This is the accessible text file for GAO report number GAO-04-586 
entitled 'Homeland Security: First Phase of Visitor and Immigration 
Status Program Operating, but Improvements Needed' which was released 
on May 11, 2004.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to Congressional Committees:

May 2004:

HOMELAND SECURITY:

First Phase of Visitor and Immigration Status Program Operating, but 
Improvements Needed:

[Hyperlink, http://www.gao.gov/cgi-bin/getrpt?GAO-04-586]: 

GAO Highlights:

Highlights of GAO-04-586, a report to the Subcommittees on Homeland 
Security, Senate and House Committees on Appropriations 

Why GAO Did This Study:

The Department of Homeland Security (DHS) has established a program—the 
United States Visitor and Immigrant Status Indicator Technology (US-
VISIT)—to collect, maintain, and share information, including biometric 
identifiers, on selected foreign nationals who travel to the United 
States. By congressional mandate, DHS is to develop and submit for 
approval an expenditure plan for US-VISIT that satisfies certain 
conditions, including being reviewed by GAO. Among other things, GAO 
was asked to determine whether the plan satisfied these conditions, and 
to provide observations on the plan and DHS’s program management.

What GAO Found:

DHS’s fiscal year 2004 US-VISIT expenditure plan and related 
documentation at least partially satisfies all conditions imposed by 
the Congress, including meeting the capital planning and investment 
control review requirements of the Office of Management and Budget 
(OMB). For example, DHS developed a draft risk management plan and a 
process to implement and manage risks. However, DHS does not have a 
current life cycle cost estimate or a cost/benefit analysis for US-
VISIT. The US-VISIT program merges four components into one integrated 
whole to carry out its mission (see figure).

US-VISIT Integrates People, Process, Technology, and Facilities: 

[See PDF for image]

[End of figure]

GAO also developed a number of observations about the expenditure plan 
and DHS’s management of the program. These generally recognize 
accomplishments to date and address the need for rigorous and 
disciplined program practices. For example, US-VISIT largely met its 
commitments for implementing an initial operating capability, known as 
Increment 1, in early January 2004, including the deployment of entry 
capability to 115 air and 14 sea ports of entry. However, DHS has not 
employed rigorous, disciplined management controls typically associated 
with successful programs, such as test management, and its plans for 
implementing other controls, such as independent verification and 
validation, may not prove effective. More specifically, testing of the 
initial phase of the implemented system was not well managed and was 
completed after the system became operational. In addition, multiple 
test plans were developed during testing, and only the final test plan, 
completed after testing, included all required content, such as 
describing tests to be performed. Such controls, while significant for 
the initial phases of US-VISIT, are even more critical for the later 
phases, as the size and complexity of the program will only increase. 
Finally, DHS’s plans for future US-VISIT resource needs at the land 
ports of entry, such as staff and facilities, are based on questionable 
assumptions, making future resource needs uncertain.

What GAO Recommends:

To better ensure that the US-VISIT program is worthy of investment, GAO 
is reiterating its previous recommendations aimed at establishing 
effective program management capabilities. Additionally, GAO is making 
several new recommendations designed to encourage stronger management 
of the initial phases of the US-VISIT program, including implementing 
effective test management practices and assessing the full impact of 
future US-VISIT deployment on land port of entry workforce levels and 
facilities. DHS agreed with all of GAO’s recommendations and most of 
its observations.

www.gao.gov/cgi-bin/getrpt?GAO-04-586.
 
To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Randolph C. Hite at (202) 
512-3439 or hiter@gao.gov.


[End of section]

Contents:

Letter: 

Compliance with Legislative Conditions:  

Status of Open Recommendations:  

Observations on the Expenditure Plan:  

Conclusions:  

Recommendations for Executive Action:  

Agency Comments and Our Evaluation:  

Appendixes:

Appendix I: Briefing to the Staffs of the Subcommittees on Homeland 
Security, Senate and House Committees on Appropriations: 

Appendix II: Comments from the Department of Homeland Security: 

GAO Comments:  

Appendix III: GAO Contact and Staff Acknowledgments: 

GAO Contact:  

Staff Acknowledgments:  

Abbreviations: 

ADIS: Arrival Departure Information System:

APIS: Advance Passenger Information System:

CBP: U.S. Customs and Border Protection:

CCD: Consular Consolidated Database:

CIO: Chief Information Officer:

CIS: U.S. Citizenship and Immigration Services:

CLAIMS 3: Computer Linked Application Information Management System 3:

DHS: Department of Homeland Security:

FFRDC: Federally Funded Research and Development Center:

IBIS: Interagency Border Inspection System:

ICE: U.S. Immigration and Customs Enforcement:

IDENT: Automated Biometric Identification System:

INS: Immigration and Naturalization Service:

IRB: Investment Review Board:

IV&V: independent verification and validation:

OMB: Office of Management and Budget:

POE: port of entry:

RF: radio frequency:

RFP: request for proposal:

SA-CMM: Software Acquisition Capability Maturity Model:

SAT: system acceptance test:

SEI: Software Engineering Institute:

SER: security evaluation report:

SEVIS: Student Exchange Visitor Information System:

US-VISIT: U.S. Visitor and Immigrant Status Indicator Technology:

Letter May 11, 2004:

The Honorable Thad Cochran: 
Chairman: 
The Honorable Robert C. Byrd: 
Ranking Minority Member: 
Subcommittee on Homeland Security: 
Committee on Appropriations: 
United States Senate:

The Honorable Harold Rogers: 
Chairman: 
The Honorable Martin Olav Sabo: 
Ranking Minority Member: 
Subcommittee on Homeland Security: 
Committee on Appropriations: 
House of Representatives:

Pursuant to the Department of Homeland Security Appropriations Act, 
2004,[Footnote 1] the Department of Homeland Security (DHS) submitted 
to the Congress in January 2004 its fiscal year 2004 expenditure plan 
for the United States Visitor and Immigrant Status Indicator Technology 
(US-VISIT) program. US-VISIT is a governmentwide program to collect, 
maintain, and share information on foreign nationals.[Footnote 2] The 
program's goals are to enhance national security, facilitate legitimate 
trade and travel, contribute to the integrity of the U.S. immigration 
system, and adhere to U.S. privacy laws and policies. On January 5, 
2004, DHS began operating the first stage of its planned US-VISIT 
operational capability, known as Increment 1, at 115 air and 14 sea 
ports of entry (POE).

As required by the appropriations act, we reviewed US-VISIT's fiscal 
year 2004 expenditure plan. Our objectives were to (1) determine 
whether the expenditure plan satisfies the legislative conditions 
specified in the act,[Footnote 3] (2) determine the status of our 
US-VISIT open recommendations,[Footnote 4] and (3) provide any other 
observations about the expenditure plan and DHS's management of 
US-VISIT.

On March 2, 2004, we provided your offices with a written briefing 
detailing the results of our review. This report summarizes and 
transmits this briefing; the full briefing, including our scope and 
methodology, is reprinted as appendix I. The purpose of this report is 
to provide the published briefing slides to you and to officially 
transmit our recommendations to the Secretary of Homeland Security.

Compliance with Legislative Conditions:

DHS satisfied or partially satisfied each of the applicable legislative 
conditions specified in the act. In particular, the plan, including 
related program documentation and program officials' statements, 
satisfied or provided for satisfying all key aspects of (1) compliance 
with the DHS enterprise architecture;[Footnote 5] (2) federal 
acquisition rules, requirements, guidelines, and systems acquisition 
management practices; and (3) review and approval by DHS and the Office 
of Management and Budget (OMB). Additionally, the plan, including 
program documentation and program officials' statements, satisfied or 
provided for satisfying many, but not all, key aspects of OMB's capital 
planning and investment review requirements. For example, DHS fulfilled 
the OMB requirement that it justify and describe its acquisition 
strategy. However, DHS does not have current life cycle costs or a 
current cost/benefit analysis for US-VISIT.

Status of Open Recommendations:

DHS has implemented one, and either partially implemented or has 
initiated action to implement most of the remaining recommendations 
contained in our reports on the fiscal year 2002 and fiscal year 2003 
expenditure plans. Each recommendation, along with its current status, 
is summarized below:

* Develop a system security plan and privacy impact assessment.

The department has partially implemented this recommendation. As to the 
first part of this recommendation, the program office does not have a 
system security plan for US-VISIT. However, the US-VISIT Chief 
Information Officer (CIO) accredited Increment 1 based upon security 
certifications[Footnote 6] for each of Increment 1's component systems 
and a review of each component's security-related documentation. 
Second, although the program office has conducted a privacy impact 
assessment for Increment 1, the assessment does not satisfy all aspects 
of OMB guidance for conducting an assessment. For example, the 
assessment does not discuss alternatives to the methods of information 
collection, and the system documentation does not address privacy 
issues.

* Develop and implement a plan for satisfying key acquisition 
management controls, including acquisition planning, solicitation, 
requirements management, program management, contract tracking and 
oversight, evaluation, and transition to support, and implement the 
controls in accordance with the Software Engineering Institute's (SEI) 
guidance.[Footnote 7]

The department plans to implement this recommendation. The US-VISIT 
program office has assigned responsibility for implementing the 
recommended controls. However, it has not yet developed explicit plans 
or time frames for defining and implementing them.

* Ensure that future expenditure plans are provided to the department's 
House and Senate Appropriations Subcommittees in advance of US-VISIT 
funds being obligated.

With respect to the fiscal year 2004 expenditure plan, DHS implemented 
this recommendation by providing the plan to the Senate and House 
subcommittees on January 27, 2004. According to the program director, 
as of February 2004 no funds had been obligated to US-VISIT.

* Ensure that future expenditure plans fully disclose US-VISIT 
capabilities, schedule, cost, and benefits.

The department has partially implemented this recommendation. 
Specifically, the plan describes high-level capabilities, high-level 
schedule estimates, categories of expenditures by increment, and 
general benefits. However, the plan does not describe planned 
capabilities by increment and provides only general information on how 
money will be spent in each increment. Moreover, the plan does not 
identify all expected benefits in tangible, measurable, and meaningful 
terms, nor does it associate any benefits with increments.

* Establish and charter an executive body composed of senior-level 
representatives from DHS and each US-VISIT stakeholder organization to 
guide and direct the program.

The department has implemented this recommendation by establishing a 
three-entity governance structure. The entities are (1) the Homeland 
Security Council, (2) the DHS Investment Review Board, and (3) the US-
VISIT Federal Stakeholders Advisory Board. The purpose of the Homeland 
Security Council is to ensure the coordination of all homeland 
security-related activities among executive departments and agencies, 
and the Investment Review Board is expected to monitor US-VISIT's 
achievement of cost, schedule, and performance goals. The advisory 
board is chartered to provide recommendations for overseeing program 
management and performance activities, including providing advice on 
the overarching US-VISIT vision; recommending changes to the vision and 
strategic direction; and providing a communications link for aligning 
strategic direction, priorities, and resources with stakeholder 
operations.

* Ensure that human capital and financial resources are provided to 
establish a fully functional and effective program office.

The department is in the process of implementing this recommendation. 
DHS has determined that US-VISIT will require 115 government personnel 
and has filled 41 of these, including 12 key management positions. 
However, 74 positions have yet to be filled, and all filled positions 
are staffed by detailees from other organizational units within the 
department.

* Clarify the operational context in which US-VISIT is to operate.

The department is in the process of implementing this recommendation. 
DHS released Version 1 of its enterprise architecture in October 
2003,[Footnote 8] and it plans to issue Version 2 in September 2004.

* Determine whether proposed US-VISIT increments will produce mission 
value commensurate with cost and risks.

The department plans to implement this recommendation. The fiscal year 
2004 expenditure plan identifies high-level benefits to be delivered, 
but the benefits are not associated with specific increments. 
Additionally, the plan does not identify the total cost of Increment 2. 
Program officials expected to finalize a cost-benefit analysis this 
past March and a US-VISIT life cycle cost estimate this past April.

* Define program office positions, roles, and responsibilities.

The department is in the process of implementing this recommendation. 
Program officials are currently working with the Office of Personnel 
Management to define program position descriptions, including roles and 
responsibilities. The program office has partially completed defining 
the competencies for all 12 key management areas. These competencies 
are to be used in defining the position descriptions.

* Develop and implement a human capital strategy for the program 
office.

The department plans to implement this recommendation in conjunction 
with DHS's ongoing workforce planning, but stated that they have yet to 
develop a human capital strategy. According to these officials, DHS's 
departmental workforce plan is scheduled for completion during fiscal 
year 2004.

* Develop a risk management plan and report all high risks areas and 
their status to the program's governing body on a regular basis.

The department has partially implemented this recommendation. The 
program has completed a draft risk management plan, and is currently 
defining risk management processes. The program is creating a risk 
management team to operate in lieu of formal processes until these are 
completed, and also maintains a risk-tracking database that is used to 
manage risks.

* Define performance standards for each program increment that are 
measurable and reflect the limitations imposed by relying on existing 
systems.

The department is in the process of implementing this recommendation. 
The program office has defined limited performance standards, but not 
all standards are being defined in a way that reflects the performance 
limitations of existing systems.

Observations on the Expenditure Plan:

Our observations recognize accomplishments to date and address the need 
for rigorous and disciplined program management practices relating to 
system testing, independent verification and validation, and system 
change control. An overview of specific observations follows:

* Increment 1 commitments were largely met. An initial operating 
capability for entry (including biographic and biometric data 
collection) was deployed to 115 air and 14 sea ports of entry on 
January 5, 2004, with additional capabilities deployed on February 11, 
2004. Exit capability (including biometric capture) was deployed to one 
air and one sea port of entry.

* Increment 1 testing was not managed effectively and was completed 
after the system became operational. The Increment 1 system acceptance 
test plan[Footnote 9] was developed largely during and after test 
execution. The department developed multiple plans, and only the final 
plan, which was done after testing was completed, included all required 
content, such as tests to be performed and test procedures. None of the 
test plan versions, including the final version, were concurred with by 
the system owner or approved by the IT project manager, as required. By 
not having a complete test plan before testing began, the US-VISIT 
program office unnecessarily increased the risk that the testing 
performed would not adequately address Increment 1 requirements and 
failed to have adequate assurance that the system was being fully 
tested. Further, by not fully testing Increment 1 before the system 
became operational, the program office assumed the risk of introducing 
errors into the deployed system. In fact, post-deployment problems 
surfaced with the Student and Exchange Visitor Information System 
(SEVIS) interface as a result of this approach, and manual work-arounds 
had to be implemented.

* The independent verification and validation contractor's roles may be 
in conflict.[Footnote 10] The US-VISIT program plans to use its 
contractor to review some of the processes and products that the 
contractor may be responsible for defining or executing. Depending on 
the products and processes in question, this approach potentially 
impedes the contractor's independence, and thus its effectiveness.

* A program-level change control board has not been 
established.[Footnote 11] Changes related to Increment 1 were 
controlled primarily through daily coordination meetings (i.e., oral 
discussions) among representatives from Increment 1 component systems 
teams and program officials, and the various boards already in place 
for the component systems. Without a structured and disciplined 
approach to change control, program officials do not have adequate 
assurance that changes made to the component systems for non-US-VISIT 
purposes do not interfere with US-VISIT functionality.

* The fiscal year 2004 expenditure plan does not disclose management 
reserve funding.[Footnote 12] Program officials, including the program 
director, stated that reserve funding is embedded within the 
expenditure plan's various areas of proposed spending. However, the 
plan does not specifically disclose these embedded reserve amounts. By 
not creating, earmarking, and disclosing a specific management reserve 
fund in the plan, DHS is limiting its flexibility in addressing 
unexpected problems that could arise in the program's various areas of 
proposed spending, and it is limiting the ability of the Congress to 
exercise effective oversight of this funding.

* Plans for future US-VISIT increments do not call for additional staff 
or facilities at land ports of entry. However, these plans are based on 
various assumptions that potential policy changes could invalidate. 
These changes could significantly increase the number of foreign 
nationals who would require processing through US-VISIT. Additionally, 
the Data Management Improvement Act Task Force's 2003 Second Annual 
Report to Congress[Footnote 13] has noted that existing land port of 
entry facilities do not adequately support even the current entry and 
exit processes. Thus, future US-VISIT staffing and facility needs are 
uncertain.

Conclusions:

The fiscal year 2004 US-VISIT expenditure plan (with related program 
office documentation and representations) at least partially satisfies 
the legislative conditions imposed by the Congress. Further, steps are 
planned, under way, or completed to address most of our open 
recommendations. However, overall progress on all of our 
recommendations has been slow, and considerable work remains to fully 
address them. The majority of these recommendations are aimed at 
correcting fundamental limitations in the program office's ability to 
manage US-VISIT in a way that reasonably ensures the delivery of 
mission value commensurate with costs and provides for the delivery of 
promised capabilities on time and within budget. Given this background, 
it is important for DHS to implement the recommendations quickly and 
completely through active planning and continuous monitoring and 
reporting. Until this occurs, the program will continue to be at high 
risk of not meeting expectations.

To the US-VISIT program office's credit, the first phase of the program 
has been deployed and is operating, and the commitments that DHS made 
regarding this initial operating capability were largely met. However, 
this was not accomplished in a manner that warrants repeating. In 
particular, the program office did not employ the kind of rigorous and 
disciplined management controls that are typically associated with 
successful programs, such as effective test management and 
configuration management practices. Moreover, the second phase of US-
VISIT is already under way, and these controls are still not 
established. These controls, while significant for the initial phases 
of US-VISIT, are even more critical for the later phases, because the 
size and complexity of the program will only increase, and the later 
that problems are found, the harder and more costly they are to fix.

Also important at this juncture in the program's life are the still 
open questions surrounding whether the initial phases of US-VISIT will 
return value to the nation commensurate with their costs. Such 
questions warrant answers sooner rather than later, because of the 
program's size, complexity, cost, and mission significance. It is 
imperative that DHS move swiftly to address the US-VISIT program 
management weaknesses that we previously identified, by implementing 
our remaining open recommendations. It is equally essential that the 
department quickly corrects the additional weaknesses that we have 
identified. Doing less will only increase the risk associated with US-
VISIT.

Recommendations for Executive Action:

To better ensure that the US-VISIT program is worthy of investment and 
is managed effectively, we are reiterating our prior recommendations, 
and we further recommend that the Secretary of Homeland Security direct 
the Under Secretary for Border and Transportation Security to ensure 
that the US-VISIT program director takes the following actions:

* Develop and approve complete test plans before testing begins. These 
plans, at a minimum, should (1) specify the test environment, including 
test equipment, software, material, and necessary training; 
(2) describe each test to be performed, including test controls, 
inputs, and expected outputs; (3) define the test procedures to be 
followed in conducting the tests; and (4) provide traceability between 
test cases and the requirements to be verified by the testing.

* Establish processes for ensuring the independence of the IV&V 
contractor.

* Implement effective configuration management practices, including 
establishing a US-VISIT change control board to manage and oversee 
system changes.

* Identify and disclose to the Appropriations Committees management 
reserve funding embedded in the fiscal year 2004 expenditure plan.

* Ensure that all future US-VISIT expenditure plans identify and 
disclose management reserve funding.

* Assess the full impact of a key future US-VISIT increment on land 
port of entry workforce levels and facilities, including performing 
appropriate modeling exercises.

To ensure that our recommendations addressing fundamental program 
management weaknesses are addressed quickly and completely, we further 
recommend that the Secretary direct the Under Secretary to have the 
program director develop a plan, including explicit tasks and 
milestones, for implementing all of our open recommendations, including 
those provided in this report. We further recommend that this plan 
provide for periodic reporting to the Secretary and Under Secretary on 
progress in implementing this plan. Lastly, we recommend that the 
Secretary report this progress, including reasons for delays, in all 
future US-VISIT expenditure plans.

Agency Comments and Our Evaluation:

In written comments on a draft of this report signed by the US-VISIT 
Director (reprinted in app. II, along with our responses), DHS agreed 
with our recommendations and most of our observations. It also stated 
that it appreciated the guidance that the report provided and described 
actions that it is taking or plans to take in response to our 
recommendations.

However, DHS stated that it did not fully agree with all of our 
findings, specifically offering comments on our characterization of the 
status of one open recommendation and two observations. First, it did 
not agree with our position that it had not developed a security plan 
and completed a privacy impact assessment. According to DHS, it has 
completed both. We acknowledge DHS's activity on both of these issues, 
but disagree that completion of an adequate security plan and privacy 
impact assessment has occurred. As we state in the report, the 
department's security plan for US-VISIT, titled Security and Privacy: 
Requirements & Guidelines Version 1.0, is a draft document, and it does 
not include information consistent with relevant guidance for a 
security plan, such as a risk assessment methodology and specific 
controls for meeting security requirements.[Footnote 14] Moreover, much 
of the document discusses guidelines for developing a security plan, 
rather than specific contents of a plan. Also, as we state in the 
report, the Privacy Impact Assessment was published but is not complete 
because it does not satisfy important parts of OMB guidance governing 
the content of these assessments, such as discussing alternatives to 
the designed methods of information collection and handling.

Second, DHS stated that it did not fully agree with our observation 
that the Increment 1 system test plan was developed largely during and 
after testing, citing several steps that it took as part of Increment 1 
requirements definition, test preparation, and test execution. However, 
none of the steps cited address our observations that DHS did not have 
a system acceptance test plan developed, approved, and available in 
time to use as the basis for conducting system acceptance testing and 
that only the version of the test plan modified on January 16, 2004 
(after testing was completed) contained all of the required test plan 
content. Moreover, DHS's comments acknowledge that the four versions of 
its Increment 1 test plan were developed during the course of test 
execution, and that the test schedule did not permit sufficient time 
for all stakeholders to review, and thus approve, the plans.

Third, DHS commented on the roles and responsibilities of its various 
support contractors, and stated that we cited the wrong operative 
documentation governing the role of its independent verification and 
validation contractor. While we do not question the information 
provided in DHS's comments concerning contractor roles, we would add 
that its comments omitted certain roles and responsibilities contained 
in the statement of work for one of its contractors. This omitted 
information is important because it is the basis for our observation 
that the program office planned to task the same contractor that was 
responsible for program management activities with performing 
independent verification and validation activities. Under these 
circumstances, the contractor could not be independent. In addition, we 
disagree with DHS's comment that we cited the wrong operative 
documentation, and note that the document DHS said we should have used 
relates to a different support contractor than the one tasked with both 
performing program activities and performing independent verification 
and validation activities.

The department also provided additional technical comments, which we 
have incorporated as appropriate into the report.

We are sending copies of this report to the Chairmen and Ranking 
Minority Members of other Senate and House committees and subcommittees 
that have authorization and oversight responsibilities for homeland 
security. We are also sending copies to the Secretary of State and the 
Director of OMB. Copies of this report will also be available at no 
charge on our Web site at [Hyperlink, http://www.gao.gov].

Should you or your offices have any questions on matters discussed in 
this report, please contact me at (202) 512-3439 or at [Hyperlink, 
hiter@gao.gov]. Another contact and key contributors to this report are 
listed in appendix III.

Signed by: 

Randolph C. Hite, 
Director, Information Technology Architecture and Systems Issues:

[End of section]

Appendixes: 

Appendix I: Briefing to the Staffs of the Subcommittees on Homeland 
Security, Senate and House Committees on Appropriations:

[See PDF for image] 

[End of figure] 

[End of section]

Appendix II: Comments from the Department of Homeland Security:

U.S. Department of Homeland Security 
Washington, DC 20528:

27 April 2004:

Randolph C. Hite:

Director, Information Technology Architecture And Systems Issues:

U.S. General Accounting Office 
Washington, DC 20548:

Dear Mr. Hite:

Thank you for the opportunity to review the draft report, Homeland 
Security: First Phase of Visitor and Immigration Status Program 
Operating, but Improvements Needed (GAO-04-586). The Department of 
Homeland Security largely agrees with GAO on the majority of the 
findings. However, there are some findings with which we cannot agree, 
and we have provided appropriate comments in the enclosure. You will 
also note that we have concurred with, and addressed, the new 
recommendations generated by this review.

As you know, US-VISIT represents the greatest advancement in border 
technology in three decades. The Department of Homeland Security 
established US-VISIT to achieve the following goals:

* Enhance the safety of our citizens and visitors;

* Facilitate legitimate travel and trade;

* Ensure the integrity of our immigration system; and:

* Protect the privacy of travelers to the United States.

The first increment of US-VISIT was deployed on time and within budget, 
and has exceeded the mandate established by Congress as it includes 
biometrics ahead of schedule. On January 5, 2004, US-VISIT entry 
procedures were operational at 115 airports and 14 seaports and by the 
end of this year US-VISIT will be in operation at our 50 busiest land 
ports of entry. In addition, we began pilot testing biometric exit 
procedures at one airport and one seaport and will be expanding to 
additional pilot locations later this summer.

As of April 20, 2004, more than three million foreign visitors have 
been processed through the US-VISIT entry procedures - without any 
increase in wait times. On average, US-VISIT procedures take less than 
15 seconds during the inspection process.

US-VISIT has already matched over 300 persons against criminal 
databases and prevented more than 100 known or suspected criminals from 
entering the country. Over 200 were matched while applying for a visa 
at a State Department post overseas.

Through the US-VISIT biometric process, the Departments of Homeland 
Security and State have identified many individuals who are the 
subjects of lookout records. These included rapists, drug traffickers, 
convicted criminals, and those who have committed immigration offenses 
or visa fraud.

US-VISIT is critical to our national security as well as our economic 
security, and its implementation is already making a significant 
contribution to the efforts of the Department to provide a safer and 
more secure America. We recognize that we have a long way still to go. 
We will build upon the initial framework and solid foundation to ensure 
that we continue to meet our goals of enhancing the security of our 
citizens and visitors while facilitating travel for the millions of 
visitors we welcome each year.

For all the successes of US-VISIT, the Department realizes, and your 
report supports the fact, that we need to improve the management of the 
program. We have already established a great deal of the foundation for 
meeting future challenges and will continue to improve the necessary 
disciplines for excellent program management. We realize that much 
needs to be done, and we appreciate the guidance that reports such as 
this provide.

Sincerely,

Signed by: 

James A. Williams:

Enclosure:

Enclosure: Proposed Changes, Clarifications, and Responses to 
Recommendations for Draft Report GAO-04-586:

Letter to Sen. Cochran and Rep. Rogers:

Page 3, Status of Open Recommendations:

1. Develop a system security plan and privacy impact assessment.

The US-VISIT program does have an existing security plan. In addition, 
as GAO notes in the explanation of this action item, US-VISIT did 
complete a Privacy Impact Assessment for Increment 1. As US-VISIT 
proceeds with future increments, these documents will be updated to 
reflect changes in the program.

Pages. 3 - 6, Status of Open Recommendations 2 through 12:

With respect to recommendations 2 through 12, we recognize GAO' 
acknowledges that US-VISIT has implemented, partially implemented, or 
plans to implement them. While we could offer minor clarifications to 
the status of these issues, we agree in general with the 
recommendations and therefore provide no further comment.

Page 6, Observations on the Expenditure Plan:

A management reserve fund has been identified in the amount of $33 
million in fiscal year 2004. However, this was not specifically 
detailed in the FY 2004 Expenditure Plan. While we concur with the 
concept for such a reserve, our concern lies with any potential 
restrictions and/or new approval processes that may accompany such a 
set-aside.

Page 10 - Recommendations for Executive Action:

1. Develop and approve complete test plans before testing begins. These 
plans, at a minimum, should (1) specify the test environment, including 
test equipment, software, material, and necessary training; (2) 
describe each test to be performed, including test controls, inputs, 
and expected outputs; (3) define the test procedures to be followed in 
conducting the tests; and (4) provide traceability between test cases 
and the requirements to be verified by the testing.

We concur. Complete test plans will be developed and approved before 
future testing begins. Corrective action completed.

2. Establish processes for ensuring the independence of the IV & V 
contractor.

We concur. US-VISIT is aggressively researching IV&V resources that 
will be utilized to independently evaluate any future development work 
to be performed by the US-VISIT prime integrator and future increments. 
Corrective action completed.

3. Implement effective configuration management practices, including 
establishing a US-VISIT change control board to manage and oversee 
system changes.

We concur. Effective configuration management practices for US-VISIT 
will be implemented. Corrective action in progress.

4. Identify and disclose management reserve funding embedded in the 
fiscal year 2004 expenditure plan to the Appropriations Committees.

We concur. The FY 2004 Expenditure Plan has been revised to identify a 
$33 million management reserve, separate from incremental spending 
Corrective action completed.

5. Ensure that all future US-VISIT expenditure plans identify and 
disclose management reserve funding.

We concur. All future expenditure plans will identify and disclose 
management reserve funding. Corrective action completed.

6. Assess the full impact of a key future US-VISIT increment [2B] on 
land port of entry workforce levels and facilities, including 
performing appropriate modeling exercises.

We concur. A full reassessment of the impact of Increment 2B will be 
performed with the new prime contractor, pending award of the contract 
in May 2004. Corrective action in progress.

Slides:

Slide 58:

The listing of membership for the US-VISIT Advisory Board needs 
correction. The "Associate Director of Operations, Customs and 
Immigration Services" needs to be changed to "...Citizenship and 
Immigration Services." In addition, the "Assistant Commissioner, Office 
of Field Operations, Customs and Border Protection" needs to be added.

Slide 70. Observation 2: The system test (SAT) plan was developed 
largely during and a ter testing (and Recommendations. Slide 103).

US-VISIT does not fully concur with the observation that the systems 
test plan was developed largely during and after testing. A 
comprehensive test strategy outlining the work pattern to be following 
for independent end-to-end testing was developed in a structured and 
disciplined fashion and was approved by the US-VISIT Chief Information 
Officer in May 2003. This document outlined the environment and 
interfaces to be tested, as well as assumptions and constraints. 
Coordination between the US-VISIT IV&V contractor and the component 
development teams (CPB/ICE/TSA/CIS) took place from July through 
September 2003 to ensure that Use Cases were documented from the US-
VISIT Functional Requirements Document and that technical requirements 
regarding the environment were resolved prior to the commencement 
of testing in September 2003. These Use Cases were the basis for the 
development of the Draft Test Plan that was delivered on September 19, 
2003. Furthermore, since US-VISIT Increment 1 leveraged established 
systems, test cases were available in previous test plans and were 
established in the test cases repository of Test Director (the software 
toolset/application utilized by the independent testers). Additional 
versions of the Test Plan were developed throughout the Systems 
Assurance Testing period due to corrections or inclusion of clarifying 
data provided by the component development teams. Throughout this 
iterative process the overarching Use Cases were never modified. US-
VISIT does agree with GAO's observation that the compressed timeline 
did not allow ample time for all US-VISIT stakeholders to review the 
draft Test Plan, although daily status reports were provided as a basis 
for validating that all Use Cases were fully tested, as documented in 
the Test Analysis Report.

Slide 90-91:

The US-VISIT program office was established in July 2003 and acquired 
two contractors, PEC (Program Office Support) and the MITRE Corporation 
(FFRDC), to initially help with the implementation of the program 
office (PO), acquisition of a prime contractor, and establishment of 
SA-CMM compliant processes and procedures to guide and manage the US-
VISIT program acquisition.

During the initiation phase, PEC is responsible for helping the PO with 
the establishment of plans, processes, and procedures for program 
planning and program/project management and control. Once these 
processes are established, PEC will assist in executing these 
processes, under PO direction. MITRE is responsible for assisting with 
strategic planning for the program and PO. MITRE is also responsible 
for assisting the PO in the acquisition and source selection of the 
prime contractor, and for working with PEC to ensure that the program 
planning, management, and control processes being developed are SA-CMM 
compliant and that an effective process improvement program is being 
put in place.

As the program moves to the execution phase, PEC will continue to 
provide program management planning and process execution support. 
MITRE will focus on providing oversight of the prime contractor and PO 
support contractor to ensure that:

SA-CMM compliant processes are being followed:

The plans, designs, and products being developed by the prime 
contractor address the program requirements, conform to the DHS 
enterprise architecture, and are cost-effective for the government:

The program risks are being identified and managed:

The peformance of the program (US-VISIT mission goals and program 
management controls) is being measured and validated:

Slide 90. Observation S: Independent verification and validation (IV&V) 
contractor's roles may be conflicting.

The US-VISIT program office endorses the concept of Independent 
Validation and Verification (IV&V) as a mechanism to provide an 
independent review of system processes and work products. Furthermore, 
US-VISIT recognizes the need for the IV&V to be independent of the 
processes and products that are being developed. US-VISIT utilized an 
existing IV&V vehicle for Increment 1 that was available through the 
Bureau of Immigration and Customs Enforcement (ICE) and identified by 
DHS as a center of excellence. Unit testing was performed by component 
system owners and their respective application development contractors 
under distinctly separate task orders, while end-to-end, security, and 
performance testing was completed by SAIC. The technology IV&V work 
completed under this contract vehicle was provided by SAIC under Task 
Order 02-SM/I-IRM-417, dated September 25, 2003. GAO incorrectly cited 
the July 18, 2003, statement of work for other general program and 
project management support. The scope of the September 25, 2003, task 
order specifically addressed the provision for technical governance, 
systems assurance standards and direction, as well as independent end-
to-end testing.

Slide 92, Observation 6: Program-level change control board has not 
been established (and Recommendations, Slide 103).

The US-VISIT program office endorses a structured and disciplined 
approach to change control and is actively building a process to 
establish and maintain the integrity of work products with its 
stakeholders. While the principles of software configuration management 
were followed based on the ICE Enterprise Systems Assurance Plan (i.e., 
the establishment of a Functional Baseline [FB] and Allocated Baseline 
[AB], versioned naming conventions for software, and recording all 
documentation to an Enterprise Library) a formal Change Control Board 
was not established prior to the implementation of Increment 1. It is 
the intention of the US-VISIT Program Office to institute a CM process 
that will define policy for any modifications or System Change Requests 
for any future releases of software.

The following are GAO's comments on the Department of Homeland 
Security's letter dated April 27, 2004.

GAO Comments:

1. We do not agree that the US-VISIT program has a security plan. In 
response to our request for the US-VISIT security plan, DHS provided a 
draft document entitled Security and Privacy: Requirements & Guidelines 
Version 1.0. However, as we state in the report, this document does not 
include information consistent with relevant guidance for a security 
plan.[Footnote 15] For example, this guidance states that a system 
security plan should (1) provide an overview of the system security 
requirements, (2) include a description of the controls in place or 
planned for meeting the requirements, (3) delineate roles and 
responsibilities of all individuals who have access to the system, 
(4) describe the risk assessment methodology to be used, and 
(5) address security awareness and training. The document provided by 
DHS addressed two of these requirements--security requirements and 
training and awareness. As we state in the report, the document does 
not (1) describe specific controls to satisfy the security 
requirements, (2) describe the risk assessment methodology, and 
(3) identify roles and responsibilities of individuals with system 
access. Further, much of the document discusses guidelines for 
developing a security plan, rather than providing the specific content 
expected of a plan.

2. Although DHS has completed a Privacy Impact Assessment for Increment 
1, the assessment is not consistent with the Office of Management and 
Budget guidance.[Footnote 16] This guidance says that a Privacy Impact 
Assessment should, among other things, (1) identify appropriate 
measures for mitigating identified risks, (2) discuss the rationale for 
the final design or business process choice, (3) discuss alternatives 
to the designed information collection and handling, and (4) address 
whether privacy is provided for in system development and 
documentation. While the Privacy Impact Assessment for US-VISIT 
Increment 1 discusses mitigation strategies for identified risks and 
briefly discusses the rationale for design choices, it does not discuss 
alternatives to the designed information collection and handling. 
Further, Increment 1 system documentation does not address privacy.

3. DHS's comments did not include a copy of its revised fiscal year 
2004 expenditure plan because, according to an agency official, OMB has 
not yet approved the revised plan for release, and thus we cannot 
substantiate its comments concerning either the amount or the 
disclosure of management reserve funding. Further, we are not aware of 
any unduly burdensome restrictions and/or approval processes for using 
such a reserve. We have modified our report to reflect DHS's statement 
that it supports establishing a management reserve and the status of 
revisions to its expenditure plan.

4. We have modified the report as appropriate to reflect these comments 
and subsequent oral comments concerning the membership of the US-VISIT 
Advisory Board.

5. We do not believe that DHS's comments provide any evidence to 
counter our observation that the system acceptance test plan was 
developed largely during and after testing. In general, these comments 
concern the Increment 1 test strategy, test contractor and component 
system development team coordination, Increment 1 use cases, and pre-
existing component system test cases, none of which are related to our 
point about the completeness of the four versions of the test plan. 
More specifically, our observation does not address whether or not an 
Increment 1 test strategy was developed and approved, although we would 
note that the version of the strategy that the program office provided 
to us was incomplete, was undated, and did not indicate any level of 
approval. Further, our observation does not address whether some 
unspecified level of coordination occurred between the test contractor 
and the component system development teams; it does not concern the 
development, modification, and use of Increment 1 "overarching" use 
cases, although we acknowledge that such use cases are important in 
developing test cases; and it does not address the pre-existence of 
component system test cases and their residence in a test case 
repository, although we note that when we previously asked for 
additional information on this repository, none was provided.

Rather, our observation concerns whether a sufficiently defined US-
VISIT Increment 1 system acceptance test plan was developed, approved, 
and available in time to be used as the basis for conducting system 
acceptance testing. As we state in the report, to be sufficient such a 
plan should, among other things, define the full complement of test 
cases, including inputs and outputs, and the procedures for executing 
these test cases. Moreover, these test cases should be traceable to 
system requirements. However, as we state in our report, this content 
was added to the Increment 1 test plan during the course of testing, 
and only the version of the test plan modified January 16, 2004, 
contained all of this content. Moreover, DHS's comments recognize that 
these test plan versions were developed during the course of test 
execution and that the test schedule did not permit sufficient time for 
all stakeholders to review the versions.

6. We do not disagree with DHS's comments describing the roles and 
responsibilities of its program office support contractor and its 
Federally Funded Research and Development Center (FFRDC) contractor. 
However, DHS's description of the FFRDC contractor's roles and 
responsibilities do not cover all of the taskings envisioned for this 
contractor. Specifically, DHS's comments state that the FFRDC 
contractor is to execute such program and project management activities 
as strategic planning, contractor source selection, acquisition 
management, risk management, and performance management. These roles 
and responsibilities are consistent with the FFRDC contractor's 
statement of work that was provided by DHS. However, DHS's comments 
omit other roles and responsibilities specified in this statement of 
work. In particular, the comments do not cite that this contractor is 
also to conduct audits and evaluations in the form of independent 
verification and validation activities. It is this audit and evaluation 
role, particularly the independence element, which is the basis for our 
concern and observation. As we note above and state in the report, US-
VISIT program plans and the contractor's statement of work provide for 
using the same contractor both to perform program and project 
management activities, including creation of related products, and to 
assess those activities and products. Under these circumstances, the 
contractor could not be sufficiently independent to effectively 
discharge the audit and evaluation tasks.

7. We do not agree with DHS's comment that we cited the wrong operative 
documentation pertaining to US-VISIT independent verification and 
validation plans. As discussed in our comment No. 6, the statement of 
work that we cite in the report relates to DHS plans to use the FFRDC 
contractor to both perform program and project management activities 
and develop related products and to audit and evaluate those activities 
and products. The testing contractor and testing activities discussed 
in DHS comments are separate and distinct from our observation about 
DHS plans for using the FFRDC contractor. Accordingly, our report does 
not make any observation regarding the independence of the testing 
contractor.

8. We agree that US-VISIT lacks a change control board and support 
DHS's stated commitment to establish a structured and disciplined 
change control process that would include such a board.

[End of section]

Appendix III: GAO Contact and Staff Acknowledgments:

GAO Contact:

Deborah Davis, (202) 512-6261:

Staff Acknowledgments:

In addition to the individual named above, Barbara Collier, Gary 
Delaney, Neil Doherty, Tamra Goldstein, David Hinchman, Thomas 
Keightley, John Mortin, Debra Picozzi, Karl Seifert, and Jessica 
Waselkow made key contributions to this report.

(310277):

FOOTNOTES

[1] Pub. L. 108-90 (Oct. 1, 2003).

[2] The US-VISIT program has a large number of government stakeholders, 
including the Departments of State, Transportation, Commerce, Justice, 
and the General Services Administration. State will play a significant 
role in creating a coordinated and interlocking network of border 
security by gathering biographic and biometric data during the 
application process for visas, grants of visa status, and the issuance 
of travel documentation. DHS inspectors will use this information at 
ports of entry to verify the identity of the foreign national.

[3] The legislative conditions are that the plan (1) meet the capital 
planning and investment control review requirements established by the 
Office of Management and Budget (OMB), including those in OMB Circular 
A-11, part 3 (capital investment and control requirements are now found 
in part 7, rather than part 3); (2) comply with DHS's enterprise 
architecture; (3) comply with the acquisition rules, requirements, 
guidelines, and systems acquisition management practices of the federal 
government; (4) be reviewed and approved by DHS and OMB; and (5) be 
reviewed by GAO.

[4] Our previous recommendations regarding US-VISIT's expenditure plans 
were published in U.S. General Accounting Office, Information 
Technology: Homeland Security Needs to Improve Entry Exit System 
Expenditure Planning, GAO-03-563 (Washington, D.C.: June 9, 2003) and 
Homeland Security: Risks Facing Key Border and Transportation Security 
Program Need to Be Addressed, GAO-03-1083 (Washington, D.C.: Sept. 19, 
2003).

[5] Enterprise architectures are blueprints, or models, simplifying the 
complexity of how agencies operate today, how they want to operate in 
the future, and how they will get there.

[6] Accreditation is the authorization and approval granted to a system 
to process sensitive data in an operational environment; this is made 
on the basis of a compliance certification by designated technical 
personnel of the extent to which design and implementation of the 
system meet defined technical requirements for achieving data security. 
Certification is the evaluation of the extent to which a system meets a 
set of security requirements. 

[7] Carnegie Mellon University Software Engineering Institute, Software 
Acquisition Capability Maturity Model", Version 1.03 (March 2002) 
defines acquisition process management controls for planning, managing, 
and controlling software-intensive system acquisitions.

[8] Department of Homeland Security Enterprise Architecture Compendium 
Version 1.0 and Transitional Strategy.

[9] The purpose of system acceptance testing is to verify that the 
complete system satisfies functional, performance, and security 
requirements and is acceptable to end users.

[10] The purpose of independent verification and validation (IV&V) is 
to provide an independent review of system processes and products. To 
be effective, the IV&V function must be performed by an entity that is 
independent of the processes and products that are being reviewed.

[11] The purpose of configuration management is to establish and 
maintain the integrity of work products (e.g., hardware, software, and 
documentation). A key ingredient to effectively controlling 
configuration change is the functioning of a change control board.

[12] The creation and use of a management reserve fund to earmark 
resources for addressing the many uncertainties that are inherent in 
large-scale systems acquisition programs is an established practice and 
a prudent management approach. 

[13] Data Management Improvement Act Task Force, Second Annual Report 
to Congress (Washington, D.C., December 2003).

[14] Office of Management and Budget Circular Number A-130, Revised 
(Transmittal Memorandum No. 4), Appendix III, "Security of Federal 
Automated Information Resources" (Nov. 28, 2000) and National Institute 
of Standards and Technology, Guide for Developing Security Plans for 
Information Systems, NIST Special Publication 800-18 (December 1998).

[15] Office of Management and Budget Circular Number A-130, Revised 
(Transmittal Memorandum No. 4), Appendix III, "Security of Federal 
Automated Information Resources" (Nov. 28, 2000) and National Institute 
of Standards and Technology, Guide for Developing Security Plans for 
Information Systems, NIST Special Publication 800-18 (December 1998).

[16] OMB Guidance for Implementing the Privacy Provisions of the E-
Government Act of 2002, OMB M-03-22 (Sept. 26, 2003).

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 	

	Voice: (202) 512-6000:

	TDD: (202) 512-2537:

	Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470:

Public Affairs:

Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.

General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.

20548: