This is the accessible text file for GAO report number GAO-11-677T 
entitled 'Joint Strike Fighter: Restructuring Places Program on Firmer 
Footing, but Progress Is Still Lagging' which was released on May 19, 
2011. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as 
part of a longer term project to improve GAO products' accessibility. 
Every attempt has been made to maintain the structural and data 
integrity of the original printed product. Accessibility features, 
such as text descriptions of tables, consecutively numbered footnotes 
placed at the end of the file, and the text of agency comment letters, 
are provided but may not exactly duplicate the presentation or format 
of the printed version. The portable document format (PDF) file is an 
exact electronic replica of the printed version. We welcome your 
feedback. Please E-mail your comments regarding the contents or 
accessibility features of this document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

United States Government Accountability Office: 
GAO: 

Testimony: 

Before the Committee on Armed Services U.S. Senate: 

For Release on Delivery: 
Expected at 9:30 a.m. EDT:
Thursday, May 19, 2011: 

Joint Strike Fighter: 

Restructuring Places Program on Firmer Footing, but Progress Is Still 
Lagging: 

Statement of Michael Sullivan, Director:
Acquisition and Sourcing Management: 

GAO-11-677T: 

GAO Highlights: 

Highlights of GAO-11-677T, a testimony before the Committee on Armed 
Services, U.S. Senate. 

Why GAO Did This Study: 

The F-35 Lightning II, also known as the Joint Strike Fighter (JSF), 
is the Department of Defense’s (DOD) most costly and ambitious 
aircraft acquisition, seeking to simultaneously develop and field 
three aircraft variants for the Air Force, Navy, Marine Corps, and 
eight international partners. The JSF is critical for recapitalizing 
tactical air forces and will require a long-term commitment to very 
large annual funding outlays. The estimated total investment cost is 
currently about $385 billion to develop and procure 2,457 aircraft. 
Because of a history of relatively poor cost and schedule outcomes, 
defense leadership over the past 15 months has directed a 
comprehensive restructuring of the JSF program that is continuing.
This testimony draws substantially from our extensive body of work on 
the JSF including our April 2011 report, the latest annual review 
mandated in the National Defense Authorization Act for Fiscal Year 
2010, Pub. L. No. 111-84 § 244 (2009). This testimony discusses (1) 
program cost and schedule changes and their implications on 
affordability; (2) progress made during 2010; (3) design and 
manufacturing maturity; and (4) test plans and progress. GAO’s work 
included analyses of a wide range of program documents and interviews 
with defense and contractor officials. 

What GAO Found: 

DOD continues to restructure the JSF program, taking positive, 
substantial actions that should lead to more achievable and 
predictable outcomes. Restructuring has consequences-—higher up-front 
development costs, fewer aircraft in the near term, training delays, 
and extended times for testing and delivering capabilities to 
warfighters. Total development funding is now estimated at $56.4 
billion to complete in 2018, a 26 percent cost increase and a 5-year 
schedule slip from the current baseline. DOD also reduced procurement 
quantities by 246 aircraft through 2016, but has not calculated the 
net effects of restructuring on total procurement costs nor approved a 
new baseline. Affordability for the U.S. and partners is challenged by 
a near doubling in average unit prices since program start and higher 
estimated life-cycle costs. Going forward, the JSF requires 
unprecedented funding levels in a period of more austere defense 
budgets. 

The program had mixed success in 2010, achieving 6 of 12 major goals 
and progressing in varying degrees on the rest. Successes included the 
first flight of the carrier variant, award of a fixed-price aircraft 
procurement contract, and an accelerated pace in development flight 
tests that accomplished three times as many flights in 2010 as the 
previous 3 years combined. However, the program did not deliver as 
many aircraft to test and training sites as planned and made only a 
partial release of software capabilities. The short takeoff and 
landing (STOVL) variant had significant technical problems and 
deficient flight test performance. DOD directed a 2-year period to 
evaluate and engineer STOVL solutions. 

After more than 9 years in development and 4 in production, the JSF 
program has not fully demonstrated that the aircraft design is stable, 
manufacturing processes are mature, and the system is reliable. 
Engineering drawings are still being released to the manufacturing 
floor and design changes continue at higher rates than desired. More 
changes are expected as testing accelerates. Test and production 
aircraft cost more and are taking longer to deliver than expected. 
Manufacturers are improving operations and implemented 8 of 20 
recommendations from an expert panel, but have not yet demonstrated a 
capacity to efficiently produce at higher production rates. 
Substantial improvements in factory throughput and the global supply 
chain are needed. 

Development testing is still early in demonstrating that aircraft will 
work as intended and meet warfighter requirements. About 4 percent of 
JSF capabilities have been completely verified by flight tests, lab 
results, or both. Only 3 of the extensive network of 32 ground test 
labs and simulation models are fully accredited to ensure the fidelity 
of results. Software development-—essential for achieving about 80 
percent of the JSF functionality-—is significantly behind schedule as 
it enters its most challenging phase. 

View [hyperlink, http://www.gao.gov/products/GAO-11-677T] or key 
components. For more information, contact Michael J. Sullivan at (202) 
512-4841 or shiversc@gao.gov. 

[End of section] 

Chairman Levin, Ranking Member McCain, and Members of the Senate Armed 
Services Committee: 

Thank you for the opportunity to discuss our work on the F-35 
Lightning II, also known as the Joint Strike Fighter (JSF). The JSF is 
the Department of Defense's (DOD) most costly and ambitious aircraft 
acquisition, seeking to simultaneously develop and field three 
aircraft variants for the Air Force, Navy, Marine Corps, and eight 
international partners. DOD is acquiring the conventional takeoff and 
landing (CTOL) variant for the Air Force, the carrier variant (CV) for 
the Navy and Marine Corps, and the short takeoff and landing (STOVL) 
variant for the Marine Corps. The JSF is the core of DOD's long-term 
tactical aircraft recapitalization plans as it is intended to replace 
hundreds of legacy aircraft. Total planned U.S. investment in JSF is 
now about $385 billion to develop and acquire 2,457 aircraft through 
2035. Acquisition costs are expected to rise when the department 
establishes a new approved program baseline next month. 

With such a substantial funding commitment amidst pressing warfighter 
requirements for this next generation capability, DOD has lately 
recognized numerous technical, financial, and management shortcomings 
and announced a major restructuring of the JSF program in February 
2010. In March 2010, the department declared that the program 
experienced a breach of the critical cost growth statutory threshold 
and subsequently certified to Congress in June 2010 that the JSF 
program should continue.[Footnote 1] Appendix I summarizes the 
evolution of JSF cost and schedule estimates at key junctures in its 
acquisition history through the Nunn-McCurdy certification. Since 
then, in January 2011, the Secretary of Defense announced additional 
development cost increases and further changes consequent to the 
ongoing restructure. 

GAO has reported on the JSF acquisition program for a number of years. 
We've identified serious and continuing problems, including escalating 
costs, deteriorating schedules, unsatisfactory performance in 
manufacturing and delivering aircraft, slow progress in testing, and 
concerns about not meeting warfighter requirements on time and in 
quantity. We issued our latest JSF report on April 7, 2011.[Footnote 
2] While we supported the thrust and rationale behind the department's 
restructuring actions, we continued to find generally slow progress 
across the program and serious affordability challenges, both in terms 
of the investment costs to acquire the JSF and the continuing costs to 
operate and support it over the life cycle. To sustain a focus on 
accountability and facilitate trade-offs within the JSF program, we 
recommended that DOD (1) maintain annual funding levels at current 
budgeted amounts; (2) establish criteria for evaluating the progress 
of the short takeoff and landing (STOVL) variant and make independent 
reviews, allowing each variant to proceed at its own pace; and (3) 
conduct an independent review of the software development and lab 
accreditation processes. DOD concurred with our recommendations, but 
this has not been the usual case. Appendix II summarizes key findings 
and recommendations in our body of work from 2001 through 2010 and the 
department's generally lukewarm responses and actions taken during 
that period. 

My comments today are focused largely on our latest review and the 
April 2011 report. This was the second annual JSF report under our 
current mandate in the National Defense Authorization Act for Fiscal 
Year 2010.[Footnote 3] For that report, we (1) evaluated program cost 
and schedule changes and their implications on affordability; (2) 
identified progress made in 2010 against established goals; (3) 
assessed elements of design stability and manufacturing maturity and 
reviewed production results; and (4) reported the status of 
development testing and technical challenges facing the program. To 
conduct this work, we evaluated DOD's restructuring actions and 
impacts on the program, tracked cost and schedule changes, and 
determined factors driving the changes. We reviewed program status 
reports, manufacturing data, test plans, and internal DOD analyses. We 
discussed results to date and future plans to complete JSF development 
and move further into procurement with officials from DOD, the JSF 
program office, contractor officials, and members of the independent 
review teams. We toured aircraft and engine manufacturing plants, 
obtained production and supply performance indicators, and discussed 
improvements underway with contractors. We conducted this performance 
audit from May 2010 to March 2011 in accordance with generally 
accepted government auditing standards. Those standards require that 
we plan and perform the audit to obtain sufficient, appropriate 
evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the 
evidence obtained provides a reasonable basis for our findings and 
conclusions based on our audit objectives. 

JSF Restructuring Improves Program, but Affordability Is Challenged by 
Rising Costs and Delays: 

DOD has substantially restructured the JSF program over the past 15 
months, taking positive actions that should lead to more achievable 
and predictable outcomes. Restructuring has consequences--higher 
development costs, fewer aircraft in the near term, training delays, 
and extended times for testing and delivering capabilities to 
warfighters. Key restructuring changes include the following: 

* The total system development cost estimate rose to $56.4 billion and 
its schedule was extended to 2018. This represents a 26 percent 
increase in cost and a 5-year slip in schedule compared to the current 
approved program baseline established in 2007. 

* Resources and time were added to development testing. Testing plans 
were made more robust by adding another development test aircraft and 
the use of several production aircraft; increasing the number of test 
flights by one-third; extending development testing to 2016; and 
reducing its overlap with initial operational testing. 

* Near-term procurement quantities were reduced by 246 aircraft 
through 2016; the annual rate of increase in production was lowered; 
and the start of full-rate production moved to 2018, a 5-year slip 
from the current baseline. 

* The military services were directed to reexamine their initial 
operational capability (IOC) requirements, the critical need dates 
when the warfighter must have in place the first increment of 
operational forces available for combat. We expect the Marine Corps' 
IOC will slip significantly from its current 2012 date and that the 
Air Force's and Navy's IOC dates will also slip from the current dates 
in 2016. 

* To address technical problems and test deficiencies for the Marine 
Corps' STOVL variant, the department significantly scaled back its 
procurement quantities and directed a 2-year period for evaluating and 
engineering technical solutions to inform future decisions on this 
variant. DOD also "decoupled" STOVL testing from the other two 
variants so as not to delay them and to allow all three to proceed at 
their own speeds. 

* The fiscal year 2012 Defense Budget reflects the financial effects 
from restructuring actions through 2016. Compared to estimates in the 
fiscal year 2010 future years defense program for the same 5-year 
period, the department increased development funding by $7.7 billion 
and decreased procurement funding by $8.4 billion reflecting plans to 
buy fewer aircraft. Table 1 summarizes the revised funding 
requirements and annual quantities following the Secretary's 
reductions. Even after decreasing near-term quantities and lowering 
the annual rate of increase in production, JSF procurement still 
escalates significantly. Annual funding levels more than double and 
quantities more than triple during this period. These numbers do not 
include the additional orders expected from the international partners. 

Table 1: Proposed Development and Procurement Funding and Quantities 
for Fiscal Years 2012-2016: 

Development funding: 

Air Force (CTOL); 
FY 2012: $1.4 billion; 
FY 2013: $1.2 billion; 
FY 2014: $0.9 billion; 
FY 2015: $0.6 billion; 
FY 2016: $0.4 billion; 
Total: $4.5 billion. 

Navy (CV); 
FY 2012: $0.7 billion; 
FY 2013: $0.7 billion; 
FY 2014: $0.7 billion; 
FY 2015: $0.6 billion; 
FY 2016: $0.5 billion; 
Total: $3.2 billion. 

Marine Corps (STOVL); 
FY 2012: $0.7 billion; 
FY 2013: $0.7 billion; 
FY 2014: $0.7 billion; 
FY 2015: $0.6 billion; 
FY 2016: $0.5 billion; 
Total: $3.2 billion. 

U.S. total; 
FY 2012: $2.7 billion; 
FY 2013: $2.7 billion; 
FY 2014: $2.3 billion; 
FY 2015: $1.8 billion; 
FY 2016: $1.3 billion; 
Total: $10.8 billion. 

Procurement funding: 

Air Force (CTOL); 
FY 2012: $3.8 billion; 
FY 2013: $4.1 billion; 
FY 2014: $5.6 billion; 
FY 2015: $6.5 billion; 
FY 2016: $8.5 billion; 
Total: $28.5 billion. 

Navy (CV); 
FY 2012: $1.8 billion; 
FY 2013: $2.5 billion; 
FY 2014: $2.8 billion; 
FY 2015: $3.3 billion; 
FY 2016: $2.9 billion; 
Total: $13.2 billion. 

Marine Corps (STOVL); 
FY 2012: $1.3 billion; 
FY 2013: $1.3 billion; 
FY 2014: $1.4 billion; 
FY 2015: $2.0 billion; 
FY 2016: $2.9 billion; 
Total: $9.0 billion. 

U.S. total; 
FY 2012: $6.9 billion; 
FY 2013: $7.9 billion; 
FY 2014: $9.8 billion; 
FY 2015: $11.8 billion; 
FY 2016: $14.3 billion; 
Total: $50.7 billion. 

Procurement Quantities: 

Air Force (CTOL); 
FY 2012: 19; 
FY 2013: 24; 
FY 2014: 40; 
FY 2015: 50; 
FY 2016: 70; 
Total: 203. 

Navy (CV); 
FY 2012: 7; 
FY 2013: 12; 
FY 2014: 14; 
FY 2015: 19; 
FY 2016: 20; 
Total: 72. 

Marine Corps (STOVL); 
FY 2012: 6; 
FY 2013: 6; 
FY 2014: 8; 
FY 2015: 12; 
FY 2016: 18; 
Total: 50. 

U.S. total; 
FY 2012: 32; 
FY 2013: 42; 
FY 2014: 62; 
FY 2015: 81; 
FY 2016: 108; 
Total: 325. 

Source: GAO analysis of fiscal year 2012 President's Budget. 

Note: Numbers may not add due to rounding. 

[End of table] 

At the time of our review, DOD did not yet know the full impact from 
restructuring actions on future procurement funding requirements 
beyond this 5-year period. Cost analysts were still calculating the 
net effects from deferring the near-term procurement of 246 aircraft 
to future years and from lowering the annual rate of increased 
procurement. After a Nunn-McCurdy breach of the critical cost growth 
threshold and DOD certification, the most recent milestone must be 
rescinded, the program restructured to address the cause of the 
breach, and a new acquisition program baseline must be approved that 
reflects the certification approved by the milestone decision 
authority. The Secretary has not yet granted new milestone B approval 
for the JSF nor approved a new acquisition program baseline; officials 
expect to do so next month. We expect future funding requirements will 
be somewhat higher than currently projected. This could reduce the 
quantities considered affordable by the U.S. and allies, further 
driving up unit costs. 

Affordability--in terms of the investment costs to acquire the JSF, 
the continuing costs to operate and maintain it over the life-cycle, 
and its impact on other defense programs--is a challenging issue. 
Including the funding added by the restructuring actions, system 
development cost estimates have increased 64 percent since program 
start. (Appendix III summarizes the increases in target prices and 
major cost drivers for the air system and primary engine development 
contracts.) Also, the estimated average unit procurement price for the 
JSF has about doubled since program start and current forecasts 
indicate that life-cycle costs will be substantially higher than the 
legacy aircraft it replaces. Rising JSF costs erode buying power and 
may make it difficult for the U.S. and its allies to buy and sustain 
as many aircraft as planned. 

Going forward, the JSF will require unprecedented demands for funding 
in a period of more austere defense budgets where it will have to 
annually compete with other defense and nondefense priorities for the 
discretionary federal dollar. Figure 1 illustrates the substantive 
annual development and procurement funding requirements--almost $13 
billion on average through program completion in 2035. This reflects 
the program's estimate at the time of the fiscal year 2012 budget 
submission. As discussed earlier, defense cost analysts are still 
computing the long-term procurement funding requirements reflecting 
the deferral of aircraft to future years. 

Figure 1: JSF Annual Development and Procurement Funding Requirements 
(April 2011 Estimate): 

[Refer to PDF for image: vertical bar graph] 

[Through FY 2010: $55.7 billion] 

Fiscal year: 1994; 
Funding requirement: $0.03 billion. 

Fiscal year: 1995; 
Funding requirement: $0.18 billion. 

Fiscal year: 1996; 
Funding requirement: $0.20 billion. 

Fiscal year: 1997; 
Funding requirement: $0.63 billion. 

Fiscal year: 1998; 
Funding requirement: $0.99 billion. 

Fiscal year: 1999; 
Funding requirement: $0.98 billion. 

Fiscal year: 2000; 
Funding requirement: $0.52 billion. 

Fiscal year: 2001; 
Funding requirement: $0.68 billion. 

Fiscal year: 2002; 
Funding requirement: $1.74 billion. 

Fiscal year: 2003; 
Funding requirement: $3.68 billion. 

Fiscal year: 2004; 
Funding requirement: $4.66 billion. 

Fiscal year: 2005; 
Funding requirement: $4.93 billion. 

Fiscal year: 2006; 
Funding requirement: $5.37 billion. 

Fiscal year: 2007; 
Funding requirement: $5.60 billion. 

Fiscal year: 2008; 
Funding requirement: $7.14 billion. 

Fiscal year: 2009; 
Funding requirement: $7.31 billion. 

Fiscal year: 2010; 
Funding requirement: $11.06 billion. 

[FY 2011 through FY 2035: $323.7 billion] 

Fiscal year: 2011; 
Funding requirement: $10.26 billion. 

Fiscal year: 2012; 
Funding requirement: $9.74 billion. 

Fiscal year: 2013; 
Funding requirement: $10.59 billion. 

Fiscal year: 2014; 
Funding requirement: $12.09 billion. 

Fiscal year: 2015; 
Funding requirement: $13.51 billion. 

Fiscal year: 2016; 
Funding requirement: $15.52 billion. 

Fiscal year: 2017; 
Funding requirement: $16.63 billion. 

Fiscal year: 2018; 
Funding requirement: $15.52 billion. 

Fiscal year: 2019; 
Funding requirement: $15.24 billion. 

Fiscal year: 2020; 
Funding requirement: $15.51 billion. 

Fiscal year: 2021; 
Funding requirement: $15.73 billion. 

Fiscal year: 2022; 
Funding requirement: $15.81 billion. 

Fiscal year: 2023; 
Funding requirement: $15.86 billion. 

Fiscal year: 2024; 
Funding requirement: $15.95 billion. 

Fiscal year: 2025; 
Funding requirement: $16.04 billion. 

Fiscal year: 2026; 
Funding requirement: $15.65 billion. 

Fiscal year: 2027; 
Funding requirement: $12.29 billion. 

Fiscal year: 2028; 
Funding requirement: $10.03 billion. 

Fiscal year: 2029; 
Funding requirement: $10.05 billion. 

Fiscal year: 2030; 
Funding requirement: $10.06 billion. 

Fiscal year: 2031; 
Funding requirement: $10.24 billion. 

Fiscal year: 2032; 
Funding requirement: $10.50 billion. 

Fiscal year: 2033; 
Funding requirement: $10.76 billion. 

Fiscal year: 2034; 
Funding requirement: $10.90 billion. 

Fiscal year: 2035; 
Funding requirement: $9.20 billion. 

Source: GAO analysis of DOD data. 

[End of figure] 

Progress in Achieving the JSF Program's 2010 Goals Was Mixed: 

The JSF program established 12 clearly stated goals in testing, 
contracting, and manufacturing for completion in calendar year 2010. 
It had mixed success, achieving 6 goals and making varying degrees of 
progress on the other 6. For example, the program exceeded its goal 
for the number of development flight tests but did not deliver as many 
test and production aircraft as planned. Also, the program awarded its 
first fixed-price contract on its fourth lot of production aircraft, 
but did not award the fixed-price engine contract in 2010 as planned. 
Table 2 summarizes JSF goals and accomplishments for 2010. 

Table 2: JSF Progress on Stated Goals for 2010: 

Key event: Complete 400 development flight tests; 
Achieved in 2010? Yes; 
Status: Completed 410 test flights. 

Key event: First vertical landing of STOVL variant; 
Achieved in 2010? Yes; 
Status: Achieved March 2010. 

Key event: Carrier variant first flight; 
Achieved in 2010? Yes; 
Status: Achieved June 2010. 

Key event: Autonomic logistic information system is operational; 
Achieved in 2010? Yes; 
Status: Began limited operations July 2010. 

Key event: Training for 125 maintenance personnel completed; 
Achieved in 2010? Yes; 
Status: Trained 138 maintenance personnel. 

Key event: Award contract for fourth aircraft production lot; 
Achieved in 2010? Yes; 
Status: Awarded contract November 2010. 

Key event: Eleven test aircraft delivered to test sites; 
Achieved in 2010? No; 
Status: Delivered eight aircraft. 

Key event: Flight test rate of 12 flights per aircraft per month 
demonstrated; 
Achieved in 2010? No; 
Status: Achieved flight test rate of 2 to 8 per month. 

Key event: At least 3 aircraft delivered to Eglin Air Force Base; 
Achieved in 2010? No; 
Status: None delivered, expected mid-2011. 

Key event: Begin flight training operations at Eglin Air Force Base; 
Achieved in 2010? No; 
Status: Expected September 2011. 

Key event: Block 1.0 software delivered to flight test; 
Achieved in 2010? No; 
Status: Delivered limited capability November 2010 with full 
capability expected June 2011. 

Key event: Award contract for fourth engine production lot; 
Achieved in 2010? No; 
Status: Awarded May 2011. 

Source: GAO analysis of DOD data. 

[End of table] 

Although still hampered by the late delivery of test aircraft to 
testing sites, the development flight test program significantly 
ramped up operations in 2010, accomplishing 3 times as many test 
flights as the previous 3 years combined. The Air Force CTOL variant 
significantly exceeded the annual plan while initial limited testing 
of the Navy's CV variant was judged satisfactory, below plans for the 
number and hours of flight but ahead on flight test points[Footnote 4] 
flown. The Marine Corps' STOVL, however, substantially underperformed 
in flight tests, experienced significant down times for maintenance, 
and was challenged by several technical issues unique to this variant 
that could add to its weight and cost. The STOVL's problems were a 
major factor in the Secretary's decision to give the STOVL a 2-year 
period to solve engineering issues, assess impacts, and inform a 
future decision as to whether and how to proceed with this variant. 
Table 3 summarizes 2010 flight test results for each variant. 

Table 3: Flight Test Performance in 2010: 

Flight tests: Actual; 
Conventional takeoff and landing variant: 171; 
Short takeoff and vertical landing variant: 212; 
Carrier variant: 27; 
Total: 410. 

Flight tests: Planned; 
Conventional takeoff and landing variant: 112; 
Short takeoff and vertical landing variant: 251; 
Carrier variant: 31; 
Total: 394. 

Flight tests: Difference; 
Conventional takeoff and landing variant: 59; 
Short takeoff and vertical landing variant: (39); 
Carrier variant: (4); 
Total: 16. 

Flight test hours: Actual; 
Conventional takeoff and landing variant: 290; 
Short takeoff and vertical landing variant: 286; 
Carrier variant: 41; 
Total: 617. 

Flight test hours: Planned; 
Conventional takeoff and landing variant: 202; 
Short takeoff and vertical landing variant: 409; 
Carrier variant: 56; 
Total: 667. 

Flight test hours: Difference; 
Conventional takeoff and landing variant: 88; 
Short takeoff and vertical landing variant: (123); 
Carrier variant: (15); 
Total: (50). 

Flight test points flown: Actual; 
Conventional takeoff and landing variant: 1373; 
Short takeoff and vertical landing variant: 1924; 
Carrier variant: 496; 
Total: 3793. 

Flight test points flown: Planned; 
Conventional takeoff and landing variant: 1064; 
Short takeoff and vertical landing variant: 2438; 
Carrier variant: 270; 
Total: 3772. 

Flight test points flown: Difference; 
Conventional takeoff and landing variant: 309; 
Short takeoff and vertical landing variant: (514); 
Carrier variant: 226; 
Total: 21. 

Source: GAO analysis of DOD data. 

[End of table] 

Program Has Still Not Fully Demonstrated a Stable Design and Mature 
Manufacturing Processes as It Enters Its Fifth Year of Production: 

After completing 9 years of system development and 4 years of 
overlapping production activities, the JSF program has been slow to 
gain adequate knowledge to ensure its design is stable and the 
manufacturing process is ready for greater levels of annual 
production. The JSF program still lags in achieving critical 
indicators of success expected from well-performing acquisition 
programs. Specifically, the program has not yet stabilized aircraft 
designs--engineering changes continue at higher than expected rates 
long after critical design reviews and well into procurement. 
Engineering drawings are still being released to the manufacturing 
floor. More changes are expected as testing accelerates. Also, 
manufacturing cost increases and delays in delivering test and 
production aircraft indicate a need for substantial improvements in 
factory throughput and performance of the global supply chain. 

Engineering drawings released since design reviews and the number and 
rate of design changes exceed those planned at program outset and are 
not in line with best practices. Critical design reviews were 
completed on the three aircraft variants in 2006 and 2007 and the 
designs declared mature, but the program continues to experience 
numerous changes. Since 2007, the program has produced 20,000 
additional engineering drawings, a 50-percent increase in total 
drawings and about five times more than best practices suggest. In 
addition, changes to drawings have not yet decreased and leveled off 
as planned. Figure 2 tracks and compares monthly design changes and 
future forecasts against contractor plans in 2007. 

Figure 2: Monthly Design Changes for JSF Aircraft: 

[Refer to PDF for image: combination vertical bar and line graph] 

2006: 

January; 
Anticipated design changes (2007 plan): 264; 
Design changes (actual): 251. 

February; 
Anticipated design changes (2007 plan): 323; 
Design changes (actual): 283. 

March; 
Anticipated design changes (2007 plan): 341; 
Design changes (actual): 362. 

April; 
Anticipated design changes (2007 plan): 374; 
Design changes (actual): 281. 

May; 
Anticipated design changes (2007 plan): 403; 
Design changes (actual): 373. 

June; 
Anticipated design changes (2007 plan): 378; 
Design changes (actual): 447. 

July; 
Anticipated design changes (2007 plan): 411; 
Design changes (actual): 347. 

August; 
Anticipated design changes (2007 plan): 513; 
Design changes (actual): 520. 

September; 
Anticipated design changes (2007 plan): 575; 
Design changes (actual): 385. 

October; 
Anticipated design changes (2007 plan): 490; 
Design changes (actual): 515. 

November; 
Anticipated design changes (2007 plan): 495; 
Design changes (actual): 505. 

December; 
Anticipated design changes (2007 plan): 547; 
Design changes (actual): 378. 

2007: 

January; 
Anticipated design changes (2007 plan): 653; 
Design changes (actual): 620. 

February; 
Anticipated design changes (2007 plan): 579; 
Design changes (actual): 567. 

March; 
Anticipated design changes (2007 plan): 576; 
Design changes (actual): 598. 

April; 
Anticipated design changes (2007 plan): 595; 
Design changes (actual): 647. 

May; 
Anticipated design changes (2007 plan): 663; 
Design changes (actual): 697. 

June; 
Anticipated design changes (2007 plan): 702; 
Design changes (actual): 634. 

July; 
Anticipated design changes (2007 plan): 747; 
Design changes (actual): 681. 

August; 
Anticipated design changes (2007 plan): 797; 
Design changes (actual): 739. 

September; 
Anticipated design changes (2007 plan): 775; 
Design changes (actual): 744. 

October; 
Anticipated design changes (2007 plan): 730; 
Design changes (actual): 876. 

November; 
Anticipated design changes (2007 plan): 761; 
Design changes (actual): 678. 

December; 
Anticipated design changes (2007 plan): 814; 
Design changes (actual): 578. 

2008: 

January; 
Anticipated design changes (2007 plan): 853; 
Design changes (actual): 606. 

February; 
Anticipated design changes (2007 plan): 828; 
Design changes (actual): 594. 

March; 
Anticipated design changes (2007 plan): 759; 
Design changes (actual): 645. 

April; 
Anticipated design changes (2007 plan): 675; 
Design changes (actual): 560. 

May; 
Anticipated design changes (2007 plan): 624; 
Design changes (actual): 387. 

June; 
Anticipated design changes (2007 plan): 599; 
Design changes (actual): 459. 

July; 
Anticipated design changes (2007 plan): 606; 
Design changes (actual): 605. 

August; 
Anticipated design changes (2007 plan): 578; 
Design changes (actual): 590. 

September; 
Anticipated design changes (2007 plan): 477; 
Design changes (actual): 590. 

October; 
Anticipated design changes (2007 plan): 428; 
Design changes (actual): 621. 

November; 
Anticipated design changes (2007 plan): 422; 
Design changes (actual): 527. 

December; 
Anticipated design changes (2007 plan): 421; 
Design changes (actual): 508. 

2009: 

January; 
Anticipated design changes (2007 plan): 389; 
Design changes (actual): 573. 

February; 
Anticipated design changes (2007 plan): 394; 
Design changes (actual): 655. 

March; 
Anticipated design changes (2007 plan): 328; 
Design changes (actual): 716. 

April; 
Anticipated design changes (2007 plan): 346; 
Design changes (actual): 629. 

May; 
Anticipated design changes (2007 plan): 330; 
Design changes (actual): 522. 

June; 
Anticipated design changes (2007 plan): 306; 
Design changes (actual): 568. 

July; 
Anticipated design changes (2007 plan): 288; 
Design changes (actual): 493. 

August; 
Anticipated design changes (2007 plan): 291; 
Design changes (actual): 492. 

September; 
Anticipated design changes (2007 plan): 301; 
Design changes (actual): 482. 

October; 
Anticipated design changes (2007 plan): 282; 
Design changes (actual): 480. 

November; 
Anticipated design changes (2007 plan): 266; 
Design changes (actual): 415. 

December; 
Anticipated design changes (2007 plan): 259; 
Design changes (actual): 302. 

2010: 

January; 
Anticipated design changes (2007 plan): 260; 
Design changes (actual): 342. 

February; 
Anticipated design changes (2007 plan): 259; 
Design changes (actual): 323. 

March; 
Anticipated design changes (2007 plan): 270; 
Design changes (actual): 363. 

April; 
Anticipated design changes (2007 plan): 258; 
Design changes (actual): 376. 

May; 
Anticipated design changes (2007 plan): 253; 
Design changes (actual): 353. 

June; 
Anticipated design changes (2007 plan): 254; 
Design changes (actual): 356. 

July; 
Anticipated design changes (2007 plan): 257; 
Design changes (actual): 314. 

Program now anticipates 10,000 more design changes than anticipated in 
2007. 

August; 
Anticipated design changes (2007 plan): 242; 
Design changes (actual): 302; 
Anticipated future design changes (2010 plan): 233. 

September; 
Anticipated design changes (2007 plan): 244; 
Anticipated future design changes (2010 plan): 230. 

October; 
Anticipated design changes (2007 plan): 226; 
Anticipated future design changes (2010 plan): 235. 

November; 
Anticipated design changes (2007 plan): 216; 
Anticipated future design changes (2010 plan): 233. 

December; 
Anticipated design changes (2007 plan): 210; 
Anticipated future design changes (2010 plan): 229. 

2011: 

January; 
Anticipated design changes (2007 plan): 202; 
Anticipated future design changes (2010 plan): 231. 

February; 
Anticipated design changes (2007 plan): 193; 
Anticipated future design changes (2010 plan): 245. 

March; 
Anticipated design changes (2007 plan): 192; 
Anticipated future design changes (2010 plan): 245. 

April; 
Anticipated design changes (2007 plan): 178; 
Anticipated future design changes (2010 plan): 241. 

May; 
Anticipated design changes (2007 plan): 168; 
Anticipated future design changes (2010 plan): 254. 

June; 
Anticipated design changes (2007 plan): 155; 
Anticipated future design changes (2010 plan): 249. 

July; 
Anticipated design changes (2007 plan): 152; 
Anticipated future design changes (2010 plan): 241. 

August; 
Anticipated design changes (2007 plan): 145; 
Anticipated future design changes (2010 plan): 256. 

September; 
Anticipated design changes (2007 plan): 142; 
Anticipated future design changes (2010 plan): 241. 

October; 
Anticipated design changes (2007 plan): 142; 
Anticipated future design changes (2010 plan): 253. 

November; 
Anticipated design changes (2007 plan): 138; 
Anticipated future design changes (2010 plan): 247. 

December; 
Anticipated design changes (2007 plan): 138; 
Anticipated future design changes (2010 plan): 238. 

2012: 

January; 
Anticipated design changes (2007 plan): 144; 
Anticipated future design changes (2010 plan): 245. 

February; 
Anticipated design changes (2007 plan): 151; 
Anticipated future design changes (2010 plan): 242. 

March; 
Anticipated design changes (2007 plan): 137; 
Anticipated future design changes (2010 plan): 245. 

April; 
Anticipated design changes (2007 plan): 140; 
Anticipated future design changes (2010 plan): 243. 

May; 
Anticipated design changes (2007 plan): 137; 
Anticipated future design changes (2010 plan): 245. 

June; 
Anticipated design changes (2007 plan): 138; 
Anticipated future design changes (2010 plan): 240. 

July; 
Anticipated design changes (2007 plan): 140; 
Anticipated future design changes (2010 plan): 240. 

August; 
Anticipated design changes (2007 plan): 137; 
Anticipated future design changes (2010 plan): 241. 

September; 
Anticipated design changes (2007 plan): 129; 
Anticipated future design changes (2010 plan): 260. 

October; 
Anticipated design changes (2007 plan): 124; 
Anticipated future design changes (2010 plan): 244. 

November; 
Anticipated design changes (2007 plan): 121; 
Anticipated future design changes (2010 plan): 257. 

December; 
Anticipated design changes (2007 plan): 105; 
Anticipated future design changes (2010 plan): 237. 

2013: 

January; 
Anticipated design changes (2007 plan): 72; 
Anticipated future design changes (2010 plan): 235. 

February; 
Anticipated design changes (2007 plan): 63; 
Anticipated future design changes (2010 plan): 235. 

March; 
Anticipated design changes (2007 plan): 55; 
Anticipated future design changes (2010 plan): 231. 

April; 
Anticipated design changes (2007 plan): 38; 
Anticipated future design changes (2010 plan): 233. 

May; 
Anticipated design changes (2007 plan): 39; 
Anticipated future design changes (2010 plan): 213. 

June; 
Anticipated design changes (2007 plan): 38; 
Anticipated future design changes (2010 plan): 229. 

July; 
Anticipated design changes (2007 plan): 30; 
Anticipated future design changes (2010 plan): 227. 

August; 
Anticipated design changes (2007 plan): 30; 
Anticipated future design changes (2010 plan): 251. 

September; 
Anticipated design changes (2007 plan): 30; 
Anticipated future design changes (2010 plan): 242. 

October; 
Anticipated design changes (2007 plan): 30; 
Anticipated future design changes (2010 plan): 262. 

November; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 260. 

December; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 268. 

2014: 

January; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 271. 

February; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 251. 

March; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 249. 

April; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 251. 

May; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 247. 

June; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 224. 

July; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 221. 

August; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 217. 

September; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 204. 

October; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 197. 

November; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 182. 

December; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 169. 

2015: 

January; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 162. 

February; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 162. 

March; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 142. 

April; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 131. 

May; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 114. 

June; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 94. 

July; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 80. 

August; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 66. 

September; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 48. 

October; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 33. 

November; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 20. 

December; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 8. 

2016: 

January; 
Anticipated design changes (2007 plan): 0; 
Anticipated future design changes (2010 plan): 0. 

Source: GAO analysis of DOD data. 

[End of figure] 

The monthly rate in 2009 and 2010 was higher than expected and the 
program now anticipates more changes over a longer period of time--
about 10,000 more changes through January 2016. With most of 
development testing still ahead for the JSF, the risk and impact from 
required design changes are significant. In addition, emerging 
concerns about the STOVL lift fan and drive shaft, fatigue cracks in a 
ground test article, and stealth-related issues may drive additional 
and substantive design changes. 

Manufacturing and delivering test jets took much more time and money 
than planned. As in prior years, lingering management inefficiencies, 
including substantial out-of-station work[Footnote 5] and part 
shortages, continued to increase the labor needed to manufacture test 
aircraft. Although there have been improvements in these factors, 
final acceptance and delivery of test jets were still delayed. Total 
labor hours required to produce the test aircraft increased over time. 
The cumulative actual labor hours through 2010 to complete the 12 test 
aircraft exceeded the budgeted hours estimated in 2007 by more than 
1.5 million hours, a 75 percent increase. Figure 3 depicts forecasted 
and actual labor hours for building test jets. 

Figure 3: JSF Labor Hours for Manufacturing Test Aircraft: 

[Refer to PDF for image: multiple line graph] 

Aircraft: BF1; 
2007 Budget: 342,647; 
2009 Budget: 361,047; 
2010 Budget: 392,006. 

Aircraft: BF2; 
2007 Budget: 233,319; 
2009 Budget: 296,681; 
2010 Budget: 356,814. 

Aircraft: BF3; 
2007 Budget: 179,892; 
2009 Budget: 254,394; 
2010 Budget: 311,830. 

Aircraft: BF4; 
2007 Budget: 155,420; 
2009 Budget: 223,391; 
2010 Budget: 354,329. 

Aircraft: AF1; 
2007 Budget: 187,781; 
2009 Budget: 262,694; 
2010 Budget: 337,244. 

Aircraft: AF2; 
2007 Budget: 145,607; 
2009 Budget: 222,396; 
2010 Budget: 275,728. 

Aircraft: AF3; 
2007 Budget: 130,955; 
2009 Budget: 209,861; 
2010 Budget: 289,143. 

Aircraft: CF1; 
2007 Budget: 239,351; 
2009 Budget: 263,064; 
2010 Budget: 310,099. 

Aircraft: CF2; 
2007 Budget: 125,602; 
2009 Budget: 218,194; 
2010 Budget: 236,538. 

Aircraft: CF3; 
2007 Budget: 118,153; 
2009 Budget: 204,908; 
2010 Budget: 240,438. 

Aircraft: BF5; 
2007 Budget: 102,505; 
2009 Budget: 191,410; 
2010 Budget: 262,069. 

Aircraft: AF4; 
2007 Budget: 91,218; 
2009 Budget: 183,480; 
2010 Budget: 222,580. 

Source: GAO analysis of DOD data. 

[End of figure] 

DOD began procuring production jets in 2007 and has now ordered 58 
aircraft on the first four low-rate initial production lots. The JSF 
program anticipated the delivery of 14 production aircraft through 
2010, but none were delivered during that period. Delivery of the two 
production jets ordered in 2007 has been delayed several times since 
the contract was signed and the first aircraft was just delivered this 
month. The prices on each of the first three cost-reimbursable 
production contracts have increased from the amounts negotiated at 
contract awards and the completion dates for delivering aircraft have 
been extended over 9 months on average. We are encouraged by DOD's 
award of a fixed-price incentive fee contract for lot 4 production and 
the prospects for the cost study to inform lot 5 negotiations, but we 
have not examined contract specifications. Accumulating a large 
backlog of jets on order but undelivered is not an efficient use of 
federal funds, tying up millions of dollars in obligations ahead of 
the ability of the manufacturing process to produce. 

The aircraft and engine manufacturers now have significantly more 
items in production flow compared to prior years and are making 
efforts to implement restructuring actions and recommendations from 
expert defense teams assembled to evaluate and improve production and 
supply operations. Eight of 20 key recommendations from the 
independent manufacturing review team have been implemented as of 
September 2010. Until improvements are fully implemented and 
demonstrated, the restructuring actions to reduce near term 
procurement quantities and establish a more achievable ramp rate are 
appropriate and will provide more time to fully mature manufacturing 
and supply processes and catch up with aircraft backlogs. Improving 
factory throughput and controlling costs--driving down labor and 
material costs and delivering on time--are essential for efficient 
manufacturing and timely delivery to the warfighter at the increased 
production rates planned for the future. 

Testing Has Been Slow and Has Not Demonstrated That the Aircraft Will 
Work in Its Intended Environment: 

Since the first flight in December 2006, only about 4 percent of JSF 
capabilities have been completely verified by flight tests, lab 
results, or both. The pace of flight testing accelerated significantly 
in 2010, but overall progress is still much below plans forecasted 
several years ago. Furthermore, only a small portion of the extensive 
network of ground test labs and simulation models are fully accredited 
to ensure the fidelity of results. Software development--essential for 
achieving about 80 percent of the JSF functionality--is significantly 
behind schedule as it enters its most challenging phase. 

Development flight testing was much more active in 2010 than prior 
years and had some notable successes, but cumulatively still lagged 
behind previous expectations. The continuing effects from late 
delivery of test aircraft and an inability to achieve the planned 
flying rates per aircraft substantially reduced the amount and pace of 
testing planned previously. Consequently, even though the flight test 
program accelerated its pace last year, the total number of flights 
accomplished during the first 4 years of the test program 
significantly lagged expectations when the program's 2007 baseline was 
established. Figure 4 shows that the cumulative number of flights 
accomplished by the end of 2010 was only about one-fifth the numbers 
forecast by this time in the 2007 test plan. 

Figure 4: Actual JSF Flight Tests Completed through 2010 Compared to 
the 2007 Plan: 

[Refer to PDF for image: multiple line graph] 

Date: January 2010: 
2007 planned : 1,155; 
2010 actual flights: 144. 

Date: February 2010; 
2007 planned flights: 1,291; 
2010 actual flights: 157. 

Date: March 2010; 
2007 planned flights: 1,420; 
2010 actual flights: 170. 

Date: April 2010; 
2007 planned flights: 1,546; 
2010 actual flights: 197. 

Date: May 2010; 
2007 planned flights: 1,681; 
2010 actual flights: 230. 

Date: June 2010; 
2007 planned flights: 1,812; 
2010 actual flights: 273. 

Date: July 2010; 
2007 planned flights: 1,953; 
2010 actual flights: 322. 

Date: August 2010; 
2007 planned flights: 2,079; 
2010 actual flights: 370. 

Date: September 2010; 
2007 planned flights: 2,250; 
2010 actual flights: 406. 

Date: October 2010; 
2007 planned flights: 2,393; 
2010 actual flights: 458. 

Date: November 2010; 
2007 planned flights: 2,519; 
2010 actual flights: 518. 

Date: December 2010; 
2007 planned flights: 2,649; 
2010 actual flights: 547. 

Source: GAO analysis of DOD data. 

[End of figure] 

By the end of 2010, about 10 percent of more than 50,000 planned 
flight test points had been completed.[Footnote 6] The majority of the 
points were earned on airworthiness tests (basic airframe handling 
characteristics) and in ferrying the planes to test sites. Remaining 
test points include more complex and stringent requirements, such as 
mission systems, ship suitability, and weapons integration that have 
yet to be demonstrated. 

The JSF test program relies much more heavily than previous weapon 
systems on its modeling and simulation labs to test and verify 
aircraft design and subsystem performance. However, only 3 of 32 labs 
and models have been fully accredited to date. The program had planned 
to accredit 11 labs and models by now. Accreditation is essential to 
validate that the models accurately reflect aircraft performance and 
it largely depends upon flight test data to verify lab results. 
Moreover, the ability to substitute ground testing for some flight 
testing is unproven. Contractor officials told us that early results 
are providing good correlation between ground and flight tests. 

Software providing essential JSF capability is not mature and releases 
to the test program are behind schedule. Officials underestimated the 
time and effort needed to develop and integrate the software, 
substantially contributing to the program's overall cost and schedule 
problems and testing delays, and requiring the retention of engineers 
for longer periods. Significant learning and development work remains 
before the program can demonstrate the mature software capabilities 
needed to meet warfighter requirements. The JSF software development 
effort is one of the largest and most complex in DOD history, 
providing functionality essential to capabilities such as sensor 
fusion, weapons and fire control, maintenance diagnostics, and 
propulsion. JSF has about 8 times more on-board software lines of code 
than the F/A-18E/F Super Hornet and 4 times for than the F-22A Raptor. 
While good progress has been reported on the writing of code, total 
lines of code have grown by 40 percent since preliminary design review 
and 13 percent since the critical design review. The amount of code 
needed will likely increase as integration and testing efforts 
intensify. A second software integration line added as part of the 
restructuring will improve capacity and output. 

Delays in developing, integrating, and releasing software to the test 
program have cascading effects hampering flight tests, training, and 
lab accreditation. While progress is being made, a substantial amount 
of software work remains before the program can demonstrate full 
warfighting capability. The program released its second block, or 
increment, to flight test nearly 2 years later than the plan set in 
2006, largely due to integration problems. Each of the remaining three 
blocks--providing full mission systems and warfighting capabilities--
are now projected to slip more than 3 years compared to the 2006 plan. 
Figure 5 illustrates the actual and projected slips for each of the 5 
software blocks in delivering software to the test program. 

Figure 5: Slips in Delivering Software to Flight Test: 

[Refer to PDF for image: illustrated table] 

Block 0.1: Flight sciences; 
Initial estimate (2006): Mid-2006; 
Current estimate (2011): Early 2007. 

Block 0.5: Initial mission systems architecture; 
Initial estimate (2006): Mid-2008; 
Current estimate (2011): Mid-2010. 

Block 1.0: Initial training capability; 
Initial estimate (2006): Late 2008; 
Current estimate (2011): Mid-2011. 

Block 2.0: Initial warfighting capability; 
Initial estimate (2006): Mid-2010; 
Current estimate (2011): Late 2013. 

Block 3.0: Full warfighting capability; 
Initial estimate (2006): Late 2011; 
Current estimate (2011): Late 2014. 

Source: GAO analysis of DOD data. 

[End of figure] 

Schedule delays require retention of engineering staff for longer 
periods of time. Also, some capabilities have been moved to future 
blocks in attempts to meet schedule and mitigate risks. Uncertainties 
pertaining to critical technologies, including the helmet-mounted 
display and advanced data links, pose risks for more delays. 

Concluding Remarks: 

The JSF program is at a critical juncture--9 years in development and 
4 years in limited production-but still early in flight testing to 
verify aircraft design and performance. If effectively implemented and 
sustained, the restructuring DOD is conducting should place the JSF 
program on a firmer footing and lead to more achievable and 
predictable outcomes. However, restructuring comes with a price--
higher development costs, fewer aircraft received in the near term, 
training delays, prolonged times for testing and delivering the 
capabilities required by the warfighter, and impacts on other defense 
programs and priorities. Reducing near-term procurement quantities 
lessens, but does not eliminate the still substantial and risky 
concurrency of development and production. Development and testing 
activities will now overlap 11 years of procurement. Flight testing 
and production activities are increasing and contractors are improving 
supply and manufacturing processes, but deliveries are still lagging. 
Slowed deliveries have led to a growing backlog of jets on order but 
not delivered. This is not a good use of federal funds, obligating 
millions of dollars well before the manufacturing process can deliver 
aircraft. 

We agree with defense leadership that a renewed and sustained focus on 
affordability by contractors and the government is critical to moving 
this important program forward and enabling our military services and 
our allies to acquire and sustain JSF forces in needed quantities. 
Maintaining senior leadership's increased focus on program results, 
holding government and contractors accountable for improving 
performance, and bringing a more responsible management approach to 
the JSF to "live within its means" may help limit future cost growth 
and the consequences for other programs in the portfolio. The JSF 
acquisition demands an unprecedented share of the DOD's future 
investment funding. The program's size and priority are such that its 
cost overruns and extended schedules must either be borne by funding 
cuts to other programs or else drive increases in the top line of 
defense spending; the latter may not be an option in a period of more 
austere budgets. Given the other priorities that DOD must address in a 
finite budget, JSF affordability is critical and DOD must plan ahead 
to address and manage JSF challenges and risks in the future. 

Chairman Levin, Ranking Member McCain, and members of the Senate Armed 
Services Committee, this completes my prepared statement. I would be 
pleased to respond to any questions you may have. 

GAO Contacts and Acknowledgments: 

For further information on this statement, please contact Michael 
Sullivan at (202) 512-4841 or sullivanm@gao.gov. Contact points for 
our Office of Congressional Relations and Public Affairs may be found 
on the last page of this statement. Individuals making key 
contributions to this statement are Bruce Fairbairn, Charlie Shivers, 
Julie Hadley, Dr. W. Kendal Roberts, LeAnna Parkey, and Matt Lea. 

[End of section] 

Appendix I: Changes in Reported JSF Program Cost, Quantities, and 
Deliveries: 

Expected quantities: 

Development quantities; 
October 2001 (system development start): 14; 
December 2003 (replan): 14; 
March 2007 (approved baseline): 15; 
April 2010 (initial program restructure): 14; 
June 2010 (Nunn-McCurdy): 14. 

Procurement quantities (U.S. only); 
October 2001 (system development start): 2,852; 
December 2003 (replan): 2,443; 
March 2007 (approved baseline): 2,443; 
April 2010 (initial program restructure): 2,443; 
June 2010 (Nunn-McCurdy): 2,443. 

Total quantities; 
October 2001 (system development start): 2,866; 
December 2003 (replan): 2,457; 
March 2007 (approved baseline): 2,458; 
April 2010 (initial program restructure): 2,457; 
June 2010 (Nunn-McCurdy): 2,457. 

Cost estimates (then-year dollars in billions): 

Development; 
October 2001 (system development start): $34.4; 
December 2003 (replan): $44.8; 
March 2007 (approved baseline): $44.8; 
April 2010 (initial program restructure): $50.2; 
June 2010 (Nunn-McCurdy): $51.8. 

Procurement; 
October 2001 (system development start): $196.6; 
December 2003 (replan): $199.8; 
March 2007 (approved baseline): $231.7; 
April 2010 (initial program restructure): $277.5; 
June 2010 (Nunn-McCurdy): $325.1. 

Military construction; 
October 2001 (system development start): $2.0; 
December 2003 (replan): $0.2; 
March 2007 (approved baseline): $2.0; 
April 2010 (initial program restructure): $0.6; 
June 2010 (Nunn-McCurdy): $5.6. 

Total program acquisition; 
October 2001 (system development start): $233.0; 
December 2003 (replan): $244.8; 
March 2007 (approved baseline): $278.5; 
April 2010 (initial program restructure): $328.3; 
June 2010 (Nunn-McCurdy): $382.5. 

Unit cost estimates (then-year dollars in millions): 

Program acquisition; 
October 2001 (system development start): $81; 
December 2003 (replan): $100; 
March 2007 (approved baseline): $113; 
April 2010 (initial program restructure): $134; 
June 2010 (Nunn-McCurdy): $156. 

Average procurement; 
October 2001 (system development start): $69; 
December 2003 (replan): $82; 
March 2007 (approved baseline): $95; 
April 2010 (initial program restructure): $114; 
June 2010 (Nunn-McCurdy): $133. 

Estimated delivery and production dates: 

First operational aircraft delivery; 
October 2001 (system development start): 2008; 
December 2003 (replan): 2009; 
March 2007 (approved baseline): 2010; 
April 2010 (initial program restructure): 2010; 
June 2010 (Nunn-McCurdy): 2010. 

Initial operational capability; 
October 2001 (system development start): 2010-2012; 
December 2003 (replan): 2012-2013; 
March 2007 (approved baseline): 2012-2015; 
April 2010 (initial program restructure): 2012-2016; 
June 2010 (Nunn-McCurdy): TBD. 

Full-rate production; 
October 2001 (system development start): 2012; 
December 2003 (replan): 2013; 
March 2007 (approved baseline): 2013; 
April 2010 (initial program restructure): 2016; 
June 2010 (Nunn-McCurdy): 2016. 

Source: GAO analysis and DOD data. 

Note: Does not reflect cost and schedule changes from additional 
restructuring actions announced since June 2010. 

[End of table] 

[End of section] 

Appendix II: Prior GAO Reports on JSF and DOD Responses and Subsequent 
Actions: 

GAO report: 2001; GAO-02-39; 
Estimated development cost & length, unit cost[A]: $34.4 billion; 10 
years; $69 million; 
Key program event: Start of system development and demonstration 
approved; 
Primary GAO message: Critical technologies needed for key aircraft 
performance elements are not mature. Program should delay start of 
system development until critical technologies are mature to 
acceptable levels; 
DOD responses and actions: DOD did not delay start of system 
development and demonstration stating technologies were at acceptable 
maturity levels and will manage risks in development. 

GAO report: 2005; GAO-05-271; 
Estimated development cost & length, unit cost[A]: $44.8 billion; 12 
years; $82 million; 
Key program event: The program undergoes re-plan to address higher 
than expected design weight, which added $7 billion and 18 months to 
development schedule; 
Primary GAO message: We recommended that the program reduce risks and 
establish executable business case that is knowledge-based with an 
evolutionary acquisition strategy; 
DOD responses and actions: DOD partially concurred but does not adjust 
strategy, believing that their approach is balanced between cost, 
schedule and technical risk. 

GAO report: 2006; GAO-06-356; 
Estimated development cost & length, unit cost[A]: $45.7 billion; 12 
years; $86 million; 
Key program event: Program sets in motion plan to enter production in 
2007 shortly after first flight of the non-production representative 
aircraft; 
Primary GAO message: The program plans to enter production with less 
than 1 percent of testing complete. We recommend program delay 
investing in production until flight testing shows that JSF performs 
as expected; 
DOD responses and actions: DOD partially concurred but did not delay 
start of production because they believe the risk level was 
appropriate. 

GAO report: 2007; GAO-07-360; 
Estimated development cost & length, unit cost[A]: $44.5 billion; 12 
years; $104 million; 
Key program event: Congress reduced funding for first two low-rate 
production buys thereby slowing the ramp up of production; 
Primary GAO message: Progress is being made but concerns remained 
about undue overlap in testing and production. We recommend limits to 
annual production quantities to 24 a year until flying quantities are 
demonstrated; 
DOD responses and actions: DOD non-concurred and felt that the program 
had an acceptable level of concurrency and an appropriate acquisition 
strategy. 

GAO report: 2008; GAO-08-388; 
Estimated development cost & length, unit cost[A]: $44.2 billion; 12 
years; $104 million; 
Key program event: DOD implemented a Mid-Course Risk Reduction Plan to 
replenish management reserves from about $400 million to about $1 
billion by reducing test resources; 
Primary GAO message: We believe new plan actually increases risks and 
DOD should revise the plan to address concerns about testing, use of 
management reserves, and manufacturing. We determine that the cost 
estimate is not reliable and that a new cost estimate and schedule 
risk assessment is needed; 
DOD responses and actions: DOD did not revise risk plan nor restore 
testing resources, stating that they will monitor the new plan and 
adjust it if necessary. Consistent with a report recommendation, a new 
cost estimate was eventually prepared, but DOD did not do a risk and 
uncertainty analysis that we felt was important to provide a range 
estimate of potential outcomes. 

GAO report: 2009; GAO-09-303; 
Estimated development cost & length, unit cost[A]: $44.4 billion; 13 
years; $104 million; 
Key program event: The program increased the cost estimate and adds a 
year to development but accelerated the production ramp up. 
Independent DOD cost estimate (JET I) projects even higher costs and 
further delays; 
Primary GAO message: Because of development problems, we stated that 
moving forward with an accelerated procurement plan and use of cost 
reimbursement contracts is very risky. We recommended the program 
report on the risks and mitigation strategy for this approach; 
DOD responses and actions: DOD agreed to report its contracting 
strategy and plans to Congress. In response to our report 
recommendation, DOD subsequently agreed to do a schedule risk 
analysis, but still had not done so as of February 2011. In February 
2010, the department announced a major restructuring of the JSF 
program, including reduced procurement and a planned move to fixed- 
price contracts. 

GAO report: 2010; GAO-10-382; 
Estimated development cost & length, unit cost[A]: $49.3 billion; 15 
years; $112 million; 
Key program event: The program was restructured to reflect findings of 
recent independent cost team (JET II) and independent manufacturing 
review team. As a result, development funds increased, test aircraft 
were added, the schedule was extended, and the early production rate 
decreased; 
Primary GAO message: Because of additional costs and schedule delays 
the program's ability to meet warfighter requirements on time is at 
risk. We recommend the program complete a full comprehensive cost 
estimate and assess warfighter and IOC requirements. We suggest that 
Congress require DOD to prepare a "system maturity matrix" - a tool 
for tying annual procurement requests to demonstrated progress; 
DOD responses and actions: DOD continued restructuring actions and 
announced plans to increase test resources and lower the production 
rate. Independent review teams evaluated aircraft and engine 
manufacturing processes. As we projected in this report, cost 
increases later resulted in a Nunn-McCurdy breach. Military services 
are currently reviewing capability requirements as we recommended. The 
department and Congress are working on a "system maturity matrix" tool 
to improve oversight and inform budget deliberations. 

Source: DOD data and GAO analysis. 

[A] Average procurement unit cost. 

[End of table] 

[End of section] 

Appendix III: System Development Contracts Target Price Changes: 

Projected development costs for the air system and primary engine 
comprise nearly 80 percent of total system development funding 
requirements. Both contracts have experienced significant price 
increases since contract awards--79 percent and 69 percent 
respectively. Figures 6 and 7 depict the price histories for these 
contracts and the reasons behind major price increases. 

Figure 6: JSF Air System Development Contract Target Price Increases: 

[Refer to PDF for image: line graph] 

Date: October 2001; 
Contract Target Price: $19 billion. 

Date: December 2003; 
Contract Target Price: $19.7 billion. 

[STOVL weight redesign] 

Date: December 2005; 
Contract Target Price: $25.7 billion. 

Date: December 2007; 
Contract Target Price: $25.9 billion. 

[Aircraft development delays and flight test extension] 

Date: December 2009; 
Contract Target Price: $27.5 billion. 

[Nunn-McCurdy restructure] 

Date: February 2011; 
Contract Target Price: $33.9 billion. 

Source: GAO analysis of DOD data. 

Note: The February 2011 cost is not the contract target price, but the 
latest government estimate from the fiscal year 2012 defense budget 
request. 

[End of figure] 

Figure 7: Primary Engine Development Contract Target Price Increases: 

[Refer to PDF for image: line graph] 

Date: October 2001; 
Contract Target Price: $4.8 billion. 

Date: December 2003; 
Contract Target Price: $4.8 billion. 

[Schedule extension due to STOVL redesign and revised thrust 
specification] 

Date: December 2005; 
Contract Target Price: $5.8 billion. 

Date: December 2007; 
Contract Target Price: $5.9 billion. 

[Development delays and engine blade issues] 

Date: December 2009; 
Contract Target Price: $6.7 billion. 

[Nunn-McCurdy restructure] 

Date: February 2011; 
Contract Target Price: $8.2 billion. 

Source: GAO analysis of DOD data. 

Note: The February 2011 cost is not the contract target price, but the 
latest government estimate from the fiscal year 2012 defense budget 
request. 

[End of section] 

Related GAO Products: 

Joint Strike Fighter: Restructuring Places Program on Firmer Footing, 
but Progress Still Lags. [hyperlink, 
http://www.gao.gov/products/GAO-11-325]. Washington, D.C.: April 7, 
2011. 

Joint Strike Fighter: Restructuring Should Improve Outcomes, but 
Progress Is Still Lagging Overall. [hyperlink, 
http://www.gao.gov/products/GAO-11-450T]. Washington, D.C.: March 15, 
2011. 

Tactical Aircraft: Air Force Fighter Force Structure Reports Generally 
Addressed Congressional Mandates, but Reflected Dated Plans and 
Guidance, and Limited Analyses. [hyperlink, 
http://www.gao.gov/products/GAO-11-323R]. Washington, D.C.: February 
24, 2011. 

Defense Management: DOD Needs to Monitor and Assess Corrective Actions 
Resulting from Its Corrosion Study of the F-35 Joint Strike Fighter. 
[hyperlink, http://www.gao.gov/products/GAO-11-171R]. Washington D.C.: 
December 16, 2010. 

Joint Strike Fighter: Assessment of DOD's Funding Projection for the 
F136 Alternate Engine. [hyperlink, 
http://www.gao.gov/products/GAO-10-1020R]. Washington, D.C.: September 
15, 2010. 

Tactical Aircraft: DOD's Ability to Meet Future Requirements is 
Uncertain, with Key Analyses Needed to Inform Upcoming Investment 
Decisions. [hyperlink, http://www.gao.gov/products/GAO-10-789]. 
Washington, D.C.: July 29, 2010. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-10-388SP]. Washington, 
D.C.: March 30, 2010. 

Joint Strike Fighter: Significant Challenges and Decisions Ahead. 
[hyperlink, http://www.gao.gov/products/GAO-10-478T]. Washington, 
D.C.: March 24, 2010. 

Joint Strike Fighter: Additional Costs and Delays Risk Not Meeting 
Warfighter Requirements on Time. [hyperlink, 
http://www.gao.gov/products/GAO-10-382]. Washington, D.C.: March 19, 
2010. 

Joint Strike Fighter: Significant Challenges Remain as DOD 
Restructures Program. [hyperlink, 
http://www.gao.gov/products/GAO-10-520T]. Washington, D.C.: March 11, 
2010. 

Joint Strike Fighter: Strong Risk Management Essential as Program 
Enters Most Challenging Phase. [hyperlink, 
http://www.gao.gov/products/GAO-09-711T]. Washington, D.C.: May 20, 
2009. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-09-326SP]. Washington, 
D.C.: March 30, 2009. 

Joint Strike Fighter: Accelerating Procurement before Completing 
Development Increases the Government's Financial Risk. [hyperlink, 
http://www.gao.gov/products/GAO-09-303]. Washington D.C.: March 12, 
2009. 

Defense Acquisitions: Better Weapon Program Outcomes Require 
Discipline, Accountability, and Fundamental Changes in the Acquisition 
Environment. [hyperlink, http://www.gao.gov/products/GAO-08-782T]. 
Washington, D.C.: June 3, 2008. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-08-467SP]. Washington, 
D.C.: March 31, 2008. 

Joint Strike Fighter: Impact of Recent Decisions on Program Risks. 
[hyperlink, http://www.gao.gov/products/GAO-08-569T]. Washington, 
D.C.: March 11, 2008. 

Joint Strike Fighter: Recent Decisions by DOD Add to Program Risks. 
[hyperlink, http://www.gao.gov/products/GAO-08-388]. Washington, D.C.: 
March 11, 2008. 

Tactical Aircraft: DOD Needs a Joint and Integrated Investment 
Strategy. [hyperlink, http://www.gao.gov/products/GAO-07-415]. 
Washington, D.C.: April 2, 2007. 

Defense Acquisitions: Assessments of Selected Weapon Programs. 
[hyperlink, http://www.gao.gov/products/GAO-07-406SP]. Washington, 
D.C.: March 30, 2007. 

Defense Acquisitions: Analysis of Costs for the Joint Strike Fighter 
Engine Program. [hyperlink, http://www.gao.gov/products/GAO-07-656T]. 
Washington, D.C.: March 22, 2007. 

Joint Strike Fighter: Progress Made and Challenges Remain. [hyperlink, 
http://www.gao.gov/products/GAO-07-360]. Washington, D.C.: March 15, 
2007. 

Tactical Aircraft: DOD's Cancellation of the Joint Strike Fighter 
Alternate Engine Program Was Not Based on a Comprehensive Analysis. 
[hyperlink, http://www.gao.gov/products/GAO-06-717R]. Washington, 
D.C.: May 22, 2006. 

Defense Acquisitions: Major Weapon Systems Continue to Experience Cost 
and Schedule Problems under DOD's Revised Policy. [hyperlink, 
http://www.gao.gov/products/GAO-06-368]. Washington, D.C.: April 13, 
2006. 

Defense Acquisitions: Actions Needed to Get Better Results on Weapons 
Systems Investments. [hyperlink, 
http://www.gao.gov/products/GAO-06-585T]. Washington, D.C.: April 5, 
2006. 

Tactical Aircraft: Recapitalization Goals Are Not Supported by 
Knowledge-Based F-22A and JSF Business Cases. [hyperlink, 
http://www.gao.gov/products/GAO-06-487T]. Washington, D.C.: March 16, 
2006. 

Joint Strike Fighter: DOD Plans to Enter Production before Testing 
Demonstrates Acceptable Performance. [hyperlink, 
http://www.gao.gov/products/GAO-06-356]. Washington, D.C.: March 15, 
2006. 

Joint Strike Fighter: Management of the Technology Transfer Process. 
[hyperlink, http://www.gao.gov/products/GAO-06-364]. Washington, D.C.: 
March 14, 2006. 

Tactical Aircraft: F/A-22 and JSF Acquisition Plans and Implications 
for Tactical Aircraft Modernization. [hyperlink, 
http://www.gao.gov/products/GAO-05-519T]. Washington, D.C: April 6, 
2005. 

Tactical Aircraft: Opportunity to Reduce Risks in the Joint Strike 
Fighter Program with Different Acquisition Strategy. [hyperlink, 
http://www.gao.gov/products/GAO-05-271]. Washington, D.C.: March 15, 
2005. 

[End of section] 

Footnotes: 

[1] Commonly referred to as Nunn-McCurdy,10 U.S.C. § 2433 establishes 
the requirement for DOD to submit unit cost reports on major defense 
acquisition programs or designated major subprograms. Two measures are 
tracked against the current and original baseline estimates for a 
program: procurement unit cost (total procurement funds divided by the 
quantity of systems procured) and program acquisition unit cost (total 
funds for development, procurement, and system-specific military 
construction divided by the quantity of systems procured). If a 
program's procurement unit cost or acquisition unit cost increases by 
at least 25 percent over the current baseline estimate or at least 50 
percent over the original baseline estimate, it constitutes a breach 
of the critical cost growth threshold. When a program experiences a 
Nunn-McCurdy breach of the critical cost growth threshold, DOD is 
required to take a number of steps, including reassessing the program 
and submitting a certification to Congress in order to continue the 
program, in accordance with 10 U.S.C. § 2433a. 

[2] GAO, Joint Strike Fighter: Restructuring Places Program on Firmer 
Footing, but Progress Still Lags, [hyperlink, 
http://www.gao.gov/products/GAO-11-325] (Washington, D.C.: Apr. 7, 
2011). Refer to the related products section for a complete list of 
GAO reports and testimonies. 

[3] Pub. L. No. 111-84, § 244 (2009). 

[4] Flight test points are specific, quantifiable objectives in flight 
plans that are needed to verify aircraft design and performance. 

[5] Out of station work occurs when manufacturing steps are not 
completed at its designated work station and must be finished 
elsewhere later in production. This is highly inefficient, increasing 
labor hours, causing delays, and sometimes quality problems. 

[6] According to program officials completion of a test point means 
that the test point has been flown and that flight engineers ruled 
that the point has met the need. Further analysis may be necessary for 
the test point to be closed out. 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: