This is the accessible text file for GAO report number GAO-09-705T 
entitled 'Space Acquisitions: DOD Faces Substantial Challenges in 
Developing New Space Systems' which was released on May 20, 2009. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on Strategic Forces, Committee on Armed 
Services, U.S. Senate: 

United States Government Accountability Office: 
GAO: 

For Release on Delivery: 
Expected at 2:00 p.m. EDT:
Wednesday, May 20, 2009: 

Space Acquisitions: 

DOD Faces Substantial Challenges in Developing New Space Systems: 
Statement of Cristina T. Chaplain, Director: Acquisition and Sourcing 
Management: 

GAO-09-705T: 

GAO Highlights: 

Highlights of GAO-09-705T, a testimony before the Subcommittee on 
Strategic Forces, Committee on Armed Services, U.S. Senate. 

Why GAO Did This Study: 

Despite a growing investment in space, the majority of large-scale 
acquisition programs in the Department of Defense’s (DOD) space 
portfolio have experienced problems during the past two decades that 
have driven up cost and schedules and increased technical risks. The 
cost resulting from acquisition problems along with the ambitious 
nature of space programs has resulted in cancellations of programs that 
were expected to require investments of tens of billions of dollars. 
Along with the cost increases, many programs are experiencing 
significant schedule delays—at least 7 years—resulting in potential 
capability gaps in areas such as positioning, navigation, and timing; 
missile warning; and weather monitoring. 

This testimony focuses on: 

* the condition of space acquisitions, causal factors, and; 
* recommendations for better positioning programs and industry for 
success. 

In preparing this testimony, GAO relied on its body of work in space 
and other programs, including previously issued GAO reports on 
assessments of individual space programs, common problems affecting 
space system acquisitions, and DOD’s acquisition policies. 

What GAO Found: 

Estimated costs for major space acquisition programs have increased by 
about $10.9 billion from initial estimates for fiscal years 2008 
through 2013. As seen in the figure below, in several cases, DOD has 
had to cut back on quantity and capability in the face of escalating 
costs. 

Figure: Total Cost Differences from Program Start to Most Recent 
Estimates (Fiscal year 2009 dollars in millions): 

[Refer to PDF for image: vertical bar graph] 

Program and start date: SBIRS, 1996; 
Initial estimate: $4,427; 
Most recent estimate: $12,210 (one less satellite and deferred 
requirements). 

Program and start date: GPS II, 2000; 
Initial estimate: $6,005; 
Most recent estimate: $7,154. 

Program and start date: WGS, 2000; 
Initial estimate: $1,152; 
Most recent estimate: $2,073 (two additional satellites). 

Program and start date: AEHF, 2001; 
Initial estimate: $6,153; 
Most recent estimate: $10,304 (one less satellite). 

Program and start date: NPOESS, 2002; 
Initial estimate: $6,455; 
Most recent estimate: $10,913 (fewer key sensors and two fewer 
satellites). 

Program and start date: MUOS, 2004; 
Initial estimate: $6,492; 
Most recent estimate: $6,411. 

Program and start date: GPS IIIA, 2008; 
Initial estimate: $3,807; 
Most recent estimate: $3,807. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

Several causes behind the cost growth and related problems consistently 
stand out. First, DOD starts more weapon programs than it can afford, 
creating competition for funding that, in part, encourages low cost 
estimating and optimistic scheduling. Second, DOD has tended to start 
its space programs before it has the assurance that the capabilities it 
is pursuing can be achieved within available resources. 

GAO and others have identified a number of pressures associated with 
the contractors that develop space systems for the government that have 
hampered the acquisition process, including ambitious requirements and 
shortages of technical expertise in the workforce. Although DOD has 
taken a number of actions to address the problems on which GAO has 
reported, additional leadership and support are still needed to ensure 
that reforms that DOD has begun will take hold. 

View [hyperlink, http://www.gao.gov/products/GAO-09-705T] or key 
components. For more information, contact Cristina T. Chaplain, 202-512-
4841, chaplainc@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

I am pleased to be here today to discuss the Department of Defense's 
(DOD) space acquisitions. The topic of today's hearing is critically 
important. Despite a growing investment in space, the majority of large-
scale acquisition programs in DOD's space portfolio have experienced 
problems during the past two decades that have driven up cost and 
schedules and increased technical risks. The cost resulting from 
acquisition problems along with the ambitious nature of space programs 
has resulted in cancellations of programs that were expected to require 
investments of tens of billions of dollars, including the recently 
proposed cancellation of the Transformational Satellite Communications 
System (TSAT). Moreover, along with the cost increases, many programs 
are experiencing significant schedule delays--at least 7 years--
resulting in potential capability gaps in areas such as positioning, 
navigation, and timing; missile warning; and weather monitoring. 

My testimony today will focus on the condition of space acquisitions, 
causal factors, and recommendations for better positioning programs for 
success. Many of these have been echoed by the Allard Commission, 
[Footnote 1] which studied space issues in response to a requirement in 
the John Warner National Defense Authorization Act for Fiscal Year 
2007, and by a study by the House Permanent Select Committee on 
Intelligence (HPSCI),[Footnote 2] among other groups. The two studies 
highlighted concerns about diffuse leadership for military and 
intelligence space efforts and declining numbers of space engineering 
and technical professionals. Members of the Allard Commission were 
unanimous in their conviction that without significant improvements in 
the leadership and management of national security space programs, U.S. 
space preeminence will erode "to the extent that space ceases to 
provide a competitive national security advantage." 

Space Acquisition Problems Persist: 

Figure 1 compares original cost estimates and current cost estimates 
for the broader portfolio of major space acquisitions for fiscal years 
2008 through 2013. The wider the gap between original and current 
estimates, the fewer dollars DOD has available to invest in new 
programs. As shown in the figure, estimated costs for the major space 
acquisition programs have increased by about $10.9 billion from initial 
estimates for fiscal years 2008 through 2013. The declining investment 
in the later years is the result of the Evolved Expendable Launch 
Vehicle (EELV) program's no longer being considered a major acquisition 
program and the cancellation and proposed cancellation of two 
development efforts that would have significantly increased DOD's major 
space acquisition investment. 

Figure 1: Comparison between Original Cost Estimates and Current Cost 
Estimates for Selected Major Space Acquisition Programs for Fiscal 
Years 2008 through 2013 (Fiscal year 2009 dollars in millions): 

[Refer to PDF for image: multiple line graph] 

Fiscal year: 2008; 
Original cost estimate:	$2832; 
Current cost estimate: $4089. 

Fiscal year: 2009; 
Original cost estimate:	$2617; 
Current cost estimate: $4782. 

Fiscal year: 2010; 
Original cost estimate:	$1888; 
Current cost estimate: $5069. 

Fiscal year: 2011; 
Original cost estimate:	$1728; 
Current cost estimate: $3514. 

Fiscal year: 2012; 
Original cost estimate:	$1499; 
Current cost estimate: $2847. 

Fiscal year: 2013; 
Original cost estimate:	$831; 
Current cost estimate: $2074. 

Source: GAO analysis of DOD data. 

Note: The acquisition programs include Advanced Extremely High 
Frequency, Global Broadcast Service, Global Positioning System II, 
Global Positioning System IIIA, Mobile User Objective System, National 
Polar-orbiting Operational Environmental Satellite System, Space Based 
Infrared System, and Wideband Global SATCOM. 

[End of figure] 

Figures 2 and 3 reflect differences in total life-cycle and unit costs 
for satellites from the time the programs officially began to their 
most recent cost estimate. As figure 2 notes, in several cases, DOD has 
had to cut back on quantity and capability in the face of escalating 
costs. For example, two satellites and four instruments were deleted 
from National Polar-orbiting Operational Environmental Satellite System 
(NPOESS) and four sensors are expected to have fewer capabilities. This 
will reduce some planned capabilities for NPOESS as well as planned 
coverage. 

Figure 2: Differences in Total Life-Cycle Program Costs from Program 
Start and Most Recent Estimates (Fiscal year 2009 dollars in millions): 

[Refer to PDF for image: vertical bar graph] 

Program and start date: SBIRS, 1996; 
Initial estimate: $4,427; 
Most recent estimate: $12,210 (one less satellite and deferred 
requirements). 

Program and start date: GPS II, 2000; 
Initial estimate: $6,005; 
Most recent estimate: $7,154. 

Program and start date: WGS, 2000; 
Initial estimate: $1,152; 
Most recent estimate: $2,073 (two additional satellites). 

Program and start date: AEHF, 2001; 
Initial estimate: $6,153; 
Most recent estimate: $10,304 (one less satellite). 

Program and start date: NPOESS, 2002; 
Initial estimate: $6,455; 
Most recent estimate: $10,913 (fewer key sensors and two fewer 
satellites). 

Program and start date: MUOS, 2004; 
Initial estimate: $6,492; 
Most recent estimate: $6,411. 

Program and start date: GPS IIIA, 2008; 
Initial estimate: $3,807; 
Most recent estimate: $3,807. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

Figure 3: Differences in Unit Costs from Program Start to Most Recent 
Estimates (Fiscal year 2009 dollars in millions): 

[Refer to PDF for image: vertical bar graph] 

Program and start date:	SBIRS, 1996; 
Initial unit cost: $885; 
Most recent unit cost: $3,052. 

Program and start date:	GPS II, 2000; 
Initial unit cost: $182; 
Most recent unit cost: $217. 

Program and start date:	WGS, 2000; 
Initial unit cost: $384; 
Most recent unit cost: $415. 

Program and start date:	AEHF, 2001; 
Initial unit cost: $1,231; 
Most recent unit cost: $2,576. 

Program and start date:	NPOESS, 2002; 
Initial unit cost: $1,076; 
Most recent unit cost: $2,728. 

Program and start date:	MUOS, 2004; 
Initial unit cost: $1,082; 
Most recent unit cost: $1,069. 

Program and start date:	GPS IIIA, 2008; 
Initial unit cost: $476; 
Most recent unit cost: $476. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

Figure 4 highlights the additional estimated months needed to complete 
programs. These additional months represent time not anticipated at the 
programs' start dates. Generally, the further schedules slip, the more 
DOD is at risk of not sustaining current capabilities. For this reason, 
DOD began a follow-on system effort, now known as Third Generation 
Infrared Surveillance, to run in parallel with the Space Based Infrared 
System (SBIRS) program. 

Figure 4: Differences in Total Number of Months to Initial Operational 
Capability (IOC) from Program Start and Most Recent Estimates: 
[Refer to PDF for image: vertical bar graph] 

Program and start date:	SBIRS, 1996; 
Initial estimate: 86 months; 
Most recent estimate: System IOC no longer defined, but program is at 
least 7 years behind its original delivery of the first satellite. 

Program and start date:	GPS II, 2000; 
Initial estimate: Not applicable because of program not estimating an 
IOC date, but program is almost 3 years behind its original schedule 
for launch of the first Block IIF satellite. 

Program and start date:	WGS, 2000; 
Initial estimate: 49 months; 
Most recent estimate: 98 months. 

Program and start date:	AEHF, 2001; 
Initial estimate: 82 months; 
Most recent estimate: 141 months. 

Program and start date:	NPOESS, 2002; 
Initial estimate: 107 months; 
Most recent estimate: 128 months. 

Program and start date:	MUOS, 2004; 
Initial estimate: 66 months; 
Most recent estimate: 77 months. 

Program and start date:	GPS IIIA, 2008; 
Initial estimate: Not applicable because of the program not estimating 
an IOC date. 

Source: GAO analysis of DOD data. 

Legend: SBIRS = Space Based Infrared System, GPS = Global Positioning 
System, WGS = Wideband Global SATCOM, AEHF = Advanced Extremely High 
Frequency, NPOESS = National Polar-orbiting Operational Environmental 
Satellite System, and MUOS = Mobile User Objective System. 

[End of figure] 

This fiscal year, DOD launched the second Wideband Global SATCOM (WGS) 
satellite. WGS had previously been experiencing technical and other 
problems, including improperly installed fasteners and data 
transmission errors. When DOD finally resolved these issues, it 
significantly advanced capability available to warfighters. 
Additionally, the EELV program had its 23rd consecutive successful 
operational launch in April. However, other major space programs have 
had setbacks. For example: 

* In September 2008, the Air Force reported a Nunn-McCurdy unit cost 
breach of the critical cost growth threshold[Footnote 3] for the 
Advanced Extremely High Frequency (AEHF) communications satellite 
because of cost growth brought on by technical issues, schedule delays, 
and increased costs for the procurement of a fourth AEHF satellite. The 
launch of the first satellite has slipped further by almost 2 years 
from November 2008 to as late as September 2010. Further, the program 
office estimates that the fourth AEHF satellite could cost more than 
twice the third satellite because some components that are no longer 
manufactured will have to be replaced and production will have to be 
restarted after a 4-year gap. Because of these delays, initial 
operational capability has slipped 3 years--from 2010 to 2013. 

* The Mobile User Objective System (MUOS) communications satellite 
estimates an 11-month delay--from March 2010 to February 2011--in the 
delivery of on-orbit capability from the first satellite. Further, 
contractor costs for the space segment have increased about 48 percent 
because of the additional labor required to address issues related to 
satellite design complexity, satellite weight, and satellite component 
test anomalies and associated rework. Despite the contractor's cost 
increases, the program has been able to remain within its baseline 
program cost estimate. 

* The first Global Positioning System (GPS) IIF satellite is now 
expected to be delayed almost 3 years from its original launch date to 
November 2009. Also, the cost of GPS IIF is now expected to be about 
$1.6 billion--about $870 million over the original cost estimate of 
$729 million. (This approximately 119 percent cost increase is not that 
noticeable in figures 2 and 3 because the GPS II modernization program 
includes the development and procurement of 33 satellites, only 12 of 
which are IIF satellites.) The Air Force has had difficulty in the past 
building GPS satellites within cost and schedule goals because of 
significant technical problems--which still threaten its delivery 
schedule--and challenges it faced with a different contractor for the 
IIF program, which did not possess the same expertise as the previous 
GPS contractor. Further, while the Air Force is structuring the new GPS 
IIIA program to prevent mistakes made on the IIF program, the Air Force 
is aiming to deploy the GPS IIIA satellites 3 years faster than the IIF 
satellites. We believe the IIIA schedule is optimistic given the 
program's late start, past trends in space acquisitions, and challenges 
facing the new contractor. 

* Total program cost for the SBIRS program is estimated around $12.2 
billion, an increase of $7.5 billion over the original program's cost, 
which included 5 geosynchronous earth orbit (GEO) satellites. The first 
GEO satellite has been delayed at least 7 years in part because of poor 
oversight, technical complexities, and rework. Although the program 
office set December 2009 as the new launch goal for the satellite, it 
is currently assessing the satellite launch schedule and expects to 
have a new plan in place by June 2009. Subsequent GEO satellites have 
also slipped as a result of flight software design issues. 

* The NPOESS program has experienced problems with replenishing the 
current constellation of aging weather satellites and was restructured 
in July 2007 in response to a Nunn-McCurdy unit cost breach of the 
critical cost-growth threshold. The program was originally estimated to 
cost about $6.5 billion for six satellites from 1995 through 2018. The 
restructured program called for reducing the number of satellites from 
six to four and included an overall increase in program costs, delays 
in satellite launches, and deletions or replacements of satellite 
sensors. Although the number of satellites has been reduced, total 
costs have increased by almost 108 percent since program start. 
Specifically, the current estimated life-cycle cost of the restructured 
program is now about $13.5 billion for four satellites through 2026. 
This amount is higher than what is reflected in figure 2 as it 
represents the most recent GAO estimate as opposed to the DOD estimates 
used in the figure. We reported last year that poor workmanship and 
testing delays caused an 8-month slip in the delivery of a complex 
imaging sensor. This late delivery caused a delay in the expected 
launch date of a demonstration satellite, moving it from late September 
2009 to early January 2011. 

This year it is also becoming more apparent that space acquisition 
problems are leading to potential gaps in the delivery of critical 
capabilities. For example, DOD faces a potential gap in protected 
military communications caused by delays in the AEHF program and the 
proposed cancellation of the TSAT program, which itself posed risks in 
schedule delays because of TSAT's complexity and funding cuts designed 
to ensure technology objectives were achievable. DOD faces a potential 
gap in ultra high frequency (UHF) communications capability caused by 
the unexpected failures of two satellites already in orbit and the 
delays resulting from the MUOS program. DOD also faces potential gaps 
or decreases in positioning, navigation and timing capabilities because 
of late delivery of the GPS IIF satellites and the late start of the 
GPS IIIA program. There are also concerns about potential gaps in 
missile warning and weather monitoring capabilities because of delays 
in SBIRS and NPOESS. 

Addressing gaps in any one of these areas is not a simple matter. While 
there may be opportunities to build less complex "gap filler" 
satellites, for example, these still require time and money that may 
not be readily available because of commitments to the longer-term 
programs. There may also be opportunities to continue production of 
"older" generation satellites, but such efforts also require time and 
money that may not be readily available and may face other challenges 
such as restarting production lines and addressing issues related to 
obsolete parts and materials. Further, satellites on orbit can be made 
to last longer by turning power off at certain points in time, but this 
may also present unacceptable trade-offs in capability. 

Underlying Reasons for Cost and Schedule Growth: 

Our past work has identified a number of causes behind the cost growth 
and related problems, but several consistently stand out. First, on a 
broad scale, DOD starts more weapon programs than it can afford, 
creating a competition for funding that encourages low cost estimating, 
optimistic scheduling, overpromising, suppressing bad news, and, for 
space programs, forsaking the opportunity to identify and assess 
potentially more executable alternatives. Programs focus on advocacy at 
the expense of realism and sound management. Invariably, with too many 
programs in its portfolio, DOD is forced to continually shift funds to 
and from programs--particularly as programs experience problems that 
require additional time and money to address. Such shifts, in turn, 
have had costly, reverberating effects. 

Second, DOD has tended to start its space programs too early, that is, 
before it has the assurance that the capabilities it is pursuing can be 
achieved within available resources and time constraints. This tendency 
is caused largely by the funding process, since acquisition programs 
attract more dollars than efforts concentrating solely on proving 
technologies. Nevertheless, when DOD chooses to extend technology 
invention into acquisition, programs experience technical problems that 
require large amounts of time and money to fix. Moreover, when this 
approach is followed, cost estimators are not well positioned to 
develop accurate cost estimates because there are too many unknowns. 
Put more simply, there is no way to accurately estimate how long it 
would take to design, develop, and build a satellite system when 
critical technologies planned for that system are still in relatively 
early stages of discovery and invention. 

While our work has consistently found that maturing technologies before 
a program's start is a critical enabler of success, it is important to 
keep in mind that this is not the only solution. Both the TSAT and the 
Space Radar development efforts, for example, were seeking to mature 
critical technologies before program start, but they faced other risks 
related to the systems' complexity, affordability, and other 
development challenges. Ultimately, Space Radar was canceled, and DOD 
has proposed the cancellation of TSAT. Last year, we cited the MUOS 
program's attempts to mature critical technologies before the program's 
start as a best practice, but the program has since encountered 
technical problems related to design issues and test anomalies. 

Third, programs have historically attempted to satisfy all requirements 
in a single step, regardless of the design challenge or the maturity of 
the technologies necessary to achieve the full capability. DOD has 
preferred to make fewer but heavier, larger, and more complex 
satellites that perform a multitude of missions rather than larger 
constellations of smaller, less complex satellites that gradually 
increase in sophistication. This has stretched technology challenges 
beyond current capabilities in some cases and vastly increased the 
complexities related to software. Programs also seek to maximize 
capability because it is expensive to launch satellites. A launch using 
a medium-or intermediate-lift EELV, for example, would cost roughly $65 
million. 

Fourth, several of today's high-risk space programs began in the late 
1990s, when DOD structured contracts in a way that reduced government 
oversight and shifted key decision-making responsibility onto 
contractors. This approach--known as Total System Performance 
Responsibility, or TSPR--was intended to facilitate acquisition reform 
and enable DOD to streamline its acquisition process and leverage 
innovation and management expertise from the private sector. 
Specifically, TSPR gave a contractor total responsibility for the 
integration of an entire weapon system and for meeting DOD's 
requirements. However, because this reform made the contractor 
responsible for day-to-day program management, DOD did not require 
formal deliverable documents--such as earned value management reports-
-to assess the status and performance of the contractor. The resulting 
erosion of DOD's capability to lead and manage the space acquisition 
process magnified problems related to requirements creep and poor 
contractor performance. Further, the reduction in government oversight 
and involvement led to major reductions in various government 
capabilities, including cost-estimating and systems-engineering staff. 
The loss of cost-estimating and systems-engineering staff in turn led 
to a lack of technical data needed to develop sound cost estimates. 

Actions Needed to Address Space and Weapon Acquisition Problems: 

Over the past decade, we have identified best practices that DOD space 
programs can benefit from. DOD has taken a number of actions to address 
the problems on which we have reported. These include initiatives at 
the department level that will affect its major weapons programs, as 
well as changes in course within specific Air Force programs. Although 
these actions are a step in the right direction, additional leadership 
and support are still needed to ensure that reforms that DOD has begun 
will take hold. 

Our work--which is largely based on best practices in the commercial 
sector--has recommended numerous actions that can be taken to address 
the problems we identified. Generally, we have recommended that DOD 
separate technology discovery from acquisition, follow an incremental 
path toward meeting user needs, match resources and requirements at 
program's start, and use quantifiable data and demonstrable knowledge 
to make decisions to move to next phases. We have also identified 
practices related to cost estimating, program manager tenure, quality 
assurance, technology transition, and an array of other aspects of 
acquisition-program management that could benefit space programs. Table 
1 highlights these practices. 

Table 1: Actions Needed to Address Space and Weapon Acquisition 
Problems: 

Before undertaking new programs: 

* Prioritize investments so that projects can be fully funded and it is 
clear where projects stand in relation to the overall portfolio. 

* Follow an evolutionary path toward meeting mission needs rather than 
attempting to satisfy all needs in a single step. 

* Match requirements to resources--that is, time, money, technology, 
and people--before undertaking a new development effort. 

* Research and define requirements before programs are started and 
limit changes after they are started. 

* Ensure that cost estimates are complete, accurate, and updated 
regularly. 

* Commit to fully fund projects before they begin. 

* Ensure that critical technologies are proven to work as intended 
before programs are started. 

* Assign more ambitious technology development efforts to research 
departments until they are ready to be added to future generations 
(increments) of a product. 

* Use systems engineering to close gaps between resources and 
requirements before launching the development process. 

During program development: 

* Use quantifiable data and demonstrable knowledge to make go/no-go 
decisions, covering critical facets of the program such as cost, 
schedule, technology readiness, design readiness, production readiness, 
and relationships with suppliers. 

* Do not allow development to proceed until certain thresholds are met--
for example, a high proportion of engineering drawings completed or 
production processes under statistical control. 

* Empower program managers to make decisions on the direction of the 
program and to resolve problems and implement solutions. 

* Hold program managers accountable for their choices. 

* Require program managers to stay with a project to its end. 

* Hold suppliers accountable to deliver high-quality parts for their 
products through such activities as regular supplier audits and 
performance evaluations of quality and delivery, among other things. 

* Encourage program managers to share bad news, and encourage 
collaboration and communication. 

Source: GAO. 

[End of table] 

DOD is attempting to implement some of these practices for its major 
weapon programs. For example, as part of its strategy for enhancing the 
roles of program managers in major weapon system acquisitions, the 
department has established a policy that requires formal agreements 
among program managers, their acquisition executives, and the user 
community that set forth common program goals. These agreements are 
intended to be binding and to detail the progress a program is expected 
to make during the year and the resources the program will be provided 
to reach these goals. DOD is also requiring program managers to sign 
tenure agreements so that their tenure will correspond to the next 
major milestone review closest to 4 years. Over the past few years, DOD 
has also been testing portfolio management approaches in selected 
capability areas--command and control, net-centric operations, 
battlespace awareness, and logistics--to facilitate more strategic 
choices for resource allocation across programs. 

Within the space community, cost estimators from industry and agencies 
involved in space have been working together to improve the accuracy 
and quality of their estimates. In addition, on specific programs, 
actions have been taken to prevent mistakes made in the past. For 
example, on the GPS IIIA program, the Air Force is using an incremental 
development approach, where it will gradually meet the needs of its 
users, use military standards for satellite quality, conduct multiple 
design reviews, exercise more government oversight and interaction with 
the contractor and spend more time at the contractor's site, and use an 
improved risk management process. On the SBIRS program, the Air Force 
acted to strengthen relationships between the government and the SBIRS 
contractor team, and to implement more effective software development 
practices as it sought to address problems related to its flight 
software system. Correspondingly, DOD's Office of the Under Secretary 
of Defense for Acquisition, Technology, and Logistics is asking space 
programs to take specific measures to better hold contractors 
accountable through linking award and incentive fees to program 
milestones. DOD interim space guidance also asks space programs to make 
independent technology readiness assessments at particular points in 
the acquisition process and to hold requirements stable. 

Furthermore, the Air Force, U.S. Strategic Command, and other key 
organizations have made progress in implementing the Operationally 
Responsive Space (ORS) initiative. This initiative encompasses several 
separate endeavors with a goal to provide short-term tactical 
capabilities as well as identifying and implementing long-term 
technology and design solutions to reduce the cost and time of 
developing and delivering simpler satellites in greater numbers. ORS 
provides DOD with an opportunity to work outside the typical 
acquisition channels to more quickly and less expensively deliver these 
capabilities. In 2008, we found that DOD has made progress in putting a 
program management structure in place for ORS as well as executing ORS- 
related research and development efforts, which include development of 
low cost small satellites, common design techniques, and common 
interfaces. 

Legislation introduced in recent years has also focused on improving 
space and weapon acquisitions. In March, the Senate Committee on Armed 
Services introduced an acquisition reform bill which contains 
provisions that could significantly improve DOD's management of space 
programs. For instance, the bill focuses on various measures, including 
increasing emphasis on systems engineering and developmental testing, 
instituting earlier preliminary design reviews and strengthening 
independent cost estimates and technology readiness assessments. Taken 
together, these measures could instill more discipline in the front end 
of the acquisition process when it is critical for programs to gain 
knowledge. The bill also requires greater involvement by the combatant 
commands in determining requirements and requiring greater consultation 
among the requirements, budget, and acquisition processes. In addition, 
several of the bill's sections, as currently drafted, would require in 
law what DOD policy already encourages, but it is not being implemented 
consistently in weapon programs. In April, the House Committee on Armed 
Services introduced a bill to similarly reform DOD's system for 
acquiring weapons by providing for, among other things, oversight early 
in product development and for appointment of independent officials to 
review acquisition programs. Both bills are moving forward in the 
Senate and House. 

The actions that the Air Force and Office of the Secretary of Defense 
have been taking to address acquisition problems are good steps. 
However, there are still more significant changes to processes, 
policies, and support needed to ensure reforms can take hold. With 
requirements, resource allocation, and acquisition processes led by 
different organizations, it is difficult to hold any one person or 
organization accountable for saying no to a proposed program or for 
ensuring that the department's portfolio of programs is balanced. This 
makes it difficult for DOD to achieve a balanced mix of weapon systems 
that are affordable and feasible. For example, diffused leadership has 
been problematic with the GPS program in terms of DOD's ability to 
synchronize delivery of space, ground, and user assets. GPS has a 
separate budget, management, oversight, and leadership structures for 
the space, ground, and user equipment segments. Several recent studies 
have also concluded that there is a need to strengthen leadership for 
military and intelligence space efforts. The Allard Commission reported 
that responsibilities for military space and intelligence programs are 
scattered across the staffs of the DOD and the Intelligence Community 
and that it appears that "no one is in charge" of national-security 
space. The HPSCI expressed similar concerns in its report, focusing 
specifically on difficulties in bringing together decisions that would 
involve both the Director of National Intelligence and the Secretary of 
Defense. Prior studies, including those conducted by the Defense 
Science Board and the Commission to Assess United States National 
Security Space Management and Organization (Space Commission)[Footnote 
4] have identified similar problems, both for space as a whole and for 
specific programs. While these studies have made recommendations for 
strengthening leadership for space acquisitions, no major changes to 
the leadership structure have been made in recent years. In fact, an 
"executive agent" position within the Air Force that was designated in 
2001 in response to a Space Commission recommendation to provide 
leadership has not been filled since the last executive resigned in 
2007. 

In addition, more actions may be needed to address shortages of 
personnel in program offices for major space programs. We recently 
reported that personnel shortages at the EELV program office have 
occurred, particularly in highly specialized areas, such as avionics 
and launch vehicle groups. Program officials stated that 7 of 12 
positions in the engineering branch for the Atlas group were vacant. 
These engineers work on issues such as reviewing components responsible 
for navigation and control of the rocket. Moreover, only half of the 
government jobs in some key areas were projected to be filled. These 
and other shortages in the EELV program office heightened concerns 
about DOD's ability to use a cost-reimbursement contract acquisition 
strategy for EELV since that strategy requires greater government 
attention to the contractor's technical, cost, and schedule performance 
information. In previous reviews, we cited personnel shortages at 
program offices for TSAT as well as for cost estimators across space. 
While increased reliance on contractor employees has helped to address 
workforce shortages, it could ultimately create gaps in areas of 
expertise that could limit the government's ability to conduct 
oversight. 

Further, while actions are being undertaken to make more realistic cost 
estimates, programs are still producing schedule estimates that are 
optimistic while promising that they will not miss their schedule 
goals. The GPS IIIA program, for example, is asking the contractor to 
develop a larger satellite bus to accommodate the future GPS increments 
and to increase the power of a new military signal by a factor of ten, 
but the schedule is 3 years shorter than the one achieved so far on GPS 
IIF. We recognize that the GPS IIIA program has built a more solid 
foundation for success than the IIF program. This foundation offers the 
best course to deliver on time, but meeting an ambitious schedule goal 
should not be the Air Force's only measure for mitigating potential 
capability gaps. Last year, we also reported that the SBIRS program's 
revised schedule estimates for addressing software problems appeared 
too optimistic. For example, software experts, independent reviewers, 
as well as the government officials we interviewed agreed that the 
schedule was aggressive, and the Defense Contract Management Agency has 
repeatedly highlighted the schedule as high risk. 

Concluding Remarks: 

In conclusion, senior leaders managing DOD's space portfolio are 
working in a challenging environment. There are pressures to deliver 
new, transformational capabilities, but problematic older satellite 
programs continue to cost more than expected, constrain investment 
dollars, pose risks of capability caps, and thus require more time and 
attention from senior leaders than well-performing efforts. Moreover, 
military space is at a critical juncture. There are critical 
capabilities that are at risk of falling behind their current level of 
service. To best mitigate these circumstances and put future programs 
on a better path, DOD needs to focus foremost on sustaining current 
capabilities and preparing for potential gaps. In addition, there is 
still a looming question of how military and intelligence space 
activities should be organized and led. From an acquisition 
perspective, what is important is that the right decisions are made on 
individual programs, the right capability is in place to manage them, 
and there is someone to hold accountable when programs go off track. 

Mr. Chairman, this concludes my prepared statement. I would be happy to 
answer any questions you or members of the subcommittee may have at 
this time. 

Contacts and Acknowledgements: 

For further information about this statement, please contact Cristina 
Chaplain at (202) 512-4841 or chaplainc@gao.gov. Contact points for our 
Offices of Congressional Relations and Pubic Affairs may be found on 
the last page of this statement. Individuals who made key contributions 
to this statement include Art Gallegos, Assistant Director; Maria 
Durant; Arturo Holguin; Laura Holliday; Rich Horiuchi; Karen Sloan; 
Alyssa Weir; and Peter Zwanzig. 

[End of section] 

Appendix I: Scope and Methodology: 

In preparing this testimony, we relied on our body of work in space 
programs, including previously issued GAO reports on assessments of 
individual space programs, common problems affecting space system 
acquisitions, and the Department of Defense's (DOD) acquisition 
policies. We relied on our best practices studies, which comment on the 
persistent problems affecting space acquisitions, the actions DOD has 
been taking to address these problems, and what remains to be done. We 
also relied on work performed in support of our 2009 annual weapons 
system assessment. The individual reviews were conducted in accordance 
with generally accepted government auditing standards. Those standards 
require that we plan and perform the audit to obtain sufficient, 
appropriate evidence to provide a reasonable basis for our findings and 
conclusions based on our audit objectives. We believe that the evidence 
obtained provides a reasonable basis for our findings and conclusions 
based on our audit objectives. 

[End of section] 

Footnotes: 

[1] Institute for Defense Analyses, Leadership, Management, and 
Organization for National Security Space: Report to Congress of the 
Independent Assessment Panel on the Organization and Management of 
National Security Space (Alexandria, Va.: July 2008). 

[2] House Permanent Select Committee on Intelligence, Report on 
Challenges and Recommendations for United States Overhead Architecture 
(Washington, D.C.: October 2008). 

[3] 10 U.S.C. § 2433 establishes the requirement for unit cost reports. 
If certain unit cost thresholds are exceeded (known as Nunn-McCurdy 
breaches), DOD is required to report to Congress and, in certain 
circumstances, if DOD determines that specific criteria are met, 
certify the program to Congress. 

[4] Department of Defense. Report of the Commission to Assess United 
States National Security Space Management and Organization (Washington, 
D.C.: Jan. 11, 2001). 

[End of section] 

GAO's Mission: 

The Government Accountability Office, the audit, evaluation and 
investigative arm of Congress, exists to support Congress in meeting 
its constitutional responsibilities and to help improve the performance 
and accountability of the federal government for the American people. 
GAO examines the use of public funds; evaluates federal programs and 
policies; and provides analyses, recommendations, and other assistance 
to help Congress make informed oversight, policy, and funding 
decisions. GAO's commitment to good government is reflected in its core 
values of accountability, integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through GAO's Web site [hyperlink, http://www.gao.gov]. Each 
weekday, GAO posts newly released reports, testimony, and 
correspondence on its Web site. To have GAO e-mail you a list of newly 
posted products every afternoon, go to [hyperlink, http://www.gao.gov] 
and select "E-mail Updates." 

Order by Phone: 

The price of each GAO publication reflects GAO’s actual cost of
production and distribution and depends on the number of pages in the
publication and whether the publication is printed in color or black and
white. Pricing and ordering information is posted on GAO’s Web site, 
[hyperlink, http://www.gao.gov/ordering.htm]. 

Place orders by calling (202) 512-6000, toll free (866) 801-7077, or
TDD (202) 512-2537. 

Orders may be paid for using American Express, Discover Card,
MasterCard, Visa, check, or money order. Call for additional 
information. 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: [hyperlink, http://www.gao.gov/fraudnet/fraudnet.htm]: 
E-mail: fraudnet@gao.gov: 
Automated answering system: (800) 424-5454 or (202) 512-7470: 

Congressional Relations: 

Ralph Dawn, Managing Director, dawnr@gao.gov: 
(202) 512-4400: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7125: 
Washington, D.C. 20548: 

Public Affairs: 

Chuck Young, Managing Director, youngc1@gao.gov: 
(202) 512-4800: 
U.S. Government Accountability Office: 
441 G Street NW, Room 7149: 
Washington, D.C. 20548: