This is the accessible text file for GAO report number GAO-03-100 
entitled 'Major Management Challenges and Program Risks: Department of 
Energy' which was released on January 01, 2003.



This text file was formatted by the U.S. General Accounting Office 

(GAO) to be accessible to users with visual impairments, as part of a 

longer term project to improve GAO products’ accessibility. Every 

attempt has been made to maintain the structural and data integrity of 

the original printed product. Accessibility features, such as text 

descriptions of tables, consecutively numbered footnotes placed at the 

end of the file, and the text of agency comment letters, are provided 

but may not exactly duplicate the presentation or format of the printed 

version. The portable document format (PDF) file is an exact electronic 

replica of the printed version. We welcome your feedback. Please E-mail 

your comments regarding the contents or accessibility features of this 

document to Webmaster@gao.gov.



Performance and Accountability Series:



January 2003:



Major Management Challenges and Program Risks:



Department of Energy:



GAO-03-100:



A Glance at the Agency Covered in This Report:



The Department of Energy is a multibillion-dollar enterprise with 

multiple, 

diverse missions, including:



* fostering secure and reliable energy systems that are environmentally 

and economically sustainable,



* providing stewardship for the nation’s nuclear weapons and nuclear 

material,



* cleaning up the environment to eliminate the legacy of early nuclear 

weapons development activities, and



* supporting U. S. leadership in energy- related science and 
technology. 



To carry out these missions, the department has more than 50 major 

facilities 

in 35 states, including national laboratories, nuclear weapons 

production 

facilities, and facilities undergoing environmental cleanup.



Figure: The Department of Energy’s Budgetary and Staff Resources:



[See PDF for image]



[End of figure]



This Series:



This report is part of a special GAO series, first issued in 1999 

and updated 

in 2001, entitled the Performance and Accountability Series: Major 

Management 

Challenges and Program Risks. The 2003 Performance and Accountability 

Series 

contains separate reports covering each cabinet department, most 

major 

independent agencies, and the U. S. Postal Service. The series also 

includes 

a governmentwide perspective on transforming the way the government 

does 

business in order to meet 21st century challenges and address long- 

term fiscal 

needs. The companion 2003 High- Risk Series: An Update identifies 

areas at high 

risk due to either their greater vulnerabilities to waste, fraud, 

abuse, and 

mismanagement or major challenges associated with their economy, 

efficiency, 

or effectiveness. A list of all of the reports in this series is 

included at 

the end of this report.



GAO Highlights:



Highlights of GAO-03-100, a report to Congress included as part 

of GAO’s 

Performance and Accountability Series:



January 2003:



Performance and Accountability Series: Department of Energy:



Why GAO Did This Report:



In its 2001 performance and accountability report on the U.S. 
Department 

of Energy (DOE), GAO identified important issues facing the department 
as 

it works to carry out its multiple, complex, and highly diverse 
missions. 

The information GAO presents in this report is intended to help to 
sustain 

congressional attention on these challenges and a departmental focus on 

continuing to make progress in addressing these challenges and 
ultimately 

overcoming them. The report should help improve government for the 
benefit 

of the American public.  This report is part of a special series of 

governmentwide and agency-specific issues.



What GAO Found:



DOE has taken steps to address the specific performance and management 

challenges that we previously identified. However, each of these 
challenges 

requires more work and vigilance to be overcome. In addition, the 
agency must 

face emerging challenges to meet the nation’s energy needs and upgrade 
DOE’s 

deteriorating infrastructure.



* Address security threats and problems. DOE has upgraded its physical, 

cyber and document security. However, the terrorist attacks of 
September 11, 

2001, changed the threat that DOE had planned for and will likely 
require new 

security measures and additional resources.



* Improve management of the nation’s nuclear weapons stockpile. NNSA, 
an 

agency within DOE, continues to develop its new planning, programming, 
and 

budgeting system and redesign its organization. However, both 
activities are 

far from complete and will need continued executive leadership to 
ensure that 

these major changes are effectively implemented. 



* Resolve problems in contract management that place DOE at high risk 
for 

fraud, waste, and abuse.  DOE has made progress in implementing 
contract 

reforms by using alternative contract types, competing more contracts, 
and 

using performance-based requirements. However, it is unclear whether 
these 

reforms have improved contractor performance. To better ensure the 

effectiveness of its initiatives, DOE must establish clear goals, 
results-

oriented outcome measures, and performance data.   



* Improve management for cleanup of DOE radioactive and hazardous 
wastes. 

DOE’s environmental management program has begun initiatives to improve 

contract management, streamline business practices, and increase the 
technical 

expertise of DOE staff. However, continued management leadership is 
needed 

to ensure that these initiatives are implemented in a safe manner to 
accomplish 

program goals of accelerating risk reduction and reducing overall 
cleanup costs.

  

* Enhance DOE leadership in meeting the nation’s energy needs. Our 
nation’s 

energy supply system is under stress and is a potential terrorist 
target. 

Enhanced DOE leadership is needed to research new energy technologies, 
help 

develop a competitive electricity generation system, and reduce the 

vulnerability of the U.S. economy to supply disruptions of petroleum.  



* Revitalize DOE’s infrastructure. DOE has a new program to spend 
billions 

of dollars to upgrade its production facilities, research and 
development 

laboratories, and other infrastructure. DOE needs to ensure that these 

major projects are managed effectively and efficiently.  



What Remains to Be Done:



GAO believes that DOE should:



* Continue its focus on security upgrades needed for meeting new 
terrorist 

threats.



* Ensure that the National Nuclear Security Agency (NNSA) continues 
progress 

with its major operational and organizational reforms.



* Establish results-oriented performance data to determine if 
contractor 

performance has improved.



* Complete initiatives to accelerate cleanup and reduce costs.



* Enhance efforts to ensure a stable, reliable energy supply.



* Manage infrastructure upgrade projects effectively.



To view the full report, click on the link above.

For more information, contact Robert A. Robinson, at 202-512-3841, or 

robinsonr@gao.gov.



Contents:



Transmittal Letter:



Major Performance and Accountability Challenges:



GAO Contacts:



Related GAO Products:



Performance and Accountability and High-Risk Series:



This is a work of the U.S. Government and is not subject to copyright 

protection in the United States. It may be reproduced and distributed 

in its entirety without further permission from GAO. It may contain 

copyrighted graphics, images or other materials. Permission from the 

copyright holder may be necessary should you wish to reproduce 

copyrighted materials separately from GAO’s product.



Transmittal Letter:



January 2003:



The President of the Senate

The Speaker of the House of Representatives:



This report addresses the major management challenges facing the U.S. 

Department of Energy (DOE) as it works to carry out its multiple and 

highly diverse missions. These missions include maintaining nuclear 

weapons, fostering a reliable energy supply, cleaning up environmental 

contamination from prior weapons activities, and promoting U.S. 

leadership in science. It is part of a special series entitled the 

Performance and Accountability Series: Major Management Challenges and 

Program Risks, which GAO has issued biennially since January 1999.



This report discusses the actions that DOE has taken or are under way 

to address the challenges GAO reported in its series 2 years ago, in 

January 2001, and major events that have occurred that significantly 

influence the environment in which the department carries out its 

mission. Also, GAO summarizes the challenges that remain and new ones 

that have emerged.



This analysis should help the new Congress and the administration carry 

out their responsibilities and improve government for the benefit of 

the American people. For additional information about this report, 

please contact Robert A. Robinson, Managing Director, Natural Resources 

and Environment, at (202) 512-3841 or at robinsonr@gao.gov.



David M. Walker

Comptroller General

of the United States:



Signed by David M. Walker:



[End of section]



Major Performance and Accountability Challenges:



The Department of Energy’s (DOE) diverse missions of maintaining the 

nation’s nuclear weapons stockpile, fostering a reliable and 

sustainable energy supply for the nation, cleaning up contamination 

from prior weapons activities, and promoting leadership in science are 

not only technically difficult and complex but also, in many cases, 

politically sensitive. In our 2001 report on management challenges and 

program risks we identified six areas, or challenges, that warranted 

the attention of DOE’s management. These issues were related to 

addressing security concerns, maintaining the nuclear weapons 

stockpile, improving contract management, cleaning up radioactive and 

hazardous wastes, achieving nonproliferation goals, and improving 

financial management. In that report we pointed out that many of those 

challenges are long-standing and that sustained management attention 

will be needed to correct the underlying weaknesses and implement 

needed improvements. We also pointed out that DOE has undertaken 

corrective action in all these areas, but because of the nature and 

difficulty of the challenges, achieving lasting improvements may take 

several years.



Over the past 2 years, two events--the terrorist attacks of September 

11, 2001, and energy shortages in several western states--have further 

complicated DOE’s missions. DOE could be an appealing target for 

terrorist groups because of its role in maintaining the nation’s 

nuclear weapons stockpile and handling vast quantities of radioactive 

and hazardous materials. Heightened security will be needed at DOE 

facilities. DOE may also have to develop new security measures. 

Similarly, energy shortages have underscored the vulnerability of our 

energy supplies and raised questions about our almost exclusive 

reliance on petroleum in some sectors. A stable and reliable energy 

supply is critical for consumers, the U.S. economy, and our national 

security. DOE must address the ramifications of these events on its 

programs, in addition to addressing its ongoing management challenges 

and program risks.



DOE continues to be an agency with multiple challenges. In this year’s 

report we identify six areas where DOE’s management attention is 

needed. Four of the areas are continued from 2001. These include 

addressing security concerns, managing the nuclear weapons stockpile, 

improving contract management, and cleaning up radioactive and 

hazardous wastes. For the most part these were continued because of the 

difficult nature of the challenge itself or because new issues arose 

within the challenge. In the case of contract management, for example, 

corrective action will take many years to be fully realized. In the 

case of DOE security, the September 11 attacks raised new major 

security concerns for DOE to address. In addition, we are adding two 

new management challenges. One relates to meeting the nation’s energy 

needs and reducing our dependence on foreign oil. DOE can provide 

enhanced leadership in addressing this key national issue. The other 

relates to revitalizing DOE’s infrastructure, which is in poor 

condition or reaching the end of its design life. DOE’s performance in 

addressing these challenges will significantly affect its ability to 

efficiently and effectively carry out its missions. Two management 

challenges from 2001 were dropped. Financial management was dropped 

because, among other things, DOE had no material internal control 

weaknesses and received a clean opinion on its financial statements for 

fiscal year 2001. Achieving nonproliferation goals was dropped because 

of improvement DOE made to obtain better access to facilities and 

information in Russia, verify the use of program funds, and better 

coordinate DOE’s nonproliferation programs.



Performance and Accountability Challenges:



Figure: Performance and Accountability Challenges:



[See PDF for image]



[End of figure]



Address Security Threats And Problems:



The terrorist attacks of September 11, 2001, brought into sharp focus 

the necessity for all federal agencies to take threats to their 

facilities seriously. For DOE and the National Nuclear Security 

Administration (NNSA), a separately organized agency within DOE, the 

threats have taken on added importance.[Footnote 1] DOE and NNSA 

facilities could be appealing targets to terrorist groups because of, 

among other things, their role in maintaining the nuclear weapons 

stockpile and handling vast quantities of radioactive and hazardous 

materials. Addressing this threat will likely require developing new 

security measures and committing significant additional resources. DOE 

must address this new challenge while addressing existing security 

problems that, in some instances, have plagued the department for many 

years. Further, DOE must balance security issues and cooperative 

scientific research with a variety of foreign countries.



As a result of the scope and magnitude of the September 11 attacks, DOE 

and NNSA undertook a number of short-term efforts to improve security. 

Immediately following the attacks, NNSA facilities instituted a 

heightened state of alert in accordance with DOE orders. In conjunction 

with this alert, security measures were enhanced to include additional 

barriers and access controls, increased vehicle searches, and increased 

patrols of perimeters and critical facilities. In addition, emergency 

operations centers at DOE headquarters and the field were staffed. 

Threat information on foreign intelligence activities was also 

distributed to field personnel. These activities increased DOE’s 

security costs by many millions of dollars.



Figure 1: Adding Concrete Barriers That Secure an NNSA Storage Vault:



[See PDF for image]



[End of figure]



DOE and NNSA also began several long-term activities to strengthen 

their overall security structure and program. Each NNSA facility was 

evaluated against various criteria including the possibility of nuclear 

detonation; radiological dispersion; and loss of program capability, 

technical staff, and life. Also, each site was asked to identify 

vulnerabilities and the projected cost of correcting them. From this 

work, NNSA compiled a prioritized list of needed security improvements. 

Work was also initiated to revise a key DOE security document called 

the Design Basis Threat. The Design Basis Threat describes the most 

credible and serious potential adversaries DOE facilities are likely to 

face. Revisions to this document could have significant consequences 

because it could change the security philosophy at DOE and NNSA sites. 

Finally, DOE and NNSA reviewed the security and assessed the 

vulnerability at each site, assessed nuclear materials management 

practices, and reviewed personnel security and transportation security. 

The results of these activities may, in the longer term, fundamentally 

change security at DOE and NNSA sites.



All of these efforts to respond to the September 11 attacks must be 

coordinated with efforts to address previously identified security 

weaknesses. Over the last several years, DOE began more than 70 

initiatives to improve security. In a March 2002 report we pointed out 

that many initiatives have been successfully implemented.[Footnote 2] 

These initiatives have eliminated the backlog of security clearance 

investigations and reinvestigations, strengthened controls over cyber 

security, and upgraded the counterintelligence program. However, we 

also pointed out that several initiatives are still in progress and 

some may take years to implement fully. In addition, during the last 

couple of years, other security problems or concerns have arisen.



In the March 2002 report we pointed out, among other things, that NNSA, 

which was created in March 2000 in part to improve security, still did 

not have a fully operational structure. The lines of authority from 

headquarters through NNSA field offices to the contractors for security 

oversight had not been clearly laid out. Also, there was still some 

confusion about the roles and authorities of DOE and NNSA security 

offices. Some contractor and NNSA field staff told us they had received 

differing guidance from DOE and from NNSA security offices and were 

uncertain about which to follow. A report by the Center for Strategic 

and International Studies,[Footnote 3] dated April 2002, found similar 

problems and recommended that DOE/NNSA clarify lines of responsibility 

and authority for security. In particular, the study wanted a more 

clearly defined chain of command. In December 2002, NNSA announced its 

plans for implementing a new organizational structure, which it expects 

to have in place in 2004.



In the information security area, we pointed out in an August 2001 

report that while DOE laboratories have taken steps to improve control 

over their classified information, DOE could make further 

improvements.[Footnote 4] DOE’s requirements for documenting when 

someone needs to know specific classified information lack specificity, 

allowing laboratory managers wide discretion in interpretation and 

implementation. Some managers provided long-term blanket approvals to 

hundreds of staff for all classified information in a vault or computer 

system. We also found that recent revisions to DOE’s Classified Matter 

Protection and Control Manual did not include some security 

requirements that were in place prior to 1998. For example, the revised 

manual did not require approving reproduction of top-secret documents 

and maintaining an access list for each top-secret document.



The cyber security area is another area where DOE has initiated 

upgrades, but more improvements are warranted. The previously mentioned 

report by the Center for Strategic and International Studies made a 

number of recommendations to DOE to improve its cyber security. These 

included placing a higher priority on the timely implementation of 

cyber security solutions that are already developed and doing more to 

evaluate emerging technologies that are being developed by other 

agencies and by the private sector. DOE’s Inspector General pointed out 

in an August 2001 report[Footnote 5] that while DOE had made 

improvements in its unclassified cyber security program, the program 

did not adequately protect data and information systems as required by 

the Government Information Security Reform Act. It found problems in 

DOE’s contingency planning, computer incident reporting, and training. 

According to the report, these weaknesses and others increased the risk 

that critical systems could be compromised or disabled by malicious or 

unauthorized users.



Another area of particular concern to DOE is physical security, 

especially since September 11. In our aforementioned March 2002 report 

we found that there was some confusion over who in DOE was responsible 

for accelerating upgrades to physical security. In a December 2001 

report,[Footnote 6] DOE’s Inspector General pointed out that 

improvements are needed at Lawrence Livermore National Laboratory for 

the site to comply with its overall security plan, protect certain 

types of nuclear material, and provide clearer guidance for site 

protective-force operations. Another DOE Inspector General 

report,[Footnote 7] dated March 2002, found that because of problems 

with DOE’s clearance and badging controls, an unauthorized individual 

could gain access to department headquarters.



New initiatives are likely to result from ongoing security evaluations 

initiated in response to the September 11 attacks. As a result, 

additional improvements are likely. However, our past work has shown 

that DOE has had difficulty making lasting security improvements, and 

security problems have recurred. In our view, this difficulty is in 

part due to DOE’s culture, because, in some instances, there has been a 

pattern of behavior where security is a secondary priority. Changing 

this culture, which has developed over decades, will require sustained 

management attention. Such attention will be needed to ensure that 

security improvements are effectively and consistently built into DOE’s 

culture as it evolves to meet new management challenges.



Improve Management of the Nation’s Nuclear Weapons Stockpile:



NNSA spends more than $5.5 billion per year to maintain the safety and 

reliability of the nation’s nuclear weapons stockpile through the 

Stockpile Stewardship Program.[Footnote 8] NNSA was created to correct 

long-standing and widely recognized management problems at DOE. NNSA 

has made progress in developing a planning, programming, and budgeting 

system and in clarifying its organization. However, NNSA needs to do 

more to have the effective and efficient management structure necessary 

for accomplishing its mission.



Numerous studies have identified problems with DOE’s planning, 

programming, and budgeting, which NNSA inherited. The problems include 

the lack of a unified planning and programming process, the absence of 

integrated long-range program plans, and the failure to fully link 

existing plans to budgets and management controls. Without a sound, 

integrated planning, programming, and budgeting process, it has been 

difficult for officials to ensure that decisions with resource 

implications are weighed against one another completely and 

consistently. In our December 2000 report on the management of the 

Stockpile Stewardship Program, we recommended that NNSA take action to 

improve and integrate its planning processes and budgetary data to 

provide information needed to manage this highly complex 

program.[Footnote 9] Overall, DOE agreed with these recommendations.



In response to our report and recommendations, NNSA’s Administrator 

changed NNSA’s planning, programming, and budgeting process by 

instituting a process similar to that used by the Department of 

Defense. The Administrator originally set a goal of having fully 

established NNSA’s version of the Department of Defense’s process--

referred to by NNSA as the Planning, Programming, Budgeting, and 

Evaluation process--by the fiscal year 2003 budget cycle. Subsequently, 

this date was pushed back to the fiscal year 2004 budget cycle because 

development was taking longer than expected.



As we reported in December 2001 and again in February 2002, while NNSA 

has made some progress in implementing some elements of the planning 

phase of the Planning, Programming, Budgeting, and Evaluation process 

for the fiscal year 2004 budget cycle, work on the other phases of the 

process has gone much more slowly. For example, NNSA has not finalized 

how the programming and evaluation phases of the process will work. 

NNSA is also just beginning to develop the automated systems needed to 

support its process. In addition, except for budgeting personnel, NNSA 

does not have sufficient personnel with the skills to conduct the 

analytical functions typically associated with the multiple phases of 

the Planning, Programming, Budgeting, and Evaluation process.



NNSA may face additional hurdles as it implements its Planning, 

Programming, Budgeting, and Evaluation process for the fiscal year 2004 

budget cycle. Rather than function as the fully implemented system 

envisioned by the Administrator for the fiscal year 2004 cycle, NNSA’s 

Planning, Programming, Budgeting, and Evaluation process should be 

considered a prototype that will likely have to be refined and 

developed in future years. Furthermore, it is too soon to tell whether 

the proposed process, when fully implemented, will effectively address 

widely recognized problems in NNSA’ s existing planning, programming, 

and budgeting practices and whether the process will include effective 

evaluation procedures.



With respect to organization, the Congress established NNSA, in part, 

to correct confused lines of authority and responsibility within the 

nuclear weapons complex that had contributed to a wide variety of 

problems, such as cost overruns and schedule slippages. In February 

2002, after several delays and almost 2 years after its creation, NNSA 

announced a new organizational structure that represents a significant 

step toward addressing important, long-standing organizational 

problems by removing excess management layers, streamlining and 

clarifying the relationship between NNSA’s headquarters offices and its 

field structure, and potentially holding federal and contractor staff 

more accountable.



However, NNSA’s reorganization is far from complete. As we noted in our 

February 2002 testimony on NNSA’s proposed plans, NNSA’s proposal did 

not address several key, long-standing organizational problems. For 

example, NNSA’s proposal did not address the fact that the nuclear 

weapons science function and nuclear weapons production function are 

managed separately, although their work must be closely coordinated to 

achieve mission goals. As we noted in our aforementioned December 2000 

report on the management of the Stockpile Stewardship Program, this 

split adversely affects coordination within the nuclear weapons 

complex. More recently, in December 2002, NNSA announced its plans for 

implementing its new organizational structure. While NNSA’s plans 

further clarify how NNSA will implement the structure it announced in 

February 2002, numerous important issues, such as how NNSA will achieve 

the 20 percent federal staff reduction it promises while maintaining 

effective federal oversight, remain to be resolved before September 

2004, when the reorganization is to be fully implemented. As NNSA 

implements its new organization, it is vital that its chains of command 

are enforced and that federal and contractor staff are held 

accountable. Otherwise, NNSA’s reorganization could simply be one more 

in a long line of missed opportunities. Underpinning NNSA’s efforts to 

improve the management of the Stockpile Stewardship Program is the need 

to address its human capital challenges. Numerous studies have pointed 

out the need to deal comprehensively with the challenge of recruiting 

and training the next generation of technical and managerial staff 

before the end of this decade. However, as we pointed out in our 

December 2001 report on NNSA’s implementation efforts, NNSA still 

lacked a long-term strategic approach that can ensure a well-managed 

workforce. While NNSA managers agreed that a strategic approach was 

needed, no timetable for developing one existed because NNSA managers 

were waiting for the outcome of NNSA’s reorganization process.



Finally, because the United States is no longer designing and building 

nuclear weapons, extending the life of each of the nine weapon types in 

the current stockpile is a key component of the Stockpile Stewardship 

Program. To fully understand the cost of these life extension projects, 

the Conference Report on the Energy and Water Development Appropriation 

Act for Fiscal Year 2002 (P.L. 107-66) directed NNSA to develop a 

series of cost reports known as Nuclear Weapon Acquisition Reports. In 

our July 2002 report we reviewed the Nuclear Weapon Acquisition Reports 

and found that while they represented a good beginning, additional 

information, such as the cost of associated research and development, 

was needed to make them a more effective project management tool for 

NNSA and the Congress.[Footnote 10] We made recommendations, which NNSA 

agreed with in part, to improve the quality and usefulness of the 

Nuclear Weapon Acquisition Reports.



Resolve Problems in Contract Management That Place DOE at High Risk for 

Fraud, Waste, and Abuse:



DOE’s contract management represents a significant challenge to the 

department. DOE is the largest civilian contracting agency in the 

federal government. About 90 percent of its annual budget is spent on 

contracts. DOE relies primarily on contractors to carry out its diverse 

missions and to operate its facilities. Since 1990, we have designated 

DOE’s contract management, which we have broadly defined to include 

contract administration and project management, as a high-risk area; we 

maintain that designation in this year’s high-risk report. In our 

January 2001 report on DOE’s major management challenges, we reported 

ongoing problems with the department’s approach to selecting an 

appropriate contract type, using competition to award contracts, 

incorporating performance-based measures into contracts, and 

minimizing cost and schedule overruns on major projects. Although DOE 

has made progress in addressing these problems through contract 

reforms, it is a long-term effort, and many challenges remain.



* With respect to selecting the appropriate contract type, we reported 

in 2002 that DOE has encouraged the use of alternative contract types, 

such as fixed-price contracts, that are tailored to the required work 

and the financial and technical risks associated with that 

work.[Footnote 11] However, the department is still in the process of 

implementing a more systematic approach for determining the best 

contract type for a given situation.



* Regarding efforts to increase competition, DOE has increased the 

proportion of major site contracts awarded competitively to 56 percent 

as of 2001, up from 38 percent as of 1996. All but one of the 11 

contracts that had not been competitively awarded as of 2001 were for 

managing research and development centers, including weapons 

laboratories, that are exempted by statute from mandatory competition. 

DOE has continued to noncompetitively extend most of these contracts, 

including some for contractors that have experienced performance 

problems, such as the University of California contract to manage and 

operate the weapons laboratories at Los Alamos and Livermore. It is 

unclear if DOE can successfully address the performance problems using 

contract mechanisms.



* Regarding the use of performance-based measures in contracts, DOE has 

reported that all of its major site contracts now incorporate 

performance-based concepts to define requirements and measure results. 

In addition, DOE has increased the emphasis on performance-based 

contracting by increasing the percentage of available fee (available 

payment to the contractor) tied to objective performance measures. 

However, developing good performance measures has continued to be a 

challenge for the department. For example, a 2001 DOE Office of 

Inspector General review of performance-based incentive measures at 

three sites concluded that the department did not use performance-based 

measures in a way that would consistently result in improved contractor 

performance.[Footnote 12] DOE acknowledges that it must make further 

progress in this area.



Despite this progress in implementing contract reforms, it is unclear 

whether contractors’ performance has improved. Instead of measuring 

outcome-oriented performance results, DOE has primarily gauged progress 

by measuring its implementation of the contract reform initiatives and 

by reviewing performance measures in individual contracts. Therefore, 

objective performance information on overall results is scarce.



Nevertheless, there are indications that the performance of DOE’s 

contractors may not have improved. For example, DOE continues to have 

difficulty keeping some of its major projects on schedule and within 

budget. In our September 2002 report, we found that in comparing cost 

and schedule performance for ongoing major DOE projects there was no 

significant improvement in performance for similar projects between 

1996 and 2001. In both 1996 and 2001, more than half of the projects 

reviewed had both schedule delays and cost increases. Furthermore, as 

shown in table 1, the proportion of projects experiencing cost growth 

of more than double the initial cost estimates or schedule delays of 5 

years or longer increased during the 6-year period.



Table 1: Comparison of Significant Cost Overruns and Schedule Delays 

for Ongoing Projects in 2001 with Ongoing Projects in 1996:



Number of projects reviewed; Number of projects: 1996: 25[A]; Number of 

projects: 1996: [Empty]; Number of projects: 2001: 16[B]; Number of 

projects: 2001: [Empty].



Projects with a revised cost estimate more than double the initial cost 

estimate; Number of projects: 1996: 7; Number of projects: 1996: (28%); 

Number of projects: 2001: 6; Number of projects: 2001: (38%).



Projects with schedule delays of 5 years or more; Number of projects: 

1996: 8; Number of projects: 1996: (32%); Number of projects: 2001: 6; 

Number of projects: 2001: (38%).



Source: DOE and GAO.



[A] We evaluated 34 projects in 1996 with estimated costs greater than 

$100 million. However, 9 of the projects were environmental restoration 

projects, and DOE’s original and/or current cost estimates did not 

estimate costs through project completion. In 1998, DOE divided these 

environmental restoration projects into multiple projects at each site. 

Therefore, we excluded these projects from our current analysis.



[B] There are 10 additional projects with total project costs greater 

than $200 million, but those projects either have been recently started 

or have been suspended.



[End of table]



Recent cost and schedule overruns include the following:



* DOE’s original 1992 baseline for the Yucca Mountain Site 

Characterization Project, a high-level waste repository, estimated a 

total project cost of $6.3 billion and a completion date for submitting 

the license application of October 2001. According to the department’s 

latest estimate, the license application will not be submitted until 

December 2004, with an estimated cost of almost $8.4 billion. We 

reported in December 2001 that DOE had stopped using the baseline to 

manage the program in March 1997 and instead had been using revised 

estimates that had never been approved and incorporated into the 

official baseline for the project.[Footnote 13] Without developing a 

baseline cost and schedule estimate and using a formal procedure to 

approve cost and schedule changes, DOE cannot ensure that the project 

is being managed effectively.



* The Tritium Extraction Facility, which is being built at DOE’s 

Savannah River Site to produce a radioactive isotope crucial to the 

nation’s nuclear weapons program, was originally scheduled for 

completion by February 2006 at a cost of $401 million. DOE’s Office of 

Inspector General reported in June 2002 that the total project cost 

could increase to as much as $500 million, may not be completed until 

almost a year later than originally scheduled and may not contain all 

elements originally specified.[Footnote 14] The Inspector General found 

that inadequate project management controls resulted in the lack of a 

viable baseline for the project. The report added that, as a result, 

the department lacks assurance that the facility will be available when 

needed or that project funds are being expended efficiently. Delays in 

completing the project could adversely affect the overall performance 

of DOE’s Stockpile Stewardship Program.



* The National Ignition Facility will be a stadium-sized laser facility 

that may, for the first time, simulate in a laboratory the 

thermonuclear conditions created in nuclear explosions. Our August 2000 

report noted that DOE estimates that the facility will cost almost $3.3 

billion and will not be completed until 2008--more than $1 billion and 

6 years later than originally estimated.[Footnote 15] Despite efforts 

by the department to make management improvements, when we revisited 

the National Ignition Facility project in June 2001, we found that DOE 

oversight problems persisted and that they continued to place the 

project at risk.



In an effort to improve cost and schedule performance on major 

projects, DOE began an initiative in 1999 to implement recommendations 

in a National Research Council review[Footnote 16] on improving project 

management. In October 2000, DOE issued a new policy and guidance on 

managing and controlling projects, and in 2001 it established a project 

tracking system that required monthly status reporting on all projects 

with total costs over $5 million. DOE has also, among other things, 

improved front-end planning for projects, required baseline validation 

for every project with a cost over $5 million, instituted an industry 

recognized management system for all projects greater than $20 million, 

and developed a competency-based career ladder for project managers. 

These are promising steps, which could help DOE take corrective action 

on projects in a timely manner. However, improvements may be difficult 

to achieve. For example, in its November 2001 follow-up assessment, the 

National Research Council found that change had been inordinately slow, 

and the Council found no evidence that DOE’s project management 

practice and performance in the field had actually improved.[Footnote 

17]



To better ensure the effectiveness of initiatives such as contract 

reform, we recommended in our September 2002 report that DOE 

incorporate the best management practices common in high-performing 

organizations. Such an approach would help ensure that DOE sets clearly 

defined goals, establishes results-oriented outcome measures, develops 

results-oriented performance data to evaluate the effectiveness of its 

initiatives, and takes corrective actions as needed. DOE has agreed to 

implement this recommendation.



DOE’s ability to resolve problems with contract and project management 

may also be affected by human capital concerns. In past reviews of 

major DOE projects such as the National Ignition Facility and in our 

January 2001 report on DOE’s major management challenges, we have cited 

inadequate oversight of contractors’ activities as a factor in poor 

performance on these projects. Furthermore, DOE faces the same human 

capital challenges that exist governmentwide--an aging workforce whose 

retirements over the next decade will severely deplete the knowledge 

and skills required to support DOE’s missions. DOE has efforts under 

way to address skill gaps in its procurement and project management 

organizations and to develop the necessary technical and managerial 

expertise for adequate oversight of its contractors through training 

and certification programs.



Effective contract and project management are vital for DOE because the 

department relies heavily on contractors to achieve its national 

security, research, and environmental cleanup missions. Over the long 

term, DOE may resolve all of the challenges in its contract management 

and become a more effective department. Until then, DOE’s ongoing 

challenges in contract management can increase costs and expose the 

government to billions of dollars in financial risks.



Improve Management for Cleanup of DOE Radioactive and Hazardous Wastes:



DOE continues to face challenges in cleaning up the many DOE facilities 

and sites that were contaminated with radioactive and hazardous wastes 

during more than 50 years of nuclear weapons research and 

production.[Footnote 18] Although DOE has reported completing cleanups 

at 74 of its 114 sites, some of the most complex and costly cleanup 

work remains to be done. For example, DOE must develop and implement 

new technologies to retrieve from aging storage tanks, process, and 

package millions of gallons of high-level radioactive wastes for long-

term storage or disposal. At one site alone this is expected to cost 

over $50 billion.



Figure 2: Waste Storage Tank Under Construction at DOE’s Hanford Site, 

September 1947:



[See PDF for image]



[End of figure]



DOE has estimated that the total cost of cleaning up its sites will 

exceed $220 billion (an increase of over $70 billion in just 4 years) 

and take more than 70 years to complete.[Footnote 19] However, only 

about one-third of the environmental management budget is going toward 

actual cleanup activities and risk-reduction work. The remainder is 

spent on maintenance, fixed costs, and other activities required to 

support safety and security.



In February 2002, recognizing that since the program’s inception in 

1989 more than $60 billion has been spent without a corresponding 

reduction in actual risk, DOE’s Assistant Secretary for Environmental 

Management reported the results of a “top to bottom review” of the 

environmental management program and its management systems.[Footnote 

20] The report concluded that DOE’s financial liability under current 

cleanup plans would continue to grow well beyond the estimated $220 

billion if significant changes to the program were not made. The report 

also stated that without higher performance standards and breakthrough 

business processes, cost growth and schedule delays will continue to 

obstruct cleanup, and the risk to workers, the public, and the 

environment will not be reduced.



The report recommended a series of initiatives to address the problems 

identified in the February 2002 review. These include developing an 

accelerated, risk-based cleanup strategy; improving contract 

management and establishing more meaningful performance measures for 

contractors; improving project management; and streamlining business 

practices. In addition, the report recommended implementing an 

effective human capital strategy to increase the technical expertise of 

DOE staff and improve accountability for results. Through these and 

other initiatives, DOE hopes to rapidly reduce environmental risk to 

workers and the public, shorten the overall cleanup time frame of 70 

years by at least 30 years, and reduce overall cleanup costs by tens of 

billions of dollars. DOE is in the process of developing the specific 

steps to carry out these initiatives safely and is now in the process 

of negotiating with its regulators at various sites to determine the 

best way to implement the accelerated approach.



DOE’s initiatives following the February 2002 review are not DOE’s 

first attempt to develop a risk-based approach to cleanup. In the past, 

the Congress, GAO, and others have recommended that DOE implement such 

a risk-based approach, and DOE has made several attempts to do so. 

However, in our May 2002 report we noted that a 1999 study to evaluate 

these efforts concluded that none of the attempts had been 

successful.[Footnote 21] Past problems included poor documentation of 

risks, inconsistent scoring of risks between sites, and DOE’s failure 

to integrate any of the risk-based approaches into the decision-making 

process. We concluded that a major challenge for DOE in successfully 

implementing its accelerated cleanup initiative is to follow through on 

its plan to develop and implement a risk-based method to prioritize 

various cleanup activities. DOE management leadership and resolve are 

needed to overcome the barriers encountered in past attempts at 

establishing a risk-based cleanup approach.



Some of the problems with the DOE’s environmental management program 

that were highlighted in the February 2002 review have also been the 

subject of GAO and DOE’s Inspector General reports during the past 2 

years. For example, we reported in 2001 that to improve use of cleanup 

resources, DOE would need to improve project baselines and integrate 

activities among DOE sites. As we reported in January 2001, DOE has 

made some progress in establishing project baselines, but has had 

continuing difficulty integrating waste treatment and disposal 

activities among its sites. For example, in our February 2001 report on 

the progress of the closure of the Rocky Flats site, we stated that one 

of the significant integration challenges was overcoming the limited 

number of transportation casks available to ship huge quantities of 

radioactive waste. Integrating waste treatment and disposal, as well as 

consolidating nuclear materials, has taken on increased importance in 

the post September 11 environment. DOE plans to improve security by 

consolidating all special nuclear materials in safeguarded facilities 

and accelerating disposal of transuranic waste currently stored at 

numerous sites around the country.



Other examples of challenges the environmental management program faces 

include managing complex cleanups, developing and deploying new 

technologies, and developing meaningful performance measures. For 

example, in 2001, we reported that the scheduled closure of the Rocky 

Flats site by 2006 was unlikely because of technical concerns, 

equipment limitations, uncertainty about contamination, and a variety 

of potential safety issues. To improve the chance of achieving the 

target closure date and cost, we recommended that DOE clarify the 

authority for reconciling competing demands on resources and establish 

a process for reconciling:



these competing demands in a timely manner. DOE agreed with and has 

implemented this recommendation. In May 2001 and January 2002, DOE’s 

Inspector General found that two Ohio sites, Miamisburg and Ashtabula, 

were not on schedule to meet their established closure dates because 

the cleanup was more difficult than originally anticipated, and DOE 

understated both time and cost to complete it.[Footnote 22] In a 2002 

report, DOE’s Inspector General noted that performance measures for the 

cleanup program focused more on discrete tasks or accomplishments, such 

as the number of high-level waste canisters placed in storage, than on 

the overall progress in site cleanup.[Footnote 23] As a result, DOE 

reported that the program was generally successful in meeting its goals 

even though the cleanup program had experienced substantial cost growth 

and schedule slippages. The Inspector General concluded that the lack 

of adequate performance measures deprived the department of a valuable 

tool that could have helped identify problems resulting in cost growth 

and schedule slippages. In response to this report, DOE’s Assistant 

Secretary for Environmental Management pledged to require cleanup sites 

to identify the key performance measures that will capture overall 

performance. These key performance measures will be included in 

integrated project baselines that will enable the sites to track cost 

and schedule progress.



The task of cleaning up DOE’s contaminated sites and facilities is a 

daunting one that has a huge price tag and could take a substantial 

portion of the 21ST century. DOE is in the process of changing its 

business and contracting processes, as well as rethinking its cleanup 

approach at many of its sites. In addition, DOE is seeking options that 

will accelerate risk reduction and reduce the overall cleanup cost. 

Congressional, regulator, and local community buy-in to new approaches 

is essential for success. While the environmental management program 

initiatives are innovative, successful results are not guaranteed. 

Continued management leadership and focus will be needed to ensure that 

these initiatives are implemented in a safe and cost-effective manner 

that provides for the accelerated cleanup of DOE sites.



Enhance DOE Leadership in Meeting the Nation’s Energy Needs:



Providing leadership in addressing the nation’s energy needs represents 

a major challenge for the department because a stable and reliable 

energy supply is critical for consumers, the U.S. economy, and our 

national security. Today, our nation’s energy supply system is under 

stress. Figure 3 shows that total U.S. energy consumption has grown 

about 180 percent in the last 50 years and is expected to increase 

another 32 percent between 2000 and 2020.



Figure 3: Total U.S. Energy Consumption 1950 to 2020:



[See PDF for image] 



[End of figure]



In some energy markets--such as electricity, natural gas, home heating 

oil, and gasoline--demand has periodically outstripped available and 

reliable supply. For example, in several western states unmet 

electrical demand led to price increases and rolling blackouts. 

Moreover, the security of oil supplies to meet the nation’s ever 

increasing needs is at risk. More than 50 percent of U.S. petroleum is 

imported, much of it from the volatile Persian Gulf region where 

conflicts underscore the ease with which supplies can be disrupted. 

More recently, these traditional energy supply issues have been 

compounded by another threat--the vulnerability of the nation’s 

domestic energy infrastructure to terrorist attacks. The large-scale 

infrastructure for oil, gas, and electricity systems makes them 

difficult and expensive to protect. This concern has resonated after 

September 11, adding another dimension to the challenge of providing 

reliable energy supplies.



DOE is in a unique position to help ensure that the nation’s energy 

needs are met. First, because DOE is the federal agency responsible for 

energy policy its leadership and direction will influence other federal 

agencies and state and local activities, as well as the energy 

industry. DOE’s role is important because the U.S. government is the 

nation’s single largest energy user. Second, DOE plays a vital role in 

linking federal government research and development and other 

government efforts with the energy industry in the United States. This 

link helps ensure that industry produces adequate energy supplies that 

are reliable, safe, affordable, diverse, innovative, and 

environmentally friendly. While DOE is in a unique position, it cannot 

solve the problem alone. This is because DOE does not control the 

economics or environmental policies that can affect the marketplace.



In the past, DOE has undertaken numerous efforts to address energy 

supply problems for all sources of energy. The nation’s current sources 

of energy to meet consumption in 2001 are shown in figure 4.



Figure 4: U.S. Energy Consumption by Source, Fiscal Year 2001:



[See PDF for image]



[End of figure]



In the future, DOE intends to play a major role in fostering U.S. 

energy supplies by, among other things, helping to develop a 

competitive electricity generation system, reducing the vulnerability 

of the U.S. economy to potential disruptions in petroleum supply (e.g., 

by fully developing the Strategic Petroleum Reserve), researching clean 

coal and other fossil and renewable energy technologies to transition 

away from petroleum, and making sure that the energy infrastructure 

serves the needs of the public. DOE budgeted about $2.3 billion in 2002 

to address this issue, and nearly one-third of all the department’s 

general performance goals relate to “energy resources.”[Footnote 24] In 

testifying on DOE’s fiscal year 2003 budget, Secretary Abraham stated 

that after September 11 our nation’s energy security is national 

security. Furthermore, he laid out new priorities for the department--

centered on an overarching mission of national security--and proposed 

the largest budget in the department’s history.



Over the past several years, in briefings, testimonies, and reports, 

GAO has addressed a number of issues related to the energy supply 

challenge. Much of this work points out ways for DOE to better meet its 

goals and more effectively focus its budgetary resources on developing 

technologies that are competitive in the marketplace. For example, in 

testimony on the department’s attempts to reduce the consumption of 

petroleum in the transportation sector, we pointed out that DOE’s 

recent involvement in a $1.2 billion multiyear partnership with the 

automotive industry would not develop a cost-competitive vehicle that 

consumers would buy.[Footnote 25] In another instance, while DOE’s 

research and development efforts were focused at developing large-scale 

wind turbines to produce electricity, we found that other companies 

elsewhere in the marketplace had already fielded similar turbines.



DOE has a history of achieving technical progress in the energy area. 

However, many times it does not study the energy marketplace to ensure 

that the results of its efforts ultimately address the energy supply 

challenge. Given the department’s large budgetary outlays for research 

and development, the importance of a reliable energy supply to the 

quality of life, and the complex and evolving marketplace in which DOE 

must work, this challenge will require enhanced management attention 

and monitoring.



Revitalize DOE’s Infrastructure:



DOE faces a major challenge in making the right investments to ensure 

that it has world-class research and development facilities for 

supporting its national security, science, environmental, and energy 

missions. The department’s physical infrastructure includes more than 

50 major facilities in 35 states, encompassing thousands of structures. 

Many of these facilities are in poor condition, and others are reaching 

the end of their design life. For example, DOE’s national laboratories 

were built during World War II and the early Cold War. Over 60 percent 

of the laboratory space is more than 30 years old, and 35 percent is 

more than 40 years old. DOE has begun to receive funding from the 

Congress to improve its infrastructure, and its offices are developing 

plans for improvements. The cost of upgrading DOE’s infrastructure will 

exceed several billion dollars. DOE’s challenge will be to spend this 

money effectively and efficiently, in a way that is consistent with its 

most important missions.



DOE’s infrastructure problems and their effect on operations are well 

known. For example, DOE noted in its 2000 Strategic Plan that the poor 

condition of its facilities adversely impacts the safety, cost, and 

continuity of research activities and hurts laboratories’ ability to 

attract and retain highly qualified scientists to work on important 

mission needs.[Footnote 26] DOE’s Inspector General has also reported 

on the poor condition of the department’s infrastructure, noting that 

conditions are deteriorating at an “alarming pace.” Facilities in poor 

condition are costly to maintain and difficult to keep in regulatory 

compliance. In a September 2000 report, the Inspector General said that 

the deteriorating conditions are causing some Nuclear Weapons Stockpile 

Stewardship milestones and goals to slip, restoration costs to 

increase, and future nuclear weapons production work to be at 

risk.[Footnote 27]



Many factors contribute to DOE’s infrastructure deficiencies, including 

deferred maintenance. For example, the Inspector General’s September 

2000 report also noted that the department has deferred substantial 

maintenance and upgrades on its nuclear weapons production facilities. 

Table 2 shows the total amount of building maintenance that DOE has 

deferred as of September 2002.



Table 2: Number of DOE Buildings and Estimated Deferred Maintenance as 

of September 2002:



Program Office: Environmental Management; Number of Buildings: 3,176; 

Average Age of Buildings: 29; Deferred Maintenance (in thousands): 

$411,145.



Program Office: Fossil Energy; Number of Buildings: 430; Average Age of 

Buildings: 16; Deferred Maintenance (in thousands): 479.



Program Office: National Nuclear Security Administration; Number of 

Buildings: 4,101; Average Age of Buildings: 33; Deferred Maintenance 

(in thousands): 782,562.



Program Office: Nuclear Energy; Number of Buildings: 293; Average Age 

of Buildings: 30; Deferred Maintenance (in thousands): 8,771.



Program Office: Power Administrations; Number of Buildings: 663; 

Average Age of Buildings: 28; Deferred Maintenance (in thousands): 133.



Program Office: Science; Number of Buildings: 1,740; Average Age of 

Buildings: 32; Deferred Maintenance (in thousands): 580,668.



Program Office: Other; Number of Buildings: 304; Average Age of 

Buildings: 34; Deferred Maintenance (in thousands): 9,758.



Program Office: Total; Number of Buildings: 10,707; Average Age of 

Buildings: 31; Deferred Maintenance (in thousands): $1,793,515.



[End of table]



Source: DOE and GAO.



The Inspector General also pointed out that DOE had not implemented a 

process to fully link workload, production capacity, and budget data to 

nuclear weapons production facility requirements, placing at risk 

current and future goals of the Stockpile Stewardship Program. Other 

factors contributing to infrastructure deficiencies have been pointed 

out by DOE’s Office of Science, which reports that its unfunded backlog 

of capital investment projections and deferred maintenance are due to 

aging of the laboratories, changing technology and mission activities, 

and insufficient capital investment and maintenance spending in the 

past. For example, the department allocates about 0.7 percent of 

replacement plant value for maintenance of the science laboratories, as 

compared with 1.5 percent to 3 percent for industry and academia and as 

suggested in guidelines from the National Research Council for federal 

facilities.[Footnote 28] The Office of Science’s April 2001 report on 

laboratory infrastructure noted that inadequate maintenance could lead 

to scientific mission failure, occupational health and safety risks, 

lost productivity, and expensive emergency repairs.



DOE’s deteriorating infrastructure threatens mission accomplishment 

and will require substantial funding to ameliorate. DOE’s Inspector 

General reports that DOE and Department of Defense officials estimated 

that $5 billion to $8 billion over current budgeted amounts will need 

to be invested over the next 10 years to offset the effects of delayed 

or neglected infrastructure activities in the nuclear weapons 

complex.[Footnote 29] For science laboratories, DOE estimates that over 

$300 million in deferred maintenance has been cataloged.



DOE recognizes the critical problems caused by the crumbling 

infrastructure and is making changes. The department has various 

infrastructure improvement initiatives underway, has pledged to improve 

internal processes for identifying needs and linking budgets to 

infrastructure requirements, and has made infrastructure needs a 

special management focus. For example, in fiscal year 2001, NNSA 

obtained new, increased, and direct appropriations to initiate a 

Facilities and Infrastructure Recapitalization Program to address an 

integrated, complex-wide priority list of maintenance and 

infrastructure investment activities above the current base operating 

levels supported by the much larger Readiness and Technical Base and 

Facilities Program (which is nearly 

25 percent of NNSA’s budget). Funding is anticipated to be $200 million 

to $500 million a year for the next 10 years. DOE’s Office of Science 

obtained $10 million in fiscal year 2002 for a new Facilities and 

Infrastructure Program to eliminate and clean up excess space. However, 

the seriousness of the infrastructure deficiencies, combined with 

competing needs from existing and emerging missions such as homeland 

security and historical weaknesses in project management, make 

implementing plans for infrastructure revitalization a management 

challenge for the department.



[End of section]



GAO Contacts:



Subject(s) covered in this report: Address New Security Threats and Old 

Security Concerns; ; Improve Management of Maintaining the Nation’s 

Nuclear Weapons Stockpile; ; Resolve Problems in Contract Management 

that Place DOE at High Risk for Fraud, Waste, and Abuse; ; Improve 

Management for Cleanup of DOE Radioactive and Hazardous Wastes; ; 

Revitalize DOE’s Infrastructure through Major Investments; Contact 

person: (Ms.) Gary L. Jones, Director

Natural Resources and Environment

(202) 512-3464

jonesgl1@gao.gov.



Subject(s) covered in this report: Establish DOE Leadership in Meeting 

the Nation’s Energy Needs; Contact person: Jim Wells, Director

Natural Resources and Environment 

(202) 512-6877

wellsj@gao.gov.



[End of section]



Related GAO Products:



Address Security Threats and Problems:



Nuclear Security: Lessons to Be Learned from Implementing NNSA’s 

Security Enhancements. GAO-02-358. Washington D.C.: March 29, 2002.



Department of Energy: NNSA Restructuring and Progress in Implementing 

Title 32. GAO-02-451T. Washington D.C.: February 26, 2002.



Nuclear Security: DOE Needs to Improve Control Over Classified 

Information. GAO-01-806. Washington D.C.: August 24, 2001.



Department of Energy: Views on the Progress of the National Nuclear 

Security Administration in Implementing Title 32. GAO-01-602T. 

Washington D.C.: April 4, 2001.



Improve Management of the Nation’s Nuclear Weapons Stockpile:



NNSA: Nuclear Weapon Reports Need to Be More Detailed and 

Comprehensive. GAO-02-889R. Washington D.C.: July 3, 2002.



Department of Energy: NNSA Restructuring and Progress in Implementing 

Title 32. GAO-02-451T. Washington D.C.: February 26, 2002.



NNSA Management: Progress in the Implementation of Title 32. GAO-02-

93R. Washington D.C.: December 12, 2001.



Nuclear Weapons: Status of Planning for Stockpile Life Extension. GAO-

02-146R. Washington D.C.: December 7, 2001.



Department of Energy: Follow-up Review of the National Ignition 

Facility. GAO-01-677R. Washington D.C.: June 1, 2001.



Department of Energy: Views on the Progress of the National Nuclear 

Security Administration in Implementing Title 32. GAO-01-602T. 

Washington D.C.: April 4, 2001.



Nuclear Weapons: Improved Management Needed to Implement Stockpile 

Stewardship Program Effectively. GAO-01-48. Washington D.C.: December 

14, 2000.



Resolve Problems in Contract Management That Place DOE at High Risk For 

Fraud, Waste, and Abuse:



Contract Reform: DOE Has Made Progress, but Actions Needed to Ensure 

Initiatives Have Improved Results. GAO-02-798. Washington D.C.: 

September 13, 2002.



Department of Energy: Contractor Litigation Costs. GAO-02-418R. 

Washington D.C.: March 8, 2002.



Department of Energy: NNSA Restructuring and Progress in Implementing 

Title 32. GAO-02-451T. Washington D.C.: February 26, 2002.



Nuclear Waste: Technical, Schedule, and Cost Uncertainties of the Yucca 

Mountain Repository Project. GAO-02-191. Washington D.C.: December 21, 

2001.



Department of Energy: Fundamental Reassessment Needed to Address Major 

Mission, Structure, and Accountability Problems. GAO-02-51. Washington 

D.C.: December 21, 2001.



NNSA Management: Progress in the Implementation of Title 32. GAO-02-

93R. Washington D.C.: December 12, 2001.



National Laboratories: Better Performance Reporting Could Aid Oversight 

of Laboratory-Directed R&D Program. GAO-01-927. Washington D.C.: 

September 28, 2001.



Department of Energy: Status of Achieving Key Outcomes and Addressing 

Major Management Challenges. GAO-01-823. Washington D.C.: June 29, 

2001.



Department of Energy: Follow-Up Review of the National Ignition 

Facility. GAO-01-677R. Washington D.C.: June 1, 2001.



Nuclear Waste: Agreement Among Agencies Responsible for the West Valley 

Site Is Critically Needed. GAO-01-314. Washington D.C.: May 11, 2001.



Department of Energy: Views on the Progress of the National Nuclear 

Security Administration in Implementing Title 32. GAO-01-602T. 

Washington D.C.: April 4, 2001.



Nuclear Cleanup: Progress Made at Rocky Flats, but Closure by 2006 Is 

Unlikely, and Costs May Increase. GAO-01-284. Washington D.C.: February 

28, 2001.



National Ignition Facility: Management and Oversight Failures Caused 

Major Cost Overruns and Schedule Delays. GAO/RCED-00-271. Washington, 

D.C.: August 8, 2000.



Improve Management for Cleanup of DOE Radioactive and Hazardous Wastes:



Waste Cleanup: Implications of Compliance Agreements on DOE’s Cleanup 

Program. GAO-02-852T. Washington D.C.: July 19, 2002.



Waste Cleanup: Status and Implications of DOE’s Compliance Agreements. 

GAO-02-567. Washington D.C.: May 30, 2002.



Nuclear Waste: Uncertainties About the Yucca Mountain Repository 

Project. GAO-02-765T. Washington D.C.: May 23, 2002.



Nuclear Waste: Uncertainties About the Yucca Mountain Repository 

Project. GAO-02-539T. Washington D.C.: March 21, 2002.



Nuclear Waste: Technical, Schedule, and Cost Uncertainties of the Yucca 

Mountain Repository Project. GAO-02-191. Washington D.C.: December 21, 

2001.



Department of Energy: Fundamental Reassessment Needed to Address Major 

Mission, Structure, and Accountability Problems. GAO-02-51. 

Washington, D.C.: December 21, 2001.



Nuclear Cleanup: DOE Should Reevaluate Waste Disposal Options Before 

Building New Facilities. GAO-01-441. Washington D.C.: May 25, 2001.



Nuclear Waste: Agreement Among Agencies Responsible for the West Valley 

Site Is Critically Needed. GAO-01-314. Washington D.C.: May 11, 2001.



Nuclear Cleanup: Progress Made at Rocky Flats, but Closure by 2006 Is 

Unlikely, and Costs May Increase. GAO-01-284. Washington D.C.: February 

28, 2001.



Enhance DOE Leadership in Meeting the Nation’s Energy Needs:



Restructured Electricity Markets: California Market Design Enabled 

Exercise of Market Power. GAO-02-828. Washington D.C.: June 21, 2002.



Energy Markets: Concerted Actions Needed by FERC to Confront Challenges 

That Impede Effective Oversight. GAO-02-656. Washington D.C.: June 14, 

2002.



Research and Development: Lessons Learned from Previous Research Could 

Benefit Freedom Car Initiative. GAO-02-810T. Washington D.C.: June 6, 

2002.



Restructured Electricity Markets: Three States’ Experience in Adding 

Generating Capacity. GAO-02-427. Washington D.C.: May 24, 2002.



California Electricity Market Options for 2001: Military Generation and 

Private Backup Possibilities. GAO-01-865R. Washington D.C.: June 21, 

2001.



Fossil Fuel R&D: Lessons Learned in the Clean Coal Technology Program. 

GAO-01-854T. Washington D.C.: June 12, 2001.



Government Performance and Results Act: Information on Science Issues 

in the Department of Energy’s Accountability Report for Fiscal Year 

1999 and Performance Plans for Fiscal Year 2000 and 2001. GAO/RCED-00-

268R. Washington D.C.: August 25, 2000.



Observations on the Department of Energy’s Fiscal Year 1999 

Accountability Report and Fiscal Year 2000/2001 Performance Plans. GAO/

RCED-00-209R. Washington D.C.: June 30, 2000.



Cooperative Research: Results of U.S.-Industry Partnership to Develop a 

New Generation of Vehicles. GAO/RCED-00-81. Washington D.C.: March 30, 

2000.



Energy Policy Act of 1992: Limited Progress in Acquiring Alternative 

Fuel Vehicles and Reaching Fuel Goals. GAO/RCED-00-59. Washington D.C.: 

February 11, 2000.



Revitalize DOE’s Infrastructure:



Department of Energy: Observations on Using External Agencies to 

Regulate Nuclear and Worker Safety in DOE’s Science Laboratories. GAO-

02-868R. Washington D.C.: June 23, 2002.



Department of Energy: Fundamental Reassessment Needed to Address Major 

Mission, Structure, and Accountability Problems. GAO-02-51. Washington 

D.C.: December 21, 2001.



Department of Energy: Views on the Progress of the National Nuclear 

Security Administration in Implementing Title 32. GAO-01-602T. 

Washington D.C.: April 1, 2001.



Nuclear Weapons: Improved Management Needed to Implement Stockpile 

Stewardship Program Effectively. GAO-01-48. Washington D.C.: December 

14, 2000.



Department of Energy: Uncertainties and Management Problems Have 

Hindered Cleanup at Two Nuclear Waste Sites. GAO/T-RCED-00-248. 

Washington D.C.: July 12, 2000.



[End of section]



Performance and Accountability and High-Risk Series:



Major Management Challenges and Program Risks: A Governmentwide 

Perspective. GAO-03-95.



Major Management Challenges and Program Risks: Department of 

Agriculture. GAO-03-96.



Major Management Challenges and Program Risks: Department of Commerce. 

GAO-03-97.



Major Management Challenges and Program Risks: Department of Defense. 

GAO-03-98.



Major Management Challenges and Program Risks: Department of Education. 

GAO-03-99.



Major Management Challenges and Program Risks: Department of Energy. 

GAO-03-100.



Major Management Challenges and Program Risks: Department of Health and 

Human Services. GAO-03-101.



Major Management Challenges and Program Risks: Department of Homeland 

Security. GAO-03-102.



Major Management Challenges and Program Risks: Department of Housing 

and Urban Development. GAO-03-103.



Major Management Challenges and Program Risks: Department of the 

Interior. GAO-03-104.



Major Management Challenges and Program Risks: Department of Justice. 

GAO-03-105.



Major Management Challenges and Program Risks: Department of Labor. 

GAO-03-106.



Major Management Challenges and Program Risks: Department of State. 

GAO-03-107.



Major Management Challenges and Program Risks: Department of 

Transportation. GAO-03-108.



Major Management Challenges and Program Risks: Department of the 

Treasury. GAO-03-109.



Major Management Challenges and Program Risks: Department of Veterans 

Affairs. GAO-03-110.



Major Management Challenges and Program Risks: U.S. Agency for 

International Development. GAO-03-111.



Major Management Challenges and Program Risks: Environmental Protection 

Agency. GAO-03-112.



Major Management Challenges and Program Risks: Federal Emergency 

Management Agency. GAO-03-113.



Major Management Challenges and Program Risks: National Aeronautics and 

Space Administration. GAO-03-114.



Major Management Challenges and Program Risks: Office of Personnel 

Management. GAO-03-115.



Major Management Challenges and Program Risks: Small Business 

Administration. GAO-03-116.



Major Management Challenges and Program Risks: Social Security 

Administration. GAO-03-117.



Major Management Challenges and Program Risks: U.S. Postal Service. 

GAO-03-118.



High-Risk Series: An Update. GAO-03-119.



High-Risk Series: Strategic Human Capital Management. GAO-03-120.



High-Risk Series: Protecting Information Systems Supporting the Federal 

Government and the Nation’s Critical Infrastructures. GAO-03-121.



High-Risk Series: Federal Real Property. GAO-03-122.



FOOTNOTES



[1] NNSA’s primary responsibility is to maintain the safety and 

reliability of the nation’s nuclear weapons stockpile through the 

Stockpile Stewardship Program. 



[2] U.S. General Accounting Office, Nuclear Security: Lessons to Be 

Learned from Implementing NNSA’s Security Enhancements, GAO-02-358 

(Washington, D.C.: Mar. 29, 2002).



[3] Center for Strategic and International Studies, Science and 

Security in the 21ST Century: A Report to the Secretary of Energy on 

the Department of Energy Laboratories (Washington, D.C.: April 2002). 



[4] U.S. General Accounting Office, Nuclear Security: DOE Needs to 

Improve Control Over Classified Information, GAO-01-806 (Washington, 

D.C.: Aug. 24, 2001).



[5] U.S. Department of Energy, The Department’s Unclassified Cyber 

Security Program, DOE/IG-0519 (Washington, D.C.: Aug. 30, 2001).



[6] U.S. Department of Energy, Lawrence Livermore National Laboratory 

Protective Force and Special Response Team, DOE/IG-0534 (Washington, 

D.C.: December 2001).



[7] U.S. Department of Energy, Personnel Security Clearances and Badge 

Access Controls At Department Headquarters, DOE/IG-0548 (Washington, 

D.C.: Mar. 26, 2002).



[8] NNSA is also responsible for preventing the proliferation of 

weapons of mass destruction and designing, building, and maintaining 

naval nuclear propulsion systems. 



[9] U.S. General Accounting Office, Nuclear Weapons: Improved 

Management Needed to Implement Stockpile Stewardship Program 

Effectively, GAO-01-48 (Washington, D.C.: Dec. 14, 2000). 



[10] U.S. General Accounting Office, NNSA: Nuclear Weapon Reports Need 

to Be More Detailed and Comprehensive, GAO-02-889R (Washington, D.C.: 

July 3, 2002).



[11] U.S. General Accounting Office, Contract Reform: DOE Has Made 

Progress, but Actions Needed to Ensure Initiatives Have Improved 

Results, GAO-02-798 (Washington, D.C.: 

Sept. 13, 2002).



[12] U.S. Department of Energy, Use of Performance-Based Incentives at 

Selected Departmental Sites, DOE/IG-0510 (Washington, D.C.: July 9, 

2001).



[13] U.S. General Accounting Office, Nuclear Waste: Technical, 

Schedule, and Cost Uncertainties of the Yucca Mountain Repository 

Project, GAO-02-191 (Washington, D.C.: Dec. 21, 2001).



[14] U.S. Department of Energy, The Department of Energy’s Tritium 

Extraction Facility, DOE/IG-0560 (Washington, D.C.: June 24, 2002).



[15] U.S. General Accounting Office, National Ignition Facility: 

Management and Oversight Failures Caused Major Cost Overruns and 

Schedule Delays, GAO/RCED-00-271 (Washington, D.C.: Aug. 8, 2000).



[16] National Research Council, Improving Project Management in the 

Department of Energy (Washington, D.C.: June 1999).



[17] National Research Council, Progress in Improving Project 

Management at the Department of Energy--2001 Assessment (Washington, 

D.C.: November 2001).



[18] Environmental cleanup includes addressing contaminated soil, 

groundwater, and surface water, as well as treating and disposing of 

hazardous and radioactive wastes. 



[19] The most recent estimate of $220 billion reflects the life-cycle 

costs of the cleanup program through the year 2070. DOE’s Office of 

Environmental Management is responsible for cleaning up radioactive and 

hazardous wastes at DOE sites.



[20] U.S. Department of Energy, A Review of the Environmental 

Management Program (Washington D.C.: Feb. 4, 2002).



[21] U.S. General Accounting Office, Waste Cleanup: Status and 

Implications of DOE’s Compliance Agreement, GAO-02-567 (Washington, 

D.C.: May 30, 2002); Consortium for Risk Evaluation with Stakeholder 

Participation, Peer Review of the U.S. Department of Energy’s Use of 

Risk in Its Prioritization Process, (New Brunswick, N.J.: Dec. 15, 

1999).



[22] U.S. Department of Energy, Remediation and Closure of the 

Miamisburg Environmental Management Project, DOE/IG-0501 (Washington, 

D.C.: May 2, 2001) and U.S. Department of Energy, Remediation and 

Closure of the Ashtabula Environmental Management Project, DOE/IG-0541 

(Washington, D.C.: Jan. 15, 2002).



[23] U.S. Department of Energy, Environmental Management Performance 

Measures, DOE/IG-0561 (Washington, D.C.: June 27, 2002).



[24] In general, the energy resources area promotes the development and 

deployment of energy systems and practices that will provide current 

and future generations with energy that is clean, reasonably priced, 

and reliable.



[25] U.S. General Accounting Office, Research and Development: Lessons 

Learned from Previous Research Could Benefit Freedom Car Initiative, 

GAO-02-810T (Washington, D.C.: June 6, 2002).



[26] U.S. Department of Energy, Strategic Plan, DOE/CR-0070 

(Washington, D.C.: September 2000).



[27] U.S. Department of Energy, Management of the Nuclear Weapons 

Production Infrastructure, DOE/IG-0484 (Washington, D.C.: September 

2000).



[28] U.S. Department of Energy, Infrastructure Frontier: A Quick Look 

Survey of the Office of Science Laboratory Infrastructure (Washington, 

D.C.: April 2001).



[29] U.S. Department of Energy, Management of the Nuclear Weapons 

Production Infrastructure, DOE/IG-0484 (Washington, D.C.: September 

2000).



GAO’s Mission:



The General Accounting Office, the investigative arm of Congress, 

exists to support Congress in meeting its constitutional 

responsibilities and to help improve the performance and accountability 

of the federal government for the American people. GAO examines the use 

of public funds; evaluates federal programs and policies; and provides 

analyses, recommendations, and other assistance to help Congress make 

informed oversight, policy, and funding decisions. GAO’s commitment to 

good government is reflected in its core values of accountability, 

integrity, and reliability.



Obtaining Copies of GAO Reports and Testimony:



The fastest and easiest way to obtain copies of GAO documents at no 

cost is through the Internet. GAO’s Web site ( www.gao.gov ) contains 

abstracts and full-text files of current reports and testimony and an 

expanding archive of older products. The Web site features a search 

engine to help you locate documents using key words and phrases. You 

can print these documents in their entirety, including charts and other 

graphics.



Each day, GAO issues a list of newly released reports, testimony, and 

correspondence. GAO posts this list, known as “Today’s Reports,” on its 

Web site daily. The list contains links to the full-text document 

files. To have GAO e-mail this list to you every afternoon, go to 

www.gao.gov and select “Subscribe to daily E-mail alert for newly 

released products” under the GAO Reports heading.



Order by Mail or Phone:



The first copy of each printed report is free. Additional copies are $2 

each. A check or money order should be made out to the Superintendent 

of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 

more copies mailed to a single address are discounted 25 percent. 

Orders should be sent to:



U.S. General Accounting Office



441 G Street NW,



Room LM Washington,



D.C. 20548:



To order by Phone: 	



	Voice: (202) 512-6000:



	TDD: (202) 512-2537:



	Fax: (202) 512-6061:



To Report Fraud, Waste, and Abuse in Federal Programs:



Contact:



Web site: www.gao.gov/fraudnet/fraudnet.htm E-mail: fraudnet@gao.gov



Automated answering system: (800) 424-5454 or (202) 512-7470:



Public Affairs:



Jeff Nelligan, managing director, NelliganJ@gao.gov (202) 512-4800 U.S.



General Accounting Office, 441 G Street NW, Room 7149 Washington, D.C.



20548: