. Evaluate results and incorporate lessons 
learned into the decision-making process. 

Principles and practices: 11. Evaluate results to determine if 
organizationwide goals have been met; 
Smithsonian's efforts: Performance metrics are a monthly feature of 
project management in OFEO. Measures of overall capital performance, 
monthly contract obligations, time and cost growth on the largest 
projects and preproject planning are included within the larger program 
of OFEO performance metrics. The preproject planning reporting is 
particularly helpful in measuring customer satisfaction, as it monitors 
the team's alignment on scope throughout the life of the project, while 
there is still time to do something about it if disagreements occur. 

Principles and practices: 12. Evaluate the decision-making process: 
reappraise and update to ensure that goals are met; 
Smithsonian's efforts: Documents such as the Project Management 
Handbook and the SD- 410 are only useful if they are up-to-date and 
used. Currently, both documents are being revised. Both revised 
documents are in the review process and will be incorporated into OFEO 
standard practices. External evaluation of OFEO projects is a useful 
tool for the largest and most complex projects. Within the past 2 
years, the Smithsonian's Inspector General's office has audited three 
projects and the Smithsonian has adopted the recommendations made. Also 
sharing lessons learned outside the organization is a valuable means of 
achieving feedback and OFEO staff has participated in events for 
numerous professional organizations such as the Federal Facilities 
Counsel and the Construction Industry Institute. 

Source: Smithsonian Institution. 

[End of table]

[End of section]

Appendix V: Facility Revitalization and Construction Project Code 
Assignment Matrix: 

Project type: Condition Level: I - Catastrophic; 
Project type: Revitalization and renewal: A: Shell/System failure: 
Priority code; (PC) - 1; 
Project type: Revitalization and renewal: B: Code compliance/Security: 
PC - 1; 
Project type: Revitalization and renewal: C: Nonroutine Capital 
Repairs: PC - 2; 
Project type: Revitalization and renewal: D: Energy/Operational 
efficiency: PC - 2; 
Construction: E: Alterations and modifications: Not applicable. 

Project type: Condition Level: II - Critical; 
Project type: Revitalization and renewal: A: Shell/System failure: PC - 
2; 
Project type: Revitalization and renewal: B: Code compliance/Security: 
PC - 2; 
Project type: Revitalization and renewal: C: Nonroutine Capital 
Repairs: PC - 3; 
Project type: Revitalization and renewal: D: Energy/Operational 
efficiency: PC - 3; 
Construction: E: Alterations and modifications: PC - 3. 

Project type: Condition Level: III - Routine; 
Project type: Revitalization and renewal: A: Shell/System failure: PC - 
3; 
Project type: Revitalization and renewal: B: Code compliance/Security: 
PC - 3; 
Project type: Revitalization and renewal: C: Nonroutine Capital 
Repairs: PC - 4; 
Project type: Revitalization and renewal: D: Energy/Operational 
efficiency: PC - 4; 
Construction: E: Alterations and modifications: PC - 4. 

Project type: Condition Level: IV - Can defer; 
Project type: Revitalization and renewal: A: Shell/System failure: PC - 
5; 
Project type: Revitalization and renewal: B: Code compliance/Security: 
PC - 5; 
Project type: Revitalization and renewal: C: Nonroutine Capital 
Repairs: PC - 5; 
Project type: Revitalization and renewal: D: Energy/Operational 
efficiency: PC - 5; 
Construction: E: Alterations and modifications: PC - 5. 

Source: Smithsonian Institution. 

Notes: Priority codes (PC) PC-1 equals the budget year. PC-2 equals the 
budget year plus 1 year. PC-3 equals the budget year plus 2 years. PC- 
4 equals the budget year plus 3 years. PC-5 equals the budget year plus 
4 years. 

Condition level: 

Catastrophic - Significant projects requiring immediate funding in 
order to correct severe safety hazards, active failures, and prevent 
the loss of facilities. Asset Impact: Detrimental or irreversible 
failure, immediate implementation. 

Critical - High priority projects requiring funding in the next fiscal 
year to avoid failure or correct serious safety/security deficiencies. 
Asset/Program Impact: Imminent failure, program begins in 1 to 3 years. 

Routine - Predicted work that needs funding within 4 years. Asset/ 
Program Impact: Moderate risk, program begins in 4 to 5 years. 

Can defer - Work that can be deferred for 5 years. Asset/Program 
Impact: Negligible risk, program begins within 5+ years. 

Project type examples: 

Shell/System failure - Roof leaks, building piping leaks, and utility 
system and equipment failures. 

Code compliance/Security - Replacement/upgrade/modification to fire 
detection/suppression systems, life safety/accessibility systems and 
security systems, and building modifications. 

Nonroutine capital repairs - One-time repair work to correct 
significant problem (i.e., all the doors in a building or a single HVAC 
component). 

Energy/Operational efficiency - Projects with a 7-year cost-effective 
payback period. 

Alterations and modification - Approved master plan projects and work 
to sustain existing or changing missions. 

[End of table]

[End of section]

Appendix VI: Flow Chart of the Prioritization Decision-Making Process 
for Minor Repair and Maintenance: 

[See PDF for image] 

[End of figure] 

[End of section]

Appendix VII: Scope and Methodology: 

To determine how the condition of the Smithsonian's facilities affects 
public and scientific access to the collections, and the collections 
themselves, we toured 11 facilities--the Arts and Industries Building, 
the Smithsonian Administration Building, the Garber Center, the 
Cultural Resource Center, the National Air and Space Museum, the 
National Museums of American History and Natural History, National 
Zoological Park, the Renwick Gallery, the Smithsonian Environmental 
Research Center, and the Victor Building. We visited these facilities 
because the Smithsonian identified them as having the most serious 
problems. The Garber Center has about 40 buildings, the National 
Zoological Park has in excess of 40 buildings and the Smithsonian 
Environmental Research Center has in excess of 30 buildings. We 
interviewed OFEO zone mangers and building mangers for the facilities 
we visited, and contacted directors of other Smithsonian facilities, 
both local and nationwide, asking them to identify their problems. 

To determine how the Smithsonian has changed its facilities management 
and prioritizes its revitalization, construction, and minor repair and 
maintenance programs, we reviewed a variety of documents including the 
National Academy of Public Administration's (NAPA) 2001 report on the 
Smithsonian, the facility organizational chart, Facilities Project 
Management Handbook, drafts of the Operation and Maintenance Handbook, 
Construction Procedural Guidelines, and Cost Management Guide (for 
estimating costs), Facility Revitalization and Construction Project 
Code Assignment Matrix, the Flow Chart of the Prioritization Decision- 
Making Process for Minor Repairs and Maintenance, minutes of the 
Capital Planning Board meetings and the Smithsonian Regents meetings 
for 2002 through 2004, the National Research Council's Committing to 
the Cost of Ownership: Maintenance and Repair of Buildings, Federal 
Facilities Council's Budgeting for Facilites Maintenance and Repair 
Activities and the Construction Industry Institute Best Practices 
Guide. We also interviewed the director and chief of staff of the 
Office of Facilities Engineering and Operations (OFEO) and the eight 
heads of the offices making up OFEO, the staff responsible for 
prioritizing both capital projects and minor repair and maintenance, 
and the head of the Smithsonian's Capital Planning Board. 

To determine the cost and status of the Smithsonian's major (more than 
$5 million) construction and revitalization projects and minor repair 
and maintenance projects, we toured 11 facilities (as previously 
identified) to view the Smithsonian's facility problems; we reviewed 
the NAPA report, three Smithsonian Inspector General reports on the 
construction of the National Museum of the American Indian, the Patent 
Office Building, and the Steven F. Udvar-Hazy Center, the 2006 to 2010 
Facility Capital Program Summary, minutes of the Capital Planning Board 
meetings and the Smithsonian Board of Regents meetings for 2002 through 
2004, individual project operational reports, monthly executive 
reports, contractor progress reports, facility assessments, and other 
appropriate reports; and interviewed the OFEO director, the directors 
of all OFEO offices, and project executives and project managers 
responsible for oversight of projects. OFEO also provided cost 
estimates for revitalization and construction projects and the minor 
repair and maintenance program. We assessed the reliability of the 
estimates by reviewing the processes used to determine both 
revitalization and construction estimates, and minor repair and 
maintenance estimates. As noted in the main body of this report, most 
of the revitalization and construction estimates are "order-of- 
magnitude" estimates that can vary by plus or minus 30 to 50 percent. 
Because such variation is typical for these types of cost estimates and 
our objective is to use these figures to provide the estimated costs of 
the Smithsonian's facilities projects, we believe that these data are 
reliable for the purposes of our report. 

To determine under what basic authorities the Smithsonian operates its 
revitalization, construction, and minor repair and maintenance 
programs, and how the Smithsonian uses its federal appropriations and 
trust monies to fund these programs, we researched the Smithsonian's 
enabling legislation; the statutes under which it currently operates, 
including appropriations acts and numerous statutes authorizing 
Smithsonian Institution facilities from the 1950s; congressional budget 
requests; fiscal year 2002, 2003, and 2004 audited financial statements 
and management letters;[Footnote 71] and project operational review 
reports. We interviewed the chief financial officer, assistant general 
counsel, and other appropriate staff. We conducted our work between 
April 2004 and April 2005 in accordance with generally accepted 
government auditing standards. 

[End of section]

Appendix VIII: Comments from the Smithsonian Institution: 

Smithsonian Institution:

Lawrence M. Small: 
Secretary:

April 7, 2005:

Mr. David M. Walker, Comptroller General: 
Government Accountability Office:
Office of the Comptroller General: 
441 G Street, NW:
Washington, DC 20548:

Dear Mr. Walker:

Thank you for your report entitled, "Facilities Management 
Reorganization is Progressing, but Funding Remains a Challenge."

This report validates the Smithsonian Institution's longstanding 
contention that its physical facilities are in seriously deteriorated 
condition. While the Institution was established for the "increase and 
diffusion of knowledge," safe, well-maintained, and efficiently- 
operated facilities provide the critical underpinning for the 
Smithsonian to be successful. The estimated $2.3 billion in costs for 
revitalization, maintenance, and construction represents a severe 
obstacle to achieving the Institution's 159-year-old mission.

Several years ago, the National Academy of Public Administration 
(NAPA), at the behest of the Congress, conducted "A Study of the 
Smithsonian's Repair, Restoration and Alteration of Facilities Program" 
that confirmed the Institution's requirement for a billion and a half 
dollars worth of revitalization, spread over a ten-year period. As a 
result of more accurate information and the addition of new facilities, 
that amount has now grown to $2.3 billion. NAPA also recommended a 
number of managerial changes to improve our ability to manage 
effectively an increased capital program and maintain better the 
existing infrastructure inventory. We have paid close attention to 
these recommendations and followed NAPA's advice. Today, we are poised 
to more effectively manage every scarce dollar we are appropriated to 
revitalize and maintain our physical plant. We are pleased the 
Government Accountability Office has recognized our progress.

We acknowledge the seriousness and magnitude of our failing 
infrastructure problem that to date has resulted in the closure of two 
major historic buildings, one of which (the Patent Office Building) is 
undergoing extensive revitalization. The second, the Arts and 
Industries Building, built in 1879-81, has failed to a point that the 
Smithsonian Regents have directed that we vacate it as soon as 
possible. We are doing this now.

The ultimate issue, as you have aptly described it, is one of securing 
the funding to resolve the $2.3 billion facilities infrastructure 
problem. With little hope of getting private funding for the basic 
needs of revitalizing infrastructure and sustaining it, we continue to 
look to the Administration and the Congress for help. It is our hope 
this report will help underscore the Smithsonian's critical need and 
assure all that every scarce resource provided will be well spent to 
arrest deterioration and bring the Institution back to its deserved 
prominence as the principal repository of the artifacts of our Nation's 
history and a place to be enjoyed by the over 20 million visitors who 
come annually to tour our museums.

All the best,

Signed by: 

Lawrence M. Small: 

[End of section]

Appendix IX: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

John Finedore, (202) 512-6248; 
Tom Keightley, (202) 512-5225: 

Staff Acknowledgments: 

In addition to those named above, Bess Eisenstadt, Susan Michal-Smith, 
Faye Morrison, and Lisa Wright-Solomon made key contributions to this 
report. 

(543096): 

FOOTNOTES

[1] The roofs of the B&O Railroad Museum in Baltimore, Maryland, and 
the O Street Market in Washington, D.C., collapsed under the weight of 
a heavy snowfall in February 2003. 

[2] In addition, the Smithsonian has approximately 166.3 million 
archival items, such as 50,000 cubic feet of paper documents and 7 
million photographs, as of 2003. 

[3] Minor repair and maintenance includes the upkeep of property and 
equipment necessary to realize the originally anticipated useful life 
of a fixed asset. It does not materially prolong the design life of 
property or equipment, or add to the asset's value. 

[4] This number includes estimates for projects that have not been 
through a design phase. According to the Construction Industry 
Institute, these types of estimates can vary by plus or minus 30 to 50 
percent. Therefore, the Smithsonian's overall $2.3 billion estimate 
should be viewed only as an approximation based on the best current 
information. 

[5] GAO, Executive Guide: Leading Practices in Capital Decision-Making, 
GAO/AIMD-99-32 (Washington, D.C.: December 1998.) 

[6] NAPA's estimate did not cover new construction because the Congress 
did not ask NAPA to review the Smithsonian's construction program. 

[7] The founding Council of the Smithsonian's National Museum of 
African American History and Culture held its first meeting on February 
8, 2005, and adopted bylaws and discussed possible collections for the 
Museum. Building costs will be equally divided between congressional 
appropriations and privately raised funds. 

[8] The $904 million is based on the Smithsonian's audited financial 
statements for fiscal year 2004. 

[9] A trust is a fiduciary relationship involving a right of property 
held by the trustee for the benefit of another. 

[10] The specific composition of the board has changed somewhat since 
1846 by law, but it is still a mixture of government and private 
individuals. At present, the board is composed of the Chief Justice of 
the United States, the Vice President, three senators appointed by the 
President of the Senate, three representatives appointed by the Speaker 
of the House, and nine citizens appointed by Joint Resolution of 
Congress--two from the District of Columbia and seven from the states. 

[11] According to Smithsonian officials, these classifications increase 
the difficulty of maintaining buildings because they involve federal 
requirements for revitalization and maintenance. The National Historic 
Preservation Act (NHPA) of 1966 outlines specific actions required of 
federal agencies (of which the Smithsonian is considered to be for the 
purposes of NHPA) to protect cultural resources listed, or eligible for 
listing, in the National Register of Historic Places. The standards 
require owners to maintain the original structure, fabric, and 
character of the site (both interior and exterior) when making 
additions or upgrades. 

[12] The construction of the Steven F. Udvar-Hazy Center was divided 
into two phases to allow for the Smithsonian to raise the private 
funding needed for the project. 

[13] Several bills were introduced in the 108TH Congress to study the 
creation of a National Museum of the American Latino Community. These 
bills were not enacted. 

[14] Report of the Commission on the Future of the Smithsonian 
Institution, 1995. 

[15] The Secretary testified before the U.S. Senate Committee on Rules 
and Administration on June 27, 2000. 

[16] H.R. Rep. No. 106-914, at 183-184 (2000). 

[17] National Academy of Public Administration, A Study of the 
Smithsonian Institution's Repair, Restoration and Alteration of 
Facilities Program, (Washington, D.C.: July 2001). This report examined 
repair, renovation, and alteration but did not examine new 
construction. 

[18] Such estimates are based on feasibility studies. Order-of- 
magnitude estimates can vary by plus or minus 30 to 50 percent. 

[19] GAO, High-Risk Series: Federal Real Property, GAO-03-122 
(Washington, D.C.: January 2003), pp. 2, 15, 25. 

[20] The Patent Office Building was acquired by the Smithsonian in 1958 
after escaping proposed demolition. This historic "Greek Revival" 
building was constructed in several stages and completed in 1867. 

[21] Museums and Facilities: Critical Assessment and Improvement 
Objectives, September 2001. 

[22] A revitalization or construction project consists of three main 
steps: (1) project planning and development, which covers the initial 
project identification, scope and cost development, prioritization, and 
any project steps up to design; (2) design, which includes developing 
the design criteria package, obtaining architectural and engineering 
services, and preparing, reviewing and approving the final design; and 
(3) construction, which includes bid packages, a request for technical 
proposals, procurement of a construction contract, and contract 
administration and management procedures. 

[23] Reliability-centered maintenance is a maintenance strategy that 
logically incorporates the optimum mix of reactive, preventive, 
predictive testing and inspection, and proactive maintenance practices. 

[24] The merger is taking place now but will not be reflected in the 
budget until fiscal year 2006. 

[25] The Construction Industry Institute is a research organization 
composed of construction contractors and owners seeking to improve the 
construction and capital investment process. The institute has 
identified 14 best practices, 8 of which--alignment, benchmarking and 
metrics, change management, disputes prevention and resolution, 
implementation of products, partnering, preproject planning, and team 
building--are aimed at owners such as the Smithsonian and 6 of which 
are aimed principally at contractors and manufacturers. 

[26] This is a checklist of 64 scope definition elements in a 1,000- 
point scoring system; each element is weighted on the basis of its 
relative importance to other elements. The overall rating determines 
whether the project should proceed through the budget cycle, allowing 
the Smithsonian to make better investment decisions. 

[27] This is a tool for measuring how well an estimate has been 
prepared for a particular project. It gives a score based on rating 
each of 45 elements that can have a significant impact on an estimate. 
It provides a reality check on the estimate for better decision making. 

[28] The Federal Facilities Council's purpose is to promote continuing 
cooperation among sponsoring federal agencies, and among the agencies 
and other elements of the building community in order to advance 
building science and technology--particularly with regard to the 
design, construction, acquisition, evaluation, and operation of federal 
facilities. The Smithsonian Institution is a sponsoring entity of the 
Federal Facilities Council. 

[29] GAO/AIMD-99-32 (Washington, D.C.: December 1998.)

[30] The Smithsonian's Capital Planning Board is made up of the chief 
financial officer (chairperson); deputy secretary and chief operating 
officer; under secretaries for Science, and Art; chief executive 
officer of Business Ventures; general counsel; director of Policy and 
Analysis; chief information officer; and OFEO director. 

[31] The buyout was available to all Smithsonian employees but was 
mostly taken by individuals already eligible for retirement or early 
retirement, according to a Smithsonian official. 

[32] The 19 positions include 1 doctor for the employee health clinic, 
1 real estate specialist, and 17 operation and maintenance positions. 

[33] This range is calculated on a weighted average based on the four 
types of estimates (1) order of magnitude, (2) factored, (3) control 
and (4) detailed/definitive. See the paragraph following table 2 for a 
discussion of this estimating process. 

[34] The purpose of stair pressurization is to inject fresh air into 
the stairwells during a fire scenario and provide a positive pressure 
differential in relation to adjoining spaces. In other words, the 
positive pressure created will prevent smoke from entering the 
stairwell as people enter it. 

[35] NAPA's estimate did not cover new construction because the 
Congress did not ask NAPA to review the Smithsonian's construction 
program. 

[36] Museums and Facilities: Critical Assessment and Improvement 
Objectives, September 2001. 

[37] The CII defines four classes of cost estimates: (1) "order of 
magnitude," which is based on feasibility cost/capacity curves and has 
an accuracy range of plus or minus 30 to 50 percent; (2) "factored," 
which applies major equipment factors for costs and has an accuracy 
range of plus or minus 25 to 30 percent; (3) "control," which is based 
on quantities from mechanical, electrical, and civil engineers' 
drawings and has an accuracy range of plus or minus 10 to 15 percent; 
and (4) "detailed/definitive," which is based on detailed drawings and 
has an accuracy range of plus or minus less than 10 percent. 

[38] Planning and project development are the initial stage and covers 
initial project identification, scope and cost development, 
prioritization and any project steps up to design. 

[39] According to the National Research Council, the appropriate level 
of spending for maintenance is 2 to 4 percent of a facility's current 
replacement value. This range is most valid for estimates developed for 
a large inventory of buildings for periods of several years, such as 
the Smithsonian has done. The range covers current requirements only 
and does not provide for work that was deferred in the past. The 
Federal Facilities Council suggests that one way to estimate the costs 
of reducing the inventory of deferred maintenance is to increase the 
range by some arbitrary percentage. The Smithsonian has increased its 
range by 2 percent to cover the deferred maintenance. As a result, the 
range now extends to 6 percent. For example, a condition index of "1" 
equates to 6 percent of a building's current replacement value, and a 
condition index of "5" equates to 2 percent of a building's current 
replacement value. Also, if the current replacement value per square 
foot exceeds $300, in order to be conservative, Facilities Reliability 
applies only one-fifth of the percentage allowance for replacement 
value of $300 per square foot. For example, if the percentage allowance 
is 5 percent, Facilities Reliability uses only 1 percent of the 
allowance for amounts over $300 a square foot. 

[40] We counted two of the projects, Asia Trail I and Asia Trail II, as 
being within budget because their total budget did not change but one 
budget increased and one budget decreased because part of the Asia 
Trail II project was moved to Asia Trail I. 

[41] This estimate was prepared by OFEO's cost-estimating section. 

[42] Contract period was extended from a planned period of 9 to 18 
months to 24 to 30 months. 

[43] Funding requests were moved from fiscal years 2005 and 2006 to 
fiscal years 2005, 2006, and 2007. 

[44] Smithsonian Institution Office of the Inspector General, Report on 
Project Management of the National Museum of the American Indian Mall 
Museum (Washington, D.C.: Sept. 30, 2002), and Report on Project 
Management of the Steven F. Udvar-Hazy Center (Washington, D.C.: July 
31, 2003). 

[45] Smithsonian Institution Office of the Inspector General, Project 
Management Review: Patent Office Building Renovation Project 
(Washington, D.C; Mar. 31, 2003). 

[46] High Risk Series: Federal Real Property, p. 46. 

[47] An Act to Authorize and Enable the President to Assert and 
Prosecute with Effect, the Claim of the United States to the Legacy 
Bequeathed to Them by James Smithson, Late of London, Deceased, to 
Found at Washington, Under the Name of the Smithsonian Institution, an 
Establishment for the Increase and Diffusion of Knowledge Among Men. 

[48] An Act to Establish the Smithsonian Institution for the Increase 
and Diffusion of Knowledge Among Men. 

[49] The permanent provisions of the Act of 1846 were reenacted in the 
Revised Statutes of the United States in Force on the First Day of 
December, One Thousand Eight Hundred and Seventy-Three (1875) as §§ 
5579-5594. Current statutes relating to the Smithsonian Institution are 
located in 20 U.S.C. §§ 41-70. 

[50] For example, see Consolidated Appropriations Act for Fiscal Year 
2005, P.L. 108-447, 118 Stat. 2809, at 3088 and 3089 (2004); Department 
of Interior Appropriations Act for Fiscal Year 2004, P.L.108-108, 117 
Stat. 1241, at 1297 and 1298 (2003); and Consolidated Appropriations 
Act for Fiscal Year 2003, P.L. 108-7, 117 Stat. 11, at 265 and 266 
(2003). 

[51] Act of June 28, 1955, Ch. 201, 69 Stat. 189. 

[52] P.L. 85-935, 72 Stat. 1794 (1958). 

[53] P.L. 89-788, 80 Stat. 1403 (1966). 

[54] P.L. 94-98, 89 Stat. 480 (1975). 

[55] P.L. 95-569, 92 Stat. 2444 (1978). 

[56] P.L. 96-36, 93 Stat. 94 (1979). 

[57] P.L. 97-203, 96 Stat. 129 (1982). 

[58] P.L. 98-73, 97 Stat. 406 (1983). 

[59] P.L. 98-523, 98 Stat. 2433 (1984). 

[60] P.L. 99-423, 100 Stat. 963 (1986). 

[61] P.L. 99-617, 100 Stat. 3488 (1986). 

[62] P.L. 101-185, 103 Stat. 1336 (1989). 

[63] P.L. 101-455, 104 Stat. 1067 (1990). 

[64] P.L. 103-57, 107 Stat. 279 (1993). 

[65] P.L. 103-151, 107 Stat. 1515 (1993). 

[66] P.L. 104-222, 110 Stat. 3025 (1996). 

[67] P.L. 106-383, 114 Stat. 1459 (2000). 

[68] P.L. 108-72, 117 Stat. 888 (2003). 

[69] P.L. 108-184, 117 Stat. 2676 (2003). 

[70] P.L. 108-331, 118 Stat. 1281 (2004). 

[71] The auditor expressed unqualified opinions on the fiscal year 
2002, 2003, and 2004 financial statements. They issued management 
letters with suggested improvements that the Smithsonian agreed to 
implement. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office

441 G Street NW, Room LM

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm

E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director,

NelliganJ@gao.gov

(202) 512-4800

U.S. Government Accountability Office,

441 G Street NW, Room 7149

Washington, D.C. 20548: