This is the accessible text file for GAO report number GAO-02-1067T 
entitled 'Highway Infrastructure: Preliminary Information on the Timely 
Completion of Highway Construction Projects' which was released on 
September 19, 2002.



This text file was formatted by the U.S. General Accounting Office 

(GAO) to be accessible to users with visual impairments, as part of a 

longer term project to improve GAO products’ accessibility. Every 

attempt has been made to maintain the structural and data integrity of 

the original printed product. Accessibility features, such as text 

descriptions of tables, consecutively numbered footnotes placed at the 

end of the file, and the text of agency comment letters, are provided 

but may not exactly duplicate the presentation or format of the printed 

version. The portable document format (PDF) file is an exact electronic 

replica of the printed version. We welcome your feedback. Please E-mail 

your comments regarding the contents or accessibility features of this 

document to Webmaster@gao.gov.



Testimony:



Before the Committee on Environment and Public Works, U.S. Senate:



United States General Accounting Office:



GAO:



For Release on Delivery Expected at 9:30 a.m. EDT September 19, 2002:



Highway Infrastructure:



Preliminary Information on the Timely Completion of Highway 

Construction Projects:



Statement of Katherine Siggerud 

Acting Director, Physical Infrastructure Issues:



GAO-02-1067T:



Mr. Chairman and Members of the Committee:



We appreciate the opportunity to testify today on the timely completion 

of highway projects that receive federal financial assistance from the 

Federal Highway Administration (FHWA) under the Transportation Equity 

Act for the 21st Century (TEA-21). My testimony today will discuss (1) 

the time involved in planning, gaining approval for, and constructing 

federally financed highway projects; (2) events that arise that affect 

completion time; and (3) federal and state initiatives to improve the 

completion times of highway projects.



The United States is the most mobile nation on the planet. 

Constructing, improving, and repairing roads and bridges is fundamental 

to meeting the nation’s mobility needs to facilitate commerce, national 

defense, and pleasure use and to promote economic growth. Therefore, it 

is important that highway projects using federal financial support are 

completed in as timely a manner as possible. My statement presents 

preliminary results of our ongoing work for this committee on the 

construction of new roads. My statement is based on our review of 

federal laws and regulations governing the construction of federally 

funded highway projects; studies and other analyses of the time it 

takes to complete new federally financed roads; and discussions with 

various federal agency officials who have responsibilities relating to 

the construction of federally financed roads, transportation 

engineering organizations, transportation professional associations, 

and state transportation officials in seven states. We also reviewed 

the time it took to complete six new highway construction projects in 

California, Florida, and Texas.



Federal and state governments do not maintain information centrally 

(or, in some cases, at all) on the time it takes to complete highway 

projects; and there is no accepted measuring stick with which to gauge 

whether project performance is timely. Our discussion of the typical 

amount of time it takes to complete major construction projects that 

involve building new roads is based on a best estimate prepared by 

FHWA. According to FHWA, it based its estimate on the professional 

judgment of its staff and several state departments of transportation. 

We also discussed typical times to complete major new highway 

construction projects with several professional associations and state 

departments of transportation. In those instances where they had 

anecdotal information, their estimates fell within the FHWA time 

frames. (See app. I for additional details, including how we picked the 

six projects to review.) We are continuing to examine this issue and 

expect to report to you on the final results of our work in Spring 

2003, to aid in your consideration of the reauthorization of TEA-21.



In summary:



* According to FHWA, and based on its professional judgment, it 

typically takes from 9 to 19 years to plan, gain approval for, and 

construct a new, major federally funded highway project that has 

significant environmental impacts. However, these projects constitute 

only about 3 percent of all federally funded projects, according to 

FHWA. These highway projects are often carried out in four phases. (See 

table 1.):



Table 1: Typical Time Necessary to Complete a Federally Financed Major 

New Construction Highway Project:



Phase: Planning; Time to complete, in years: 4-5.



Phase: Preliminary design and environmental review; Time to complete, 

in years: 1-5.



Phase: Final design and right-of-way acquisition; Time to complete, in 

years: 2-3.



Phase: Construction; Time to complete, in years: 2-6.



Phase: Total; Time to complete, in years: 9-19.



Note: The durations of the phases are approximate. The preliminary 

design/environmental review steps and the final design/right-of-way 

acquisition steps often overlap.



Source: FHWA.



[End of table]



The time required varies with the size of the project, its complexity, 

and the public interest in the project. Some projects may take as few 

as 3 years or as many as 20 years or more to complete. The six new 

highway construction projects that we reviewed ranged from a $1.7 

million project in Florida to upgrade an existing dirt road to a two-

lane paved road, which took 8 years to complete, to a $50 million 

project to build a six-lane, 

15 mile divided highway in Texas, which took over 15 years to complete 

(excluding the planning phase, for which information was not 

available). Constructing a new, major roadway typically takes this long 

to complete because there can be as many as 200 major steps involved 

throughout a project’s life, with approvals or input required from a 

number of federal, state, and other stakeholders.



* Not surprisingly, officials in federal and state agencies and other 

knowledgeable organizations indicate that delivering larger, more 

complex or controversial projects may take longer to complete than is 

typical for most highway projects. In addition to needing more time 

because of their size and complexity, they often take longer to 

complete because they must comply with more federal and state 

requirements and because of the public interest that they may generate. 

A survey of 33 state departments of transportation conducted by the 

American Association of State Highway and Transportation Officials 

agree that larger projects take longer to complete.[Footnote 1] 

However, both our work and the association’s survey are based on 

anecdotal information and officials’ memories, as no federal or state 

baseline information exists on how long highway projects take. While 

there are many reasons for new highway construction projects to take a 

long time to complete, most studies on the topic focused on the timely 

resolution of environmental issues to improve project completion times, 

rather than examining all aspects of highway projects. The officials we 

contacted generally stated that environmental reviews resulted in 

better project decisions; but reaching those decisions was difficult 

and time consuming, complicated by such factors as incomplete permit 

applications, limited resources at environmental agencies, and 

environmental opposition to projects.



* Federal and state agencies have undertaken several initiatives to 

improve completion times for highway construction projects. Most of 

these initiatives address opportunities for reducing the time required 

to obtain environmental approvals. For example, FHWA is working with 

federal agencies that conduct environmental and historic preservation 

reviews to promote uniform practices and to clarify and update 

guidance. At the state level, according to FHWA, 34 states are using 

interagency funding agreements to hire additional staff at state and 

federal environmental agencies to facilitate environmental reviews and 

approval. With respect to nonenvironmental issues, North Carolina and 

Texas, for example, are identifying utilities that need to be moved 

earlier in the design phase than was previously done. This is intended 

to reduce delays during the construction phase. Texas and Florida are 

providing monetary incentives to contractors to finish construction 

more quickly.



Background:



In fiscal year 2001, FHWA obligated over $20 billion to the states for 

roadway projects.[Footnote 2] Generally, states are required to use 

their own funds to pay up to 20 percent of the project costs. Federally 

funded highway projects vary in size, from new lane striping to 

resurfacing an existing road to building a new road or interchange. 

Most federally funded highway projects are minor rehabilitation or 

reconstruction projects rather than major new road construction 

projects. Of the approximately 27,000 miles of roadway projects funded 

in 2000 (latest data available), about 26,000 miles (96 percent) 

involved either the addition of capacity, preservation, or improvements 

(such as widening lanes, resurfacing, and rehabilitation of roadways). 

Only about 1,100 miles of new road construction projects were underway.



Although federal, state, and local governments all have a role in the 

construction of federally financed highway projects, the state 

department of transportation is typically the focal point for these 

activities. It is responsible for setting the transportation goals for 

the state. To do so, it works with the state’s transportation 

organizations and local governments and metropolitan planning 

organizations.[Footnote 3] State departments of transportation are 

responsible for planning safe and efficient transportation between 

cities and towns in the state. They are also responsible for designing 

most projects, acquiring property for highway projects, and awarding 

contracts for highway construction. Local governments also carry out 

many transportation planning functions, such as scheduling improvements 

and maintenance for local streets and roads. Citizens and community 

action organizations also generally have the opportunity to provide 

their views and have them considered.



At the federal level, FHWA is the primary agency involved in 

transportation project decisionmaking. FHWA oversees the 

transportation planning and project activities of state departments of 

transportation and metropolitan planning organizations by approving 

state transportation plans, certifying that states have met 

requirements involving environmental protection, and approving 

acquisition of property for certain state highway projects. FHWA also 

provides advice and training on transportation topics ranging from 

pavement technology to efficient operations of highway systems, and it 

provides funding to the states for transportation planning and 

projects. Because any transportation project using federal funding must 

be examined for potential effects on the environment before federal 

decisions are made, FHWA also works with other federal agencies and 

state, local, and tribal governments; public and private organizations; 

and the public to understand a project’s potential impact on the 

environment and historic properties.[Footnote 4] Other federal agencies 

with environmental and historic preservation responsibilities that 

often are affected by federally funded highway projects include:



* the Environmental Protection Agency (air and water quality; wetlands 

preservation);



* the Fish and Wildlife Service (endangered species) and the Bureau of 

Land Management (may own lands on which a highway is to be constructed) 

within the Department of the Interior;



* National Marine Fisheries Service (for example, effects on fish and 

spawning grounds) within the Department of Commerce;



* the Army Corps of Engineers (effects on wetlands);



* the Coast Guard (bridge and navigation responsibilities); and:



* the Advisory Council on Historic Preservation (protecting historic 

sites).



Concerned about how long the completion of highway projects takes, 

Congress included provisions in TEA-21 to streamline environmental 

review. These provisions require FHWA to identify and work with federal 

agencies that have environmental and historic preservation jurisdiction 

over highway and transit projects to cooperatively establish realistic 

project development time frames among the transportation and 

environmental agencies and to work with these agencies to adhere to 

those time frames. Because transportation projects are also affected by 

state and local environmental requirements, TEA-21 allows individual 

states to participate in these streamlining initiatives, as long as all 

affected states’ agencies participate. Finally, FHWA can approve state 

requests to use their federal-aid highway and mass transit funds to 

provide additional federal environmental personnel to help expedite 

environmental reviews.



Time to Complete Highway Projects:



According to FHWA, and based on its professional judgment, planning, 

gaining approval for, and constructing a federally funded major highway 

project that involves new construction and has a significant 

environmental impact typically takes from 9 to 19 years. However, these 

projects constitute about 3 percent of all federally funded projects, 

according to FHWA. Some projects may take as few as 3 years or as many 

as 20 years or more to complete. The six new construction projects that 

we reviewed did not all meet FHWA’s criteria yet fell within the time 

range FHWA estimates that it takes to complete more complex projects. 

These six projects ranged from 8 years to upgrade an existing dirt road 

in Florida to a two-lane paved road to over 15 years to build a six-

lane, 15 mile divided highway in Texas (excluding the planning phases 

on both projects, for which information was not available).



Completing a new, major highway construction project takes a number of 

years because of the many tasks, requirements, approvals, and 

stakeholders involved. As many as 200 major steps can be involved in 

developing a transportation project from the identification of project 

need to the start of construction, depending on the project type and 

complexity. (See fig. 1.) Smaller projects (such as new lane striping) 

as well as larger projects (such as constructing a new highway) must go 

through many steps that require multiple stakeholder reviews and 

approvals. Because most federally funded highway construction projects 

are minor rehabilitation or reconstruction projects rather than major 

new road construction projects, these projects generally will not 

require extensive planning studies and will not have significant 

environmental impacts. As a result, according to FHWA, most federally 

funded highway construction projects advance from planning to 

construction within 1 year but may take up to 4-6 years, depending on 

the individual project’s characteristics.



Figure 1: Typical Amount of Time Involved in Planning, Approving, and 

Building a Major New Highway Project:



[See PDF for imaage]



Note: The durations of the phases are approximate. The preliminary 

design/environmental review steps and the final design/right-of-way 

acquisition steps often overlap.



Source: FHWA.



[End of figure]



According to FHWA, the planning phase for a major new construction 

project typically takes from 4 to 5 years. In this phase, most projects 

must first be identified in long-range (for example, covering a 20 year 

period) and short-range (for example, covering a 3 to 5 year period) 

state transportation plans.[Footnote 5] Planners look at transportation 

alternatives and work with the public to select the alternatives that 

make the most sense for their areas and that are consistent with 

federal requirements, such as helping to adhere to air quality 

standards for the area. Short-range plans may have some citizen 

involvement and must be approved by state and local transportation 

officials as well as FHWA. States and metropolitan areas must 

demonstrate that funding is available for the projects included in the 

short-range plans. Finally, the length of the planning phase for a 

project will depend on whether the project is located in an urbanized 

area that does not meet federal air quality standards.[Footnote 6]



The preliminary design and environmental review phase typically takes 

from 1 to 5 years depending on the complexity of the design and 

possible environmental impacts that must be considered, according to 

FHWA. During preliminary design, states identify the preliminary 

engineering issues, proposed alignment of the roadway, cost, and 

project details, such as turn-lane identification. The proposed project 

and alternatives to it are examined for any impacts on the natural 

environment (such as on endangered species) and public health and 

welfare (such as on safety and historic preservation). These 

environmental reviews require state and FHWA officials to address and 

comply with as many as 60 federal laws, as well as applicable state 

laws. More complex projects require more time for the completion of 

preliminary designs and environmental reviews. Transportation and 

environmental officials told us that reaching a decision on how to 

address projects with significant environmental impacts has taken 

several years. A 2001 FHWA study on the amount of time required for 

environmental reviews of projects with significant environmental 

impacts found that the average amount of time taken to complete these 

reviews in 1998 was about 5 1/2 years.[Footnote 7] In comparison, these 

officials told us that projects in which the environmental impact was 

initially unclear and later determined to be insignificant took less 

time. These officials also told us that completing environmental 

reviews for projects that FHWA had determined as having no significant 

environmental impact from the start of the review process, including 

those categories of projects statutorily excluded from environmental 

review (for example, landscaping or installation of road signs), took 

only a matter of months. The previously cited anecdotal survey of 33 

state departments of transportation conducted by the American 

Association of State Highway and Transportation Officials in 2000 found 

that reviews involving projects for which the environmental impact was 

determined to be insignificant or the initial environmental impact was 

unclear took an average of nearly 2 years and about 3 1/2 years, 

respectively. FHWA has found that 91 percent of federally funded 

roadway projects have no significant environmental impact and, in 

another 6 percent of the projects, the initial impact was unclear.



Final design and acquiring the right of way for a major new highway 

construction project typically takes from 2 to 3 years, according to 

FHWA. During this phase, state departments of transportation must 

develop detailed engineering plans consistent with environmental 

documents and updated environmental studies, and must finalize cost 

estimates. If a significant amount of time has passed since the 

preliminary design work was performed, right-of-way maps and other 

information may need to be updated. Acquiring property for the project 

includes determining any restrictions to state ownership of the 

property; determining the identities of property owners; making offers 

to property owners based on appraisal price; negotiating a purchase 

price; and sometimes invoking eminent domain.[Footnote 8] This phase 

may take a significant amount of time, especially if residents must be 

relocated. Utilities must also be located, marked, and surveyed, which 

can be complicated if there are many underground utilities that require 

professional engineers, geologists, and licensed land surveyors for 

determining the exact location of utilities.



According to FHWA, the construction phase typically takes from 2 to 

6 years. To begin construction, the state department of transportation 

must request and evaluate bids on the project and award a contract. 

Projects that receive federal-aid highway funds require FHWA 

concurrence on the award. During construction, the contractor and the 

state must resolve any unexpected problems that may arise, such as 

removal of hazardous waste discovered at the construction site. Once 

satisfied that construction has been carried out as agreed to with the 

contractor, the state must approve the final completion of 

construction.[Footnote 9]



Many Events May Affect Project Completion Time:



Not surprisingly, officials in federal and state agencies and other 

knowledgeable organizations indicate that larger, more complex or 

controversial projects take longer to complete than is usual for most 

highway projects. This is because large, complex projects are subject 

to more requirements, involve more federal stakeholders, and attract 

more public interest. For example, in the previously cited survey of 33 

state departments of transportation, projects that involve many federal 

agencies took longer to complete than projects requiring only state-

level review. The survey reported that state-only reviews typically 

occur for simpler, less complicated projects, which involve fewer 

stakeholders. However, both the information we collected and the state 

survey are anecdotal and based on interviewees’ memories, because 

states do not maintain centralized information on project completion 

times. State officials told us that an effort to capture those data 

systematically would require resources that the state departments of 

transportation could use more productively to complete projects.



Although the six medium-sized and large highway projects in California, 

Florida, and Texas that we reviewed did not meet all of FHWA’s criteria 

for a major project, they still took from nearly 7 years to over 15 

years to complete, excluding the planning phase for which data were not 

available. (See table 2.) The time required to complete these six 

projects fell within the typical time FHWA has estimated that it takes 

to complete more complex projects. Only two of the six projects, both 

in California, were required to complete the preparation of an 

environmental impact statement.



Table 2: Duration of Six Medium-sized and Large New Construction 

Highway Projects in California, Florida, and Texas:



[See PDf for image]



N/A - not available.



[A] Total time may not equal the sum of each phase. In some instances 

total time is less than the sum of each phase because phases overlap, 

most noticeably with the two projects in Texas. In addition, the State 

Route 115 project in Florida was a spin-off of an existing project. As 

a result, there is a 

15-month gap between the end of the preliminary design and 

environmental review phase and the start of the final design and right-

of-way acquisition phase for this spin-off project.



Source: GAO analysis of state documentation and discussions with state 

department of transportation officials.



[End of table]



Another way of assessing project timeliness is to compare how long it 

takes to complete a project with how long state transportation 

officials expected completion to take. For the six projects we 

reviewed, state officials established milestones for each phase of the 

project (excluding the planning phase, for which state officials could 

not provide information) but not always for the project 

overall.[Footnote 10] We attempted to compare the time it took to 

complete each phase against the time expected for the projects that we 

reviewed. For the two California projects, the project phases were 

generally completed within a year of established time frames. However, 

aspects of the two projects in Texas took substantially longer to 

complete than planned. For example, the preliminary design and 

environmental review phase for the U.S. 290 project took 6 years and 7 

months longer to complete than planned. In addition, the right-of-way 

acquisition for this project took 4 years and 

7 months longer to complete than planned. For the Texas State Highway 

146 project, the preliminary design and environmental review phase took 

2 years and 8 months longer to complete than planned, and the right-of-

way acquisition took 2 years longer to complete than planned. State 

officials were able to provide a qualitative recollection or in some 

cases documentation of events that affected their ability to complete 

highway projects on time. (See table 3.) For example, three of the six 

projects encountered problems in both the final design and right-of-way 

acquisition phase and in the construction phase.



Table 3: Events Affecting Selected Projects:



Project: State Route 198 (California); Planning: Funding shortages; 
Preliminary design 

and environmental review: No events cited; Final design and right-of-

way acquisition: Following earthquakes, project shelved in favor of 

seismic retrofit work around the state; Construction: Weather delays; 
contract 

change orders; contractor performance issues.



Project: State Route 168 (California); Planning: Not available[A]; 
Preliminary design 

and environmental review: No events cited; Final design and right-of-

way acquisition: No events cited; Construction: No events cited.



Project: Fort Green/Ona Road (Florida); Planning: Not available[A]; 
Preliminary design 

and environmental review: No events cited; Final design and right-of-

way acquisition: Contractor had to devote time and resources to other 

ongoing projects; redesigns on account of drainage problems; property 

owners resisted right-of-way acquisition; Construction: Quality issues 
with paving 

material used; poor contractor performance; weather delays.



Project: State Road 115 (Florida); Planning: No events cited; 
Preliminary design and 

environmental review: No events cited; Final design and right-of-way 

acquisition: No events cited; Construction: Weather delays; vibration 
damage 

complaints from adjacent homeowners necessitated change in construction 

equipment.



Project: State Highway 146 (Texas); Planning: No events cited; 
Preliminary design and 

environmental review: Design changes to accommodate large truck 

vertical clearance necessitated changes to schematics and environmental 

documents; Final design and right-of-way acquisition: Lengthy process 

to hire design consultant; parcels of land had numerous title problems; 

one property owner died during negotiations leading to probate issues; 

unidentified natural gas line; Construction: No events cited.



Project: U.S. Highway 290 (Texas); Planning: No events cited; 
Preliminary design and 

environmental review: Various access design changes to accommodate 

historic property; wetlands previously undiscovered at the site had to 

be addressed; Final design and right-of-way acquisition: Property 

owners refused state’s purchase offer necessitating condemnation; 

utility adjustments; Construction: Slope stability problems required an 
extensive 

redesign effort.



[A] State officials could not provide this information.



Source: GAO review of project documentation and discussion with state 

department of transportation officials.



[End of table]



Most studies we identified on timely completion of highway projects 

have examined the timely resolution of environmental issues for 

improving project completion times. For example, the previously cited 

2001 FHWA study indicated that some larger, more complex projects tend 

to take longer than is typical in the preliminary design and 

environmental review phase. In an attempt to establish a baseline for 

evaluating project completion times, FHWA analyzed the time required 

for 37 projects with significant environmental impacts to complete the 

environmental review process. (As noted above, projects of this class 

are usually major projects rather than small, less complex ones.) This 

analysis indicated that the average amount of time taken to complete 

these reviews was 5 years and 

7 months--exceeding the 5 years that a “typical” major highway project 

was expected to take for the entire preliminary design and 

environmental review phase. According to FHWA, these types of projects 

constitute only about 3 percent of all federally funded highway 

projects. Most federally funded projects are minor rehabilitation or 

reconstruction projects that do not have significant environmental 

impacts.



The survey of 33 state departments of transportation conducted in 2000 

for the American Association of State Highway and Transportation 

Officials indicated that state departments of transportation may 

underestimate the time that completing an environmental review would 

require. The survey indicated that the environmental reviews for 31 to 

48 percent of projects with no significant environmental impacts, and 

for 43 to 64 percent of projects with potential environmental impacts, 

took longer to complete than expected. According to the survey results, 

these projects took three times longer than planned to complete federal 

environmental review requirements related to public lands and historic 

resources, historic resources and cultural resources, and wetlands.



Federal and state transportation officials and transportation 

engineering organizations identified the timely resolution of 

environmental issues as providing the greatest opportunity for reducing 

the time it takes to complete highway projects. These officials 

generally stated that environmental reviews resulted in better project 

decisions, but that reaching the decisions was difficult and time 

consuming. For example, officials with the Army Corps of Engineers in 

Texas told us that the permit applications that it receives are 

sometimes incomplete or inaccurate, resulting in added time to process 

environmental permits related to waterways. In addition, officials with 

the Fish and Wildlife Service and the California Department of 

Transportation identified staffing shortfalls and workloads at the Fish 

and Wildlife Service as contributing to increased time to perform 

environmental consultations. Finally, officials with the Environmental 

Protection Agency stated that public opposition to major transportation 

projects can result in greater scrutiny of environmental analyses or 

the proposed mitigation of environmental impacts, and therefore 

increases the length of the environmental review phase.



Initiatives to Improve the Timely Completion of Highway Projects:



Federal and state agencies have undertaken several initiatives to 

improve completion times for highway construction projects. Most of 

these initiatives address environmental review; however, some states 

have undertaken initiatives to improve completion times in other 

aspects of a project, such as construction. Generally, the impact of 

these initiatives is unclear because of the brevity of time they have 

been in place.



At the federal level, FHWA environmental streamlining efforts have 

included working with federal agencies involved in environmental and 

historic preservation reviews to conduct agency-specific training 

workshops in 2001 and 2002. FHWA has conducted these workshops for 

field staff to promote uniform practices and to clarify and update 

guidance. In addition, FHWA has started tracking the time to complete 

environmental reviews of federally funded highway projects this year. A 

recent FHWA report indicated that since the enactment of the TEA-21 

environmental streamlining provisions in 1998, the average review time 

for projects with significant environmental impacts has decreased from 

70 months to 62 months.[Footnote 11] FHWA officials told us that the 

improved review times could be a result of such things as reinvented 

processes, programmatic agreements, and accelerated review times. FHWA 

has also developed guidance for states on how to use federal-aid 

highway funds to reimburse federal agencies that meet agreed-upon 

targets for environmental reviews. FHWA has catalogued environmental 

streamlining best practices and publicized them on its Web site.



State departments of transportation are using interagency funding 

agreements to hire additional staff at state and federal environmental 

agencies to facilitate environmental review and approval.[Footnote 12] 

According to FHWA, 34 states are using these agreements. A 2001 survey 

by the American Association of State Highway and Transportation 

Officials indicated that the people in these positions made permit 

reviews more efficient and consistent, improved communication between 

agencies, and fostered greater trust and understanding, thus 

facilitating project approvals and making the process less 

controversial.[Footnote 13]



Forty-one states have some level of delegated authority for historic 

resources that allows them to process many projects quickly, according 

to FHWA. For example, the Vermont Agency of Transportation has an 

agreement with the state historic preservation office that allows the 

transportation department rather than the state historic preservation 

office to enforce historic preservation requirements. According to 

Vermont transportation agency officials, this agreement has resulted 

in, among other things, expedited permit acquisition, enhanced public 

participation, effective internal and inter-agency communication, and 

the best possible treatment of historic properties. These officials 

estimate that this agreement has shaved weeks from routine projects and 

will shave months from more complex ones.



Outside of the environmental review process, states such as Florida, 

North Carolina, and Texas are identifying utilities in certain urban 

areas earlier in the design phase, in order to avoid delays during 

construction. Texas and Florida have also developed strategies to 

accelerate construction for some projects by increasing contractor 

incentives for early completion, and Florida has documented savings in 

time and cost from this approach.



Mr. Chairman, this concludes my prepared statement. I would be pleased 

to answer any questions that you or Members of the Committee may have.



Contacts and Acknowledgments:



For further information on this testimony, please contact Katherine 

Siggerud at (202) 512-2834 or siggerudk@gao.gov. Individuals making key 

contributions to this testimony were Jennifer Clayborne, Kenya Jones, 

Heather Martin, James Ratzenberger, Deena Richart, Stacey Thompson, and 

Matthew Zisman.



[End of section]



Appendix I: Scope and Methodology:



To perform our work, we reviewed laws and regulations governing the 

construction of federally financed highway projects. We discussed these 

requirements, the time required to complete projects, and initiatives 

to reduce this time with officials from FHWA, the Advisory Council on 

Historic Preservation, the Environmental Protection Agency, the Army 

Corps of Engineers, the Coast Guard, the Fish and Wildlife Service, the 

American Association of State Highway and Transportation Officials, the 

American Road and Transportation Builders Association, the American 

Society of Civil Engineers, private transportation engineering firms, 

and others. We also interviewed officials from California, Florida, 

North Carolina, Texas, Vermont, Washington, and Wisconsin departments 

of transportation about highway project completion times and 

initiatives to improve the timely completion of these projects. We 

chose these states either because they spent the most federal-aid 

highway funds or because officials we interviewed identified these 

states as making efforts to reduce project time. We also reviewed 

federal and private studies on highway project completion.



We reviewed the time it took to complete six new highway construction 

projects in California, Florida, and Texas. We selected three of the 

four states that spent the most National Highway System and Surface 

Transportation Program Funds in fiscal year 2000 (latest data 

available). These represent the primary sources of federal funds for 

new road construction. In each state, we selected two new construction 

projects that were completed between June 30, 1999, and June 30, 2002. 

In each state we selected the largest project (in terms of federal 

funds received) and a medium-sized project. In selecting these 

projects, we had no knowledge of the project itself or of how long it 

took to complete. We did not independently verify the information in 

the FHWA information system that contained these data. For the six 

projects, we obtained documentation and interviewed state department of 

transportation officials to determine how the projects were planned, 

approved, and carried out.



We conducted our work from May 2002 through September 2002 in 

accordance with generally accepted government auditing standards.



FOOTNOTES



[1] TransTech Management, Inc., Environmental Streamlining: A Report on 

Delays Associated with the Categorical Exclusion and Environmental 

Assessment Processes (Washington, D.C.: Oct. 2000). 



[2] Most of the funding for roadway projects comes from the Highway 

Trust Fund. The Highway Trust Fund is derived from highway user taxes 

such as excise taxes on motor fuels, tires, and the sale of trucks and 

trailers, and from taxes on the use of heavy vehicles.



[3] Among other things, metropolitan planning organizations propose 

short-and long-term solutions to transportation and transportation-

related concerns.



[4] Environmental review is governed by the National Environmental 

Policy Act of 1969, which established a national environmental policy 

requiring that any project using federal funding or approval, including 

transportation projects, examine the effects of the proposal and 

alternative choices on the environment and historic properties before a 

federal decision is made.



For federally funded highway projects that FHWA determines will have a 

significant impact on the environment, FHWA must prepare a statement 

that describes the project, characterizes the surrounding environment, 

analyzes the environmental effects of all reasonable construction 

alternatives, and indicates plans for complying with applicable 

environmental laws and mitigating environmental damage. Other federal 

agencies with responsibilities for these laws, such as the 

Environmental Protection Agency, Army Corps of Engineers, and Fish and 

Wildlife Service, often cooperate in the preparation of these 

statements. If it is clearly known that a highway project will not 

individually or cumulatively have significant environmental impacts, 

FHWA issues a statement indicating this. However, if it is not 

initially clear whether significant impacts would occur, FHWA must 

conduct additional analysis. If significant impacts are then 

identified, FHWA must prepare a statement for significant impacts as 

described above. Otherwise, FHWA issues a statement that it found no 

significant impacts.



[5] TEA-21 requires a Statewide Transportation Improvement Program or a 

metropolitan area’s Transportation Improvement Program that contains 

individual transportation projects. FHWA requires the development of 

these improvement programs on at least a 

2 year cycle.



[6] The Environmental Protection Agency sets maximum safe amounts of 

pollution that a region or state can have in the air. How much 

pollution is allowed from cars, trucks, and buses to the air will vary 

depending on the area’s climate, wind, and other pollution sources and 

factors.



[7] Federal Highway Administration, Evaluating the Performance of 

Environmental Streamlining: Development of a NEPA Baseline for 

Measuring Continuous Performance (Washington, D.C.: Jan. 2001).



[8] Eminent domain is the right of a government to take private 

property for public use in exchange for just compensation by virtue of 

the sovereign power over all lands within its jurisdiction.



[9] In some cases, FHWA approves the final completion of construction.



[10] Florida officials could not provide information on planned 

completion times for the phases of the two projects we reviewed. 

Therefore, we could not determine if project phases were completed 

within planned time frames.



[11] Federal Highway Administration, Highway and Transit Environmental 

Streamlining Progress Summary (Washington, D.C.: Feb. 2002).



[12] Under these agreements, state departments of transportation are 

providing funding or positions to agencies that are involved in 

environmental and historic preservation reviews.



[13] Venner Consulting, AASHTO Standing Committee on the Environment, 

Natural Resources Subcommittee internal survey and white paper, July 

2001.