Allegations of an Inappropriate Army Sole-Source Award for Commercial Construction Equipment

PLRD-82-13 Published: Oct 15, 1981. Publicly Released: Oct 28, 1981.
Jump To:
Skip to Highlights

Highlights

Pursuant to a congressional request, GAO reviewed the Army's decision to buy commercial construction equipment on a sole-source basis. The proposed procurement is designed to replace outdated earth moving equipment because the present equipment, purchased between 1962 and 1969, had an expected life ranging from 8 to 10 years. Because of the age of this equipment, maintenance is hampered due to the shortage of spare parts. Thus, the rapid deployment mission is or could be adversely affected.

Full Report

Office of Public Affairs

Topics

Army procurementConstruction equipmentIrregular procurementSole source procurementMilitary forcesGovernment procurementProcurementSpecificationsEquipment maintenanceBid proposals