This is the accessible text file for GAO report number GAO-04-393 
entitled 'Defense Acquisitions: Stronger Management Practices Are 
Needed to Improve DOD's Software-Intensive Weapon Acquisitions' which 
was released on March 01, 2004.

This text file was formatted by the U.S. General Accounting Office 
(GAO) to be accessible to users with visual impairments, as part of a 
longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov.

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately.

Report to the Committee on Armed Services, U.S. Senate:

United States General Accounting Office:

GAO:

March 2004:

Defense Acquisitions:

Stronger Management Practices Are Needed to Improve DOD's Software-
Intensive Weapon Acquisitions:

GAO-04-393:

GAO Highlights:

Highlights of GAO-04-393, a report to the Committee on Armed Services, 
U.S. Senate 

Why GAO Did This Study:

The Department of Defense (DOD) has been relying increasingly on 
computer software to introduce or enhance performance capabilities of 
major weapon systems. To ensure successful outcomes, software 
acquisition requires disciplined processes and practices. Without such 
discipline, weapon programs encounter difficulty in meeting cost and 
schedule targets. For example, in fiscal year 2003, DOD might have 
spent as much as $8 billion to rework software because of quality-
related issues. 

GAO was asked to identify the practices used by leading companies to 
acquire software and to analyze the causes of poor outcomes of 
selected DOD programs. GAO also was asked to evaluate DOD’s efforts to 
develop programs for improving software acquisition processes and to 
assess how those efforts compare with leading companies’ practices.

What GAO Found:

Software developers and acquirers at firms that GAO visited use three 
fundamental management strategies to ensure the delivery of high-
quality products on time and within budget: working in an evolutionary 
environment, following disciplined development processes, and 
collecting and analyzing meaningful metrics to measure progress. When 
these strategies are used together, leading firms are better equipped 
to improve their software development processes on a continuous basis. 
An evolutionary approach sets up a more manageable environment—one in 
which expectations are realistic and developers are permitted to make 
incremental improvements. The customer benefits because the initial 
product is available sooner and at a lower, more predictable cost. 
This avoids the pressure to incorporate all the desired capabilities 
into a single product right away. Within an evolutionary environment, 
there are four phases that are common to software development: setting 
requirements, establishing a stable design, writing code, and testing. 
At the end of each of these phases, developers must demonstrate that 
they have acquired the right knowledge before proceeding to the next 
development phase. To provide evidence that the right knowledge was 
captured, leading developers emphasize the use of meaningful metrics, 
which helps developers, managers, and acquirers to measure progress. 
These metrics focus on cost, schedule, the size of a project, 
performance requirements, testing, defects, and quality.

In a review of five DOD programs, GAO found that outcomes were mixed 
for software-intensive acquisitions. The F/A-18 C/D, a fighter and 
attack aircraft, and the Tactical Tomahawk missile had fewer 
additional cost and schedule delays. For these programs, developers 
used an evolutionary approach, disciplined processes, and meaningful 
metrics. In contrast, the following programs, which did not follow 
these management strategies, experienced schedule delays and cost 
growth: F/A-22, an air dominance aircraft; Space-Based Infrared 
System, a missile-detection satellite system; and Comanche, a 
multimission helicopter.

In response to congressional requirements, DOD, the military services, 
and the Missile Defense Agency have taken positive steps to improve 
the environment for acquiring software-intensive systems. However, 
their plans to implement software process improvement programs are not 
yet complete and more work is required to ensure controls that would 
help managers increase the chances of successful acquisition outcomes. 
Such controls include documenting baseline requirements agreements 
between the developer and acquirer that leverage systems engineering 
knowledge, meeting with the developer for periodic reviews (gates) 
during the development process, and obtaining meaningful metrics from 
the developer to manage the program. Furthermore, there are no 
assurances that program managers will be held accountable for using 
the plans once they are completed.

What GAO Recommends:

GAO recommends that the Secretary of Defense direct the military 
services and agencies to adopt specific controls to improve software 
acquisition outcomes. These practices should be incorporated into DOD 
policy, software process improvement plans, and development contracts. 
DOD concurred with two revised recommendations and partially concurred 
with two others.

www.gao.gov/cgi-bin/getrpt?GAO-04-393.

To view the full product, including the scope and methodology, click 
on the link above. For more information, contact Katherine V. Schinasi 
at (202) 512-4841 or schinasik@gao.gov.

[End of section]

Contents:

Letter:

Results in Brief:

Background:

Successful Outcomes Are Largely the Result of Creating the 
Right Environment, Disciplined Processes, and Useful Metrics:

Outcomes on DOD's Software-Intensive Acquisitions Were Influenced by 
Environment, Processes, and Metrics:

DOD, the Services, and MDA Have Begun to Improve the Acquisition 
Environment, but Controls Needed to Assist Acquisition Managers:

Conclusions:

Recommendations for Executive Action:

Agency Comments and Our Evaluation:

Scope and Methodology:

Appendix I: Comments from the Department of Defense:

Appendix II: Software Models:

Appendix III: Section 804. Improvement of Software Acquisition 
Processes:

Related GAO Products:

Tables:

Table 1: Metrics Used by Leading Software Developers:

Table 2: Program Outcomes Linked to Management Controls:

Table 3: Highlights of SW-CMM:

Table 4: Highlights of SA-CMM:

Table 5: Highlights of CMMI Model:

Figures:

Figure 1: Key Management Practices That Increase Chances of Successful 
Outcomes:

Figure 2: Highlights of the Knowledge-Based Software Development 
Process:

Abbreviations:

CMM®: Capability Maturity Models:

CMMI®: Capability Maturity Model Integration:

CSC: Computer Sciences Corporation:

DOD: Department of Defense:

GSG: Global Software Group:

MDA: Missile Defense Agency:

NCRNational Cash Register Corporation:

SA-CMM®: Software Acquisition Capability Maturity Model:

SBIRS; Space-Based Infrared System:

SW-CMM®: Capability Maturity Model for Software:

United States General Accounting Office:

Washington, DC 20548:

March 1, 2004:

The Honorable John W. Warner: 
Chairman: 
The Honorable Carl Levin: 
Ranking Minority Member: 
Committee on Armed Services: 
United States Senate:

Computer software has increasingly become a critical component for 
Department of Defense (DOD) weapon systems. The development of complex 
software represents a potential leap forward in operational capability 
for any number of DOD defense acquisitions--from stabilizing a weapon 
to providing all of the key functions needed in an avionics system. 
Technological advancements have even made it possible for software to 
perform functions once handled by hardware. As the demand for complex 
software grows, the need for discipline while developing and delivering 
software also increases. In recent years, DOD has attributed 
significant cost and schedule overruns of software-intensive systems to 
difficulties in developing and delivering software. DOD estimates that 
it spends about 40 percent of its Research, Development, Test, and 
Evaluation budget on software--$21 billion for fiscal year 2003. 
Furthermore, DOD and industry experience indicates that about 
$8 billion (40 percent) of that amount may be spent on reworking 
software because of quality-related issues. We previously reported that 
DOD did not have effective and consistent corporate or software 
processes for software acquisitions, has had difficulty in implementing 
disciplined processes developed by industry experts, and some 
components had no software acquisition programs focused on improving 
processes and practices. We recommended that DOD correct these 
deficiencies by developing software process improvement 
programs.[Footnote 1]

In December 2002 Congress required the Secretaries of each military 
service and the head of those defense agencies that manage major 
defense software-intensive acquisition programs to develop process 
improvement programs for software acquisitions. Subsequently, the 
Senate Committee on Armed Services requested that we (1) identify the 
best practices and knowledge-based metrics used by leading companies to 
develop software, (2) analyze the causes of poor outcomes of selected 
DOD software-intensive acquisition programs, and (3) evaluate DOD's 
efforts to develop software process improvement programs and assess how 
those efforts compare with leading companies' practices to improve 
software acquisition processes.

Results in Brief:

The leading companies we visited focus attention on the software 
development environment, have disciplined development processes, and 
use metrics methodically to ensure that software is developed within 
cost, schedule and performance targets. Software acquirers, or 
organizations that purchase software, and developers work in an 
evolutionary environment where they are permitted to make incremental 
improvements to performance--rather than feeling pressured to set 
unrealistic expectations--and to strive to improve their software 
development processes on a continuous basis. This environment limits 
development to what is possible to manage. Software developers also are 
required to follow disciplined development processes. Each development 
phase--setting requirements, establishing a stable design, writing 
code, and testing--ends in a management review, or gate, to ensure that 
the project is on track. Additionally, software engineering requires 
peer reviews so knowledgeable staff can check each other's work and 
work together to remove defects at the earliest stage of development. 
To pass the management reviews, developers must demonstrate they have 
met the acquirer's expectations and quality standards before advancing 
to the next development phase. Having this knowledge in hand not only 
significantly increases the chances of successful outcomes but also 
helps leading companies identify opportunities to improve their 
software development processes over time. To track progress, confirm 
knowledge, manage risk, improve processes, and ensure that acquirers 
are well-informed, the leading developers we visited collect metrics 
from their development processes. These metrics include cost, schedule, 
size, requirements, tests, defects, and quality. By using these 
metrics, leading developers are able to maintain consistent development 
practices and quantify process outcomes.

In our review of five DOD weapon programs, we found that software 
outcomes were mixed. Software for the F/A-18 C/D, a fighter and attack 
aircraft, and the Tactical Tomahawk missile were very successful in 
meeting initial cost and schedule estimates. These programs emulated 
leading software development companies' practices. They were 
evolutionary, that is, they upgraded and fielded systems in incremental 
blocks of time, had achievable requirements that were managed 
carefully, required developers to gain the knowledge they needed to 
pass a management review at each gate in the development process, and 
collected meaningful metrics for management oversight. On the other 
hand, the following complex development programs experienced cost 
increases and schedule delays because of significant difficulties with 
software development: F/A-22, an air superiority and ground attack 
aircraft; Space-Based Infrared System (SBIRS), a missile-detection 
satellite system; and Comanche, a multi-mission helicopter. While each 
of these programs has been restructured with more oversight and has 
instituted more realistic controls over software requirements, each 
experienced significant requirements growth and cited that growth as a 
leading cause of development problems. Before restructuring the 
programs, neither the DOD program managers nor the software developers 
for these programs had a process with reliable reviews and deliverables 
to reduce development risk. None of the software developers for these 
programs were able to demonstrate sufficient use of metrics to track 
progress or whether the metrics they used were implemented consistently 
over time and used as a basis for comparison to provide oversight.

DOD's military services and the Missile Defense Agency (MDA) are at 
various stages of responding to the congressional direction[Footnote 2] 
to improve software processes. The efforts so far provide a good 
starting point for changing the environment under which the services 
are managing software acquisition, but they are not complete. DOD's 
software acquisition practices could be strengthened by incorporating 
practices we found at leading companies, such as documenting agreements 
between the developer and acquirer that contain baseline requirements 
for the software developer based on systems engineering knowledge, 
meeting with the developer for gated reviews during the development 
process, and obtaining meaningful metrics from the developer to manage 
the program. Two other tasks assigned by Congress to DOD in the 2003 
Authorization Act--setting criteria for how contractors are selected 
and establishing a best practices clearinghouse--are not yet complete.

We are making four recommendations to the Secretary of Defense to 
strengthen DOD's practices for managing software requirements, to 
ensure use of disciplined processes and metrics, and to include 
provisions in DOD's acquisition policy, plans, and contracts for 
improving outcomes of software acquisition. In written comments on a 
draft of this report, DOD concurred with two recommendations that we 
modified to incorporate wording that DOD suggested. The department 
partially concurred with two other recommendations. DOD agreed that the 
report provides useful insight for improving the software acquisition 
process and is consistent with the department's efforts to improve the 
process as it continues to implement section 804 of the Fiscal Year 
2003 National Defense Authorization Act. DOD also agreed to take the 
report's findings into account as it monitors the process for 
continuous improvement and to apply our recommendations as further 
guidance to its component services and agencies.

Background:

DOD's major weapon systems rely more heavily on software to achieve 
their performance characteristics than ever before. According to 
information in a 2000 Defense Science Board Report, in the last 
40 years, functionality provided by software for aircraft, for example, 
has increased from about 10 percent in the early 1960s for the F-4 to 
80 percent for the F/A-22, which is currently under 
development.[Footnote 3] The reasons for this are simple: performance 
requirements for weapon systems have become increasingly demanding, and 
breakthroughs in software capability have led to a greater reliance on 
software to provide more capability when hardware limitations are 
reached. Along with this, DOD's practice of expecting leaps in 
capability has placed extreme reliance on software development in most 
acquisitions. As DOD moves to more complex acquisitions--such as the 
integration of multiple systems in a single "system of systems"--
understanding and addressing software development issues have become 
even more critical for DOD in order to control cost and deliver systems 
on time.

We have issued a series of reports on the knowledge that leading 
commercial firms gain and use to manage and control the acquisition and 
development costs of their products. Leading firms attain knowledge 
early in the development process about the technology they plan to 
incorporate and ensure that resources match requirements. They make 
sure the design is mature before approving production and have 
production processes under control before production begins. Implicit 
in this approach to product development is the successful development 
of software. Software is rapidly becoming a significant, if not the 
most significant, part of DOD's acquisitions. For example, software 
enables a missile to recognize a target; on some weapon systems, 
functionality as basic as flight is no longer possible without 
sophisticated software.

In addition to successful commercial practices and other significant 
resources that have proven effective for managing software acquisition 
and development, DOD has at its disposal numerous reports and 
recommendations by industry experts to transform DOD's software 
development process. This community of experts includes independent 
engineering teams, senior advisors on DOD's Defense Science Board, and 
Carnegie Mellon University's Software Engineering Institute. Although 
they have offered detailed guidance, DOD's software-intensive weapon 
system acquisitions remain plagued by cost overruns, schedule delays, 
and failure to meet performance goals.

The Software Development Process:

DOD is an acquisition organization--that is, it acquires major weapon 
systems and manages the overall acquisition process as well as the 
contractors who are tasked with developing the systems and associated 
software. The more managers know about software development processes 
and metrics, the better equipped they are to acquire software. On DOD's 
weapon system programs, the software development process is a part of 
the larger weapon system acquisition process. Software development has 
similar phases and--in the case of new systems--occurs in parallel with 
hardware development until software and hardware components are 
integrated. The following describes the four phases common to all 
software development:

Determining requirements: Software development begins with performance 
requirements for the component or for the fully integrated product. 
Ideally, a team of system and software engineers, users, acquirers or 
their representatives analyzes the overall requirements--operational 
characteristics, user interfaces, speed, maneuverability, 
survivability, and usability--and translates them into specific 
requirements, allocating some to software and others to hardware. In 
more mature organizations, before making a commitment to develop a 
component or product, the software developer validates that the 
requirements allocated to software are realistic, valid, testable, and 
supportable. Management approves the requirements before the design 
phase begins.

Systems engineering, a comprehensive technical management tool, 
provides the knowledge necessary to translate the acquirer's 
requirements into specific capabilities. With systems engineering 
knowledge in hand, the acquirer and the developer can work together to 
close gaps between expectations and available resources--well before a 
program is started. Some gaps can be resolved by the developer's 
investments, while others can be closed by finding technical or design 
alternatives. Remaining gaps--capabilities the developer does not have 
or cannot get without increasing the price and timing of the product 
beyond what the acquirer will accept--must be resolved through trade-
offs and negotiation. The basic steps in systems engineering include 
the following:

* defining what the acquirer wants, how the final product is to be 
used, what the operating environment will be, and what the performance 
characteristics are;

* turning the requirements into a set of specific functions that the 
system must perform; and:

* identifying the technical and design solutions needed to meet the 
required functions.

Completion of these steps leads to a product design.

Establishing a stable design: The software development team develops a 
design that meets the software's desired functions. Numerous activities 
and documents typically are necessary to demonstrate that all of the 
software requirements are incorporated into a preliminary design and 
that functionality can be fully tested. The developer may construct a 
prototype for the acquirer to test the understanding of the 
requirements during the design phase. If management approves the 
preliminary design, the developer refines the design and managers 
conduct a critical design review before giving approval for the coding 
phase to begin.

Manufacturing code: Software code translates requirements and a 
detailed design into an executable series of instructions. In more 
mature software development organizations, developers are required to 
follow strict coding practices. These include ensuring that the code:

* is reviewed by knowledgeable peers:

* addresses requirements specified in the final design and:

* follows strict configuration control procedures to ensure that no 
"secret code" is put in the system and generally follows coding 
documentation guidelines that enable software engineers other than the 
coder to understand and maintain the software.

Testing to validate that software meets requirements: To ensure that 
the design is ready for coding, testing activities start during the 
design phase and then continue through the coding phase. The testing of 
code is an important and critical phase and results in a series of 
quality-assurance tasks that seek to discover and remove defects that 
would hinder the software's performance. Completing these tasks 
requires the testers to coordinate with various stakeholders, such as 
the quality assurance group, to define test criteria that sufficiently 
test the approved software requirements.

Resources for Quality Software Development:

Significant resources are available to DOD for improving its software 
acquisition outcomes. Among these is Carnegie Mellon University's 
Software Engineering Institute, a federally funded research and 
development center. The Software Engineering Institute has identified 
specific processes and practices that have proven successful in 
fostering quality software development. The institute has constructed 
models for developing and acquiring software, developing and 
implementing software process improvement programs, and integrating 
hardware and software into a weapon system. To help organizations meet 
cost, schedule, and performance goals, the institute has issued 
guidance for adopting its models. The commercial firms we visited and 
DOD, both of which use the institute's models, consider them to be an 
industry standard. The institute created the models to provide general 
guidance for software development and acquisition activities that 
programs can tailor to meet their needs. These models can also be used 
to assess an organization's capability for developing or acquiring 
software.

The Software Capability Maturity Model[Footnote 4]®, for example, 
focuses on improving software development processes. The model rates 
software maturity according to five levels of maturity:

* Initial: The software process is characterized as ad hoc. Success 
depends on individual effort.

* Repeatable: The basic process is in place to track cost, schedule, 
and functionality. Some aspects of the process can be applied to 
projects with similar applications.

* Defined: There is a standardized software process for the 
organization. All projects use some approved version of this process to 
develop and maintain software.

* Managed: The organization uses and collects detailed data to manage 
and evaluate progress and quality.

* Optimizing: Quantitative feedback about performance and innovative 
ideas and technologies contribute to continuous process improvement.

In addition, the institute has created a model specifically for 
software acquisition. This model follows the same five principles as 
the previous model but emphasizes acquisition issues and the needs of 
individuals and groups who are planning and managing software 
acquisition activities. A third model focuses on the integration of 
hardware and software and has a heavier emphasis in systems 
engineering. (See appendix II for a description of the three models.):

Problems with DOD's Software Development Are Well Known:

Despite acknowledgment of significant problems and access to extensive 
resources, DOD's problems with software acquisition have continued. In 
2000 the Defense Science Board's Task Force on Defense Software 
reviewed selected DOD software-intensive systems and found that the 
programs lacked a well thought out, disciplined program management plan 
and software development process. The programs lacked meaningful cost, 
schedule, and requirements baselines, making it difficult to track 
progress. These findings are echoed by the work of DOD's Tri-Service 
Assessment Initiative, an independent group that evaluates Army, Air 
Force, and Department of Navy programs' software management processes 
and offers guidance for developing software in a disciplined manner. 
The Tri-Service Initiative found that three of the leading causes of 
problems in software-intensive systems are process capability, 
requirements management, and organizational management. A 1999 study 
performed by the Standish Group, an organization that researches risk, 
cost, and investment return for information technology investments, 
found that about one-third of software development programs--commercial 
or military--resulted in cancellation. Furthermore, in a series of 
studies completed through the 1990s, the group, found that the average 
cost overrun was 189 percent; the average schedule overrun was 
222 percent of the original estimate; and, on average, only 61 percent 
of the projects were delivered with originally specified features or 
functions.

To address its problems with weapon acquisition, including software-
intensive weapon systems, DOD recently revised its requirements 
generation and acquisition policies to incorporate a more evolutionary 
framework and improve its ability to deliver more capability to the 
acquirer faster.

Successful Outcomes Are Largely the Result of Creating the 
Right Environment, Disciplined Processes, and Useful Metrics:

Leading software companies we visited have been successful at software 
development largely because they establish a manageable product 
development environment, disciplined processes, and strong metrics to 
manage program outcomes. Key characteristics of a successful 
environment include evolutionary product development and continuous 
improvement of development capabilities so outcomes are more 
predictable. Within this environment, these companies use a structured 
management review process, and at the end of each of four key 
development phases--requirements, design, coding, and testing--the 
companies conduct reviews so that the development team does not 
progress to the next phase unless it attains a certain level of 
knowledge. A great deal of management attention is placed on the 
requirements-setting phase because missing, vague, or changing 
requirements tend to be a major cause of poor software development 
outcomes. Finally, leading developers we visited track cost and 
schedule outcomes with the help of a critical management tool, called 
earned value, a key indicator, or metric, for identifying and 
mitigating risk. In addition to earned value, developers use metrics 
for the size of a project, requirements, tests, defects, and quality to 
assess software development progress and to identify potential areas of 
improvement. Developers share this information with acquirers, who use 
the data to assess the risk software development has on overall product 
development and to make informed decisions about acquisitions. Figure 1 
shows that a manageable environment, disciplined processes, and useful 
metrics are used together to form an effective process for software 
development.

Figure 1: Key Management Practices That Increase Chances of Successful 
Outcomes:

[See PDF for image]

[End of figure]

The Right Environment Reduces Software Development Risk:

Three leading companies we visited--General Motors Powertrain Unit 
Motorola Global Software Group (GSG); and Teradata, a division of 
National Cash Register Corporation (NCR)--made a concerted effort to 
establish an environment that lowers risk and increases the chances of 
successful software development outcomes. This environment focuses on 
producing what is possible by establishing evolutionary product 
development while adhering to well-understood, well-defined, 
manageable requirements and encouraging continuous improvement of 
development processes. The environment enables leading companies to 
effectively compete in markets where delivery times are paramount and 
the acquirer expects reasonable prices and can go elsewhere with its 
business if not satisfied. Over time, these leading companies have 
learned that an evolutionary process emphasizing knowledge and quality 
enables successful outcomes. In comparison, an environment that allows 
too many risks, unknowns, and immature processes into product 
development can have poor outcomes. In high-risk, low-technology 
maturity environments, developers find themselves forcing software to 
meet unrealistic expectations.

Officials at each of the companies we visited said that evolutionary 
product development is one of the fundamental elements of a manageable 
environment. Evolutionary development reduces risk because it allows 
software to be developed in small, manageable increments, with the 
availability of the complete software package coming later in the 
development life cycle. The General Motors Powertrain unit, which 
manufactures engines and transmissions, follows an evolutionary 
approach that calls for four to eight releases of the software product 
line each year. This approach offers many benefits, including allowing 
the software teams to restrict the size of projects to make them more 
manageable and to reduce risk. In addition, only well-defined 
requirements are included in the scope of the work, allowing the 
software teams to make improvements to previous releases.

These leading companies consider continuous improvement to be an 
important part of their environment and culture, and most have 
implemented one of the Software Engineering Institute's Capability 
Maturity Models®. They have found that ad-hoc processes make it 
impossible to gain a clear understanding of when and how defects occur 
and make it difficult to fix processes so that the same defects can be 
avoided in the future. Motorola GSG officials told us it is not enough 
to hire talented software developers to achieve successful outcomes. 
Rather, companies must establish the right environment and use 
disciplined processes to help developers work efficiently and then 
target their recruiting efforts toward staff who can work in a process-
oriented environment. This is not an easy task. Companies must be 
willing to invest time and money to develop new processes, collect 
meaningful data on a consistent basis, and train employees to follow 
the processes and interpret the data. In addition, management must 
display a strong commitment toward implementing the improved processes.

Disciplined Software Development Processes Improve Software Outcomes:

Within a low-risk, continuous improvement environment, leading 
companies we visited use a very structured, gated software development 
process that requires teams to obtain knowledge about the maturity of 
their software projects at key points in time. They plan, manage, and 
track activities for requirements, design, coding, and testing and rely 
heavily on such activities as configuration management, peer reviews, 
and quality assurance to help ensure the quality of their software. 
They also identify areas of risk and take actions to control the risks. 
Developers pay particular attention to the requirements-setting process 
because requirements are the foundation of a development effort. If 
requirements are not well defined or if there are too many changes, the 
result is additional, sometimes unmanageable risk.

Figure 2 is a general depiction of the process used by the companies we 
visited to manage software development. There are four development 
phases: determining requirements, establishing a stable design, 
manufacturing code, and testing to validate that the software meets the 
requirements and to detect errors. Within each phase are key activities 
that must take place and knowledge, or information, that must be 
attained to pass a review and move to the next phase of development.

Figure 2: Highlights of the Knowledge-Based Software Development 
Process:

[See PDF for image]

[End of figure]

In addition to the four software development phases, these companies 
consider quality assurance, configuration management, measurement, and 
analysis to be integral parts of their software development activities. 
These activities assist developers in adequately managing software 
projects and collectively give the developer and the acquirer a level 
of confidence that the software is being developed within cost, 
schedule, performance, and quality targets. For example, configuration 
management allows developers to maintain a historical perspective of 
each software version change, keep a record of the comments made about 
the changes, and verify the resolution of defects. Quality assurance 
activities are typically focused on detecting and resolving defects. 
However, some companies, like Motorola GSG, may assign responsibility 
for detecting and resolving defects to the project team and focus their 
quality assurance activities on evaluating whether project-associated 
work products adhere to the applicable process standards and 
procedures. In this case, quality assurance activities would also 
include ensuring that when the project teams do not comply with 
processes, these instances are identified, reported, and resolved at 
the appropriate level. Officials at each company we visited told us 
that the earlier defects are found and fixed, the less costly it is to 
the organization. If the defects are not found in the phase in which 
they occur, the cost to correct them grows in subsequent phases to the 
point where it could cost the company a significant amount of money to 
fix the problem once the software is fielded than if it had been 
corrected earlier.

Requirements:

Senior managers at software development and acquisition companies we 
visited expect requirements to be managed and controlled before design 
work begins and virtually all lower-level design elements to be 
adequately defined before the start of coding. Without adequate 
definition and validation of requirements and design, software 
engineers could be coding to an incorrect design, resulting in missing 
functionality or errors. Motorola GSG, a communications company, and 
Teradata, a division of NCR that specializes in database technology, 
estimate that about 95 percent of their requirements are set by the end 
of the requirements phase and 98 percent by the end of the design 
phase. Officials view managing requirements as the most critical 
development task to ensure successful software outcomes. They said that 
many software problems, often referred to as defects, could be traced 
to missing, vague, or changing requirements. Although company officials 
stated that some requirements-related defects are inevitable, such as 
those that arise when requirements are not sufficiently detailed, they 
said significant time and effort are necessary to elicit and document 
all requirements and determine the appropriate sequence for meeting 
these requirements. Nevertheless, mature organizations take time to 
conduct the various activities to sufficiently document and validate 
requirements before proceeding to preliminary design.

Leading software developers told us they typically devote about 20 to 
30 percent of their software development time to requirements-setting 
activities. Doing so ensures that developers will be able to provide 
managers with key knowledge at the requirements review gate and show 
that requirements have been properly vetted with the acquirer and that 
they are achievable and well written. Activities they complete are 
highlighted below.

* Establish integrated project teams: Representatives from all acquirer 
and developer stakeholder groups use sound systems engineering 
techniques to establish software requirements.

* Categorize requirements: Acquirer and software team develop a 
comprehensive list of requirements and then categorize them on the 
basis of how critical they are to the product's performance.

* Negotiate requirements: Software team develops resource and schedule 
estimates on the basis of system engineering knowledge and past 
projects of similar size and scope. The software team then advises the 
acquirer which requirements may have to be delayed or sacrificed on the 
basis of resource and schedule goals.

* Agree to requirements baseline: Software team and acquirer agree to a 
requirements baseline that details the software requirements, including 
cost, schedule, performance, and quality goals the software team is 
expected to achieve.

* Develop more detailed software requirements: Using systems 
engineering, software team breaks the requirements into lower-level 
requirements, discusses the requirements with the acquirer, and 
formally documents the more detailed requirements.

* Perform quality check: Organization performs quality checks on 
requirements-related documents, such as the functional requirements 
document, to ensure that requirements are written clearly and all of 
the acquirer's requirements have been adequately addressed.

Company officials stress that to develop effective software 
requirements, the acquirer and developer must work closely together and 
have open and honest discussions about what can and cannot be done 
within desired time frames. Motorola GSG officials, for example, 
emphasize the importance of a written requirements baseline agreement 
with the acquirer to solidify software requirements and then strict 
adherence to requirements agreed to in order to avoid cost and schedule 
growth. They also perform detailed quality reviews to detect 
requirements problems early and to avoid costly rework in later stages.

Once developers establish requirements, they must also effectively 
manage the number and timing of requirements changes. Each developer we 
visited acknowledged that requirements could change at any point. 
However, officials told us that they aggressively manage requirements 
changes to make sure that they are reasonable and do not have a 
detrimental impact on project outcomes. For example, before making 
changes, they analyze the potential impact on cost, schedule, and 
performance and negotiate with the acquirer about whether the changes 
should be made within the ongoing project or in a future release. The 
negotiation usually involves preparing an impact report for review by 
the acquirer or a governing board. Teradata, a division of NCR, goes 
further by limiting the number of changes it will make during the 
development cycle.

Design:

A stable design ensures that all requirements are addressed and that 
components and interfaces are defined. A Motorola GSG official stated 
that at least 90 percent of the company's software designs are stable 
before coding and suggested that developers that do not effectively 
manage the design phase could spend as much as 40 percent of a 
project's resources on rework activities. Leading companies complete a 
series of activities to stabilize their design and assure management 
that the software team is ready to advance to the next stage of 
development. These activities include, among other things, defining the 
overall functions and structure of the software on the basis of 
established requirements; selecting a system design; and developing the 
detailed system design specifications, which are sometimes referred to 
as the low-level design.

Typically, software teams will have two management reviews during this 
phase of development. A preliminary design review is used to examine 
the design rationale and design assumptions to ensure that the 
resulting software systems will meet the stated requirements. 
Particular attention is given to high-priority aspects of the system, 
such as performance, security, maintainability, and system recovery. 
User manuals and software test plans may also be examined at this time. 
A critical design review is conducted once the detailed design of the 
software system has been completed. The purpose of this review is to 
examine all design features to determine if they meet the acquirer's 
requirements. Throughout this phase companies typically perform peer 
reviews of design documents to detect errors and may also construct 
prototypes for the acquirers to test their understanding of the 
requirements.

Coding and Testing:

During the coding phase, software developers translate the requirements 
and design into a series of software steps that will control the 
system. According to company officials, well-written, achievable 
requirements, as well as very detailed designs, greatly enhance a 
software developer's ability to create software with relatively few 
defects. Additional processes that are critical to the success of this 
phase include peer reviews, coding standards, frequent unit testing, 
access to a library of pre-coded and tested functionality, and use of 
programming languages that enable the software engineer to document the 
code to facilitate understanding at a later time. For example, the 
leading companies we visited rely heavily on previously developed 
software to reduce development time, costs, and testing. According to 
company officials, it is not uncommon for them to reuse 70 percent of 
previously developed software on a new project. General Motors 
Powertrain officials emphasized that reuse is a top consideration for 
their projects and they have developed a software product line that 
teams use to complete requirements, design, and coding activities. Over 
the past few years, they have also re-engineered some of their 
electronic modules to allow for greater standardization of components 
within and across their Powertrain portfolio. This has greatly enhanced 
their ability to reuse software.

Testing is then performed to uncover defects or gaps in the code. 
Leading software companies we visited develop test plans after 
requirements are stable and take steps to ensure that there are one or 
more tests for each requirement. Through testing, teams assess the 
quality of the software to make it as defect-free as possible. For 
Motorola GSG, the software team is in control of all of the coding, 
testing, and quality-assurance activities. Officials stated that teams 
have access to online training and rely on libraries of previously used 
and tested code. They use peer reviews and inspections extensively 
during the requirements, design, and coding phases, for all software 
documents and test software and hardware components together to 
identify any integration problems that must be corrected.

Metrics Provide Useful Insight to Software Development Activities:

Leading developers we visited commonly use seven major types of 
metrics--cost, schedule, size, requirements, tests, defects and 
quality--to gauge a project's progress and identify areas for 
improvement. Acquirers use some of these same metrics to assess whether 
the developer will be able to deliver the software within cost, 
schedule, performance, and quality parameters.

We found that leading developers are relentless in their efforts to 
collect metrics to improve project outcomes and processes. The 
importance of metrics to these companies cannot be overemphasized. 
Motorola GSG and Teradata, a division of NCR, measure key aspects of 
software development for individual projects from the usual cost and 
schedule goals to process-improvement-type metrics that track the 
number and type of defects within each software development phase. They 
also have goals and metrics for companywide initiatives, such as cost-
reduction efforts and customer satisfaction. Equally important, they 
have emphasized the critical nature of measuring processes, collecting 
metrics, and using them to analyze performance into their workforce 
through training.

Table 1 provides an overview of the seven categories of metrics used by 
the leading developers we visited, examples of their specific metrics, 
and how the companies use the metrics to manage their projects. Company 
officials cautioned that a variety of metrics could be used to satisfy 
each category listed in table 1 and that no one set of specific metrics 
would necessarily apply to all companies. Rather, companies tailor 
metrics from each category to fit their own needs.

Table 1: Metrics Used by Leading Software Developers:

Major metric: Cost; Examples of metrics used: 
* Cost and effort per phase; 
* Planned versus actual cost; 
* Cost performance index; 

Major metric: Cost; Usefulness of metrics: 
Cost performance metrics, products of an earned value management 
system, indicate actual progress toward completing the software 
development against the plan. Large deviations between actual and 
estimated costs indicate that the project will have problems meeting 
cost and schedule goals. Management may have to consider taking 
actions such as reducing the scope of the project to meet release 
dates or even canceling the program.

Major metric: Schedule; Examples of metrics used: 
* Planned versus actual delivery dates; 
* Schedule estimation accuracy; 
* Percentage of project on time; 
* Schedule performance index; 

Major metric: Schedule; Usefulness of metrics: 
Schedule performance metrics, also products of an earned value 
management system, indicate achieved schedule progress against the 
plan. They are used throughout the software development phases to 
gauge progress toward developing key products or meeting critical 
milestones. Close attention to schedule deviations allows management 
to identify the team's ability to meet project goals and to determine 
if and when additional resources need to be added.

Major metric: Size; Examples of metrics used: 
* Amount of new, modified, and reused code; 
* Size estimation accuracy; 

Major metric: Size; Usefulness of metrics: 
Size metrics are used by management to compare the amount of code 
produced with the amount estimated. Changes to the size needed 
indicate potential cost and schedule problems.

Major metric: Requirements; Examples of metrics used: 
* Total requirements or features committed to deliver; 
* Percentage of requirements completed; 
* Number of requirements changes by phase; 

Major metric: Requirements; Usefulness of metrics: 
Requirements metrics are used to assess the organization's progress 
towards meeting the acquirer's performance demands. Developers try to 
avoid a large number of requirements changes or late changes because 
changes can impact cost and schedule commitments and can also result 
in software with a higher number of defects.

Major metric: Tests; Examples of metrics used: 
* Number of tests planned, completed, and passed; 
* Percent of planned tests completed; 

Major metric: Tests; Usefulness of metrics: 
Test metrics are used to determine the extent to which planned 
software tests have been successfully accomplished. Deviations from 
the planned number of tests suggest that software might not have been 
adequately tested and may have quality problems, which could lead to 
costly rework in later phases.

Major metric: Defects; Examples of metrics used: 
* Number of defects per phase; 
* Phase defect originated versus phase found; 
* Cost to fix defect; 
* Severity of defects; 
* Total unresolved defects; 

Major metric: Defects; Usefulness of metrics: 
Defect metrics are used to track problems with the software. 
Developers track defects to the phase where they were found, where 
they should have been found, and the cost to fix the problem. Large 
numbers of defects, particularly those that are found after the phase 
in which they were created, indicate performance problems that may 
lead to increased cost and schedule due to rework and the need to 
review development processes so that defects are found earlier. 
Identifying fewer defects than expected could also be problematic. For 
example, it may indicate that there is inadequate test coverage in the 
testing phase or that an insufficient formal technical review was 
performed on design documents in the design phase.

Major metric: Quality; Examples of metrics used: 
* Cost of quality efforts; 
* Cost of poor quality (rework); 
* Number of quality goals missed and achieved; 
* Customer satisfaction survey results; 

Major metric: Quality; Usefulness of metrics: 
Quality metrics provide information on the potential reliability of 
the delivered software and also provide an indication of the amount of
money and time the developer invested in the development process in an 
attempt to assure a given level of quality. If defects are found and 
fixed during the phase in which they occur, this provides an 
indication that quality activities are performing well. If a defect is 
not identified in the phase in which it occurred, it becomes more 
expensive and time-consuming to fix and indicates weaknesses in the 
development process that need to be addressed. 

Source: GAO's analysis of leading companies' practices.

[End of table]

Leading developers we visited use metrics from each category above to 
actively oversee their projects and continuously assess their processes 
and projects to identify opportunities for improvement. Motorola GSG, 
for example, uses a standard set of metrics to enable project managers, 
as well as other levels of management, to assess the status of their 
individual software projects, staff productivity, requirements 
volatility, cost and schedule estimation accuracy, and the 
effectiveness of their quality assurance processes. Management also 
uses the information to compare similar projects within a software 
center or across the company to identify trends and areas that can be 
improved. They are particularly interested in tracking the number of 
defects by software development phase, the amount of rework associated 
with correcting the defect, and the amount of project resources spent 
to ensure quality. For example, data from one project show that 
developers were able to find and correct 92 percent of their problems 
during the phase in which they occurred. The other 8 percent were 
corrected by the end of the system test phase, resulting in only 
1 percent of total project resources being spent to correct defects.

Motorola GSG uses an earned value management system to track the actual 
amount of time and effort it spends on project activities versus what 
it estimated for the projects. The earned value system, when properly 
implemented, provides developers and acquirers with early warnings of 
problems that could significantly affect the software project's cost 
and schedule. For example, according to private industry research, once 
a project is over 15 percent complete, developers will be unable to 
make up any overruns incurred to that point and the overruns will be 
even greater once the project is finished. This is often because 
project planning typically underestimates the time and effort required 
to implement planned tasks.

Motorola GSG uses a project time-tracking system to record the time 
spent on project activities attributed to the cost of quality and cost 
of poor quality metrics. The cost of quality metric tracks the amount 
of time and money spent on such activities as formal quality reviews, 
testing, defect prevention, and rework to ensure a reliable product. If 
more resources were expended on these activities than expected, 
Motorola GSG would identify the reasons for this occurrence and improve 
its processes to try to prevent overruns from happening again. The cost 
of poor quality is also a concern to Motorola GSG because it quantifies 
the amount of rework that was necessary to address any product 
nonconformance, such as defects before (internal failure) and after 
(external failure) releasing the software product to the acquirer. 
According to company officials, the cost of poor quality is a direct 
reflection of the effectiveness of a company's software development 
processes. Generally speaking, poor processes lead to greater rework 
and a higher cost of poor quality, while better processes lead to a 
small amount of rework and a low cost of poor quality. Motorola GSG 
officials stated they have been able to hold the cost of poor quality 
(rework) to less than 5 percent for its projects by identifying when 
defects occur and then looking for improvements in their processes to 
try to prevent them from happening again.

Acquirers also need the types of metrics presented in table 1 to plan, 
manage, and track overall product development. These types of metrics 
allow acquirers to make their own assessments of the status of the 
software development project, where the software project is headed, the 
potential risk that software presents to overall product development, 
and if the developer's processes are effective in terms of reducing 
cost and schedule and improving quality. The earned value management 
system could provide acquirers with key information for calculating 
cost and schedule variations and also determining how much effort will 
be needed to complete a project on time when a project is behind 
schedule. If acquirers determine that software is likely to be late or 
over cost at completion, they then have the option to move some of the 
software requirements to a later development effort or allow the 
software development team more time to complete the project.

Outcomes on DOD's Software-Intensive Acquisitions Were Influenced by 
Environment, Processes, and Metrics:

In our reviews of five major DOD software-intensive weapon system 
acquisitions, we found mixed results. When DOD managers had a smaller, 
more evolutionary product with manageable requirements, used 
disciplined development process with gated reviews, and collected and 
used metrics to manage software development progress--such as the 
Tactical Tomahawk and the F/A-18-C/D programs--they delivered their 
product with less cost increase and less schedule delay. When DOD 
managers had expectations of developing revolutionary capabilities and 
did not use structured management reviews or collect and use metrics 
for software development--such as the F/A-22, SBIRS, and Comanche 
programs--they experienced significant cost growth and schedule delays. 
Table 2 illustrates how an evolutionary environment, effective process 
management, and use of meaningful metrics correlate with cost and 
schedule outcomes experienced by each program.

Table 2: Program Outcomes Linked to Management Controls:

Program: Tomahawk; 
Evolutionary environment: Yes; 
Disciplined process: Yes; 
Use of meaningful metrics: Yes; 
Percent change in research, development, test, and evaluation cost 
estimate: 7.6; 
Percent change in cycle time estimate: 22.4.

Program: F/A-18 C/D; 
Evolutionary environment: Yes; 
Disciplined process: Yes; 
Use of meaningful metrics: Yes; 
Percent change in research, development, test, and evaluation cost 
estimate: 36.4; 
Percent change in cycle time estimate: 6.2.

Program: F/A-22[A]; 
Evolutionary environment: No; 
Disciplined process: No; 
Use of meaningful metrics: No; 
Percent change in research, development, test, and evaluation cost 
estimate: 127; 
Percent change in cycle time estimate: 104.

Program: SBIRS[A]; 
Evolutionary environment: No; 
Disciplined process: No; 
Use of meaningful metrics: No; 
Percent change in research, development, test, and evaluation cost 
estimate: 88; 
Percent change in cycle time estimate: Not available.

Program: Comanche[A]; 
Evolutionary environment: No; 
Disciplined process: No; 
Use of meaningful metrics: No; 
Percent change in research, development, test, and evaluation cost 
estimate: 231; 
Percent change in cycle time estimate: 120. 

Source: GAO's analysis of DOD programs and selected acquisition 
reports.

[A] GAO's assessment of the evolutionary environment, disciplined 
process, and use of meaningful metrics addresses conditions found 
before these programs were restructured.

[End of table]

Successful Outcomes for Two DOD Acquisitions:

The Tactical Tomahawk and F/A-18 C/D programs were developed in an 
evolutionary environment, engaged in extensive work on requirements, 
controlled requirements' changes, collected and used detailed metrics 
to track development progress, and had less cost and schedule increase 
than the other programs we reviewed.

The Navy's Tactical Tomahawk missile will provide ships and submarines 
with enhanced capability to attack targets on land. New features 
include improved anti-jamming global positioning system, in-flight 
retargeting, and the ability to transmit battle damage imagery. 
Tomahawk program developers had disciplined development processes and 
used extensive peer reviews to discover defects and provided the 
acquirer with insight at each stage in development: requirements, 
design, code and test. They were responsible for collecting and 
reporting data on a monthly basis, relying on metrics--cost, schedule, 
effort, size, requirements, testing, and defects that are similar to 
those used by leading commercial firms. The program office managed the 
acquisition based on the trends found in these metrics.

The F/A-18 C/D is a Navy attack fighter aircraft that has been deployed 
for a number of years. Periodically, the Navy upgrades the flight 
software to incorporate new features, add the capability to fire new 
munitions, and correct deficiencies discovered since the last upgrade. 
Working in an evolutionary environment, F/A-18 C/D program officials 
recognized that the success of the software upgrade to incorporate 
additional performance into the flight operations software depended on 
extensive requirements analysis before program start and firm control 
as requirements changed throughout development. This analysis ensured 
that the effort needed to meet requirements was well understood at the 
beginning of development, thus limiting the amount of redesign. 
Proposals for new requirements or changes to requirements after the 
program began were analyzed for cost, schedule, and performance impact. 
As with the Tomahawk program, FA-18 developers adhered to disciplined 
development processes, used extensive peer reviews to discover defects, 
and collected meaningful metrics to track progress.

Outcomes Were Poor for Programs That Did Not Use an Evolutionary 
Approach, Disciplined Processes, and Meaningful Metrics:

The F/A-22, SBIRS, and Comanche are complex programs that attempted to 
achieve quantum leaps in performance requiring extensive use of 
software rather than follow an evolutionary approach to software 
development. They all initially lacked controls over requirements, 
software processes, and metrics, causing major program upheavals. They 
encountered significant requirements changes, schedule slips, and cost 
increases because software defects were not discovered until later 
stages of the programs. Each of these programs has been restructured to 
incorporate requirements management controls, more-defined software 
development processes, and additional metrics.

The Air Force's F/A-22, originally planned to be an air dominance 
aircraft, will also have air-to-ground attack capability. It is 
expected to have advanced features, such as stealth characteristics, to 
make it less detectable to adversaries and capable of high speeds for 
long ranges. The F/A-22's avionics are designed to greatly improve 
pilots' awareness of the situation surrounding them. Early in the 
development process for the F/A-22, we reported that the program's 
planned strategy for software development and acquisition was generally 
sound.[Footnote 5] We cited the Air Force's plans to collect software 
costs and other software metrics to measure progress as examples of 
this sound strategy. At that time, we endorsed the program's plans to 
be event-rather than schedule-driven. However, as early as 1994, many 
features of this sound strategy were not being followed. Delayed 
software deliveries contributed to cost increases and schedule delays. 
Requirements and design changes accounted for 37 percent of the 
critical problem reports leading to avionics shutdowns in the F/A-22, 
according to program office reports. Program officials and contractor 
personnel agreed that requirements volatility had been a problem; 
however, they were unable to provide any specific measure of 
requirements changes because they had not tracked the overall growth in 
software requirements since the first 3 years of the program.

According to Lockheed Martin officials, the avionics system software is 
made up of 84 computer software configuration items,[Footnote 6] each 
of which accounts for a specific avionics function, such as the 
interaction between the pilot and the aircraft. In our discussion with 
contractor and program personnel, they stated that disciplined 
processes in requirements control, design, testing, and configuration 
management were not uniformly followed because of cost and schedule 
pressures. The F/A-22 software strategy also called for the collection 
of software metrics to measure costs. Program and contractor officials 
were unable to provide metrics for sufficient management visibility 
over the overall progress of the software. The contractor stated that 
the Air Force did not compile metrics from lower levels into major 
segments such as avionics.

The Air Force's SBIRS satellites are being developed to replace DOD's 
older missile-warning satellites. In addition to missile warning and 
missile defense missions, the satellites will perform technical 
intelligence and battlespace characterization missions. Since the 
program was initiated in 1996, SBIRS has faced cost, scheduling, and 
technology problems. We have reported that SBIRS has experienced 
serious software design problems. Officials from Lockheed Martin, the 
prime contractor, stated that the program had uncontrolled requirements 
growth as well as overly optimistic expectations about reusing software 
from a previous program. Program and contractor officials agreed that 
deficient systems engineering and the scarcity of personnel in software 
engineering disciplines contributed to ineffective control and to not 
understanding how much of the previous software could be reused. These 
officials also stated that neither the program office nor the 
contractor had a change management control process in place to analyze 
change requests. A thorough analysis late in the program revealed that 
very little of the software could be reused. Furthermore, because of a 
deficiency in resources devoted to systems engineering, the total 
requirements for the system were not adequately defined.

A report from an independent review team stated that more robust 
systems engineering could have precluded some of the problems. The 
report concluded that problems with the first SBIRS increment were 
primarily due to problems with software development and poor program 
execution. Peer reviews and engineering review boards were in place to 
monitor development, but, for reasons ranging from schedule pressures 
to reduced staffing, these decision bodies were ineffective. SBIRS 
contractor officials stated that they collected data on additions to 
requirements and on the number of lines of code, but because there were 
no restrictions on accepting new requirements and no control limits to 
the size of code, the metrics were not used to manage the project on a 
daily basis.

The Army's Comanche is a multi-mission helicopter intended to perform 
tactical armed reconnaissance. It is designed to operate in adverse 
weather across a wide spectrum of threat environments and provide 
improved speed, agility, reliability, maintainability, and low 
observability over existing helicopters. Since the program's first cost 
estimate, originally approved in 1985, the research and development 
cost for Comanche has almost quadrupled, and the time to obtain an 
initial capability has increased from 9 to over 21 years.

Several studies have identified software development as a problem area 
and highlighted requirements volatility and inadequate requirements 
analysis as having a large impact on the program. The lack of a 
disciplined process for Comanche's software acquisition was also cited 
as a reason for program shortfalls; however, the exact percentage of 
cost growth attributed to software is not known because the program 
office lacked adequate visibility into the software development process 
and, therefore, has little historical data on software. Comanche 
officials stated that initially they did not require a uniform set of 
metrics from the contractor. They said they received earned value 
information from the contractor, but it combined software and hardware 
development data.

All three programs have been restructured and have instituted changes 
to bring more knowledge into the programs. For example, F/A-22 program 
officials report that their contractors have teamed with divisions 
within their companies that have more disciplined processes and they 
are reporting fewer problems with the avionics software. SBIRS program 
officials stated that they have instituted more controls over 
requirements changes, requiring analysis and approval at higher levels. 
Comanche officials reported that the program office has quarterly 
software reviews to focus attention on software development progress 
with the contractor and has adopted an incremental, block development 
strategy for software development. Program officials stated that they 
have asked for more-detailed metrics by which to manage the programs.

DOD, the Services, and MDA Have Begun to Improve the Acquisition 
Environment, but Controls Needed to Assist Acquisition Managers:

As a result of congressional requirements to initiate improvement plans 
and revisions to requirements and acquisition policies, DOD, the 
military services and MDA have created a more conducive environment for 
software acquisition and development. However, additional steps must be 
taken. We have found that leading software acquirers and developers we 
visited create disciplined software development processes and collect 
useful metrics for management oversight. These practices have proven to 
be a significant factor in their ability to achieve successful 
outcomes. DOD, the services, and MDA still lack controls in these areas 
that would put acquisition program managers in a better position to 
achieve successful program outcomes.

The plans that the services and MDA have begun in response to 
congressional direction have varying levels of detail and are at 
various stages of approval within the organizations. The Army, for 
example, has completed and has begun to implement its plan. The plan 
includes using pilot programs to provide information on metrics, and 
the Army expects to team with the Software Engineering Institute to 
identify training needs and continuous improvement. MDA has prepared a 
detailed draft that includes forming a baseline assessment of each 
missile defense element and making recommendations to the program 
office for each element to adopt improvement processes. MDA expects the 
elements to begin work once the baseline assessment is complete. The 
Navy's response includes teaming with the Software Engineering 
Institute to identify a course of action, including a training program 
for acquisition professionals and identifying software acquisition 
requirements and management initiatives. The Air Force has called for a 
working group to begin in March 2004 to baseline Air Force practices 
and to suggest a course of action. These efforts establish an 
environment of change for the services and provide a platform upon 
which to make additional improvements. Furthermore, they make explicit 
to software an evolutionary approach to systems development and 
acquisition that DOD included in the recently revised requirements 
generation and acquisition policies.[Footnote 7]

However, the services' and MDA's planning does not include practices we 
found at leading commercial firms that enable those firms to have 
successful outcomes. Furthermore, the plans do not incorporate controls 
that would ensure that the plans now being formulated are incorporated 
into acquisition practice. The plans could be strengthened by adding 
specific criteria to ensure that:

* requirements' baselines based on systems engineering are documented 
and agreed to by both the acquirer and developer before a program's 
initiation and that cost/benefit analyses are required when new 
requirements are proposed;

* software developers and acquirers make efforts to continually improve 
practices over time;

* gated reviews and deliverables are integrated into the development 
processes; and:

* developers collect and analyze metrics, including earned value to 
obtain knowledge about development progress and to manage risk.

Army, Navy, Air Force, and MDA officials said they have high-level 
support for improving software acquisition and for the plans they are 
developing, and the Army and MDA stated that they had included funding 
for software improvements in their budgets. Officials at the leading 
companies we visited emphasized that strong management support is 
needed to ensure success with process improvements. Although DOD has 
embraced an evolutionary approach in its acquisition policy, DOD has 
not yet incorporated a requirement specific to software process 
improvement into the policy. Furthermore, DOD has not said how it will 
require individual program offices to follow the guidance once the 
services and MDA establish full-fledged programs to improve software 
development processes.

Apart from the software acquisition improvement plans, DOD has taken 
some initiatives to strengthen software acquisition and development as 
well as address repeated performance shortfalls attributed to software. 
Since 1999 the Tri-Service Initiative has conducted detailed 
assessments of software-intensive programs to identity and mitigate 
software risks. The initiative has assessed about 50 programs spanning 
all military branches. While the results of individual initiatives are 
confidential to their programs, an overview shows three of the main 
causes of critical program performance problems: (1) the ability of the 
programs to establish and adhere to processes to meet program needs, 
(2) requirements management, and (3) organizational management. Process 
capability was a problem in 91 percent of case studies while problems 
with requirements management and organizational management were 
identified as problems 87 percent of the time. These findings are 
consistent with our discussions with leading companies about 
significant problem areas for software development management. This 
kind of information could prove useful to the military services and 
agencies as they plan for improving software acquisition. DOD has begun 
another initiative to strengthen the role that systems engineering 
plays in weapons system development as well as in software development. 
According to DOD officials, this initiative will include provisions for 
gated reviews of systems engineering baselines on an event-driven 
basis. Furthermore, the officials stated that they were working to 
incorporate the new systems engineering directives into acquisition 
policy.

DOD has tasked a source selection criteria working group with 
clarifying policy regarding source selection criteria for software-
intensive systems, and another working group is creating a 
clearinghouse for best practices. The source selection criteria working 
group is discussing the application of software product maturity 
measures, and the Software Intensive Systems office is developing a 
proposal for a centralized clearinghouse of software best practices, 
but these initiatives are not complete.

To provide a better method of estimating the cost of software, DOD 
added a requirement to its acquisition policy to report such 
information as type of project, size, effort, schedule, and quality 
data to the Cost Analysis Improvement Group. DOD policy requires the 
Software Resource Data Report for major defense programs for any 
software development element with a projected software effort greater 
than $25 million.

Conclusions:

Organizations we visited that have established a strong, consistent, 
evolutionary environment and practices for setting product 
requirements, maintaining a disciplined development process, and using 
metrics to oversee development progress achieve favorable cost, 
schedule, and quality outcomes for software projects. These practices 
limit development efforts to what can be managed and result in 
decisions throughout the development process that are based on 
knowledge obtained through systems engineering that is sufficient to 
adequately gauge risks. The organizations we visited made business 
decisions to invest time and resources in achieving high process 
maturity levels to improve these practices. For the most part, in the 
programs reviewed, DOD garnered poor results from its software 
acquisition process because it has not employed consistent practices in 
these areas. Much as we have found in DOD's overall acquisition 
management process, the decisions to begin programs and to make 
significant investments throughout development are made without 
matching requirements to available resources and without demanding 
sufficient knowledge at key points. The acquisition programs we 
reviewed that used evolutionary environments, disciplined processes, 
and managed by metrics were more successful, and the programs that did 
not use these practices were less successful.

DOD has attempted to improve acquisition outcomes by establishing a 
framework for an evolutionary environment in its requirements 
generation and acquisition policies that develops manageable increments 
of capability. This is a positive step. However, DOD's policies do not 
contain the controls needed to ensure individual programs will adhere 
to disciplined requirements and development processes, nor do they 
include the metrics needed to do so. As DOD works to finalize its 
software process improvement plans, it has the opportunity to put in 
place those practices that have proven successful in achieving improved 
outcomes for software-intensive systems. In moving into a more complex, 
"system of systems" acquisition environment, much more will be demanded 
from software. The need for consistent practices and processes for 
managing software development and acquisition will become paramount if 
DOD is to deliver capabilities as promised.

Recommendations for Executive Action:

We have previously made recommendations to DOD to adopt certain 
specific practices developed by the Software Engineering Institute. As 
DOD changes the way it manages software intensive systems, it must take 
steps to ensure better acquisition outcomes. We recommend the Secretary 
of Defense take the following four actions:

* To assure DOD appropriately sets and manages requirements, we 
recommend that DOD document that software requirements are achievable 
based on knowledge obtained from systems engineering prior to beginning 
development and that DOD and the contractor have a mutual understanding 
of the software requirements. Furthermore, we recommend that trade-off 
analyses be performed, supported by systems engineering analysis, 
considering performance, cost, and schedule impacts of major changes to 
software requirements.

* To ensure DOD acquisitions are managed to a disciplined process, 
acquirers should develop a list of systems engineering deliverables 
(including software), tailored to the program characteristics, and 
based on the results of systems engineering activities that software 
developers are required to provide at the appropriate stages of the 
system development phases of requirements, design, fabrication/coding, 
integration, and testing.

* To ensure DOD has the knowledge it needs to oversee software-
intensive acquisitions, we recommend that acquirers require software 
contractors to collect and report metrics related to cost, schedule, 
size, requirements, tests, defects, and quality to program offices on a 
monthly basis and before program milestones and that acquirers should 
ensure that contractors have an earned value management system that 
reports cost and schedule information at a level of work that provides 
information specific to software development.

* These practices should be included and enforced with controls and 
incentives in DOD's acquisitions policy, software acquisition 
improvement plans and development contracts.

Agency Comments and Our Evaluation:

DOD provided us with written comments on a draft of this report. The 
department concurred with two of the recommendations, subject to our 
incorporating some minor revisions. Since the suggested revisions did 
not materially change the intent of the recommendations, we revised 
them. For two other recommendations, the department partially 
concurred. The department agreed that the report provides useful 
insight for improving the software acquisition process and is 
consistent with its efforts to improve the process as it continues to 
implement section 804 of the Fiscal Year 2003 National Defense 
Authorization Act. It also agreed to take the report's findings into 
account as it monitors the process for continuous improvement and to 
apply our recommendations as further guidance to its component services 
and agencies.

The department further noted that the techniques highlighted in the 
report should not be seen as a panacea. We agree. Our report provides 
evidence that acquisitions can succeed if they take place in an 
evolutionary environment rather than an environment that requires 
complex solutions for a single quantum leap in software capabilities. 
To augment an evolutionary environment, requirements must be carefully 
managed and existing systems and software engineering knowledge must be 
taken into account, the development processes must be disciplined and 
transparent to decision makers, and key metrics must be gathered and 
used to support decisions. We disagree with the department's 
observation that the report "plays down significant challenges 
associated with acquisition of complex defense systems .…" To the 
contrary, our report highlights those challenges as inherent to 
acquisitions that proceed with limited knowledge about how to achieve 
quantum leaps in capability in a single acquisition. Our comparison of 
two successful evolutionary programs (Tactical Tomahawk and F/A-18 C/D, 
both categorized as major defense acquisition programs) with three 
revolutionary programs (F/A-22, SBIRS, and Comanche) shows different 
outcomes in terms of cost, schedule, and delivery of equipment to the 
warfighter.

DOD's rationale for providing programs with data less frequently than 
we recommended in our third recommendation suggested that data did not 
create knowledge and that knowledgeable software professionals are 
needed to interpret data. We agree that both knowledgeable people and 
data are needed, but those professionals must have data to interpret. 
We found that initially the F/A-22, SBIRS, and Comanche programs had 
knowledgeable staff but little data to analyze.

DOD indicated that it was already addressing software acquisition in 
policy in response to the fourth recommendation and cited multiple 
sections of DOD Directive 5000.1 as evidence. We do not agree that the 
current policy puts adequate controls in place to improve software 
practices to a level achieved by leading commercial companies. DOD is 
silent about including incentives in contracts for improving software 
processes. The department's comments are printed in appendix I.

Scope and Methodology:

To determine the best practices commercial companies use to manage 
software development and acquisition, we first conducted general 
literature searches. From these literature searches and discussions 
with experts, we identified numerous companies that follow structured 
and mature processes for software development and acquisition. We 
visited the following commercial companies:

Computer Sciences Corporation (CSC) develops individual business 
solutions for commercial and government markets worldwide. The company 
is specialized in management and information technology consulting, 
systems consulting and integration, operations support, and information 
services outsourcing. In 2003, the company generated revenues of 
$11.3 billion. We visited CSC's Federal Sector office in Moorestown, 
New Jersey, and discussed its practices for developing and acquiring 
commercial and federal software. The Federal Sector unit has achieved a 
Level 5 Capability Maturity Model" rating.

Diebold, Incorporated manufactures self-service products, such as 
automated teller machines, electronic and physical security products, 
and software and integrated systems. In 2002 the company reported 
revenues of $1.9 billion. We visited the company's headquarters in 
North Canton, Ohio, and discussed the process it uses to develop 
software for automated teller systems.

General Motors, the world's largest vehicle manufacturer, designs, 
builds, and markets cars and trucks worldwide. In 2002 the company 
reported total net sales of $186.7 billion. We spoke with 
representatives from the Powertrain Group to discuss the processes used 
to develop and acquire electronic controls.

Motorola GSG provides integrated communications and embedded electronic 
solutions, such as wireless phones, two-way radio products, and 
internet-access products to consumers, network operators, commercial, 
government, and industrial customers. In 2002 the company reported net 
sales of $26.7 billion. We visited its Global Software Group offices in 
Montreal, Canada, and discussed the company's software and product 
development processes. The Global Software Group has achieved a Level 5 
Capability Maturity Model" rating.

NCR offers solutions for data warehousing, retail store automation, and 
financial self-services. In 2002 the company reported sales totaling 
approximately $5.6 billion. We visited the Teradata Data Warehousing 
group office in San Diego, California, and discussed the software 
development process for the company's Teradata database software. The 
Teradata unit has achieved a Level 4 Capability Maturity Model" rating.

Software acquisition covers myriad activities and processes from 
planning and solicitation, to transition, to the support of a developed 
product. In fact, the Software Engineering Institute's Capability 
Maturity Models (CMM)® for software acquisition and development 
delineate more than a dozen different processes of this nature and 
offer principles governing the goals, activities, necessary resources 
and organizations, measurements, and validation of each process. This 
report does not attempt to judge software acquisitions against all of 
those processes. Instead, our scope targets practices in three critical 
management areas we identified as problem areas from our previous work 
on weapon systems acquisitions and through discussions with leading 
companies. We limited our focus to ways to develop an environment that 
encourages continual improvement; improve the management of software 
development processes, including software requirements; and metrics to 
improve overall weapon system acquisition outcomes. In doing so, we 
borrowed criteria from each CMM® that offered a road map for continuous 
improvement in each of those specific areas.

At each of the five companies, we conducted structured interviews with 
representatives to gather uniform and consistent information about the 
practices, processes, and metrics that each company uses to manage 
software development and software acquisition. During meetings with 
representatives, we obtained a detailed description of the practices 
and processes they use to develop software within cost and schedule and 
ensure quality. We also consistently used a structured data collection 
instrument to collect metrics from the companies on their software 
projects. We met with company directors, software engineers, project 
managers, configuration managers, and quality assurance personnel.

Our report highlights several best practices in software development 
and acquisition on the basis of our fieldwork. As such, they are not 
intended to describe all practices or suggest that commercial companies 
are without flaws. Representatives from the commercial companies we 
visited told us that their practices have evolved over many years and 
that they continue to be improved on the basis of lessons learned and 
new ideas and information. This is not to say that the application and 
use of these practices have always been consistent or without error or 
that they subscribe to a single model for their practices and 
processes. However, they strongly suggested that the probability of 
success in developing and acquiring software is greatly enhanced by the 
use of these practices and processes.

We also selected five DOD weapon systems: RAH-66 Comanche, F/A-22, F/
A-18 C/D, SBIRS, and Tactical Tomahawk. These systems are at various 
stages of development. We compared the practices, processes, and 
metrics the programs were using to manage software development and 
acquisition with the best practices commercial companies use. To 
identify the current policy, processes, and acquisition practices used 
in software development, for each program we visited, we conducted 
structured interviews with representatives from the program office and 
prime contractors Boeing Sikorsky for Comanche; Lockheed Martin, 
Marietta, Georgia, for F/A-22; and Lockheed Martin, Boulder, Colorado, 
for SBIRS. We also used a data collection instrument to determine which 
metrics program offices were collecting.

We selected Air Force, Army, and Navy programs because they all manage 
major defense acquisition programs. We also obtained the responses to 
date that the services and MDA have prepared in response to section 804 
of the Bob Stump National Defense Authorization Act for Fiscal Year 
2003. The legislation states that the Secretary of each military 
service and the head of each defense agency that manages a major 
defense acquisition program with a substantial software component shall 
establish a program to improve the software acquisition processes of 
that military service or defense agency. To determine how DOD responded 
to Congress's requirement, we met with DOD officials from the Tri-
Service Assessment Initiative and the Software Intensive Systems Office 
and the staff responsible for developing the process improvement plans 
for the Air Force, Army, Department of the Navy, and MDA. We also met 
with officials from the Office of the Under Secretary of Defense 
(Acquisition, Technology and Logistics) concerning systems engineering 
initiatives and officials from the Office of the Assistant Secretary of 
Defense (Networks and Information Integration) concerning the software 
improvement plans. Because the plans are in varying stages of 
completeness, we did not evaluate to what degree the military services 
and MDA have complied with section 804. To determine whether the 
responses so far would help improve DOD's software acquisition, we 
evaluated the responses on the basis of the information we obtained 
from leading organizations concerning environment, disciplined 
processes, and collection of meaningful metrics.

We conducted our review between March 2003 and February 2004 in 
accordance with generally accepted government auditing standards.

We are sending copies of this report to the Secretary of Defense; the 
Secretaries of the Air Force, Army, and Navy; the Director of the 
Missile Defense Agency; and the Director of the Office of Management 
and Budget. We will also provide copies to others on request. In 
addition, the report will be available at no charge on the GAO Web site 
at http://www.gao.gov.

Please contact me at (202) 512-4841 if you have any questions 
concerning this report. Other key contributors to this report were 
Cheryl Andrew, Beverly Breen, Lily Chin, Ivy Hubler, Carol Mebane, Mike 
Sullivan, Sameena Nooruddin, Marie Penny Ahearn, Madhav Panwar, and 
Randy Zounes.

Signed by: 

Katherine V. Schinasi: 
Director, Acquisition and Sourcing Management:

[End of section]

Appendix I: Comments from the Department of Defense:

OFFICE OF THE UNDER SECRETARY OF DEFENSE:
3000 DEFENSE PENTAGON 
WASHINGTON, DC 20301-3000:

ACQUISITION, TECHNOLOGY AND LOGISTICS:

FEB 20 2004:

Ms. Katherine V. Schinasi:

Director, Acquisition and Sourcing Management 
U.S. General Accounting Office:

Washington, D.C. 20548:

Dear Ms. Schinasi,

The Department of Defense (DoD) offers the following response to the 
GAO draft report, "WEAPONS ACQUISITIONS: Strong Management, Processes, 
and Metrics Needed to Improve Software Acquisition," dated January 29, 
2004, (GAO Code 120215/GAO-04-393).

The draft report provides useful feedback and insight into software 
acquisition areas that require improvement, and in fact is consistent 
with the Department's current efforts to re-vitalize the state of the 
practice across the defense acquisition community. We will take the 
findings from this report into consideration as we continue to monitor 
our software acquisition process improvement activities, and 
continuously improve our acquisition practices. We further agree with 
findings depicting the Department's implementation of the FY03 National 
Defense Authorization Act, Section 804 as progressing in accordance 
with legislated requirements. Specific recommendations relating to 
Section 804 will be applied as further guidance to improvement programs 
within the Department's Component Services and Agencies.

Although we concur with comments and amplifications to the report's 
recommendations, it is important to note that while the specific 
techniques highlighted may improve insight and impose better controls 
over software development, they should not be seen as a panacea. In 
fact, the report plays down significant challenges associated with 
acquisition of complex defense systems by generalizing software 
development across programs. It is important to take into account a 
program's acquisition characteristics (size, complexity, stage of 
development, technology precedent, team makeup, length of service) 
before concluding, as this report does, that the difficulties 
experienced by DoD's complex developmental programs (e.g. F22, 
Comanche) were primarily due to failure to implement software best 
practices of commercial wireless phone manufacturers and database-
software developers.

Detailed comments to specific recommendations made in this report are 
provided at TAB A. Under separate cover, additional technical comments 
have been forwarded to your staff to correct/clarify information in 
selected sections of the report.

Signed by: 

Glenn F. Lamartin: 
Director: 
Defense Systems:

Enclosure: As stated:

GAO DRAFT REPORT - DATED JANUARY 29, 2004 GAO CODE 120215/GAO-04-393:

"WEAPONS ACQUISITIONS: STRONG MANAGEMENT, PROCESSES, AND METRICS NEEDED 
TO IMPROVE SOFTWARE ACQUISITION":

DEPARTMENT OF DEFENSE COMMENTS TO THE RECOMMENDATIONS:

RECOMMENDATION 1: We recommend that DOD document that software 
requirements are achievable based on knowledge obtained from systems 
engineering prior to beginning development and that DOD and the 
contractor have a mutual understanding of the software requirements. 
Further, we recommend that costs and benefits of major changes to 
software requirements are supported by systems engineering analysis. 
(revised recommendation, ref. email from GAO received 4 Feb 04):

DOD RESPONSE: Partial concur. We concur with the recommendation with 
modification of the last sentence to read "Further, we recommend that 
tradeoff analyses be performed, supported by systems engineering 
analysis, considering performance, cost, and schedule impacts of major 
changes to software requirements." This acknowledges that performance, 
schedule and cost impacts, are all considered when evaluating 
requirements changes.

The report supports this recommendation with description of the 
commercial sector's ability to freeze 95 % of their requirements by the 
end of the requirements phase, 98 % by the end of design. The DoD must 
retain some flexibility for rapid development, prototyping and 
experimentation to realize objectives of force transformation. Military 
software functionality and associated requirements are sometimes 
subject to unpredictable and unforeseen perturbations due to changes in 
global capabilities and the attendant need for systems to adapt to such 
changes and technological enhancements.

RECOMMENDATION 2: The GAO recommended that the Secretary of Defense 
ensure that DoD acquisitions are managed to a disciplined process by 
developing a list of software knowledge deliverables based on the 
completion of systems engineering that contractors are required to 
provide at the end of software phases, requirements, design, coding and 
testing. (p. 32/GAO Draft Report):

DOD RESPONSE: Partial concur. We would modify the second recommendation 
with the italicized wording to read "... the Secretary of Defense 
ensure DoD acquisitions are managed to a disciplined process by 
developing a list of systems engineering deliverables (including 
software), tailored to the program characteristics, and based on the 
results of systems engineering activities that software developers are 
required to provide at the appropriate stages of the system development 
phases of requirements, design, fabrication/coding, integration and 
testing".

Deliverables for each development phase are standard in DoD 
acquisition. It is important that these deliverables are timed 
appropriately, tailored to the program's requirements, complexity, and 
risk, and balanced against the cost to deliver them. The DoD is 
currently piloting new processes on several acquisition programs in 
which acquisition oversight is altered in accordance with requisite 
program risk. This risk-balanced acquisition oversight is seeing some 
positive results, and is breaking new ground in rewarding acquisition 
capability improvement while maintaining realistic contractor 
expectations.

We strongly believe that integration should be added as one of the 
development phases. The report's focus is on weapon systems, where 
software development is truly embedded into larger systems.	Integration 
has become one of the most critical activities in system development, 
given its impact and complexity increase with the size and complexity 
of the total system, or system of systems. This includes the 
integration of multiple software modules in development, integration of 
developed software with COTS or existing software, integration of 
hardware and software components, and integration of the software with 
other systems. DoD's move to acquire systems within a capabilities 
context that are interoperable and supportive of network centric 
enterprise services makes integration a key risk area that must be 
managed to achieve success.

RECOMMENDATION 3: The GAO recommended that the Secretary of Defense 
ensure that DoD has the knowledge it needs to oversee software 
intensive acquisitions by requiring software contractors to collect and 
report metrics related to cost, schedule, size, requirements, tests, 
defects, and quality to program offices on a monthly basis and before 
program milestones; require contractors to have an earned value 
management system that reports cost and schedule information at a level 
of work that provides information specific to software development. (p. 
32/GAO Draft Report):

DOD RESPONSE: Partial Concur. We believe the report's third 
recommendation should be modified to read that "...the Secretary of 
Defense ensure that DoD has the knowledge it needs to oversee software 
intensive acquisitions by requiring software developers to collect and 
report metrics related to cost, schedule, size, requirements, tests, 
defects, and quality to program offices in support of program 
decisions. Commensurate with each program's complexity and risk, the 
DoD should also require developers to implement earned value management 
systems to report cost and schedule information specific to software 
development at the configuration item level.

This recommendation increases DoD insight into the developer's 
processes, but the implementation, and associated costs need to be 
balanced with the program's requirements, complexity and level of risk. 
Further, we have seen that obtaining data from the contractor does not 
provide the "knowledge" that DoD requires to oversee software intensive 
acquisition as stated in the recommendation. Experienced and trained 
software acquisition professionals possess the knowledge to oversee a 
software intensive acquisition. Without this, data collected from the 
contractor is irrelevant.

RECOMMENDATION 4: These practices should be included and enforced with 
controls and incentives in DOD's acquisitions policy, software 
acquisition improvement plans and development contracts.

DOD RESPONSE: This final statement in the recommendations section of 
the report discusses establishing control and incentives in policy. The 
Department's policy already addresses these issues as exemplified in 
the following table.

DoD 5000.1, paragraph E1.25; "Software Intensive Systems. Acquisition 
of software intensive systems shall use process improvement and 
performance measures. Selection of sources shall include consideration 
of product maturity and past performance.”  

DoD 5000.1, paragraph 4.3.2; "Responsiveness. Advanced technology 
shall be integrated into producible systems and deployed in. the 
shortest time practicable. Approved, time- phased capability needs 
matched with available technology and resources enable evolutionary 
acquisition strategies. Evolutionary acquisition strategies are the 
preferred approach to satisfying operational needs. Spiral development 
is the referred process for executing such strategies.”  

DoD 5000.1, paragraph 4.3.4; "Discipline. PMs shall manage programs 
consistent with statute and the regulatory requirements specified in 
this Directive and in reference (b). Every PM shall establish program 
goals for the minimum number of cost, schedule, and performance 
parameters that describe the program over its life cycle. Approved 
program baseline parameters shall serve as control objectives. PMs 
shall identify deviations from approved acquisition program baseline 
parameters and exit criteria.”  

DoD 5000.2, paragraph 3.7.2; "Entrance Criteria. Entrance into this 
[SDD] phase depends on technology maturity (including software), 
approved requirements, and funding. Unless some other factor is 
overriding in its impact, the maturity of the technology shall 
determine the path to be followed. Programs that enter the acquisition 
process at Milestone B shall have an. ICD that provides the context in 
which the capability was determined and approved, and a CDD that 
describes specific program requirements.”  

DoD 5000.2, Appendix E, Table E3.T3; Software Resources Data Report. 
All major contracts and subcontracts, regardless of contract type, for 
contractors developing/producing software elements within ACAT I and 
ACAT IA programs for any software development element with a projected 
software effort greater than $25M (FY. 2002 constant dollars). Submit 
data on each software element at the following times: 
-180 days prior to contract award. 
-60 days after contract award. 
-60 days after start of subsequent software releases 
-within 120 days after software release or final delivery. 

[End of table]

The report acknowledges the DoD's actions to incorporate systems 
engineering directives into policy. OSD oversight of service and agency 
implementation of Section 804 will provide additional controls as 
necessary.

The DoD recognizes the importance of good software development 
practices, and has undertaken many successful initiatives that are also 
acknowledged in the report. DoD strongly believes that software success 
is fundamentally dependent upon the greater systems engineering 
success. It is here where our attention, focus, and improvement can 
make the greatest contribution to achieving successful system 
acquisitions.

[End of section]

Appendix II: Software Models:

Software Development:

The Capability Maturity Model for Software (SW-CMM)[Footnote 8]® 
describes the principles and practices underlying software process 
maturity and is intended to help software organizations improve the 
maturity of their software process in terms of an evolutionary path 
organized into five maturity levels. Except for level 1, each maturity 
level is decomposed into several key process areas that indicate the 
areas that an organization should focus on to improve its software 
process. Table 3 describes the characteristics of each level of process 
maturity and the applicable key process areas.

Table 3: Highlights of SW-CMM:

(Continued From Previous Page)

Level: 1 Initial; 
Characteristics: The software process is ad hoc, and occasionally 
chaotic. Few processes are defined, and success depends on individual 
effort; 
Key process areas: [Empty].

Level: 2 Repeatable; 
Characteristics: Basic project management processes are established to 
track cost, schedule, and functionality. The necessary process 
discipline is in place to repeat earlier successes on projects with 
similar applications; 
Key process areas: 
* Requirements Management; 
* Software Project Planning; 
* Software Project Tracking & Oversight; 
* Software Subcontract Management; 
* Software Quality Assurance; 
* Software Configuration Management.

Level: 3 Defined; 
Characteristics: The software process for both management and 
engineering activities is documented, standardized, and integrated 
into a standard software process for the organization. All projects 
use an approved, tailored version of the organization's standard 
software process for developing and maintaining software; 
Key process areas: 
* Organization Process Focus; 
* Organization Process Definition; 
* Training; 
* Integrated Software Management; 
* Software Product Engineering; 
* Intergroup Coordination; 
* Peer Reviews.

Level: 4 Managed; 
Characteristics: Detailed measures of the software process and product 
quality are collected. Both the software process and products are 
quantitatively understood and controlled; 
Key process areas: 
* Quantitative Process Management; 
* Software Quality Management.

Level: 5 Optimizing; 
Characteristics: Continuous process improvement is enabled by 
quantitative feedback from the process and from plotting innovative 
ideas and technologies; 
Key process areas: 
* Defect Prevention; 
* Technology Change Management; 
* Process Change Management. 

Source: Software Engineering Institute, Carnegie Mellon University.

[End of table]

Software Acquisition:

The Software Acquisition Capability Maturity Model (SA-CMM)® is a model 
for benchmarking and improving the software acquisition process. The 
model follows the same architecture as SW-CMM® but with a unique 
emphasis on acquisition issues and the needs of individuals and groups 
who are planning and managing software acquisition efforts. Each 
maturity level indicates an acquisition process capability and has 
several Key Process Areas. Each area has goals and common features and 
organizational practices intended to institutionalize common practice.

Table 4: Highlights of SA-CMM:

Level: 1 Initial; 
Focus: Competent people and heroics; 
Key process areas: [Empty].

Level: 2 Repeatable; 
Focus: Basic Project Management; 
Key process areas: 
* Transition to Support; 
* Evaluation; 
* Contract Tracking and Oversight; 
* Project Management; 
* Requirements Development and Management; 
* Solicitation; 
* Software Acquisition Planning.

Level: 3 Defined; 
Focus: Process Standardization; 
Key process areas: 
* Training Program; 
* Acquisition Risk Management; 
* Contract Performance Management; 
* Project Performance Management; 
* Process Definition and Maintenance.

Level: 4 Quantitative; 
Focus: Quantitative Management; 
Key process areas: 
* Quantitative Acquisition Management; 
* Quantitative Process Management.

Level: 5 Optimizing; 
Focus: Continuous Process Improvement; 
Key process areas: 
* Acquisition Innovation Management; 
* Continuous Process Improvement.

Source: Software Engineering Institute, Carnegie Mellon University.

[End of table]

Integrated Model:

In 1997 a team led by DOD, in conjunction with Software Engineering 
Institute, government, and industry, concentrated on developing an 
integrated framework for maturity models and associated products. The 
result was the Capability Maturity Model Integration (CMMI)®,[Footnote 
9] which is intended to provide guidance for improving an 
organization's processes and the ability to manage the development, 
acquisition, and maintenance of products and services while reducing 
the redundancy and inconsistency caused by using stand-alone models. 
CMMI® combines earlier models from Software Engineering Institute and 
the Electronic Industries Alliance into a single model for use by 
organizations pursuing enterprise-wide process improvement. 
Ultimately, CMMI® is to replace the models that have been its starting 
point.

Many integrated models consist of disciplines selected according to 
individual business needs. Models can include systems engineering, 
software engineering, integrated product and process development, and 
supplier sourcing. There are also two representations of each CMMI® 
model: staged and continuous. A representation reflects the 
organization, use, and presentation of model elements. Table 5 shows 
the CMMI® model for staged groupings.

Table 5: Highlights of CMMI Model:

Staged grouping: Maturity Level 2; 
Process area: 
* Requirements Management; 
* Project Planning; 
* Project Monitoring and Control; 
* Supplier Agreement Management; 
* Measurement and Analysis; 
* Process and Product Quality Assurance; 
* Configuration Management.

Staged grouping: Maturity Level 3; 
Process area: 
* Requirements Development; 
* Technical Solution; 
* Product Integration; 
* Verification; 
* Validation; 
* Organizational Process Focus; 
* Organizational Process Definition; 
* Organizational Training; 
* Integrated Project Management; 
* Risk Management; 
* Integrated Teaming; 
* Integrated Supplier Management; 
* Decision Analysis and Resolution; 
* Organizational Environment for Integration.

Staged grouping: Maturity Level 4; 
Process area: 
* Organizational Process Performance; 
* Quantitative Project Management.

Staged grouping: Maturity Level 5; 
Process area: 
* Organizational Innovation and Deployment; 
* Causal Analysis and Resolution. 

Source: Software Engineering Institute, Carnegie Mellon University.

[End of table]

[End of section]

Appendix III: Section 804. Improvement of Software Acquisition 
Processes:

Establishment of Programs: 

(1) The Secretary of each military department shall establish a program 
to improve the software acquisition processes of that military 
department.

(2) The head of each Defense Agency that manages a major defense 
acquisition program with a substantial software component shall 
establish a program to improve the software acquisition processes of 
that Defense Agency. (3) The programs required by this subsection shall 
be established not later than 120 days after the date of the enactment 
of this Act.

(b) Program Requirements.--A program to improve software acquisition 
processes under this section shall, at a minimum, include the 
following:

(1) A documented process for software acquisition planning, 
requirements development and management, project management and 
oversight, and risk management. (2) Efforts to develop appropriate 
metrics for performance measurement and continual process improvement. 
(3) A process to ensure that key program personnel have an appropriate 
level of experience or training in software acquisition. (4) A process 
to ensure that each military department and Defense Agency implements 
and adheres to established processes and requirements relating to the 
acquisition of software.

(c) Department of Defense Guidance--The Assistant Secretary of Defense 
for Command, Control, Communications, and Intelligence, in consultation 
with the Under Secretary of Defense for Acquisition, Technology, and 
Logistics, shall:

(1) prescribe uniformly applicable guidance for the administration of 
all of the programs established under subsection (a) and take such 
actions as are necessary to ensure that the military departments and 
Defense Agencies comply with the guidance; and (2) assist the 
Secretaries of the military departments and the heads of the Defense 
Agencies to carry out such programs effectively by:

(A) ensuring that the criteria applicable to the selection of sources 
provides added emphasis on past performance of potential sources, as 
well as on the maturity of the software products offered by the 
potential sources; and (B) identifying, and serving as a clearinghouse 
for information regarding, best practices in software development and 
acquisition in both the public and private sectors.

(d) Definitions--In this section:

(1) The term "Defense Agency" has the meaning given the term in section 
101(a)(11) of title 10, United States Code. (2) The term "major defense 
acquisition program" has the meaning given such term in section 
139(a)(2)(B) of title 10, United States Code.

[End of section]

Related GAO Products:

Defense Acquisitions: DOD's Revised Policy Emphasizes Best 
Practices, but More Controls Are Needed. GAO-04-53. Washington, D.C.: 
November 10, 2003.

Best Practices: Setting Requirements Differently Could Reduce 
Weapon Systems' Total Ownership Costs. GAO-03-57. Washington, D.C.: 
February 11, 2003.

Best Practices: Capturing Design and Manufacturing Knowledge 
Early Improves Acquisition Outcomes. GAO-02-701. Washington, D.C.: 
July 15, 2002.

Defense Acquisitions: DOD Faces Challenges in Implementing Best 
Practices. GAO-02-469T. Washington, D.C.: February 27, 2002.

DOD Information Technology: Software and Systems Process Improvement 
Programs Vary in Use of Best Practices. GAO-01-116. Washington, D.C.: 
March 30, 2001.

Best Practices: Better Matching of Needs and Resources Will Lead 
to Better Weapon System Outcomes. GAO-01-288. Washington, D.C.: 
March 8, 2001.

Best Practices: A More Constructive Test Approach Is Key to 
Better Weapon System Outcomes. GAO/NSIAD-00-199. Washington, D.C.: 
July 31, 2000.

Defense Acquisition: Employing Best Practices Can Shape Better Weapon 
System Decisions. GAO/T-NSIAD-00-137. Washington, D.C.: April 26, 
2000.

Best Practices: DOD Training Can Do More to Help Weapon System Program 
Implement Best Practices. GAO/NSIAD-99-206. Washington, D.C.: August 
16, 1999.

Best Practices: Better Management of Technology Development Can Improve 
Weapon System Outcomes. GAO/NSIAD-99-162. Washington, D.C.: July 30, 
1999.

Defense Acquisitions: Best Commercial Practices Can Improve Program 
Outcomes. GAO/T-NSIAD-99-116. Washington, D.C.: March 17, 1999.

Defense Acquisition: Improved Program Outcomes Are Possible. GAO/T-
NSIAD-98-123. Washington, D.C.: March 17, 1998.

Best Practices: DOD Can Help Suppliers Contribute More to Weapon System 
Programs. GAO/NSIAD-98-87. Washington, D.C.: March 17, 1998.

Best Practices: Successful Application to Weapon Acquisition Requires 
Changes in DOD's Environment. GAO/NSIAD-98-56. Washington, D.C.: 
February 24, 1998.

Best Practices: Commercial Quality Assurance Practices Offer 
Improvements for DOD. GAO/NSIAD-96-162. Washington, D.C.: 
August 26, 1996.

FOOTNOTES

[1] See U.S. General Accounting Office, DOD Information Technology: 
Software and Systems Process Improvement Programs Vary in Use of Best 
Practices, GAO-01-116 (Washington, D.C.: Mar. 30, 2001). 
Recommendations contained in this report also called for specific 
components to consider basing their improvement programs on the 
Software Engineering Institute's IDEAL SM model. (IDEAL is a service 
mark of Carnegie Mellon University.)

[2] Bob Stump National Defense Authorization Act for Fiscal Year 2003, 
Pub. L. No. 107-314, sec. 804, Dec. 2, 2002. The text is in appendix 
III.

[3] Report of the Defense Science Board Task Force on Defense Software, 
Office of the Undersecretary of Defense, Acquisition and Technology, 
November 2000.

[4] Capability Maturity Model is registered in the U.S. Patent and 
Trademark Office by Carnegie Mellon University.

[5] U.S. General Accounting Office, Air Force F-22 Embedded Computers, 
GAO/AIMD-94-177R (Washington, D.C.: Sept. 23, 1994).

[6] A computer software configuration item is a software program that 
performs a common end-use function, follows its own development cycle, 
and is individually managed.

[7] DOD Directive 5000.1, The Defense Acquisition System, describes the 
management principles for DODís acquisition programs DOD Instruction 
5000.2, The Operation of the Defense Acquisition System, outlines a 
framework for managing acquisition programs. Collectively, these are 
known as the 5000 series. Chairman of the Joint Chiefs of Staff 
Instruction 3170.01C describes requirements generation policies and 
procedures of the Joint Capabilities Integration and Development 
System.

[8] CMM is registered in the U.S. Patent and Trademark Office by 
Carnegie Mellon University.

[9] CMMI is registered with the U.S. Patent and Trademark Office by 
Carnegie Mellon University.

GAO's Mission:

The General Accounting Office, the investigative arm of Congress, 
exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability.

Obtaining Copies of GAO Reports and Testimony:

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics.

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading.

Order by Mail or Phone:

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to:

U.S. General Accounting Office

441 G Street NW,

Room LM Washington,

D.C. 20548:

To order by Phone: 	

	Voice: (202) 512-6000:

	TDD: (202) 512-2537:

	Fax: (202) 512-6061:

To Report Fraud, Waste, and Abuse in Federal Programs:

Contact:

Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov

Automated answering system: (800) 424-5454 or (202) 512-7470: