This is the accessible text file for GAO report number GAO-06-564T 
entitled 'Defense Acquisitions: Improved Business Case Key for Future 
Combat System's Success' which was released on April 4, 2006. 

This text file was formatted by the U.S. Government Accountability 
Office (GAO) to be accessible to users with visual impairments, as part 
of a longer term project to improve GAO products' accessibility. Every 
attempt has been made to maintain the structural and data integrity of 
the original printed product. Accessibility features, such as text 
descriptions of tables, consecutively numbered footnotes placed at the 
end of the file, and the text of agency comment letters, are provided 
but may not exactly duplicate the presentation or format of the printed 
version. The portable document format (PDF) file is an exact electronic 
replica of the printed version. We welcome your feedback. Please E-mail 
your comments regarding the contents or accessibility features of this 
document to Webmaster@gao.gov. 

This is a work of the U.S. government and is not subject to copyright 
protection in the United States. It may be reproduced and distributed 
in its entirety without further permission from GAO. Because this work 
may contain copyrighted images or other material, permission from the 
copyright holder may be necessary if you wish to reproduce this 
material separately. 

Testimony: 

Before the Subcommittee on Tactical Air and Land Forces, Committee on 
Armed Services, House of Representatives: 

United States Government Accountability Office: 

GAO: 

For Release on Delivery Expected at 2:00 p.m. EDT: 

Tuesday, April 4, 2006: 

Defense Acquisitions: 

Improved Business Case Key for Future Combat System's Success: 

Statement of Paul L. Francis, Director, Acquisition and Sourcing 
Management: 

GAO-06-564T: 

GAO Highlights: 

Highlights of GAO-06-564T, a testimony before the Subcommittee on 
Tactical Air and Land Forces, Committee on Armed Services, House of 
Representatives: 

Why GAO Did This Study: 

The Future Combat System (FCS) is a networked family of weapons and 
other systems in the forefront of efforts by the Army to become a 
lighter, more agile, and more capable combat force. When considering 
complementary programs, projected investment costs for FCS are 
estimated to be on the order of $200 billion. 

FCS’s cost is of concern given that developing and producing new weapon 
systems is among the largest investments the government makes, and FCS 
adds significantly to that total. Over the last 5 years, the Department 
of Defense (DOD) doubled its planned investments in such systems from 
$700 billion in 2001 to $1.4 trillion in 2006. At the same time, 
research and development costs on new weapons continue to grow on the 
order of 30 to 40 percent. 

FCS will be competing for significant funds at a time when federal 
fiscal imbalances are exerting great pressures on discretionary 
spending. In the absence of more money being available, FCS and other 
programs must be executable within projected resources. 

Today, I would like to discuss (1) the business case needed for FCS to 
be successful and (2) our recent recommendations to DOD and matters for 
congressional consideration regarding the FCS program. 

What GAO Found: 

There are a number of compelling aspects of the FCS program, and it is 
hard to argue with the program’s goals. However, the elements of a 
sound business case for such an acquisition program--firm requirements, 
mature technologies, a knowledge-based acquisition strategy, a 
realistic cost estimate, and sufficient funding—are not yet present. 
FCS began product development prematurely in 2003. Since then, the Army 
has made several changes to improve its approach for acquiring FCS. Yet 
today, the program remains a long way from having the level of 
knowledge it should have had before starting product development. FCS 
has all the markers for risks that would be difficult to accept for any 
single system, much less a complex, multiprogram effort. These 
challenges are even more daunting in the case of FCS not only because 
there are so many of them but because FCS represents a new concept of 
operations that is predicated on technological breakthroughs. Thus, 
technical problems, which accompany immaturity, not only pose 
traditional risks to cost, schedule, and performance; they pose risks 
to the new fighting concepts envisioned by the Army. 

Last month, we made recommendations to the Secretary of Defense to take 
several actions, prior to DOD’s long-term commitment to the program, to 
improve the FCS business case and establish knowledge-based measures to 
guide oversight of FCS progress. These recommendations detailed 
specific steps DOD should take leading up to a major milestone review 
of the program in 2008 when the program is expected to have achieved 
the level of knowledge it should have had in 2003. We believe it is at 
this point the program should be reviewed as to whether it has 
established enough of a solid business case to continue. While DOD 
concurred with the intent of our recommendations, it did not agree to 
limit its commitment to the FCS program or to do much beyond what it 
had already planned to do. This concerns us. As a result, we have also 
raised to Congress several matters for consideration to ensure that FCS 
has a sound business case before future funding commitments are made. 
We believe the actions we have recommended to DOD and the matters for 
consideration we have presented to Congress are necessary to improve 
the prospects for FCS success and to protect the government’s ability 
to change course if the program does not progress as the Army plans. 

www.gao.gov/cgi-bin/getrpt?GAO-06-564T. 

To view the full product, including the scope and methodology, click on 
the link above. For more information, contact Paul Francis at (202) 512-
2811 or francisp@gao.gov. 

[End of section] 

Mr. Chairman and Members of the Subcommittee: 

I am pleased to be here today to discuss the Department of the Army's 
Future Combat System (FCS), a networked family of weapons and other 
systems. FCS is in the forefront of efforts to help the Army transform 
itself into a lighter, more agile, and more capable combat force by 
using a new concept of operations, new technologies, and a new 
information network linking whole brigades together. This is a 
tremendous undertaking that will involve a total investment cost on the 
order of $200 billion. 

The context within which the FCS investment is being made is important. 
Fiscal imbalances faced by the federal government will continue to 
constrain discretionary spending. One of the single largest investments 
the government makes is the development and production of new weapon 
systems. Over the last 5 years, the Department of Defense (DOD) has 
doubled its planned investments in new weapon systems from about $700 
billion in 2001 to nearly $1.4 trillion in 2006. At the same time, 
research and development cost growth on new weapons maintains its 
historical level of about 30 to 40 percent. This is the lens that must 
be used to look at major new investments, such as FCS, because more 
money may not be an option for the future. Rather, the key to getting 
better outcomes is to make individual programs more executable. 

My statement today is based on our recently issued report about the 
need for an improved business case for the FCS. This report responds to 
the National Defense Authorization Act for Fiscal Year 2006, which 
requires GAO to report annually on the product development phase of the 
FCS's acquisition.[Footnote 1] Recently, we testified before the Senate 
Armed Services Committee about the FCS's business case and related 
business arrangements.[Footnote 2] 

Today, I would like to discuss (1) the scope of the business case that 
we feel is necessary for the FCS to be successful and (2) our recent 
recommendations to DOD and matters for congressional consideration 
regarding the FCS program. 

Summary: 

The critical role played by U.S. ground combat forces is underscored 
today in Operation Iraqi Freedom. That the Army should ensure its 
forces are well equipped with the capabilities they will need in the 
coming years is unquestioned. Moreover, the top-level goals the Army 
has set for its future force seem inarguable: to be as lethal and 
survivable as the current force, but significantly more sustainable and 
mobile. However, the Army's approach to meeting these needs--embodied 
in the FCS and its complementary systems--does raise questions. 

On the one hand, the FCS is the result of the Army leadership's taking 
a hard look at how it wants its forces to fight in the future. Army 
leadership has had the courage to break with tradition on FCS; it would 
have likely been much easier to win support for successor vehicles to 
the Abrams and Bradley. On the other hand, FCS does not present a good 
business case for an acquisition program. It is necessary that a major 
new investment like FCS have a compelling, well thought-out concept, 
but this alone is not sufficient. FCS began product development 
prematurely in 2003, and today is a long way from having the level of 
knowledge it should have had before committing the high level of 
resources associated with a new product development effort. The 
elements of a sound business case--firm requirements, mature 
technologies, a knowledge-based acquisition strategy, a realistic cost 
estimate, and sufficient funding--are not yet present. FCS has all the 
markers for risks that would be difficult to accept for any single 
system. They are even more daunting in the case of FCS, not only 
because of their multiplicity, but because FCS represents a new concept 
of operations predicated on technological breakthroughs. Thus, 
technical problems, which accompany immaturity, not only pose 
traditional risks to cost, schedule, and performance, but also pose 
risks to the new fighting concepts envisioned by the Army. 

A full commitment to the Army's strategy for acquiring FCS is not yet 
warranted because the Army has not demonstrated sufficient knowledge by 
providing the confidence it can deliver a fully capable FCS within 
projected costs and time frames. As DOD proceeds with its decisions, it 
must preserve its ability to change course on acquiring FCS 
capabilities to guard against a situation in which FCS will have to be 
acquired at any cost. It must also be able to hold the Army accountable 
for delivering FCS within budgeted resources. Last month, we made 
recommendations to the Secretary of Defense to take several actions, 
prior to DOD's long-term commitment to the program, to improve the FCS 
business case and establish knowledge-based measures to guide oversight 
of FCS progress. These recommendations detailed specific steps DOD 
should take leading up to a major milestone review of the program in 
2008, when the program is expected to have achieved the level of 
knowledge it should have had in 2003. We believe it is at this point 
the program should be reviewed as to whether it has established enough 
of a solid business case to continue. While DOD concurred with the 
intent of our recommendations, it did not agree to limit its commitment 
to the FCS program or to do much beyond what it had already planned to 
do. This concerns us. As a result, we have also raised to Congress 
several matters for consideration to ensure that FCS has a sound 
business case before future funding commitments are made. We believe 
the actions we have recommended to DOD and the matters for 
consideration we have presented are necessary to improve the prospects 
for FCS success and to protect the government's ability to change 
course if the program does not progress as the Army plans. 

Background: 

The FCS concept is part of a pervasive change to what the Army refers 
to as the Future Force. The Army is reorganizing its current forces 
into modular brigade combat teams, meaning troops can be deployed on 
different rotational cycles as a single team or as a cluster of teams. 
The Future Force is designed to transform the Army into a more rapidly 
deployable and responsive force and to enable the Army to move away 
from the large division-centric structure of the past. Each brigade 
combat team is expected to be highly survivable and the most lethal 
brigade-sized unit the Army has ever fielded. The Army expects FCS- 
equipped brigade combat teams to provide significant warfighting 
capabilities to DOD's overall joint military operations. The Army is 
implementing its transformation plans at a time when current U.S. 
ground forces are playing a critical role in the ongoing conflicts in 
Iraq and Afghanistan. 

The FCS family of weapons includes 18 manned and unmanned ground 
vehicles, air vehicles, sensors, and munitions linked by an information 
network. These vehicles, weapons, and equipment will constitute the 
majority of the equipment needed for a brigade combat team. The Army 
plans to buy 15 brigades' worth of FCS equipment by 2025. See figure 1 
for the various elements of the FCS program. 

Figure 1: FCS's Core Systems: 

[See PDF for image] 

[End of figure] 

If successful, the FCS system-of-systems concept will leverage 
individual capabilities of weapons and platforms and will facilitate 
interoperability and open system designs. This would be a significant 
improvement over the traditional approach of building superior 
individual weapons that must be retrofitted and netted together after 
the fact. This transformation, in terms of both operations and 
equipment, is under way with the full cooperation of the Army 
warfighter community. In fact, the development and acquisition of FCS 
is being accomplished using a uniquely collaborative relationship among 
the Army's developers, the participating contractors, and the 
warfighter community. 

FCS Restructures the Program and Changes Contracting Approach: 

As a key element of its efforts to transform itself, the Army has 
recognized FCS from its outset as the greatest technology and 
integration challenge it has ever undertaken. In May 2003, DOD approved 
the FCS program to begin the system development and demonstration 
phase, a milestone that ideally marks the completion of technology 
development and the start of product development. However, FCS's entry 
into this phase was premature given the program had failed to satisfy 
basic tenets of DOD acquisition policy. We have reported that, as FCS 
started product development, it did not have mature technologies or 
adequately defined requirements. 

Responding to direction from the Army Chief of Staff, the Army 
announced in July 2004 its plans to restructure the FCS program. The 
Army added 4 years to develop and mature the manned ground vehicles, 
added more demonstrations and experiments, and established an 
evaluation unit to demonstrate FCS capabilities. The restructuring 
reintroduced 4 systems that previously had been left unfunded, raising 
the total number of FCS-related systems to 18. The restructure also 
included plans to spin off mature FCS capabilities as they become 
available to current force units. With the restructuring, the FCS 
program now plans to achieve initial operational capability in fiscal 
year 2015 and full operational capability in fiscal year 2017. FCS low- 
rate production is expected to start in fiscal year 2012, and full-rate 
production in fiscal year 2016. The Army intends to continue FCS 
procurement through fiscal year 2025, eventually equipping 15 brigade 
combat teams. 

The restructuring was not the only major modification to the FCS 
program. Because of congressional concerns that the Army's contracting 
approach incorporated insufficient safeguards to protect the 
government's interests, the Army is preparing a new contract that is to 
be completed and finalized in late March 2006 and is based on the 
Federal Acquisition Regulation, which governs acquisitions within the 
federal government. The new contract will incorporate standard Federal 
Acquisition Regulation clauses such as those relating to procurement 
integrity, Truth in Negotiations, and Cost Accounting Standards. 
Previously, the lead systems integrator had been performing FCS work 
for the Army under a contractual instrument called an "other 
transaction agreement" that was not subject to the Federal Acquisition 
Regulation. The other transaction agreement gave the Army considerable 
flexibility to negotiate the terms and conditions for contractors 
involved in FCS development. The Army's purpose for using such an 
agreement was to encourage innovation and to use its wide latitude in 
tailoring business, organizational, and technical relationships to 
achieve the program goals. In April 2005, the Army decided to 
incorporate into its agreement the procurement integrity, Truth in 
Negotiations, and Cost Accounting Standards clauses from the 
regulation. 

After Congress raised questions about the Army using an other 
transaction agreement for the development of a program as large and 
risky as FCS and about the Army's choice not to include standard 
Federal Acquisition Regulation clauses in the agreement, the Secretary 
of the Army directed that the other transaction agreement be converted 
to a Federal Acquisition Regulation-based contract. All of the work 
performed under the product development phase as of September 2005 will 
be accounted for under the prior other transaction agreement, and all 
work after September 2005 will be performed under the new contract. The 
Army expects the content of the program--its statement of work--will 
remain largely the same, and it does not expect the cost, schedule, and 
performance of the overall development effort to change materially. 

Elements of a Business Case: 

We have frequently reported on the importance of using a solid, 
executable business case before committing resources to a new product 
development. In its simplest form, this is evidence that (1) the 
warfighter's needs are valid and can best be met with the chosen 
concept, and (2) the chosen concept can be developed and produced 
within existing resources--that is, proven technologies, design 
knowledge, adequate funding, and adequate time to deliver the product 
when needed. 

At the heart of a business case is a knowledge-based approach to 
product development demonstrating high levels of knowledge before 
significant commitments are made. In essence, knowledge supplants risk 
over time. This building of knowledge can be described as three levels, 
or knowledge points, that should be attained over the course of a 
program: 

* First, at program start, the customer's needs should match the 
developer's available resources--mature technologies, time, and 
funding. An indication of this match is the demonstrated maturity of 
the technologies needed to meet customer needs. 

* Second, about midway through development, the product's design should 
be stable and demonstrate it is capable of meeting performance 
requirements. The critical design review takes place at that point of 
time because it generally signifies when the program is ready to start 
building production-representative prototypes. 

* Third, by the time of the production decision, the product must be 
shown to be producible within cost, schedule, and quality targets and 
have demonstrated its reliability, and the design must demonstrate that 
it performs as needed through realistic system-level testing. 

The three knowledge points are related in that a delay in attaining one 
delays the points that follow. Thus, if the technologies needed to meet 
requirements are not mature, then design and production maturity will 
be delayed. 

Objectives, Scope, and Methodology: 

To develop the information on the Future Combat System program's 
progress toward meeting established goals, the contribution of critical 
technologies and complementary systems, and the estimates of cost and 
affordability, we interviewed officials of the Office of the Under 
Secretary of Defense (Acquisition, Technology, and Logistics); the Army 
G-8; the Office of the Under Secretary of Defense (Comptroller); the 
Secretary of Defense's Cost Analysis Improvement Group; the Director of 
Operational Test and Evaluation; the Assistant Secretary of the Army 
(Acquisition, Logistics, and Technology); the Army's Training and 
Doctrine Command; Surface Deployment and Distribution Command; the 
Program Manager for the Future Combat System (Brigade Combat Team); the 
Future Combat System Lead Systems Integrator; and other contractors. We 
reviewed, among other documents, the Future Combat System's Operational 
Requirements Document, the Acquisition Strategy Report, the Baseline 
Cost Report, the Critical Technology Assessment and Technology Risk 
Mitigation Plans, and the Integrated Master Schedule. We attended or 
reviewed the results of the FCS System-of-Systems Functional Review, In-
Process Reviews, Board of Directors Reviews, and multiple system 
demonstrations. In our assessment of the FCS, we used the knowledge- 
based acquisition practices drawn from our large body of past work as 
well as DOD's acquisition policy and the experiences of other programs. 
We conducted the above in response to the National Defense 
Authorization Act of Fiscal Year 2006, which requires GAO to annually 
report on the product development phase of the FCS acquisition. We 
performed our review from June 2005 to March 2006 in accordance with 
generally accepted government auditing standards. 

Improved Business Case Is Needed for the FCS's Success: 

The FCS program started its product development phase with inadequate 
knowledge in several key areas. After almost 3 years and progress in 
key areas, the elements of a sound business case, namely firm 
requirements, mature technologies, a knowledge-based acquisition 
strategy, a realistic cost estimate, and sufficient funding, are not 
yet demonstrably present. Given that, an improved business case for the 
FCS program is essential to help ensure the program is successful in 
the long run. The importance of a business case is amplified by the 
fact that the program is developing 18 systems and a network under a 
single program office and lead system integrator in the same amount of 
time it would take to develop a single system. 

While Progress Has Been Made, Requirements Still Remain Uncertain: 

The Army has made significant progress defining FCS's system-of-systems 
requirements, particularly when taking into account the daunting number 
of them involved--nearly 11,500 at this level. Yet system-level 
requirements are not yet stabilized and will continue to change, 
postponing the needed match between requirements and resources. Now the 
Army and its contractors are working to complete the definition of 
system-level requirements, and the challenge is in determining if those 
requirements are technically feasible and affordable. Army officials 
say it is almost certain some FCS system-level requirements will have 
to be modified, reduced, or eliminated; the only uncertainty is by how 
much. We have previously reported unstable requirements can lead to 
cost, schedule, and performance shortfalls. Once the Army gains a 
better understanding of the technical feasibility and affordability of 
the system-level requirements, trade-offs between the developer and the 
warfighter will have to be made, and the ripple effect of such trade- 
offs on key program goals will have to be reassessed. Army officials 
have told us it will be 2008 before the program reaches the point that 
it should have reached before it started in May 2003 in terms of stable 
requirements. 

FCS Success Hinges on Numerous Undemonstrated Technologies and 
Complementary Programs: 

Development of concrete program requirements depends in large part on 
stable, fully mature technologies. Yet, according to the latest 
independent assessment, the Army has not fully matured any of the 
technologies critical to FCS's success.[Footnote 3] Some of FCS's 
critical technologies may not reach a high level of maturity until the 
final major phase of acquisition, the start of production. The Army 
considers a lower level of demonstration as acceptable maturity, but 
even against this standard, only about one-third of the technologies 
are mature. We have reported going forward into product development 
without demonstrating mature technologies increases the risk of cost 
growth and schedule delays throughout the life of the program. The Army 
is also facing challenges with several of the complementary programs 
considered essential for meeting FCS's requirements. Some are 
experiencing technology difficulties, and some have not been fully 
funded. These difficulties underscore the gap between requirements and 
available resources that must be closed if the FCS business case is to 
be executable. 

Technology readiness levels (TRL) are measures pioneered by the 
National Aeronautics and Space Administration and adopted by DOD to 
determine whether technologies are sufficiently mature to be 
incorporated into a weapon system. Our prior work has found TRLs to be 
a valuable decision-making tool because they can presage the likely 
consequences of incorporating a technology at a given level of maturity 
into a product development. The maturity levels range from paper 
studies (level 1), to prototypes tested in a realistic environment 
(level 7), to an actual system proven in mission operations (level 9). 
Successful DOD programs have shown critical technologies should be 
mature to at least a TRL 7 before the start of product development. 

Table 1: Number of FCS Critical Technologies Sorted by TRLs: 

TRL: TRL 7 and higher; 
Critical technology assessment as of April 2003: 1; 
Critical technology assessment as of April 2005: 0. 

TRL: TRL 6; 
Critical technology assessment as of April 2003: 7; 
Critical technology assessment as of April 2005: 18. 

TRL: TRL 5 and lower; 
Critical technology assessment as of April 2003: 24; 
Critical technology assessment as of April 2005: 31. 

TRL: Total; 
Critical technology assessment as of April 2003: 32; 
Critical technology assessment as of April 2005: 49. 

Source: U.S. Army (data); GAO (analysis and presentation). 

Note: The April 2003 assessment was organized into 31 technology areas, 
one of which had two different TRL ratings for separate technologies. 
For the April 2005 assessment, the original 31 technology areas were 
subdivided into 54 individual technologies. Five of the original 
technologies are no longer being tracked, leaving a total of 49. 

[End of table] 

Table 1 shows that in the latest independent FCS technology assessment, 
none of the critical technologies are at TRL 7, and only 18 of the 49 
technologies currently rated have demonstrated TRL 6, defined as 
prototype demonstration in a relevant environment. None of the critical 
technologies may reach TRL 7 until the production decision in fiscal 
year 2012, according to Army officials. Projected dates for FCS 
technologies to reach TRL 6 have slipped significantly since the start 
of the program. In the 2003 technology assessment, 87 percent of FCS's 
critical technologies were projected to be mature to a TRL 6 by 2005. 
When the program was looked at again in April 2005, 31 percent of the 
technologies were expected to mature to a TRL 6 by 2005, and all 
technologies are not expected to be mature to that level until 2009. 

FCS Acquisition Strategy Will Demonstrate Design Maturity after 
Production Begins: 

The knowledge deficits for requirements and technologies have created 
enormous challenges for devising an acquisition strategy that can 
demonstrate the maturity of design and production processes. Several 
efforts within the FCS program are facing significant problems that may 
eventually involve reductions in promised capabilities and may lead to 
cost overruns and schedule delays. Even if requirements setting and 
technology maturity proceed without incident, FCS design and production 
maturity will still not be demonstrated until after the production 
decision is made. Production is the most expensive phase in which to 
resolve design or other problems. 

The Army's acquisition strategy for FCS does not reflect a knowledge- 
based approach. Figure 2 shows how the Army's strategy for acquiring 
FCS involves concurrent development, design reviews occurring late, and 
other issues out of alignment with the knowledge-based approach 
outlined in DOD policy. 

Figure 2: FCS Acquisition Compared with Commercial Best Practices' 
Approach: 

[See PDF for image] 

[End of figure] 

Ideally, the preliminary design review occurs at or near the start of 
product development. Review at this point can help reveal key technical 
and engineering challenges and can help determine if a mismatch exists 
between what the customer wants and what the product developer can 
deliver. An early preliminary design review is intended to help 
stabilize cost, schedule, and performance expectations. The critical 
design review ideally occurs midway into the product development phase. 
The critical design review should confirm the system design is stable 
enough to build production-representative prototypes for testing. 

The FCS acquisition schedule indicates several key issues: 

* The program did not have the basic knowledge needed for program start 
in 2003. While the preliminary design review normally occurs at or near 
the start of product development, the Army has scheduled it in fiscal 
year 2008, about 5 years after the start of product development. 

* Instead of the sequential development of knowledge, major elements of 
the program are being conducted concurrently. 

* The critical design review is scheduled in fiscal year 2010, just 2 
years after the scheduled preliminary review and the planned start of 
detailed design. The timing of the design reviews is indicative of how 
late knowledge will be attained in the program, assuming all goes 
according to plan. 

* The critical design review is also scheduled just 2 years before the 
initial FCS low-rate production decision in fiscal year 2012, leaving 
little time for product demonstration and correction of any issues 
identified at that time. 

The FCS program is thus susceptible to late-cycle churn, which refers 
to the additional--and unanticipated--time, money, and effort that must 
be invested to overcome problems discovered late through testing. 

FCS's Higher Costs May Result in Funding Challenge: 

The total cost for the FCS program, now estimated at $160.7 billion 
(then-year dollars), has climbed 76 percent from the Army's first 
estimate. Because uncertainties remain regarding FCS's requirements and 
the Army faces significant challenges in technology and design 
maturity, we believe the Army's latest cost estimate still lacks a firm 
knowledge base. Furthermore, this latest estimate does not include 
complementary programs that are essential for FCS to perform as 
intended, or the necessary funding for spin-outs. The Army has taken 
some steps to help manage the growing cost of FCS, including 
establishing cost ceilings or targets for development and production. 
However, program officials told us that setting cost limits may result 
in accepting lower capabilities. As FCS's higher costs are recognized, 
it remains unclear whether the Army will have the ability to fully fund 
the planned annual procurement costs for the FCS current program of 
record. FCS affordability depends on the accuracy of the cost estimate, 
the overall level of development and procurement funding available to 
the Army, and the level of competing demands. 

At the start of product development, FCS program officials estimated 
that the program would require about $20 billion in then-year dollars 
for research, development, testing, and evaluation and about $72 
billion to procure the FCS systems to equip 15 brigade combat teams. At 
that time, program officials could only derive the cost estimate on the 
basis of what they knew then--requirements were still undefined and 
technologies were immature. The total FCS program is now expected to 
cost $160.7 billion in then-year dollars, a 76 percent increase. Table 
2 summarizes the growth of the FCS cost estimate. 

Table 2: Comparison of Original Cost Estimate and Current Cost Estimate 
for FCS Program: 

(in billions of then-year dollars). 

Research, development, testing, and evaluation; 
Original estimate: $19.6; 
Revised estimate (as of 1/2006): $30.5; 
Percentage increase: 56%. 

Procurement; 
Original estimate: $71.8; 
Revised estimate (as of 1/2006): $130.2; 
Percentage increase: 81%. 

Total; 
Original estimate: $91.4; 
Revised estimate (as of 1/2006): $160.7; 
Percentage increase: 76%. 

Source: Army (data); GAO (analysis and presentation). 

[End of table] 

According to the Army, the current cost estimate is more realistic, 
better informed, and based on a more reasonable schedule. The estimate 
accounts for the restructure of the FCS program and its increased 
scope, the 4-year extension to the product development schedule, the 
reintroduction of four systems that had been previously deferred, and 
the addition of a spin-out concept whereby mature FCS capabilities 
would be provided, as they become available, to current Army forces. 
The estimate also reflects a rate of production reduced from an average 
of 2 brigade combat teams per year to an average of 1.5 brigades per 
year. Instead of completing all 15 brigades by 2020, the Army would 
complete production in 2025. This cost estimate has also benefited from 
progress made in defining system-of-systems requirements. 

Figure 3 compares the funding profiles for the original program and for 
the latest restructured program. 

Figure 3: Comparison of Original Cost Estimate and Current Cost 
Estimate for FCS Program between Fiscal Years 2003 and 2026: 

[See PDF for image] 

[End of figure] 

The current funding profile is lower than the original through fiscal 
year 2013, but is substantially higher than the original after fiscal 
year 2013. It still calls for making substantial investments before key 
knowledge has been demonstrated. Stretching out FCS development by 4 
years freed up about $9 billion in funding through fiscal year 2011 for 
allocation to other Army initiatives. Originally, FCS annual funding 
was not to exceed $10 billion in any 1 year. Now, the cost estimate is 
expected to exceed $10 billion in each of 9 years. While it is a more 
accurate reflection of program costs than the original estimate, the 
latest estimate is still based on a low level of knowledge about 
whether FCS will work as intended. The cost estimate has not been 
independently validated, as called for by DOD's acquisition policy. The 
Cost Analysis Improvement Group will not release its updated 
independent estimate until spring 2006, after the planned Defense 
Acquisition Board review of the FCS program. 

The latest cost estimate does not include all the costs that will be 
needed to field FCS capabilities. For instance, 

* Costs for the 52 essential complementary programs are separate, and 
some of those costs could be substantial. For example, the costs of the 
Joint Tactical Radio System Clusters 1 and 5 programs were expected to 
be about $32.6 billion (then-year dollars).[Footnote 4] 

* Some complementary programs, such as the Mid-Range Munition and 
Javelin Block II, are currently not funded for their full development. 
These and other unfunded programs would have to compete for already 
tight funding. 

* Procurement of the spin-outs from the FCS program to current Army 
forces is not yet entirely funded. Procuring the FCS items expected to 
be spun out to current forces is expected to cost about $19 billion, 
and the needed installation kits may add $4 billion. Adding these items 
brings the total required FCS investment to the $200 billion range. 

Through fiscal year 2006, the Army will have budgeted over $8 billion 
for FCS development. Through fiscal year 2008, when the preliminary 
design review is held, the amount budgeted for FCS will total over $15 
billion. By the time the critical design review is held in 2010, about 
$22 billion will have been budgeted. By the time of the production 
decision in 2012, about $27 billion will have been budgeted. 

The affordability of the FCS program depends on several key 
assumptions. First, the program must proceed without exceeding its 
currently projected costs. Second, the Army's annual procurement 
budget--not including funds specifically allocated for the modularity 
initiative--is expected to grow from about $11 billion in fiscal year 
2006 to at least $20 billion by fiscal year 2011. Even if this 
optimistic projection comes to pass, FCS annual procurement costs will 
dominate the Army procurement funding. If the Army budget remains at 
fiscal year 2011 levels, FCS procurement will represent about 60 to 70 
percent of Army procurement from fiscal years 2014 to 2022. With the 
remainder, the Army will have to address current force upgrades, 
including spin-outs from FCS, the procurement of FCS complementary 
programs, aviation procurement, trucks, ammunition, and other 
equipment. Further, FCS will have to compete for funding with other 
Army "big-ticket" items, such as missile defense systems and the future 
heavy lift helicopter. 

Figure 4 compares the projected FCS budget with the funds the Army 
projects for its total procurement budget. 

Figure 4: Comparison of FCS Budget with Total Army Procurement Budget: 

[See PDF for image] 

[End of figure] 

The large annual procurement costs for FCS are expected to begin in 
fiscal year 2012, which is beyond the current Future Years Defense Plan 
period (fiscal years 2006-2011). This situation is typically called a 
funding bow wave. The term "bow wave" is used to describe a requirement 
for more funds just beyond the years covered in the current defense 
plan that are subject to funding constraints. As it prepares the next 
defense plan, the Army will face the challenge of allocating sufficient 
funding to meet the increasing needs for FCS procurement in fiscal 
years 2012 and 2013. According to an Army official, if all the needed 
funding cannot be identified, the Army will consider reducing the FCS 
procurement rate or delaying or reducing items to be spun out to 
current Army forces. However, reducing the procurement rate would 
increase the FCS unit costs and extend the time needed to deploy FCS-
equipped brigade combat teams. 

Recent FCS Recommendations and Matters for Congressional Consideration: 

In our most recent report on the FCS, we made specific recommendations 
to the Secretary of Defense, with the intent that DOD limit its 
commitment to the FCS until it demonstrates a solid business case. DOD, 
in its response to our draft report, concurred with the intent of the 
recommendations but did not agree to limit its commitment to the FCS 
program or to take any action beyond what it had already planned to do. 
Consequently, we added several matters for congressional consideration 
in order to highlight key issues and actions that Congress may want to 
take. 

Recommendations to DOD: 

In our March report we made several specific recommendations to the 
Secretary of Defense, which are intended to limit DOD's commitment to 
the FCS until a sound business case that is consistent with DOD 
acquisition policy and best practices can be clearly demonstrated. 

Specifically, we recommended that the Secretary of Defense lay the 
groundwork for the Army's development of a sound FCS business case by 
tasking the spring 2006 Defense Acquisition Board to do the following: 

* Revaluate the FCS business case--including requirements, 
technologies, complementary programs, acquisition strategy, cost, and 
funding availability--in light of its own acquisition policies. 

* If the business case for FCS is found not to be executable, determine 
whether investments in FCS design-and production-related activities 
should be curbed until system-level requirements are firm and 
technologies are mature. 

* If the deficiencies in the FCS business case are judged to be 
recoverable, establish the incremental markers that are needed to 
demonstrate that FCS is proceeding on a knowledge-based approach and to 
hold the Army accountable, through periodic reporting or other means, 
for achieving those markers. 

We also recommended that the Secretary of Defense reassess the FCS cost 
estimate and funding availability based on the independent cost 
estimate and any program changes to improve its business case. 

Finally, we recommended that the Secretary of Defense establish a 
milestone review by the Defense Acquisition Board following the Army's 
preliminary design review scheduled for 2008. This should be a go/no-go 
review of the FCS program that is based on (1) the program's ability to 
demonstrate whether it is meeting the knowledge markers outlined above 
at times consistent with DOD policy and best practices and (2) whether 
the funds can still be made available to afford its costs. 

DOD Comments on Our Report and Our Evaluation: 

DOD concurred with the intent of our recommendations but did not agree 
to limit its commitment to the FCS program or to take any action beyond 
what it had already planned to do. DOD stated it is committed to the 
Army's transformation, and that effort, in particular the FCS program, 
requires a disciplined, yet agile, acquisition construct. DOD's 
response to our draft report did not specifically address our findings 
on the FCS program's lack of a sound business case. DOD added that the 
Defense Acquisition Executive has determined that the FCS program is 
based on a viable acquisition strategy and that it would reevaluate the 
FCS acquisition strategy and reassess FCS cost estimates and funding in 
the spring 2006 Defense Acquisition Board review. DOD also noted a 
Defense Acquisition Board review would be held for the time frame 
(2008) of the FCS preliminary design review, but it refrained from 
committing to making a milestone decision review. 

Regarding a commitment to a milestone review in 2008, we noted that the 
FCS was allowed to proceed into Systems Development and Demonstration 
prematurely, while DOD had directed a full milestone review update be 
held in November 2004. However, the review has not yet occurred, and it 
now appears it will not occur. Thus, there is no commitment by DOD to 
review the FCS business case (including all elements in addition to the 
acquisition strategy), culminating in a go/no-go decision in 2008 based 
on the preliminary design review. The increased responsibility of 
making a declarative decision adds a higher level of discipline and 
accountability than a review implies. We maintain our position that 
such a decision is warranted. 

Matters for Congressional Consideration: 

Based on DOD's response to our report, it did not appear that DOD 
planned to assess the FCS business case against best practices or its 
own policies. Nor did DOD agree to hold a go/no-go milestone review in 
2008 based on the preliminary design review. Congress will likely be 
asked to approve fiscal years 2008 and 2009 funding requests before the 
FCS business case is adequately demonstrated. In light of DOD's 
response, Congress should consider directing the Secretary of Defense 
to: 

* report on the results of the May 2006 Defense Acquisition Board's 
review of the FCS program business case in the areas of requirements, 
technologies, acquisition strategy, cost, and funding, and: 

* direct DOD to conduct and report the results of a milestone review in 
2008, following the preliminary design review, that will be a go/no-go 
review of the FCS program based on its demonstration of a sound 
business case. 

Congress should also consider restricting annual appropriations for 
fiscal years 2008 and 2009 for the FCS program until definitive 
progress in establishing a sound business case is demonstrated in terms 
of firm requirements, mature technologies, a knowledge-based 
acquisition strategy, a realistic cost estimate, and sufficient 
funding. Most important, the Army must provide sufficient evidence FCS 
will work. 

Mr. Chairman, this concludes my prepared statement. I would be happy to 
answer any questions you or members of the subcommittee may have. 

Contacts and Staff Acknowledgments: 

For future questions about this statement, please contact me at (202) 
512-4841. Individuals making key contributions to this statement 
include Robert L. Ackley, Noah B. Bleicher, Lily J. Chin, Randolfo E. 
DeLeon, Marcus C. Ferguson, William R. Graveline, Michael J. Hesse, 
Guisseli Reyes, John P. Swain, and Carrie R. Wilson. 

FOOTNOTES 

[1] GAO, Defense Acquisitions: Improved Business Case Is Needed for 
Future Combat System's Successful Outcome. GAO-06-367. (Washington, 
D.C.: Mar. 14, 2006). 

[2] GAO, Defense Acquisitions: Business Case and Business Arrangements 
Key for Future Combat System's Success. GAO-06-478T. (Washington, D.C.: 
Mar. 1, 2006). 

[3] Office of the Deputy Assistant Secretary of the Army for Research 
and Technology, Technology Readiness Assessment Update, April 2005. 

[4] The ongoing operational assessment of the Joint Tactical Radio 
System functionality could result in a program restructure, which would 
have an impact on the program's costs. 

GAO's Mission: 

The Government Accountability Office, the investigative arm of 
Congress, exists to support Congress in meeting its constitutional 
responsibilities and to help improve the performance and accountability 
of the federal government for the American people. GAO examines the use 
of public funds; evaluates federal programs and policies; and provides 
analyses, recommendations, and other assistance to help Congress make 
informed oversight, policy, and funding decisions. GAO's commitment to 
good government is reflected in its core values of accountability, 
integrity, and reliability. 

Obtaining Copies of GAO Reports and Testimony: 

The fastest and easiest way to obtain copies of GAO documents at no 
cost is through the Internet. GAO's Web site ( www.gao.gov ) contains 
abstracts and full-text files of current reports and testimony and an 
expanding archive of older products. The Web site features a search 
engine to help you locate documents using key words and phrases. You 
can print these documents in their entirety, including charts and other 
graphics. 

Each day, GAO issues a list of newly released reports, testimony, and 
correspondence. GAO posts this list, known as "Today's Reports," on its 
Web site daily. The list contains links to the full-text document 
files. To have GAO e-mail this list to you every afternoon, go to 
www.gao.gov and select "Subscribe to e-mail alerts" under the "Order 
GAO Products" heading. 

Order by Mail or Phone: 

The first copy of each printed report is free. Additional copies are $2 
each. A check or money order should be made out to the Superintendent 
of Documents. GAO also accepts VISA and Mastercard. Orders for 100 or 
more copies mailed to a single address are discounted 25 percent. 
Orders should be sent to: 

U.S. Government Accountability Office 

441 G Street NW, Room LM 

Washington, D.C. 20548: 

To order by Phone: 

Voice: (202) 512-6000: 

TDD: (202) 512-2537: 

Fax: (202) 512-6061: 

To Report Fraud, Waste, and Abuse in Federal Programs: 

Contact: 

Web site: www.gao.gov/fraudnet/fraudnet.htm 

E-mail: fraudnet@gao.gov 

Automated answering system: (800) 424-5454 or (202) 512-7470: 

Public Affairs: 

Jeff Nelligan, managing director, 

NelliganJ@gao.gov 

(202) 512-4800 

U.S. Government Accountability Office, 

441 G Street NW, Room 7149 

Washington, D.C. 20548: