This is the accessible text file for GAO report number GAO-04-415 
entitled 'Nuclear Regulation: NRC Needs to More Aggressively and 
Comprehensively Resolve Issues Related to the Davis-Besse Nuclear Power 
Plant's Shutdown' which was released on May 18, 2004.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to Congressional Requesters: 

May 2004: 

NUCLEAR REGULATION: 

NRC Needs to More Aggressively and Comprehensively Resolve Issues 
Related to the Davis-Besse Nuclear Power Plant's Shutdown: 

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-04-415]: 

GAO Highlights: 

Highlights of GAO-04-415, a report to congressional requesters 

Why GAO Did This Study: 

In March 2002, the most serious safety issue confronting the nation’s 
commercial nuclear power industry since Three Mile Island in 1979 was 
identified at the Davis-Besse plant in Ohio. After the Nuclear 
Regulatory Commission (NRC) allowed Davis-Besse to delay shutting down 
to inspect its reactor vessel for cracked tubing, the plant found that 
leakage from these tubes had caused extensive corrosion on the vessel 
head—a vital barrier preventing a radioactive release. GAO determined 
(1) why NRC did not identify and prevent the corrosion, (2) whether the 
process NRC used in deciding to delay the shutdown was credible, and 
(3) whether NRC is taking sufficient action in the wake of the incident 
to prevent similar problems from developing at other plants.

What GAO Found: 

NRC should have but did not identify or prevent the corrosion at Davis-
Besse because its oversight did not generate accurate information on 
plant conditions. NRC inspectors were aware of indications of leaking 
tubes and corrosion; however, the inspectors did not recognize the 
indications’ importance and did not fully communicate information about 
them. NRC also considered FirstEnergy—Davis-Besse’s owner—a good 
performer, which resulted in fewer NRC inspections and questions about 
plant conditions. NRC was aware of the potential for cracked tubes and 
corrosion at plants like Davis-Besse but did not view them as an 
immediate concern. Thus, NRC did not modify its inspections to identify 
these conditions. 

NRC’s process for deciding to allow Davis-Besse to delay its shutdown 
lacks credibility. Because NRC had no guidance specifically for making 
a decision on whether a plant should shut down, it used guidance for 
deciding whether a plant should be allowed to modify its operating 
license. NRC did not always follow this guidance and generally did not 
document how it applied the guidance. The risk estimate NRC used to 
help decide whether the plant should shut down was also flawed and 
underestimated the amount of risk that Davis-Besse posed. Further, even 
though underestimated, the estimate still exceeded risk levels 
generally accepted by the agency. 

NRC has taken several significant actions to help prevent reactor 
vessel corrosion from recurring at nuclear power plants. For example, 
NRC has required more extensive vessel examinations and augmented 
inspector training. However, NRC has not yet completed all of its 
planned actions and, more importantly, has no plans to address three 
systemic weaknesses underscored by the incident. Specifically, NRC has 
proposed no actions to help it better (1) identify early indications of 
deteriorating safety conditions at plants, (2) decide whether to shut 
down a plant, or (3) monitor actions taken in response to incidents at 
plants. Both NRC and GAO had previously identified problems in NRC 
programs that contributed to the Davis-Besse incident, yet these 
problems continue to persist.

What GAO Recommends: 

Because the nation’s nuclear power plants are aging, GAO is 
recommending that NRC take more aggressive actions to mitigate the risk 
of serious safety problems occurring at Davis-Besse and other nuclear 
power plants. 

NRC disagreed with two of the report’s five recommendations—that it 
develop (1) additional means to better identify safety problems early 
and (2) guidance for making decisions whether to shut down a plant. GAO 
continues to believe these recommendations are appropriate and should 
be implemented.

www.gao.gov/cgi-bin/getrpt?GAO-04-415.

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Jim Wells at (202) 
512-3841 or wellsj@gao.gov.

[End of section]

Contents: 

Letter: 

Scope and Methodology: 

Results in Brief: 

Background: 

NRC's Actions to Oversee Davis-Besse Did Not Provide an Accurate 
Assessment of Safety at the Plant: 

NRC's Process for Deciding Whether to Allow a Delayed Davis-Besse 
Shutdown Lacked Credibility: 

NRC Has Made Progress in Implementing Recommended Changes, but Is Not 
Addressing Important Systemic Issues: 

Conclusions: 

Recommendations for Executive Action: 

Agency Comments and Our Evaluation: 

Appendixes: 

Appendix I: Time Line Relating Significant Events of Interest: 

Appendix II: Analysis of the Nuclear Regulatory Commission's 
Probabilistic Risk Assessment for Davis-Besse: 

Appendix III: Davis-Besse Task Force Recommendations to NRC and Their 
Status, as of March 2004: 

Appendix IV: Comments from the Nuclear Regulatory Commission: 

GAO Comments: 

Appendix V: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Staff Acknowledgments: 

Related GAO Products: 

Table: 

Table 1: Status of Davis-Besse Lessons-Learned Task Force 
Recommendations, as of March 2004: 

Figures: 

Figure 1: Major Components of a Pressurized Water Reactor: 

Figure 2: Major Components of the Davis-Besse Reactor Vessel Head and 
Pressure Boundary: 

Figure 3: Diagram of the Cavity in Davis-Besse's Reactor Vessel Head: 

Figure 4: The Cavity in Davis-Besse's Reactor Vessel Head after 
Discovery: 

Figure 5: Rust and Boric Acid on Davis-Besse's Vessel Head as Shown to 
Resident Inspector during the 2000 Refueling Outage: 

Figure 6: NRC's Acceptance Guidelines for Core Damage Frequency: 

Abbreviations: 

NRC: Nuclear Regulatory Commission: 

PRA: Probabilistic risk assessment: 

Letter May 17, 2004: 

Congressional Requesters: 

In 2002, the most serious safety issue confronting the nation's 
commercial nuclear power industry since the accident at Three Mile 
Island in 1979 was identified at the Davis-Besse nuclear power plant in 
northwestern Ohio. On March 7, 2002, during shutdown for inspection and 
refueling, the owner of the Davis-Besse plant--FirstEnergy Nuclear 
Operating Company--discovered a pineapple-sized cavity in the plant's 
carbon steel reactor vessel head. The reactor vessel head is an 18-
foot-diameter, 6-inch-thick, 80-ton cap that is bolted to the reactor 
vessel. The vessel head is an integral part of the reactor coolant 
pressure boundary that serves as a vital barrier for protecting the 
environment from any release of radiation from the reactor core. In 
pressurized water reactors such as the one at Davis-Besse, the reactor 
vessel contains the nuclear fuel, as well as water with diluted boric 
acid that cools the fuel and helps control the nuclear reaction. At the 
Davis-Besse plant, vertical tubes had cracked that penetrate the 
reactor vessel head and that contain this water as well as drive 
mechanisms used to lower and raise the fuel, thus allowing leaked boric 
acid to corrode the reactor vessel head. The corrosion had extended 
through the vessel head to a thin stainless steel lining and had likely 
occurred over a period of several years. The lining, which is less than 
one-third of an inch thick and was not designed as a pressure barrier, 
was found to have a slight bulge with evidence of cracking. Had this 
lining given way, the water within the reactor vessel would have 
escaped, triggering a loss-of-coolant accident, which--if back-up 
safety systems had failed to operate--likely would have resulted in the 
melting of the radioactive core and a subsequent release of radioactive 
materials into the environment. In March 2004, after 2 years of 
increased NRC oversight and considerable repairs by FirstEnergy, NRC 
approved the restart of Davis-Besse's operations.

Under the Atomic Energy Act of 1954, as amended, and the Energy 
Reorganization Act of 1974, as amended, the Nuclear Regulatory 
Commission (NRC) and the operators of nuclear power plants share the 
responsibility for ensuring that nuclear reactors are operated safely. 
NRC is responsible for issuing regulations, licensing and inspecting 
plants, and requiring action, as necessary, to protect public health 
and safety; plant operators have the primary responsibility for safely 
operating the plants in accordance with their licenses. NRC has the 
authority to order plant operators to take actions, up to and including 
shutting down a plant, if licensing conditions are not being met and 
the plant poses an undue risk to public health and safety. In carrying 
out its responsibilities, NRC relies on, among other things, on-site 
NRC resident inspectors to assess plant conditions and quality 
assurance programs, such as those for maintenance and operations, that 
operators establish to ensure safety at the plant.

Before the discovery of the cavity in the Davis-Besse reactor vessel 
head, NRC had requested that operators of Davis-Besse and other similar 
pressurized water reactors (1) thoroughly inspect the vertical tubing 
on their reactor vessel heads by December 31, 2001, for possible 
cracking, or (2) justify why their tubing and reactor vessel heads were 
sufficiently safe without being inspected. This request was a reaction 
to cracked vertical tubing found on a pressurized water reactor vessel 
head at another plant. Such thorough inspections require that the 
reactor be shut down. FirstEnergy, believing that its reactor vessel 
head was safe, asked NRC if its shutdown could be delayed until the end 
of March 2002 to coincide with an already scheduled shutdown for 
refueling--during which time it would conduct the requested inspection. 
FirstEnergy provided evidence supporting its assertion that the reactor 
could continue operating safely. After considerable discussion, and 
after NRC developed a risk assessment estimate for deciding that Davis-
Besse would not pose an unacceptable level of risk, NRC and FirstEnergy 
compromised, and FirstEnergy agreed to shut down the reactor in mid-
February 2002 for inspection. Soon after Davis-Besse was shut down, the 
cracked tubes and the significant reactor vessel head corrosion were 
discovered.

You asked us to determine (1) why NRC did not identify and prevent the 
vessel head corrosion at Davis-Besse, (2) whether the process NRC used 
when deciding to allow FirstEnergy to delay its shutdown was credible, 
and (3) whether NRC is taking sufficient action in the wake of the 
Davis-Besse incident to prevent similar problems from developing in the 
future at Davis-Besse and other nuclear power plants. As agreed with 
your offices, our review focused on NRC's role in the events leading up 
to Davis-Besse's shutdown, NRC's response to the problems discovered, 
and NRC's management controls over programs and processes that may have 
contributed to the Davis-Besse incident. We did not evaluate the role 
of FirstEnergy because, at the time of our review, NRC's Office of 
Investigations and the Department of Justice were conducting separate 
inquiries into the potential liability of FirstEnergy concerning its 
knowledge of conditions at Davis-Besse, including the condition of the 
reactor vessel head. We also did not review NRC's March 2004 decision 
to allow the plant to restart.

Scope and Methodology: 

To determine why NRC did not identify and prevent the vessel head 
corrosion at the Davis-Besse nuclear power plant, we reviewed NRC's 
lessons-learned task force report;[Footnote 1] FirstEnergy's root cause 
analysis reports;[Footnote 2] NRC's Office of the Inspector General 
reports on Davis-Besse;[Footnote 3] NRC's augmented inspection team 
report;[Footnote 4] and NRC's inspection reports and licensee 
assessments from 1998 through 2001. We also reviewed NRC generic 
communications issued on boric acid corrosion and on nozzle cracking. 
In addition, we interviewed NRC regional officials who were involved in 
overseeing Davis-Besse at the time corrosion was occurring, and when 
the reactor vessel head cavity was found, to learn what information 
they had, their knowledge of plant activities, and how they 
communicated information to headquarters. We also held discussions with 
the resident inspector who was at Davis-Besse at the time that 
corrosion was occurring to determine what information he had and how 
this information was communicated to the regional office. Further, we 
met with FirstEnergy and NRC officials at Davis-Besse and walked 
through the facility, including the containment building, to understand 
the nature and extent of NRC's oversight of licensees. Additionally, we 
met with NRC headquarters officials to discuss the oversight process as 
it related to Davis-Besse, and the extent of their knowledge of 
conditions at Davis-Besse. We also met with county officials from 
Ottawa County, Ohio, to discuss their views on NRC and Davis-Besse 
plant safety. Further, we met with representatives from a variety of 
public interest groups to obtain their thoughts on NRC's oversight and 
the agency's proposed changes in the wake of Davis-Besse.

To determine whether the process NRC used was credible when deciding to 
allow Davis-Besse to delay its shutdown, we evaluated NRC guidelines 
for reviewing licensee requests for temporary and permanent license 
changes, or amendments to their licenses. We also reviewed NRC guidance 
for making and documenting agency decisions, such as those on whether 
to accept licensee responses to generic communications, as well as 
NRC's policies and procedures for taking enforcement action. We 
supplemented these reviews with an analysis of internal NRC 
correspondence related to the decision-making process, including e-mail 
correspondence, notes, and briefing slides. We also reviewed NRC's 
request for additional information to FirstEnergy following the 
issuance of NRC's generic bulletin for conducting reactor vessel head 
and nozzle inspections, as well as responses provided by FirstEnergy. 
In addition, we reviewed the draft shutdown order that NRC prepared 
before accepting FirstEnergy's proposal to conduct its inspection in 
mid-February 2002. We reviewed these documents to determine whether the 
basis for NRC's decision was clearly laid out, persuasive, and 
defensible to a party outside of NRC.

As part of our analysis for determining whether NRC's process was 
credible, we also obtained and reviewed NRC's probabilistic risk 
assessment (PRA) calculations that it developed to guide its decision 
making. To conduct this analysis, we relied on the advice of 
consultants who, collectively, have an extensive background in nuclear 
engineering, PRA, and metallurgy. These consultants included Dr. John 
C. Lee, Professor and Chair, Nuclear Engineering and Radiological 
Sciences at the University of Michigan's College of Engineering; Dr. 
Thomas H. Pigford, Professor Emeritus, at the University of California-
Berkeley's College of Engineering; and Dr. Gary S. Was, Associate Dean 
for Research in the College of Engineering, and Professor, Nuclear 
Engineering and Radiological Sciences at the University of Michigan's 
College of Engineering. These consultants reviewed internal NRC 
correspondence relating to NRC's PRA estimate, NRC's calculations, and 
the basis for these calculations. These consultants also discussed the 
basis for NRC's estimates with NRC officials and outside contractors 
who provided information to NRC as it developed its estimates. These 
consultants were selected on the basis of recommendations made by other 
nuclear engineering experts, their résumés, their collective 
experience, lack of a conflict of interest, and previous experience 
with assessing incidents at nuclear power plants such as Three Mile 
Island.

To determine whether NRC is taking sufficient action in the wake of the 
Davis-Besse incident to prevent similar problems from developing in the 
future, we reviewed NRC's lessons-learned task force recommendations, 
NRC's analysis of the underlying causes for failing to identify the 
corrosion of the reactor vessel head, and NRC's action plan developed 
in response to the task force recommendations. We also reviewed other 
NRC lessons-learned task force reports and their recommendations, our 
prior reports to identify issues related to those at Davis-Besse, and 
NRC's Office of the Inspector General reports. We met with NRC 
officials responsible for implementing task force recommendations to 
obtain a clear understanding of the actions they were taking and the 
status of their efforts, and discussed NRC's recommendations with NRC 
regional officials, on-site inspectors, and representatives from public 
interest groups. We conducted our review from November 2002 through May 
2004 in accordance with generally accepted government auditing 
standards.

Results in Brief: 

NRC should have but did not identify or prevent the vessel head 
corrosion at Davis-Besse because both its inspections at the plant and 
its assessments of the operator's performance yielded inaccurate and 
incomplete information on plant safety conditions. With respect to 
inspections, NRC resident inspectors had information revealing 
potential problems, such as boric acid deposits on the vessel head and 
air monitors clogged with boric acid deposits, but this information did 
not raise alarms about the plant's safety. NRC inspectors did not know 
that these indications could signal a potentially significant problem 
and therefore did not fully communicate their observations to other NRC 
staff, some of whom might have recognized the significance of the 
problem. However, even if these staff had been informed, according to 
NRC officials, the agency would have taken action only if these 
indications were considered significant safety concerns. Furthermore, 
NRC's assessments of Davis-Besse, which include inspection results as 
well as other data, did not provide complete and accurate information 
on FirstEnergy's performance. For example, NRC consistently assessed 
Davis-Besse's operator as a "good performer" during those years when 
the corrosion was likely occurring, and the operator was not correctly 
identifying the source of boric acid deposits. NRC had been aware for 
several years that corrosion and cracking were issues that could 
possibly affect safety, but did not view them as immediate safety 
concerns and therefore had not fully incorporated them into its 
oversight process.

NRC's process for deciding whether Davis-Besse could delay its shutdown 
to inspect for nozzle cracking lacks credibility because the guidance 
NRC used was not intended for making such a decision and the basis for 
the decision was not fully documented. In the absence of written 
guidance specifically intended to direct the decision-making process 
for a shutdown, NRC used guidance designed for considering operator 
requests for license amendments. This guidance describes safety factors 
that NRC should consider in deciding whether to approve a license 
amendment, as well as a process for considering the relative risk the 
amendment could pose. However, the guidance does not specify how NRC 
should use the safety factors, and we could not determine if NRC 
appropriately followed this guidance because it did not clearly 
document the basis for its decision. For example, NRC initially decided 
that several safety factors were not met and considered issuing a 
shutdown order. Regardless, the agency allowed FirstEnergy to delay its 
shutdown, even though it is not clear whether--and if so, how--the 
safety factors were subsequently met. Further, NRC did not provide a 
rationale for its decision for more than a year. NRC also did not 
follow other aspects of its guidance. In the absence of specific 
guidance, and with little documentation of the decision-making process, 
we could not judge whether the agency's decision was reasonable. Our 
consultants identified substantial problems with how NRC developed and 
used its risk estimate when making the decision. For example, NRC did 
not perform an analysis of the uncertainty associated with the risk 
estimate; if it had, our consultants believe the uncertainty would have 
been so large as to render NRC's risk estimate of questionable value. 
Further, the risk estimate indicated that the likelihood of an accident 
occurring at Davis-Besse was greater than the level of risk generally 
accepted as being reasonable by NRC.

Responding to the Davis-Besse incident, NRC has taken several 
significant actions to help prevent boric acid from corroding reactor 
vessel heads at nuclear power plants. NRC issued requirements that 
licensees more extensively examine their reactor vessel heads, revised 
NRC inspection guidance used to identify and resolve licensee problems 
before they affect operations, augmented training to keep its 
inspectors better informed about boric acid and cracking issues, and 
revised guidance to better ensure that licensees implement commitments 
to change their operations. However, NRC has not yet implemented more 
than half of its planned actions, and resource constraints could affect 
the agency's ability to fully and effectively implement the actions. 
More importantly, NRC is not addressing three systemic problems 
underscored by the Davis-Besse incident. First, its process for 
assessing safety at nuclear power plants is not adequate for detecting 
early indications of deteriorating safety. In this respect, the process 
does not effectively identify changes in the operator's performance or 
approach to safety before a more serious safety problem can develop. 
Second, NRC's decision-making guidance does not specifically address 
shutdown decisions or explain how different safety considerations, such 
as quantitative estimates of risk, should be weighed. Third, NRC does 
not have adequate management controls for systematically tracking 
actions that it has taken in response to incidents at plants to 
determine if the actions were sufficient to resolve underlying problems 
and thereby prevent future incidents. Analyses of earlier incidents at 
other plants identified several issues, such as inadequate 
communication, that contributed to the Davis-Besse incident. Such 
management controls may have helped to resolve these issues before the 
Davis-Besse incident occurred. While NRC is monitoring how it 
implements actions taken as a result of the Davis-Besse incident, the 
agency has not yet committed to a process for assessing the 
effectiveness of actions taken.

Given NRC's actions in response to Davis-Besse, severe vessel head 
corrosion is unlikely to occur at a plant any time soon. However, in 
part because of unresolved systemic problems, another incident 
unrelated to vessel head corrosion could occur in the future. As a 
result, we are recommending that NRC take more aggressive and specific 
actions in several areas, such as revising how it assesses plant 
performance, establishing a more specific methodology for deciding to 
shut down a plant, and establishing management controls for monitoring 
and assessing the effectiveness of changes made in response to task 
force findings.

In commenting on a draft of this report, NRC generally addressed only 
those findings and recommendations with which it disagreed. While 
commenting that it agreed with many of our findings, the agency said 
that the report overall does not appropriately characterize or provide 
a balanced perspective on NRC's actions surrounding the discovery of 
the reactor vessel head condition at Davis-Besse or its efforts to 
incorporate the lessons learned from that experience into its 
processes. More specifically, NRC stated that the report does not 
acknowledge that NRC must rely heavily on its licensees to provide 
complete and accurate information. NRC also expressed concern about the 
report's characterization of its use of risk estimates. We believe that 
the report fairly and accurately describes NRC's actions regarding the 
Davis-Besse incident. Nonetheless, we expanded our discussion of NRC's 
roles and responsibilities to point out that licensees are required to 
provide NRC with complete and accurate information.

NRC disagreed with our recommendations to develop (1) specific guidance 
and a well-defined process for deciding when to shut down a plant and 
(2) a methodology to assess early indications of deteriorating safety 
at nuclear power plants. NRC stated that it has sufficient guidance to 
make plant shutdown decisions. NRC also stated that, as regulators, the 
agency is not charged with managing licensees' facilities and that 
direct involvement with those aspects of licensees' operations that 
could provide it with information on early indications of deteriorating 
safety crosses over to a management function. We continue to believe 
that NRC should develop specific guidance and a well-defined process to 
decide when to shut down a plant. In absence of such guidance for 
making the Davis-Besse shutdown decision, NRC used its guidance for 
considering operators' requests for amendments to their licenses. This 
guidance describes safety factors that NRC should consider in deciding 
whether to approve license changes, as well as a process for 
considering the relative risk the amendment would pose. This guidance 
does not specify how NRC should use the safety factors. We also 
continue to believe that NRC should develop a methodology to assess 
aspects of licensees' operations as a means to have an early warning of 
developing safety problems. In implementing this recommendation, we 
envision that NRC would be analyzing data for changes in operators' 
performance or approach to safety, not prescribing how the plants are 
managed.

Background: 

NRC's Role and Responsibilities: 

NRC, as an independent federal agency, regulates the commercial uses of 
nuclear material to ensure adequate protection of public health and 
safety and the environment. NRC is headed by a five-member commission 
appointed by the President and confirmed by the Senate; one 
commissioner is appointed as chairman.[Footnote 5] NRC has about 2,900 
employees who work in its headquarters office in Rockville, Maryland, 
and its four regional offices. NRC is financed primarily by fees that 
it imposes on commercial users of the nuclear material that it 
regulates. For fiscal year 2004, NRC's appropriated budget of $626 
million includes about $546 million financed by these fees.

NRC regulates the nation's commercial nuclear power plants by 
establishing requirements for plant owners and operators to follow in 
the design, construction, and operation of the nuclear reactors. NRC 
also licenses the reactors and individuals who operate them. Currently, 
104 commercial nuclear reactors at 65 locations are licensed to 
operate.[Footnote 6] Many of these reactors have been in service since 
the early to mid-1970s. NRC initially licensed the reactors to operate 
for 40 years, but as these licenses approach their expiration dates, 
NRC has been granting 20-year extensions.

To ensure the reactors are operated within their licensing requirements 
and technical specifications, NRC oversees them by both inspecting 
activities at the plants and assessing plant performance.[Footnote 7] 
NRC's inspections consist of both routine, or baseline, inspections and 
supplemental inspections to assess particular licensee programs or 
issues that arise at a power plant. Inspections may also occur in 
response to a specific operational problem or event that has occurred 
at a plant. NRC maintains inspectors at every operating nuclear power 
plant in the United States and supplements the inspections conducted by 
these resident inspectors with inspections conducted by staff from its 
regional offices and from headquarters. Generally, inspectors verify 
that the plant's operator qualifications and operations, engineering, 
maintenance, fuel handling, emergency preparedness, and environmental 
and radiation protection programs are adequate and comply with NRC 
safety requirements. NRC also oversees licensees by requesting 
information on their activities. NRC requires that information provided 
by licensees be complete and accurate and, according to NRC officials, 
this is an important aspect of the agency's oversight.[Footnote 8] 
While we have added information to this report on the requirement that 
licensees provide NRC with complete and accurate information, we 
believe that NRC's oversight program should not place undue reliance on 
this requirement.

Nuclear power plants have many physical structures, systems, and 
components, and licensees have numerous activities under way, 24-hours 
a day, to ensure the plants operate safely. Programs to ensure quality 
assurance and safe operations include monitoring, maintenance, and 
inspection. To carry out these programs, licensees typically prepare 
several thousand reports per year describing conditions at the plant 
that need to be addressed to ensure continued safe operations. Because 
of the large number of activities and physical structures, systems, and 
components, NRC focuses its inspections on those activities and pieces 
of equipment or systems that are considered to be most significant for 
protecting public health and safety. NRC terms this a "risk-informed" 
approach for regulating nuclear power plants. Under this risk-informed 
approach, some systems and activities that NRC considers to have 
relatively less safety significance receive little NRC oversight. NRC 
has adopted a risk-informed approach because it believes it can focus 
its regulatory resources on those areas of the plant that the agency 
considers to be most important to safety. In addition, it was able to 
adopt this approach because, according to NRC, safety performance at 
nuclear power plants has improved as a result of more than 25 years of 
operating experience.

To decide whether inspection findings are minor or major, NRC uses a 
process it began in 2000 to determine the extent to which violations 
compromise plant safety. Under this process, NRC characterizes the 
significance of its inspection findings by using a significance 
determination process to evaluate how an inspection finding impacts the 
margin of safety at a power plant. NRC has a range of enforcement 
actions it can take, depending on how much the safety of the plant had 
been compromised. For findings that have low safety significance, NRC 
can choose to take no formal enforcement action. In these instances, 
nonetheless, licensees remain responsible for addressing the identified 
problems. For more serious findings, NRC may take more formal action, 
such as issuing enforcement orders. Orders can be used to modify, 
suspend, or even revoke an operating license. NRC has issued one 
enforcement order to shut down an operating power plant in its 28-year 
history--in 1987, after NRC discovered control room personnel sleeping 
while on duty at the Peach Bottom nuclear power plant in Pennsylvania. 
In addition to enforcement orders, NRC can issue civil penalties of up 
to $120,000 per violation per day. Although NRC does not normally use 
civil penalties for violations associated with its Reactor Oversight 
Process, NRC will consider using them for issues that are willful, have 
the potential for impacting the agency's regulatory process, or have 
actual public health and safety consequences. In fiscal year 2003, NRC 
proposed imposing civil penalties totaling $120,000 against two power 
plant licensees for the failure to provide complete and accurate 
information to the agency.

NRC uses generic communications--such as bulletins, generic letters, 
and information notices--to provide information to and request 
information from the nuclear industry at large or specific groups of 
licensees. Bulletins and generic letters both usually request 
information from licensees regarding their compliance with specific 
regulations. They do not require licensees to take any specific 
actions, but do require licensees to provide responses to the 
information requests. In general, NRC uses bulletins, as opposed to 
generic letters, to address significant issues of greater urgency. NRC 
uses information notices to transmit significant recently identified 
information about safety, safeguards, or environmental issues. 
Licensees are expected to review the information to determine whether 
it is applicable to their operations and consider action to avoid 
similar problems.

Operation of Pressurized Water Nuclear Power Plants and Events Leading 
to the March 2002 Discovery of Serious Corrosion: 

The Davis-Besse Nuclear Power Station, owned and operated by 
FirstEnergy Nuclear Operating Company, is an 882-megawatt electric 
pressurized water reactor located on Lake Erie in Oak Harbor, Ohio, 
about 20 miles east of Toledo. The power plant is under NRC's Region 
III oversight, which is located in Lisle, Illinois. Like other 
pressurized water reactors, Davis-Besse is designed with multiple 
barriers between the radioactive heat-producing core and the outside 
environment--a design concept called "defense-in-depth." Three main 
design components provide defense-in-depth. First, the reactor core is 
designed to retain radioactive material within the uranium oxide fuel, 
which is also covered with a layer of metal tubing. Second, a 6-inch-
thick carbon steel vessel, lined with three-sixteenth-inch-thick 
stainless steel, surrounds the reactor core. Third, a steel containment 
structure, surrounded by a thick reinforced concrete building, encloses 
the reactor vessel and other systems and components important for 
maintaining safety. The containment structure and concrete building are 
intended to help not only prevent a release of radioactivity to the 
environment, but also shield the reactor from external hazards like 
tornados and missiles. The reactor vessel, in addition to housing the 
reactor core, contains highly pressurized water to cool the radioactive 
heat-producing core and transfer heat to a steam generator. 
Consequently, the vessel is referred to as the reactor pressure vessel. 
From the vessel, hot pressurized water is piped to the steam generator, 
where a separate supply of water is turned to steam to drive turbines 
that generate electricity. (See fig. 1.): 

Figure 1: Major Components of a Pressurized Water Reactor: 

[See PDF for image]

[End of figure]

The top portion of the Davis-Besse reactor pressure vessel consisted of 
an 18-foot-diameter vessel head that was bolted to the lower portion of 
the pressure vessel. At Davis-Besse, 69 vertical tubes penetrated and 
were welded to the vessel head. These tubes, called vessel head 
penetration nozzles, contained control rods that, when raised or 
lowered, were used to moderate or shut down the nuclear reaction in the 
reactor.[Footnote 9] Because control rods attach to control rod drive 
mechanisms, these types of nozzles are referred to as control rod drive 
mechanism nozzles. A platform, known as the service structure, sat 
above the reactor vessel head and the control rod drive mechanism 
nozzles. Inside the service structure and above the pressure vessel 
head was a layer of insulation to help contain the heat emanating from 
the reactor. The sides of the lower portion of the service structure 
were perforated with 18 5-by 7-inch rectangular openings, termed 
"mouse-holes," that were used for vessel head inspections. In 
pressurized water reactors such as Davis-Besse, the reactor vessel, the 
vessel head, the nozzles, and other equipment used to ensure a 
continuous supply of pressurized water in the reactor vessel are 
collectively referred to as the reactor coolant pressure boundary. (See 
fig. 2.): 

Figure 2: Major Components of the Davis-Besse Reactor Vessel Head and 
Pressure Boundary: 

[See PDF for image]

[End of figure]

To better control the nuclear reaction at nuclear power plants, boron 
in the form of boric acid crystals is dissolved in the cooling water 
contained within the reactor vessel and pressure boundary. Boric acid, 
under certain conditions, can cause corrosion of carbon steel. For 
about 3 decades, NRC and the nuclear power industry have known that 
boric acid had the potential to corrode reactor components. In general, 
if leakage occurs from the reactor coolant system, the escaping coolant 
will flash to steam and leave behind a concentration of impurities, 
including noncorrosive dry boric acid crystals. However, under certain 
conditions, the coolant will not flash to steam, and the boric acid 
will remain in a liquid state where it can cause extensive and rapid 
degradation of any carbon steel components it contacts. Such extensive 
degradation, in both domestic and foreign pressurized water reactor 
plants, has been well documented and led NRC to issue a generic letter 
in 1988 requesting information from pressurized water reactor licensees 
to ensure they had implemented programs to control boric acid 
corrosion. NRC was primarily concerned that boric acid corrosion could 
compromise the reactor coolant pressure boundary. This concern also led 
NRC to develop a procedure for inspecting licensees' boric acid 
corrosion control programs and led the Electric Power Research 
Institute to issue guidance on boric acid corrosion control.[Footnote 
10]

NRC and the nuclear power industry have also known that nozzles made of 
alloy 600,[Footnote 11] used in several areas within nuclear power 
plants, were prone to cracking. Cracking had become an increasingly 
topical issue as the nuclear power plant fleet has aged. In 1986, 
operators at domestic and foreign pressurized water reactors began 
reporting leaks in various types of alloy 600 nozzles. In 1989, after 
leakage was detected at a domestic plant, NRC identified the cause of 
the leakage as cracking due to primary water stress corrosion.[Footnote 
12] However, NRC concluded that the cracking was not an immediate 
safety concern for a few reasons. For example, the cracks had a low 
growth rate, were in a material with an extremely high flaw tolerance 
and, accordingly, were unlikely to spread. Also, the cracks were axial-
-that is, they ran the length of the nozzle rather than its 
circumference. NRC and the nuclear power industry were more concerned 
that circumferential cracks could result in broken or snapped nozzles. 
NRC did, however, issue a generic information notice in 1990 to inform 
the industry of alloy 600 cracking. Through the early 1990s, NRC, the 
Nuclear Energy Institute,[Footnote 13] and others continued to monitor 
alloy 600 cracking. In 1997, continued concern over cracking led NRC to 
issue a generic letter to pressurized water reactor licensees 
requesting information on their plans to monitor and manage cracking in 
vessel head penetration nozzles as well as to examine these nozzles.

In the spring of 2001, licensee inspections led to the discovery of 
large circumferential cracking in several vessel head penetration 
nozzles at the Oconee Nuclear Station, in South Carolina. As a result 
of the discovery, the nuclear power industry and NRC categorized the 69 
operating pressurized water reactors in the United States into 
different groups on the basis of (1) whether cracking had already been 
found and (2) how similar they were to Oconee in terms of the amount of 
time and the temperature at which the reactors had operated. The 
industry had developed information indicating that greater operating 
time and temperature were related to cracking. In total, five reactors 
at three locations were categorized as having already identified 
cracking, while seven reactors at five locations were categorized as 
being highly susceptible, given their similarity to Oconee.[Footnote 
14]

In August 2001, NRC issued a bulletin requesting that licensees of 
these reactors provide, within 30 days, information on their plans for 
conducting nozzle inspections before December 31, 2001.[Footnote 15] In 
lieu of this information, NRC stated that licensees could provide the 
agency with a reasoned basis for their conclusions that their reactor 
vessel pressure boundaries would continue to meet regulatory 
requirements for ensuring the structural integrity of the reactor 
coolant pressure boundary until the licensees conducted their 
inspections. NRC used a bulletin, as opposed to a generic letter, to 
request this information because cracking was considered a significant 
and urgent issue. All of the licensees of the highly susceptible 
reactors, except Davis-Besse and D.C. Cook reactor unit 2, provided NRC 
with plans for conducting inspections by December 31, 2001.[Footnote 
16]

In September 2001, FirstEnergy proposed conducting the requested 
inspection in April 2002, following its planned March 31, 2002, 
shutdown to replace fuel. In making this proposal, FirstEnergy 
contended that the reactor coolant pressure boundary at Davis-Besse met 
and would continue to meet regulatory requirements until its 
inspection. NRC and FirstEnergy exchanged information throughout the 
fall of 2001 regarding when FirstEnergy would conduct the inspection at 
Davis-Besse. NRC drafted an enforcement order that would have shut down 
Davis-Besse by December 2001 for the requested inspection in the event 
that FirstEnergy could not provide an adequate justification for safe 
operation beyond December 31, 2001, but ultimately compromised on a 
mid-February 2002 shutdown date. NRC, in deciding when FirstEnergy had 
to shut down Davis-Besse for the inspection, used a risk-informed 
decision-making process, including probabilistic risk assessment 
(PRA), to conclude that the risk that Davis-Besse would have an 
accident in the interim was relatively low. PRA is an analytical tool 
for estimating the probability that a potential accident might occur by 
examining how physical structures, systems, and components, along with 
employees, work together to ensure plant safety.

Following the mid-February 2002 shutdown and in the course of its 
inspection in March 2002, FirstEnergy removed about 900 pounds of boric 
acid crystals and powder from the reactor vessel head, and subsequently 
discovered three cracked nozzles. The number of nozzles that had 
cracked, as well as the extent of cracking, was consistent with 
analyses that NRC staff had conducted prior to the shutdown. However, 
in examining the extent of cracking, FirstEnergy also discovered that 
corrosion had caused a pineapple-sized cavity in the reactor vessel 
head. (See figs. 3 and 4.): 

Figure 3: Diagram of the Cavity in Davis-Besse's Reactor Vessel Head: 

[See PDF for image]

[End of figure]

Figure 4: The Cavity in Davis-Besse's Reactor Vessel Head after 
Discovery: 

[See PDF for image]

[End of figure]

After this discovery, NRC directed FirstEnergy to, among other things, 
determine the root cause of the corrosion and obtain NRC approval 
before restarting Davis-Besse. NRC also dispatched an augmented 
inspection team consisting of NRC resident, regional, and headquarters 
officials.[Footnote 17] The inspection team concluded that the cavity 
was caused by boric acid corrosion from leaks through the control rod 
drive mechanism nozzles in the reactor vessel head. Primary water 
stress corrosion cracking of the nozzles caused through-wall cracks, 
which led to the leakage and eventual corrosion of the vessel head. 
NRC's inspection team also concluded, among other things, that this 
corrosion had gone undetected for an extended period of time--at least 
4 years--and significantly compromised the plant's safety margins. As 
of May 2004, NRC had not yet completed other analyses, including how 
long Davis-Besse could have continued to operate with the corrosion it 
had experienced before a vessel head loss-of-coolant accident would 
have occurred.[Footnote 18] However, on May 4, 2004, NRC released 
preliminary results of its analysis of the vessel head and cracked 
cladding. Based on its analysis of conditions that existed on February 
16, 2002, NRC estimated that Davis-Besse could have operated for 
another 2 to 13 months without the vessel head failing. However, the 
agency cautioned that this estimate was based on several uncertainties 
associated with the complex network of cracks on the cladding and the 
lack of knowledge about corrosion and cracking rates. NRC plans to use 
this data in preparing its preliminary analysis of how, and the 
likelihood that, the events at Davis-Besse could have led to core 
damage. NRC plans to complete this preliminary analysis in the summer 
of 2004.

NRC also established a special oversight panel to (1) coordinate NRC's 
efforts to assess FirstEnergy's performance problems that resulted in 
the corrosion damage, (2) monitor Davis-Besse's corrective actions, and 
(3) evaluate the plant's readiness to resume operations. The panel, 
which is referred to as the Davis-Besse Oversight Panel, comprises 
officials from NRC's Region III office in Lisle, Illinois; NRC 
headquarters; and the resident inspector office at Davis-Besse. In 
addition to overseeing FirstEnergy's performance during the shutdown 
and through restart of Davis-Besse, the panel holds public meetings in 
Oak Harbor, Ohio, where the plant is located, and nearby Port Clinton, 
Ohio, to inform the public about its oversight of Davis-Besse's restart 
efforts and its views on the adequacy of these efforts. The panel 
developed a checklist of issues that FirstEnergy had to resolve prior 
to restarting: (1) replacing the vessel head and ensuring the adequacy 
of other equipment important for safety, (2) correcting FirstEnergy 
programs that led to the corrosion, and (3) ensuring FirstEnergy's 
readiness to restart. To restart the plant, FirstEnergy, among other 
things, removed the damaged reactor vessel head, purchased and 
installed a new head, replaced management at the plant, and took steps 
to improve key programs that should have prevented or detected the 
corrosion. As of March 2004, when NRC gave its approval for Davis-Besse 
to resume operations, the shutdown and preparations for restart had 
cost FirstEnergy approximately $640 million.[Footnote 19]

In addition, NRC established a task force to evaluate its regulatory 
processes for assuring reactor pressure vessel head integrity and to 
identify and recommend areas for improvement that may be applicable to 
either NRC or the nuclear power industry. The task force's report, 
which was issued in September 2002, contains 51 recommendations aimed 
primarily at improving NRC's process for inspecting and overseeing 
licensees, communicating with industry, and identifying potential 
emerging technical issues that could impact plant safety. NRC developed 
an action plan to implement the report's recommendations.

NRC's Actions to Oversee Davis-Besse Did Not Provide an Accurate 
Assessment of Safety at the Plant: 

NRC's inspections and assessments of FirstEnergy's operations should 
have but did not provide the agency with an accurate understanding of 
safety conditions at Davis-Besse, and thus NRC failed to identify or 
prevent the vessel head corrosion. Some NRC inspectors were aware of 
the indications of corrosion and leakage that could have alerted NRC to 
corrosion problems at the plant, but they did not have the knowledge to 
recognize the significance of this information. These problems were 
compounded by NRC's assessments of FirstEnergy that led the agency to 
believe FirstEnergy was a good performer and could or would 
successfully resolve problems before they became significant safety 
issues. More broadly, NRC had a range of information that could have 
identified and prevented the incident at Davis-Besse but did not 
effectively integrate it into its oversight.

Several Factors Contributed to the Inadequacy of NRC's Inspections for 
Determining Plant Conditions: 

Three separate, but related, NRC inspection program factors contributed 
to the development of the corrosion problems at Davis-Besse. First, 
resident inspectors did not know that the boric acid, rust, and 
unidentified leaking indicated that the reactor vessel head might be 
degrading. Second, these inspectors thought they understood the cause 
for the indications, based on licensee actions to address them. 
Therefore, resident inspectors, as well as regional and headquarters 
officials, did not fully communicate information on the indications or 
decide how to address them, and therefore took no action. Third, 
because the significance of the symptoms was not fully recognized, NRC 
did not direct sufficient inspector resources to aggressively 
investigate the indicators. NRC might have taken a different approach 
to the Davis-Besse situation if its program to identify emerging issues 
important to safety had pursued earlier concerns about boric acid 
corrosion and cracking and recognized how they could affect safety.

Inspectors Did Not Know Safety Significance of Observed Problems: 

NRC limits the amount of unidentified leakage from the reactor coolant 
system to no more than 1 gallon per minute. When this limit is 
exceeded, NRC requires that licensees identify and correct any sources 
of unidentified leakage. NRC also prohibits any leakage from the 
reactor coolant pressure boundary, of which the reactor vessel is a key 
component. Such leakage is prohibited because the pressure boundary is 
key to maintaining adequate coolant around the reactor fuel and thus 
protects public health and safety. Because of this, NRC's technical 
specification states that licensees are to monitor reactor coolant 
leakage and shut down within 36 hours if leakage is found in the 
pressure boundary.

In the years leading up to FirstEnergy's March 2002 discovery that 
Davis-Besse's vessel head had corroded extensively, NRC had several 
indications of potential leakage problems. First, NRC knew that the 
rates of leakage in the reactor coolant system had increased. Between 
1995 and mid-1998, the unidentified leakage rate was about 0.06 gallon 
per minute or less, according to FirstEnergy's monitoring. In mid-1998, 
the unidentified reactor coolant system leakage rate increased 
significantly--to as much as 0.8 gallon per minute. The elevated 
leakage rate was dominated by a known problem with a leaking relief 
valve on the reactor coolant system pressurizer tank, which masked the 
ongoing leak on the reactor pressure vessel head. However, the elevated 
leak rate should have raised concerns.

To investigate this leakage, as well as to repair other equipment, 
FirstEnergy shut down the plant in mid-1999. It then identified a 
faulty relief valve that accounted for much of the leakage and repaired 
the valve. However, after restarting Davis-Besse, the unidentified 
leakage rate remained significantly higher than the historical average. 
Specifically, the unidentified leakage rate varied between 0.15 and 
0.25 gallon per minute as opposed to the historical low of about 0.06 
gallon or less. While NRC was aware that the rate was higher than 
before, NRC did not aggressively pursue the difference because the rate 
was well below NRC's limit of no more than 1 gallon per minute, and 
thus the leak was not viewed as being a significant safety concern. 
Following the repair in 1999, NRC's inspection report concluded that 
FirstEnergy's efforts to reduce the leak rate during the outage were 
effective.

Second, NRC was aware of increased levels of boric acid in the 
containment building--an indication that components containing reactor 
coolant were leaking. So much boric acid was being deposited that 
FirstEnergy officials had to repeatedly clean the containment air 
cooling system and radiation monitor filters. For example, before 1998, 
the containment air coolers seldom needed cleaning, but FirstEnergy had 
to clean them 28 times between late 1998 and May 2001. Between May 2001 
and the mid-February 2002 shutdown, the containment air coolers were 
not cleaned, but at shutdown, FirstEnergy removed 15 5-gallon buckets 
of boric acid from the coolers--which is almost as much as was found on 
the reactor pressure vessel head. Rather than seeing these repeated 
cleanings as an indication of a problem that needed to be addressed, 
FirstEnergy made cleaning the coolers a routine maintenance activity, 
which NRC did not consider significant enough to require additional 
inspections. Furthermore, the radiation monitors, used to sample air 
from the containment building to detect radiation, typically required 
new filters every month. However, from 1998 to 2002, these monitors 
became clogged and inoperable hundreds of times because of boric acid, 
despite FirstEnergy's efforts to fix the problem.

Third, NRC was aware that FirstEnergy found rust in the containment 
building. The radiation monitor filters had accumulated dark colored 
iron oxide particles--a product of carbon steel corrosion--that were 
likely to have resulted from a very small steam leak. NRC inspection 
reports during the summer and fall of 1999 noted these indications and, 
while recognizing FirstEnergy's aggressive attempts to identify the 
reasons for the phenomenon, concluded that they were a "distraction to 
plant personnel." Several NRC inspection reports noted indications of 
leakage, boric acid, and rust before the agency adopted its new Reactor 
Oversight Process in 2000, but because the leakage was within NRC's 
technical specifications and NRC officials thought that the licensee 
understood and would fix the problem, NRC did not aggressively pursue 
the indications. NRC's new oversight process, implemented in the spring 
of 2000, limited the issues that could be discussed in NRC inspection 
reports to those that the agency considers to have more than minor 
significance. Because the leakage rates were below NRC's limits, NRC's 
inspection reports following the implementation of NRC's new oversight 
process did not identify any discussion of these problems at the plant.

Fourth, NRC was aware that FirstEnergy found rust on the Davis-Besse 
reactor vessel head, but it did not recognize its significance. For 
instance, during the 2000 refueling outage, a FirstEnergy official said 
he showed one of the two NRC resident inspectors a report that included 
photographs of rust-colored boric acid on the vessel head. (See fig. 
5.): 

Figure 5: Rust and Boric Acid on Davis-Besse's Vessel Head as Shown to 
Resident Inspector during the 2000 Refueling Outage: 

[See PDF for image]

[End of figure]

According to this resident inspector, he did not recall seeing the 
report or photographs but had no reason to doubt the FirstEnergy 
official's statement. Regardless, he stated that had he seen the 
photographs, he would not have considered the condition to be 
significant at the time. He said that he did not know what the rust and 
boric acid might have indicated, and he assumed that FirstEnergy would 
take care of the vessel head before restarting. The second resident 
inspector said he reviewed all such reports at Davis-Besse but did not 
recall seeing the photographs or this particular report. He stated that 
it was quite possible that he had read the report, but because the 
licensee had a plan to clean the vessel head, he would have concluded 
that the licensee would correct the matter before plant restart. 
However, FirstEnergy did not accomplish this, even though work orders 
and subsequent licensee reports indicated that this was done. According 
to the NRC resident inspector and NRC regional officials, because of 
the large number of licensee activities that occur during a refueling 
outage, NRC inspectors do not have the time to investigate or follow up 
on every issue, particularly when the issue is not viewed as being 
important to safety. While the resident inspector informed regional 
officials about conditions at Davis-Besse, the regional office did not 
direct more inspection resources to the plant, or instruct the resident 
inspector to conduct more focused oversight. Some NRC regional 
officials were aware of indications of boric acid corrosion at the 
plant; others were not. According to the Office of the Inspector 
General's investigation and 2003 report on Davis-Besse,[Footnote 20] 
the NRC regional branch chief--who supervised the staff responsible for 
overseeing FirstEnergy's vessel head inspection activities during the 
2000 refueling outage--said that he was unaware of the boric acid 
leakage issues at Davis-Besse, including its effects on the containment 
air coolers and the radiation monitor filters. Had his staff been 
requested to look at these specific issues, he might have directed 
inspection resources to that area. (App. I provides a time line showing 
significant events of interest.): 

NRC Did Not Fully Communicate Indications: 

NRC was not fully aware of the indications of a potential problem at 
Davis-Besse because NRC's process for transmitting information from 
resident inspectors to regional offices and headquarters did not ensure 
that information was fully communicated, evaluated, or used. NRC staff 
communicated information about plant operations through inspection 
reports, licensee assessments, and daily conference calls that included 
resident, regional, and headquarters officials. According to regional 
officials, information that is not considered important is not 
routinely communicated to NRC management and technical specialists. For 
example, while the resident inspectors at Davis-Besse knew all of the 
indications of leakage, and there was some level of knowledge about 
these indications at the regional office level, the knowledge was not 
sufficiently widespread within NRC to alert a technical specialist who 
might have recognized their safety significance. According to NRC 
Region III officials, the region uses an informal means--memorandums 
sent to other regions and headquarters--of communicating information 
identified at plants that it considers to be important to safety. 
However, because the indications at Davis-Besse were not considered 
important, officials did not transmit this information to headquarters. 
Further, because the process is informal, these officials said they did 
not know whether--and if so, how--other NRC regions or headquarters 
used this information.

Similarly, NRC officials said that NRC headquarters had no systematic 
process for communicating information, such as on boric acid corrosion, 
cracking, and small amounts of unidentified leakage, that had not yet 
risen to a relatively high level of concern within the agency, in a 
timely manner to its regions or on-site inspectors. For example, the 
regional inspector that oversaw FirstEnergy's activities during the 
2000 refueling outage, including the reactor vessel head inspection, 
stated that he was not aware of NRC's generic bulletins and letters 
pertaining to boric acid and corrosion, even though NRC issues only a 
few of these bulletins and generic letters each year.[Footnote 21] In 
addition, according to NRC regional officials and the resident 
inspector at Davis-Besse, there is little time to review technical 
reports about emerging safety issues that NRC compiles because they are 
too lengthy and detailed. Ineffective communication, both within the 
region and between NRC headquarters and the region, was a primary 
factor cited by NRC's Office of the Inspector General in its 
investigation of NRC's oversight of Davis-Besse boric acid leakage and 
corrosion.[Footnote 22] For example, it found that ineffective 
communication resulted in senior regional management being largely 
unaware of repeated reports of boric acid leakage at Davis-Besse. It 
also found that headquarters, in communications with the regions, did 
not emphasize the issues discussed in its generic letters or bulletins 
on boric acid corrosion or cracking. NRC programs for informing its 
inspectors about issues that can reduce safety at nuclear power plants 
were not effective. As a result, NRC inspectors did not recognize the 
significance of the indications at Davis-Besse, fully communicate 
information about the indications, or spend additional effort to follow 
up on the indications.

Resource Constraints Affected NRC Oversight: 

NRC also did not focus on the indications that the vessel head was 
corroding because of several staff constraints. Region III was 
directing resources to other plants that had experienced problems 
throughout the region, and these plants thus were the subject of 
increased regulatory oversight. For example, during the refueling 
outages in 1998 and 2000, while NRC oversaw FirstEnergy's inspection of 
the reactor vessel head, the region lacked senior project engineers to 
devote to Davis-Besse. A vacancy existed for a senior project engineer 
responsible for Davis-Besse from June 1997 until June 1998, except for 
a one month period, and from September 1999 until May 2000, which 
resulted in fewer inspection hours at the facility than would have been 
normal. Other regional staff were also occupied with other plants in 
the region that were having difficulties, and NRC had unfilled 
vacancies for resident and regional inspector positions that strained 
resources for overseeing Davis-Besse.

Even if the inspector positions had been filled, it is not certain that 
the inspectors would have aggressively followed up on any of the 
indications. According to our discussions with resident and regional 
inspectors and our on-site review of plant activities, because nuclear 
power plants are so large, with many physical structures, systems, and 
components, an inspector could miss problems that were potentially 
significant for safety. Licensees typically prepare several hundred 
reports per month for identifying and resolving problems, and NRC 
inspectors have only a limited amount of time to follow up on these 
licensee reports. Consequently, NRC selects and oversees the most 
safety significant structures, systems, and components.

NRC's Assessment Process Did Not Indicate Deteriorating Performance: 

Under NRC's Reactor Oversight Process, NRC assesses licensees' 
performance using two distinct types of information: (1) NRC's 
inspection results and (2) performance indicators reported by the 
licensees. These indicators, which reflect various aspects of a plant's 
operations, include data on, for example, the failure or unavailability 
of certain important operating systems, the number of unplanned power 
changes, and the amount of reactor coolant system leakage. NRC 
evaluates both the inspection results and the performance indicators to 
arrive at licensee assessments, which it then color codes to reflect 
their safety significance. Green assessments indicate that performance 
is acceptable, and thus connote a very low risk significance and impact 
on safety. White, yellow, and red assessments each represent a greater 
degree of safety significance. After NRC adopted its Reactor Oversight 
Process in April 2000, FirstEnergy never received anything but green 
designations for its operations at Davis-Besse and was viewed by NRC as 
a good performer until the 2002 discovery of the vessel head 
corrosion.[Footnote 23] Similarly, prior to adopting the Reactor 
Oversight Process, NRC consistently assessed FirstEnergy as generally 
being a good performer. NRC officials stated, however, that significant 
issues were identified and addressed as warranted throughout this 
period, such as when the agency took enforcement action in response to 
FirstEnergy's failure to properly repair important components in 1999-
-a failure caused by weaknesses in FirstEnergy's boric acid corrosion 
control program.

Key Davis-Besse programs for ensuring the quality and safe operation of 
the plant's engineered structures, systems, and components include, for 
example,

* a corrective action program to ensure that problems at the plant that 
are relevant to safety are identified and resolved in a timely manner,

* an operating experience program to ensure that experiences or 
problems that occur are appropriately identified and analyzed to 
determine their significance and relevance to operations, and: 

* a plant modification program to ensure that modifications important 
to safety are implemented in a timely manner.

As at other commercial nuclear power plants, NRC conducted routine, 
baseline inspections of Davis-Besse to determine the effectiveness of 
these programs. Reports documenting these inspections noted incidences 
of boric acid leakage, corrosion, and deposits. However, between 
February 1997 and March 2000, the regional office's assessment of the 
licensee's performance addressed leakage in the reactor coolant system 
only once and never noted the other indications. Furthermore, Davis-
Besse was not the subject of intense scrutiny in regional plant 
assessment meetings because plants perceived as good performers--such 
as Davis-Besse--received substantially less attention. Between April 
2000--when NRC's revised assessment process took effect--until the 
corrosion was discovered in March 2002, none of NRC's assessments of 
Davis-Besse's performance noted leakage or other indications of 
corrosion at the plant. As a result, NRC may have missed opportunities 
to identify weaknesses in the Davis-Besse programs intended to detect 
or prevent the corrosion.

After the corrosion was discovered, NRC analyzed the problems that led 
to the corrosion on the reactor vessel head and concluded that 
FirstEnergy's programs for overseeing safety at Davis-Besse were weak, 
as seen in the following examples: 

* Davis-Besse's corrective action program did not result in timely or 
effective actions to prevent indications of leakage from reoccurring in 
the reactor coolant system.

* FirstEnergy officials did not always enter equipment problems into 
the corrective action program because individuals who had identified 
the problem were often responsible for resolving it.

* For over a decade, FirstEnergy had delayed plant modifications to its 
service structure platform, primarily because of cost. These 
modifications would have improved its ability to inspect the reactor 
vessel head nozzles. As a result, FirstEnergy could conduct only 
limited visual inspections and cleaning of the reactor pressure vessel 
head through the small "mouse-holes" that perforated the service 
structure.

NRC was also unaware of the extent to which various aspects of 
FirstEnergy's safety culture had degraded--that is, FirstEnergy's 
organization and performance related to ensuring safety at Davis-Besse. 
This degradation had allowed the incident to occur with no forewarning 
because NRC's inspections and performance indicators do not directly 
assess safety culture. Safety culture is a group of characteristics and 
attitudes within an organization that establish, as an overriding 
priority, that issues affecting nuclear plant safety receive the 
attention their significance warrants. Following FirstEnergy's March 
2002 discovery, NRC found numerous indications that FirstEnergy 
emphasized production over plant safety. First, Davis-Besse routinely 
restarted the plant following an outage, even though reactor pressure 
vessel valves and control rod drive mechanisms leaked. Second, staff 
was unable to remove all of the boric acid deposits from the reactor 
pressure vessel head because FirstEnergy's schedule to restart the 
plant dictated the amount of work that could be performed. Third, 
FirstEnergy management was willing to accept degraded equipment, which 
indicated a lack of commitment to resolve issues that could potentially 
compromise safety. Fourth, Davis-Besse's program that was intended to 
ensure that employees feel free to raise safety concerns without fear 
of retaliation had several weaknesses. For example, in one instance, a 
worker assigned to repair the containment air conditioner was not 
provided a respirator in spite of his concerns that he would inhale 
boric acid residue. According to NRC's lessons-learned task force 
report, NRC was not aware of weaknesses in this program because its 
inspections did not adequately assess it.

Given that FirstEnergy concluded that one of the causes for the Davis-
Besse incident was human performance and management failures, the panel 
overseeing FirstEnergy's efforts to restart Davis-Besse requested that 
FirstEnergy assess its safety culture before allowing the plant to 
restart. To oversee FirstEnergy's efforts to improve its safety 
culture, NRC (1) reviewed whether FirstEnergy had adequately identified 
all of the root causes for management and human performance failures at 
Davis-Besse, (2) assessed whether FirstEnergy had identified and 
implemented appropriate corrective actions to resolve these failures, 
and (3) assessed whether FirstEnergy's corrective actions were 
effective. As late as February 2004, NRC had concerns about whether 
FirstEnergy's actions would be adequate in the long term. As a result, 
the Davis-Besse safety culture was one of the issues contributing to 
the delay in restarting the plant. In March 2004, NRC's panel concluded 
that FirstEnergy's efforts to improve its safety culture were 
sufficient to allow the plant to restart. In doing so, however, NRC 
officials stated that one of the conditions the panel imposed was for 
FirstEnergy to conduct an independent assessment of the safety culture 
at Davis-Besse annually over the course of the next 5 years.

NRC Did Not Effectively Incorporate Long-Standing Knowledge about 
Corrosion, Nozzle Cracking, and Leak Detection into Its Oversight: 

NRC has been aware of boric acid corrosion and its potential to affect 
safety since at least 1979. It issued several notices to the nuclear 
power industry about boric acid corrosion and, specifically, the 
potential for it to degrade the reactor coolant pressure boundary. In 
1987, two licensees found significant corrosion on their reactor 
pressure vessel heads, which heightened NRC's concern. A subsequent 
industry study concluded that concentrated solutions of boric acid 
could result in unacceptably high corrosion rates--up to 4 inches per 
year--when primary coolant leaks onto surfaces and concentrates at 
temperatures found on the surface of the reactor vessel.[Footnote 24] 
After considering this information and several more instances of boric 
acid corrosion at plants, NRC issued a generic letter in 1988 
requesting licensees to implement boric acid corrosion control 
programs.

In 1990, NRC visited Davis-Besse to assess the adequacy of the plant's 
boric acid corrosion control program. At that time, NRC concluded that 
the program was acceptable. However, in 1999, NRC became aware that 
FirstEnergy's boric acid corrosion control program was inadequate 
because boric acid had corroded several bolts on a valve, and NRC 
issued a violation. As a result of the violation, FirstEnergy agreed to 
review its boric acid corrosion procedures and enhance its program. NRC 
inspectors evaluated FirstEnergy's completed and planned actions to 
improve the boric acid corrosion control program and found them to be 
adequate. According to NRC officials, they never inspected the 
remaining actions--assuming that the planned actions had been 
implemented effectively. In 2000, NRC adopted its new Reactor Oversight 
Process and discontinued its inspection procedure for plants' corrosion 
control programs because these inspections had rarely been conducted 
due to higher priorities. Thus, NRC had no reliable or routine way to 
ensure that the nuclear power industry fully implemented boric acid 
corrosion control programs.

NRC also did not routinely review operating experiences at reactors, 
both in the United States and abroad, to keep abreast of boric acid 
developments and determine the need to emphasize this problem. Indeed, 
NRC did not fully understand the circumstances in which boric acid 
would result in corrosion, rather than flash to steam. Similarly, NRC 
did not know the rate at which carbon steel would corrode under 
different conditions. This lack of knowledge may be linked to 
shortcomings in its program to review operating experiences at 
reactors, which could have been exacerbated by the 1999 elimination of 
the office specifically responsible for reviewing operating 
experiences.[Footnote 25] This office was responsible for, among other 
things, (1) coordinating operational data collection, (2) 
systematically analyzing and evaluating operational experience, (3) 
providing feedback on operational experience to improve safety, (4) 
assessing the effectiveness of the agencywide program, and (5) acting 
as a focal point for interaction with outside organizations on issues 
pertaining to operational safety data analysis and evaluation. 
According to NRC officials who had overseen Davis-Besse at the time of 
the incident, they would not have suspected the reactor vessel head or 
cracked head penetration nozzles as the source of the filter clogging 
and unidentified leakage because they had not been informed that these 
could be potential problems. According to these officials, the vessel 
head was "not on the radar screen.": 

With regard to nozzle cracking, NRC, for more than two decades, was 
aware of the potential for nozzles and other components made of alloy 
600 to crack. While cracks were found at nuclear power plants, NRC 
considered their safety significance to be low because the cracks were 
not developing rapidly. In contrast, other countries considered the 
safety significance of such cracks to be much higher. For example, 
concern over alloy 600 cracking led France, as a preventive measure, to 
institute requirements for an extensive nondestructive examination 
inspection program for vessel head penetration nozzles, including the 
removal of insulation, during every fuel outage. When any indications 
of cracking were observed, even more frequent inspections were 
required, which, because of economic considerations, resulted in the 
replacement of vessel heads when indications were found. The effort to 
replace the vessel heads is still under way. Japan replaced those 
vessel heads whose nozzles it considered most susceptible to cracking, 
even though no cracks had yet been found. Both France and Sweden also 
installed enhanced leakage monitoring systems to detect leaks early. 
However, according to NRC, such systems cannot detect the small amounts 
of leakage that may be typical from cracked nozzles.

NRC recognized that an integrated, long-term program, including 
periodic inspections and monitoring of vessel heads to check for nozzle 
cracking, was necessary. In 1997, it issued a generic letter that 
summarized NRC's efforts to address cracking of control rod drive 
mechanism nozzles and requested information on licensees' plans to 
inspect nozzles at their reactors. More specifically, this letter asked 
licensees to provide NRC with descriptions of their inspections of 
these nozzles and any plans for enhanced inspections to detect cracks. 
At that time, NRC was planning to review this information to determine 
if enhanced licensee inspections were warranted. Based on its review of 
this information, NRC concluded that the current inspection program was 
sufficient. As a result, between 1998 and 2001, NRC did not issue or 
solicit additional information on nozzle cracking or assess its 
requirements for inspecting reactor vessels to determine whether they 
were sufficient to detect cracks. At Davis-Besse, NRC also did not 
determine if FirstEnergy had plans or was implementing any plans for 
enhanced nozzle inspections, as noted in the 1997 generic letter. NRC 
took no further action until the cracks were found in 2001 at the 
Oconee plant, in South Carolina. NRC attributed its lack of focus on 
nozzle cracking, in part, to the agency's inability to effectively 
review, assess, and follow up on industry operating experience events. 
Furthermore, as with boric acid corrosion, NRC did not obtain or 
analyze any new data about cracking that would have supported making 
changes in either its regulations or inspections to better identify or 
prevent corrosion on the vessel head at Davis-Besse.

NRC's technical specifications regarding allowable leakage rates also 
contributed to the corrosion at Davis-Besse because the amount of 
leakage that can cause extensive corrosion can be significantly less 
than the level that NRC's specifications allow. According to NRC 
officials, NRC's requirements, established in 1973, were based on the 
best available technology at that time. The task of measuring 
identified and unidentified leakage from the reactor coolant system is 
not precise. It requires licensees to estimate the amount of coolant 
that the reactor is supposed to contain and identify any difference in 
coolant levels. They then have to account for the estimated difference 
in the actual amount of coolant to arrive at a leakage rate; to do 
this, they identify all sources and amounts of leakage by, among other 
things, measuring the amount of water contained in various sump 
collection systems. If these sources do not account for the difference, 
licensees know they have an unidentified source of leakage. This 
estimate can vary significantly from day to day between negative and 
positive numbers.

According to analyses that FirstEnergy conducted after it identified 
the corrosion in March 2002, the leakage rates from the nozzle cracks 
were significantly below NRC's reactor coolant system unidentified 
leakage rate of 1 gallon per minute. Specifically, the leakage from the 
nozzle around which the vessel head corrosion occurred was predicted to 
be 0.025 gallon per minute. If such small leakage can result in such 
extensive corrosion, identifying if and where such leakage occurs is 
important. NRC staff recognized as early as 1993 it would be prudent 
for the nuclear power industry to consider implementing an enhanced 
method for detecting small leaks during plant operation, but NRC did 
not require this action, and the industry has not taken steps to do so. 
Furthermore, NRC has not consistently enforced its requirement for 
reactor coolant pressure boundary leakage. As a result, the NRC Davis-
Besse task force concluded that inconsistent enforcement may have 
reinforced a belief that alloy 600 nozzle leakage was not actually or 
potentially a safety significant issue.

NRC's Process for Deciding Whether to Allow a Delayed Davis-Besse 
Shutdown Lacked Credibility: 

Although FirstEnergy operated Davis-Besse without incident until 
shutting it down in February 2002, certain aspects of NRC's 
deliberations allowing the delayed shutdown raise questions about the 
credibility of the agency's decision making, if not about the Davis-
Besse decision itself. NRC does not have specific guidance for deciding 
on plant shutdowns. Instead, agency officials turned to guidance 
developed for a different purpose--reviewing requests to amend license 
operating conditions--and even then did not always adhere to this 
guidance. In addition, NRC did not document its decision-making 
process, as called for by its guidance, and its letter to FirstEnergy 
to lay out the basis for the decision--sent a year after the decision-
-did not fully explain the decision. NRC's lack of guidance, coupled 
with the lack of documentation, precludes us from independently judging 
whether NRC's decision was reasonable. Finally, some NRC officials 
stated that the shutdown decision was based, in part, on the agency's 
probabilistic risk assessment (PRA) calculations of the risk that 
Davis-Besse would pose if it delayed its shutdown and inspection. 
However, as noted by our consultants, the calculations were flawed, and 
NRC's decision makers did not always follow the agency's guidance for 
developing and using such calculations.

NRC Did Not Have Specific Guidance for Deciding on Plant Shutdowns: 

NRC believed that Davis-Besse could have posed a potential safety risk 
because it was, in all likelihood, failing to comply with NRC's 
technical specification that no leakage occur in the reactor coolant 
pressure boundary. Its belief was based on the following indicators of 
probable leakage: 

* All six of the other reactors manufactured by the same company as 
Davis-Besse's reactor had cracked nozzles and identified 
leakage.[Footnote 26]

* Three of these six reactors had identified circumferential cracking.

* FirstEnergy had not performed a recent visual examination of all of 
its nozzles.

Furthermore, a FirstEnergy manager agreed that cracks and leakage were 
likely.

NRC has the authority to shut down a plant when it is clear that the 
plant is in violation of important safety requirements, and it is clear 
that the plant poses a risk to public health and safety.[Footnote 27] 
Thus, if a licensee is not complying with technical specifications, 
such as those for no allowable reactor vessel pressure boundary 
leakage, NRC can order a plant to shut down. However, NRC decided that 
it could not require Davis-Besse to shut down on the basis of other 
plants' cracked nozzles and identified leakage or the manager's 
acknowledgement of a probable leak. Instead, it believed it needed more 
direct, or absolute, proof of a leak to order a shutdown. This standard 
of proof has been questioned. According to the Union of Concerned 
Scientists,[Footnote 28] for example, if NRC needed irrefutable proof 
in every case of suspected problems, the agency would probably never 
issue a shutdown order. In effect, in this case NRC created a Catch-22: 
It needed irrefutable proof to order a shutdown but could not get this 
proof without shutting down the plant and requiring that the reactor be 
inspected.

Despite NRC's responsibility for ensuring that the public is adequately 
protected from accidents at commercial nuclear power plants, NRC does 
not have specific guidance for shutting down a plant when the plant may 
pose a risk to public health and safety, even though it may be 
complying with NRC requirements. It also has no specific guidance or 
standards for quality of evidence needed to determine that a plant may 
pose an undue risk. Lacking direct or absolute proof of leakage at 
Davis-Besse, NRC instead drafted a shutdown order on the basis that a 
potentially hazardous condition may have existed at the plant. NRC had 
no guidance for developing such a shutdown order, and therefore, it 
used its guidance for reviewing license amendment requests. NRC 
officials recognized that this guidance was not specifically designed 
to determine whether NRC should shut down a power plant such as Davis-
Besse. However, NRC officials stated that this guidance was the best 
available for deciding on a shutdown because, although the review was 
not to amend a license, the factors that NRC needed to consider in 
making the decision and that were contained in the guidance were 
applicable to the Davis-Besse situation.

To use its guidance for reviewing license amendment requests, NRC first 
determined that the situation at Davis-Besse posed a special 
circumstance because new information revealed a substantially greater 
potential for a known hazard to occur, even if Davis-Besse was in 
compliance with the technical specification for leakage from the 
reactor coolant pressure boundary. The special circumstance stemmed 
from NRC's determination that requirements for conducting vessel head 
inspections were not sufficient to detect nozzle cracking and, thus, 
small leaks.[Footnote 29] According to NRC officials, this 
determination allowed NRC to use its guidance for reviewing license 
amendment requests when deciding whether to order a shutdown.

The Extent of NRC's Reliance on License Amendment Guidance Is Not 
Clear: 

Under NRC's license amendment guidance, NRC considers how the license 
change affects risk, but not how it has previously assessed licensee 
performance, such as whether the licensee was viewed as a good 
performer. With regard to the Davis-Besse decision, the guidance 
directed NRC to determine whether the plant would comply with five NRC 
safety principles if it operated beyond December 2001 without 
inspecting the reactor vessel head. As applied to Davis-Besse, these 
principles were whether the plant would (1) continue to meet 
requirements for vessel head inspections, (2) maintain sufficient 
defense-in-depth, (3) maintain sufficient safety margins, (4) have 
little increase in the likelihood of a core damage accident, and (5) 
monitor the vessel head and nozzles. The guidance, however, does not 
specify how to apply these safety principles, how NRC can demonstrate 
it has followed the principles and ensured they are met, or whether any 
one principle takes precedence over the others. The guidance also does 
not indicate what actions NRC or licensees should take if some or all 
of the principles are not met.

In mid-September 2001, NRC staff concluded that Davis-Besse complied 
with the first safety principle but did not meet the remaining four. 
According to the staff, Davis-Besse did not meet three safety 
principles because the requirements for vessel head inspections were 
not adequate. Specifically, the requirements do not require the 
inspector to remove the insulation above the vessel head, and thus 
allow all of the nozzles to be visually inspected. NRC therefore could 
not ensure that FirstEnergy was maintaining defense-in-depth and 
adequate safety margins or sufficiently monitoring the vessel head and 
nozzles. The staff believed that Davis-Besse did not meet the fourth 
safety principle because the risk estimate of core damage approached an 
unacceptable level and the estimate itself was highly uncertain.

Between early October and the end of November 2001, NRC requested and 
received additional information from FirstEnergy regarding its risk 
estimate of core damage--its PRA estimate--and met with the company to 
determine the basis for the estimate. NRC was also developing its own 
risk estimate, although its numbers kept changing. At some point during 
this time, NRC staff also concluded that the first safety principle was 
probably not being met, although the basis for this conclusion is not 
known.

At the end of November 2001, NRC contacted FirstEnergy and informed it 
that a shutdown order had been forwarded to the NRC commissioners and 
asked if FirstEnergy could take any actions that would persuade NRC to 
not issue the shutdown order. The following day, FirstEnergy proposed 
measures to mitigate the potential for and consequences of an accident. 
These measures included, among other things, lowering the operating 
temperature from 605 degrees Fahrenheit to 598 degrees Fahrenheit to 
reduce the driving force for stress corrosion cracking on the nozzles, 
identifying a specific operator to initiate emergency cooling in 
response to an accident, and moving the scheduled refueling outage up 
from March 31, 2002, to no later than February 16, 2002. NRC staff 
discussed these measures, and NRC management asked the staff if they 
were concerned about extending Davis-Besse's operations until mid-
February 2002. While some of the staff were concerned about continued 
operations, none indicated to NRC management that cracking in control 
rod drive mechanism nozzles was likely extensive enough to cause a 
nozzle to eject from the vessel head, thus making it unsafe to operate. 
NRC formally accepted FirstEnergy's compromise proposal within several 
days, thus abandoning its shutdown order.

NRC Did Not Fully Explain or Document the Basis for Its Decision: 

We could not fully assess NRC's basis for accepting FirstEnergy's 
proposal. NRC did not document its deliberations, even though its 
guidance requires that it do so. This documentation is to include the 
data, methods, and assessment criteria used; the basis for the 
decisions made; and essential correspondence sufficient to document the 
persons, places, and matters dealt with by NRC. Specifically, the 
guidance requires that the documentation contain sufficient detail to 
make possible a "proper scrutiny" of NRC decisions by authorized 
outside agencies and provide evidence of how basic decisions were 
formed, including oral decisions. NRC's guidance also states that NRC 
should document all important staff meetings.

In reviewing NRC's documentation on the Davis-Besse decision, we found 
no evidence of an in-depth or formal analysis of how Davis-Besse's 
proposed measures would affect the plant's ability to satisfy the five 
safety principles. Thus, it is unclear whether the safety principles 
contained in the guidance were met by the measures that FirstEnergy 
proposed. However, several NRC officials stated that FirstEnergy's 
proposed measures had no impact on plant operations or safety. For 
example, according to one NRC official, FirstEnergy's proposal to 
reduce the operating temperature would have had little impact on safety 
because the small drop in operating temperature over a 7-week period 
would have had little effect on the growth rate of any cracks in a 
nozzle. As such, this official considered the measures as "window 
dressing." A proposed measure that NRC staff did consider as having a 
significant impact on the risk was for FirstEnergy to dedicate an 
operator for manually turning on safety equipment in the event that a 
nozzle was ejected. Subsequent to approving the delayed shutdown, NRC 
learned that FirstEnergy had not, in fact, planned to dedicate an 
operator for this task--rather, FirstEnergy planned to have an operator 
do this task in addition to other regularly assigned duties.

According to an NRC official, once NRC decided not to issue a shutdown 
order for December 2001, NRC staff needed to discuss how NRC's 
assessment of whether the five safety principles had been met had 
changed in the course of the staff's deliberations. However, there was 
no evidence in the agency's records to support that this discussion was 
held, and other key meetings, such as the one in which the agency made 
its decision to allow Davis-Besse to operate past December 31, 2001, 
were not documented. Without documentation, it is not clear what 
factors influenced NRC's decision. For example, according to the NRC 
Office of the Inspector General's December 2002 report that examined 
the Davis-Besse incident, NRC's decision was driven in large part by a 
desire to lessen the financial impact on FirstEnergy that would result 
from an early shutdown.[Footnote 30] While NRC disputed this finding, 
we found no evidence in the agency's records to support or refute its 
position.

In December 2001, when NRC informed FirstEnergy that it accepted the 
company's proposed measures and the February 16, 2002, shutdown date, 
it also said that the company would receive NRC's assessment in the 
near future. However, NRC did not provide the assessment until a full 
year later--in December 2002. In addition, the December 2002 
assessment, which includes a four-page evaluation, does not fully 
explain how the safety principles were used or met--other than by 
stating that if the likelihood of nozzle failure were judged to be 
small, then adequate protection would be ensured. Even though NRC's 
regulations regarding the reactor coolant pressure boundary dictate 
that the reactor have an extremely low probability of failing, NRC 
stated it did not believe that Davis-Besse needed to demonstrate strict 
conformance with this regulation. As evidence of the small likelihood 
of failure, NRC cited the small size of cracks found at other power 
plants, as well as its preliminary assessment of nozzle cracking, which 
projected crack growth rates. NRC concluded that 7 weeks of additional 
operation would not result in an appreciable increase in the size of 
the cracks.[Footnote 31] While NRC included its calculated estimates of 
the risk that Davis-Besse would pose, it did not detail how it 
calculated its estimates.

NRC's PRA Estimate Was Flawed and Its Use in Deciding to Delay the 
Shutdown Is Unclear: 

In moving forward with its more risk-informed regulatory approach, NRC 
has established a policy to increase the use of PRA methods as a means 
to promote regulatory stability and efficiency. Using PRA methods, NRC 
and the nuclear power industry can estimate the likelihood that 
different accident scenarios at nuclear power plants will result in 
reactor core damage and a release of radioactive materials. For 
example, one of these accident scenarios begins with a "medium break" 
loss-of-coolant accident in which the reactor coolant system is 
breached and a midsize--about 2-to 4-inch--hole is formed that allows 
coolant to escape from the reactor pressure boundary. The probability 
of such an accident scenario occurring and the consequences of that 
accident take into account key engineering safety system failure rates 
and human error probabilities that influence how well the engineered 
systems would be able to mitigate the consequences of an accident and 
ensure no radioactive release from the plant.

For Davis-Besse, NRC needed two estimates: one for the frequency of a 
nozzle ejecting and causing a loss-of-coolant accident and one for the 
probability that a loss-of-coolant accident would result in core 
damage. NRC first established an estimate, based partially on 
information provided by FirstEnergy, for the frequency of a plant 
developing a cracked nozzle that would initiate a medium break loss-of-
coolant accident. NRC estimated that the frequency of this occurring 
would be about 2x10^-2, or 1 chance in 50,[Footnote 32] per year. NRC 
then used an estimate, which FirstEnergy provided, for the probability 
of core damage given a medium break loss-of-coolant accident. This 
probability estimate was 2.7x10^-3, or about 1 chance in 370.[Footnote 
33] Multiplying these two numbers, NRC estimated that the potential for 
a nozzle to crack and cause a loss-of-coolant accident would increase 
the frequency of core damage at Davis-Besse by about 5.4x10^-5per year, 
or about 1 in 18,500 per year.[Footnote 34] Converting this frequency 
to a probability associated with continued operation for 7 weeks, NRC 
calculated that the increase in the probability of core damage was 
approximately 5x10^--6 or 1 chance in 200,000.[Footnote 35] While NRC 
officials currently disagree that this was the number it used, this is 
the number that it included in its December 2002 assessment provided to 
FirstEnergy. Further, we found no evidence in the agency's records to 
support NRC's current assertion.

According to our consultants, the way NRC calculated and used the PRA 
estimate was inadequate in several respects. (See app. II for the 
consultants' detailed report.) First, NRC's calculations did not take 
into account several factors, such as the possibility of corrosion and 
axial cracking that could lead to leakage. For example, the consultants 
concluded that NRC's estimate of risk was incorrectly too small, 
primarily because the calculation did not consider corrosion of the 
vessel head. In reviewing how NRC developed and used its PRA estimates 
for Davis-Besse, our consultants noted that the calculated risk was 
smaller than it should have been because the calculations did not 
consider corrosion of the reactor vessel from the boric acid coolant 
leaking through cracks in the nozzles. According to the consultants, 
apparently all NRC staff involved in the Davis-Besse decision were 
aware that coolant under high pressure was leaking from valves, 
flanges, and possibly from cracks but evidently thought that the 
coolant would immediately flash into steam and noncorrosive compounds 
of boric acid. Our consultants, however, stated that because boric acid 
could potentially cause corrosion, except at temperatures much higher 
than 600 degrees Fahrenheit, NRC should have anticipated that corrosion 
could occur. Our consultants further stated that as evaporation occurs, 
boric acid becomes more concentrated in the remaining liquid--making it 
far more corrosive--and as vapor pressure decreases, evaporation is 
further slowed. They said it should be expected that some of the boric 
acid in the escaping coolant could reach the metal surfaces as wet or 
moist, highly corrosive material underlying the surface layers of dry 
noncorrosive boric acid, which is evidently what happened at Davis-
Besse.

Our consultants concluded that NRC staff should have been aware of the 
experience at French nuclear power plants, where boric acid corrosion 
from leaking reactor coolant had been identified during the previous 
decade, the safety significance had been recognized, and safety 
procedures to mitigate the problem had been implemented. Furthermore, 
tests had been conducted by the nuclear power industry and in 
government laboratories on boric acid corrosion that were widely 
available to NRC. They stated that keeping abreast of safety issues at 
similar plants, whether domestic or foreign, and conveying relevant 
safety information to licensees are important functions of NRC's safety 
program. According to NRC, the agency was aware of the experience at 
French nuclear power plants. For example, NRC concluded, in a December 
15, 1994, internal NRC memo, that primary coolant leakage from a 
through-wall crack could cause boric acid corrosion of the vessel head. 
However, because it concluded that some analyses indicated that it 
would take at least 6 to 9 years before any corrosion would challenge 
the structural integrity of the head, NRC concluded that cracking was 
not a short-term safety issue.

Our consultants also stated that NRC's risk analysis was inadequate 
because the analysis concerned only the formation and propagation of 
circumferential cracks that could result in nozzle failure, loss of 
coolant, and even control rod ejection. Although there is less chance 
of axial cracks causing complete nozzle failure, these cracks open 
additional pathways for coolant leakage. In addition, their long 
crevices provide considerably greater opportunity for the coolant to 
concentrate near the surface of the vessel head. However, according to 
our consultants, NRC was convinced that the boric acid they saw 
resulted from leaking flanges above the reactor vessel head, as opposed 
to axial cracks in the nozzles.

Second, NRC's analysis was inadequate because it did not include the 
uncertainty of its risk estimate and use the uncertainty analysis in 
the Davis-Besse decision-making process, although NRC staff should have 
recognized large uncertainties associated with its risk estimate. Our 
consultants also concluded that NRC failed to take into account the 
large uncertainties associated with estimates of the frequency of core 
damage resulting from the failure of nozzles. PRA estimates for nuclear 
power plants are subject to significant uncertainties associated with 
human errors and other common causes of system component failures, and 
it is important that proper uncertainty analyses be performed for any 
PRA study. NRC guidance and other NRC reports on advancing PRA 
technology for risk-informed decisions emphasize the need to understand 
and characterize uncertainties in PRA estimates. Our consultants stated 
that had the NRC staff estimated the margin of error or uncertainty 
associated with its PRA estimate for Davis-Besse, the uncertainty would 
likely have been so high as to render the estimate of questionable 
value.

Third, NRC's analysis was inadequate because the risk estimates were 
higher than generally considered acceptable under NRC guidance. Despite 
PRA's important role in the decision, our consultants found that NRC 
did not follow its own guidance for ensuring that the estimated risk 
was within levels acceptable to the agency. NRC required the nuclear 
power industry to develop a baseline estimate for how frequently a core 
damage accident could occur at every nuclear power plant in the United 
States. This baseline estimate is used as a basis for deciding whether 
changes at a plant that affect the core damage frequency are 
acceptable. The baseline core damage frequency estimate for the Davis-
Besse plant was between 4x10^-5 and 6.6x10^-5 per year (which is between 
1 chance in 25,000[Footnote 36] per year and about 1 chance in 
15,150[Footnote 37] per year). NRC guidance for reviewing and approving 
license amendment requests indicates that any plant-specific change 
resulting in an increase in the frequency of core damage of 1x10^-5 per 
year (which is 1 chance in 100,000 per year) or more would fall within 
the highest risk zone: In this case, NRC would generally not approve 
the change because the risk criterion would not be met. If a license 
change would result in a core damage frequency change of 1x10^-5per year 
to 1x10^--6er year (which is 1 chance in 100,000 per year to 1 chance in 
1 million per year), the risk criterion would be considered marginally 
met and NRC would consider approving the change but would require 
additional analysis. Finally, if a license change would result in a 
core damage frequency change of 1x10^-6 per year (which is 1 chance in 1 
million per year) or less, the risk would fall within the lowest risk 
zone and NRC would consider the risk criterion to be met and would 
generally consider approving the change without requiring additional 
analysis. (See fig. 6.): 

Figure 6: NRC's Acceptance Guidelines for Core Damage Frequency: 

[See PDF for image]

[A] Risk criterion is met and license changes would generally be 
considered.

[B] Risk criterion is considered marginally met and while license 
changes are generally considered, they require additional analysis.

[C] Risk criterion is not met and license changes are generally not 
allowed.

[End of figure]

However, NRC's PRA estimate for Davis-Besse--an increase in the 
frequency of core damage of 5.4x10^-5, or 1 chance in about 18,500 per 
year--was higher than the acceptable level. While an NRC official who 
helped develop the risk estimate said that additional NRC and industry 
guidance was used to evaluate whether its PRA estimate was acceptable, 
this guidance also suggests that NRC's estimate was too high. NRC's 
estimate of the increase in the frequency of core damage of 5.4x10^-5 
per year equates to an increase in the probability of core damage of 
5x10^-6, or 1 chance in 200,000, for the 7-week period December 31, 
2001, to February 16, 2002.335NRC's guidance for evaluating requests to 
relax NRC technical specifications suggests that a probability increase 
higher than 5x10^-7 or 1 chance in 2 million[Footnote 38], is 
considered unacceptable for relaxing the specifications. Thus, NRC's 
estimate would not be considered acceptable under this guidance. NRC's 
estimate would also not be considered acceptable under Electric Power 
Research Institute or Nuclear Energy Institute guidance unless further 
action were taken to evaluate or manage risk. According to NRC 
officials, NRC viewed its PRA estimate as being within acceptable 
bounds because it was a temporary situation--7 weeks--and NRC had, at 
other times, allowed much higher levels of risk at other plants. 
However, at the time that NRC made its decision, it did not document 
the basis for accepting this risk estimate, even though NRC's guidance 
explicitly states that the decision on whether PRA results are 
acceptable must be based on a full understanding of the contributors to 
the PRA results and the reasoning must be well documented. In defense 
of its decision, NRC officials said that the process they used to 
arrive at the decision is used to make about 1,500 licensing decisions 
such as this each year.

Lastly, NRC's analysis was inadequate because the agency does not have 
clear guidance for how PRA estimates are to be used in the decision-
making process. Our consultants concluded that NRC's process for risk-
informed decision making is ill-defined, lacks guidelines for how it is 
supposed to work, and is not uniformly transparent within NRC. 
According to NRC officials involved in the Davis-Besse decision, NRC's 
guidance is not clear on the use of PRA in the decision-making process. 
For example, while NRC has extensive guidance, this guidance does not 
outline to what extent or how the resultant PRA risk number and 
uncertainty should be weighed with respect to the ultimate decision. 
One factor complicating this issue is the lack of a predetermined 
methodology to weigh risks expressed in PRA numbers against traditional 
deterministic results and other factors.[Footnote 39] Absent this 
guidance, the value assigned to the PRA analysis is largely at the 
discretion of the decision maker. The process, which NRC stated is 
robust, can result in a decision in which PRA played no role, a partial 
role, or one in which it was the sole deciding factor. According to our 
consultants, this situation is made worse by the lack of guidelines for 
how, or by whom, decisions in general are made at NRC.

It is not clear how NRC staff used the PRA risk estimate in the Davis-
Besse decision-making process. For example, according to one NRC 
official who was familiar with some of the data on nozzle cracking, 
these data were not sufficient for making a good probabilistic 
decision. He stated that he favored issuing an order requiring that 
Davis-Besse be shut down by the end of December 2001 because he 
believed the available data were not sufficient to assure a low enough 
probability for a nozzle to be ejected. Other officials indicated that 
they accepted FirstEnergy's proposed February 16, 2002, shutdown date 
based largely on NRC's PRA estimate for a nozzle to crack and be 
ejected. According to one of these officials, allowing the additional 7 
weeks of operating time was not sufficiently risk significant under 
NRC's guidance. He stated that safety margins at the plant were 
preserved and the PRA number was within an acceptable range. Still 
another official said he discounted the PRA estimate and did not use it 
at all when recommending that NRC accept FirstEnergy's compromise 
proposal. This official also stated that it was likely that many of the 
staff did base their conclusions on the PRA estimate. According to our 
consultants, although the extent to which the PRA risk analysis 
influenced the decision making will probably never be known, it is 
apparent that it did play an important role in the decision to allow 
the shutdown delay.

NRC Has Made Progress in Implementing Recommended Changes, but Is Not 
Addressing Important Systemic Issues: 

NRC has made significant progress in implementing the actions 
recommended by the Davis-Besse lessons-learned task force. While NRC 
has implemented slightly less than half--21 of the 51--recommendations 
as of March 2004, it is scheduled to have more than 70 percent of them 
implemented by the end of 2004. For example, NRC has already taken 
actions to improve staff training and inspections that would appear to 
help address the concern that NRC inspectors viewed FirstEnergy as a 
good performer and thus did not subject Davis-Besse to the level of 
scrutiny or questioning that they should have. It is not certain when 
actions to implement the remaining recommendations will occur, in part 
because of resource constraints. NRC also faces challenges in fully 
implementing the recommendations, also in part because of resource 
constraints, both in the staff needed to develop specific corrective 
actions and in the additional staff responsibilities and duties to 
carry them out. Further, while NRC is making progress, the agency is 
not addressing three systemic issues highlighted by the Davis-Besse 
experience: (1) an inability to detect weakness or deterioration in 
FirstEnergy's safety culture, (2) deficiencies in NRC's process for 
deciding on a shutdown, and (3) lack of management controls to track, 
on a longer-term basis, the effectiveness of actions implemented in 
response to incidents such as Davis-Besse, so that they do not occur at 
another power plant.

NRC Does Not Expect to Complete Its Actions until 2006, in Part Because 
of Resource Constraints: 

NRC's lessons-learned task force for Davis-Besse developed 51 
recommendations to address the weaknesses that contributed to the 
Davis-Besse incident. Of these 51 recommendations, NRC rejected 2 
because it concluded that agency processes or procedures already 
provided for the recommendations' intent to be effectively carried 
out.[Footnote 40] To address the remaining 49 recommendations, NRC 
developed a plan in March 2003 that included, for each recommendation, 
the actions to be taken, the responsible NRC office, and the schedule 
for completing the actions. When developing its schedule, NRC placed 
the highest priority on implementing recommendations that were most 
directly related to the underlying causes of the Davis-Besse incident 
as well as those recommendations responding to vessel head corrosion. 
NRC assigned a lower priority to the remaining recommendations, which 
were to be integrated into the planning activities of those NRC offices 
assigned responsibility for taking action on the recommendations. In 
assigning these differing priorities, NRC officials stated they 
recognized that the agency has many other pressing matters to address 
that are not related to the Davis-Besse incident, such as renewing 
operating licenses, and they did not want to divert resources away from 
these activities. (App. III contains a complete list of the task 
force's recommendations, NRC actions, and the status of the 
recommendations as of March 2004.): 

To better track the status of the agency's actions to implement the 
recommendations, we split two of the 49 recommendations that NRC 
accepted into 4; therefore, our analysis reflects NRC's response to 51 
recommendations. As shown in table 1, as of March 2004, NRC had made 
progress in implementing the recommendations, although some completion 
dates have slipped.

Table 1: Status of Davis-Besse Lessons-Learned Task Force 
Recommendations, as of March 2004: 

Status: Completed as of March 2004; 
Number of recommendations: 21.

Status: Scheduled for completion April through December 2004; 
Number of recommendations: 17.

Status: Scheduled for completion in 2005; 
Number of recommendations: 6.

Status: Completion date yet to be determined; 
Number of recommendations: 7.
Total; 
Number of recommendations: 51.

Source: GAO analysis of NRC data.

Note: This table does not include the two recommendations NRC rejected.

[End of table]

As the table shows, as of March 2004, NRC had implemented 21 
recommendations and scheduled another 17 for completion by December 
2004. However, some slippage has already occurred in this schedule--
primarily because of resource constraints--and NRC has rescheduled 
completion of some recommendations. NRC's time frames for completing 
the recommendations depend on several factors--the recommendations' 
priority, the amount of work required to develop and implement actions, 
and the need to first complete actions on other related 
recommendations.

Of the 21 implemented recommendations, 10 called upon NRC to revise or 
enhance its inspection guidance or training. For example, NRC revised 
the guidance it uses to assess the implementation of licensees' 
programs to identify and resolve problems before they affect 
operations. It took this action because the task force had concluded 
that FirstEnergy's weak corrective action program implementation was a 
major contributor to the Davis-Besse incident. NRC has also developed 
Web-based training modules to improve NRC inspectors' knowledge of 
boric acid corrosion and nozzle cracking. The other 11 completed 
recommendations concerned actions such as: 

* collecting and analyzing foreign and domestic information on alloy 
600 nozzle cracking,

* fully implementing and revising guidance to better assure that 
licensees carry out their commitments to make operational changes, and: 

* establishing measurements for resident inspector staffing levels and 
requirements.

By the end of 2004, NRC expects to complete another 17 recommendations, 
12 of which generally address broad oversight or programmatic issues, 
and 5 of which provide for additional inspection guidance and training. 
On the broader issues, for example, NRC is scheduled to complete a 
review of the effectiveness of its response to past NRC lessons-learned 
task force reports by April 2004. By December 2004, NRC expects to have 
a framework established for moving forward with implementing 
recommended improvements to its agencywide operating experience 
program.

In 2005, 4 of the 6 recommendations scheduled for completion concern 
leakage from the reactor coolant system. For example, NRC is to (1) 
develop guidance and criteria for assessing licensees' responses to 
increasing leakage levels and (2) determine whether licensees should 
install enhanced systems to detect leakage from the reactor coolant 
system. The fifth recommendation calls for NRC to inspect the adequacy 
of licensees' programs for controlling boric acid corrosion, and the 
final recommendation calls on NRC to assess the basis for canceling a 
series of inspection procedures in 2001.

NRC did not assign completion dates to 7 recommendations because, among 
other things, their completion depends on completing other 
recommendations or because of limited resources. Even though it has not 
assigned completion dates for these recommendations, NRC has begun to 
work on 5 of the 7: 

* Two recommendations will be addressed when requirements for vessel 
head inspections are revised. To date, NRC has taken some related, but 
temporary, actions. For example, since February 2003, it has required 
licensees to more extensively examine their reactor vessel heads. NRC 
has also issued a series of temporary instructions for NRC inspectors 
to oversee the enhanced examinations. NRC expects to replace these 
temporary steps with revised requirements for vessel head inspections.

* Two recommendations call upon NRC to revise requirements for 
detecting leaks in the reactor coolant pressure boundary. In response, 
NRC has, for example, begun to review its barrier integrity 
requirements and has contracted for research on enhanced detection 
capabilities.

* One recommendation is directed at improving follow-up of licensee 
actions taken in response to NRC generic communications. NRC is 
currently developing a temporary inspection procedure to assess the 
effectiveness of licensee actions taken in response to generic 
communications. Additionally, as a long-term change in the operating 
experience program, the agency plans to improve the verification of how 
effective its generic communications are.

The remaining two recommendations address NRC's need to (1) evaluate 
the adequacy of methods for analyzing the risks posed by passive 
components, such as reactor vessels, and integrate these methods and 
risks into NRC's decision-making process and (2) review a sample of 
plant assessments conducted between 1998 and 2000 to determine if any 
identified plant safety issues have not been adequately assessed. NRC 
has not yet taken action on these recommendations.

Some recommendations will require substantial resources to develop and 
implement. As a result, some implementation dates have slipped and some 
plans in response to the recommendations have changed in scope. For 
example, owing to resource constraints, NRC has postponed indefinitely 
the evaluation of methods to analyze the risk associated with passive 
reactor components such as the vessel head. Also, in part due to 
resource constraints, NRC has reconceptualized its plan to review 
licensee actions in response to previous generic communications, such 
as bulletins and letters.

Staff resources will be strained because implementing the 
recommendations adds additional responsibilities or duties--that is, 
more inspections, training, and reviews of licensee reports. For 
example, NRC's revised inspection guidance for more thorough 
examinations of reactor vessel heads and nozzles, as well as new 
requirements for NRC oversight of licensees' corrective action 
programs, will require at least an additional 200 hours of inspection 
per reactor per year. As of February 2004, NRC was also revising other 
inspection requirements that are likely to place additional demands on 
inspectors' time. Thus, to respond to these increased demands, NRC will 
either need to add inspectors or reduce oversight of other licensee 
activities.

To its credit, in its 2004 budget plan, NRC increased the level of 
resources for some inspection activities. However, it is not certain 
that these increases will be maintained. The number of inspection hours 
has fallen by more than one-third between 1995 and 2001. In addition, 
NRC is aware that resident inspector vacancies are filled with staff 
having varying levels of experience--from the basic level that would be 
expected from a newly qualified inspector to the advanced level that is 
achieved after several years' experience. According to the latest 
available data, as of May 2003, about 12 percent of sites had only one 
resident inspector; the remaining 88 percent had two inspectors of 
varying levels of experience. Because of this situation, NRC augments 
these inspection resources with regional inspectors and contractors to 
ensure that, at a minimum, its baseline inspection program can be 
implemented throughout the year. Because of surges in the demand for 
inspections, NRC in 2003 increased its use of contractors and 
temporarily pulled qualified inspectors from other jobs to help 
complete the baseline inspection program for every plant. According to 
NRC, it did not expect to require such measures in 2004.

Similarly, NRC may require additional staff to identify and evaluate 
plants' operating experiences and communicate the results to licensees, 
as the task force recommended. NRC has currently budgeted an increase 
of three full-time staff in fiscal year 2006 to implement a centralized 
system, or clearinghouse, for managing the operating experience 
program. However, according to an NRC official, questions remain about 
the level of resources needed to fully implement the task force 
recommendations. NRC's operating experience office, before it was 
disbanded in 1999, had about 33 staff whose primary responsibility was 
to collect, evaluate, and communicate activities associated with safety 
performance trends, as reflected in licensees' operating experiences, 
and participate in developing rulemakings. However, it is too early to 
know the effectiveness of this clearinghouse approach and the adequacy 
of resources in the other offices available for collecting and 
analyzing operating experience information. Neither the operating 
experience office before it was disbanded nor the other offices flagged 
boric acid corrosion, cracking, or leakage as problems warranting 
significantly greater oversight by NRC, licensees, or the nuclear power 
industry.

NRC Has Not Proposed Any Specific Actions to Correct Systemic 
Weaknesses in Oversight and Decision-Making Processes: 

NRC's Davis-Besse task force did not make any recommendations to 
address two systemic problems: evaluating licensees' commitment to 
safety and improving the agency's process for deciding on a shutdown.

NRC's Task Force Recommendations Did Not Address Licensee Safety 
Culture: 

NRC's task force identified numerous problems at Davis-Besse that 
indicated human performance and management failures and concluded that 
FirstEnergy did not foster an environment that was fully conducive to 
ensuring that plant safety issues received appropriate attention. 
Although the task force report did not use the term safety culture, as 
evidence of FirstEnergy's safety culture problems, the task force 
pointed to: 

* an imbalance between production and safety, as evidenced by 
FirstEnergy's efforts to address symptoms (such as regular cleanup of 
boric acid deposits) rather than causes (finding the source of the 
leaks during refueling outages);

* a lack of management involvement in or oversight of work at Davis-
Besse that was important for maintaining safety;

* a lack of a questioning attitude by senior FirstEnergy managers with 
regard to vessel head inspections and cleaning activities;

* ineffective and untimely corrective action;

* a long-standing acceptance of degraded equipment; and: 

* inadequate engineering rigor.

The task force concluded that NRC's implementation of guidance for 
inspecting and assessing a safety-conscious work environment and 
employee concerns programs failed to identify significant safety 
problems. Although the task force did not make any specific 
recommendations that NRC develop a means to assess licensees' safety 
culture, it did recommend changes to focus more effort on assessing 
programs to promote a safety-conscious work environment.

NRC has taken little direct action in response to this task force 
recommendation. However, to help enhance NRC's capability to assess 
licensee safety culture by indirect means, NRC modified the wording in, 
and revised its inspection procedure for, assessing licensees' ability 
to identify and resolve problems, such as malfunctioning plant 
equipment. These revisions included requiring inspectors to: 

* review all licensee reports on plant conditions,

* analyze trends in plant conditions to determine the existence of 
potentially significant safety issues, and: 

* expand the scope of their reviews to the prior 5 years in order to 
identify recurring issues.

This problem identification and resolution inspection procedure is 
intended to assess the end results of management's safety commitment 
rather than the commitment itself. However, by measuring only the end 
results, early signs of a deteriorating safety culture and declining 
management performance may not be readily visible and may be hard to 
interpret until clear violations of NRC's regulations occur. 
Furthermore, because NRC directs its inspections at problems that it 
recognizes as being more important to safety, NRC may overlook other 
problems until they develop into significant and immediate safety 
problems. Conditions at a plant can quickly degrade to the extent that 
they can compromise public health and safety.

The International Atomic Energy Agency and its member nations have 
developed guidance and procedures for assessing safety culture at 
nuclear power plants, and today several countries, such as Brazil, 
Canada, Finland, Sweden, and the United Kingdom, assess plant safety 
culture or licensees' own assessments of their safety culture.[Footnote 
41] In assessing safety culture, an advisory group to the agency 
suggests that regulatory agencies examine whether, for example, (1) 
employee workloads are not excessive, (2) staff training is sufficient, 
(3) responsibility for safety has been clearly assigned within the 
organization, (4) the corporation has clearly communicated its safety 
policy, and (5) managers sufficiently emphasize safety during plant 
meetings. One reason for assessing safety culture, according to the 
Canadian Nuclear Safety Commission, is because management and human 
performance aspects are among the leading causes of unplanned events at 
licensed nuclear facilities, particularly in light of pressures such as 
deregulation of the electricity market. Finland specifically requires 
that nuclear power plants maintain an advanced safety culture and its 
inspections target the importance that has been embedded in factors 
affecting safety, including management. NRC had begun considering 
methods for assessing organizational factors, including safety culture, 
but in 1998, NRC's commissioners decided that the agency should have a 
performance-based inspection program of overall plant performance and 
should infer licensee management performance and competency from the 
results of that program. They chose this approach instead of one of 
four other options: 

* conduct performance-based inspections in all areas of facility 
operation and design, but not infer or articulate conclusions regarding 
the performance of licensee management;

* assess the performance of licensee management through targeted 
operations-based inspections using specific inspection procedures, 
trained staff, and contractors to assess licensee management--a task 
that would require the development of inspection procedures and 
significant training--and to document inspection results;

* assess the performance of licensee management as part of the routine 
inspection program by specifically evaluating and documenting 
management performance attributes--a larger effort that would require 
the development of assessment tools to evaluate safety culture as well 
as additional resources; or: 

* assess the competency of licensee management by evaluating management 
competency attributes--an even larger effort that would require that 
implementation options and their impacts be assessed.

When adopting the proposal to infer licensee management performance 
from the results of its performance-based inspection program, NRC 
eliminated any resource expenditures specifically directed at 
developing a systematic method of inferring management performance and 
competency. NRC stated that it currently has a number of means to 
assess safety culture that provide indirect insights into licensee 
safety culture. These means include, for example, (1) insights from 
augmented inspection teams, (2) lessons-learned reviews, and (3) 
information obtained in the course of conducting inspections under the 
Reactor Oversight Process. However, insights from augmented inspection 
teams and lessons-learned reviews are reactionary and do not prevent 
problems such as those that occurred at Davis-Besse. Further, before 
the Davis-Besse incident, NRC assumed its oversight process would 
adequately identify problems with licensees' safety culture. However, 
NRC has no formalized process for collectively assessing information 
obtained in the course of its problem identification and resolution 
inspection to ensure that individual inspection results would identify 
poor management performance. NRC stated that its licensee assessments 
consider inputs such as inspection results and insights, correspondence 
to licensees related to inspection observations, input from resident 
inspectors, and the results of any special investigations. However, 
this information may not be sufficient to inform NRC of problems at a 
plant in advance of these problems becoming safety significant.

In part because of Davis-Besse, NRC's Advisory Committee on Reactor 
Safeguards[Footnote 42] recommended that NRC again pursue the 
development of a methodology for assessing safety culture. It also 
asked NRC to consider expanding research to identify leading indicators 
of degradation in human performance and work to develop a consistent 
comprehensive methodology for quantifying human performance. During an 
October 2003 public meeting of the advisory committee's Human 
Performance Subcommittee, the subcommittee's members again reiterated 
the need for NRC to assess safety culture. Specifically, the members 
recognized that certain aspects of safety culture, such as beliefs, 
perceptions, and management philosophies, are ultimately the nuclear 
power industry's responsibility but stated that NRC should deal with 
patterns of behavior and human performance, as well as organizational 
structures and processes. At this meeting, NRC officials discussed 
potential safety culture indicators that NRC could use, including, 
among other things, how many times a problem recurs at a plant, 
timeliness in correcting problems, number of temporary modifications, 
and individual program and process error rates. Committee members 
recommended that NRC test various safety culture indicators to 
determine whether (1) such indicators should ultimately be incorporated 
into the Reactor Oversight Process and (2) a significance determination 
process could be developed for safety culture. As of March 2004, NRC 
had yet to respond to the advisory committee's recommendation.

Despite the lack of action to address safety culture issues, NRC's 
concern over FirstEnergy's safety culture at Davis-Besse was one of the 
last issues resolved before the agency approved Davis-Besse's restart. 
NRC undertook a series of inspections to examine Davis-Besse's safety 
culture and determine whether FirstEnergy had (1) correctly identified 
the underlying causes associated with its declining safety culture, (2) 
implemented appropriate actions to correct safety culture problems, and 
(3) developed a process for monitoring to ensure that actions taken 
were effective for resolving safety culture problems. In December 2003, 
NRC noted significant improvements in the safety culture at Davis-
Besse, but expressed concern with the sustainability of Davis-Besse's 
performance in this area. For example, a survey of FirstEnergy and 
contract employees conducted by FirstEnergy in November 2003 indicated 
that about 17 percent of employees believed that management cared more 
about cost and schedule than resolving safety and quality issues--
again, production over safety.

NRC's Task Force Recommendations Did Not Address NRC's Decision-Making 
Process: 

NRC's task force also did not analyze NRC's process for deciding not to 
order a shutdown of the Davis-Besse plant. It noted that NRC's written 
rationale for accepting FirstEnergy's justification for continued plant 
operation had not yet been prepared and recommended that NRC change 
guidance requiring NRC to adequately document such decisions. It also 
made a recommendation to strengthen guidance for verifying information 
provided by licensees. According to an NRC official on the task force, 
the task force did not assess the decision-making process in detail 
because the task force was charged with determining why the degradation 
at Davis-Besse was not prevented and because NRC had coordinated with 
NRC's Office of the Inspector General, which was reviewing NRC's 
decision making.

NRC's Failure to Track the Resolution of Identified Problems May Allow 
the Problems to Recur: 

The NRC task force conducted a preliminary review of prior lessons-
learned task force reports to determine whether they suggested any 
recurring or similar problems. As a result of this preliminary review, 
the task force recommended that a more detailed review be conducted to 
determine if actions that NRC took as a result of those reviews were 
effective. These previous task force reports included: Indian Point 2 
in Buchanan, New York, in February 2000; Millstone in Waterford, 
Connecticut, in October 1993; and South Texas Project in Wadsworth, 
Texas, from 1988 to 1994.[Footnote 43] NRC's more detailed review, as 
of May 2004, was still under way. We also reviewed these reports to 
determine whether they suggested any recurring problems and found that 
they highlighted broad areas of continuing programmatic weaknesses, as 
seen in the following examples: 

* Inspector training and information sharing. All three of the other 
task forces also identified inspector training issues and problems with 
information collection and sharing. The Indian Point task force called 
upon NRC to develop a process for promptly disseminating technical 
information to NRC inspectors so that they can review and apply the 
information in their inspection program.

* Oversight of licensee corrective action programs. Two of the three 
task forces also identified inadequate oversight of licensee corrective 
action programs. The South Texas task force recommended improving 
assessments of licensees' corrective action programs to ensure that NRC 
identifies broader licensee problems.

* Better identification of problems. Two of the three task force 
reports also noted the need for NRC to develop a better process for 
identifying problem plants, and one report noted the need for NRC 
inspectors to more aggressively question licensees' activities.

Over the past two decades, we have also reported on underlying causes 
similar to those that contributed, in part, to the incident at Davis-
Besse. (See Related GAO Products.) For example, with respect to the 
safety culture at nuclear power plants, in 1986, 1995, and 1997, we 
reported on issues relevant to NRC assessing plant management so that 
significant problems could be detected and corrected before they led to 
incidents such as the one that later occurred at Davis-Besse. 
Regardless of our 1997 recommendation that NRC require that the 
assessment of management's competency and performance be a mandatory 
component of NRC's inspection process, NRC subsequently withdrew 
funding to accomplish this. In terms of inspections, in 1995 we 
reported that NRC, itself, had concluded that the agency was not 
effectively integrating information on previously identified and long-
standing issues to determine if the issues indicated systemic 
weaknesses in plant operations. This report further noted that NRC was 
not using such information to focus future inspection activities. In 
1997 and 2001, we reported on weaknesses in NRC's inspections of 
licensees' corrective action programs. Finally, with respect to 
learning from plants' operating experiences, in 1984 we noted that NRC 
needed to improve its methods for consolidating information so that it 
could evaluate safety trends and ensure that generic issues are 
resolved at individual plants. These recurring issues indicate that 
NRC's actions, in response to individual plant incidents and 
recommendations to improve oversight, are not always institutionalized.

NRC guidance requires that resolutions to action plans be described and 
documented, and while NRC is monitoring the status of actions taken in 
response to Davis-Besse task force recommendations and preparing 
quarterly and semiannual reports on the status of actions taken, the 
Davis-Besse action plan does not specify how long NRC will monitor 
them. It also does not describe how long NRC will prepare quarterly and 
semiannual status reports, even though, according to NRC officials, 
these semiannual status reports will continue until all items are 
completed and the agency is required to issue a final summary report. 
The plan also does not specify what criteria the agency will use to 
determine when the actions in response to specific task force 
recommendations are completed. Furthermore, NRC's action plan does not 
require NRC to assess the long-term effectiveness of recommended 
actions, even though, according to NRC officials, some activities 
already have an effectiveness review included. As in the past and in 
response to prior lessons-learned task force reports and 
recommendations, NRC has no management control in place for assessing 
the long-term effectiveness of efforts resulting from the 
recommendations. NRC officials acknowledged the need for a management 
control, such as an agencywide tracking system, to ensure that actions 
taken in response to task force recommendations effectively resolve the 
underlying issue over the long term, but the officials have no plans to 
establish such a system.

Conclusions: 

It is unlikely, given the actions that NRC has taken to date, that 
extensive reactor vessel corrosion will occur any time soon at another 
domestic nuclear power plant. However, we do not yet have adequate 
assurances from NRC that many of the factors that contributed to the 
incident at Davis-Besse will be fully addressed. These factors include 
NRC's failure to keep abreast of safety significant issues by 
collecting information on operating experiences at plants, assessing 
their relative safety significance, and effectively communicating 
information within the agency to ensure that oversight is fully 
informed. The underlying causes of the Davis-Besse incident underscore 
the potential for another incident unrelated to boric acid corrosion or 
cracked control rod drive mechanism nozzles to occur. This potential is 
reinforced by the fact that both prior NRC lessons-learned task forces 
and we have found similar weaknesses in many of the same NRC programs 
that led to the Davis-Besse incident. NRC has not followed up on prior 
task force recommendations to assess whether the lessons learned were 
institutionalized. NRC's actions to implement the Davis-Besse lessons-
learned task force recommendations, to be fully effective, will require 
an extensive effort on NRC's part to ensure that these are effectively 
incorporated into the agency's processes. However, NRC has not 
estimated the amount of resources necessary to carry out these 
recommendations, and we are concerned that resource limitations could 
constrain their effectiveness. For this reason, it is important for NRC 
to not only monitor the implementation of Davis-Besse task force 
recommendations, but also determine their effectiveness, in the long 
term, and the impact that resource constraints may have on them. These 
actions are even more important because the nation's fleet of nuclear 
power plants is aging.

Because the Davis-Besse task force did not address NRC's unwillingness 
to directly assess licensee safety culture, we are concerned that NRC's 
oversight will continue to be reactive rather than proactive. NRC's 
oversight can result in NRC making a determination that a licensee's 
performance is good one day, yet the next day NRC discovers the 
performance to be unacceptably risky to public health and safety. Such 
a situation does not occur overnight: Long-standing action or inaction 
on the part of the licensee causes unacceptably risky and degraded 
conditions. NRC needs better information to preclude such conditions. 
Given the complexity of nuclear power plants, the number of physical 
structures, systems, and components, and the manner in which NRC 
inspectors must sample to assess whether licensees are complying with 
NRC requirements and license specifications, it is possible that NRC 
will not identify licensees that value production over safety. While we 
recognize the difficulty in assessing licensee safety culture, we 
believe it is sufficiently important to develop a means to do so.

Given the limited information NRC had at the time and that an accident 
did not occur during the delay in Davis-Besse's shutdown, we do not 
necessarily question the decision the agency made. However, we are 
concerned about NRC's process for making that decision. It used 
guidance intended to make decisions for another purpose, did not 
rigorously apply the guidance, established an unrealistically high 
standard of evidence to issue a shutdown order, relied on incomplete 
and faulty PRA analyses and licensee evidence, and did not document key 
decisions and data. It is extremely unusual for NRC to order a nuclear 
power plant to shut down. Given this fact, it is more imperative that 
NRC have guidance to use when technical specifications or requirements 
may be met, yet questions arise over whether sufficient safety is being 
maintained. This guidance does not need to be a risk-based approach, 
but rather a more structured risk-informed approach that is 
sufficiently flexible to ensure that the guidance is applicable under 
different circumstances. This is important because NRC annually makes 
about 1,500 licensing decisions relating to operating commercial 
nuclear power plants. While we recognize the challenges NRC will face 
in developing such guidance, the large number and wide variety of 
decisions strongly highlight the need for NRC to ensure that its 
decision-making process and decisions are sound and defensible.

Recommendations for Executive Action: 

To ensure that NRC aggressively and comprehensively addresses the 
weaknesses that contributed to the Davis-Besse incident and could 
contribute to problems at nuclear power plants in the future, we are 
recommending that the NRC commissioners take the following five 
actions: 

* Determine the resource implications of the task force's 
recommendations and reallocate the agency's resources, as appropriate, 
to better ensure that NRC effectively implements the recommendations.

* Develop a management control approach to track, on a long-term basis, 
implementation of the recommendations made by the Davis-Besse lessons-
learned task force and future task forces. This approach, at a minimum, 
should assign accountability for implementing each recommendation and 
include information on the status of major actions, how each 
recommendation will be judged as completed, and how its effectiveness 
will be assessed. The approach should also provide for regular--
quarterly or semiannual--reports to the NRC commissioners on the status 
of and obstacles to full implementation of the recommendations.

* Develop a methodology to assess licensees' safety culture that 
includes indicators of and inspection information on patterns of 
licensee performance, as well as on licensees' organization and 
processes. NRC should collect and analyze this data either during the 
course of the agency's routine inspection program or during separate 
targeted assessments, or during both routine and targeted inspections 
and assessments, to provide an early warning of deteriorating or 
declining performance and future safety problems.

* Develop specific guidance and a well-defined process for deciding on 
when to shut down a nuclear power plant. The guidance should clearly 
set out the process to be used, the safety-related factors to be 
considered, the weight that should be assigned to each factor, and the 
standards for judging the quality of the evidence considered.

* Improve NRC's use of probabilistic risk assessment estimates in 
decision making by (1) ensuring that the risk estimates, uncertainties, 
and assumptions made in developing the estimates are fully defined, 
documented, and communicated to NRC decision makers; and (2) providing 
guidance to decision makers on how to consider the relative importance, 
validity, and reliability of quantitative risk estimates in conjunction 
with other qualitative safety-related factors.

Agency Comments and Our Evaluation: 

We provided a draft of this report to NRC for review and comment. We 
received written comments from the agency's Executive Director for 
Operations. In its written comments, NRC generally addressed only those 
findings and recommendations with which it disagreed. Although 
commenting that it agreed with many of the report's findings, NRC 
expressed an overall concern that the report does not appropriately 
characterize or provide a balanced perspective on NRC's actions 
surrounding the discovery of the Davis-Besse reactor vessel head 
condition or NRC's actions to incorporate the lessons learned from that 
experience into its processes. Specifically, NRC stated that the report 
does not acknowledge that NRC must rely heavily on its licensees to 
provide it with complete and accurate information, as required by its 
regulations. NRC also expressed concern about the report's 
characterization of its use of risk estimates--specifically the 
report's statement that NRC's estimate of risk exceeded the risk levels 
generally accepted by the agency. In addition, NRC disagreed with two 
of our recommendations: (1) to develop specific guidance and a well-
defined process for deciding on when to shut down a plant and (2) to 
develop a methodology to assess licensees' safety culture.

With respect to NRC's overall concern, we believe that the report 
accurately captures NRC's performance. Our draft report, in discussing 
NRC's regulatory and oversight role and responsibilities, stated that 
according to NRC, the completeness and accuracy of the information 
provided by licensees is an important aspect of the agency's oversight. 
To respond further to NRC's concern, we added a statement to the effect 
that licensees are required under NRC's regulations to provide the 
agency with complete and accurate information. While we do not want to 
diminish the importance of this responsibility on the part of the 
licensees, we believe that NRC also has a responsibility, in designing 
its oversight program, to implement management controls, including 
inspection and enforcement, to ensure that it has accurate information 
on and is sufficiently aware of plant conditions. In this respect, it 
was NRC's decision to rely on the premise that the information provided 
by FirstEnergy was complete and accurate. As we point out in the 
report, the degradation of the vessel head at Davis-Besse occurred over 
several years. NRC knew about several indications that problems were 
occurring at the plant, and the agency could have requested and 
obtained additional information about the vessel head condition.

We also believe that the report's characterization of NRC's use of risk 
estimates is accurate. The NRC risk estimate that we and our 
consultants found for the period leading up to the December 2001 
decision on Davis-Besse's shutdown, including the risk estimate used by 
the staff during key briefings of NRC management, indicated that the 
estimate for core damage frequency was 5.4x10^-5, as used in the report. 
The 5x10^-6 referenced in NRC's December 2002 safety evaluation is for 
core damage probability, which equates to a core damage frequency of 
approximately 5x10^-5--a level that is in excess of the level generally 
accepted by the agency. The impression of our consultants is that some 
confusion about the differences in these terms may exist among NRC 
staff.

Concerning NRC's disagreement with our recommendation to develop 
specific guidance for making plant shutdown decisions, NRC stated that 
its regulations, guidance, and processes are robust and do provide 
sufficient guidance in the vast majority of situations. The agency 
added that from time to time a unique situation may present itself 
wherein sufficient information may not exist or the information 
available may not be sufficiently clear to apply existing rules and 
regulations definitively. According to NRC, in these unique instances, 
the agency's most senior managers, after consultation with staff 
experts and given all of the information available at the time, decide 
whether to require a plant shutdown. While we agree that NRC has an 
array of guidance for making decisions, we continue to believe that NRC 
needs specific guidance and a well-defined process for deciding when to 
shut down a plant. As discussed in our report, the agency used its 
guidance for approving license change requests to make the decision on 
when to shut down Davis-Besse. Although NRC's array of guidance 
provides flexibility, we do not believe that it provides the structure, 
direction, and accountability needed for important decisions such as 
the one on Davis-Besse's shutdown.

In disagreeing with our recommendation concerning the need for a 
methodology to assess licensees' safety culture, NRC said that the 
Commission, to date, has specifically decided not to conduct direct 
evaluations or inspections of safety culture as a routine part of 
assessing licensee performance due to the subjective nature of such 
evaluations. According to NRC, as regulators, agency officials are not 
charged with managing licensees' facilities, and direct involvement 
with organizational structure and processes crosses over to a 
management function. We understand NRC's position that it is not 
charged with managing licensees' facilities, and we are not suggesting 
that NRC should prescribe or regulate the licensees' organizational 
structure or processes. Our recommendation is aimed at NRC monitoring 
trends in licensees' safety culture as an early warning of declining 
performance and safety problems. Such early warnings can help preclude 
NRC from assessing a licensee as being a good performer one day, and 
the next day being faced with a situation that it considers a 
potentially significant safety risk. As discussed in the report, 
considerable guidance is available on safety culture assessment, and 
other countries have established safety culture programs.

NRC's written response also contained technical comments, which we have 
incorporated into the report, as appropriate. (NRC's comments and our 
responses are presented in app. IV.): 

As arranged with your staff, unless you publicly announce its contents 
earlier, we plan no further distribution of this report until 30 days 
from its issue date. At that time, we plan to provide copies of this 
report to the appropriate congressional committees; the Chairman, NRC; 
the Director, Office of Management and Budget; and other interested 
parties. We will also make copies available to others upon request. In 
addition, this report will be available at no charge on the GAO Web 
site at [Hyperlink, http://www.gao.gov]. If you or your staff have any 
questions, please call me at (202) 512-3841. Key contributors to this 
report are listed in appendix V.

Signed by: 

Jim Wells Director, Natural Resources and Environment: 

List of Congressional Requesters: 

The Honorable George V. Voinovich: 
United States Senate: 

The Honorable Dennis J. Kucinich: 
House of Representatives: 

The Honorable Steven C. LaTourette:
House of Representatives: 

[End of section]

Appendixes: 

[End of section]

Appendix I: Time Line Relating Significant Events of Interest: 

[See PDF for image]

[End of figure]

[End of section]

Appendix II: Analysis of the Nuclear Regulatory Commission's 
Probabilistic Risk Assessment for Davis-Besse: 

Report of the Committee to Review the NRC's Oversight of the Davis-
Besse Nuclear Power Station:

John C. Lee 
Department of Nuclear Engineering and Radiological Sciences 
University of Michigan 
Ann Arbor, MI 48109:

Thomas H. Pigford Department of Nuclear Engineering 
University of California 
Berkeley, CA 94720:

Gary S. Was 
Department of Nuclear Engineering and Radiological Sciences 
University of Michigan 
Ann Arbor, MI 48109:

Table of Contents:

1. Scope of the Review: 

2. Key Findings of the Committee: 

3. NRC Probabilistic Risk Assessment Model and Database: 

3.1 Basic PRA Methodology and Data Used for the DB Risk Analysis: 

3.2 DB Calculation of Risk due to CRDM Nozzle Failures: 

3.3 NRC Calculation of Risk due to CRDM Nozzle Failures: 

4. Assumptions and Uncertainties in NRC Risk Analysis: 

4.1 The Discovery of Massive Corrosion Wastage at Davis-Besse: 

4.2 Assumption that Boric Acid in Hot Escaping Coolant Will Not
Corrode: 

4.3 Control Rod Ejection and Reactivity Transient: 

4.4 Need to Account for Corrosion in Risk Analysis: 

4.5 Uncertainties in Predicting Risk from Nozzle Cracking: 

4.6 Lack of Uncertainty Analysis in DB Risk Estimation: 

5. Relevant Regulations and Guidelines: 

5.1 Use of Regulatory Guide 1.174 and Other Guidelines in the DB 
Decision: 

5.2 Technical Specifications and General Design Criteria Regarding 
Coolant Leak: 

5.3 Balance between Probabilistic and Deterministic Indicators for Risk 
Assessment: 

6. Review of the November 2001 NRC Decision Regarding Davis-Besse: 

6.1 Involvement of NRC Staff and Management in the DB Decision: 

6.2 Coordination among NRR, RES, and Inspectors: 

6.3 Arbitrariness of the Requested Shutdown Date: 

6.4 The Role of NRC's Advisory Committee on Reactor Safeguards: 

6.5 NRC Staff Workload Affecting Its Ability for Detailed Risk 
Assessment: 

6.6 Davis-Besse, NRC, and Three Mile Island: 

7. Recommendations for Improved Use of Probabilistic Risk Assessment: 

References: 

Report of the Committee to Review the NRC's Oversight of the Davis-
Besse Nuclear Power Station:

1. Scope of the Review:

The U. S. General Accounting Office formed a committee in September-
October 2003 to review the oversight that the U. S. Nuclear Regulatory 
Commission provided on matters related to the pressure vessel head 
corrosion at the Davis-Besse (DB) Nuclear Power Station. The GAO charge 
to the committee was to respond to the questions:

(1) What probabilistic risk assessment model did NRC use and is it an 
appropriate model?

(2) What was the source of key data used to run NRC's probabilistic 
risk assessment and were these data valid?

(3) What key assumptions implicit in the model did NRC use to govern 
the estimated risk of different scenarios and were these reasonable?

(4) Is probabilistic risk assessment an appropriate tool for making 
such decision in these instances?

(5) How could NRC improve its use of probabilistic risk assessment to 
make more informed decisions?

The committee was initially provided with a set of 53 documents, which 
included GAO's preliminary analysis of the issues involved and 
chronology of the DB events during 2001 and 2002. The GAO reports 
summarized NRC-DB interactions in fall 2001 
related to NRC Bulletin 2001-01 on control rod drive mechanism (CRDM) 
nozzle cracking, the eventual shutdown of the plant on 16 February 
2002, and the subsequent discovery of pressure vessel head corrosion. 
Included also were:

(1) Official NRC documents, Generic Letters, Bulletins, and Information 
Notices transmitted to licensees including Davis-Besse,

(2) DB reports submitted to NRC related to the CRDM nozzle issues, (3) 
NRC documents summarizing the staffs positions and discussions,

(4) Summaries of NRC staff presentations to NRC's Advisory Committee on 
Reactor Safeguards (ACRS) and to the Commission Technical Assistants,

(5) Event inquiry report of the NRC Office of Inspector General (OIG) 
and response from the NRC Chair,

(6) Redacted transcripts of OIG interviews of NRC staff, and (7) 
Transcripts of GAO interviews with NRC staff.

The committee reviewed the initial set of documents received from GAO 
and conducted discussion on the phone and quite frequently via email. 
One member (GSW) provided a set of initial questions, which GAO used in 
a meeting with the NRC staff in 
October 2003. Another member (JCL) met with Mark Reinhart of NRC at the 
November American Nuclear Society meeting to discuss relevant technical 
issues and to prepare for a meeting of the review committee with NRC 
staff, which took place on December 11, 2003. At the meeting, two 
members (GSW, JCL) discussed technical and management issues with a 
total of nine NRC officials.

The review committee also consulted a number of experts from the 
industry and national laboratories, and reviewed a number of additional 
materials including:

(1) Several NRC Regulatory Guides,

(2) NRC Augmented Inspection Report and Lessons-Learned Task Force 
Report,

(3) Additional NRC reports on significance assessment of the DB CRDM 
degradations and the October 2003 OIG review of NRC's oversight on DB,

(4) Reports (including one proprietary version) from Electric Power 
Research Institute and Nuclear Energy Institute,

(5) Notes from William Shack, Argonne National Laboratory (ANL), 
describing his calculation of CRDM nozzle failure probability,

(6) DB probabilistic risk assessment (PRA) study performed for NRC by 
the Idaho National Engineering and Environmental Laboratory,

(7) Transcripts of several ACRS meetings during 2001-2003, and (8) 
Select papers in engineering journals and proceedings.

The committee conducted an extensive review and discussion on the 
probabilistic risk calculations performed both by the FirstEnergy 
Nuclear Operating Company (FENOC) and NRC for Davis-Besse. One 
committee member (JCL) also developed a simplified analytical model to 
determine the CRDM failure probability, which provided a rough check on 
numerical calculations performed at ANL.

Following the 11 December 2003 meeting with the NRC staff, the 
committee made an effort to follow up on a number of questions that 
required additional information or clarifications. One essential piece 
of information is the core damage probability due to the postulated 
CRDM failure and ejection that NRC actually used in connection with the 
decision to allow continued DB operation until February 16, 2002. After 
a long wait, finally on February 24, 2004, the committee received a 
response from Jin Chung, Richard Barrett, and Gary Holahan, 
summarizing, to the extent they could reconstruct, how NRC arrived at 
key quantitative risk estimates in November 2001.

We present in Section 2 key findings of the committee on NRC's 
oversight related to the DB issues. We provide responses to the first 
four GAO charges in Sections 3 through 6, in a slightly restructured 
format, covering (a) PRA methodology and data used in NRC's risk 
assessment, (b) assumptions and uncertainties in the risk assessment, 
(c) relevant regulations and guidelines, and (d) November 2001 NRC 
decision. Our response to the fifth GAO charge is finally presented in 
Section 7.

2. Key Findings of the Committee:

The committee presents key findings of its review on NRC's oversight on 
Davis-Besse and related safety and regulatory issues:

(1) NRC's Risk Analysis for Davis-Besse:

(a) To guide a risk-informed decision on whether to grant an extension 
beyond its December 31, 2001 date for shutdown of Davis-Besse for 
nozzle inspection, NRC relied on its PRA of risks from crack-induced 
failure of control-rod housing nozzles. The calculated risk was 
incorrectly small because the calculations did not consider corrosion 
of the reactor vessel due to boric acid in coolant leaking through the 
cracks. The calculated risk was also subject to large uncertainties. As 
a result, NRC staff found it difficult to balance results of 
quantitative risk calculations against qualitative considerations. 
Regulatory Guide 1.174 provided little help in this regard.

(b) NRC did not perform uncertainty analysis in applying PRA in the DB 
decision-making process and there was confusion regarding the 
interpretation of core damage frequency (CDF) and core damage 
probability (CDP) as risk attributes within the framework of RG 1.174. 
NRC staff should have recognized large uncertainties associated with 
the CDF estimated for CRDM nozzle failures:

(c) NRC's risk analysis was poorly documented and inadequately 
understood by NRC staff.

(d) Even now, NRC is unable to provide estimates of the risk from 
continued operation of Davis-Besse from December 31, 2001 to February 
16, 2002, taking into account the large corrosion cavity in the reactor 
vessel head found in March 2002. The risks from that operation prior to 
shutdown are likely to have been unacceptably large. Thus, with proper 
risk analysis, quantified risk calculations would have provided clear 
guidance for prompt shutdown.

(2) Relevant Regulations and Guidelines:

(a) Coolant leakage through flanges and valves was allowed under the DB 
Technical Specifications, leading the DB personnel and NRC resident 
inspectors to treat boric acid deposits in various locations in the 
containment as routine events, and hence not risk significant.

(b) NRC has no predetermined methodology to weigh PRA against 
deterministic factors. NRC needs to develop a set of guidelines for the 
use of PRA in decision-making.

(3) November 2001 Davis-Besse Decision:

(a) The proposed shutdown date of 31 December 2001 was arbitrary. There 
was significant pressure from DB to delay the shutdown for financial 
reasons, but no cost-benefit analysis was presented.

(b) Communication was seriously lacking between NRC headquarters and 
Region III and also between resident inspectors and Region III 
administrators regarding the extent of coolant leakage and boric-acid 
corrosion.

(c) NRC staff incorrectly assumed that the visible white deposits of 
anhydrous boric acid resulted entirely from rapid evaporation and 
drying of the leaking coolant and were not associated with corrosion.

(d) The transparency of the decision-making process within NRC is not 
uniform. The NRC lacks an established and well-defined process for 
decision-making.

(4) General Safety and Regulatory Issues:

(a) How to ensure safety from corrosion by leaking coolant is generic 
to all pressurized water reactors (PWRs). There is no evidence that it 
has been evaluated as such by NRC's Advisory Committee on Reactor 
Safeguards.

(b) The root cause of this near miss of a serious accident at Davis-
Besse is human error: inadequate evaluation of the effect of 
simplifying assumptions in the risk analysis and inadequate perception 
and understanding of the many clues that challenged those assumptions.

(c) NRC is slow to integrate new safety information into its programs, 
and to share that information with its licensees.

3. NRC Probabilistic Risk Assessment Model and Database:

3.1 Basic PRA Methodology and Data Used for the DB Risk Analysis:

The NRC staff relied on a Standardized Plant Analysis Risk (SPAR) study 
[Sat00] for Davis-Besse that Idaho National Engineering and 
Environmental Laboratory performed. The Saphire code [Sap98] provided 
the PRA tools and database for key system failure rates and human error 
probabilities in the SPAR study. The PRA methodology combines semi-
pictorial structures of event and fault trees to estimate the 
probability of occurrence of rare events, in particular, the core 
damage frequency (CDF) and large early release frequency (LERF) of 
radioactivity associated with the operation of a nuclear power plant. 
An event tree is constructed for each major sequence of events 
beginning with an initiating event, e.g., a medium-break loss-of-
coolant accident (MBLOCA), and following through multiple stages of 
safety systems to be activated. The probability of failure or 
unreliability of a safety system that is called upon to function is 
determined as the probability of the top event of a fault tree, which 
is determined through Boolean logic representing failure probabilities 
of components making up the top event. Uncertainties in the CDF and 
LERF are then obtained by a Monte Carlo convolution of probability 
density functions representing failure rates of components in fault 
trees and of safety systems in event trees.

The MBLOCA, which is assumed to occur following the failure and 
ejection of CRDM nozzles at Davis-Besse, is analyzed in the SPAR report 
[Sat00] as one of 12 major internal events postulated to lead to core 
damage and radioactivity release. A 
baseline CDF of 1.0x10 ^-7/year for MBLOCA results from a generic value 
[Pol99] of the initiating event frequency of 4.0x10^-5/year for the 
MBLOCA combined with the failure probabilities of a number of 
engineered safety features, including high-and low-pressure injection 
systems. This results in an estimate of 2.5x 10^-3for the conditional 
core damage probability (CCDP) for MBLOCA. The CCDP of 2.5x10^^-3is 
almost entirely due to the failure of low-pressure recirculation pumps, 
which in turn depends heavily on the ability of the operator to 
properly align and start the pumps. Based on human factor analysis, an 
estimate of 1.0x10^-3 for the operator error is included in determining 
the CCDP of 2.5x10^-3. The baseline or point-estimate CDF of 1.0 x 
10^-7 1e/year for 
MBLOCA contributes 0.5% toward the total baseline CDF of 2.0 x 10^-5/
year, with uncertainties represented as CDF = {5th percentile, median, 
mean, 95th percentile 16.3x 10^-6, 1.6x 10^-5, 5.1x10^-5, 9.6x10^-5} 
per year. The SPAR report for Davis-Besse provides only baseline CDF 
estimates for individual core damage events; hence no uncertainty 
estimates are available for the MBLOCA event. The mean overall CDF = 
5.1x10-5/year for Davis-Besse compares well with the those for internal 
initiating events for three PWR plants analyzed extensively as part of 
NRC's severe accident evaluation project in NUREG-1150 [Nrc90]: Surry 
Unit 1, 4x10^-5/year; Sequoyah Unit 1, 6x10^-5/year; and Zion Unit 1, 
6x 10^-/year. The CDF estimates for the four PWRs are, however, an 
order of magnitude larger than those for two boiling water reactors 
analyzed in NUREG-1150: Peach Bottom Unit 2, 5x10/year, and Grand Gulf 
Unit 1, 4x10/year.

3.2 DB Calculation of Risk due to CRDM Nozzle Failures:

The DB calculation of the nozzle failure probability consisted of the 
following steps [Cam01c]. The nozzles were divided into three groups 
based on the extent of visual inspection possible during refueling 
outage (RFO) 10, 11 and 12. Group 1 consisted of 15 nozzles that were 
not inspected during RFO 10 and 11. Group 2 consisted of 5 additional 
nozzles that were not inspected during RFO 12. Group 3 consisted of 45 
nozzles, all of which were inspected during all outages. This analysis 
accounts for 65 nozzles, four short of the total number of nozzles on 
the DB head. The four nozzles not 
included in this analysis are at the center of the head. They were 
determined by a Structural Integrity Associates analysis [Cam01d] d] to 
have no demonstrable annular gaps, and therefore, were considered as 
not susceptible to circumferential cracking and were excluded from the 
calculation. This particular assumption turned out to be quite 
inappropriate, since the February-March 2002 inspection revealed that 
three central nozzles (Nos. 1, 2, 3) had developed through-wall axial 
cracks and that nozzle 2 also had a circumferential crack.

Leak frequencies were determined for each group according to the 
equation: leak frequency = 1.1/year x F„ where F, is the fraction of 
the total nozzles (65) in group i, and the value of 1.1 is the 
estimated frequency of CRDM leaks per reactor year based on 
observations on 5 other Babcock and Wilcox (B&W) plants. Data on CRDM 
cracking noted in the 2001-01 NRC Bulletin were incorporated into the 
PRA analysis [Cam01c] in calculating the leak frequency. Specifically, 
recent inspections had revealed that there were sixteen leaking nozzles 
identified in the B&W plants, Arkansas Nuclear One Unit 1 (ANO-1), 
Crystal River Unit 3 (CR-3), Oconee Nuclear Station Unit 1 (ONS-1), 
ONS-2 and ONS-3. The assumption was made that all leaks appeared during 
the most recent two fuel cycles. Assuming 1.5 years per fuel cycle, 2 
cycles per plant and 5 plants, a product of these three values yields 
15 reactor years of operation. Sixteen leaking nozzles over 15 years of 
operation yields a leak frequency of about 1.1 leaks per reactor year. 
This value then incorporated the most recent data on CRDM cracking at 
other B&W plants.

An event tree was constructed for each CRDM group, beginning with the 
CRDM leak frequency, accounting for crack growths and failures during 
subsequent operation and CRDM nozzle inspection failures and 
culminating with a total CDF. The event tree 
analysis included CCDP = 2.7x 10^-3 for all groups. The resulting total 
CDF summed over all three groups was 6.97x 1 e/year. Dividing by the 
CCDP yielded a value of the initiating event (IE) frequency of 2.58x 
10^-3/year representing an MBLOCA due to CRDM nozzle ejection. Using 
the IE frequency, one would then calculate an IE probability of 3.4x 
10^-4 for continued DB operation for another 0.13 year, representing 
the period between 31 December 2001 and 16 February 2002. We note here 
also that the DB estimation of CCDP = 2.7x 10^-3 agrees closely with 
the SPAR estimate of 2.5x 10^-3 discussed in Section 3.1.

The probability of missing a leak in an inspection was estimated by 
Framatome [Cam01b] using human reliability analysis. Their estimates 
[CamOld] indicated that the probability of missing a leak was 0.06 in 
the first inspection (RFO 10), 0.065 in the second inspection (RFO 11) 
and 0.11 in subsequent inspections. Davis-Besse's analysis [Cam01c], 
however, uses a single probability of value 0.05 applied to all of the 
nozzles covered in RFO 10, 11 and in subsequent inspections. The 
document [Cam01c] references the Framatome analysis [cam01b], but does 
not indicate why a different value was used and why a single, lower 
value was applied for all inspections. Correcting, however, the 
calculation to account for the three separate failure detection 
probabilities results in an IE frequency of 2.64x10^-3 /year vs. 
2.58x10^-3 /year assumed [Cam01c].

3.3 NRC Calculation of Risk due to CRDM Nozzle Failures:

Although documents provided to the review committee do not provide 
sufficient details on how NRC arrived at the incremental CDF or core 
damage probability (CDP), it appears that the NRC staff used the DB 
estimate of CCDP = 2.7x 10^-3 for the MBLOCA initiated by CRDM nozzle 
failure and ejection. The NRC did not have the in-house expertise to 
determine the nozzle ejection probability for Davis-Bessie. They had 
two sources for estimates of the nozzle ejection probability. One 
source was Dr. William Shack at Argonne National Laboratory (ANL). Dr. 
Shack conducted a rather extensive 
analysis of the failure probability consisting of 5 steps: 1) the 
number of cracked nozzles, 2) the crack size distribution, 3) the crack 
growth rate, 4) a time to failure based on initial crack size and crack 
growth rate, and 5) a probability of failure, based on a Monte Carlo 
analysis of failure times. The end result was a plot and a table with 
failure probability vs. time that was provided to NRC and is described 
in several references [Sha01, Sha03, Nrc01 a]. The second source of 
information on the MBLOCA frequency was the DB estimate [Cam01c] for IE 
frequency of 2.58x10^-3/year, discussed in Section 3.2.

Documents provided to the review committee [Rei03, Chu04] list the IE 
probability of 2.0x10^-3 for continued operation for another 0.13 year, 
representing the period between 31 December 2001 and 16 February 2002, 
but reference Dr. Shack as the source. However, the values provided by 
Shack to the NRC [Sha01 ] do not agree with this number and apparently 
NRC decided not to use the ANL analysis, as it was viewed as 
preliminary, and a work in progress.

In a final response [Chu04] to questions the review committee raised 
following the 11 December 2003 meeting with nine NRC staff, Jin Chung, 
Richard Barrett, and Gary Holahan confirmed that NRC used the DB 
estimate of CCDP = 2.7x10^-3, coupled with 
the IE frequency of 2.0x 10^-2/year, to obtain an incremental CDF = 
5.4x 10"5/year, associated with the postulated CRDM failure and 
ejection leading to an MBLOCA. They indicate that, instead of allowing 
for the inspection failure probability of 0.05 for RFO 10, assumed in 
the Framatome risk calculation [CamOlc], NRC allowed no credit to 
discover the nozzle cracking. NRC, however, used the same crack growth 
and failure rates as in the Framatome PRA submittal to arrive at the IE 
frequency of 3.4x 10-2/year, which is an order of magnitude larger than 
the Framatome estimate of 2.58x10-3/year. Dr. Chung then decided to 
reduce the IE frequency to 2.0x 10^-2/year, to "reflect best estimate 
rather than 75 percentile fracture mechanics," which is the best 
description of the adjustment that NRC is able to present in February 
2004. The adjusted value of IE frequency = 2.0x 10'2/year is then used 
together with CCDP = 2.7x 10"3 to yield the incremental CDF = 5.4x 10^-
5/year. Finally, to convert the incremental CDF to an incremental CDP, 
associated with the continued DB operation for 0.13 year, NRC again 
rounded off the resulting CDP = 7.0x 10"6 to 5.0x 10^-6. In the 
deliberations leading to the 28 November 2001 DB decision, NRC 
apparently used the adjusted, rounded-off risk estimates: incremental 
CDF = 5.4x 10^-5/year. and incremental CDP = 5.0x 10-6.

The conclusion of the review committee is that the determination of IE 
probability is questionable, and that the error or uncertainty 
associated with this probability is likely to be very high, rendering 
it of questionable value. In the February 2004 response [Chu04] 
to the review committee questions, NRC confirms that no uncertainty 
analysis was performed on the incremental CDF and CDP estimates they 
used in November 2001. Furthermore, NRC proposes an unusual use of the 
incremental CDF and CDP values to compare with the quantitative 
guidelines given in RG 1.174 [Nrc02a]. This will be discussed further 
in Section 5.1.

4. Assumptions and Uncertainties in NRC Risk Analysis:

4.1 The Discovery of Massive Corrosion Wastage at Davis-Besse:

The most serious shortcoming in NRC's risk analysis was the complete 
neglect of any consideration of corrosion of the reactor vessel by 
boric acid in reactor coolant known to be leaking from the high-
pressure cooling system. After finally shutting down the reactor and 
inspecting the control housing nozzles, Davis-Besse discovered 
extensive corrosive wastage of the steel pressure vessel. Boric acid in 
leaking coolant had reacted with iron to form a mass of corrosion 
products which, when removed, left a cavity the size of a 
pineapple. Corrosion had penetrated the 6-inch thick steel head of the 
reactor vessel and exposed the thin corrosion-resistant vessel liner, 
found to be only about 0.2 inches thick at that location.

The reactor had been operating for months, maybe years, perilously 
close to rupture of the vessel liner and rapid loss of reactor coolant. 
In response to our repeated requests to NRC to share with us what it 
has learned about the risks from corrosion-induced failure of the 
coolant pressure boundary, NRC states that such analysis has not been 
completed, awaiting completion of laboratory tests on relevant failure 
mechanics at the Oak Ridge National Laboratory. That answer is most 
disappointing.

An earmark of a responsive safety program is prompt incorporation of 
new safety information, by undertaking new risk analysis, whether 
deterministic, probabilistic, or both, to guide new procedures that 
would avoid such a potential accident and to guide 
research and testing necessary for proper risk-informed decision 
making. Now, some two years since the discovery of massive and 
dangerous corrosion wastage at Davis-Besse, NRC seems unable to supply 
even preliminary analysis of the magnitude of potential safety problems 
arising from coolant leakage and corrosion. This harks back to the 
1977-79 era, when NRC failed to recognize the implications of a near 
miss of a serious reactor accident at Davis-Besse, discussed further in 
Section 6.6. If NRC had made a prompt analysis of Davis-Besse's 1977 
operator errors and the implications for a more serious accident if not 
corrected, and if that analysis had been communicated to other 
licensees, the tragic accident at Three Mile Island could have been 
avoided. It appears that NRC has not fully recovered from its mistakes 
in 1977-79.

4.2 Assumption that Boric Acid in Hot Escaping Coolant Will Not 
Corrode:

Apparently all NRC staff who were involved in the November 2001 
decision on Davis-Besse were aware that high-pressure coolant was 
leaking from valves, flanges, and possibly from cracks, but they 
evidently thought that the hot coolant, at 600 °F, would immediately 
flash into steam and non-corrosive anhydrous compounds of boric acid. 
As evidence, they referred to the readily visible deposits of white 
fluffy anhydrous boric acid observed on plant equipment. But 
evaporation concentrates boric acid in the remaining liquid, which 
becomes far more corrosive. Its vapor pressure decreases and slows 
further evaporation. Thus, one should expect that some of the boric 
acid in the escaping coolant can reach the metal surfaces as wet or 
moist highly corrosive material underlying the white fluffy surface 
layers. That is evidently what happened. It should have been 
anticipated.

Also the geometry of a cracked nozzle was not considered in NRC's 
thoughts about boric acid corrosion. NRC was focused on the metal 
surface because they were convinced that the boric acid they saw came 
from "dripping" from the leaky valves above the head. However, in a 
leaking nozzle, the escape path of the water is some 6-8 inches - from 
the clad to the vessel surface. Such a long crevice provides 
considerably greater opportunity for concentration of the liquid behind 
the evaporation front at or near the vessel head surface where the 
steam escapes.

NRC staff should also have been aware of experience at the French 
nuclear plants, where boric acid corrosion from leaking reactor coolant 
had been identified during the previous decade, the safety significance 
had been recognized, and safety procedures to 
mitigate the problem had been implemented. Keeping abreast of safety 
issues at similar plants, whether domestic or abroad, and conveying 
relevant safety information to its licensees is an important function 
of NRC's safety program.

NRC staff were involved a few years earlier in discussions regarding 
boric acid deposits on the reactor pressure vessel head [Epr01]. Boric-
acid corrosion programs were initiated. But to the NRC staff involved 
in the November 2001 decision on Davis-Besse, boric-acid corrosion was 
not viewed as a significant safety concern; rather, there was concern 
that the anhydrous crystals could obscure indication of leakage from 
the nozzles above the reactor head. But already several tests of boric 
acid corrosion had been underway in industry and government 
laboratories. Representative tests of nozzle leakage showed that 
corrosion rates from boric acid solutions dripping onto carbon steel at 
600 °F can be in the range of four inches per year [Nrc02b]. Drip tests 
sponsored by the Electric Power Research Institute [Sri98, Epr01] 
showed that the corrosion rate is much higher for carbon-steel surfaces 
at 600 °F than at lower temperature. Only at temperatures much higher 
than 600 °F is the vaporization rate high enough to produce anhydrous 
boric acid crystals with little corrosion.

NRC personnel involved in the November 2001 safety review evidently 
were not aware of these corrosion tests or else they had forgotten 
about them. An NRC resident inspector at Davis-Besse was shown, by a 
Davis-Besse engineer, a photograph that 
revealed streaks of rust-colored corrosion products on the head of the 
reactor vessel, in the midst of the expected white crystals. But the 
inspector was not aware of the significance of these rust streaks, and 
he did not report this information to other NRC personnel. At other 
times, Davis-Besse reported the presence of airborne rust particles 
that had lodged on the surveillance filters, but the significance of 
this information was not recognized.

After the discovery of the corrosion wastage in 2002, an NRC official 
was asked about the corrosion data reported by the Electric Power 
Research Institute (EPRI). He replied that those data were not 
considered in the discussions with Davis-Besse because 
EPRI had not "submitted" the report of those data to NRC. EPRI points 
out that the corrosion data had been published in 1998 in a widely 
available technical report, well known to industry and NRC. EPRI had 
not formally "submitted" the report because NRC charges a fee for the 
submittal process.

4.3 Control Rod Ejection and Reactivity Transient:

In discussions related to the consequences of CRDM nozzle ejections at 
Davis-Besse, NRC duly considered the effects of the control rods 
ejected, thereby made inoperable, in the resulting LOCA. They 
apparently concluded before the 28 November 2001 Davis-Besse decision 
that the negative reactivity feedback resulting from the overheating 
and boiling of coolant in a LOCA would easily overshadow any potential 
decrease in the amount of subcritical reactivity that would ensure safe 
shutdown of the reactor. Furthermore, a more recent NRC report [Dye03] 
evaluating the significance of the Davis-Besse CRDM penetration 
cracking and pressure vessel head degradation presents a similar 
conclusion. Here, a combined thermal-hydraulic and reactivity transient 
analysis performed with the RELAP code indicates that the boiling of 
the reactor coolant coupled with the addition of boric acid in the 
emergency coolant water injected is sufficient to maintain the shutdown 
condition, thereby obviating the concern for an anticipated transient 
without scram (ATWS).

One consequence of the CRDM nozzle ejection that has not been, however, 
analyzed is the positive reactivity inserted into the reactor core when 
the control rod ejection occurs in a hot zero power (HZP) rather than a 
hot full power (HFP) condition. The consequences of postulated control 
rod ejection accidents are generally more severe, if initiated in a HZP 
condition when the system is fully pressurized but at low power. This 
is because at HZP the control rods would be inserted deeply into the 
core, thereby adding 
a larger positive reactivity when the rods are ejected, than that 
resulting in a HFP rod ejection accident. Thus, a HZP CRDM nozzle 
ejection could result in a power level above rated power before a 
significant coolant heating or boiling occurs. This combination of 
postulated accidents requires an integrated analysis of two PWR design 
basis accidents, LOCA and rod ejection accident, and should be 
performed for a complete evaluation of CRDM nozzle ejection 
consequences.

4.4 Need to Account for Corrosion in Risk Analysis:

NRC's analysis of risks from nozzle cracking was concerned only with 
the formation and propagation of circumferential cracks that could 
result in nozzle failure, loss of coolant, and even control rod 
ejection. The formation of axial cracks was neglected in the risk 
analysis. There is less chance of axial cracks causing complete failure 
of a nozzle but they do open additional pathways for coolant leakage. 
Leakage from axial cracks is believed to have been the main source for 
the massive corrosion wastage at Davis-Besse.

Neglecting axial cracking and corrosion wastage that could result in 
rupture of the reactor vessel and a more serious loss-of-coolant 
accident was a principal deficiency in NRC's risk assessment.

NRC has not described to us any plans for extensions to its risk 
analysis that would predict the dangers of corrosion wastage. In our 
view, the necessary additional ingredients of the probabilistic risk 
analysis must include:

* Formation and growth of axial cracks in control-rod-housing nozzles, 
* Flow of leaking coolant from cracks,

* Evaporation of leaking coolant and concentration of boric acid, * 
Corrosion of the steel pressure vessel,

* Time-dependent penetration of the corrosion front into the pressure 
vessel, * Corrosion and stress-corrosion cracking of the vessel liner,

* Time-dependent calculation of stress on the vessel and its failure if 
ruptured, and * Loss-of-coolant analysis of reactor core damage if 
rupture occurs.

Some of the possible parameters for such an analysis were developed for 
this report from sources other than NRC, as outlined in the next 
section. The wide variations in some of the key parameters illustrate 
uncertainties that must be resolved to make accurate predictions of 
risk and its uncertainty.

4.5 Uncertainties in Predicting Risks from Nozzle Cracking':

For risk-informed decision making, it is important to include 
calculation of uncertainties in the predicted risks. NRC informs us 
that it has not calculated uncertainties in its present risk 
assessments of nozzle cracking. It does believe that its present 
results on core-damage risks are accurate "to within a factor of 2 or 
3". NRC did not provide the basis for their belief. The information 
necessary for probabilistic risk calculation should include enough data 
for uncertainty analysis. NRC should perform uncertainty calculations.

A major uncertainty arises in attempting to predict the corrosion 
wastage that would rupture the reactor vessel, particularly after 
boric-acid-induced corrosion has penetrated all the way through the 
carbon steel and exposed the thin stainless steel liner that would 
serve as the reactor coolant system pressure boundary, as occurred at 
Davis-Besse. From other sources [PinWa,b], we are informed that in 
early 2003 an internal NRC memo concluded that there was no danger of 
imminent rupture of the Davis-Besse reactor prior 
to its shutdown in February 2002. The memo cited calculations by the 
Oak Ridge National Laboratory, that the as-discovered cavity could have 
supported twice the operating pressure of 2185 psia before rupturing 
and that, "had the cavity enlarged under continued operation, at least 
twelve months remained before the cavity would reach a size that 
rupture would occur at normal operating temperature and pressure." It 
was assumed that "the wastage cavity was actively growing at a maximum 
rate of seven inches per year" [Pin03a], much greater than the 4 inches 
per year quoted earlier by NRC. The NRC memo stated that the need for 
more accurate data on the morphology and depth of cladding cracks 
necessitates a revision of these calculations and expects a possible 
reduction in the amount of margin that was originally calculated.

A report by Structural Integrity Associates [Sia02], commissioned by 
FirstEnergy, calculated that the cladding could withstand pressures of 
more than 5000 psia. Davis-Besse concluded that vessel rupture "was 
therefore considered not to be a credible event". Later in 2003, an Oak 
Ridge National Laboratory study, conducted on a spare reactor-vessel 
head with a machined-out cavity simulating wastage, reported two 
rupture tests, one occurring at 2000 psia, the other at 2700 psia. If 
these two results are applicable, Davis-Besse had been operating at 
2185 psia with significant probability of vessel rupture. NRC's project 
manager for these tests stated in October 2003 that the Oak Ridge test 
results would be made public "probably within weeks." The report is not 
yet released.

An important feature of the Oak Ridge tests was taking into account the 
"dissimilar weld" between the carbon-steel vessel head and the 
stainless steel cladding. The Union of Concerned Scientists pointed out 
that the Oak Ridge tests revealed that the weld overlay process used 
for the Davis-Besse vessel left a thin interface that was not as strong 
as either of the adjoining layers. Also, the tests were conducted 
quasi-statically, whereas pressure transients during reactor operation 
must be considered [Pin03b].

These are examples of crucial data uncertainties that need to be 
resolved. Such uncertainties must be considered in reporting 
probabilistic risks.

It is not enough to finesse such uncertainties by instituting new 
procedures intended to eliminate the possibility of operator error. The 
near accident at Davis-Besse resulted from human error, errors by 
reactor operators, by NRC on-site inspectors and by the staffs at 
Davis-Besse and NRC. The experience at Three Mile Island has taught us 
that human errors can occur and must be included in responsible risk 
analysis.

4.6 Lack of Uncertainty Analysis in DB Risk Estimation:

As discussed in Section 4.5, an important issue regarding the 
application of quantitative guidelines for risk management and 
regulatory decisions, as in the Davis-Besse case under review, is the 
need to account for uncertainties in risk values determined through PRA 
techniques. It was noted in Sections 3.1 and 3.3 that we are unable to 
obtain any uncertainty estimates for the SPAR baseline CDF of 1.0x10^-
7/year for Davis-Besse MBLOCA, without CRDM nozzle failures, or the NRC 
estimate of 5.4x 10^-5/year for the corresponding MBLOCA CDF accounting 
for CRDM nozzle failures. It is well known among the PRA community that 
all quantitative risk estimates for nuclear power plants are subject to 
significant uncertainties and that it is imperative that proper 
uncertainty analysis be performed for any PRA study for nuclear power 
plants. This point was made abundantly clear in a recent NRC report 
[Fle03], prepared at the request of NRC's Advisory Committee on Reactor 
Safeguards (ACRS), for the purpose of evaluating practices and issues 
regarding PRA applications. The need to understand and characterize 
uncertainties in PRA and risk-informed regulatory activities was also 
emphasized in both RG 1.174 [Nrc02a] and RG 1.200 [Nrc03]. Furthermore, 
it was primarily for the purpose of duly accounting for uncertainties 
in the calculated risks of postulated severe accidents that NRC and its 
contractors had to go through two draft versions of the massive volumes 
of the severe accidents risk study of NUREG-1150 [Nrc90] before 
releasing the final version in 1990. Nonetheless, it is rather clear to 
the review committee that the NRC staff and management did not give due 
considerations to the impact of large uncertainties, in particular, in 
the frequency of MBLOCA initiated by the postulated Davis-Besse CRDM 
nozzle ejection in their Davis-Besse deliberations in November 2001. In 
addition, the SPAR calculation of CCDP = 2.5x 10^-3 is subject to 
significant uncertainties associated with human errors and common cause 
failures represented in the fault tree analysis. Questions were also 
raised in GAO interviews with the NRC staff if the staff had the proper 
understanding of the impact on the CCDP estimate of the compensatory 
measures proposed by Davis-Besse before the November 2001 decision.

During the 11 December 2003 meeting with the NRC staff, we got the 
indication that several NRC staff felt that Regulatory Guide 1.174 
[Nrc02a], with its PRA framework, does account for uncertainties in 
risk estimates including the effects of unknown events, e.g., the 
Davis-Besse pressure vessel head wastage, through the defense-in-depth 
philosophy. As discussed in detail in the February 2003 NRC Region III 
report [Dye03], it is very much doubtful how the system modeling 
uncertainties and unknown events could possibly have been represented 
through a simple application of RG 1.174. It is noteworthy that the 
ACRS, at its first full committee meeting [Acr02] after the Davis-Besse 
cavity findings, repeatedly criticized the NRC staff for not having 
performed any uncertainty analysis for the CRDM nozzle failure issues 
and suggested that the staff had drifted away from the RG 1.174 
guidelines. Had the staff gone through even a simple analysis, without 
any detailed uncertainty calculations or invoking RG 1.174, they should 
have realized that the incremental CDF of 5.4x10 5/year would result in 
doubling the total CDF for Davis-Besse, even with the mean SPAR value 
of 5.1x10-5/year. Note furthermore that the SPAR baseline CDF is 1.6x 
105/year. Thus, the staff should have readily recognized the risk 
significance of the incremental CDF = 5.4x10^-5/year estimated in 
November 2001 for the CRDM nozzle failure event.

One regulatory decision-making case where PRA applications were 
questioned is the ATWS issue. A recent review [Rau03] emphasizes that 
the uncertainty in the calculated values of the reactor scram system 
reliability requires maintaining defense in depth regarding ATWS, 
rather than relying heavily on PRA results. Thus, despite small values 
of scram failure probabilities calculated in the early 1980s, system 
changes, including improved reactor shutdown systems and circuits, were 
implemented but only after incipient ATWS events had occurred at the 
Salem Unit 1 plant in 1983 [Sci83]. We suggest that the NRC staff 
should have applied the lessons learned from the ATWS rulemaking case 
to the DB case, which would have reduced the NRC staffs heavy reliance 
on the quantitative risk. Although we will never be able to determine 
the extent by which the incremental CDF or CDP values influenced the 
decision making, it is rather apparent to the review committee that the 
quantitative risk values, without due considerations for uncertainties, 
did play an important role in the 28 November 2001 decision.

5. Relevant Regulations and Guidelines:

5.1 Use of Regulatory Guide 1.174 and Other Guidelines in the DB 
Decision:

One key set of guidelines discussed extensively among the NRC staff and 
management before the 28 November 2001 DB decision is RG 1.174 
[Nrc02a], which is intended to 
promote risk-informed decisions on plant-specific changes. Included in 
RG 1.174 is one particular quantitative metric in the form of 
incremental CDF. According to Figure 3 illustrating acceptance 
guidelines, any plant-specific changes resulting in an incremental CDF 
of 1 x 10^-5/year or higher should not be allowed. In addition, there 
apparently was considerable discussion and lack of unanimity among the 
NRC staff prior to the 28 November 2001 decision if the other four 
safety principles of RG 1.174 were satisfied. The February 2003 NRC 
Region III report [Dye03] documenting the significance of the Davis-
Besse CRDM penetration cracking and pressure vessel head degradation 
leaves, however, no question that all five safety principles of REG 
1.174 were violated at Davis-Besse in November 2001. Included in this 
report is a revised estimate of incremental MBLOCA frequency of 
3.0x10^-2/year; yielding estimates of incremental CDF in the range of 
[1 x 10^-5,1x10^-6] per year, due to the ejection of three central CRDM 
nozzles. These estimates of incremental CDF bracket the value of 
5.4x10^^-/year presented to the review committee [Rei03] and would have 
clearly resulted in violation of the sole quantitative metric of RG 
1.174.

Although the February 2003 findings of NRC rendering Davis-Besse in the 
"red" status are attained certainly with the benefits of hindsight, it 
is worth summarizing the reasoning presented in the report, rather than 
presenting the review committee's evaluations:

(1) Principle 1: Regulations were not met, because reactor coolant 
system (RCS) pressure boundary leakage occurred over an extended period 
of time and the RCS was not inspected and maintained properly. This 
resulted in violation of the General Design Criteria.

(2) Principle 2: Performance and maintenance deficiency degraded the 
level of defense in depth required for safe operation of the plant.

(3) Principle 3: Safety margins were not maintained because the 
integrity of the RCS pressure boundary relied solely on the vessel 
lining, which was not designed for this purpose.

(4) Principle 4: Calculated risk violated the quantitative guideline.

(5) Principle 5: There was no basis for assuring that degradations due 
to CRDM leaks would be properly monitored and managed.

It goes without saying that nobody anticipated in November 2001 the 
severe vessel wastage that was uncovered in March 2002, which resulted 
in an unambiguous verdict regarding Principle 3 above. Nonetheless, 
there were sufficient indications in November 2001 to question if 
safety margins were not violated, as voiced by a number of the NRC 
staff before the 28 November 2001 decision. This in turn raises 
questions if NRC made proper application of RG 1.174 in arriving at the 
decision to allow a delay of the shutdown of Davis-Besse for the 
pressure vessel head inspection required in NRC Bulletin 2001-01 
[Nrc01c].

During the 11 December 2003 meeting with the NRC staff, the review 
committee was offered a number of other NRC and industry guidelines 
that the NRC staff apparently used for the Davis-Besse decision. A 
review of these additional guidelines further:

suggests that the NRC value for the incremental CDF = 5.4x10^-5/year 
for seven weeks of additional Davis-Besse operation could not have 
satisfied these guidelines either. To clarify the point here, we follow 
the process NRC used to convert the incremental CDF = 5.4x 10^-5/year 
to the incremental core damage probability (CDP) for seven weeks or 
0.13 year: incremental CDP = 5.4x 10^-5/year x 0.13 year = 7.0x le, 
rounded off to 5.0x 10^-6, which is roughly equivalent to approximating 
7 weeks as 0.1 year. We may now compare this incremental CDP estimate 
with three additional guidelines for risk-informed decision-making 
processes 

(1) RG 1.177 [Nrc98] intended for evaluating Technical Specification 
changes suggests that an incremental CDP of 5x10 is acceptable for 
relaxation of allowed outage time or surveillance test intervals.

(2) PSA Applications Guidelines [Tru95] proposed by the Electric Power 
Research Institute indicates that an incremental CDP in the range of 
[1x10, 1x10^-5] requires assessment of non-quantifiable factors.

(3) NUMARC 93-01 [Nei96] suggests that an incremental CDP in the range 
of [1 x10, 1x10^-5] requires risk management actions adding further 
that any decisions resulting in an incremental CDP greater than 1x10^-
5 should not be allowed.

Thus, NRC's incremental CDP value of 5x10 would have resulted in 
violation of RG 1.177 and would have required risk management actions 
according to both the EPRI and Nuclear Energy Institute guidelines. In 
addition, during the 11 December 2003 meeting with the NRC staff, 
Richard Barrett insisted that the quantitative RG 1.174 guidelines are 
supposed to be applied in terms of incremental CDP, not incremental CDF 
as stipulated clearly in the Regulatory Guide. In the February 2004 
response [Chu04] to the review committee questions, NRC now proposes 
that the incremental CDF used as a key metric in RG 1.174 is meant to 
be an annual average. Thus, NRC now suggests that the incremental CDF = 
5.4x 10^-5/year for 13% of a year should be combined with CDF = 0.0 for 
the remaining 87% of the year to yield an annual-average incremental 
CDF = 5x 10 ./year. This new interpretation is at best unusual and 
certainly is inconsistent with clear RG 1.174 guidelines regarding the 
use of incremental CDF. This reinforces the impression of the review 
committee that perhaps there was in November 2001 and possibly is still 
some confusion among the NRC staff regarding basic quantitative metrics 
that should be considered in evaluating regulatory and safety issues.

A recent release of RG 1.200 [Nrc03] is intended to provide guidance 
for determining the technical adequacy of PRA results in regulatory 
decision making. The Regulatory Guide discusses various technical 
characteristics and attributes that should be included in PRA, and 
highlights the importance of capturing system dependencies in risk 
evaluations. RG 1.200 also emphasizes that understanding uncertainties 
in PRA is an essential aspect of risk characterization and refers to RG 
1.174 for guidance on how to address the uncertainties. As reviewed in 
connection with the DB decision-making process, however, we feel that 
the guidelines in RG 1.174 are not specific enough, especially for PRA 
results subject to large uncertainties and for representing events not 
well understood.

5.2 Technical Specifications and General Design Criteria Regarding 
Coolant Leak:

Davis-Besse technical specification 3.4.6.2 requires that no reactor 
coolant pressure boundary (RCPB) leakage is allowed. The General Design 
Criteria, 10 CFR 50 Appendix A, addresses reactor coolant pressure 
boundary leakage in GDC 14, GDC 31, and GDC 32. GDC 14 specifies that 
the RCPB have an extremely low probability of abnormal leakage, or 
rapidly propagating failure, and of gross rupture. GDC 31 specifies 
that the probability of rapidly propagating fracture of the RCPB be 
minimized. GDC 32 specifies that components which are part of the RCPB 
have the capability of being periodically inspected to assess their 
structural and leaktight integrity.

The FENOC response [Cam01a] to the NRC Bulletin 2001-01 applies the GDC 
against the situation of potentially cracked nozzles at Davis-Besse. 
Specifically the following points were made:

* The presence of cracked and leaking vessel head penetration (VHP) 
nozzles is not consistent with GDC14 or GDC 31.

* Inspection practices that do not permit reliable detection of VHP 
nozzle cracking are not consistent with GDC 32.

The situation regarding primary coolant leakage can be summarized as 
follows. The Davis-Besse technical specifications (TS) present a 
definitive criterion that allows no RCPB leakage. The GDC are not as 
definitive by virtue of their reference to probability of occurrence, 
which is not an absolute or definitive condition. GDC 14 and 31 are in 
agreement with the TS in principle, but not in their level of 
definitiveness. Therefore, there exists the possibility that a specific 
condition can be considered to satisfy the GDC but not the TS. 
Furthermore, the GDC implemented in the TS for DB allows for 1 gpm of 
unidentified reactor coolant system (RCS) leakage and 10 gpm. of 
identified RCS leakage, with the interpretation that leakage past 
seals, flanges, and gaskets is not pressure boundary leakage.

GDC 32 refers to the capability to inspect the leaktight integrity of 
the nozzles. Inspections were acknowledged to be incomplete because of 
failure to inspect all nozzles. They were insufficient because it was 
acknowledged that visual inspection may be inadequate in detecting 
cracks. By virtue of the inadequacy of the inspections in achieving 
their intended purpose, GDC 32 was largely not satisfied.

According to the 2002 OIG Event Inquiry [Bel02], FENOC's own risk-
informed evaluation estimated that Davis-Besse had between one and nine 
leaking CRDM nozzles, depending on the analysis used. According to the 
NRC, FENOC reported [Nrc02c] an estimate of 8.8 leaking nozzles to 
ACRS. From the results and analysis of the-inspection data from five 
other B&W plants that revealed 16 cracked nozzles in 15 reactor years 
of operation [Cam01c] there should be 1-2 leaking nozzles since the 
last outage (RFO 12 in April 2000). So from the available data, it was 
highly likely that there were leaks in the pressure boundary. These 
data were circumstantial as there was no direct evidence of the leaks, 
in part due to the inadequacy of the visual inspection techniques.

Given that positive identification of nozzle leakage was not obtainable 
because of the nature and capability of the inspections, and given that 
multiple analyses show that as many as 9 leaking nozzles were likely, 
it can be concluded that Davis-Besse was likely in violation of their 
Technical Specifications. This point was further discussed in the NRC 
Significance Assessment Report [Dye03].

The incorporation of PRA into the decision-making process at NRC should 
have compelled the NRC to consider the likelihood of leaking nozzles in 
the decision on whether to allow Davis-Besse to continue to operate. 
However, "the NRR Director told OIG that from a legal point of view, 
there was an issue about constructing an order without knowing with 
certainty that there were cracks" [Bel02]. This position had a 
significant impact on the NRC decision as the key decision-maker in 
this case, Brian Sheron, believed that NRC had no case to shut down the 
plant based on the technical specification that there be no RCPB 
leakage. The potential conflict between PRA and legal considerations 
must be resolved for PRA to play any role in the decision-making 
process of the NRC.

5.3 Balance between Probabilistic and Deterministic Indicators for Risk 
Assessment:

NRC management is responsible for decision-making. The technical staff 
is responsible for providing the technical case that serves as the 
foundation for decisions by 
management. The technical case includes both deterministic and PRA 
analysis that both involve models, data and calculations.

NRC has adopted "risk-informed" decision-making. However, the process 
is ill-defined and lacks guidelines as to exactly how it is supposed to 
work. The management does not have a set formula, process or procedure 
for incorporating PRA into its decision making process. Brian Sheron 
was the key decision-maker in the Davis-Besse case. He stated in the 
December 11 interview with the review team that the PRA analysis was 
used as a "calibration point" that gives NRC a ballpark figure of the 
risk. He indicated that the PRA value is not of much consequence unless 
it is of a "wildly" extreme value. He also indicated that there is 
little clear guidance on the use of PRA in the decision-making process. 
This point was supported by comments from Jack Strosnider and Gary 
Holahan who confirmed in their December 11 interview with the review 
team that there is no documentation or guidance that outlines to what 
extent or how the NRC should weigh the resultant risk number and 
uncertainty with respect to the ultimate decision.

This viewpoint indicates that NRC has no predetermined methodology to 
weigh the PRA result against a deterministic result or other factors. 
That is, the value assigned to the PRA analysis is largely at the 
discretion of the decision-maker and there is no guidance as to the 
weight to assign to this result. Such a process can result in a 
decision in which PRA plays a role anywhere from 0 to 100%. Clearly, 
there is need for the NRC to provide guidance for the use of PRA in 
decision-making.

6. Review of the November 2001 NRC Decision Regarding Davis-Besse:

6.1 Involvement of NRC Staff and Management in the DB Decision:

The basis of the November 28 decision to allow Davis-Besse to operate 
until February 16 was a meeting involving both technical staff and 
management. The meeting was called by Brian Sheron and was held on 
November 28, 2001. Following discussion of the various issues regarding 
Davis-Besse, Brian Sheron asked the staff if they could accept an 
extension of operation of the plant until February 16, 2002. Three 
staff members had objections. Mr. Sheron then refrained the question 
and asked the staff if any of them thought that Davis-Besse was not 
safe to operate until that date. None thought that this was the case. 
Based on this result, NRC accepted the February 16, 2002 date proffered 
by FENOC.

During the discussion, both deterministic analyses and PRA results were 
considered. However, a cost-benefit type of analysis of the situation 
was not performed. In an interview with the review team, Richard 
Barrett explained that NRC followed the RG 
1.174 and RIS 2001-02 [Nrc01b] argument, based on a "special 
circumstance." This special circumstance was that the regulations (ASME 
inspection codes) at the time were not adequate to detect cracked and/
or leaking nozzles and thus NRC had to take special action to address 
the special circumstance. Once the existence of a special circumstance 
was established, NRC used RG 1.174 to determine if the problem was risk 
significant enough. NRC determined that the problem was not risk 
significant, per RG 1.174, because "defense-in-depth" was preserved. 
Therefore, NRC did not consider the third factor, which would have been 
"higher level NRC management thoughts," such as a "cost-benefit" 
analysis or impact/burden on license.

However, as noted by several staff, there was pressure on the NRC from 
industry, Congress and the NRC Commissioners to keep plants running. It 
is not clear how much influence this pressure had on the decision-
making process.

The transparency of the decision-making process within NRC is not 
uniform. In the case of a shutdown order, the Executive Director for 
Operations (Office Director) would be the official responsible for 
signing the order. If the issue does not involve an order, 
the process is less clear. The specification of decision-maker appears 
to depend on the importance of the issue. There does not appear to be a 
policy that identifies what individuals are empowered to make what 
decisions. Strosnider and Holahan indicated that a routine response to 
a generic letter may be handled by a project manager, or perhaps by the 
Divisions of Licensing Project Management, with the concurrence of the 
involved sections or other divisions. NRC has no standard process or 
guidelines for decision-making. Sometimes the decision process involves 
a memo describing the licensee's request and NRC's response that is 
routed around and signed off on by relevant NRC staff. Other times, NRC 
will pull together a meeting of decision stakeholders.

The lack of an established and well-defined process for decision-making 
within the agency is a significant problem that needs to be addressed.

6.2 Coordination among NRR, RES, and Inspectors:

The analysis and decision-making process for the Davis-Besse case 
involved numerous individuals and offices. Included in the 
consideration of issues regarding Davis-Besse were the Directorate for 
Project Licensing & Technical Analysis, the Division of Engineering, 
and Division of System Safety and Analysis and the technical staff of 
the several Branches that report to those Division Directors of the 
Office of Nuclear Reactor Regulation (NRR). In addition, the Office of 
Research (RES) and ACRS played roles, as did the regional office and 
the regional inspector at Davis-Besse.

While there were a number of individuals and offices involved in the 
technical assessment of nozzle cracking, the interplay between offices 
and individuals is impossible to reconstruct. However, there are two 
cases that highlight problems with 
communication between offices and between individuals. The first is in 
the assessment of the initiating event probability. Based on interviews 
with some 12 different individuals, all significantly involved in the 
Davis-Besse issue and analysis, and spanning two Offices, one 
Directorate, two Divisions and several Branches, there was no sense of 
understanding about how the initiating event probability used in the 
PRA analysis was determined and by whom. In fact, the origin of the 
value for the initiating event probability that appears to have been 
used in the PRA analysis was variously ascribed to Bill Shack at ANL, 
FENOC, Framatome and EMC'. Further, the perception of who within NRC 
was responsible for establishing this quantity was not consistent. This 
situation indicates a very uneven understanding of one of the key 
underlying quantities for the entire PRA analysis. The origin of this 
term remains an outstanding issue, even with the February 2004 NRC 
response [Chu04]. It was clear that there was substantial interaction 
among offices and individuals during the period of intense analysis in 
the Fall of 2001. However, communication did not appear to be well 
structured, complete or effective in establishing a value for the 
initiating event probability.

A second problem was evident in the communication between the various 
components (headquarters, regional office, regional inspector at Davis-
Besse) of the NRC. The resident inspector appears to have played little 
or no role in providing 
information relevant to the issues being analyzed at NRC HQ. Further, 
there appears to have been no communication between the resident 
inspector and HQ. In the December 11th interview with the review team, 
Mr. Strosnider stated that it was rare one would think a resident 
inspector would offer substantive help. He did not believe that the 
resident inspector at Davis-Besse was, in fact, contacted. He also 
believed that the resident inspector is busy with other things, and 
that he probably had not been part of the 
vessel head inspections, and that he lacked the technical aptitude 
needed to contribute to the issue.

There were several indications of operational irregularities that 
should have been noted by an inspector in residence at the plant. These 
include: 1) radiological surveys showing a contamination plume effect 
originating from the service structure ventilation exhaust over the 
East D-ring [Dye02], 2) significant increase in the cleaning of 
containment air coolers, 3) the removal of fifteen, 5-gallon buckets of 
boric acid from the ductwork and plenum of the containment air coolers 
and the discovery of significant boric acid elsewhere in the 
containment, such as service water piping, stairwells, and other areas 
of low ventilation, and 4) the sudden change to rust-colored boric acid 
in June of 1999. That these events were occurring without the knowledge 
or appreciation of the resident NRC inspector highlights a major 
weakness of the role of the resident inspector in helping to ensure 
safe operation of the plant at which he/she is stationed.

6.3 Arbitrariness of the Requested Shutdown Date:

The 12/31/01 date for completing inspections of reactor vessel head 
nozzles imposed on licensees by the NRC was arbitrarily set. The 
arbitrariness of the 12/31/01 date was confirmed by Brian Sheron in his 
interview with the review committee in which he stated that there was 
nothing magical about the December 31st date, and that it just as 
easily could have been February 28tH or March 31st.

The arbitrariness of the date caused difficulty for the NRC when 
challenged by FENOC. The challenge resulted in a perceived reversal of 
the burden of proof from the licensee to the NRC. NRC believed that 
they needed to make a case in order to force a shutdown of DB to look 
for cracks. Unfortunately, their authority to act was perceived to be 
undermined by the lack of a defensible rationale for the selection of 
the inspection date.

NRC has been encouraging the use of risk analysis as part of the risk-
informed decision-making process. Yet NRC did not consider including 
risk analysis in the original call for inspection. The inclusion of risk 
analysis in the formulation of the inspection date could have provided 
the NRC with the justification for enforcement that they lacked under 
the present circumstances. If the call for inspection were based on a 
risk-informed decision-making strategy, then the calculations of the 
likelihood of nozzle failure and LOCA would have provided the support 
they needed to call for an inspection. The practical considerations in 
this strategy are not trivial. Yet had NRC followed its commitment to 
incorporate risk analysis in its decision-making process at the outset, 
the decision regarding Davis-Besse may have been much more 
straightforward.

6.4 The Role of NRC's Advisory Committee on Reactor Safeguards:

Although we recognize that ACRS does not provide routine guidance on 
plant-specific issues, we feel that NRC staffs should have recognized 
the CRDM nozzle failures as a generic issue and should have solicited 
in-depth assistance from ACRS before the 28 November 2001 decision. 
Thus, relying on a narrow interpretation of the CRDM nozzle . failure 
issues, the staff missed an opportunity to obtain important expert 
perspectives on the issues. We recommend that the NRC staff make more 
direct use of ACRS to augment in-house expertise on the staff, which 
may be limiting at times.

6.5 NRC Staff Workload Affecting Its Ability for Detailed Risk 
Assessment:

An NRC manager raised the question if NRC had sufficient personnel, 
given the workload, to perform detailed studies on complex regulatory 
or licensing issues such as the Davis-Besse case. Although the upper 
level management seems to be satisfied with the overall staff 
performance, we recommend a review of the workload and technical 
competence of the staff required to provide licensing and regulatory 
support in a timely manner.

6.6 Davis-Besse, NRC, and Three Mile Island:

The human errors on the parts of Davis-Besse and NRC, resulting in a 
near miss of a serious accident, echo a similar chain of events that 
originated at Davis-Besse in 1977 and culminated in America's most 
serious reactor accident at Three Mile Island in 1979. It began in 
September 1977 at Davis-Besse when a relief valve on the reactor 
coolant pressurizer stuck open. The coolant pressure fell but the water 
level in the pressurizer increased, the result of an anomaly in the 
pressurizer piping. Thinking that the reactor was getting too much 
water, the operator improperly interfered with the high-pressure 
injection system. Fortunately, a supervisor recognized what was 
happening and closed the relief valve twenty minutes later and re-
admitted coolant. No damage was done to the reactor because it had been 
operating at only 9 percent power.

The incident was investigated by both NRC and by B&W, the reactor 
supplier, but no information calling attention to the correct operating 
actions was provided to other utilities. A B&W engineer had stated in 
an internal memorandum that if the Davis-Besse event had occurred in a 
reactor operating at full power, "it is quite possible, perhaps 
probable, that core uncovering and possible fuel damage would have 
occurred.":

In 1978 an NRC official pointed out the likelihood of erroneous 
operator action in B&W reactors. The NRC did not notify utilities about 
the lessons learned at Davis-Besse and the pressing need for new 
training to avoid the confusing interpretation of water level 
indicators at B&W plants. Fourteen months later the core-melt accident 
happened at Three Mile Island.

In March 1979, a similar B&W reactor was operating at full power at 
Three Mile Island in Pennsylvania. Again, the pressure relief valve 
stuck open, reactor coolant escaped, coolant pressure fell and the 
operators made the same mistake as had the operators two years earlier 
at Davis-Besse. They turned off the high-pressure coolant injection. 
Unfortunately, the ensuing control room confusion did not lead to 
early 
diagnosis and restoration of reactor water. With. the high-pressure 
injection water incorrectly turned off, the reactor continued to 
generate heat and boil coolant, ultimately uncovering the reactor core 
and melting a substantial portion of the reactor fuel. When a 
supervisor finally diagnosed the problem and restored high-pressure 
injection water, some two hours later, enormous fuel damage had been 
done and considerable radioactivity released to the reactor building.

The President's Commission on the Accident at Three Mile Island [Kem79] 
concluded that the major factor that turned the TMI incident into a 
serious accident was inappropriate operator action, deficiencies in 
training and failure of responsible organizations, especially the NRC, 
to learn the proper lessons from previous incidents. There was a 
serious lack of recognition of the safety implications of new 
information and there was serious lack of questioning of the adequacy 
of assumptions made in the reactor design, in the operating procedures, 
and in the follow up of events. The Commission concluded that, starting 
with the Davis-Besse 1977 event and given all the deficiencies of the 
safety system and its regulation, an accident like Three Mile Island 
was eventually inevitable.

For many months and even years it was not realized that the TMI 
accident had resulted in such extensive core damage. More responsive 
earlier analyses by NRC of the 1977 Davis-Besse precursor event and its 
potential consequences would have alerted NRC to forewarn the utilities 
of the incipient danger. Similarly, the seeming lack of aggressive 
followup by NRC and industry to understand the risks from the recent 
near miss at Davis-Besse is a serious concern. History should not be 
allowed to repeat itself.

7. Recommendations for Improved Use of Probabilistic Risk Assessment:

There are several ways in which NRC can improve the use of PRA in its 
decision-making process:

(1) Establish an appreciation for PRA across the spectrum of NRC 
technical and managerial personnel. There is great divergence in the 
appreciation for, and understanding of PRA and its value in the 
decision-making process. In a sense, NRC needs to get their staff "on 
the same page" with regard to PRA applications in regulatory and 
licensing issues.

(2) Establish a set of guidelines for the use of PRA in decision-
making. No guidelines currently exist for how PRA should be 
incorporated into the decision-making process other than the general 
philosophy that risk analysis should be part of a risk-informed 
decision-making process. A set of guidelines that establishes the level 
and nature of consideration of PRA is needed. In particular, guidance 
should be provided on how to balance PRA results against deterministic 
or qualitative evaluations, especially when the PRA results are subject 
to large uncertainties.

(3) Establish a set of guidelines for how decisions are made at NRC and 
by whom. This is a necessary precursor to the success of recommendation 
2. The decision-making process must be defined in order to incorporate 
risk analysis into that process. Further, the offices and individuals 
responsible for making decisions need to be defined in order to 
successfully determine who needs to be aware of and familiar with PRA 
as discussed in recommendation 1.

(4) Establish a better protocol for estimating and incorporating 
uncertainties in PRA. PRA results without associated uncertainties are 
of little value. As a result, it is difficult to incorporate results of 
an analysis into a decision strategy without an understanding of the 
bounds of the validity of the result.

(5) Provide for unanticipated events. Corrosion of the Davis-Besse 
pressure vessel head was not an anticipated event. As put by NRC 
personnel, it was not even on the radar screen. As such, it was not 
incorporated into the event tree analysis in PRA. However, PRA needs to 
be able to anticipate the consequences of such oversight.

(6) Establish a better system at NRC for recognizing generic problems 
and transmitting information and concerns about these potential 
problems to other plants.

(7) NRC should issue preliminary analyses of risks from nozzle cracking 
that include leakage through axial cracks, evaporation of leaking 
coolant, concentration of and corrosion by boric acid, corrosion of the 
carbon-steel vessel and the vessel liner, the time-dependent 
probability of rupture of the corroded vessel, core damage resulting 
from loss of coolant, and the effects of human failure to make and 
interpret surveillance inspections. The results and possible 
interpretations of the recent Oak Ridge tests of vessel failure should 
be made known to the safety community.

References:

[Acr02] Transcript of the 491st Meeting of the Advisory Committee on 
Reactor Safeguards, U. S. Nuclear Regulatory Commission (2002).

[Bar03] R. Barrett. "Note for GAO Meeting on Dec 1, 2003," private 
communication to the review committee (2003).

[Bel02] H. T. Bell, "NRC's Regulation of Davis-Besse Regarding Damage 
to the Reactor Vessel Head (Case No. 02-03S)," U. S. Nuclear Regulatory 
Commission (2002).

[Cam01a] G. G. Campbell, "Response to NRC Bulletin 2001-01, 
Circumferential Cracking of Reactor Pressure Vessel Head Penetration 
Nozzles," FirstEnergy Nuclear Operating Company, Docket Number 50-346, 
License Number NPF-3, Serial Number 2731 (2001).

[Cam0lb] G. G. Campbell, "Response to Requests for Additional 
Information Concerning NRC Bulletin 2001-01, Circumferential Cracking 
of Reactor Pressure Vessel Head Penetration Nozzles," FirstEnergy 
Nuclear Operating Company, Docket Number 50-346, License Number NPF-3, 
Serial Number 2741 (2001).

[Cam0lc] G. G. Campbell, "Transmittal of Davis-Besse Nuclear Power 
Station Risk Assessment of Control Rod Drive Mechanism Nozzle Cracks," 
FirstEnergy Nuclear Operating Company, Docket Number 50-346, License 
Number NPF-3, Serial Number 2745 (2001).

[Cam01d] G. G. Campbell, "Supplemental Information in Response to NRC 
Bulletin 2001-01, Circumferential Cracking of Reactor Pressure Vessel 
Head Penetration Nozzles," FirstEnergy Nuclear Operating Company, 
Docket Number 50-346, License Number NPF-3, Serial Number 2735 (2001).

[Chu04] J. Chung, R. Barrett, and G. Holahan, "Response to GAO 
Questions," communication to M. B. McWreath, February 24, 2004.

[Dye02] "Davis-Besse Nuclear Power Station NRC Augmented Inspection 
Team - Degradation of the Reactor Pressure Vessel Head, Report No. 50-
346/02-03(DRS)," U. S. Nuclear Regulatory Commission (2002).

[Dye03] J. E. Dyer, "Davis-Besse Control Rod Drive Mechanism 
Penetration Cracking and Reactor Pressure Vessel Head Degradation 
Preliminary Significance Assessment, Report No. 50-346/2002-08(DRS)," 
U. S. Nuclear Regulatory Commission (2003).

[Epr01] "Boric Acid Corrosion Handbook, Revision 1," Report 1000975, 
Electric Power Research Institute (2001).

[Fle03] K. N. Fleming, "Issues and Recommendations for Advancement of 
PRA Technology in Risk-Informed Decision Making," NUREG/CR-6813, U. S. 
Nuclear Regulatory Commission (2003).

[Hub03] "NRC's Oversight of Davis-Besse Boric Acid Leakage and 
Corrosion During the April 2000 Refueling Outage (Case No. 03-02S)," 
Memorandum from H. T. Bell, 
Inspector General, to Chairman Diaz, U. S. Nuclear Regulatory 
Commission, October 17, 2003.

[Kem79] J. G. Kemeny, B. Babbitt, P. E. Haggerty, C. Lewis, P. A. 
Marks, C. B. Marrett, L. McBride, H. C. McPherson, R. W. Peterson, T. 
H. Pigford, T. B. Taylor, A. D. Trunk, "The Need For Change: The Legacy 
of TMI," Report of the Presidential Commission on The Accident at Three 
Mile Island (1979).

[Nei96] "Industry Guideline for Monitoring the Effectiveness of 
Maintenance at Nuclear Power Plants," NUMARC 93-01, Rev. 2, Nuclear 
Energy Institute (1996).

[Nrc01a] "Preliminary Staff Technical Assessment for Pressurized Water 
Reactor Vessel Head Penetration Nozzles Associated with NRC Bulletin 
2001-01, Circumferential Cracking of Reactor Pressure Vessel Head 
Penetration Nozzles," U. S. Nuclear Regulatory Commission (2001).

[Nrc01b] "Guidance on Risk-informed Decisionmaking in License Amendment 
Reviews," Regulatory Issue Summary (RIS) 2001-02, U. S. Nuclear 
Regulatory Commission (2001).

[Nrc01c] "Circumferential Cracking of Reactor Pressure Vessel Head 
Penetration Nozzles," U. S. Nuclear Regulatory Commission (2001).

[Nrc02a] "An Approach for Using Probabilistic Risk Assessment in Risk-
Informed Decisions on Plant-Specific Changes to the Licensing Basis," 
Regulatory Guide 1.174, U. S. Nuclear Regulatory Commission (2002).

[Nrc02b] "Davis-Besse Reactor Vessel Head Degradation Lessons-Learned 
Task Force Report," U. S. Nuclear Regulatory Commission (2002).

[Nrc02c] Transcript of the 20 August 2002 Interview, Office of 
Investigations, U. S. Nuclear Regulatory Commission (2002).

[Nrc03] "An Approach for Determining the Technical Adequacy of 
Probabilistic Risk Assessment Results for Risk-Informed Activities," 
Regulatory Guide 1.200, U. S. Nuclear Regulatory Commission (2003).

[Nrc90] "Severe Accident Risks: An Assessment for Five U.S. Nuclear 
Power Plants," NUREG-1150, U. S. Nuclear Regulatory Commission (1990).

[Nrc98] "An Approach for Plant-Specific Risk-Informed Decisionmaking: 
Technical Specifications," Regulatory Guide 1.177, U.S. Nuclear 
Regulatory Commission (1998).

[Pin03a] Platts: Inside NRC, McGraw-Hill Companies, February 16, 2003.

[Pin03b] Platts: Inside NRC, McGraw-Hill Companies, November 3, 2003.

[Pol99] J. P. Poloski, et al., "Rates of Initiating Events at U. S. 
Nuclear Power Plants: 1987-1995," NUREG/CR-5750, U. S. Nuclear 
Regulatory Commission (1999).

[Rau03] W. S. Raughley and G. F. Lanik, "Regulatory Effectiveness of 
the Anticipated Transient Without Scram Rule," NUREG-1780, U. S. 
Nuclear Regulatory Commission (2003).

[Rei03] "Jin Chung's email dated May 29, 2003 and subsequent 
discussion," email communication from M. Reinhart, November 25, 2003.

[Sap98] "Systems Analysis Program for Hands-On Integrated Reliability 
Evaluations (SAPHIRE)," Technical Reference Manual, Version 6, NUREG/
CR-6116, U. S. Nuclear Regulatory Commission (1998).

[Sat00] M. B. Sattison, J. K. Knudsen, L. M. Wolfram, and S. T. Beck, 
"Standardized Plant Analysis Risk Model for Davis-Besse," ASP PWR D, 
Rev. 3i, Idaho National Engineering and Environmental Laboratory 
(2000).

[Sci83] "The Salem Case: A Failure of Nuclear Logic," Science, 220,280 
(1983).

[Sha0l] W. Shack, DavisBesseANL.pdf file, October 27, 2001.

[Sha03] W. Shack, Integrated model outline.pdf file, private 
communication to G. S. Was, 2003.

[Sia02] "Elastic-Plastic Finite Element Stress Analysis of Davis-Besse 
RPV Head Wastage Cavity with Different Enlarged Areas and Thicknesses," 
Non-Proprietary Version, Structural Integrity Associates, Inc. (2002).

[Sri98] "Boric Acid Corrosion Evaluation (BACE) Corrosion Program --
Phase II Corrosion Testing," Topical Report, Southwest Research 
Institute (1998).

[Tru95] D. True, K. Fleming, G. Parry, B. Putney, and J-P Sursock, "PSA 
Applications Guide," TR-105396, Electric Power Research Institute 
(1995).

[End of section]

Appendix III: Davis-Besse Task Force Recommendations to NRC and Their 
Status, as of March 2004: 

Completed recommendations: 

Recommendation: Either fully implement or revise guidance to manage 
licensee commitments. Determine whether the periodic report on 
commitment changes submitted by licensees should continue; 
NRC actions and status as of March 2004: Revised instructions for these 
submittals and reviews to ensure that these tasks are accomplished. 
Completed in May 2003.

Recommendation: Determine if stress corrosion cracking models are 
appropriate for predicting susceptibility of vessel head penetration 
nozzles to pressurized water stress corrosion cracking. Determine if 
additional analysis and testing is needed to reduce modeling 
uncertainties for their continued applicability in regulatory decision 
making; 
NRC actions and status as of March 2004: Evaluated existing stress 
corrosion cracking models for their continuing use in determining 
susceptibility. Completed in July 2003.

Recommendation: Revise the problem identification and resolution 
approach so that safety problems noted in daily licensee reports are 
reviewed and assessed. Enhance guidance to prescribe the format of 
information that is screened when deciding which problems to review; 
NRC actions and status as of March 2004: Revised inspection procedure 
for determining licensee ability to promptly identify and resolve 
conditions adverse to quality or safety. Completed in September 2003.

Recommendation: Provide enhanced inspection guidance to pursue issues 
and problems identified during reviews of plant operations; 
NRC actions and status as of March 2004: Revised inspection procedure 
for determining licensee capability to promptly identify and resolve 
conditions adverse to quality or safety. Completed in September 2003.

Recommendation: Revise inspection guidance to provide for longer-term 
follow-up of previously identified issues that have not progressed to 
an inspection finding; 
NRC actions and status as of March 2004: Revised inspection procedure 
for determining licensee capability to promptly identify and resolve 
conditions adverse to quality or safety. Completed in September 2003.

Recommendation: Revise inspection guidance to assess (1) the safety 
implications of long-standing unresolved licensee equipment problems, 
(2) the impact of phased in corrective actions, and (3) the 
implications of deferred plant modifications; 
NRC actions and status as of March 2004: Revised inspection procedure 
for determining licensee capability to identify and resolve conditions 
adverse to quality or safety. Completed in September 2003.

Recommendation: Revise inspection guidance to allow for establishing 
reactor oversight panels even when a significant performance problem, 
as defined under NRC's Reactor Oversight Process, does not exist; 
NRC actions and status as of March 2004: Revised inspection guidance 
for establishing reactor oversight panels. Completed in October 2003.

Recommendation: Assess the scope and adequacy of requirements for 
licensees to review operating experience; 
NRC actions and status as of March 2004: Included in NRC's 
recommendation to develop a program for collecting, analyzing, and 
disseminating information on experiences at operating reactors. 
Completed in November 2003.

Recommendation: Ensure inspector training includes (1) boric acid 
corrosion effects and control, and (2) pressurized water stress 
corrosion cracking of nickel-based alloy nozzles; 
NRC actions and status as of March 2004: Developed and implemented Web-
based training and a means for ensuring training is completed. 
Completed in December 2003.

Recommendation: Provide training and reinforce expectations to managers 
and staff to (1) maintain a questioning attitude during inspection 
activities, (2) develop inspection insights from Davis-Besse on 
symptoms of reactor coolant leakage, (3) communicate expectations to 
follow up recurring and unresolved problems, and (4) maintain an 
awareness of surroundings while conducting inspections. Establish 
mechanisms to perpetuate this training; 
NRC actions and status as of March 2004: Developed Web-based inspector 
training and a means for ensuring that training has been completed. NRC 
headquarters provided an overview of the training to NRC regional 
offices. (Training modules will be added and updated as needed.) 
Completed in December 2003.

Recommendation: Reinforce expectations that regional management should 
make every effort to visit each reactor at least once every 2 years; 
NRC actions and status as of March 2004: Discussed at regional 
counterparts meeting. Completed in December 2003.

Recommendation: Develop guidance to address impacts of regional 
oversight panels on regional resource allocations and organizational 
alignment; 
NRC actions and status as of March 2004: Evaluated past and present 
oversight panels. Developed enhanced inspection approaches for 
oversight panels and issued revised procedures. Completed in December 
2003.

Recommendation: Evaluate (1) the capacity to retain operating 
experience information and perform long-term operating experience 
reviews; 
(2) thresholds, criteria, and guidance for initiating generic 
communications; 
(3) opportunities for more gains in effectiveness and efficiency by 
realigning the organization (i.e., feasibility of a centralized 
operating experience "clearinghouse"); 
(4) effectiveness of the generic Issues program; 
and (5) effectiveness of internal dissemination of operating experience 
information to end users; 
NRC actions and status as of March 2004: Developed program objectives 
and attributes and obtained management endorsement of a plan to 
implement the recommendation. Developed specific recommendations to 
improve program. Evaluation completed in November 2003. (Implementation 
of recommendations resulting from this evaluation expected to be 
completed in December 2004.).

Recommendation: Ensure that generic requirements or guidance are not 
inappropriately affected when making unrelated changes to other 
programs, processes, guidance, etc; 
NRC actions and status as of March 2004: Revised inspection guidance. 
Completed in February 2004.

Recommendation: Develop inspection guidance to assess scheduler 
influences on amount of work performed during refueling outages; 
NRC actions and status as of March 2004: Revised the appropriate 
inspection procedure. Completed in February 2004.

Recommendation: Establish guidance to ensure that NRC decisions 
allowing licensees to deviate from guidelines and recommendations 
issued in generic communications are adequately documented; 
NRC actions and status as of March 2004: Update guidance to address 
documentation. Develop training and distribute to NRC offices and 
regions to emphasize compliance with the updated guidance. Follow up to 
assess the effectiveness of the training. Completed follow-up in 
February 2004.

Recommendation: Develop or revise inspection guidance to ensure that 
NRC reviews vessel head penetration nozzles and the reactor vessel head 
during licensee inspection activities; 
NRC actions and status as of March 2004: Develop or revise inspection 
guidance to ensure that nozzles and the vessel head are reviewed during 
licensee inspection. Issued interim guidance in August 2003 and a 
temporary inspection procedure in September 2003. Additional guidance 
expected in March 2004.

Recommendation: Develop inspection guidance to assess (1) repetitive or 
multiple technical specification actions in NRC inspection or licensee 
reports, and (2) radiation dose implications for conducting repetitive 
tasks; 
NRC actions and status as of March 2004: Revise the appropriate 
inspection procedure to reflect this need. Completion expected in March 
2004.

Recommendation: Develop guidance to periodically inspect licensees' 
boric acid corrosion control programs; 
NRC actions and status as of March 2004: Issued temporary guidance in 
November 2003. Completion of further inspection guidance changes 
expected in March 2004.

Recommendation: Reinforce expectations for managers responsible for 
overseeing operations at nuclear power plants regarding site visits, 
coordination with resident inspectors, and assignment duration. 
Reinforce expectations to question information about operating 
conditions and strengthen guidance for reviewing license amendments to 
emphasize consideration of current system conditions, reliability, and 
performance data in safety evaluation reports. Strengthen guidance for 
verifying licensee-provided information; 
NRC actions and status as of March 2004: Update project manager 
handbook that provides guidance on activities to be conducted during 
site visits and interactions with NRC regional staff. Also, revise 
guidance for considering plant conditions during licensing action and 
amendment reviews. Completion expected in March 2004.

Recommendation: Assemble and analyze foreign and domestic information 
on Alloy 600 nozzle cracking. If additional regulatory action is 
warranted, propose a course of action and implement a schedule to 
address the results; 
NRC actions and status as of March 2004: Assemble and analyze alloy 600 
cracking data. Completion expected in March 2004.

Recommendations due to be completed between April and December 2004: 

Recommendation: Conduct an effectiveness review of actions taken in 
response to past NRC lessons-learned reviews; 
NRC actions and status as of March 2004: Review past lessons- learned 
actions. Completion expected in April 2004.

Recommendation: Provide inspection and oversight refresher training to 
managers and staff; 
NRC actions and status as of March 2004: Develop a training module. 
Completion expected in June 2004.

Recommendation: Establish guidance for accepting owners group and 
industry recommended resolutions for generic communications and generic 
issues, including guidance for verifying that actions are taken; 
NRC actions and status as of March 2004: Revise office instructions to 
provide recommended guidance. Completion expected in June 2004.

Recommendation: Review inspection guidance to determine the inspection 
level that is sufficient during refueling outages, including inspecting 
reactor areas inaccessible during normal operations and passive 
components; 
NRC actions and status as of March 2004: Revised an inspection 
procedure to reflect these changes. Some inspection procedure changes 
were completed in November 2003, and additional changes are expected in 
August 2004.

Recommendation: Evaluate, and revise as necessary, guidance for 
proposing candidate generic issues; 
NRC actions and status as of March 2004: Evaluate and revise guidance. 
Completion expected in October 2004.

Recommendation: Assemble and analyze foreign and domestic information 
on boric acid corrosion of carbon steel. If additional regulatory 
action is warranted, propose a course of action and implement a 
schedule to address the results; 
NRC actions and status as of March 2004: Review Argonne National 
Laboratory study on boric acid corrosion. Analyze data to revise 
inspection requirements. Completion expected in October 2004.

Recommendation: Conduct a follow-on verification of licensee actions to 
implement a sample of significant generic communications with emphasis 
on those that are programmatic in nature; 
NRC actions and status as of March 2004: Screen candidate generic 
communications to identify those most appropriate for follow-up using 
management-approved criteria. Develop and approve verification plan. 
Completion expected in November 2004.

Recommendation: Strengthen inspection guidance for periodically 
reviewing licensee operating experience; 
NRC actions and status as of March 2004: Incorporated into the 
recommendation pertaining to NRC's capacity to retain operating 
experience information. Completion expected in December 2004.

Recommendation: Enhance the effectiveness of processes for collecting, 
reviewing, assessing, storing, retrieving, and disseminating foreign 
operating experience; 
NRC actions and status as of March 2004: Incorporated into the 
recommendation pertaining to NRC's capacity to retain operating 
experience information. Completion expected in December 2004.

Recommendation: Update operating experience guidance to reflect the 
changes implemented in response to recommendations for operating 
experience; 
NRC actions and status as of March 2004: Incorporated into the 
recommendation pertaining to NRC's capacity to retain operating 
experience information. Completion expected in December 2004.

Recommendation: Review a sample of NRC evaluations of licensee actions 
made in response to owners groups' commitments to identify whether 
intended actions were effectively implemented; 
NRC actions and status as of March 2004: Conduct the recommended 
review. Completion expected in December 2004.

Recommendation: Develop general inspection guidance to periodically 
verify that licensees implement owners groups' commitments; 
NRC actions and status as of March 2004: Develop inspection procedure 
to provide a mechanism for regions to support project managers' ability 
to verify that licensees implement commitments. Completion expected in 
December 2004.

Recommendation: Conduct follow-on verification of licensee actions 
pertaining to a sample of resolved generic issues; 
NRC actions and status as of March 2004: No specific actions have been 
identified. Completion expected in December 2004.

Recommendation: Review the range of baseline inspections and plant 
assessment processes to determine sufficiency to identify and dispose 
of problems like those at Davis-Besse; 
NRC actions and status as of March 2004: No specific actions have been 
identified. Completion expected in December 2004.

Recommendation: Identify alternative mechanisms to independently assess 
licensee plant performance for self-assessing NRC oversight processes 
and determine the feasibility of such mechanisms; 
NRC actions and status as of March 2004: No specific actions have been 
identified. Completion expected in December 2004.

Recommendation: Establish measurements for resident inspector staffing 
levels and requirements, including standards for satisfying minimum 
staffing levels; 
NRC actions and status as of March 2004: Develop standardized staffing 
measures and implement details. Metrics were developed in December 
2003. Completion expected in December 2004.

Recommendation: Structure and focus inspections to assess licensee 
employee concerns and a "safety conscious work environment."; 
NRC actions and status as of March 2004: No specific actions have been 
identified. Completion expected in December 2004.

Recommendations due to be completed in calendar year 2005: 

Recommendation: Develop inspection guidance and criteria for addressing 
licensee response to increasing leakage levels and/or adverse trends in 
unidentified reactor coolant system leakage; 
NRC actions and status as of March 2004: Develop recommendations for 
guidance with action levels to trigger greater NRC interaction with 
licensees in response to increased leakage. Completion expected in 
January 2005.

Recommendation: Reassess the basis for the cancellation, in 2001, of 
certain inspection procedures (i.e., boric acid control programs and 
operational experience feedback) to assess if these procedures are 
still applicable; 
NRC actions and status as of March 2004: Review revised procedures and 
reactivate as necessary. Completion expected in March 2005.

Recommendation: Assess requirements for licensee procedures to respond 
to plant alarms for leakage to determine whether requirements are 
sufficient to identify reactor coolant pressure boundary leakage; 
NRC actions and status as of March 2004: Review and assess adequacy of 
requirements and develop recommendations to (1) improve procedures to 
identify leakage from boundary, (2) establish consistent technical 
specifications for leakage, and (3) use enhanced leakage detection 
systems. Completion expected in March 2005.

Recommendation: Determine whether licensees should install enhanced 
systems to detect leakage from the reactor coolant system; 
NRC actions and status as of March 2004: Re-evaluate the basis for 
current leakage requirements and assess the capabilities of current 
leakage detection systems. Develop recommendations to (1) improve 
procedures for identifying leakage, (2) establish consistent technical 
specifications, and (3) use enhanced leakage detection systems. 
Completion expected in March 2005.

Recommendation: Inspect the adequacy of licensee's programs to control 
boric acid corrosion, including effectiveness of implementation; 
NRC actions and status as of March 2004: Develop guidance to assess 
adequacy of corrosion control programs, including implementation and 
effectiveness, and evaluate the status of this effort after the first 
year of inspections. Guidance expected to be developed by March 2004. 
Follow-up scheduled for completion in March 2005.

Recommendation: Continue ongoing efforts to review and improve the 
usefulness of barrier integrity performance indicators and evaluate the 
use of primary system leakage that licensees have identified but not 
yet corrected as a potential indicator; 
NRC actions and status as of March 2004: Develop and implement improved 
performance indicators based on current requirements and measurements. 
Explore the use of additional performance indicators to track the 
number, duration, and rate of system leakage. Determine the feasibility 
of establishing a risk-informed performance indicator for barrier 
integrity. Completion expected in December 2005.

Recommendations whose completion dates have yet to be determined: 

Recommendation: Encourage the American Society of Mechanical Engineers 
to revise inspection requirements for nickel-based alloy nozzles. 
Encourage changes to requirements for nonvisual, nondestructive 
inspections of vessel head penetration nozzles. Alternatively, revise 
NRC regulations to address the nature and scope of these inspections; 
NRC actions and status as of March 2004: Monitor and provide input to 
industry efforts to develop revised inspection requirements. 
Participate in American Society of Mechanical Engineers' meetings and 
communicate with appropriate stakeholders. Decide whether to endorse 
the revised American Society of Mechanical Engineers' code 
requirements. These actions parallel a larger NRC rulemaking effort. 
Completion date yet to be determined.

Recommendation: Revise processes to require short-and long-term 
verification of licensee actions to respond to significant NRC generic 
communications before closing out issues; 
NRC actions and status as of March 2004: Target date to be set upon 
completion of review of NRC's generic communications program. 
Completion date yet to be determined.

Recommendation: Determine whether licensee reactor vessel head 
inspection summary reports should be submitted to NRC and, if so, 
revise submission requirements and report disposition guidance, as 
appropriate; 
NRC actions and status as of March 2004: Will be included as part of 
revised American Society of Mechanical Engineers' requirements for 
inspection of reactor vessel heads and vessel head penetration nozzles. 
Completion date yet to be determined.

Recommendation: Evaluate the adequacy of methods for analyzing the risk 
of passive component degradation and integrate these methods and risks 
into NRC's decision-making processes; 
NRC actions and status as of March 2004: No specific actions have been 
identified. Completion date yet to be determined.

Recommendation: Review pressurized water reactor technical 
specifications to identify plants that have nonstandard reactor coolant 
pressure boundary leakage requirements and change specifications to 
make them consistent among all plants; 
NRC actions and status as of March 2004: Assessed plants for 
nonstandard technical specifications. Completed in July 2003. Change 
leakage detection specifications in coordination with other changes in 
leakage detection requirements. Completion date yet to be determined.

Recommendation: Improve requirements for unidentified leakage in 
reactor coolant system to ensure they are sufficient to (1) 
discriminate between unidentified leaks from the coolant system and 
leaks from the reactor coolant pressure boundary and (2) ensure that 
plants do not operate with pressure boundary leakage; 
NRC actions and status as of March 2004: Issue regulations implementing 
the improved requirements when these requirements are determined. 
Completion date yet to be determined.

Recommendation: NRC should review a sample of plant assessments 
conducted between 1998 and 2000 to determine if any identified plant 
safety issues have not been adequately assessed; 
NRC actions and status as of March 2004: No specific actions have been 
identified. Completion expected in March 2004.

Recommendations rejected by NRC management: 

Recommendation: Review industry approaches licensees use to consider 
economic factors for inspection and repair and consider this 
information in formulating future positions on the performance of non-
visual inspections of vessel head penetration nozzles; 
NRC actions and status as of March 2004: Recommendation rejected by NRC 
management. No completion date.

Recommendation: Revise the criteria for review of industry topical 
reports to allow for NRC staff review of safety-significant reports 
that have generic implications but have not been formally submitted for 
NRC review in accordance with the existing criteria; 
NRC actions and status as of March 2004: Recommendation rejected by NRC 
management. No completion date. 

Source: GAO analysis of NRC data.

[End of table]

[End of section]

Appendix IV: Comments from the Nuclear Regulatory Commission: 

UNITED STATES NUCLEAR REGULATORY COMMISSION 
WASHINGTON, D.C. 20555-0001:

May 5, 2004:

Mr. James Wells, Director:

Natural Resources and Environment 
United States General Accounting Office 
441 G Street, NW:
Washington, D.C. 20548:

Dear Mr. Wells:

On behalf of the U.S. Nuclear Regulatory Commission (NRC), I am 
responding to your letter of April 2, 2004, requesting the NBC's review 
of the draft report entitled "Nuclear Regulation: NRC Needs to More 
Aggressively and Comprehensively Resolve Issues Related to the Davis-
Besse Nuclear Power Plant's Shutdown" (GAO-04-415). I appreciate the 
opportunity to provide comments to the General Accounting Office (GAO) 
on this report.

I am concerned that the draft report does not appropriately 
characterize or provide a balanced perspective on the NBC's actions 
surrounding the discovery of the Davis-Besse reactor vessel head 
condition or NBC's actions to incorporate the lessons learned from that 
experience into our processes. The NRC also does not agree with two of 
the report's recommendations, as discussed in the following paragraphs.

The first sentence of the draft report states: "...oversight did not 
generate accurate, complete information on plant conditions." I agree 
that our oversight program should have identified certain evolving 
plant conditions for regulatory follow-up. This was also identified in 
the report of the Davis-Besse Lessons Learned Task Force (LLTF) that 
the NRC formed to ensure that lessons from the Davis-Besse experience 
are learned and appropriately captured in the NBC's formal processes. 
However, the draft report does not acknowledge that the NRC, in 
carrying out its safety responsibilities, must rely heavily on our 
licensees to provide us with complete and accurate information. In 
fact, Title 10 of the Code of Federal Regulations Section 50.9 requires 
that information provided to the NRC by a licensee be complete and 
accurate in all material respects. The report should clearly indicate 
that NBC's licensees are responsible for providing us with accurate and 
complete information. While the NBC's Davis-Besse LLTF concluded that 
the NRC, the Davis-Besse licensee (FirstEnergy), and the nuclear 
industry failed to adequately review, assess, and follow up on relevant 
operating experience, they also noted that the information that 
FirstEnergy provided in response to Bulletin 2001-01, "Circumferential 
Cracking of Reactor Pressure Vessel Head Penetration Nozzles" was 
inconsistent with information identified by the task force. Further, 
the LLTF report stated that had this information been known in the fall 
of 2001, "...the NRC may have identified the VHP [vessel head 
penetration] nozzle leaks and RPV [reactor pressure vessel] head 
degradation a few months sooner than the March 2002 discovery by the 
licensee." As you are aware, there is an ongoing investigation by the 
Department of Justice regarding the completeness and accuracy of 
information that FirstEnergy provided to the NRC on the condition of 
Davis-Besse.

The NRC is particularly concerned about the draft report's 
characterization of the NBC's use of risk estimates. The statement in 
the report that the NBC's "estimate of risk exceeded the risk 
levels generally accepted by the agency" is not factually correct. NRC 
officials pointed out to GAO and GAO's consultants, both in interviews 
and in written responses to GAO questions, that our estimate of delta 
core damage frequency was 5x10[^-6] per reactor year, not 5x10^-5 per 
reactor year as indicated in the report. In fact, the NRC staff safety 
evaluation (attached to a December 3, 2002, letter to FirstEnergy) 
stated that the change in core damage frequency due to the potential 
for control rod drive mechanism nozzle ejection was consistent with the 
guidelines of Regulatory Guide 1.174, "An Approach for Using 
Probabilistic Risk Assessment in Risk-Informed Decisions on Plant-
Specific Changes to the Licensing Basis." The enclosure to this letter 
provides detailed comments on issues of correctness and clarity in the 
report, many of which are related to the NBC's estimate of risk at 
Davis-Besse.

We disagree with the finding that the NRC does not have specific 
guidance for deciding on plant shutdowns and with the report's related 
recommendation identifying the need for NRC to develop specific 
guidance and a well-defined process for deciding when to shut down a 
nuclear power plant. We believe our regulations, guidance, and 
processes that cover whether and when to shut down a plant are robust 
and do, in fact, provide sufficient guidance in the vast majority of 
situations. Plant technical specifications, as well as many other NRC 
requirements and processes, provide a spectrum of conditions under 
which plant shutdown would be required. Plants have shut down numerous 
times in the past in accordance with NRC requirements. From time to 
time, however, a unique situation may present itself wherein sufficient 
information may not exist or the information available may not be 
sufficiently clear to apply existing rules and regulations 
definitively. In these unique instances, the NBC's most senior 
managers, after consultation with staff experts and given all of the 
information available at the time, will decide whether or not to 
require a plant shutdown. Risk information is used in accordance with 
Regulatory Guide 1.174. This process considers deterministic factors as 
well as probabilistic factors (i.e., risk information). We regard the 
combined use of deterministic and probabilistic factors to be a 
strength of our decision-making process.

Another issue identified in the draft report as a systemic weakness is 
that the NRC has not proposed specific actions to address a licensee's 
commitment to safety, also known as safety culture. We disagree with 
the report's recommendation that NRC should develop a methodology to 
assess licensees' safety culture that includes indicators of and/or 
information on patterns of licensee behavior, as well as on licensee 
organizational structures and processes. To date, the Commission has 
specifically decided not to conduct direct evaluations or inspections 
of safety culture as a routine part of assessing licensee performance 
due to the subjective nature of such evaluations. As regulators, we are 
not charged with managing our licensees' facilities. Direct involvement 
with safety culture, organizational structure, and processes crosses 
over to a management function. The NRC does conduct a number of 
assessments that adequately evaluate how effectively licensees are 
managing safety. These include an inspection procedure for assessing 
licensees' employee concerns programs, the NRC allegation program, 
enforcement of employee protection regulations, and safety-conscious 
work environment assessments during problem identification and 
resolution (PI&R) inspections. In addition, the NBC's LLTF made several 
recommendations (which are being addressed) to enhance the NBC's 
capability in this area. The NRC does not assess, nor does it plan to 
assess, licensee management competence, capability, or optimal 
organizational structure as part of safety culture.

While there are a number of factual errors in the draft report, as 
noted in the enclosure, we agree with many of the findings in the draft 
report. Most of GAO's findings are similar to the findings of the NBC's 
Davis-Besse LLTF. The NRC staff has made significant progress in 
implementing actions recommended by the LLTF and expects to complete 
implementation of more than 70 percent of them, on a prioritized basis, 
by the end of calendar year 2004. Reports tracking the status of these 
actions are provided to the Commission semiannually and will continue 
until all items are completed, at which time a final summary report 
will be issued.

I have enclosed the NBC's detailed comments on the draft report. If you 
have any questions, please contact Stacey L. Rosenberg, of my staff, at 
(301) 415-3868.

Sincerely,

Signed for: 

William D. Travers: 
Executive Director for Operations:

Enclosure:

1. NRC Comments on GAO Draft Report on Davis-Besse 2. Memorandum from 
EDO to OIG dated April 19, 2004:

NRC Comments on Draft Report, GAO-04-415:

1. The draft report does not speak to a key issue, the responsibility of 
licensees to provide complete and accurate information to the NRC. In 
carrying out its safety responsibilities, NRC must rely heavily on our 
licensees to provide us with complete and accurate information. Title 
10 of the Code of Federal Regulations Section 50.9 requires that 
information provided to the NRC by a licensee be complete and accurate 
in all material respects. By not recognizing this explicitly and its 
role in this matter, the draft report conveys the expectation that the 
NRC staff should have known about the thick layer of boron on the 
reactor vessel head. The Davis-Besse Lessons Learned Task Force (LLTF), 
which NRC formed to ensure that lessons from the Davis-Besse experience 
are learned and appropriately captured in the NBC's formal processes, 
noted that the information that FirstEnergy provided in response to 
Bulletin 2001-01, "Circumferential Cracking of Reactor Pressure Vessel 
Head Penetration Nozzles" was inconsistent with information identified 
by the task force. Further, the LLTF report stated that had this 
information been known in the fall of 2001, the NRC may have identified 
the vessel head penetration (VHP) nozzle leaks and reactor pressure 
vessel (RPV) head degradation a few months sooner than the March 2002 
discovery by the licensee. See also the related information in response 
#2.

2. Page 7, first sentence of the last paragraph states: "NRC should have 
but did not identify or prevent the vessel head corrosion at Davis-
Besse because both its inspections at the plant and its assessments of 
the operator's performance yielded inaccurate and incomplete 
information on plant safety conditions.":

Response: This statement is misleading. We agree that our oversight 
program should have identified certain evolving plant conditions for 
regulatory follow-up. This was also 
identified in the report of the Davis-Besse Lessons LLTF. It is the 
responsibility of licensees to provide the NRC with complete and 
accurate information. In fact, Title 10 of the Code of Federal 
Regulations Section 50.9 requires that information provided to the NRC 
by a licensee be complete and accurate in all material respects. The 
report should clearly indicate that NBC's licensees are responsible for 
providing us with accurate and complete information. While the NBC's 
Davis-Besse LLTF concluded that the NRC, the Davis-Besse licensee 
(FirstEnergy), and the nuclear industry failed to adequately review, 
assess, and follow up on relevant operating experience, the LLTF also 
noted that the information that FirstEnergy provided in response to 
Bulletin 2001-01 was inconsistent with information identified by the 
task force. Further, the LLTF report stated that had this information 
been known in the fall of 2001, the NRC may have identified the vessel 
head penetration nozzle leaks and the reactor vessel head degradation a 
few months sooner than the March 2002 discovery by the licensee. As you 
are aware, there is an ongoing investigation by the Department of 
Justice regarding the completeness and accuracy of information that 
FirstEnergy provided to the NRC on the condition of Davis-Besse.

3. Page 8, last sentence states: "Further, the risk estimate indicated 
that the likelihood of an accident occurring at Davis-Besse was greater 
than the level of risk generally accepted as being reasonable by NRC.":

Response: This is incorrect. NRC staff explained to the GAO consultants 
that NRC guidance produces an estimate for the change in core damage 
frequency of 5x10 per year, not 5x10"5 as indicated in the GAO report. 
According to Regulatory Guide 
(RG) 1.174, for Davis-Besse, this estimate is within acceptable bounds. 
NRC specifically documented the acceptability of the estimate in the 
December 2002 assessment. Thus, the December 3, 2002, safety evaluation 
concluded that the delta core damage frequency was consistent with the 
guidelines of RG 1.174.

4. Page 15 states that borax (i.e., sodium borate) is dissolved in the 
water. This is incorrect. Please replace the word "borax" with "boric 
acid crystals.":

5. Page 18, first full paragraph states: "NRC, in deciding on when 
FirstEnergy had to shutdown Davis-Besse for the inspection,...":

Response: In addition, the staff relied upon information provided by 
the licensee regarding the condition of the vessel head (i.e., previous 
leakage and action taken to. repair leaks and clean the vessel head).

6. Page 26, beginning on line 4, states: "According to the NRC regional 
branch chief-who supervised the staff responsible for overseeing 
FirstEnergy's vessel head inspection activities during the 2000 
refueling outage-he was unaware of the boric acid leakage issues at 
Davis-Besse, including its effects on the containment air coolers and 
the radiation monitor filters.":

Response: According to the individual to whom this statement is 
attributed, the statement would be correct if the phrase, "he was 
unaware ... filters" is changed to "he was unaware that boric acid was 
found on the reactor vessel head during the outage.":

7. Page 27, first sentence states: "Similarly, NRC officials said that 
NRC headquarters had no systematic process for communicating 
information in a timely manner to its regions or on-site inspectors.":

Response: If the "information" in question refers to issues of 
potential safety significance into which inspectors should look, then 
this statement is inaccurate. The systematic process for temporarily 
focusing inspection activity in a coordinated program-wide manner on 
high-priority issues is the "Temporary Instruction" (TI) process, which 
is well established within the NRC Inspection Manual and frequently 
used. The legitimate point 
to be made is that until the Davis-Besse event, the NRC had not 
concluded that boric acid corrosion was a sufficient safety concern 
that reached the threshold for using the TI process.

8. Page 33, middle paragraph states: "For example, concern over alloy 
600 cracking led France, as a preventive measure, to develop plans for 
replacing all of its reactor vessel heads and installing removable 
insulation to better inspect for cracking." Response: French regulators 
instituted requirements for an extensive, non-visual nondestructive 
examination inspection program for vessel head penetration nozzles that 
resulted in plant operators deciding, on the basis of economic 
considerations, to replace vessel heads in lieu of conducting such 
examinations.

9. Page 34, last paragraph states: "If such small leakage can result in 
such extensive corrosion... ":

Response: Small leakage alone was not the cause of the corrosion. It 
was a combination of prolonged leakage in conjunction with allowing 
caked-on boron to remain on the vessel head.

10. Page 36, middle paragraph states: "However, NRC decided that it 
could not order Davis-Besse to shut down on the basis of other plants' 
cracked nozzles and identified leakage or the manager's acknowledgment 
of a probable leak. Instead, it believed it needed more direct, or 
absolute, proof of a leak to order a shutdown." Response: As discussed 
at the NRC-GAO exit conference, plant Technical Specifications, as well 
as many other NRC requirements and processes, provide a number of 
circumstances in which a plant shutdown would or could be required, 
including the existence of reactor coolant pressure boundary leakage 
while operating at power.

Please note that there was no legal objections to the draft order and 
the stated basis for deciding to not issue the order was not an 
insufficient legal basis.

11. Page 36, last paragraph states: ":..NRC does not have specific 
guidance for shutting down a plant when the plant may pose a risk to 
public health and safety even though it may be complying with NRC 
requirements.":

Response: We disagree with this finding and with the report's related 
recommendation on Page 63 identifying the need for NRC to develop 
specific guidance and a well-defined process for deciding when to shut 
down a nuclear power plant. We believe our regulations, guidance, and 
processes that cover whether and when to shut down a plant are robust 
and do, in fact, provide sufficient guidance in the vast majority of 
situations. Plant technical specifications, as well as many other NRC 
requirements and processes, provide a spectrum of conditions under 
which plant shutdown would be required. Plants have shut down numerous 
times in the past in accordance with NRC requirements. From time to 
time, however, a unique situation may present itself wherein sufficient 
information may not exist or the information available may not be 
sufficiently clear to apply existing rules and regulations 
definitively. In these unique instances, the NRC's most senior 
managers, after consultation with staff experts and given all of the 
information available at the time, will decide whether or not to 
require a plant shutdown. Risk information is used in accordance with 
RG 1.174. This process considers deterministic factors as well as 
probabilistic factors (i.e., risk information). We regard the combined 
use of deterministic and probabilistic factors to be a strength of our 
decisionmaking process.

12. Page 38, third paragraph states: "At some point during this time, 
NRC staff also concluded that the first safety principle was probably 
not being met, although the basis for this conclusion is not known.":

Response: The report should clarify GAO's basis for this statement. NRC 
staff believed that the regulations were met.

13. Page 40, last paragraph states: "However, NRC did not provide the 
assessment until a full year later-in December 2002. In addition, the 
December 2002 assessment, which includes a 4 -page evaluation, does not 
fully explain how the safety principles were used or met-other than by 
stating that if the likelihood of nozzle failure were judged to be 
small, then adequate protection would be ensured.":

Response: The attachment to the December 3, 2002, letter is an 8-page 
evaluation, not 4 pages. We note this to make sure GAO is referring to 
the same document. The assessment addresses four of the five safety 
principles. In the NRC's December 2002 safety evaluation, the staff 
stated that the criterion related to compliance with the regulations 
was being met because the inspections performed by the licensee were in 
conformance with the ASME Code. In addition, the safety evaluation 
stated that Davis-Besse met the criterion related to defense-in-depth 
because all three barriers against release of radiation were intact and 
reliable; they met the margin criterion because even the largest 
circumferential cracks found in pressurized-water reactors had 
considerable margin to structural failure, and they met the low-risk 
impact criterion based on a comparison of delta core damage frequency 
estimates with the guidelines of RG 1.174. The fifth safety principle, 
requiring a monitoring program, was not relevant to a decision that 
lasted only 6 weeks.

14. Page 42, first paragraph states: "Multiplying these two numbers, NRC 
estimated that the potential for a nozzle to crack and cause a loss-of-
coolant accident would increase the frequency of core damage at Davis-
Besse by about 5.4x1015 per year, or about 1 in 18,500 per year. 
Converting this frequency to a probability, NRC 
calculated that the increase in probability of core damage was 
approximately 5.0x10, or 1 chance in 200,000. While NRC officials 
currently disagree that this was the number it used, this is the number 
that it included in its December 2002 assessment provided to 
FirstEnergy. Further, we found no evidence in the agency's records to 
support NRC's current assertion.":

Response: These statements mischaracterize the facts. NRC estimated 
that the probability of nozzle cracking leading to a loss-of-coolant 
accident during the first 6 weeks in 2002 would increase the annual 
core damage frequency (CDF) by about 5.4x10^-6 per year, or about 1 in 
185,000 per year. The estimate of 5x10^-5 was an intermediate step in 
our calculation. The estimate of 5x10^-5 represents the change in CDF 
if Davis-Besse were allowed to operate for one year without shutting 
down for inspection of the vessel head. Allowing Davis-Besse to 
continue to operate for one year was never a consideration. Thus, 
multiplying by the fraction of time in one year under consideration (in 
this case:

7 weeks) was the final step in the calculation of delta CDF. The 
confusion about the estimate NRC used in the decisionmaking process may 
be due to NRC's method of calculating delta CDF for plant conditions 
which do not persist for the entire year. If this final step (the 
fraction of the year the plant is allowed to operate) were not part of 
the calculation, then the risk estimate of allowing the licensee to 
continue to operate for:

7 weeks, as compared to one year, would be the same. Logically, this 
does not make sense. Therefore, the estimate of 5x10"5 does not 
automatically convert to a probability, as GAO's statement implies. 
Because the period of operation under consideration was approximately 
0.13 years, the annual average change in CDF was about 5x10^-6 per 
year, and the increase in the probability of core damage was about 
5x106 as well. NRC officials agree that 5x106 was the estimate used in 
the decisionmaking process and is the estimate provided in the December 
2002 assessment.

15. Page 42, second paragraph states: "For example, the consultants 
concluded that NRC's estimate of risk was incorrectly too small, 
primarily because the calculation did not consider corrosion of the 
vessel head.":

Response: An underlying assumption in any risk assessment is that you 
have complete and accurate information from the licensee. NRC staff was 
of the understanding that efforts had been made to remove boric acid 
accumulation from the vessel head during previous outages. For all six 
B&W plants that found signs of penetration leakage, the leakage 
manifested itself in the form of small amounts of dry boron crystals on 
the vessel head, which are not corrosive, and did not produce any 
corrosion on the vessel heads of these six B&W plants. Boron leaking 
onto a clean vessel head does not cause corrosion. Therefore, corrosion 
this extensive was not anticipated at the time. Also, it is important 
to note that had Davis-Besse shut down on December 31, 2001, the same 
corrosion would have been found.

16. Page 43, first full paragraph discusses the experience at French 
nuclear power plants. Response: The NRC staff was aware of the issue as 
illustrated in an internal memorandum dated December 15, 1994, from 
Brian Grimes to Charles Rossi.

17. Page 44, first full paragraph states: "Third, NRC's analysis was 
inadequate because the risk estimates were higher than generally 
considered acceptable under NRC guidance. Despite PRA's [probabilistic 
risk assessment's] important role in the decision, our consultants 
found that NRC did not follow its guidance for ensuring that the 
estimated risk was within levels acceptable to the agency. Page 45, 
first paragraph states: "...NRC's PRA estimate for Davis-Besse resulted 
in an increase in the frequency of core damage of 5.4x10^-5 or 1 chance 
in about 18,500 per year was higher than the acceptable level.":

Response: This conclusion is not supported by the facts and it is 
misleading. The estimate referenced by GAO is an intermediate 
calculation in our process, and was not used, and should not be used, 
in the decisionmaking process. NRC staff explained to the GAO 
consultants that NRC guidance produces an estimate for the change in 
core damage frequency of 5x10^-6 per year, not 5x10^-5 as indicated in 
the GAO report. According to RG 1.174, for Davis-Besse, this estimate 
is within acceptable bounds. NRC specifically documented the 
acceptability of the estimate in the December 2002 assessment. Thus, 
the December 3, 2002, safety evaluation concluded that the delta CDF 
was consistent with the guidelines of RG 1.174.

18. Page 45, first paragraph states: "NRC's guidance for evaluating 
requests to relax NRC technical specifications suggests that a 
probability increase higher than 5x10^-7 or 1 chance in 2 million is 
considered unacceptable for relaxing the specifications. Thus, NRC's 
estimate would not be considered acceptable under this guidance." 
Response: This criterion in RG 1.177 is not relevant to the Davis-Besse 
decision. It is confined to decisions on allowed outage times (AOT) for 
equipment, and is defined to avoid very high instantaneous risks (CDF > 
10^-3) for very short periods (5 hours).

19. Page 46, first full paragraph states: "Lastly, NRC's analysis was 
inadequate because the agency does not have clear guidance for how PRA 
estimates are to be used in the decision-making process.":

Response: The NRC's process for risk-informed decision-making is 
considerably more robust than characterized in this section. Regulatory 
Guide 1.174 comprises 40 pages of guidance on how to use risk in 
decisions of this type, and it is backed up by equally detailed 
guidance for specific types of decisions such as technical 
specifications, in-service inspection programs, in-service testing, 
and quality assurance. The NRC has 
amassed a great deal of experience in application of the guidance. Risk 
assessment is a tool to help better inform decisions that are based on 
engineering judgements.

20. Page 46, last paragraph states: "it is not clear how NRC staff used 
the PRA risk estimate in the Davis-Besse decision-making process.":

Response: The December 3, 2002, safety evaluation clearly states how 
the PRA estimate was used in the decisionmaking process; the estimate 
was compared with the guidelines of RG 1.174. The safety evaluation 
also points out that N RC staff who are expert in non-PRA disciplines 
such as probabilistic fracture mechanics, gave more weight to 
deterministic factors, such as the structural margin that remains in 
the nozzles with circumferential cracks. The NRC considers the combined 
use of deterministic and probabilistic factors to be a strength of our 
decisionmaking process.

21. Page 48, last paragraph states: ":..NRC had made progress in 
implementing the recommendations, although some completion dates have 
slipped.":

Response: The schedules for implementation of all high priority 
recommendations have not slipped. The implementation schedule for 
certain low or medium priority recommendations slip only in accordance 
with NRC's Planning, Budgeting and Performance Management (PBPM) 
process, which explicitly considers safety significance when making 
budget priority decisions.

22. Page 51, top of page, first full bullet states: "One recommendation 
is directed at improving NRC's generic communications program. NRC 
is...":

Response: We recommend re-wording this as follows: "One recommendation 
is directed at improving follow up of licensee actions taken in 
response to NRC generic communications. A Temporary Instruction 
(Inspection Procedure) is currently being 
developed to assess the effectiveness of licensee actions taken in 
response to generic communications. Additionally, improvements in the 
verification of effectiveness of generic communications are planned as 
a long-term change in the operating experience program.":

23. Page 51, last paragraph states: "...NRC's revised inspection 
guidance for more thorough examinations of reactor vessel heads and 
nozzles, as well as new requirements for NRC oversight of licensees' 
corrective action programs, will require at least an additional 200 
hours of inspection per reactor per year." Response: It is unclear 
where this number comes from, but the changes to the corrective action 
program procedure require only about 16 hours per reactor year for the 
trend review.

24. Page 53, first paragraph discusses the NRC's Office of the Inspector 
General's (OIG's) findings on communications.

Response: The NRC's actions are not limited primarily to improving 
communication about boric acid corrosion and cracking. There are 
multiple task force recommendations, and other NRC initiatives, that 
are aimed at addressing the broader implications stemming from 
communication lapses noted by the task force and the OIG. For example, 
actions have been implemented to more effectively disseminate operating 
experience to end users, reenforce a questioning attitude in the 
inspection staff, and discuss Davis-Besse lessons learned at various 
forums.

NRC's initial response to the OIG did not directly address the broader 
actions we are taking to improve communications. Our response to the 
OIG only indirectly addressed this by discussing the operating 
experience program enhancements. Part of the 
enhancements to the operating experience program is the expectations 
for improved communications. In addition, communication improvement 
initiatives with internal and external stakeholders are in progress to 
address shortcomings in this critical area. Our revised response to the 
OIG on this issue, dated April 19, 2004, is provided as Enclosure 2.

25. Page 53, second paragraph states: "NRC's Davis-Besse task force did 
not make any recommendations to address two systemic problems: 
evaluating licensees' commitment to safety and improving the agency's 
process for deciding on a shutdown. ":

Response: The LLTF did not make a recommendation for improving the 
agency's process for deciding on a shutdown. This area was not reviewed 
in detail by the task force because of coordination with the OIG. 
Moreover, the task force review efforts were focused on why the 
degradation cavity was not prevented. While related, the shutdown issue 
had little to do with the degradation cavity.

The task force made multiple recommendations aimed at enhancing NRC's 
capability to evaluate the licensees' commitment to safety, by indirect 
means. Refer to task force recommendations: 3.2.5(1), 3.2.5(2), 
3.3.2(2), 3.3.4(5), and Appendix F.

26. Page 54, last paragraph states: "This problem identification and 
resolution inspection procedure is intended to assess the end-results 
of management's safety commitment rather than the commitment itself.":

Response: This statement is inaccurate. Regarding its accuracy, the 
PI&R inspection procedure (IP 71152) actually has six stated inspection 
objectives (refer to section 71152-01) including: (1) provide for early 
warning of potential performance issues that could 
result in crossing threshold in the action matrix and (2) to provide 
insights into whether licensees have established a safety-conscious 
work environment. Using this IP, inspectors seek factual evidence of 
the licensee's assumed commitment to safety (by reviewing their 
identification and correction of actual problems). Inspection issues 
routinely are raised with regard to a licensee's weakness in correcting 
recurrent problems or in adequately addressing issues that could become 
a future significant safety concern. The statement on Page 55 of the 
report, "Furthermore, because NRC directs its inspections at problems 
that it recognizes as being more important to safety, NRC may overlook 
other problems until they develop into significant and immediate safety 
problems" does not accurately reflect the stated objectives and 
demonstrable implementation of IP 71152.

27. Pages 55-56, discuss safety culture.

Response: To a significant degree, the areas referenced in this draft 
report are addressed either by NRC requirements or inspection 
activities. For example, the NRC has requirements limiting work hours 
for critical plant staff members such as security officers and plant 
operators. The NRC has requirements governing operator training. 
Inspectors routinely monitor various licensee meetings and job 
briefings to evaluate the licensee's emphasis on safety.

Moreover, the NRC has a number of other means to indirectly assess 
safety culture. Other NRC tools that provide indirect insights into 
licensee safety culture include:

inspection procedure for assessing the licensee's employee concerns 
program, NRC's allegation program,

enforcement of employee protection regulations,

Safety-Conscious Work Environment (SCWE) assessments during problem 
identification and resolution inspections,

lessons-learned reviews such as the one conducted for the Davis-Besse 
reactor pressure vessel head degradation; and:

Reactor Oversight Process cross-cutting issues of human performance, 
problem identification and resolution, and SCWE.

28. Page 58, paragraph under the first header states: "it recognized 
that NRC's written rationale for accepting FirstEnergy's justification 
for continued plant operation was not prepared until 1 year after its 
decision...":

Response: For clarification, the documentation of the decision about 
one year later was corrective action from a task force finding.

29. Page 58, paragraph under second header states: "The NRC task force 
did not address NRC's failure to learn from previous incidents at power 
plants and prevent their recurrence.":

Response: This sentence is factually inaccurate. The task force 
performed a limited review of past lessons-learned reports and actually 
identified many more potentially recurring programmatic issues as a 
result of that review than the three examples cited by the GAO in this 
section of the draft report. As discussed during the NRC-GAO exit 
conference, the task force made a recommendation to perform a more 
detailed effectiveness review of the actions stemming from other past 
NRC lessons learned reviews (Appendix F). This review is currently in 
progress.

UNITED STATES:

NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001:

April 19, 2004:

MEMORANDUM TO: 
Hubert T. Bell Inspector General:

FROM: William D. Travers [RA Carl J. Paperiello Acting For] 
Executive Director for Operations:

SUBJECT: FEBRUARY 2, 2004, OFFICE OF INSPECTOR GENERAL (OIG) MEMORANDUM 
CONCERNING AGENCY RESPONSE TO OIG EVENT INQUIRY CASE NO. 03-02S (NRC'S 
OVERSIGHT OF DAVIS-BESSE BORIC ACID LEAKAGE AND CORROSION DURING THE 
APRIL 2000 REFUELING OUTAGE):

This memorandum responds to your memorandum to Chairman Diaz, dated 
February 2, 2004, concerning the Nuclear Regulatory Commission (NRC) 
staff's response of January 12, 2004, to OIG Event Inquiry 03-02S. The 
referenced OIG event inquiry was initiated in response to a 
Congressional request that OIG determine how the NRC staff handled 
Davis-Besse Condition Report (CR) 2000-0782 at the time of discovery in 
refueling outage (RFO) 12 (2000) and whether the CR was considered in 
the November 2001 decision to allow Davis-Besse to continue to operate 
to February 16, 2002. The NRC staff's previous response to OIG (January 
12, 2004) regarding this issue provided a matrix of those 
recommendations from the Davis-Besse Lessons Learned Task Force 
(DBLLTF) report that specifically addressed the event inquiry findings 
and referenced the report for a complete picture of the staff's 
efforts. The OIG response of February 2, 2004, stated that the NRC 
staff had not addressed the problem of communications as an underlying 
cause of the findings of the OIG event inquiry and that the agency 
should include an expectation of improved communication between and 
among NRC Headquarters and regional staff and should outline specific 
guidance to achieve this goal. In addition, OIG specifically concluded 
that "had the [Davis-Besse Nuclear Power Station] DBNPS inspectors been 
better informed of ongoing NRC industry-wide efforts to address coolant 
pressure boundary leakage and the effects of boric acid corrosion, they 
would have recognized the significance of Condition Report 2000-0782 
and highlighted the information to regional management.":

The DBLLTF report discusses the NBC's and industry's failure to 
understand the significance of boric acid corrosion of the reactor 
vessel head. The NRC staff believes that this failure caused the 
underlying communications lapses. Although the potential for this type 
of degradation existed previously, the significance of boric acid 
deposits was not understood by the staff. The assumption throughout NRC 
was that the boric acid deposits would be in a dry, powder-like form 
that could easily be removed and would not accumulate in a condition 
that would be corrosive to the reactor vessel head. As identified in 
the event inquiry, the inspectors did communicate a substantial amount 
of information to the region and the NRR Project Manager, particularly 
regarding the fouling of the containment air coolers and radiation 
monitor filter 
elements; however, the significance of this information was also not 
appreciated at the time. This same failure to understand the 
significance of the situation was the cause of the lack of 
communication from Headquarters to the regions. Several elements of the 
matrixed DBLLTF Action Plans address this underlying issue of lack of 
recognition of the significance of the evidence. The desired outcome 
for these actions is for all NRC staff to maintain a questioning 
attitude and lower thresholds for communications concerning materials 
degradation corrosion.

Contact: Edwin M. Hackett, NRR/DLPM/PDII 415-1485:

More broadly, the NRC staff agrees that communications are of critical 
importance in all aspects of NRC activities and particularly important 
as an underlying cause for issues discovered at DBNPS. The corrective 
actions outlined in the DBLLTF Action Plans address communications 
beyond the topic of boric acid corrosion control. For example, 
corrective actions in the area of operating experience development and 
use are focused on enhancing communications. The recommendations to 
strengthen inspection guidance, institute training to reinforce a 
questioning attitude on the part of management and staff, and change 
the Inspection Manual to provide guidance for the staff to pursue 
issues identified during plant status reviews are intended to establish 
more definitive expectations for improved communications of operating 
experience. As discussed in the February 23, 2004, semiannual update 
report and at the February 26, 2004, Commission meeting, implementation 
plans for this area are still under development and may significantly 
influence the way the agency does business in the future. Developing 
the most effective and efficient communications channels will be key to 
the successful implementation of an effective operating experience 
program.

Beyond the DBLLTF Action Plan, the agency has several ongoing 
initiatives that provide examples of efforts to more broadly improve 
intra-agency communications. These examples include establishment of a 
Communication Council reporting to the Executive Director for 
Operations and the creation of a communications specialist position 
reporting to the Office of Nuclear Reactor Regulation (NRR) Associate 
Director for Inspections and Programs. NRR also continues to improve 
and enhance its Web site as a focused means of communicating with both 
internal and external stakeholders. From a regional perspective, 
examples of communication enhancements include lowering the threshold 
for communication of plant issues on morning status calls, devoting 
additional time to discussing lessons learned from plant events and 
inspection findings during counterpart meetings, and developing 
enhanced guidance for documenting significant operational event 
followup decisions. Collectively, these examples provide a strong 
indication that NRC Headquarters and regional staff have begun to 
internalize two of the most important lessons from the Davis-Besse 
event. These are that on occasion, information initially considered to 
have low significance by the first NRC recipient is later found to be 
of greater significance once the information is shared and evaluated 
more collegially; and with regard to the complex nature of commercial 
nuclear power operations, no one person can be aware of all aspects of 
an issue. As a result, the more information that is shared, the more 
likely significant problems will be identified and appropriate 
action(s) taken.

In summary, the NRC staff recognizes that communication failures were 
an underlying cause of the agency's problems concerning the delayed 
discovery of the boric acid corrosion at DBNPS. Our January 12, 2004, 
response to the event inquiry specifically addressed what we considered 
to be the root cause of the event-specific communication failures, 
namely that the entire staff 
did not recognize the potential significance of boric acid corrosion. 
Expectations for improved communications will be developed as an 
integral part of our operating experience program enhancements. More 
broadly, communication improvement initiatives with internal and 
external 
stakeholders are in progress to enhance agency performance in this 
critical area of our responsibilities. We regret that our initial 
response did not clearly address the broader actions we are taking to 
improve communications and appreciate the opportunity to clarify our 
response.

cc: Chairman Diaz 
Commissioner McGaffigan 
Commissioner Merrifield 
SECY:
LReyes:

The following are GAO's comments on the Nuclear Regulatory Commission's 
letter dated May 5, 2004.

GAO Comments: 

1. We agree with NRC that 10 C.F.R. § 50.9 requires that information 
provided to NRC by a licensee be complete and accurate in all material 
respects, and we have added this information to the report. NRC also 
states that in carrying out its oversight responsibilities, NRC must 
"rely heavily" on licensees providing accurate information. However, we 
believe that NRC's oversight program should not place undue reliance on 
applicants providing complete and accurate information. NRC also 
recognizes that it cannot rely solely on information from licensees, as 
evidenced by its inspection program and process for determining the 
significance of licensee violations. Under this process, NRC considers 
whether there are any willful aspects associated with the violation--
including the deliberate intent to violate a license requirement or 
regulation or falsify information. We believe that management controls, 
including inspection and enforcement, should be implemented by NRC so 
as to verify whether licensee-submitted information considered to be 
important for ensuring safety is complete and accurate as required by 
the regulation. In this regard, as stated in NRC's enforcement policy 
guidance, NRC is authorized to conduct inspections and investigations 
(Atomic Energy Act § 161); revoke licenses for, among other things, a 
licensee's making material false statements or failing to build or 
operate a facility in accordance with the terms of the license (Atomic 
Energy Act § 186); and impose civil penalties for a licensee's knowing 
failure to provide certain safety information to NRC (Energy 
Reorganization Act § 206).

With regard to the draft report conveying the expectation that NRC 
should have known about the thick layer of boron on the reactor vessel 
head, we note in the draft report that since at least 1998, NRC was 
aware that (1) FirstEnergy's boric acid corrosion control program was 
inadequate, (2) radiation monitors within the containment area were 
continuously being clogged by boric acid deposits, (3) the containment 
air cooling system had to be cleaned repeatedly because of boric acid 
buildup, (4) corrosion was occurring within containment as evidenced by 
rust particles being found, and (5) the unidentified leakage rate had 
increased above the level that historically had been found at the 
plant. NRC was also aware of the repeated but ineffective attempts by 
FirstEnergy to correct many of these recurring problems--evidence that 
the licensee's programs to identify and correct problems were not 
effective. Given these indications at Davis-Besse, NRC could have taken 
more aggressive follow-up action to determine the underlying causes. 
For example, NRC could have taken action during the fuel outage in 
1998, the shutdown to repair valves in mid-1999, or the fuel outage in 
2000 to ensure that staff with sufficient knowledge appropriately 
investigated the types of conditions that could cause these 
indications, or followed up to ensure that FirstEnergy had fully 
investigated and successfully resolved the cause of the indications.

2. With respect to the responsibility of the licensee to provide 
complete and accurate information, see comment 1. As to the Davis-Besse 
lessons-learned task force finding, we agree that some information 
provided by FirstEnergy in response to Bulletin 2001-01 may have been 
inconsistent with some information subsequently identified by NRC's 
lessons-learned task force, and that had some of this information been 
known in the fall of 2001, the vessel head leakage and degradation may 
have been identified sooner than March 2002. This information included 
(1) the boric acid accumulations found on the vessel head by 
FirstEnergy in 1998 and 2000, (2) FirstEnergy's limited ability to 
visually inspect the vessel head, (3) FirstEnergy's boric acid 
corrosion control procedures relative to the vessel head, (4) 
FirstEnergy's program to address the corrosive effects of small amounts 
of reactor coolant leakage, (5) previous nozzle inspection results, (6) 
the bases for FirstEnergy's conclusion that another source of leakage-
-control rod drive mechanism flanges--was the source of boric acid 
deposits on the vessel head that obscured multiple nozzles, and (7) 
photographs of vessel head penetration nozzles. However, various NRC 
officials knew some of this information, other information should have 
been known by NRC, and the remaining information could have been 
obtained had NRC requested it from FirstEnergy. For example, according 
to the senior resident inspector, he reviewed every Davis-Besse 
condition report on a daily basis to determine whether the licensee 
properly categorized the safety significance of the conditions. Vessel 
head conditions found by FirstEnergy in 1998 and 2000 were noted in 
such condition reports or in potential-condition-adverse-to-quality 
reports. According to a FirstEnergy official, photographs of the 
pressure vessel head nozzles were specifically provided to NRC's 
resident inspector, who, although he did not specifically recall seeing 
the photographs, stated that he had no reason to doubt the FirstEnergy 
official's statement. NRC had been aware, in 1999, of limitations in 
FirstEnergy's boric acid corrosion control program and, while it cited 
FirstEnergy for its failure to adequately implement the program, NRC 
officials did not follow up to determine if the program had improved. 
Lastly, while NRC questioned the information provided by FirstEnergy in 
its submissions to NRC in response to Bulletin 2001-01 (regarding 
vessel head penetration nozzle inspections), NRC staff did not 
independently review and assess information pertaining to the results 
of past reactor pressure vessel head inspections and vessel head 
penetration nozzle inspections. Similarly, NRC did not independently 
assess the information concerning the extent and nature of the boric 
acid accumulations found on the vessel head by the licensee during past 
inspections.

On page 2 of the report, we note that the Department of Justice has an 
ongoing investigation concerning the completeness and accuracy of 
information that FirstEnergy provided to NRC on the conditions at 
Davis-Besse. The investigation may or may not find that FirstEnergy 
provided inaccurate or incomplete information. While NRC notes that it 
might have detected something months earlier if information had been 
known in the fall of 2001, we would also note that the degradation of 
the reactor vessel head likely took years to occur.

3. We believe that the statement is correct. NRC produced an estimate 
of 5x10^-5 per year for the change in core damage frequency, as we state 
in the report. NRC specifically documented this calculation in its 
December 2002 assessment: 

"The NRC staff estimated that, giving credit only to the [FirstEnergy] 
inspection performed in 1996, the probability of a [control rod drive 
mechanism] nozzle ejection during the period of operation from December 
31, 2001, to February 16, 2002, was in the range of 2E-3 and was an 
increase in the overall [loss of coolant accident] probability for the 
plant. The increase in core damage probability and large early release 
probability were estimated as approximately 5E-6 and 5E-08, 
respectively."[Footnote 44]

The probability of a large early release--5E-6--equates to a frequency 
of 5x10^-5 per year.[Footnote 45] As we note in the report, according to 
NRC's regulatory guide 1.174, this frequency would be in the highest 
risk zone and NRC would generally not approve the requested change.

On several occasions, we met with the NRC staff that developed the risk 
estimate in an attempt to understand how it was calculated. We obtained 
from NRC staff the risk estimate information provided to senior 
management in late November 2001, as well as several explanations of 
how the staff developed its calculations. We were provided with no 
evidence that NRC estimated the frequency of core damage as being 5x10^-
6 per year until February 2004, after our consultants and we had 
challenged NRC's estimate as being in the highest risk zone under NRC's 
regulatory guide 1.174. Furthermore, several NRC staff involved in 
deciding whether to issue the order to shut down Davis-Besse, or to 
allow it to continue operating until February 16, 2002, stated that the 
risk estimate they used was relatively high.

4. We agree that existing regulations provide a spectrum of conditions 
under which a plant shutdown could occur and that could be interpreted 
as covering the vast majority of situations. However, we continue to 
believe that NRC lacks sufficient guidance for making plant shutdown 
decisions. We disagree on two grounds: First, the decision-making 
guidance used by NRC to shut down Davis-Besse was guidance for 
approving license change requests. This guidance provides general 
direction on how to make risk-informed decisions when licensees request 
license changes. It does not address important aspects of decision-
making involved in deciding whether to shut down a plant. It also does 
not provide direction on how NRC should weigh deterministic factors in 
relation to probabilistic factors in making shutdown decisions. 
Secondly, while NRC views the flexibility afforded by its existing 
array of guidance as a strength, we are concerned that, even on the 
basis of the same information or circumstances, staff can arrive at 
very different decisions. Without more specific guidance, NRC will 
continue to lack accountability and the degree of credibility needed to 
convince the industry and the public that its shutdown decisions are 
sufficiently sound and reasoned for protecting public health and 
safety.

5. We are aware that the commissioners have specifically decided not to 
conduct direct evaluations or inspections of safety culture. We agree 
that as regulators, NRC is not charged with managing licensees' 
facilities, but disagree that any direct NRC involvement with safety 
culture crosses over to a management function. Management is an 
embodiment of corporate beliefs and perceptions that affect management 
strategies, goals, and philosophies. These, in turn, impact licensee 
programs and processes and employee behaviors that have safety 
outcomes. We believe that NRC should not assess corporate beliefs and 
perceptions or management strategies, goals, or philosophies. Rather, 
we believe that NRC has a responsibility to assess licensee programs 
and processes, as well as employee behaviors. We cite several areas of 
safety culture in the report as being examples of various aspects of 
safety culture that NRC can assess which do not constitute "management 
functions." The International Atomic Energy Agency has extensive 
guidance on assessing additional aspects of licensee performance and 
indicators of safety culture.[Footnote 46] Such assessments can provide 
early indications of declining safety culture prior to when negative 
safety outcomes occur, such as at Davis-Besse.

We also agree that NRC has indirect means by which it attempts to 
assess safety culture. For example, NRC's problem identification and 
resolution inspection procedure's stated objective is to provide an 
early warning of potential performance issues and insight into whether 
licensees have established safety conscious work environments. However, 
we do not believe that the implementation of the inspection procedure 
has been demonstrated to be effective in meeting its stated objectives. 
The inspection procedure directs inspectors to screen and analyze 
trends in all reported power plant issues. In doing so, the procedure 
directs that inspectors annually review 3 to 6 issues out of 
potentially thousands of issues that can arise and that are related to 
various structures, systems, and components necessary for the safe 
operation of the plant. This requires that inspectors judgmentally 
sample 3 to 6 issues on which they will focus their inspection 
resources. While we do not necessarily question inspector judgment when 
sampling for these 3 to 6 issues, NRC inspectors stated that due to the 
large number of issues that they can sample from, they try to focus on 
those issues that they believe have the most relevance for safety. 
Thus, if an issue is not yet perceived as being important to safety, it 
is less likely to be selected for follow up. Further, even if an issue 
were selected for follow up and this indicated that the licensee did 
not properly identify and resolve underlying problems that contributed 
to the issue, according to NRC officials, it is highly unlikely that 
this one issue would rise to a high enough level of significance for it 
to be noted under NRC's Reactor Oversight Process. Additionally, the 
procedure is dependant on the inspector being aware of, and having the 
capability to, identify issues or trends in the area of safety culture. 
According to NRC officials, inspectors are not trained in what to look 
for when assessing licensee safety culture because they are, by and 
large, nuclear engineers. While they may have an intuition that 
something is wrong, they may not know how to assess it in terms of 
safety culture.

Additional specific examples NRC cites for indirectly assessing a 
selected number of safety culture aspects have the following 
limitations: 

* NRC's inspection procedure for assessing licensees' employee concerns 
program is not frequently used. According to NRC Region III officials, 
approval to conduct such an inspection must be given by the regional 
administrator and the justification for the inspection to be performed 
has to be based on a very high level of evidence that a problem exists. 
Because of this, these officials said that the inspection procedure has 
only been implemented twice in Region III.

* NRC's allegation program provides a way for individuals working at 
NRC-regulated plants and the public to provide safety and regulatory 
concerns directly to NRC. It is a reactive program by nature because it 
is dependent upon licensees' employees feeling free and able to come 
forward to NRC with information about potential licensee misconduct. 
While NRC follows up on those plants that have a much higher number of 
allegations than other plants to determine what actions licensees are 
taking to address any trends in the nature of the allegations, the 
number of allegations may not always provide an indication of a poor 
safety culture, and in fact, may be the reverse. For example, the 
number of allegations at Davis-Besse prior to the discovery of the 
cavity in the reactor head in March 2002 was relatively small. Between 
1997 and 2001, NRC received 10 allegations from individuals at the 
plant. In contrast, NRC received an average of 31 allegations per plant 
over the same 5-year period from individuals at other plants.

* NRC's lessons-learned reviews, such as the one conducted for Davis-
Besse, are generally conducted when an incident having potentially 
serious safety consequences has already occurred.

* With respect to NRC's enforcement of employee protection regulations, 
NRC, under its current enforcement policy, would normally only take 
enforcement action when violations are of very significant or 
significant regulatory concern. This regulatory concern pertains to 
NRC's primary responsibility for ensuring safety and safeguards and 
protecting the environment. Examples of such violations would include 
the failure of a system designed to prevent a serious safety incident 
not working when it is needed, a licensed operator being inebriated 
while at the control of a nuclear reactor, and the failure to obtain 
prior NRC approval for a license change that has implications for 
safety. If violations of employee protection regulations do not pose 
very significant or significant safety, safeguards, or environmental 
concerns, NRC may consider such violations minor. In such cases, NRC 
would not normally document such violations in inspection reports or 
records, and would not take enforcement action.

* NRC's Reactor Oversight Process, instituted in April 2000, focuses on 
seven specific "cornerstones" that support the safety of plant 
operations to ensure reactor safety, radiation safety, and security. 
These cornerstones are: (1) the occurrence of operations and events 
that could lead to a possible accident if safety systems did not work, 
(2) the ability of safety systems to function as intended, (3) the 
integrity of the three safety barriers, (4) the effectiveness of 
emergency preparedness, (5) the effectiveness of occupational radiation 
safety, (6) the ability to protect the public from radioactive 
releases, and (7) the ability to physically protect the plant. NRC's 
process also includes three elements that cut across these seven 
cornerstones: (1) human performance, (2) a licensee's safety-conscious 
work environment, and (3) problem identification and resolution. NRC 
assumes that problems in any of these three crosscutting areas will be 
evidenced in one or more of the seven cornerstones in advance of any 
serious compromise in the safety of a plant. However, as evidenced by 
the Davis-Besse incident, this assumption has not proved to be true.

NRC also cites lessons-learned task force recommendations to improve 
NRC's ability to detect problems in licensee's safety culture, as a 
means to achieve our recommendation to directly assess licensee safety 
culture. These lessons-learned task force recommendations include (1) 
developing inspection guidance to assess the effect that a licensee's 
fuel outage shutdown schedule has on the scope of work conducted during 
a shutdown; (2) revising inspection guidance to provide for assessing 
the safety implications of long-standing, unresolved problems; 
corrective actions being phased in over the course of several years or 
refueling outages; and deferred plant modifications; (3) revising the 
problem identification and resolution inspection approach and guidance; 
and (4) reviewing the range of NRC's inspections and assessment 
processes and other NRC programs to determine whether they are 
sufficient to identify and dispose of the types of problems experienced 
at Davis-Besse. While we commend these recommendations, we do not 
believe that revising such guidance will necessarily alert NRC 
inspectors to early declines in licensee safety culture before they 
result in negative safety outcomes. Further, because of the nature of 
NRC's process for determining the relative safety significance of 
violations under NRC's new Reactor Oversight Process, we do not believe 
that any indications of such declines will result in a cited violation.

6. We have revised the report to reflect that boron in the form of 
boric acid crystals is dissolved in the cooling water. (See p. 13.): 

7. On page 41 of the report, we recognize that NRC also relied on 
information provided by FirstEnergy regarding the condition of the 
vessel head. For example, in developing its risk estimate, NRC credited 
FirstEnergy with a vessel head inspection conducted in 1996. However, 
NRC decided that the information provided by FirstEnergy documenting 
vessel head inspections in 1998 and 2000 was of such poor quality that 
it did not credit FirstEnergy with having conducted them. As a result, 
NRC's risk estimate was higher than had these inspections been given 
credit.

8. The statement made by the NRC regional branch chief was taken 
directly from NRC's Office of the Inspector General report on NRC's 
oversight of Davis-Besse during the April 2000 refueling 
outage.[Footnote 47]

9. We agree that up until the Davis-Besse event, NRC had not concluded 
that boric acid corrosion was a high priority issue. We clarified the 
text of the report to reflect this comment. (See p. 25.): 

10. We agree that plant operators in France decided to replace their 
vessel heads in lieu of performing the extensive inspections instituted 
by the French regulatory authority. The report has been revised to add 
these details. (See p. 31.): 

11. We agree that caked-on boron, in combination with leakage, could 
accelerate corrosion rates under certain conditions. However, even 
without caked-on boron, corrosion rates could be quite high. 
Westinghouse's 1987 report on the corrosive effects of boric acid 
leakage concluded that the general corrosion rate of carbon steel can 
be unacceptably high under conditions that can prevail when primary 
coolant leaks onto surfaces and concentrates at the temperatures that 
are found on reactor surfaces. In one series of tests that it 
performed, boric acid solutions corroded carbon steel at a rate of 
about 0.4 inches per month, or about 4.8 inches a year. This was 
irrespective of any caked-on boron. In 1987, as a result of that report 
and extensive boric acid corrosion found at two other nuclear reactors 
that year--Salem unit 2 and San Onofre unit 2--NRC concluded that a 
review of existing inspection programs may be warranted to ensure that 
adequate monitoring procedures are in place to detect boric acid 
leakage and corrosion before it can result in significant degradation 
of the reactor coolant pressure boundary. However, NRC did not take any 
additional action.

12. We agree that NRC has requirements and processes that provide a 
number of circumstances in which a plant shutdown would or could be 
required. We also recognize that there were no legal objections to the 
draft enforcement order to shut down the plant, and that the basis for 
not issuing the order was NRC's belief that the plant did not pose an 
unacceptable risk to public health and safety. The statement in our 
report that NRC is referring to is discussing one of these 
circumstances--the licensee's failure to meet NRC's technical 
specification--and whether NRC believed that it had enough proof that 
the technical specification was not being met. The statement is not 
discussing the basis for NRC issuing an enforcement order. We revised 
the report to clarify this point. (See p. 34.): 

13. The basis for our statement that NRC staff concluded that the first 
safety principle was probably not met was its November 29, 2001, 
briefing to NRC's Executive Director's Office and its November 30, 
2001, briefing to the NRC commissioners' technical assistants. These 
briefings, the basis for which are included in documented briefing 
slides, took place shortly before NRC formally notified FirstEnergy on 
December 4, 2001, that it would accept its compromise shutdown date.

14. We are referring to the same document that NRC is referring to--
NRC's December 3, 2002, response to FirstEnergy (NRC's ADAMS accession 
number ML023300539). The response consists of a 2-page transmittal 
letter and an 7.3-page enclosure. The 7.3-page enclosure is 3 pages of 
background and 4.3 pages of the agency's assessment. The assessment 
includes statements that the safety principles were met but does not 
provide an explanation of how NRC considered or weighed deterministic 
and probabilistic information in concluding that each of the safety 
factors were met. For example, NRC concluded that the likelihood of a 
loss-of-coolant accident was acceptably small because of the (1) 
staff's preliminary technical assessment for control rod drive 
mechanism cracking, (2) evidence of cracking found at other plants 
similar to Davis-Besse, (3) analytical work performed by NRC's research 
staff in support of the effort, and (4) information provided by 
FirstEnergy regarding past inspections at Davis-Besse. However, the 
assessment does not explain how these four pieces of information 
successfully demonstrated if and how each of the safety principles was 
met. The assessment also states that NRC examined the five safety 
principles, the fifth of which is the ability to monitor the effects of 
a risk-informed decision. The assessment is silent on whether this 
principle is met. However, in NRC's November 29, 2001, briefing to 
NRC's Executive Director's Office and in its November 30, 2001, 
briefing to the NRC commissioners' technical assistants, NRC concluded 
that this safety principle was not met. As noted above, NRC formally 
notified FirstEnergy on December 4, 2001, that it would accept 
FirstEnergy's February 16, 2002, shutdown date.

15. See comment 3. We do not agree that the report statements 
mischaracterize the facts. Rather, we are concerned that NRC is 
misusing basic quantitative mathematics. In addition, with regard to 
NRC's concept of an annual average change in the frequency of core 
damage, NRC stated that the agency averaged the frequency of core 
damage that would exist for the 7-week period of time (representing the 
period of time between December 31, 2001, and February 16, 2002) over 
the entire 1-year period, using the assumption that the frequency of 
core damage would be zero for the remainder of the year--February 17, 
2002, to December 31, 2002. According to our consultants, this 
calculation artificially reduced NRC's risk estimate to a level that is 
acceptable under NRC's guidance. By this logic, our consultants stated, 
risks can always be reduced by spreading them over time; by assuming 
another 10 years of plant operation (or even longer) NRC could find 
that its calculated "risks" are completely negligible. They further 
stated that NRC's approach is akin to arguing that an individual, who 
drives 100 miles per hour 10 percent of the time, with his car 
otherwise garaged, should not be cited because his time-average speed 
is only 10 miles per hour.

Further, our consultants concluded that the "annual-average" core 
damage frequency approach was also clearly unnecessary, since one need 
only convert a core damage frequency to a core damage probability to 
handle part-year cases like the Davis-Besse case. Lastly, we find no 
basis for the calculation in any NRC guidance. According to our 
consultants, this new interpretation of NRC's guidance is at best 
unusual and certainly is inconsistent with NRC's guidelines regarding 
the use of an incremental core damage frequency. This interpretation 
also reinforces our consultants' impression that perhaps there was, in 
November 2001 and possibly is still today, some confusion among the NRC 
staff regarding basic quantitative metrics that should be considered in 
evaluating regulatory and safety issues. As noted in comment 3, we 
found no evidence of this calculation prior to February 2004.

16. While we agree that vessel head corrosion as extensive as later 
found at Davis-Besse was not anticipated, NRC had known that leakage of 
the primary coolant from a through-wall crack could cause boric acid 
corrosion of the vessel head, as evidenced by the Westinghouse work 
cited above. Regardless of information provided to NRC by individual 
licensees, such as FirstEnergy, NRC's model should account for known 
risks, including the potential for corrosion.

17. We agree that NRC was aware of control rod drive mechanism nozzle 
cracking at French nuclear power plants. NRC provided us additional 
information consisting of a December 15, 1994, internal memo, in which 
NRC concluded that primary coolant leakage from a through-wall crack 
could cause boric acid corrosion of the vessel head. However, because 
some analyses indicated that it would take at least 6 to 9 years before 
any corrosion would challenge the structural integrity of the head, NRC 
concluded that cracking was not a short-term safety issue. We revised 
the report to include this additional information. (See p. 40.): 

18. See comment 15.

19. We agree that while not directly relevant to the Davis-Besse 
situation, NRC uses regulatory guide 1.177 to make decisions on whether 
certain equipment can be inoperable while a nuclear reactor is 
operating, which can pose very high instantaneous risks for very short 
periods of time. However, we include the reference to this particular 
guidance in the report because it was cited by an NRC official involved 
in the Davis-Besse decision-making process as another piece of guidance 
used in judging whether the risk that Davis-Besse posed was acceptable.

20. While regulatory guide 1.174 comprises 25 pages of guidance on how 
to use risk in making decisions on whether to allow license changes, it 
does not lay out how NRC staff are to use quantitative estimates of 
risk or probabilistic factors, or how robust these estimates must be in 
order to be considered along with more deterministic factors. The 
regulatory guide, which was first issued in mid-1998, had been in 
effect for only about 1.5 years when NRC staff was tasked with making 
their decision on Davis-Besse. According to the Deputy Executive 
Director of Nuclear Reactor Programs at the time the decision was being 
made, the agency was trying to bring the staff through the risk-
informed decision-making process because Davis-Besse was a learning 
tool. He further stated that it was really the first time the agency 
had used the risk-informed decision-making process on operational 
decisions as opposed to programmatic decisions for licensing. At the 
time the decision was made, and currently, NRC has no guidance or 
criteria for use in assessing the quality of risk estimates or clear 
guidance or criteria for how risk estimates are to be weighed against 
other risk factors.

21. The December 3, 2002, safety assessment or evaluation did state 
that the estimated increase in core damage frequency was consistent 
with NRC's regulatory guidelines. However, as noted in comment 3, we 
disagree with this conclusion. In addition, while we agree that NRC has 
staff with risk assessment disciplines, we found no reference to these 
staff in NRC's safety evaluation. We also found no reference to NRC's 
statement that these staff gave more weight to deterministic factors in 
arriving at the agency's decision. While we endorse NRC's consideration 
of deterministic as well as probabilistic factors and the use of a 
risk-informed decision-making process, we continue to maintain that NRC 
needs clear guidance and criteria for the quality of risk estimates, 
standards of evidence, and how to apply deterministic as well as 
probabilistic factors in plant shutdown decisions. As the agency 
continues to incorporate a risk-informed process into much of its 
regulatory guidance and programs, such criteria will be increasingly 
important when making shutdown as well as other types of decisions 
regarding nuclear power plants.

22. The information that NRC provided us indicates that completion 
dates for 2 of the 22 high priority recommendations have 
slipped.[Footnote 48] One, the completion date for encouraging the 
American Society of Mechanical Engineers to revise vessel head 
penetration nozzle inspection requirements or, alternatively, for 
revising NRC's regulations for vessel head inspections has slipped from 
June 2004 to June 2006. Two, the completion date for assessing NRC's 
requirements that licensees have procedures for responding to plant 
leakage alarms to determine if the requirements are sufficient for 
identifying reactor coolant pressure boundary leakage has slipped from 
March 2004 to March 2005.

23. We agree with this comment and have revised the report to reflect 
this clarification. (See p. 49.): 

24. Our estimate of at least an additional 200 hours of inspection per 
reactor per year is based on: 

* NRC's new requirement that its resident inspectors review all 
licensee corrective action items on a daily basis (approximately 30 
minutes per day). Given that reactors are intended to operate 
continuously throughout the year, this results in about 3.5 hours per 
week for reviewing corrective action items, or about 182 hours per 
year. In addition, resident inspections are now required to determine, 
on a semi-annual basis, whether such corrective action items reflect 
any trends in licensee performance (16 to 24 hours per year). The total 
increase for these new requirements is about 198 to 206 hours per 
reactor per year.

* A new NRC requirement that its resident inspectors validate that 
licensees comply with additional inspection commitments made in 
response to NRC's 2002 generic bulletin regarding reactor pressure 
vessel head and vessel head penetration nozzles. This requirement 
results in an additional 15 to 50 hours per reactor per fuel outage.

25. Our draft report included a discussion that NRC management's 
failure to recognize the scope or breadth of actions and resources 
necessary to fully implement task force recommendations could adversely 
affect how effective the actions may be. We made this statement based 
on NRC's initial response to the Office of the Inspector General's 
October 2003 report on Davis-Besse.[Footnote 49] That report concluded 
that ineffective communication within NRC's Region III and between 
Region III and NRC headquarters contributed to the Davis-Besse 
incident. NRC, in its January 2004 response to the report, stated that 
among other things, it had developed training on boric acid corrosion 
and revised its inspection program to require semi-annual trend 
reviews. In February 2004, the Office of the Inspector General 
criticized NRC for limiting the agency's efforts in responding to its 
findings. Specifically, it stated that NRC did not address underlying 
and generic communication failures identified in the Office's report. 
In response to the criticism, on April 19, 2004 (while our draft report 
was with NRC for review and comment), NRC provided the Office of the 
Inspector General with additional information to demonstrate that its 
actions to improve communication within the agency were broader than 
indicated in the agency's January 2004 response. Based on NRC's April 
19, 2004, response and the Office's agreement that NRC's actions 
appropriately address its concerns about communication within the 
agency, we deleted this discussion in the report.

26. We recognize that the lessons-learned task force did not make a 
recommendation for improving the agency's decision-making process 
because the task force coordinated with the Office of the Inspector 
General regarding the scope of their respective review activities and 
because the task force was primarily charged with determining why the 
vessel head degradation was not prevented. (See p. 55.): 

27. We agree that NRC's December 3, 2002, documentation of its decision 
was prepared in response to a finding by the Davis-Besse lessons-
learned task force. We revised our report to incorporate this fact. 
(See p. 55.): 

28. We agree that NRC's lessons-learned task force conducted a 
preliminary review of reports from previous lessons-learned task forces 
and, as a result of that review, made a recommendation that the agency 
perform a more detailed effectiveness review of the actions taken in 
response to those reviews. We revised the report to reflect that NRC's 
detailed review is currently underway. (See p. 55.): 

[End of section]

Appendix V: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

Jim Wells, (202) 512-3841 Ray Smith, (202) 512-6551: 

Staff Acknowledgments: 

In addition, Heather L. Barker, David L. Brack, William F. Fenzel, 
Michael L. Krafve, William J. Lanouette, Marcia Brouns McWreath, Judy 
K. Pagano, Keith A. Rhodes, and Carol Hernstadt Shulman made key 
contributions to this report.

[End of section]

Related GAO Products: 

[End of section]

Management Weaknesses Affect Nuclear Regulatory Commission Efforts to 
Address Safety Issues Common to Nuclear Power Plants. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-84-149]
Washington, D.C.: September 19, 1984.

Probabilistic Risk Assessment: An Emerging Aid to Nuclear Power Plant 
Safety Regulation. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-85-11] 
Washington, D.C.: June 19, 1985.

The Nuclear Regulatory Commission Should Report on Progress in 
Implementing Lessons Learned from the Three Mile Island Accident. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-85-72] 
Washington, D.C.: July 19, 1985.

Nuclear Regulation: Oversight of Quality Assurance at Nuclear Power 
Plants Needs Improvement. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-86-41.
Washington, D.C.: January 23, 1986.

Nuclear Regulation: Efforts to Ensure Nuclear Power Plant Safety Can Be 
Strengthened. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-87-141] 
Washington, D.C.: August 13, 1987.

Nuclear Regulation: NRC's Restart Actions Appear Reasonable--but 
Criteria Needed. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-89-95].
Washington, D.C.: May 4, 1989.

Nuclear Regulation: NRC's Efforts to Ensure Effective Plant Maintenance 
Are Incomplete. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-91-36]. 
Washington, D.C.: December 17, 1990.

Nuclear Regulation: NRC's Relationship with the Institute of Nuclear 
Power Operations. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-91-122]. 
Washington, D.C.: May 16, 1991.

Nuclear Regulation: Weaknesses in NRC's Inspection Program at a South 
Texas Nuclear Power Plant. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-96-10]. 
Washington, D.C.: October 3, 1995.

Nuclear Regulation: Preventing Problem Plants Requires More Effective 
NRC Action. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-97-145]. 
Washington, D.C.: May 30, 1997.

Nuclear Regulatory Commission: Preventing Problem Plants Requires More 
Effective Action by NRC. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-T-RCED-98-252]. 
Washington, D.C.: July 30, 1998.

Nuclear Regulatory Commission: Strategy Needed to Develop a Risk-
Informed Safety Approach. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-T-RCED-99-71]. 
Washington, D.C.: February 4, 1999.

Nuclear Regulation: Strategy Needed to Regulate Safety Using 
Information on Risk. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-RCED-99-95] 
Washington, D.C.: March 19, 1999.

Nuclear Regulation: Regulatory and Cultural Changes Challenge NRC. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO/T-RCED-00-115]. 
Washington, D.C.: March 9, 2000.

Major Management Challenges and Performance Risks at the Nuclear 
Regulatory Commission. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-01-259]. 
Washington, D.C.: January 2001.

Nuclear Regulation: Progress Made in Emergency Preparedness at Indian 
Point 2, but Additional Improvements Needed. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-01-605]. 
Washington, D.C.: July 30, 2001.

Nuclear Regulation: Challenges Confronting NRC in a Changing Regulatory 
Environment. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-01-707T]. 
Washington, D.C.: May 8, 2001.

Nuclear Regulatory Commission: Status of Achieving Key Outcomes and 
Addressing Major Management Challenges. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-01-760]
Washington, D.C.: June 29, 2001.

Managing for Results: Efforts to Strengthen the Link between Resources 
and Results at the Nuclear Regulatory Commission. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-03-258] 
Washington, D.C.: December 10, 2002.

Nuclear Regulatory Commission: Oversight of Security at Commercial 
Nuclear Power Plants Needs to Be Strengthened. 
[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-03-752] 
Washington, D.C.: September 4, 2003.
(360292): 

FOOTNOTES

[1] NRC, Degradation of Davis-Besse Nuclear Power Station Reactor 
Pressure Vessel Head Lessons-Learned Report (Washington, D.C.; Sept. 
30, 2002).

[2] FirstEnergy, Davis-Besse Nuclear Power Station, Root Cause Analysis 
Report: Significant Degradation of the Reactor Pressure Vessel Head, CR 
2002-089 (Oak Harbor, Ohio; Aug. 27, 2002) and Root Cause Analysis 
Report: Failure to Identify Significant Degradation of the Reactor 
Pressure Vessel Head, CR-02-0685, 02-0846, 02-0891, 02-1053, 02-1128, 
02-1583, 02-1850, 02-2584, and 02-2585 (Oak Harbor, Ohio; Aug. 13, 
2002).

[3] NRC, Office of the Inspector General, NRC's Regulation of Davis-
Besse Regarding Damage to the Reactor Vessel Head (Washington, D.C.; 
Dec. 30, 2002) and NRC's Oversight of Davis-Besse Boric Acid Leakage 
and Corrosion during the April 2000 Refueling Outage (Washington, D.C.: 
Oct. 17, 2003).

[4] NRC, Davis-Besse Nuclear Power Station NRC Augmented Inspection 
Team--Degradation of the Reactor Pressure Vessel Head (Washington, 
D.C.; May 3, 2002). 

[5] Two commissioner positions are currently vacant.

[6] These licensed reactors include Browns Ferry Unit 1--one of three 
reactors owned by the Tennessee Valley Authority in Alabama--which was 
shut down in 1985. The Tennessee Valley Authority plans to restart the 
reactor in 2007, which will require NRC approval. 

[7] NRC's oversight program has changed significantly since the 
beginning of 1998. The third and most recent change occurred in mid-
2000, when the agency adopted its Reactor Oversight Process. Under this 
process, NRC continues to rely on inspection results to assess licensee 
performance. However, it supplements this information with other 
indicators of self-reported licensee performance, such as how 
frequently unscheduled shutdowns occur. 

[8] 10 C.F.R. § 50.9 requires that information provided by licensees be 
complete and accurate in all material respects. 

[9] While Davis-Besse had 69 nozzles, 7 were spare and 1 was used for 
head vent piping. 

[10] The Electric Power Research Institute is a nonprofit energy 
research consortium whose members include utilities. It provides 
science and technology-based solutions to members through its 
scientific research, technology development, and product 
implementation program. 

[11] Alloy 600 is an alloy of nickel, chromium, iron, and minor amounts 
of other elements. The alloy is highly resistant to general corrosion 
but can be susceptible to cracking at high temperatures.

[12] Primary water stress corrosion cracking refers to cracking under 
stress and in primary coolant water. The primary water coolant system 
is that portion of a nuclear power plant's coolant system that cools 
the reactor core in the reactor pressure vessel and deposits heat to 
the steam generator. 

[13] The Nuclear Energy Institute comprises companies that operate 
commercial power plants and supports the commercial nuclear industry; 
and universities, research laboratories, and labor unions affiliated 
with the nuclear industry. Among other things, it provides a forum to 
resolve technical and business issues and offers information to its 
members and policymakers on nuclear issues.

[14] Reactors that were categorized as having already identified 
cracking or were highly susceptible included Arkansas Nuclear reactor 
unit 1; D.C. Cook reactor unit 2; Davis-Besse; North Anna reactor units 
1 and 2; Oconee reactor units 1, 2 and 3; Robinson reactor unit 2; 
Surry reactor units 1 and 2; and Three Mile Island reactor unit 1.

[15] NRC, "Circumferential Cracking of Reactor Pressure Vessel Head 
Penetration Nozzles" (Bulletin 2001-01, Aug. 8, 2001).

[16] The licensee for D.C. Cook reactor unit 2 proposed to shut down in 
mid-January 2002 for its inspection. NRC agreed to the delay after 
crediting D.C. Cook for having been shut down for about a month during 
the fall of 2001, thus reducing the reactor's operating time.

[17] NRC forms such inspection teams to ensure that the agency 
investigates significant operational events in a timely, objective, 
systematic, and technically sound manner, and identifies and documents 
the causes of such events.

[18] NRC has an Accident Sequence Precursor Analysis Program to analyze 
significant events that occur at nuclear power plants to determine how, 
and the likelihood that, the events could have led to core damage.

[19] FirstEnergy spent about $293 million on operations, maintenance, 
and capital projects (including $47 million for the new reactor vessel 
head) and $348 million to purchase power to replace the power that 
Davis-Besse would have generated over the 2-year shutdown period. In 
contrast, during a more routine refueling outage, Davis-Besse would 
spend about $60 million--about $37 million on operations, maintenance, 
and capital projects and $23 million on replacing the power that would 
have been generated over a 42-day shutdown period. These latter 
estimates are based on the Davis-Besse refueling outage in midcalendar 
year 2000.

[20] NRC, Office of the Inspector General, NRC's Oversight of Davis-
Besse during the April 2000 Refueling Outage (Washington, D.C.: Oct. 
17, 2003).

[21] Over the last 10 years, NRC has issued an average of about two 
generic bulletins and about four generic letters a year.

[22] NRC, Office of the Inspector General, NRC's Oversight of Davis-
Besse during the April 2000 Refueling Outage (Washington, D.C.; Oct. 
17, 2003).

[23] Before adopting the Reactor Oversight Process, NRC also assessed 
licensee performance based on inspection results and other information; 
however, NRC did not assign color codes to assessment results.

[24] Westinghouse Electric Company, Corrosion Effects of Boric Acid 
Leakage on Steel under Plant Operating Conditions--A Review of 
Available Data (Pittsburgh: October 1987).

[25] NRC's Office for Analysis and Evaluation of Operating Data was 
established in response to a recommendation that we made to the agency 
in 1978 that it have a systematic process for analyzing operating 
experience and feeding this information back to licensees and the 
industry. NRC eliminated this office, and its responsibilities were 
transferred to other NRC offices in an effort to gain efficiencies.

[26] Davis-Besse's manufacturer was the Babcock and Wilcox Company, 
which is an operating unit of McDermott International.

[27] Ordinarily, NRC would not suspend a license for a failure to meet 
a requirement unless the failure was willful and adequate corrective 
action had not been taken. 

[28] The Union of Concerned Scientists is a nonprofit partnership of 
scientists and citizens that augments scientific analyses and policy 
development for identifying environmental solutions to issues such as 
energy production.

[29] Specifically, reactor vessel head inspection requirements do not 
require that insulation be removed. Because of this, reactor vessel 
head inspections performed without removing the insulation above the 
vessel head could not result in 100 percent of the nozzles being 
visually inspected.

[30] NRC, Office of the Inspector General, NRC's Regulation of Davis-
Besse Regarding Damage to the Reactor Vessel Head (Washington, D.C.; 
Dec. 30, 2002). 

[31] NRC, Preliminary Staff Technical Assessment for Pressurized Water 
Reactor Vessel Head Penetration Nozzles Associated with NRC Bulletin 
2001-01, "Circumferential Cracking of Reactor Pressure Vessel Head 
Penetration Nozzles" (Washington, D.C.; Nov. 6, 2001).

[32] Here is how to calculate the frequency estimate: 2x10^-2 equates to 
0.02, or 2/100, which equals 1/50. 

[33] Here is how to calculate the probability estimate: 2.7x10^-3 
equates to 0.0027, or 27/10,000, which equals 1/370.37.

[34] Here is how to calculate the frequency estimate: 5.4x10^-5 equates 
to 0.000054, or 54/1,000,000, which equals 1/18,518.52.

[35] Here is how to calculate the probability estimate: 5x10^-6 equates 
to 0.000005, or 5/1,000,000, which equals 1/200,000.

[36] Here is how to calculate the frequency estimate: 4x10^-5equates to 
0.00004, or 4/100,000, which equals 1/25,000.

[37] Here is how to calculate the frequency estimate: 6.6x10^-5equates 
to 0.000066, or 66/1,000,000, which equals 1/15,151.51.

[38] Here is how to calculate the probability estimate: 5x10^-7 equates 
to 0.0000005, or 5/10,000,000, which equals 1/2,000,000.

[39] The deterministic approach considers a set of safety challenges 
and how those challenges should be mitigated through engineering safety 
margins and quality assurance standards. The probabilistic approach 
extends this by allowing for the consideration of a broader set of 
safety challenges, prioritizing safety challenges based on risk 
significance, and allowing for a broader set of mitigation mechanisms.

[40] These two recommendations were for NRC to (1) review how industry 
considers economic factors in making decisions to repair equipment and 
consider these factors in developing guidance for nonvisual inspections 
of vessel head penetration nozzles, and (2) revise the criteria for 
reviewing industry topical reports that have not been formally 
submitted to NRC for review but that have generic safety implications.

[41] The International Atomic Energy Agency is an international 
organization affiliated with the United Nations that provides advice 
and assistance to its members on nuclear safety matters.

[42] The Advisory Committee on Reactor Safeguards is an independent 
committee comprising nuclear experts that advises NRC on matters of 
licensing and safety-related issues, and provides technical advice to 
aid the NRC commissioners' decision-making process. 

[43] NRC formed the Indian Point lessons-learned task force in response 
to a steam-generator-tube rupture that forced a reactor shutdown. NRC 
formed the Millstone lessons-learned task force because the plant 
operated outside its design standards while refueling. NRC formed the 
South Texas task force in response to concerns about the effectiveness 
of NRC's inspection program and the adequacy of the licensee's employee 
concerns program.

[44] The numbers 2E-3, 5E-6, and 5E-8 can also be written as 2x10^-3, 
5x10^-6, and 5x10^-8.

[45] The probability of an event occurring is the product of the 
frequency of an event and a given time period. In this case, the time 
period--7 weeks--was approximated as one-tenth of the year. Thus, 
5.4x10^-5 per year multiplied by 0.10 equates to a probability of 
5.4x10^-6. According to NRC, it revised 5.4x10^-6 to 5.0x10^-6 to account 
for uncertainties.

[46] The International Atomic Energy Agency, International Nuclear 
Safety Advisory Group, Safety Culture (Vienna, Austria: February 1991).

[47] NRC, Office of the Inspector General, NRC's Oversight of Davis-
Besse during the April 2000 Refueling Outage (Washington, D.C.: Oct. 
17, 2003).

[48] Of NRC's 21 high priority recommendations, we categorized 1 
recommendation as 2 so that we could better track actions taken to 
implement it. Thus, we have 22 recommendations categorized as high 
priority.

[49] NRC, Office of the Inspector General, NRC's Oversight of Davis-
Besse during the 2000 Refueling Outage (Washington, D.C.: Oct. 17, 
2003).

GAO's Mission: 

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

	Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: