This is the accessible text file for GAO report number GAO-11-692T 
entitled 'Commercial Launch Vehicles: NASA Taking Measures to Manage 
Delays and Risks' which was released on May 26, 2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
GAO: 

Testimony: 

Before the Subcommittee on Space and Aeronautics, Committee on 
Science, Space and Technology, House of Representatives: 

For Release on Delivery: 
Expected at 10:00 a.m. EST:
Thursday, May 26, 2011: 

Commercial Launch Vehicles: 

NASA Taking Measures to Manage Delays and Risks: 

Statement of Cristina T. Chaplain, Director: 
Acquisition and Sourcing Management: 

GAO-11-692T: 

GAO Highlights: 

Highlights of GAO-11-692T, a report to the Subcommittee on Space and 
Aeronautics, Committee on Science, Space, and Technology, House of 
Representatives. 

Why GAO Did This Study: 

Since the National Aeronautics and Space Administration (NASA) created 
the strategy for the Commercial Orbital Transportation Services (COTS) 
project in 2005, the space landscape has changed significantly—the 
Space Shuttle program is retiring and the Ares I will not be available—
increasing the importance of the timely development of COTS vehicles. 
The lack of alternatives for supplying the International Space Station 
and launching science missions have all contributed to an increased 
need for the COTS vehicles. The two COTS project partners, Orbital and 
SpaceX, have made progress in the development of their respective 
vehicles; however, both providers are behind schedule. As a result, 
the project recently received an additional $300 million to augment 
development efforts with risk reduction milestones. 

This testimony focuses on: (1) COTS development activities, including 
the recent funding increase; (2) the extent to which any COTS 
demonstration delays have affected commercial resupply services (CRS) 
missions and NASA’s plans for meeting the space station’s cargo 
resupply needs; and (3) lessons learned from NASA’s acquisition 
approach for COTS. 

To prepare this statement, GAO used its prior relevant work and 
conducted additional audit work, such as analyzing each partner’s 
agreement with NASA and interviewing NASA officials. New data in this 
statement was discussed with agency and company officials who provided 
technical comments, which we included as appropriate. 

What GAO Found: 

SpaceX and Orbital continue to make progress completing milestones 
under their COTS agreements with NASA, but both partners are working 
under aggressive schedules and have experienced delays in completing 
demonstration missions. SpaceX successfully flew its first 
demonstration mission in December 2010, but the mission was 18 months 
late and the company’s second and third demonstration missions have 
been delayed by almost 2 years due to design, development, and 
production challenges with the Dragon spacecraft and Falcon 9 launch 
vehicle. Orbital faced technical challenges developing the Taurus II 
launch vehicle and the Cygnus spacecraft and in constructing launch 
facilities, leading to multiple delays in completing program 
milestones, including its demonstration mission. NASA has amended its 
agreements with the partners to include a number of new milestones, 
such as additional ground and flight tests, to reduce remaining 
developmental and schedule risks; most of the new milestones completed 
thus far were finished on time, but many milestones remain. 

Based on the current launch dates for SpaceX’s and Orbital’s upcoming 
COTS demonstration missions, it is likely that neither will launch its 
initial CRS mission on time, but NASA has taken steps to mitigate the 
short-term impact to the space station. The launch windows for 
SpaceX’s first and second CRS flights are scheduled to occur either 
before or during its upcoming COTS demonstration flights and will need 
to be rescheduled. Orbital’s first CRS flight will also likely shift 
due to a Taurus II test flight. NASA officials said that the agency 
will have to renegotiate the number of flights needed from each 
partner and re-baseline the launch windows for future CRS missions 
once COTS demonstration flights are completed. NASA has taken steps to 
mitigate the short-term impact of CRS delays through prepositioning of 
cargo, some of which will be delivered on the last space shuttle 
flight. Despite these efforts, NASA officials said they would still 
need one flight in 2012 from SpaceX’s and Orbital’s vehicles to meet 
science-related cargo needs. 

In considering the use of a Space Act agreement for COTS, NASA 
identified several advantages. These advantages include sharing costs 
with agreement partners and promoting innovation in the private 
sector. A disadvantage, however, is that NASA is limited in its 
ability to influence agreement partners in their approach. At the time 
the agreements were awarded, NASA was willing to accept the risks of 
using a Space Act agreement given the goals of the project and 
alternative vehicles that were available to deliver goods to the space 
station. As the project has progressed, however, and these 
alternatives are no longer viable or available, NASA has become less 
willing to accept the risk involved and has taken steps aimed at risk 
mitigation. Given a critical need, the risk is present that the 
government will be required to make additional investments to meet 
mission needs. The amount of investment can be lessened by ensuring 
that accurate knowledge about requirements, cost, schedule, and risks 
is achieved early on. GAO has made recommendations to NASA and NASA is 
taking steps to help ensure that these fundamentals are present in its 
major development efforts to increase the likelihood of success. 

View [hyperlink, http://www.gao.gov/products/GAO-11-692T] or key 
components. For more information, contact Cristina Chaplain at 
(202) 512-4841 or chaplainc@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

Thank you for inviting me here today to discuss the status of the 
National Aeronautics and Space Administration's (NASA) Commercial 
Orbital Transportation Services (COTS) project. GAO conducted work 
examining the COTS project in 2009 and reported that progress was 
being made, but several risks persisted given aggressive project 
schedules.[Footnote 1] Since NASA devised its strategy for the COTS 
project in 2005, the space landscape has changed quite significantly, 
increasing the importance of the timely development and success of 
COTS vehicles to NASA. Specifically, with the impending retirement of 
the space shuttle in July 2011, the United States will lack a domestic 
capability to send crew and cargo to the International Space Station 
and face a cargo resupply shortfall between 2012 and 2020 that cannot 
be met by international partners' space vehicles alone.[Footnote 2] 
The Ares I project, which was originally intended to be operational in 
2010 and to fill the gap between the retirement of the Space Shuttle 
program and the availability of the COTS vehicles, pushed its launch 
readiness date to 2015 and is now being restructured into a new 
program that will not be operational until at least 2016. Further, the 
Delta II launch vehicle, which has carried the majority of NASA's 
science missions over the last several years, is retiring, the impact 
of which is beginning to be felt by NASA's science projects.[Footnote 
3] These changes have resulted in an increased need for the vehicles 
being developed for COTS not only to address the cargo resupply 
shortfall as intended, but also to support a large number of future 
science missions at a reasonable cost to NASA. While COTS partners 
have made progress in the development of their vehicles, they have 
also experienced delays and NASA has provided additional funding to 
the partners to reduce the risk that their vehicles would experience 
further delays. 

Against this backdrop, my testimony today will focus on: (1) the COTS 
development activities, including a discussion of the need for the 
recent funding augmentation; (2) the extent to which any COTS 
demonstration delays have affected Commercial Resupply Services (CRS) 
missions to the space station and NASA's plans for meeting space 
station cargo resupply needs; and (3) lessons learned from NASA's 
acquisition approach for COTS. 

In preparing this statement, we relied on our prior report related to 
the COTS project and conducted additional audit work in May 2011 to 
update information from that report.[Footnote 4] Specifically, we 
analyzed each COTS partner's agreement with NASA, amendments to those 
agreements, documentation from NASA and partner quarterly program 
management reviews, and each partner's CRS contract. We interviewed 
NASA COTS and International Space Station program officials and 
company officials. We discussed new information presented in this 
statement with agency and company officials who provided technical 
comments that we incorporated as appropriate. Our prior work on the 
COTS project, as well as the work conducted for this statement, was 
performed in accordance with generally accepted government auditing 
standards. Those standards require that we plan and perform the audit 
to obtain sufficient, appropriate evidence to provide a reasonable 
basis for our findings and conclusions based on our audit objectives. 
We believe that the evidence obtained provides a reasonable basis for 
our findings and conclusions based on our audit objectives. 

Background: 

In 2004, President George W. Bush announced his Vision for Space 
Exploration that included direction for NASA to pursue commercial 
opportunities for providing transportation and other services to 
support the space station after 2010. When the project was established 
in 2005, the approach that NASA laid out was a marked change in 
philosophy for how the agency planned to service the space station--by 
encouraging innovation in the private sector with the eventual goal of 
buying services at a reasonable price. As a result, the agency chose 
to utilize its other transaction authority under the National 
Aeronautics and Space Act of 1958,[Footnote 5] as opposed to a more 
traditional Federal Acquisition Regulation (FAR) based contract. 
Generally speaking, other transaction authority enhances the 
government's ability to acquire cutting-edge science and technology, 
in part through attracting companies that typically have not pursued 
government contracts because of the cost and impact of complying with 
government procurement requirements. These types of agreements are not 
considered federal government contracts, and are therefore generally 
not subject to those federal laws and regulations that apply to 
federal government contracts. 

NASA established the Commercial Crew and Cargo program office at 
Johnson Space Center in 2005 and budgeted $500 million for fiscal 
years 2006 through 2010 for the development and demonstration of cargo 
transport capabilities. COTS partners, Orbital Sciences Corporation 
(Orbital) and Space Exploration Technologies Corporation (SpaceX), 
have also made significant investments in developing these 
capabilities. The COTS project was originally intended to be executed 
in two sequential phases: (1) private industry development of cargo 
transport capabilities in coordination with NASA and (2) procurement 
of commercial resupply services to the space station once cargo 
transport capabilities had been successfully demonstrated. In August 
2006, NASA competitively awarded a $278 million Space Act agreement to 
SpaceX to develop and demonstrate end-to-end transportation systems, 
including the development of the Falcon 9 launch vehicle and Dragon 
spacecraft, ground operations, and berthing with the space station. In 
February 2008, NASA awarded a $170 million Space Act agreement to 
Orbital to develop two COTS cargo capabilities, unpressurized and 
pressurized[Footnote 6] cargo delivery and disposal, to culminate in 
one demonstration flight of its Taurus II launch vehicle and Cygnus 
spacecraft.[Footnote 7] 

Before either partner had successfully demonstrated its COTS cargo 
transport capabilities, the International Space Station program office 
awarded two CRS contracts in December 2008 to Orbital and SpaceX under 
a separate competitive procurement from COTS. These FAR-based 
contracts were for the delivery of at least 40 metric tons 
(approximately 88,000 pounds) to the space station between 2010 and 
2015. Orbital was awarded 8 cargo resupply missions for approximately 
$1.9 billion and SpaceX was awarded 12 cargo resupply missions for 
approximately $1.6 billion. 

In June 2009, we found that while SpaceX and Orbital had made progress 
against development milestones, the companies were working under 
aggressive schedules and had experienced schedule slips that delayed 
upcoming demonstration launch dates by several months. In addition, we 
reported that the vehicles being developed through the COTS project 
were essential to NASA's ability to fully utilize the space station 
after its assembly was completed and the space shuttle was retired. 
Finally, we found that NASA's management of the COTS project generally 
adhered to critical project management tools and activities. 

Since our 2009 report, the two COTS project partners, Orbital and 
SpaceX, have made progress in the development of their respective 
vehicles. SpaceX successfully flew its first COTS demonstration 
mission in December 2010 and Orbital is planning to fly its COTS 
demonstration mission in December 2011. Both providers, however, are 
behind schedule--SpaceX's first COTS demonstration mission slipped 18 
months and Orbital's first mission was initially planned for March 
2011. Such delays are not atypical of development efforts, especially 
efforts that are operating under such aggressive schedules. 
Nonetheless, the criticality of these vehicles to the space station's 
operations, as well as NASA's ability to affordably execute its 
science missions has heightened the importance of their timely and 
successful completion and lessened the level of risk that NASA is 
willing to accept in this regard. As a result, the project recently 
requested and received an additional $300 million to augment the 
partner development efforts with, according to NASA, risk reduction 
milestones. 

Demonstration Missions Have Been Delayed, but Progress Against New 
Milestones Could Reduce Further Technical and Schedule Risk: 

SpaceX: Performance Against Prior Milestones: 

SpaceX has successfully completed 18 of 22 milestones to date, but has 
experienced lengthy delays in completing key milestones since we last 
reported on the company's progress in June 2009. SpaceX's agreement 
with NASA established 22 development milestones that SpaceX must 
complete in order to successfully demonstrate COTS cargo capabilities. 
SpaceX's first demonstration mission readiness review was completed 15 
months behind schedule and its successful first demonstration mission 
was flown in December 2010, 18 months late. The company's second and 
third demonstration missions have been delayed by almost 2 years to 
November 2011 and January 2012, respectively.[Footnote 8] Several 
factors contributed to the delay in SpaceX's first demonstration 
mission readiness review and demonstration mission. These factors 
include, among others, delays associated with (1) launching the maiden 
Falcon 9 (non-COTS mission), such as Falcon 9 software and database 
development; (2) suppliers; (3) design instability and production; (4) 
Dragon spacecraft testing and software development; and (5) obtaining 
flight safety system approval. For example, SpaceX encountered welding 
issues during production of the Dragon propellant tanks and also had 
to redesign the Dragon's battery. 

In preparing for its second COTS demonstration flight, SpaceX has 
experienced additional design, development, and production delays. For 
example, several propulsion-related components needed to be 
redesigned, the Dragon spacecraft's navigation sensor experienced 
development testing delays, and delays were experienced with launch 
vehicle tank production. For example, SpaceX's decision to incorporate 
design changes to meet future CRS mission requirements has delayed the 
company's second demonstration mission. Integration challenges on the 
maiden Falcon 9 launch and the first COTS demonstration mission have 
also kept SpaceX engineers from moving on to the second COTS 
demonstration mission. 

SpaceX officials cited the completion of Dragon development efforts, 
NASA's safety verification process associated with berthing with the 
space station, and transitioning into efficient production of the 
Falcon 9 and Dragon to support space station resupply missions as key 
drivers of technical and schedule risk going forward. For completing 
18 of the 22 milestones, SpaceX has received $258 million in milestone 
payments thus far, with $20 million yet to be paid. Appendix I 
describes SpaceX's progress meeting the COTS development milestones in 
its agreement with NASA. 

Orbital: Performance Against Prior Milestones: 

Orbital has successfully completed 15 of 19 COTS milestones to date--8 
more than when we initially reported on the program in June 2009. 
Programmatic changes and developmental difficulties, however, have led 
to multiple delays of several months' duration and further delays are 
projected for completing the remaining milestones. For example, 
according to Orbital officials, the demonstration mission of Orbital's 
Taurus II launch vehicle and Cygnus spacecraft has been delayed 
primarily due to an increase in design effort to develop a pressurized 
cargo carrier in place of the original Cygnus unpressurized cargo 
design. After NASA awarded Orbital a CRS contract for eight 
pressurized cargo missions, NASA and Orbital amended their COTS 
demonstration agreement to replace the unpressurized cargo 
demonstration mission with a pressurized cargo demonstration. This 
delayed existing milestones, and the schedule was revised to shift the 
COTS demonstration mission from December 2010 to March 2011. Since 
that time, the schedule for some of Orbital's milestones has been 
revised again and the demonstration mission is now planned for 
December 2011. 

COTS program and Orbital officials also noted technical challenges as 
reasons for milestone delays. For example, Orbital officials said 
there are several critical Taurus II engine and stage one system tests 
that need to be completed by the end of the summer, but that the risk 
inherent in these tests is mitigated through an incremental approach 
to testing. Specifically, single engine testing has been successfully 
completed, and testing will be extended this summer to the full stage 
one (i.e., two-engine) testing. COTS program and Orbital officials 
also noted delays in Cygnus avionics manufacturing, primarily driven 
by design modifications aimed at increasing the safety and robustness 
of the system. According to these officials, integration and assembly 
of the first Cygnus spacecraft has begun and is now in the initial 
electrical testing phase. 

Additionally, the completion of the company's launch facilities at the 
Mid-Atlantic Regional Space Port in Wallops Island, Virginia, remains 
the key component of program risk. NASA COTS program and Orbital 
officials cite completion of the Wallops Island launch facilities as 
the critical factor for meeting the COTS demonstration mission 
schedule. Orbital officials said additional resources have been 
allocated to development of the launch complex to mitigate further 
slips, and an around-the-clock schedule will be initiated later this 
summer to expedite the completion of verification testing of the 
liquid fueling facility, which is the primary risk factor in 
completing the launch facility. 

For completing 15 of the 19 milestones, Orbital has received $157.5 
million, with $12.5 million remaining to be paid. Appendix I depicts 
Orbital's progress in meeting the COTS development milestones in its 
agreement with NASA. 

Risk Reduction Milestones Recently Added to COTS Agreements: 

In addition to the prior milestones negotiated under the COTS project, 
NASA has amended its agreements with SpaceX and Orbital to include a 
number of additional milestones aimed at reducing remaining 
developmental and schedule risks. COTS officials told us that some 
milestones reflect basic risk reduction measures, such as thermal 
vacuum testing, that NASA would normally require on launch vehicle or 
spacecraft development. A series of amendments were negotiated from 
December 2010 to May 2011 after Congress authorized $300 million for 
commercial cargo efforts in fiscal year 2011. These amendments add 
milestones to (1) augment ground and flight testing, (2) accelerate 
development of enhanced cargo capabilities, or (3) further develop the 
ground infrastructure needed for commercial cargo capabilities. These 
milestones were added incrementally due to NASA operating under 
continuing resolutions through the first half of fiscal year 2011. 

In May 2009, the President established a Review of U.S. Human Space 
Flight Plans Committee composed of space industry experts, former 
astronauts, government officials, and academics.[Footnote 9] In its 
report, the committee stated that it was concerned that the space 
station, and particularly its utilization, may be at risk after 
Shuttle retirement as NASA would be reliant on a combination of new 
international vehicles and as-yet-unproven U.S. commercial vehicles 
for cargo transport. The committee concluded that it might be prudent 
to strengthen the incentives to the commercial providers to meet the 
schedule milestones. NASA officials stated that if funding were 
available, negotiating additional, risk reduction milestones would 
improve the chance of mission success, referring specifically to the 
companies' COTS demonstration missions. Of the $300 million, $236 
million, divided equally between SpaceX and Orbital, will be paid upon 
completion of the additional milestones.[Footnote 10] Additionally, 
NASA officials stated the International Space Station program office 
will pay SpaceX and Orbital $10 million each to fund early cargo 
delivery to the space station on the companies' final COTS 
demonstration missions. The COTS program manager stated that SpaceX 
and Orbital recognize their responsibility under the COTS agreements 
for any cost overruns associated with their development efforts, and 
that the companies did not come to NASA with a request for additional 
funding. 

SpaceX has completed 4 of its new milestones on time but has 
experienced minor delays in completing 3 others. SpaceX's agreement 
with NASA was amended three times between December 2010 and May 2011 
to add 18 development milestones that SpaceX must complete in order to 
successfully demonstrate COTS cargo capabilities. Some of the new 
milestones, for example, are designed to increase NASA's confidence 
that SpaceX's Dragon spacecraft will successfully fly approach 
trajectories to the space station while others are intended to improve 
engine acceptance rates and vehicle production time frames. Milestones 
completed thus far include a test of the spacecraft's navigation 
sensor and thermal vacuum tests. For completing 7 of the 18 
milestones, SpaceX has received $40 million in milestone payments thus 
far, with $78 million yet to be paid. 

Orbital has completed 4 of its 10 new milestones on schedule and 1 of 
the new milestones was delayed by about 1 month. In concurrence with 
NASA's request, Orbital agreed to add an initial flight test of the 
Taurus II launch vehicle to reduce overall cargo service risk. The 
test flight not only separates the risks of the first flight of Taurus 
II from the risks of the first flight of the Cygnus spacecraft, but 
provides the opportunity to measure the Taurus II flight environments 
using an instrumented Cygnus mass simulator. The Taurus II test flight 
is scheduled for October 2011. Overall technical risks associated with 
Cygnus development are expected to be reduced through additional 
software and avionics tests. Milestones completed thus far include 
early mission analyses and reviews, as well as delivery of mission 
hardware. For completing the first 5 new milestones, Orbital has 
received $69 million, with $49 million remaining to be paid. Appendix 
I describes SpaceX's and Orbital's progress meeting the new COTS 
development milestones in their agreements with NASA. 

COTS Delays Will Likely Cause Resupply Flights to Slip, but NASA Has 
Taken Steps to Mitigate Short-Term Impact: 

Based on the current launch dates for SpaceX's and Orbital's upcoming 
COTS demonstration missions, it is likely that both commercial 
partners will not launch their initial CRS missions on time, but NASA 
has taken steps to mitigate the short-term impact to the space 
station. The launch window for SpaceX's first CRS flight is from April 
to June 2011 and from October to December 2011 for its second CRS 
flight. These launch windows are either scheduled to occur before or 
during SpaceX's upcoming COTS demonstration flights and thus will need 
to be rescheduled. In the case of Orbital, NASA officials told us that 
the launch window for its first CRS flight is from January to March 
2012, but will likely slip from those dates given the Taurus II test 
flight added to its milestone schedule. NASA officials added that once 
SpaceX and Orbital have finished completing their COTS demonstration 
flights, NASA will have to renegotiate the number of flights needed 
from each partner and re-baseline the launch windows for future CRS 
missions. 

International Space Station program officials told us they have taken 
steps to mitigate the short-term impact of CRS flight delays through 
prepositioning of cargo on the last space shuttle flights, including 
cargo that is being launched on the planned contingency space shuttle 
flight in early July 2011. Officials added that these flights and the 
planned European Space Agency's Automated Transfer Vehicle and Japan's 
H-II Transfer Vehicle flights in 2012 will carry enough cargo to 
sustain the six person space station crew through 2012 and to meet 
science-related cargo needs through most of 2012. Despite these steps, 
NASA officials said they would still need one flight each from 
SpaceX's and Orbital's vehicles in order to meet science-related cargo 
needs in 2012. Beyond 2012, NASA is highly dependent on SpaceX's and 
Orbital's vehicles in order to fully utilize the space station. For 
example, we reported in April 2011 that 29 percent of the flights 
planned to support space station operations through 2020 were 
dependent on those vehicles.[Footnote 11] In addition, NASA officials 
confirmed that the agency has no plans to purchase additional cargo 
flights on Russian Progress vehicles beyond 2011 and the European 
Space Agency and the Japan Aerospace Exploration Agency have no 
current plans to manufacture additional vehicles beyond their existing 
commitments or to accelerate production of planned vehicles. We 
reported previously that if the COTS vehicles are delayed, NASA 
officials said they would pursue a course of "graceful degradation" of 
the space station until conditions improve. In such conditions, the 
space station would only conduct minimal science experiments.[Footnote 
12] 

Even With Identified Advantages, NASA Has Taken Measures to Address 
Risks to COTS Strategy: 

NASA's intended use of the COTS Space Act agreements was to stimulate 
the space industry rather than acquiring goods and services for its 
direct use. Traditional FAR contracts are to be used when NASA is 
procuring something for the government's direct benefit.[Footnote 13] 
NASA policy provides that funded Space Act agreements can only be used 
if no other instrument, such as a traditional FAR contract, can be 
used.[Footnote 14] Therefore, Space Act agreements and FAR-based 
contracts are to be used for different purposes. In considering the 
use of funded Space Act agreements for COTS, NASA identified several 
advantages. For example: 

* The government can share costs with the agreement partner with fixed 
government investment. 

* Payment to partner is made only after successful completion of 
performance-based milestones. 

* The government can terminate the agreement if the partner is not 
reasonably meeting milestones. 

* Limited government requirements allow optimization of systems to 
meet company's commercial business needs. 

These types of agreements can also have disadvantages, however. For 
example, Space Act agreements may have more limited options for 
oversight as compared to other science mission and human spaceflight 
development efforts that are accomplished under more traditional FAR 
contracts. NASA identified other disadvantages of using a Space Act 
agreement. For example: 

* The government has limited ability to influence agreement partners 
in their approach. 

* The government lacks additional management tools (beyond performance 
payments at milestones) to incentivize partners to meet technical and 
schedule performance. 

Given the intended goals of the project and the availability of 
alternative vehicles to deliver goods to the space station when the 
COTS agreements were signed, NASA was willing to accept the risks 
associated with the disadvantages of using a Space Act agreement. 
[Footnote 15] As the project has progressed, however, and these 
alternatives are no longer viable or available, NASA has become less 
willing to accept the risks involved. As a result, the agency took 
steps aimed at risk mitigation, primarily through additional funding. 

I would like to point out that neither Space Act agreements nor more 
traditional FAR contracts guarantee positive outcomes. Further, many 
of the advantages and disadvantages identified by NASA for using a 
Space Act agreement can also be present when using FAR-based 
contracts, depending on how the instrument is managed or written. For 
example, both a FAR contract and a Space Act agreement can provide for 
cost sharing and the government also has the ability to terminate a 
FAR contract or a Space Act agreement if it is dissatisfied with 
performance. The ineffective management of the instrument can be an 
important contributor to poor outcomes. For example, although a Space 
Act agreement may lack management tools to incentivize partners, we 
have reported in the past that award fees, which are intended to 
incentivize performance on FAR-based contracts, are not always applied 
in an effective manner or even tied to outcomes.[Footnote 16] 
Additionally, the oversight that NASA conducts under a FAR-based 
contract has not always been used effectively to ensure that projects 
meet cost and schedule baselines.[Footnote 17] 

Even with the advantages and disadvantages that can be present in 
various instruments, given a critical need, the government bears the 
risk for having to make additional investments to get what it wants, 
when it wants it. The additional investment required, however, can be 
lessened by ensuring that accurate knowledge about requirements, cost, 
schedule, and risks is achieved early on. We have reported for years 
that disciplined processes are key to ensuring that what is being 
proposed can actually be accomplished within the constraints that bind 
the project, whether they are cost, schedule, technical, or any other 
number of constraints.[Footnote 18] We have made recommendations to 
NASA and NASA is taking steps to address these recommendations to help 
ensure that these fundamentals are present in its major development 
efforts to increase the likelihood of success. 

Mr. Chairman, this concludes my prepared statement. I would be happy 
to respond to any questions you may have at this time. 

[End of section] 

Appendix I: COTS Partners' Progress Completing Prior and New 
Milestones: 

Table 1: SpaceX's Progress Completing Prior COTS Development 
Milestones: 

Milestone number: 1; 
Milestone description: Project Management Plan Review; 
Scheduled completion date: September 2006; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $23.1 million. 

Milestone number: 2; 
Milestone description: Demo 1 System Requirements Review; 
Scheduled completion date: November 2006; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 3; 
Milestone description: Demo 1 Preliminary Design Review; 
Scheduled completion date: February 2007; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $18.1 million. 

Milestone number: 4; 
Milestone description: Financing Round 1; 
Scheduled completion date: March 2007; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 5; 
Milestone description: Demo 2 System Requirements Review; 
Scheduled completion date: March 2007; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $31.1 million. 

Milestone number: 6; 
Milestone description: Demo 1 System Critical Design Review; 
Scheduled completion date: August 2007; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $8.1 million. 

Milestone number: 7; 
Milestone description: Demo 3 System Requirements Review; 
Scheduled completion date: October 2007; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $22.3 million. 

Milestone number: 8; 
Milestone description: Demo 2 Preliminary Design Review; 
Scheduled completion date: December 2007; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $21.1 million. 

Milestone number: 9; 
Milestone description: Draco Initial Hot-Fire; 
Scheduled completion date: March 2008; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $6 million. 

Milestone number: 10; 
Milestone description: Financing Round 2; 
Scheduled completion date: March 2008; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 11; 
Milestone description: Demo 3 Preliminary Design Review; 
Scheduled completion date: June 2008; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $22 million. 

Milestone number: 12; 
Milestone description: Multi-engine Test; 
Scheduled completion date: September 2008; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $22 million. 

Milestone number: 13; 
Milestone description: Demo 2/Demo 3 System Critical Design Review; 
Scheduled completion date: December 2008; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $25 million. 

Milestone number: 14; 
Milestone description: Financing Round 3; 
Scheduled completion date: March 2009; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 15; 
Milestone description: Demo 1 Readiness Review; 
Scheduled completion date: March 2009; 
Completed on time (Yes/No): No; 
Delay if applicable (months): 15; 
Payment amount: $5 million. 

Milestone number: 16; 
Milestone description: Communications Unit Flight Unit Design, Accept, 
Delivery; 
Scheduled completion date: May 2009; 
Completed on time (Yes/No): No; 
Delay if applicable (months): 2; 
Payment amount: $9 million. 

Milestone number: 17; 
Milestone description: Demo 1 Mission; 
Scheduled completion date: June 2009; 
Completed on time (Yes/No): No; 
Delay if applicable (months): 18; 
Payment amount: $5 million. 

Milestone number: 18; 
Milestone description: Demo 2 Readiness Review; 
Scheduled completion date: September 2009[A]; 
Completed on time (Yes/No): No; 
Delay if applicable (months): 24 (projected); 
Payment amount: $5 million. 

Milestone number: 19; 
Milestone description: Demo 2 Mission; 
Scheduled completion date: November 2009[A]; 
Completed on time (Yes/No): No; 
Delay if applicable (months): 24 (projected); 
Payment amount: $5 million. 

Milestone number: 20; 
Milestone description: Cargo Integration Demonstration; 
Scheduled completion date: Jan. 2010; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 21; 
Milestone description: Demo 3 Readiness Review; 
Scheduled completion date: Jan. 2010[A]; 
Completed on time (Yes/No): No; 
Delay if applicable (months): 23 (projected); 
Payment amount: $5 million. 

Milestone number: 22; 
Milestone description: Demo 3 Mission; 
Scheduled completion date: Mar. 2010[A]; 
Completed on time (Yes/No): No; 
Delay if applicable (months): 22 (projected); 
Payment amount: $5 million. 

Total:
Payment amount: $278 million for the completion of all milestones; 
$258 million paid to date. 

Source: NASA and SpaceX. 

[A] NASA is currently reviewing a proposed amendment that would change 
the completion dates for milestones 18, 19, 21, and 22. In particular, 
Demo Mission 2 (milestone 19) would take place in November 2011 and 
Demo Mission 3 in January 2012. 

[End of table] 

Table 2: Orbital's Progress Completing Prior COTS Development 
Milestones: 

Milestone number: 1; 
Milestone description: Program Plan Review; 
Scheduled completion: date: March 2008; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 2; 
Milestone description: Demo Mission System Requirements Review; 
Scheduled completion: date: June 2008; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $20 million. 

Milestone number: 3; 
Milestone description: Unpressurized Cargo Module Preliminary Design 
Review; 
Scheduled completion: date: July 2008; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 4; 
Milestone description: Deleted; COTS System Preliminary Design Review 
was milestone 4, but it has been renumbered as milestone 10; 
Scheduled completion: date: No longer applicable; 
Completed on time (Yes/No): No longer applicable; 
Delay, if applicable (months): [Empty]; 
Payment amount: No longer applicable. 

Milestone number: 5; 
Milestone description: COTS Integration/Operations Facility Review; 
Scheduled completion: date: September 2008; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 6; 
Milestone description: Pressurized Cargo Module Preliminary Design 
Review; 
Scheduled completion: date: October 2008; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 7; 
Milestone description: Deleted; Unpressurized Cargo Module Critical 
Design Review; 
Scheduled completion: date: No longer applicable; 
Completed on time (Yes/No): No longer applicable; 
Delay, if applicable (months): [Empty]; 
Payment amount: No longer applicable. 

Milestone number: 8; 
Milestone description: Instrumentation Program and Command List; 
Scheduled completion: date: February 2009; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 9; 
Milestone description: Completion of ISS Phase 1 Safety Review; 
Scheduled completion: date: March 2009; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 10; 
Milestone description: COTS System Preliminary Design Review; 
Scheduled completion: date: April 2009; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 1; 
Payment amount: $20 million. 

Milestone number: 11; 
Milestone description: Deleted; Unpressurized Cargo Module Fabrication 
Started; 
Scheduled completion: date: No longer applicable; 
Completed on time (Yes/No): No longer applicable; 
Delay, if applicable (months): [Empty]; 
Payment amount: No longer applicable. 

Milestone number: 11; 
Milestone description: Pressurized Cargo Module Critical Design Review; 
Scheduled completion: date: July 2009; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 12; 
Milestone description: Cygnus Avionics Test; 
Scheduled completion: date: August 2009; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 13; 
Milestone description: Completion of ISS Phase 2 Safety Review; 
Scheduled completion: date: August 2009; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 3; 
Payment amount: $10 million. 

Milestone number: 14; 
Milestone description: COTS System Critical Design Review; 
Scheduled completion: date: September 2009; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 6; 
Payment amount: $10 million. 

Milestone number: 15; 
Milestone description: Service Module Core Assembly Completed; 
Scheduled completion: date: December 2009; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 8; 
Payment amount: $7.5 million. 

Milestone number: 16; 
Milestone description: Service Module Test Readiness Review; 
Scheduled completion: date: April 2010; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 7; 
Payment amount: $7.5 million. 

Milestone number: 17; 
Milestone description: Service Module Initial Comprehensive 
Performance Test; 
Scheduled completion: date: July 2010[A]; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 11 (projected); 
Payment amount: $5 million. 

Milestone number: 18; 
Milestone description: Launch Vehicle Stage 1 Assembly Complete; 
Scheduled completion: date: October 2010[A]; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 11 (projected); 
Payment amount: $2.5 million. 

Milestone number: 19; 
Milestone description: Cargo Integration Demonstration; 
Scheduled completion: date: December 2010; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $2.5 million. 

Milestone number: 20; 
Milestone description: Mission Readiness Review; 
Scheduled completion: date: February 2011[A]; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 8 (projected); 
Payment amount: $2.5 million. 

Milestone number: 21; 
Milestone description: System Demonstration Flight; 
Scheduled completion: date: March 2011[A]; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): 9 (projected); 
Payment amount: $2.5 million. 

Total:
Payment amount: $170 million for completion of all milestones; $157.5 
million paid to date. 

Source: NASA and Orbital. 

Note: When Orbital amended its agreement with NASA in March 2009, it 
deleted milestones 7 and 11, and moved milestone 4 to become milestone 
10. These changes are indicated in this revised schedule. 

[A] Milestones 17, 18, 20, and 21 were amended in March 2011 to 
reflect updated milestone descriptions and completion dates. In 
particular, the System Demonstration Flight (milestone 21) is now 
planned for December 2011. 

[End of table] 

Table 3: SpaceX's Progress Completing New COTS Development Milestones: 

Milestone number: 23; 
Milestone description: Modal Test Plan and Setup; 
Scheduled completion date: November 2010; 
Completed on time (Yes/No): Yes[A]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 24; 
Milestone description: Modal Test; 
Scheduled completion date: December 2010; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 25; 
Milestone description: Light Detection and Ranging (LIDAR) Test (open 
loop); 
Scheduled completion date: December 2010; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 26; 
Milestone description: Solar Array Deployment and Component Thermal 
Vacuum Tests; 
Scheduled completion date: December 2010; 
Completed on time (Yes/No): Yes; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 27; 
Milestone description: Light Detection and Ranging (LIDAR) Test Plan 
(closed loop); 
Scheduled completion date: March 2011; 
Completed on time (Yes/No): No; 
Delay if applicable (months): less than 1[B]; 
Payment amount: $5 million. 

Milestone number: 28; 
Milestone description: Thermal Vacuum System Test Plan and Procurement; 
Scheduled completion date: March 2011; 
Completed on time (Yes/No): No; 
Delay if applicable (months): less than 1[C]; 
Payment amount: $5 million. 

Milestone number: 29; 
Milestone description: Overall Infrastructure Plan and Long Lead 
Procurement; 
Scheduled completion date: March 2011; 
Completed on time (Yes/No): No; 
Delay if applicable (months): less than 2[D]; 
Payment amount: $10 million. 

Milestone number: 30; 
Milestone description: Thermal Vacuum System Tests; 
Scheduled completion date: July 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $20 million. 

Milestone number: 31; 
Milestone description: Test Site Infrastructure Implementation; 
Scheduled completion date: June 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 32; 
Milestone description: Dragon Trunk Acoustic Test; 
Scheduled completion date: June 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 33; 
Milestone description: Light Detection and Ranging (LIDAR) Test 
(closed loop); 
Scheduled completion date: August 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 34; 
Milestone description: Design Review of Enhanced Powered Cargo 
Accommodations; 
Scheduled completion date: August 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 35; 
Milestone description: Design Review of Pressurized Cargo Volume 
Increase; 
Scheduled completion date: August 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 36; 
Milestone description: Full Dragon Electromagnetic 
Interference/Capability Test and Second Flight-Like Hardware in the 
Loop Simulator; 
Scheduled completion date: July 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 37; 
Milestone description: Dragon Cargo Racks and Hatch Simulator; 
Scheduled completion date: August 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $3 million. 

Milestone number: 38; 
Milestone description: Ground Demonstration of Enhanced Powered Cargo; 
Scheduled completion date: September 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 39; 
Milestone description: Launch Site Infrastructure Implementation; 
Scheduled completion date: September 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 40; 
Milestone description: Production Infrastructure Implementation; 
Scheduled completion date: September 2011; 
Completed on time (Yes/No): [Empty]; 
Delay if applicable (months): [Empty]; 
Payment amount: $5 million. 

Total: 
Payment amount: $118 million for the completion of all milestones; 
$40 million paid to date. 

Source: NASA and SpaceX. 

[A] The fifth amendment to SpaceX's agreement with NASA included 
Milestone 23 with a due date of November 2010. Because NASA did not 
sign this amendment until December 2010 and SpaceX completed the 
milestone that same month, NASA views this milestone as having been 
completed on time. 

[B] SpaceX successfully completed Milestone 27 on April 18, 2011. 

[C] SpaceX successfully completed Milestone 28 on April 28, 2011. 

[D] SpaceX successfully completed Milestone 29 on May 10, 2011. 

[End of table] 

Table 4: Orbital's Progress Completing New COTS Development Milestones: 

Milestone number: 22; 
Milestone description: Mission Concept Review for Taurus II Maiden 
Test Flight; 
Scheduled completion date: December 2010; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $20 million. 

Milestone number: 23; 
Milestone description: Taurus II Maiden Flight Preliminary Mission 
Analysis; 
Scheduled completion date: February 2011; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 24; 
Milestone description: Cygnus Mass Simulator Design Review; 
Scheduled completion date: March 2011; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 25; 
Milestone description: Installation of Additional Processor in the 
Loop Simulators; 
Scheduled completion date: April 2011; 
Completed on time (Yes/No): No; 
Delay, if applicable (months): less than 1[A]; 
Payment amount: $5 million. 

Milestone number: 26; 
Milestone description: PROX Flight Equivalent Unit Test Unit; 
Scheduled completion date: May 2011; 
Completed on time (Yes/No): [Empty]; 
Delay, if applicable (months): [Empty]; 
Payment amount: $5 million. 

Milestone number: 27; 
Milestone description: Taurus II Maiden Flight Stage 1 Core delivered 
to Wallops Flight Facility (WFF); 
Scheduled completion date: April 2011; 
Completed on time (Yes/No): Yes; 
Delay, if applicable (months): [Empty]; 
Payment amount: $24 million. 

Milestone number: 28; 
Milestone description: Taurus II Maiden Flight Upper Stage delivered 
to WFF; 
Scheduled completion date: June 2011; 
Completed on time (Yes/No): [Empty]; 
Delay, if applicable (months): [Empty]; 
Payment amount: $20 million. 

Milestone number: 29; 
Milestone description: Taurus II Maiden Flight Cygnus Mass Simulator 
at WFF in preparation for integration with Taurus II Maiden Flight 
Launch Vehicle; 
Scheduled completion date: June 2011; 
Completed on time (Yes/No): [Empty]; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 30; 
Milestone description: Taurus II Maiden Flight Launch Vehicle Stage 1 
Assembly Complete; 
Scheduled completion date: July 2011; 
Completed on time (Yes/No): [Empty]; 
Delay, if applicable (months): [Empty]; 
Payment amount: $10 million. 

Milestone number: 31; 
Milestone description: Taurus II Maiden Flight; 
Scheduled completion date: October 2011; 
Completed on time (Yes/No): [Empty]; 
Delay, if applicable (months): [Empty]; 
Payment amount: $4 million. 

Total: 
Payment amount: $118 million for the completion of all milestones; 
$69 million paid to date. 

Source: NASA and Orbital: 

[A] Orbital successfully completed Milestone 25 on May 20, 2011. 

[End of table] 

[End of section] 

Appendix II: GAO Contacts and Staff Acknowledgments: 

GAO Contacts: 

For questions about this statement, please contact me at (202) 512-
4841 or chaplainc@gao.gov. Contact points for our Offices of 
Congressional Relations and Public Affairs may be found on the last 
page of this testimony. 

Staff Acknowledgments: 

Individuals making key contributions to this statement include Shelby 
S. Oakley, Assistant Director; Jeff Hartnett; Andrew Redd; Megan 
Porter; Laura Greifner; and Alyssa Weir. 

[End of section] 

Footnotes: 

[1] GAO, NASA: Commercial Partners Are Making Progress, but Face 
Aggressive Schedules to Demonstrate Critical Space Station Cargo 
Transport Capabilities, [hyperlink, 
http://www.gao.gov/products/GAO-09-618] (Washington, D.C.: June 16, 
2009). 

[2] International partners' vehicles include the Russian Federal Space 
Agency's Progress (cargo) and Soyuz (crew), the European Space 
Agency's Automated Transfer Vehicle (cargo), and the Japan Aerospace 
Exploration Agency's H-II Transfer Vehicle (cargo). 

[3] GAO, NASA: Medium Launch Transition Strategy Leverages Ongoing 
Investments but is Not Without Risk, [hyperlink, 
http://www.gao.gov/products/GAO-11-107] (Washington, D.C.: Nov. 22, 
2010). 

[4] [hyperlink, http://www.gao.gov/products/GAO-09-618]. 

[5] Pub. L. No. 85-568, § 203 (1958). This act is commonly referred to 
as the Space Act and agreements signed utilizing NASA's other 
transaction authority are known as Space Act agreements. 

[6] Pressurized cargo refers to cargo that is carried inside the 
spacecraft. This cargo includes items such as food, water, and 
materials to support scientific experiments. 

[7] NASA originally awarded a $207 million Space Act agreement to 
Rocketplane Kistler (RpK), but the agreement was terminated in October 
2007 after RpK had missed technical and financial milestones. 
Subsequently, Orbital was awarded the remaining funds--$170 million. 
In March 2009, Orbital and NASA amended this agreement, removing its 
unpressurized cargo demonstration and replacing it with a pressurized 
demonstration, scheduled for March 2011. 

[8] According to the COTS program manager, NASA is also discussing 
with SpaceX about the possibility of combining the second and third 
demonstration missions into a single mission. SpaceX officials told us 
they have already begun building the Dragon spacecraft for the second 
COTS demonstration mission so that it can be fully capable of berthing 
with the space station. 

[9] Review of U.S. Human Spaceflight Plans Committee, Seeking a Human 
Spaceflight Program Worthy of a Great Nation (Washington, D.C.: 
October 2009). 

[10] The COTS program manager reported that $34 million of the $300 
million was for NASA Headquarters and Johnson Space Center program 
support and administration as well as technical and mission support 
for the remaining COTS demonstration flights and $10 million would be 
spent on milestone payments for Orbital's Milestones 20 and 21 and 
SpaceX's Milestone 22. 

[11] GAO, International Space Station (ISS) - Ongoing Assessments for 
Life Extension Appear to be Supported, [hyperlink, 
http://www.gao.gov/products/GAO-11-519R] (Washington, D.C.: Apr. 11, 
2011). 

[12] GAO, International Space Station: Significant Challenges May 
Limit Onboard Research, [hyperlink, 
http://www.gao.gov/products/GAO-10-9] (Washington, D.C.: Nov. 25, 
2009). 

[13] 31 U.S.C. § 6303. 

[14] NASA Policy Directive 1050.1I, Authority to Enter into Space Act 
Agreements (Dec. 23, 2008). 

[15] NASA goals were to: (1) implement Space Exploration policy with 
investments to stimulate the commercial space industry; (2) facilitate 
U.S. private industry demonstrations of cargo and crew space 
transportation capabilities with the goal of achieving safe, reliable, 
cost-effective access to low-Earth orbit; and (3) create a market 
environment where commercial services are available to the government 
and private sector customers. 

[16] GAO, NASA Procurement: Use of Award Fees for Achieving Program 
Outcomes Should Be Improved, [hyperlink, 
http://www.gao.gov/products/GAO-07-58] (Washington, D.C.: Jan. 17, 
2007). 

[17] GAO, NASA: Assessments of Selected Large-Scale Projects, 
[hyperlink, http://www.gao.gov/products/GAO-11-239SP] (Washington, 
D.C.: Mar. 3, 2011). 

[18] GAO, NASA: Assessments of Selected Large-Scale Projects, 
[hyperlink, http://www.gao.gov/products/GAO-09-306SP] (Washington, 
D.C.: Mar. 2, 2009); GAO, NASA: Assessments of Selected Large-Scale 
Projects, [hyperlink, http://www.gao.gov/products/GAO-10-227SP] 
(Washington, D.C.: Feb. 1, 2010); and GAO-11-239SP. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: