This is the accessible text file for GAO report number GAO-10-588SP 
entitled 'Department Of Homeland Security: Assessments of Selected 
Complex Acquisitions' which was released on July 1, 2010. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Report to Congressional Addressees: 

United States Government Accountability Office: 
GAO: 

June 2010: 

Department Of Homeland Security: 

Assessments of Selected Complex Acquisitions: 

GAO-10-588SP: 

GAO Highlights: 

Highlights of GAO-10-588SP, a report to congressional addressees. 

Why GAO Did This Study: 

Department of Homeland Security (DHS) acquisitions represent hundreds 
of billions of dollars in life-cycle costs to support a wide range of 
missions. Creating acquisition policies and processes to provide 
insight into the performance of a wide array of complex investments, 
while also providing oversight for many component agencies new to 
acquisition management, has been an ongoing challenge for DHS. 

GAO performed this review because DHS implementation and 
transformation is on GAO’s high risk list. This report (1) provides an 
update on DHS’s efforts to implement acquisition oversight for all 
investments; (2) describes acquisition performance and common 
challenges across selected programs; and (3) provides individual 
profiles for 18 selected programs, 15 of which were major programs 
that had initiated acquisition activities. GAO selected programs based 
on relevance to frontline homeland security missions and assessed cost 
and schedule performance and acquisition planning challenges. 

What GAO Found: 

DHS continues to develop its acquisition oversight function and has 
begun to implement a revised acquisition management directive that 
includes more detailed guidance for programs to use when informing 
component and departmental decision making. The senior-level 
Acquisition Review Board (ARB) has begun to meet more frequently and 
has provided programs decision memorandums with action items to 
improve performance. The ARB reviewed 24 major acquisition programs in 
fiscal years 2008 and 2009; however, more than 40 major acquisition 
programs had not been reviewed, and programs have not consistently 
implemented review action items by established deadlines. 
Additionally, DHS has developed a database to capture and track key 
program information, including cost and schedule performance, contract 
awards, and program risks. At the component level, oversight officials 
are establishing new acquisition executive positions to manage 
acquisition processes, but departmental leadership has limited their 
decision authority due to staffing levels and inconsistencies between 
component- and department-level acquisition policies. Further, DHS 
acquisition management processes do not inform budget decisions as 
required by DHS policy, and as a result DHS is at risk of failing to 
maximize resources and ultimately meet critical mission needs. 

GAO has found that program performance metrics for cost and schedule 
can provide useful indicators of the health of acquisition programs 
and can be valuable tools for improving insight and oversight of 
programs. Further, realistic program baselines with stable 
requirements, an adequate and skilled program office workforce, and 
knowledge of long-term support requirements are important factors to 
successful acquisitions. However, program performance cannot be 
accurately assessed without valid baseline requirements established at 
the program start, particularly those that establish the minimum 
acceptable threshold required to satisfy user needs. Using the best 
available information, GAO found that of the 15 major programs that 
had started acquisition activities, 12 reported cost growth, and 
almost all programs reported schedule delays. DHS policy requires 
acquisition oversight officials to assess the accuracy of life-cycle 
cost estimates for all major programs estimated to exceed $1 billion 
and provides guidance for programs to develop life-cycle cost 
estimates. The responsible DHS acquisition oversight officials have 
raised concerns about the accuracy of cost estimates for most major 
programs, making it difficult to assess the significance of the 
reported cost growth. Further, over half of the programs GAO reviewed 
initiated acquisition activities without approved key planning 
documents that set operational requirements and establish program 
baselines. Programs also experienced other acquisition planning 
challenges, such as staffing shortages, and lack of sustainment 
planning, as well as execution challenges related to technical 
capability, partner dependence, and funding issues. 

DHS’s success in improving acquisition depends on further 
implementation of needed improvements and sustained management 
attention. 

What GAO Recommends: 

GAO is not making any new recommendations as this is intended as a 
status report. However, GAO has previously made numerous 
recommendations intended to improve acquisition management. DHS 
generally agreed with the findings and noted actions taken and efforts 
under way to improve the Department’s acquisition review process. 

View [hyperlink, http://www.gao.gov/products/GAO-10-588SP] or key 
components. For more information, contact John P. Hutton at (202) 512-
4841 or huttonj@gao.gov. 

[End of section] 

Contents: 

Forward: 

Letter: 

DHS Continues To Develop and Implement Acquisition Oversight: 

Acquisition Performance and Program Challenges: 

Program Assessments: 

Agency Comments and Our Evaluation: 

Appendix I: Objectives, Scope and Methodology: 

Appendix II: Comments From The Department Of Homeland Security: 

Appendix III: The Acquisition Life Cycle, Systems Engineering Life 
Cycle and Key Acquisition Documents at DHS: 

Related GAO Products: 

Tables: 

Table 1: DHS Oversight Officials' Roles and Responsibilities: 

Table 2: Comparison of Department and Component-Level Review under 
Acquisition Management Directive 102-01 (Interim) and Management 
Directive 1400: 

Table 3: Acquisition Decision Memo Action Items (fiscal years 2008 and 
2009): 

Table 4: DHS Major Acquisition Program Costs: 

Table 5: Summary of Major Program Planning Challenges: 

Table 6: Status of Integrated Logistics Support Plans (ILSP): 

Figures: 

Figure 1: Summary of DHS Acquisition Programs Assessed: 

Figure 2: Programs with Estimated Schedule Delay to Full Capability: 

Figure 3: Key Document Approval Timeframes: 

Figure 4: DHS Major Program Government Staff and Contractor Support: 

Abbreviations: 

APB: Acquisition Program Baseline: 

ARB: Acquisition Review Board: 

C4ISR: Command, Control, Communications, Computers, Intelligence, 
Surveillance, and Reconnaissance: 

CAE: Component Acquisition Executive: 

CBP: Customs and Border Protection: 

CDC: Centers for Disease Control: 

DCI: Data Collection Instrument: 

DHS: Department of Homeland Security: 

DOD:; Department of Defense: 

EDS: Explosive Detection System: 

FBI: Federal Bureau of Investigations: 

FDA: Food and Drug Administration: 

FEMA: Federal Emergency Management Agency: 

FOC: Full Operating Capability: 

ILSP: Integrated Logistics Support Plans: 

IOC: Initial Operating Capability: 

NASA: National Aeronautics and Space Administration: 

OMB: Office of Management and Budget: 

SBInet: Secure Border Initiative Network: 

TSA: Transportation Security Administration: 

USDA: United States Department of Agriculture: 

US-VISIT: United States Visitor and Immigrant Status Indicator 
Technology: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

June 30, 2010: 

Congressional Addressees: 

I am pleased to present GAO's assessment of complex acquisitions at 
the Department of Homeland Security (DHS). This report provides a 
snapshot of DHS acquisition oversight, planning, and execution--a 
topic that has been of interest since DHS was created in 2003. Soon 
after DHS began operations, we designated its implementation and 
transformation as a high-risk area due to the enormous management 
challenge of integrating 22 disparate agencies, and the size, 
complexity, and importance of the effort to the nation's security. 
[Footnote 1] 

Our prior work has highlighted the issues DHS has faced in designing 
and implementing the necessary management structure and processes to 
support some of the broadest and most complex needs among federal 
agencies. Critical issues include the need for sound acquisition 
planning to reduce program management challenges that lead to cost and 
schedule growth, and the department's need to integrate acquisition 
review and budgeting for major investments. In order to accomplish a 
wide range of frontline homeland security missions, as well as provide 
management information capabilities, DHS's acquisition spending has 
increased by 66 percent--from $8.5 billion in fiscal year 2004 to 
$14.2 billion in fiscal year 2009[Footnote 2]--and its portfolio of 
complex acquisitions continues to expand. While DHS has made recent 
progress in clarifying acquisition oversight processes, much remains 
to be done to ensure proper implementation and department wide 
coordination. In a time of fiscal constraints, it is increasingly 
important that DHS's acquisitions maximize resources to effectively 
meet critical homeland security missions. 

Signed by: 

Gene L. Dodaro: 
Acting Comptroller General of the United States: 

[End of section] 

United States Government Accountability Office: 
Washington, DC 20548: 

June 30, 2010: 

Congressional Addressees: 

In fiscal year 2009, the Department of Homeland Security (DHS) had 67 
major acquisitions intended to support a wide range of missions 
including securing our borders, mitigating natural disasters, and 
investigating security threats. Our work on major acquisitions at 
other federal departments and agencies has provided a framework for 
assessing DHS's acquisitions.[Footnote 3] We have found that a program 
must have a sound business case that includes firm requirements, a 
knowledge-based acquisition strategy, and realistic cost estimates in 
order to reduce program challenges.[Footnote 4] Further, we have found 
that acquisition oversight is more effective when regular reviews are 
held, an adequate workforce has been developed, and reliable cost, 
schedule and performance metrics are available.[Footnote 5] These 
conditions provide a program a reasonable chance of meeting its 
challenges yet delivering on time and within budget. 

The department's acquisitions, representing hundreds of billions of 
dollars in life-cycle costs, are managed by 12 components and offices 
through a structure of dual accountability. While the Undersecretary 
for Management serves as the Chief Acquisition Officer and bears 
responsibility for acquisition policy, the component heads bear 
responsibility for individual programs designed to achieve mission 
specific goals and objectives. Many of the 67 major acquisition 
programs existed prior to the creation of DHS and were managed by 1 of 
the 22 separate agencies that merged to form the department. Creating 
acquisition policies and processes to provide insight into the 
performance of a wide array of complex acquisitions, while also 
providing oversight for many component agencies new to acquisition 
management, has been an ongoing need. Our work over the past several 
years has consistently pointed to the challenges involved in 
effectively managing and overseeing this large and varied acquisition 
portfolio to meet performance expectations. We have raised these 
concerns in the context of our work on the department's acquisition 
oversight and in assessments of specific acquisitions across various 
components. 

We have reported that DHS's implementation of its investment review 
process generally resulted in investment decisions that were 
inconsistent with established policy and oversight, and weaknesses in 
some component management practices further compounded the problem. 
[Footnote 6] The department has not always reviewed its major 
investments at key phases in the acquisition life cycle, employed 
reliable cost and schedule estimating practices, or used effective 
requirements development and test management practices. These 
management weaknesses have led to major programs aimed at delivering 
important mission capabilities not living up to expectations.[Footnote 
7] For example, we reported that the Rescue 21 program did not follow 
established processes for managing requirements which contributed to 
deployment delays and limited the Coast Guard's ability to conduct 
search and rescue missions.[Footnote 8] U.S. Visitor and Immigrant 
Status Indicator Technology (US-VISIT) did not sufficiently define 
what capabilities and benefits would be delivered, by when, and at 
what cost, which contributed to development and deployment delays. 
[Footnote 9] Secure Border Initiative Network (SBInet) did not 
adequately define requirements, perform testing, or oversee 
contractors, delaying security of the southwest border.[Footnote 10] 
The department has acknowledged many of these issues and is making 
efforts to address them at the departmental and program levels. 

Because DHS relies on its complex acquisitions to fulfill critical 
homeland security missions, we assessed the department's oversight and 
implementation of complex acquisitions. This report (1) provides an 
update on the department's efforts to implement acquisition oversight 
for all acquisitions; (2) describes acquisition performance and common 
challenges across selected programs; and (3) provides individual 
profiles for each of the selected programs. 

To provide an update on acquisition oversight, we assessed the 
department's efforts to implement its interim acquisition management 
directive. We reviewed the department's acquisition management 
directives, acquisition decision memorandums, and key program tracking 
documents, and we interviewed departmental acquisition oversight 
officials. At the component level, we interviewed acquisition 
officials at the six components in our review--Customs and Border 
Protection, Federal Emergency Management Agency, National Protection 
and Programs Directorate, Office of Health Affairs, Transportation 
Security Administration, and the United States Coast Guard--about 
their policies and practices, staffing, departmental coordination, and 
relevant challenges. We did not, however, specifically assess the 
extent to which the department's acquisition guidance is consistent 
with best practices.[Footnote 11] 

To assess the implementation of complex acquisitions, we focused on 
acquisition planning. We selected 18 programs across six components--
16 major acquisition programs, as well as 2 smaller programs critical 
to DHS's mission based on several factors, including total projected 
funding for fiscal years 2007 through 2012, current stage in the DHS 
acquisition life cycle, and relevance to front-line homeland security 
missions. The 18 programs selected represent about $100 billion in 
life-cycle costs and about $38 billion in acquisition costs. We 
developed a data collection instrument to obtain key data on program 
cost, schedule, performance, and staffing, for the selected programs, 
and we reviewed it with program offices to clarify data requested in 
advance of completion. We also researched cost data reported in the 
Office of Management and Budget's (OMB) Exhibit 300 as part of the 
executive branch capital planning process and Coast Guard's Quarterly 
Acquisition Reports to Congress. We based our analysis on these 
sources as they represented more complete and official data used for 
making important planning and budgeting decisions. We interviewed 
officials from the 18 program offices to learn more about acquisition 
performance and program challenges. We also reviewed relevant GAO and 
DHS Inspector General reports on the selected acquisitions. The 
analysis of acquisition performance and common challenges across the 
selected programs focuses on 15 programs for which data were 
available.[Footnote 12] The profiles of the selected programs include 
all 18 programs selected for our review. All data were current as of 
2009, with the exception of latest estimates of program costs obtained 
from OMB Exhibits 300, which were current as of either January or 
February 2010. 

We assessed program data using criteria based on best practices 
established in prior work on major acquisitions. We have frequently 
reported on the importance of using a solid, executable business case 
before committing resources to a new acquisition. Our body of work on 
best practices has shown that a sound business case is one that 
provides demonstrated evidence that (1) needs are valid and can best 
be met with the chosen concept; and (2) the chosen concept can be 
developed and produced within existing resources. If a valid business 
case is not established by the start of an acquisition program, then 
requirements are likely to change, which can lead to significant cost 
increases and schedule delays as the government and contractor gain a 
better understanding of requirements. Program cost, schedule, and 
performance, and changes in these factors over time can provide useful 
indicators of the health of acquisition programs. When assessed 
regularly for changes and the reasons that cause changes, such 
indicators can be valuable tools for improving insight and oversight 
of individual programs as well as total portfolio of major 
acquisitions.[Footnote 13] However, performance metrics are of little 
value without knowledge-based, realistic program baselines, which are 
critical to acquisition programs achieving goals. Without realistic 
baselines established at the start of a program, there is no 
foundation for accurately measuring the knowledge and health of 
programs. 

We conducted our work from March 2009 to June 2010 in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings 
and conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. See appendix I for 
additional information on our scope and methodology. We do not make 
recommendations in this report; however, we have previously made 
numerous recommendations intended to improve the department's 
acquisition management and oversight, and DHS is taking steps to 
address them. We provided a draft of this report to DHS for review and 
comment. DHS generally concurred with our findings citing the review 
of actions taken and efforts under way to improve the acquisition 
review process, particularly the development and implementation of the 
department's acquisition management directive. The department's 
comments are reprinted in appendix II. DHS also provided technical 
comments which we incorporated as appropriate and where supporting 
documentation was provided. 

DHS Continues To Develop and Implement Acquisition Oversight: 

DHS continues to develop its acquisition oversight function and has 
produced and begun to implement a revised acquisition management 
directive. As part of the implementation process, the senior-level 
Acquisition Review Board (ARB) has begun to meet more frequently and 
has provided decision memorandums with action items to improve program 
performance. The ARB reviewed 24 major acquisition programs in fiscal 
years 2008 and 2009; however, more than 40 major acquisition programs 
had not been reviewed, and programs have not consistently implemented 
review action items by established deadlines. The acquisition 
oversight office has created a tracking system to monitor key program 
information for all acquisitions. At the component level, acquisition 
oversight offices have begun to update policies and staff capacity 
needed to oversee program activities. While these efforts are positive 
steps toward improving acquisition management and oversight, the 
department has not yet established a departmentwide requirements 
oversight body for all acquisitions or integrated the acquisition 
review and budget processes as required by DHS policy. As a result, 
DHS is at risk of failing to maximize resources and ultimately meet 
critical mission needs. DHS's success in improving acquisition depends 
on further implementation and sustained management attention. 

Acquisition Management Directive: 

In 2008, we reported that DHS had not effectively implemented its 
investment review process, and as a result, the department had not 
provided the oversight needed to identify and address cost, schedule, 
and performance problems for its major acquisitions.[Footnote 14] 
Since the time of that review, DHS has established a revised oversight 
process and begun to implement an interim acquisition management 
directive and an accompanying guidebook explaining how the department 
should meet the directive's requirements.[Footnote 15] The interim 
directive includes more detailed guidance than the previous 2006 
management directive for programs to use in preparing key 
documentation to support component and departmental decision making. 
For example, the interim directive, in effect at the time we reviewed 
the selected acquisitions, establishes four acquisition life-cycle 
phases: (1) identify a capability need; (2) analyze and select the 
means to provide that capability; (3) obtain the capability; and (4) 
produce, deploy and support the capability. The directive requires ARB 
review of each major acquisition program at least three times at key 
acquisition decision events during a program's acquisition life cycle. 
Table 1 describes the roles and responsibilities of the entities 
involved in the review process. 

Table 1: DHS Oversight Officials' Roles and Responsibilities: 

Officials: Acquisition Review Board members; 
Roles: Officials that comprise the departmental executive board that 
reviews major acquisition programs; 
The chair of the Board is the Acquisition Decision Authority; 
individual authority differs depending on the level of the acquisition; 
Members include the Under Secretary for Management, Assistant 
Secretary for Policy, General Counsel, Chief Financial Officer, Chief 
Procurement Officer, Chief Information Officer, Chief Administrative 
Officer, Chief Security Officer, Director of Operational Test and 
Evaluation, and user representatives from components sponsoring the 
capability, and other representatives as appropriate; 
Responsibilities: Review Level 1 and Level 2 acquisitions for 
executable business strategy, resources, management, accountability, 
and alignment to strategic initiatives. Support the Acquisition 
Decision Authority as it reviews acquisitions to ensure compliance 
with Acquisition Management Directive AD 102-01, and approves 
acquisitions to proceed to their next acquisition life-cycle phases 
upon satisfaction of applicable criteria. 

Officials: Chief Acquisition Officer; 
Roles: Normally serves as the Acquisition Decision Authority for Level 
1 and Level 2 acquisitions (see table 2); 
Designates the Component Acquisition Executives; 
Responsibilities: Management, administration, and oversight of the 
department's acquisition policies and procedures. 

Officials: Director of the Acquisition Program Management Division, 
Office of the Chief Procurement Officer; 
Roles: Serves as the DHS executive agent and coordinator for the 
acquisition review process and as the executive secretary of the 
Acquisition Review Board; 
Responsibilities: Developing and maintaining acquisition policy, 
procedures, and guidance; providing support and assistance to 
department acquisition and acquisition personnel. 

Officials: Director of the Cost Analysis Division, Office of the Chief 
Procurement Officer; 
Roles: Serves as the focal point within DHS for policy, process, and 
procedures regarding acquisition cost estimating and analysis; 
Responsibilities: Assessing life-cycle cost estimates for Level 1 
acquisitions, assisting acquisition management offices by providing 
guidance and support regarding data sources, methodology, modeling, 
and documentation. 

Officials: Component Head; 
Roles: The highest ranking individual within a component, nominates 
the Component Acquisition Executive; 
Responsibilities: Oversees acquisition within the component in 
accordance with DHS acquisition policies and procedures, and ensures 
sound management, review, support, approval, and oversight of all 
types of acquisitions within the component. 

Officials: Component Acquisition Executive; 
Roles: Nominated by the component head and designated by the Chief 
Acquisition Officer, the senior acquisition official within a 
component; 
Responsibilities: Establishing acquisition processes within the 
component; managing the component's acquisition portfolio; and serving 
as the Acquisition Decision Authority for Level 3 acquisitions, and 
Level 2 acquisitions if assigned by the Chief Acquisition Officer (see 
table 2). 

Source: GAO presentation of Department of Homeland Security 
Acquisition Management Directive AD 102-01, interim version, and 
Acquisition Instruction/Guidebook 102-01-001, interim version. 

[End of table] 

ARB reviews provide an opportunity to determine a program's readiness 
to proceed to the following life-cycle phase. The directive also 
requires the ARB chairperson to approve key acquisition documents 
critical to establishing a program's business case, operational 
requirements, acquisition baseline, and document testing and support 
plans. See appendix III for the four phases of the acquisition life 
cycle, related acquisition decision events, and key acquisition 
documents, such as the Mission Need Statement, Operational 
Requirements Document and Acquisition Program Baseline. 

The directive also changes the basis for program reviews from total 
acquisition costs to total life-cycle costs and assigns specific 
oversight responsibilities to the DHS components based on life-cycle 
cost estimates.[Footnote 16] The Under Secretary for Management can 
delegate authority for oversight of major acquisition programs with 
life-cycle cost estimates of less than $1 billion to a designated 
Component Acquisition Executive (CAE) with responsibility for managing 
the acquisition functions at each component.[Footnote 17] See table 2 
for a comparison of program review responsibilities based on dollar 
thresholds for the interim and previous acquisition management 
directive. 

Table 2: Comparison of Department and Component-Level Review under 
Acquisition Management Directive 102-01 (Interim) and Management 
Directive 1400: 

Acquisition Management Directive 102-01: 

Cost basis and level of review for each management directive: Life- 
cycle cost estimate; 
Level 1: $1 billion or greater (major programs); 
Level 2: $300 million to $1 billion (major programs); 
Level 3: Less than $300 million (nonmajor programs). 

Cost basis and level of review for each management directive: Level of 
review; 
Level 1: Department; 
Level 2: Department or component; 
Level 3: Component. 

Management Directive 1400: 

Cost basis and level of review for each management directive: Life- 
cycle cost estimate (for information technology investments); 
Level 1: Greater than $200 million; 
Level 2: Between $100 million and $200 million; 
Level 3: Between $20 million and $100 million. 

Cost basis and level of review for each management directive: 
Acquisition cost (for other than information technology investments); 
Level 1: Greater than $100 million; 
Level 2: Between $50 million and $100 million; 
Level 3: N/A. 

Cost basis and level of review for each management directive: Level of 
review; 
Level 1: Department; 
Level 2: Department; 
Level 3: Department. 

Source: GAO presentation of information in Acquisition Management 
Directive 102-01 and Management Directive 1400. 

[End of table] 

Acquisition Review Board Activities: 

DHS has increased its departmental oversight activities, reviewing 7 
programs in fiscal year 2008 and 25 programs--10 more than originally 
planned--in fiscal year 2009.[Footnote 18] However, at the end of 
fiscal year 2009, only 24 of 67 major acquisition programs had been 
reviewed by the ARB. As they have not yet been able to review all 
programs, DHS oversight officials told us they have prioritized ARB 
reviews based on program funding levels and a program's stage in the 
acquisition life cycle. Officials also indicated they may waive some 
oversight requirements on a case-by-case basis, without clear 
criteria, for programs that have passed certain phases--such as 
departmental approval of a Mission Need Statement for a program that 
has already deployed a capability.[Footnote 19] Additionally, to 
provide some level of departmental oversight for major programs not 
yet reviewed by the ARB, DHS acquisition oversight staff worked with 
selected components to conduct brief reviews of acquisition portfolios 
and examined 61 of 67 major acquisition programs during fiscal year 
2009. These reviews have helped DHS to identify and prioritize 
programs for the more detailed ARB reviews. 

DHS acquisition oversight officials said that funding and staffing 
levels have limited the number of programs they can review. The 
department's oversight office increased its staff from 8 government 
employees in 2008 to 22 government employees by the end of fiscal year 
2009 and plans to hire another 11 government employees in 2010. 
However, budget documentation suggests this staffing level will not 
provide the capacity needed to support the 50 to 60 annual ARB 
meetings that acquisition oversight officials said would be needed to 
oversee all of DHS's major acquisitions. DHS has not produced a plan 
identifying overall staffing and skill levels needed to meet the 
department's acquisition oversight needs. We have previously 
recommended that DHS identify and align sufficient management 
resources to implement oversight reviews in a timely manner throughout 
the investment life cycle.[Footnote 20] 

In 2008, we found that limitations in the department's ability to 
conduct formal investment reviews led DHS component officials to seek 
approval directly from the Deputy Secretary; as a result, some 
decisions were very informal and DHS officials said they did not 
always know whether a decision had been made. We recommended that DHS 
ensure investment decisions are transparent and documented as 
required. Oversight officials have since documented ARB decisions with 
Acquisition Decision Memorandums including action items and timeframes 
for addressing them. Memorandums from fiscal years 2008 and 2009 ARB 
meetings most often instructed programs to draft or redraft key 
acquisition documents that help present business cases. Our work at 
the Department of Defense (DOD) has found that a program must have the 
key elements of a business case before any measurement of its 
performance can be valuable.[Footnote 21] Action items also instructed 
programs to identify alternative acquisition approaches; document 
testing, implementation or support plans; and produce summaries of 
related activities within DHS and DOD, including similar acquisitions. 
Oversight officials and program officials said they work together to 
address action items and noted that it can be an iterative process. As 
of September 2009, oversight officials reported that 13 of 26 programs 
[Footnote 22] had not addressed all action items by established 
deadlines, and approximately a quarter of all action items were 
completed late or overdue, as shown in table 3. 

Table 3: Acquisition Decision Memorandum Action Items (fiscal years 
2008 and 2009): 

Action items: Completed; 
Assigned: 57; 
Late or overdue: 17. 

Action items: Outstanding; 
Assigned: 98; 
Late or overdue: 24. 

Action items: Total; 
Assigned: 155; 
Late or overdue: 41. 

Source: GAO presentation of DHS data for 26 programs reviewed in 
fiscal years 2008 and 2009. 

[End of table] 

Tracking Program Status: 

In 2008, we found DHS had not fully implemented the periodic reporting 
system intended to track program performance data, and many programs 
had cost, schedule, or performance shortfalls, while nearly 80 percent 
of major programs lacked basic acquisition documents, such as program 
baselines. We recommended that DHS establish a mechanism to track on a 
regular basis major investments and ensure compliance with department- 
level decisions. DHS's directive requires major programs to 
participate in an acquisition reporting process, and DHS has developed 
the Next Generation Periodic Reporting System, to capture and track 
key program information, including cost and schedule performance, 
contract awards, and program risks. The database became fully 
operational in September 2009, and DHS expects program offices to 
update program data each month. As of November 2009, DHS told us that 
108 major and nonmajor programs were reporting into the database. 
Acquisition oversight officials review these data in preparation for 
upcoming reviews; however, the database relies on self-reported data, 
which is not independently verified outside of the program. 

Component Oversight: 

With regard to component oversight, the DHS guidebook allows the Under 
Secretary for Management to delegate acquisition decision authority 
for Level 2 acquisition programs provided that (1) the respective 
component has a departmentally approved Component Acquisition 
Executive (CAE) in place, (2) the component has working policies and 
processes consistent with the current acquisition management 
directive, and (3) the component's CAE has adequate support staff 
commensurate with the size of the delegated portfolio. In 2008, we 
found that component review processes were not fully in place, and we 
recommended that DHS ensure that components have established processes 
to manage major investments consistent with departmental policies and 
establish a mechanism to ensure major investments comply with 
established component and departmental investment review policy 
standards. In 2008, DHS established the position of CAE to implement, 
manage, and oversee the components' acquisition processes. As of 
November 2009, the Under Secretary for Management had approved CAE 
nominations at seven components, but had not yet delegated decision 
authority because components are still in the process of developing 
policies consistent with the department's revised directive and 
reaching staff levels sufficient to oversee their respective 
acquisition programs. Component acquisition oversight activities vary 
across components. While officials from five of the six component 
acquisition oversight offices we met with said that they had accounted 
for and were tracking all of their major acquisition programs, Federal 
Emergency Management Agency acquisition officials said they were still 
working to identify all of their major acquisitions, and that they had 
only assessed programs accounting for about $5 billion of $30 billion 
in estimated life-cycle costs for their acquisition portfolio. 
[Footnote 23] Furthermore, four of the components we reviewed reported 
challenges involving staffing levels, and two of the four specifically 
stated that staff vacancies were preventing them from further 
supporting oversight efforts. 

Acquisition Oversight and Budget Decisions: 

In 2008, we found that the acquisition review process had not 
appropriately informed DHS's annual budget process for funding major 
programs, and that many major programs received funding without 
validation of mission needs and requirements, largely because 
department-level reviews were seldom conducted. We reported that the 
Joint Requirements Council, which is responsible for validating 
program requirements, stopped meeting in 2006 and had not effectively 
carried out its responsibilities involving identification of 
crosscutting opportunities and overlapping or common requirements. We 
recommended that the department ensure that budget decisions are 
informed by the results of investment reviews including approved 
acquisition information and life-cycle cost estimates and reinstate 
the Joint Requirements Council or establish another departmental 
oversight board to perform this function. 

The department's guidebook states that both the Joint Requirements 
Council and the ARB should inform the department's budget decisions, 
and that they must do so effectively in order to deliver needed 
capabilities to end users. However, while the ARB has begun to meet 
more frequently, most major programs have not been reviewed. Further, 
acquisition management processes do not inform budget decisions as 
required by DHS policy. DHS has not reestablished the Joint 
Requirements Council, although DHS oversight officials said that by 
fall 2010, they expect to complete a proposal for DHS leadership to 
consider and approve that would address this need. Shortly thereafter, 
DHS plans to initiate a limited pilot program, which will not review 
all programs departmentwide. 

Acquisition Performance and Program Challenges: 

Our prior work has found that program performance metrics for cost and 
schedule can provide useful indicators of the health of acquisition 
programs and, when assessed regularly for changes and the reasons that 
cause changes, such indicators can be valuable tools for improving 
insight and oversight of individual programs as well as the total 
portfolio of major acquisitions.[Footnote 24] We have also found that 
the following factors are important to successful acquisitions 
delivering capabilities within cost and schedule: realistic program 
baselines with stable requirements for cost, schedule, and 
performance; an adequate and skilled program office workforce; and 
knowledge of long-term support requirements.[Footnote 25] Importantly, 
program performance cannot be accurately assessed without valid 
baseline requirements established at the program start, particularly 
those that establish the minimum acceptable threshold required to 
satisfy user needs.[Footnote 26] 

Most of the selected DHS programs we reviewed exhibited cost growth 
and schedule delays from initial estimates. DHS acquisition oversight 
officials have raised concerns about the accuracy of cost estimates 
for most major programs, making it difficult to assess the 
significance of the cost growth we identified. Further, over half of 
the programs we reviewed awarded contracts to initiate acquisition 
activities without component or department approval of documents 
essential to planning acquisitions, setting operational requirements, 
and establishing acquisition program baselines. Programs also 
experienced other acquisition planning challenges--potential and 
realized program issues that contribute to negative performance 
outcomes--such as staffing shortages, and lack of sustainment planning 
as well as common execution challenges related to a range of technical 
capability, partner dependence, and funding issues. 

We selected 18 DHS programs for this review--16 major programs and two 
nonmajor programs. The two nonmajor programs selected, and one major 
program that had not started acquisition activities at the time of our 
review,[Footnote 27] were excluded from the analysis of overall 
acquisition performance and program challenges. As a result, we 
reviewed cost or schedule data for 15 major programs. Schedule data 
were not complete for two programs--the Automated Commercial 
Environment and US-VISIT.[Footnote 28] Figure 1 provides the status of 
the selected programs at the time of our review. 

Figure 1: Summary of DHS Acquisition Programs Assessed: 

[Refer to PDF for image: vertical bar graph] 

Total programs reviewed: 18: 
Excluded from analysis: Nonmajor programs: 2; 
Excluded from analysis: Pre-acquisition programs: 1; 
Programs included in analysis: 15; 
Programs with incomplete schedule data: 2; 
Programs with cost growth or schedule delays: 12; 
Programs without cost growth or schedule delays: 1. 

Source: GAO analysis of DHS data. 

[End of figure] 

Most Programs Experienced Cost Increases and Schedule Delays: 

We assessed life-cycle cost and acquisition cost data for the 15 major 
acquisition programs in our review. Accurate cost estimates are 
critical to making funding decisions, evaluating resource 
requirements, and developing performance measurement baselines. Life-
cycle costs include all resources and associated cost elements 
required to develop, produce, deploy, and sustain a particular program 
from initial concept through operations, support, and disposal. 
Acquisition costs include costs for all supplies and services for a 
designated investment. DHS policy requires acquisition oversight 
officials to assess the accuracy of life-cycle cost estimates for all 
major programs estimated to exceed $1 billion. The DHS guidebook 
includes an appendix on life-cycle cost estimates.[Footnote 29] The 
responsible officials have raised concerns that many programs used 
cost estimation methods that did not follow established best 
practices, such as fully defining program requirements, accounting for 
sustainment costs, and including costs for the full life cycle of a 
program. As a result, officials have doubts about the credibility, 
comprehensiveness, and accuracy of most program cost estimates. 
Officials said they are working to address this concern by assisting 
programs in developing cost estimates, and obtaining independent cost 
estimates for selected high-risk programs. [Footnote 30] To provide 
additional support, they have temporarily placed cost analysis 
specialists within selected components. 

Most programs we reviewed reported cost growth from initial to latest 
estimates. Inaccurate or incomplete cost estimates were likely a 
factor in cost growth for the programs we reviewed, according to DHS 
officials. In some cases, programs reported that changes in scope or 
requirements contributed to cost growth. Further, initial cost 
estimates for most programs were developed after the start of 
acquisition activities, so they do not capture earlier cost changes. 
Because DHS does not have one consistent source for acquisition and 
life-cycle cost estimates, we analyzed the best available data 
reported to OMB and congressional appropriations committees for each 
of the major programs in our review.[Footnote 31] Table 4 summarizes 
the changes to life-cycle and acquisition cost estimates for the 
programs in our review. 

Table 4: DHS Major Acquisition Program Costs: 

Customs and Border Protection: 

Automated Commercial Environment; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$2,125; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$2,222; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 5%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$4,776; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$4,532; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: -5%; 
Months between initial and current estimates: 37. 

SBInet; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$284; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$1,885; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 564%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$579; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$3,738; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 546%; 
Months between initial and current estimates: 42. 

TECS Modernization; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$406; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$410; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 1%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$888; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$1,104; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 24%; 
Months between initial and current estimates: 24. 

Western Hemisphere Travel Initiative; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$312; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$311; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 0%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$863; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$1,362; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 58%; 
Months between initial and current estimates: 24. 

National Protection and Programs Directorate: 

National Cybersecurity Protection System; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$664; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$546; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: -18%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$1,366; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$1,257; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: -8%; 
Months between initial and current estimates: 8. 

US-VISIT Unique Identity; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$160; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$79; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: -51%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$225; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$132; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: -41%; 
Months between initial and current estimates: 8. 

Transportation Security Administration: 

Electronic Baggage Screening Program; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$11,360; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$15,316; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 35%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$19,930; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$23,696; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 19%; 
Months between initial and current estimates: 17. 

Passenger Screening Program; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$1,872; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$2,559; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 37%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$2,593; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$4,306; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 66%; 
Months between initial and current estimates: 17. 

Secure Flight; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$97; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$153; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 59%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$685; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$1,362; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 99%; 
Months between initial and current estimates: 28. 

United States Coast Guard: 

C4ISR; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$1,353; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$1,353; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 0%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$1,353; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$1,353; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 0%; 
Months between initial and current estimates: 28. 

Maritime Patrol Aircraft; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$1,706; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$2,223; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 30%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$22,773; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$12,285; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: -46%; 
Months between initial and current estimates: 42. 

National Security Cutter; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$3,450; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$4,749; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 38%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$22,998; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$24,277; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 6%; 
Months between initial and current estimates: 42. 

Rescue 21; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$827; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$1,067; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 29%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$1,639; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$2,693; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 64%; 
Months between initial and current estimates: 28. 

Response Boat-Medium; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$401; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$610; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 52%; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$1,210; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$1,419; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: 17%; 
Months between initial and current estimates: 68. 

Sentinel; 
Acquisition cost estimate (then-year dollars in millions): Initial: 
$3,206; 
Acquisition cost estimate (then-year dollars in millions): Current: 
$3,928; 
Acquisition cost estimate (then-year dollars in millions): Percentage 
change: 23%; 
[Empty]; 
Life-cycle cost estimate (then-year dollars in millions): Initial: 
$22,256; 
Life-cycle cost estimate (then-year dollars in millions): Current: 
$14,475; 
Life-cycle cost estimate (then-year dollars in millions): Percentage 
change: -35%; 
Months between initial and current estimates: 31. 

Source: GAO analysis of official cost data reported in Acquisition 
Program Baselines and Quarterly Acquisition Reports to Congress to the 
House and Senate Appropriations Committees for the Maritime Patrol 
Aircraft, National Security Cutter, Response Boat-Medium and Sentinel 
Class programs. For all other programs, GAO analyzed official cost 
data in the Exhibit 300 required by OMB. 

[End of table] 

Changes in life-cycle cost estimates ranged widely from decreases of 
over 40 percent to an increase of over 500 percent. Nine of the 15 
programs reported cost growth from initial to current estimates. The 
three programs reporting significant cost decreases also reported 
inconsistencies in estimating life-cycle costs. The interval of 
initial and latest cost estimates varied from 8 months to over 5 years 
for the programs we reviewed, and as a result some programs had a 
longer period of time to incur cost growth. Changes in acquisition 
cost estimates also ranged widely--from a decrease of 50 percent to an 
increase of over 500 percent. Of the 11 programs with acquisition cost 
growth, 8 programs reported cost growth of over 25 percent. 

Almost all of the selected major acquisition programs experienced 
delays in delivering system capabilities. We assessed schedule 
performance for delivering both initial capabilities, when initial end-
users would receive the new system and could use it operationally, as 
well as delivery of full capabilities, the point at which all end-
users would receive the system. DHS guidance requires major programs 
to set a formal schedule baseline prior to the start of an acquisition 
in order to measure program performance in achieving its 
goals.[Footnote 32] Schedule delays can lead to loss of program 
credibility with stakeholders, increased acquisition costs, new 
systems not being available to meet department needs, and continued 
use of less capable systems. Fifteen of the major programs we reviewed 
reported estimated or actual schedule delays in delivery of initial 
operating capability of an average of 12 months, and eight programs 
reported delays of a year or more. Thirteen programs reporting data on 
delivery of full operating capability indicated estimated delays of 
over 2 years on average. None of the selected programs reported 
delivering full operating capability for all increments. Figure 2 
summarizes the estimated schedule delays to full operating capability 
for major programs reporting data. 

Figure 2: Programs with Estimated Schedule Delay to Full Capability: 

[Refer to PDF for image: vertical bar graph] 

On time: 3 programs; 
Up to 2 years late: 4 programs; 
Over 2 years to 4 years late: 1 program; 
More than 4 years late: 5 programs. 

Source: GAO analysis of DHS data. 

Note: Programs do not total to 15 as 2 programs did not report: 
Automated Commercial Environment and US-VISIT. 

[End of figure] 

Several Program Challenges Affect Ability to Deliver Within Cost and 
on Time: 

The major acquisition programs we assessed experienced similar 
planning challenges affecting cost and schedule outcomes: unapproved 
or unstable baseline requirements; program office workforce shortages; 
long-term support, and acquisition cost planning. Table 5 summarizes 
the program planning challenges for each of the programs we reviewed. 
Our prior work has shown that establishing a sound business case is 
key to a successful acquisition that delivers capabilities within cost 
and schedule and minimizes the challenges we identified.[Footnote 33] 
The first, and perhaps best, opportunity to reduce acquisition risk is 
in the planning phase, when critical decisions are made that have 
significant implications for the overall success of an acquisition. We 
also identified execution challenges related to a range of technical 
capability, partner dependence, and funding issues. 

Table 5: Summary of Major Program Planning Challenges: 

Customs and Border Protection: 

Automated Commercial Environment; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: N/A[D]. 

SBInet, Block 1[C]; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Empty]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Check]; 
Lack of sustainment planning: [Empty]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

TECS Modernization; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

Western Hemisphere Travel Initiative; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Empty]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

National Protections and Programs Directorate: 

National Cybersecurity Protection System; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Empty]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Check]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Empty]; 
Performance: Schedule delays: [Empty]. 

US-VISIT Unique Identity; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Check]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Empty]; 
Performance: Schedule delays: N/A[D]. 

Transportation Security Administration: 

Electronic Baggage Screening Program; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Check]; 
Lack of sustainment planning: [Empty]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

Passenger Screening Program; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Empty]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

Secure Flight; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

United States Coast Guard: 

C4ISR; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Empty]; 
Performance: Cost growth[B]: [Empty]; 
Performance: Schedule delays: [Check]. 

Maritime Patrol Aircraft; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Check]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

National Security Cutter; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Check]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

Rescue 21; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Empty]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Empty]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

Response Boat-Medium; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Check]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Empty]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Check]; 
Lack of sustainment planning: [Check]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

Sentinel; 
Major program planning challenges: Baseline requirements: Unapproved 
or unstable baseline requirements: Customs and Border Protection: 
[Empty]; 
Major program planning challenges: Baseline requirements: Lack of 
timely approval of acquisition documents[A]: [Empty]; 
Major program planning challenges: [Empty]; 
Major program planning challenges: Program office workforce shortages: 
[Empty]; 
Lack of sustainment planning: [Empty]; 
Performance: Cost growth[B]: [Check]; 
Performance: Schedule delays: [Check]. 

Source: GAO analysis of DHS data: 

[A] We assessed whether key acquisition documents were approved at 
either the component or department level. 

[B] Cost Growth refers to either acquisition or life-cycle cost growth 
or both. 

[C] Cost performance refers to the entire SBInet program. 

[D] N/A indicates that reportable data were not available. 

[End of table] 

Baseline Requirements: 

Our prior work has found that program performance cannot be accurately 
assessed without valid baseline requirements established at the 
program start[Footnote 34]. According to DHS guidance, the baseline 
requirements must include a threshold value that is the minimum 
acceptable value which, in the user's judgment, is necessary to 
satisfy the need. If threshold values are not achieved, program 
performance is seriously degraded, the program may be too costly, or 
the program may no longer be timely. Failure to achieve a threshold 
would require rebaselining or termination of the program based upon a 
decision by the Acquisition Decision Authority. Inadequate knowledge 
of program requirements is a key cause of poor acquisition outcomes, 
and as programs move into the execution phase of the acquisition 
process, problems become much more costly to fix. DHS's acquisition 
guidance states that the program baseline is the contract between the 
program and departmental oversight officials regarding cost, schedule, 
and technical performance of the program. 

Over half of the programs we reviewed awarded contracts to initiate 
acquisition activities without component or department approval of 
documents essential to planning acquisitions, setting operational 
requirements, and establishing acquisition program baselines. Our 
prior work has shown that the development, review, and approval of 
these key documents minimize the risks of poorly defined requirements 
and plans negatively affecting program performance.[Footnote 35] The 
Federal Acquisition Streamlining Act of 1994 requires agencies to 
approve or define the cost, performance, or schedule goals for major 
acquisition programs. Although DHS policy has required major 
acquisition programs to set cost, schedule, and performance goals 
prior to the start of an acquisition since its first acquisition 
policy was issued in 2003,[Footnote 36] 7 of 15 programs in our review 
did not have approved baselines until 2 years or more after program 
start. For example, the Secure Flight program did not have an approved 
program baseline until over 4 years after program start, and the TECS 
Modernization program did not have a component or department approved 
baseline after more than 6 years. 

Among the 15 programs, delays ranged from 1 month to over 4 years 
after contract award for other key acquisition documents, such as the 
Mission Need Statement and the Operational Requirements Document. The 
Mission Need Statement outlines the specific functional capabilities 
required to accomplish DHS's mission and objectives, along with 
deficiencies and gaps in these capabilities. The Operational 
Requirements Document includes key performance parameters and 
describes the mission, capabilities, and objectives to provide needed 
capabilities. Figure 3 shows programs with key documents and when they 
were approved. 

Figure 3: Key Document Approval Time frames: 

[Refer to PDF for image: vertical bar graph] 

On time: 
Mission Need Statement: 6 programs; 
Operational Requirements Document: 3 programs; 
Acquisition Program Baseline: 7 programs. 

Up to 1 year late: 
Mission Need Statement: 4 programs; 
Operational Requirements Document: 2 programs; 
Acquisition Program Baseline: 0. 

More than 1 year late: 
Mission Need Statement: 5 programs; 
Operational Requirements Document: 10 programs; 
Acquisition Program Baseline: 8 programs. 

Source: GAO analysis of DHS data. 

[End of figure] 

Most of the programs that had established baseline requirements 
changed or plan to change them. For example, seven programs with an 
approved program baseline changed key requirements after their initial 
approval. An additional three programs were revising baseline 
requirements, pending APB approval, at the time we completed our 
review. 

Program Office Workforce: 

Program offices reported filling 79 percent of all government staff 
positions; however, programs also reported high levels of government 
staff vacancies for certain positions.[Footnote 37] Our prior work at 
DHS found shortcomings in acquisition workforce planning, including a 
lack of sufficient data to assess gaps in skills and staffing levels. 
[Footnote 38] Lack of adequate staff, both in terms of skill and 
staffing levels, increases the risk of insufficient program planning 
and contractor oversight, and has been associated with negative cost 
and schedule outcomes in major acquisition programs, emphasizing the 
importance of sufficient, experienced staff for successful acquisition 
outcomes.[Footnote 39] Figure 4 provides more details on government 
and contractor staff for the programs we reviewed. 

Figure 4: DHS Major Program Government Staff and Contractor Support: 

[Refer to PDF for image: stacked horizontal bar graph] 

Total workforce: 
Government staff: 40%; 
Contractor staff: 60%; 
Total: 1,760. 

Customs and Border Protection: 

Automated Commercial Environment: 
Government staff: 63%; 
Contractor staff: 37%; 
Total: 108. 

SBInet: 
Government staff: 50%; 
Contractor staff: 50%; 
Total: 175. 

TECS Modernization: 
Government staff: 57%; 
Contractor staff: 43%; 
Total: 7. 

Western Hemisphere Travel Initiative: 
Government staff: 23%; 
Contractor staff: 77%; 
Total: 88. 

National Protection and Programs Directorate: 

National Cybersecurity Protection System: 
Government staff: 8%; 
Contractor staff: 92%; 
Total: 133. 

US-VISIT: 
Government staff: 38%; 
Contractor staff: 62%; 
Total: 421. 

Transportation Security Administration: 

Electronic Baggage Screening Program: 
Government staff: 23%; 
Contractor staff: 77%; 
Total: 116. 

Passenger Screening Program: 
Government staff: 33%; 
Contractor staff: 67%; 
Total: 48. 

Secure Flight: 
Government staff: 38%; 
Contractor staff: 62%; 
Total: 300. 

U.S. Coast Guard: 

C4ISR: 
Government staff: 31%; 
Contractor staff: 69%; 
Total: 103. 

Maritime Patrol Aircraft: 
Government staff: 85%; 
Contractor staff: 15%; 
Total: 7. 

National Security Cutter: 
Government staff: 63%; 
Contractor staff: 37%; 
Total: 79. 

Rescue 21: 
Government staff: 81%; 
Contractor staff: 19%; 
Total: 80. 

Response Boat-Medium: 
Government staff: 56%; 
Contractor staff: 44%; 
Total: 71. 

Sentinel Class Patrol Boat: 
Government staff: 54%; 
Contractor staff: 46%; 
Total: 24. 

Source: GAO analysis of DHS data. 

Note: US-VISIT totals include staff for all investments within the 
program. 

[End of figure] 

Filled government positions for each program ranged from 42 percent to 
100 percent. Over half of the major programs reported that contractors 
comprised 50 percent or more of all staff supporting program offices. 
Similarly, our review of major acquisitions at the DOD found that, in 
2009, contractors filled 51 percent of program office positions. 
[Footnote 40] 

Further, our work on contractors in the workforce has noted that use 
of contractors to perform certain functions can place the government 
at risk of transferring government responsibilities to contractors, 
and potentially result in loss of government control over and 
accountability for policy and program decisions.[Footnote 41] We 
previously found that DHS used contractor support to provide services 
related to planning activities, acquisition support, and policy 
development--services that closely supported inherently governmental 
functions. As a result, we recommended that DHS establish guidance for 
determining the appropriate mix of government and contractor staff to 
meet mission needs, and assess program office staff and expertise 
necessary to provide sufficient oversight of contractor 
services.[Footnote 42] DHS is still working to address this 
recommendation. 

All programs we reviewed report having a permanently assigned program 
manager certified to manage a major acquisition as required by DHS 
policy. By comparison, in 2007, 40 percent of major DHS programs 
lacked a program manager with the required acquisition certification 
level.[Footnote 43] Four programs reported program manager tenure of 3 
or more years, and six programs report program manager tenure of 1 
year or less. Our prior work has found frequent program manager 
turnover can result in a lack of accountability for a program's 
business case and performance outcomes.[Footnote 44] 

Sustainment Planning: 

Prior to the start of an acquisition, DHS acquisition policy requires 
an approved Integrated Logistics Support Plan for all major programs. 
This plan defines the program's sustainment and supportability 
strategy and can comprise a significant portion of total life-cycle 
costs--approximately 60 percent or more according to DHS guidance. 
OMB's capital planning guide also calls for sustainment planning to 
properly plan for and actively manage investments throughout the 
program. Our prior work has found that understanding how programs will 
be sustained in future years, along with the associated costs, is a 
prerequisite for valid life-cycle cost estimates.[Footnote 45] 

Most programs reported that they have developed a support plan, but 
only six programs have a support plan approved at the component level, 
and none of the programs in our review had a plan approved by DHS, as 
required. Table 6 shows the status of the plans for the 15 programs 
reporting. 

Table 6: Status of Integrated Logistics Support Plans (ILSP): 

Component: Customs and Border Protection: 

Program: Automated Commercial Environment; 
ILSP (approved or unapproved): [Empty]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Program: SBInet, Block 1; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Check]; 
DHS-approved ILSP: [Empty]. 

Program: TECS Modernization; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Program: Western Hemisphere Travel Initiative; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Component: National Protections and Programs Directorate: 

Program: National Cybersecurity Protection System; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Program: US-VISIT Unique Identity; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Component: Transportation Security Administration: 

Program: Electronic Baggage Screening Program; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Check]; 
DHS-approved ILSP: [Empty]. 

Program: Passenger Screening Program; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Check]; 
DHS-approved ILSP: [Empty]. 

Program: Secure Flight; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Component: United States Coast Guard: 

Program: C4ISR; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Check]; 
DHS-approved ILSP: [Empty]. 

Program: Maritime Patrol Aircraft; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Program: National Security Cutter; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Program: Rescue 21; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Check]; 
DHS-approved ILSP: [Empty]. 

Program: Response Boat-Medium; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Empty]; 
DHS-approved ILSP: [Empty]. 

Program: Sentinel Class Patrol Boat; 
ILSP (approved or unapproved): [Check]; 
Component-approved ILSP: [Check]; 
DHS-approved ILSP: [Empty]. 

Number of programs: 
ILSP (approved or unapproved): 14; 
Component-approved ILSP: 6; 
DHS-approved ILSP: 0. 

Total number of programs with available data: 
ILSP (approved or unapproved): 15; 
Component-approved ILSP: 15; 
DHS-approved ILSP: 15. 

Source: GAO analysis of DHS-provided data. 

[End of table] 

Program Execution Challenges: 

In addition to challenges related to acquisition planning, the 
programs we reviewed reported program execution challenges related to 
technical capability, partner dependence, and funding. While the 
challenges we identify below are not exhaustive, this summary provides 
insight into the issues programs reported. 

Technical capability includes hardware or software functionality, such 
as the operation of radar equipment in the case of SBInet, or legacy 
equipment nearing the end of its useful life in the case of the 
Electronic Baggage Screening Program. Testing helps to ensure that 
programs meet technical requirements to deliver needed capabilities, 
and our prior work has found that programs proceeding with 
acquisitions prior to completion of testing can result in delays in 
achieving technical capability. Several programs in our review 
reported substantial investment in acquisitions prior to completion of 
testing. For example, three Coast Guard programs we reviewed, Maritime 
Patrol Aircraft, Response Boat-Medium and Sentinel, reported placing 
orders for or receiving significant numbers of units prior to 
completing testing to demonstrate that what the programs are buying 
meets Coast Guard needs. Our prior work has found that resolution of 
problems discovered during testing can sometimes require costly 
redesign or rework.[Footnote 46] 

Programs also raised dependence on corporations, other agencies, or 
other programs as a challenge to delivering certain capabilities. For 
example, Secure Flight officials reported dependence on commercial 
aircraft operators complying with the implementation schedule as the 
greatest program risk. In another case, Customs and Border 
Protection's delays in network upgrades have negatively affected 
response times for the Western Hemisphere Travel Initiative. 

Almost half of all programs reported concerns over funding, although 
the nature and cause of those concerns varied among programs. Our 
prior work found that the budget process for funding major 
acquisitions and the investment review process were not aligned. As a 
result, many major DHS investments received funding without 
determining that mission needs and requirements were justified. For 
example, after DHS approved and funded the Automated Commercial 
Environment program, program officials found that they did not have a 
full understanding of all requirements and have experienced cost 
growth. Program officials said the future of the program is dependent 
on departmental funding decisions. In addition, our past work found 
that many major acquisition budget decisions were reached without life-
cycle cost estimates, which are essential to making informed budget 
decisions. For example, the Electronic Baggage Screening Program 
reported that annual compliance costs and recapitalization expenses, 
when combined with recurring programwide costs, have sometimes 
exceeded the budget. In future years, program costs could grow 
significantly as cost estimates are reassessed to include new 
requirements. DHS has been working toward validating the program's 
cost estimate. Changes in mandated requirements, such as legal or 
regulatory changes that require system changes, can also affect 
program budgets. For example, Rescue 21 reported cost increases due to 
new protocols and external technology standards. 

Program Assessments: 

The two-page assessments of the 18 programs we reviewed provide an 
overview of each program and describe the reported challenges. On the 
first page of the assessment, we present a general description; a 
program status narrative; a timeline identifying key dates for the 
program; essential information about the program; a table showing the 
initial and latest estimates of cost, schedule, and quantities; and 
key program issues under "Program Challenges." We present approval 
dates for key program documents requiring departmental or component 
approval depending on the phase of the acquisition. On the second page 
of the assessment, we provide background information, a description of 
program performance, and an analysis of key program challenges. 

The assessments are based on program office reported information as of 
2009 with the exception of the cost data. We based our analysis of 
cost on OMB's Exhibit 300s as of January or February 2010 and the 
Coast Guard's Quarterly Acquisition Reports to Congress as these 
sources represented more complete and official data used for making 
important planning and budgeting decisions. See appendix I for more 
information on our scope and methodology for reporting on cost and 
schedule data, program challenges, and program office workforces. 

[End of section] 

Customs and Border Protection: Automated Commercial Environment: 

[Photograph: Source: Automated Commercial Environment Program] 

The Automated Commercial Environment is the commercial trade 
processing system being	developed by U.S. Customs and Border 
Protection (CBP) that aims to facilitate the movement of legitimate 
trade, strengthen border security, and serve as the single point of 
collection and access for trade data among federal agencies. 

Current Status: 
The initial software releases delivered between 2003 and 2005 
significantly exceeded their estimated costs. Three remaining software 
releases will not be completed as initially planned and future 
releases will be funded based on individual business cases. 
	
Timeline: 

Start of acquisition (5/01); 
Initial capability (Release 1) (2/03); 
Release 2 (10/03); 
DHS program approval (11/03); 
Release 3 (8/04); 
Release 4 (4/05); 
Advanced targeting (9/07); 
Reference data (1/09); 
Additional entry summary types (2/10); 
Full operating capability (TBD). 
				
Program Essentials: 

Component: Customs and Border Protection; 
Major contractor(s): International Business Machines Global Services; 
Fiscal year 2010 funding requested: $268 million; 
Program office workforce: 68 total government positions planned; 68 
total government staff employed; 40 support contractors. 

Program Challenges: 
* Unstable and undefined requirements; 
* Software testing issues; 
* Schedule delays; 
* Cost growth and lack of funding. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $2,125 million[A]; 
Total acquisition cost: Latest estimate: $2,222 million[A]; 
Life-cycle cost estimate: Initial estimate: $4,776 million[A]; 
Life-cycle cost estimate: Latest estimate: $4,532 million[A]; 
Quantity: Initial estimate: N/A; 
Quantity: Latest estimate: N/A; 
Initial capability: Initial estimate: Feb. 2003; 
Initial capability: Latest estimate: Feb. 2003; 
Full capability: Initial estimate: Sept. 2010; 
Full capability: Latest estimate: TBD. 

[A] Note: Estimates submitted to the Office of Management and Budget 
for 2008 and 2011. Program officials do not expect ACE to deliver all 
initially planned capabilities. 

Key Program Documents: 

Initial version of:Acquisition Program Baseline; 
Department approval date: Jan. 2006. 

Initial version of:Mission Need Statement; 
Department approval date: Oct. 2004. 

Initial version of:Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of:Acquisition Plan; 
Department approval date: Oct. 2004. 

Initial version of:Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Automated Commercial Environment: 

Background: 

Initiated in 2001 to support Title VI of the North American Free Trade 
Agreement, commonly known as the Customs Modernization Act, the 
Automated Commercial Environment program seeks to replace and 
supplement existing cargo processing technology. 

Deployed in phases, the program incrementally provides capabilities 
across all modes of transportation, replacing existing systems with a 
single, multimodal manifest system for land, air, rail, and sea cargo. 
The program will serve as the central data collection system for 
federal agencies needing access to international trade data, and is 
expected to deliver these capabilities in a secure, paper-free, web-
enabled environment. 

Operational capabilities already delivered by the program include 
screening cargo and conveyances, analyzing data to support targeting 
of high-risk entities, and processing truck manifests electronically. 

Performance: 

The initial software releases delivered between 2003 and 2005 
significantly exceeded their estimated costs. ACE's software lines of 
code increased from the acquisition program baselines's figure of 
1,156,566 to 4,255,000. According to program officials, the remaining 
software releases will not be completed in accordance with the program 
baseline, due to the program lacking sufficient funding to complete 
them as planned. The estimated cost growth for these releases is not 
yet included in the latest cost estimate, pending a decision being 
made on the future of the program. Due to limited funding, one release 
will likely be eliminated from the program and the two others will 
likely be disaggregated into a number of smaller projects, some of 
which will be discontinued. The decision as to which projects will be 
continued or cut will be based on available funding. 

The program office found in 2005 that it did not have a full 
understanding of all requirements and that existing requirements were 
missing about 20 percent of needed functionality. Program officials 
acknowledged the development of some software releases was not divided 
into sufficiently manageable blocks and requirements were not well 
defined from the outset of the program. 

Additionally, software integration testing of a key project was 
incomplete and allowed poor code to enter the system, although this 
code was not deployed. This resulted in a much longer system 
integration testing period than originally estimated, leading to 
programwide schedule delays. 

Challenges: 

The program has been executed using component-approved operational 
requirements that are not yet approved by DHS. Program officials said 
requirements growth and lack of requirements definition contributed to 
the schedule delays and contract cost overruns. Program officials said 
the future of the program is dependent on a number of factors, such as 
DHS funding decisions and the results of software testing. Program 
officials expect the remaining planned projects to move to smaller 
programs so they will have better-defined and more manageable 
requirements. Officials believe that simply restructuring the existing 
program would result in additional cost growth and schedule delays. 
The program is working with the department to better manage future 
requirements and program risks. For example, the department has 
recently tasked a high-level component official with taking the lead 
on the program's requirements' oversight and prioritization. 

Program Office Comments: 

The program office provided technical comments on a draft of this 
assessment, which were incorporated as appropriate. 

[End of section] 

Customs and Border Protection: SBInet Block 1: 

[Photograph: Source: SBInet Program Office] 

SBInet Block 1 is a surveillance, command, control, communications, 
and intelligence system being fielded in Arizona that is intended to 
mitigate or eliminate vulnerabilities along the international border 
between ports of entry. Block 1 is an element of DHS's Secure Border 
Initiative, a comprehensive, multiyear plan to secure the borders of 
the United States and reduce illegal cross border activities such as 
smuggling of economic migrants, illegal drugs, and people with 
terrorist intent. 

Current Status: 

DHS plans to complete Block 1 operational testing and evaluation and 
complete final acceptance of systems at the initial Block 1 sites by 
March 2011. Future project funding is being delayed by DHS until an 
assessment of SBInet is completed. 

Timeline: 
Start of acquisition (9/06); 
Preliminary design review (4/07); 
Procurement start (6/08); 
Program baseline approval (3/09); 
Operational testing complete (3/11); 
Nogales/Sonoita	deployments (12/11); 
Ajo-2/Casa Grande deployments (3/12); 
Naco/Douglas/Wilcox deployments (6/12)
Full operating capability (12/13). 
							
Program Essentials: 
Component: Customs and Border Protection; 
Major contractor(s): The Boeing Company; 
Fiscal year 2010 funding requested: $297.2 million; 
Program Office workforce: 161 total government positions planned; 
87 total government staff employed; 88 support contractors. 

Program Challenges: 
* Delayed approval of program baseline; 
* Schedule delays; 
* Technical problems; 
* Understaffing. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $284 million[A]; 
Total acquisition cost: Latest estimate: $1,885 million[A]; 
Life-cycle cost estimate: Initial estimate: $579 million[A]; 
Life-cycle cost estimate: Latest estimate: $3,738 million[A]; 
Quantity: Initial estimate: 1; 
Quantity: Latest estimate: 1; 
Initial capability: Initial estimate: Oct. 2008
Initial capability: Latest estimate: Mar. 2011
Full capability: Initial estimate: Dec. 2008
Full capability: Latest estimate: Dec. 2013 

[A] Note: Cost estimates are for overall SBInet program submitted to 
the Office of Management and Budget for 2008 and 2011.		
		
Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Mar. 2009. 

Initial version of: Mission Need Statement; 
Department approval date: Not yet approved. 

Initial version of: Operational Requirements Document; 
Department approval date: Mar. 2007. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

SBInet Block 1: 

Background: 

SBInet Block 1 is a border security system being developed and 
deployed to help secure portions of the international border in 
Arizona. The system will detect and track intruders using a set of 
fixed surveillance towers. The program is initially deploying to two 
sites, known as Tucson-1 and Ajo-1. The program plans to complete 
testing before DHS approves deployment at additional Block 1 sites. 
Tucson-1, the planned site of Block 1 operational testing and 
evaluation, covers 23 miles of border in one of CBP's busiest areas. 
We have reported since 2007 on acquisition and information technology 
management issues that increase the risk of SBInet underperformance.
Systems previously deployed in the Tucson area under the SBInet 
Project 28 pilot in 2008 did not fully meet CBP's expectations; Block 
1 will replace these systems. Our reviews and covert tests conducted 
over the years identified numerous security vulnerabilities along U.S. 
international borders and operational issues in program delays that 
limited SBInet usefulness to CBP. CBP told us in 2008 that Block 1 
would help address these vulnerabilities. 

Performance: 

The December 2006 SBInet Expenditure Plan that was approved by DHS 
planned for SBInet to be deployed in the Tucson and Yuma Sectors by 
December 2008. However, program officials now expect system 
deployments to continue until December 2013. They expect to complete 
operational testing and final acceptance of the initial Block 1 
systems at the Tucson-1 and Ajo-1 sites by March 2011. The Block 1 
program baseline currently requires the deployment of SBInet at all 
sites in Arizona by September 2011. Program officials told us that a 
decision on the deployment of SBInet beyond Block 1 at other locations 
would be made in the future. Contract cost estimates related to the 
Block 1 deployments have risen significantly higher than the initially 
estimated amounts. Program officials said that Block 1's delays, have 
led to substantial cost growth, and they expect to have an updated 
program cost estimate before SBInet's next department-level review. 
The program office reported that systems at Tucson-1 were
operational and used by Border Patrol for night operations as of March 
2010. The Homeland Security Secretary ordered a reassessment of the 
SBInet program in January 2010 citing unacceptable delays. In March 
2010, she announced that $50 million in program funding is being 
reallocated to other border security technologies, and that funding 
for future projects is on hold, pending the completion of an 
assessment of SBInet. 

Challenges: 

DHS approved the Block 1 acquisition program baseline more than 2 
years after the start of the SBInet acquisition, and 4 months after 
completion of the critical design review, precluding the initial 
design from being informed by approved program requirements. As of the 
fall of 2009, the program had identified several high and moderate 
risks that could prevent SBInet from delivering a system that meets 
the Border Patrol's needs under the existing schedule. Among these 
risks are problems with radar functionality, problems with image 
clarity, a lack of program analysis tools, and system security and 
sustainment risks. Program officials said that the radar may be 
modified to a point that it is no longer a commercial off-the-shelf 
item, possibly leading to higher costs and to the program not meeting 
a program requirement for using unmodified commercial equipment. 
Program officials identified risks related to unique environmental 
requirements at certain sites that could cause some systems deployed 
after Tucson-1 to undergo significant rework or not meet program 
requirements for correctly identifying detected subjects. 
Additionally, the SBInet program office is staffed substantially below 
planned staffing levels for government positions. 

Program Office Comments: 

The program office provided technical comments, which were 
incorporated as appropriate. As of March 2010, SBInet program 
officials indicated they did not expect any previously identified 
challenges to delay the completion of Tucson-1 or interfere with other 
currently planned program activities. 

[End of section] 

Customs and Border Protection: TECS Modernization: 

[Photograph: Source: Customs and Border Protection] 

The Department of the Treasury brought TECS online in the 1980s. DHS 
is now responsible for the system. Customs and Border Protection uses 
the mainframe-based application to disseminate data to support 
inspections of travelers at ports of entry. The TECS Modernization 
program plans to improve search capabilities, enhance data 
integration, provide the flexibility necessary to respond to evolving 
threats, and eliminate older, unreliable technology. 

Current Status: 

Customs and Border Protection plans to execute the modernization 
program in five segments. Customs and Border Protection has begun 
segments 1, 2 and 3, and expects to achieve full operating capability 
for all five segments by the end of fiscal year 2015. 

Timeline: 

Start of acquisition (12/07); 
Segment 1 and 2 start (4/08); 
Segment 3 start (11/09); 
Initial operating capability (3/10); 
Segment 4 start (10/10); 
Segment 5 start (1/12); 
Full operating capability (9/15). 

Program Essentials: 
Component: Customs and Border Protection; 
Major contractor(s): BART & Associates and Mythics; 
Fiscal year 2010 funding requested: $50 million; 
Program office workforce: 1 total government position planned; 4 
government staff employed*; 3 support contractors. 

* Government staff numbers refer to full time equivalents. 

Program Challenges: 
* Schedule delays due to funding constraints; 
* Lack of approved baseline, requirements and planning documents; 
* Understaffing. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $406 million[A]; 
Total acquisition cost: Latest estimate: $410 million[A]; 
Life-cycle cost estimate: Initial estimate: $888 million[A]; 
Life-cycle cost estimate: Latest estimate: $1,104 million[A]; 
Quantity: Initial estimate: Not applicable; 
Quantity: Latest estimate: Not applicable; 
Initial capability: Initial estimate: Mar. 2010; 
Initial capability: Latest estimate: Mar. 2010; 
Full capability: Initial estimate: Sept. 2013; 
Full capability: Latest estimate: Sept. 2015. 

[A] Note: Cost estimates submitted to the Office of Management and 
Budget for 2009 and 2011, represent both Customs and Border Protection 
and Immigration and Customs Enforcement efforts. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Not yet approved. 

Initial version of: Mission Need Statement; 
Department approval date: Not yet approved. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

TECS Modernization: 

Background: 

TECS is increasingly difficult to maintain because of technology 
obsolescence, and inability to support new requirements, particularly 
those involving access to other systems. Customs and Border Protection 
is migrating the system to a new architecture in order to meet DHS's 
mission requirements. Additionally, Immigration and Customs 
Enforcement manages a parallel but independent project modernizing the 
functionality of TECS unique to its respective mission. 

Performance: 

The modernization program lacks an approved baseline, Operational 
Requirements Document, and Acquisition Plan. Customs and Border 
Protection expected full operating capability by the end of fiscal 
year 2013, but program officials state that milestone has slipped by 2 
years due to funding constraints. 

The program has consolidated several projects originally identified as 
independently providing capability. In September 2008, the program 
office planned to execute system modernization through 16 discrete 
projects, but by June 2009, the program office had reduced that number 
to 13. In September 2009, these projects were further consolidated 
into 5 discrete projects due to departmental guidance. 

The program office also determined that its original cost estimation 
approach did not accurately capture costs as part of the life-cycle 
cost estimate. Costs considered part of the acquisition effort in 2007 
were recategorized as part of the maintenance effort in 2009, and 
program planning cost estimates increased because the program office 
was required to maintain its planning function after the system 
achieved full operating capability, and therefore needed to include 
those costs in the estimates. 

Challenges: 

The system modernization program office submitted the program's 
Operational Requirements Document, Acquisition Program Baseline, Test 
Evaluation Master Plan, and Integrated Logistics Support Plan to DHS 
oversight officials who reviewed the documents in July and August 
2009. These documents were returned to Customs and Border Protection 
to be revised, and had not yet been approved as of February 2010. 

The program office requested and received funding to hire one full-
time government staff member in fiscal year 2009. In addition, three 
other personnel funded through the Passenger Systems Program Office 
were assigned to the system modernization program as of September 
2009. The DHS Chief Information Officer reviewed the program in 
October 2009, and stated that the program office appears understaffed 
with respect to the size and scope of the program. 

Program Office Comments: 

DHS provided technical comments on a draft of this assessment, which 
were incorporated as appropriate. Additionally, DHS emphasized that 
the consolidation of projects did not reduce the scope of the program, 
and that the planned full operating capability date changed to 2015 
because anticipated funding increases for fiscal years 2011 through 
2013 failed to materialize. 

[End of section] 

Customs and Border Protection: Western Hemisphere Travel Initiative: 

[Photograph: Source: Western Hemisphere Travel Initiative] 

The Western Hemisphere Travel Initiative acquisition program intends 
to enable Customs and Border Protection to effectively and efficiently 
address new traveler documentation requirements. The program deploys 
Radio Frequency Identification and License Plate Reader (RFID/LPR) 
hardware and Vehicle Primary Client (VPC) software to land ports of 
entry to improve traveler processing. The program has completed the 
installation of VPC software. 

Current Status: 

The first phase of the program achieved full operating capability in 
fiscal year 2009. However, program officials explained that the 
program has been expanded and now expect a second phase to continue 
through the end of fiscal year 2010. 

Timeline: 
Start of acquisition (9/06); 
Cost benefit analysis (10/07); 
VPC preliminary and critical design review (11/07); 
RFID/LPR preliminary design review (2/08); 
RFID/LPR critical design review (4/08); 
Initial operating capability (9/08); 
Phase I full operating capability (6/09); 
Phase II full operating capability (9/10). 

Program Essentials: 
Component: Customs and Border Protection; 
Major contractor(s): IBM, Unisys Corp., and ITS Services; 
Fiscal year 2010 funding requested: $168 million; 
Program office workforce: 20 total government positions planned; 
20 government staff employed; 68 support contractors. 

Program Challenges: 
* Increased program scope; 
* Unfunded requirements; 
* Delays in Customs and Border Protection network upgrades. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $312 million[A]; 
Total acquisition cost: Latest estimate: $311 million[A]; 
Life-cycle cost estimate: Initial estimate: $863 million[A]; 
Life-cycle cost estimate: Latest estimate: $1,362 million[A]; 
Quantity (RFID/LPR): Initial estimate: 354; 
Quantity (RFID/LPR): Latest estimate: 487; 
Initial capability: Initial estimate: Oct. 2008; 
Initial capability: Latest estimate: Sept. 2008; 
Full capability: Initial estimate: June 2009; 
Full capability: Latest estimate: Sept. 2010. 

[A] Note: Cost estimates submitted to the Office of Management and 
Budget for 2009 and 2011; latest cost estimate does not account for 
any acquisition costs beyond fiscal year 2010. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Jan. 2009. 

Initial version of: Mission Need Statement; 
Department approval date: Feb. 2007. 

Initial version of: Operational Requirements Document; 
Department approval date: Apr. 2008. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Western Hemisphere Travel Initiative: 

Background: 

The Intelligence Reform and Terrorism Prevention Act of 2004 required 
the Secretary of Homeland Security in consultation with the Secretary 
of State to develop and implement a plan, known as the Western 
Hemisphere Travel Initiative, which requires all travelers to present 
a passport or other acceptable document denoting identity and 
citizenship when entering the United States. 

Customs and Border Protection determined that the initiative could 
increase costs to the traveling public and increase the agency's 
workload. Improved processes, technology and facilities were needed to 
prevent longer inspection processing times, and the program is 
expected to limit potential border crossing delays created by new 
traveler requirements. 

Performance: 

In June 2009, the program provided the full operating capability 
originally expected. However, the program's scope and capability 
requirements have been expanded, and a second phase of the program is 
now scheduled to continue through September 2010. Customs and Border 
Protection decided to increase the number of RFID/LPR deployed as well 
as VPC installations. Additionally, the RFID/LPR equipment was 
originally required to be compatible with four different types of 
identification documents, but was revised to be compatible with twelve.
Program officials expect the program's acquisition costs, including 
phase 2, to be $1 million lower than originally estimated due to lower 
costs for the technology and individual RFID/LPR and VPC installations. 

Challenges: 

Although the current acquisition cost estimate is lower than the 
program's original estimate, program officials anticipate total 
funding shortfalls for fiscal years 2011 through 2015 because program 
funding does not fully cover life-cycle cost estimates. This shortfall 
would likely require the program to scale back operations and 
maintenance efforts and delay future enhancements. 

Additionally, program officials expect DHS to expand the program's 
scope beyond the second phase during fiscal year 2010 to address new 
requirements for pedestrian and outbound vehicle processing. 

Further, schedule delays for a Customs and Border Protection effort to 
upgrade local and wide area network bandwidth capacity at ports of 
entry could jeopardize program performance, particularly in terms of 
response times. Originally scheduled for completion by June 2009, as 
of January 2010, Customs and Border Protection had not yet determined 
when the wide area network upgrades would occur at 19 of 151 sites, or 
when local area network upgrades would occur at 144 of 163 sites. 
However, actual response times exceeded the objective performance 
levels from June 2009 to June 2010. 

Program Office Comments: 

The program office generally concurred with the assessment and 
provided technical comments which were incorporated as appropriate. 
Additionally, DHS emphasized that the program provided the full 
operating capability originally expected in June 2009, and that the 
rollout of the second phase caused the change in the full capability 
date. 

[End of section] 

Federal Emergency Management Agency: Integrated Public Alert and 
Warning System: 

[Illustration: Source: Federal Emergency Management Agency] 

The Integrated Public Alert and Warning System is the nation's next-
generation infrastructure of alert and warning networks expanding upon 
the traditional audio-only radio and television Emergency Alert System 
by providing one message over more media to more people before, 
during, and after a disaster. When complete, the program is planned as 
a "system of systems" forming the country's comprehensive public alert 
system. 

Current Status: 

The program is awaiting component approval of key program 
documentation, including the initial acquisition program baseline and 
the first operational requirements document. 

Timeline: 
Start of acquisition (9/06); 
Preliminary design review (3/10); 
Critical design	review (9/10); 
Test readiness review (12/10); 
Initial operating capability (3/12); 
Full operating capability (TBD). 

Program Essentials: 
Component: Federal Emergency Management Agency; 
Major contractor(s): Booz Allen Hamilton, CACI, and Acuity Consulting; 
Fiscal year 2010 funding requested: $16.8 million; 
Program office Workforce: 11 total government positions planned; 10 
total government staff employed; 23 support contractors. 

Program Challenges: 
* Requirements instability; 
* Lacking approved baseline, requirements, and planning documents; 
* Turnover in program leadership and staffing. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $115 million[A]; 
Total acquisition cost: Latest estimate: $136 million[A]; 
Life-cycle cost estimate: Initial estimate: $279 million[A]; 
Life-cycle cost estimate: Latest estimate: $264 million[A]; 
Quantity*: Initial estimate: 32; 
Quantity*: Latest estimate: 32; 
Initial capability: Initial estimate: TBD; 
Initial capability: Latest estimate: Not available; 
Full capability: Initial estimate: Mar. 2012; 
Full capability: Latest estimate: Not available. 

[A] Note: Cost data provided by program office. 
* Quantities are for Primary Entry Point stations. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Not available. 

Initial version of: Mission Need Statement; 
Department approval date: Not available. 

Initial version of: Operational Requirements Document; 
Department approval date: Not available. 

Initial version of: Acquisition Plan; 
Department approval date: Not available. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not available. 

Integrated Public Alert and Warning System: 

Background: 

Through the Integrated Public Alert and Warning System program, the 
Federal Emergency Management Agency (FEMA) seeks to expand the 
Emergency Alert System to include more modern technologies. Since the 
program began awarding contracts in 2005, program requirements have 
changed. 

The program originally planned to build an infrastructure to deliver 
state and local alerts through multiple pathways. However, program 
officials told us their vision changed to focus exclusively on 
disseminating presidential messages and setting alert and warning 
technical standards in 2007. In early 2009, the program shifted focus 
to again include infrastructure for state and local alerts.
We have previously reported that FEMA has not systematically assessed 
program outcomes or lessons learned from pilot projects, and has not 
periodically reported on program progress as required by a June 2006 
Executive Order. 

Our prior work has shown that without validated requirements or a 
program baseline, DHS will not know whether the program expenditures 
fully satisfy department needs, how well the program is executed, or 
whether further investments are warranted. 

Performance: 

Although the program was initiated in 2004, FEMA has not yet approved 
an acquisition program baseline for the program or other key program 
documents. According to program office officials, the program did not 
begin to develop programwide life-cycle cost estimates until 2009, and 
these estimates have not yet been finalized or approved. 

Program officials told us that they are working with stakeholders to 
better define requirements, and have drafted an operational 
requirements document and acquisition program baseline. These 
documents are currently under review by FEMA, which oversees the 
program as a nonmajor acquisition. 

Program officials said that they are transitioning to operate under 
the November 2008 Department of Homeland Security acquisition guidance. 

Challenges: 

The program must overcome significant challenges in order to deliver a 
comprehensive public alert and warning system. Program officials said 
they face challenges in upgrading some Primary Entry Point stations, 
which are radio stations providing emergency information, to meet 
changing survivability requirements—as they are subject to legal 
restrictions concerning the enhancement of private property using 
government funds. This could have a significant negative impact on 
system reliability and operations. 

Moreover, frequent changes in organizational leadership and other 
staffing-related issues have affected program performance. The program 
office recently hired its fourth Program Director in 5 years. FEMA 
officials acknowledge that leadership changes and high turnover make 
it difficult to consistently manage the program. 

Program Office Comments: 

The program office provided technical comments, which were 
incorporated as appropriate. Program officials indicated that 
Acquisition Review Board reviews by both FEMA and DHS were planned to 
occur by May 2010, and all required program documentation has been 
drafted. Program officials stated that a recent FEMA program 
management review provided top scores for scope, performance, cost, 
schedule, and risk management controls and processes on the program. 

[End of section] 

National Protection and Programs Directorate: National Cybersecurity 
Protection System: 

[Photograph: Source: National Cybersecurity Protection System Program 
Office] 

The National Cybersecurity Protection System is intended to reduce the 
federal government's vulnerabilities to cyber threats by decreasing 
the frequency of cyberspace disruptions, and by minimizing the 
duration and damage of those disruptions. The program consists of four 
discrete "blocks," including the current state and three follow-on end-
to-end system upgrades. 

Current Status: 

The block 1.0 deployment began in 2003 and was completed after 
deploying capabilities at 31 sites. DHS is currently deploying block 
2.0, and plans to complete the deployment by March 2013. DHS plans to 
deploy block 2.1 during fiscal years 2010 and 2011. DHS has classified 
the block 3.0 deployment schedule. 

Timeline: 
Start of acquisition (6/08); 
Block 2.0 operational readiness review (2/09); 
Block 2.0 initial operating capability (8/09); 
Block 2.1 operational readiness review (12/09); 
Block 2.1 initial operating capability (9/10); 
Block 2.1 full operating capability (6/11); 
Block 2.0 full operating capability (3/13). 
	
Program Essentials: 
Component: National Protection and Programs Directorate; 
Major contractor(s): General Dynamics Advanced Information Systems; 
Fiscal year 2010 funding requested: $186 million; 
Program office workforce: 26 total government positions planned; 
11 total government staff employed; 122 support contractors. 

Program Challenges: 
* Schedule slippage; 
* Unstable architecture and deployment strategy; 
* Lacks risk mitigation and key project management capabilities. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $664 million[A]; 
Total acquisition cost: Latest estimate: $546 million[A]; 
Life-cycle cost estimate: Initial estimate: $1,366 million[A]; 
Life-cycle cost estimate: Latest estimate: $1,257 million[A]; 
Quantity: Initial estimate: 100; 
Quantity: Latest estimate: 100; 
Initial capability (Block 2.0): Initial estimate: June 2009; 
Initial capability (Block 2.0): Latest estimate: Aug. 2009; 
Full capability (Block 2.0): Initial estimate: Mar. 2013; 
Full capability (Block 2.0): Latest estimate: Mar. 2013. 

[A] Note: Cost estimates submitted to the Office of Management and 
Budget for 2010 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Feb. 2009. 

Initial version of: Mission Need Statement; 
Department approval date: Feb. 2009. 

Initial version of: Operational Requirements Document; 
Department approval date: Oct. 2009. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date:Not yet approved. 

National Cybersecurity Protection System: 

Background: 

We have reported over the last several years that DHS has yet to fully 
satisfy its cybersecurity responsibilities. In response to National 
Security Presidential Directive 54/Homeland Security Presidential 
Directive 23, and the Comprehensive National Cybersecurity Initiative, 
the National Cyber Security Division of the National Protection and 
Programs Directorate established two programs—the National 
Cybersecurity Protection Program and the National Cybersecurity 
Protection System. The program encompasses the people, activities, 
processes, and technologies intended to fulfill DHS's cyber mission, 
and the system is expected to integrate the hardware and software 
procured to support the program. 

Block 1.0 currently provides flow collection and data storage 
capabilities. Block 2.0 will add intrusion detection capabilities. 
Block 2.1 will enhance visualization capabilities. Block 3.0 
capabilities are classified. DHS also plans future blocks to improve 
inter-department information sharing and add near real-time detect-and-
protect capabilities; however, schedules for these blocks have not yet 
been determined. 

The Consolidated Security, Disaster Assistance, and Continuing 
Appropriations Act, 2009 and the Department of Homeland Security 
Appropriations Act of 2010 required DHS to submit an expenditure plan 
for House and Senate Appropriations Committees' approval prior to 
receiving 50 percent of the National Cyber Security Division's budget. 

Performance: 

In July 2009, program officials notified component and department-
level oversight officials that the program needed to reschedule the 
deployments of blocks 2.1 and 3.0. The block 2.1 full operating 
capability date slipped from the third quarter of fiscal year 2010 to 
the third quarter of fiscal year 2011. The new deployment schedule for 
block 3.0 is classified. Program officials attributed the
rescheduling to a delay in receiving half of 2009 funding based on 
approval of the National Cyber Security Division's fiscal year 2009 
expenditure plan. The funding was made available in June 2009. 

Program officials said delayed funding also delayed the implementation 
of the program's continuity of operations plan by 7 months. Program 
officials said that the plan is expected to ensure that the system can 
continue to operate despite disruptions, and will improve system data 
services, which cannot currently handle block 2.0 data volume and 
replication requirements. Program officials now expect completion of 
the plan by the end of 2011. 

Challenges: 

The acquisition program's architecture and deployment strategy has not 
been stabilized for blocks 2.0 and 3.0, although the block 2.0 
deployment has begun, and DHS is planning to accelerate development 
and implementation of certain block 3.0 activities. DHS has 
acknowledged that the acquisition program lacks risk mitigation and 
key project management capabilities. DHS has stated that the program 
has efforts planned and under way to implement more effective 
controls. Program officials said that they are developing a risk 
mitigation plan based on an exercise concluding in 2010 or 2011, 
depending on the decision to execute an additional, optional phase. 

Program Office Comments and Our Response: 

The program office provided technical comments to a draft of this 
assessment, which were incorporated as appropriate. Regarding the 
statement that the architecture and deployment strategy has not been 
stabilized, the program office suggested that the December 2008 
baseline provided such a strategy. However, in December 2008, the 
program reported to the DHS acquisition oversight board that this 
instability was a program risk, and the program also reported the risk 
to us in July and October 2009. 

[End of section] 

National Protection and Programs Directorate: US-VISIT Unique Identity: 

[Photograph: Source: US-VISIT] 

United States Visitor and Immigrant Status Indicator Technology (US-
VISIT) collects, maintains, and shares information on foreign 
nationals, including biometric identifiers, acquired by several source 
agencies. Unique Identity, one of several investments under US-VISIT, 
is modernizing the current biometric data system by introducing 10-
print finger scans and adding identity management capabilities such as 
data sharing and interoperability with Department of Defense (DOD) and 
Federal Bureau of Investigation (FBI) systems.	 

Current Status: 
US-VISIT does not have an approved program baseline including all 
relevant investments as DHS is restructuring the program. According to 
program documents, Unique Identity will achieve full operating 
capability in September 2014. 

Timeline: 
Start of Unique Identity acquisition (6/04); 
Interoperability preliminary design review (3/08); 
Interoperability critical design review (6/08); 
Interoperability initial operating capability (10/08); 
10-print initial operating capability (3/09); 
Unique Identity full operating capability (9/14). 

Program Essentials: 
Component: National Protection and Programs Directorate; 
Major contractor(s): Accenture LLP; 
Fiscal year 2010 funding requested: $28.7 million; 
Program office: Not available for the separate workforce	
investments under US-VISIT. 

Program Challenges: 
* Unstable and unapproved requirements; 
* Lack of approved program baseline; 
* Dependence on outside agency to achieve full operating capability. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $160 million[A]; 
Total acquisition cost: Latest estimate: $79 million[A]; 
Life-cycle cost estimate: Initial estimate: $225 million[A]; 
Life-cycle cost estimate: Latest estimate: $132 million[A]; 
Quantity: Initial estimate: Not applicable; 
Quantity: Latest estimate: Not applicable; 
Initial capability: Initial estimate: Sept. 2008; 
Initial capability: Latest estimate: Mar. 2009; 
Full capability: Initial estimate: Not defined; 
Full capability: Latest estimate: Sept. 2014. 

[A] Note: Estimates submitted to the Office of Management and Budget 
for Unique Identity 2010 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Not yet approved. 

Initial version of: Mission Need Statement; 
Department approval date: Not yet approved. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: June 2009. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

US-VISIT Unique Identity: 

Background: 

The US-VISIT program was started to meet congressional mandates to 
record the entry and exit of foreign nationals. The program currently 
provides identity management services through operations and 
maintenance of IDENT—the current automated biometric identification 
system, the Arrival and Departure Information System, and US-VISIT's 
analytic support services. At the time of our review, US-VISIT was 
restructuring the program into individual investments to provide 
better visibility and traceability of investment dollars to individual 
projects. Because of the restructuring, the program was unable to 
provide complete data at either the program or project level. As a 
result, we were not able to fully assess the program in its entirety. 

US-VISIT development and deployment efforts consist of two ongoing 
projects: (1) Unique Identity and (2) Comprehensive Exit. In fiscal 
year 2015, Unique Identity is projected to enter the operations and 
maintenance phase and become part of the overall IDENT investment. We 
did not include Comprehensive Exit in our review because DHS did not 
request fiscal year 2010 funds for this project. 

We have previously reported on limitations and made recommendations to 
improve DHS's efforts to plan and execute its efforts to deliver a 
Comprehensive Exit capability. 

Program Performance: 

US-VISIT, which includes the Unique Identity investment, lacks an 
approved acquisition program baseline and other acquisition planning 
and requirements documents. The Enhanced Border Security and Visa 
Entry Reform Act of 2002, as amended, mandated the use of a biometric 
standard developed under the USA Patriot Act to track entry and exit 
of foreign nationals by 2005. The program partially meets that 
requirement, capturing fingerprint data for all foreign nationals 
entering the U.S., transmitting the data to a central database, and 
analyzing that data. Currently, an entry capability operates at almost 
300 U.S. ports of entry but a Comprehensive Exit capability does not. 

Although program officials said that the program has largely 
transitioned from a 2-print to a 10-print system, the program has yet 
to fully develop and deploy a back-end system to match the 10-prints 
against other biographic or biometric data. Unique Identity has 
reached initial operational capability and is interoperable with the 
FBI's fingerprint database. According to program officials, most 
responses from the FBI system are completed within 15 minutes; 
however, this system can require up to 72 hours for results. Full 
operational capability, which is in the initial planning stage, will 
include record linking between the US-VISIT and the FBI fingerprint 
systems, improved response times for searches, and notification 
capabilities when updating a biometric record. 

The program reported that cost estimates submitted to the Office of 
Management and Budget for 2011 reflect Unique Identity cost reductions 
to fit within budgetary constraints. 

Challenges: 

According to program officials, capabilities and requirements 
constantly change as a result of new legislative and administrative 
mandates. Officials do not know when US-VISIT will be fully 
interoperable with the FBI fingerprint database, but they have already 
agreed on capabilities and requirements work, which is in progress. 
Interoperability depends upon completion of specific tasks on the 
FBI's Next Generation biometric and fingerprint system, projected for 
completion in 2014. 

Program Office Comments: 

The program office provided technical comments on a draft of this 
assessment, which were incorporated as appropriate. Officials also 
noted that the program has been restructured, increasing the scope of 
Unique Identity, since our review began. 

[End of section] 

Office of Health Affairs: Biosurveillance Common Operating Network: 

[Illustration: Source: SAIC] 

The mission of the National Biosurveillance Integration Center is to 
collect, integrate, analyze, and disseminate information from existing 
human health, animal, plant, food, and water surveillance systems, and 
relevant threat and intelligence information to provide early 
recognition of bioevents in order to mitigate the consequences. The 
Biosurveillance Common Operating Network, formerly known as National 
Biosurveillance Integration System 2.0, is the information technology 
system supporting the Center. 

Current Status: 
Program officials said that data backup capability has been delayed a 
year and consider this delay a significant operational risk. The 
Network is currently in the operations and maintenance phase. 

Timeline: 
Start of acquisition (9/06); 
Preliminary design review (12/06); 
Critical design	review (3/07); 
Initial operating capability (3/08); 
Full operating capability (9/08). 

Program Essentials: 
Component: Office of Health Affairs; 
Major contractor(s): SAIC; 
Fiscal year 2010 funding requested: $2.1 million; 
Program office	workforce: N/A total government positions planned; 
1.25 total government staff employed; 2.5 support contractors. 

Program Challenges: 
* Lack of data sharing between agencies; 
* Delay in data backup; 
* Operations and maintenance cost increases. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $14.3 million[A]; 
Total acquisition cost: Latest estimate: $13.1 million[A]; 
Life-cycle cost estimate: Initial estimate: $26.5 million[A]; 
Life-cycle cost estimate: Latest estimate: $26.5 million[A]; 
Quantity: Initial estimate: 1; 
Quantity: Latest estimate: 1; 
Initial capability: Initial estimate: Nov. 2007; 
Initial capability: Latest estimate: Mar. 2008; 
Full capability: Initial estimate: Mar. 2008; 
Full capability: Latest estimate: Sept. 2008*. 

* Note: Capabilities delivered varied substantially from initial 
estimates; the Center was not fully operational as an integration 
center by Sept. 2008. 

[A] Program reported cost estimates for 2006 and 2008. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Not available. 

Initial version of: Mission Need Statement; 
Department approval date: Not available. 

Initial version of: Operational Requirements Document; 
Department approval date: Not available. 

Initial version of: Acquisition Plan; 
Department approval date: Apr. 2006. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date:Not available. 

Biosurveillance Common Operating Network: 

Background: 

The Center was created to integrate real-time biosurveillance data 
from multiple federal agencies such as the Centers for Disease Control 
(CDC), the Food and Drug Administration (FDA), and the United States 
Department of Agriculture (USDA) in order to rapidly identify and 
characterize a bioterrorist attack. Once a potential event is 
detected, the Center disseminates alerts to enable rapid response to a 
biological event to mitigate the potential consequences. 

In July 2007, the DHS Office of Inspector General reported that the 
Center lacked sustained program leadership and was not a priority, 
because ownership of the program shifted among department 
organizations numerous times, with corresponding fluctuations in the 
program approach, priority, and accomplishments. 

The original information technology system was designed to process 
structured data received directly from federal partners, such as CDC, 
FDA, and USDA. However, the Center receives limited data from federal 
partners and generally lacks assignments of personnel from other 
agencies to leverage analytical expertise. As a result, the Network is 
primarily used to search the Internet for media articles that may 
contain relevant biosurveillance information for the Center's analysts. 

Performance: 

Program officials told us that the Network spent about $1 million less 
on acquisition costs than initially estimated, although delivery of 
full operating capability was delayed by 6 months. The program was 
affected by lack of available biosurveillance data from other federal 
agencies. The program significantly modified the system design to use 
unstructured data from public sources rather than structured data from 
other agencies. The program reduced costs by dropping three of six 
systems, due to no longer requiring these classified systems. 

Officials previously told us that they planned to add a software tool 
to the Network to refine results when performing historical analysis 
of archived data, but this has been put on hold due to budget 
constraints. 

Challenges: 

We previously reported that the Center does not receive the kind of 
data it has identified as most critical for supporting its mission—
particularly, data generated at the earliest stages of an event. The 
Center is not fully equipped to carry out its mission because it lacks 
key resources from its partner agencies—data and personnel—which
may be partially attributed to the need for greater collaboration. In 
interviews with partner agencies, we found confusion, uncertainty, and 
skepticism as to the value of participation in the interagency 
community, as well as to the mission and purpose of the Center within 
that community. Agency officials also expressed a lack of clarity 
about roles, responsibilities, joint strategies, policies, and 
procedures for operating across agency boundaries. 

The program reported that the Network's operations and maintenance 
costs are greater than originally anticipated, so the data backup 
capability will be delayed for a year. Program officials consider this 
delay a significant operational risk. 

The program reported that no full-time government personnel are 
dedicated to the Network. The Network and other Center functions share 
staff, including contractor support. Furthermore, the program does not 
have an approved sustainment plan although it is in the operations and 
maintenance phase. 

Program Office Comments and Our Response: 

In responding to a draft of this assessment, the program office 
provided technical comments, which were incorporated as appropriate. 
Program officials stated that all of the program's key acquisition 
documents were component approved in December 2004. However, they were 
unable to provide documentation of this at the time of our review. 
Because the program is not a major investment, departmental approval 
of key program documents is not required. 

[End of section] 

Office of Health Affairs: BioWatch Generation-3: 

[Photograph: Source: BioWatch] 

The BioWatch program's mission is to rapidly detect airborne 
biological agents in order to speed response and recovery from a 
terrorist event. BioWatch Generation-3 replaces manually-intensive, 
primarily outdoor legacy systems with an automated detection 
capability allowing a quicker response to a biological attack. This is 
expected to greatly reduce the number of potential fatalities caused 
by an attack by shortening the time elapsed between exposure and 
treatment. 

Current Status: 

The program is currently evaluating biodetection technologies for a 
future acquisition. Delivery of an initial capability has been delayed 
18 months due to unavailability of vendor equipment, change in testing 
responsibilities, and additional time required to complete DHS reviews. 

Timeline: 
Production readiness review (9/10); 
Operational testing (9/11); 
First Generation-3 deployment (9/11); 
Initial	operating capability (6/12); 
Full operating capability (3/15). 

Program Essentials: 				
Component: Office of Health Affairs; 
Major contractor(s): Hamilton Sundstrand Northrup-Grumman; 
Fiscal year 2010 funding requested: $122 million; 
Program office workforce: 5 total government positions planned; 
3 total government staff employed; 9 support contractors. 

Program Challenges: 
* Understaffing; 
* Technical risk. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $407 million[A]; 
Total acquisition cost: Latest estimate: $493 million[A]; 
Life-cycle cost estimate: Initial estimate: $921 million[A]; 
Life-cycle cost estimate: Latest estimate: $2,106 million[A]; 
Quantity: Initial estimate: 2,570; 
Quantity: Latest estimate: 2,570; 
Initial capability: Initial estimate: Dec. 2010; 
Initial capability: Latest estimate: June 2012; 
Full capability: Initial estimate: Mar. 2014; 
Full capability: Latest estimate: Mar. 2015. 

[A] Note: Estimates submitted to the Office of Management and Budget 
for 2010 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Not yet approved. 

Initial version of: Mission Need Statement; 
Department approval date: Dec. 2009. 

Initial version of: Operational Requirements Document; 
Department approval date: Apr. 2009. 

Initial version of: Acquisition Plan; 
Department approval date: May 2009. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

BioWatch Generation-3: 

Background: 

Program officials told us that BioWatch Generation 1 and 2 detection 
systems do not provide a long-term solution, because the collection 
process is labor intensive and can require up to 36 hours to identify 
a biological agent. The BioWatch Generation-3 detection system is 
planned as a fully autonomous, networked biosensor that collects and 
analyzes samples on-site and autonomously transmits the results to 
BioWatch labs where the state laboratory directors interpret the 
signal. Generation-3 is intended to detect all biological agents on 
BioWatch's list of biological threats. 

DHS's Office of Health Affairs developed the original Generation-3 
requirements in coordination with the Science and Technology 
Directorate. "Assay" validation-—testing to validate systems that can 
detect biological agents—-was subsequently transitioned to the 
BioWatch program. 

Program officials expect to replace the about 600 existing legacy 
collection systems and deploy approximately 2,000 additional detection 
systems. 

Performance: 

Program officials said they are in the process of validating vendor 
technologies to ensure meeting Generation-3 requirements. At the time 
of our review, plans for testing and evaluation of new technologies 
were not yet finalized. Program officials said that if no vendor 
systems are proven to meet requirements, the program will return to 
developing the technology of the Science and Technology Directorate. 
The program is preparing for a competitive procurement. 

Program officials reported that the shift of assay validation from the 
Science and Technology Directorate to the Office of Health Affairs 
required the program to establish a capability for evaluating existing 
assays, leading to cost growth and testing delays as compared with 
initial estimates. Officials also reported schedule delays due to 
longer than expected time frames for vendors to deliver equipment and 
internal review cycles. 

The program reported a lack of concurrence with the Centers for 
Disease Control on criteria for actionable assays that contributed to 
increased cost and schedule delays. To address this issue, BioWatch 
invested resources with a national lab and the Centers for Disease 
Control to initiate a detailed plan of action for documenting 
requirements for public health actionable assays. 

Challenges: 

The program reported that the Consolidated Security, Disaster 
Assistance, and Continuing Appropriations Act, 2009 resulted in the 
program using a competitive procurement, which prevented the use of 
the incumbent contractor's more mature technologies developed by the 
program. Program officials said that inclusion of the more mature 
technologies would give the existing contractor an unfair advantage in 
procuring future contracts. DHS officials stated that they expect the 
currently identified candidate technologies to perform as well or 
better than the previously developed prototypes. The program currently 
lacks clear requirements due to lack of agreement between the program 
office and the Centers for Disease Control on what constitutes a 
public health assay. However, program officials do not expect this to 
affect the first phase of the program, because they intend to use 
contractor assays for this phase. 

In addition, officials reported that insufficient program staffing 
contributed to delays in developing plans and required documentation, 
and that they were in the process of hiring additional staff. 

Program Office Comments: 

The program office provided technical comments on a draft of this 
assessment, which were incorporated as appropriate. 

[End of section] 

Transportation Security Administration: Electronic Baggage Screening 
Program: 

[Photograph: Source: Transportation Security Administration] 

The Electronic Baggage Screening Program is responsible for screening 
all checked airline baggage in the United States, to reduce the 
probability of a successful terrorist or criminal attack to the air 
transportation system. The program relies on Explosive Detection 
System (EDS) equipment and Explosives Trace Detector devices as 
primary screening technologies.	 

Current Status: 

The program does not have a required department-approved program 
baseline or program requirements. The program is acquiring and 
deploying next-generation explosive detection technology to replace 
legacy systems and meet emerging threats. The program received $700 
million in American Recovery and Reinvestment Act (Recovery Act) funds 
which it is using to accelerate systems deployment by over 2 years. 

Timeline: 
Start of acquisition (8/03); 
Initial operating capability (12/03); 
EDS test and evaluation (5/10); 
Award EDS procurement (1/11); 
Full operating capability (9/19). 

Program Essentials: 
Component: Transportation Security Administration (TSA); 
Major contractor(s): GE Homeland Protection, L-3 Communications, and 
Reveal; 
Fiscal year 2010 funding requested: $336 million; 
Program office workforce: 35 total government positions planned; 27 
total government staff employed; 89 support contractors. 

Program Challenges: 
* Unapproved requirements; 
* Lack of approved program baseline and planning documents; 
* Technical problems. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $11,360 million[A]; 
Total acquisition cost: Latest estimate: $15,316 million[A]; 
Life-cycle cost estimate: Initial estimate: $19,930 million[A]; 
Life-cycle cost estimate: Latest estimate: $23,696 million[A]; 
Quantity: Initial estimate: Not applicable; 
Quantity: Latest estimate: Not applicable; 
Initial capability: Initial estimate: Dec. 2002; 
Initial capability: Latest estimate: Dec. 2003; 
Full capability: Initial estimate: Sept. 2029; 
Full capability: Latest estimate: Sept. 2019. 

[A] Note: Estimates submitted to the Office of Management and Budget 
for 2010 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Not yet approved. 

Initial version of: Mission Need Statement; 
Department approval date: Not yet approved. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Electronic Baggage Screening Program: 

Background: 

The Electronic Baggage Screening Program has received substantial 
increases in funding since September 11, 2001. In addition to 
receiving large supplemental appropriations in recent years, the 
program received $700 million in Recovery Act funding to enhance 
current threat detection capabilities, increase the efficiency of the 
checked-baggage screening process, and contribute to the long-term 
development of a flexible security infrastructure capable of 
accommodating future growth. 

Program officials explained that requirements could change in response 
to emerging threats. The program does not directly fund research and 
development of new technology. Instead, DHS's Science and Technology 
Directorate or the Transportation Security Administration provide 
specifications to vendors, allow vendors to build the systems, and 
then run certification tests to verify that systems meet requirements. 
If systems qualify, they undergo operational testing at TSA's System 
Integration Facility. 

Performance: 

After a DHS review of the program's life-cycle cost estimate, program 
officials informed the DHS Acquisition Review Board in November 2009 
that the current estimate of $24 billion (then-year dollars) needed 
more comprehensive detail and that its degree of accuracy could not be 
determined. Program officials expected a complete estimate validated 
by DHS in January 2010, after determining solutions for addressing 
emerging threats and equipment upgrades. Program officials said that 
other key program documents are moving forward in the approval process. 

The program intends to award contracts for a competitive procurement 
for Explosive Detection Systems screening technology by January 2011. 
Program officials indicated that the sole-source contracts used for 
legacy equipment were costly for the program. Program officials told 
us that vendors are expected to meet the minimum subset of the new 
detection requirements that include three different capability levels 
for detecting homemade explosives. 

Program officials reported that full capability will be reached when 
optimal solutions have been deployed at all airports. However, the 
time frame depends upon airport readiness and the ability of airports 
to fund their share of project costs. TSA provides funding for 
equipment purchase and installation and a portion of facility 
modification costs, while the airport contributes the remaining share 
of the funding. 

Challenges: 

Program officials indicated that some schedule delays have been caused 
by activities related to testing, including data collection 
activities, development of test sets, equipment availability, and test 
scheduling. Future delays could be caused by new threats leading to 
new requirements and a need for additional vendor development and 
testing. Program officials stated that currently they can only test 
new requirements based on the minimum level of detection required. 

Furthermore, a substantial portion of legacy equipment is now nearing 
the projected end of its useful life. In July 2009, the program 
reported that annual compliance costs and recapitalization expenses, 
when combined with recurring programwide costs, sometimes exceed the 
budget. In future years, program costs could grow significantly as 
cost estimates are reassessed to include new requirements. 
Additionally, the program has no department-approved program documents. 

Program Office Comments and Our Response: 

The program office provided technical comments on a draft of this 
assessment, which were incorporated as appropriate. Program officials 
commented that detection requirements changed in January 2010 as a 
result of a change in threats, rather than a failure to manage 
requirements changes. However, detection requirements are only a 
portion of program requirements, and the program does yet not have a 
department-approved baseline. 

[End of section] 

Transportation Security Administration: Passenger Screening Program: 

[Photograph: Source: Transportation Security Administration] 

The Passenger Screening Program tests, deploys, and sustains screening 
equipment to identify threats at airport terminal passenger screening 
checkpoints. The program relies primarily on commercial-off-the-shelf 
software technologies to meet requirements. 

Current Status: 

The Passenger Screening Program deploys next generation detection 
systems to address existing security gaps and detect a wider variety 
of threats (such as new explosive materials and nonmetallic weapons). 
The program received $300 million in American Recovery and 
Reinvestment Act (Recovery Act) funds to accelerate deployment of new 
equipment by more than 3 years. 

Timeline: 
Start of acquisition (9/03); 
Advanced Imaging Technology initial operating capability (3/10); 
Bottled Liquids	Scanner full operating capability (6/11); 
Enhanced Metal Detector full operating capability (3/15); 
Explosives Trace Detector 2 full operating capability (6/15). 

Program Essentials: 
Component: Transportation Security Administration; 
Major contractor(s): Smiths Detection, Rapiscan, and L-3 
Communications; 
Fiscal year 2010 funding requested: $155.1 million; 
Program office workforce: 20 total government positions planned; 16 
total government staff employed; 32 support contractors. 

Program Challenges: 
* Unstable requirements; 
* Technical problems; 
* Sustainment funding. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $1,872 million[A]; 
Total acquisition cost: Latest estimate: $2,559 million[A]; 
Life-cycle cost estimate: Initial estimate: $2,593 million[A]; 
Life-cycle cost estimate: Latest estimate: $4,306 million[A]; 
Quantity: Initial estimate: Not applicable; 
Quantity: Latest estimate: Not applicable; 
Initial capability: Initial estimate: Dec. 2002; 
Initial capability: Latest estimate: Apr. 2006; 
Full capability: Initial estimate: Dec. 2009; 
Full capability: Latest estimate: June 2015. 

[A] Note: Estimates submitted to the Office of Management and Budget 
for 2010 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: May 2006. 

Initial version of: Mission Need Statement; 
Department approval date: Sept. 2008. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Passenger Screening Program: 

Background: 

The Transportation Security Administration reported meeting the 
statutory deadline for screening passengers and baggage in 2002, but 
with some capability shortfalls and the opportunity to improve 
effectiveness and efficiency of passenger screening checkpoints and 
equipment. Since fiscal year 2002, DHS invested over $921 million in 
airline passenger screening technologies. Program officials told us 
that ever-changing threats necessitate ongoing investment in new and 
improved technology, to provide the traveling public with optimal 
security screening benefits. 

The program is acquiring numerous advanced technological systems and 
testing and evaluating the systems based on detection and nondetection 
requirements. Systems need to detect explosives, fit within the 
constraints of existing airport floor space, and maintain passenger 
and baggage screening throughput requirements. 

In 2009, we reported that the Transportation Security Administration 
had been unable to assess the extent to which technology investments 
have reduced or mitigated the risk of terrorist attacks. We also 
reported that Explosives Trace Portals were deployed without resolving 
performance problems or validating operational requirements, and that 
these systems have not been proven to increase security at 
checkpoints. Explosive Trace Portals deployment was halted in June 
2006 because of performance problems and high installation costs. 

Performance: 

DHS approved the program baseline in 2006; however, according to 
program officials, the requirements have been revised each year since 
2001 due to rapidly changing technologies and threats. DHS asked the 
program manager to revise the life-cycle cost estimate to include long-
term costs. The program is also revising its Acquisition Program 
Baseline to incorporate updated technologies. 

Four projects have not begun acquisition activities and an additional 
four are in the integration and testing phase. Achievement of full 
operating capability for the program was initially planned for 2009, 
but has been delayed until June 2015, due in part to changes in 
technologies. 

Challenges: 

Program officials reported they are not able to field new technologies 
quickly. The program must qualify new technology before the vendor can 
compete at the direct order level. They also noted that commercial-off-
the-shelf technology may not address perceived threats to aviation. 
Program officials also said that poor test results of new technologies 
negatively affect the program because they cannot rapidly deploy new 
technology. According to program officials, it is sometimes difficult 
for detection systems to meet program requirements and vendors may 
require multiple attempts to pass tests because they lack access to 
restricted explosives. 

The accelerated deployment using the $300 million in Recovery Act 
funds—almost twice the amount of the program's budget request for 
fiscal year 2010—places increased demands on the program staff to meet 
the new schedule. Additionally, the program may not have the 
maintenance and system sustainment funds to support the accelerated 
deployment. 

Program Office Comments: 

Program office officials provided technical comments which were 
incorporated as appropriate. Program officials stated that certain key 
program documents did not previously require departmental approval and 
that the component has produced life-cycle cost estimates from product 
acquisition to disposal. However, they also told us that life-cycle 
cost estimates have not yet been validated. In addition, they stated 
new capability requirements are added within the existing program, 
rather than creating new programs as time progresses, which affects 
program schedule. 

[End of section] 

Transportation Security Administration: Secure Flight: 

[Photograph: Source: Transportation Security Administration] 

The Secure Flight program allows the Transportation Security 
Administration (TSA) to compare air passengers' information to 
Terrorist Screening Center watch lists for international and domestic 
flights. Aircraft operators collect passenger information and transmit 
the data to TSA. Secure Flight conducts automated comparisons for all 
passengers for whom data are submitted, and more than 99 percent will 
be cleared in advance of their arrival at the airport, according to 
program officials. 

Current Status: 
Program officials reported that Secure Flight achieved initial 
operating capability in January 2009, and planned to implement the 
program with all aircraft operators by December 2010. The program is 
currently in the process of deploying the system to airlines. 

Timeline: 
Start of acquisition (2/04); 
Preliminary design review (5/08); 
Critical design review (7/08); 
Production readiness review (12/08); 
Initial operating capability (1/09); 
Full operating capability (12/10). 

Program Essentials: 
Component: Transportation Security Administration; 
Major contractor(s): Infozen, Deloitte, and International Business 
Machines; 
Fiscal year 2010 funding requested: $85 million; 
Program office workforce: 113 total government positions planned; 
113 total government staff employed; 187 support contractors. 

Program Challenges: 
* Unstable and unapproved requirements; 
* Cost growth; 
* Schedule delays; 
* Aircraft operator compliance. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $97 million[A]; 
Total acquisition cost: Latest estimate: $153 million[A]; 
Life-cycle cost estimate: Initial estimate: $685 million[A]; 
Life-cycle cost estimate: Latest estimate: $1,362 million[A]; 
Quantity: Initial estimate: Not applicable; 
Quantity: Latest estimate: Not applicable; 
Initial capability: Initial estimate: Dec. 2008; 
Initial capability: Latest estimate: Jan. 2009; 
Full capability: Initial estimate: Dec. 2009; 
Full capability: Latest estimate: Dec. 2010. 

[A] Note: Cost estimates submitted to the Office of Management and 
Budget for 2009 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Dec. 2006. 

Initial version of: Mission Need Statement; 
Department approval date: Oct. 2006. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Apr. 2008. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Secure Flight: 

Background: 

Prior to the Secure Flight program, aircraft operators were 
responsible for screening passengers based on watch list data provided 
to airlines by the Transportation Security Administration. This 
resulted in inconsistent screening processes from airline to airline, 
as well as limited control over sensitive homeland security data after 
watch list information was distributed outside the U.S. government. 
When Secure Flight is fully implemented, it will provide passenger 
watch list matching for all covered airline flights, including flights 
into and out of the U.S., flights over the continental U.S., and 
international flights conducted by covered U.S. airlines. Secure 
Flight intends to provide more consistent matching, enhanced redress 
procedures, and improved privacy controls. In January 2009, Secure 
Flight started implementing the program with a small number of 
volunteer airlines and officials estimate full implementation with all 
covered aircraft operators by December 2010. Program officials 
estimate that Secure Flight will screen more than 2.5 million 
passengers daily at full capacity. 

We reported in May 2009 that Secure Flight had generally achieved 9 of 
10 statutory requirements for the program, and had conditionally 
achieved the last requirement regarding reliable cost and schedule 
estimates. We have since concluded that the program has met the last 
requirement. 

Performance: 

The Secure Flight program achieved initial operating capability in 
January 2009, without significant delay to the milestone. However, the 
estimated date of full operating capability has slipped by a year, to 
December 2010. Program acquisition cost estimates have increased by
$57 million, or 59 percent over 2 years. Life-cycle cost estimates 
have also increased by nearly 100 percent ($677 million). 

Secure Flight officials attribute schedule delays and cost growth to 
the program needing to increase total system capacity as a result of 
system requirements changes during the rulemaking process. As the 
program progressed, officials became more aware of the system size 
requirements and aircraft operator system capabilities, which led to 
cost increases for the volume and number of records to be processed. 
Also, program scope increased as the initial schedule did not include 
implementation with foreign airlines, according to officials. 

Challenges: 

In 2006, Secure Flight made significant changes in program 
requirements due to privacy and security concerns. Requirements have 
changed further since 2006, and only two of six performance 
requirements remained the same in the revised 2008 acquisition program 
baseline. For example, the program added requirements regarding the 
Service Center, the Secure Flight customer service center that 
provides resolution of airline operator inquiries. Program officials 
report the risk of aircraft operators not complying with the 
implementation schedule as the greatest program challenge. Officials 
said that they are working with aircraft operators on a daily basis to 
address schedule compliance. Some operators have expressed concern 
about meeting the schedule because of the complexity and the cost of 
system upgrade requirements. The program also faces risk with the 
Service Center government and contractor personnel not receiving 
timely security clearances. 

Program Office Comments and Our Response: 

Program officials emphasized that the cost increases and schedule 
delays since 2006 were due to expanded program scope and modification 
of the implementation strategy that resulted in rebaselining. They 
point out that cost growth has been minimal since the rebaselining in 
2008. They noted that performance requirements were altered in 2008 to 
better measure the key metrics of quality for the program, but they do 
not think that this indicates requirements instability. 

[End of section] 

U.S. Coast Guard: Command, Control, Communications, Computers, 
Intelligence, Surveillance, and Reconnaissance (C4ISR): 

[Illustration: Source: U.S. Coast Guard] 

The Coast Guard's Command, Control, Communications, Computers, 
Intelligence, Surveillance, and Reconnaissance (C4ISR) program is 
designed to be an interoperable network that combines information from 
Coast Guard assets and sensors, allowing the Coast Guard to see, 
comprehend, and communicate rapidly. 

Current Status: 
C4ISR is being developed incrementally: the first increment became 
operational in 2009, the second is currently in design development, 
and a third is in the "need" or requirements development phase.	 

Timeline: 
Start of acquisition (6/02); 
Segment 1 initial operating capability (4/09); 
Segment 2, Spiral 1 preliminary design review (6/09)
Segment 2, Spiral 1 critical design review (9/09); 
Full operating capability (2014). 
			
Program Essentials: 
Component: United States Coast Guard; 
Major contractor(s): Integrated Coast Guard Systems; 
Fiscal year 2010 funding requested: $35 million; 
Program office workforce: 38 total government positions planned; 32 
government staff employed; 71 support contractors. 

Program Challenges: 
* Schedule delays; 
* Development risk; 
* Lack of approved requirements and acquisition planning documents. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $1,353 million[A]; 
Total acquisition cost: Latest estimate: $1,353 million[A]; 
Life-cycle cost estimate: Initial estimate: $1,353 million[A]; 
Life-cycle cost estimate: Latest estimate: $1,353 million[A]; 
Quantity: Initial estimate: Not applicable; 
Quantity: Latest estimate: Not applicable; 
Initial capability: Initial estimate: June 2007; 
Initial capability: Latest estimate: Apr. 2009; 
Full capability: Initial estimate: Sept. 2014; 
Full capability: Latest estimate: Sept. 2014. 

[A] Note: Cost estimates submitted to the Office of Management and 
Budget for 2009 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: May 2007. 

Initial version of: Mission Need Statement; 
Department approval date: Apr. 2005. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

C4ISR: 

Background: 

The Coast Guard is currently developing an infrastructure for C4ISR 
that would introduce new sensors and communications systems in its 
future, as well as some existing, assets. As designed, this 
infrastructure will collect, integrate, and present information into a 
single common operating picture to facilitate mission execution. The 
Coast Guard is developing C4ISR in an evolutionary fashion, with more 
functionality and assets added in increments, also referred to as 
segments. Segment 2, which is currently in development, will produce 
two spirals of capability intended to correct issues found in Segment 
1, update software to avoid obsolescence, and add some new 
functionality in the way that data are displayed, recorded, and 
managed. Program officials state that development of the third segment 
has been delayed due to funding constraints, although development of 
capabilities for key assets, such as the Offshore Patrol Cutter, will 
continue. 

Performance: 

According to program officials, the Coast Guard lacked visibility into 
the software development processes and the requirements used by 
Integrated Coast Guard Systems as a basis for Segment 1 development. 
According to Coast Guard and contractor officials, costs grew as the 
Coast Guard refined requirements to better meet their needs. Although 
development and acquisition of C4ISR continues, DHS continues to 
reevaluate and review C4ISR requirements, schedule, and costs. Despite 
the lack of a department-approved acquisition program baseline, the 
Coast Guard approved an acquisition strategy and awarded a contract—
authorized by DHS—for the design and development of Segment 2, which 
includes options for up to $78 million worth of work through 2011. 

Challenges: 

According to program officials, the timely completion of acquisition 
documentation is one of their challenges, especially as responsibility 
for development shifts from Integrated Coast Guard Systems to the 
Coast Guard, and could result in delays to future contract awards and 
schedule. A second challenge is the dependence of requirements for 
Segment 3 on the development of the Offshore Patrol Cutter. C4ISR 
could be at risk of schedule delays if the Offshore Patrol Cutter does 
not develop as anticipated. 

A second challenge reported by program officials is the ability to 
keep communications secure, especially in transferring classified 
information. To maintain this capability, the Coast Guard must upgrade 
key software and systems to remain in compliance with the regulations 
of the agencies maintaining the architecture for secure 
communications. If not planned and executed properly, the need for 
upgrades to, or replacement of, key systems could result in cost 
growth that delays the delivery of future capabilities. To facilitate 
timely system upgrades and replacement, Coast Guard officials state 
that they have obtained all the necessary data rights and software 
code for Segment 1, and intend to develop future increments of 
capability in a manner allowing the Coast Guard to support C4ISR 
systems. 

Program Office Comments and Our Response: 

The program office provided technical comments, which were 
incorporated as appropriate. Program officials indicated in their 
comments that the planned full operating capability date for C4ISR has 
been delayed to fiscal year 2018. However, the most recent Coast Guard 
Quarterly Acquisition Report to Congress indicates the date as 2014.
	
[End of section] 

U.S. Coast Guard: Maritime Patrol Aircraft: 

[Photograph: Source: Integrated Coast Guard Systems] 

The Maritime Patrol Aircraft is intended to be a transport and 
surveillance, fixed-wing aircraft used to perform search and rescue 
missions, enforce laws and treaties, and transport cargo and	
personnel. The aircraft is to use the Mission System Pallet, a suite 
of electronic equipment designed to provide the aircraft with improved 
surveillance sensors and operational awareness, to complete homeland 
security and other missions. 

Current Status: 

The program plans to procure 36 aircraft. Eight of the 11 aircraft 
under contract were delivered, and 9 more have been approved for low-
rate production. The program expects to have its full-rate	
production decision after the completion of operational test and 
evaluation, in fiscal year 2012. 

Timeline: 
Start of acquisition (5/03); 
Preliminary design review (12/04); 
Critical design review (6/05); 
Production readiness review (2/06); 
Initial operating capability (4/09); 
Operational testing completed (9/12); 
Full operating capability (9/20). 
	
Program Essentials: 
Component: United States Coast Guard; 
Major contractor(s): Integrated Coast Guard Systems; 
Fiscal year 2010 funding requested: $175 million; 
Program office workforce: 7 total government positions planned; 5.5 
total government staff employed; 1 support contractor. 

Program Challenges: 
* Planning significant procurement before completion of operational 
testing; 
* Understaffing; 
* Lacking approved requirements and planning documents. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $1,706 million[A]; 
Total acquisition cost: Latest estimate: 2,223 million[A]; 
Life-cycle cost estimate: Initial estimate: $22,773 million[A]; 
Life-cycle cost estimate: Latest estimate: $12,285 million[A]; 
Quantity: Initial estimate: 36; 
Quantity: Latest estimate: 36; 
Initial capability: Initial estimate: Dec. 2007; 
Initial capability: Latest estimate: Apr. 2009; 
Full capability: Initial estimate: Sept. 2016; 
Full capability: Latest estimate: Sept. 2020. 

[A] Note: Estimates based on May 2007 baseline and Dec. 2009 U.S. 
Coast Guard Quarterly Report to Congress. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Feb. 2009. 

Initial version of: Mission Need Statement; 
Department approval date: Apr. 2005, 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Maritime Patrol Aircraft: 

Background: 

The Maritime Patrol Aircraft program plans to procure and maintain 36 
aircraft, each equipped with a Mission Systems Pallet. Initially part 
of the Deepwater program, in February 2009, DHS approved a separate 
acquisition program baseline for the program. In that same month, the 
Coast Guard submitted a test plan to DHS with the intent of obtaining 
approval for full-rate production based on the results of a November 
2008 operational assessment. In April 2009, the DHS Director, 
Operational Test and Evaluation, approved the plan for testing leading 
up to initial operational test and evaluation, but required the Coast 
Guard to update and resubmit the plan before operational testing 
begins. DHS and Coast Guard policy require operational testing to be 
conducted before approval of full-rate production. The Coast Guard has 
made a significant investment in this program before operational 
testing can demonstrate that what it is buying meets Coast Guard needs. 

Performance: 

According to the February 2009 Program Baseline document, the program 
is 4 years behind schedule for delivering full capability, due to 
aircraft and mission system pallet cost increases, delays in the 
mission system pallet, and funding limitations. However, the program 
is currently on schedule to procure 16 aircraft by fiscal year 2014. 
Should the schedule slip further, the service life of the legacy 
aircraft may be extended, which may lead to additional legacy aircraft 
sustainment costs. 

Challenges: 

With 8 of 36 Maritime Patrol Aircraft delivered, and another 3 under 
contract, the Coast Guard has made a significant investment before 
testing can demonstrate that the product meets Coast Guard needs. The 
Coast Guard plans to procure 16 aircraft by the end of fiscal year 2014.
According to the senior official responsible for managing aviation 
assets, budget constraints may limit the total amount procured on low-
rate production contracts to 17 of 20 aircraft. 

DHS has not approved the operational requirements for the program, 
which could increase the risk of having an unrealistic program baseline.
Further, the Coast Guard manages the program with 5.5 full-time 
equivalent government staff and one support contractor. 

Program Office Comments: 

The program office provided technical comments on a draft of this 
assessment, which were incorporated as appropriate. In March 2010, 
program officials said that the program's latest life-cycle cost 
estimate is $23,879 million, $11,594 million more than reported to 
Congress in December, 2009. Program officials also said that the 
program's Acquisition Plan and requirements documents were Coast Guard 
approved in accordance with relevant guidance at the time of their 
approvals. Program officials told us the program office workforce is 
assisted by staff working for other Coast Guard offices, including 
staff at the Aviation Logistics Center, the Aviation Training Center, 
and various Coast Guard technical authorities on integrated product 
teams. 

[End of section] 

U.S. Coast Guard: National Security Cutter: 

[Photograph: Source: U.S. Coast Guard] 

The Coast Guard's National Security Cutter is intended to be the 
flagship of the Coast Guard's fleet. The 418-foot cutter is designed 
to achieve a 12,000 nautical mile range and to provide an extended on-
scene presence and the capability to perform long transits and forward 
deployment. The cutter and its aircraft and boat assets are to operate 
worldwide. Each cutter is expected to have a 30 year service life. 

Current Status: 

Two of the eight cutters have been delivered and the Coast Guard 
expects operational testing to be complete by September 2011. Delivery 
of full operating capability is expected in 2018—more than 3 years 
later than initially planned. 

Timeline: 
Start of acquisition (7/02); 
Preliminary design review (3/03); 
Critical design review (6/03); 
Production readiness review (5/04); 
Initial operating capability (6/08); 
Operational assessment (4/10); 
Operational testing completed (9/11); 
Full operating capability: (6/18). 
	
Program Essentials: 
Component: United States Coast Guard; 
Major contractor(s): Integrated Coast Guard Systems; 
Fiscal year 2010 funding requested: $281.5 million; 
Program office workforce: 50 total government positions planned; 50 
total government staff employed; 29 support contractors. 

Program Challenges: 
* Limitations in operational performance; 
* Insufficient support assets; 
* Lacking approved operational requirements and planning documents. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $3,450 million[A]; 
Total acquisition cost: Latest estimate: $4,749 million[A]; 
Life-cycle cost estimate: Initial estimate: $22,998 million[A]; 
Life-cycle cost estimate: Latest estimate: $24,277 million[A]; 
Quantity: Initial estimate: 8; 
Quantity: Latest estimate: 8; 
Initial capability: Initial estimate: Sept. 2008; 
Initial capability: Latest estimate: June 2008; 
Full capability: Initial estimate: Sept. 2014; 
Full capability: Latest estimate: June 2018. 

[A] Note: Estimates based on 2006 baseline and 2009 U.S. Coast Guard 
Quarterly Report to Congress. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: May. 2007. 

Initial version of: Mission Need Statement; 
Department approval date: Apr. 2005. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

National Security Cutter: 

Background: 
The National Security Cutter program is projected to take delivery of 
a total of eight cutters between 2008 and 2018 and operate them for 30 
years. In May 2008, the Coast Guard took delivery of the first-in-
class Bertholf, and took delivery of the second-in-class Waesche in 
November 2009. 

In 2002, the Coast Guard awarded a contract to Integrated Coast Guard 
Systems to produce and manage the National Security Cutter and other 
Deepwater assets as systems integrator. After a series of project 
failures, the Coast Guard announced in April 2007 that it would take 
over the system integrator role for all Deepwater assets, including 
the National Security Cutter. DHS subsequently approved an acquisition 
program baseline for the Cutter separate from other Deepwater projects 
in December 2008. 

Performance: 

The Cutter program has experienced significant cost growth, which the 
program partially attributes to changes in economic factors, such as 
labor and commodity prices and international currency exchange rate 
fluctuations. 

Program officials stated that completion of operational testing and 
evaluation has been delayed by a year beyond the initially estimated 
date to allow for extended testing. The eighth and final cutter, 
planned for 2014 in the original baseline, is now expected to be fully 
operational in June 2018 based on current production plans. 

Challenges: 

According to Coast Guard officials, the cutters face deficiencies that 
need to be addressed before the first and second cutters can be 
certified as fully operational, currently planned for the fourth 
quarter of fiscal year 2011 for the first-in-class Bertholf. 

The cutters currently lack a shipboard classified information facility 
required for participation in certain Department of Defense missions 
and exercises. According to the Coast Guard, installation of this 
facility is meeting schedule goals. However, as of July 2009, full 
installation of sub-systems that aid the movement of helicopters into 
the Cutter's two hangars was not yet complete, as the helicopters 
accompanying the Cutter had not yet been modified to use this 
subsystem. Additionally, the Coast Guard plans to deploy the first 
cutter without unmanned aircraft—key support assets intended to 
operate with the National Security Cutter. 

The Coast Guard is conducting an analysis of alternatives to address 
this issue and also assessing a Navy unmanned helicopter. Continued 
delays in the delivery of these assets will result in the cutter's 
operating with less capability than originally planned.
Operational requirements and acquisition planning documents are not 
yet DHS approved, although they have been approved by the Coast Guard. 

Program Office Comments: 

The program office provided technical comments on a draft of this 
assessment, which were incorporated as appropriate. Program officials 
stated that key program documents did not require departmental 
approval at the time they were created. They reported the Coast Guard 
approved the program baseline and requirements documents in 2005-2006 
and the Acquisition Plan in 2008. 

[End of section] 

U.S. Coast Guard: Rescue 21: 

[Illustration: Source: U.S. Coast Guard] 

Rescue 21 is an advanced command, control, and communications system 
designed to improve the Coast Guard's ability to execute all missions 
in the coastal zone, and is essential to its search and rescue 
mission. The system seeks to leverage technology to more accurately 
locate distress calls, enhance distress call clarity, reduce	
coverage gaps, and provide significantly increased operational 
availability. 

Current Status: 

The Rescue 21 program is currently deployed in 24 out of 39 locations. 
The program plans to deliver full capability at all locations by the 
end of fiscal year 2017, 9 years later than the date established in 
its 2005 program baseline. 

Timeline: 
Start of acquisition (9/02); 
Developmental test and evaluation (2/05); 
Operational test and evaluation (3/05); 
Initial operating capability (9/06); 
Low-rate initial production (12/06); 
Western Rivers project deployed (9/12); 
Full operating capability (9/17). 
		
Program Essentials: 
Component: United States Coast Guard; 
Major contractor(s): General Dynamics C4 Systems; 
Fiscal year 2010 funding requested: $117 million; 
Program office workforce: 71 total planned government positions; 65 
total government staff employed; 15 support contractors. 

Program Challenges: 
* Cost growth; 
* Tower availability; 
* Technical problems; 
* Risk of technology becoming obsolete. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $827 million
Total acquisition cost: Latest estimate: $1,067 million
Life-cycle cost estimate: Initial estimate: $1,639 million
Life-cycle cost estimate: Latest estimate: $2,693 million
Quantity: Initial estimate: 46; 
Quantity: Latest estimate: 39; 
Initial capability: Initial estimate: Sept. 2005; 
Initial capability: Latest estimate: Sept. 2006; 
Full capability: Initial estimate: Sept. 2008; 
Full capability: Latest estimate: Sept. 2017. 

[A] Note: Estimates submitted to the Office of Management and Budget 
for 2009 and 2011. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Apr. 2006; 

Initial version of: Mission Need Statement; 
Department approval date: Not yet approved. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Rescue 21: 

Background: 

Rescue 21 is replacing antiquated communications systems used to 
monitor the international distress frequency, coordinate rescue 
operations, and communicate with vessels. The program is deploying 
systems to 39 locations across the United States. The program's 
contract with the prime contractor covers 34 locations and is 
scheduled to end in fiscal year 2012. The Coast Guard is currently the 
system integrator for the Ohio River Valley, the Lower Mississippi, 
Upper Mississippi, and two Alaska locations. DHS decided not to 
exercise additional contract options because the contractor's system 
would require extensive modifications to work at remote Alaska sites, 
and the Coast Guard had experience maintaining legacy systems fielded 
before Rescue 21. 

Performance: 

Rescue 21 has experienced significant cost growth and delays. Since 
its initial cost estimate under DHS in 2003, total program costs 
increased by 131 percent. Achievement of full operating capability has 
been delayed by 9 years since 2005. The program identified several 
factors contributing to cost growth, including: underestimation of 
costs for program management, deployment, operations, and maintenance; 
schedule delays; a 6-year extension of the system's planned useful 
life to 2027; and an unfunded mandate related to protocols and 
standards requirements. Changes in out-year funding projections 
required the program to modify its deployment tactic, resulting in 
schedule delays. 

According to program officials, Rescue 21's direction finding 
capability—which allows the Coast Guard to locate boaters in distress—
is only possible in approximately one-third of the 65 tower sites in 
the Alaska region. However, we have previously reported that the 
direction-finding capability is more accurate and more reliable than 
the legacy system, so regions lacking direction finding capability 
will continue to be at risk of performing larger and potentially more 
costly searches. 

Challenges: 

The Coast Guard is facing unanticipated challenges at some fielded 
antenna tower sites. These challenges include availability of towers, 
tower leasability, environmental concerns, electronic interference 
with other communication systems, and telephone system outages.
Program officials acknowledge that challenges related to selecting 
future antenna tower sites may put the program at risk of additional 
schedule delays. Each site has unique factors being addressed 
individually by the program. 

Program officials said they must continually stay abreast of external 
technology standards in order for the system to continue to operate 
properly. According to officials, the program monitors technology 
standards in order to mitigate any risk of the program not keeping up 
with standards changes and has attempted to build related costs into 
program cost estimates. 

The program reported that its operational requirements and acquisition 
planning documents have been approved by the Coast Guard, although 
they have not yet received DHS approval. 

Program Office Comments: 

The program office provided technical comments on a draft of this 
assessment, which were incorporated as appropriate. Program officials 
stated that Rescue 21's key program documents did not require DHS 
approval at the time they were created. Program officials also said 
that the Rescue 21 system is mature and operational, and that the 
program's remaining challenge is related to technical standards, 
rather than system technical problems. 

[End of section] 

U.S. Coast Guard: Response Boat-Medium: 

[Photograph: Source: U.S. Coast Guard] 

The Response Boat-Medium replaces aging 41-foot utility boats and 
other larger nonstandard boats to perform the Coast Guard's missions 
of Search and Rescue, law enforcement, drug and migrant interdiction, 
and homeland security. The boats will operate along the coasts of the 
United States and its territories, as well as in larger lakes and 
rivers. 

Current Status: 

The program has completed operational testing and evaluation of the 
boats and has achieved initial operating capability and entered full 
rate production. During full production, the program plans to order 30 
boats per year contingent upon program funding. 

Timeline: 
Start of acquisition (6/06); 
Critical design review (7/07); 
Production review (7/07); 
First asset delivered (3/08); 
Initial operating capability (4/10); 
Full operating capability (9/15). 
					
Program Essentials: 
Component: United States Coast Guard
Major contractor(s): Marinette Marine Corp.
Fiscal year 2010 funding requested: $103 million; 
Program office workforce: 63 total government positions planned; 40 
total government staff employed; 31 support contractors. 

Program Challenges: 
* Funding issues; 
* Understaffing; 
* Acquisition strategy risks. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $401 million[A]; 
Total acquisition cost: Latest estimate: $610 million[A]; 
Life-cycle cost estimate: Initial estimate: $1,210 million[A]; 
Life-cycle cost estimate: Latest estimate: $1,419 million[A]; 
Quantity: Initial estimate: 180; 
Quantity: Latest estimate: 180; 
Initial capability: Initial estimate: Sept. 2008; 
Initial capability: Latest estimate: Apr. 2010; 
Full capability: Initial estimate: Sept. 2013; 
Full capability: Latest estimate: Sept. 2015. 

[A] Note: Estimates based on 2005 baseline and 2009 U.S. Coast Guard 
Quarterly Report to Congress. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: Sept. 2006. 

Initial version of: Mission Need Statement; 
Department approval date: Not yet approved. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Not yet approved. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Response Boat-Medium: 

Background: 

The Response Boat-Medium program, authorized in 2002, plans to procure 
180 medium-size boats intended to replace the aging 41-foot Utility 
boat, as well as other nonstandard large boats in the Coast Guard 
fleet. While the 41-foot Utility boat was designed to primarily engage 
in Search and Rescue missions, the Response Boat-Medium will have 
greater speed and range than its predecessor to fulfill expanding 
operations in Ports, Waterways and Coastal Security consistent with 
homeland security needs. The Coast Guard has awarded a contract to 
Marinette Marine Corporation to produce the boats at facilities in 
Kent, Washington, and Green Bay, Wisconsin. The program had ordered 66 
boats as of September 2009, and the program reports receiving delivery 
of 16 boats. The program expects to reach full operating capability by 
the end of fiscal year 2015. 

Performance: 

According to Coast Guard officials, the new boats have successfully 
met all technical requirements such as speed and range. While there 
have been some modifications to boats, the program considers them 
minor, and reports that costs of modifications have been within the 
change order budget. For example, the program found performance issues 
in air conditioning systems and seat design. 

The program's projected acquisition costs grew $209 million (52 
percent) from the initial estimate. Program officials attribute the 
increase to contract costs, among others. The program awarded the 
prime contract after the initial estimate, and the award price was 
higher than originally projected. Logistics planning expenses also 
increased over original estimates. Program officials reported that 
they had planned to revise the life-cycle cost estimate before making 
a full production decision in December 2009, and they expect further 
cost growth related to maintenance and personnel expenses not included 
in the current estimate. Currently 2 years behind schedule, the 
program has also experienced significant schedule delays. Program 
officials attribute the schedule delays to bid protests that delayed 
the contract award. 

Challenges: 

With over one-third of boats ordered as of September 2009, the program 
has made a substantial investment before the completion of operational 
testing. The program reports that initial testing results have been 
positive with no major design issues identified. Program officials 
reported a shortage of government staff to support full-rate 
production. For example, the Green Bay production facility has been 
understaffed, and the program has used contractors to meet needs where 
possible. The contract includes terms to increase unit price if the 
program does not order a minimum number of boats in a given year, 
according to officials. Program officials indicated they have not 
incurred any price increases for late orders, but there is a risk that 
future-year budgets will not be sufficient to maintain the order 
schedule. The program schedule could also slip if the program does not 
order a minimum number of boats. 

Program Office Comments and Our Response: 

Program officials stated that Response Boat-Medium completed 
operational testing and evaluation in December 2009, and has entered 
full-rate production. They stated that required personnel for full-
rate production have been approved and the Green Bay production 
facility is now appropriately staffed. However, program office data 
show that the program remains understaffed. Program officials stated 
that key program documents did not require departmental approval at 
the time they were approved. The program provided us with a revised 
cost estimate, approved by the Coast Guard in January 2010 that shows 
life-cycle costs increased to over $2 billion. The cost increase is 
primarily due to operating crew personnel costs previously not 
included in life-cycle estimates, as well as increased fuel costs. 

[End of section] 

U.S. Coast Guard: Sentinel Class Patrol Boat: 

[Photograph: Source: Bollinger Shipyards, Inc.] 

The Sentinel class patrol boat, previously known as the Fast Response 
Cutter, is conceived as a patrol boat with high readiness, speed, 
adaptability, and endurance to perform a wide range of missions. After 
terminating previous design efforts under a systems integrator, the 
Coast Guard pursued acquisition of a modified, commercially available 
patrol boat. The Sentinel class will replace the legacy 110 foot 
patrol boats. 

Current Status: 

In December 2009 the Coast Guard awarded a contract for three low-rate 
production boats, bringing the total number of boats under contract to 
four. Delivery is scheduled to begin in	December 2011 with 58 boats 
planned at a total acquisition cost of $3.9 billion.
	
Timeline: 
Start of acquisition (9/08); 
Preliminary design review (4/09); 
Critical design review (11/09); 
Low-rate production decision (12/09); 
Initial operating capability (12/12); 
Full operating capability (9/22). 

Program Challenges: 
* Cost increases; 
* Schedule delays; 
* Test and integration risks; 
* Lack of approved requirements. 

Program Essentials: 
Component: United States Coast Guard; 
Major contractor(s): Bollinger Shipyards; 
Fiscal year 2010 funding requested: $243 million; 
Program office workforce: 14 total government positions planned; 13 
total government staff employed; 11 support contractors. 

Performance (then-year dollars): 

Total acquisition cost: Initial estimate: $3,206 million[A]; 
Total acquisition cost: Latest estimate: $3,928 million[A]; 
Life-cycle cost estimate: Initial estimate: $22,256 million[A]; 
Life-cycle cost estimate: Latest estimate: $14,475 million[A]; 
Quantity: Initial estimate: 58; 
Quantity: Latest estimate: 58; 
Initial capability: Initial estimate: Sept. 2011; 
Initial capability: Latest estimate: Dec. 2012; 
Full capability: Initial estimate: Sept. 2016; 
Full capability: Latest estimate: Sept. 2022. 

[A] Note: Estimates based on 2007 baseline and 2009 U.S. Coast Guard 
Quarterly Acquisition Report to Congress. 

Key Program Documents: 

Initial version of: Acquisition Program Baseline; 
Department approval date: May 2007. 

Initial version of: Mission Need Statement; 
Department approval date: Apr. 2005. 

Initial version of: Operational Requirements Document; 
Department approval date: Not yet approved. 

Initial version of: Acquisition Plan; 
Department approval date: Oct. 2009. 

Initial version of: Integrated Logistics Support Plan; 
Department approval date: Not yet approved. 

Sentinel Class Patrol Boat: 

Background: 

In February 2008, the Coast Guard terminated the original patrol boat 
designs proposed by Integrated Coast Guard Systems, the primary 
contractor for Deepwater, after approximately $39 million had been 
allocated. Since the need for a new patrol boat was pressing, the 
Coast Guard pursued acquisition of a modified commercially available 
patrol boat with similar performance capabilities to the original 
design—now known as the Sentinel class patrol boat. In December 2009, 
after Department of Homeland Security (DHS) authorization, the Coast 
Guard awarded a contract to Bollinger Shipyards for low-rate initial 
production of three boats, bringing the total number of boats on 
contract to four. 

Performance: 

The project is currently estimated at approximately $722 million over 
its original $3.2 billion baseline for acquisition cost, though the 
number of planned boats has not changed. According to program 
officials, the estimated life-cycle cost has decreased by over $7.8 
billion due to an adjustment of the expected service life and use of 
actual costs for support. Previous estimates for service life of the 
two proposed Integrated Coast Guard Systems designs were 35 years and 
15 years. The Sentinel class is expected to have a service life of 20 
years, which reduces the years in service overall and, therefore, the 
costs expected over the life cycle. Due to program restructuring and 
contract delays, the project has experienced delays in the achievement 
of both initial and full operating capability. 

Challenges: 

Because of the pressing need for the Sentinel class patrol boats, the 
Coast Guard awarded a design and construction contract for the first 
patrol boat before completing all the acquisition reviews and 
documentation required. According to Coast Guard officials, DHS 
reviewed the operational requirements document for Sentinel in 
December 2009, prior to authorization and award of the low-rate 
initial production contract, but further revisions are necessary 
before approving the document. 

The Coast Guard acknowledges that due to its accelerated schedule the 
Sentinel class program faces testing, integration, and software 
challenges. Currently the Coast Guard plans to place on contract up to 
15 boats before completing operational testing and evaluation. This 
could lead to expensive changes to the design once production has 
begun if significant weaknesses are found in testing, a challenge the 
Coast Guard acknowledges and expects to mitigate through the design 
and review processes. Though the Coast Guard uses an existing design 
for the Sentinel class, there may be challenges with integrating the 
required sensors and antennae in a way that minimizes interference. 
The Navy's Naval Surface Warfare Center in Dahlgren, Virginia, will 
assess the placement of the sensors and antennae and provide 
recommendations to the Coast Guard to mitigate this problem. The Coast 
Guard's plan to use existing government command and control software 
to utilize many of these sensors may result in software and hardware 
integration challenges. To address this challenge, the Coast Guard 
plans to test the software on two operational mock-ups prior to 
installation. 

Program Office Comments: 

The operational requirements document for the Sentinel class patrol 
boat received approval from the Coast Guard in September 2009 and DHS 
in March 2010. Other technical comments were incorporated as 
appropriate. 

[End of section] 

Agency Comments and Our Evaluation: 

We provided a draft of this report to DHS for review and comment. DHS 
generally concurred with our findings, citing the review of actions 
taken and efforts under way to improve the acquisition review process, 
particularly the development and implementation of the department's 
acquisition management directive. The department's comments are 
reprinted in appendix II. DHS also provided technical comments which 
we incorporated as appropriate and where supporting documentation was 
provided. DHS provided specific comments on four areas of our 
findings, as follows. 

With regard to our review of DHS's acquisition oversight, DHS noted 
that we reported that more than 40 major programs have not yet been 
reviewed by the ARB, and stated that the department complemented the 
ARB process with a portfolio review process used for 61 of 67 major 
acquisition programs in fiscal year 2009, which were used to 
prioritize programs for ARB reviews. We acknowledge in our report that 
in order to provide some level of departmental oversight for major 
programs not yet reviewed by the ARB, DHS acquisition oversight staff 
worked with selected components to conduct these portfolio reviews. 
However, it is important to observe that these portfolio reviews do 
not take the place of formal ARB reviews, do not include the senior 
officials who comprise the ARB, and are not part of the acquisition 
review process as described in DHS's acquisition management directive. 

In response to a point in the report indicating that DHS may waive 
some oversight requirements on a case-by-case basis, without clear 
criteria, for programs that have passed certain phases, DHS stated 
that flexibility was built into the acquisition review process to 
allow programs to tailor some documentation requirements. DHS further 
commented that this "tailoring criterion provides clear (albeit not 
explicit) guidance" to program managers and the Acquisition Program 
Management Division. However, DHS did not provide any examples of how 
these requirements are tailored or how these waivers are applied and 
documented, and we have no evidence that this is clearly understood by 
program managers. 

With regard to our statement that acquisition management processes do 
not inform budget decisions as required by DHS policy, the department 
stated that they designed acquisition policy to "interlink" with both 
the budgeting and strategic requirements key decision processes. 
Specifically, the Acquisition Program Management Division participates 
in the budget formulation process. We agree that this is positive 
collaboration. However, we reported in 2008 that DHS's previous 
investment review process also highlighted links to the budget, yet 
the results of oversight reviews did not consistently inform budget 
decisions. While DHS's interim acquisition management directive more 
clearly creates a link between the budget and requirements processes, 
DHS has not provided evidence that budget decisions are informed by 
the acquisition review process. Further, DHS has not yet reestablished 
the Joint Requirements Council, which the department's revised 
acquisition management directive states should inform the department's 
budget decisions in order to deliver needed capabilities to end users. 

With regard to our analysis of program cost, DHS stated that we chose 
to use OMB's Exhibit 300 data for the programs we reviewed in lieu of 
life-cycle cost estimates. DHS further stated that the Exhibit 300 
data are based on the approved budget for a particular program, and 
most of these data for existing DHS programs are not based on 
validated cost estimates. Therefore, DHS believes that there is a 
likelihood of significant error in cost growth comparisons and 
analyses using these data. We explain in our analysis in the report 
that we used the official Exhibit 300 data DHS reports to OMB because 
DHS expressed concerns about the cost data programs reported to us in 
our data collection instrument, and DHS was unable to provide us with 
one consistent source for acquisition and life-cycle cost estimates. 
The Exhibit 300 data, as part of the executive branch capital planning 
process, are designed to meet the requirement for reports to the 
Congress to ensure reliable business cases for investments[Footnote 
47] and the data reported are intended to represent valid acquisition 
and life-cycle cost estimates. Our analysis of cost growth provides 
insights into how planned investment amounts for some acquisitions 
have significantly increased over time, which can result in 
insufficient funding to fulfill future mission requirements. 

While DHS has made recent progress in clarifying acquisition oversight 
processes, much remains to be done to ensure proper implementation and 
departmentwide coordination. Managing hundreds of billions of dollars 
of investments to maximize resources and effectively meet critical 
homeland security missions will require DHS to ensure consistent 
oversight, evaluation of affordability and trade-offs, and accurate 
cost estimates for making investment decisions. 

We are sending copies of this report to interested congressional 
committees, the Secretary of Homeland Security, and the Director of 
the Office of Management and Budget. In addition, the report will be 
available at no charge on GAO's Web site at [hyperlink, 
http://www.gao.gov] . 

If you or your staff have questions about this report, please contact 
me at (202) 512-4841 or huttonj@gao.gov. Contact points for our 
Offices of Congressional Relations and Public Affairs may be found on 
the last page of this report. Principal contributors to this report 
were Amelia Shachoy, Assistant Director; Sean Seales; Celina Davidson; 
Daniel Novillo; LeAnna Parkey; Nathan Tranquilli; J. Kristopher 
Keener; Kenneth Patton; Sylvia Schatz; Morgan Delaney Ramaker; and 
Robert Swierczek. 

Signed by: 

John P. Hutton, Director: 
Acquisition and Sourcing Management: 

List of Addressees: 

The Honorable Joseph I. Lieberman:
Chairman:
The Honorable Susan M. Collins:
Ranking Member:
Committee on Homeland Security and Governmental Affairs:
United States Senate: 

The Honorable Frank R. Lautenberg:
Interim Chairman:
Subcommittee on Homeland Security:
Committee on Appropriations:
United States Senate: 

The Honorable Claire C. McCaskill:
Chairman:
Ad Hoc Subcommittee on Contracting Oversight:
Committee on Homeland Security and Governmental Affairs:
United States Senate: 

The Honorable Bennie G. Thompson:
Chairman:
Committee on Homeland Security:
House of Representatives: 

The Honorable Edolphus Towns:
Chairman:
The Honorable Darrell E. Issa:
Ranking Member:
Committee on Oversight and Government Reform:
House of Representatives: 

The Honorable David E. Price:
Chairman:
The Honorable Harold Rogers:
Ranking Member:
Subcommittee on Homeland Security:
Committee on Appropriations:
House of Representatives: 

The Honorable Gus M. Bilirakis:
Ranking Member:
Subcommittee on Management, Investigations, and Oversight:
Committee on Homeland Security:
House of Representatives: 

[End of section] 

Appendix I: Objectives, Scope and Methodology: 

Our objectives were to (1) provide an update on DHS's efforts to 
implement acquisition oversight for all acquisitions; (2) describe 
acquisition performance and common challenges across selected 
programs; and (3) provide individual profiles for each of the selected 
programs. 

To provide an update on acquisition oversight, we reviewed the 
department's interim acquisition management directive that was in 
effect during the period of our review--Acquisition Management 
Directive 102-01--and related guidance, and we identified whether 
fiscal year 2009 oversight activities for all 67 major acquisition 
programs were completed in accordance with the directive. To do this, 
we collected and analyzed Acquisition Review Board (ARB) decision 
memorandums, summary tracking documents, and program documents for key 
decision events for major acquisitions. We identified ARB decision 
memorandum action items, and characterized and identified the status 
of those items. We also reviewed recommendations from our prior work 
and the status of their implementation. To obtain a better 
understanding of departmental oversight initiatives, we interviewed 
officials responsible for acquisition oversight, including 
representatives of the Chief Procurement Officer's Acquisition Program 
Management and Cost Analysis Division, the Office of Policy's 
Screening Coordination Office, and the Science and Technology 
Directorate's Test & Evaluation and Standards Division. To learn more 
about component-level oversight, we reviewed which components had 
nominated and received departmental approval of Component Acquisition 
Executives (CAE), and we interviewed acquisition officials at the six 
components in our review--Customs and Border Protection, Federal 
Emergency Management Agency, National Protection and Programs 
Directorate, Office of Health Affairs, Transportation Security 
Administration, and the United States Coast Guard--about their 
acquisition policies and practices, staffing, departmental 
coordination, and relevant challenges. We did not, however, 
specifically assess the extent to which the department's acquisition 
guidance is consistent with best practices. 

To describe acquisition performance and common challenges and to 
profile selected programs, we took several steps. We selected 18 
programs across six components--16 major acquisition programs, as well 
as 2 smaller programs critical to DHS's mission--based on several 
factors, including total projected funding for fiscal years 2007 
through 2012, current stage in the DHS acquisition life cycle, and 
relevance to front-line homeland security missions. The 18 programs 
selected represent about $100 billion in life-cycle costs and about 
$38 billion in acquisition costs. The analysis of acquisition 
performance and common challenges across the selected programs focused 
on 15 programs. We did not include in this analysis two nonmajor 
programs, which are not subject to the same requirements as major 
programs--Biosurveillance Common Operating Network and the Integrated 
Public Alert and Warning System--and one major program that had not 
started acquisition activities at the time of our review, BioWatch 
Generation-3. The profiles of the selected programs include all 18 
programs selected for our review. To evaluate the program data, we 
drew on criteria from our prior work on acquisition management, 
including the methodologies we used for assessments of Department of 
Defense (DOD) and the National Aeronautics and Space Administration 
(NASA) programs;[Footnote 48] acquisition guidance from DHS and other 
federal agencies; and OMB's guidance on capital planning.[Footnote 49] 
We also reviewed relevant GAO and DHS Inspector General reports on the 
selected acquisitions. 

Data Collection and Limitations: 

To collect program data, we developed a standardized data collection 
instrument (DCI) for key data on performance and challenges for the 
selected programs, and we met with the program offices to clarify data 
requested in advance of completion. The DCI was organized by 
categories including program contracts; issues; cost; schedule; 
requirements; staffing; technology; design; and software. To confirm 
the DCI data, we reviewed available official documents from each 
program, including: the Acquisition Program Baseline; Acquisition 
Plan; Acquisition Decision Memorandums; Program Management Review and 
other relevant briefings; cost performance or Earned Value Management 
reports; and Integrated Master Schedule. To learn more about program 
data and issues, we interviewed program officials for each of the 18 
programs we reviewed. 

Because DHS acquisition oversight officials expressed concerns about 
the reliability of the cost data reported by program offices in the 
DCI, we also researched DHS Exhibit 300 cost data reported to OMB as 
part of the executive branch capital planning process.[Footnote 50] 
For four Coast Guard programs,[Footnote 51] we also reviewed the Coast 
Guard's Quarterly Acquisition Reports to Congress and Acquisition 
Program Baselines to obtain the best available data. We based our 
analysis on these sources as they represented more complete and 
official data used for making important planning and budgeting 
decisions. In addition, not all programs reported data for all of the 
categories in the DCI because some requested data did not apply to the 
program, or the program could not obtain the requested data. We 
excluded these programs from certain analyses. DCI information was 
self-reported by the program offices, and we did not independently 
verify the data provided, but we took appropriate steps to address 
data reliability including reviewing related documentation; 
interviewing knowledgeable agency officials; testing of data; and 
reviewing related internal controls. Those data that were found to be 
sufficiently reliable were used to report on the condition of selected 
DHS acquisition programs. Findings from program data analysis cannot 
be generalized to the total DHS portfolio of acquisition programs. All 
data was current as of 2009, with the exception of latest estimates of 
program costs obtained from OMB Exhibits 300, which were current as of 
January or February 2010. 

Cost and Schedule Analysis: 

To assess cost and schedule performance across the selected DHS major 
programs, we aggregated official program data and compared initial 
cost and schedule estimates to latest available estimates. We used 
initial cost and schedule estimates since 2003, after the creation of 
DHS, although some of the 18 programs were initiated by other federal 
agencies prior to 2003. All cost data are presented in nominal "then 
year" dollars consistent with cost data available from OMB Exhibit 
300s, the Coast Guard's Quarterly Acquisition Reports to congressional 
appropriations committees, and official Acquisition Program Baselines. 
[Footnote 52] BioWatch Generation-3, which had not started acquisition 
activities at the time of our review, and two nonmajor programs in our 
review--Biosurveillance Common Operating Network and Integrated Public 
Alert and Warning System--were excluded from the overall analysis. 

To assess schedule performance, we calculated the average delay from 
initial to latest estimates for Initial Operating Capability (IOC) and 
Full Operating Capability (FOC) for all selected programs having 
available data. Initial capabilities are delivered when initial end- 
users have received the new system and can use it operationally, and 
delivery of full capabilities occurs when all end-users have received 
the system. Some programs reported multiple IOC or FOC dates. In these 
cases we used the first and last planned delivery of capabilities to 
operational users as the basis for the program-level IOC and FOC date. 
In some cases, programs reported schedule milestones using a period of 
time, such as a month or year, and in these cases we used the last 
date of the given period as the basis for the estimated date. Two 
programs, Automated Commercial Environment and US-VISIT Unique 
Identity, were unable to provide complete schedule data due to 
unavailable information and, therefore, we excluded these programs 
from all or part of the schedule analysis. 

Common Program Challenges Analysis: 

As federal acquisition policy and guidance emphasize the importance of 
sound acquisition planning, we focused in particular on acquisition 
planning issues. To assess common challenges for the selected 
programs, we analyzed information programs reported on requirements, 
key acquisition documents, program office staffing, and sustainment 
planning across the programs. We also analyzed relevant program 
documentation and assessed information from interviews with program 
officials. Three programs were excluded from the assessment of overall 
performance: the two nonmajor programs, the Biosurveillance Common 
Operating Network and Integrated Public Alert and Warning System, and 
the BioWatch Generation-3 program, which was pre-acquisition at the 
time we collected the data. Challenges we identified do not represent 
an exhaustive list; however, past work identifies these challenges as 
detrimental to program performance. 

To assess baseline requirements stability, we analyzed delays in 
setting baseline requirements as well as changes to existing 
requirements. According to DHS guidance, the baseline requirements 
must include a threshold value that is the minimum acceptable value 
which, in the user's judgment, is necessary to satisfy the need. If 
threshold values are not achieved, program performance may be 
seriously degraded, the program may be too costly, or the program may 
no longer be timely. Baseline requirements, also referred to as Key 
Performance Parameters, were categorized as cost, performance or 
schedule requirements. We compared requirements from initial baselines 
from 2003 or later, to most recent Acquisition Program Baseline (APB) 
requirements. We also examined the approval of key acquisition 
documents, including the Mission Need Statement, Operational 
Requirements Document, and Acquisition Program Baseline, prior to 
initiation of acquisition activities. We evaluated whether key 
acquisition documents were approved at either the component or 
department level prior to awarding contracts to initiate acquisition 
activities. 

To assess staffing levels, we evaluated planned and filled positions 
for government staff and contractor support. We analyzed government 
vacancy levels by primary function and calculated the ratios of 
government staff and contractor support to total reported positions. 
We obtained data on acquisition program managers, including 
certification level, length of time as program manager, and permanent 
assignment to the program. 

To assess sustainment planning, we reviewed approval dates for the 
Integrated Logistics Support Plan, and whether the plan was approved 
beyond the program, at either the component or department level, as 
required by DHS guidance. 

To identify common program execution challenges, we analyzed 
challenges reported in data collection instruments, program documents, 
and interviews. We developed the following broad categories for 
execution challenges: technical capability, partner dependence, and 
funding issues. The execution challenges we identified are not 
exhaustive; however, they provide a sense of the issues programs 
reported. 

Individual Program Assessments: 

To assess each of the 18 selected acquisition programs, we summarized 
individual program data in a two-page report format. We prepared the 
individual program assessments based on DCI data and supporting 
documentation, interviews with program officials, and our prior work. 
Each individual program assessment outlines essential program 
information including a description of program objectives and purpose; 
current status, cost, and schedule performance; major contractors; 
2010 budget request; staffing profile; a summary of program 
challenges; and status of department-or component-level approval of 
key acquisition documents. In addition, we provide a summary of 
program background, performance, and challenges. 

To present cost and schedule performance data, we compared initial 
cost and schedule estimates to latest available estimates. We used 
initial cost and schedule estimates since 2003, after the start of 
DHS, although some of the 18 programs were initiated prior to this 
time. All cost data are presented in then-year dollars, consistent 
with official program budget documents, with the exception of the 
Integrated Public Alert and Warning System program cost data which 
were available in constant dollars only. To assess schedule 
performance, we compared initial and latest estimates for IOC and FOC. 
Other schedule milestones were also reported on the program timeline 
including Preliminary Design Review; Critical Design Review; 
Production Readiness Review; and First Asset Delivery. In some cases, 
a milestone significant to the program was also included in the 
timeline. 

To assess the challenges for each program, we reviewed the data 
reported by category in the DCI and official program documents, and we 
interviewed the program office representatives about the information 
reported. For individual programs we collected program data on 
potential challenges, including requirements stability; staffing; 
sustainment planning; contracting activity; technology maturity; 
design maturity; and software development. Our analysis of 
requirements stability, staffing and sustainment planning is 
consistent with methods discussed above. 

For programs reporting on technology maturity and design data, we 
requested data based on best practice indicators[Footnote 53] for 
technology maturity and design stability drawn from our body of work 
established in DOD and NASA assessments of selected systems. However, 
the selected DHS programs reported limited data on technology maturity 
and design data as they do not consistently use technology readiness- 
level data for critical technologies, and programs used varying 
metrics to measure design stability. Furthermore, many of the programs 
make extensive use of commercial-off-the-shelf products not developed 
by the program. 

We conducted our work from March 2009 to June 2010 in accordance with 
generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings 
and conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

[End of section] 

Appendix II: Comments from the Department of Homeland Security: 

U.S. Department of Homeland Security: 
Washington, DC 20528: 

June 22, 2010: 

Mr. John P. Hutton: 
Director, Acquisition and Sourcing Management: 
U.S. Government Accountability Office: 
441 G Street, NW: 
Washington, DC 20548: 

Dear Mr. Hutton: 

The Department of Homeland Security (DHS) appreciates the opportunity 
to comment on the draft Government Accountability Office (GAO) report, 
GAO-10-588SP, entitled "Assessments of Selected Complex Acquisitions." 

The Department is encouraged that the draft report cites the progress 
that we have made over the past several years to improve acquisition 
processes. We have instituted several major changes that are beginning 
to show results. The development and implementation of Directive 102-
01 (Acquisition Management) has provided improved discipline and 
structure to the Department's acquisition and governance processes. 
The improved Acquisition Review Board (ARB) process has been used over 
sixty times since March 2008. The ARB provides a focused, issue-
oriented governance process ensuring that major programs are 
accurately evaluated, and that decisions and actions are properly 
documented and tracked to completion. The establishment of the 
Acquisition Program Management Division and the Cost Analysis Division 
in the Office of the Chief Procurement Officer has provided a 
knowledgeable cadre of acquisition-experienced individuals that 
support the governance process, and provide assistance to acquisition 
programs on a day-to-day basis. Between these accomplishments, and 
other initiatives currently underway, we expect to see additional 
improvements in the near future. 

DHS does wish to point out several areas where the Department 
evaluation differs from that of GAO in this report: 

* GAO identified that more than forty major programs have not yet been 
reviewed by the ARB. 
- DHS complements the ARB process with a portfolio review process 
executed by the Acquisition Program Management Division in conjunction 
with the Component Acquisition Executive (CAE) or the Component's 
senior acquisition staff. This review process, in its second year of 
operation, executes a focused, collaborative review of each 
Component's major program portfolio with APMD, and helps identify 
program issues, including programs which need to proceed to an ARB on 
an accelerated basis. In FY 2009, the portfolio process reviewed 61 of 
the 67 DHS major acquisition programs. 

* GAO evaluated the DHS acquisition management processes as not 
sufficiently informing budget processes as required by DHS policy.
- DHS designed the revised acquisition policy to "interlink" with both 
the budgeting and the strategic requirements key decision processes. 
Key leaders in both these decision processes sit the Acquisition 
Review Team and the Acquisition Review Board, ensuring that these 
processes' perspectives are incorporated in the decisions made by the 
ARB. In turn, APMD participates reciprocally with both processes. 
Specifically, APMD is a standing team member with the Program Analysis 
and Evaluation (PA&E) division in the review of submitted Resource 
Allocation Proposals, and in the execution of the annual Program 
Review Board process (a key component of DHS' annual budget 
formulation process). 

* GAO elected to use the OMB 300 budget submissions for the current 
state of program costs, for the assessed major programs in this 
report, in lieu of life cycle cost estimates (LCCEs). This was done 
due to the early stage of LCCE implementation in DHS.
- DHS notes that OMB 300 data is based on the approved budget for the 
particular program. Since LCCE information for DHS programs is in its 
infancy, most OMB 300 data for existing programs is not based on 
validated program LCCEs. Since the OMB 300 data in many cases is not 
derived from validated cost estimates, DHS believes that there is the 
likelihood of significant error in cost growth comparisons and 
analyses using this data. 

* GAO identified that DHS may "waive some oversight requirements on a 
case-by-case basis, without clear criteria, for programs that passed 
certain phases--such as departmental approval of a Mission Need 
Statement for a program that has already deployed capability."
- DHS, in implementing the Directive 102-01 acquisition policy and 
process in November 2008, was faced with the task of transitioning 67 
operating major acquisition programs to this new directive. 
Flexibility was built into the new process to allow programs that were 
well into the "obtain" or "produce /deploy/support" phases of the D-
102-01 Acquisition Life Cycle to tailor some D-102-01 requirements 
(for instance, not to generate documentation from earlier phases of 
the life cycle). That tailoring criterion provides clear (albeit not 
explicit) guidance to the program manager and APMD as each program is 
assessed upon its entry into the new policy. 

Technical comments are provided as an enclosure to this letter. 

DHS wishes to thank you and the GAO audit team for the professionalism 
and excellent dialog which characterized the execution of this audit. 
This was particularly important given the challenges in implementing 
this particular complex audit process (which will be re-executed on an 
annual basis) in a way that addresses the specifics of this 
Department's processes. 

DHS looks forward to continuing our partnership, with the common goal 
of improving the Department's execution of its acquisition 
responsibilities. 

Sincerely, 

Signed by: 

Jerald E. Levine: 
Director: 
Departmental GAO/OIG Liaison Office: 

Enclosure: 

[End of section] 

Appendix III: The Acquisition Life Cycle, Systems Engineering Life 
Cycle and Key Acquisition Documents at DHS: 

[Figure: Refer to PDF for image: Life cycle map] 

Acquisition decision Event: ADE 1; 
Acquisition Life Cycle Phase: Need; 
Documents Requiring Department Approval: MNS; CDP; AP. 

Acquisition decision Event: ADE 2A; 
Acquisition Life Cycle Phase: Analyze/Select; 
Systems Engineering Life Cycle Phase: Solution Engineering; 
Documents Requiring Department Approval: APB; ILSP; AP; ORD. 

Acquisition decision Event: ADE 2B; 
Acquisition Life Cycle Phase: Obtain; 
Systems Engineering Life Cycle Phase: Planning; 
Documents Requiring Department Approval: APB; ILSP; TEMP; SELC/SE TP; 
Systems Engineering Life Cycle Phases: Requirements Definition; 
Design; Development; Integration and Testing; Implementation; 

Acquisition Decision Event: ADE 3; 
Acquisition Life Cycle Phase: Produce/Deploy/Support; 
Systems Engineering Life Cycle Phase: Operations and Maintenance; 
Disposition; 
Documents Requiring Department Approval: APB; ILSP. 

MNS: Mission Need Statement; 
CDP: Capability Development Plan; 
AP: Acquisition Plan; 
APB: Acquisition Program Baseline; 
ILSP: Integrated Logistics Support Plan; 
ORD: Operational Requirements Document; 
TEMP: Test and Evaluation Master Plan; 
SELC/SE TP: Systems Engineering Life Cycle Tailoring Plan. 

Source: DHS Acquisition Instruction/Guidebook 102-01-001, interim, 
version 1.9, Nov. 7, 2008. 

[End of figure] 

Table: Key Acquisition Documents Requiring Department-level Approval: 

Document Name: Mission Need Statement; 
Description: Provides a high-level description of the mission need, 
whether from a current or impending gap, based on business-case 
planning. The Mission Need Statement, prepared by the Component, 
outlines only the concept of the solution to fill the gap and does not 
provide information on specific acquisitions/types of acquisition that 
could provide that capability. 

Document Name: Capability Development Plan; 
Description: Serves as the agreement between the Component Head, the 
Program/Project Manager, and the Acquisition Decision Authority on the 
activities, cost, schedule, and performance boundaries of the work to 
be performed in the Analyze/Select phase. 

Document Name: Acquisition Plan; 
Description: A living document that spans the life of the acquisition. 
It provides a top-level strategy for future sustainment and support 
and a recommendation for the overall acquisition approach and types of 
acquisition. 

Document Name: Acquisition Program Baseline; 
Description: A summary of the critical cost, schedule, and performance 
parameters, expressed in measurable, quantitative terms, which must be 
met in order to accomplish the goals of the investment. 

Document Name: Integrated Logistics Support Plan; 
Description: The formal acquisition management document that describes 
the management approach for obtaining a highly supportable capability 
with an affordable and effective support structure. 

Document Name: Operational Requirements Document; 
Description: The Operational Requirements Document captures the 
business or operational user Key Performance Parameters. They are 
overarching documents that describe the mission, objectives, and 
capabilities in operationally relevant terms. 

Document Name: Test and Evaluation Master Plan; 
Description: The basic "top-level" planning document for Test and 
Evaluation related activities for major acquisition programs. 
Describes the necessary Developmental Test and Evaluation and 
Operational Test and Evaluation that needs to be conducted to 
determine system technical performance, operational 
effectiveness/suitability, and limitations. 

Document Name: Systems Engineering Life Cycle Tailoring Plan; 
Description: This plan tailors the phases, products and reviews in the 
system engineering life cycle to meet the specific needs of each 
program and project. 

Source: DHS Acquisition Instruction/Guidebook 102-01-001 Version 1.9 
and Appendices D and L. 

[End of table] 

[End of section] 

Related GAO Products: 

GAO Review of the Department of Homeland Security's Certification of 
the Secure Flight Program--Cost and Schedule Estimates. [hyperlink, 
http://www.gao.gov/products/GAO-10-535R]. Washington, D.C.: April 5, 
2010. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-10-388SP]. Washington, 
D.C.: March 30, 2010. 

NASA: Assessments of Selected Large-Scale Projects. [hyperlink, 
http://www.gao.gov/products/GAO-10-227SP]. Washington, D.C.: February 
1, 2010. 

Secure Border Initiative: DHS Needs to Address Testing and Performance 
Limitations That Place Key Technology Program at Risk. [hyperlink, 
http://www.gao.gov/products/GAO-10-158]. Washington, D.C.: January 29, 
2010. 

Defense Acquisitions: Managing Risk to Achieve Better Outcomes. 
[hyperlink, http://www.gao.gov/products/GAO-10-374T]. Washington, 
D.C.: January 20, 2010. 

Biosurveillance: Developing a Collaboration Strategy Is Essential to 
Fostering Interagency Data and Resource Sharing. [hyperlink, 
http://www.gao.gov/products/GAO-10-171]. Washington, D.C.: December 
18, 2009. 

Homeland Security: Key US-VISIT Components at Varying Stages of 
Completion, but Integrated and Reliable Schedule Needed. [hyperlink, 
http://www.gao.gov/products/GAO-10-13]. Washington, D.C.: November 19, 
2009. 

Information Technology: Agencies Need to Improve the Implementation 
and Use of Earned Value Techniques to Help Manage Major System 
Acquisitions. [hyperlink, http://www.gao.gov/products/GAO-10-2]. 
Washington, D.C.: October 8, 2009. 

Aviation Security: DHS and TSA Have Researched, Developed, and Begun 
Deploying Passenger Checkpoint Screening Technologies, but Continue to 
Face Challenges. [hyperlink, http://www.gao.gov/products/GAO-10-128]. 
Washington, D.C.: October 7, 2009. 

Secure Border Initiative: Technology Deployment Delays Persist and the 
Impact of Border Fencing Has Not Been Assessed. [hyperlink, 
http://www.gao.gov/products/GAO-09-1013T]. Washington, D.C.: September 
17, 2009. 

Homeland Security: Despite Progress, DHS Continues to Be Challenged in 
Managing Its Multi-Billion Dollar Annual Investment in Large-Scale 
Information Technology Systems. [hyperlink, 
http://www.gao.gov/products/GAO-09-1002T]. Washington, D.C.: September 
15, 2009. 

Secure Border Initiative: Technology Deployment Delays Persist and the 
Impact of Border Fencing Has Not Been Assessed. [hyperlink, 
http://www.gao.gov/products/GAO-09-896]. Washington, D.C.: September 
9, 2009. 

Emergency Preparedness: Improved Planning and Coordination Necessary 
for Modernization and Integration of Public Alert and Warning System. 
[hyperlink, http://www.gao.gov/products/GAO-09-834]. Washington, D.C.: 
September 9, 2009. 

Coast Guard: Better Logistics Planning Needed to Aid Operational 
Decisions Related to the Deployment of the National Security Cutter 
and Its Support Assets. [hyperlink, 
http://www.gao.gov/products/GAO-09-497]. Washington, D.C.: July 17, 
2009. 

Coast Guard: As Deepwater Systems Integrator, Coast Guard Is 
Reassessing Costs and Capabilities but Lags in Applying Its 
Disciplined Acquisition Approach. [hyperlink, 
http://www.gao.gov/products/GAO-09-682]. Washington, D.C.: July 14, 
2009. 

Aviation Security: TSA Has Completed Key Activities Associated with 
Implementing Secure Flight, but Additional Actions Are Needed to 
Mitigate Risks. [hyperlink, http://www.gao.gov/products/GAO-09-292]. 
Washington, D.C.: May 13, 2009. 

Defense Acquisitions: Measuring the Value of DOD's Weapon Programs 
Requires Starting with Realistic Baselines. [hyperlink, 
http://www.gao.gov/products/GAO-09-543T]. Washington, D.C.: April 1, 
2009. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-09-326SP]. Washington, 
D.C.: March 30, 2009. 

Defense Acquisitions: DOD Must Prioritize Its Weapon System 
Acquisitions and Balance Them with Available Resources. [hyperlink, 
http://www.gao.gov/products/GAO-09-501T]. Washington, D.C.: March 18, 
2009. 

GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs. [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP]. Washington, D.C.: March 2, 
2009. 

High-Risk Series: An Update. [hyperlink, 
http://www.gao.gov/products/GAO-09-271SP]. Washington, D.C.: January 
22, 2009. 

Department of Homeland Security: A Strategic Approach Is Needed to 
Better Ensure the Acquisition Workforce Can Meet Mission Needs. 
[hyperlink, http://www.gao.gov/products/GAO-09-30]. Washington, D.C.: 
November 19, 2008. 

Department of Homeland Security: Billions Invested in Major Programs 
Lack Appropriate Oversight. [hyperlink, 
http://www.gao.gov/products/GAO-09-29]. Washington, D.C.: November 18, 
2008. 

Secure Border Initiative: DHS Needs to Address Significant Risks in 
Delivering Key Technology Investment. [hyperlink, 
http://www.gao.gov/products/GAO-08-1086]. Washington, D.C.: September 
22, 2008. 

Critical Infrastructure Protection: DHS Needs to Better Address Its 
Cybersecurity Responsibilities. [hyperlink, 
http://www.gao.gov/products/GAO-08-1157T]. Washington, D.C.: September 
16, 2008. 

Secure Border Initiative Fiscal Year 2008 Expenditure Plan Shows 
Improvement, but Deficiencies Limit Congressional Oversight and DHS 
Accountability. [hyperlink, http://www.gao.gov/products/GAO-08-739R]. 
Washington, D.C.: June 26, 2008. 

Coast Guard: Change in Course Improves Deepwater Management and 
Oversight, but Outcome Still Uncertain. [hyperlink, 
http://www.gao.gov/products/GAO-08-745]. Washington, D.C.: June 24, 
2008. 

Border Security: Summary of Covert Tests and Security Assessments for 
the Senate Committee on Finance, 2003-2007. [hyperlink, 
http://www.gao.gov/products/GAO-08-757]. Washington, D.C.: May 16, 
2008. 

Department of Homeland Security: Better Planning and Assessment Needed 
to Improve Outcomes for Complex Service Acquisitions. [hyperlink, 
http://www.gao.gov/products/GAO-08-263]. Washington, D.C.: April 22, 
2008. 

Privacy: Government Use of Data from Information Resellers Could 
Include Better Protections. [hyperlink, 
http://www.gao.gov/products/GAO-08-543T]. Washington, D.C.: March 11, 
2008. 

Homeland Security: Strategic Solution for US-VISIT Program Needs to Be 
Better Defined, Justified, and Coordinated. [hyperlink, 
http://www.gao.gov/products/GAO-08-361]. Washington, D.C.: February 
29, 2008. 

Secure Border Initiative: Observations on the Importance of Applying 
Lessons Learned to Future Projects. [hyperlink, 
http://www.gao.gov/products/GAO-08-508T]. Washington, D.C.: February 
27, 2008. 

Military Readiness: Navy Is Making Progress Implementing Its Fleet 
Response Plan, but Has Not Fully Developed Goals, Measures, and 
Resource Needs. [hyperlink, http://www.gao.gov/products/GAO-08-264]. 
Washington, D.C.: February 1, 2008. 

Terrorist Watch List Screening: Recommendations to Promote a 
Comprehensive and Coordinated Approach to Terrorist-Related Screening. 
[hyperlink, http://www.gao.gov/products/GAO-08-253T]. Washington, 
D.C.: November 8, 2007. 

Information Technology: Improvements for Acquisition of Customs Trade 
Processing System Continue, but Further Efforts Needed to Avoid More 
Cost and Schedule Shortfalls. [hyperlink, 
http://www.gao.gov/products/GAO-08-46]. Washington, D.C.: October 25, 
2007. 

Department of Homeland Security: Improved Assessment and Oversight 
Needed to Manage Risk of Contracting for Selected Services. 
[hyperlink, http://www.gao.gov/products/GAO-07-990]. Washington, D.C.: 
September 17, 2007. 

United States Coast Guard: Improvements Needed in Management and 
Oversight of Rescue System Acquisition. [hyperlink, 
http://www.gao.gov/products/GAO-06-623]. Washington, D.C.: May 31, 
2006. 

Defense Acquisitions: Actions Needed to Ensure Adequate Funding for 
Operation and Sustainment of the Ballistic Missile Defense System. 
[hyperlink, http://www.gao.gov/products/GAO-05-817]. Washington, D.C.: 
September 6, 2005. 

Homeland Security: Successes and Challenges in DHS's Efforts to Create 
an Effective Acquisition Organization. [hyperlink, 
http://www.gao.gov/products/GAO-05-179]. Washington, D.C.: March 29, 
2005. 

Defense Acquisitions: Information for Congress on Performance of Major 
Programs Can Be More Complete, Timely, and Accessible. [hyperlink, 
http://www.gao.gov/products/GAO-05-182]. Washington, D.C.: March 28, 
2005. 

[End of section] 

Footnotes: 

[1] GAO, High-Risk Series: An Update, [hyperlink, 
http://www.gao.gov/products/GAO-09-271SP] (Washington, D.C.: Jan. 22, 
2009). 

[2] In 2009 constant dollars. 

[3] GAO, Defense Acquisitions: Assessments of Selected Weapon Program, 
[hyperlink, http://www.gao.gov/products/GAO-10-388SP] (Washington, 
D.C.: Mar. 30, 2010) and NASA: Assessments of Selected Large-Scale 
Projects, [hyperlink, http://www.gao.gov/products/GAO-10-227SP] 
(Washington, D.C.: Feb. 1, 2010). 

[4] GAO, Defense Acquisitions: Managing Risk to Achieve Better 
Outcomes, [hyperlink, http://www.gao.gov/products/GAO-10-374T] 
(Washington, D.C.: Jan. 20, 2010). 

[5] GAO, Department of Homeland Security: Billions Invested in Major 
Programs Lack Appropriate Oversight, [hyperlink, 
http://www.gao.gov/products/GAO-09-29] (Washington, D.C.: Nov. 18, 
2008); Homeland Security: Challenges in Creating an Effective 
Acquisition Organization, [hyperlink, 
http://www.gao.gov/products/GAO-06-1012T] (Washington, D.C.: July 27, 
2006); and Defense Acquisitions: Measuring the Value of DOD's Weapon 
Programs Requires Starting with Realistic Baselines, [hyperlink, 
http://www.gao.gov/products/GAO-09-543T] (Washington, D.C.: Apr. 1, 
2009). 

[6] GAO, Department of Homeland Security: Billions Invested in Major 
Programs Lack Appropriate Oversight, [hyperlink, 
http://www.gao.gov/products/GAO-09-29] (Washington, D.C.: Nov. 18, 
2008). 

[7] GAO, Homeland Security: Despite Progress, DHS Continues to Be 
Challenged in Managing Its Multi-Billion Dollar Annual Investment in 
Large-Scale Information Technology Systems, [hyperlink, 
http://www.gao.gov/products/GAO-09-1002T] (Washington, D.C.: Sept.15, 
2009). 

[8] [hyperlink, http://www.gao.gov/products/GAO-09-29] and [hyperlink, 
http://www.gao.gov/products/GAO-09-1002T]. 

[9] [hyperlink, http://www.gao.gov/products/GAO-09-1002T]. 

[10] [hyperlink, http://www.gao.gov/products/GAO-09-1002T]. 

[11] In a September 2009 testimony we did, however, discuss how DHS 
acquisition and investment management processes had not adequately 
addressed how DHS determines and ensures that an investment is aligned 
with its Enterprise Architecture. See GAO-09-1002T. 

[12] The two nonmajor programs selected--the Biosurveillance Common 
Operating Network and the Integrated Public Alert and Warning System-- 
and one major program that had not started acquisition activities at 
the time of our review, BioWatch Generation-3, were excluded from the 
analysis of overall acquisition performance and program challenges. 
Nonmajor programs at DHS are not subject to the same acquisition 
planning requirements as major programs. Because BioWatch Generation-3 
had not awarded contracts, it was considered pre-acquisition according 
to our methodology. 

[13] [hyperlink, http://www.gao.gov/products/GAO-09-543T]. 

[14] GAO, Department of Homeland Security: Billions Invested in Major 
Programs Lack Appropriate Oversight, [hyperlink, 
http://www.gao.gov/products/GAO-09-29] (Washington, D.C.: Nov.18, 
2008). 

[15] The department operated under the March 2006 Management Directive 
No. 1400 on the Investment Review Process until November 2008 when DHS 
issued Acquisition Management Directive 102-01, interim version, which 
superseded Management Directive No. 1400. In January, 2010, DHS issued 
Directive Number 102-01, Revision Number 01, which DHS officials 
stated does not differ substantially from the interim acquisition 
management directive. 

[16] Acquisition costs include costs for all items and services for a 
designated investment. Life-cycle costs include all resources and 
associated cost elements required to develop, produce, deploy, and 
sustain a particular program from initial concept through operations, 
support, and disposal. 

[17] DHS Acquisition Management Directive 102-01, interim version, and 
DHS Acquisition Instruction/Guidebook 102-01-001, Interim Version 1.9 
(Nov. 7, 2008). 

[18] Fiscal year 2008 and fiscal year 2009 reviews included 5 nonmajor 
programs, and 3 programs reviewed in fiscal year 2008 were again 
reviewed in fiscal year 2009. 

[19] Directive 102-01, Revision number 01 states that it applies to 
acquisitions in existence on the directive's issuance date to the 
maximum extent possible and to all future acquisitions; whereas, the 
interim Directive 102-01 stated that it applied to all acquisitions 
regardless of their life-cycle stage. 

[20] [hyperlink, http://www.gao.gov/products/GAO-09-29] and GAO, 
Homeland Security: Successes and Challenges in DHS's Efforts to Create 
an Effective Acquisition Organization, [hyperlink, 
http://www.gao.gov/products/GAO-05-179] (Washington, D.C.: Mar. 29, 
2005). 

[21] GAO, Defense Acquisitions: Measuring the Value of DOD's Weapon 
Programs Requires Starting with Realistic Baselines, [hyperlink, 
http://www.gao.gov/products/GAO-09-543T] (Washington, D.C.: Apr. 1, 
2009). 

[22] As of September 2009, 26 programs were assigned action items: 16 
major acquisition programs reviewed by the ARB; 7 major acquisition 
programs not reviewed by the ARB but assigned action items as part of 
DHS oversight reviews; 3 nonmajor acquisition programs reviewed by the 
ARB. Additionally, 8 major acquisition programs reviewed by the ARB in 
fiscal years 2008 or 2009 had not yet been assigned action items. 

[23] The acquisition portfolio for the Federal Emergency Management 
Agency includes both programs and major services, as defined by DHS's 
acquisition management directive. The $5 billion assessed represents 
programs. Officials said they were still working to identify 
additional programs and the major services. 

[24] [hyperlink, http://www.gao.gov/products/GAO-09-543T]. 

[25] GAO, Defense Acquisitions: Managing Risk to Achieve Better 
Outcomes, [hyperlink, http://www.gao.gov/products/GAO-10-374T] 
(Washington, D.C.: Jan. 20, 2010). 

[26] [hyperlink, http://www.gao.gov/products/GAO-09-543T]. 

[27] The two nonmajor programs are Biosurveillance Common Operating 
Network and the Integrated Public Alert and Warning System. BioWatch 
Generation-3 had not started acquisition activities at the time of our 
review. 

[28] Automated Commercial Environment and US-VISIT programs could not 
provide both initial and latest schedule estimates for reaching full 
capability. 

[29] This appendix is based on GAO, Cost Assessment Guide: Best 
Practices for Estimating and Managing Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-07-1134SP] (Washington, D.C.: July 
2007). 

[30] DHS officials report that three programs--Secure Flight, Sentinel 
Class Patrol Boat and Western Hemisphere Travel Initiative--have 
validated life-cycle cost estimates. 

[31] For four Coast Guard programs, we analyzed the Quarterly 
Acquisition Reports to Congress to the Senate and House appropriators. 
For the nine other programs, we analyzed data reported in the Exhibit 
300 required by OMB Circular No. A-11, Part 7: Planning, Budgeting, 
Acquisition and Management of Capital Assets. 

[32] According to DHS guidance, the program manager sets the point at 
which initial operating capability is met during planning. The initial 
operating capability milestone is not a specific time reference, but 
reflects a point that indicates there is a major new capability with 
measurable program benefit available to the designated user. 

[33] [hyperlink, http://www.gao.gov/products/GAO-10-374T]. 

[34] [hyperlink, http://www.gao.gov/products/GAO-09-543T]. 

[35] GAO, Defense Acquisitions: DOD Must Prioritize Its Weapon System 
Acquisitions and Balance Them with Available Resources, [hyperlink, 
http://www.gao.gov/products/GAO-09-501T] (Washington, D.C.: Mar. 25, 
2009). 

[36] DHS, Management Directive No. 1400, Investment Review Process 
(Washington, D.C.: 2006) and DHS Acquisition Instruction Guidebook 102-
01-001 Version 1.9 (Washington, D.C.: Nov. 7, 2008). 

[37] All programs did not report data for all categories of program 
office staffing requested in the data collection instrument. 15 
programs reported total staffing data; 8 programs reported government 
staffing data by function; and 6 reported contractor staffing by 
function. Of the programs reporting government staffing by function, 
programs indicated high levels of vacancies for scientist, program 
management, financial management, and test and evaluation positions. 
All workforce data are as of 2009. 

[38] GAO, Department of Homeland Security: A Strategic Approach Is 
Needed to Better Ensure the Acquisition Workforce Can Meet Mission 
Needs, [hyperlink, http://www.gao.gov/products/GAO-09-30] (Washington, 
D.C.: Nov. 19, 2008). 

[39] GAO, Department of Homeland Security: Better Planning and 
Assessment Needed to Improve Outcomes for Complex Service 
Acquisitions, [hyperlink, http://www.gao.gov/products/GAO-08-263] 
(Washington, D.C.: Apr. 22, 2008). 

[40] GAO, Defense Acquisitions: Assessments of Selected Weapon 
Programs, [hyperlink, http://www.gao.gov/products/GAO-10-388SP] 
(Washington, D.C.: Mar. 30, 2010). 

[41] [hyperlink, http://www.gao.gov/products/GAO-10-374T]. 

[42] GAO, Department of Homeland Security: Improved Assessment and 
Oversight Needed to Manage Risk of Contracting for Selected Services, 
[hyperlink, http://www.gao.gov/products/GAO-07-990] (Washington, D.C.: 
Sept. 17, 2007). 

[43] [hyperlink, http://www.gao.gov/products/GAO-09-30]. 

[44] GAO, Defense Acquisitions: Assessments of Selected Weapon 
Programs, [hyperlink, http://www.gao.gov/products/GAO-08-467SP] 
(Washington, D.C.: Mar. 31, 2008). 

[45] GAO, GAO Cost Estimating and Assessment Guide: Best Practices for 
Developing and Managing Capital Program Costs, [hyperlink, 
http://www.gao.gov/products/GAO-09-3SP] (Washington, D.C.: Mar. 2, 
2009). 

[46] See for example: GAO, Best Practices: High Levels of Knowledge at 
Key Points Differentiate Commercial Shipbuilding from Navy 
Shipbuilding, [hyperlink, http://www.gao.gov/products/GAO-09-322] 
(Washington, D.C.: May 13, 2009); Joint Strike Fighter: Significant 
Challenges and Decisions Ahead, [hyperlink, 
http://www.gao.gov/products/GAO-10-478T] (Washington, D.C.: Mar. 24, 
2010); and Cost Increases in the Airborne Laser Program, GAO-04-643R 
(Washington, D.C.: May 17, 2004). 

[47] 41 U.S.C. § 263 

[48] GAO, Defense Acquisitions: Assessments of Selected Weapon 
Programs, [hyperlink, http://www.gao.gov/products/GAO-09-326SP] 
(Washington, D.C.: Mar. 30, 2009); NASA: Assessments of Selected Large-
Scale Projects, [hyperlink, http://www.gao.gov/products/GAO-10-227SP] 
(Washington, D.C.: Feb. 1, 2010). 

[49] OMB, Circular A-11, Part 7: Planning, Budgeting, and Acquisition 
of Capital Assets, Capital Programming Supplement. 2006. 

[50] We used OMB Exhibit 300 reports for all programs except four 
Coast Guard programs: Sentinel Class, Maritime Patrol Aircraft, 
Response Boat-Medium, and National Security Cutter. An Exhibit 300 
must be submitted for all executive branch agency major investments, 
and is designed to coordinate collection of agency information for 
reports to Congress required by the Federal Acquisition Streamlining 
Act of 1994 (FASA Title V). FASA requires agencies to establish cost, 
schedule and measurable performance goals for all major acquisition 
programs and achieve on average 90 percent of those goals. The Exhibit 
300 is a component of the total performance budget justification for 
executive agencies. Agencies are required to report total estimated 
life-cycle costs and acquisition costs for programs in the Exhibit 300. 

[51] The four Coast Guard programs are: Sentinel Class, Maritime 
Patrol Aircraft, Response Boat-Medium, and National Security Cutter. 

[52] We used official program acquisition program baselines for 
initial cost estimates, and Quarterly Acquisition Reports to 
congressional appropriations committees as current cost estimates for 
the Sentinel Class, Maritime Patrol Aircraft, Response Boat-Medium, 
and National Security Cutter programs. Acquisition program baselines 
(APB) formally document a program's critical cost parameters, 
including acquisition costs and life-cycle costs. The Quarterly 
Acquisition Report to congressional appropriations committees includes 
Total Acquisition Costs and Life-Cycle Cost Estimates reported to 
Congress for Coast Guard programs. 

[53] Our prior work has identified certain knowledge metrics regarding 
technology and design. Specifically, our body of work on best 
practices in product development indicates that (1) focus should be on 
achieving a high level of technology maturity at the start of system 
development in that critical technologies needed to meet essential 
product requirements must be demonstrated to work in their intended 
environment. The technology readiness level for each critical 
technology is the metric we use to measure technology maturity; and 
(2) product's design is stable as evidenced by the development of 
engineering prototypes and the completion of engineering drawings for 
an integrated product at the system design review. A best practice is 
to achieve design stability at the system-level critical design 
review, usually held midway through development. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: